Boq Cilacap
Boq Cilacap
ARDISON
Direktur Utama
KOP PERUSAHAAN
A PEKERJAAN BETON
1 Kolom K1 ( 30 x 30 ) cm
- Beton K-250 A.4.1.1.8 7,110 m³ 937.354,00 6.664.586,94 733.104,56 7.397.691,50
- Pembesian Besi A.4.1.1.17 723,401 kg 13.734,05 9.935.225,50 1.092.874,81 11.028.100,31
- Begisting 2 x pakai A.4.1.1.22 37,920 m² 182.996,00 6.939.208,32 763.312,92 7.702.521,24
2 Kolom K3 ( 20 x 20 ) cm
- Beton K-250 A.4.1.1.8 0,608 m³ 937.354,00 569.911,23 62.690,24 632.601,47
- Pembesian Besi A.4.1.1.17 80,173 kg 13.734,05 1.101.099,99 121.121,00 1.222.220,99
- Begisting 2 x pakai A.4.1.1.22 4,053 m² 182.996,00 741.682,79 81.585,11 823.267,89
3 Kolom Praktis / KP ( 15 x 15 ) cm
- Beton K-225 A.4.1.1.7 1,997 m³ 923.072,33 1.843.375,44 202.771,30 2.046.146,74
- Pembesian Besi A.4.1.1.17 295,431 kg 13.734,05 4.057.464,13 446.321,05 4.503.785,18
- Begisting 2 x pakai A.4.1.1.22 8,875 m² 182.996,00 1.624.089,50 178.649,85 1.802.739,35
4 Balok Latai ( 12 x 12 ) cm
- Beton K-225 A.4.1.1.7 1,125 m³ 923.072,33 1.038.456,37 114.230,20 1.152.686,57
- Pembesian Besi A.4.1.1.17 166,220 kg 13.734,05 2.282.873,79 251.116,12 2.533.989,91
- Begisting 2 x pakai A.4.1.1.23 6,667 m² 187.396,00 1.249.369,13 137.430,60 1.386.799,74
5 Ringbalk ( 15 x 25 ) cm
- Beton K-225 A.4.1.1.7 15,150 m³ 923.072,33 13.984.545,80 1.538.300,04 15.522.845,84
- Pembesian Besi A.4.1.1.17 2.621,475 kg 13.734,05 36.003.468,72 3.960.381,56 39.963.850,28
- Begisting 2 x pakai A.4.1.1.23 87,533 m² 187.396,00 16.403.334,07 1.804.366,75 18.207.700,82
6 Balok Induk B1A ( 30 x 70 ) cm
- Beton K-250 A.4.1.1.8 1,453 m³ 937.354,00 1.361.975,36 149.817,29 1.511.792,65
- Pembesian Besi A.4.1.1.17 204,834 kg 13.734,05 2.813.200,40 309.452,04 3.122.652,44
- Begisting A.4.1.1.23 12,191 m² 187.396,00 2.284.544,64 251.299,91 2.535.844,55
7 Balok Induk B1 ( 25 x 55 ) cm
- Beton K-250 A.4.1.1.8 7,428 m³ 937.354,00 6.962.665,51 765.893,21 7.728.558,72
- Pembesian Besi A.4.1.1.17 1.464,240 kg 13.734,05 20.109.945,37 2.212.093,99 22.322.039,36
- Begisting A.4.1.1.23 76,701 m² 187.396,00 14.373.460,60 1.581.080,67 15.954.541,26
8 Balok Induk B2 ( 25 x 45 ) cm
- Beton K-250 A.4.1.1.8 14,091 m³ 937.354,00 13.208.255,21 1.452.908,07 14.661.163,29
- Pembesian Besi A.4.1.1.17 2.707,139 kg 13.734,05 37.179.982,38 4.089.798,06 41.269.780,45
- Begisting A.4.1.1.23 155,428 m² 187.396,00 29.126.585,49 3.203.924,40 32.330.509,89
9 Balok Anak B3 ( 20 x 40 ) cm
- Beton K-250 A.4.1.1.8 2,724 m³ 937.354,00 2.553.352,30 280.868,75 2.834.221,05
- Pembesian Besi A.4.1.1.17 601,049 kg 13.734,05 8.254.837,02 908.032,07 9.162.869,09
- Begisting A.4.1.1.23 36,974 m² 187.396,00 6.928.779,70 762.165,77 7.690.945,47
10 Balok Anak B4 ( 15 x 30 ) cm
- Beton K-250 A.4.1.1.8 0,648 m³ 937.354,00 607.405,39 66.814,59 674.219,99
- Pembesian Besi A.4.1.1.17 246,589 kg 13.734,05 3.386.665,66 372.533,22 3.759.198,88
- Begisting A.4.1.1.23 12,240 m² 187.396,00 2.293.727,04 252.309,97 2.546.037,01
11 Plat Beton, T: 12 cm
- Beton K-250 A.4.1.1.8 54,019 m³ 937.354,00 50.634.925,73 5.569.841,83 56.204.767,56
- Pembesian Besi A.4.1.1.17 5.716,234 kg 13.734,05 78.507.043,57 8.635.774,79 87.142.818,36
- Begisting A.4.1.1.24 432,585 m² 235.796,00 102.001.812,66 11.220.199,39 113.222.012,05
12 Plat Tangga, Anak Tangga & Bordes
- Beton K-250 A.4.1.1.8 2,448 m³ 937.354,00 2.294.642,59 252.410,69 2.547.053,28
- Pembesian Besi A.4.1.1.17 735,086 kg 13.734,05 10.095.707,88 1.110.527,87 11.206.235,74
- Begisting A.4.1.1.24 22,200 m² 235.796,00 5.234.671,20 575.813,83 5.810.485,03
13 Plat Topi - Topi Depan
- Beton K-225 A.4.1.1.7 2,324 m³ 923.072,33 2.145.220,09 235.974,21 2.381.194,31
- Pembesian Besi A.4.1.1.17 257,685 kg 13.734,05 3.539.058,67 389.296,45 3.928.355,13
- Begisting 2 x pakai A.4.1.1.23 13,280 m² 187.396,00 2.488.618,88 273.748,08 2.762.366,96
SUB TOTAL 569.236.610,33
" B. LANTAI 2 "
HARGA JUMLAH PAJAK JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA 11% BIAYA
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8
B PEKERJAAN PASANGAN & PLESTERAN
1 Pemasangan Dinding Bata Merah Tebal 1/2 Bata Camp. 1SP : 6PP A.4.4.1.11 476,338 m² 106.959,60 50.948.921,94 5.604.381,41 56.553.303,36
2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm A.4.4.2.6 952,676 m² 41.529,40 39.564.062,67 4.352.046,89 43.916.109,57
3 Pemasangan Acian A.4.4.2.27 952,676 m² 30.272,92 28.840.284,33 3.172.431,28 32.012.715,61
SUB TOTAL 132.482.128,54
C PEKERJAAN PINTU, JENDELA ALUMINIUM
1 1 Unit Pekerjaan Pasang Pintu - Type ( PD1 ) Ksn. 1 1,000 unit 2.750.000,00 2.750.000,00 302.500,00 3.052.500,00
2 1 Unit Pekerjaan Pasang Pintu - Type ( P1 ) Ksn. 2 7,000 unit 1.350.000,00 9.450.000,00 1.039.500,00 10.489.500,00
3 1 Unit Pekerjaan Pasang Pintu - Type ( P2 ) Ksn. 3 3,000 unit 1.475.000,00 4.425.000,00 486.750,00 4.911.750,00
4 1 Unit Pekerjaan Pasang Pintu - Type ( P4 ) Ksn. 5 2,000 unit 1.550.000,00 3.100.000,00 341.000,00 3.441.000,00
5 1 Unit Pekerjaan Pasang Jendela - Type ( J1 ) Ksn. 7 8,000 unit 1.250.000,00 10.000.000,00 1.100.000,00 11.100.000,00
6 1 Unit Pekerjaan Pasang Jendela - Type ( J2 ) Ksn. 8 6,000 unit 1.575.000,00 9.450.000,00 1.039.500,00 10.489.500,00
7 1 Unit Pekerjaan Pasang Boven - Type ( BV ) Ksn. 9 2,000 unit 750.000,00 1.500.000,00 165.000,00 1.665.000,00
8 Pemasangan Rooster 20 x 20 Taksir 288,000 bh 110.000,00 31.680.000,00 3.484.800,00 35.164.800,00
SUB TOTAL 80.314.050,00
D PEKERJAAN RANGKA & PENUTUP ATAP
1 Pemasangan Rangka Atap Bajaringan Taksir 423,440 m² 75.000,00 31.758.000,00 3.493.380,00 35.251.380,00
2 Pemasangan Atap Genteng Metal Lapis Pasir A.4.5.2.32 423,440 m² 81.279,00 34.416.779,76 3.785.845,77 38.202.625,53
3 Pemasangan Nok Genteng Metal A.4.5.2.36 55,900 m' 82.797,00 4.628.352,30 509.118,75 5.137.471,05
4 Pasang listplank Woodplank taksir 86,600 m' 110.000,00 9.526.000,00 1.047.860,00 10.573.860,00
5 Pasang talang vertikal dihitung 11,000 m' 175.000,00 1.925.000,00 211.750,00 2.136.750,00
SUB TOTAL 91.302.086,59
E PEKERJAAN LANGIT - LANGIT
1 Memasang Plafond PVC + Rangka Hollo dan List Taksir 392,614 m² 75.000,00 29.446.050,00 3.239.065,50 32.685.115,50
SUB TOTAL 32.685.115,50
F PEKERJAAN PENUTUP LANTAI & DINDING
1 Pemasangan Lantai Keramik 60 x 60 cm A.4.4.3.34m 313,944 m² 190.330,25 59.753.040,01 6.572.834,40 66.325.874,41
2 Pemasangan Lantai Keramik 25 x 25 cm A.4.4.3.36 8,416 m² 170.963,83 1.438.831,59 158.271,48 1.597.103,07
3 Pemasangan Dinding Keramik 25 x 40 cm A.4.4.3.54.c 35,720 m² 240.845,00 8.602.983,40 946.328,17 9.549.311,57
4 Memasang Stepnosing tangga 10 cm kasar garis garis Taksir 29,700 m' 125.000,00 3.712.500,00 408.375,00 4.120.875,00
SUB TOTAL 81.593.164,05
G PEKERJAAN ELEKTRIKAL
a Pekerjaan Penerangan
1 Downlight Slim 20 watt Philips Taksir 36,000 bh 127.500,00 4.590.000,00 504.900,00 5.094.900,00
2 Exhaust fan type wall kap. 50 CFM Taksir 3,000 bh 750.000,00 2.250.000,00 247.500,00 2.497.500,00
3 Saklar Ganda Taksir 4,000 bh 45.900,00 183.600,00 20.196,00 203.796,00
4 Saklar Tunggal Taksir 12,000 bh 41.250,00 495.000,00 54.450,00 549.450,00
5 Titik Inst. Penerangan (NYM 3 X 2,5 mm²) dalam conduit high impact 20 mm Taksir 39,000 titik 115.000,00 4.485.000,00 493.350,00 4.978.350,00
PPn 11 % -
TOTAL -
PEMBULATAN -
……………………………………………………………………………………………………………………
Kota./Kab.,Tgl/Bln/Thn
Penawar,
PT./CV. ……………………
Nama Terang
Jabatan
DAFTAR HARGA SATUAN PEKERJAAN
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
( Rp )
Penawar,
PT./CV. ……………………
Nama Terang
Jabatan
DAFTAR ANALISA HARGA SATUAN PEKERJAAN
HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
A A.2.3.1 HARGA SATUAN PEKERJAAN TANAH
2 A.2.3.1.9 1 m³ Pengurugan Kembali ( di hitung dari 1/3 kali koefisien Pekerjaan galian ) -
A TENAGA -
L.01 0,50 OH Pekerja 100.000,00 50.000,00
L.04 0,050 OH Mandor 140.000,00 7.000,00
B BAHAN
C PERALATAN
D Jumlah A + B + C 57.000,00
E Overhead & Profit 10% 5.700,00
F Harga Satuan Pekerjaan (D+E) 62.700,00
1 A.4.4.1.11 1 m² Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP -
A Tenaga -
L.01 0,30 OH Pekerja 100.000,00 30.000,00
L.02 0,1 OH Tukang Batu 120.000,00 12.000,00
L.03 0,01 OH Kepala Tukang 130.000,00 1.300,00
L.04 0,015 OH Mandor 140.000,00 2.100,00
B Bahan -
70 Buah Bata Merah Panggisari 460,00 32.200,00
8,32 Kg Portland Semen 1.083,33 9.013,33
0,049 m3 Pasir Pasang 110.000,00 5.390,00
C PERALATAN
D Jumlah A + B + C 92.003,33
E Overhead & Profit 10% 9.200,33
F Harga Satuan Pekerjaan (D+E) 101.203,67
D A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A.4.1.1.5 1 m³ Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 -
A Tenaga -
L.01 1,65 OH Pekerja 100.000,00 165.000,00
L.02 0,275 OH Tukang Batu 120.000,00 33.000,00
L.03 0,028 OH Kepala Tukang 130.000,00 3.640,00
L.04 0,083 OH Mandor 140.000,00 11.620,00
B Bahan -
326,00 Kg Portland Semen 1.083,33 353.166,67
0,48 kg Pasir Beton 110.000,00 52.800,00
0,71 kg Kerikil (maksimum 30 mm) 214.000,00 151.940,00
215,00 ltr Air 100 21.500,00
C PERALATAN
D Jumlah A + B + C 792.666,67
E Overhead & Profit 10% 79.266,67
F Harga Satuan Pekerjaan (D+E) 871.933,33
2 A.4.1.1.7 1 m³ Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 -
A Tenaga -
L.01 1,650 OH Pekerja 100.000,00 165.000,00
L.02 0,275 OH Tukang Batu 120.000,00 33.000,00
L.03 0,028 OH Kepala Tukang 130.000,00 3.640,00
L.04 0,083 OH Mandor 140.000,00 11.620,00
B Bahan -
371,00 Kg Portland Semen 1.083,33 401.916,67
0,44 kg Pasir Beton 110.000,00 48.400,00
0,72 kg Kerikil (maksimum 30 mm) 214.000,00 154.080,00
215,00 ltr Air 100,00 21.500,00
C PERALATAN
D Jumlah A + B + C 839.156,67
E Overhead & Profit 10% 83.915,67
F Harga Satuan Pekerjaan (D+E) 923.072,33
3 A.4.1.1.8 1 m³ Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 -
A Tenaga -
L.01 1,650 OH Pekerja 100.000,00 165.000,00
L.02 0,275 OH Tukang Batu 120.000,00 33.000,00
L.03 0,028 OH Kepala Tukang 130.000,00 3.640,00
L.04 0,083 OH Mandor 140.000,00 11.620,00
B Bahan -
384,00 Kg Portland Semen 1.083,33 416.000,00
0,43 kg Pasir Beton 110.000,00 47.300,00
0,72 kg Kerikil (maksimum 30 mm) 214.000,00 154.080,00
215,00 ltr Air 100,00 21.500,00
C PERALATAN
D Jumlah A + B + C 852.140,00
E Overhead & Profit 10% 85.214,00
F Harga Satuan Pekerjaan (D+E) 937.354,00
4 A.4.1.1.17 1 Kg Pembesian dg Besi Polos -
A Tenaga -
L.01 0,0070 OH Pekerja 100.000,00 700,00
L.02 0,0070 OH Tukang Besi 120.000,00 840,00
L.03 0,0007 OH Kepala Tukang 130.000,00 091,00
L.04 0,0004 OH Mandor 140.000,00 056,00
B Bahan -
1,05 Kg Besi Beton (polos) 10.000,00 10.500,00
0,015 Kg Kawat Beton 19.900,00 298,50
C PERALATAN
D Jumlah A + B + C 12.485,50
E Overhead & Profit 10% 1.248,55
F Harga Satuan Pekerjaan (D+E) 13.734,05
1 A.5.1.1.1 1 Unit Memasang Closet Duduk / Mono Blok+ Komplit & acc -
A Tenaga -
L.01 3,3 OH Pekerja 100.000,00 330.000,00
L.02 1,1 OH Tukang Batu 120.000,00 132.000,00
L.03 0,001 OH Kepala Tukang 130.000,00 130,00
L.04 0,16 OH Mandor 140.000,00 22.400,00
B Bahan
1 Buah Kloset Duduk / Monoblok 700.000,00 700.000,00
1 Buah Shower Spray 600.000,00 600.000,00
0,06 Kelengkapan 6% dari harga Kloset 42.000,00 2.520,00
C PERALATAN
D Jumlah A + B + C 1.787.050,00
E Overhead & Profit 10% 178.705,00
F Harga Satuan Pekerjaan (D+E) 1.965.755,00
1 A.4.7.1.10 1 m² Pengecat Tembok Baru / dalam (1lap.Plamir, 1lap Cat Dasar, 2 lap. Cat Penutup) -
A Tenaga -
L.01 0,02 OH Pekerja 100.000,00 2.000,00
L.02 0,063 OH Tukang Cat 120.000,00 7.560,00
L.03 0,0063 OH Kepala Tukang 130.000,00 819,00
L.04 0,0030 OH Mandor 140.000,00 420,00
B Bahan
0,1 Kg Plamir 25.000,00 2.500,00
0,1 Kg Cet Dasar 140.300,00 14.030,00
0,26 Kg Cat Penutup 2 kali ( sek. Mowilex / dalam ) 52.080,00 13.540,80
C PERALATAN
D Jumlah A + B + C 40.869,80
E Overhead & Profit 10% 4.086,98
F Harga Satuan Pekerjaan (D+E) 44.956,78