PT PELSART TAMBANG KENCANA

Weekly OPERATIONAL MEETING


15 Desember 2023
14:00 WITA
ATTENDEES
Management : Dadang, Budy Enviro : Toni SCM : Yuan, Judi
HSE : Judika Exploration : Jonferry CSR : Septamto
Security/SP: Kusbandono, Demy Drilling: Muji Permitting: Eric
Maint. Mobile Plan: Helmy Admin: Yusuf MGS: Wahyudin
Project Service: Achwan, Djundu IT : Dody Survey: Ucu Minutes Taker : Immaculata
TOPIC FOLLOW UP ACTION STATUS PIC
ISSUE SAFETY
1. Property damage → pecah kaca pintu (property damage). Info Arri
2. Fuel Station → agar dilakukan reiview disesuaikan dengan peraturan perundangan, minimal pemasangan pagar. Time line untuk
Follow up Dadang/Yuan/Judika
penentuan titik pagar 7 hari.
SAFETY
1. Incident 1. Incident: 10 Desember 2023, Akses Quarry/Badak, Kronologis: Pecah kaca kabin ADT702 (Property Damage). Info Judika
2. Activities 2.- Induksi keselamatan
- Pelatihan JSA (2batch) total peserta 43 orang.
- Patroli dan Observer Continue Judika
- Membuat, memasang dan merawat rambu
- Assessment akses Haraan.
ENVIRONMENT
1. Pengelolaan Lingkungan 1.a. Pengelolaan LB3:
- Telah dilakukan sosialisasi pengelolaan LB3, 15 peserta (wakil masing-masing departemen).
b. Pengelolaan Limbah Non B3:
- Pengumpulan rutin → untuk dilanjutkan pengomposan (manifest week 49 adalah 95.64 ton) dan atau diambil oleh vendor.
2. Revegetasi 2.a. Hydroseeding: luas yang telah dilakukan 1243.5 M² dari target 5000 M² (25%)
b. Revegetasi telah dilakukan di area terganggu (area samping bukit KM 7, area KM 8 (HLH) dan area KM 9). Total luas area yg telah Info Toni
direvegetasi 670 M² menggunakan tanaman sengon dan trembesi.
3. Nursery 3. Nursery masih berlanjut.
4. Pemantauan Lingkungan 4.a. Curah Hujan: minggu 49 sebenyak 7.5 mm (Banian). Akumulasi bulan Desember 2023 adalah 66 mm.
b. Pemantauan Kebisingan: dilakukan di Banian dan Badak. Hasil pengukuran masih sesuai (dibawah 85 dB).
5. Timber Cruising 5.a. Area TPA dan WWTP TSP LHC 07:
- Pembayaran PSDH dan DR 25% → on progress.
- Penyusunan Laporan Rencana Penebangan → on progress.
b. Area Camp Jinpeng dan Open Channel LHC 05: Info Toni
- Pembayaran PSDH 25% dan DR 25% → on progress.
- Penyusunan Laporan Rencana Penebangan → on progress.
c. Area CITEC dan Plant LHC 08:
- Melakukan timber cruising pada area yang akan dilakukan pembukaan lahan → on progress.
EKSPLORASI
1. Eksplorasi PTK Timburu 1.- Drilling Kembatang → D712 dan D718
- Total resource Timburu (INF+IND+MEA) → 1.640 Moz gold eq → 980 koz Resv.
- Progress pengeboran 98% dari target 53.000 M
- Target pengeboran 2024 → follow up hasil pemetaan, survei geofisika airborne, IP-Res dan groundmag-VLF
2. Issue 2.- Morfologi area eksplorasi terjal, rawan longsor
- Musim penghujan
- Pengaturan 2 unit exca dan 2 unit dozer → support pengeboran 6 rig di Kembatang dan 2 rig di Haraan.
3. Overview Eksplorasi 3.a. Pengeboran Timburu:
- KK → 6 rig (Infill-inpit, Pit Extension)
- HR → 2 rig (Infill-Inpit, Pit Extension), HR Central
b. Trenching → rod-cut channeling
c. Prospecting program → survei geofisika di Menteu Utara untuk mencari high resistivity pada anomaly Groundmag-VLF On Progress Jon
4. Pengeboran Kembatang Kecil 4.a. Section Holes KKDD091 Kembatang Kecil:
- Intercept mineralisasi pada zona litologi (Slum)
- Intercept Qfp teralterasi kuarsa-karbonat dan hadirnya vein halo sulfida pada vein-neinlets silika-serisit.
- Intercept SLUM
- Pengeboran dengan tujuan untuk target pengeboran menaikkan reserve 2024.
5. Lain-Lain 5.a. Per 14 Desember 2023 → 3.213 sampel masih menunggu untuk dikirimkan.
b. Analisis assay sudah kembali dilakukan oleh Lab Internal IMK (Au, Ag, Cu, Pb, Zn)
c. Core storage di Direksi Keet sudah selesai pembangunan. Progress pemindahan core storage Banian ke Badak.
d. Camp Haraan → kapasitas 146 orang. Camp Kembatang → kapasitas 80 orang.
e. Progress pembuatan camp non staff Menteu baru (80%)
DRILLING
1. Update pengeboran 1. Total Diamond Drill week 49 adalah 685.50 M, secara total pengeboran tahun 2023 sebanyak 55.823 M dari Eksplorasi PTK
Continue Muji
2. Kegiatan workshop Banian 2. Repair engine Kubota 2203
MGS
1. Pemetaan Struktur 1.a Area Haraan: progress 92%
b. Area Kembatang: progress 100%
c. Area Menteu: progress 20.4%
2. Pengujian Kepadatan Tanah 2. DCP Test di KM7:
- Pekerjaan DCP → ditunda, kedatangan unit dozer.
- Progress 33.3%
3. Kegiatan Hidrologi dan Hidrogeologi Pengukuran debit air, monitoring curah hujan, Pengukuran muka air tanah dan pengukuran debit sungai masih berjalan rutin.
4. Pengukuran Debit Air 4.a. Mata air: pada 2 titik, rata-rata debit 0.04 l/s.
b. Sungai Kembatang - Haraan: pada 7 titik, progress 58%, debit 220 l/s
5. Pengukuran Muka Air Tanah 5. Dilakukan sekali dalam sebulan; total 11 sumur di area Timburu; progress 90%
6. Curah Hujan 6. Curah hujan di Kembatang 41 mm; Badak 88 mm; Menteu 100 mm. Continue Wahyuddin
7. Earthwork 7. Site access to Quarry: plan cut 247.512 ton, progress 81.876 ton (33%)
- Access to Open Channel: Plan cut 5.641 ton, progress 5.289 ton (87%). Plan fill: 3.434 ton, progress 823 ton (87%)
- Access to Quarry (Sequence 3): cut material & sloping bench to RL+297.5; Bench sloping to RL+297.5; Road construction from
RL+297.5 to RL+300
- Access road to KM7: total fill 65,260 ton. Actual cumulative 62,134 ton (95%)
- Access road to KM7: dumping clay from access to Quarry; dozing and compacting material; road construction and embankment
repair.
- Stockpile Topsoil KM 10: total movement week49: 0 ton
- Waterfall analysis week 49: mostly rain and sleepery.
- Face position: fleet allocation loading clay 5 ADT (material 7,145 ton), loading soil 4 DT (1,746 ton)
- Dump face position: total material move 7,145 ton. Fill from RL+149 ton to RL+156
8. Lain-lain 8. SOP Curah Hujan di area aktif rawan longsor Follow up Wahyuddin

SURVEY
1. Topography detail 1. Sedpond Pit Menteu progress 43.7% dengan luasan 11.80 ha dari target 27 ha; Sedpond Waste dump MN progress 89% dengan
luasan 20.02 Ha dari target 22.5 ha; Sedpond Waste dump MS progress 53.8% dengan luasan 13.31 Ha dari target 24.75 Ha

Continue Ucu
2. Stake out & pick up 2. Haraan 1 collar, Kembatang 2 collar

3. Survey Kusan 3. Agar dibuatkan laporan hasil survey Kusan

MMP

1. Progress Maintenance 1.a. Untuk PA Main production Actual 84.7% dari target 91,00%
Continue
b. Untuk PA Ancillary actual 96.8% dari target 92.1% diatas target.
Helmy
2. Update Unit Breakdown 2. Unit breakdown: EX704, ADT705, TR702, DT701
3. Maintenance Issue 3. terdapat PO/PR parts, tools, material dan soncumable yang diperlukan segera.
SCM
1. Purchasing Activities - PO Order PTK All → 132
- Total line order → 346
- Total amount → 2.968.778.639 IDR
2. Fuel B35 2. Balance stock 21,915 Liter; Received 39,870 Liter; Consumption 26,851 Liter; daily average cons 3,835 Liter/day
3. Purchasing Activities 3.- PR/PO urgent: Part Excavator, Dozer, Checker plate, HQ reamer shell, autoelectric parts, valve AC LV 704, presure gauge volvo,
grease long life.
- PR/PO urgent received on site: steel onsumable on order, laptop permitting.
4. Warehouse Activities 4.- Order stock cost core tray HQ4 jalur eksplorasi → done; core tray PQ → TBA
- Penerimaan fuel B35 periode I Desember 2023.
- Pengiriman sampel assay ke PTK site.
- Pemakaian storage LB3 untuk lubricant di Direksi Keet.
5. CAPEX Update: 5.a. Supply CAPEX update: On Progress Yuan
- 2 unit Exca EC350 Volvo → ETA site 27 Des 2023
- 3 unit Compactor Volvo Fad foot → ETA site 27 Des 2023
- 2 unit Dozer Zoomlion ZD220-3 → ETA 16 Des 2023
- 1 unit Telehandler Multi → ETA 27 Des 2023.
b. Training alat berat → on progress training operasi dan maintenance alat berat Volvo, SDLG dan crane truck
6. Project Support 6. Project support: All material Mess E, Workshop building, camp01,02&03 earthwork, DW&WD, Storage LB3, sample prep
temporary, Water intake batu7, expedite and chase up material priority.
7. Issue 7.- Operasi Fuel station direksi keet.
- Pembagian Warehouse Direksi Keet untuk SCM dan Project → on progress.
- Instalasi 2 container kosong untuk storage consigment VHS Volvo
TOPIC FOLLOW UP ACTION STATUS PIC
PERMITTING
1. Activities 1.- Tali asih → done.
- Pos Kikil dan Pos Liyut → permintaan tidak dibongkar.
- Kegiatan survey di Kusan → done.
Follow up Eric
- Kegiatan survey PLN → done
- LDA 07 → done
- LHV05 & LHV07 → on progress
CSR
1. Pendapatan Riil 1.a. Pertanian:
- Desa Buluh Kuning: Penanaman tanaman baru komoditas cabai keriting dan tiung
- Desa Gendang Timburu: Kelompok Laudatosi: Panen 50 Kg; Omset Rp 3.000.000 (hasil panen diserap Tata Wisata)
- Desa Batuah: Pemasangan mulsa dan semai, penanaman rempah dan cabai tiung dan keriting. Jumlah anggota 20 orang.
Komunikasi dengan eks PETI dan ex Ojek panggul Kikil jumlah anggota 20 orang → Pemberian arahan terkait pertanian
dengan sistem keswadayaan.
b. Peternakan Itik:
- Desa Buluh Kuning: Kelompok Manunggal Berkah Bersama (3 orang); Jumlah ternak 130 ekor; Omset Rp 2.940.000 periode 8-14
Desember
- Desa Gendang Timburu: Kelompok Gendang Timburu (3 orang); Jumlah ternak 100; Omset Rp 1.840.000 periode 8-14 Desember

2. CSR Activities 2.a. Pendidikan:


- Pelaksanaan vocational training alat berat → done Continue Sept
- Penyerahan sertifikat dilakukan oleh KTT dan Direksi PTK.
- Pelaksanaan vocational training carpenter → on progress.
b. Infrastruktur: air bersih: penggantian MCB sumur bor air bersih di pasar Desa Buluh Kuning.
c. Ekonomi: penyerapan hasil makanan siap saji UMKM lokal
3. Internal Support 3.a. Survey: pendampingan survey awal dan pemasangan BM di Blok Kusan.
b. SCM: Koordinasi penawaran koperasi untuk angkut sampel dari Banian-IMK; Mendampingi SCM bertemu dengan pengurus
BUMDES Batuah.
c. HR: fasilitasi penerimaan surat lamaran pekerjaan dari masyarakat.
4. Humas & Isu 4.- Koordinasi dengan tokoh masyarakat Kumdatus.
- Koordinasi dengan tokoh masyarakat Gendang Timburu terkait pondok Pak Patok.
- Identifikasi isu terkait PETI di daerah Kura-kura.
- Partisipasi kegiatan Hari Juang TNI
- Memberikan pemahaman pada masyarakat terkait isu tenaga kerja.
SECURITY
1. Activity 1. Kegiatan Pengamanan:
a. Patroli Shift 1-2 sektor Utara dan Selatan
b. Pemasangan Police Line di area Eks PETI gunung Telkom
c. Patroli Karang Sindang dan aplusan BKO
d. Pendampingan kegiatan survey dan pengecekan PETI di Blok Kusan Hulu → berlanjut. Continue Demy
e. Pengawalan dan pengecekan sumur pantau → berlanjut.
f. Pengamanan kegiatan drilling → berlanjut.
g. Penjagaan puncak tower wifi → berlanjut
h. Escort → 17 trip
PROJECT SERVICE
1. Activities 1.- Fuel station → pembuatan dan pemasangan pagar.
Follow up Djundu
- Genset 110 KVA → akan dipasang di Banian (area fuel station atau current genset station).
ADMINISTRASI
1. Update - Recruitment progress masih continue. 1 safety officer, 1 senior mekanik, 1 dispatcher MPM.
- Hasil MCU akan di follow up oleh tim medic bagi karyawan yang memiliki hasil perlu ditindaklanjuti.
- POP → akan submit list pengajuan nama pada KTT (25 orang), Dilaksanakan pada minggu ke-3 bulan Januari 2024.
- ID card untuk masuk pagar → on progress follow up. On Progress Yusuf
- Asuransi Jhondeer → akan di follow up.
- Agar dibuat list recruitment report mingguan.
- TA dan medical check up karyawan → agar dapat diambil oleh admin di Finance (mempermudah mobilisasi).
IT
1. Koneksi 1.- Bandwidth Icon+ 200Mbps mengalami gangguan koneksi pada 13&14 Desember 2023
- Bandwidth Icon+ dedicated 30Mbps mengalami gangguan koneksi pada 13&14 Desember 2023
- Bandwidth Astinet 20Mbps mengalami gangguan koneksi pada 14 Desember 2023
2. Activities 2.- Penggantian ACCU dan MPPT controller solar panel.
- Config CH Radio Rig di unit.
Continue Dody
3. Issue 3.- Penambahan instalasi grounding gunung Telkom
- Electrical repeater Haraan & Menteu masih belum stabil.
- Follow up PR pending.
- Evaluasi CH radio area jalan dan hauling.
- Monitor unlicense software adobe, corel draw, etc.
MANAGEMENT 16 Hari menuju 22024, agar tetap Fokus menjaga Keselamatan Pertambangan