PERHITUNGAN PEMBAYARAN PEKERJAAN KONSTRUKSI

NILAI KONTRAK 1,000,000,000


UANG MUKA 30%

TERMIJN PEMBAYARAN
URAIAN TERM 1
PROGRESS FISIK 25%
PROGRESS FISIK RIIL 45%
PEMBAYARAN 40%

PERHITUNGAN PEMBAYARAN
Uang Muka 30 % x 1000000000. 300,000,000
Term Pembayaran I (40 % x 1000000000.) 400,000,000
Dibayar setelah progress fisik melebihi 25 % (45%= 450000000.)
Cicilan/Angsuran Uang Muka (30 % x 450000000.) 135,000,000
PPn ( 10% x 400000000.) 40,000,000
Total Pembayaran Termin I 225,000,000
Term Pembayaran II (15 % x 1000000000.) 150,000,000
Dibayar setelah progress fisik melebihi 50 % (60 %)
Cicilan/Angsuran Uang Muka (30 % x 150000000.) 45,000,000
PPn ( 10% x 150000000.) 15,000,000
Total Pembayaran Termin II 90,000,000
Term Pembayaran III (30 % x 1000000000.) 300,000,000
Dibayar setelah progress fisik melebihi 75 % (90 %)
Cicilan/Angsuran Uang Muka (30 % x 300000000.) 90,000,000
PPn ( 10% x 300000000.) 30,000,000
Total Pembayaran Termin III 180,000,000
Term Pembayaran IV (10 % x 1000000000.) 100,000,000
Dibayar setelah progress fisik mencapai 100 % (100 %)
Cicilan/Angsuran Uang Muka (30 % x 100000000.) 30,000,000
PPn ( 10% x 100000000.) 10,000,000
Total Pembayaran Termin IV 60,000,000
Pembayaran Akhir FHO (5 % x 1000000000.) 50,000,000
TERM 2 TERM 3 TERM 4 TERM 5 JUMLAH
25% 25% 25% 100%
15% 30% 10% 100%
15% 30% 10% 5% 100%

Cicilan Uang Muka

135,000,000 40,500,000

45,000,000

90,000,000

30,000,000

300,000,000
PERHITUNGAN PEMBAYARAN PEKERJAAN KONSTRUKSI

NILAI KONTRAK 44,310,112,000


UANG MUKA 20%

TERMIJN PEMBAYARAN
URAIAN TERM 1
PEMBAYARAN 20%
Cicilan Uang Muka 20%

PERHITUNGAN PEMBAYARAN
Uang Muka 20 % x 44310112000. 8,862,022,400
Term Pembayaran I (20 % x 44310112000.) 8,862,022,400
Cicilan/Angsuran Uang Muka (20 % x 8862022400.) 1,772,404,480
Total Pembayaran Termin I 7,089,617,920
Term Pembayaran II (30 % x 44310112000.) 13,293,033,600
Cicilan/Angsuran Uang Muka (30 % x 8862022400.) 2,658,606,720
Total Pembayaran Termin II 10,634,426,880
Term Pembayaran III (20 % x 44310112000.) 8,862,022,400
Cicilan/Angsuran Uang Muka (20 % x 8862022400.) 1,772,404,480
Total Pembayaran Termin III 7,089,617,920
Term Pembayaran IV (20 % x 44310112000.) 8,862,022,400
Cicilan/Angsuran Uang Muka (20 % x 8862022400.) 1,772,404,480
Total Pembayaran Termin IV 7,089,617,920
Pembayaran Akhir FHO (10 % x 44310112000.) 4,431,011,200
Cicilan/Angsuran Uang Muka (10 % x 8862022400.) 886,202,240
Total Pembayaran Termin V 3,544,808,960
Total Pembayaran (Uang muka + Termin) 44,310,112,000
TERM 2 TERM 3 TERM 4 TERM 5 JUMLAH
30% 20% 20% 10% 100%
30% 20% 20% 10% 100%

Cicilan Uang
Muka

1,772,404,480

2,658,606,720

1,772,404,480

1,772,404,480

886,202,240

8,862,022,400