PKDST I
PEMODELAN KOMPUTER DALAM SISTEM TENAGA
1.3.1 Toolbars
Edit Mode digunakan untuk membuat gambar baru New Case atau memodifikasi
gambar yang sudah ada
Run Mode digunakan untuk menjalankan Single Solution atau menjalankan
animasi
Log berisi pesan tentang hasil Power Flow Solution
Abort digunakan untuk memberhentikan sementara simulasi (pause)
Digunakan untuk Open Simulation Case, Open Online, Save Online, Save Case
dan mencetak (print)
Digunakan untuk inset gambar seperti bus, transformator, transmisi, beban dan
lain sebagainya.
Bus Bar
Generator
Transformator
Transmission
Line
5. Ulangi langkah-langkah tersebut untuk menggambar transmision line dari 2-5 dan
2-4
1.4.2.5 E. Menggambar Load
1. Gambar load pada bus 2
2. Klik Insert pilih Load atau klik Load pada Toollbar (Insert Peltte)
3. Klik-kiri pada bus yang akan diberi beban (bus 2) dan akan muncul kotak dialog seperti
gambar 1.12. Kemudian lengkapi kotak dialog Load Information pada Load Option.
Orientation pilih Down untu beban yang arahnya ke bawah. Model beban ada tiga
pilihan yaitu daya konstan, arus konstan dan impedansi konstan dan dalam satuan MW
untuk daya aktif dan MVAR untuk daya reaktif.
Beban/Load
VbaseLL
VbaseLN = 3
Pp – jQp = Vp . Ip
−
Dan arus : IP = PP *jQP
VP
Ip bertanda positif apabila arus mengalir ke bus dan bertanda negatif bila arus
mengalir dari bus.
Bila elemen shunt tidak termasuk dalam matriks parameter maka arus total pada
bus P adalah :
I p= Pp − *jQp −YpVp
Vp
ypq
I pq = (Vp −Vq )ypq +Vp
2
Dimana :
ypq = admitansi kawat p ke q
y’pq= admitansi shunt kawat p-q
y'pq
V1 = kontribusi arus pada bus p
oleh arus shunt. 2
c. Persamaan Daya
atau,
y
'
* * pq
se
dangkan
daya
yang
mengalir
dari bus
q ke p : y
' * pq '
[
Pi =|Vi | ∑ |Vj | Gij cos(θi −θj )+ Bij sin(θi −θj ) ]
j
[
Qi =|Vi | ∑ |Vj | Gij sin(θi −θj )− Bij cos(θi −θj ) ]
j
=1
S = P + jQ (VA,kVA,MVA)
P = V I cosϕ (W,kW,MW))
Q = V I sinϕ (Var,kVar,MVar)
cosϕ= cos⎛⎜tan−1 Q ⎞⎟
⎝ P⎠
P
cosϕ =
P +Q 2
2
Eth
IC =
Zth − jX C
V2
reaktif, QC =+
var. X
C
1 Swing/Slack 1.0 0 - - 0 0 - -
2 Load - - 0 0 8.0 2.8 - -
3 V Controled 1.05 - 5.2 - 0.8 0.4 4.0 -2.8
4 Load - - 0 0 0 0 - -
5 Load - - 0 0 0 0 - -
Bus-to-Bus R X G B Maksimum
(pu) (pu) (pu) (pu) MVA (pu)
2-4 0.0090 0.100 0 1.72 12.0
2-5 0.0045 0.050 0 0.88 12.0
4-5 0.00225 0.025 0 0.44 12.0
Voltage
Number Name Angle
kV
1 SATU
2 DUA
3 TIGA
4 EMPAT
5 LIMA
5 LIMA 1 SATU
4 EMPAT 2 DUA
2 DUA 4 EMPAT
5 LIMA 2 DUA
2 DUA 5 LIMA
3 TIGA 4 EMPAT
4 EMPAT 3 TIGA
5 LIMA 4 EMPAT
4 EMPAT 5 LIMA
Pembangkitan
P(MW) Q(Mvar)
G1
G2
PERCOBAAN 2
2.2 POWER WORLD : PENGARUH PERUBAHAN BEBAN
DALAM ANALISA ALIRAN DAYA
3. Klik Simulation, Play untuk mulai simulasi (sebelum mengklik Play direset dahulu)
4. Amati dan catat hasilnya (lengkapi tabel Tabel 3.1).
5. Naikan beban P pada bus 2 dari 800 MW denga step 20 MW (820 MW, 840 MW, 880
MW). Setiap step amati dan catat hasilnya serta simpan hasilnya.
6. Turunkan beban P pada bus 2 dari 800MW dengan step 100MW (700 MW, 600 MW,
500 MW). Setiap step amati dan catat hasilnya dan simpan hasilnya.
Bus1
Bus 2
P = 880 Bes 3
Bus 4
Bus 5
Bus1
P = 860 Bus 2
Bes 3
Bus 4
Bus 5
Bus1
Bus 2
P = 840 Bes 3
Bus 4
Bus 5
Bus 1
P =820 Bus 2
Bes 3
Bus 4
Bus 5
Bus 1
Bus 2
P = 800 Bes 3
Bus 4
Bus 5
Bus 1
P = 700 Bus 2
Bes 3
Bus 4
Bus 5
Bus 1
Bus 2
P = 600 Bes 3
Bus 4
Bus 5
Bus 1
P = 500 Bus 2
Bes 3
Bus 4
Bus 5
Bus 5
Bus 2
Step II Bus 4
Bus 5
Bus 2
Step III Bus 4
Bus 5
Bus 2
Step IV Bus 4
Bus 5
PERCOBAAN 2
3. POWER WORLD : ANALISA HUBUNG SINGKAT
3.1 2.2.1 ANALISA HUBUNG SINGKAT TIGA PHASA
SIMETRI
Dengan demikian:
Ia = Ib = Ic
Va =Vb =Vc
Persamaan urutan tegangan adalah:
Ia0 =13(Ia + Ib + Ic ) = 0
Va1 = Ea − Ia1Z1
0 = Ea −Ia1Z1 →
3. Masukkan data-data dari generator, transformator dan saluran transmisi seperti terlihat
dalam tabel berikut :
Tabel 5.1 Data Generator
Bus Reaktansi Sub Transien Generator X” (pu)
1 0.045
3 0.0225
*Sbase = 100MVA, Vbase = 15 kV di bus 1,3 dan 345 kVdi bus 2,4,5
6. Klik Calculate.
7. Amati hasil simulasi dan lengkapi tabel hasil percobaan
8. Untuk melihat arah aliran arus klik Play pada toolbar.
9. Simpan hasilnya dengan nama file HasilPercobaan06
2 DUA
3 TIGA
4 EMPAT
5 LIMA
2 DUA
3 TIGA
4 EMPAT
5 LIMA
4 EMPAT 2 DUA
5 LIMA 2 DUA
3 TIGA 4 EMPAT
5 LIMA 4 EMPAT
3 TIGA
6.1. Tujuan :
Setelah melakukan percobaan, mahasiswa diharapkan :
1. Mampu mensimulasikan analisa hubung singkat satu phasa ke tanah dengan
PowerWord Simulator
2. Mampu menganalisis dan menjelaskan hasil simulasi analisa hubung singkat satu
phasa ketanah
maka:
Va = 0; Ib = 0; Ic = 0
Dengan:
Ib = Ic = 0
Maka diperoleh:
Gambar 6.2: Rangkaian ekivalen urutan gangguan hubung singkat satu phasa ke tanah
Gambar 6.2. menujukkan rangkaian ekivalen urutan untuk gangguan hubung singkat
satu phasa ke tanah. Dari gambar tersebut dapat ditentukan arus satu phasa ke tanah (Ia)
adalah:
Ea
Ia0 = Ia1 = Ia2 = Z0 + Z1 +
Z2
3Ea
Ia = 3Ia1 =
Z0 +Z1 +Z2
3. Masukkan data-data dari generator, transformator dan saluran transmisi seperti terlihat
dalam tabel berikut :
Tabel 6.1 Data Generator
Bus X0 (pu) X1(Xd”) X2 Reaktansi Netral Xn (pu)
1 0.0125 0.045 0.045 0
3 0.005 0.0225 0.0225 0.0025
*Sbase = 100MVA, Vbase = 15 kV di bus 1,3 dan 345 kVdi bus 2,4,5
2 DUA
3 TIGA
4 EMPAT
5 LIMA
2 DUA
3 TIGA
4 EMPAT
5 LIMA
4 EMPAT 2 DUA
5 LIMA 2 DUA
3 TIGA 4 EMPAT
5 LIMA 4 EMPAT
1 SATU
3 TIGA
7.1. Tujuan :
Setelah melakukan percobaan, mahasiswa diharapkan :
1. Mampu mensimulasikan analisa hubung singkat antar phasa dengan PowerWord
Simulator
2. Mampu menganalisis dan menjelaskan hasil simulasi analisa hubung singkat dua
phasa
Gambar 7.1 menunjukkan gangguan hubung singkat antar phasa b dan c, sedangkan
Gambar 7.2 menunjukkan rangkaian ekivalen urutan untuk gangguan hubung singkat antar
phasa tersebut.
Dengan demikian:
Vb =Vc ; Ib =−Ic ; Ia = 0
a1
Va1 =Va2
Ia0 =13(Ia + Ib + Ic ) = 0
Maka:
Ia1 =−Ia2
Ea
Ia1 = Z1
+
Z2
Ea
Ia2 =
Z1 +Z2
*Sbase = 100MVA, Vbase = 15 kV di bus 1,3 dan 345 kVdi bus 2,4,5
4. Klik Options/Tools pilih Fault Aanalysis
5. Pilih lokasi gangguan dan jenis gangguan
6. Klik Calculate.
7. Amati hasil simulasi dan lengkapi tabel hasil percobaan
8. Untuk melihat arah aliran arus klik Play pada toolbar.
9. Simpan hasilnya dengan nama file HasilPercobaan07
2 DUA
3 TIGA
4 EMPAT
5 LIMA
2 DUA
3 TIGA
4 EMPAT
5 LIMA
4 EMPAT 2 DUA
5 LIMA 2 DUA
3 TIGA 4 EMPAT
5 LIMA 4 EMPAT
3 TIGA
8.1. Tujuan :
Setelah melakukan percobaan, mahasiswa diharapkan :
1. Mampu mensimulasikan analisa hubung singkat dua phasa ke tanah dengan
PowerWord Simulator
2. Mampu menganalisis dan menjelaskan hasil simulasi analisa hubung singkat dua
phasa ketanah
Jika gangguan hubung singkat terjadi pada phasa b dan c ke tanah, seperti ditunjukkan
pada Gambar 8.1, maka arus dan tegangannya adalah:
Eb = Ec = 0 dan Ia = 0
Dengan demikian:
Ea
Ia1 = Z1 + Z2 xZ0
Z2 + Z0
Z2 xEa
Ia2 =−
Z1Z2 +Z1Z0 + Z2Z0
Z0 xEa
Ia0 =−
Z1Z0 + Z1Z2 + Z2Z0
3. Masukkan data-data dari generator, transformator dan saluran transmisi seperti terlihat
dalam tabel berikut :
Tabel 8.1 Data Generator
Bus X0 (pu) X1(Xd”) X2 Reaktansi Netral Xn (pu)
1 0.0125 0.045 0.045 0
3 0.005 0.0225 0.0225 0.0025
*Sbase = 100MVA, Vbase = 15 kV di bus 1,3 dan 345 kVdi bus 2,4,5
4. Klik Options/Tools pilih Fault Aanalysis
6. Klik Calculate.
2 DUA
3 TIGA
4 EMPAT
5 LIMA
2 DUA
3 TIGA
4 EMPAT
5 LIMA
4 EMPAT 2 DUA
5 LIMA 2 DUA
3 TIGA 4 EMPAT
3 TIGA
Dhar, R.N. 1984. Computer Aided Power System Operation and Analysis. New Delhi : Tata
McGraw-Hill Publishing Company Limited.
El-Hawary,ME. 1995. Electrical Power Systems. New York : The Institute of Electrical and
Electronics Engineers,Inc.
Grainger, JJ. and Stevenson,JR. WD. 1994. Power System Analysis. Singapore : McGraw-
Hill, Inc.
Glover,J Duncan, Sarma Mulukutla S., 2002, Power System Analysis and Design,
Brooks/Cole Thomson Learning
Pai. 1979. Computer Techniques in Power System Analysis. New Delhi : Tata McGraw-Hill
Publishing Company Limited.
Stevenson, Jr. WD. 1996. Analisis Sistem Tenaga. Jakarta : Penerbit Erlangga.
Sulasno. 1993. Analisa Sistem Tenaga Listrik. Semarang : Penerbit Satya Wacana.
PERCOBAAN 4
4. ETAPS : PEMODELAN DAN ANALISA ALIRAN
DAYA
4.1 4. Structure
This section describes the structure of the ETAP 12.6 package. The demo has
been designed to allow sampling of most of the editing and analysis tools in ETAP.
This window is immediately displayed as soon as you run the ETAP 12.6 Demo
program. It gives you the following options:
The New Project option allows you to open a new ETAP project where you can
build a one-line diagram from scratch. The system that you build can have as many
as twelve AC buses and ten DC buses. You can perform all enabled analysis on this
newly created project, but you cannot save the changes you make. Please refer to
Section 2 for a list of all the studies that you can perform or need to enable using
your Return Key Code.
If you select this option, an example project will open which has been setup to
run all the available ETAP modules. The example project contains several links to
allow you to view the getting started documents for ETAP. It also contains valuable
information regarding one-line diagrams editing features. In this project, all symbols
and studies are based on ANSI standard.
If you select this option, an example project will open which has been setup to
run all the available ETAP modules. The example project contains several links to
Operation Technology, Inc. 6 ETAP 14 Demo
Getting Started Analysis Capabilities
allow you to view the getting started documents for ETAP. It also contains valuable
information regarding one-line diagrams editing features. In this project, all symbols
and studies are based on IEC standard.
If you select this option, a large project file opens which can only be browsed.
This project is provided as an example of larger systems and how they can be divided
into subsystems or “composite networks” to simplify and organize one-line
diagrams. This project is a bigger version of the example project. It is very important
to know that ETAP does not have any system size limitations; this means that you
can have an unlimited number of buses.
The ETAP GIS Video option shows the process of building and synchronizing an
ETAP project with a GIS project.
Here you can graphically add, delete, relocate, and connect elements, zoom in or
out, display grid off or on, change element size, change element orientation, change
symbols, hide or show protective Devices, enter properties, set operating status, and
more.
Menu Bar
The Menu bar contains a comprehensive list of menu options. Each option
activates a drop-down list of commands such as, File operations, Printing, Database
Conversions, Data Exchange, OLE objects, Project Standards, Project Settings and
Project Options, Libraries, Defaults, Annotation Fonts, Base and Revision Data, and
more.
The Project toolbar contains buttons that provide shortcuts for many
commonly used functions. Those functions are: Create Projects, Open Projects, Save
Projects, Print, Print Preview, Cut, Copy, Paste, Pan, Zoom, Undo, Redo, Text Box, Grid
Display, Continuity Check, Themes, Get Template, Add to OLV Template, Hyperlink,
Power Calculator, Find, and Help.
4.4 6. TUTORIAL
This chapter is intended to give you a brief overview of some of the features
of ETAP. After going through this series of tutorials, you will be familiar with many
of the key concepts and capabilities of ETAP. Each section is available in an interactive
format, allowing you to visualize each step as it is explained in this chapter.
The tutorials are all independent of each other, so you do not need to worry
about being introduced to everything at once. Simply choose any number of
sections that you are interested in learning. The breakdown of the sections is
described below.
Section 1: How to build and manipulate a one-line diagram
Section 2: How to set up and run a load flow study
Section 3: How to set up and run an unbalanced load flow study
Section 4: An introduction to ANSI and IEC short circuit studies
Section 5: How to set up an run arc flash analysis
Section 6: How to set up and run both static and dynamic motor acceleration
studies
Section 7: A brief overview of a harmonic analysis of a system
Section 8: How to simulate and analyze system transients
Section 9: An overview of the basic operation of the Protective Device Coordination
(Star) module
Section 10: An introduction to Optimal Power Flow analysis
Section 11: How to setup and run a reliability analysis
Section 12: An overview of the DC Load Flow module
Section 13: How to run a DC Short-Circuit study and make multiple study cases
Section 14: An introduction to Battery Sizing and Battery Discharge
Section 15: A brief overview of the Underground Raceway Systems module
Section 16: How to build and run studies on a Ground Grid Systems
The first tutorial shows you how to create a small system. For this section
you can use the “New Project” option when the Select Demo Project
window appears. For the rest of the tutorials (with the exception of Star),
you should use the “Example Project” option instead.
The first tutorial shows you how to create a small system. For this
section you can use the “New Project” option when the Select Demo
Project window appears. For the rest of the tutorials (with the exception
of Star), you should use the “Example Project” option instead.
30
You can stretch buses by placing the mouse pointer over either end of
the bus, until a double arrow appears. Then click and drag to the desired
length.
☺Helpful Tips… You can zoom in , zoom out , and zoom to fit page the OLV by
clicking on the respective buttons located in the Project Toolbar.
31
Now connect the elements in the one-line. Place the mouse pointer over
the connection pin of an element, and it will turn red. Then click and drag
to the connection pin of another element. Follow this procedure to
☺Helpful Tips… You can change the size, orientation and symbol standard for
an element by right-clicking on the element and selecting the attribute you would like
to change.
Power Grid U1 1250 MVAsc X/R = 120
Cable1 NEC 5.0kV 3/C CU, 133% Size = 4/0 Length = 200ft
Transformer T1 Prim. kV = 4.16kV Sec. kV = 0.48kV 20 MVA %Z = 6 X/R = 17
Motor Mtr1 400 HP
Node automatically inserted
32
Click the Library button on the Info page to select a cable. Then click OK
to exit both the Quick Pick window and the editor window. The
engineering properties of the selected cable are now entered in the editor.
33
34
Adding a Protective Device (PD) to your One-Line Ensure that there is enough
room between the elements you wish to add a PD. Adding a PD to your one-line does
not require you to delete the line connecting the elements, instead, insert the PD on
to the line where you like it to be. The PD will automatically connect to the line. Follow
this procedure to add the remaining PDs shown in the final one-line.
Creating a one-line diagram in ETAP is fast and easy. Once complete, you
can take full advantage of all the powerful tools that ETAP has to offer.
35
Click the Load Flow Analysis button on the Mode toolbar to switch to
Load Flow Analysis mode. Now you can run a study by clicking on the Run
Load Flow button on the Load Flow toolbar. You will be prompted to enter
a name for your output report if Prompt is selected. Later, you will learn
how to customize your study by changing options in the Load Flow Study
Case editor.
The results of the study can be seen on the OLD. The information shown
on the OLD can be changed in the Display Options. For even more detailed
results, output reports can be viewed.
To view any overload problems, simply click the Alert View button on
the Load Flow toolbar. This will open a window containing a list of
undersized equipment. Please note that the alert view button is disabled
in the ETAP Demo.
36
Note that the operating voltage of Bus1 is 97.94%. This caused the bus
to be flagged as marginally under voltage in the Alert View window. The
criteria for which a condition is flagged can be changed in the Load Flow
Study Case editor, which will be discussed in the next lesson. We will now
use the bus voltage regulation feature of the Transformer Editor to change
our Load Flow results.
ETAP allows Auto LTC settings to be applied to regulate buses that are
directly or indirectly connected to a transformer. For example, we can use
transformer T4 to regulate Bus1 at 100% of nominal voltage. Open the
editor of T4 by double clicking on its graphic. On the Tap tab, enable
(check) the Auto LTC box on the primary winding.
Open the LTC settings window by clicking on the LTC box and change
the Regulated Bus ID to Bus1. Click OK for both the LTC window and the
Transformer Editor window.
Now you can run a Load Flow study again, with attention paid to the
operating voltage of Bus1. Click the Run Load Flow button on the Load
Flow toolbar to do so.
Notice that the operating voltage of Bus1 is now within a tap step of the
desired 100% regulation value. This is just one example of the many
features of the ETAP Load
Element Parameters
Type Element Parameters
MOV MOV3, MOV5 Initial Status = Throttle
Lump Load Lump2 PF=85%, Constant kVA Load = 50%, Rated kV =
13.8
Lump4 & Lump 6 PF=85%, Constant kVA Load = 80%, Rated kV =
0.46
Static Load Load1, Load6, Load8 kV = Bus Nominal kV, PF=80%
Load3, Load5 kV = Bus Nominal kV, PF=100%
Capacitor CAP1 kV=4.16, kvar/Bank = 150 kvar, # of Banks = 2
Syn Motor Syn1 PF @ 100% Load = 80%, FLA = 403.5
Syn2, Syn4 PF@100% Load =91.71%, FLA = 220.1
Name Configuration
DesignLoad Use Design load without diversity factor.
Use Design for generation category.
Use default values for Adjustment Page.
Loading and generator overexcited alert: Critical = 100%,
Marginal = 95%.
90%Load Use global diversity factor to set all load to
90 Use the default setting for Adjustment.
All Loading and generator overexcited alert: Critical = 100%,
Marginal = 95%.
3. You will notice a large number of under voltage conditions throughout the system
4. Correct these under voltage conditions in the system
5. For a solution to this problem please select the following
Revision = Solution
Configuration = Solution-
CFG
PERCOBAAN 4
5. ETAPS : ANALISA HUBUNG SINGKAT
5.1 4. TUJUAN
Analisis Hubung Singkat memiliki tujuan, yaitu sebagai berikut.
1. Untuk menentukan arus maksimum dan minimum hubung singkat.
2. Untuk menentukan arus gangguan tak simetris bagi gangguan satu dan dua
line ke tanah, gangguan line ke line, dan rangkaian terbuka
Untuk menentukan distribusi arus gangguan dan tingkat tegangan busbar selama gangguan.
5.2 TEORI
Berdasarkan ANSI/IEEE Std. 100-1992 gangguan didefinisikan sebagai suatu
kondisi fisis yang disebabkan kegagalan suatu perangkat, komponen, atau suatu
elemen untuk bekerja sesuai dengan fungsinya. Gangguan hampir selalu ditimbulkan
oleh hubung singkat antar fase atau hubung singkat fase ke tanah. Suatu gangguan
hampir selalu berupa hubung langsung atau melalui impedansi. Istilah gangguan
identik dengan hubung singkat, sesuai standart ANSI/IEEE Std. 100-1992.
menjadi tiga sistem fasor yang seimbang. Himpunan seimbang komponen itu adalah
(Stevenson, 1982: 260):
1. Komponen urutan positif, yang terdiri dari tiga fasor yang sama besarnya,
terpisah satu dengan yang lainnya dalam phasa sebesar 120o, dan
mempunyai urutan phasa yang sama seperti fasor aslinya.
2. Komponen urutan negatif, yang terdiri dari tiga fasor yang sama besarnya,
terpisah satu dengan yang lainnya dalam phasa sebesar 120o, dan
mempunyai urutan phasa yang berlawanan dengan fasor aslinya.
3. Komponen urutan nol, yang terdiri dari tiga fasor yang sama besarnya dan
dengan Pergeseran phasa nol antara fasor yang satu dengan yang lain.
Tujuan lain adalah untuk memperlihatkan bahwa setiap phasa dari sistem tiga
phasa tak seimbang dapat di pecah menjadi tiga set komponen.
Ia0 = 0;
5.3.1 Purpose
1. To navigate and retrieve data from each library into respective devices
2. To test the protection and coordination settings of this system by generating TCCs
3. Demonstrate STAR TCC Features
REPORT
6.1 Bus
Initial Voltage
Bus1 SWNG 12.470 12.470 1
100.00 0.00
3 Buses Total
U1 Bus1 200.000 12.470 12.00 4.15227 49.82730 Wye - Solid 12.00 4.152270 49.82
Mtr1 Motor 1 87.70 0.460 3600 5.46 3.515 19.19 47.99 Wye Open 5.69 3.515
Bus3 Total 0.00 19.828 0.00 98.97 99.32 20.171 20.171 9.97E+001 5.98E+002 9.79E+001 5.67E
Bus2 Bus3 91.97 19.240 95.76 100.00 96.13 19.779 20.171 * 1.02E+002 6.17E+002 9.79E+001 5.67E
Mtr1 Bus3 104.35 0.589 104.35 104.35 104.35 0.392 0.000 3.68E+003 2.01E+004
* Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer
Bus3 0.48 3.258 -19.559 19.828 3.351 -19.891 20.171 16.929 2.818 17.162 -
18.661 7.309 20.041
All fault currents are symmetrical momentary (1/2 Cycle network) values in rms kA
* LLG fault current is the larger of the two faulted line currents
Bus3 0.480 0.00230 0.01379 0.01398 0.00230 0.01380 0.01399 0.00225 0.01305
0.01325
13.1.1 Procedure
1. Open project STAR_Exercise1A
2. Create the One-line Diagram for the system
3. Input data for the elements shown below
13.1.2 Phase CT
13.1.3 Ground CT
Note that the selected relay type has two input types: Phase and Ground
Phase Settings
Ground Settings
13.1.4 Cable
Luas penampang cable8 diubah menjadi 120 mm2 dan Luas penampang cable9
diubah menjadi 120 mm2. Terlihat tidak ada perubahan pada arus gangguan. Hal ini
karena perubahan luas penampang dari kabel hanya berada pada kisaran
mm2sehingga sangat kecil untuk berubah. Oleh karena itu, tidak ada perubahan yang
signifikan pada analisis hubung singkat.
Kemudian, dilakukan perubahan jenis kabel pada cable8 dan cable9 menjadi
aluminium. Terlihat tidak ada perubahan pada arus gangguan yang diperoleh. Hal ini
karena nilai hambatan jenis tidak terlalu besar perubahannya. Oleh karena itu, tidak
terdapat perubahan yang signifikan pada analisis hubung singkat.
Dari percobaan yang telah dilakukan, terlihat bahwa arus gangguan akan
semakin besar ketika panjang saluran semakin kecil. Dan sebaliknya, arus gangguan
akan semakin kecil ketika panjang saluran semakin besar. Arus gangguan terlihat
tidak terpengaruh secara signifikan ketika ada perubahan jenis konduktor dan
besarnya luas penampang konduktor. Hal ini karena perubahan jenis konduktor dan
besarnya luas penampang hanya berpengaruh sangat kecil pada persamaan
impedansi saluran.
Dari percobaan tersebut, dapat diperoleh arus gangguan yang mungkin terjadi
pada Sistem Tenaga Listrik sehingga dapat dilakukan perancangan proteksi yang
tepat bagi sistem. Dengan perancangan proteksi yang tepat pada sistem, risiko akan
rusaknya sistem dan komponen sistem dapat diminimalisasi. Oleh karena itu, Analisis
Hubung Singkat sangat penting dalam menentukan sistem proteksi yang tepat pada
Sistem Tenaga Listrik untuk melindungi peralatan dari kerusakan akibat arus
gangguan yang dihasilkan pada saat terjadi gangguan hubung singkat.
Dari percobaan yang telah dilakukan, arus gangguan pada Sistem Tenaga Listrik
dapat diperoleh besarnya dengan menggunakan Short-Circuit Analysis pada
software ETAP. ETAP memudahkan engineer dalam melakukan Analisis Hubung
Singkat. Dengan demikian, ETAP dapat digunakan untuk melakukan Analisis Hubung
Singkat untuk menentukan sistem proteksi yang tepat pada Sistem Tenaga Listrik.
KESIMPULAN
2. Besarnya arus gangguan hubung singkat bergantung pada impedansi saluran yang
bergantung pada panjang saluran, jenis konduktor, dan luas penampang konduktor.
Semakin panjang saluran, semakin kecil arus gangguan. Semakin besar hambatan jenis
konduktor, semakin kecil arus gangguan. Dan semakin besar luas penampang
4. Analisis hubung singkat dapat digunakan untuk memperoleh besarnya arus gangguan
hubung singkat sehingga dapat ditentukan proteksi yang tepat pada Sistem Tenaga
Listrik.
ETAP dapat digunakan untuk melakukan Analisis Aliran Daya, Analisis Hubung Singkat, dan
Analisis Starting Motor pada Sistem Tenaga Listrik.
PERCOBAAN 4
14. DIGSILENT : PEMODELAN RELE JARAK
14.1 4. TUJUAN
Setelah extract folder sudah selesei selanjutnya proses install software, pilih powerfactory-
Workstation kemudian install > harlock
Proses selanjutnya persetujuan license, centang “ I accept the terms in the license agreement”
> click next.
Jalankan software digsilent, isikan nama sesuai keinginan dan password sesuai keinginan.
Password yang yang dimasukan tersebut sebagai proteksi hasil kerja. Password ini digunakan
untuk membuka kembali hasil kerja yang sudah dikerjakan > OK
Berikut ditampilkan kotak dialog penamaan untuk project yang akan dikerjakan, > click
OK.
Langkah selanjutnya penamaan lembar kerja pada project yang akan di kerjakan, sebagai
berikut:
Pada toolbar sebelah kanan click beberapa komponen yang akan digunakan sebagai simulasi,
contohnya adalah busbar, kemudian pemberian nama pada busbar contohnya Busbar A.
Pada busbar A click 2x sehingga akan muncul kotak dialog sebagai berikut, pada baris type
click pada panah arah bawah pilih new project type.
Sehingga akan muncul kotak dialog sebagai berikut, setting rating tegangan akan bisa
ditentukan sesuai kebutuhan.
Hasil dari new project type diatas adalah sebagai berikut, selanjutnya dengan cara yang sama
lakukan pada Zona dan Area.
Click 2x pada line transmission line, sehingga akan muncul kotak dialog sebagai berikut,
selanjutnya melakukan penamaan pada transmission line dan pengisian parameter dengan
cara click panah arah bawah baris type > New project type > Line type
Sehingga muncul kotak dialog sebagai berikut, langkah selanjutnya mengisi parameter
transmission line sesuai dengan kondisi nyata lapangan, sebagai berikut:
Berikut hasil dari pengisian data parameter transmission line di atas:
Pengisian data parameter CT dengan cara click panah arah bawa baris type > New project
type > isi data sesuai dengan kebutuhan.
Hasil pengisian data parameter pada CT adalah sebagai berikut:
Pengisian data parameter CVT dengan cara click panah arah bawa baris type > New
project type > isi data sesuai dengan kebutuhan:
Hasil pengisian data parameter pada CVT adalah sebagai berikut:
Untuk pemilihan jenis rele > click pada panah arah bawah baris relay type > select global
type
Pilih merk dan jenis rele sesuai dengan kebutuhan simulasi > Click OK
Maka hasilnya akan seperti dibawah ini, kemudian langkah selanjutnya mensetting rele
distance berdasarkan zona > Setting Zona 1 > Setting Zona 2+timer > Setting Zona 3+timer
> Click OK
Gangguan misal terjadi pada penghantar ACSR GANNET, ditampilkan berikut ini: Click
ACSR GANNET > Click OK
Ketik lokasi terjadinya gangguan: Relative > 50% (Gangguan terjadi pada 50% dari
panjang saluran).
Kemudian Click Execute, maka hasilnya akan ditampilkan sebagai berikut.
Pada transmission line click kanan > Path > New > OK
Pada transmission line click kanan > Path > R-X Plot
Maka hasilnya akan muncul sebagai berikut, guna menganalisa gangguan berdasarkan zona.
Lingkaran – lingkaran berikut ini merupakan zona proteksi dari rele distance.
Pada transmission line click kanan > Path > Time Distance Diagram
Maka hasilnya akan tampak sebagai berikut:
Dengan cara di atas berikut di sajikan project yang lebih komplek, terdiri dari 3 GITET
(Paiton, Kediri, Pedan) yag saling interkoneksi dan koordinasi.
Gangguan pada saluran arah Kediri - Paiton
Gangguan pada busbar Kediri : Klick user selection > Busbar Kediri > OK
Tampilan proteksi berdasarkan zona dengan 2 rele distance.
14.4 Tampilan time distance protection
Tampilan report pembacaan dari distance rele: Run project > Output calculation analysis >
Execute > Vew output window