REPUBLIK INDONESIA

KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT


DIREKTORAT JENDERAL BINA MARGA
SATUAN KERJA PERENCANAAN DAN PENGAWASAN JALAN NASIONAL (P2JN)
PROVINSI PAPUA BARAT

LAPORAN BULANAN
( )

Data Konsultan Tanggal Kontrak :


: Tahun Anggaran :
LEMBAR PENGESAHAN
LAPORAN BULANAN ..... (.........2021)
PEMBANGUNAN JEMBATAN .........................................

PAKET : PENGAWASAN TEKNIS JALAN DAN JEMBATAN ...............................

TANDA
URAIAN NAMA DAN JABATAN TANGGAL
TANGAN

Disusun Oleh: .............................


Sipervision Engineer

Asisten Pengawasan P2JN


Provinsi Papua Barat
Diperiksa Oleh:
Ryo Dua Lembang, ST
Nip. 19880521 201802 1 001

PPK Pengawasan P2JN


Provinsi Papua Barat
Disahkan Oleh:
Bina Aleida Saroy, ST
Nip. 19850927 201505 2 001
KOP PERUSAHAAN

Manokwari,............................

Nomor : .............................................
Lampiran : -

Kepada Yth,
Pejabat Pembuat Komitmen
Pengawasan Satker P2JN Provinsi Papua Barat
Jln............................................
Di, -
.............

Perihal : LAPORAN BULANAN 03


( Maret 2021)

Dengan Hormat,

Berdasarkan Surat Perjanjian Kontrak Konsultan Supervisi No Kontrak :


..............................., pada Tanggal .................., Paket Pengawasan Teknis Jalan dan Jembatan
di ................... Provinsi ................, bersama ini kami sampaikan Laporan Bulanan 03 (Maret
2021) Paket Pembangunan Jembatan .........................

Demikian kami sampaikan, atas perhatian dan diterimanya laporan ini diucapkan terima kasih.

Hormat Kami
Konsultan Supervisi

...................................
Supervision Engineer

Tembusan :
1. Kepala Balai Pelaksana Jalan Nasional ......................
2. Kepala Satuan Kerja PJN Wilayah.........Provinsi Papua Barat
3. Kasatker P2JN Provinsi Papua Barat
4. Pejabat Pembuat Komitmen ....... Provinsi Papua Barat
5. Arsip.
RINGKASAN KEMAJUAN PEKERJAAN (EXECUTIVE SUMMARY)

PENGAWASAN TEKNIS JALAN DAN JEMBATAN D…............TAHUN 2021

PEKERJAAN : PEMBANGUNAn ......................................... ...............................


Bulan :

DATA PROYEK REKAPITULASI PROGRES PEKERJAAN PEMBAYARAN U. MUKA / SERTF BULANAN: STATUS PEKERJAAN
SERTIFIKAT BULAN KUMULATIF
NAMA PAKET : PEMBANGUNAN JEMBATAN WAI HANOLI CS T Waktu Pelaksaaan (Hari) = 390 Pekerjaan Mobilisasi
NOMOR KONTRAK : HK.102-Bb16/498675.2.3/01/2020 I Waktu Pemeliharaan (Hari) = 730 UANG MUKA Februari Rp. 8.217.695.400 Pekerjaan Tanah dan Geosintetik
TANGGAL KONTRAK : 13 FEBRUARI 2020 M Waktu Terpakai (Hari) = 285 MC 01 Februari Rp. 212.905.000 Pekerjaan Struktur
NOMOR AMANDEMAN 01 : ADD.01/HK0102-Bb16/498675.2.3/01/2020 E Sisa Waktu (Hari) = 105 MC 02 Maret Rp. 843.147.000
TANGGAL AMANDEMAN 01 : 23 MARET 2020 Waktu Terpakai ( % ) = 73,077 MC 03 April Rp. 8.605.240.000 PROBLEM
NOMOR AMANDEMAN 02 : ADD.02/HK0102-Bb16/498675.2.3/01/2020 B Schedule (%) = 73,380 MC 04 Mei Rp. 1.456.633.000
TANGGAL AMANDEMAN 02 : 23 APRIL 2020 O ( Kontrak CCO-01 ) MC 05 Juni Rp. 6.891.692.000 - Sulitnya melakukan/menyuplay bahan-bahan fabrikasi sebagai
NOMOR AMANDEMAN 03 : ADD.03/HK0102-Bb16/498675.2.3/01/2020 B Progres Aktual (%) = 85,780 MC 06 Juli Rp. 6.552.294.000 akibat dari merebaknya pandemi global Corona Virus Desease
MC 07 Agustus Rp. 1.738.390.000 2019 (Covid-19)
TANGGAL AMANDEMAN 03 : 05 Oktober 2020 O
TARGET : 15 Meter, 60 Meter, 11 Meter, 13 Meter, 11 Meter T Deviasi (%) = 12,400 MC 08 September Rp. 2.893.569.000 - Terkait status paket Pekerjaan Pembangunan Jembatan Wai
PEMIMPIN KEGIATAN : YOHANIS B. MELSSASAIL, ST MC 09 Oktober Rp. 1.425.082.000 Hanoli Cs yang mana sebelumnya merupakan SYC dan di alihkan
menjadi MYC maka alokasi anggaran di tahun 2020 ini hanya
KONTRAKTOR : PT. RAJABATU KIERAHA PERKASA MC 10 November Rp. 6.366.537.000
sebesar Rp. 34.653.000.000 dan sisanya sebesar Rp.
KONSULTAN SUPERVISI : PT. ROSARI KONSULTAN 6.434.477.000 akan di anggarkan pada tahun 2021 mendatang.
NOMOR / TANGGAL KONTRAK : HK.02.01-Bb.16/485474.02/2020 30 Januari 2020
SITE ENGINEER : ASRUKI,ST TOTAL PEMBAYARAN MC Rp. 36.985.489.000 - Stok material batu kali untuk pekerjaan Bronjong dan Pasangan
GENERAL SUPERINTENDENT : RUDY SETIAWAN, ST TOTAL (Termasuk Uang Muk Rp. 45.203.184.400 Batu semakin menipis
TANGGAL MULAI PELAKSANAAN : 13 FEBRUARI 2020
TANGGAL SELESAI (PHO) : 12 DESEMBER 2020 TINDAKAN YANG DIAMBIL
JANGKA WAKTU PELAKSANAAN : 300 Hari Kalender
Menginstruksikan kepada pihak Kontraktor Pelaksana agar
JANGKA WAKTU PEMELIHARAAN : 730 Hari Kelender - segera mengurus surat di Satuan Tugas Covid-19 Provinsi
NOMOR SPMK : 01/SMPK/Bb.16/498675.2.3/2020 Maluku agar kiranya dapat mempermudah proses pengangkutan
TANGGAL SPMK : 17 FEBRUARI 2020 bahan fabrikasi menuju lokasi pekerjaan.
NILAI KONTRAK AWAL : Rp 41.088.477.000,00 - Progres pekerjaan yang di lakukan akan menyusuaikan dengan
NILAI ADDENDUM KONTRAK : Rp alokasi anggaran yang di anggarkan pada tahun berjalan
- Pihak Kontraktor Pelaksana akan mencari lokasi quayi lain
PROGRES FISIK PEKERJAAN SESUAI KATEGORI DIVISI : sehingga kebutuhan material batu akan terpenuhi.
s/d s/d
BULAN
BOBOT BULAN BULAN
DIV URAIAN INI
LALU INI MONITORING FISIK (%) MONITORING FISIK (%)
TAHUN 2020 (%) (%) 2021
(%) (%) BULAN BULAN NOVEMBER 2020
BULAN FEB MARET APRIL MEI JUNI JULI AGUST SEPT OKT NOV DES JAN FEB MART MINGGU 1 2 3 4
KOMULATIF BULAN 1 2 3 4 5 6 7 8 9 10 11 12 13 14 KOMULATIF MINGGU 37 38 39 40
1 UMUM DRAINASE 8,357 6,67 0,30 6,97
PROG. S CHEDULE (%) 0,26 2,25 6,11 10,68 22,57 38,51 60,37 76,05 93,09 99,69 100,00 PROG. SCHEDULE (%) 66,992 69,032 71,229 73,380
2 PERKERASAN TANAH 0,000 0,00 0,00 0,00
PROG. S CHEDULE (%) CCO 01 6,10 19,45 31,87 45,50 60,57 65,35 86,40 97,33 100,00 PRGRES ACTUAL (%) 71,42 74,79 79,90 85,78
3 PERKERASA BERBUTIR DAN PERKERASAN BETON SEMEN 4,985 3,52 2,97 6,49
PROG. SCHEDULE (%) CCO 02 65,06 73,38 80,96 92,29 97,56 100,00 DEVIASI (%) 4,43 5,76 8,67 12,40
5 PERKERASAN ASPAL 6,408 0,00 1,32 1,32
PRGRES ACTUAL (%) 0,52 2,68 22,35 27,09 43,86 59,78 64,01 66,82 70,29 85,78
6 STRUKTUR 7,267 0,00 0,00 0,00
DEVIASI (%) 0,26 0,43 16,25 7,65 11,99 14,28 3,44 1,47 5,23 12,40
7 PEKERJAAN HARIAN DAN PEKERJAAN LAIN - LAIN 70,793 60,10 10,80 70,90 MONITORING KEUANGAN (%)
9
RENCANA 0,52 2,64 23,51 27,06 43,83 59,78 64,01 66,82 70,29 85,78 2,190 0,00 0,11 0,00
REALISASI 0,52 2,12 21,39 24,93 41,71 57,65 61,89 64,70 68,17 83,66

TOTAL 100 70,29 15,50 85,79

21
Daftar isi

halaman

Sampul Laporan
Lembar Pengesahan
Surat Pengantar
Executive Summery
Daftar Isi

BAB. I PENDAHULUAN

1.1. Latar Belakang……………………………………………………………..……..

1.2. Maksud dan Tujuan…………………………………………………………..…...

1.3. Sasaran……………………………………………………………………….…....

1.4. Lingkup Kegiatan………………………………………………………….……...

1.5. Metode Pelaksanaan Pekerjaan.......................………………………….….…….

1.6. Manajemen Mutu……………………………………………….…....................

BAB. II. INFORMASI PENGGUNA JASA DAN PENYEDIA JASA

2.1. Struktur Organisasi Kerja P2JN Provinsi Papua Barat.....…………………......

2.2. Struktur Organisasi PPK 2.3....................……...…………………………….....

2.3. Data Organisasi Konsultan Supervisi…............…...…………………………….

2.3.1. Data Kontrak Konsultan Supervisi.............................................................

2.4. Data Kontraktor Pelaksana........................……...…………………....………….

2.4.1. Data Kontrak Fisik......................................................................................


BAB. III. LAPORAN PELAKSANAAN FISIK

3.1. Data Umum............................................................……………………………

3.1.1. Jembatan ............. ...................................................................

3.1.2. Jembatan .............. ......................................................................

3.2. Peta Lokasi Kegiatan Pekerjaan dan Lokasi Quary...…………………….........

3.3. Sketsa Map Lokasi Pekerjaan.………………………...….………………….....

3.4. Strip Map Pekerjaan..................…………………………..…………….....…...

3.5. Typical Penampang Konstruksi...............………………………………….......

3.6. Narasi Kegiatan Kontraktor, Permasalahan dan Solusi..………………….……

3.7. Jadwal Pelaksanaan Pekerjaan (Curva “s”)...................………………….……

3.8. Data Kemajuan Fisik.....................................................………………….….…

3.9. Sertifikast Bulanan (MC)..............................................…………………..……

3.10. Rangkuman Pembayaran MC........................................………………….……

3.11. Daftar Personil Kontraktor ........................................................…………..…..

3.12. Struktur Organisasi Kontraktor ..................................................……….……

3.13. Daftar Peralatan Kontraktor ...........................................................................

3.14. Status Revisi Design dan Contract Change Order (CCO)..................................

3.15. Ringkasan Pengendalian Mutu......................................………………….….…


BAB. IV. KEGIATAN KONSULTAN SUPERVISI

4.1. Daftar Personil Konsultan Supervisi………………………....……..….……….

4.2 . Rencana dan Realisasi Penugasan Konsultan Supervisi......…………...……….

4.3. Struktur Organisasi Konsultan...........……………………………….………….

4.4. Realisasi Kegiatan Pengawasan..................……………………….……………

4.5. Uraian Kegiatan di Laboratorium...............………………………….…………

4.6. Uraian Kegiatan Lapangan.........................…………………………….………

4.7. Uraian Kegiatan Kantor.........................……………….....…………….………

BAB. V. P E N U T U P

5.1. Kesimpulan.....................................………………………....……..….……….

5.2. Saran ..................................................................................…………...……….

5.3. Rekomendasi......................................................................…………...……….

LAMPIRAN – LAMPIRAN

- Laporan Bulanan K3L

- Pelaksanaan Padat Karya (Jika ada )

- Surat Menyurat

- Data Curah Hujan

- Foto-Foto / Dokumentasi
DAFTAR GAMBAR

Halaman

Gambar 01 (..........................................) ..................................... 01

Gambar 02 (..........................................) .....................................

Gambar 03 (..........................................) ......................................

Gambar 04 (.........................................) .....................................

Gambar 05 (.........................................) .....................................

Gambar 06 (.........................................) .....................................

Gambar 07 (.........................................) .....................................


Gambar 08 (.........................................) .....................................
Gambar 09 (.........................................) .....................................
Gambar 10 (.........................................) ....................................
Dst..............

DAFTAR TABEL

Tabel 01 (..........................................) ..................................... 01

Tabel 02 (..........................................) .....................................

Tabel 03 (..........................................) ......................................

Tabel 04 (.........................................) .....................................

Tabel 05 (.........................................) .....................................

Tabel 06 (.........................................) .....................................

Tabel 07 (.........................................) .....................................


Tabel 08 (.........................................) .....................................
Tabel 09 (........................................) ......................................
Tabel 10 (.........................................) .....................................
Dst..............
BAB. I. PENDAHULUAN
LAPORAN BULANAN 01 (................) 2021
Pengawasan Teknis Jalan & Jembatan di ..............................

1.1. Latar Belakang

Program Pembinaan Pembangunan dan Peningkatan Jalan dan Jembatan


merupakan salah satu upaya pemerintah dalam mendukung pencapaian
sasaran pembangunan nasional secara umum dan Provinsi Papua Barat
khususnya. Pengawasan pelaksanaan kontruksi jalan di Provinsi Papau Barat
dilaksanakan oleh Balai Pelaksana Jalan Nasional (BPJN) Papua Barat yang
memiliki wewenang dan tanggung jawab dalam pembinaan sasaran
transportasi Jalan Nasional maupun Konstruksi Jembatannya. Pembinaan
jaringan Jalan dan Jembatan sangat terkait dengan pemerataan pembangunan
beserta hasilnya melalui pengembangan prasarana Jalan dan Jembatan yang
bertujuan untuk meningkatkan kondisi jalan dan jembatan sesuai dengan
tuntutan laju pertumbuhan lalu lintas yang diakibatkan oleh perkembangan
dan pertumbuhan ekonomi di Provinsi Maluku umumnya.
Jalan juga merupakan salah satu prasarana yang cukup vital sebagai
pendukung bagi pertumbuhan dan pembangunan ekonomi secara menyeluruh,
terutama untuk mendukung Mobilitas arus lalu–lintas barang dan jasa yang
melintas pada jalan.

Ketersediaan prasarana transportasi jalan juga menjadi salah satu aspek


yang diperlukan untuk menunjang roda perekonomian dan sarana dalam
menyebarkan gerak laju pembangunan disegala bidang secara merata
keseluruh wilayah. Dalam beberapa hal, tingkat kemajuan pembangunan dapat
diukur dari keberadaan jalan maupun Jembatannya, baik dari segi kualitas
maupun kuantitasnya.

PT. ................................. 1
Dengan peranan dan fungsinya yang juga cukup besar, maka keberadaan
segmen Jalan harus ditangani dan diperlukan dengan perencanaan dan
pengawasan yang matang. Baik yang sifatnya pembangunan jalan ataupun
rehabilitasi struktur terhadap konstruksi jalan yang kuat dan berkualitas
merupakan syarat mutlak untuk kelancaran arus mobilitas penumpang atau
barang terutama pada daerah yang strategis seperti kawasan sentra
produktif baik dari sektor pertanian, perkebunan, maupun dari pariwisata yang
akan berkembang kedepannya.

Berkaitan dengan hal tersebut maka Balai Pelaksa Jalan Nasional (BPJN)
Papua Barat, bermaksud untuk menangani pekerjaan di Provinsi Papua Barat
khususnya paket Pembangunan ............................ pada ruas jalan
…...........................

Untuk menjamin pelaksanaan pekerjaan tersebut sesuai dengan rencana mutu,


biaya dan waktu yang telah ditetapkan di dalam Kontrak Jasa Konstruksi,
diperlukan adanya Tim Pengawas yang akan berperan membantu Pejabat
Pembuat Komitmen (PPK) Fisik dalam hal mengawal Kontrak dan pelaksanaan
kegiatan di lapangan.

Salah satu Perusahaan Jasa Konsultansi Pengawasan yaitu


PT.................. yang akan menangani Pengawasan Teknis Pembangunan Jalan
dan Jembatan .................. khususnya paket Pembangunan Jembatan
................. yang diantaranya :

- Pembangunan Jembatan ............................

- Pembangunan Jembatan.............................

- Pembangunan Jembatan .............................

- Pembangunan Jembatan ..............................


1.2. Maksud dan Tujuan
Pekerjaan-pekerjaan yang akan dilaksanakan merupakan upaya mewujudkan
pelayanan yang sebaik-baiknya kepada masyarakat pengguna jalan.
Pembangunan jembatan tersebut di atas, merupakan salah satu upaya
Direktorat Jenderal Bina Marga dalam menunjang kelancaran arus lalu lintas
pada ruas jalan yang bersangkutan.
Pekerjaan dimaksud, berlokasi di ...................... pada Ruas Jalan
.................. yang menghubungkan daerah-daerah yang cukup potensial,
sehingga diharapkan setelah selesainya pembangunan jembatan tersebut,
secara tidak langsung dapat mempercepat peningkatan kemajuan pada semua
sektor kehidupan masyarakat dalam kota yang bersangkutan, sejalan dengan
kemajuan / perkembangan ekonomi dan bidang lainnya di Provinsi Papua Barat
Memenuhi hal tersebut di atas, Satuan Kerja Perencanaan dan Pengawasan
Jalan Nasional Provinsi Papua Barat akan mengupayakan untuk menyediakan
Jasa Konsultan dengan peran sebagai Konsultan Pengawasan Teknis pada
kegiatan dimaksud.

1.3. Sasaran
Sasaran dari Kegiatan Pengawasan adalah :
1. Tersusunnya Laporan Pelaksanaan Pengawasan Teknik Jalan dan
Jembatan ........................................................
2. Diharapkan hasil produk pengawasan teknik jalan dan jembatan yang
berwawasan lingkungan dan berkeselamatan.
3. Terbangunnya hasil pengawasan fisik yang Tepat Mutu, Tepat Waktu,
Tepat Biaya dan tertib Administrasi
1.4. Lingkup Pekerjaan
Sesuai dengan KAK (Kerangka Acuan Kerja) konsultan, lingkup pengawasan
Supervisi konstruksi adalah Pembangunan Jembatan ...............yang
mencakup :

- Pembangunan Jembatan ........................

- Pembangunan Jembatan ........................

1.5. Metode Pelaksanaan Pekerjaan

 Pekerjaan Persiapan
Pekerjaan persiapan dimulai segera setelah pihak kontraktor dan konsultan
menerima Surat Perintah Mulai Kerja dari Satuan Kerja Provinsi
Papua Barat Tahapan pekerjaan pengawasan ini merupakan kegiatan awal
yang sangat penting untuk dapat melaksanakan tahap pelaksanaan
konstruksi dengan baik. Secara umum pekerjaan persiapan akan
mencakup kegiatan evaluasi data perencanaan terhadap kondisi lapangan
yang ada,proses mobilisasi kontraktor dan koordinasi awal. Dalam
kegiatan pekerjaan persiapan, konsultan akan melakukan detil aktivitas
sebagai berikut :
o Koordinasi Awal
Dalam melaksanakan pekerjaan konstruksi diperlukan koordinasi
antara pihak-pihak Kepala Satuan Kerja, Konsultan dan Kontraktor.
Koordinasi kerja diperlukan untuk memperlancar pelaksanaan
pekerjaan serta pencapaian hasil pekerjaan sebaik-baiknya. Untuk itu
diperlukan kejelasan mengenai tugas, wewenang dan tanggung jawab
masing-masing pihak. Dalam hal ini, Konsultan Supervisi bertugas
membantu Kepala Satuan Kerja dalam pengawasan teknis,
memberikan nasehat dan saran penyelesaian permasalahan serta
pengadministrasian kegiatan proyek.
Selanjutnya koordinasi yang erat selama periode pelaksanaan
konstruksi dilakukan dengan mengadakan pertemuan berkala secara
teratur.
o Evaluasi Dokumen Kontrak
Konsultan akan melakukan pengecekan secara detail terhadap seluruh
kelengkapan data yang akan dipergunakan sebagai acuan
pelaksanaan konstruksi, anatara lain :
- Persyaratan Kontrak
- Spesifikasi Teknik
- Gambar Rencana
o Mobilisasi Kontraktor
Pelaksanaan konstruksi akan terselenggara dengan baik apabila
didukung dengan personil, peralatan dan perlengkapan teknis lainnya
secara lengkap dengan kondisi baik serta tepat waktu dalam
pengadaannya.
Untuk itu Konsultan akan memeriksa dan memberikan saran-saran
yang mencakup proses mobilisasi sebagai berikut :
- Rencana Layout base camp
- Mobilisasi personil dan peralatan Kontraktor
- Pemasangan Batching Plant dan perlengkapan laboratorium
(jika diperlukan).
Selain dari pada itu, Konsultan akan mengevaluasi secara detail
terhadap Rencana Kerja Kontraktor seperti berikut :
- Jadwal pelaksanaan pekerjaan
- Rencana Anggaran Biaya
- Metode pelaksanaan
- Metode pengujian mutu bahan dan pekerjaan terlaksana
- Prosedur pengujian dan persetujuan melaksanakan pekerjaan
- Sistim pelaporan
- Rapat kordinasi
Konsultan akan memeriksa, memberikan koreksi perbaikan dan
meberikan masukan agar diperoleh efisiensi dan biaya pelaksanaan
konstruksi dengan pertimbangan yang dapat diterima secara teknis.
o Persiapan Konsultan Supervisi
Konsultan akan menyiapkan format standar untuk dipergunakan dalam
pelaksanaan pengawasan konstruksi, berupa format :
- Laporan Harian dan mingguan inspector
- Laporan Pengujian mutu bahan dan pekerjaan terlaksana
- Pengukuran topografi
- Pengukuran dan perhitungan kwantitas pekerjaan
- Permohonan dan persetujuan pelaksanaan pekerjaan
- Pemakaian peralatan / kendaraan
- Korespondensi Proyek

 Pekerjaan Detail Teknis


Konsultan akan melakukan pengawasan dan monitor secara rutin setiap
hari terhadap seluruh kegiatan Kontraktor yang berkaitan dengan
pelaksanaan pekerjaan konstruksi.
Secara garis besarnya kegiatan pengawasan detil teknik ini akan
mencakup aspek-aspek sebagai berikut :
1. Pengendalian Mutu
Kendali mutu merupakan salah satu aspek penting dalam pengawasan
teknik ini, konsultan akan menggunakan metode, langka pengawasan
serta sistim pelaporan yang teliti sehingga dapat menjamin setiap
pekerjaan konstruksi termasuk pelaksanaan pekerjaan sesuai dengan
Spesifikasi. Pekerjaan pengendalian mutu akan meliputi kegiatan –
kegiatan sebagai berikut :
a) Penentuan titik referensi pengukuran
Sebelum pelaksanan pekerjaan konstruksi dimulai, konsultan
bersama dengan kontraktor akan memeriksa semua patok Bench
Mark (BM) sebagai titik control vertical dari horizontal. Untuk
kemudahan pelaksanaan kontruksi dapat dibuat patok bench mark
tambahan. Konsultan juga akan memeriksa ketepatan seluruh stake
out yang dibuat Kontraktor. Setiap Penyimpanan akan dicatat dan
diselesaikan bersama-sama dengan Kontraktor, seluruh data survey
ini akan dirangkum dalam bentuk Buku Lapangan.
b) Pengujian bahan dan pekerjaan terlaksana.
Pekerjaan pengujian mutu dilakukan oleh Kontraktor dengan
menggunakan peralatan test dilapangan maupun laboratorium yang
disediakan kontraktor serta mengikuti standar prosedur pengujian
seperti yang tercantum di dalam Dokumen Kontrak.
Pengujian mutu dilakukan secara rutin dengan mengambil contoh
secara acak pada lokasi- lokasi yang ditentukan Konsultan, secara
garis besarnya pekerjaan pengujian akan mencakup :
- Pengujian material konstruksi
Pengujian ini antara lain berupa tes penentuan kehancuran
agregat, test ekstraksi aspal, test Portland cement secara
khusus perlu diperhatikan terhadap bahan agregat yang
berasal dari lokasi pengembilan batu serta bahan konstruksi
dari borrow pit dan test slump pada campuran beton.
- Pengujian hasil pekerjaan terlaksana
Pengujian ini antara lain test kepadatan, analisa butiran,
perkerasan, stabilitas, penetrasi aspal dan kuat tekan beton.
- Pengujian campuran bahan
Pengujian ini antara lain berupa test terhadap bahan
campuran
Untuk perkerasan jalan, bahan agregat dan beton.
Konsultan akan mengawasi, memeriksa dan mengevaluasi
setiap pekerjaan pengujian laboratorium dan pengetesan di
lapangan terhadap material konstruksi yang akan
dipergunakan maupun pekerjaan terlaksana, berdasarkan
hasil pengujian tersebut, Konsultan akan membuat
rekomendasi berupa persetujuan atau penolakan berikut
alasan teknis sesuai dengan persyaratan teknis dalam
spesifikasi.
c). Pengawasan detil dan inspeksi
Pekerjaan ini merupakan dasar untuk menjamin mutu pekerjaan
terlaksana sesuai dengan spesifikasi, selain melakukan pengawasan
dan monitor pelaksanaan konstruksi, konsultan akan melakukan
setiap usaha membantu kontraktor dalam menyelesaikan
permaslahan yang ada, menghindari kesalahan konstruksi
mengoptimasikan biaya dan waktu pelaksanaan.
Untuk memulai suatu pekerjaan tertentu, kontraktor harus mengajukan
surat permintaan memulai pekerjaan (request) kepada konsultan.
Dalam pengajuan tersebut harus dilengkapi dengan penjelasan detil
mengenai jenis pekerjaan, lokasi pekerjaan, gambar kerja, perkiraan
volume, rencana jadwal kerja, metode pelaksanaan dan kelengkapan
pengujian bahan yang kan dipergunakan, konsultan akan membuat
koreksi-koreksi dan meminta tambahan kelengkapan lainnya yang
diperlukan. Apabila seluruh persyaratan telah dipenuhi, maka konsultan
akan menyatakan persetujuan untuk memulai atau melanjutkan
pekerjaan tersebut.
Konsultan kan melakukan pengawasan secara rutin dan detil terhadap
metode pelaksanaan, jumlah biuruh, kondisi peralatan dan construction
plant, tingkat dan mutu produksi, penggunaan material yang lolos uji,
pekerjaan pengujian mutu serta keselamatan kerja. Konsultan akan
menginformasikan dan memberikan saran pemecahan permasalahan
atas kekurangan kekurangan, kerusakan-kerusakan serta perbaikan-
perbaikan yang harus segera diambil, selain melakukan pengawasan
seperti di atas, konsultan akan memonitor secara rutin terhadadap
tingkat produksi dan kemajuan pekerjaan untuk disesuaikan dengan
rencana kerja.
Konsultan akan membuat laporan kegiatan harian yang mencakup
seluruh aspek kegiatan pelaksanaan pekerjaan antara lain : lokasi kerja,
kondisi cuaca, jumlah tenaga, jenis dan jumlah peralatan, perkiraan hasil
pekerjaan serta kondisi-kondisi khusus yang terjadi berkaitan dengan
pelaksanaan pekerjaan. Rangkuman dari seluruh hasil pengawasan dan
monitor akan dituangkan dalam bentuk Laporan Kemajuan Bulanan. Hal-
hal khusus yang diperlukan untuk penyelesaian akan dilaporkan secara
tertulis atau dengan mengadakan pertemuan yang membahas perincian
permasalahan yang ada dan usulan pemecahannya.
Pada setiap bagian pekerjaan yang telah selesai, konsultan akan
melakukan inspeksi akhir dan apabila pekerjaan telah dilaksanakan
sesuai dengan sfesifikasi dan ketentuan lain dalam dokumen kontrak,
konsultan segera membuat rekomendasi secara resmi kepada Kepala
Satuan Kerja untuk penerimaan pekerjaan. Pekerjaan yang tidak dapat
diterima yang disebabkan oleh hasil kerja yang buruk dan tidak sesuai
dengan spesifikasi akan dilaporkan kepada Kepala Satuan Kerja
selanjutnya ditolak dengan secara tertulis berikut catatan dan alasan
penolakannya.

1. Kendali Biaya Konstruksi


Konsultan akan melakukan setiap usaha pengendalian biaya yang
berhubungan dengan proyek dari permulaan hingga akhir tahap
konstruksi, system pengolahan data pengontrolan biaya proyek akan
dilakukan secara cepat dan teliti agar dapat dicapai optimasi biaya
sesuai dengan prosedur administrasi tanpa mengakibatkan
keterlambatan terhadap kemajuan pekerjaan.
Konsultan akan memeriksa surat penagihan pembayaran dari kontraktor,
jumlah pembayaran akan diteliti dan dihitung terhadap pekerjaan
terlaksana yang telah selesai dan diterima secara kwantitatif maupun
kwalitatif yaitu berdasarkan hasil pengukuran dan perhitungan kwantitas
serta hasil pengujian mutu yang telah diperiksa dan disetujui, sertifikat ini
ditanda tangani oleh konsultan dan kontraktor dan diteruskan kepada
Kepala Satuan Kerja untuk pemeriksaan terakhir serta persetujuan
pembayaran.
Konsultan akan menyimpan setiap data pembayaran proyek secara
berurutan dan menjumlahkan secara akumulasi sampai dengan data
pembayaran bulanan terakhir. Disamping itu konsultan akan membuat
evaluasi secara berkala terhadap pekerjaan sisa yang masih akan
dilaksanakan untuk membuat perkiraan biaya. Perkiraan keseimbangan
biaya pekerjaan sisa secara berkesinambungan akan dilaporkan kepada
Kepala Satuan Kerja P2JN Provinsi Papua Barat. Untuk itu konsultan
akan menyiapkan jadwal pembayaran berdasarkan kemajuan pekerjaan
yang diperkirakan dan akan diperbaiki secara berkala sejalan dengan
kemajuan pekerjaan yang sebenarnya termasuk adanya setiap
perubahan jadwal pekerjaan.

2. Kendali Jadwal Pelaksanaan Pekerjaan


Jadwal pelaksanaan pekerjaan secara menyeluruh telah ditetapkan
pada tahap pekerjaan persiapan,demikian pula jadwal kerja untuk setiap
jenis pekerjaan harus diajukan kontraktor dalam surat permohonan
memulai pekerjaan dan ditetapkan sebelum pelaksanaan suatu jenis
pekerjaan dimulai.
Konsultan akan memonitor dan mengevaluasi jadwal kerja kontraktor
secara berkesinambungan berdasarkan data kemajuan pekerjaan
mingguan, hal ini dilakukan untuk memperoleh data tingkat kemajuan
pekerjaan, mendeteksi kemungkinan terjadi keterlambatan termasuk
factor penyebabnya dan menentukan langkah-langkah perbaikan yang
harus diambil secara lebih awal.
Penyebab keterlambatan antara lain dapat berupa kelemahan organisasi
kerja, metode pelaksanaan, program pengendalian mutu, penyediaan
material, penugasan personil, penggunaan peralatan, Sub Kontraktor
(bila ada) dan lain-lainnya.
Apabila keterlambatan akan mempengaruhi critical path, konsultan
segera mengadakan rapat khusus dengan kontraktor untuk
mendiskusikan seluruh item pekerjaan yang berkaitan dengan masalah
tersebut, menunjukkan secara tepat permasalahannya, memberikan

PT.................................... 10
pengarahan untuk pemecahannya dan menginstruksikan kontraktor
untuk segera mengambil tindakan.
Penyelenggaraan program kendlai waktu juga dilakukan di dalam rapat
koordinasi mingguan, dalam rapat ini dikonfimasikan data-data tingkat
kemajuan pekerjaan mingguan terlaksana, penetuan rencana kerja
mingguan selanjutnya, pelaporan permasalahan dan penentuan
langkah-langkah perbaikan. Dengan koordinasi yang baik akan
dimungkinkan tercapainya kendali waktu pelaksanaan pekerjaan secara
optimum.

3. Pekerjaan Tambah Kurang


Dalam periode pelaksanaan pekerjaan, terdapat kemungkinan timbulnya
perubahan beberapa jenis pekerjaan yang akan tertuang dalam bentuk
Perintah Perubahan Pekerjaan.
Konsultan akan melakukan evaluasi yang diperlukan sehubungan
dengan rencana perubahan pekerjaan, sebagai bahan evaluasi,
konsultan akan menyiapkan data penunjang dan mebuat analisa
terhadap perubahan :
- Rencana Pendahuluan pekerjaan perubahan
- Perkiraan Kwantitas pekerjaan
- Kebutuhan personil dan peralatan
- Perkiraan biaya konstruksi
- Perkiraan waktu pelaksanaan
- Persyaratan umum dan spesifikasi teknik
- Aspek-aspek yang mempengaruhi keseluruhan proyek
Selanjutnya hasil evaluasi konsultan ini akan diserahkan kepada Kepala
Satuan Kerja untuk evaluasi akhir dan pengambilan keputusan. Apabila
rencana perubahan pekerjaan diterima, konsultan akan menyiapkan
Perintah Perubahan Pekerjaan untuk ditandatangani oleh Satuan Kerja
dan Kontraktor. Pekerjaan yang tercakup dalam perintah perubahan
akan dinilai pada harga satuan sesuai Dokumen Kontrak, apabila jenis
pekerjaan tambahan tersebut belum tercantum didalam Dokumen
Kontrak, Konsultan akan membuat analisa harga satuan baru untuk
dipergunakan oleh Kepala Satuan Kerja dalam penentuan harga denga
kontraktor.

 Koordinasi Kerja
Dengan mengadakan koordinasi kerja yang harmonis antara Kepala
Satuan Kerja / PPK, Konsultan dan Kontraktor akan dapat dicapai hasil
yang sebaik-baiknya dalam menyelesaikan pelaksanaan pekerjaan
konstruksi. Koordinasi kerja akan dilakukan dengan mengadakan
pertemuan secara teratur maupun pada waktu-waktu tertentu yang secara
khusus diperlukan antara lain seperti :
a. Rapat Mingguan
- Tim Konsultan
Rapat intern konsultan dilakukan pada akhir dan dihadiri oleh tenaga
ahli dan teknis konsultan supervisi, tim akan membahas segala
aktivitas mingguan kontraktor yang mencakup pekerjaan pengujian,
hasil inspecksi pekerjaan, kemajuan pekerjaan, pengukuran
kwantitas dan permasalahan di lapangan serta menyiapkan agenda
untuk pertemuan mingguan dengan pihak kontraktor.
- Kepala Satuan Kerja /PPK – Konsultan – Kontraktor
Rapat ini dilakukan pada awal pekan untuk merangkum seluruh
kegiatan yang dilaksanakan dalam periode minggu yang lalu dan
menjelaskan rencana kerja mingguan berikutnya termasuk
permasalahan dan solusi yang akan ditempuh.
Konsultan akan menyusun risalah rapat ini sebagai salah satu arsip
proyek.
b. Rapat Bulanan
Rapat bulanan ini dilakukan pada akhir atau awal bulan dan dihadiri
oleh Kepala Satuan Kerja beserta staf, tenaga ahli konsultan dan tim
inti kontraktor, konsultan akan menyampaikan agenda rapat dan
melaporkan hasil pengawasan bulanan terhadap kegiatan
pelaksanaan pekerjaan yang mencakup masalah kemajuan
pekerjaan kendali mutu, pengajuan pembayaran serta penanganan
permasalahan yang ada.
Status kemajuan pekerjaan terakhir disajikan dalam grafik dan
ditetapkan sebagai acuan untuk kemajuan pekerjaan selanjutnya.
Konsultan akan menyiapkan risalah rapat yang merupakan arsip
proyek.

 Penyelesaian Konstruksi
Konsultan akan menyiapkan langkah-langkah yang diperlukan untuk
membantu tahap penyelesaian konstruksi teliti. Sekurang-kurngnya 30 hari
sebelum tanggal penyelesaian pekerjaan, konsultan akan meminta dan
memeriksa rencana demobilasi Kontraktor yang mencakup pekerja,
peralatan konstruksi dan laboratorium, construction plant, gedung dan
kantor, gambar kerja dan gambar terlaksana, pelaporan dan sebagainya.
Konsultan akan melakukan inspeksi pendahuluan dan membuat daftar
koreksi kekurangan yang masih ada. Inspeksi akhir dilaksanakan untuk
menjamin penyelesaian pekerjaan yang lengkap dan memuaskan sesuai
dengan Dokumen Kontrak dan Konsultan akan memberikan rekomendasi
kepada PPK 1.1 Propinsi Papua Barat untuk proses penerimaan proyek.
Konsultan akan membantu PPK 1.1 Provinsi Papua Barat dalam hal
melaksanakan proses Provisional Hand Over yaitu dalam menyiapkan
seluruh data teknis dan administrasi yang diperlukan.
Bagan Alir Metode Pengawasan Pekerjaan (terlampir).
Bagan Alir Metode Pengawasan Pekerjaan

Keterangan :
MULAI
P : Setiap kegiatan harus
Memiliki Petunjuk / P1
Instruksi Kerja MOBILISASI
Q : Setiap kegiatan harus
Memiliki kriteria pene- Q1
rimaannya
YA
P2
REKAYASA
LAPANGAN

TIDAK
Q2

YA

PEMERIKSAAN
RENCANA KERJA

TIDAK
Q3

P3 P4 P5 YA
P6
PENGAWASAN PENGAWASAN PENGAWASAN
LAPANGAN MATERIAL LABORATORIUM

TIDAK
Q4

YA

OPNAME
LAPANGAN

TIDAK
Q5

YA

SERTIFIKASI
AS-BUILT KONTRAKTOR
DRAWINGS

LAPORAN AKHIR

TIDAK
Q6 P1

YA
SELESAI
1.6. Manajemen Mutu
Pekerjaan harus dilaksanakan melalui proses manajemen mutu, memanfaatkan
sumber daya Pengguna Jasa, Pengawasan Pekerjaan, Penyedia Jasa dan
semua pihak yang terkait. Pengguna Jasa menerima definisi – definisi yang
berhubungan dengan Manajemen Mutu :
 Pengendalian Mutu (Quality Control, QC) Proses memeriksa mutu hasil
produk atau jasa pelayanan tertentu dari penyedia jasa untuk menentukan
apakah hasil-hasil tersebut memenuhi standar mutu terkait yangdisyaratkan
di dalam spesifikasi teknik,memperbaiki kesalahan – kesalahan atas mutu
yang diperoleh lebih rendah serta cara-cara mengidentifikasi untuk
menghilangkan sebab-sebab produk atau kinerja jasa pelayanan yang tidak
memenuhi syarat. Proses pemeriksaan dan persetujuan / penolakan mutu
produk atau kinerja jasa pelayanan tertentu ini dilakukan oleh Manager
Kendali Mutu (QCM) yang disiapkan oleh Penyedia Jasa mengontrol dan
menjamin secara internal mutu hasil pelaksanaan pekerjaan konstruksi
oleh wakil Penyedia Jasa (General Superintendent/GS) sesuai yang
dipersyaratkan di dalam spesifikasi teknis ini. Laporan hasil QC dari QCM
disampaikan kepada Penyedia Jasa dengan tembusan kepada Pengawas
Pekerjaan.
 Jaminan Mutu (Quality Assurance, QA): proses mengevaluasi prosedur
standard dan insturksi kerja seluruh produk atau jasa pelayanan, yang
dievaluasi oleh Pengawas Pekerjaan untuk dapat menjamin bahwa mutu
hasil pekerjaan yang dilaksanakan oleh Penyedia Jasa dapat diterima atau
ditolak sebagai dasar persetujuan pembayaran pekerjaan yang memenuhi
syarat kontrak.
Program mutu di dalam manajemen mutu mempunyai dua komponen kunci
yaitu :
 Pengendalian Mutu (QC) tanggung jawab Penyedia Jasa
 Jaminan Mutu (QA) tanggung jawab Pengawas Pekerjaan menurut
Rencana Jaminan Mutu (QA Plant) Pengawas Pekerjaan.
Tiap komponen dari program harus dialamatkan pada bahan, proses,
kecakapan-kerja, produk, dan dokumentasi yang harus dituangkan ke dalam
Program Mutu (PM). PM disusun dan kemudian disajikan oleh Penyedia Jasa
pada saat diadakan rapat persiapan pelaksanaan (PCM) dengan konten yang
terdiri dari :
1. Ruang Lingkup pekerjaan
2. Organisasi Kerja Penyedia Jasa termasuk Uraian Tugas dan Tanggung
Jawab
3. Jadwal Pelaksanaan terinci per item dari pekerjaan
4. Rincian Prosedur Pelaksanaan Pekerjaan
5. Rincian Prosedur Standar Instruksi Kerja dan Daftar Simak
6. Formulir Bukti Kerja
7. Daftar Personil Pelaksana.
Penyedia jasa harus menyediakan akses yang tidak dibatasi terhadap semua
kegiatan dan dokumentasi Pengendalian Mutu yang dihasilakan oleh atau atas
nama Penyedia Jasa dan harus memberikannya kepada Pengawas Pekerjaan
untuk mendapat akses sepenuhnya pada setiap saat.
Pengawas Pekerjaan akan meninjau kinerja Penyedia Jasa atas pekerjaan dan
menentukan diterimanya Pekerjaan berdasarkan hasil Jaminan Mutu
Pengawas Pekerjaan dan bilamana dianggap memadai oleh Pengawas
Pekerjaan, didukung oleh hasil-hasil Pengendalian Mutu Penyedia Jasa.
Pekerjaan yang gagal memenuhi Syarat-syarat Kontrak harus dipandang
sebagai Pekerjaan Tidak dapat diterima. Pengawas Pekerjaan dapat
memandang semua pekerjaan dari pengujian Jaminan Mutu terakhir yang telah
diterima masih dimungkinkan terdapat pekerjaan yang tidak dapat diterima,
penyedia jasa tidak berhak untuk menuntut pembayaran untuk pekerjaan yang
dokumentasi Pengendalian Mutunya masih kurang memadai yang diperiksa
oleh Manager Kendali Mutu Penyedia Jasa sebagaimana disyaratkan dalam
kontrak.
Penyedia jasa harus melaksanakan koordinasi yang baik terhadap semua
kegiatan yang berhubungan dengan Pekerjaan dan akan mengorganisasi
timnya untuk pelaksanaannya sehubungan dengan tujuan melakukan hal-hal
yang terdapat dalam kegiatan pengendalian mutu suatu produk
BAB. II. INFORMASI PENGGUNA JASA
DAN PENYEDIA JASA
2.1. Struktur Organisasi Kerja P2JN Provinsi Papau Barat
Adapun Struktur Organisasi Satuan Kerja Perencanaan dan Pengawasan Jalan
Nasional Provinsi Papua Barat disajikan pada gambar di bawah ini :
2.2. Struktur Organisasi PPK 1.1

PEJABAT PEMBUAT KOMITMEN

...............................................
Nip. ...................................

DIREKSI PENATA KEUANGAN

...................................... ........................................
Nip. .................................. Nip. 1

PENGAWAS DAN QUALITY

AGIL
MULKADAR
SAMUEL LATUMETEN, ST
RICKY NIELSEN KAILOLA
JEFRY TELEHALA, Amd
2.3. Data Konsultan Supervisi
2.3.1. Data Kontrak Konsultan Supervisi
Pada Tabel di bawah ini disajikan data kontrak Paket Pengawasan Teknik
Jalan dan Jembatan ............................................. sebagai berikut :

Data Kontrak Paket di ....................

1 Nama Kegiatan

2 Nama Pengguna Jasa

3 Alamat Pengguna Jasa


4 Nama Penyedia Jasa
5 Alamat Penyedia Jasa
6 Lokasi Kegiatan
7 Nomor Kontrak
8 Tanggal Kontrak
9 Nomor Amandemen 01
10 Tanggal Amandemen 01

11 Nilai Kontrak

12 Sumber Dana
13 Nomor SMPK
14 Tanggal SPMK
15 Masa Pelaksanaan
16 Akhir Masa Kontrak
17 Tanggal Mobilisasi
18 Site Engineer Tim II
19 Alamat Kantor Proyek
20 Paket Pengawasan Fisk
2.4. Data Kontaktor Pelaksana
2.4.1. Data Kontrak Fisik
Data Kontrak Fisik Pembangunan Jembatan .................................

1 Satuan Kerja

2 Pekerjaan
3 Lokasi
4 Sumber Dana
5 Kontraktor

6 Alamat

7 Nomor Kontrak
8 Tanggal Kontrak
9 Nomor Addendum 01
10 Tanggal Addendum 01
11 Nomor Addendum 02
12 Tanggal Addendum 02
13 Nomor Addendum 03
14 Tanggal Addendum 03
15 Nilai Kontrak
16 Sumber Dana
17 Nomor SMPK
18 Tanggal SPMK
19 Masa Pelaksanaan
20 Masa Pemeliharaan
21 PHO
22 FHO

23 Konsultan Supervisi

PT. Rosari Consultan 20


BAB. III. LAPORAN
PELAKSANAAN FISIK
3.1. Data Umum

3.1.1. Jembatan ......................................


Jembatan Wae Salatena merupakan salah satu jembatan yang tergabung
dalam paket paket pekerjaan pembangunan Jembatan ................. yang
merupakan jembatan pertama di paket PPK ..... yang terletak pada ruas jalan
........................................................................................
Eksisting jembatan ini merupakan jembatan kayu sementara dengan konstruksi
bangunan bawah berupa konstruksi pondasi pasangan batu dengan panjang
bentangan 5 meter dan lebar 3,5 meter, rencana konstruksi pembangunan
jembatan ini adalah GTI dengan panjang bentang 15 meter. Kondisi eksisting
jembatan ini dapat di lihat pada gambar berikut :

Kondisi Eksisting
Pembangunan Jembatan Wai
Salatena
STA 05+400
3.1.2. Jembatan ..................
Wai Hanoli merukan salah satu sungai yang berada daerah
Kabupaten .........................yang melintas pada ruas jalan
........................tepatnya terletak pada STA .....................................................
kondisi sungai ini kering pada saat musim kemarau da akan di aliri air yang
cukup deras dari hulu di saat musim hujan, kondisi ini menyebabkan aktifitas
warga yang melintas di jalan ini terganggu sehingga perlu kiranya di bangun
jembatan sesuai kebutuhan di maksud. Rencana pembangunan jembatan ini
adalah berupa Jembatan Rangka Baja bentangan 60 meter. Kondisi eksisting
sungai ini dapat di lihat pada gambar berikut :

Kondisi Eksisting
Pembangunan Jembatan
Wai
STA 20+100 (Taniwel)

3.1.3. Jembatan Wai Kapala


Jembatan Wai Kapala merupakan salah satu jembatan yang terletak di
Kabupaten .......................... tepatnya di ruas jalan ...........................................
pada STA 25+850 (Taniwel).
Kondisi eksisting jembatan ini merupakan jembatan kayu bentangan 10 M
dengan kondisi kayu yang lapuk sehingga membahayakan para mengguna
yang melewati jembatan di maksud. Rencana pembangunan jembatan ini
adalah berupa Box Culvert bentangan 13,1 M. Kondisi awal jembatan ini dapat
di lihat pada gambar berikut :
Kondisi Eksisting
Pembangunan Jembatan
Wai Kapala
STA 25+850

3.1.4. Jembatan .........................


Jembatan Wai Masama merupakan salah satu jembatan yang terletak di
kabupaten .................................... tepatnya di ruas jalan Taniwel – Saleman
pada STA 28+200 (Taniwel).
Kondisi eksisting jembatan ini merupakan jembatan kayu bentangan 10 M
dengan kondisi kayu yang lapuk sehingga membahayakan para mengguna
yang melewati jembatan di maksud. Rencana pembangunan jembatan ini
adalah berupa Box Culvert bentangan 13,1 M. Kondisi awal jembatan ini dapat
di lihat pada gambar berikut :

Kondisi Eksisting
Pembangunan Jembatan
Wai Masama
STA 28+200 (Taniwel)
3.1.5. Jembatan ..........................
Jembatan .......................merupakan salah satu jembatan yang terletak di
Kabupaten....................... tepatnya di ruas jalan . . . . . . . . . . . . . . . . .
Sebelumnya jembatan ini tidak termasuk dalam paket pekerjaan tahun
anggaran ini (2021) namun sesuai hasil CCO yang di lakukan dan telah di
sapakati untuk menambah 1 buah jembatan betupa box culvert, Adapun kondisi
eksisting dan permasalahan-permasalahan yang di temui di lapangan salah
satunya adalah terkait dengan paket pekerjaan Preservasi Jalan Taniwel –
Saleman dengan panjang penanganan 24,00 Km dan sesuai hasil kajian teknis
yang telah dilakukan oleh tim paket pekerjaan Preservasi Jalan tersebut maka
target panjang 24,00 Km tidak terpenuhi dikarenakan terpotong oleh
pelaksanaan paket Pembangunan Jembatan Wai Hanoli Cs dengan panjang
total jembatan + oprit adalah 1,23 Km sehingga panjang paket pekerjaan
Preserfasi Jalan Taniwel – Saleman menjadi berkurang menjadi 22,77 Km.
Sesuai kondisi permasalahan yang ada tersebut di atas, maka diadakan kajian
teknis kembali susuai dengan kondisi yang terjadi di lapangan, maka
berdasarkan hal tersebut PPK 2.3 mengusulkan untuk dilakukannya perubahan
kontrak (Amandemen) dalam rangka untuk mengakomodir kebutuhan dari
panjang penanganan paket pekerjaan Preservasi Jalan Taniwel – Saleman
dengan panjang penanganan 24,00 Km dengan mengusulkan :
a. Mata pembayaran Lapis Resap Pengikat, Lapis Perekat, Laston Lapis
Aus Asbuton, Laston Lapis Antara Asbuton pada Paket Pembangunan
Jembatan Wai Hanoli Cs di hilangkan.
b. Akibat mata pembayaran yang di hilangkan tersebut, maka terjadi selisih
nilai kontrak sehingga untuk mengakomodir selisih tersebut maka
ditambahkan pembangunan 1 (satu) buah jembatan tipe double box
culvert dengan panjang bertang 11,1 M.
Kondisi eksisting jembatan ini merupakan jembatan kayu bentangan 10 M
dengan kondisi kayu yang lapuk sehingga membahayakan para mengguna
yang melewati jembatan di maksud. Rencana pembangunan jembatan ini
adalah berupa Box Culvert bentangan 11,1 M. Kondisi awal jembatan ini dapat
di lihat pada gambar berikut :

Kondisi Eksisting
Pembangunan Jembatan
Wai Yole
STA 28+050 (Taniwel)
3.2. Peta Lokasi Kegiatan Pekerjaan dan Lokasi Quari

Titik Koordinat di Jelaskan Pada Peta Lokasi


LAPORAN BULANAN .............................
Pengawasan Teknis Jalan & Jembatan ....................................

3.3. Sket Map Lokasi Pekerjaan

J
ary Sungai K Qu e
m
aput b
y a
Sta t
03+000 a
n
W
a
i

Y
o
l
e
S
t
a

2
8

0
5
0

Taniwel

Je mbatan Wai Je Jem J


Salatena mb bata e
Sta 05+400 at n m
an Wai b
W Kap a
ai ala t
Ha Sta a
nol 25+ n
i 850
St
a W
20 a
+1 i
00

m
a
s
a
m
Kantor
a Kantor Mess Konsultan I
Mess
Lapangan
Lapangan Konsultan
II
S
t Ko ntrakto r
a
Sta Sta
Sta 20+100
30+3 30+34
2 00 0
8
+
2 30+3
0
0 20

Desa Sukaraja
Kec.Taniwel Timur

Mess
Konsultan
III

Sta 31+250
3.4. Strip Map Pekerjaan

Jembatan ...........................

Jembatan ..................

PT. 29
.........RosaConsultan
Jembatan ....................

Jembatan ...........................

PT. Rosari Consultan 30


3.5. Typical Penampang Konstruksi
Jembatan .........................
Jembatan .........................
Jembatan .............................
3.6. Narasi Kegiatan Kontraktor, Permasalahan dan Solusi
3.7. Jadwal Pelaksanaan Pekerjaan (Curva S)
Satuan Kerja : Pelaksanaan Jalan Nasional Wilayah II Propinsi Maluku
Pelaksana Kegiatan : PPK 2.3 Provinsi Maluku
Nomor Kontrak : HK0102-Bb16/498675.2.3/01/2020
Tanggal Kontrak : 13 Februari 2020 Addendum 03
Nama Paket : Pembangunan Jembatan Wai Hanoli Cs Addendum 02 05 Oktober 2020
Lokasi : Pulau Seram 23 April 2020
TIME SCHEDULLE PEMBANGUNAN JEMBATAN WAI HANOLI CS ( CCO-02 )
CCO-02 TAHUN 2020 (MASA PELAKSANAAN : 17 FEBRUARI - 31 DESEMBER 2020)
NO Uraian Kegiatan Sat. FEBRUARI MARET A MEI J J J AGUSTUS S OKTOBER NOPEMBER DESEMBER K
APRIL P U U U E JANUARI FEBRUARI E
R N L L P MARET T
/ / /
J A O
Perkiraan U G K
L S T

Bobot
Kuantitas (%) M Mgu-11 Mgu-12 Mgu-13 Mgu-14 Mgu-15 Mgu-16 Mgu-17 Mgu-18 Mgu-19 Mgu-20 Mgu-21 Mgu-22 Mgu-23 Mgu-24 Mgu-25 Mgu-26 Mgu-27 Mgu-28 Mgu-29 Mgu-30 Mgu-31 Mgu-32 Mgu-33 Mgu-34 Mgu-35 Mgu-36 Mgu-37 Mgu-38 Mgu-39 Mgu-40 Mgu-41 Mgu-42 Mgu-43
Mgu-1 gu Mgu-44 Mgu-45
Mgu-2 Mgu-3 Mgu-4 - Mgu-47 Mgu-48 Mgu-49 Mgu-50 Mgu-51 Mgu-52 Mgu-53 Mgu-54 Mgu-55 Mgu-56 Mgu-57 Mgu-58 Mgu-59
Mgu-5 Mgu-6 Mgu-7 10
Mgu-8 Mgu-9
a b c d g 17/2-23/2 24/2 - 1/3 2/3 - 8/3 9/3 - 15/3 16/3-22/3 23/3-29/3 30/3 - 5/4 6/4 - 12/4 13/4- 19/4 20/4-23/4 24/4-26/4 27/4 - 3/5 4/5 - 10/5 11/5 - 17/5 18/5 - 24/5 25/5 - 31/5 1/6 - 7/6 8/6 - 14/6 15/6 - 21/6 22/6-28/6 29/6 - 5/7 6/7 - 12/7 13/7-19/7 20/7-26/7 27/7 - 2/8 3/8 - 9/8 10/8-16/8 17/8-23/8 24/8-30/8 31/8 - 6/9 7/9 - 13/9 14/9-20/9 21/9- 27/9 28/9- 04/10 5/10-11/10
12/10-18/10 19/10-25/10 26/10-1/11 2/11-8/11 9/11-15/11 16/11-22/11 23/11-29/11 30/11-6/12 7/12-13/12 14/12-20/12 21/12-27/12 28/12-31/12 01/01-03/01 4/1-10/1 11/1-17/1 18/1-24/1 25/1-31/1 1/2-7/2 8/2-14/2 15/2-21/12 22/2-28/2 29/2-6/3 7/3-12/3 13/3-19/3 20/3-26/3 27/3-31/3

'PERPANJANGAN WAKTU 90 HARI


DIV. 1 UMUM
1.2 Mobilisasi LS 1,00 4,145 0, 259 0, 259
0, 259 0,259 0, 259 0,259 0,259 0, 259 0,259 0,130 0,130 0, 259 0,259 0, 259 0,259
0,17
3
0,17
3
0,17
3
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1,00 0,977 0,019 0, 019 0,019 0, 019 0, 019 0,019 0, 019 0,010 0,010 0,019 0, 019 0,019 0, 019 0,019 0, 019 0,019 0, 019 0,019 0, 019 0,019 0, 019 0,019 0, 019 0,019 0, 019 0,019 0, 019 0,019 0, 019 0,019 0, 019 0,019 0,014
0,014 0, 014 0,014 0, 014 0,014 0, 014 0,014 0,014 0, 014 0,014 0,014 0,014 0, 014 0,014 0, 014 0,014 0, 014 0,014 0, 014 0,014 0, 014 0,014 0, 014 0,014 0, 014 0,014
1.8.(2) Jembatan Sementara LS 1,00 1,560 0,083 0, 083 0, 083 0,083 0, 083 0,042 0,042 0,083 0, 083 0,083 0, 083 0,083 0, 083 0, 083 0,083 0, 083
0,156 0, 156
1.17.(1a) Pengujian pH Buah 36,00 0,048 0,016 0, 016
1.17.(1a) Pengujian pH Buah 9,00 0,005
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 36,00 0,048 0,016 0, 016
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 9,00 0,006
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 36,00 0,048 0,016 0, 016
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 9,00 0,006
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 36,00 0,048 0,016 0, 016
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 9,00 0,006
90

1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 36,00 0,048 0,016 0, 016
0, 016
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 9,00 0,006
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 36,00 0,048 0,016 0, 016
0, 016 K
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 9,00 0,007 u
1.17.(1g) Pengujian Coliform Buah 36,00 0,048 0,016 0, 016 r
0, 016 v
1.17.(1g) Pengujian Coliform Buah 9,00 0,010 a
1.17.(1h) Pegujian E. Coli Buah 36,00 0,048 0,016 0, 016
0, 016
1.17.(1h) Pegujian E. Coli Buah 9,00 0,008 R
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 45,00 0,060 0,016 e
0,016 0, 028 80 n
1.17.(1j) Pengujian Temperatur (Suhu) Buah 36,00 0,048 0,016 0, 016 c
0,016 a
1.17.(1j) Pengujian Temperatur (Suhu) Buah 9,00 0,005 n
1.17.(1k) Pengujian Parameter Kualitas Air Lainnya Buah 36,00 0,048 0,016 0, 016 a
0, 016 R
1.17.(1k) Pengujian Parameter Kualitas Air Lainnya Buah 9,00 0,005 e
s
c
h
e
d
u
l
e

(
C
C
O
-
0
2
)
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan dan Kesehatan Buah 45,00 0,060 0,016 0, 028
1.17.(2c) Pengujian Tingkat Getaran Kendaraan Bermotor Buah 45,00 0,060 0,016 0, 028

1.17.(3a) Pengujian NoX Buah 36,00 0,048 0,016 0, 016


1.17.(3a) Pengujian NoX Buah 9,00 0,010
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 45,00 0,060 0,016 0, 016
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 45,00 0,060 0,016 0, 016
70

1.17.(3h) Pengujian Parameter Udara Emisi dan Ambien lainnya Buah 45,00 0,060 0,016 0, 016
1,19 Keselamatan dan Kesehatan Kerja LS 1,00 0,799 0,016 0, 016 0,016 0, 016 0, 016 0,016 0, 016 0,008 0,008 0,016 0, 016 0,016 0, 016 0,016 0, 016 0,016 0, 016 0,016 0, 016 0,016 0, 016 0,016 0, 016 0,016 0, 016 0,016 0, 016 0,016 0, 016 0,016 0,016 0,016 0,012
0, 012 0,012 0, 012 0,012 0, 012 0,012 0, 012 0,012 0,012 0, 012 0,012 0, 012 0,012 0, 012 0,012 0, 012 0,012 0, 012 0,012 0, 012 0,012 0, 012 0,012 0, 012 0,012 0, 012
1,21 Manajemen Mutu LS 1,00 0,904 0,018 0, 018 0,018 0, 018 0, 018 0,018 0, 018 0,009 0,009 0,018 0, 018 0,018 0, 018 0,018 0, 018 0,018 0, 018 0,018 0, 018 0,018 0, 018 0,018 0, 018 0,018 0, 018 0,018 0, 018 0,018 0, 018 0,018 0,018 0,018 0,013
0, 013 0,013 0, 013 0,013 0, 013 0,013 0, 013 0,013 0,013 0, 013 0,013 0, 013 0,013 0, 013 0,013 0, 013 0,013 0, 013 0,013 0, 013 0,013 0, 013 0,013 0, 013 0,013 0, 013
DIV. 3 PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1) Galian Biasa M3 3.256,63 0,430 0, 028 0,028 0, 028 0,028 0, 028 0,028 0, 028 0,028 0, 028 0,028 0, 028 0,028 0, 028 0,028 0, 028 0,010
3.1.(1) Galian Biasa M3 4.682,90 0,410
0,205 0, 205
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M3 748,80 0,183 0,020 0,020 0, 020 0,020 0,010 0,010 0, 020 0,020 0, 020 0,020
0,003
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M3 662,99 0,229 0, 057 0,057
0,057 0, 057
3.2.(1a) Timbunan Biasa dari Sumber Galian M3 5.940,25 2,782 0, 232 0,232 0, 232 0,232 0, 232 0,232 0, 232 0,232 0, 232 0,232 0, 232 0,232
3.2.(1a) Timbunan Biasa dari Sumber Galian M3 2.591,60 1,025
3.2.(1b) Timbunan biasa dari hasil galian M3 123,17 0,012 0, 002 0,002 0,002 0,002 0,002 0,002
3.2(4) Penimbunan Kembali Berbutir (Granular Backfill) M3 1.695,58 1,491 0,373 0,373
0, 149
3.4(1) Pembersihan dan Pengupasan Lahan M2 4.190,34 0,204 0, 051 0,051 0, 051 0,051
3.4.(2) Pemotongan Pohon Pilihan diameter 15-30 cm buah 5,00 0,002 0, 001 0,001
3.4.(3) Pemotongan Pohon Pilihan diameter >30 - 50 cm buah 18,00 0,010 0,001 0,001 0, 001 0,001 0, 001 0,001 0, 001
3.4.(3) Pemotongan Pohon Pilihan diameter >30 - 50 cm buah 5,00 0,001
0,001
3.4(5) Pemotongan Pohon Pilihan diameter >75 cm buah 6,00 0,004 0, 001 0,001 0, 001
DIV. 5 PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
5.1.(1) Lapis Pondasi Agregat Kelas A M3 1.263,38 1,936 - - - - - - - 0,53087
0,387 0, 387 0,387 0, 387
DIV. 6 PERKERASAN ASPAL
6.1 (1) Lapis Resap Pengikat - Aspal Cair/Emulsi Liter - -
6.1 (2a) Lapis Perekat - Aspal Cair/Emulsi Liter - -
6.5.(1) Laston Lapis Aus Asbuton (AC-WC Asb) Ton - -
6.5.(2) Laston Lapis Antara Asbuton (AC-BC Asb) Ton - -
DIV. 7 STRUKTUR
7.1 (5a) Beton struktur fc’30 Mpa M3 1.377,75 8,809 0, 153 0,153 0, 153 0,153 0, 153 0,153 0, 153 0,153 0, 153 0,153 0, 153 0,153 0, 153 0,153 0,153 0, 153 0,153 0, 153 0,153 0,153 0,153
0,306 0, 306 0,306 0, 306 0,306 0, 306 0,306 0,306 0, 306 0,306 0, 306 0,306 0, 306 0,306 0, 306 0,306 0, 306 0,398
7.1 (5c) Beton struktur memadat sendiri, fc’30 Mpa M3 119,90 0,708 0, 118 0,118 0, 118
7.1 (5c) Beton struktur memadat sendiri, fc’30 Mpa (Harga Timpang) M3 13,45 0,069 0, 012 0,012 0, 012
40
7.1 (8) Beton fc'15 Mpa M3 327,89 1,365
7.1 (8) Beton fc'15 Mpa M3 5,13 0,019
7.1 (10) Beton fc'10 Mpa M3 68,00 0,252 0, 024 0,012 0,012 0, 024 0,024 0,024 0,024
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 13.130,45 0,681 0, 036 0,036 0,018 0,018 0, 022 0,022 0, 022 0,022 0, 022 0,022 0, 022 0,022 0, 022 0,022 0, 022 0,022 0,022 0,036
0,036 0,036 0, 036 0,036 0, 036 0,036 0,0357
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 12.424,26 0,572 0,072 0,072
0,072 0,072 0, 072 0,072 0, 072 0,072
7.3 (4) Baja Tulangan Sirip-BjTS 420B Kg 204.933,83 10,659 0, 371 0,371 0,186 0,186 0, 193 0,193 0, 193 0,193 0, 193 0,193 0, 193 0,193 0, 193 0,193 0, 193 0,193 0,385 0, 771 0,771 0, 771 0,963 0, 193 0,385 0, 385 0,385 0,385
0,223 0, 223 0,223 0, 223 0,223 0, 223 0,223 0,282
7.3 (4) Baja Tulangan Sirip-BjTS 420B (Harga Timpang) Kg 53.305,83 2,485
0,207 0, 207 0,207 0, 207 0,207 0, 207 0,104 0,207 0, 414 0,414 0, 104
7.4.(3) Penyediaan Struktur Jembatan Rangka Baja Standart 60 m Kelas A Kg 183.750,00 14,846 0,337 0,337 0,337 0,337 0,675 0,675 0,675 0,675 0,675 0,675 0,675 0,675 0, 675 0,675 1, 012 0,675 1, 012 1,012 1, 012 1,012 1,012
7.4.(4) Pemasangan Jembatan Rangka Baja Standart Panjang 60 m Kg 183.750,00 1,467 0,550 0,550 0,138 0,138
0, 092 R 0,829 Deviasi - 0,000 - 0,541 0,428 1,273 0,938 17,490 17,345
Fondasi Cerucuk, Penyediaan dan Pemancangan M' e 1,141 0,000 - 0,000
7.6.(1) a 2,076 - 0,000
510,00 0,121 2,676
Rencana Kemajuan Pekerjaan (CCO - 01) (%) 0,458 0,505 0,944 1,281 1,409 1,608 1,645 2,159 2,543 2,543 2,652 2,687 2,770 2,646 2,667 2,632 2,632 2,802 2,933 2,873 2,833 3,032 3,032 2,675 3,727
0,024 0,024 0, 024 0,024 0,012 0,012 4,008
30
4,568 3,346 2,481 2,147 3,178 2,772 2,220 2,602 1,446 0,944
7.6.(1) Fondasi Cerucuk, Penyediaan dan Pemancangan (Harga Timpang) M' 22,039 Rencana Kemajuan Kumulatif Pekerjaan C
5,466 5,971 6,915 8,196 9,605 11,213 12,858 15,017 17,560 20,103 22,754 25,441 28,211 30,857 33,524 36,156 38,788 41,590 44,523 47,396 50,229 53,261 56,293 58,968 78,864 82,210 84,690 86,837 90,015 92,788 95,008 97,610
282,00 0,054 22,353 (CCO - 01) C
99,056 100,000
0,027 0,027 O
Realisasi Kemajuan Pekerjaan (CCO - 01) (%) 0,314 0,604 0,480 0,842 0,642 2,172 0,562 0,076 2,052 14,077 2,044 2,920 5,170 5,784 0,400 0,220 0,820 1,280 1,512 0,273 0,593 1,453 0,491 0,433
7.6 (8c) Penyediaan Tiang Pancang Baja Diameter 600 mm tebal 12 mm M1
R
Realisasi Kemajuan Kumulatif Pekerjaan 22,353 22,957 23,437 24,279 24,921 27,093 27,655 27,731 29,783 43,860 45,904 48,824 53,994 59,778 60,178 60,398 61,218 62,498 64,010 64,283 64,876 66,329 66,820 67,253
1.536,00 12,795 e
0,291 0,291 0,291 0,582 0,582 0, 582 0,582 0, 582 0,582
(CCO - 01)
a
0, 872 0,872 0,582 0,872 0,582 0, 582 0,582 0,582 0,582 Deviasi (%) 16,887 16,986 16,523 16,083 15,317 15,880 14,797 12,714 12,223 23,757 23,150 23,383 25,783 28,921 26,654 24,242 22,430 20,908 19,487 16,887 14,647 13,068 10,528 8,285
0,582 0,582 0,582 0,582 Rencana Kemajuan Pekerjaan (CCO - 02) (%) 0,609
7.6 (14b)a Pemancangan Tiang Pancang Baja Diameter 600 mm M1 1,653 1,771 2,060 1,931 2,040 2,197 2,151 2,054 1,802 1,815 1,911 1,984 1,877 1,888 1,941 1,877 1,762 1,586 1,138 1,038 1,507 0,875 0,791 0,297 0,250 0,228
924,00 1,132 Rencana Kemajuan Kumulatif Pekerjaan C
59,577 61,230 63,001 65,061 66,992 69,032 71,229 73,380 75,434 77,235 79,050 80,961
0,189 0,189 0,189 0,189 0,189 0,189 (CCO - 02) C
82,945 84,821 86,710 88,650 90,528 92,290 93,876 95,014 96,052 97,559 98,434
O
7.6 (14b)b Pemancangan Tiang Pancang Baja Diameter 600 mm M1 99,226 99,523 99,772 100,000
612,00 0,779 Realisasi Kemajuan Pekerjaan (CCO - 02) (%) 0,433
0,156 0,156 0,156 0,156 0,156 1,325 1,048 0,665 1,130 3,370 5,110 5,882
Realisasi Kemajuan Kumulatif Pekerjaan R
7.9.(1) Pasangan Batu M3 e 67,253 68,578 69,626 70,291 71,421 74,791 79,901 85,783
4.971,26 14,365 (CCO - 02)
a
0, 276 0,138 0, 138 0,138 0, 138 0,138 0, 138 0,138 0, 138 Deviasi (%) 8,285
0, 138 0,138 0,138 0,138 0, 138 0,138 0,138 0,276 0, 276 7,348 6,625 5,230 4,429 5,759 8,672 12,403
0, 276 0,276 0, 276 0,276 0, 493 0,493 0,493 0,493 0,493
0,493 0,493 0,493 PEJABAT PEMBUAT KOMITMEN 2.3
0,740 0,493 0,493 0,493 0,493 PT. RAJABATU KIERAHA PERKASA P
0,493 0,247 0,493 0,493 0,493 0,493 0,493 0,493
PROVINSI MALUKU PENYEDIA JASA T
7.9.(1) Pasangan Batu (Harga Timpang) M3 .
58,90
R
0,145
0,012 0, 012 0,012 0,012 YOHANIS.
0,012 B. MELSASAIL,
0,012 0, 012 S.T. 0,012 RUDY SETIAWAN, S.T. O
0, 012 0,012 0, 012 0,012 S
7.10.(2) Pasangan Batu Kosong NIP. 19800724 201012 1 001 M3 General Superintendent A
289,28 0,507 R
0, 046 0,046 0, 046 0,023 0,023 0,040 0, 040 0,040 0, 040
0, 080 0,080 I
7 C
0,129 0,129
. 0, 129 0,517 O
1 0, 388 0,388 N
7 0, 582 0,194
. 0, 388 0,388 S
1 0, 194 0,388 U
7 0, 776 0,194
. 0, 299 0,299
L
1 0, 299 0,299 T
0, 299 0,299 A
0, 299 0,776
N
0, 103 0,103
0, 034

K
O
20
N
7.13.(1) Sandaran (Railing) M1 S
100,60 0,288
0, 072 0, 072
U
0,072 0, 072 L
7.14.(1) Papan Nama Jembatan Buah T
10,00 A
0,035 N
0, 007
0, 007
0, 007
0, 007
P
0, 007
E
7.15 (1) Pembongkaran Pasangan Batu M3
16,20 N
0,021 G
0,021 A
7.15 (1) Pembongkaran Pasangan Batu (Harga Timpang) M3 W
65,76 A
0,057 S
0,057
7.15 (7) Pembongkaran Lantai Jembatan Kayu M2
30,00 A
0,015 S
0,015
R
7.15 (7) Pembongkaran Lantai Jembatan Kayu M2 U
37,50 K
0,012 I
0,006 0,006
,
7.16.(1) Deck drain Buah S
46,00 T
0,087
0,015 0, 015
0,015 0, 015 S
0, 029 i
7.16.(1) Deck drain Buah t
6,00 e
0,009
0, 009
7.16.(2a) Pipa Drainase Baja Diameter 1500 E
mm n
74,00 g
0,006 0, 006 i
0, 006 n
DIV. 9 PEKERJAAN HARIAN DAN
e
PEKERJAAN LAIN-LAIN e
9.2.(1) Marka Jalan Termoplastik r
-
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade Buah
16,00
0,052
0, 009 0,013 0, 009 0,009 0,
0, 004
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade Buah
4,00
0,006
0,001 0,001 0,001 0,001 0,002
9.2.(5) Patok Pengarah Buah
172,00 0,096
0,011 0, 011 0,011 0, 011 0,011 0, 011 0,011
0, 016 0,005
9.2.(5) Patok Pengarah Buah
32,00
0,012
0, 001
0, 001 0,001 0, 001 0,001 0, 001 0,001 0, 002
0, 001
9.2.(14) Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED Buah
14,00
1,082
0, 135 0,135 0, 135 0,135 0, 135 0,135 0, 203
0, 068
9.2.(14) Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED Buah
2,00
0,084
0, 010 0,010 0, 010 0,010 0,
0, 010 0,010
9.2.(14) Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED Buah
6,00
0,169
0, 032 0,032 0, 032 0,032 0,
0, 011

A JUMLAH 100,000
0

Rencana
0,259 0,259 0,311 0,311 0,395 0,713 0,487 0,895
Kemajua
0,919 0,458 0,458 0,634 0,978 1,025 1,287 1,287
n 2,615 2,924 2,924 3,425 3,834 3,610 3,578 4,921
Pekerj 4,617 4,652 4,676 4,676 3,242 3,500 3,879 4,162
an 4,141 4,187 4,128 2,778 2,884 3,064 1,916 1,932
1,071 1,026 0,652 0,311
(Kontrak
Awal)

(%)
Rencana Kemajuan Kumulatif Pekerjaan (Kontrak Awal) (%)
0,259 0,518 0,830 1,141 1,536 2,249 2,735 3,631
4,550 5,008 5,466 6,100 7,078 8,104 9,390 10,677
13,292 16,216 19,140 22,565 26,399 30,009 33,587 38,508
43,125 47,776 52,452 57,127 60,370 63,870 67,749 71,911
76,051 80,238 84,366 87,144 90,028 93,092 95,008 96,940
98,011 99,037 99,689 100,000
Realisasi Kemajuan Pekerjaan (Kontrak Awal) (%)
0,259 0,259 0,311 0,311 0,935 0,600 1,332 0,560
17,471 0,314
Realisasi n (Kontrak Awal) (%)
Kemajuan
Kumulati
LAPORAN BULANAN 03 ........................
Pengawasan Teknis Jalan & Jembatan ...............................

3.8. Data Kemajuan Fisik

PT. Rosari Consultan 39


LAPORAN KEMAJUAN PEKERJAAN BULANAN
PEKERJAAN : PEMBANGUNAN JEMBATAN WAI HANOLI Cs PERIODE LAPORAN

NOMOR KONTRAK : HK 102-Bb16/498675.2.3/01/2020 BULAN KE : 09 (Oktober)

TANGGAL KONTRAK : 13 FEBRUARI 2020

NILAI KONTRAK : Rp. 41.088477.000,- PERIODE TANGGAL : 28 Sept - 01 Nov 2020

KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT NOMOR ADDENDUM 01/TANGGAL : ADD.01/HK0102-Bb/498675.2.3/01/2020 Tanggal 23 Maret 2020

DIREKTORAT JENDERAL BINA MARGA NOMOR ADDENDUM 02/TANGGAL : ADD.02/HK0102-Bb/498675.2.3/01/2020 Tanggal 23 April 2020 PROGRES PEKERJAAN

SATUAN KERJA PELAKSANAAN JALAN NASIONAL WILAYAH I NOMOR ADDENDUM 03/TANGGAL : ADD.03/HK0102-Bb/498675.2.3/01/2020 Tanggal 05 Oktober 2020 RENCANA : 65,06

PROVINSI MALUKU KONTRAKTOR : PT. RAJABATU Kieraha Perkasa REALISASI : 70,29

BAGIAN PELAKSANA KEGIATAN JALAN PULAU SERAM KONSULTAN : PT. ROSARI CONSULTAN DEVIASI (+/-) : 5,23

I JLN.Ir.M.PUTUHENA, WAILELA - AMBON MASA PELAKSANAAN : 390 HARI KALENDER WAKTU PEKERJAAN

MASA PEMELIHARAAN : 730 HARI KALENDER RENCANA : 390

TAHUN ANGGARAN : 2020 REALISASI : 257

LOKASI : PULAU SERAM SISA : 133

KONTRAK CCO-02 PROGRES BULAN LALU PROGRESS BULAN INI PROGRESS S/D BULAN INI
BOBOT THDP.
HARGA JUMLAH BOBOT
No. URAIAN KEGIATAN BOBOT BOBOT BOBOT
SATUAN VOLUME SATUAN HARGA VOLUME VOLUME VOLUME REALISASI
RENCAN (%) (%)
( Rp.) ( Rp.) (%)
A
DIV. 1 UMUM
1.2 Mobilisasi LS 1,00 1.548.400.000,00 1.548.400.000,00 4,15% 0,87 3,626 - - 0,87 3,63 87,50
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1,00 365.000.000,00 365.000.000,00 0,98% 0,88 0,86 - - 0,88 0,69 70,25
1.8.(2) Jembatan Sementara LS 1,00 582.811.800,60 582.811.800,60 1,56% 1,00 1,56 - - 1,00 1,25 79,95
1.17.(1a) Pengujian pH Buah 36,00 500.000,00 18.000.000,00 0,05% 12,00 0,02 - - 12,00 0,02 33,33
1.17.(1a) Pengujian pH (Harga Timpang) Buah 9,00 215.000,00 1.935.000,00 0,01% - - - - - - -
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 36,00 500.000,00 18.000.000,00 0,05% 12,00 0,02 - - 12,00 0,02 33,33
1.17.(1b) Pengujian Oksigen Terlarut (DO) (Harga Timpang) Buah 9,00 240.000,00 2.160.000,00 0,01% - - - - - - -
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 36,00 500.000,00 18.000.000,00 0,05% 12,00 0,02 - - 12,00 0,02 33,33
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) (Harga Timpang) Buah 9,00 230.000,00 2.070.000,00 0,01% - - - - - - -
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 36,00 500.000,00 18.000.000,00 0,05% 12,00 0,02 - - 12,00 0,02 33,33
1.17.(1d) Pengujian Zat Tersuspensi (TSS) (Harga Timpang) Buah 9,00 230.000,00 2.070.000,00 0,01% - - - - - - -
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 36,00 500.000,00 18.000.000,00 0,05% 12,00 0,02 - - 12,00 0,02 33,33
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) (Harga Timpang) Buah 9,00 245.000,00 2.205.000,00 0,01% - - - - - - -
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 36,00 500.000,00 18.000.000,00 0,05% 12,00 0,02 - - 12,00 0,02 33,33
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) (Harga Timpang) Buah 9,00 305.000,00 2.745.000,00 0,01% - - - - - - -
1.17.(1g) Pengujian Coliform Buah 36,00 500.000,00 18.000.000,00 0,05% 12,00 0,02 - - 12,00 0,02 33,33
1.17.(1g) Pengujian Coliform (Harga Timpang) Buah 9,00 400.000,00 3.600.000,00 0,01% - - - - - - -
1.17.(1h) Pegujian E. Coli Buah 36,00 500.000,00 18.000.000,00 0,05% 12,00 0,02 - - 12,00 0,02 33,33
1.17.(1h) Pegujian E. Coli (Harga Timpang) Buah 9,00 328.000,00 2.952.000,00 0,01% - - - - - - -
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 45,00 500.000,00 22.500.000,00 0,06% 12,00 0,02 - - 12,00 0,02 26,67
1.17.(1j) Pengujian Temperatur (Suhu) Buah 36,00 500.000,00 18.000.000,00 0,05% 12,00 0,02 - - 12,00 0,02 33,33
1.17.(1j) Pengujian Temperatur (Suhu) (Harga Timpang) Buah 9,00 215.000,00 1.935.000,00 0,01% - - - - - - -
1.17.(1k) Pengujian Parameter Kualitas Air Lainnya Buah 36,00 500.000,00 18.000.000,00 0,05% 12,00 0,02 - - 12,00 0,02 33,33
1.17.(1k) Pengujian Parameter Kualitas Air Lainnya (Harga Timpang) Buah 9,00 215.000,00 1.935.000,00 0,01% - - - - - - -
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan dan Kesehatan Buah 45,00 500.000,00 22.500.000,00 0,06% 12,00 0,02 - - 12,00 0,02 26,67
1.17.(2c) Pengujian Tingkat Getaran Kendaraan Bermotor Buah 45,00 500.000,00 22.500.000,00 0,06% - - - - - - -
1.17.(3a) Pengujian NoX Buah 36,00 500.000,00 18.000.000,00 0,05% 12,00 0,02 - - 12,00 0,02 33,33
1.17.(3a) Pengujian NoX (Harga Timpang) Buah 9,00 413.666,67 3.723.000,03 0,01% - - - - - - -
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 45,00 500.000,00 22.500.000,00 0,06% 12,00 0,02 - - 12,00 0,02 26,67
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 45,00 500.000,00 22.500.000,00 0,06% 12,00 0,02 - - 12,00 0,02 26,67
1.17.(3h) Pengujian Parameter Udara Emisi dan Ambien lainnya Buah 45,00 500.000,00 22.500.000,00 0,06% 12,00 0,02 - - 12,00 0,02 26,67
1,19 Keselamatan dan Kesehatan Kerja LS 1,00 298.578.000,00 298.578.000,00 0,80% 0,63 0,50 - - 0,63 0,40 50,17
1,21 Manajemen Mutu LS 1,00 337.500.000,00 337.500.000,00 0,90% 0,62 0,56 - - 0,62 0,45 49,31
KONTRAK CCO-02 PROGRES BULAN LALU PROGRESS BULAN INI PROGRESS S/D BULAN INI
BOBOT THDP.
HARGA JUMLAH BOBOT
No. URAIAN KEGIATAN BOBOT BOBOT BOBOT
SATUAN VOLUME SATUAN HARGA VOLUME VOLUME VOLUME REALISASI
RENCAN (%) (%)
( Rp.) ( Rp.) (%)
A
3.492.619.800,63 9,35%
DIV. 3 PEKERJAAN TANAH DAN GEOSINTETIK
3.1.(1) Galian Biasa M
3 3.256,63 49.371,00 160.782.994,07 0,43% 4.363,50 0,58 - - 4.363,50 0,58 133,99
3.1.(1) Galian Biasa (Harga Timpang) M
3 4.682,90 32.677,94 153.027.683,50 0,41% - - - - - - -
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M
3 748,80 91.416,00 68.451.888,29 0,18% 1.062,92 0,26 - - 1.062,92 0,26 141,95
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M
3 662,99 128.779,00 85.379.085,01 0,23% 224,66 0,08 - - 224,66 0,08 33,89
3.2.(1a) Timbunan Biasa dari Sumber Galian M
3 5.940,25 174.940,00 1.039.188.123,93 2,78% 6.004,77 2,81 - - 6.004,77 2,81 101,09
3.2.(1a) Timbunan Biasa dari Sumber Galian (Harga Timpang) M
3 2.591,60 147.733,99 382.867.998,93 1,02% - - - - - - -
3.2.(1b) Timbunan biasa dari hasil galian M
3 123,17 35.195,00 4.335.087,57 0,01% - - - - - -
3.2(4) Penimbunan Kembali Berbutir (Granular Backfill) M
3 1.695,62 328.528,00 557.060.285,73 1,49% - - - - - -
3.4(1) Pembersihan dan Pengupasan Lahan M
2 4.190,34 18.162,00 76.104.955,08 0,20% 4.190,34 0,20 - - 4.190,34 0,20 100,00
3.4.(2) Pemotongan Pohon Pilihan diameter 15-30 cm buah 5,00 151.630,00 758.150,00 0,00% 5,00 0,00 - - 5,00 0,00 100,00
3.4.(3) Pemotongan Pohon Pilihan diameter >30 - 50 cm buah 18,00 200.451,00 3.608.118,00 0,01% 18,00 0,01 - - 18,00 0,01 100,00
3.4.(3) Pemotongan Pohon Pilihan diameter >30 - 50 cm (Harga Timpang) buah 5,00 50.531,05 252.655,25 0,00% - - - - - - -
3.4(5) Pemotongan Pohon Pilihan diameter >75 cm buah 6,00 272.369,00 1.634.214,00 0,00% 6,00 0,00 - - 6,00 0,00 100,00
2.533.451.239,35 6,78%
DIV. 5 PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN
3
5.1.(1) Lapis Pondasi Agregat Kelas A M 1.263,38 572.335,00 723.074.302,96 1,94% - - - - - - -
723.074.302,96 1,94%
DIV. 6 PERKERASAN ASPAL
6.1 (1) Lapis Resap Pengikat - Aspal Cair/Emulsi Liter - 19.672,00 - 0,00% - - - - - - -
6.1 (2a) Lapis Perekat - Aspal Cair/Emulsi Liter - 20.312,00 - 0,00% - - - - - - -
6.5.(1) Laston Lapis Aus Asbuton (AC-WC Asb) Ton - 1.531.969,00 - 0,00% - - - - - - -
6.5.(2) Laston Lapis Antara Asbuton (AC-BC Asb) Ton - 1.471.629,00 - 0,00% - - - - - - -
- 0,00%
DIV. 7 STRUKTUR
7.1 (5a) Beton struktur fc’30 Mpa M
3 1.377,75 2.388.244,00 3.290.395.516,68 8,81% 795,99 5,09 267,52 1,71 1.063,51 6,80 77,19
7.1 (5c) Beton struktur memadat sendiri, fc’30 Mpa M
3 119,90 2.205.516,00 264.441.368,40 0,71% 119,90 0,71 - - 119,90 0,71 100,00
7.1 (5c) Beton struktur memadat sendiri, fc’30 Mpa (Harga Timpang) M
3 13,45 1.923.081,89 25.860.470,48 0,07% 13,45 0,07 - - 13,45 0,07 100,02
7.1 (8) Beton fc'15 Mpa M
3 327,89 1.554.801,00 509.806.498,53 1,36% - - 13,36 0,06 13,36 0,06 4,07
7.1 (8) Beton fc'15 Mpa (Harga Timpang) M
3 5,13 1.404.772,09 7.200.580,78 0,02% - - - - - - -
7.1 (10) Beton fc'10 Mpa M
3 68,00 1.386.599,00 94.284.572,20 0,25% 51,46 0,19 - - 51,46 0,19 75,68
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 13.130,45 19.377,00 254.428.652,96 0,68% 5.897,28 0,31 - - 5.897,28 0,31 44,91
7.3 (1) Baja Tulangan Polos-BjTP 280 (Harga Timpang) Kg 12.424,26 17.202,50 213.728.372,34 0,57% - - 4.693,36 0,22 4.693,36 0,22 37,78
7.3 (4) Baja Tulangan Sirip-BjTS 420B Kg 204.933,83 19.429,00 3.981.659.367,78 10,66% 174.854,51 9,09 - - 174.854,51 9,09 85,32
7.3 (4) Baja Tulangan Sirip-BjTS 420B (Harga Timpang) Kg 53.305,83 17.414,19 928.277.878,39 2,49% - - 4.442,15 0,21 4.442,15 0,21 8,33
7.4.(3) Penyediaan Struktur Jembatan Rangka Baja Standart 60 m Kelas A Kg 183.750,00 30.180,00 5.545.575.000,00 14,85% 183.750,00 14,85 - - 183.750,00 14,85 100,00
7.4.(4) Pemasangan Jembatan Rangka Baja Standart Panjang 60 m Kg 183.750,00 2.982,00 547.942.500,00 1,47% 183.750,00 1,47 - - 183.750,00 1,47 100,00
7.6.(1) Fondasi Cerucuk, Penyediaan dan Pemancangan M' 510,00 88.318,00 45.042.180,00 0,12% 510,00 0,12 - - 510,00 0,12 100,00
7.6.(1) Fondasi Cerucuk, Penyediaan dan Pemancangan (Harga Timpang) M' 282,00 71.331,07 20.115.361,74 0,05% 30,00 0,01 252,00 0,05 282,00 0,05 100,00
7.6 (8c) Penyediaan Tiang Pancang Baja Diameter 600 mm tebal 12 mm M
1 1.536,00 3.111.647,00 4.779.489.792,00 12,80% 1.536,00 12,80 - - 1.536,00 12,80 100,00
7.6 (14b) Pemancangan Tiang Pancang Baja Diameter 600 mm(salatena) M
1 612,00 475.575,00 291.051.900,00 0,78% 612,00 0,78 - - 612,00 0,78 100,00
7.6 (14b) Pemancangan Tiang Pancang Baja Diameter 600 mm(hanoli) M
1 924,00 457.575,00 422.799.300,00 1,13% 924,00 1,13 - - 924,00 1,13 100,00
7.9.(1) Pasangan Batu 3 4.971,26 1.079.338,00 5.365.668.882,80 14,36% 2.188,51 6,32 346,29 1,00 2.534,80 7,32 50,99
M
7.9.(1) Pasangan Batu (Harga Timpang) 3 58,90 919.838,82 54.174.857,93 0,15% - - - - - - -
M
7.10.(2) Pasangan Batu Kosong 3 289,28 654.637,00 189.375.682,59 0,51% 198,32 0,35 90,96 0,16 289,28 0,51 100,00
M
7.10.(3a) Bronjong dengan Kawat yang dilapisi Galvanis 3 3.110,00 936.571,00 2.912.735.810,00 7,80% 1.120,00 2,81 - - 1.120,00 2,81 36,01
M
7.11.(1a) Sambungan Siar Muai Tipe Asphaltic Plug, Fixed 1 36,00 2.128.094,00 76.611.384,00 0,21% - - - - - - -
M
KONTRAK CCO-02 PROGRES BULAN LALU PROGRESS BULAN INI PROGRESS S/D BULAN INI
BOBOT THDP.
HARGA JUMLAH BOBOT
No. URAIAN KEGIATAN BOBOT BOBOT BOBOT
SATUAN VOLUME SATUAN HARGA VOLUME VOLUME VOLUME REALISASI
RENCAN (%) (%)
( Rp.) ( Rp.) (%)
A
7.12.(3) Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran 400 mm x 300 mm x 52 mm Buah 16,00 786.312,00 12.580.992,00 0,03% - - 16,00 0,03 16,00 0,03 100,00
7.13.(1) Sandaran (Ralling) M
1 100,80 1.068.396,00 107.694.316,80 0,29%
7.14.(1) Papan Nama Jembatan Buah 10,00 1.317.900,00 13.179.000,00 0,04% - - - - - - -
7.15 (1) Pembongkaran Pasangan Batu M
3 16,20 492.949,00 7.985.773,80 0,02% 16,20 0,02 - - 16,20 0,02 100,00
7.15 (1) Pembongkaran Pasangan Batu (Harga Timpang) M
3 65,76 322.139,63 21.184.212,61 0,06% 30,98 0,03 - - 30,98 0,03 47,11
7.15 (7) Pembongkaran Lantai Jembatan Kayu M
2 30,00 183.415,00 5.502.450,00 0,01% 30,00 0,01 - - 30,00 0,01 100,00
7.15 (7) Pembongkaran Lantai Jembatan Kayu (Harga Timpang) M
2 37,50 114.748,75 4.303.078,13 0,01% - - 37,50 0,01 37,50 0,01 100,00
7.16.(1) Deck drain Buah 46,00 708.280,00 32.580.880,00 0,09% 24,00 0,05 22,00 0,04 46,00 0,09 100,00
7.16.(1) Deck drain (Harga Timpang) Buah 6,00 551.232,00 3.307.392,00 0,01% - - - - - - -
1
7.16.(2a) Pipa Drainase Baja Diameter 150 mm M 74,00 195.000,00 14.430.000,00 0,04% - - - - - - -
30.043.414.024,95 80,43%
DIV. 9 PEKERJAAN HARIAN DAN PEKERJAAN LAIN-LAIN
9.2.(1) Marka Jalan Termoplastik M
2 - 396.858,00 - 0,00% - - - - - - -
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade Buah 16,00 1.205.723,00 19.291.568,00 0,05% - - - - - - -
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade (Harga Timpang) Buah 4,00 574.527,37 2.298.109,48 0,01% - - - - - - -
9.2.(5) Patok Pengarah Buah 172,00 207.435,00 35.678.820,00 0,10% - - - - - - -
9.2.(5) Patok Pengarah (Harga Timpang) Buah 32,00 145.103,01 4.643.296,32 0,01% - - - - - - -
9.2.(14) Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED Buah 14,00 28.876.094,00 404.265.316,00 1,08% - - - - - - -
9.2.(14) Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED (Harga Timpang) Buah 2,00 15.621.079,22 31.242.158,44 0,08% - - - - - - -
9.2.(14) Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED (Harga Timpang) Buah 4,00 15.795.689,21 63.182.756,84 0,17% - - - - - - -
560.602.025,08 0,02

A JUMLAH FISIK PEKERJAAN 37.353.161.392,98


REALISASI 67,50 3,48 70,29
B PPN 10 % 3.735.316.139,30
100,00%
C JUMLAH ( A + B ) 41.088.477.532,27 RENCANA 56,93 0,00 65,06
D TOTAL DIBULATKAN 41.088.477.000,00 DEVIASI (+/-) 10,57 3,48 5,227

Disetujui Oleh Diperiksa Oleh Dibuat Oleh :


DIREKSI PU KONSULTAN SUPERVISI PENYEDIA JASA
PPK 2.3 PROVINSI MALUKU PT. ROSARI CONSULTAN PT. RAJABATU KIERAHA PERKASA
SATKER PJN WILAYAH II MALUKU

A S R U K I, S T MUH. TAHIR S. SIREGAR, Amd


Site Engineer Site Manager
YOHANIS B. MELSASAIL, ST
Nip. 19800724 201012 1 001
LAPORAN BULANAN 03 (...................)
Pengawasan Teknis Jalan & Jembatan di.............................

3.9. Sertifikat Bulanan (MC)

PT. Rosari Consultan 40


3.10. Rangkuman Pembayaran MC
3.11. Daftar Personil Kontraktor .......................................................

Pengal Ket
No Nama Pendidikan Jabatan Sertifikat
aman
S1 Teknik General 5 tahun SKA Ahli Tdk
1 .................................... Sipil Superintend Madya ada
ent Jembatan
S1 Teknik Site 5 Tahun SKA Ahli Ada
2 .................................. Sipil Manager Madya
Jembatan
S1 Teknik Manager 5 Tahun SKA Ahli Ada
3 ................................... Sipil Mutu Madya
Jembatan
4 D3 Teknik Pelaksana 3 Tahun - Ada
..................................
Sipil Jembatan
5 ................................. S1 Teknik Quality 2 Tahun - Ada
Sipil Engineer
6 S1 Teknik Quantity 2 Tahun - Ada
.................................
Sipil Engineer
7 S1 Teknik Administrasi 2 Tahun - Ada
.................................
Sipil Teknik 1
8 D3 Teknik Administrasi 2 Tahun - Ada
..................................
Sipil Teknik 2
9 D3 Teknik Petugas K3 2 Tahun - Tdk
.................................
Sipil ada
10 D3 Teknik Surveyor 2 Tahun - Ada
.................................
Sipil
3.12. Struktur Organisasi Kontraktor (PT.........................................)

Struktur Organisasi Pelaksanaan Pembangunan Jembatan .........................

.............................
General Superintendent

..........................
Adminitrasi Teknik
............................
Manager Kendali Mutu

......................... ............................. .......................


Ahli K3 Quality Control Site Manager

............................. .............. ........................ ........................


Pelaksana Surveyor Quantity/Drafter Adm. Teknik
3.13. Daftar Peralatan Kontraktor (PT. ......................................)

Data Peralatan Kontraktor


Paket Pembangunan Jembatan ...............

No. Jenis Alat Jumlah Satuan Keterangan

1 Alat Ukur
- Total Station 1 Set Ada
- Waterpass 1 Set Ada
- Meter Baja 100 M 1 Buah Ada
- Kamera Foto 3 Buah Ada
- Kamera Foto Udara 1 Set Tidak Ada
2 Alat Laboratorium
- Silinder Mold 40 Buah Ada
- Slump Test 1 Set Ada
- Sand Cone Test 2 Set Ada
- Speedy Test 1 Set Ada
- Digital Balance 1 Buah Ada
- Saringan 1 Set Ada
3 Alat Berat
- Excavator PC200 4 Unit Ada
- Stone Crusher 1 Set Ada
- Genset 2 Set Ada
- Batching Plant Mini 1 Set Ada
- Truck Mixer Kap. 2,5 M3 3 Unit Ada
- Motor Grader 1 Unit Ada
- Vibrator Roller 1 Unit Ada
- Water Tank Truck 1 Unit Ada
- Asphalt Finisher 1 Unit Ada
- Tandem Roller 1 Unit Ada
- Pneumatic Tire Roller 1 Unit Ada
- Dump Truck 6 Ton 5 Unit Ada
- Alat Pancang 1 Set Ada
- Pile Driver + Hammer 1 Set Ada
3,5 Ton 1 Set
- Welding Set 1 Set Ada
- Peralatan Erection Baja 1 Set Ada
- Mobil Pick – Up 1 Unit Ada
- Pompa Air 2 Unit Ada
3.14. Status Revisi Design dan Contrak Change Order (CCO)
Satuan Kerja :
PPK :
Nama Paket :
No. Paket Kontrak :
Tanggal Kontrak

DAFTAR KUANTITAS DAN HARGA

Keterangan Hasil
Harga Satuan CC01 Pekerjaan Tambah Pekerjaan Kurang CCO-02

NO Uraian Kegiatan Original Harga Baru Satuan Jumlah Harga Bobot Jumlah harga Jumlah Harga Jumlah Harga Bobot CCO 02 Terhadap
Kuantitas Kuantitas Kuantitas Kuantitas CCO 01
(Rp.) (Rp.) (Rupiah) (%) (Rp.) (Rp.) (Rp.) (%)

a b c d e f g = (c x f) h i j k l m n o p
DIV. 1 UMUM
1.2 Mobilisasi LS 1,00 1.548.400.000,00 4,15 - - - 1,00 1.548.400.000,00 4,15 Tetap
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1,00 292.000.000,00 0,78 1,00 73.000.000,00 - - 1,00 365.000.000,00 0,98 Tetap
1.8.(2) Jembatan Sementara LS 1,00 466.249.440,48 1,25 1,00 116.562.360,12 - - 1,00 582.811.800,60 1,56 bertambah
1.17.(1a) Pengujian pH Buah 36,00 18.000.000,00 0,05 - - 36,00 18.000.000,00 0,05 Tetap
1.17.(1a) Pengujian pH (Harga Timpang) Buah - - 9,00 1.935.000,00 - - 9,00 1.935.000,00 0,01 harga timpang
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 36,00 18.000.000,00 0,05 - - 36,00 18.000.000,00 0,05 Tetap
1.17.(1b) Pengujian Oksigen Terlarut (DO) (Harga Timpang) Buah - - 9,00 2.160.000,00 - - 9,00 2.160.000,00 0,01 Harga Timpang
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 36,00 18.000.000,00 0,05 - - 36,00 18.000.000,00 0,05 Tetap
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) (Harga Timpang) Buah - - 9,00 2.070.000,00 - - 9,00 2.070.000,00 0,01 Harga Timpang
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 36,00 18.000.000,00 0,05 - - 36,00 18.000.000,00 0,05 Tetap
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah - - 9,00 2.070.000,00 - - 9,00 2.070.000,00 0,01 Harga Timpang
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 36,00 18.000.000,00 0,05 - - 36,00 18.000.000,00 0,05 Tetap
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah - - 9,00 2.205.000,00 - - 9,00 2.205.000,00 0,01 Harga Timpang
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 36,00 18.000.000,00 0,05 - - 36,00 18.000.000,00 0,05 Tetap
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah - - 9,00 2.745.000,00 - - 9,00 2.745.000,00 0,01 Harga Timpang
1.17.(1g) Pengujian Coliform Buah 36,00 18.000.000,00 0,05 - - 36,00 18.000.000,00 0,05 Tetap
1.17.(1g) Pengujian Coliform Buah - - 9,00 3.600.000,00 - - 9,00 3.600.000,00 0,01 Bertambah
1.17.(1h) Pegujian E. Coli Buah 36,00 18.000.000,00 0,05 - - 36,00 18.000.000,00 0,05 Tetap
1.17.(1h) Pegujian E. Coli Buah - - 9,00 2.952.000,00 - - 9,00 2.952.000,00 0,01 Harga Timpang
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 36,00 18.000.000,00 0,05 9,00 4.500.000,00 - - 45,00 22.500.000,00 0,06 Bertambah
1.17.(1j) Pengujian Temperatur (Suhu) Buah 36,00 18.000.000,00 0,05 - - 36,00 18.000.000,00 0,05 Tetap
1.17.(1j) Pengujian Temperatur (Suhu) Buah - - 9,00 1.935.000,00 - - 9,00 1.935.000,00 0,01 Harga Timpang
1.17.(1k) Pengujian Parameter Kualitas Air Lainnya Buah 36,00 18.000.000,00 0,05 - - 36,00 18.000.000,00 0,05 Tetap
1.17.(1k) Pengujian Parameter Kualitas Air Lainnya Buah - - 9,00 1.935.000,00 - - 9,00 1.935.000,00 0,01 Harga Timpang
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan dan Kesehatan Buah 36,00 18.000.000,00 0,05 9,00 4.500.000,00 - - 45,00 22.500.000,00 0,06 Bertambah
1.17.(2c) Pengujian Tingkat Getaran Kendaraan Bermotor Buah 36,00 18.000.000,00 0,05 9,00 4.500.000,00 - - 45,00 22.500.000,00 0,06 Bertambah
1.17.(3a) Pengujian NoX Buah 36,00 18.000.000,00 0,05 - - 36,00 18.000.000,00 0,05 Tetap
1.17.(3a) Pengujian NoX Buah - 9,00 3.723.000,03 - - 9,00 3.723.000,03 0,01 Harga Timpang
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 36,00 18.000.000,00 0,05 9,00 4.500.000,00 - - 45,00 22.500.000,00 0,06 Bertambah
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 36,00 18.000.000,00 0,05 9,00 4.500.000,00 - - 45,00 22.500.000,00 0,06 Bertambah
1.17.(3h) Pengujian Parameter Udara Emisi dan Ambien lainnya Buah 36,00 18.000.000,00 0,05 9,00 4.500.000,00 - - 45,00 22.500.000,00 0,06 Bertambah
1,19 Keselamatan dan Kesehatan Kerja LS 1,00 238.862.400,00 0,64 1,00 59.715.600,00 - - 1,00 298.578.000,00 0,80 Bertambah
1,21 Manajemen Mutu LS 1,00 270.000.000,00 0,72 1,00 67.500.000,00 - - 1,00 337.500.000,00 0,90 Bertambah
- -
Jumlah Harga DIVISI 1 3.121.511.840,48 8,36 371.107.960,15 - 3.492.619.800,63 9,35

DIV. 3 PEKERJAAN TANAH DAN GEOSINTETIK -


3.1.(1) Galian Biasa M
3
4.661,94 230.164.727,67 0,62 - 1.405,31 69.381.733,60 3.256,63 160.782.994,07 0,43 Berkurang
3.1.(1) Galian Biasa (Harga Timpang) M
3
- - 4.682,90 153.027.683,50 - - 4.682,90 153.027.683,50 0,41 Harga Timpang
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter M
3
1.062,92 97.167.938,36 0,26 - - 314,12 28.716.050,07 748,80 68.451.888,29 0,18 Berkurang
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter M
3
224,66 28.932.115,68 0,08 438,32 56.446.969,33 - - 662,99 85.379.085,01 0,23 Bertambah
3.2.(1a) Timbunan Biasa dari Sumber Galian M
3
7.217,83 1.262.686.322,48 3,38 - 1.277,57 223.498.198,56 5.940,25 1.039.188.123,93 2,78 Berkurang
3.2.(1a) Timbunan Biasa dari Sumber Galian (Harga Timpang) M
3
- - 2.591,60 382.867.998,93 - - 2.591,60 382.867.998,93 1,02 Harga Timpang
3.2.(1b) Timbunan biasa dari hasil galian M
3
2.250,37 79.201.839,80 0,21 - - 2.127,20 74.866.752,23 123,17 4.335.087,57 0,01 Berkurang
3.2(4) Penimbunan Kembali Berbutir (Granular Backfill) M
3
248,74 81.718.543,41 0,22 1.446,88 475.341.742,32 - - 1.695,62 557.060.285,73 1,49 Bertambah
3.4(1) Pembersihan dan Pengupasan Lahan M
2
4.190,34 76.104.955,08 0,20 - - - - 4.190,34 76.104.955,08 0,20 Tetap
Harga Satuan CC01 Pekerjaan Tambah Pekerjaan Kurang CCO-02
Keterangan Hasil
NO Uraian Kegiatan Original Harga Baru Satuan Jumlah Harga Bobot Jumlah harga Jumlah Harga Jumlah Harga Bobot CCO 02 Terhadap
Kuantitas Kuantitas Kuantitas Kuantitas CCO 01
(Rp.) (Rp.) (Rupiah) (%) (Rp.) (Rp.) (Rp.) (%)

a b c d e f g = (c x f) h i j k l m n o p
3.4.(2) Pemotongan Pohon Pilihan diameter 15-30 cm buah 5,00 758.150,00 0,00 - - - - 5,00 758.150,00 0,00 Tetap
3.4.(3) Pemotongan Pohon Pilihan diameter >30 - 50 cm buah 18,00 3.608.118,00 0,01 - - - 18,00 3.608.118,00 0,01 Tetap
3.4.(3) Pemotongan Pohon Pilihan diameter >30 - 50 cm (Harga Timpang) buah - - 5,00 252.655,25 - - 5,00 252.655,25 0,00 Harga Timpang
3.4(5) Pemotongan Pohon Pilihan diameter >75 cm buah 6,00 1.634.214,00 0,00 - - - - 6,00 1.634.214,00 0,00 Tetap

Jumlah Harga DIVISI 3 1.861.976.924,48 4,98 1.067.937.049,33 396.462.734,46 2.533.451.239,35 6,78

DIV. 5 PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN


5.1.(1) Lapis Pondasi Agregat Kelas A M
3
4.182,38 2.393.720.167,96 6,41 - - 2.919,00 1.670.645.865,00 1.263,38 723.074.302,96 1,94 Berkurang

Jumlah Harga DIVISI 5 2.393.720.167,96 6,408 - 1.670.645.865,00 723.074.302,96 1,94

DIV. 6 PERKERASAN ASPAL


6.1 (1) Lapis Resap Pengikat - Aspal Cair/Emulsi Liter 5.817,30 114.438.020,03 0,31 - - 5.817,30 114.438.020,03 - - - Dihilangkan
6.1 (2a) Lapis Perekat - Aspal Cair/Emulsi Liter 1.232,33 25.031.043,90 0,07 - - 1.232,33 25.031.043,90 - - - Dihilangkan
6.5.(1) Laston Lapis Aus Asbuton (AC-WC Asb) Ton 683,08 1.046.449.913,41 2,80 - - 683,08 1.046.449.913,41 - - - Dihilangkan
6.5.(2) Laston Lapis Antara Asbuton (AC-BC Asb) Ton 1.038,77 1.528.676.899,50 4,09 - - 1.038,77 1.528.676.899,50 - - - Dihilangkan

Jumlah Harga DIVISI 6 2.714.595.876,84 7,267 - 2.714.595.876,84 - -

DIV. 7 STRUKTUR
7.1 (5a) Beton struktur fc’30 Mpa M
3
1.049,07 2.505.426.392,11 6,71 328,68 784.969.124,57 - - 1.377,75 3.290.395.516,68 8,81 Bertambah
7.1 (5c) Beton struktur memadat sendiri, fc’30 Mpa M
3
119,90 264.441.368,40 0,71 - - - 119,90 264.441.368,40 0,71 Tetap
7.1 (5c) Beton struktur memadat sendiri, fc’30 Mpa (Harga Timpang) M
3
13,45 25.860.470,48 0,07 - - - - 13,45 25.860.470,48 0,07 Tetap
7.1 (8) Beton fc'15 Mpa M
3
448,00 696.550.848,00 1,86 - - 120,11 186.744.349,47 327,89 509.806.498,53 1,36 Berkurang
7.1 (8) Beton fc'15 Mpa (Harga Timpang) M
3
41,75 58.651.763,35 0,16 - - 36,63 51.451.182,57 5,13 7.200.580,78 0,02 Berkurang
7.1 (10) Beton fc'10 Mpa M
3
51,46 71.351.611,34 0,19 16,54 22.932.960,86 - - 68,00 94.284.572,20 0,25 Bertambah
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 13.130,45 254.428.652,96 0,68 - - - 13.130,45 254.428.652,96 0,68 Tetap
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg - - 12.424,26 213.728.372,34 - 12.424,26 213.728.372,34 0,57 Harga Timpang
7.3 (4) Baja Tulangan Sirip-BjTS 420B Kg 214.011,10 4.158.021.661,90 11,13 - 9.077,27 176.362.294,12 204.933,83 3.981.659.367,78 10,66 Berkurang
7.3 (4) Baja Tulangan Sirip-BjTS 420B (Harga Timpang) Kg 52.437,30 913.153.056,08 2,44 868,53 15.124.822,31 - 53.305,83 928.277.878,39 2,49 Harga Timpang
7.4.(3) Penyediaan Struktur Jembatan Rangka Baja Standart 60 m Kelas A Kg 183.750,00 5.545.575.000,00 14,85 - - - - 183.750,00 5.545.575.000,00 14,85 Tetap
7.4.(4) Pemasangan Jembatan Rangka Baja Standart Panjang 60 m Kg 183.750,00 547.942.500,00 1,47 - - - - 183.750,00 547.942.500,00 1,47 Tetap
7.6.(1) Fondasi Cerucuk, Penyediaan dan Pemancangan M' 510,00 45.042.180,00 0,12 - - - 510,00 45.042.180,00 0,12 Tetap
7.6.(1) Fondasi Cerucuk, Penyediaan dan Pemancangan (Harga Timpang) 30,00 2.139.932,10 0,01 252,00 17.975.429,64 282,00 20.115.361,74 0,05 Harga Timpang
7.6 (8c) Penyediaan Tiang Pancang Baja Diameter 600 mm tebal 12 mm M
1
1.536,00 4.779.489.792,00 12,80 - - - - 1.536,00 4.779.489.792,00 12,80 Tetap
7.6 (14b)a Pemancangan Tiang Pancang Baja Diameter 600 mm (Hanoli) M
1
924,00 422.799.300,00 1,13 - - - - 924,00 422.799.300,00 1,13 Tetap
7.6 (14b)b Pemancangan Tiang Pancang Baja Diameter 600 mm (salatena) M
1
612,00 291.051.900,00 0,78 - - - - 612,00 291.051.900,00 0,78 Tetap
7.9.(1) Pasangan Batu M
3
3.255,34 3.513.616.629,35 9,41 1.715,91 1.852.052.253,45 - - 4.971,26 5.365.668.882,80 14,36 Bertambah
7.9.(1) Pasangan Batu (harga Timpang) M
3
- - 58,90 54.174.857,93 - - 58,90 54.174.857,93 0,15 Bertambah
7.10.(2) Pasangan Batu Kosong M
3
198,32 129.826.955,20 0,35 90,96 59.548.727,39 - - 289,28 189.375.682,59 0,51 Bertambah
7.10.(3a) Bronjong dengan Kawat yang dilapisi Galvanis M
3
2.188,75 2.049.919.776,25 5,49 921,25 862.816.033,75 - - 3.110,00 2.912.735.810,00 7,80 Bertambah
7.11.(1a) Sambungan Siar Muai Tipe Asphaltic Plug, Fixed M
1
36,00 76.611.384,00 0,21 - - - - 36,00 76.611.384,00 0,21 Tetap
7.12.(3) Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran 400 mm x 300 mm x 52 mm Buah 16,00 12.580.992,00 0,03 - - - - 16,00 12.580.992,00 0,03 Tetap
7.13.(1) Sandaran (Railing) M
1 - 100,80 107.694.316,80 100,80 107.694.316,80 0,29 Item baru
7.14.(1) Papan Nama Jembatan Buah 8,00 10.543.200,00 0,03 2,00 2.635.800,00 - - 10,00 13.179.000,00 0,04 Bertambah
7.15 (1) Pembongkaran Pasangan Batu M
3
16,20 7.985.773,80 0,02 - - - 16,20 7.985.773,80 0,02 Tetap
7.15 (1) Pembongkaran Pasangan Batu (Harga Timpang) M
3
30,98 9.979.793,61 0,03 34,78 11.204.419,01 65,76 21.184.212,61 0,06 Bertambah
7.15 (7) Pembongkaran Lantai Jembatan Kayu M
2
30,00 5.502.450,00 0,01 - - - 30,00 5.502.450,00 0,01 Tetap
7.15 (7) Pembongkaran Lantai Jembatan Kayu (Harga Timpang) M
2
- - 37,50 4.303.078,13 - - 37,50 4.303.078,13 0,01 Bertambah
7.16.(1) Deck drain Buah 46,00 32.580.880,00 0,09 - - - 46,00 32.580.880,00 0,09 Tetap
7.16.(1) Deck drain (Harga Timpang) Buah - - 6,00 3.307.392,00 - - 6,00 3.307.392,00 0,01 Harga Timpang
7.16.(2a) Pipa Drainase Baja Diameter 1500 mm M
1
63,00 12.285.000,00 0,03 11,00 2.145.000,00 - - 74,00 14.430.000,00 0,04 Bertambah

Jumlah Harga DIVISI 7 26.443.359.262,93 70,79 4.014.612.588,18 414.557.826,16 30.043.414.024,95 80,43


Harga Satuan CC01 Pekerjaan Tambah Pekerjaan Kurang CCO-02
Keterangan Hasil
NO Uraian Kegiatan Original Harga Baru Satuan Jumlah Harga Bobot Jumlah harga Jumlah Harga Jumlah Harga Bobot CCO 02 Terhadap
Kuantitas Kuantitas Kuantitas Kuantitas CCO 01
(Rp.) (Rp.) (Rupiah) (%) (Rp.) (Rp.) (Rp.) (%)

a b c d e f g = (c x f) h i j k l m n o p

DIV. 9 PEKERJAAN HARIAN DAN PEKERJAAN LAIN-LAIN


9.2.(1) Marka Jalan Termoplastik M
2
904,01 358.761.616 0,96 - - 904,01 358.761.616,29 - - - Dihilangkan
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade Buah 16,00 19.291.568 0,05 - - - 16,00 19.291.568,00 0,05 Tetap
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade (Harga Timpang) 4,00 2.298.109,48 - - 4,00 2.298.109,48 0,01 Bertambah
9.2.(5) Patok Pengarah Buah 172,00 35.678.820 0,10 - - - 172,00 35.678.820,00 0,10 Tetap
9.2.(5) Patok Pengarah (Harga Timpang) 32,00 4.643.296,32 - - 32,00 4.643.296,32 0,01 Bertambah
9.2.(14) Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED Buah 14,00 404.265.316 1,08 - - - 14,00 404.265.316,00 1,08 Tetap
9.2.(14) Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED (Harga Timpang) Buah 2,00 31.242.158,44 - - 2,00 31.242.158,44 0,08 Bertambah
9.2.(14) Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED (Harga Timpang) Buah 4,00 63.182.756,84 - - 4,00 63.182.756,84 0,17 Bertambah
- - - - - -

Jumlah Harga DIVISI 9 817.997.320,29 2,19 101.366.321,08 358.761.616,29 560.602.025,08 1,50

A TOTAL 37.353.161.392,98 100,00 5.555.023.918,75 5.555.023.918,75 37.353.161.392,98 100,00


B PPN (10% x A) 3.735.316.139,30 555.502.391,87 555.502.391,87 3.735.316.139,30
C TOTAL BIAYA TERMASUK PPN (A + B) 41.088.477.532,27 6.110.526.310,62 6.110.526.310,62 41.088.477.532,27
D NILAI KONTRAK (Dibulatkan) 41.088.477.000,00 6.110.526.000,00 6.110.526.000,00 41.088.477.000,00

Disetujui oleh;,
PPK 2.3 PROVINSI.............
Diperiksa oleh; Dibuat oleh
PT. ................................. PT........................
.....

.............................................. ...................... ....................................


NIP. .Site Engineer General Superintendent
Satuan Kerja :

PPK :

Nama Paket :

No. Paket Kontrak :

Tanggal Kontrak :

DAFTAR KUANTITAS DAN HARGA


Harga Satuan CC0 02 2020 2021
NO Uraian Kegiatan Original Harga Baru Satuan Jumlah Harga Bobot Jumlah Harga Bobot Jumlah Harga Bobot
Kuantitas Kuantitas Kuantitas
(Rp.) (Rp.) (Rupiah) (%) (Rp.) (%) (Rp.) (%)
a b c e f g = (c x f) h m n o m n o
DIV. 1 UMUM
1.2 Mobilisasi LS 1,00 1.548.400.000,00 4,15 1,00 1.548.400.000,00 4,92 - -
1.8.(1) Manajemen dan Keselamatan Lalu Lintas LS 1,00 365.000.000,00 0,98 1,00 328.500.000,00 1,04 1,00 36.500.000,00 0,62
1.8.(2) Jembatan Sementara LS 1,00 582.811.800,60 1,56 1,00 582.811.800,60 1,85 - -
1.17.(1a) Pengujian pH Buah 36,00 18.000.000,00 0,05 36,00 18.000.000,00 0,06 - - -
1.17.(1a) Pengujian pH (Harga Timpang) Buah 9,00 1.935.000,00 0,01 4,50 967.500,00 0,00 4,50 967.500,00 0,02
1.17.(1b) Pengujian Oksigen Terlarut (DO) Buah 36,00 18.000.000,00 0,05 36,00 18.000.000,00 0,06 - - -
1.17.(1b) Pengujian Oksigen Terlarut (DO) (Harga Timpang) Buah 9,00 2.160.000,00 0,01 4,50 1.080.000,00 0,00 4,50 1.080.000,00 0,02
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) Buah 36,00 18.000.000,00 0,05 36,00 18.000.000,00 0,06 - - -
1.17.(1c) Pengujian Zat Padat Terlarut (TDS) (Harga Timpang) Buah 9,00 2.070.000,00 0,01 4,50 1.035.000,00 0,00 4,50 1.035.000,00 0,02
1.17.(1d) Pengujian Zat Tersuspensi (TSS) Buah 36,00 18.000.000,00 0,05 36,00 18.000.000,00 0,06 - - -
1.17.(1d) Pengujian Zat Tersuspensi (TSS) (Harga Timpang) Buah 9,00 2.070.000,00 0,01 4,50 1.035.000,00 0,00 4,50 1.035.000,00 0,02
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) Buah 36,00 18.000.000,00 0,05 36,00 18.000.000,00 0,06 - - -
1.17.(1e) Pengujian Biological Oxygen Demand (BOD) (Harga Timpang) Buah 9,00 2.205.000,00 0,01 4,50 1.102.500,00 0,00 4,50 1.102.500,00 0,02
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) Buah 36,00 18.000.000,00 0,05 36,00 18.000.000,00 0,06 - - -
1.17.(1f) Pengujian Chemical Oxygen Demand (COD) (Harga Timpang) Buah 9,00 2.745.000,00 0,01 4,50 1.372.500,00 0,00 4,50 1.372.500,00 0,02
1.17.(1g) Pengujian Coliform Buah 36,00 18.000.000,00 0,05 36,00 18.000.000,00 0,06 - - -
1.17.(1g) Pengujian Coliform (Harga Timpang) Buah 9,00 3.600.000,00 0,01 4,50 1.800.000,00 0,01 4,50 1.800.000,00 0,03
1.17.(1h) Pegujian E. Coli Buah 36,00 18.000.000,00 0,05 36,00 18.000.000,00 0,06 - - -
1.17.(1h) Pegujian E. Coli (Harga Timpang) Buah 9,00 2.952.000,00 0,01 4,50 1.476.000,00 0,00 4,50 1.476.000,00 0,03
1.17.(1i) Pengujian Destruksi Cu, Pb, Cd, Ni, Fe, Zn, Ag, Co, Mn Buah 45,00 22.500.000,00 0,06 40,50 20.250.000,00 0,06 4,50 2.250.000,00 0,04
1.17.(1j) Pengujian Temperatur (Suhu) Buah 36,00 18.000.000,00 0,05 36,00 18.000.000,00 0,06 - - -
1.17.(1j) Pengujian Temperatur (Suhu) (Harga Timpang) Buah 9,00 1.935.000,00 0,01 4,50 967.500,00 0,00 4,50 967.500,00 0,02
1.17.(1k) Pengujian Parameter Kualitas Air Lainnya Buah 36,00 18.000.000,00 0,05 36,00 18.000.000,00 0,06 - - -
1.17.(1k) Pengujian Parameter Kualitas Air Lainnya (Harga Timpang) Buah 9,00 1.935.000,00 0,01 4,50 967.500,00 0,00 4,50 967.500,00 0,02
1.17.(2a) Pengujian Vibrasi Lingkungan untuk Kenyamanan dan Kesehatan Buah 45,00 22.500.000,00 0,06 40,50 20.250.000,00 0,06 4,50 2.250.000,00 0,04
1.17.(2c) Pengujian Tingkat Getaran Kendaraan Bermotor Buah 45,00 22.500.000,00 0,06 40,50 20.250.000,00 0,06 4,50 2.250.000,00 0,04
1.17.(3a) Pengujian NoX Buah 36,00 18.000.000,00 0,05 36,00 18.000.000,00 0,06 - - -
1.17.(3a) Pengujian NoX (Harga Timpang) Buah 9,00 3.723.000,03 0,01 4,50 1.861.500,02 0,01 4,50 1.861.500,02 0,03
1.17.(3b) Pengujian Sulfurdioksida (SO2) Buah 45,00 22.500.000,00 0,06 40,50 20.250.000,00 0,06 4,50 2.250.000,00 0,04
1.17.(3f) Pengujian Total Partikulat (TSP) - Debu Buah 45,00 22.500.000,00 0,06 40,50 20.250.000,00 0,06 4,50 2.250.000,00 0,04
1.17.(3h) Pengujian Parameter Udara Emisi dan Ambien lainnya Buah 45,00 22.500.000,00 0,06 40,50 20.250.000,00 0,06 4,50 2.250.000,00 0,04
Harga Satuan CC0 02 2020 2021
NO Uraian Kegiatan Original Harga Baru Satuan Jumlah Harga Bobot Jumlah Harga Bobot Jumlah Harga Bobot
Kuantitas Kuantitas Kuantitas
(Rp.) (Rp.) (Rupiah) (%) (Rp.) (%) (Rp.) (%)
a b c e f g = (c x f) h m n o m n o

DIV. 3 PEKERJAAN TANAH DAN GEOSINTETIK


3.1.(1) Galian Biasa 3 3.256,63 0,43 3.256,63 160.782.994,07 0,51 -
M
3.1.(1) Galian Biasa (Harga Timpang) 3 4.682,90 0,39 4.682,90 153.027.683,50 0,49 -
M
3.1.(4) Galian Struktur dengan kedalaman 0 - 2 meter 3 748,80 0,18 748,80 68.451.888,29 0,22 - - -
M
3.1.(5) Galian Struktur dengan kedalaman 2 - 4 meter 3 662,99 0,23 662,99 85.379.085,01 0,27 - - -
M
3.2.(1a) Timbunan Biasa dari Sumber Galian 3 5.940,25 2,78 5.940,25 1.039.188.123,93 3,30 - - -
M
3.2.(1a) Timbunan Biasa dari Sumber Galian (Harga Timpang) 3 2.591,60 1,02 2.248,93 332.243.459,52 1,05 342,67 50.624.539,41 0,87
M
3.2.(1b) Timbunan biasa dari hasil galian 3 123,17 0,01 123,17 4.335.087,57 0,01 -
M
3.2(4) Penimbunan Kembali Berbutir (Granular Backfill) 3 1.695,62 1,49 1.031,06 338.732.075,41 1,08 664,56 218.328.210,32 3,73
M
3.4(1) Pembersihan dan Pengupasan Lahan 2 4.190,34 0,20 4.190,34 76.104.955,08 0,24 -
M
3.4.(2) Pemotongan Pohon Pilihan diameter 15-30 cm buah 5,00 0,00 5,00 758.150,00 0,00 -
3.4.(3) Pemotongan Pohon Pilihan diameter >30 - 50 cm buah 18,00 0,01 18,00 3.608.118,00 0,01 -
3.4.(3) Pemotongan Pohon Pilihan diameter >30 - 50 cm (Harga Timpang) buah 5,00 0,00 5,00 252.655,25 0,00 -
3.4(5) Pemotongan Pohon Pilihan diameter >75 cm buah 6,00 0,00 6,00 1.634.214,00 0,01 -

Jumlah Harga DIVISI 3 6,76 2.264.498.489,63 7,19 268.952.749,73 4,60

DIV. 5 PERKERASAN BERBUTIR DAN PERKERASAN BETON SEMEN


5.1.(1) Lapis Pondasi Agregat Kelas A 3 1.263,38 1,94 - 1.263,38 723.074.302,96 12,36
M

Jumlah Harga DIVISI 5 1,936 - - 723.074.302,96 12,36

DIV. 6 PERKERASAN ASPAL


6.1 (1) Lapis Resap Pengikat - Aspal Cair/Emulsi Liter - - - - -
6.1 (2a) Lapis Perekat - Aspal Cair/Emulsi Liter - - - - -
6.5.(1) Laston Lapis Aus Asbuton (AC-WC Asb) Ton - - - - -
6.5.(2) Laston Lapis Antara Asbuton (AC-BC Asb) Ton - - - - -

Jumlah Harga DIVISI 6 - - - - -

DIV. 7 STRUKTUR
7.1 (5a) Beton struktur fc’30 Mpa 3 1.377,75 8,81 1.274,55 3.043.935.303,55 9,66 103,20 246.460.213,13 4,21
M
7.1 (5c) Beton struktur memadat sendiri, fc’30 Mpa 3 119,90 0,71 119,90 264.441.368,40 0,84 -
M
7.1 (5c) Beton struktur memadat sendiri, fc’30 Mpa (Harga Timpang) 3 13,45 0,07 13,45 25.860.470,48 0,08 - -
M
7.1 (8) Beton fc'15 Mpa 3 327,89 1,36 - 327,89 509.806.498,53 8,71
M
7.1 (8) Beton fc'15 Mpa (Harga Timpang) 3 5,13 0,02 - - - 5,13 7.200.580,78 0,12
M
7.1 (10) Beton fc'10 Mpa 3 68,00 0,25 68,00 94.284.572,20 0,30 - - -
M
7.3 (1) Baja Tulangan Polos-BjTP 280 Kg 13.130,45 0,68 13.130,45 254.428.652,96 0,81 - - -
7.3 (1) Baja Tulangan Polos-BjTP 280 (Harga Timpang) Kg 12.424,26 0,57 10.306,16 177.291.728,13 0,56 2.118,10 36.436.644,21 0,62
7.3 (4) Baja Tulangan Sirip-BjTS 420B Kg 204.933,83 10,66 204.933,83 3.981.659.367,78 12,64 - - -
7.3 (4) Baja Tulangan Sirip-BjTS 420B (Harga Timpang) Kg 53.305,83 2,49 45.638,62 794.759.610,65 2,52 7.667,21 133.518.267,74 2,28
7.4.(3) Penyediaan Struktur Jembatan Rangka Baja Standart 60 m Kelas A Kg 183.750,00 14,85 183.750,00 5.545.575.000,00 17,60 - -
7.4.(4) Pemasangan Jembatan Rangka Baja Standart Panjang 60 m Kg 183.750,00 1,47 183.750,00 547.942.500,00 1,74 - -
7.6.(1) Fondasi Cerucuk, Penyediaan dan Pemancangan M' 510,00 0,12 510,00 45.042.180,00 0,14 - -
7.6.(1) Fondasi Cerucuk, Penyediaan dan Pemancangan (Harga Timpang) M' 282,00 0,05 282,00 20.115.361,74 0,06 - - -
7.6 (8c) Penyediaan Tiang Pancang Baja Diameter 600 mm tebal 12 mm 1 1.536,00 12,80 1.536,00 4.779.489.792,00 15,17 - -
M
7.6 (14b)a Pemancangan Tiang Pancang Baja Diameter 600 mm (Hanoli) 1 924,00 1,13 924,00 422.799.300,00 1,34 - -
M
Harga Satuan CC0 02 2020 2021
NO Uraian Kegiatan Original Harga Baru Satuan Jumlah Harga Bobot Jumlah Harga Bobot Jumlah Harga Bobot
Kuantitas Kuantitas Kuantitas
(Rp.) (Rp.) (Rupiah) (%) (Rp.) (%) (Rp.) (%)
a b c e f g = (c x f) h m n o m n o
7.10.(2) Pasangan Batu Kosong 3 289,28 0,51 289,28 189.375.682,59 0,60 - - -
M
7.10.(3a) Bronjong dengan Kawat yang dilapisi Galvanis 3 3.110,00 7,80 - - - 3.110,00 2.912.735.810,00 49,79
M
7.11.(1a) Sambungan Siar Muai Tipe Asphaltic Plug, Fixed 1 36,00 0,21 36,00 76.611.384,00 0,24 - - -
M
7.12.(3) Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran 400 mm x 300 m Buah 16,00 0,03 16,00 12.580.992,00 0,04 - - -
7.13.(1) Sandaran (Railing) M' 100,80 0,31 78,60 83.975.925,60 0,27 22,20 23.718.391,20 0,41
7.14.(1) Papan Nama Jembatan Buah 10,00 0,04 8,00 10.543.200,00 0,03 2,00 2.635.800,00 0,05
7.15 (1) Pembongkaran Pasangan Batu 3 16,20 0,02 16,20 7.985.773,80 0,03 - - -
M
7.15 (1) Pembongkaran Pasangan Batu (Harga Timpang) 3 65,76 0,06 65,76 21.184.212,61 0,07 - - -
M
7.15 (7) Pembongkaran Lantai Jembatan Kayu 2 30,00 0,01 30,00 5.502.450,00 0,02 - - -
M
7.15 (7) Pembongkaran Lantai Jembatan Kayu (Harga Timpang) 2 37,50 0,01 37,50 4.303.078,13 0,01 - - -
M
7.16.(1) Deck drain Buah 46,00 0,09 46,00 32.580.880,00 0,10 - - -
7.16.(1) Deck drain (Harga Timpang) Buah 6,00 0,01 - 6,00 3.307.392,00 0,06
7.16.(2a) Pipa Drainase Baja Diameter 1500 mm 1 74,00 0,04 68,00 13.260.000,00 0,04 6,00 1.170.000,00 0,02
M

Jumlah Harga DIVISI 7 80,45 25.872.881.782,49 82,13 4.170.532.242,47 71,29

DIV. 9 PEKERJAAN HARIAN DAN PEKERJAAN LAIN-LAIN


9.2.(1) Marka Jalan Termoplastik 2 - - - -
M
9.2.(3a) Rambu Jalan Tunggal dengan Permukaan Pemantul Engineering Grade Buah 16,00 0,05 - 16,00 19.291.568,00 0,33

9.2.(3a) (Harga Timpang) Buah 4,00


0,01 - 4,00 2.298.109,48 0,04

9.2.(5) Patok Pengarah Buah 172,00 0,10 - 172,00 35.678.820,00 0,61


9.2.(5) Patok Pengarah (Harga Timpang) Buah 32,00 0,01 - 32,00 4.643.296,32 0,08
9.2.(14) Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED Buah 14,00 1,08 - 14,00 404.265.316,00 6,91
Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED (Harga Timpang)
9.2.(14) Wai Yole 0,08 - 2,00 31.242.158,44 0,53
Buah 2,00
Unit lampu Penerangan Jalan Lengan Tunggal, Tipe LED (Harga Timpang)
9.2.(14) 0,17 - 4,00 63.182.756,84 1,08
Wai Salatena Buah 4,00
- -

Jumlah Harga DIVISI 9 1,50 - - 560.602.025,08 9,58

A TOTAL 100,00 31.502.727.272,73 100,00 5.850.434.120,25 100,00


B PPN (10% x A) 3.150.272.727,27 585.043.412,02
C TOTAL BIAYA TERMASUK PPN (A + B) 34.653.000.000,00 6.435.477.532,27
D NILAI KONTRAK (Dibulatkan) 34.653.000.000,00 6.435.477.000,00

Disetujui oleh Di periksa Oleh : Di buat Oleh


PPK..... Provinsi ............ PT. ................................ PT.....................

................................ ................................. ...................................


NIP : ...................... Supervision Engineer General Superintendent
LAPORAN BULANAN ....(..................) 2021
Pengawasan Teknis Jalan & Jembatan
......................................

3.15. Ringkasan Pengendalian Mutu

PT. Rosari Consultan 47


PT. Rosari Consultan 50
BAB. IV. KEGIATAN
KONSULTAN SUPERVISI
4.1. Daftar Personil Konsultan Supervisi
Kebutuhan Tenaga Ahli dan Tenaga Pendukung / Tenaga Penunjang untuk
Paket Pengawasan Teknik Jalan dan Jembatan ................................ pada
paket Penggantian Jembatan .............................. sebagai berikut :

a. Tenaga Ahli
1. Ketua Tim / Site Engineer
2. Quality Engineer
3. Quantity Engineer

b. Tenaga Pendukung
1. Inspector
2. Surveyor
3. Material & laboratorium Technician

c. Tenaga Penunjang
LAPORAN BULANAN 03 (............2021)
Pengawasan Teknis Jalan & Jembatan ..................................

4.2. Rencana dan Realisasi Penugasan Konsultan Supervisi

JADWAL PENUGASAN PERSONIL


Paket Pengawasan Teknis Jalan dan Jembatan di .......................

PT. Rosari Consultan 55


4.3. Struktur Organisasi Konsultan

Struktur Organisasi Konsultan Supervisi berdasarkan KAK Paket Pengawasan Teknik Jalan dan Jembatan ................
sebagai berikut :

Struktur Organisasi Konsultan


LAPORAN BULANAN 03 (.............2021)
Pengawasan Teknis Jalan & Jembatan .........................

4.4. Realisasi Kegiatan Pengawasan

Sesuai dengan surat mobilisasi dari Pejabat Pembuat Komitmen (PPK)


Pengawasan P2JN Provinsi Papua Barat Nomor ................. dimana aktifitas
Konsultan Supervisi dalam bulan ini yakni :
 Melaksanakan rapat kordinasi dengan PPK dan penyedia jasa terkait
pelaksanaan pekerjaan.
 Mengawasi pelaksanaan pengecoran beton struktur FC’30 Mpa.
 Mengawasi pelaksanaan pengecoran beton struktur FC’15 Mpa untuk
bahu jalan pada jembatan Wai Kapala dan Wai Masama.
 Melakukan pemerikasaan terhadap pekerjaan pembesian Baja
Tulangan Sirip dan Baja Tulangan Polos.
 Mengawasi dan menghitung volume pekerjaan pasangan batu.
 Mempelajari dan mendalami spesifikasi yang baru untuk penerapan
pelaksanaan pekerjaan dilapangan.
 Koordinasi internal dengan team supervis untuk pelaksanaan
pengawasan dilapangan agar dikemudian hari tidak terjadi kendala.
 Menyusun laporan Harian, Mingguan, Bulanan serta invoce .

4.5. Uraian Kegiatan di Laboratorium


Pekerjaan saat ini yang berkaitan dengan seluruh material, semua berpedoman
Desain Mix Formula (DMF) yang dibuat sebelumnya dan merupakan jaminan
Mutu beton itu sendiri, dan pengujian kuat tarik baja yang dilaksanakan
sebelum material di drop dilapangan dimana dalam hal ini konsultan hanya
mengwasinya agar tercapai mutu yang diharafkan sesuai dengan spesifikasi.

4.6. Uraian Kegiatan Lapangan


Adapun kegiatan Konsultan Supervisi adalah dimulai dari Mobilisasi dan
berakhir pada tahap Demobilisasi, dalam melakukan kegiatan sejenis,
berdasarkan pemahaman serta pengalaman konsultan, jika diberi suatu
kepercayaan akan melaksanakan kegiatan sesuai dengan jadwal diprogramkan
dari awal. Adapun jadwal yang disusun tidak memuat semua kegiatan

PT. Rosari Consultan 57


konsultan pada tahap pendahuluan, tahap konstruksi, tahap pelaporan hingga
berakhir masa layanan.
Adapun Kegiatan Lapangan Konsultan Supervisi sampai dengan bulan
November 2020 adalah sebagai berikut :
 Mengadakan rapat kordinasi di kantor direksi jembatan wai Hanoli
bersama PPK dan pelaksana.
 Mengarahkan pihak pelaksana agar setiap memulai suatu kegiatan
pekerjaan mengajukan requet sheet untuk memantau setiap pekerjaan
yang akan dilaksanakan agar bisa terkendali baik kuantitas maupun
kualitas.
 Melakukan pengawasan pekerjaan Gailian Biasa, Beton Struktur 30
Mpa, Agregat Klas A, Pemasangan Sandaran (Relling), Pemasangan
Patok Pengarah, di Jembatan Wai Salatena, Wai Kapala, Wai Hanoli
dan Wai Masama
 Koordinasi internal antar sesame ti.......................
 Mengarahkan pihak kontraktor agar bekerja sesuai dengan desain
yang ada dan memberikan masukan dalam hal pelaksanaan pekerjaan
dilapangan
 Menyiapkan laporan (bulan .................)
 Memantau cuaca di lokasi proyek yang dituang dalam laporan cuaca.

4.7. Uraian Kegiatan Kantor

Konsultan Supervisi mempunyai kantor sendiri dilapangan sesuai kontrak yang


diperuntukan untuk tempat merampung semua data fisik pekerjan yang
dikumpulkan oleh semua tim supervisi sesuai dengan job masing-masing pada
lokasi pekerjaan yang ada.
Tim supervisi yang dilakukan selama periode ............................. sebagai
berikut :
 Mengumpulkan semua data hasil pelaksanaan dilapangan untuk bahan
laporan.
 Memeriksa back up data kuantitas setiap pekerjaan yang telah
dilaksanakan
 Mengadakan rapat kordinasi internal setiap akhir pekan sebagai bahan
evaluasi pengawasan di lapangan
 Memproses laporan mingguan
 Membuat surat-surat instruksi lapangan
 Menyusun laporan bulanan dan laporan keuangan.
BAB. V. P E N U T U P
5.1. Kesimpulan
Hasil Progres pelaksanaan pekerjan Pembangunan Jembatan ...............pada
bulan ...............................sebagai berikut :
Rencana : .......%
Realisasasi : ...... %
Deviasi : .......%

5.2. Saran
 Pembagian tugas pelaksanaan di lapangan di lingkup internal pihak
kontraktor harus di tingkatkan agar pekerjaan bisa terlaksana dengan
baik.
 Kerjasama antara personil di lapangan baik di pihak kontraktor
pelaksana, Konsultan Supervisi maupun staf PU hendaknya tetap
membangun komunikasi dengan baik.
 Hendaknya selalu melakukan rapat-rapat rutin mingguan agar
rencana pencapaian target pekerjaan yang telah direncanakan dapat
di tindak lanjuti.

5.3. Rekomendasi
 Direkomendasi kepada seluruh personil kontraktor senantiasa
memakai APD di area proyek, sehingga harapan dari Sistem
Manajemen Keselamatan Kerja (SMK-3) dapat berfungsi sesuai
dengan tanggung jawabnya.
 Sehubungan dengan merebaknya berbagai penyakit saat ini
terkhusunya Desease Corona Virus 2019 (Covid-19) maka kami

PT. Rosari Consultan 60


merekomendasikan hendaknya selalu menjaga kebersihan di area
proyek dan selau menerapkan protokol kesehatan seperti memaikai
masker, mencuci tangan dan menjaga jarak.
LAMPIRAN
FORMAT LAMPIRAN PELAKSANAAN PADAT KARYA

Nama Paket :
Lokasi :
Nama Konsultan Pengawasan :
No. Kontrak :

NO PEKERJAAN YANG SATU VOLUME JUMLAH FOTO DOKUMENTASI


DIKERJAKAN AN PEKERJAAN TENAGA KERJA

2 i

8
LAPORAN CURAH HUJAN

Nama Paket :
Nama Kontraktor :
Nomor Kontrak Kontraktor :
Konsultan :
Nomor Kontrak Konsultan/ :

BULAN ......................2021
Jam TANGGAL

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

00.00 - 01.00
01.00 - 02.00
02.00 - 03.00
03.00 - 04.00
04.00 - 05.00
05.00 - 06.00
06.00 - 07.00
07.00 - 08.00
08.00 - 09.00
09.00 - 10.00
10.00 - 11.00
11.00 - 12.00
12.00 - 13.00
13.00 - 14.00
14.00 - 15.00
15.00 - 16.00
16.00 - 17.00
17.00 - 18.00
18.00 - 19.00
19.00 - 20.00
20.00 - 21.00
21.00 - 22.00
22.00 - 23.00
23.00 - 24.00

Keterangan
H = Hujan B = Berawan C = Cerah
Cuaca

. ...............................2021
Konsultan Supervisi
PT..................................

......................................
Inspector
SATKER :
PAKET :
KONTRAKTOR :
KONSULTAN :

FOTO –FOTO PELAKSANAAN

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA ;
SATKER :
PAKET :
KONTRAKTOR :
KONSULTAN :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA ;

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :
SATKER :
PAKET :
KONTRAKTOR :
KONSULTAN :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :
SATKER :
PAKET :
KONTRAKTOR :
KONSULTAN :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :
SATKER :
PAKET :
KONTRAKTOR :
KONSULTAN :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :
SATKER :
PAKET :
KONTRAKTOR :
KONSULTAN :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :
SATKER :
PAKET :
KONTRAKTOR :
KONSULTAN :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :
SATKER :
PAKET :
KONTRAKTOR :
KONSULTAN :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :
SATKER :
PAKET :
KONTRAKTOR :
KONSULTAN :

TANGGAL : PEKERJAAN : LOKASI :

KONDISI : STA :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :
SATKER :
PAKET :
KONTRAKTOR :
KONSULTAN :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :
SATKER : PERENCANAAN DAN PENGAWASAN JALAN NASIONAL PROPINSI MALUKU
PAKET : PEMBANGUNAN JEMBATAN WAI HANOLI CS
KONTRAKTOR : PT. RAJA BATU KIE RAHA PERKASA
KONSULTAN : PT. ROSARI CONSULTAN

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :

TANGGAL : PEKERJAAN : LOKASI :


KONDISI : STA :