CONTOH RAB DETAIL PEMBANGUNAN TPT

NO. URAIAN VOLUME SATUAN HARGA JUMLAH 


SAT.
(Rp) (Rp)
1 2 4 5 6 7
A MATERIAL
Kayu 5/7 x 2 m 12 batang 15,000 180,000
Paku biasa 2"-5" 2 kg 15,000 30,000
Kayu papan 3/20 x 2 cm 10 lembar 72,000 720,000
Batu Belah 15/20 27 m3 210,000 5,670,000
Semen portland 50 zak 65,000 3,250,000
Pasir pasang 6 rit 1,450,000 8,700,000
Pipa PVC 1.5 inc 6 batang 25,000 150,000
Jumlah Sub V 18,700,000
B Tenaga Kerja
Pekerja 20 oh 70,000 1,400,000
Tukang Batu 20 oh 75,000 1,500,000
Kepala Tukang 20 oh 80,000 1,600,000
Mandor 20 oh 90,000 1,800,000
Jumlah Sub V 6,300,000

JUMLAH TOTAL 25,000,000