Anda di halaman 1dari 19

PEDOMAN DAN TATACARA PEMERIKSAAN INSPECTION GUIDELINES FOR SAFETY ON

KESELAMATAN KERJA ATAS INSTALASI, FACILITIES, EQUIPMENT AND


PERALATAN DAN TEKNIK YANG TECHNOLOGY USED IN OIL AND GAS AND
DIPERGUNAKAN DALAM USAHA GEOTHERMAL ACTIVITY
PERTAMBANGAN MINYAK DAN GAS BUMI
DAN PENGUASAAN SUMBERDAYA PANAS
BUMI

Keputusan Direktur Jenderal Minyak dan Gas Bumi The Director General of Oil and gas Decree Nor:
Nomor : 84.K/38/DJM/1998 84.K/38/DJM/1998

DEPARTEMEN PERTAMBANGAN DAN


ENERGI REPUBLIK INDONESIA DEPARTMENT OF MINES AND ENERGY OF
DIREKTUR JENDERAL MINYAK DAN GAS THE REPUBLIC INDONESIA
BUMI, DIRECTOR GENERAL OF OIL AND GAS

Menimbang : Considering:
Bahwa dalam rangka kelancaran pelaksanaan that in order to smoothen the inspection guidelines
pemeriksaan keselamatan kerja atas instalasi, for safety on installation, equipment and techniques
peralatan dan teknik yang dipergunakan dalam usaha in oil and gas and geothermal activities and as
pertambangan minyak dan gas bumi dan further implementation of the Mines and Energy
pengusahaan sumberdaya panas bumi dan sebagai Minister's Regulation Number 06 P/ 0746/
pelaksanaan lebih lanjut Peraturan Menteri M.PE/1991 dated 19 November 1991, it is deemed
Pertambangan dan Energi Nomor 06 P/0746/ necessary to stipulate Inspection Guidelines for
M.PE/1991 tanggal 19 November 1991, dianggap Safety on Installation, Equipment, and Techniques
perlu menetapkan Pedoman dan Tatacara in Oil and Gas and Geothermal Activities in a
Pemeriksaan Keselamatan Kerja atas Instalasi, Decree of the Director General of Oil and Gas;
Peralatan dan Teknik Yang Dipergunakan Dalam
Usaha Pertambangan minyak dan Gas bumi Dan
Pengusahaan Sumberdaya Panasbumi dalam suatu
keputusan Direktur Jenderal Minyak Gas Bumi

Mengingat: In view of:


1. Undang-undang Nomor 44 Prp Tahun 1960 1. 1. Law No.44 Prp Year 1960 (L.N 1960 No.
(L.N. Tahun 1960 Nomor 33, TLN Nomor 33, TLN No. 2070);
2070);
2. Undang-undang Nomor 8 Tahun 1971 (L.N. 2. 2. Law No. 8 Year 1971 (L.N. 1971 No. 76,
Tahun 1971 Nomor 76, TLN Nomor 2970) TLN No. 2970)
3. Peraturan Pemerintah Nomor 11 tahun 1979 3. Government Regulation No. 11 Year 1979
(L.N. Tahun 1979 Nomor 18, TLN Nomor (L.N. Year 1979 No. 18, TLN Nomor 3135).
3135)
4. Keputusan Presiden Nomor 22 Tahun 1981 4. Decree of President No. 22 Year 1981, 1 June
tanggal 1 Juni 1981 jo Keputusan Presiden 1981 jo Decree of President No. 45 1991, 1
Nomor 45 1991 tanggal 1 Oktober 1991; October 1991;
5. Keputusan Presiden Nomor 374/M Tahun 1995 5. Decree of President No. 374/M Year 1995, 23
tanggal 23 November 1995; November 1995;
6. Peraturan Menteri Pertambangan dan Energi 6. Regulation of Mines and Energy’s minister No.
Nomor 02/PM/Pertamb/1975 tanggal 10 Maret 02/PM/Pertamb/1975, 10 March 1975;
1975;
7. Keputusan Menteri Pertambangan dan Energi 7. Decree of Mines and Energy No. 02
Nomor 02 P/M/Pertam/1979 tanggal 30 Juni P/M/Pertamb/1979, 30 June 1979;
1979;
8. Keputusan Menteri Pertambangan dan Energi 8. Decree of Mines and Energy No.
Nomor 521/Kpts/1979 tanggal 20 Juni 1979; 521/Kpts/1979, 20 June 1979;

Page 1 of 19
9. Peraturan Menteri Pertambangan dan Energi 9. Regulation of Mines and Energy No. 06
Nomor 06 P/0746/M.PE/1991 tanggal 19 P/0746/M.PE/1991, 19 November 1991;
Nopember 1991;
10. Keputusan Menteri Pertambangan dan Energi 10. Decree of Mines and Energy No.
Nomor 300.K/38/M.PE/1997 tanggal 28 April 300.K/38/M.PE/1997, 28 Avril 1997;
1997;
11. Peraturan Direktur Jenderal Minyak dan Gas 11. Regulation of Mines and Energy No.
Bumi Nomor 43/382/DDJ/1992 tanggal 19 43/382/DDJ/1992,
September 1992;

MEMUTUSKAN : HAS DECIDED :


Menetapkan : To Determine:

Pasal 1 Article 1
(1) Segala definisi atau pengertian yang (1) All definitions or understandings used in this
dipergunakan dalam Keputusan ini adalah Decree shall be the definitions or
definisi atau pengertian sebagaimana dimaksud understandings as referred to in Article 1 of the
dalam Pasal 1 Keputusan Menteri Minister of Mines and Energy's Decree No.
Pertambangan dan Energi Nomor 06P/0746/M.PE/1991 dated 19 November
06P/0746/M.PE/1991 tanggal 19 Nopember 1991.
1991.
(2) Selain sebagaimana telah ditetapkan pada ayat (2) Other than as stipulated in subsection (1), in
(1), dalam Keputusan ini yang dimaksud this Decree:
dengan :
a. Sertifikat Kelayakan Penggunaan, adalah a. Worthiness Certificate shall be any
persetujuan yang diberikan Direktur approval given by the Director General for
Jenderal atau operasi atau penggunaan the operation or use of Installation and
Instalasi dan Peralatan setelah dilakukan Equipment after Work Safety Inspection in
pemeriksaan Keselamatan Kerja, yang the form of Installation Worthiness
berupa Sertifikat Kelayakan Penggunaan Certification (SKPI) and Equipment
Instalasi (SKPI) dan Sertifikat Kelayakan Worthiness Certificate (SKPP);
Penggunaan Peralatan (SKPP);
b. Direktorat Jenderal, adalah Direktorat b. Directorate General, shall be the
Jenderal Minyak dan Gas Bumi; Directorate General Oil and gas;
c. Direktut, adalah Direktur Teknik c. Directorate General, shall be the
Pertambangan Minyak dan Gas Bumi. Directorate General Oil and gas
d. Direktorat Teknik, adalah Direktorat d. Director of Engineering, shall be Director
Teknik Pertambangan Minyak dan Gas of Oil and gas Mining Techniques;
Bumi;
e. Kepala Pelaksana Inspeksi Tambang, e. Executive Head of Mine Inspection, shall
adalah Kepala Inspeksi Tambang Minyak be the Head of Oil and gas Mine
dan Gas Bumi. Inspection;
f. Pelaksana Inspeksi Tambang, adalah f. Mine Inspector, shall be the official of the
pejabat Direktorat Jenderal yang diangkat Directorate General appointed by the
oleh Direktur jenderal; Director General;
g. Perusahaan adalah Pertamina, Kontraktor g. Company shall be Pertamina, Production
Kontrak Production Sharing, Technical Sharing Contractor, Technical Assistance
Assistance Contract, Join Operating Body, Contract, Joint Operating Body, and other
dan mitra kerja Pertamina lainnya dalam partners of Pertamina in Oil and gas
Operasi Bersama Pengusahaan Sumberdaya operation and Joint Operation Contractor
Panasbumi; for Geothermal Exploration;
h. Perusahaan Jasa adalah Perusahaan Jasa h. Service Company shall be a Company of
Inspeksi Teknik dalam bidang Technical Inspection Services in oil and
pertambangan minyak dan gas bumi dan gas mining activities and geothermal

Page 2 of 19
pengusahaan sumberdaya panasbumi yang exploration that has been assigned by the
telah mendapatkan penunjukkan Direktur Director General.
Jenderal;

Pasal 2 Article 2
(1) Terhadap Instansi dan Peralatan dalam Operasi (1) With regard to Installation and Equipment in
pertambangan minyak dan gas bumi wajib Oil and gas mining activities shall be obligated
dilaksanakan pemeriksaan Keselamatan Kerja. to carry out Work Safety Inspection.
(2) Pemeriksaan Keselamatan Kerja sebagaimana (2) The Work Safety Inspection as referred to in
dimaksud pada ayat (1) dilakukan terhadap subsection (1) shall be carried out upon
Instansi dan Peralatan yang : Installation and Equipment:
a. akan dipasang atau didirikan; a. To be installed or constructed;
b. sedang dipasang atau didirikan; b. Being installed or constructed;
c. telah dipasang atau didirikan. c. Already installed or constructed.
(3) Terhadap peralatan yang dibuat berdasarkan (3) With regard to any equipment made based on
pesanan dan bukan merupakan produksi massal, order and not constituting mass production,
pemeriksaan Keselamatan Kerja dapat Work Safety Inspection can be carried out on
dilakukan ditempat pembuatan peralatan. the equipment manufacturing plant.

Pasal 3 Article 3
Instalasi dan Peralatan yang wajib dilaksanakan The Installation and Equipment subject to a Work
pemeriksaan Keselamatan Kerja adalah sebagaimana Safety Inspection shall be as referred to in Annex I
termaksud dalam Lampiran I Keputusan ini. of this Decree.

Pasal 4 Article 4
(1) Pemeriksaan Keselamatan Kerja atas Instansi (1) Work Safety Inspection for the Installation and
dan Peralatan sebagaimana dimaksud dalam Equipment as referred to in Article 2 carried
Pasal 2 dilaksanakan oleh Pelaksana Inspeksi out by the Mine Inspector and or by Service
Tambang dan atau oleh Perusahaan Jasa. Company.
(2) Tata cara Pemeriksaan Keselamatan Kerja atas (2) Procedure for Work Safety Inspection for the
Instansi dan Peralatan adalah sebagaimana Installation and Equipment shall be as referred
termaksud dalam Lampiran II Keputusan ini. to in subsection II of this Decree.

Pasal 5 Article 5
(1) Terhadap Instansi dan Peralatan yang telah (1) Any Installation and Equipment for which a
dilaksanakan pemeriksaan Keselamatan Kerja Work Safety Inspection has been carried out,
diberikan Sertifikat Kelayakan Penggunaan shall be given a Installation Worthiness
Instansi (SKPI) dan Sertifikat Kelayakan Certificate (SKPI) and Equipment Worthiness
Penggunaan Peralatan (SKPP) oleh Direktur Certificate (SKPP) by the Director General.
Jenderal.
(2) Sertifikat Kelayakan Penggunaan Instansi (2) Installation Worthiness Certificate (SKPI) and
(SKPI) dan Sertifkat Kelayakan Penggunaan Equipment Worthiness Certificate (SKPP) as
Peralatan (SKPP) sebagaimana dimaksud pada referred to in subsection (1) shall be effective
ayat (1) berlaku selama jangka waktu 5 (lima) for a period of 5 (five) years for SKPI and 3
tahun untuk SKPI dan 3 (tiga) tahun untuk (three) years for SKPP, or less than the period
SKPP, atau kurang dari jangka waktu tersebut as mentioned above if the Installation and
di atas apabila Instansi dan Peralatan tersebut Equipment have been amended or their
mengalami perubahan atau diragukan capability is doubted.
kemampuannya.
(3) Setelah selesainya jangka waktu sebagaimana (3) After the expiry of period as referred to in

Page 3 of 19
dimaksud pada ayat (2), terhadap Instansi dan subsection (2), the Installation and Equipment
Peralatan wajib dilakukan pemeriksaan shall be subject to a Work Safety Inspection as
Keselamatan Kerja sebagaimana dimaksud referred to in Article 2.
dalam 2.

Pasal 6 Article 6
Setelah dilaksanakan evaluasi terhadap teknik yang After the techniques to be applied have been
akan dipergunakan sebagaimana termaksud dalam evaluated as referred to in Annex I letter C, Director
Lampiran I huruf C, Direktur Jenderal Cq Direktur General in this case the Director giving the
memberikan pengesahan authorization.

Pasal 7 Article 7
Besarnya biaya pemeriksaan Keselamatan Kerja atas The costs for Work Safety Inspection for the
Instansi Peralatan yang dilaksanakan oleh Installation and Equipment carried out by the
Perusahaan Jasa ditetapkan berdasarkan mekanisme Service Company shall be stipulated pursuant to the
pasar tenaga kerja bidang minyak dan gas bumi. manpower market mechanism in the field of oil and
gas.

Pasal 8 Article 8
Dalam jangka waktu 6 (enam) bulan sejak Within the period of 6 (six) months as of the
berlakunya Keputusan ini, Perusahaan yang telah enactment of this Decree, any Company that has
beroperasi atau telah menggunakan Instansi dan been in operation or has been using the Installation
Peralatan dan belum melakukan ketentuan dan and Equipment and not yet carried out the provisions
Keputusan ini wajib mengajukan permohonan of this Decree shall be obligated to request a Work
pemeriksaan Keselamatan Kerja atas Instansi, Safety Inspection for the Installation, Equipment and
Peralatan dan Teknik yang dipergunakan kepada Techniques used to the Director General in this case
Direktorat Jenderal cq. Direktorat Teknik. the Directorate of Engineering.

Pasal 9 Article 9
Apabila terdapat kekurangan-kekurangan pada If there are shortcomings in the Installation or
Instansi atau Peralatan setelah diadakan pemeriksaan Equipment after a Work Safety Inspection, then
Keselamatan Kerja, maka dalam waktu yang within the period as stipulated by Director, the
ditetapkan oleh Direktur, Perusahaan wajib Company shall be obligated to carry out repair or
mengadakan perbaikan atau perubahan sehingga modification so the Installation and Equipment meet
Instansi dan Peralatan tersebut memenuhi hal-hal the requirements pursuant to the prevailing laws and
yang disyaratkan oleh peraturan perundang- regulations.
undangan yang berlaku.

Pasal 10 Article 10
Keputusan ini berlaku pada tanggal ditetapkan. This Decree shall be effective on the date of its
enactment.

Ditetapkan di Jakarta Stipulated in Jakarta


Pada tanggal 19 Agustus 1988 On 19 August 1998

Direktur Jenderal Minyak dan Gas Bumi Director General of Oil and gas,

Soepraptono Soeleiman Soepraptono Soeleiman

Page 4 of 19
Lampiran I Keputusan Direktur Annex I of the Director General of
Jenderal Minyak dan Gas Bumi Oil and gas' Decree
Nomor: /38/DJM/1988 No.: /38/DJM/1998
Tanggal Date :

Intalasi dan Peralatan yang Wajib Dilaksanakan Installation and Equipment for which a Work
Pemeriksaan Keselamatan Kerja Safety Inspection is Obligatorily Carried Out

A. Instalasi A. Installations
1. Instalasi Eksplorasi dan Eksploitasi: 1. Exploitation and exploration instalation
a. Instansi pemboran; a. Drilling installation;
b. Instalasi produksi; b. Production installation;
c. Instalasi pengumpul; c. Collecting installation;
d. Other installation associated with
d. Instalasi lainnya yang terkait dengan Exploration and Exploitation
kegiatan Eksplorasi dan Eksploitasi. activities.
2. 1Instalasi Pemurnian dan Pengolahan : 2. Purification and Processing Installations
a. Instalasi Pemurnian dan Pengolahan; a. Purification and Processing
installation;
b. Pembongkaran dan Pemuatan; b. Loading and Unloading;
c. Instalasi lainnya yang terkait dengan c. Other installations associated with
kegiatan Pemurnian dan Pengolahan Purification and Processing activities
baik langsung maupun tidak langsung in connection, either directly or
berhubungan dengan kegiatan indirectly, with the corresponding
termaksud. activities.
3. Instalasi Penimbunan dan Pemasaran yang 3. Storage and Marketing installations:
dimaksud adalah :
a. Instalasi Seafed Depot; a. Seafed Depot Installation;
b. Instalasi Inland Depot; b. Inland Depot Installation;
c. Instalasi Depot Pengisian Pesawat c. Airplane Filling Depot Installation
Udara (DPPU); (DPPU);
d. Intalasi Transit Terminal; d. Transit Terminal Installation;
e. Instalasi Stasiun Pengisi Bahan Bakar e. Public Gas Station (SPBU) and Gas
(SPBU) dan Stasiun Pengisian Bahan Fuel Filling Station Gas (SPBG);
Bakar Gas (SPBG);
f. Instansi lainnya yang terkait dengan f. Other installations associated with
kegiatan penimbunan dan pemasaran. storage and marketing activities.

B. Peralatan B. Equipment.
1. Katup pengamanan, yaitu peralatan yang 1. Safety Valves namely any equipment useful
berguna untuk melindungi peralatan dan to protect relevant equipment and facilities
fasilitas yang terkait meliputi : cover:

Page 5 of 19
a. Safety Valve; a. Safety Valve;
b. Relief Valve; b. Relief Valve;
c. Safety Relief Valve; c. Safety Relief Valve;
d. Thermal Relief Valve; d. Thermal Relief Valve;
e. Pilot Operated Safety Valve; e. Pilot Operated Safety Valve;
f. Vacuum Relief Valve. f. Vacuum Relief Valve;

2. Bejana Tekan dan sejenisnya, yaitu 2. Pressure Vessel and similar devices namely
peralatan yang bekerja dengan tekanan any equipment working under a work
kerja didalam peralatan melebihi 1/2 Atm pressure in the equipment exceeding 1/2
tekanan lebih (gauge), atau bejana vakum Atm of overpressure (gauge), or vacuum
dengan tekanan kerja didalam peralatan pressure under a work pressure in the
kurang dari 1 atm absolut. equipment less than 1 Atm absolute.
3. Pesawat Angkat, yaitu untuk 3. Lifting Devices namely any equipment to
memindahkan, mengangkat barang secara remove, to lift any goods in vertical and or
vertikal dan atau horizontal dalam jarak horizontal direction in a stipulated
ditentukan, antara lain meliputi: distance, cover:
a. Pesawat Angkat Bergerak; a. Mobile lifting device;
b. Pesawat Angkat Tetap; b. Fixed lifting device;
c. Pesawat Angkat di atas kepala. c. Overhead lifting device;
4. Peralatan Listrik, yaitu peralatan yang 4. Electrical Equipment namely any
membangkit, mendistribusi dan equipment which generates, distributes and
mengendalikan sistem tenaga listrik, controls a power system covers:
meliputi :
a. Unit Power Generator; a. Power Generator Unit;
b. Unit Power Transformer; b. Power Transformer Unit;
c. Unit Switchgear; c. Switchgear Unit;
d. Unit Motor Control Center. d. Motor Control Center Unit.
5. Peralatan Putar, yaitu peralatan yang 5. Rorating Equipment namely any equipment
berfungsi memindahkan atau memanpatkan serving to remove or compress petroleum,
minyak, gas serta panasbumi meliputi : gas, and geotherm covers:
a. Unit Kompresor; a. Compressor Unit;
b. Unit Pompa. b. Pump Unit.
6. Pipa Penyalur, yaitu bentang pipa berikut 6. Distribution pipes, namely a network of
fasilitas-fasilitas terkait yang digunakan pipes with relevant facilities used to flow
untuk mengalirkan dan menyalurkan and distribute oil and gas and geotherm.
minyak dan gas bumi serta panas bumi.

c. Teknik Yang Dipergunakan a. Techniques Used


Teknik yang dipergunakan, yatiu tatacara atau Techniques used namely procedures to be used in
prosedur yang akan dipergunakan dalam operasi Oil and gas mining activities cover:
pertambangan minyak dan gas bumi antara lain,
meliputi :
1. Spesifikasi Prosedur Las (WPS) dan Rekaman 1. Specification of Welding Procedures (WPS) and
Kualifikasi Prosedur (PQR); Procedure Qualification Records (PQR);
2. Catatan Unjuk Kerj (Sertifikat) Juru 2. Performance Note (Certificate) of
Las/Operator Las; Welder/Welding Operator;
3. Prosedur Uji Tekan Pipa Penyalur; 3. Pressure Testing Procedures of Distribution

Page 6 of 19
Pipes;
4. Prosedur Uji Beban Pesawat Angkat; 4. Load Test Procedures of Lifting Devices;
5. Prosedur Reparasi, Modifikasi dan Alterasi. 5. Procedures for Reparation, Modification and
Alteration.

Ditetapkan di Jakarta Stipulated in Jakarta


Pada tanggal 19 Agustus 1998 On,August 19,1998

Direktur Jenderal Minyak dan Gas Bumi Director General of Oil and gas

Soepraptono Soeleiman Soepraptono Soeleiman


Lampiran II Keputusan Direktur Annex I of the Director General of
Jenderal Minyak dan Gas Bumi Oil and gas' Decree
Nomor Number: /38/DJM/1998
Tanggal Date :

Tata Cara Pemeriksaan Keselamatan Kerja atas Procedure for Work Safety Inspection for The
Instalasi dan Peralatan Installation and Equipment

I. Pemeriksaan Keselamatan Kerja Instalasi I. Work Safety Inspection of Installation

A. Pemeriksaan Keselamatan Kerja Instalasi A. Work Safety Inspection of Installation coveres


meliputi penilaian perencanaan dengan evaluation of planning by carrying out review of
melaksanakan penelaahan terhadap data : data:
a. Peralatan proses, utilitas dan pengolah b. Process equipmeSnt, utilities and waste
limbah; processing equipment;
b. Alat ukur dan metering; c. Measuring devices and metering;
c. Sistem perpipaan; d. Piping system;
d. Sistem instrumentasi; e. Instrumentation system;
e. Piranti Pengaman f. Safety devices;
f. Tangki Timbul; g. Storage tanks;
g. Sistem pencegahan dan penanggulangan h. Fire prevention and control system;
kebakaran;
h. Sistem pencegahan dan pemantauan i. Environmental pollution prevention and
pencemaran lingkungan; monitoring system;
i. Peralatan lain; j. Other equipment;
j. Diagram alir proses dan diagram pipa & k. Process flow diagrams and pipe &
instrumen; instrument diagrams;
k. Gambar tata letak peralatan; l. Layout drawing of equipment;
l. Pekerjaan sipil; m. Civil works;

Page 7 of 19
m. Klasifikasi daerah berbahaya (hazardous n. Hazardous area classification;
area classification);
n. Electrical one line diagram; o. Electrical one-line diagram;
o. Gambar tata letak pentanahan (grounding p. Grounding layout drawing;
lay-out);
p. Diagram cause & effect / SAFE Chart; q. Cause & effect diagram / SAFE Chart;
q. Prosedur kerja pengoperasian peralatan; r. Operating procedures for equipment;
r. Prosedur evakuasi darurat; s. Procedures for emergency evacuation;
s. Surat persetujuan atau rekomendasi dari t. Letter of approval or recommendation from
instansi yang berwenang untuk program the authorized institution for the
Pengolahan dan Pemantauan Lindungan environmental management and
Lingkungan. management proggrams.

A. Pemeriksaan Fisik A. Physical Inspection.


Pemeriksaan fisik meliputi : Physician inspection covers:
1. Pemeriksaan Instalasi untuk memastikan 3. Inspection of Installation to verify the
sesuai tidaknya Intalasi dengan conformance of Installation with the
perencanaan, spesifikasi, prosedur planning, specification, production and
pembuatan dan pemasangan. installation procedures.
2. Memeriksa Kelengkapan Mutu Peralatan, 4. Inspection of Equipment Quality, Work
Teknik Keselamatan Kerja dan Lindungan Safety Techniques and Environmental
Lingkungan meliputi : Protection covers:
a. Alat Pemadam kebakaran; a. Fire fighting equipment;
b. Alat deteksi api, panas, asap dan gas b. Fire, heat, smoke and hazardous gas
berbahaya; detection devices;
c. Alat perlengkapan penyelamatan dan c. Individual safety and protection
pelindung perorangan; equipment;
d. Sistem komunikasi; d. Communication system;
e. Sistem kontrol dan penghentian darurat e. Emergency control and shutdown
(emergency shutdown system); system;
f. Pemeriksaan tangga, lampu, bordes dan f. Inspection of stairs, lamps, balustrade
handrail; and handrail;
g. Flaring; g. Flaring;
h. Rock Muffler; h. Rock Muffler;
i. Peralatan pencegahan dan i. Environmental pollution prevention and
penanggulangan pencemaran control equipment;
lingkungan;
j. Sistem untuk meniadakan bahaya listrik j. System to eliminate static electrical
statis dan arus listrik lainnya; hazards and other electrical current;
k. Tanda-tanda keselamatan kerja, antara k. Work safety signs, such as; warning
lain; tanda peringatan, larangan kode signs, prohibitions, color code and other
warna dan tanda lainnya. signs.
1. Memeriksa Kelengkapan Sertifikat 1. Inspection of the completeness of Equipment
Kelayakan Penggunaan peralatan, Sertifikat Worthiness Certificate, Platform
Kelayakan Konstruksi Platform serta Ijin Construction Worthiness Certificate, Permit
Penggunaan dari Instansi teknis terkait of Use from the relevant technical institution
antara lain: such as:
d. Katup Pengaman; d. Safety valve;
e. Bejana Tekan dan peralatan lain e. Pressure vessel and other similar
sejenisnya; equipment;

Page 8 of 19
f. Peralatan Berputar (unit pompa dan unit f. Rotating Equipment (pump units and
kompresor); compressor units);
g. Peralatan listrik; g. Electrical equipment;
h. Pesawat Angkat; h. Lifting devices;
i. Pipa Penyalur; i. Distribution pipes;
j. Struktur Anjungan Lepas Pantai; j. Offshore Platform Structure;
k. Ketel Uap & Bejana, Alat bantu k. Steam Boiler & Steam Vessel,
Navigasi, Alat Ukur dan Metering, Alat Navigation Devices, Measuring Devices
Timbang, Helideck, Zat Radio Aktif, & Metering, Weighting Devices,
Bahan Peledak, dan lain-lain; Helideck, Radioactive Materials,
Explosives, etc.;
l. Peralatan penyelamatan dan pelindung l. Individual Safety and Protection
perorangan. Equipment.
3. Khusus Instalasi pemboran wajib dilakukan 3. Particularly for the Drilling Installation,
pemeriksaan berkala sesuai dengan periodic inspection shall be obligatorily
Pedoman Pelaksanaan Pemboran Darat dan carried out pursuant to Implementative
Lepas Pantai Yang Aman di Indonesia (KK- Guidance for Safe Land and Offshore
01-DJM). Operation in Indonesia (KK-01-DJM).
4. Pemeriksaan Pre-Commissioning, 4. Pre-Commissioning, Commissioning and
Commissioning dan Pengujian. Testing Inspection.

A. Pelaporan B. Reporting
Menyusul seluruh hasil pemeriksaan teknis
berbentuk dokumen untuk diserahkan ke To prepare all results of technical inspection in
Direktur Direktorat Teknik Pertambangaan the form of documents to be submitted to the
Minyak dan Gas Bumi sebagai bahan evaluasi Director of the Directorate of Oil and gas Mining
untuk penerbitan Sertifikat Kelayakan Techniques as evaluation materials for the
Penggunaan Instansi. issuance of Installation Worthiness Certificate.

II. Pemeriksaan Keselamatan kerja atas Peralatan I. Work Safety Inspection of Equipment

A. Pemeriksaan Keselamatan Kerja Katup A. Work Safety Inspection of Safety Valve


Pengaman

Pemeriksaan teknis katup pengaman meliputi : Technical inspection OF safety valve includes:
a. Penelaahan Dokumen c. Review of Documents
− P & ID (Piping & Instrumen Diagram) − P & ID (Piping & Instrument Diagram)
− Dokumen katup pengaman − Safety valve documents
− Plat nama − Name plates
− Tipe katup pengaman − Types of safety valve:
− Konvensional − Conventional
− Pilot − Pilot
− Balance − Balance
− Sertifikat Kelayakan Penggunaan test bench − Worthiness Certificate for test bench
− Rekaman Kalibrasi presure gauge/indicator − Calibration Records for pressure gauge/
indicator
− Perhitungan tekanan uji cold diff untuk − Calculation of cold diff. testing pressure to

Page 9 of 19
menentukan tekanan buka nyata determine real open pressure
a. Pelaksanaan pengujian a. Implementation of testing
− Uji tekanan buka − Open pressure test
− Uji bojor − Leakage test
b. Rekaman Hasil Uji b. Records of Test Results
Rekaman hasil uji diisi berdasarkan dokumen Records of test are completed pursuant to the
katup pengaman, data plat nama serta data documents of safety valve, data of name plate
pengujian sebagai bahan evaluasi penertiban and data of testing as evaluation materials for the
Sertifikat Kelayakan Penggunaan Peralatan. issuance of Equipment Worthiness Certificate.
c. Penyegelan d. Sealing
Penyegelan katup pengaman dilakukan oleh Sealing of safety valve shall be carried out by the
Pelaksana Inspeksi Tambang pada pengatur Mine Inspector in the controller of safety valve
katup pengaman yang telah diuji dengan hasil already tested with good results using Oil and gas
baik dengan menggunakan Segel Migas. seal.

B. Pemeriksaan Keselamatan Kerja Bejana Tekan A. Work Safety Inspection of Pressure Vessel and
dan Sejenisnya Similar Equipment

Pemeriksaan Teknis bejana tekan dan sejenisnya Technical inspection of pressure vessel and similar
dibedakan menjadi 3 (tiga) bagian : equipment shall be differentiated into 3 (three) parts:
1. Bejana tekan dan sejenisnya yang baru dan atau 2. Pressure vessel and its new similar equipment
akan dipasang. and or those to be installed.
2. Bejana tekan dan sejensinya yang lama dan atau 3. Pressure vessel and its old similar equipment and
telah dipasang. or those to be installed.
3. Bejana tekan dan sejenisnya yang mengalami 4. Pressure vessel and its similar equipment
reparasi/alterasi/modifikasi. experiencing any
reparation/alteration/modification.

A.1 Pemeriksaan teknis bejana tekan dan C.1 Technical inspection of pressure vessel and its
sejenisnya yang baru dan atau akan dipasang new similar equipment and or those to be
installed.
a. Penelaahan data yang meliputi : a. Review of data covers:
− Gambar konstruksi dan perhitungan − Construction drawing and calculation
bejana takan; of pressure vessel;
− Spesifikasi material yang digunakan; − Specification of materials to be used;
− Spesifikasi prosedur las dan rekanan − Specification of welding procedures
kualifikasi prosedur serta catatan and procedure qualification records
kualifikasi (sertifikat) unjuk kerja and qualification notes (certificates)
juru / operator las; of welder/welding operator
performance;
− Prosedur uji tidak merusak dan − Non-destructive procedures and
kualifikasi personilnya; personal qualification;
− Prosedur reparasi; − Reparation procedures;
− Prosedur perlakuan panas pasca las − Post-welding heat treatment
(bila diisyaratkan); procedures (if required);
− Prosedur uji tekan; − Pressure testing procedures;
b. Pemeriksaan fisik yang meliputi : b. Physical inspection covers;
− Verifikasi sistem pengendalian mutu − Verification of manufacturing quality
manufaktur; control system;

Page 10 of 19
− Identifikasi material yang akan − Identification of materials to be used;
digunakan;
− Verifikasi pembentukan bejana; − Verification of formation of vessels;
− Verifikasi pemasangan sambungan; − Verification of joint installation;
− Verifikasi persiapan pengelasan; − Verification of welding preparation;
− Pemeriksaan hasil las serta verifikasi − Inspection of welding results and
hasil uji coba tanpa merusak; verification of results non-destructive
testing;
− Pengukuran dimensi bejana dan − Measurement of vessel dimensions
pemeriksaan internal; and internal inspection;
− Uji bocor dan uji tekan. − Leakage and pressure tests;
− Verifikasi formulir pemanufaktur dan − Verification of manufacturing form
plat nama bejana. and name plate of vessel.
a. Uji Tekanan : b. Pressure test:
− Pemeriksaan rekaman kalibrasi alat − Inspection of records of calibration of
pengukur dan alat pencatat tekatan, the measuring devices and pressure
termasuk daerah jangkau yang recorders, including ranges allowed
diijinkan untuk tekanan uji yang for the corresponding testing pressure,
bersangkutan, dimana skala in which the scale of maximum
penunjukkan maksimum peralatan indication of the corresponding
termaksud 1,5 - 4 kali tekanan uji. equipment is 1.5-4 times the testing
pressure.
− Uji tekan dilaksanakan dengan − Pressure test shall be carried out by
menaikkan tekanan secara bertahap gradually increasing pressure and
dan dicatat dengan alat pencatat recorded with a pressure recorder up
tekanan sampai tekanan uji yang telah to the stipulated testing pressure, then
ditentukan kemudian tekanan ditahan the pressure is held for a period of
minimum selama 2 (dua) jam dan minimum 2 (two) hours and after the
setelah itu tekanan dikeluarkan secara pressure is gradually released.
bertahap.
a. Pelaporan b. Reporting
Menyusun seluruh hasil pemeriksaan teknis To prepare all results of technical
berbentuk dokumen untuk diserahkan ke inspection in the form of documents to be
Direktur Direktorat Teknik Pertambangan submitted to the Director of the Directorate
Minyak dan Gas Bumi sebagai bahan of Oil and gas Mining Techniques as
evaluasi untuk penerbitan Sertifikat evaluation materials for the issuance of
Kelayakan Penggunaan Peralatan. Equipment Worthiness Certificate.

A.2 Pemeriksaan teknis bejana tekan dan A.2 Technical inspection of pressure vessel and
sejenisnya yang lama dan atau akan dipasang its old similar equipment and or those
already installed.
b. Penelaahan data yang meliputi : b. Review of data covers:
− Sertifikat kelayakan penggunaan − Equipment Worthiness Certificate
peralatan yang akan diperpanjang the effective period of which will
masa berlakunya; be extended;
− Catatan riwayat penggunaan bejana; − Historical Notes of vessel;
− Gambar bangunan bejana (as built − Construction drawing of vessel (as
drawing); built drawing);
− Salinan plat nama atau marka keras − Copy of name plate or other hard
lainnya; marks;
− Prosedur kerja aman melakukan − Safe work procedures to carry out

Page 11 of 19
pemeriksaan. inspection.
a. Penelaahan data yang meliputi : b. Review of Data covers:
− Pemeriksaan visual kondisi bejana; − Inspection visual of vessel
conditions;
− Verifikasi hasil pengukuran terakhir − Verification of results of last
tebal bejana yang dilakukan oleh measurement of vessel thickness
perusahaan; carried out by the Company.
− Melakukan pengukuran tebal bejana; − Measurement of vessel thickness
− Uji tidak merusak (bila diperlukan) − Non-destructive testing (if
required)
− Verifikasi hasil perhitungan sisa − Verification of results of
umur bejana. calculation of remaining age of
vessel.
c. Pelaporan a. Reporting
To prepare all results of technical
Menyusun seluruh hasil pemeriksaan teknis inspection in the form of documents to
berbentuk dokumen untuk diserahkan ke be submitted to the Director of the
Direktur Direktorat Teknik Pertambangan Directorate of Oil and gas Mining
minyak dan Gas Bumi sebagai bahan Techniques as evaluation materials to
evaluasi untuk menerbitkan Sertifikat control Equipment Worthiness
Kelayakan. Penggunaan Peralatan. Certificates.

B.3 Pemeriksaan teknis bejana tekan dan A.3 Technical inspection of pressure vessel and its
sejenisnya yang mengalami similar equipment experiencing
reparasi/alterasi/modifikasi reparation/alteration/modification
c. Penalaahan Data yang meliputi : c. Data study are cover :
− Sertifikat Kelayakan Penggunaan − Equipment Worthiness Certificate to
Peralatan yang akan diterbitkan dan be issued and or the effective period
atau diperpanjang masa berlakunya; of which is extended;
− Catatan riwayat penggunaan bejana; − Historical notes on use of vessel;
− Gambar bangunan dan konstruksi − Drawing of building and construction
bejana; of vessel;
− Salinan plat nama atau marka keras − Copy of name plate or other hard
lainnya; marks;
− Prosedur kerja aman melakukan − Safe work procedures to carry out
pemeriksaan. inspection;
− Prosedur reparasi/alterasi/modifikasi; − Procedures for reparation
/alteration/modification;
− Calculation of reparation/alteration/ − Calculation of reparation/alteration/
modification; modification;
− Spesifikasi material bahan pengganti; − Specification of substitute materials;
− Spesifikasi prosedur las dan rekaman − Specification of welding procedures
kualifikasi prosedur serta catatan and procedure qualification records
kualifikasi (sertifikat) unjuk kerja and qualification notes (certificate) of
juru/operator las; welder/welding operator performance;
− Prosedur uji tidak merusak dan − Procedures for non-destructive testing
kualifikasi personilnya; and personal qualification
− Prosedur perlakuan panas pasca las − Procedures for post-welding heat
(bila diisyaratkan); treatment (if required);
a. Pemeriksaan fisik yang meliputi : c. Physical inspection covers:

Page 12 of 19
− Verifikasi sistem pengendalian mutu − Verification of manufacturing quality
pemanufaktur; control system;
− Identifikasi material yang akan − Identification of materials to be used;
digunakan;
− Verifikasi pemebentukan bejana; − Verification of formation of vessel;
− Verifikasi pemasangan sambungan; − Verification of joint installation;
− Verifikasi persiapan pengelasan; − Verification of welding preparation;
− Pemeriksaan hasil las serta verifikasi − Inspection of welding results and
hasil uji tanpa merusak; verification of results of non-
destructive tests;
− Pengukuran dimensi bejana; − Measurement of vessel dimensions;
− Uji bocor dan uji tekan (bila − Leake and pressure tests (if required);
diperlukan);
− Verifikasi formulir pemanufaktur dan − Verification of manufacturing forms
plat nama bejana; and name plate of vessel;
− Verifikasi hasil pengukuran tebal − Verification of results of
bejana yang dilakukan oleh measurement of vessel thickness that
Perusahaan; will be carried out by the Company;
− Melakukan pengukuran tebal bejana; − Measurement of vessel thickness;
− Verifikasi hasil perhitungan sisa − Verification of results of calculation
umur bejana; of remaining age of vessel;
a. Pelaporan a. Reporting
Menyusun seluruh hasil pemeriksaan
teknis berbentuk dokumen untuk To prepare all results of technical
diserahkan ke Direktur Direktorat Teknik inspection in the form of documents to be
Pertambangan minyak dan Gas Bumi submitted to the Director of the Directorate
sebagai bahan evaluasi untuk menerbitkan Oil and gas Mining Techniques as
Sertifikat Kelayakan. Penggunaan evaluation materials for the issuance of
Peralatan. Equipment Worthiness Certificate.

A. Pemeriksaan Keselamatan Kerja Pesawat Angkat A. Work Safety Inspection of Lifting Devices

Pemeriksaan teknis pesawat angkat meliputi : Technical inspection of lifting devices covers:
b. Penelaahan Dokumen d. Study of Documents
1. Spesifikasi perencanaan dan tabel beban 4. Specification of planning and load table
2. Perhitungan perencanaan 5. Calculation of planning
3. Gambar perencanaan 6. Drawing of planning
4. Material yang digunakan 7. Materials to be used
5. Spesifikasi sambungan 8. Specification of joints
6. Sumber tenaga yang digunakan 9. Power sources used
7. Petunjuk operasi (Operasi Manual) 10. Operation Manual
a. Pemeriksaan fisik a. Physical inspection
6. Pemeriksaan sambungan-sambungan 1. Inspection of joints
7. Pemeriksaan kait pemegang beban 2. Inspection of load holding hook
8. Pemeriksaan bagan yang bergerak serta 3. Inspection of moving and rotating parts
berputar

Page 13 of 19
4. Inspection of hydraulic / pneumatic
9. Pemeriksaan sistem hidrolik/pneumatik system
10. Pemeriksaan kondisi tali baja (wire rope) 5. Inspection of steel wire rope conditions
termasuk ikatan simpul dan jumlah lilitaan. including knot binding and number of
windings
11. Verifikasi fungsi indikator-indikator 6. Verification of functions of indicators
12. Verifikasi dimensi boom 7. Verification of boom dimensions
13. Verifikasi counter weight 8. Verification of counter weight
14. Pemeriksaan persiapan pengujian 9. Inspection of testing preparation
− Persiapan tempat pengujian − Preparation of testing locations
− Prosedur pengujian − Procedures of testing
− Persiapan alat uji antara lain : − Preparation of testing devices such as:
− Alat ukur beban (load cell) − Load measuring devices (load cells)
− Beban uji − Testing loads
− Alat-alat ukur lainnya − Other measuring devices
− Operator yang sudah berkualifikasi − Qualified operators
a. Pelaksanaan pengujian c. Implementation of testing
− Uji fungsi tanpa beban − Functional tests without load
− Uji beban sesuai dengan prosedur uji beban − Load tests pursuant to the load test
yang telah mendapat pengesahan Direktur procedures already approved by the Director.
e. Pemeriksaan setelah pengujian a. Post-testing inspection
Pemeriksaan atas seluruh bagian-bagian Inspection of all parts, either loaded, moving,
terbebani dan bergerak ataupun yang diam untuk or standstill to know any possibility of
mengetahui kemungkinan adanya deformasi, deformation, crack, loose bolts or other
retak, longgar pada baut dan atau cacat-cacat defects.
lainnya.
d. Pemeriksaan khusus a. Special inspection
− Apabila pesawat angkat mengalami − If a lifting device experiences any damage
kerusakan atau diragukan kemampuannya. or its capacity is doubted.
− Apabila diadakan perbaikan atau perubahan − If any principal repair or change is done
prinsipil pada pesawat angkat. on a lifting device.
g. Rekaman hasil uji a. Records of test results
Rekaman hasil uji diisi berdasarkan atas data Records of test results are completed pursuant
pesawat angkat dan hasil uji. to the data of lifting device and test results.
a. Pelaporan a. Reporting
Menyusun seluruh hasil pemeriksaan teknis To report all results of technical inspection in
berbentuk dokumen untuk diserahkan ke the form of documents to be submitted to the
Direktur Direktorat Teknik Pertambangan Director of the Directorate of Oil and gas
minyak dan Gas Bumi sebagai bahan evaluasi Mining Techniques as evaluation materials for
untuk menerbitkan Sertifikat Kelayakan. the issuance of Equipment Worthiness
Penggunaan Peralatan Certificate.

B. Pemeriksaan Keselamatan Kerja Unit Pompa, B. Inspection of Work Safety of Pump Units,
Unit Kompresor dan Penggeraknya Compressor Units and Their Driving Force

Pemeriksaan teknis unit pompa, unit kompresor dan Technical inspection of pump units, compressor
penggeraknya meliputi : units and their driving force covers:

Page 14 of 19
a. Penilaian terhadap rancang bangun unit Pompa, a. Evaluation of design of pump units,
unit Kompresor dan penggeraknya dengan compressor units and their driving force by
melaksanakan penelaahan data : reviewing the data:
− Spesifikasi perencanaan; − Specification of planning;
− Gambar dan perhitungan perencanaan; − Drawing and calculation of planning;
− Spesifikasi material yang digunakan; − Specification of materials to be used;
− Spesifikasi sambungan yang digunakan; − Specification of joints to be used;
− Spesifikasi komponen utama dan pendukung − Specification of main and support
serta piranti pengaman yang digunakan; components and safety devices used;
− Pedoman pengoperasian dan − Operation and maintenance manual.
pemeliharaannya.
b. Penilaian pabrikasi dengan melaksanakan a. Evaluation of fabrication by reviewing any
penelaahan laporan inspeksi yang dilakukan oleh reports of inspection carried out by an
Pihak Ketiga yang indenpenden di pabrik independent Third Party at the manufacturer's
pembuat yang terdiri dari antara lain : plant consisting of:
− Identifikasi material; − Identification of materials;
− Verifikasi pipa-pipa instrumen; − Verification of instrument pipes;
− Verifikasi pengujian komponen-komponen − Verification of testing of main components;
utama;
− Hasil uji balancs; − Results of balance tests;
− Hasil pemeriksaan kelurusan (aligment) − Results of alignment inspection of coupling
kopling dan poros/kompresor dengan and pump/compressor shafts with their
penggeraknya; driving force;
− Hasil "factory acceptance test" yang telah − Results of "factory acceptance test" already
dilakukan di pabrik pembuat; carried at the manufacturer's plant;
− Pemeriksaan terhadap sistem penggeraknya. − Inspection of driving force system.
c. Pemeriksaan fisik, yaitu pemeriksaan mengikuti c. Physical inspection, namely inspection following
proses pemasangan unit Pompa/unit Kompresor the installation process of pump
dengan penggeraknya di lokasi pemasangan units/compressor units with their driving force at
dengan melakukan: the installation location by carrying out:
− Identifikasi peralatan komponen; − Identification of equipment and components;
− Pemeriksaan kondisi struktur pondasi; − Inspection of structural foundation
conditions;
− Pemeriksaan kelengkapan alat ukur dan − Inspection of completeness of measuring
piranti pengaman; devices and safety devices;
− Pemeriksaan umum kondisi pemasangan unit − General inspection installation conditions for
Pompa/unit Kompresor dan penggeraknya; pump units/compressor units and their
driving force;
− Uji mekanikal, kelistrikan dan instrumen; − Mechanical, electrical and instrumentation
tests;
− Uji coba piranti pengaman; − Trial tests of safety devices;
− Pemeriksaan pelaksanaan "start-up"; − Inspection of "start-up";
− Uji kemampuan. − Performance tests.

d. Pelaporan d. Reporting
Menyusun seluruh hasil pemeriksaan teknis To prepare all technical results of inspection in
berbentuk dokumen untuk diserahkan ke the form of documents to be submitted to the
Direktur Direktorat Teknik Pertambangan Director of the Directorate of Oil and gas Mining

Page 15 of 19
minyak dan Gas Bumi sebagai bahan evaluasi Techniques as evaluation materials for the
untuk menerbitkan Sertifikat Kelayakan. issuance of Equipment Worthiness Certificate.
Penggunaan Peralatan

E. PEMERIKSAAN KESELAMATAN KERJA E. WORK SAFETY INSPECTION


PIPA PENYALUR DISTRIBUTION PIPES
Pemeriksaan teknis pipa penyalur meliputi : Technical inspection of distribution pipes covers:
a. Penelaahan Dokumen : a. Study of Documents:
− Umum − General
0. Lokasi 1. Location
0. Jadwal penyelesaian pembangunan 2. Construction completion schedule
0. Spesifikasi perencanaan 3. Specification of planning
0. Spesifikasi prosedur las dan rekaman 4. Specification of welding procedures and
kualifikasi prosedur serta catatan procedure qualification records and
kualifikasi (sertifikat) unjuk kerja qualification notes (certificates) for the
juru/operator las performance of welder/welding operator
0. Prosedur reparasi 5. Procedures of reparation
0. Spesifikasi material yang digunakan 6. Specification of materials used
0. Prosedur pengoperasian dan 7. Operation and maintenance procedures
pemeliharaan
0. Prosedur pembersihan dan pengeringan 8. Cleaning and drying procedures
0. Data Piranti pengaman 9. Data of safety devices
a. Rancang bangun a. Construction
1. Penelaahan peta jalur bentang pipa penyalur 0. Study of map of distribution pipes such as:
antara lain :
− Kedalaman letak pipa penyalur − Depth of maximum and minimum
maksimum dan minimum (khusus pipa distribution pipes (particularly offshore
penyalur lepas pantai) distribution pipes)
− Sudut kemiringan − Inclination angle
− Keadaan perparitan − Depth of ditch
− Jarak bentangan maksimum yang − Maximum span distance with support
tersangga
− Right of Way (ROW) − Right of Way (ROW)
2. Penelaahan metode pelengkungan pipa di 2. Study of pipe bending method in the location
lokasi meliputi: covers:
− diameter pipa − Pipe diameter
− ketebalan pipa − Pipe thickness
− radius lengkung pipa − Pipe bending radius
3. Penelaahan beban pipa penyalur : 3. Study of distribution pipe loads :
− Beban operasi antara berat sendiri, − Operation loads such as own weight,
tekanan internal dan eksternal,ekspansi internal and external pressures, heat
panas, daya apung dan lain-lain. expansion, floating power, etc.
− Beban lingkungan antara lain − Environmental loads such as wave,
gelombang, arus, angin, gempa dam current, wind, earthquake etc.
lain-lain.
− Beban pemasangan antara lain − Installation loads such as buckling,
buckling, residual stress yang terjadi residual stresses occurring during pipe

Page 16 of 19
saat instalasi pipa. installation.
4. Penelaahan perhitungan perhitungan 4. Study of calculation of distribution pipe
kekuatan pipa penyalur antara lain : power such as:
− Tegangan yang terjadi pada pipa − Stress occurring in the distribution
penyalur, buckling, on bottom stability pipes, Buckling, on bottom stability
(khusus pipa penyalur lepas pantai) (particularly offshore distribution pipes)
− Perhitungan penyangga pipa penyalur − Calculation of distribution pipe support
− Perhitungan tekanan uji yang akan − Calculation of testing pressure to be
dilakukan. carried out.

5. Penelaahan perhitungan pengendalian korosi 5. Study of calculation of corrosion control


antara lain: such as:
− Karateristik korosi − Characteristics of corrosion
− Metode pengendalian korosi − Corrosion control methods
− Spesifikasi dan dimensi coating − Specification and dimensions of coating
− Kebutuhan pengendalian korosi yang − Corrosion control needs
diperlukan
6. Penelaahan pada fasilitas terkait dan sistem 6. Study of relevant facilities and
instrumentasi antara lain : instrumentation system such as:
− Sistem pipa terkait seperti riser, pig − Relevant pipe system such as riser, pig
launcher, pig receiver,sistem metering launcher, pig receiver, metering system,
dan lain-lain etc.
− Stasiun penguat − Reinforcing station
− Sistem instrumentasi seperti sistem − Instrumentation system such as
penghentian darurat, katup pengaman emergency termination system, safety
dan lain-lain. valve, etc.
7. Penelaahan surat persetujuan atau 7. Study of letter of approval or
rekomendasi dari instansi yang berwenang recommendation from the authorized
untuk program pengelolaan dan pemantauan institution for the environmental
lingdungan lingkungan. management and monitoring programs.
8. Penelaahan data rencana operasi 8. Study of data of operation plans
− Penggunaan (service) − Use (service)
− Specific grafity − Specific gravity
− Tekanan normal masuk − Inlet normal pressure
− Tekanan normal keluar − Outlet normal pressure
− Tekanan operasi maksimum − Maximum operation pressure
− Temperatur operasi − Operation temperature
Laju aliran operasi Operation flow rate
c. Pemeriksaan fisik meliputi : c. Physical inspection covers:
− Identifikasi material yang akan digunakan; − Identification of materials to be used;
− Pemeriksaan lokasi jalur pipa penyalur untuk − Inspection of location of distribution pipe
memastikan klasifikasi area, tipe konstruksi routes to confirm classification area, type of
dari jarak aman yang tersedia; construction and safe distance average;
− Pemeriksaan persiapan pengelasan dan − Inspection of welding preparation and
kesamaan sumbu serta kelurusan sambungan similarity of axis and alignment of pipe
pipa; joints;
− Pemeriksaan sistem penyangga dan − Inspection of support and ditch system;

Page 17 of 19
perparitan;
− Penelaahan hasil uji tidak merusak; − Study of results of non-destructive test;
− Kondisi dan rekaman hasil uji sistem − Conditions and records of test results of
pengendalian korosi serta pemberat pipa corrosion control system and pipe weightier
(khusus pipa penyalur lepas pantai); (particularly offshore distribution pipes);
− Pemeriksaan pelaksanaan pembersihan dan − Inspection of cleaning and drying in
pengeringan dalam pipa penyalur; distribution pipes;
− Pemeriksaan kelengkapan piranti pengaman; − Inspection of completeness of safety devices;
d. Pemeriksaan pelaksanaan uji tekan d. Inspection implementation of pressure test
Kelengkapan peralatan uji yang terdiri dari : Completeness of testing equipment consisting of:
− Deat weight tester (DWT) − Dead weight tester (DWT)
− Pengukuran tekanan − Pressure measuring device
− Pengukuran temperatur − Temperature measuring device
− Pencatat tekanan (pressure recorder) − Pressure recorder
− Perekam Temperatur − Temperature recorder
− Pompa − Pump
Alat pengukur dan pencatat tersebut harus Measuring devices and recorders must be
dikalibrasi sebelum digunakan, dan skala calibrated before use, and the scale of maximum
penunjukkan maksimumnya adalah 1,5 - 4 kali indication shall be 1.5-4 times the testing
tekanann uji. pressure.
e. Uji tekan e. Pressure test
Uji tekan dilaksanakan dengan menaikkan Pressure test shall be carried out by gradually
tekanan secara bertahap sampai dengan tekanan raising the pressure up to the testing pressure and
uji dan ditahan mikimum selama 24 (dua puluh maintained minimum for 24 (twenty-four) hours
empat) jam untuk pipa penyalur didarat, for distribution pipes on land, minimum for 8
mikimum 8(delapan) jam untuk pipa penyalur (eight) hours for office-shore distribution pipes
dilepas pantai dan mikimum 2 (dua) jam untuk and minimum for 2 (two) hours for geothermal
pipa penyalur uap panas bumi. steam distribution pipes.
f. Pelaporan f. Reporting
Menyusun seluruh hasil pemeriksaan teknis
berbentuk dokumen untuk diserahkan ke To prepare all results of technical inspection in
Direktur Dirkloret Teknik Pertambangan Minyak the form of documents to be submitted to the
dan Gas Bumi sebagai bahan evaluasi untuk Director of the Directorate of Oil and gas Mining
penerbitan Sertifikat Kelayakan Penggunaan Techniques as evaluation materials for the
Peralatan. issuance of Equipment Worthiness Certificate.

F. Pemeriksaan Keselamatan Kerja Unit Power F. Work Safety Inspection for Power Generator,
Generator, Unit Transformer, Unit Switchgear Transformer, Switchgear and Motor Control
dan Unit Motor Control Center Center Units

Pemeriksaan teknis Peralatan Listrik meliputi : Technical inspection of Electrical Equipment covers:

a. Penelaahan Dokumen a. Study of Documents


Standar yang digunakan Standards to be used
− Spesifikasi unit peralatan listrik/data sheet − Specification of electrical equipment unit
(generator, transformer, switchgear dan /data sheet (Generator, Transformer,
motor control center); Switchgear and Motor Control Center);
− Gambar perencanaan; − Drawing of planning;

Page 18 of 19
− Spesifikasi perencanaan dan konstruksi; − Specification of planning & construction;
− Spesifikasi material; − Specification of materials;
− Perhitungan perencanaan (bila disyaratkan); − Calculation of planning (if required);
− Prosedur pengoperasian & pemeliharaan; − Operation & maintenance procedures;
− Klasifikasi area; − Classification of area;
− Piranti pengaman; −
− Klas isolasi; − Isolation classes
b. Pemeriksaan fisik meliputi : b. Physical inspection covers:
− Pemeriksaan peralatan dan komponennya − Inspection of equipment and its componen
− Verifikasi plat nama − Verification of name plate
− Pemeriksaan umum kondisi pemasangan di − General inspection of installation conditions
lokasi in the location
− Pemeriksaan lay out peralatan dan area − Inspection of lay out of equipment and
klasifikasi classification area
− Pemeriksaan panel kendali − Inspection of control panel
− Pemeriksaan terminal kabel utama dan − Inspection of main cable terminal and
penetralan neutralization
c. Pengujian meliputi : c. Testing covers:
− Pengujian ketahanan isolasi − Testing of isolation resistance
− Pengujian panel kendali − Testing of control panel
− Pengujian Hi-pot kabel − Testing of Hi-pot cable
− Setting relay pengaman − Setting of safety relay
− Pengujian sinkronisasi − Testing of synchronization
− Pengujian automatic start unit emergency − Testing of automatic start of emergency unit
− Pengujian tanpa beban dan dengan beban − Testing without load and with load
− Penilaian penerimaan (test value) − Evaluation of acceptance (test values)
− Pre-commisioning dan Commissioning − Pre-commissioning and Commissioning
d. Pelaporan d. Reporting
Menyusun seluruh hasil pemeriksaan teknis To prepare all results of technical inspection in
berbentuk dokumen untuk diserahkan ke the form of documents to be submitted to the
Direktur Direktorat Teknik Pertambangan Director of the Directorate of Oil and gas Mining
Minyak dan Gas Bumi sebagai bahan evaluasi Techniques as evaluation materials for the
untuk penerbitan Sertifikat Kelayakan issuance of Equipment Worthiness Certificate.
Penggunaan Peralatan.

Ditetapkan di Jakarta Stipulated in Jakarta


Pada tanggal 19 Agustus 1998 On,August 19 1998
Direktur Jendral Minyak dan Gas Bumi Director General of Oil and gas

Soepraptono Soeleiman Soepraptono Soeleiman

Page 19 of 19

Anda mungkin juga menyukai