SCHEDULE PELAKSANAAN PROYEK PEMASANGAN X-RAY XR6000

Maret (Tentative)
ITEM PEKERJAAN
20 21 22 23 24 25 26 27 28 29 30 31
A. Pekerjaan Persiapan
1 Pemindahan Mesin X-Ray Eksisting

B. Pekerjaan Bongkaran
1 Bongkar Plafon Pintu Selasar Akses Ruang Panel SDP 1
2 Bor Tembok Belakang Radiologi untuk Jalur Kabel Power dan Grounding
3 Bongkar Paving Blok Belakang Kamar Jenazah untuk Stick Rod Grounding
4 Pelepasan Lampu Penerangan Selasar Akses ke Ruang Panel SDP 1
5 Bongkar Lantai Ruang Radiologi untuk Jalur Cable Duct

C Pekerjaan Pembersihan dan Buangan


1 Buang Puing

D Pekerjaan Pemasangan Power Listrik


1 Pemasangan Panel Kontrol Mesin X-Ray
2 Pemasangan Cable Duct
4 Penarikan Kabel Power dari Panel SDP 1A menuju Panel Kontorl X-Ray
5 Pemasangan Accessoris Listrik (Stop Kontak dan Emergency Push Button)
6 Penarikan Kabel 3x2.5 mm2 untuk Accessoris Listrik

E Pekerjaan Pemasangan Grounding


1 Penarikan Kabel Grounding
2 Pemasangan Stick Rod Grounding

F Pekerjaan Perkuatan
1 Pengeboran Titik Titik Perkuatan Mesin XR6000

G. Pekerjaan Pemasangan XR6000


1 Pemasangan XR6000
2 Koneksi Kabel dan Setting Alat XR6000 (by GE)
3 Uji Test Alat XR6000 (by GE)

H. Pekerjaan Finishing
1 Pemasangan dan Perapihan Paving Blok
2 Pemasangan dan Perapihan Keramik Lantai

I. Hand Over Ruang Radiologi


SPESIFIKASI PANEL KONTROL

No Material Jumlah Satuan Keterangan


A. PANEL KONTROL 1 unit sesuai kebutuhan
1 MCCB Schneider Easy Pack EZC 125 A, 25kA 1 unit
2 Main Contactor Schneider TeSys F, LC1F150 1 unit
3 Coil Contactor Schneider LX1FF220 1 unit
4 Omron Timer H3CRG8EL 220 VAC, 5-60s 1 unit
5 Fuse 250 VAC, 10 A 1 unit
6 Fuse 250 VAC, 1A 3 unit
7 Pilot Lamp 220 VAC warna merah 1 unit
8 Pilot Lamp 220 VAC warna kuning 1 unit
9 Pilot Lamp 220 VAC warna hijau 1 unit
10 Bus Bar Plate Netral (5x30x300)mm 1 unit
11 Bus Bar Plate Ground (5x30x300)mm 1 unit
12 Isolator Panel SM-40 (50x40)mm 3 unit Dipasang pada busbar Ground
13 MCB 6 A, 1 phase 6 unit
14 Voltmater GAE 1 unit
SPESIFIKASI PANEL KONTROL

No Material Jumlah Satuan Keterangan


A. PANEL KONTROL 1 unit sesuai kebutuhan
1 MCCB Schneider Easy Pack EZC 125 A, 25kA 1 unit
2 Main Contactor Schneider TeSys F, LC1F150 1 unit
3 Coil Contactor Schneider LX1FF220 1 unit
4 Omron Timer H3CRG8EL 220 VAC, 5-60s 1 unit
5 Fuse 250 VAC, 10 A 1 unit
6 Fuse 250 VAC, 1A 3 unit
7 Pilot Lamp 220 VAC warna merah 1 unit
8 Pilot Lamp 220 VAC warna kuning 1 unit
9 Pilot Lamp 220 VAC warna hijau 1 unit
10 Bus Bar Plate Netral (5x30x300)mm 1 unit
11 Bus Bar Plate Ground (5x30x300)mm 1 unit
12 Isolator Panel SM-40 (50x40)mm 3 unit Dipasang pada busbar Ground
13 MCB 6 A, 1 phase 6 unit
14 Voltmater GAE 1 unit
MCCB 125 A UNTUK POWER MESIN XR6000

PANEL SDP 1A
RS. PERSADA MEDIKA JATIRAHAYU
JL. HANKAM RAYA NO. 17, JATIRAHAYU, PONDOK GEDE,
KOTA BEKASI - JAWA BARAT, BEKASI, WEST JAVA, ID
REV DATE MODIFICATIONS
01 - Cover Sheet Disra Agifral
02 - Equipment Layout
03 - Floor - Electrical Layout GE Healthcare +62 811 1941196
04 - Floor Structural Details Disra.agifral@ge.com
05 - Power Requirements
06 - HVAC - Environment - Connectivity
07 - Equipment Dimensions - Views - Clearance PRE-INSTALLATION REQUIREMENTS FOR
08 - Interconnections - Delivery - Disclaimer
XR 6000
A mandatory component of this drawing set is the GE Healthcare Pre Installation manual. Failure to reference the Pre Installation manual will result in
FINAL STUDY
incomplete documentation required for site design and preparation.
Pre Installation documents for GE Healthcare products can be accessed on the web at: www.gehealthcare.com/siteplanning Drawn by Verified by S.O. PIM Ref & Rev Date Rev
GE does not take responsibility for any damages resulting from changes on drawings made by others. Errors may occur by not referring to the complete Michelle Jose ---- - 5275600-100 Rev 8 23/ FEB/2017 ----
set of final issue drawing. GE cannot accept responsibility for any damage due to the partial use of GE final issue drawings, however caused. All
dimensions are in millimeters unless otherwise specified. Do not scale from printed pdf files. GE accepts no responsibility or liability for defective work
due to scaling from these drawings. Scale 1:50 Format A3 2_RAD-45349-13282-FIN.DWG 01/12
EXISTING LAYOUT

WALL - ACCORDING TO RECEIVED DRAWING


108 6525
EXAM ROOM HEIGHT
SLAB TO SLAB HEIGHT -
104

FALSE CEILING HEIGHT rec 3.00 m/ Avail 2.75m

612
694
526
300
1488

1428

3726
300 405

424 418
603

188
2502

900 313
2815
292
424
1988

923

3215
3107

RS. PERSADA MEDIKA JATIRAHAYU XR 6000 2_RAD-45349-13282-FIN.DWG


1:50 Rev:---- Rev Date: 23/ FEB/2017 Existing Layout 02/12
SCOPE OF WORKS

RS. PERSADA MEDIKA JATIRAHAYU XR 6000 2_RAD-45349-13282-FIN.DWG


1:50 Rev:---- Rev Date: 23/ FEB/2017 Scope of Works 03/12
EQUIPMENT LAYOUT
DIMENSIONS WEIGHT
ITEM DESCRIPTION LxWxH (mm) (kg)

1 STANDARD INTEGRATED TABLE 2300x1271x2240 240


2 WALL STAND 651x284.5x2060 106.5
3 POWER DISTRIBUTION BOX (PDB) 800x600x300 42
4 OPERATOR CONSOLE 340x240x110 2

WALL - ACCORDING TO RECEIVED DRAWING


6525
EXAM ROOM HEIGHT
SLAB TO SLAB HEIGHT -
FALSE CEILING HEIGHT rec 3.00 m
3726

SCAN ROOM
1988

CONSOLE ROOM

2707
3107

RS. PERSADA MEDIKA JATIRAHAYU XR 6000 2_RAD-45349-13282-FIN.DWG


1:50 Rev:---- Rev Date: 23/ FEB/2017 Equipment Layout 04/12
FLOOR REINFORCEMENT

6525

290

1474
800

2500
3726

800
2325 2500 1700

936
1988

RS. PERSADA MEDIKA JATIRAHAYU XR 6000 2_RAD-45349-13282-FIN.DWG


1:50 Rev:---- Rev Date: 23/ FEB/2017 Floor Reinforcement 05/12
FLOOR - ELECTRICAL LAYOUT
ITEM QTY DESCRIPTION

1 Table anchoring (see Floor Structural Details)


2 Wall Stand anchoring (see Floor Structural Details)

6525

1400
2000
3726

4102
1988

2707
3107

RS. PERSADA MEDIKA JATIRAHAYU XR 6000 2_RAD-45349-13282-FIN.DWG


1:50 Rev:---- Rev Date: 23/ FEB/2017 Floor - Electrical Layout 06/12
FLOOR MOUNTING FLOOR MOUNTING

TABLE AND WALLSTAND OPERATOR CONSOLE ON PEDESTAL

2160

1300 330

4 holes 210 for screw M6

4 holes 80
Cable entrance screw M10
screw M10 240
X-Ray Axis

2 holes Cable
TABLE BASE 36x16 41 entrance

WALL STAND BASE


1130

The supplied anchors require a minimum embedment of 55 mm into the concrete. If the floor thickness is less The supplied anchors require a minimum embedment of 55 mm into the concrete. If the floor thickness is less
than 75 mm, it is recommended that the unit be secured using a through-bolt method with a reinforcement than 75 mm, it is recommended that the unit be secured using a through-bolt method with a reinforcement
plate on the back side. The ground surface must be flat and leveled. plate on the back side. The ground surface must be flat and leveled.
Table weight: 240 kg (max patient load is 180 kg), Wall Stand weight: 106.5 kg Console on pedestal weight: 6 kg
Anchors supplied by GE. Anchors supplied by GE.
SCALE 1:20 SCALE 1:10

CABLE MANAGEMENT

FLUSH FLOOR DUCT VERTICAL DUCT ON WALL

waterproof joint removable cover Removable coverplate

NOT TO SCALE

RS. PERSADA MEDIKA JATIRAHAYU XR 6000 2_RAD-45349-13282-FIN.DWG Rev:---- Rev Date: 23/ FEB/2017 Floor Structural Details 07/12
FLOOR REINFORCEMENT

POWER DISCONNECT BOX

RS. PERSADA MEDIKA JATIRAHAYU XR 6000 2_RAD-45349-13282-FIN.DWG


1:50 Rev:---- Rev Date: 23/ FEB/2017 Single Line Diagram 08/12
POWER AND NETWORK REQUIREMENTS POWER DISTRIBUTION

POWER SUPPLY
FREQUENCIES
MAXIMUM INPUT POWER (0.1 sec max) 70 kVA Main supply
MAXIMUM LINE RESISTANCE 380V : 0.15 Ohm / 415V : 0.18 Ohm 3 phases Ground
PER 2 PHASES WIRES (Ohm) 440V : 0.20 Ohm / 480V : 0.24 Ohm

TNC neutral point connection must not be used.


Line supply should come into a power distribution box (PDB) containing the protective units and controls.
The section of the supply cable should be calculated in accordance with its length and the maximum 50A
permissible voltage drops.
There must be discrimination between supply cable protective device at the beginning of the installation
(main low-voltage transformer side) and the protective devices in the PDB.

SUPPLY CHARACTERISTICS PDB


Power input must be separated from any others which may generate transients (elevators, air conditioning,
radiology rooms equipped with high speed film changers...)
All equipment (lighting, power outlets, etc...) installed with GE system components must be powered
separately. 400V
24V 24V 24V
50A
GROUND SYSTEM
Equipotential: the equipotential link will be by means of an equipotential bar. This equipotential bar should be
connected to the protective earth conductors in the ducts of the non GE cableways and to additional 24V
equipotential connections linking up all the conducting units in the rooms where GE units are located.
SEO L Y G L1

CABLES
Power and cable installation must comply with the distribution diagram below.
All cables must be isolated and flexible, cable color codes must comply with standards for electrical
installation.
Case PDB furnished by GE: The cables for signals and remote control (Y, SEO, L...) will go to PDB with a pigtail PDB Power Distribution Box
length of 1.5 m, and will be connected during installation. Each conductor will be identified and isolated Y System remote-control locked when power OFF, "ON" and "OFF" impulse
(screw connector). buttons with indicator lamps red=on / green=off
L System ON light - 24V - Located near access doors
CABLEWAYS
L1 X-Ray ON light - 24V - Located near access doors
The general rules for laying cableways should meet the conditions laid down in current standards and regulations, SEO Emergency OFF, near access doors
with regard to: G Generator cabinet
Protecting cables against water (cableways should be waterproof)
Protecting cables against abnormal temperatures (proximity to heating pipes or ducts)
Protecting cables against temperature shocks
Replacing cables (cableways should be large enough for cables to be replaced)
Cable SUPPLIED BY CUSTOMER
Metal cableways should be grounded.
Equipment SUPPLIED BY CUSTOMER
NETWORK REQUIREMENTS Equipment SUPPLIED BY GE
Equipment CAN BE ORDERED FROM GE
1 RJ 45 socket is required. The network connection is made at the Operator Console. 100BaseT network
connection is preferred. 10BaseT network connection is acceptable.

RS. PERSADA MEDIKA JATIRAHAYU XR 6000 2_RAD-45349-13282-FIN.DWG Rev:---- Rev Date: 23/ FEB/2017 Power Requirements 09/12
TEMPERATURE AND HUMIDITY SPECIFICATIONS CONNECTIVITY REQUIREMENTS

IN-USE CONDITIONS Broadband Connections are necessary during the installation process and going forward to ensure full support
from the Engineering Teams for the customers system. Maximum performance and availability for the customers
EXAM ROOM CONTROL ROOM
system is maintained and closely monitored during the lifetime of the system. Proactive and reactive maintenance
Min Recommended Max Min Recommended Max
Temperature is available utilising the wide range of digital tools using the connectivity solutions listed below:

Temperature gradient <1 <1 Site-to-Site VPN/GE Solution


Relative humidity (1) 30% to 75% 30% to 80%
Humidity gradient < 30%/h < 30%/h Site-to-Site VPN/Customer Solution
System heat dissipation 0.725 kW 0.006 kW
Connection through Dedicated Service Network

Internet Access - connectivity for InSite 2.0


STORAGE CONDITIONS
Temperature STORAGE values only refer to equipment that is still in shipping The requirements for these connectivity solutions are explained in the broadband solutions catalogue (separate
containers. If the equipment is partially or completely installed, refer to document).
Relative humidity (1) 20% to 90% IN-USE values.
Temperature gradient < 20 C/h
Humidity gradient < 30%/h
Material should not be stored for more than 90 days.
(1) non-condensing

AIR RENEWAL
According to local standards.

NOTE
In case of using air conditioning systems that have a risk of water leakage it is recommended not to install it above electric equipment or to
take measures to protect the equipment from dropping water.

ENVIRONMENTAL SPECIFICATIONS

MAGNETIC INTERFERENCE
To guarantee specified imaging performance:
X-ray tubes and control console equipment must be located in ambient static field of less than 10 gauss.

ACOUSTIC OUTPUT
Measured 1 m from any point in system.
In-use: less than 60 dBA
Stand-by: less than 55 dBA

RS. PERSADA MEDIKA JATIRAHAYU XR 6000 2_RAD-45349-13282-FIN.DWG Rev:---- Rev Date: 23/ FEB/2017 HVAC - Enviroment - Connectivity 10/12
INTEGRATED TABLE FRONT VIEW INTEGRATED TABLE SIDE VIEW
855

692

2100 847

995
2000

2300 1271

INTEGRATED TABLE WITH WALL STAND FRONT VIEW

1000

RS. PERSADA MEDIKA JATIRAHAYU XR 6000 2_RAD-45349-13282-FIN.DWG


1:20 Rev:---- Rev Date: 23/ FEB/2017 Equipment Dimensions - Views - Clearance 11/12
INTERCONNECTIONS DISCLAIMER
EXAM ROOM GENERAL SPECIFICATIONS
Power
input GE is not responsible for the installation of developers and associated equipment, lighting, cassette trays and
protective screens or derivatives not mentioned in the order.
13m*/15m
The final study contains recommendations for the location of GE equipment and associated devices, electrical
10m*/12m wiring and room arrangements. When preparing the study, every effort has been made to consider every
aspect of the actual equipment expected to be installed.
The layout of the equipment offered by GE, the dimensions given for the premises, the details provided for
the pre-installation work and electrical power supply are given according to the information noted during
on-site study and the wishes expressed by the customer.
WS The room dimensions used to create the equipment layout may originate from a previous layout and may not
be accurate as they may not have been verified on site. GE cannot take any responsibility for errors due to
Integrated Table
lack of information.
Dimensions apply to finished surfaces of the room.
CONTROL ROOM Actual configuration may differ from options presented in some typical views or tables.
If this set of final drawings has been approved by the customer, any subsequent modification of the site must
be subject to further investigation by GE about the feasibility of installing the equipment. Any reservations
must be noted.

Operator console
customer's responsibility to ensure that the site and final equipment placement complies with all applicable
local requirements.
All work required to install GE equipment must be carried out in compliance with the building regulations and
........m - Total length the safety standards of legal force in the country concerned.
.......m* - Usable length These drawings are not to be used for actual construction purposes. The company cannot take responsibility
for any damage resulting therefrom.

DELIVERY CUSTOMER RESPONSIBILITIES


It is the responsibility of the customer to prepare the site in accordance with the specifications stated in the
THE CUSTOMER/CONTRACTOR SHOULD: final study. A detailed site readiness checklist is provided by GE. It is the responsibility of the customer to
ensure all requirements are fulfilled and that the site conforms to all specifications defined in the checklist and
Provide an area adjacent to the installation site for delivery and unloading of the GE equipment.
Ensure that the dimensions of all doors, corridors, ceiling heights are sufficient to accommodate the
up and ensure that actions in the checklist are complete, and if necessary, will aid in the rescheduling of the
movement of GE equipment from the delivery area into the definitive installation room.
delivery and installation date.
Ensure that access routes for equipment will accommodate the weights of the equipment and any
Prior to installation, a structrual engineer of record must ensure that the floor and ceiling is designed in such a
transportation, lifting and rigging equipment.
way that the loads of the installed system can be securely borne and transferred. The layout of additional
Ensure that all necessary arrangements for stopping and unloading on public or private property not
structural elements, dimensioning and the selection of appropriate installation methods are the sole
belonging to the customer have been made.
responsibility of the structural engineer. Execution of load bearing structures supporting equipment on the
ceiling, floor or walls are the customer's responsibility.

RADIO-PROTECTION
DIMENSIONS
Suitable radiological protection must be determined by a qualified radiological physicist in conformation with
local regulations. GE does not take responsibility for the specification or provision of radio-protection.
TABLE TUBE STAND WALL STAND BASIC WALL STAND

LENGTH (mm) 2440 2440 2190 1960


WIDTH (mm) 1220 610 800 530 THE UNDERSIGNED, HEREBY CERTIFIES THAT I HAVE READ AND APPROVED THE PLANS IN THIS DOCUMENT.
HEIGHT (mm) 1200 840 850 520
WEIGHT (kg) 640 230 220 160 DATE NAME SIGNATURE

Shipping boxes are included.

RS. PERSADA MEDIKA JATIRAHAYU XR 6000 2_RAD-45349-13282-FIN.DWG Rev:---- Rev Date: 23/ FEB/2017 Interconnections - Delivery - Disclaimer 12/12