Proyek : Suppression System FM200

Lokasi : Pertamina - Kutowinangun

PROJECT SCHEDULE DURASI MINGGU -1 MINGGU -2 MINGGU -3 MINGGU -4

No Descriptions Dur Start Finish Hari-1 Hari-2 Hari-3 Hari-4 Hari-5 Hari-6 Hari-7 Hari-8 Hari-9 Hari-10 Hari-11 Hari-12 Hari-13 Hari-14 Hari-15 Hari-16 Hari-17 Hari-18 Hari-19 Hari-20 Hari-21 Hari-22 Hari-23 Hari-24 Hari-25

I PROJECT 25 d Hari-1 Hari-25

I.1 WORK OF PREPARATION 5d Hari-1 Hari-5

1 ENGINEERING 2d Hari-2 Hari-4

a. Issue Drawing for Approval 3d Hari-4 Hari-6

b. Purchase Requested of Material 3d Hari-3 Hari-5

2 Wiring Ruang MCC/Panel

a. Installation 5d Hari-6 Hari-11


- Wirirng kabel Smoke Detector, Flame Detector
- Wirirng kabel Alarm Bell, Evacuation, DNE Lamp,Abort& Manual
b. Pemasangan Equipment & Accessories 3 d Hari-12 Hari-15
- Pemasangan Alarm Bell, Evacuation, DNE Lamp,Abort& Manual

3 Piping Ruang MCC/Panel

a. Installation 5 d Hari-16 Hari-20


- Maping
- Pengukuran pipa & pabrikasi,painting
- Pemasangan support pipa
- Pemasangan pipa

b. Pemasangan Equipment & Accessories 2 d Hari-22 Hari-23


- Pemasangan Nozle, solenoid valve, cylinder

4 TESTING / SETING PANEL / SYSTEM 1 d Hari-24 Hari-24

5 Hand Over 1 d Hari-25 Hari-25