JADWAL MOBILISASI ALAT, BAHAN DAN MATERIAL

SATKER : DINAS KESEHATAN KABUPATEN DONGGALA


PEKERJAAN : PEMBANGUNAN RUMAH DINAS DOKTER PUSKESMAS LALUNDU
LOKASI : DESA LALUNDU KECAMATAN RIO PAKAVA KABUPATEN DONGGALA
TAHUN ANGG. : 2018

WAKTU PELAKSANAAN PEKERJAAN 180 ( SERATUS DELAPAN PULUH ) HARI KALENDER


NO. URAIAN PEKERJAAN sat Bulan - I = 28 Hari Bulan - II = 28 Hari Bulan - III = 28 Hari Bulan - IV = 28 Hari Bulan - V = 28 Hari Bulan - VI = 28 Hari 12 Hari
VOLUME KET.
Kalender Kalender Kalender Kalender Kalender Kalender Kalender
7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 7 Hari 5 Hari

1. BAHAN DAN MATERIAL


Batu Pecah Manual 1,000
Tanah dan Pasir 1,000
Batu 1,000
Kayu 1,000
Batu Cetak
Kapur 28,968
Semen 11,587
BESI BETON POLOS 20,850
KAWAT 2,414
BAHAN ALUMINIUM 12,480
PAKU - PAKUAN
BAHAN ATAP 18,767
TALANG 7,242
BAHAN LANTAI / KERAMIK
BAHAN PINTU & LANGIT - LANGIT 3,600

)RENCANA PENYERAHAN PERTAMA (PHO


BAHAN KACA 1,365
BAHAN PIPA & AKSESORIS 0,340
BAHAN PENGGANTUNG 0,840
BAHAN SANITAIR 1,577
BAHAN LISTRIK 0,410
CAT KAYU
CAT TEMBOK 144,780
MINYAK CAT 16,980
BAHAN FINISHING 17,000

2. PERSONIL
- SITE MANAGER 1,000 OH
- AHLI MANAJEMEN 1,000 OH
- MANDOR 1,000 OH
- TUKANG DAN PEKERJA 0,000 OH
- KEPALA TUKANG 0,000 OH

3. PERALATAN DAN PERLENGKAPAN


- Dump Truck 1,000 Unit
- Sepeda Motor 2,000 Unit
- Beton Molen 1,000 Unit
Genset 1,000 Unit
Tangki Air 1,000 Unit

Palu, 20 April 2018


Penyedia,-
CV. WANA MITRA SEJATI

HAYS YUSUF
Direktur