ERECTION GIRDER METODE

ERECTION
CYCLE
JEMBATAN PATUNUANG TIME &
MENGGUNAKAN LAUNCHER SCHEDHULE

2017
APRIL
PROYEK JEMBATAN PATUNUANG – SULAWESI SELATAN
1.SETTING LAUNCHER DI ATAS ABUTMENT(1 hari 15 jam)
2.ERECTION GIRDER DARI ABT. KE ABT.
1st PHASE  Persiapan Posisi Pekerja & Alat (15”)
2nd PHASE  Dongkrak Girder Pada Kedua Sisi(5”)
3rd PHASE  Setting Trolley Launching Pada Girder(5”)
4th PHASE  Setting Girder Di Atas Trolley Launching(10”)
5th PHASE  Bracing Girder Ke Trolley(5”)
6th PHASE  Launching Girder Dan Setting Girder Ke Hoist 1(50”)
7th PHASE  Launching Girder Ke Posisi ABT. Dan Setting Girder Ke Hoist 2(30”)
8th PHASE  Geser Girder Ke Posisi Bearingpad(20”)
9th PHASE  Turunkan Girder Ke Bearingpad(15”)
9th PHASE  Install Bracing Girder(25”)
10th PHASE  Launcher Kembali Ke Posisi Semula(15”)
11th PHASE  Pekerjan Erection Di Lakukan Dengan Metode Yang Sama Hingga Ter-erection Satu Bentang(3 Girder 1
hari)