NO. URAIAN PEKERJAAN JUMLAH HARGA (Rp)

" A. LANTAI 1 "


A SISTEM MENEJEMEN KESELAMATAN KONTRUKSI ( SMKK ) Rp. 41.347.500,00
B PEKERJAAN PERSIAPAN Rp. 26.689.404,00
C PEKERJAAN TANAH Rp. 16.871.679,59
D PEKERJAAN BETON Rp. 181.191.596,89
E PEKERJAAN PASANGAN & PLESTERAN Rp. 247.793.531,54
F PEKERJAAN PINTU, JENDELA ALUMINIUM Rp. 66.777.600,00
G PEKERJAAN LANGIT - LANGIT Rp. 28.722.415,50
H PEKERJAAN PENUTUP LANTAI & DINDING Rp. 103.794.026,77
I PEKERJAAN ELEKTRIKAL Rp. 19.767.102,00
J PEKERJAAN PENGECATAN Rp. 52.559.158,97
K PEKERJAAN PLAMBING Rp. 37.394.229,45
JUMLAH - A Rp. 822.908.244,70
" B. LANTAI 2 "
A PEKERJAAN BETON Rp. 569.236.610,33
B PEKERJAAN PASANGAN & PLESTERAN Rp. 132.482.128,54
C PEKERJAAN PINTU, JENDELA ALUMINIUM Rp. 80.314.050,00
D PEKERJAAN RANGKA & PENUTUP ATAP Rp. 91.302.086,59
E PEKERJAAN LANGIT - LANGIT Rp. 32.685.115,50
F PEKERJAAN PENUTUP LANTAI & DINDING Rp. 81.593.164,05
G PEKERJAAN ELEKTRIKAL Rp. 40.565.616,00
H PEKERJAAN PENGECATAN Rp. 33.278.313,65
I PEKERJAAN PLAMBING Rp. 21.266.398,98
J PEKERJAAN LAIN - LAIN Rp. 70.368.271,66
JUMLAH - B Rp. 1.153.091.755,29

JUMLAH - A + B Rp. 1.976.000.000,00

===Satu Milyard Sembilan Ratus Tujuh Puluh Enam Juta Rupiah===

Bekasi, 26 April 2024

PT ARMA JAYA KONSTRUKSI

ARDISON
Direktur Utama
KOP PERUSAHAAN

RENCANA ANGGARAN BIAYA ( RAB )

PEKERJAAN : PENGEMBANGAN GEDUNG KANTOR PENCARIAN DAN PERTOLONGAN KELAS B CILACAP

LOKASI : KANTOR PENCARIAN DAN PERTOLONGAN KELAS B CILACAP


TAHUN ANGGARAN : 2024

" A. LANTAI 1 "


HARGA JUMLAH PAJAK JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA 11% BIAYA
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8

A SISTEM MENEJEMEN KESELAMATAN KONTRUKSI ( SMKK )


1 Penyiapan RKK Taksir 1,000 ls 3.000.000,00 3.000.000,00 330.000,00 3.330.000,00
- Pembuatan dokumen Rencana Keselamatan Kontruksi
- Pembuatan Prosedur dan Intruksi Kerja
- Penyiapan Formulir
2 Sosialisasi, Promosi dan Pelatihan
- Spanduk ( banner ) Taksir 1,000 ls 150.000,00 150.000,00 16.500,00 166.500,00
- Papan Informasi K3 Taksir 1,000 bh 550.000,00 550.000,00 60.500,00 610.500,00
3 Alat Pelindung Kerja dan Alat Pelindung Diri
- Topi Pelindung ( Safety Helmet ) Taksir 10,000 bh 175.000,00 1.750.000,00 192.500,00 1.942.500,00
- Pelindung Pernafasan dan Mulut ( Masker ) Taksir 20,000 bh 15.000,00 300.000,00 33.000,00 333.000,00
- Rompi ( Safety Vest ) Taksir 15,000 bh 155.000,00 2.325.000,00 255.750,00 2.580.750,00
- Sarung Tangan ( Safety Gloves ) Taksir 25,000 psg 55.000,00 1.375.000,00 151.250,00 1.526.250,00
- Sepatu Keselamatan ( Safety Shoes ) Taksir 10,000 psg 375.000,00 3.750.000,00 412.500,00 4.162.500,00
4 Asuransi dan Perizinan
- Asuransi Taksir 1,000 ls 15.000.000,00 15.000.000,00 1.650.000,00 16.650.000,00
5 Personel K3 kontruksi
- Petugas K3 kontruksi Taksir 1,000 ho 3.750.000,00 3.750.000,00 412.500,00 4.162.500,00
6 Fasilitas, Sarana dan Prasarana kesehatan
- Peralatan P3K ( Kotak P3K, Obat Luka, Perban, dll ) Taksir 1,000 ls 1.250.000,00 1.250.000,00 137.500,00 1.387.500,00
7 Rambu - Rambu yang diperlukan
- Rambu Peringatan Taksir 2,000 ls 150.000,00 300.000,00 33.000,00 333.000,00
8 Lain - Lain Pengendalian Risiko Keselamatan Kontruksi Taksir 1,000 ls 3.750.000,00 3.750.000,00 412.500,00 4.162.500,00
SUB TOTAL 41.347.500,00
B PEKERJAAN PERSIAPAN
1 Papan Nama Proyek Taksir 1,000 ls 550.000,00 550.000,00 60.500,00 610.500,00
2 Pemasangan bouwplank Taksir 1,000 ls 3.938.520,11 3.938.520,11 433.237,21 4.371.757,32
3 Direksi Keet / gudang kerja 3 m x 9 m (sewa) Taksir 27,000 m² 250.000,00 6.750.000,00 742.500,00 7.492.500,00
4 Bongkaran dan Pembersihan Lokasi Taksir 1,000 ls 6.505.988,00 6.505.988,00 715.658,68 7.221.646,68
5 Pengaman lokasi kerja / proyek dari seng t = 2 m (sewa) Taksir 60,000 m' 100.000,00 6.000.000,00 660.000,00 6.660.000,00
6 Administrasi/dokumentasi Taksir 1,000 ls 300.000,00 300.000,00 33.000,00 333.000,00
SUB TOTAL 26.689.404,00
C PEKERJAAN TANAH
1 Galian Tanah A.2.3.1.1 137,188 m³ 86.350,00 11.846.183,80 1.303.080,22 13.149.264,02
2 Urugan Tanah kembali A.2.3.1.9 34,297 m³ 62.700,00 2.150.421,90 236.546,41 2.386.968,31
3 Urugan Pasir A.2.3.1.11 7,846 m³ 153.340,00 1.203.105,64 132.341,62 1.335.447,26
SUB TOTAL 16.871.679,59
D PEKERJAAN BETON
1 Trus Pile Ø 30
- Beton K-225 A.4.1.1.7 6,041 m³ 923.072,33 5.576.279,95 613.390,79 6.189.670,74
- Pembesian Besi A.4.1.1.17 925,827 kg 13.734,05 12.715.354,31 1.398.688,97 14.114.043,28
- Begisting Buis Beton Ø 30 cm Taksir 85,500 m' 115.550,00 9.879.525,00 1.086.747,75 10.966.272,75
2 Lantai Kerja 5 cm, K-175 A.4.1.1.5 1,336 m³ 908.893,33 1.214.281,49 133.570,96 1.347.852,45
3 Foot Plat F1 ( 120 x 120 ) cm
- Beton K-250 A.4.1.1.8 6,480 m³ 937.354,00 6.074.053,92 668.145,93 6.742.199,85
- Pembesian Besi A.4.1.1.17 1.191,456 kg 13.734,05 16.363.516,28 1.799.986,79 18.163.503,07
4 Foot Plat F2 & F3 ( 80 x 80 ) cm
- Beton K-250 A.4.1.1.8 1,536 m³ 937.354,00 1.439.775,74 158.375,33 1.598.151,08
- Pembesian Besi A.4.1.1.17 252,160 kg 13.734,05 3.463.178,05 380.949,59 3.844.127,63
5 Sloof_ S1 ( 20 x 30 ) cm
- Beton K-225 A.4.1.1.7 7,020 m³ 923.072,33 6.479.967,76 712.796,45 7.192.764,21
- Pembesian Besi A.4.1.1.17 924,550 kg 13.734,05 12.697.815,93 1.396.759,75 14.094.575,68
- Begisting 2 x pakai A.4.1.1.21 35,100 m² 126.247,00 4.431.269,70 487.439,67 4.918.709,37
6 Sloof_ S2 ( 15 x 20 ) cm
- Beton K-225 A.4.1.1.7 4,545 m³ 923.072,33 4.195.363,74 461.490,01 4.656.853,75
- Pembesian Besi A.4.1.1.17 526,069 kg 13.734,05 7.225.057,95 794.756,37 8.019.814,32
- Begisting 2 x pakai A.4.1.1.21 30,300 m² 126.247,00 3.825.284,10 420.781,25 4.246.065,35
7 Kaki Kolom F1 ( 30 x 30 ) cm
- Beton K-250 A.4.1.1.8 1,881 m³ 937.354,00 1.763.162,87 193.947,92 1.957.110,79
- Pembesian Besi A.4.1.1.17 407,912 kg 13.734,05 5.602.283,80 616.251,22 6.218.535,02
- Begisting 2 x pakai A.4.1.1.22 8,360 m² 182.996,00 1.529.846,56 168.283,12 1.698.129,68
8 Kaki Kolom F2 ( 25 x 25 ) cm
- Beton K-250 A.4.1.1.8 0,375 m³ 937.354,00 351.507,75 38.665,85 390.173,60
- Pembesian Besi A.4.1.1.17 74,368 kg 13.734,05 1.021.373,83 112.351,12 1.133.724,95
- Begisting 2 x pakai A.4.1.1.22 3,650 m² 182.996,00 667.935,40 73.472,89 741.408,29
9 Kolom K1 ( 30 x 30 ) cm
- Beton K-250 A.4.1.1.8 6,071 m³ 937.354,00 5.690.676,13 625.974,37 6.316.650,51
- Pembesian Besi A.4.1.1.17 1.115,002 kg 13.734,05 15.313.493,22 1.684.484,25 16.997.977,47
- Begisting 2 x pakai A.4.1.1.22 40,470 m² 182.996,00 7.405.848,12 814.643,29 8.220.491,41
10 Kolom K2 ( 25 x 25 ) cm
- Beton K-250 A.4.1.1.8 0,913 m³ 937.354,00 855.804,20 94.138,46 949.942,66
- Pembesian Besi A.4.1.1.17 180,961 kg 13.734,05 2.485.327,42 273.386,02 2.758.713,44
- Begisting 2 x pakai A.4.1.1.22 4,867 m² 182.996,00 890.641,53 97.970,57 988.612,10
11 Kolom K3 ( 20 x 20 ) cm
- Beton K-250 A.4.1.1.8 0,584 m³ 937.354,00 547.414,74 60.215,62 607.630,36
- Pembesian Besi A.4.1.1.17 96,472 kg 13.734,05 1.324.951,27 145.744,64 1.470.695,91
- Begisting 2 x pakai A.4.1.1.22 3,893 m² 182.996,00 712.403,43 78.364,38 790.767,81
12 Kolom Praktis / KP ( 15 x 15 ) cm
- Beton K-225 A.4.1.1.7 3,754 m³ 923.072,33 3.465.213,53 381.173,49 3.846.387,01
- Pembesian Besi A.4.1.1.17 593,738 kg 13.734,05 8.154.427,38 896.987,01 9.051.414,39
- Begisting 2 x pakai A.4.1.1.22 12,514 m² 182.996,00 2.290.011,94 251.901,31 2.541.913,26
13 Balok Latai ( 12 x 12 ) cm
- Beton K-225 A.4.1.1.7 1,592 m³ 923.072,33 1.469.531,15 161.648,43 1.631.179,58
- Pembesian Besi A.4.1.1.17 235,268 kg 13.734,05 3.231.182,48 355.430,07 3.586.612,55
- Begisting 2 x pakai A.4.1.1.23 7,077 m² 187.396,00 1.326.201,49 145.882,16 1.472.083,66
14 Balok Frame Pintu Urtama
- Beton K-225 A.4.1.1.7 0,216 m³ 923.072,33 199.383,62 21.932,20 221.315,82
- Pembesian Besi A.4.1.1.17 59,460 kg 13.734,05 816.626,61 89.828,93 906.455,54
- Begisting 2 x pakai A.4.1.1.23 2,880 m² 187.396,00 539.700,48 59.367,05 599.067,53
SUB TOTAL 181.191.596,89
E PEKERJAAN PASANGAN & PLESTERAN
1 Pasangan Pondasi Batu Belah 1 : 6 A.3.2.1.4 48,825 m³ 711.381,00 34.733.177,33 3.820.649,51 38.553.826,83
2 Pemasangan Dinding Bata Merah Tebal 1/2 Bata Camp. 1SP : 6PP A.4.4.1.11 752,319 m² 106.959,60 80.467.739,31 8.851.451,32 89.319.190,64
3 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm A.4.4.2.6 1.504,638 m² 41.529,40 62.486.713,36 6.873.538,47 69.360.251,83
4 Pemasangan Acian A.4.4.2.27 1.504,638 m² 30.272,92 45.549.785,80 5.010.476,44 50.560.262,24
SUB TOTAL 247.793.531,54
" A. LANTAI 1 "
HARGA JUMLAH PAJAK JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA 11% BIAYA
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8
F PEKERJAAN PINTU, JENDELA ALUMINIUM
1 1 Unit Pekerjaan Pasang Pintu - Type ( PD1 ) Ksn. 1 3,000 unit 2.750.000,00 8.250.000,00 907.500,00 9.157.500,00
2 1 Unit Pekerjaan Pasang Pintu - Type ( P1 ) Ksn. 2 12,000 unit 1.350.000,00 16.200.000,00 1.782.000,00 17.982.000,00
3 1 Unit Pekerjaan Pasang Pintu - Type ( P2 ) Ksn. 3 3,000 unit 1.475.000,00 4.425.000,00 486.750,00 4.911.750,00
4 1 Unit Pekerjaan Pasang Pintu - Type ( P3 ) Ksn. 4 1,000 unit 1.550.000,00 1.550.000,00 170.500,00 1.720.500,00
5 1 Unit Pekerjaan Pasang Pintu - Type ( P4 ) Ksn. 5 1,000 unit 1.250.000,00 1.250.000,00 137.500,00 1.387.500,00
6 1 Unit Pekerjaan Pasang Pintu - Type ( PD2 ) Ksn. 6 1,000 unit 1.950.000,00 1.950.000,00 214.500,00 2.164.500,00
7 1 Unit Pekerjaan Pasang Jendela - Type ( J1 ) Ksn. 7 7,000 unit 1.575.000,00 11.025.000,00 1.212.750,00 12.237.750,00
8 1 Unit Pekerjaan Pasang Jendela - Type ( J2 ) Ksn. 8 3,000 unit 1.670.000,00 5.010.000,00 551.100,00 5.561.100,00
9 1 Unit Pekerjaan Pasang Boven - Type ( BV ) Ksn. 9 4,000 unit 750.000,00 3.000.000,00 330.000,00 3.330.000,00
10 Bongkar Pasang Pintu Utama Kaca Frameless + Asesoris Taksir 1,000 unit 7.500.000,00 7.500.000,00 825.000,00 8.325.000,00
SUB TOTAL 66.777.600,00
G PEKERJAAN LANGIT - LANGIT
1 Memasang Plafond PVC + Rangka Hollo dan List Taksir 345,014 m² 75.000,00 25.876.050,00 2.846.365,50 28.722.415,50
SUB TOTAL 28.722.415,50
H PEKERJAAN PENUTUP LANTAI & DINDING
1 Pemasangan Ubin Granito Uk. 60 x 60 cm A.4.4.3.9.m 28,640 m² 198.533,50 5.685.999,44 625.459,94 6.311.459,38
2 Pemasangan Lantai Keramik 60 x 60 cm A.4.4.3.34m 388,832 m² 190.330,25 74.006.491,77 8.140.714,09 82.147.205,86
3 Pemasangan Lantai Keramik 25 x 25 cm A.4.4.3.36 11,838 m² 170.963,83 2.023.869,82 222.625,68 2.246.495,50
4 Pemasangan Dinding Keramik 25 x 40 cm A.4.4.3.54.c 48,960 m² 240.845,00 11.791.771,20 1.297.094,83 13.088.866,03
SUB TOTAL 103.794.026,77
I PEKERJAAN ELEKTRIKAL
a Pekerjaan Penerangan
1 Lampu RMI LED 2 X 18 Watt ( casing 63,5 x 32 x 8,5 ) Taksir 6,000 bh 135.000,00 810.000,00 89.100,00 899.100,00
2 Downlight Slim 20 watt Philips Taksir 40,000 bh 127.500,00 5.100.000,00 561.000,00 5.661.000,00
3 Exhaust fan type wall kap. 50 CFM Taksir 4,000 bh 750.000,00 3.000.000,00 330.000,00 3.330.000,00
4 Saklar Ganda Taksir 8,000 bh 45.900,00 367.200,00 40.392,00 407.592,00
5 Saklar Tunggal Taksir 12,000 bh 41.250,00 495.000,00 54.450,00 549.450,00
6 Titik Inst. Penerangan (NYM 3 X 2,5 mm²) dalam conduit high impact 20 mm Taksir 50,000 titik 115.000,00 5.750.000,00 632.500,00 6.382.500,00

b Pekerjaan Stop Kontak


1 Stop kontak 200 VA (umum) Taksir 12,000 bh 75.500,00 906.000,00 99.660,00 1.005.660,00
2 Titik inst. Stop Kontak (NYM 3 X 2,5 mm²) dalam Conduit High Impact Ø 20 Taksir 12,000 titik 115.000,00 1.380.000,00 151.800,00 1.531.800,00
SUB TOTAL 19.767.102,00
J PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru Nodrop A.4.7.1.10 1.053,247 m² 44.956,78 47.350.593,66 5.208.565,30 52.559.158,97
SUB TOTAL 52.559.158,97
K PEKERJAAN PLAMBING
1 Memasang Closet Duduk / Mono Blok+ Komplit & acc A.5.1.1.1 4,000 Unit 1.965.755,00 7.863.020,00 864.932,20 8.727.952,20
2 Memasang Urinoir A.5.1.1.4 2,000 Unit 1.721.060,00 3.442.120,00 378.633,20 3.820.753,20
3 Memasang Wastafel A.5.1.1.5 3,000 Unit 1.277.650,00 3.832.950,00 421.624,50 4.254.574,50
4 Pemasangan Floor Drain A.5.1.1.14 5,000 bh 121.000,00 605.000,00 66.550,00 671.550,00
5 Pemasangan Kran A.5.1.1.19 4,000 bh 122.001,00 488.004,00 53.680,44 541.684,44
6 Pemasangan Zink + Kran Cuci Piring Stainless Fleksibel A.5.1.1.19.a 1,000 bh 1.017.401,00 1.017.401,00 111.914,11 1.129.315,11
7 Pipa Air Bersih PVC AW - dia. 3/4" Taksir 70,000 m' 88.000,00 6.160.000,00 677.600,00 6.837.600,00
8 Fitting & Accessories Taksir 1,000 ls 150.000,00 150.000,00 16.500,00 166.500,00
9 Pipa Air Bekas PVC AW - dia. 3" Taksir 70,000 m' 96.500,00 6.755.000,00 743.050,00 7.498.050,00
10 Pipa Air Kotor Padat PVC AW - dia.4" Taksir 25,000 m' 135.000,00 3.375.000,00 371.250,00 3.746.250,00
SUB TOTAL 37.394.229,45
JUMLAH KONSTRUKSI "A. LANTAI 1" -
" B. LANTAI 2 "
HARGA JUMLAH PAJAK JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA 11% BIAYA
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8

A PEKERJAAN BETON
1 Kolom K1 ( 30 x 30 ) cm
- Beton K-250 A.4.1.1.8 7,110 m³ 937.354,00 6.664.586,94 733.104,56 7.397.691,50
- Pembesian Besi A.4.1.1.17 723,401 kg 13.734,05 9.935.225,50 1.092.874,81 11.028.100,31
- Begisting 2 x pakai A.4.1.1.22 37,920 m² 182.996,00 6.939.208,32 763.312,92 7.702.521,24
2 Kolom K3 ( 20 x 20 ) cm
- Beton K-250 A.4.1.1.8 0,608 m³ 937.354,00 569.911,23 62.690,24 632.601,47
- Pembesian Besi A.4.1.1.17 80,173 kg 13.734,05 1.101.099,99 121.121,00 1.222.220,99
- Begisting 2 x pakai A.4.1.1.22 4,053 m² 182.996,00 741.682,79 81.585,11 823.267,89
3 Kolom Praktis / KP ( 15 x 15 ) cm
- Beton K-225 A.4.1.1.7 1,997 m³ 923.072,33 1.843.375,44 202.771,30 2.046.146,74
- Pembesian Besi A.4.1.1.17 295,431 kg 13.734,05 4.057.464,13 446.321,05 4.503.785,18
- Begisting 2 x pakai A.4.1.1.22 8,875 m² 182.996,00 1.624.089,50 178.649,85 1.802.739,35
4 Balok Latai ( 12 x 12 ) cm
- Beton K-225 A.4.1.1.7 1,125 m³ 923.072,33 1.038.456,37 114.230,20 1.152.686,57
- Pembesian Besi A.4.1.1.17 166,220 kg 13.734,05 2.282.873,79 251.116,12 2.533.989,91
- Begisting 2 x pakai A.4.1.1.23 6,667 m² 187.396,00 1.249.369,13 137.430,60 1.386.799,74
5 Ringbalk ( 15 x 25 ) cm
- Beton K-225 A.4.1.1.7 15,150 m³ 923.072,33 13.984.545,80 1.538.300,04 15.522.845,84
- Pembesian Besi A.4.1.1.17 2.621,475 kg 13.734,05 36.003.468,72 3.960.381,56 39.963.850,28
- Begisting 2 x pakai A.4.1.1.23 87,533 m² 187.396,00 16.403.334,07 1.804.366,75 18.207.700,82
6 Balok Induk B1A ( 30 x 70 ) cm
- Beton K-250 A.4.1.1.8 1,453 m³ 937.354,00 1.361.975,36 149.817,29 1.511.792,65
- Pembesian Besi A.4.1.1.17 204,834 kg 13.734,05 2.813.200,40 309.452,04 3.122.652,44
- Begisting A.4.1.1.23 12,191 m² 187.396,00 2.284.544,64 251.299,91 2.535.844,55
7 Balok Induk B1 ( 25 x 55 ) cm
- Beton K-250 A.4.1.1.8 7,428 m³ 937.354,00 6.962.665,51 765.893,21 7.728.558,72
- Pembesian Besi A.4.1.1.17 1.464,240 kg 13.734,05 20.109.945,37 2.212.093,99 22.322.039,36
- Begisting A.4.1.1.23 76,701 m² 187.396,00 14.373.460,60 1.581.080,67 15.954.541,26
8 Balok Induk B2 ( 25 x 45 ) cm
- Beton K-250 A.4.1.1.8 14,091 m³ 937.354,00 13.208.255,21 1.452.908,07 14.661.163,29
- Pembesian Besi A.4.1.1.17 2.707,139 kg 13.734,05 37.179.982,38 4.089.798,06 41.269.780,45
- Begisting A.4.1.1.23 155,428 m² 187.396,00 29.126.585,49 3.203.924,40 32.330.509,89
9 Balok Anak B3 ( 20 x 40 ) cm
- Beton K-250 A.4.1.1.8 2,724 m³ 937.354,00 2.553.352,30 280.868,75 2.834.221,05
- Pembesian Besi A.4.1.1.17 601,049 kg 13.734,05 8.254.837,02 908.032,07 9.162.869,09
- Begisting A.4.1.1.23 36,974 m² 187.396,00 6.928.779,70 762.165,77 7.690.945,47
10 Balok Anak B4 ( 15 x 30 ) cm
- Beton K-250 A.4.1.1.8 0,648 m³ 937.354,00 607.405,39 66.814,59 674.219,99
- Pembesian Besi A.4.1.1.17 246,589 kg 13.734,05 3.386.665,66 372.533,22 3.759.198,88
- Begisting A.4.1.1.23 12,240 m² 187.396,00 2.293.727,04 252.309,97 2.546.037,01
11 Plat Beton, T: 12 cm
- Beton K-250 A.4.1.1.8 54,019 m³ 937.354,00 50.634.925,73 5.569.841,83 56.204.767,56
- Pembesian Besi A.4.1.1.17 5.716,234 kg 13.734,05 78.507.043,57 8.635.774,79 87.142.818,36
- Begisting A.4.1.1.24 432,585 m² 235.796,00 102.001.812,66 11.220.199,39 113.222.012,05
12 Plat Tangga, Anak Tangga & Bordes
- Beton K-250 A.4.1.1.8 2,448 m³ 937.354,00 2.294.642,59 252.410,69 2.547.053,28
- Pembesian Besi A.4.1.1.17 735,086 kg 13.734,05 10.095.707,88 1.110.527,87 11.206.235,74
- Begisting A.4.1.1.24 22,200 m² 235.796,00 5.234.671,20 575.813,83 5.810.485,03
13 Plat Topi - Topi Depan
- Beton K-225 A.4.1.1.7 2,324 m³ 923.072,33 2.145.220,09 235.974,21 2.381.194,31
- Pembesian Besi A.4.1.1.17 257,685 kg 13.734,05 3.539.058,67 389.296,45 3.928.355,13
- Begisting 2 x pakai A.4.1.1.23 13,280 m² 187.396,00 2.488.618,88 273.748,08 2.762.366,96
SUB TOTAL 569.236.610,33
" B. LANTAI 2 "
HARGA JUMLAH PAJAK JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA 11% BIAYA
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8
B PEKERJAAN PASANGAN & PLESTERAN
1 Pemasangan Dinding Bata Merah Tebal 1/2 Bata Camp. 1SP : 6PP A.4.4.1.11 476,338 m² 106.959,60 50.948.921,94 5.604.381,41 56.553.303,36
2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm A.4.4.2.6 952,676 m² 41.529,40 39.564.062,67 4.352.046,89 43.916.109,57
3 Pemasangan Acian A.4.4.2.27 952,676 m² 30.272,92 28.840.284,33 3.172.431,28 32.012.715,61
SUB TOTAL 132.482.128,54
C PEKERJAAN PINTU, JENDELA ALUMINIUM
1 1 Unit Pekerjaan Pasang Pintu - Type ( PD1 ) Ksn. 1 1,000 unit 2.750.000,00 2.750.000,00 302.500,00 3.052.500,00
2 1 Unit Pekerjaan Pasang Pintu - Type ( P1 ) Ksn. 2 7,000 unit 1.350.000,00 9.450.000,00 1.039.500,00 10.489.500,00
3 1 Unit Pekerjaan Pasang Pintu - Type ( P2 ) Ksn. 3 3,000 unit 1.475.000,00 4.425.000,00 486.750,00 4.911.750,00
4 1 Unit Pekerjaan Pasang Pintu - Type ( P4 ) Ksn. 5 2,000 unit 1.550.000,00 3.100.000,00 341.000,00 3.441.000,00
5 1 Unit Pekerjaan Pasang Jendela - Type ( J1 ) Ksn. 7 8,000 unit 1.250.000,00 10.000.000,00 1.100.000,00 11.100.000,00
6 1 Unit Pekerjaan Pasang Jendela - Type ( J2 ) Ksn. 8 6,000 unit 1.575.000,00 9.450.000,00 1.039.500,00 10.489.500,00
7 1 Unit Pekerjaan Pasang Boven - Type ( BV ) Ksn. 9 2,000 unit 750.000,00 1.500.000,00 165.000,00 1.665.000,00
8 Pemasangan Rooster 20 x 20 Taksir 288,000 bh 110.000,00 31.680.000,00 3.484.800,00 35.164.800,00
SUB TOTAL 80.314.050,00
D PEKERJAAN RANGKA & PENUTUP ATAP
1 Pemasangan Rangka Atap Bajaringan Taksir 423,440 m² 75.000,00 31.758.000,00 3.493.380,00 35.251.380,00
2 Pemasangan Atap Genteng Metal Lapis Pasir A.4.5.2.32 423,440 m² 81.279,00 34.416.779,76 3.785.845,77 38.202.625,53
3 Pemasangan Nok Genteng Metal A.4.5.2.36 55,900 m' 82.797,00 4.628.352,30 509.118,75 5.137.471,05
4 Pasang listplank Woodplank taksir 86,600 m' 110.000,00 9.526.000,00 1.047.860,00 10.573.860,00
5 Pasang talang vertikal dihitung 11,000 m' 175.000,00 1.925.000,00 211.750,00 2.136.750,00
SUB TOTAL 91.302.086,59
E PEKERJAAN LANGIT - LANGIT
1 Memasang Plafond PVC + Rangka Hollo dan List Taksir 392,614 m² 75.000,00 29.446.050,00 3.239.065,50 32.685.115,50
SUB TOTAL 32.685.115,50
F PEKERJAAN PENUTUP LANTAI & DINDING
1 Pemasangan Lantai Keramik 60 x 60 cm A.4.4.3.34m 313,944 m² 190.330,25 59.753.040,01 6.572.834,40 66.325.874,41
2 Pemasangan Lantai Keramik 25 x 25 cm A.4.4.3.36 8,416 m² 170.963,83 1.438.831,59 158.271,48 1.597.103,07
3 Pemasangan Dinding Keramik 25 x 40 cm A.4.4.3.54.c 35,720 m² 240.845,00 8.602.983,40 946.328,17 9.549.311,57
4 Memasang Stepnosing tangga 10 cm kasar garis garis Taksir 29,700 m' 125.000,00 3.712.500,00 408.375,00 4.120.875,00
SUB TOTAL 81.593.164,05
G PEKERJAAN ELEKTRIKAL
a Pekerjaan Penerangan
1 Downlight Slim 20 watt Philips Taksir 36,000 bh 127.500,00 4.590.000,00 504.900,00 5.094.900,00
2 Exhaust fan type wall kap. 50 CFM Taksir 3,000 bh 750.000,00 2.250.000,00 247.500,00 2.497.500,00
3 Saklar Ganda Taksir 4,000 bh 45.900,00 183.600,00 20.196,00 203.796,00
4 Saklar Tunggal Taksir 12,000 bh 41.250,00 495.000,00 54.450,00 549.450,00
5 Titik Inst. Penerangan (NYM 3 X 2,5 mm²) dalam conduit high impact 20 mm Taksir 39,000 titik 115.000,00 4.485.000,00 493.350,00 4.978.350,00

b Pekerjaan Stop Kontak


1 Stop kontak 200 VA (umum) Taksir 14,000 bh 75.500,00 1.057.000,00 116.270,00 1.173.270,00
2 Titik inst. Stop Kontak (NYM 3 X 2,5 mm²) dalam Conduit High Impact Ø 20 Taksir 14,000 titik 115.000,00 1.610.000,00 177.100,00 1.787.100,00

c Pekerjaan Penangkal Petir


1 Head Penangkal Petir non radioaktif radius 100 m Taksir 1,000 unit 7.450.000,00 7.450.000,00 819.500,00 8.269.500,00
2 Down Conductor NYY 1x70 mm Taksir 15,000 m 115.000,00 1.725.000,00 189.750,00 1.914.750,00
3 Grounding Sistem, Bak Kontrol dan instalasi Taksir 1,000 unit 325.000,00 325.000,00 35.750,00 360.750,00
4 Ijin Depnaker Taksir 1,000 ls 2.875.000,00 2.875.000,00 316.250,00 3.191.250,00
5 Testing comissioning Taksir 1,000 ls 9.500.000,00 9.500.000,00 1.045.000,00 10.545.000,00
SUB TOTAL 40.565.616,00
" B. LANTAI 2 "
HARGA JUMLAH PAJAK JUMLAH
NO URAIAN PEKERJAAN ANALISA VOLUME SATUAN HARGA 11% BIAYA
Rp. Rp. Rp. Rp.
1 2 3 4 5 6 7 8
H PEKERJAAN PENGECATAN
1 Pengecat Tembok Baru A.4.7.1.10 666,873 m² 44.956,78 29.980.462,75 3.297.850,90 33.278.313,65
SUB TOTAL 33.278.313,65
I PEKERJAAN PLAMBING
1 Memasang Closet Duduk / Mono Blok+ Komplit & acc A.5.1.1.1 3,000 Unit 1.965.755,00 5.897.265,00 648.699,15 6.545.964,15
2 Memasang Wastafel A.5.1.1.5 1,000 Unit 1.277.650,00 1.277.650,00 140.541,50 1.418.191,50
3 Pemasangan Floor Drain A.5.1.1.14 4,000 bh 121.000,00 484.000,00 53.240,00 537.240,00
4 Pemasangan Kran A.5.1.1.19 3,000 bh 122.001,00 366.003,00 40.260,33 406.263,33
5 Pipa Air Bersih PVC AW - dia. 3/4" Taksir 38,000 m' 88.000,00 3.344.000,00 367.840,00 3.711.840,00
6 Fitting & Accessories Taksir 1,000 ls 150.000,00 150.000,00 16.500,00 166.500,00
7 Pipa Air Bekas PVC AW - dia. 3" Taksir 40,000 m' 96.500,00 3.860.000,00 424.600,00 4.284.600,00
8 Pipa Air Kotor Padat PVC AW - dia.4" Taksir 28,000 m' 135.000,00 3.780.000,00 415.800,00 4.195.800,00
SUB TOTAL 21.266.398,98
J PEKERJAAN LAIN - LAIN
1 Memasang Alumunium Composite Panel ( ACP ) Dihit. 01 80,800 m² 350.257,17 28.300.779,34 3.113.085,73 31.413.865,06
2 Pekerjaan Raling Tangga Taksir 9,600 m² 750.000,00 7.200.000,00 792.000,00 7.992.000,00
3 Pemasangan Partisi Gypsum Dua Sisi Rangka Metal Stud + cat Taksir 221,881 m² 55.000,00 12.203.455,00 1.342.380,05 13.545.835,05
4 Pemasangan Atap Kaca Teras ( kaca 8mm + rangka aluminium ) Taksir 22,800 m² 125.000,00 2.850.000,00 313.500,00 3.163.500,00
5 Pemasangan Tiang Api Prosot ø 4 inci Taksir 1,000 ls 3.750.000,00 3.750.000,00 412.500,00 4.162.500,00
6 Pemasangan Kisi Kisi dr Hollo ( Belakang Tulisan ) Taksir 22,523 m² 135.000,00 3.040.605,00 334.466,55 3.375.071,55
7 Pasang Huruf " BASARNAS CILACAP " Stailes stell Taksir 1,000 ls 5.500.000,00 5.500.000,00 605.000,00 6.105.000,00
8 Pengadaan dan Pemasangan toren air 1000 liter Taksir 1,000 bh 550.000,00 550.000,00 60.500,00 610.500,00
SUB TOTAL 70.368.271,66
JUMLAH KONSTRUKSI "B. LANTAI 2" -
-

JUMLAH TOTAL KONSTRUKSI " A + B " -

PPn 11 % -

TOTAL -

PEMBULATAN -

……………………………………………………………………………………………………………………
Kota./Kab.,Tgl/Bln/Thn
Penawar,
PT./CV. ……………………

Nama Terang

Jabatan
DAFTAR HARGA SATUAN PEKERJAAN

HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
( Rp )

A A.2.3.1 HARGA SATUAN PEKERJAAN TANAH


1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m³ 86.350,00
2 A.2.3.1.9 Pengurugan Kembali ( di hitung dari 1/3 kali koefisien Pekerjaan galian ) m³ 62.700,00
3 A.2.3.1.11 Urugan Pasir m³ 153.340,00

B A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI


1 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m³ 711.381,00

C A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


1 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m² 101.203,67

D A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN


1 A.4.4.2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m² 41.529,40
2 A.4.4.2.27 Pemasangan Acian m² 30.272,92

E A.4.1.1 HARGA SATUAN PEKERJAAN BETON


1 A.4.1.1.5 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 m³ 871.933,33
2 A.4.1.1.7 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 m³ 923.072,33
3 A.4.1.1.8 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m³ 937.354,00
4 A.4.1.1.17 Pembesian dg Besi Polos kg 13.734,05
5 A.4.1.1.21 Memasang Bekisting untuk Sloof m² 126.247,00
6 A.4.1.1.22 Memasang Bekisting untuk Kolom m² 182.996,00
7 A.4.1.1.23 Memasang Bekisting untuk Balok m² 187.396,00
8 A.4.1.1.24 Memasang Bekisting untuk Lantai m² 235.796,00

F A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 A.4.5.2.32 Pemasangan Atap Genteng Metal Lapis Pasir m² 81.279,00
2 A.4.5.2.36 Pemasangan Nok Genteng Metal m' 82.797,00

G A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT


1 Dihit. 01 Memasang Alumunium Composite Panel ( ACP ) m² 745.257,17

H A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


1 A.5.1.1.1 Memasang Closet Duduk / Mono Blok+ Komplit & acc Unit 1.965.755,00
2 A.5.1.1.4 Memasang Urinoir Unit 1.718.860,00
3 A.5.1.1.5 Memasang Wastafel Unit 1.275.450,00
4 A.5.1.1.14 Pemasangan Floor Drain buah 121.000,00
5 A.5.1.1.19 Pemasangan Kran buah 122.001,00
6 A.5.1.1.19.a Pemasangan Zink + Kran Cuci Piring Stainless Fleksibel buah 1.017.401,00

I A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.11 Pemasangan Kusen Allumunium 4" m' 164.354,30

J A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA


1 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m² 114.460,50

K A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING


1 A.4.4.3.9.m Pemasangan lantai Ubin Granito Uk. 60 x 60 cm m² 198.533,50
2 A.4.4.3.34m Pemasangan Lantai Keramik 60 x 60 cm m² 190.330,25
3 A.4.4.3.36 Pemasangan Lantai Keramik 25 x 25 cm m² 170.963,83
4 A.4.4.3.54.c Pemasangan Dinding Keramik 25 x 40 cm m² 236.789,67
HARGA SATUAN
NO. KODE URAIAN PEKERJAAN SAT PEKERJAAN
( Rp )
L A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN
1 A.4.7.1.10 Pengecat Tembok Baru / dalam (1lap.Plamir, 1lap Cat Dasar, 2 lap. Cat Penutup) m² 44.956,78

M Suplemen HARGA SATUAN PEKERJAAN PINTU & JENDELA


1 Ksn. 1 1 Unit Pekerjaan Pasang Pintu - Type ( PD1 ) unit 2.750.000,00
2 Ksn. 2 1 Unit Pekerjaan Pasang Pintu - Type ( P1 ) unit 1.350.000,00
3 Ksn. 3 1 Unit Pekerjaan Pasang Pintu - Type ( P2 ) unit 1.475.000,00
4 Ksn. 4 1 Unit Pekerjaan Pasang Pintu - Type ( P3 ) unit 1.550.000,00
5 Ksn. 5 1 Unit Pekerjaan Pasang Pintu - Type ( P4 ) unit 1.250.000,00
6 Ksn. 6 1 Unit Pekerjaan Pasang Pintu - Type ( PD2 ) unit 1.950.000,00
7 Ksn. 7 1 Unit Pekerjaan Pasang Jendela - Type ( J1 ) unit 1.575.000,00
8 Ksn. 8 1 Unit Pekerjaan Pasang Jendela - Type ( J2 ) unit 1.670.000,00
9 Ksn. 9 1 Unit Pekerjaan Pasang Boven - Type ( BV ) unit 750.000,00
Kota./Kab.,Tgl/Bln/Thn

Penawar,
PT./CV. ……………………

Nama Terang

Jabatan
DAFTAR ANALISA HARGA SATUAN PEKERJAAN

DAERAH : KABUPATEN PURBALINGGA

HARGA
BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN
Rp Rp
A A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 1 m³ Menggali Tanah Biasa Sedalam 1 m -


A TENAGA -
L.01 0,75 OH Pekerja 100.000,00 75.000,00
L.04 0,025 OH Mandor 140.000,00 3.500,00
B BAHAN
C PERALATAN
D Jumlah A + B + C 78.500,00
E Overhead & Profit 10% 7.850,00
F Harga Satuan Pekerjaan (D+E) 86.350,00

2 A.2.3.1.9 1 m³ Pengurugan Kembali ( di hitung dari 1/3 kali koefisien Pekerjaan galian ) -
A TENAGA -
L.01 0,50 OH Pekerja 100.000,00 50.000,00
L.04 0,050 OH Mandor 140.000,00 7.000,00
B BAHAN
C PERALATAN
D Jumlah A + B + C 57.000,00
E Overhead & Profit 10% 5.700,00
F Harga Satuan Pekerjaan (D+E) 62.700,00

3 A.2.3.1.11 1 m³ Urugan Pasir -


A TENAGA -
L.01 0,30 OH Pekerja 100.000,00 30.000,00
L.04 0,01 OH Mandor 140.000,00 1.400,00
B BAHAN -
1,2 m³ Pasir Urug 90.000,00 108.000,00
C PERALATAN
D Jumlah A + B + C 139.400,00
E Overhead & Profit 10% 13.940,00
F Harga Satuan Pekerjaan (D+E) 153.340,00
B A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI

1 A.3.2.1.4 1 m³ Pemasangan Pondasi Batu Belah 1SP : 6 PP -


A TENAGA -
L.01 1,5 OH Pekerja 100.000,00 150.000,00
L.02 0,750 OH Tukang Batu 120.000,00 90.000,00
L.03 0,075 OH Kepala Tukang 130.000,00 9.750,00
L.04 0,075 OH Mandor 140.000,00 10.500,00
B BAHAN -
1,2 m³ Batu Belah 15/20 165.000,00 198.000,00
117 Kg Portland Sement 1.083,33 126.750,00
0,561 m³ Pasir Pasang 110.000,00 61.710,00
C PERALATAN
D Jumlah A + B + C 646.710,00
E Overhead & Profit 10% 64.671,00
F Harga Satuan Pekerjaan (D+E) 711.381,00
C A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

1 A.4.4.1.11 1 m² Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP -
A Tenaga -
L.01 0,30 OH Pekerja 100.000,00 30.000,00
L.02 0,1 OH Tukang Batu 120.000,00 12.000,00
L.03 0,01 OH Kepala Tukang 130.000,00 1.300,00
L.04 0,015 OH Mandor 140.000,00 2.100,00
B Bahan -
70 Buah Bata Merah Panggisari 460,00 32.200,00
8,32 Kg Portland Semen 1.083,33 9.013,33
0,049 m3 Pasir Pasang 110.000,00 5.390,00
C PERALATAN
D Jumlah A + B + C 92.003,33
E Overhead & Profit 10% 9.200,33
F Harga Satuan Pekerjaan (D+E) 101.203,67
D A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

1 A.4.4.2.6 1 m² Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm -


Tenaga -
L.01 0,1 OH Pekerja 100.000,00 10.000,00
L.02 0,15 OH Tukang batu 120.000,00 18.000,00
L.03 0,010 OH Kepala Tukang 130.000,00 1.300,00
L.04 0,005 OH Mandor 140.000,00 700,00
Bahan -
4,416 Kg Portland Semen 1.083,33 4.784,00
0,027 m3 Pasir Pasang 110.000,00 2.970,00
C PERALATAN
D Jumlah A + B + C 37.754,00
E Overhead & Profit 10% 3.775,40
F Harga Satuan Pekerjaan (D+E) 41.529,40

2 A.4.4.2.27 1 m² Pemasangan Acian -


A Tenaga -
L.01 0,10 OH Pekerja 100.000,00 10.000,00
L.02 0,10 OH Tukang batu 120.000,00 12.000,00
L.03 0,010 OH Kepala Tukang 130.000,00 1.300,00
L.04 0,005 OH Mandor 140.000,00 700,00
B Bahan -
3,25 Kg Portland Semen 1.083,33 3.520,83
C PERALATAN
D Jumlah A + B + C 27.520,83
E Overhead & Profit 10% 2.752,08
F Harga Satuan Pekerjaan (D+E) 30.272,92
E A.4.1.1 HARGA SATUAN PEKERJAAN B E T O N

1 A.4.1.1.5 1 m³ Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 -
A Tenaga -
L.01 1,65 OH Pekerja 100.000,00 165.000,00
L.02 0,275 OH Tukang Batu 120.000,00 33.000,00
L.03 0,028 OH Kepala Tukang 130.000,00 3.640,00
L.04 0,083 OH Mandor 140.000,00 11.620,00
B Bahan -
326,00 Kg Portland Semen 1.083,33 353.166,67
0,48 kg Pasir Beton 110.000,00 52.800,00
0,71 kg Kerikil (maksimum 30 mm) 214.000,00 151.940,00
215,00 ltr Air 100 21.500,00
C PERALATAN
D Jumlah A + B + C 792.666,67
E Overhead & Profit 10% 79.266,67
F Harga Satuan Pekerjaan (D+E) 871.933,33

2 A.4.1.1.7 1 m³ Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 -
A Tenaga -
L.01 1,650 OH Pekerja 100.000,00 165.000,00
L.02 0,275 OH Tukang Batu 120.000,00 33.000,00
L.03 0,028 OH Kepala Tukang 130.000,00 3.640,00
L.04 0,083 OH Mandor 140.000,00 11.620,00
B Bahan -
371,00 Kg Portland Semen 1.083,33 401.916,67
0,44 kg Pasir Beton 110.000,00 48.400,00
0,72 kg Kerikil (maksimum 30 mm) 214.000,00 154.080,00
215,00 ltr Air 100,00 21.500,00
C PERALATAN
D Jumlah A + B + C 839.156,67
E Overhead & Profit 10% 83.915,67
F Harga Satuan Pekerjaan (D+E) 923.072,33

3 A.4.1.1.8 1 m³ Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 -
A Tenaga -
L.01 1,650 OH Pekerja 100.000,00 165.000,00
L.02 0,275 OH Tukang Batu 120.000,00 33.000,00
L.03 0,028 OH Kepala Tukang 130.000,00 3.640,00
L.04 0,083 OH Mandor 140.000,00 11.620,00
B Bahan -
384,00 Kg Portland Semen 1.083,33 416.000,00
0,43 kg Pasir Beton 110.000,00 47.300,00
0,72 kg Kerikil (maksimum 30 mm) 214.000,00 154.080,00
215,00 ltr Air 100,00 21.500,00
C PERALATAN
D Jumlah A + B + C 852.140,00
E Overhead & Profit 10% 85.214,00
F Harga Satuan Pekerjaan (D+E) 937.354,00
4 A.4.1.1.17 1 Kg Pembesian dg Besi Polos -
A Tenaga -
L.01 0,0070 OH Pekerja 100.000,00 700,00
L.02 0,0070 OH Tukang Besi 120.000,00 840,00
L.03 0,0007 OH Kepala Tukang 130.000,00 091,00
L.04 0,0004 OH Mandor 140.000,00 056,00
B Bahan -
1,05 Kg Besi Beton (polos) 10.000,00 10.500,00
0,015 Kg Kawat Beton 19.900,00 298,50
C PERALATAN
D Jumlah A + B + C 12.485,50
E Overhead & Profit 10% 1.248,55
F Harga Satuan Pekerjaan (D+E) 13.734,05

5 A.4.1.1.21 1 m² Memasang Bekisting untuk Sloof -


A Tenaga -
L.01 0,52 OH Pekerja 100.000,00 52.000,00
L.02 0,26 OH Tukang Kayu 120.000,00 31.200,00
L.03 0,026 OH Kepala Tukang 130.000,00 3.380,00
L.04 0,026 OH Mandor 140.000,00 3.640,00
B Bahan -
0,023 m³ Kayu Klas IV (Terentang) 750.000,00 17.250,00
0,3 Kg Paku Biasa 2" - 5" 20.000,00 6.000,00
0,1 Ltr Minyak Bekisting 13.000,00 1.300,00
C PERALATAN
D Jumlah A + B + C 114.770,00
E Overhead & Profit 10% 11.477,00
F Harga Satuan Pekerjaan (D+E) 126.247,00

6 A.4.1.1.22 1 m² Memasang Bekisting untuk Kolom -


A Tenaga -
L.01 0,66 OH Pekerja 100.000,00 66.000,00
L.02 0,33 OH Tukang Kayu 120.000,00 39.600,00
L.03 0,033 OH Kepala Tukang 130.000,00 4.290,00
L.04 0,033 OH Mandor 140.000,00 4.620,00
B Bahan -
0,02 m³ Kayu Klas IV (Terentang) 750.000,00 15.000,00
0,4 Kg Paku Biasa 2" - 5" 20.000,00 8.000,00
0,2 Ltr Minyak Bekisting 13.000,00 2.600,00
0,35 Lbr Triplek tebal 6mm 75.000,00 26.250,00
C PERALATAN
D Jumlah A + B + C 166.360,00
E Overhead & Profit 10% 16.636,00
F Harga Satuan Pekerjaan (D+E) 182.996,00
7 A.4.1.1.23 1 m² Memasang Bekisting untuk Balok -
A Tenaga -
L.01 0,66 OH Pekerja 100.000,00 66.000,00
L.02 0,33 OH Tukang Kayu 120.000,00 39.600,00
L.03 0,033 OH Kepala Tukang 130.000,00 4.290,00
L.04 0,033 OH Mandor 140.000,00 4.620,00
B Bahan -
0,02 m³ Kayu Klas IV (Terentang) 750.000,00 15.000,00
0,4 Kg Paku Biasa 2" - 5" 20.000,00 8.000,00
0,2 Ltr Minyak Bekisting 13.000,00 2.600,00
0,35 Lbr Triplek tebal 6mm 75.000,00 26.250,00
0,5 Btg Bambu diameter 8 - 10 cm / 4 m 8.000,00 4.000,00
C PERALATAN
D Jumlah A + B + C 170.360,00
E Overhead & Profit 10% 17.036,00
F Harga Satuan Pekerjaan (D+E) 187.396,00

8 A.4.1.1.24 1 m² Memasang Bekisting untuk Lantai -


A Tenaga -
L.01 0,66 OH Pekerja 100.000,00 66.000,00
L.02 0,33 OH Tukang Kayu 120.000,00 39.600,00
L.03 0,033 OH Kepala Tukang 130.000,00 4.290,00
L.04 0,033 OH Mandor 140.000,00 4.620,00
B Bahan -
0,02 m³ Kayu Klas IV (Terentang) 750.000,00 15.000,00
0,4 Kg Paku Biasa 2" - 5" 20.000,00 8.000,00
0,2 Ltr Minyak Bekisting 13.000,00 2.600,00
0,35 Lbr Triplek tebal 6mm 75.000,00 26.250,00
6 Btg Bambu diameter 8 - 10 cm / 4 m 8.000,00 48.000,00
C PERALATAN
D Jumlah A + B + C 214.360,00
E Overhead & Profit 10% 21.436,00
F Harga Satuan Pekerjaan (D+E) 235.796,00
F A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

1 A.4.5.2.32 1 m² Pemasangan Atap Genteng Metal Lapis Pasir -


A Tenaga -
L.01 0,2 OH Pekerja 100.000,00 20.000,00
L.02 0,1 OH Tukang Kayu 120.000,00 12.000,00
L.03 0,01 OH Kepala Tukang 130.000,00 1.300,00
L.04 0,01 OH Mandor 140.000,00 1.400,00
B Bahan -
1,02 m² Genteng Metal Lapis Pasir 34.500,00 35.190,00
0,20 Kg Paku Biasa Ø ½" - 1" 20.000,00 4.000,00
C PERALATAN
D Jumlah A + B + C 73.890,00
E Overhead & Profit 10% 7.389,00
F Harga Satuan Pekerjaan (D+E) 81.279,00

2 A.4.5.2.36 1 m' Pemasangan Nok Genteng Metal -


A Tenaga -
L.01 0,250 OH Pekerja 100.000,00 25.000,00
L.02 0,150 OH Tukang Kayu 120.000,00 18.000,00
L.03 0,015 OH Kepala Tukang 130.000,00 1.950,00
L.04 0,013 OH Mandor 140.000,00 1.820,00
B Bahan
1,1 Buah Nok Genteng 25.000,00 27.500,00
0,05 Kg Paku Biasa 1/2" - 1" 20.000,00 1.000,00
C PERALATAN
D Jumlah A + B + C 75.270,00
E Overhead & Profit 10% 7.527,00
F Harga Satuan Pekerjaan (D+E) 82.797,00
G A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT

1 Dihit. 01 1 m² Memasang Alumunium Composite Panel ( ACP ) -


A Tenaga -
L.01 0,39 OH Pekerja 100.000,00 39.000,00
L.02 0,70 OH Tukang Las 120.000,00 84.000,00
L.03 0,070 OH Kepala Tukang 130.000,00 9.100,00
L.04 0,007 OH Mandor 140.000,00 980,00
B Bahan
1,100 m2 Alumunium Composite 153.000,00 168.300,00
4,800 m' Hollow Besi Galvanis Uk 4 x 4 x 1 mm 31.300,00 150.240,00
0,267 btg Braket Siku / spigot / stiffener 11.560,00 3.086,52
0,080 kg Paku Skrup Beton 20.000,00 1.600,00
0,110 kg Paku Skrup 20.000,00 2.200,00
1,000 tube Sealant 35.000,00 35.000,00
C PERALATAN
0,020 set Sewa Stager (2set) 450.000,00 9.000,00
1,000 ls Listrik Kerja / Pemgelasan 25.000,00 25.000,00
1,000 ls Alat bantu lainnya 150.000,00 150.000,00
D Jumlah A + B + C 677.506,52
E Overhead & Profit 10% 67.750,65
F Harga Satuan Pekerjaan (D+E) 745.257,17
H A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

1 A.5.1.1.1 1 Unit Memasang Closet Duduk / Mono Blok+ Komplit & acc -
A Tenaga -
L.01 3,3 OH Pekerja 100.000,00 330.000,00
L.02 1,1 OH Tukang Batu 120.000,00 132.000,00
L.03 0,001 OH Kepala Tukang 130.000,00 130,00
L.04 0,16 OH Mandor 140.000,00 22.400,00
B Bahan
1 Buah Kloset Duduk / Monoblok 700.000,00 700.000,00
1 Buah Shower Spray 600.000,00 600.000,00
0,06 Kelengkapan 6% dari harga Kloset 42.000,00 2.520,00
C PERALATAN
D Jumlah A + B + C 1.787.050,00
E Overhead & Profit 10% 178.705,00
F Harga Satuan Pekerjaan (D+E) 1.965.755,00

2 A.5.1.1.4 1 Unit Memasang Urinoir -


A Tenaga -
L.01 1 OH Pekerja 100.000,00 100.000,00
L.02 1 OH Tukang Batu 120.000,00 120.000,00
L.03 0,1 OH Kepala Tukang 130.000,00 13.000,00
L.04 0,1 OH Mandor 140.000,00 14.000,00
B Bahan
1 Buah Urinoir 1.200.000,00 1.200.000,00
0,3 - Perlengkapan 30% Harga Urinoir 360.000,00 108.000,00
6 Kg Portland Semen 1.083,33 6.500,00
0,01 m3 Pasir Pasang 110.000,00 1.100,00
C PERALATAN
D Jumlah A + B + C 1.562.600,00
E Overhead & Profit 10% 156.260,00
F Harga Satuan Pekerjaan (D+E) 1.718.860,00

3 A.5.1.1.5 1 Unit Memasang Wastafel -


A Tenaga -
L.01 1,2 OH Pekerja 100.000,00 120.000,00
L.02 0,145 OH Tukang Batu 120.000,00 17.400,00
L.03 0,15 OH Kepala Tukang 130.000,00 19.500,00
L.04 0,1 OH Mandor 140.000,00 14.000,00
B Bahan
1 Buah Wastafel 900.000,00 900.000,00
0,3 - Perlengkapan 30% Harga Wastafel 270.000,00 81.000,00
6 Kg Portland Semen 1.083,33 6.500,00
0,01 m3 Pasir Pasang 110.000,00 1.100,00
C PERALATAN
D Jumlah A + B + C 1.159.500,00
E Overhead & Profit 10% 115.950,00
F Harga Satuan Pekerjaan (D+E) 1.275.450,00
4 A.5.1.1.14 1 buah Pemasangan Floor Drain -
A Tenaga -
L.01 0,010 OH Pekerja 100.000,00 1.000,00
L.02 0,100 OH Tukang Batu 120.000,00 12.000,00
L.03 0,010 OH Kepala Tukang 130.000,00 1.300,00
L.04 0,005 OH Mandor 140.000,00 700,00
B Bahan
1 bh Floor Drain 95.000,00 95.000,00
C PERALATAN
D Jumlah A + B + C 110.000,00
E Overhead & Profit 10% 11.000,00
F Harga Satuan Pekerjaan (D+E) 121.000,00

5 A.5.1.1.19 1 buah Pemasangan Kran -


A Tenaga -
L.01 0,010 OH Pekerja 100.000,00 1.000,00
L.02 0,400 OH Tukang Batu 120.000,00 48.000,00
L.03 0,040 OH Kepala Tukang 130.000,00 5.200,00
L.04 0,005 OH Mandor 140.000,00 700,00
B Bahan
1,00 bh Keran 56.000,00 56.000,00
0,0025 bh Sealtape 4.000,00 010,00
C PERALATAN
D Jumlah A + B + C 110.910,00
E Overhead & Profit 10% 11.091,00
F Harga Satuan Pekerjaan (D+E) 122.001,00

6 A.5.1.1.19.a 1 buah Pemasangan Zink + Kran Cuci Piring Stainless Fleksibel -


A Tenaga -
L.01 0,010 OH Pekerja 100.000,00 1.000,00
L.02 0,400 OH Tukang Batu 120.000,00 48.000,00
L.03 0,040 OH Kepala Tukang 130.000,00 5.200,00
L.04 0,005 OH Mandor 140.000,00 700,00
B Bahan
1,00 bh Kran Cuci Piring Stainless & Fleksibel Kran Sink 870.000,00 870.000,00
0,0025 bh Sealtape 4.000,00 010,00
C PERALATAN
D Jumlah A + B + C 924.910,00
E Overhead & Profit 10% 92.491,00
F Harga Satuan Pekerjaan (D+E) 1.017.401,00
I A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM

1 A.4.2.1.11 1 m' Pemasangan Kusen Allumunium 4" -


A Tenaga -
L.01 0,043 OH Pekerja 100.000,00 4.300,00
L.02 0,043 OH Tukang Besi 120.000,00 5.160,00
L.03 0,0043 OH Kepala Tukang 130.000,00 559,00
L.04 0,0021 OH Mandor 140.000,00 294,00
B Bahan
1,1 m' Rangka Allumunium 4" Alexindo 120.000,00 132.000,00
2 buah Skrup Fixer 2.500,00 5.000,00
0,06 Tube Sealant 35.000,00 2.100,00
C PERALATAN
D Jumlah A + B + C 149.413,00
E Overhead & Profit 10% 14.941,30
F Harga Satuan Pekerjaan (D+E) 164.354,30
J A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA

1 A.4.6.2.17 1 m² Pemasangan Kaca tebal 5 mm -


A Tenaga -
L.01 0,015 OH Pekerja 100.000,00 1.500,00
L.02 0,15 OH Tukang Kaca 120.000,00 18.000,00
L.03 0,015 OH Kepala Tukang 130.000,00 1.950,00
L.04 0,00075 OH Mandor 140.000,00 105,00
B Bahan
1,1 m² Kaca tebal 5mm 75.000,00 82.500,00
C PERALATAN
D Jumlah A + B + C 104.055,00
E Overhead & Profit 10% 10.405,50
F Harga Satuan Pekerjaan (D+E) 114.460,50
K A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING

1 A.4.4.3.9.m 1 m² Pemasangan lantai Ubin Granito Uk. 60 x 60 cm -


A Tenaga -
L.01 0,250 OH Pekerja 100.000,00 25.000,00
L.02 0,125 OH Tukang Batu 120.000,00 15.000,00
L.03 0,013 OH Kepala Tukang 130.000,00 1.690,00
L.04 0,013 OH Mandor 140.000,00 1.820,00
B Bahan
1,00 m² Ubin Granito 60x60 cm 120.000,00 120.000,00
11,1 Kg Portland Semen 1.083,33 12.025,00
0,045 m3 Pasir Pasang 110.000,00 4.950,00
C PERALATAN
D Jumlah A + B + C 180.485,00
E Overhead & Profit 10% 18.048,50
F Harga Satuan Pekerjaan (D+E) 198.533,50

2 A.4.4.3.34m 1 m² Pemasangan Lantai Keramik 60 x 60 cm -


A Tenaga -
L.01 0,70 OH Pekerja 100.000,00 70.000,00
L.02 0,35 OH Tukang Batu 120.000,00 42.000,00
L.03 0,035 OH Kepala Tukang 130.000,00 4.550,00
L.04 0,035 OH Mandor 140.000,00 4.900,00
B Bahan
1,00 m² Keramik 60 x 60 cm 36.000,00 36.000,00
9,81 Kg Portland Semen 1.083,33 10.627,50
0,045 m3 Pasir Pasang 110.000,00 4.950,00
C PERALATAN
D Jumlah A + B + C 173.027,50
E Overhead & Profit 10% 17.302,75
F Harga Satuan Pekerjaan (D+E) 190.330,25

3 A.4.4.3.36 1 m² Pemasangan Lantai Keramik 25 x 25 cm -


A Tenaga -
L.01 0,70 OH Pekerja 100.000,00 70.000,00
L.02 0,35 OH Tukang Batu 120.000,00 42.000,00
L.03 0,035 OH Kepala Tukang 130.000,00 4.550,00
L.04 0,035 OH Mandor 140.000,00 4.900,00
B Bahan
1,0 m² Ubin Keramik 25 x 25 cm 16.000,00 16.000,00
12,02 Kg Portland Semen 1.083,33 13.021,67
0,045 m3 Pasir Pasang 110.000,00 4.950,00
C PERALATAN
D Jumlah A + B + C 155.421,67
E Overhead & Profit 10% 15.542,17
F Harga Satuan Pekerjaan (D+E) 170.963,83

4 A.4.4.3.54.c 1 m² Pemasangan Dinding Keramik 25 x 40 cm -


A Tenaga -
L.01 0,9 OH Pekerja 100.000,00 90.000,00
L.02 0,45 OH Tukang Batu 120.000,00 54.000,00
L.03 0,045 OH Kepala Tukang 130.000,00 5.850,00
L.04 0,045 OH Mandor 140.000,00 6.300,00
B Bahan
1,0 m² Keramik 25 x 40 cm, 45.000,00 45.000,00
11,2 Kg Portland Semen 1.083,33 12.133,33
0,018 m3 Pasir Pasang 110.000,00 1.980,00
C PERALATAN
D Jumlah A + B + C 215.263,33
E Overhead & Profit 10% 21.526,33
F Harga Satuan Pekerjaan (D+E) 236.789,67
L A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

1 A.4.7.1.10 1 m² Pengecat Tembok Baru / dalam (1lap.Plamir, 1lap Cat Dasar, 2 lap. Cat Penutup) -
A Tenaga -
L.01 0,02 OH Pekerja 100.000,00 2.000,00
L.02 0,063 OH Tukang Cat 120.000,00 7.560,00
L.03 0,0063 OH Kepala Tukang 130.000,00 819,00
L.04 0,0030 OH Mandor 140.000,00 420,00
B Bahan
0,1 Kg Plamir 25.000,00 2.500,00
0,1 Kg Cet Dasar 140.300,00 14.030,00
0,26 Kg Cat Penutup 2 kali ( sek. Mowilex / dalam ) 52.080,00 13.540,80
C PERALATAN
D Jumlah A + B + C 40.869,80
E Overhead & Profit 10% 4.086,98
F Harga Satuan Pekerjaan (D+E) 44.956,78