1 Mandor hr 96,000.00
2 Tenaga hr 72,000.00
3 Kepala Tukang Batu hr 90,000.00
4 Tukang Batu hr 84,000.00
5 Pembantu Tukang Batu hr 72,000.00
6 Kepala Tukang Kayu hr 96,000.00
7 Tukang Pasang Keramik hr 90,000.00
8 Tukang Kayu Kasar hr 84,000.00
9 Tukang Kayu Halus hr 90,000.00
10 Pembantu Tukang Kayu hr 78,000.00
11 Kepala Tukang Besi hr 90,000.00
12 Tukang Besi hr 85,000.00
13 Pembantu Tukang Besi hr 72,000.00
14 Kepala Tukang Cat hr 90,000.00
15 Tukang Cat hr 85,000.00
16 Tukang Listrik hr 96,000.00
17 Tenaga (Pekerjaan Listrik) hr 78,000.00
18 Tukang Pipa hr 90,000.00
19 Tukang Gali Sumur hr 115,000.00
20 Kepala Tukang Aspal hr 90,000.00
21 Juru Godog hr 84,000.00
22 Juru Semprot hr 84,000.00
23 Mekanik Terlatih hr 96,000.00
24 Pembantu Mekanik hr 84,400.00
25 Operator Terlatih hr 96,000.00
26 Operator Semi Terlatih hr 90,000.00
27 Pembantu Operator hr 78,000.00
28 Pembantu Sopir hr 78,000.00
29 Sopir hr 90,000.00
30 Jaga Malam hr 72,000.00
31 Tenaga Kebersihan hr 72,000.00
32 Operator Alat Berat hr 96,000.00
33 Pembantu Operator hr 72,000.00
34 Tukang Bongkar hr 72,000.00
35 Pekerja Galian & Urug hr 72,000.00
36 Tukang Pipa Air Bersih hr 84,000.00
37 Pengawas / Ahli Teknik hr 119,500.00
38 Ahli ukur hr 114,000.00
39 Asisten ahli ukur hr 97,000.00
DAFTAR SATUAN KAYU DAN BARANG DARI KAYU
GLUGU
1 Usuk Kayu Glugu 5/7 1 m1
2 Balok Kayu Glugu 6/12 1 m1
3 Balok Kayu Glugu 8/14 1 m1
KRUING
1 Lis & Jalusi 1/3 1 m1
2 Lis & Jalusi 1/5 1 m1
3 Lis & Jalusi 2/4 1 m1
BENGKIRAI 1 m1
1 Papan Kayu 2/15
2 Papan Kayu 2/20 1 m1
3 Papan Kayu 2/25 1 m1
4 Papan Kayu 3/18 1 m1
5 Papan Kayu 3/20 1 m1
6 Papan Kayu 3/30 1 m1
MERANTI
1 Papan Kayu 2/15 1 m1
2 Papan Kayu 2/20 1 m1
3 Papan Kayu 2/25 1 m1
4 Papan Kayu 3/18 1 m1
5 Papan Kayu 3/20 1 m1
6 Papan Kayu 3/30 1 m1
KAMPER
1 Papan Kayu 2/15 1 m1
2 Papan Kayu 2/20 1 m1
3 Papan Kayu 2/25 1 m1
4 Papan Kayu 3/18 1 m1
5 Papan Kayu 3/20 1 m1
6 Papan Kayu 3/30 1 m1
KRUING
1 Papan Kayu 2/15 1 m1
2 Papan Kayu 2/20 1 m1
3 Papan Kayu 2/25 1 m1
4 Papan Kayu 3/18 1 m1
5 Papan Kayu 3/20 1 m1
6 Papan Kayu 3/30 1 m1
BENGKIRAI
1 Bingkai, Reng & Kaso 2/3 1 m1
2 Bingkai, Reng & Kaso 3/4 1 m1
3 Bingkai, Reng & Kaso 4/6 1 m1
4 Bingkai, Reng & Kaso 5/7 1 m1
KAMPER
1 Bingkai, Reng & Kaso 2/3 1 m1
2 Bingkai, Reng & Kaso 3/4 1 m1
3 Bingkai, Reng & Kaso 4/6 1 m1
4 Bingkai, Reng & Kaso 5/7 1 m1
MERANTI
1 Bingkai, Reng & Kaso 2/3 1 m1
2 Bingkai, Reng & Kaso 3/4 1 m1
3 Bingkai, Reng & Kaso 4/6 1 m1
4 Bingkai, Reng & Kaso 5/7 1 m1
KRUING
1 Bingkai, Reng & Kaso 2/3 1 m1
2 Bingkai, Reng & Kaso 3/4 1 m1
3 Bingkai, Reng & Kaso 4/6 1 m1
4 Bingkai, Reng & Kaso 5/7 1 m1
BENGKIRAI
1 Balok 6/8 1 m1
2 Balok 6/10 1 m1
3 Balok 6/12 1 m1
4 Balok 8/10 1 m1
5 Balok 8/12 1 m1
KAMPER
1 Balok 6/8 1 m1
2 Balok 6/10 1 m1
3 Balok 6/12 1 m1
4 Balok 8/10 1 m1
5 Balok 8/12 1 m1
MERANTI
1 Balok 6/8 1 m1
2 Balok 6/10 1 m1
3 Balok 6/12 1 m1
4 Balok 8/10 1 m1
5 Balok 8/12 1 m1
KRUING
1 Balok 6/8 1 m1
2 Balok 6/10 1 m1
3 Balok 6/12 1 m1
4 Balok 8/10 1 m1
5 Balok 8/12 1 m1
BALOK
1 Kayu Jati 1 m3
2 Kayu Bengkirai 1 m3
3 Kayu Meranti 1 m3
4 Kayu Kamper 1 m3
5 Kayu Kruing 1 m3
PAPAN
1 Kayu Jati 1 m3
2 Kayu Bengkirai 1 m3
3 Kayu Meranti 1 m3
4 Kayu Kamper 1 m3
5 Kayu Kruing 1 m3
NG DARI KAYU
29,030.00
72,576.00
112,896.00
5,400.00
7,800.00
12,300.00
29,700.00
42,300.00
55,500.00
59,898.11
60,750.00
97,200.00
14,652.00
22,500.00
28,800.00
33,000.00
36,355.93
43,956.00
27,720.00
33,600.00
46,200.00
49,896.00
55,440.00
83,160.00
23,400.00
32,100.00
40,125.00
43,335.00
48,150.00
72,225.00
3,513.33
8,520.00
20,190.00
29,860.00
5,702.40
11,404.80
22,809.60
33,264.00
2,930.00
5,860.80
11,721.60
17,094.00
3,465.96
6,937.92
14,940.00
21,600.00
43,200.00
58,500.00
62,100.00
72,000.00
85,280.00
45,619.20
57,024.00
68,428.80
76,032.00
85,250.00
23,443.20
29,304.00
40,500.00
45,173.08
52,250.00
27,751.68
34,689.60
48,000.00
53,315.70
60,930.00
15,102,586.12
12,700,000.00
4,440,000.00
8,640,000.00
5,260,000.00
13,150,000.00
11,160,000.00
5,040,000.00
10,200,000.00
5,760,000.00
DAFTAR HARGA FASILITAS LALU LINTAS JALAN
1 RAMBU JALAN
a Ukuran 45x45 cm bh
b Ukuran 60x60 cm bh
c Ukuran 75x75 cm bh
d Papan Tambahan bh
2 RPPJ
a Ukuran 105x140 cm bh
b Ukuran 120x120 cm bh
c Ukuran 120x180 cm bh
3 PAGAR PENGAMAN JALAN m1
4 MARKA JALAN m2
5 BAHAN MARKA JALAN
a Thermoplastik kg
b Glassbeads kg
c Cat Preimer kg
6 PAKU MARKA (ROADSTUD)
a Ukuran 2x10x10 cm bh
b Ukuran 2x10x12 cm bh
7 APILL
a Simpang Tiga (Dengan Lampu Pijar) unit
b Simpang Empat (Dengan Lampu Pijar) unit
c Simpang Tiga (Dengan Lampu LED) unit
d Simpang Empat (Dengan Lampu LED) unit
e Lampu Peringatan (Warning Light) unit
8 KOMPONEN APILL
a Box Lampu 3 Aspek Diameter 30 cm unit
b Box Lampu 3 Aspek Diameter 20 cm unit
c Box Lampu 2 Aspek Diameter 30 cm unit
d Box Lampu 2 Aspek Diameter 20 cm unit
e Fitting Mika bh
f Lampu Pijar Traffic Light bh
g Reflektor 30 cm bh
h Reflektor 20 cm bh
i Kaca Aspek 30 cm bh
j Kaca Aspek 20 cm bh
k Box Lampu LED 3 Aspek Diameter 20 cm bh
l Box Lampu LED 2,5 Aspek Diameter 20 cm bh
m Tiang Pendek bh
n Tiang Overhead bh
o Box Control bh
p Count Down Timer bh
q Pengeboran Horizontal Untuk Instalasi APILL m1
9 PATOK TIKUNGAN (DELINIATOR)
a bahan Pipa Plastik bh
b Bahan Pipa Besi bh
10 CERMIN TIKUNGAN unit
11 KERUCUT LALU LINTAS
a Ukuran 90 cm bh
b Ukuran 75 cm bh
c Ukuran 60 cm bh
12 SENTER LALULINTAS bh
13 APLIKASI MARKA bh
14 PLAT UJI KENDARAAN BERMOTOR keping
15 BUKU UJI KENDARAAN BERMOTOR bh
16 STIKER TANDA SAMPING KENDARAAN BERMOTOR pasang
NTAS JALAN
541,200.00
726,000.00
871,200.00
165,000.00 ukuran 20x50 cm
2,970,000.00
4,950,000.00
8,580,000.00
1,254,000.00
132,000.00 sudah termasuk glassbeads
51,800.00
64,800.00
54,000.00
296,200.00
307,000.00
180,180,000.00
252,252,000.00
247,500,000.00
330,000,000.00
33,000,000.00 satu lengan
5,270,200.00
2,594,500.00
3,513,500.00
1,729,700.00
99,000.00
90,000.00
297,200.00
178,375.00
475,675.00
297,200.00
9,900,000.00
7,260,000.00
2,640,000.00
4,620,000.00
39,600,000.00 merk Qumicom
29,040,000.00 lengkap dengan tiang
231,000.00
505,945.00
380,540.00
5,945,940.00 diameter 1 m
499,400.00
463,700.00
440,000.00
396,000.00
39,600,000.00
3,630.00
9,900.00
12,540.00
ALAT-ALAT LISTRIK/PENERANGAN JALAN UMUM
B LAMPU HIAS
1 Lampu Anggur isi 100 pcs 87,120
2 Lampu Anggur isi 140 pcs 102,000
3 Lampu Capsul isi 100 pcs 107,400
4 Lampu Capsul isi 140 pcs 288,000
5 Lampu Rice Light 10m pcs 102,000
6 Lampu Rice Light isi 100 pcs 80,400
7 Lampu Rice Light isi 140 pcs 96,000
8 Lampu Slang 2 Jalur (sekualitas Sinyoku) roll 3,105,000
9 Lampu Slang 3 Jalur (sekualitas Sinyoku) roll 3,591,000
10 Lampu Tirai 2 x 2 m bh 648,000
11 LH - Butterfly Lamp (DC-009) pcs 23,558,400
12 LH - Christmast Lamp (DC-008) pcs 18,124,800
13 LH - Cottonrose Lamp (DC-004) pcs 21,645,600
14 LH - Double Piled Fountain Lamp (DC-019) pcs 21,647,400
15 LH - Dragon Flying Lamp (DC-016) pcs 18,622,800
16 LH - Dragon Phoenix (DC-013) pcs 20,655,000
17 LH - Fireworks Lamp (DC-001) 6 m pcs 19,658,400
18 LH - Fireworks Lamp (DC-001) 8 m pcs 22,072,800
19 LH - Floor Lamp (DC-017) pcs 14,107,200
20 LH - Flower Pot Lamp (DC-020+B47) pcs 22,146,600
21 LH - Fountain Lamp (DC-014) pcs 20,655,000
22 LH - Fountain Lamp Ball (DC-006) pcs 18,360,000
23 LH - Hepla Lamp (DC-011) unit 20,655,600
24 LH - Logo Kota Besar unit 13,500,000
25 LH - Logo Kota Sedang pcs 7,425,000
26 LH - Lucky Lamp (DC-005) pcs 16,618,800
27 LH - No. 1 Lamp (DC-010) pcs 21,141,000
28 LH - Octopus Lamp (DC-018) unit 20,641,000
29 LH - Ornament Lingkungan 2D unit 7,415,000
30 LH - Ornament Lingkungan 3D pcs 13,500,000
31 LH - Redbud Flower Lamp (DC-015) pcs 21,398,400
32 LH - Seplendiel Lamp (DC-002) pcs 22,149,000
33 LH - Star Flower Lamp (DC-007) pcs 20,655,000
34 LH - Windmill Lamp (DC-003) pcs 21,648,000
C BALAST / TRAVO
1 Mercury / HPL 80W 220V bh 128,000
2 Mercury / HPL 125W 220V bh 156,000
3 Mercury / HPL 250W 220V bh 186,000
4 Mercury / HPL 400W 220V bh 203,500
5 Metal Halide 70W 220V bh 162,000
6 Metal Halide 100W 220V bh 201,000
7 Metal Halide 150W 220V bh 231,000
8 Metal Halide 250W 220V bh 341,000
9 Metal Halide 400W 220V bh 505,750
10 Metal Halide 1000W 220V bh 505,750
11 SON 70W 220V bh 156,000
12 SON 150W 220V bh 235,000
13 SON 250W 220V bh 285,000
14 SON 400W 220V bh 516,000
15 SON 1000W 220V bh 1,764,000
16 Dimming SON / HPS T PIA 250W 220V bh 390,000
17 Dimming SON / HPS T PIA 400W 220V bh 760,000
18 Dimming SON / HPS T PIA 1000W 220V bh 2,458,000
19 TL 20W bh 43,680
20 TL 40W bh 52,000
E KAPASITOR
1 Kapasitor 4 µf bh 35,000
2 Kapasitor 8 µf bh 47,291
2 Kapasitor 12 µf bh 55,000
3 Kapasitor 18.O µf bh 62,000
4 Kapasitor 30.O µf bh 74,167
5 Kapasitor 32.O µf bh 89,000
6 Kapasitor Metal Halide 70W 220V bh 93,000
7 Kapasitor Metal Halide 100W 220V bh 88,200
8 Kapasitor Metal Halide 150W 220V bh 96,000
9 Kapasitor Metal Halide 250W 220V bh 132,000
10 Kapasitor Bank 5500 bh 780,000
11 Kapasitor Bank 7700 bh 990,000
G FITTING
1 Fitting Duduk Lampu 125W bh 18,000
2 Fitting Duduk Lampu 250W bh 38,000
3 Fitting TL 20W bh 6,600
4 Fitting TL 40W bh 6,600
5 Fitting Lampu PLL bh 8,160
6 Fitting Sport Par 38 (1) Oog bh 168,000
7 Fitting Sport Duduk bh 190,000
8 Fitting Sport Taman bh 190,000
H ARMATURE
1 Kap HP 400 unit 900,000
2 Kap HP 125 unit 630,000
3 Kotak Sorot Kosong, Philips unit 2,066,400
4 EKOROLA TRX800 118 IC / TLD 18W unit 600,000
5 EKOROLA TRX800 136 IC PLL unit 660,000
6 IP 65 Komplit (Kualitas SGP 328 SON 150) unit 3,891,300
7 IP 65 Komplit (Kualitas SGP 328 SON 250) unit 4,177,800
8 IP 65 Komplit (Kualitas SGP 810 SON 70) unit 3,254,760
9 IP 65 Komplit (Kualitas SGP 882 SON 150) unit 4,542,000
10 IP 65 Komplit (Kualitas SGP 882 SON 250) unit 4,718,400
11 SRP810 IXSON-T 100W BG unit 2,991,840
12 SRP810 IXSON-T 100W BG GREY unit 3,116,520
13 SRP810 IXSON-T 150W BG unit 2,991,840
14 SRP810 IXSON-T 150W BG GREY unit 3,401,400
15 SRP810 IXSON-T 70W BG unit 2,732,400
16 SSP 328 SON-T 150W unit 3,600,000
17 SSP 368 SON-T 250W unit 3,960,000
18 Spectrum MPP368 IXHPI-T 250W BG SILVER unit 3,492,000
19 Spectrum MPP368 IXSON-T 150W BG SILVER unit 3,600,000
20 Spectrum MPP368 IXSON-T 250W BG SILVER unit 3,750,000
21 Spectrum MPP368 IXSON-T 250W BG SILVER DMMI unit 4,140,000
22 Spectrum SSP368 IXSON-T 400W BG SILVER unit 4,502,400
23 Spectrum SSP368 IXSON-T 600W BG SILVER unit 5,280,000
24 Tango MMF 383 1 x HPI-T 250W ASYMMETRIC unit 2,303,100
25 Tango MMF 383 1 x HPI-T 250W SYMMETRIC unit 2,303,100
26 Tango MMF 383 1 x HPI-T 400W ASYMMETRIC unit 2,443,200
27 Tango MMF 383 1 x HPI-T 400W SYMMETRIC unit 2,443,200
28 Tango MMF 283 1 x MHN-TD 150W SYMMETRIC unit 2,419,200
29 Tango MMF 283 1 x MHN-TD 70W SYMMETRIC unit 2,275,200
30 Tango SMF 383 1 x HPI-T 250W SYMMETRIC unit 2,880,000
31 Tango SMF 383 1 x HPI-T 400W SYMMETRIC unit 2,880,000
32 Tango SMF 383 1 x SON-T 150W SYMMETRIC unit 2,619,000
33 Tango SMF 383 1 x SON-T 250W SYMMETRIC unit 2,880,000
34 Tango SMF 383 1 x SON-T 400W SYMMETRIC unit 3,600,000
35 Tango SMF 283 1 x SON PLUS 150W SYMMETRIC unit 2,310,000
36 Tango SMF 283 1 x SON PLUS 70W SYMMETRIC unit 2,160,000
37 Tango SMF 383 1 x HPI-T 250W ASYMMETRIC unit 2,880,000
38 Tango SMF 383 1 x HPI-T 400W ASYMMETRIC unit 2,880,000
39 Tango SMF 383 1 x SON-T 250W ASYMMETRIC unit 2,880,000
40 Tango SMF 383 1 x SON-T 400W ASYMMETRIC unit 3,600,000
41 Broadway MGP268/ 1XHPI-T 250W unit 4,347,600
42 Broadway MGP268/ 1XHPI-T 400W unit 4,588,800
43 Broadway SGP268/ 1XSON-T 150W unit 4,434,000
44 Broadway SGP268/ 1XSON-T 250W unit 4,635,600
45 Broadway SGP268/ 1XSON-T 400W unit 5,334,000
46 con Tempo RVP250 MHN-TD 150W IC 220V-50HZ S Sp unit 1,728,000
47 con Tempo RVP250 MHN-TD 70W IC 220V-50HZ S Sp unit 1,627,200
48 con Tempo RVP250 SON-T 150W IC 220V-50HZ A Sp unit 1,590,000
49 con Tempo RVP250 SON-T 70W IC 220V-50HZ A Sp unit 1,344,000
50 con Tempo RVP250 SON-TD 150W IC 220V-50HZ S Sp unit 1,584,000
51 con Tempo RVP250 SON-TD 70W IC 220V-50HZ S Sp unit 1,344,000
52 con Tempo RVP350 HPI-T 250W IC 220V-50HZ A Sp unit 1,800,000
53 con Tempo RVP350 HPI-T 250W IC 220V-50HZ S Sp unit 1,800,000
54 con Tempo RVP350 HPI-T 400W IC 220V-50HZ A Sp unit 2,016,000
55 con Tempo RVP350 HPI-T 400W IC 220V-50HZ S Sp unit 2,016,000
56 con Tempo RVP350 SON-T 250W IC 220V-50HZ A Sp unit 1,814,400
57 con Tempo RVP350 SON-T 250W IC 220V-50HZ S Sp unit 1,814,400
58 con Tempo RVP350 SON-T 400W IC 220V-50HZ A Sp unit 2,310,000
59 con Tempo RVP350 SON-T 400W IC 220V-50HZ S Sp unit 2,310,000
60 Velo City MPG328 1XHPI-T 250W unit 4,148,400
61 Velo City MPG328 1XHPI-T 250W BLUE unit 4,247,400
62 Velo City MPG328 1XHPI-T 250W GREY unit 4,247,400
63 Velo City MPG338 1XHPI-T 250W unit 4,582,200
64 Velo City MPG338 1XHPI-T 250W GREY unit 4,720,800
65 Velo City MPG338 1XHPI-T 400W unit 5,058,000
66 Velo City MPG338 1XHPI-T 400W BLUE unit 5,196,600
67 Velo City MPG338 1XHPI-T 400W GREY unit 5,196,600
68 Velo City SGP338 1XSON-T 250W unit 4,594,800
69 Velo City SGP338 1XSON-T 250W GREY unit 4,733,400
70 Velo City SGP338 1XSON-T 400W unit 5,428,200
71 Velo City SGP338 1XSON-T 400W GREY unit 5,566,800
72 Velo City SGP328 1XSON-T 70W unit 3,442,800
73 Velo City SGP328 1XSON-T 70W GREY unit 3,542,400
74 Velo City SGP328 1XSON-T 100W GREY unit 3,839,400
75 Velo City SGP328 1XSON-T 150W unit 3,978,000
76 Velo City SGP328 1XSON-T 150W GREY unit 4,066,800
77 Velo City SGP328 1XSON-T 250W unit 4,208,400
78 Velo City SGP328 1XSON-T 250W unit 4,308,000
I AKSESORIS JARINGAN
1 Kabel Skun 6 mm s/d 16 mm bh 3,900
2 BC 6 mm bh 10,500
3 Cover MCB bh 7,800
4 Ground Road bh 4,200
5 Service Link dan Clamp bh 6,000
6 Stenles Stell 0,70 x 20 bh 8,260
7 Stoping Buckle bh 3,120
8 Terminal Kabel bh 31,800
9 Wadge Type / Service Wedge Clamp bh 9,000
10 Alqua / Taping Conector bh 9,000
11 Terminal Nol bh 30,000
12 Kondoit bh 18,240
13 Rel MCB btg 27,600
14 Beugel Ø5" x Ø2" ps 60,000
J BOX PANEL
1 Box MCB plastik bh 10,200
2 Box Panel 10 x 10 x15 bh 7,800
3 Box Panel 20 x 15 x 10 bh 78,000
4 Box Panel 20 x 40 x 50 bh 480,000
5 Box Panel 25 x 25 x 12 bh 174,000
6 Box Panel 25 x 25 x 20 bh 225,000
7 Box Panel 30 x 40 x 15 bh 237,600
8 Box Panel 30 x 40 x 20 bh 378,000
9 Box Panel KWH Meter 20 x 40 x 50 bh 870,000
10 Box Panel KWH Meter 20 x 40 x 60 bh 1,020,000
11 Box Panel KWH Meter 25 x 35 x 20 bh 870,000
12 Box Panel KWH Meter 25 x 40 x703 bh 1,536,000
13 Tutup Panel 30 x 30 bh 81,000
K KABEL
1 Kabel DX 2 x 10 Sqmm /m 9,720
2 Kabel DX 2 x 16 Sqmm /m 12,360
3 Kabel DX 2 x 25 Sqmm /m 30,600
4 Kabel NYA 1 x 1,5 Sqmm (panjang 50m) rol 210,000
5 Kabel NYA 1 x 2,5 Sqmm (panjang 50m) rol 345,000
6 Kabel NYFG by 3 x 4 Sqmm sekualitas Eterna /m 4,320
7 Kabel NYFG by 3 x 6 Sqmm sekualitas Eterna /m 63,000
8 Kabel NYFG by 3 x 10 Sqmm sekualitas Supreme /m 76,800
9 Kabel NYFG by 4 x 6 Sqmm sekualitas Eterna /m 67,800
10 Kabel NYFG by 4 x 10 Sqmm sekualitas Supreme /m 100,800
11 Kabel NYM 2 x 1,5 Sqmm sekualitas Supreme (panjang 50m) rol 468,000
12 Kabel NYM 2 x 2,5 Sqmm sekualitas Supreme (panjang 50m) rol 835,200
13 Kabel NYM 2 x 4 Sqmm sekualitas Supreme (panjang 50m) rol 1,020,000
14 Kabel NYM 3 x 1,5 Sqmm sekualitas Supreme (panjang 50m) rol 624,000
15 Kabel NYM 3 x 2,5 Sqmm sekualitas Supreme (panjang 50m) rol 1,126,800
16 Kabel NYM 3 x 4 Sqmm sekualitas Supreme (panjang 50m) rol 1,290,000
17 Kabel NYY 2 x 2,5 Sqmm sekualitas Supreme (panjang 50m) rol 690,000
18 Kabel NYY 2 x 4 Sqmm sekualitas Supreme /m 23,100
19 Kabel NYY 3 x 1,5 Sqmm sekualitas Supreme /m 15,600
20 Kabel NYY 3 x 2,5 Sqmm sekualitas Supreme /m 24,000
21 Kabel NYY 3 x 4 Sqmm sekualitas Supreme /m 30,600
22 Kabel NYY 3 x 6 Sqmm sekualitas Supreme /m 39,000
23 Kabel NYY 3 x 10 Sqmm sekualitas Supreme /m 62,400
24 Kabel NYY 4 x 6 Sqmm sekualitas Supreme /m 51,000
25 Kabel NYY 4 x 10 Sqmm sekualitas Supreme /m 82,200
26 Kabel Twisted NFA2X 2 x 10 Sqmm /m 9,720
27 Kabel Twisted NFA2X 2 x 16 Sqmm /m 12,360
L STANG LAMPU
1 Stang Ornament GIP Ø 1,1" L= 3 m btg 225,600
2 Stang Ornament GIP Ø 2" L= 1 m btg 120,000
3 Stang Ornament GIP Ø 2" L= 2 m btg 264,000
4 Stang Ornament GIP Ø 2" L= 2,2 m btg 258,000
5 Stang Ornament GIP Ø 2" L= 3 m btg 278,400
6 Stang Ornament GIP Ø 2" L= 4 m btg 294,000
7 Stang Ornament GIP Ø 2" L= 6 m btg 432,000
M TIANG
1 Tiang Galvanis Cb. 1, t= 5 m, tanam Ø 2" btg 927,600
2 Tiang Galvanis Cb. 1, t= 6 m, base plate btg 342,400
3 Tiang Galvanis Cb. 1, t= 7 m, base plate btg 3,578,400
4 Tiang Galvanis Cb. 1, t= 9 m, base plate btg 4,860,000
5 Tiang Galvanis Cb. 1, t= 11 m, base plate btg 5,738,400
6 Tiang Galvanis Cb. 2, t= 6 m, base plate btg 3,598,800
7 Tiang Galvanis Cb. 2, t= 9 m, base plate btg 4,125,000
8 Tiang Galvanis Cb. 1, t= 6 m, base plate btg 2,160,000
9 Tiang Galvanis Cb. 1, t= 6 m, base plate btg 2,520,000
10 Tiang Lampu Highmask Cb. 2, t= 20 m, hidrolik btg 182,250,000
11 Tiang Lampu Highmask Cb. 4, t= 20 m, hidrolik btg 182,250,000
12 Tiang Lampu Manggis Cb. 1, t= 2 m btg 2,397,600
13 Tiang Lampu Manggis Cb. 1, t= 4 m btg 3,692,400
14 Tiang Lampu Octagonal Cb. 1, t= 6 m btg 2,763,600
15 Tiang Lampu Octagonal Cb. 1, t= 7 m btg 3,250,800
16 Tiang Lampu Octagonal Cb. 1, t= 8 m btg 3,780,000
17 Tiang Lampu Octagonal Cb. 1, t= 9 m btg 4,998,600
18 Tiang Lampu Octagonal Cb. 1, t= 10 m btg 5,212,800
19 Tiang Lampu Octagonal Cb. 1, t= 11 m btg 5,448,000
20 Tiang Lampu Octagonal Cb. 1, t= 12 m btg 6,160,200
21 Tiang Lampu Octagonal Cb. 1, t= 13 m btg 6,756,000
22 Tiang Lampu Octagonal Cb. 1, t= 14 m btg 7,446,000
23 Tiang Lampu Octagonal Cb. 1, t= 15 m btg 8,044,800
24 Tiang Lampu Octagonal Cb. 2, 90ᴼ t= 9 m btg 6,621,600
25 Tiang Lampu Octagonal Cb. 2, 90ᴼ t= 11 m btg 7,730,400
26 Tiang Lampu Octagonal Cb. 2, 180ᴼ t= 9 m btg 6,621,600
27 Tiang Lampu Octagonal Cb. 2, 180ᴼ t= 11 m btg 7,730,400
28 Tiang Lampu Octagonal Cb. 2, 90ᴼ / 180ᴼ, t= 6 m btg 3,328,800
29 Tiang Lampu Octagonal Cb. 2, 90ᴼ / 180ᴼ, t= 7 m btg 3,918,000
30 Tiang Lampu Octagonal Cb. 2, 90ᴼ / 180ᴼ, t= 8 m btg 4,621,200
31 Tiang Lampu Octagonal Cb. 2, 90ᴼ / 180ᴼ, t= 10 m btg 6,942,000
32 Tiang Lampu Octagonal Cb. 2, 90ᴼ / 180ᴼ, t= 12 m btg 7,945,200
33 Tiang Lampu Octagonal Cb. 2, 90ᴼ / 180ᴼ, t= 13 m btg 8,100,000
34 Tiang Lampu Octagonal Cb. 2, 90ᴼ / 180ᴼ, t= 14 m btg 8,550,000
35 Tiang Lampu Octagonal Cb. 2, 90ᴼ / 180ᴼ, t= 15 m btg 9,019,200
36 Tiang Lampu Antik Cb. 1, t= 2 m btg 3,480,000
37 Tiang Lampu Antik Cb. 2, t= 2 m btg 3,480,000
38 Tiang Lampu Antik Cb. 3, t= 2 m btg 4,200,000
N SAKELAR
1 Sakelar TPDT 30A bh 60,000
2 Sakelar Engkel IB bh 14,160
3 Sakelar Engkel Ob bh 14,880
4 Sakelar Seri IB bh 17,100
5 Sakelar Seri OB bh 23,640
6 Stop Kontak IB bh 15,900
7 Stop Kontak OB bh 16,500
8 Tusuk Kontak 2Kutub dengan pembumian/arde bh 5,400
9 Tusuk Kontak 2Kutub dengan pembumian/arde (tanam) bh 8,820
10 Tusuk Kontak 2Kutub dengan pembumian/arde (timbul) bh 8,100
11 Tusuk Kontak 2Kutub tanpa pembumian/arde bh 8,820
12 Tusuk Kontak 2Kutub tanpa pembumian/arde (tanam) bh 10,140
13 Tusuk Kontak 2Kutub tanpa pembumian/arde (timbul) bh 43,920
14 Tusuk Kontak hubungan bagi dengan selengkup isolasi 1 Fasa bh 30,480
250V/6A (timbul)
15 Tusuk Kontak hubungan bagi dengan selengkup isolasi 1 Fasa bh 40,500
250V/10A (timbul)
16 Tusuk Kontak hubungan bagi dengan selengkup isolasi 1 Fasa bh 50,760
250V/6A (tanam)
17 Tusuk Kontak hubungan bagi dengan selengkup isolasi 1 Fasa bh 50,760
250V/10A (tanam)
O FLASHER
1 Flasher Lampu Hias Kipas bh 3,900,000
2 Flasher Lampu Hias Buterfly bh 3,900,000
3 Flasher Lampu Hias Kembang Api Besar bh 3,900,000
4 Flasher Lampu Hias Kembang Api Kecil bh 3,900,000
P PERALATAN
1 Betel bh 26,400
2 Betel Mokuba bh 66,600
3 Box Tool Kit bh 420,000
4 daunGergaji Besi bh 21,000
5 Tool Kit Listrik unit 3,900,000
6 Tool Kit Bengkel unit 3,180,000
7 Sengkang Gergaji bh 105,600
8 Isosali bh 8,400
9 Kunci Inggris bh 81,000
10 Kunci ring pas (set) set 270,000
11 Kunci Pas (set) set 198,000
12 Kunci L besar bh 84,000
13 Kunci T 8,10,12 bh 34,200
14 Linggis besar btg 180,000
15 Mata Bor Besi set 132,000
16 Mata bor Beton set 450,000
17 Mata Bor Beton 12 mm bh 45,600
18 Mata Bor Pipa Ø 20 mm bh 51,000
19 Mesin Bor Tangan Bosch 10 GMB RZ bh 1,662,000
20 Mesin Gerinda bh 1,170,000
21 Obeng +/- set 91,200
22 Obeng Minus set 91,200
23 Obeng Plus set 91,200
24 Obeng Tespen biasa bh 12,600
25 Obeng Tespen Sinyal bh 31,800
26 Palu Besi Bulat 1LB Kecil bh 28,200
27 Palu Besi Bulat 2 11/2 LB Besar bh 43,200
28 Palu Besi New Zealand 11/2 LB besar bh 34,200
29 Pengupas Kabel (Wire Striper Sellert) bh 54,000
30 Sabuk Pengaman bh 3,510,000
31 Kaos Tangan Kulit ps 81,000
32 Helm Pengaman bh 66,000
33 Rool Kabel 50 m bh 1,500,000
34 Rool Kabel 25 m bh 780,000
35 Senter 4 baterai bh 390,000
36 Stabilizer 500 VA unit 3,900,000
37 Tang Buaya bh 63,000
38 Tang Kombinasi bh 60,000
39 Tang Potong bh 54,000
40 Tang Lancip bh 54,000
41 Tang Skoon / Lopster 1-16 mm bh 558,000
42 Tangga Lipat t= 3 m bh 2,028,000
43 Tangga Sorong 2 x 3 meter (alumunium model PLN) bh 3,900,000
44 Tangga Sorong 2 x 6 meter (alumunium model PLN) bh 7,620,000
45 Tangga Sorong 2 x 3 meter (Fiberglas model PLN) bh 9,000,000
46 Tangga Sorong 2 x 6 meter (Fiberglas model PLN) bh 17,280,000
47 Tracker Kabel DX bh 1,500,000
48 Tracker Plat Janur bh 1,186,200
49 Clamp Skun bh 390,000
Q ALAT UKUR
1 Lux Meter Digital bh 3,206,400
2 Meteran Analog bh 1,958,400
3 Meteran Bulat Essen 5 m bh 18,000
4 Multitester Analog sekualitas Sanwa bh 225,600
5 Muultitester Digital sekualitas Sanwa Japan bh 1,098,000
6 Tang Amper Digital sekualitas Kyoritsu japan bh 1,173,600
7 Marger Test bh 1,056,000
R TALI
1 Kabel Ties 10 cm pcs 18,600
2 Kabel Ties 15 cm pcs 26,400
3 Kabel Ties 20 cm pcs 31,200
4 Kabel Ties 25 cm pcs 37,800
5 Tali Kabel Plister roll 45,000
HARGA SATUAN ( Rp. )
No. MACAM BAHAN SATUAN
UD. SINAR LEMATANGTB. PULUNG
1 2 3 4
PORTANLD SEMEN ( PC )
1 Portland semen ( PC 40 Kg ) 1 zak 36,000.00 38,000.00
2 PC Warna 1 kg 11,000.00 12,000.00
3 PC Putih 1 kg 3,000.00 4,000.00
JENIS BETON
1 Buis beton Ø 25 cm 1 bh
2 Buis beton 1/2 Ø 25 cm 1 bh
3 Buis beton Ø 80 cm 1 bh
4 Batako 10x20x40 cm 1 bh
5 Roster beton 20x20 cm 1 bh
6 Beton conblok warna tebal 6 cm K-175 1 m2
7 Beton conblok warna tebal 8 cm K-200 1 m2
8 Beton conblok natural tebal 6 cm K-175 1 m2
9 Beton conblok natural tebal 8 cm K-200 1 m2
JENIS BESI
1 Besi beton polos 1 kg
2 Besi beton ulir 1 kg
3 Bendrat ( kawat beton ) 1 kg 20,000.00 20,000.00
4 Baut, Mur 1 kg 6,000.00 6,500.00
5 Paku eternite 1 kg 25,000.00 28,000.00
6 Paku reng 1 kg 15,000.00 15,500.00
7 Paku usuk 1 kg 14,000.00 14,500.00
8 Paku scrup gypsum 1 bh 250.00 250.00
9 Seng plate lebar 60 cm BJLS 30 1 m' 21,000.00 28,000.00
10 Seng plate lebar 90 cm BJLS 30 1 m' 29,000.00 36,000.00
11 Scafolding ( sewa ) 1 unit
12 Kuda-kuda baja ringan zinkalum 1 m2
13 Hollow metal furing 4x4 cm 1 m' 23,500.00
JENIS KAYU
BENGKIRAI
1 Balok 8x12x4 m 400,000.00
2 Balok 8x12x3 m 300,000.00
3 Balok 6x12x4 m 300,000.00
4 Balok 6x12x3 m 225,000.00
5 Balok 6x10x4 m 250,000.00
6 Balok 6x10x3 m 190,000.00
KAMPER
1 Balok 8x12x4 m 315,000.00
2 Balok 8x12x3 m 235,000.00
3 Balok 6x12x4 m 235,000.00
4 Balok 6x12x3 m 180,000.00
5 Balok 6x10x4 m 200,000.00
6 Balok 6x10x3 m 160,000.00
KRUING
1 Balok 8x12x4 m 285,000.00
2 Balok 8x12x3 m 215,000.00
3 Balok 6x12x4 m 215,000.00
4 Balok 6x12x3 m 165,000.00
5 Balok 6x10x4 m 185,000.00
6 Balok 6x10x3 m 145,000.00
BENGKIRAI
1 Usuk, 5x7x4 m 125,000.00
2 Usuk, 5x7x3 m 95,000.00
3 Usuk, 5x7x2.5 m 77,000.00
4 Usuk, 5x7x2 m 57,000.00
5 Usuk plafond, 4x6x4 m 86,000.00
6 Usuk plafond, 4x6x3 m 64,000.00
7 Usuk plafond, 4x6x2.5 m 54,500.00
8 Usuk plafond, 4x6x2 m 42,000.00
KAMPER
1 Usuk, 5x7x4 m 107,000.00
2 Usuk, 5x7x3 m 82,000.00
3 Usuk, 5x7x2.5 m 66,000.00
4 Usuk, 5x7x2 m 50,000.00
5 Usuk plafond, 4x6x4 m 74,000.00
6 Usuk plafond, 4x6x3 m 55,000.00
7 Usuk plafond, 4x6x2.5 m 47,000.00
8 Usuk plafond, 4x6x2 m 35,000.00
KRUING
1 Usuk, 5x7x4 m 93,000.00
2 Usuk, 5x7x3 m 70,000.00
3 Usuk, 5x7x2.5 m 58,000.00
4 Usuk, 5x7x2 m 43,000.00
5 Usuk plafond, 4x6x4 m 64,000.00
6 Usuk plafond, 4x6x3 m 48,000.00
7 Usuk plafond, 4x6x2.5 m 41,000.00
8 Usuk plafond, 4x6x2 m 31,000.00
BENGKIRAI
1 Reng, 2x3x4 m 385,000.00
2 Reng, 2x3x3 m 300,000.00
3 Reng, 2x3x2.5 m 250,000.00
4 Reng, 2x3x2 m 205,000.00
KAMPER
1 Reng, 2x3x4 m 360,000.00
2 Reng, 2x3x3 m 270,000.00
3 Reng, 2x3x2.5 m 230,000.00
4 Reng, 2x3x2 m 185,000.00
KRUING
1 Reng, 2x3x4 m 320,000.00
2 Reng, 2x3x3 m 245,000.00
3 Reng, 2x3x2.5 m 210,000.00
4 Reng, 2x3x2 m 175,000.00
BENGKIRAI
1 Papan, 2x20x4 m 220,000.00
2 Papan, 2x25x4 m 310,000.00
3 Papan, 3x30x4 m 540,000.00
4 Papan, 3x25x4 m 450,000.00
5 Papan, 3x20x4 m 324,000.00
KAMPER
1 Papan, 2x20x4 m 178,000.00
2 Papan, 2x25x4 m 260,000.00
3 Papan, 3x30x4 m 465,000.00
4 Papan, 3x25x4 m 390,000.00
5 Papan, 3x20x4 m 290,000.00
KRUING
1 Papan, 2x20x4 m 146,000.00
2 Papan, 2x25x4 m 230,000.00
3 Papan, 3x30x4 m 426,000.00
4 Papan, 3x25x4 m 350,000.00
5 Papan, 3x20x4 m 265,000.00
BENGKIRAI
1 Ram pintu, 3x10x4m 176,000.00
2 Ram pintu, 3x12x4m 211,000.00
3 Ram pintu, 3x8x4m 142,000.00
KAMPER
1 Ram pintu, 3x10x4m 156,000.00
2 Ram pintu, 3x12x4m 192,000.00
3 Ram pintu, 3x8x4m 181,000.00
KRUING
1 Ram pintu, 3x10x4m 130,000.00
2 Ram pintu, 3x12x4m 181,000.00
3 Ram pintu, 3x8x4m 110,000.00
JENIS CAT
1 Cat kayu produk " EMCO LUX " No.70 1 kg 61,500.00 62,000.00
2 Cat tembok " CATYLAC " ( dinding interio 1 kg 22,400.00 113,000.00
3 Cat tembok " CATYLAC " ( dinding exterio 1 kg 31,000.00 158,000.00
4 Cat genteng 1 kg 38,000.00 25,400.00
5 Minyak cat 1 ltr 19,500.00 40,000.00
6 Plamur dinding 1 kg 112,000.00 114,000.00
7 Plamur kayu 1 kg 28,000.00 30,000.00
8 Meni besi 1 kg 28,000.00 30,000.00
9 Meni kayu 1 kg 28,000.00 30,000.00
LAIN-LAIN
1 Air 1 m3
2 Lem kayu 1 kg 12,000.00 14,000.00
3 Minyak begisting 1 ltr
UAN ( Rp. ) HARGA YG KETERANGAN
TB. KHARISMA DIGUNAKAN (Rp. )
4 5
250,000.00
-
850.00 800.00
-
-
295,000.00
250,000.00
150,000.00
100,000.00
6,000.00 6,000.00
-
37,500.00 36,000.00
11,500.00 11,000.00
3,500.00 3,000.00
36,500.00 36,500.00
-
56,000.00 49,000.00
50,000.00 50,000.00
50,000.00 50,000.00
-
-
-
-
-
-
-
-
-
-
-
20,000.00 20,000.00
6,000.00
30,000.00 25,000.00
14,000.00 14,000.00
14,000.00 14,000.00
150.00 150.00
28,000.00 21,000.00
38,000.00 29,000.00
-
-
23,500.00
-
-
-
-
-
-
400,000.00
300,000.00
300,000.00
225,000.00
250,000.00
190,000.00
315,000.00
235,000.00
235,000.00
180,000.00
200,000.00
160,000.00
285,000.00
215,000.00
215,000.00
165,000.00
185,000.00
145,000.00 62,960.00
125,000.00
95,000.00
77,000.00
57,000.00
86,000.00
64,000.00
54,500.00
42,000.00
107,000.00
82,000.00
66,000.00
50,000.00
74,000.00
55,000.00
47,000.00
35,000.00
93,000.00
70,000.00
58,000.00
43,000.00
64,000.00
48,000.00
41,000.00
31,000.00
385,000.00
300,000.00
250,000.00
205,000.00
360,000.00
270,000.00
230,000.00
185,000.00
320,000.00
245,000.00
210,000.00
175,000.00
220,000.00
310,000.00
540,000.00
450,000.00
324,000.00
178,000.00
260,000.00
465,000.00
390,000.00
290,000.00
146,000.00
230,000.00
426,000.00
350,000.00
265,000.00
176,000.00
211,000.00
142,000.00
156,000.00
192,000.00
181,000.00
130,000.00
181,000.00
110,000.00
10,000.00
18,500.00
108,000.00
117,500.00 94,000.00
-
-
-
-
-
-
-
-
65,000.00 58,000.00
139,000.00
246,000.00
58,000.00
-
10,000.00 10,000.00
5,000.00 5,000.00
-
57,000.00 57,000.00
112,500.00 22,400.00
31,000.00
25,400.00
20,000.00 19,500.00
17,500.00 17,500.00
27,500.00 27,500.00
27,500.00 27,500.00
27,500.00 27,500.00
4,875.00 4,875.00
6,750.00 6,750.00
9,250.00 9,250.00
21,250.00 21,125.00
33,125.00 32,750.00
16,000.00 16,000.00
65,000.00 59,000.00
1,380,000.00
140,000.00 140,000.00
69,000.00
215,000.00 215,000.00
245,000.00
40,000.00 40,000.00
20,000.00 20,000.00
-
10,000.00 10,000.00
14,000.00 14,000.00
9,000.00 9,000.00
6,500.00 6,500.00
-
14,000.00 12,000.00
DAFTAR HARGA TANAMAN HIAS/PERINDANG
I. TANAMAN PERINDANG
1 Angsana batang 50,000.00 #
2 Angsana batang 90,000.00
3 Asem jawa batang 40,000.00
4 Bauhmis(Orchid tree) batang 40,000.00
5 Beringin batang 50,000.00
6 Beringin batang 140,000.00
7 Beringin batang 300,000.00
8 Biola Cantik batang 300,000.00
9 Biola Cantik batang 140,000.00
10 Biola Cantik batang 75,000.00
11 Filisium batang 40,000.00
12 Gayam batang 40,000.00
13 Glodogan Biasa batang 40,000.00
14 Glodogan Biasa batang 50,000.00
15 Kenari batang 30,000.00
16 Kepel batang 60,000.00
17 Ketepeng batang 40,000.00
18 Mahoni batang 40,000.00
19 Sawo kecik batang 60,000.00
20 Sentul batang 40,000.00
21 Tanjung batang 50,000.00
22 Tanjung batang 80,000.00
23 Glodogan Pecut batang 40,000.00
24 Glodogan Pecut batang 100,000.00
25 Bungur batang 50,000.00
26 Bungur batang 70,000.00
27 Merbau batang 50,000.00
II TANAMAN HIAS
a. Rumput
1 Rumput Gajah m2 15,000.00
2 Rumput Gajah m2 18,000.00
3 Rumput Gajah Mini m2 50,000.00
4 Rumput Manila m2 15,000.00
5 Rumput golf m2 - #
6 Rumput gebalan m2 10,000.00 #
b. Perdu
1 Bambu Air rumpun 25,000.00
2 Batavia/Jatropa batang 35,000.00
3 Batavia/ Jatropa batang 130,000.00
4 Bougenville batang 40,000.00
5 Bougenville batang 75,000.00
6 Bougenville varigata batang 150,000.00
7 Classia planisicua batang 20,000.00
8 Cordata rumpun 25,000.00
9 Kembang Sepatu (Bangkok) batang 15,000.00
10 Kembang Sepatu (lokal) batang 7,500.00
11 Mawar batang 10,000.00
12 Melati Air rumpun 30,000.00
13 Palem Botol batang 150,000.00
14 Palem kuning rumpun 15,000.00
15 Palem kuning rumpun 25,000.00
16 Palem kuning rumpun 130,000.00
17 Palem kuning rumpun 175,000.00
18 Palem Merah rumpun 150,000.00
19 Palem wregu rumpun 35,000.00
20 Palem Putri batang 80,000.00
21 Palem Putri batang 155,000.00
22 Papyrus rumpun 30,000.00
23 Parikesit rumpun 30,000.00
24 Puring Bangkok batang 15,000.00
25 Phonix batang 150,000.00
26 Serut batang 500,000.00
27 Serut batang 750,000.00
28 Soka pagar batang 10,000.00 #
29 Bougenville batang -
c. Pohon
1 Cemara kipas batang 50,000.00
2 Cemara kipas batang 75,000.00
3 Cemara lilin batang 40,000.00
4 Cemara Rantes batang 75,000.00
5 Cemara Udang batang 600,000.00
6 Cemara Norvox batang 50,000.00
7 Cemara Norvox batang 80,000.00
8 Cepoko Mulyo batang 15,000.00
9 Cepoko Mulyo batang 40,000.00
10 Ceplok Piring batang 7,500.00
11 Ceplok Piring batang 20,000.00
12 Kelapa gading batang 200,000.00
13 Nusa Indah batang 10,000.00
14 Nusa Indah batang 30,000.00
15 Palem ekor tupai batang 100,000.00
16 Palem ekor tupai batang 160,000.00
17 Palem Jepang rumpun 50,000.00
18 Palem Jepang rumpun 100,000.00
19 Palem raja batang 200,000.00
20 Palem raja batang 300,000.00
21 Palem raja batang 1,500,000.00
22 Glodogan Pecut batang -
23 Glodogan Pecut batang -
d. Semak
1 Alamanda rumpun 7,500.00
2 Anthurium rumpun 25,000.00
3 Bakung rumpun 5,000.00
4 Bambu pangkas batang 12,500.00
5 Canna holland rumpun 15,000.00
6 Canna Lokal rumpun 7,500.00
7 Cendrawasih batang 5,000.00
8 Cantik manis batang 3,000.00
9 Dieffenbachia batang 10,000.00
10 Dracaena rumpun 50,000.00
11 Ficus repens batang 7,500.00
12 Hanjuang batang 3,000.00
13 Helogenia rumpun 5,000.00
14 Iler rumpun 5,000.00
15 Kayu besi batang 7,500.00
16 Krisdoren rumpun 20,000.00
17 Kayu besi rumpun 7,500.00
18 Kuncira rumpun 4,000.00
19 Kuping gajah rumpun 7,500.00
20 Lantana rumpun 4,000.00
21 Lantana rumpun 5,000.00
22 Melati batang 10,000.00
23 Nanas Kuning rumpun 15,000.00
24 Nanas Merah rumpun 30,000.00
25 Patah Tulang rumpun 4,000.00
26 Phylodendron rumpun 7,500.00
27 Sansivera rumpun 7,500.00
28 Sirih Gading rumpun 4,000.00
29 Soka Bangkok batang 8,000.00
30 Soka Jepang batang 5,000.00
31 Stevanut batang 20,000.00
32 Stivera batang 35,000.00
33 Taiwan beauty rumpun 4,000.00
34 Teh-tehan hijau bulat batang 10,000.00
35 Teh-tehan hijau bulat batang 25,000.00
36 Teh-tehan hijau bulat (pagar) batang 5,000.00
37 Teh-tehan hijau bulat (pagar) batang 2,500.00
38 Teh-tehan kuning batang 500.00
39 Teh-tehan kuning bulat batang 5,000.00
40 Tela-tela rumpun 4,500.00
41 Tricolour batang 7,500.00
42 Tricolour batang 12,500.00
43 Varent rumpun 4,500.00
44 Yuca batang 30,000.00
45 Yuca batang 70,000.00
46 Yuliana rumpun 5,000.00
47 Phylodendron rumpun - #
48 Dieffenbachia batang - #
h Pelengkap Taman
1 Kerb Taman tinggi 50 cm m 75,000.00
2 Pengecatan Kerb Taman m2 17,500.00
3 Para/ Jala m 17,500.00
4 Polybag kg 20,000.00
5 Pot Tanah kecil buah 10,000.00
6 Pot Tanah sedang buah 15,000.00
7 Pot Tanah besar buah 25,000.00
8 Pot Hias buah 75,000.00
S/PERINDANG
KETERANGAN
tinggi ± 2 m Ø 3.00 cm
tinggi ± 3 m Ø 5.00 cm
tinggi ± 1.5 m Ø 2.00 cm
tinggi ± 2 m Ø 2.00 cm
tinggi ± 1 m Ø 2.00 cm
tinggi ± 2 m Ø 3.00 cm
tinggi ± 3 m Ø 4.00 cm
tinggi ± 3 m Ø 5.00 cm
tinggi ± 2 m Ø 4.00 cm
tinggi ± 1.5 m Ø 3.00 cm
tinggi ± 1.5 m Ø 2.00 cm
tinggi ± 1.5 m Ø 2.00 cm
tinggi ± 1 m Ø 1.50 cm
tinggi ± 2.5 m Ø 3.00 cm
tinggi ± 1.5 m Ø 2.00 cm
tinggi ± 1.5 m Ø 3.00 cm
tinggi ± 1.5 m Ø 2.00 cm
tinggi ± 1.5 m Ø 2.00 cm
tinggi ± 1.5 m Ø 2.00 cm
tinggi ± 1.5 m Ø 2.00 cm
tinggi ± 1 m Ø 2.00 cm
tinggi ± 3 m Ø 3.00 cm
tinggi ± 2 m
tinggi ± 4 m
tinggi ± 2 m Ø 2.00 cm
tinggi ± 3 m Ø 3.00 cm
tinggi ± 2 m Ø 2.00 cm
tanam
gebalan
tanam
gebalan
tinggi ± 1.5 m
tinggi ± 0.5 m
tinggi ± 1.5 m
tinggi ± 0.5 m
tinggi ± 0,7 m
tinggi ± 0,8 m
tinggi ± 0.5 m
tinggi ± 0.4 m
tinggi ± 0.2 m
tinggi ± 0.4 m
tinggi ± 0,25 m
tinggi ± 0.4 m
tinggi ± 0,8 m
tinggi ± 0.6 m
tinggi ± 1 m
tinggi ± 1,5 - 2 m
tinggi ± 2-3 m
tinggi ± 2-3 m
tinggi ± 0.6 m
tinggi ± 1 m
tinggi ± 2 m
tinggi ± 0,7 m
tinggi ± 0,7 m
tinggi ± 0,6 m
tinggi ± 1 m
tinggi ± 1 - 1.5 m
tinggi ± 1.5 m
tinggi ± 0.3 m
tinggi ± 1 m
tinggi ± 0.5 m
tinggi ± 1.5 m
tinggi ± 1.5 m
tinggi ± 1 m
tinggi ± 1 - 1,5 m
tinggi ± 0.6 m
tinggi ± 1.5 m
tinggi ± 0.5 m
tinggi ± 1 m
tinggi ± 0.5 m
tinggi ± 1 m
tinggi ± 3 m
tinggi ± 0.5 m
tinggi ± 1 m
tinggi ± 2 m
tinggi ± 2 m
tinggi ± 1 m
tinggi ± 2 m
tinggi ± 4 m
tinggi ± 6 m
tinggi ± 7 m
tinggi ± 1 m
tinggi ± 2 m
tinggi ± 0.2 m
tinggi ± 0.3 m
tinggi ± 0.3 m
tinggi ± 0.15 m
tinggi ± 0.3 m
tinggi ± 0.5 m
tinggi ± 0.15 m
tinggi ± 0.2 m
tinggi ± 0.2 m
tinggi ± 1 m
tinggi ± 0.25 m
tinggi ± 0.4 m
tinggi ± 0.5 m
tinggi ± 0.5 m
tinggi ± 0.5 m
tinggi ± 0.3 m
tinggi ± 0.25 m
tinggi ± 0.2 m
tinggi ± 0.3 m
tinggi ± 0.2 m
tinggi ± 0.2 m
tinggi ± 0.2 m
tinggi ± 0.3 m
tinggi ± 0.4 m
1 rumpun
tinggi ± 0.25 m
tinggi ± 0.2 m
tinggi ± 0.2 m
tinggi ± 0.3 m
tinggi ± 0.2 m
tinggi ± 0.25 m
tinggi ± 0.5 m
tinggi ± 0.4 m
tinggi ± 0.25 m
tinggi ± 0.15 m
tinggi ± 0.3 m
tinggi ± 0.2 m
tinggi ± 0.2 m
tinggi ± 0.25 m
tinggi ± 0.25 m
tinggi ± 0.4 m
tinggi ± 0.75 m
tinggi ± 0.3 m
tinggi ± 0.7 m
tinggi ± 0.5 m
tinggi ± 0.1 m
tinggi ± 0.15 m
tinggi ± 0.4 m
tinggi ± 0.2 m
tinggi ± 0.3 m
tinggi ± 0.2 m
tinggi ± 0.2 m
tinggi ± 0.2 m
pot kecil
tinggi ± 0.2 m
tinggi ± 0.3 m
tinggi ± 0.25 m
tinggi ± 0.15 m
tinggi ± 0.4 m
tinggi ± 0.4 m
terpasang
terpasang
ANALISA UNTUK PEKERJAAN PELUMPURAN
a x (L + 75)
k =
275
k = Biaya yang dicari per m3
a = Upah pekerja per hari
L = Jarak pengangkutan dalam m1
Dalam perhitungan biaya diatas sudah termasuk harga alat yang dipakai
Dalam perhitungan biaya diatas sudah termasuk harga alat yang dipakai
Dalam perhitungan biaya diatas sudah termasuk harga alat yang dipakai
Dalam perhitungan biaya diatas sudah termasuk harga alat yang dipakai
4 1 m3 Membuang tanah ke luar lokasi
0.20 oh Pekerja @ Rp.
0.10 oh Mandor @ Rp.
0.10 hr Sewa mobil bak @ Rp.
JUMLAH
JASA ( >0 % - ≤ 10 %)
JUMLAH
DIBULATKAN
-
-
- -
-
-
-
-
-
- -
-
-
-
-
-
- - -
-
-
-
-
-
-
- - -
-
-
-
Membong
kar beton
- rabat
-
-
- -
-
-
-
-
-
- -
-
-
-
-
-
- -
-
-
-
-
-
- - -
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
- -
-
-
-
-
-
- -
-
-
-
-
-
- -
-
-
-
-
-
- - -
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
- -
-
-
-
-
-
- - -
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
ANALISA CLEANING SERVICE
No Macam Pekerjaan
(1) (2)
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
ANALISA HARGA SATUAN PEKERJAAN PENGANGKUTAN
Macam Pekerjaan
(1)
Macam Pekerjaan
(1)
Macam Pekerjaan
(1)
Macam Pekerjaan
(1)
1.00 m2 Sweeping
0.00002500 bh Sapu lidi
0.00000093 bh Tangkai sapu
0.00000556 bh Tomblok
0.00000023 bh Hareg
0.00000278 bh Keruk
0.00000023 bh Gerobak
0.00000046 bh Seragam
0.00000556 bh Sarung tangan
0.00000046 bh Sepatu
0.00000023 bh Helm
0.00001111 bh Masker
0.00000556 bh Serok
0.00008333 org Pekerja
0.00000833 org Mandor
Macam Pekerjaan
(1)
Macam Pekerjaan
(1)
Macam Pekerjaan
(1)
Macam Pekerjaan
(1)
1.00 m2 Penyiraman tanaman
0.00040000 buah Truk Tangki Air
0.00000009 buah Alat pompa
0.00000440 org Sopir
0.00000440 org Tenaga penyiram
0.00000072 buah Seragam
0.00000109 buah Sarung tangan
0.00000145 buah Sepatu
0.00000072 buah Helm
JUMLAH (BELUM PPN)
JASA 10%
JUMLAH
Macam Pekerjaan
(1)
Macam Pekerjaan
(1)
Macam Pekerjaan
(1)
Macam Pekerjaan
(1)
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
Upah Rp. Alat Rp. Jumlah Rp.
(3) (4) (5)
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
- - -
-
-
n Kecil m 2
-
-
- - -
-
-
-
-
- - -
-
-
ANALISA KPUT
Tiap m2
1/100 x - + -
Biaya menggilas
1/200 x - + -
Sewa motor walls
1/200 x -
JUMLAH ( BELUM TERMASUK PPN )
JASA 10 %
JUMLAH
DIBULATKAN
Tiap m2
1/100 x - + -
Biaya menggilas
1/200 x - + -
Sewa motor walls
1/200 x -
JUMLAH ( BELUM TERMASUK PPN )
JASA 10 %
JUMLAH
DIBULATKAN
Tiap m2
1/100 x - + -
Biaya menggilas
1/150 x - + -
Sewa motor walls
1/150 x -
JUMLAH ( BELUM TERMASUK PPN )
JASA 10 %
JUMLAH
DIBULATKAN
Tiap m2 Pembuatan lapis pondasi atas (base) tebal 8 cm padat
8/10 x - + -
Biaya menggilas
1/150 x - + -
Sewa motor walls
1/150 x -
JUMLAH ( BELUM TERMASUK PPN )
JASA 10 %
JUMLAH
DIBULATKAN
Tiap m2
1/100 x - + -
Biaya menggilas
4/12,5/200 x - + -
Sewa motor walls
1/200 x -
JUMLAH ( BELUM TERMASUK PPN )
JASA 10 %
JUMLAH
DIBULATKAN
-
-
- - -
-
-
- - -
-
-
-
-
-
-
-
-
-
- - -
-
bal 20 cm padat
-
-
-
-
-
-
- - -
-
- -
- -
-
- - -
-
-
-
bal 15 cm padat
-
-
-
-
-
-
- - -
-
- -
- -
-
- - -
-
-
-
-
-
-
-
-
-
- - -
-
- -
- -
-
- - -
-
-
-
- -
- -
-
- - -
-
-
-
- -
- -
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
- -
- -
-
- - -
-
-
-
-
-
-
-
-
-
- - -
-
- -
- -
5,591.25
- 5,591.25 5,591.25
559.13
6,150.38
6,150.00
- -
- -
-
- - -
-
-
-
tebal 1 cm jereng
-
-
-
-
-
-
- - -
-
- -
- -
-
- - -
-
-
-
- -
- -
-
- - -
-
-
-
-
-
-
-
-
- - -
-
- -
- - -
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
- -
- - -
-
-
-
- -
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
FORMULIR STANDAR UNTUK PEREKAMAN ANALISA
MASING MASING HARGA SATUAN
NO KOMPONEN SATUAN
A TENAGA
1 Pekerja ( L 01 ) Jam
2 Mandor ( L 03 ) Jam
B BAHAN
1 Agregat Kasar ( M 03 ) M3
2 Agregat Halus ( M 04 ) M3
3 Filler ( M 05 ) Kg
4 Aspal ( M 10 ) Kg
C PERALATAN
1 Wheel Loader ( E 15 ) Jam
2 AMP ( E 01 ) Jam
3 Genset ( E 12 ) Jam
4 Dump Truck ( E 09 ) Jam
5 Aspal Finisher ( E 02 ) Jam
6 Tandem Roller ( E 17 ) Jam
7 Pneumatic Tyre Roller ( E 18 ) Jam
8 Alat Bantu Ls
JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau uk
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termas
biaya biaya lainnya
URAIAN ANALISA HARGA SATUAN LATASTON ( HRS )
SATUAN : M2
No URAIAN
I ASUMSI
1 Menggunakan alat berat ( cara mekanik )
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan
5 Tebal lapisan padat
6 Jam kerja efektif 1 hari
7 Faktor kehilangan material
- Agregat
- Aspal
II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat
langsung ke dalam Dump Truck dan diangkut ke lokasi pekerjaan.
3 Campuran panas HRS dihampar dengan Finisher dan dipadatakan dengan
Tandem dan Peneumatic Tire Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu
2 ALAT
a Wheel Loader
Kapasitas bucket
Faktor bucket
Faktor efisiensi alat
Waktu siklus
- Muat
- Lain lain
No URAIAN
Koefisien Alat / m2 = 1 / Q2
Koefisien Alat / m2 = 1 / Q3
d Dump Truk ( DT )
Kapasitas bak
Faktor efisiensi alat
Kecepatan rata rata bermuatan
Kecepatan rata rata kosong
Kapasitas AMP batch
Waktu menyiapkan 1 batch HRS
Waktu Siklus
- Mengisi bak = ( V : Q2b ) x Tb
- Angkut = ( L : v1 ) x 60 menit
- Tunggu + Dumping + Putar
- Kembali = ( L : v2 ) x 60 menit
Koefisien Alat / m2 = 1 / Q4
e Finisher
Kapasitas produksi
Faktor efisiensi alat
Koefisien Alat / m2 = 1 / Q5
f Tandem Roller
Kecepatan rata rata alat
Lebar efektif pemadatan
Jumlah lintasan
Faktor efisiensi alat
Koefisien Alat / m2 = 1 / Q6
No URAIAN
Koefisien Alat / m2 = 1 / Q7
h Alat Bantu
Diperlukan :
- Kereta dorong = 2 bh
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan
3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP )
Produksi HRS / hari = Tk x Q2
Kebutuhan tenaga
- Pekerja
- Mandor
Rp 0.00 / M2
NO KOMPONEN SATUAN
A TENAGA
1 Pekerja ( L 01 ) Jam
2 Mandor ( L 03 ) Jam
B BAHAN
1 Agregat Kasar ( M 03 ) M3
2 Agregat Halus ( M 04 ) M3
3 Filler ( M 05 ) Kg
4 Aspal ( M 10 ) Kg
C PERALATAN
1 Wheel Loader ( E 15 ) Jam
2 AMP ( E 01 ) Jam
3 Genset ( E 12 ) Jam
4 Dump Truck ( E 09 ) Jam
5 Aspal Finisher ( E 02 ) Jam
6 Tandem Roller ( E 17 ) Jam
7 Pneumatic Tyre Roller ( E 18 ) Jam
8 Alat Bantu Ls
JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau uk
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termas
biaya biaya lainnya
No URAIAN
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan
5 Tebal lapisan ( AC ) padat
6 Jam kerja efektif 1 hari
7 Faktor kehilangan material
- Agregat
- Aspal
II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat
langsung ke dalam Dump Truck dan diangkut ke lapangan
3 Campuran panas AC dihampar dengan Finisher dan dipadatakan dengan
Tandem dan Tire Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu
2 ALAT
a Wheel Loader
Kapasitas bucket
Faktor bucket
Faktor efisiensi alat
Waktu siklus
- Muat
- Lain lain
No URAIAN
Koefisien Alat / m2 = 1 / Q2
Koefisien Alat / m2 = 1 / Q3
d Dump Truk ( DT )
Kapasitas bak
Faktor efisiensi alat
Kecepatan rata rata bermuatan
Kecepatan rata rata kosong
Kapasitas AMP batch
Waktu menyiapkan 1 batch AC
Waktu Siklus
- Mengisi bak = ( V : Q2b ) x Tb
- Angkut = ( L : v1 ) x 60 menit
- Tunggu + Dumping + Putar
- Kembali = ( L : v2 ) x 60 menit
Koefisien Alat / m2 = 1 / Q4
e Finisher
Kapasitas produksi
Faktor efisiensi alat
Koefisien Alat / m2 = 1 / Q5
f Tandem Roller
Kecepatan rata rata alat
Lebar efektif pemadatan
Jumlah lintasan
Faktor efisiensi alat
No URAIAN
Koefisien Alat / m2 = 1 / Q7
h Alat Bantu
Diperlukan :
- Rambu = 2 bh
- Kereta dorong = 2 bh
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan
3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP )
Produksi AC / hari = Tk x Q2
Kebutuhan tenaga
- Pekerja
- Mandor
Rp 0.00 / M2
6 WAKTU PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan = . . . . . . . Bulan
NO KOMPONEN SATUAN
A TENAGA
1 Pekerja ( L 01 ) Jam
2 Mandor ( L 03 ) Jam
B BAHAN
1 Agregat Kasar ( M 03 ) M3
2 Agregat Halus ( M 04 ) M3
3 Filler ( M 05 ) Kg
4 Aspal ( M 10 ) Kg
C PERALATAN
1 Wheel Loader ( E 15 ) Jam
2 AMP ( E 01 ) Jam
3 Genset ( E 12 ) Jam
4 Dump Truck ( E 09 ) Jam
5 Aspal Finisher ( E 02 ) Jam
6 Tandem Roller ( E 17 ) Jam
7 Pneumatic Tyre Roller ( E 18 ) Jam
8 Alat Bantu Ls
JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau uk
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termas
biaya biaya lainnya
SATUAN : M3
No URAIAN
I ASUMSI
1 Menggunakan alat berat ( Cara mekanik )
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan
5 Tebal lapisan ( ATB ) padat
6 Jam kerja efektif 1 hari
7 Faktor kehilangan material
- Agregat
- Aspal
II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat
langsung ke dalam Dump truck dan diangkut ke lokasi pekerjaan
3 Campuran panas ATB dihampar dengan Finisher dan dipadatakan dengan
Tandem dan Pneumatic Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu
III PEMAKAIAN BAHAN ALAT DAN TENAGA
1 BAHAN
a Agregat kasar = {( CA x D1 x 1 m3 ) x ( Fh 1 )}/ D2
b Agregat halus = {( FA x D1 x 1 m3 ) x ( Fh 1 )}/ D2
c Filler = {( FF x D1 x 1 m3 ) x ( Fh 1 )}
d Aspal = {( AS x D1 x 1 m3 ) x ( Fh 2 )}
2 ALAT
a Wheel Loader
Kapasitas bucket
Faktor bucket
Faktor efisiensi alat
Waktu siklus
- Muat
- Lain lain
No URAIAN
Koefisien Alat / m3 = 1 / Q2
Koefisien Alat / m3 = 1 / Q3
d Dump Truk ( DT )
Kapasitas bak
Faktor efisiensi alat
Kecepatan rata rata bermuatan
Kecepatan rata rata kosong
Kapasitas AMP batch
Waktu menyiapkan 1 batch ATB
Waktu Siklus
- Mengisi bak = ( V : Q2b ) x Tb
- Angkut = ( L : v1 ) x 60 menit
- Tunggu + Dumping + Putar
- Kembali = ( L : v2 ) x 60 menit
Koefisien Alat / m3 = 1 / Q4
e Finisher
Kapasitas produksi
Faktor efisiensi alat
Koefisien Alat / m3 = 1 / Q5
f Tandem Roller
Kecepatan rata rata alat
Lebar efektif pemadatan
Jumlah lintasan
Faktor efisiensi alat
Koefisien Alat / m3 = 1 / Q6
No URAIAN
Koefisien Alat / m3 = 1 / Q7
h Alat Bantu
Diperlukan :
- Kereta dorong = 2 bh
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan
3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP )
Produksi ATB / hari = Tk x Q2
Kebutuhan tenaga
- Pekerja
- Mandor
Rp 0.00 / M3
NO KOMPONEN SATUAN
A TENAGA
1 Pekerja ( L 01 ) Jam
2 Mandor ( L 03 ) Jam
B BAHAN
1 Aspal ( M 10 ) ( M 10 ) Kg
2 Karosene ( M 11 ) ( M 11 ) Liter
C PERALATAN
1 Asphalt Sprayer ( E 03 ) Jam
2 Compresor ( E 05 ) Jam
3 Dump Truck ( E 08 ) Jam
JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau uk
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termas
biaya biaya lainnya
SATUAN : L
No URAIAN
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Jarak rata rata Base Camp ke Lokasi pekerjaan
4 Jam kerja efektif 1 hari
5 Faktor kehilangan material
6 Komposisi campuran AC ( Spesifikasi )
- Aspal AC - 10 atau AC - 20
- Minyak Flux / pencair
8 Bahan dasar ( aspal dan minyak pencair ) semuanya diterima di Lokasi Pekerjaan
II METODA KERJA
1 Aspal dan minyak Flux dicampur dan dipanaskan sehingga menjadi campuran aspal cair
2 Permukaan yang akan dilapis dibersihkan dari debu dan kotoran dg air kompresor
3 Campuran aspal cair disemprotkan dg aspahalt sprayer ke atas permukaan yg akan dilapis
4 Angkutan aspal dan minyak Flux menggunakan Dump truck
2 ALAT
a Asphalt Sprayer
Kapasitas alat
Faktor efisiensi alat
Waktu siklus ( termasuk proses pemanasan )
b Air Compresor
Kapasitas alat -----------> Diambil
Aplikasi Lapis Resap Pengikat Rata rata ( Spesifikasi )
No URAIAN
c Dump Truk ( DT )
Sebagai alat pengangkut bahan di lokasi pekerjaan Dump Truck melayani alat
Asphalt Sprayer
Kapasitas Produksi / jam = V x Fa
Ts
Koefisien Alat / m2 = 1 / Q3
3 TENAGA
Produksi menentukan : ASPALT FINISHER
Produksi Lapis Resap Pengikat / hari = Tk x Q4
Kebutuhan tenaga
- Pekerja
- Mandor
Rp 0.00 / LITER
NO KOMPONEN SATUAN
A TENAGA
1 Pekerja ( L 01 ) Jam
2 Mandor ( L 03 ) Jam
B BAHAN
1 Agregat Kasar ( M 03 ) M3
2 Agregat Halus ( M 04 ) M3
C PERALATAN
1 Wheel Loader ( E 15 ) Jam
2 Dump Truck ( E 09 ) Jam
3 Motor Grader ( E 13 ) Jam
4 Vibratory Roller ( E 19 ) Jam
5 Pneumatic Tyre Roller ( E 18 ) Jam
6 Water Tank Truck ( E 23 ) Jam
7 Alat Bantu Ls
JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN
UNTUK 1 M2 TEBAL 20 CM
UNTUK 1 M2 TEBAL 15 CM
UNTUK 1 M2 TEBAL 10 CM
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau uk
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termas
biaya biaya lainnya
SATUAN : M3
No URAIAN
I ASUMSI
1 Menggunakan alat berat Cara mekanik
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan
5 Tebal Agregat padat
6 Faktor kembang material ( padat - lepas )
7 Jam kerja efektif per hari
8 Proporsi campuran
- Agregat Kasar
- Agregat halus
II METODA KERJA
1 WHEEL LOADER mencampur dan memuat agregat ke dalam Dump Truck di
Base camp
2 Dump Truck mengangkut Agregat ke lokasi pekerjaan dan dihampar dg motor
Grader
3 Hamparan Agregat di basahi dengan Water Tank Truck sebelum dipadatkan
dengan Tandem Roller & PTR
4 Selama pemadatan sekelompok pekerja akan merapikan tepi hamparan dan level
permukaan dengan menggunakan alat bantu
2 ALAT
a Wheel Loader
Kapasitas bucket
Faktor bucket
Faktor efisiensi alat
Waktu siklus
- Mencampur
- Memuat dan Lain lain
b Dump Truk ( DT )
Kapasitas bak
Faktor efisiensi alat
Kecepatan rata rata bermuatan
Kecepatan rata rata kosong
Waktu Siklus
- Waktu tempuh isi = ( L : v1 ) x 60 menit
- Waktu tempuh kosong = ( L : v2 ) x 60 menit
- lain lain termasuk menurunkan Agregat
No URAIAN
Koefisien Alat / m3 = 1 / Q2
c Motor Grader
Panjang hamparan
Lebar efektif kerja blade
Faktor Efisiensi alat
Kecepatan rata rata alat
Jumlah lintasan
Waktu siklus
- Perataan 1 Lintasan = Lh : ( v x 1000 x 60 menit )
- Lain lain
Koefisien Alat / m3 = 1 / Q3
d Vibratory Roller
Kecepatan rata rata alat
Lebar efektif pemadatan
Jumlah lintasan
Faktor efisiensi alat
Koefisien Alat / m3 = 1 / Q4
Koefisien Alat / m3 = 1 / Q6
No URAIAN
g Alat Bantu
Diperlukan :
- Kereta dorong = 2 bh
- Skop = 3 bh
- Garpu = 2 bh
3 TENAGA
Produksi menentukan : WHEEL LOADER
Produksi Agregat / hari = Tk x Q1
Kebutuhan tenaga
- Pekerja
- Mandor
Rp 0.00 / M2
6 WAKTU PELAKSANAAN YANG DIPERLUKAN
Masa Pelaksanaan = . . . . . . . . .Bulan
NO KOMPONEN SATUAN
A TENAGA
1 Pekerja ( L 01 ) Jam
2 Mandor ( L 03 ) Jam
B BAHAN
1 Agregat Kasar ( M 03 ) M3
2 Agregat Halus ( M 04 ) M3
C PERALATAN
1 Wheel Loader ( E 15 ) Jam
2 Dump Truck ( E 09 ) Jam
3 Motor Grader ( E 13 ) Jam
4 Vibratory Roller ( E 19 ) Jam
5 Pneumatic Tyre Roller ( E 18 ) Jam
6 Water Tank Truck ( E 23 ) Jam
7 Alat Bantu Ls
JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN
UNTUK 1 M2 TEBAL 20 CM
UNTUK 1 M2 TEBAL 15 CM
UNTUK 1 M2 TEBAL 10 CM
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau uk
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termas
biaya biaya lainnya
SATUAN : M3
No URAIAN
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan
5 Tebal Agregat padat
6 Faktor kembang material ( padat - lepas )
7 Jam kerja efektif per hari
8 Proporsi campuran
- Agregat Kasar
- Agregat halus
II METODA KERJA
1 WHEEL LOADER mencampur dan memuat agregat ke dalam Dump Truck di
Base camp
2 Dump Truck mengangkut Agregat ke lokasi pekerjaan dan dihampar dengan
motor Grader
3 Hamparan Agregat di basahi dengan Water Tank Truck sebelum dipadatkan
dengan Tandem Roller & PTR
4 Selama pemadatan sekelompok pekerja akan merapikan tepi hamparan dan level
permukaan dengan menggunakan alat bantu
b Dump Truk ( DT )
Kapasitas bak
Faktor efisiensi alat
Kecepatan rata rata bermuatan
Kecepatan rata rata kosong
Waktu Siklus
- Waktu tempuh isi = ( L : v1 ) x 60 menit
- Waktu tempuh kosong = ( L : v2 ) x 60 menit
- lain lain termasuk menurunkan Agregat
No URAIAN
Koefisien Alat / m2 = 1 / Q2
c Motor Grader
Panjang hamparan
Lebar efektif kerja blade
Faktor Efisiensi alat
Kecepatan rata rata alat
Jumlah lintasan
Waktu siklus
- Perataan 1 Lintasan = ( Lh x 60 ) : ( v x 1000 )
- Lain lain
d Vibratory Roller
Kecepatan rata rata alat
Lebar efektif pemadatan
Jumlah lintasan
Faktor efisiensi alat
Koefisien Alat / m2 = 1 / Q4
Koefisien Alat / m2 = 1 / Q5
Koefisien Alat / m2 = 1 / Q6
No URAIAN
g Alat Bantu
Diperlukan :
- Kereta dorong = 2 bh
- Skop = 3 bh
- Garpu = 2 bh
3 TENAGA
Produksi menentukan : WHEEL LOADER
Produksi Agregat / hari = Tk x Q1
Kebutuhan tenaga
- Pekerja
- Mandor
Rp 0.00 / M2
NO KOMPONEN SATUAN
A TENAGA
1 Pekerja ( L 01 ) Jam
2 Mandor ( L 03 ) Jam
B BAHAN
1 Aspal ( M 10 ) Kg
2 Kerosene ( M 11 ) Liter
C PERALATAN
1 Asphalt Sprayer ( E 03 ) Jam
2 Compresor ( E 05 ) Jam
3 Dump Truck ( E 08 ) Jam
JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau uk
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termas
biaya biaya lainnya
SATUAN : M3
No URAIAN
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Jarak rata rata Base Camp ke Lokasi pekerjaan
4 Jam kerja efektif 1 hari
5 Faktor kehilangan material
6 Komposisi campuran ( Spesifikasi )
- Aspal AC - 10 atau AC - 20
- Minyak Flux / pencair
2 ALAT
a Asphalt Sprayer
Kapasitas alat
Faktor efisiensi alat
Waktu siklus ( termasuk proses pemanasan )
b Air Compresor
Kapasitas alat . . . . . Diambil
Aplikasi Lapis Resap Pengikat Rata rata ( Spesifikasi )
No URAIAN
c Dump Truk ( DT )
Sebagai alat pengangkut bahan di lokasi pekerjaan Dump Truck melayani alat
Asphalt Sprayer
Koefisien Alat / m2 = 1 / Q3
3 TENAGA
Produksi menentukan : ASPALT FINISHER
Produksi Lapis Perekat / hari = Tk x Q4
Kebutuhan tenaga
- Pekerja
- Mandor
Rp 0.00 / Liter
NO KOMPONEN SATUAN
A TENAGA
1 Pekerja ( L 01 ) Jam
2 Mandor ( L 02 ) Jam
C PERALATAN
1 Motor Grader ( E 13 ) Jam
2 Vibratory Roller ( E 19 ) Jam
3 Water Tank Truck ( E 23 ) Jam
4 Alat Bantu Ls
JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau uk
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dar
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termas
biaya biaya lainnya
SATUAN : M2
No URAIAN
I ASUMSI
1 Pekerjaan dilakukan pada hanya pada tanah galian
2 Pekerjaan dilakukan secara mekanis
3 Lokasi pekerjaan : sepanjang jalan
4 Kondisi jalan : jelek / belum padat
5 Jam kerja efektif per hari
II URUTAN KERJA
1 Motor Grader meratakan permukaan hasil galian
2 Vibro Roller memadatkan permukaan jalan yang telah diratakan oleh Motor grader
3 Sekelompok pekerja akan membanru meratakan badan jalan dengan alat bantu
permukaan dengan menggunakan alat bantu
2 ALAT
a Motor Grader
Panjang hamparan
Lebar efektif kerja blade
Faktor Efisiensi alat
Kecepatan rata rata alat
Jumlah lintasan
Waktu siklus
- Perataan 1 Lintasan = Lh : ( v x 1000 x 60 menit )
- Lain lain
Koefisien Alat / m3 = 1 / Q1
b Vibratory Roller
Kecepatan rata rata alat
Lebar efektif pemadatan
Jumlah lintasan
Faktor efisiensi alat
Koefisien Alat / m3 = 1 / Q2
No URAIAN
Koefisien Alat / m3 = 1 / Q3
g Alat Bantu
Diperlukan :
- Skop = 3 bh
3 TENAGA
Produksi menentukan : VIBRATORY ROLLER
Produksi Pekerjaan / hari = Tk x Q2
Kebutuhan tenaga
- Pekerja
- Mandor
Rp 0.00 / M2
Analisa EI - 633
HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
0.0113 -
0.0016 -
0.0121 -
0.0232 -
4.8004 -
5.2962 -
0.0011 -
0.0016 -
0.0016 -
0.0143 -
0.0020 -
0.0017 -
0.0013 -
1.0000 -
-
-
-
-
L 20.0 Km
t 0.03 m
Tk 7.00 Jam
Fh 1 1.10 -
Fh 2 1.05 -
CA 29.50 %
FA 56.50 %
FF 6.49 %
As 7.51 %
D1 2.24 t / m3
D2 1.80 t / m3
D3 2.00 t / m3
D4 1.03 t / m3
M03 0.0121 m3
M04 0.0232 m3
M05 4.8004 Kg
M10 5.2962 Kg
( E 15 )
V 1.50 m3
Fb 0.90 -
Fa 0.83 -
Ts 1
T1 1.50 menit
T2 0.50 menit
Ts 1 2.00 menit
Q1 900.40 m2
( E 15 ) 0.0011 Jam
( E 01 )
V 50.00 ton / jam
Fa 0.83 -
Q2 617.56 m2
( E 01 ) 0.0016 Jam
( E 12 )
Q3 617.56 m2
( E 12 ) 0.0016 Jam
( E 09 )
V 8.00 ton
Fa 0.83 -
v1 40.00 km / jam
v2 50.00 km / jam
Q2 b 0.50 ton
Tb 1.00 menit
Ts2
T1 16.00 menit
T2 30.00 menit
T3 15.00 menit
T4 24.00 menit
Ts2 85.00 menit
Q4 69.75 m2
( E 09 ) 0.0143 Jam
( E 02 )
V 40.00 km / jam
Fa 0.83 -
Q5 494.05 m2
( E 02 ) 0.0020 Jam
( E 17 )
v 3.50 km/jam
b 1.20 m
n 6.00 lintasan
Fa 0.83 -
Q6 581.00 m2
( E 17 ) 0.0017 Jam
( E 18 )
v 5.00 km / jam
b 1.50 m
n 8.00 lintasan
Fa 0.83 -
Q7 778.13 m2
( E 18 ) 0.0013 Jam
Lump sum
Q2 617.56 m2 / jam
Qt 4,322.92 m2
P 7.00 orang
M 1.00 orang
( L 01 ) 0.0113 jam
( L 03 ) 0.0016 jam
EREKAMAN ANALISA
RGA SATUAN
Analisa EI - 634
HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
0.0217 -
0.0022 -
0.0336 -
0.0149 -
4.8015 -
6.6150 -
0.0015 -
0.0022 -
0.0022 -
0.0348 -
0.0027 -
0.0016 -
0.0023 -
1.0000 -
-
-
-
-
TUAN LASTON ( AC )
Analisa EI - 634
L 20.0 Km
t 0.04 m
Tk 7.00 Jam
Fh 1 1.10 -
Fh 2 1.05 -
CA 61.15 %
FA 27.00 %
FF 4.85 %
As 7.00 %
D1 2.25 t / m3
D2 1.80 t / m3
D3 2.00 t / m3
D4 1.03 t / m3
M03 0.034 m3
M04 0.015 m3
M05 4.802 Kg
M10 6.615 Kg
( E 15 )
V 1.50 m3
Fb 0.90 -
Fa 0.83 -
Ts 1
T1 1.50 menit
T2 0.50 menit
Ts 1 2.00 menit
Q1 672.30 m3
( E 15 ) 0.0015 Jam
( E 01 )
V 50.00 ton / jam
Fa 0.83 -
Q2 461.11 m2
( E 01 ) 0.0022 Jam
( E 12 )
Q3 461.11 m2
( E 12 ) 0.0022 Jam
( E 09 )
V 4.00 m3
Fa 0.83 -
v1 40.00 km / jam
v2 50.00 km / jam
Q2 b 0.50 ton
Tb 1.00 menit
Ts2
T1 8.00 menit
T2 29.99 menit
T3 15.00 menit
T4 23.99 menit
Ts2 76.98 menit
Q4 28.75 m2
( E 09 ) 0.0348 Jam
( E 02 )
V 40.00 ton / jam
Fa 0.83 -
Q5 368.89 m2
( E 02 ) 0.0027 Jam
( E 17 )
v 2.50 km / jam
b 1.20 m
n 4.00 lintasan
Fa 0.83 -
Q6 622.50 m2
( E 17 ) 0.0016 Jam
( E 18 )
v 3.50 km / jam
b 1.20 m
n 8.00 lintasan
Fa 0.83 -
Q7 435.75 m2
( E 18 ) 0.0023 Jam
Lump sum
Q2 461.11 m2 / jam
Qt 3,227.78 m2
P 10.00 orang
M 1.00 orang
( L 01 ) 0.0217 jam
( L 03 ) 0.0022 jam
EREKAMAN ANALISA
RGA SATUAN
Analisa EI - 635
HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
0.3880 -
0.0554 -
0.7028 -
0.5341 -
139.2 -
157.0 -
0.0380 -
0.0554 -
0.0554 -
0.4906 -
0.0767 -
0.0430 -
0.0321 -
1.0000 -
-
-
-
-
Analisa EI - 635
L 20.0 Km
t 0.04 m
Tk 7.00 Jam
Fh 1 1.10 -
Fh 2 1.05 -
CA 50.00 %
FA 38.00 %
FF 5.50 %
As 6.50 %
D1 2.30 t / m3
D2 1.80 t/m3
D3 2.00 t/m3
D4 1.03 t/m3
M03 0.7028 m3
M04 0.5341 m3
M05 139.2 Kg
M10 157.0 Kg
( E 15 )
V 1.50 m3
Fb 0.90 -
Fa 0.83 -
Ts 1
T1 1.50 menit
T2 0.50 menit
Ts 1 2.00 menit
Q1 26.31 m3
( E 15 ) 0.0380 Jam
( E 01 )
V 50.00 ton / jam
Fa 0.83 -
Q2 18.04 m3
( E 01 ) 0.0554 Jam
( E 12 )
Q3 18.04 m3
( E 12 ) 0.0554 Jam
( E 09 )
V 8.00 ton
Fa 0.83 -
v1 40.00 km / jam
v2 50.00 km / jam
Q2 b 0.50 ton
Tb 1.00 menit
Ts2
T1 16.00 menit
T2 29.99 menit
T3 15.00 menit
T4 23.99 menit
Ts2 84.99 menit
Q4 2.04 m3
( E 09 ) 0.4906 Jam
V 40.00 ton/jam
Fa 0.75 -
Q5 13.04 m3
( E 02 ) 0.0767 Jam
( E 17 )
v 3.50 km / jam
b 1.20 m
n 6.00 lintasan
Fa 0.83 -
Q6 23.24 m3
( E 17 ) 0.0430 Jam
( E 18 )
v 5.00 km / jam
b 1.50 m
n 8.00 lintasan
Fa 0.83 -
Q7 31.13 m3
( E 18 ) 0.0321 Jam
Lump sum
Q2 18.04 m3 / jam
Qt 126.30 m3
P 7.00 orang
M 1.00 orang
( L 01 ) 0.3880 jam
( L 03 ) 0.0554 jam
EREKAMAN ANALISA
RGA SATUAN
ME COAT)
Analisa EI - 611
HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
0.0301 -
0.0060 -
0.6417 -
0.4889 -
0.0030 -
0.0031 -
0.0030 -
-
-
-
-
Analisa EI - 611
L 20.00 Km
Tk 7.00 Jam
Fh 1.10 -
AS 56 % 100 Bagian
K 44 % 80 Bagian
D1 1.05 Kg / Lt
D2 0.80 Kg / Lt
si Pekerjaan
( E 03 )
V 800.00 liter
Fa 0.83 -
Ts 2.00 jam
Q1 332.00 liter
( E 03 ) 0.0030 jam
( E 05 )
V 400.00 m2 / jam
Ap 0.80 liter / m2
Q2 320.00 liter
( E 05 ) 0.0031 jam
( E 08 )
Q3 332.00 liter
( E 08 ) 0.0030 jam
Q4 332.00 Liter
Qt 2,324.00 Liter
P 10.00 orang
M 2.00 orang
( L 01 ) 0.0301 jam
( L 03 ) 0.0060 jam
EREKAMAN ANALISA
RGA SATUAN
Analisa EI - 511
HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
0.4373 -
0.0625 -
0.7680 -
0.4320 -
0.0625 -
0.1994 -
0.0117 -
0.0178 -
0.0043 -
0.0211 -
1.0000 -
-
-
-
-
-
-
-
Analisa EI - 511
M03 0.7680 m3
M04 0.4320 m3
( E 15 )
V 1.50 m3
Fb 0.90 -
Fa 0.83 -
Ts 1
T1 2.50 menit
T2 1.00 menit
Ts 1 3.50 menit
Q1 16.01 m3
( E 15 ) 0.0625 Jam
( E 09 )
V 6.00 m3
Fa 0.83 -
v1 45.00 km / jam
v2 60.00 km / jam
Ts2
T1 26.65 menit
T2 19.99 menit
T3 3.00 menit
Q2 5.02 m3
( E 09 ) 0.1994 Jam
( E 13 )
Lh 50.00 m
b 2.40 m
Fa 0.83 -
v 4.00 km / jam
n 6.00 Lintas 3 x pp
Ts 3
T1 0.75 menit
T2 1.00 menit
Ts 3 1.75 menit
Q3 85.37 m3
( E 02 ) 0.0117 Jam
( E 19 )
v 3.00 km / jam
b 1.20 m
n 8.00 lintasan
Fa 0.83 -
Q4 56.03 m3
( E 19 ) 0.0178 Jam
( E 18 )
v 5.00 km/jam
b 1.50 m
n 4.00 lintasan
Fa 0.83 -
Q5 233.44 m3
( E 18 ) 0.0043 Jam
( E 23 )
v 4.00 m3
Wc 0.07 m3
n 1.00 kali
Fa 0.83 -
Q6 47.43 m3
( E 23 ) 0.0211 Jam
Lump sum
Q1 16.01 m3 / jam
Qt 112.05 m3
P 7.00 orang
M 1.00 orang
( L 01 ) 0.4373 jam
( L 03 ) 0.0625 jam
EREKAMAN ANALISA
RGA SATUAN
Analisa EI - 512
HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
0.4373 -
0.0625 -
0.7080 -
0.4920 -
0.0625 -
0.1994 -
0.0117 -
0.0178 -
0.0043 -
0.0211 -
1.0000 -
-
-
-
-
-
-
-
Analisa EI - 512
L 20.0 Km
t 0.15 m
Fk 1.20
Tk 7.00 Jam
M03 0.7080 m3
M04 0.4920 m3
( E 15 )
V 1.50 m3
Fb 0.90 -
Fa 0.83 -
Ts 1
T1 2.50 menit
T2 1.00 menit
Ts 1 3.50 menit
Q1 16.01 m3
( E 15 ) 0.0625 Jam
( E 09 )
V 6.00 m3
Fa 0.83 -
v1 45.00 km / jam
v2 60.00 km / jam
Ts2
T1 26.65 menit
T2 19.99 menit
T3 3.00 menit
Q2 5.02 m3
( E 09 ) 0.1994 Jam
( E 13 )
Lh 50.00 m
b 2.40 m
Fa 0.83 -
v 4.00 km / jam
n 6.00 Lintas 3 x pp
Ts 3
T1 0.75 menit
T2 1.00 menit
Ts 3 1.75 menit
Q3 85.37 m3
( E 02 ) 0.0117 Jam
( E 17 )
v 3.00 km / jam
b 1.20 m
n 8.00 lintasan
Fa 0.83 -
Q4 56.03 m3
( E 17 ) 0.0178 Jam
( E 18 )
v 5.00 km / jam
b 1.50 m
n 4.00 lintasan
Fa 0.83 -
Q5 233.44 m3
( E 18 ) 0.0043 Jam
( E 23 )
v 4.00 km / jam
Wc 0.07 m3
n 1.00 lintasan
Fa 0.83 -
Q6 47.43 m3
( E 23 ) 0.0211 Jam
Lump sum
Q1 16.01 m3 / jam
Qt 112.05 m3 / jam
P 7.00 orang
M 1.00 orang
( L 01 ) 0.4373 jam
( L 03 ) 0.0625 jam
EREKAMAN ANALISA
RGA SATUAN
Analisa EI - 612
HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
0.0301 -
0.0060 -
-
0.8880 -
0.2530 -
0.0030 -
0.0063 -
0.0030 -
-
-
-
-
Analisa EI - 612
L 20.00 Km
Tk 7.00 Jam
Fh 1.10 -
AS 77 % 100 Bagian
K 23 % 30 Bagian
D1 1.05 Kg / Lt
D2 0.80 Kg / Lt
PC 1.1000 Liter Campuran
M10 0.8880 Kg
M11 0.2530 Liter
( E 03 )
V 800.00 Liter
Fa 0.83 -
Ts 2.00 Jam
Q1 332.00 Liter
( E 03 ) 0.0030 Jam
( E 05 )
V 400.00 m2 / jam
Ap 0.40 Liter / m2
Q2 160.00 Liter
( E 05 ) 0.0063 Jam
( E 08 )
Q3 332.00 Liter
( E 08 ) 0.0030 Jam
Q4 332.00 Liter
Qt 2,324.00 Liter
P 10.00 orang
M 2.00 orang
( L 01 ) 0.0301 jam
( L 03 ) 0.0060 jam
EREKAMAN ANALISA
RGA SATUAN
HARGA JUMLAH
KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
0.0161 -
0.0040 -
-
0.0025 -
0.0040 -
0.0105 -
1.0000 -
-
-
-
-
Analisa EI - 33
Tk 7.00 Jam
Motor grader
( E 13 )
Lh 50.00 m
b 2.40 m
Fa 0.83 -
v 2.00 km / jam
n 6.00 Lintas 3 x pp
Ts 1
T1 1.50 menit
T2 1.00 menit
Ts 1 2.50 menit
Q1 398.40 m3
( E 02 ) 0.0025 Jam
( E 19 )
v 2.00 km / jam
b 1.20 m
n 8.00 lintasan
Fa 0.83 -
Q2 249.00 m3
( E 19 ) 0.0040 Jam
( E 23 )
v 4.00 m3
Wc 0.07 m3
n 2.00 kali
Fa 0.83 -
Q3 94.86 m3
( E 23 ) 0.0105 Jam
Lump sum
Q2 249.00 m3 / jam
Qt 1,743.00 m3
P 4.00 orang
M 1.00 orang
( L 01 ) 0.0161 jam
( L 03 ) 0.0040 jam
No. Macam Pekerjaan
(1) (2)
21 1.00 Unit Upah Pasang Box Panel dan Panel Kontrol 1 Unit
0.5000 org Tukang Listrik @ Rp.
0.7500 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
1.0000 ls Pasang Panel Kontrol @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
30 1.00 Unit Pekerjaan Pasang Baru Box Panel & Panel Kontrol + KWH 1300 VA
1.0000 Unit Box Panel 20x40x50 @ Rp.
3.0000 bh MCB 6 A @ Rp.
1.0000 bh MCB 10 A @ Rp.
0.3000 m1 Rel MCB @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m1 BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
3.4100 m1 Kabel NYY 3 x 6 Sqmm @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
1,300.00 VA Administrasi 900 - 2200 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
31 1.00 Unit Pekerjaan Pasang Baru Box Panel & Panel Kontrol + KWH 2200 VA
1.0000 Unit Box Panel 20x40x50 @ Rp.
3.0000 bh MCB 10 A @ Rp.
1.0000 bh MCB 16 A @ Rp.
0.3000 m1 Rel MCB @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m1 BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
3.4100 m1 Kabel NYY 3 x 6 Sqmm @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
2,200.00 VA Administrasi 900 - 2200 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
32 1.00 Unit Pekerjaan Pasang Baru Box Panel & Panel Kontrol + KWH 3500 VA
1.0000 Unit Box Panel 20x40x50 @ Rp.
3.0000 bh MCB 16 A @ Rp.
1.0000 bh MCB 20 A @ Rp.
0.3000 m1 Rel MCB @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m1 BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
3.4100 m1 Kabel NYY 3 x 6 Sqmm @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
3,500.00 VA Administrasi 3500 - 11000 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
33 1.00 Unit Pekerjaan Pasang Baru Box Panel & Panel Kontrol + KWH 4400 VA
1.0000 Unit Box Panel 20x40x50 @ Rp.
3.0000 bh MCB 20 A @ Rp.
1.0000 bh MCB 25 A @ Rp.
0.3000 m1 Rel MCB @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m1 BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
3.4100 m1 Kabel NYY 3 x 6 Sqmm @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
4,400.00 VA Administrasi 3500 - 11000 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
34 1.00 Unit Pekerjaan Pasang Baru Box Panel & Panel Kontrol + KWH 7700 VA
1.0000 Unit Box Panel 20x40x50 @ Rp.
3.0000 bh MCB 25 A @ Rp.
1.0000 bh MCB 35 A @ Rp.
0.3000 m1 Rel MCB @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m1 BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
3.4100 m1 Kabel NYY 3 x 6 Sqmm @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
7,700.00 VA Administrasi 3500 - 11000 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
35 1.00 Unit Pekerjaan Pasang Baru Box Panel & Panel Kontrol + KWH 11000 VA
1.0000 Unit Box Panel 20x40x50 @ Rp.
3.0000 bh MCB 35 A @ Rp.
1.0000 bh MCB 40 A @ Rp.
0.3000 m1 Rel MCB @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m1 BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
3.4100 m1 Kabel NYY 3 x 6 Sqmm @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
11,000.00 VA Administrasi 3500 - 11000 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
36 1.00 Unit Pekerjaan Pasang Baru Box Panel & Panel Kontrol + KWH 11000 VA (2
2.0000 Unit Box Panel 20x40x50 @ Rp.
4.0000 bh MCB 35 A @ Rp.
2.0000 bh MCB 40 A @ Rp.
0.6000 m1 Rel MCB @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m1 BC 6 mm @ Rp.
5.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
2.0000 bh Terminal Nol @ Rp.
4.0000 bh Sekering kecil @ Rp.
3.0000 m1 Kabel NYY 3 x 6 Sqmm @ Rp.
4.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
2.0000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
11,000.00 VA Administrasi 3500 - 11000 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
- - -
-
-
-
No. Macam Pekerjaan
(1) (2)
6 1.00 Gawang Pasang Kabel DX 2x10 Sqmm + Accessories (Gawang) untuk Lampu Ekoro
50.0000 m1 Kabel DX 2x10 Sqmm @ Rp.
2.0000 bh Stoping Buckle @ Rp.
2.0000 bh Wadge tape @ Rp.
0.3000 m1 Stainless Steel @ Rp.
1.0000 set Service Link dan Clamp @ Rp.
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
0.5000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
7 1.00 Gawang Pasang Kabel DX 2x16 Sqmm + Accessories (Gawang) untuk Lampu Ekoro
50.0000 m1 Kabel DX 2x16 Sqmm @ Rp.
2.0000 bh Stoping Buckle @ Rp.
2.0000 bh Wadge tape @ Rp.
0.5000 m 1
Stainless Steel @ Rp.
1.0000 set Service Link dan Clamp @ Rp.
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
0.5000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
8 32.00 m1 Pasang Kabel DX 2x10 Sqmm + Accessories (Gawang) untuk Lampu Ekoro
32.0000 m1 Kabel DX 2x10 Sqmm @ Rp.
2.0000 bh Stoping Buckle @ Rp.
2.0000 bh Wadge tape @ Rp.
0.3000 m1 Stainless Steel @ Rp.
1.0000 set Service Link dan Clamp @ Rp.
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
0.5000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
9 40.00 m1 Pasang Kabel DX 2x16 Sqmm + Accessories (Gawang) untuk Lampu PJU
40.0000 m1 Kabel DX 2x16 Sqmm @ Rp.
2.0000 bh Stoping Buckle @ Rp.
2.0000 bh Wadge tape @ Rp.
0.3000 m1 Stainless Steel @ Rp.
1.0000 set Service Link dan Clamp @ Rp.
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
0.5000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
22 1.00 m1 Pasang Kabel NYY 3x4 Sqmm dibawah Aspal dengan sistem bor
1.0000 m1 Pipa PVC 1" @ Rp.
1.0000 m1 Kabel NYY 3x4 Sqmm @ Rp.
1.0000 m1 Bor lubang dibawah aspal @ Rp.
0.0050 org Tukang Listrik @ Rp.
0.0050 org Pekerja @ Rp.
0.0050 org Mandor @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
23 1.00 m1 Pasang Kabel NYY 3x4 Sqmm dengan PVC tanpa galian
1.0000 m1 Kabel NYY 3x4 Sqmm @ Rp.
1.0000 m1 Pipa PVC 1" @ Rp.
0.0150 org Tukang Listrik @ Rp.
0.0250 org Pekerja @ Rp.
0.0050 org Mandor @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
24 1.00 Unit Upah Pasang Box Panel dan Panel Kontrol 1 Unit
0.5000 org Tukang Listrik @ Rp.
0.7500 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
1.0000 ls Pasang Panel Kontrol @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
35 1.00 Buah Pasang MCB Ampere + box tutup panel ukuran 30x30
1.0000 bh MCB 10 Ampere @ Rp.
1.0000 bh Tutup panel 30x30 @ Rp.
0.2500 org Tukang Listrik @ Rp.
0.2000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
38 1.00 Set Upah Pasang Stang Ornamen 2 meter + Lampu SRP 822/250 Watt Son
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.2500 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
39 1.00 Set Upah Pasang Stang Ornamen 2.2 meter + Lampu SRP 822/250 Watt Son
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.2500 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
40 1.00 Set Upah Pasang Stang Ornamen 6 meter + Lampu SRP 822/250 Watt Son
0.2500 org Tenaga Ahli @ Rp.
0.6500 org Tukang Listrik @ Rp.
2.5000 org Pekerja @ Rp.
0.3500 org Mandor @ Rp.
0.5500 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
41 1.00 Set Upah Pasang Tiang Octogonal Cabang 1, h= 7 meter + lampu SRP 822/250 W
0.4200 m3 Pondasi tiang beton bertulang @ Rp.
2.8500 org Pekerja @ Rp.
2.8500 org Tukang Listrik @ Rp.
2.0075 org Pengawas @ Rp.
1.0000 org Mandor @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
42 1.00 Set Upah Pasang Tiang Octogonal Cabang 1, h= 9 meter + lampu SRP 822/250 W
0.4200 m 3
Pondasi tiang beton bertulang @ Rp.
3.1000 org Pekerja @ Rp.
3.1000 org Tukang Listrik @ Rp.
2.5000 org Pengawas @ Rp.
1.2100 org Mandor @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
43 1.00 Set Upah Pasang Tiang Octogonal Cabang 2, h= 9 meter + lampu SRP 822/250 W
0.4200 m 3
Pondasi tiang beton bertulang @ Rp.
3.3000 org Pekerja @ Rp.
3.3000 org Tukang Listrik @ Rp.
2.5782 org Pengawas @ Rp.
1.2433 org Mandor @ Rp.
1.0000 ls Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
44 1.00 Set Upah Pasang Tiang Octogonal Cabang 3, h= 9 meter + lampu SRP 822/250 W
0.4200 m3 Pondasi tiang beton bertulang @ Rp.
3.8100 org Pekerja @ Rp.
3.8100 org Tukang Listrik @ Rp.
2.6626 org Pengawas @ Rp.
1.2650 org Mandor @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
45 1.00 Set Upah Pasang Tiang Octogonal Cabang 3, h= 11 meter + lampu SRP 822/250
0.4200 m 3
Pondasi tiang beton bertulang @ Rp.
4.2500 org Pekerja @ Rp.
4.2500 org Tukang Listrik @ Rp.
2.9287 org Pengawas @ Rp.
1.2939 org Mandor @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
46 1.00 Set Bongkar armatur pada stang ornamen existing + pasang Lampu SRP 822/70
0.7500 org Pengawas @ Rp.
0.8750 org Tukang Listrik @ Rp.
1.6995 org Pekerja @ Rp.
0.6798 org Mandor @ Rp.
0.0500 unit Retur material existing ke gudang Pemda @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
47 1.00 Set Bongkar armatur pada stang ornamen existing + pasang Lampu SRP 822/15
0.7500 org Pengawas @ Rp.
0.8750 org Tukang Listrik @ Rp.
1.6995 org Pekerja @ Rp.
0.8418 org Mandor @ Rp.
0.0500 unit Retur material existing ke gudang Pemda @ Rp.
1.0000 ls Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
48 1.00 Set Bongkar armatur pada stang ornamen existing + pasang Lampu SRP 822/25
0.7500 org Pengawas @ Rp.
0.8750 org Tukang Listrik @ Rp.
1.6995 org Pekerja @ Rp.
0.8418 org Mandor @ Rp.
0.0500 unit Retur material existing ke gudang Pemda @ Rp.
1.0000 ls Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
49 1.00 Set Bongkar komponen lama existing + pasang Lampu SRP 822/250 Watt SON
0.7500 org Pengawas @ Rp.
0.8750 org Tukang Listrik @ Rp.
1.6995 org Pekerja @ Rp.
0.7822 org Mandor @ Rp.
0.0500 unit Retur material existing ke gudang Pemda @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
50 1.00 Batang Pasang Stang ornamen 1 m + Lampu sekualitas SRP 810 SON 70 W
1.0000 bh Stang Ornamen GIP dia. 2" L= 1 m @ Rp.
1.0000 bh Armature IP 65 Komplit (sekualitas SRP 810 SON 70 W) @ Rp.
2.0000 bh Beugel @ Rp.
1.0000 bh MCB 4 A @ Rp.
1.0000 set Box MCB @ Rp.
2.0000 m 1
Kabel NYM 2 x 2.5 sqmm @ Rp.
2.0000 bh Banded @ Rp.
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.2500 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
51 1.00 Batang Pasang Stang ornamen 3 m + Armature IP 65 (sekualitas SGP 328 SON=T 1
1.0000 bh Stang Ornamen GIP dia. 2" L= 3 m @ Rp.
2.0000 bh Armature IP 65 (sekualitas SGP 328 SON-T 150 W) @ Rp.
2.0000 bh Beugel @ Rp.
1.0000 bh MCB 4 A @ Rp.
1.0000 bh Cover MCB @ Rp.
4.0000 m1 Kabel NYM 2 x 2.5 sqmm @ Rp.
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.2500 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
52 1.00 Batang Pasang Stang ornamen 3 m + Armature IP 65 (sekualitas SGP 328 SON-T 2
1.0000 bh Stang Ornamen GIP dia. 2" L = 3 m @ Rp.
1.0000 bh Armature IP 65 (sekualitas SGP 828 SON-T 250 W) @ Rp.
2.0000 bh Beugel @ Rp.
1.0000 bh MCB 4 A @ Rp.
1.0000 bh Cover MCB @ Rp.
4.0000 m 1
Kabel NYM 2 x 2.5 sqmm @ Rp.
2.0000 bh Banded @ Rp.
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.2500 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
55 1.00 Batang Pasang Tiang GIP Cb.1 2",3", 3", 4", h = 9 m / Tiang Bulat 7 m Cb.1 + Ump
1.0000 btg Tiang GIP Cb. 2 2", 3", 4", t = 7 m, tanam @ Rp.
1.0000 bh Umpak @ Rp.
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.2500 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
56 1.00 Batang Pasang Tiang GIP Cb.1 2",3", 3", 4", h = 9 m / Tiang Bulat 9 m Cb.1 + Ump
1.0000 btg Tiang GIP Cb. 2 2", 3", 4", t = 9 m, tanam @ Rp.
1.0000 bh Umpak @ Rp.
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.2500 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
57 1.00 Batang Pasang Kembali Tiang Bulat 7 m Cb.1 (GIP cb.1 2", 3", 4" h = 7 m) + Umpa
2.0000 bh Wadge tape @ Rp.
0.5000 m1 Stainless Steel @ Rp.
2.0000 bh Banded @ Rp.
1.0000 bh Umpak @ Rp.
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.2500 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
58 1.00 Batang Pasang Kembali Tiang Bulat 9 m Cb.1 (GIP cb.1 2", 3", 4" h = 7 m) + Umpa
2.0000 bh Wadge tape @ Rp.
0.5000 m1 Stainless Steel @ Rp.
2.0000 bh Banded @ Rp.
1.0000 bh Umpak @ Rp.
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.2500 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
64 1.00 Set Pasang Lp sorot Tango SMF 383 SON-T 150 Watt
1.0000 unit Armature Tango SMF 383 1xSON-T 150W SYMETRIC @ Rp.
1.0000 m1 Kabel NYM 2 x 2.5 Sqmm @ Rp.
1.0000 bh MCB 4 A @ Rp.
0.5000 org Tukang Listrik @ Rp.
0.7500 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
1.0000 set Alat Bantu Pasang/Bongkar - (Lampu, Armature, Stang) @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
65 1.00 Unit Pekerjaan Pasang Box Panel & Panel Kontrol + KWH 1300 VA
1.0000 Unit Box Panel 20x40x60 @ Rp.
4.0000 bh Beugel @ Rp.
6.0000 m1 Pipa Galvanis 1.5" @ Rp.
21.0000 m 1
Kabel DX 2 x 16 Sqmm @ Rp.
2.0000 bh Knee pipa PVC 1.5" @ Rp.
1.0000 bh Magnetik Kontraktor SN-20 @ Rp.
1.0000 bh Invoring @ Rp.
3.0000 bh MCB 6 A @ Rp.
1.0000 bh MCB 10 A @ Rp.
0.3000 m 1
Rel MCB @ Rp.
1.0000 bh Timer TB 388 @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m1 BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
0.5000 m 1
Pipa Spiral 1.5" @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel Box @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
1,300.00 VA Adminatrasi 900 - 2200 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
66 1.00 Unit Pekerjaan Pasang Box Panel & Panel Kontrol + KWH 2200 VA
1.0000 Unit Box Panel 20x40x60 @ Rp.
4.0000 bh Beugel @ Rp.
6.0000 m1
Pipa Galvanis 1.5" @ Rp.
21.0000 m1 Kabel DX 2 x 16 Sqmm @ Rp.
2.0000 bh Knee pipa PVC 1.5" @ Rp.
1.0000 bh Magnetik Kontraktor SN-20 @ Rp.
1.0000 bh Invoring @ Rp.
3.0000 bh MCB 10 A @ Rp.
1.0000 bh MCB 16 A @ Rp.
0.3000 m1 Rel MCB @ Rp.
1.0000 bh Timer TB 388 @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m1 BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
0.5000 m1 Pipa Spiral 1.5" @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel Box @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
2,200.00 VA Adminatrasi 900 - 2200 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
67 1.00 Unit Pekerjaan Pasang Box Panel & Panel Kontrol + KWH 3500 VA
1.0000 Unit Box Panel 20x40x60 @ Rp.
4.0000 bh Beugel @ Rp.
6.0000 m 1
Pipa Galvanis 1.5" @ Rp.
21.0000 m1 Kabel DX 2 x 16 Sqmm @ Rp.
2.0000 bh Knee pipa PVC 1.5" @ Rp.
1.0000 bh Magnetik Kontraktor SN-20 @ Rp.
1.0000 bh Invoring @ Rp.
3.0000 bh MCB 16 A @ Rp.
1.0000 bh MCB 20 A @ Rp.
0.3000 m1 Rel MCB @ Rp.
1.0000 bh Timer TB 388 @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m 1
BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
0.5000 m1 Pipa Spiral 1.5" @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel Box @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
3,500.00 VA Adminatrasi 3500 - 11000 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
68 1.00 Unit Pekerjaan Pasang Box Panel & Panel Kontrol + KWH 4400 VA
1.0000 Unit Box Panel 20x40x60 @ Rp.
4.0000 bh Beugel @ Rp.
6.0000 m 1
Pipa Galvanis 1.5" @ Rp.
21.0000 m 1
Kabel DX 2 x 16 Sqmm @ Rp.
2.0000 bh Knee pipa PVC 1.5" @ Rp.
1.0000 bh Magnetik Kontraktor SN-20 @ Rp.
1.0000 bh Invoring @ Rp.
3.0000 bh MCB 20 A @ Rp.
1.0000 bh MCB 25 A @ Rp.
0.3000 m 1
Rel MCB @ Rp.
1.0000 bh Timer TB 388 @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m 1
BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
0.5000 m 1
Pipa Spiral 1.5" @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel Box @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
4,400.00 VA Adminatrasi 3500 - 11000 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
69 1.00 Unit Pekerjaan Pasang Box Panel & Panel Kontrol + KWH 7700 VA
1.0000 Unit Box Panel 20x40x60 @ Rp.
4.0000 bh Beugel @ Rp.
6.0000 m1 Pipa Galvanis 1.5" @ Rp.
21.0000 m1
Kabel DX 2 x 16 Sqmm @ Rp.
2.0000 bh Knee pipa PVC 1.5" @ Rp.
1.0000 bh Magnetik Kontraktor SN-20 @ Rp.
1.0000 bh Invoring @ Rp.
3.0000 bh MCB 25 A @ Rp.
1.0000 bh MCB 35 A @ Rp.
0.3000 m1 Rel MCB @ Rp.
1.0000 bh Timer TB 388 @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m1 BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
0.5000 m1 Pipa Spiral 1.5" @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel Box @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
7,700.00 VA Adminatrasi 3500 - 11000 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
70 1.00 Unit Pekerjaan Pasang Box Panel & Panel Kontrol + KWH 11000 VA
1.0000 Unit Box Panel 20x40x60 @ Rp.
4.0000 bh Beugel @ Rp.
6.0000 m 1
Pipa Galvanis 1.5" @ Rp.
21.0000 m1 Kabel DX 2 x 16 Sqmm @ Rp.
2.0000 bh Knee pipa PVC 1.5" @ Rp.
1.0000 bh Magnetik Kontraktor SN-20 @ Rp.
1.0000 bh Invoring @ Rp.
3.0000 bh MCB 35 A @ Rp.
1.0000 bh MCB 40 A @ Rp.
0.3000 m1 Rel MCB @ Rp.
1.0000 bh Timer TB 388 @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m 1
BC 6 mm @ Rp.
3.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
1.0000 bh Terminal Nol @ Rp.
2.0000 bh Sekering kecil @ Rp.
0.5000 m1 Pipa Spiral 1.5" @ Rp.
3.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
1.5000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel Box @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
11,000.00 VA Adminatrasi 3500 - 11000 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
71 1.00 Unit Pekerjaan Pasang Box Panel & Panel Kontrol + KWH 11000 VA (2 Unit Box
2.0000 Unit Box Panel 20x40x50 @ Rp.
8.0000 bh Beugel @ Rp.
12.0000 m 1
Pipa Galvanis 1.5" @ Rp.
27.0000 m1 Kabel DX 2 x 16 Sqmm @ Rp.
2.0000 bh Knee pipa PVC 1.5" @ Rp.
2.0000 bh Magnetik Kontraktor SN-20 @ Rp.
1.0000 bh Invoring @ Rp.
4.0000 bh MCB 35 A @ Rp.
2.0000 bh MCB 40 A @ Rp.
0.6000 m1 Rel MCB @ Rp.
2.0000 bh Timer TB 388 @ Rp.
1.0000 btg Ground Rod (Galvanist) @ Rp.
3.0000 m 1
BC 6 mm @ Rp.
5.0000 bh Pilot Lamp @ Rp.
1.0000 ls Kabel Pengawatan Panel @ Rp.
2.0000 bh Terminal Nol @ Rp.
4.0000 bh Sekering kecil @ Rp.
0.5000 m1 Pipa Spiral 1.5" @ Rp.
3.0000 m 1
Kabel NYY 3 x 6 Sqmm @ Rp.
4.0000 org Pekerja @ Rp.
0.2500 org Tenaga Ahli @ Rp.
2.0000 org Tukang Listrik @ Rp.
0.5000 org Mandor @ Rp.
0.5000 set Alat Bantu Pasang/Bongkar - Panel Box @ Rp.
1.0000 ls Pasang Instalasi Panel @ Rp.
1.0000 ls Penyambungan Beban @ Rp.
11,000.00 VA Adminatrasi 3500 - 11000 VA @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
75 1.00 Batang Pasang armature (sekualitas SGP 328 SON 250W) - Komplit
1.0000 bh Armature IP 65 (sekualitas SGP 328 SON 250W) @ Rp.
2.0000 bh Beugel @ Rp.
1.0000 bh MCB 4 A @ Rp.
1.0000 bh Cover MCB @ Rp.
4.0000 m1 Kabel NYM 2 x 2.5 Sqmm @ Rp.
2.0000 bh Banded @ Rp.
0.5000 org Pengawas @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
79 1.00 Buah Bongkar lampu dan balast + Pasang Lampu SON-T 250W dan balast
1.0000 bh Lampu SON-T 250W 220V @ Rp.
1.0000 bh Balast SON 250w 220V @ Rp.
1.0000 bh Ignitor Metal Halide 250W 220V @ Rp.
0.0625 org Pengawas @ Rp.
0.1250 org Mandor @ Rp.
0.1750 org Tukang Listrik @ Rp.
0.3750 org Pekerja @ Rp.
0.1200 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
0.1250 jam Alat angkut @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
81 1.00 Unit Pasang Tiang Oktagonal Cb. 1, t=11m + Armature Komplit (sekualitas SGP
T 250 Symmetric - Kabel Udara
1.0000 btg Tiang lampu Octagonal Cb. 1, t=11m @ Rp.
1.0000 unit Armature IP 65 Komplit (sekualitas SGP 822 SON 250W) @ Rp.
1.0000 bh Armature Tango SMF 383 1xSON-T 250W Symmetric @ Rp.
2.0000 bh MCB 6 A @ Rp.
0.2000 m 1
Rel MCB @ Rp.
30.0000 m1 Kabel NYM 2 x 2.5 Sqmm @ Rp.
4.0000 bh Banded @ Rp.
0.4200 m 3
Pondasi tiang beton bertulang @ Rp.
4.2500 org Pekerja @ Rp.
4.2500 org Tukang Listrik @ Rp.
2.9287 org Pengawas @ Rp.
1.2939 org Mandor @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
82 1.00 Unit Pasang Tiang Oktagonal Cb. 1, t=11m + Armature Komplit (sekualitas SGP
1.0000 btg Tiang lampu Octagonal Cb. 1, t=11m @ Rp.
1.0000 unit Armature IP 65 Komplit (sekualitas SGP 822 SON 250W) @ Rp.
1.0000 bh MCB 6 A @ Rp.
0.1000 m1 Rel MCB @ Rp.
12.0000 m 1
Kabel NYM 2 x 2.5 Sqmm @ Rp.
0.4200 m 3
Pondasi tiang beton bertulang @ Rp.
4.2500 org Pekerja @ Rp.
4.2500 org Tukang Listrik @ Rp.
2.9287 org Pengawas @ Rp.
1.2939 org Mandor @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
83 1.00 Set Pasang Lampu Spot MMF 283 MHN TD 150W + Pondasi
1.0000 bh Armature Tango MMF 283 1xMHN-TD 70W Symmetric @ Rp.
1.0000 m1 Kabel NYM 2 x 2.5 Sqmm @ Rp.
1.0000 bh Cover MCB @ Rp.
1.0000 bh MCB 4 A @ Rp.
1.0000 bh Pondasi / Umpak @ Rp.
0.5000 org Tukang Listrik @ Rp.
0.7500 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.0600 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
84 1.00 Set Pasang Lampu Sorot Tango SMF 383 SON-T 150 Watt + Pondasi
1.0000 bh Armature Tango SMF 383 1x SON-T 150W Symmetric @ Rp.
1.0000 m1 Kabel NYM 2 x 2.5 Sqmm @ Rp.
1.0000 bh MCB 4 A @ Rp.
1.0000 bh Cover MCB @ Rp.
1.0000 bh Pondasi / Umpak @ Rp.
0.5000 org Tukang Listrik @ Rp.
0.7500 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.0600 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
93 1.00 Unit Pasang Tiang Oktagonal Cb. 1, t=11m + Armature Komplit (sekualitas SGP
1.0000 btg Tiang lampu Octagonal Cb. 1, t=11m @ Rp.
1.0000 unit Armature IP 65 Komplit (sekualitas SGP 822 HPIT 250W) @ Rp.
1.0000 bh MCB 6 A @ Rp.
0.1000 m 1
Rel MCB @ Rp.
12.0000 m 1
Kabel NYM 2 x 2.5 Sqmm @ Rp.
0.4200 m3 Pondasi tiang beton bertulang @ Rp.
4.2500 org Pekerja @ Rp.
4.2500 org Tukang Listrik @ Rp.
2.9287 org Pengawas @ Rp.
1.2939 org Mandor @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
98 1.00 Unit Pasang Armatur lampu saja (sekualitas SGP 328 SON 150W)
1.0000 bh MCB 4 A @ Rp.
1.0000 bh Cover MCB @ Rp.
0.5000 org Pengawas @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
100 1.00 Unit Bongkar dan Ganti Komponen lama pada Armature IP 65 (sekualitas SGP 3
1.0000 bh Lampu SON-T 150W 220V @ Rp.
1.0000 bh Balast SON 150W 220V @ Rp.
1.0000 bh Kapasitor 20 mF @ Rp.
1.0000 bh Ignitor Metal Halide 150W 220V @ Rp.
0.0625 org Pengawas @ Rp.
0.1250 org Mandor @ Rp.
0.1750 org Tukang Listrik @ Rp.
0.3750 org Pekerja @ Rp.
0.1200 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
0.1250 jam Alat angkut @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
106 1.00 Batang Pasang Lampu Sorot Tango SMF 383 Symetric CDMT-D 400 W
1.0000 Unit Armature Tango SMF 383 1xHPI-T 400W Symmetric @ Rp.
2.0000 bh Beugel @ Rp.
1.0000 bh MCB 4 A @ Rp.
1.0000 bh Cover MCB @ Rp.
4.0000 m1 Kabel NYM 2 x 2.5 Sqmm @ Rp.
2.0000 bh Banded @ Rp.
0.4000 org Pengawas @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
107 1.00 Batang Pasang Lampu Sorot Tango SMF 383 Symetric CDMT-D 150 W
1.0000 Unit Armature Tango SMF 383 1xHPI-T 400W Symmetric @ Rp.
2.0000 bh Beugel @ Rp.
1.0000 bh MCB 4 A @ Rp.
1.0000 bh Cover MCB @ Rp.
4.0000 m1 Kabel NYM 2 x 2.5 Sqmm @ Rp.
2.0000 bh Banded @ Rp.
0.4000 org Pengawas @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
108 1.00 Bh Bongkar lampu dan balast + pasang lampu SON 70W (setipe) dan balast
1.0000 bh Lampu SON 70W 220V @ Rp.
1.0000 bh Balast SON 70W 220V @ Rp.
1.0000 bh Kapasitor 12.5 mF @ Rp.
0.0625 org Pengawas @ Rp.
0.1250 org Mandor @ Rp.
0.1750 org Tukang Listrik @ Rp.
0.3750 org Pekerja @ Rp.
0.1200 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
0.1250 jam Alat angkut @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
110 1.00 Set Upah Pasang stang Ornamen 3 meter + Lampu SRP 822/250 Watt Son
0.1250 org Tenaga Ahli @ Rp.
0.5000 org Tukang Listrik @ Rp.
2.0000 org Pekerja @ Rp.
0.2500 org Mandor @ Rp.
0.2500 set Alat Bantu Pasang/Bongkar - Tiang PJU @ Rp.
1.0000 ttk Pengetesan dan Penyalaan @ Rp.
JUMLAH
JASA 10 %
JUMLAH
DIBULATKAN
118 1.00 m2 Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutu
0.1000 Kg Plamir tembok @ Rp.
0.1000 Kg Cat dasar @ Rp.
0.2600 Kg Cat penutup 2 x @ Rp.
0.0200 oh Pekerja @ Rp.
0.0630 oh Tukang Cat @ Rp.
0.0063 oh Kepala tukang @ Rp.
0.0025 oh Mandor @ Rp.
JUMLAH
DIBULATKAN
Upah Bahan Jumlah
(3) (4) (5)
-
-
-
- -
-
-
-
-
-
-
- -
-
-
-
-
-
-
- -
-
-
-
-
-
-
- -
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
- - -
-
-
-
n sistem bor
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
-
-
- -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
- - -
-
-
-
810 SON 70 W
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
H 1300 VA
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
H 2200 VA
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
H 3500 VA
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
H 4400 VA
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
H 7700 VA
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
H 11000 VA
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
Komplit (sekualitas SGP 328 SON-T 250W) + Lampu Tango SMF 383 1xSON-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
att + Pondasi
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
MT-D 400 W
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
MT-D 150 W
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
- - -
-
-
-
- - -
-
-
-
- -
-
-
-
- -
-
-
-
- - -
-
-
-
-
-
-
-
- - -
-
-
-
-
-
-
- - -
-
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru a Umur Ekonomis
b Jam Kerja dalam 1 Tahun
c Harga Alat
5 Alat yang dipakai a Umur Ekonomis
b Jam Kerja dalam 1 Tahun
c Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru a Umur Ekonomis
b Jam Kerja dalam 1 Tahun
c Harga Alat
5 Alat yang dipakai a Umur Ekonomis
b Jam Kerja dalam 1 Tahun
c Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru a Umur Ekonomis
b Jam Kerja dalam 1 Tahun
c Harga Alat
5 Alat yang dipakai a Umur Ekonomis
b Jam Kerja dalam 1 Tahun
c Harga Alat
II BIAYA PASTI PER JAM KERJA
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru Umur Ekonomis
Jam Kerja dalam 1 Tahun
Harga Alat
5 Alat yang dipakai a Umur Ekonomis
b Jam Kerja dalam 1 Tahun
c Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
II BIAYA PASTI PER JAM KERJA
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
URAIAN ANALISA ALAT
No URAIAN
I URAIAN PERALATAN
1 Jenis Peralatan
2 Tenaga
3 Kapasitas
4 Alat Baru : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
5 Alat Yang Dipakai : a. Umur Ekonomis
b. Jam Kerja dalam 1 Tahun
c. Harga Alat
V LAIN LAIN
1 Tingkat suku bunga
2 Upah Operator / Sopir
3 Upah Pembantu Operator / Pembantu Sopir
4 Bahan bakar bensin
5 Bahan bakar solar
6 Minyak Pelumas
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
ISA ALAT
Pw 150.00 HP
Cp 50.00 Ton/jam
A 10.00 Tahun
W 1,500.00 Jam
B Rupiah
A' 10.00 Tahun Alat Baru
W' 1,500.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.24 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
H2 - Rupiah Khusus AMP
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rp
T - Rp
ISA ALAT
Pw 47.00 HP
Cp 6.00 Ton
A 6.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 6.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.30 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 15.00 HP
Cp 800.00 Liter
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 140.00 HP
Cp Ton
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 80.00 HP
Cp Ton
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 105.00 HP
Cp 1.50 Ton
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
Pw 50.00 HP
Cp 8.00 Ton
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 60.00 HP
Cp 10.00 Ton
A 5.00 Tahun
W 1,800.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 1,800.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 125.00 HP
Cp 8.00 Ton
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 175.00 HP
Cp 125.00 KVA
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 125.00 HP
Cp - -
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 75.00 HP
Cp 7.00 Ton
A 4.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 4.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.39 -
E - Rupiah
F - Rupiah
G - Rp
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rp
T - Rp
ISA ALAT
KODE KOEF. SATUAN KET.
Pw 100.00 HP
Cp 4,000.00 Liter
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rp
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rp
T - Rp
ISA ALAT
Pw 3.00 HP
Cp - Liter
A 4.00 Tahun
W 1,000.00 Jam
B Rupiah
A' 4.00 Tahun Alat Baru
W' 1,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.39 -
E - Rupiah
F - Rupiah
G - Rp
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rp
T - Rp
ISA ALAT
STAMPER E25
Pw 5.00 HP
Cp 0.17 Ton
A 4.00 Tahun
W 1,000.00 Jam
B Rupiah
A' 4.00 Tahun Alat Baru
W' 1,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.39 -
E - Rupiah
F - Rupiah
G - Rp
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rp
T - Rp
ISA ALAT
Pw 220.00 HP
Cp 50.00 Ton/Jam
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rp
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rp
T - Rp
ISA ALAT
Pw 55.00 HP
Cp 8.00 Ton
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rp
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rp
T - Rp
ISA ALAT
Pw 10.00 HP
Cp - -
A 4.00 Tahun
W 1,000.00 Jam
B Rupiah
A' 4.00 Tahun Alat Baru
W' 1,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.39 -
E - Rupiah
F - Rupiah
G - Rp
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rp
T - Rp
ISA ALAT
KODE KOEF. SATUAN KET.
Pw 15.00 HP
Cp 500.00 Liter
A 4.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 4.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.39 -
E - Rupiah
F - Rupiah
G - Rp
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rp
T - Rp
ISA ALAT
Pw 150.00 HP
Cp 15.00 Ton
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rp
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rp
T - Rp
ISA ALAT
Pw 100.00 HP
Cp 6.00 Ton
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 80.00 HP
Cp 0.50 M3
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 100.00 HP
Cp 4.00 M3
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 6.00 HP
Cp - -
A 2.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 2.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.65 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
ISA ALAT
Pw 75.00 HP
Cp - -
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
Pw 90.00 HP
Cp 1.60 M3
A 5.00 Tahun
W 2,000.00 Jam
B Rupiah
A' 5.00 Tahun Alat Baru
W' 2,000.00 Jam Alat Baru
B' - Rupiah Alat Baru
C - Rupiah
D 0.33 -
E - Rupiah
F - Rupiah
G - Rupiah
H1 - Rupiah
I - Rupiah
K - Rupiah
L - Rupiah
M - Rupiah
P - Rupiah
T - Rupiah
(i) 20.00 % / Tahun
U1 Rp / Jam
U2 Rp / Jam
Mb Liter
Ms Liter
Mp Liter
Dalam bahasa Indonesia
Rupiah
Terbilang :
Satu Milyar Dua Ratus Lima Puluh Juta Rupiah
In English
Rupiah
in Words :
One Billion Two Hundred Fifty Million Rupiah
'file:///conversion/tmp/activity_task_scratch/531966043.xlsx'#$Nominal THP 1
D
tch/531966043.xlsx'#$Nominal THP 1
Dalam bahasa Indonesia
In English
'file:///conversion/tmp/activity_task_scratch/531966043.xlsx'#$Nominal THP 2
D
tch/531966043.xlsx'#$Nominal THP 2
ANALISA HARGA SATUAN PEKERJAAN KONSTRUKSI
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
9 1.0000 m3 Membuat beton mutu f’c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
AK 326.0000 kg Portland Cement @ Rp. 1,100.00 358,600.00
0.5429 m3 Pasir beton @ Rp. 195,000.00 105,865.50
0.7622 m3 Kerikil beton (split) @ Rp. 290,000.00 221,038.00
215.0000 Liter Air @ Rp. 38.00 8,170.00
1.6500 oh Pekerja @ Rp. 57,250.00 94,462.50
0.2750 oh Tukang batu @ Rp. 65,000.00 17,875.00
0.0280 oh Kepala tukang @ Rp. 68,500.00 1,918.00
0.0830 oh Mandor @ Rp. 70,500.00 5,851.50
JUMLAH ( BELUM PPN ) 128,277.00 685,503.50 813,780.50
JASA 10 % 81,378.05
JUMLAH 895,158.55
DIBULATKAN 895,158.00
PEKERJAAN PLESTERAN
24 1.0000 m1 Sponengan (untuk saluran dan sejenisnya)
AK 0.3600 kg PC @ Rp. 1,250.00 450.00
0.0009 m3 Pasir pasang @ Rp. 80,000.00 68.80
0.0900 oh Pekerja @ Rp. 57,250.00 5,152.50
0.0300 oh Tukang batu @ Rp. 65,000.00 1,950.00
0.0030 oh Kep. Tk. Batu @ Rp. 68,500.00 205.50
0.0045 oh Mandor @ Rp. 70,500.00 317.25
JUMLAH ( BELUM PPN ) 7,625.25 518.80 8,144.05
JASA 10 % 814.41
JUMLAH 8,958.46
DIBULATKAN 8,958.00
PEKERJAAN CONBLOCK
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
1 Pipa Wavin S.8 Tekanan Nominal 12,5 bar (1,25 MPA). SNI 06-0084-2002 0,5" m1
0,75" m1
1" m1
1,25" m1
2 Pipa Wavin S.10 Tekanan Nominal 10 bar (1,0 MPA). SNI 06-0084-2002 0,5" m1
0,75" m1
1" m1
1,25" m1
1,5" m1
3 Pipa Wavin S.10 Tekanan Nominal 10 bar (1,0 MPA). SNI 06-0084-2002 2" m1
3" m1
4" m1
6" m1
8" m1
10" m1
12" m1
4 Pipa Wavin S.12,5 Tekanan Nominal 8 bar (0,8 MPA). SNI 06-0084-2002 2" m1
3" m1
4" m1
6" m1
8" m1
10" m1
12" m1
5 Pipa Wavin S.12,5 Tekanan Nominal 8 bar (0,8 MPA). SNI 06-0084-2002 1,5" m1
Pipa Wavin S.16 Tekanan Nominal 8 bar (0,8 MPA). SNI 06-0084-2002 2" m1
3" m1
4" m1
6" m1
8" m1
10" m1
12" m1
16" m1
20" m1
22" m1
6 Pipa Wavin S.20 Tekanan Nominal 5 bar (0,5 MPA). SNI 06-0084-2002 3" m1
4" m1
6" m1
7 Pipa Wavin S.8 Tekanan Nominal 12,5 bar (1,25 MPA). SNI 06-0084-2002 2" m1
3" m1
4" m1
6" m1
8" m1
10" m1
12" m1
8 Pipa PVC dia 0,50" Wavin 4m btg
Pipa PVC dia 0,75" Wavin 4m btg
Pipa PVC dia 1" Wavin 4m btg
Pipa PVC dia 1,25" Wavin 4m btg
Pipa PVC dia 1,50" Wavin 4m btg
Pipa PVC dia 2" Wavin 4m btg
Pipa PVC dia 2,50" Wavin 4m btg
Pipa PVC dia 3" Wavin 4m btg
Pipa PVC dia 4" Wavin 4m btg
9 Pipa Galvanis (Medium Class) 0,5" 6m btg
Pipa Galvanis (Medium Class) 0,75" 6m btg
Pipa Galvanis (Medium Class) 1" 6m btg
Pipa Galvanis (Medium Class) 1,25" 6m btg
Pipa Galvanis (Medium Class) 1,5" 6m btg
Pipa Galvanis (Medium Class) 2" 6m btg
Pipa Galvanis (Medium Class) 2,5" 6m btg
Pipa Galvanis (Medium Class) 3" 6m btg
Pipa Galvanis (Medium Class) 4" 6m btg
Pipa Galvanis (Medium Class) 5" 6m btg
Pipa Galvanis (Medium Class) 6" 6m btg
Pipa Galvanis (Medium Class) 8" tebal 6,35 mm 6m btg
Pipa Galvanis (Medium Class) 8" tebal 7,04 mm 6m btg
Pipa Galvanis (Medium Class) 8" tebal 8,16 mm 6m btg
Pipa Galvanis (Medium Class) 10" 6m btg
Pipa Galvanis (Medium Class) 12" tebal 9,53" 6m btg
Pipa Galvanis (Medium Class) 12" tebal 10,3" 6m btg
Pipa Galvanis (Medium Class) 14" tebal 9,53" 6m btg
Pipa Galvanis (Medium Class) 14" tebal 11,13" 6m btg
Pipa Galvanis (Medium Class) 16" 6m btg
Pipa Galvanis (Medium Class) 18" 6m btg
Pipa Galvanis (Medium Class) 20" 6m btg
Pipa Galvanis (Medium Class) 24" 6m btg
10 Pipa HDPE PN 10-SDR 17 SNI 06-4829-2005 PE 100 0,75" m1
1" m1
1,25" m1
1,5" m1
2" m1
2,5" m1
3" m1
4" m1
5" m1
6" m1
11 Bak Hidran Umum Fiberglass (FRP) 1 m3 bh
2 m3 bh
3 m3 bh
Bak Hidran Umum Fiberglass (FRP) Horizontal 6 m3 bh
12 Bak Hidran Umum Polyethylene (PE) 1 m3 bh
2 m3 bh
3 m3 bh
4 m3 bh
5 m3 bh
13 Water Meter Domestik 0,5" bh
0,75" bh
1" bh
1,5" bh
14 Stop Kran / Gate Valve Ulir Dalam 0,5" bh
0,75" bh
1" bh
1,5" bh
2" bh
15 Gate Valve All Flange CI 40 mm bh
50 mm bh
65 mm bh
80 mm bh
100 mm bh
125 mm bh
150 mm bh
200 mm bh
250 mm bh
16 Batu Kali Utuh Bulat m3
17 Batu Kali Belah Hitam m3
18 Batu Putih m3
19 Batu Bata 90x195x95 bh
20 Batu Bata 110x230x95 m3
21 Kayu Begesting m3
22 Kayu Bakar (Sekualitas Angsana) m3
23 Kayu Perancah m3
24 Kayu Papan 2x200x20 lbr
25 Kerb Beton (Tengah) m3
26 Kerb Beton (Tepi) m3
27 Bambu Apus btg
28 Bambu Petung btg
29 Batu Pecah Mesin 0,5-1cmm m3
30 Batu Pecah Mesin 1-2cm m3
31 Batu Pecah Mesin 2-3cm m3
32 Batu Pecah Mesin 3-4cm m3
33 Batu Pecah Mesin 5-7cm m3
34 Batu Pecah Tangan 1-2cm m3
35 Batu Pecah Tangan 2-3cm m3
36 Batu Pecah Tangan 3-4cm m3
37 Batu Pecah Tangan 5-7cm m3
38 Batu Krokos 1-1cm m3
39 Batu Krokos 1-2cm m3
40 Batu Koral 2-3cm m3
41 Batu Koral 3-4cm m3
42 Batu Koral 5-7cm m3
43 Filler kg
44 Pasir Pasang m3
45 Pasir Cor / beton m3
46 Pasir Saring m3
47 Pasir Urug m3
48 Tanah Urug m3
49 Sirtu m3
50 Buis Beton dia 20cm bh
51 Buis Beton dia 30cm bh
52 Buis Beton dia 40cm bh
53 Buis Beton dia 50cm bh
54 Buis Beton dia 60cm bh
55 Buis Beton dia 80cm bh
56 Buis Beton dia 100cm bh
57 Semen PC Holcim 40 kg zak
58 Semen PC Holcim 50 kg zak
59 Semen PC Gresik 40 kg zak
60 Semen PC Gresik 50 kg zak
61 Besi Beton Polos SNI kg
62 Besi Beton Ulir SNI kg
63 Bendrat kg
64 Cat Besi EMCO 1kg kg
65 Cat kayu EMCO 1kg kg
66 Cat Tembok Catylac 5kg galon
67 Cat Tembok Decolith 5kg galon
68 Meni Besi 1kg kg
69 Plamir Tembok 1kg kg
70 Kertas Gosok lbr
71 Pipa Besi Galvanis 2,5" 6m btg
72 Pipa Besi Galvanis 3" 6m btg
73 Pipa Besi Galvanis 4" 6m btg
74 Pipa Besi Galvanis 5" 6m btg
75 Kayu Lapis Triplek 92x244 4 mm lbr
76 Kayu Lapis Triplek 122x244 3 mm lbr
77 Kayu Lapis Triplek 122x244 4 mm lbr
78 Kayu Lapis Triplek 122x244 6 mm lbr
79 Kayu Lapis Triplek 122x244 9 mm lbr
80 Kayu Lapis Triplek 122x244 12 mm lbr
81 Kayu lapis Teakwood 90x120 4 mm lbr
82 Kayu lapis Teakwood 90x240 4 mm lbr
83 Paku Usuk kg
84 Paku Reng kg
85 Paku Gording kg
86 Paku Payung kg
87 Mur dan Baut kg
88 Begel Kuda-Kuda kg
89 Conblock Cetak Manual 6 cm m2
90 Conblock Cetak Mesin 6 cm m2
91 Besi Siku 50x50x5 6m btg
92 Besi Siku 70x70x7 6m btg
93 Kapur Bakar m3
94 Ijuk ikat
95 Tangki Air Standar Polyethylene (PE) 1200 lt bh
96 Tangki Air Standar Polyethylene (PE) 2300 lt bh
97 Tangki Air Standar Polyethylene (PE) 3000 lt bh
98 Keramik Lantai 30x30 m2
99 Batako 20x40x10 bh
100 Batu Bata 5,5x11x23 bh
101 Batu Tela 20x30x10 bh
102 Beton Roster / Kerawang bh
103 Papur Pasang Kawur m3
104 Asbes 100x100 3 mm lbr
105 Kayu Lapis 120x240 4 mm lbr
106 Bubungan Genteng Plenthong "SS" bh
107 Genteng Plenthong bh
108 Seng Datar BJLS 0,3 mm m1
109 Seng Gelombang Kecil lbr
110 Bubungan Asbes m1
111 Asbes Gelombang Kecil lbr
112 Kayu Balok Klas I m3
113 Kayu Balok Klas II (Bengkirai) m3
114 Kayu Papan Klas II (Bengkirai) m3
115 Kayu Papan Klas III (Kruing) m3
116 Kayu Papan Klas IV m3
117 Kayu Lapis 8"x4" 4 mm lbr
118 Kayu Lapis 8"x4" 12 mm lbr
119 Pipa GIP dia 1" m1
120 Pipa GIP dia 1,5" m1
121 Pipa GIP dia 2" m1
122 Klosed Duduk Keramik (Belum Termasuk Tempat Air) bh
123 Klosed Duduk Keramik (Belum Termasuk Aksesoris) unit
124 Cat Besi kg
125 Cat Dinding (Dekolith) kg
126 Cat Kayu kg
127 Kaca Bening 5mm m2
128 Sewa Alat Ukur hr
129 Besi strip kg
130 Seng plat 3" x 6" BJLS 24 lbr
131 Kayu dolken m3
132 Kayu dolken Ø 8 - 10/400 cm btg
133 Jendela nako bh
134 Kunci tanam bh
135 Ijuk m3
136 Paving segi 6 Natural t : 8 cm m2
137 Paving segi 6 Merah t : 8 cm m2
138 Paving segi 6 natural t : 6 cm m2
139 Paving Segi 6 Merah t : 6 cm m2
140 Thinner Liter
141 Amplas Lembar
142 Kusen alumunium 3' CA/slvr/std m'
143 Jendela casement silver (60 x 120) + kaca polos 5 mm Bh
144 Pintu swing + kaca polos 5 mm Bh
145 Pipa Galvanis Dim 0.5" 1 Btg
146 Pipa Galvanis Dim 1" 1 btg
147 Pipa Galvanis Dim 1.5" 1 btg
148 Pipa Galvanis Dim 2" 1 btg
149 Pipa Galvanis Dim 2.5" 1 btg
150 Pipa Galvanis Dim 3" 1 btg
151 Baut Dim 10mm Kg
152 Plat Besi Tebal 3mm Lmbr
153 Batu Tempel Hias Hitam/andhesit m2
154 Pipa Schedule Sch 40 Diameter 0.5 inch Stainless Steel 1 btg
155 Pipa Schedule Sch 40 Diameter 1 inch Stainless Steel 1 btg
156 Pipa Schedule Sch 40 Diameter 2 inch Stainless Steel 1 btg
157 Pipa Schedule Sch 40 Diameter 2.5 inch Stainless Steel 1 btg
158 Besi Siku 40 x40 cm t : 4mm bh
159 Ijuk Bh
160 sewa stamper hr
161 Kerb Tipe 60x22x20x18 cm bh
162 Kerb Tipe 40x20x15x10 cm bh
163 Gazebo kayu 2x2 m Bh
164 Siemese Connection bh
165 Pillar Hydrant unit
166 Box Hydrant + Kelengkapannya unit
167 Plat besi 10 mm Kg
168 Wermes 5M Lbr
169 Baja Ringan Metal Stud Btg
GRC ( 120 x 240 x 4 ) mm Lbr
AN TERTINGGI
3,500.00
5,700.00
Wavinsafe (socket lem)
9,100.00
12,000.00
3,100.00
4,600.00
7,300.00 Wavinsafe (socket lem)
11,600.00
17,800.00
28,100.00 Wavinsafe (socket lem)
58,300.00
87,700.00
183,700.00
Wavinlok (ring karet)
286,200.00
444,300.00
183,700.00
22,700.00 Wavinsafe (socket lem)
47,800.00
70,700.00
150,700.00
Wavinlok (ring karet)
232,700.00
363,000.00
580,000.00
15,300.00 Wavinsafe (socket lem)
19,300.00
38,300.00
Wavinsafe (socket lem)
56,200.00
118,400.00
190,500.00
294,400.00
468,200.00
Wavinlok (ring karet)
757,400.00
1,177,000.00
1,870,600.00
30,400.00
44,900.00 Wavinsafe (socket lem)
97,600.00
35,300.00
71,200.00
106,600.00
223,300.00 Wavinlok (ring karet)
Wavinlok (ring karet)
349,700.00
542,600.00
863,700.00
17,300.00
22,900.00
28,400.00
29,000.00
30,300.00
43,700.00
52,000.00
64,100.00
107,100.00
168,500.00
219,500.00
339,300.00
437,200.00
497,900.00
703,600.00
905,500.00
1,171,900.00
1,671,300.00
2,253,500.00
2,677,000.00
SNI NO.07-0039-87 /BS. 1387-
3,099,800.00
85
3,425,400.00
3,958,900.00
5,609,600.00
6,871,800.00
7,415,800.00
7,553,800.00
8,781,100.00
8,662,600.00
10,839,900.00
10,959,400.00
13,093,500.00
8,200.00
12,300.00
19,500.00
30,000.00
47,800.00
67,400.00
96,500.00
143,700.00
230,100.00
300,300.00
3,289,000.00
6,682,500.00
8,222,500.00
23,996,500.00
2,102,100.00
5,307,500.00
6,655,000.00
8,305,000.00
10,477,500.00
440,000.00
495,000.00
831,600.00
1,636,800.00
30,000.00
35,000.00
37,000.00
40,000.00
50,000.00
819,500.00
907,500.00
1,155,000.00
1,320,000.00
1,760,000.00
2,310,000.00
2,860,000.00
4,565,000.00
6,875,000.00
247,500.00
265,100.00
343,800.00
500.00
600.00
2,887,500.00
295,600.00 diameter minimal 10cm
3,872,000.00
22,400.00
61,400.00
28,900.00
20,600.00
123,800.00
288,800.00
309,400.00
293,300.00
302,500.00
295,600.00
292,600.00
268,100.00
261,300.00
260,700.00
336,900.00
330,000.00
275,000.00
292,600.00
315,700.00
1,400.00 Semen PC
200,000.00
244,000.00
300,400.00
144,100.00
82,500.00
158,100.00
59,400.00
68,800.00
73,200.00
75,600.00
79,800.00
91,300.00
11,200.00
60,500.00
72,600.00
60,500.00
72,600.00
18,700.00
18,700.00
18,400.00
52,800.00
67,600.00
91,400.00
104,400.00
24,100.00
18,200.00
3,300.00
1,027,800.00
557,400.00
894,000.00
1,440,800.00
72,400.00
74,000.00
94,200.00
128,500.00
178,100.00
246,600.00
106,200.00
132,300.00
22,200.00
22,700.00
19,300.00
26,100.00
19,600.00
44,400.00
34,600.00
43,500.00
141,600.00
232,900.00
259,500.00
7,200.00
1,600,000.00
3,000,000.00
3,250,000.00
46,500.00
2,200.00
800.00
5,800.00
197,700.00
16,800.00
66,000.00
5,500.00
1,300.00
13,800.00
73,300.00
30,000.00
88,000.00
20,911,700.00
10,599,000.00
8,880,200.00
6,302,100.00
5,442,700.00
6,440.00
151,300.00
233,900.00
346,500.00
470,700.00
389,300.00
2,875,000.00
57,000.00
16,300.00
67,600.00
89,600.00
100,000.00
30,250.00
47,700.00
3,435,000.00
12,500.00
28,500.00
40,000.00
800,000.00
57,900.00
68,750.00
45,800.00
56,800.00
12,000.00
2,000.00
60,000.00
450,000.00
1,000,000.00
155,000.00
300,000.00
455,000.00
620,000.00
790,000.00
1,020,000.00
12,000.00
455,000.00
125,000.00
289,900.00
569,520.00
680,400.00
913,920.00
300,000.00
9,000.00
120,000.00
50,000.00
30,000.00
14,500,000.00
2,350,000.00
2,625,000.00
2,520,000.00
30,000.00
220,000.00
39,000.00
60,000.00
ANALISA SATUAN PEKERJAAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
SNI 1.0000 m1 Pengukuran dan pemasangan bouwplank untuk gedung dan saluran
6.4 0.0120 m3 Kayu meranti 5/7 @ Rp. 19,000.00 228.00
03-2835-2002 0.0200 kg Paku reng @ Rp. 22,743.00 454.86
0.0070 m3 Kayu meranti papan 3/20 @ Rp. 32,500.00 227.50
0.1000 org Tukang kayu @ Rp. 82,500.00 8,250.00
0.0100 org Kepala tukang kayu @ Rp. 88,000.00 880.00
0.1000 org Pekerja @ Rp. 66,000.00 6,600.00
0.0050 org Mandor @ Rp. 88,000.00 440.00
JUMLAH ( BELUM PPN ) 16,170.00 910.36 17,080.36
JASA 10 % 1,617.00 91.04 1,708.04
JUMLAH 17,787.00 1,001.40 18,788.40
DIBULATKAN 17,787.00 1,001.00 18,788.00
A14 1.0000 m3 Mengangkut hasil galian dan bongkaran dengan dump truck jarak angkut 5 km
org Pekerja @ Rp. -
org Mandor @ Rp. -
0.2400 jam Dump truck @ Rp. 224,770.92 53,945.02
JUMLAH ( BELUM PPN ) - 53,945.02 53,945.02
JASA 10 % - 5,394.50 5,394.50
JUMLAH - 59,339.52
DIBULATKAN - 59,339.00
AK 1.0000 m2 Pasang usuk 5/7 kayu jati, reng 2/3 kayu bengkirai
2.2000 m1 Usuk kayu jati 5/7 @ Rp. -
5.0000 m1 Reng kayu bengkirai 2/3 @ Rp. 6,400.00 32,000.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. 82,500.00 8,250.00
0.0100 org Kep. Tk. Kayu @ Rp. 88,000.00 880.00
0.1000 org Pekerja @ Rp. 66,000.00 6,600.00
0.0025 org Mandor @ Rp. 88,000.00 220.00
JUMLAH ( BELUM PPN ) 15,950.00 37,604.60 53,554.60
JASA 10 % 1,595.00 3,760.46 5,355.46
JUMLAH 17,545.00 41,365.06 58,910.06
DIBULATKAN 17,545.00 41,365.00 58,910.00
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu jati
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 37,000.00 81,400.00
5.0000 m1 Reng jati 2/3 @ Rp. -
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. 82,500.00 8,250.00
0.0100 org Kep. Tk. Kayu @ Rp. 88,000.00 880.00
0.1000 org Pekerja @ Rp. 66,000.00 6,600.00
0.0025 org Mandor @ Rp. 88,000.00 220.00
JUMLAH ( BELUM PPN ) 15,950.00 87,004.60 102,954.60
JASA 10 % 1,595.00 8,700.46 10,295.46
JUMLAH 17,545.00 95,705.06 113,250.06
DIBULATKAN 17,545.00 95,705.00 113,250.00
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu bengkirai
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 37,000.00 81,400.00
5.0000 m1 Reng kayu bengkirai 2/3 @ Rp. 6,400.00 32,000.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. 82,500.00 8,250.00
0.0100 org Kep. Tk. Kayu @ Rp. 88,000.00 880.00
0.1000 org Pekerja @ Rp. 66,000.00 6,600.00
0.0025 org Mandor @ Rp. 88,000.00 220.00
JUMLAH ( BELUM PPN ) 15,950.00 119,004.60 134,954.60
JASA 10 % 1,595.00 11,900.46 13,495.46
JUMLAH 17,545.00 130,905.06 148,450.06
DIBULATKAN 17,545.00 130,905.00 148,450.00
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu jati lokal
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 37,000.00 81,400.00
4.0000 m1 Reng kayu jati 3/4 lokal @ Rp. -
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. 82,500.00 8,250.00
0.0100 org Kep. Tk. Kayu @ Rp. 88,000.00 880.00
0.1000 org Pekerja @ Rp. 66,000.00 6,600.00
0.0025 org Mandor @ Rp. 88,000.00 220.00
JUMLAH ( BELUM PPN ) 15,950.00 87,004.60 102,954.60
JASA 10 % 1,595.00 8,700.46 10,295.46
JUMLAH 17,545.00 95,705.06 113,250.06
DIBULATKAN 17,545.00 95,705.00 113,250.00
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu bengkirai
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 37,000.00 81,400.00
4.0000 m1 Reng kayu bengkirai 3/4 @ Rp. 6,400.00 25,600.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. 82,500.00 8,250.00
0.0100 org Kep. Tk. Kayu @ Rp. 88,000.00 880.00
0.1000 org Pekerja @ Rp. 66,000.00 6,600.00
0.0025 org Mandor @ Rp. 88,000.00 220.00
JUMLAH ( BELUM PPN ) 15,950.00 112,604.60 128,554.60
JASA 10 % 1,595.00 11,260.46 12,855.46
JUMLAH 17,545.00 123,865.06 141,410.06
DIBULATKAN 17,545.00 123,865.00 141,410.00
SNI 1.0000 m2 Pasang pintu teakwood rangkap, rangka kayu jati lokal
6.19 0.0196 m3 Papan kayu jati lokal @ Rp. -
03-3434-2002 0.0300 kg Paku biasa 1/2" - 1" @ Rp. -
0.3000 kg Lem kayu @ Rp. -
1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp. -
2.0000 org Tukang kayu @ Rp. 82,500.00 165,000.00
0.2000 org Kepala tukang kayu @ Rp. 88,000.00 17,600.00
0.6000 org Pekerja @ Rp. 66,000.00 39,600.00
0.0300 org Mandor @ Rp. 88,000.00 2,640.00
JUMLAH ( BELUM PPN ) 224,840.00 - 224,840.00
JASA 10 % 22,484.00 - 22,484.00
JUMLAH 247,324.00 - 247,324.00
DIBULATKAN 247,324.00 - 247,324.00
SNI 1.0000 m2 Pasang pintu dan jendela kaca kayu jati lokal
6.9 0.0350 m3 Papan kayu jati lokal @ Rp. 12,604,000.00 441,140.00
03-3434-2002 2.0000 org Tukang kayu @ Rp. 82,500.00 165,000.00
0.2000 org Kepala tukang kayu @ Rp. 88,000.00 17,600.00
0.8000 org Pekerja @ Rp. 66,000.00 52,800.00
0.0400 org Mandor @ Rp. 88,000.00 3,520.00
JUMLAH ( BELUM PPN ) 238,920.00 441,140.00 680,060.00
JASA 10 % 23,892.00 44,114.00 68,006.00
JUMLAH 262,812.00 485,254.00 748,066.00
DIBULATKAN 262,812.00 485,254.00 748,066.00
SNI 1.0000 m2 Mengerjakan daun pintu / jendela panil kayu jati lokal
6.7 0.0400 m3 Kayu jati papan lokal @ Rp. 12,604,000.00 504,160.00
03-3434-2002 2.5000 org Tukang kayu @ Rp. 82,500.00 206,250.00
0.2500 org Kepala tukang kayu @ Rp. 88,000.00 22,000.00
1.0000 org Pekerja @ Rp. 66,000.00 66,000.00
0.0500 org Mandor @ Rp. 88,000.00 4,400.00
JUMLAH ( BELUM PPN ) 298,650.00 504,160.00 802,810.00
JASA 10 % 29,865.00 50,416.00 80,281.00
JUMLAH 328,515.00 554,576.00 883,091.00
DIBULATKAN 328,515.00 554,576.00 883,091.00
PEKERJAAN PLAFOND
SNI 1.0000 m2 Pasang rangka langit-langit (1,00 x 1,00) m, kayu lama
03-3434-2002 0.1000 kg Paku biasa 2" - 5" @ Rp. -
0.2500 org Tukang kayu @ Rp. 82,500.00 20,625.00
0.0250 org Kepala tukang kayu @ Rp. 88,000.00 2,200.00
0.1500 org Pekerja @ Rp. 66,000.00 9,900.00
0.0075 org Mandor @ Rp. 88,000.00 660.00
JUMLAH ( BELUM PPN ) 33,385.00 - 33,385.00
JASA 10 % 3,338.50 - 3,338.50
JUMLAH 36,723.50 - 36,723.50
DIBULATKAN 36,723.00 - 36,723.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kamper tanpa plepet
0.0120 m3 Kayu kamper balok @ Rp. 8,880,200.00 106,562.40
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
0.3200 org Tukang kayu @ Rp. 82,500.00 26,400.00
0.0320 org Kepala tukang kayu @ Rp. 88,000.00 2,816.00
0.1800 org Pekerja @ Rp. 66,000.00 11,880.00
0.0090 org Mandor @ Rp. 88,000.00 792.00
JUMLAH ( BELUM PPN ) 41,888.00 106,562.40 148,450.40
JASA 10 % 4,188.80 10,656.24 14,845.04
JUMLAH 46,076.80 117,218.64 163,295.44
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
DIBULATKAN 46,076.00 117,218.00 163,295.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kruing tanpa plepet
0.0120 m3 Kayu kruing balok @ Rp. 6,302,000.00 75,624.00
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
0.3200 org Tukang kayu @ Rp. 82,500.00 26,400.00
0.0320 org Kepala tukang kayu @ Rp. 88,000.00 2,816.00
0.1800 org Pekerja @ Rp. 66,000.00 11,880.00
0.0090 org Mandor @ Rp. 88,000.00 792.00
JUMLAH ( BELUM PPN ) 41,888.00 75,624.00 117,512.00
JASA 10 % 4,188.80 7,562.40 11,751.20
JUMLAH 46,076.80 83,186.40 129,263.20
DIBULATKAN 46,076.00 83,186.00 129,263.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka bengkirai tanpa plepet
0.0120 m3 Kayu bengkirai balok @ Rp. 10,598,900.00 127,186.80
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
0.3200 org Tukang kayu @ Rp. 82,500.00 26,400.00
0.0320 org Kepala tukang kayu @ Rp. 88,000.00 2,816.00
0.1800 org Pekerja @ Rp. 66,000.00 11,880.00
0.0090 org Mandor @ Rp. 88,000.00 792.00
JUMLAH ( BELUM PPN ) 41,888.00 127,186.80 169,074.80
JASA 10 % 4,188.80 12,718.68 16,907.48
JUMLAH 46,076.80 139,905.48 185,982.28
DIBULATKAN 46,076.00 139,905.00 185,982.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kayu lama dg plepet
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
2.6000 m1 Plepet kayu @ Rp. -
0.0100 kg Paku eternit @ Rp. -
0.0100 kg Paku plepet @ Rp. -
0.3200 org Tukang kayu @ Rp. 82,500.00 26,400.00
0.0320 org Kepala tukang kayu @ Rp. 88,000.00 2,816.00
0.1800 org Pekerja @ Rp. 66,000.00 11,880.00
0.0090 org Mandor @ Rp. 88,000.00 792.00
JUMLAH ( BELUM PPN ) 41,888.00 - 41,888.00
JASA 10 % 4,188.80 - 4,188.80
JUMLAH 46,076.80 - 46,076.80
DIBULATKAN 46,076.00 - 46,076.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kayu kamper dg plepet
0.0120 m3 Kayu kamper balok @ Rp. 8,880,200.00 106,562.40
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
2.6000 m1 Plepet kayu @ Rp. -
0.0100 kg Paku eternit @ Rp. -
0.0100 kg Paku plepet @ Rp. -
0.3200 org Tukang kayu @ Rp. 82,500.00 26,400.00
0.0320 org Kepala tukang kayu @ Rp. 88,000.00 2,816.00
0.1800 org Pekerja @ Rp. 66,000.00 11,880.00
0.0090 org Mandor @ Rp. 88,000.00 792.00
JUMLAH ( BELUM PPN ) 41,888.00 106,562.40 148,450.40
JASA 10 % 4,188.80 10,656.24 14,845.04
JUMLAH 46,076.80 117,218.64 163,295.44
DIBULATKAN 46,076.00 117,218.00 163,295.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kayu kruing dg plepet
0.0120 m3 Kayu kruing balok @ Rp. 6,302,000.00 75,624.00
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
2.6000 m1 Plepet kayu @ Rp. -
0.0100 kg Paku eternit @ Rp. -
0.0100 kg Paku plepet @ Rp. -
0.3200 org Tukang kayu @ Rp. 82,500.00 26,400.00
0.0320 org Kepala tukang kayu @ Rp. 88,000.00 2,816.00
0.1800 org Pekerja @ Rp. 66,000.00 11,880.00
0.0090 org Mandor @ Rp. 88,000.00 792.00
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
JUMLAH ( BELUM PPN ) 41,888.00 75,624.00 117,512.00
JASA 10 % 4,188.80 7,562.40 11,751.20
JUMLAH 46,076.80 83,186.40 129,263.20
DIBULATKAN 46,076.00 83,186.00 129,263.00
6.13 1.0000 m2 Langit2 gypsum t;l 9 mm, rangka 60 x 120 kayu kruing
0.0130 m3 Kayu kruing @ Rp. 6,302,000.00 81,926.00
0.3600 lbr Gypsum board 9 mm @ Rp. -
0.0500 roll Kasa gypsum @ Rp. -
0.4500 kg Tepung gypsum @ Rp. -
0.0030 kg Alkasit @ Rp. -
0.0500 kg Paku gypsum @ Rp. -
0.1200 kg Paku usuk @ Rp. -
0.3700 org Tukang kayu @ Rp. 82,500.00 30,525.00
0.0370 org Kepala tukang kayu @ Rp. 88,000.00 3,256.00
0.2400 org Pekerja @ Rp. 66,000.00 15,840.00
0.0120 org Mandor @ Rp. 88,000.00 1,056.00
JUMLAH ( BELUM PPN ) 50,677.00 81,926.00 132,603.00
JASA 10 % 5,067.70 8,192.60 13,260.30
JUMLAH 55,744.70 90,118.60 145,863.30
DIBULATKAN 55,744.00 90,118.00 145,863.00
6.13 1.0000 m2 Langit2 kalsiboard t;l 3.5 mm, rangka 60 x 120 ky kruing
0.0130 m3 Kayu kruing @ Rp. 6,302,000.00 81,926.00
0.3600 lbr Kalsiboard 3.5 mm @ Rp. -
0.0500 roll Kasa gypsum @ Rp. -
0.4500 kg Tepung gypsum @ Rp. -
0.0030 kg Alkasit @ Rp. -
0.0500 kg Paku gypsum @ Rp. -
0.1200 kg Paku usuk @ Rp. -
0.3700 org Tukang kayu @ Rp. 82,500.00 30,525.00
0.0370 org Kepala tukang kayu @ Rp. 88,000.00 3,256.00
0.2400 org Pekerja @ Rp. 66,000.00 15,840.00
0.0120 org Mandor @ Rp. 88,000.00 1,056.00
JUMLAH ( BELUM PPN ) 50,677.00 81,926.00 132,603.00
JASA 10 % 5,067.70 8,192.60 13,260.30
JUMLAH 55,744.70 90,118.60 145,863.30
DIBULATKAN 55,744.00 90,118.00 145,863.00
PEKERJAAN LISPLANG
1.0000 m1 Pasang lisplank ukuran (2 x 20) cm, kayu jati
0.0048 m3 Kayu jati papan @ Rp. -
0.0600 kg Paku biasa 2" - 5" @ Rp. -
0.1000 org Tukang kayu @ Rp. 82,500.00 8,250.00
0.0100 org Kepala tukang kayu @ Rp. 88,000.00 880.00
0.1000 org Pekerja @ Rp. 66,000.00 6,600.00
0.0050 org Mandor @ Rp. 88,000.00 440.00
JUMLAH ( BELUM PPN ) 16,170.00 - 16,170.00
JASA 10 % 1,617.00 - 1,617.00
JUMLAH 17,787.00 - 17,787.00
DIBULATKAN 17,787.00 - 17,787.00
PEKERJAAN TALANG
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu kamper
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0096 m3 Kayu kamper papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 82,500.00 33,000.00
0.0250 org Kepala tukang kayu @ Rp. 88,000.00 2,200.00
0.1500 org Pekerja @ Rp. 66,000.00 9,900.00
0.0013 org Mandor @ Rp. 88,000.00 110.00
JUMLAH ( BELUM PPN ) 45,210.00 - 45,210.00
JASA 10 % 4,521.00 - 4,521.00
JUMLAH 49,731.00 - 49,731.00
DIBULATKAN 49,731.00 - 49,731.00
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu kruing
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0096 m3 Kayu kruing papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 82,500.00 33,000.00
0.0250 org Kepala tukang kayu @ Rp. 88,000.00 2,200.00
0.1500 org Pekerja @ Rp. 66,000.00 9,900.00
0.0013 org Mandor @ Rp. 88,000.00 110.00
JUMLAH ( BELUM PPN ) 45,210.00 - 45,210.00
JASA 10 % 4,521.00 - 4,521.00
JUMLAH 49,731.00 - 49,731.00
DIBULATKAN 49,731.00 - 49,731.00
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu bengkirai
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0096 m3 Kayui bengkirai papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 82,500.00 33,000.00
0.0250 org Kepala tukang kayu @ Rp. 88,000.00 2,200.00
0.1500 org Pekerja @ Rp. 66,000.00 9,900.00
0.0013 org Mandor @ Rp. 88,000.00 110.00
JUMLAH ( BELUM PPN ) 45,210.00 - 45,210.00
JASA 10 % 4,521.00 - 4,521.00
JUMLAH 49,731.00 - 49,731.00
DIBULATKAN 49,731.00 - 49,731.00
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu kamper
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0190 m3 Kayu kamper papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 82,500.00 33,000.00
0.0250 org Kepala tukang kayu @ Rp. 88,000.00 2,200.00
0.0400 org Pekerja @ Rp. 66,000.00 2,640.00
0.0013 org Mandor @ Rp. 88,000.00 110.00
JUMLAH ( BELUM PPN ) 37,950.00 - 37,950.00
JASA 10 % 3,795.00 - 3,795.00
JUMLAH 41,745.00 - 41,745.00
DIBULATKAN 41,745.00 - 41,745.00
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu kruing
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0190 m3 Kayu kruing papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 82,500.00 33,000.00
0.0250 org Kepala tukang kayu @ Rp. 88,000.00 2,200.00
0.0400 org Pekerja @ Rp. 66,000.00 2,640.00
0.0013 org Mandor @ Rp. 88,000.00 110.00
JUMLAH ( BELUM PPN ) 37,950.00 - 37,950.00
JASA 10 % 3,795.00 - 3,795.00
JUMLAH 41,745.00 - 41,745.00
DIBULATKAN 41,745.00 - 41,745.00
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu bengkirai
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0190 m3 Kayu bengkirai papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 82,500.00 33,000.00
0.0250 org Kepala tukang kayu @ Rp. 88,000.00 2,200.00
0.0400 org Pekerja @ Rp. 66,000.00 2,640.00
0.0013 org Mandor @ Rp. 88,000.00 110.00
JUMLAH ( BELUM PPN ) 37,950.00 - 37,950.00
JASA 10 % 3,795.00 - 3,795.00
JUMLAH 41,745.00 - 41,745.00
DIBULATKAN 41,745.00 - 41,745.00
SNI 1.0000 m2 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper
03-3434-2002 0.0195 m3 Kayu kamper balok @ Rp. -
6.56 0.0070 m3 Kayu kamper papan @ Rp. -
0.1000 kg Paku biasa 2" - 5" @ Rp. -
0.5600 kg Lem kayu @ Rp. -
1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp.
0.4500 org Tukang kayu @ Rp. 82,500.00 37,125.00
0.0450 org Kepala tukang kayu @ Rp. 88,000.00 3,960.00
0.1500 org Pekerja @ Rp. 66,000.00 9,900.00
0.0750 org Mandor @ Rp. 88,000.00 6,600.00
JUMLAH ( BELUM PPN ) 57,585.00 - 57,585.00
JASA 10 % 5,758.50 - 5,758.50
JUMLAH 63,343.50 - 63,343.50
DIBULATKAN 63,343.00 - 63,343.00
PEKERJAAN ATAP
H.2A 1.0000 m2 Pas. genteng beton besar Natural ( isi 9 / m2 ) untuk r. tingkat
9.0000 bh Genteng beton natural @ Rp. -
0.1000 org Tukang batu @ Rp. 77,000.00 7,700.00
0.0100 org Kep. Tk. Batu @ Rp. 82,500.00 825.00
0.3000 org Pekerja @ Rp. 66,000.00 19,800.00
0.0150 org Mandor @ Rp. 88,000.00 1,320.00
JUMLAH ( BELUM PPN ) 29,645.00 - 29,645.00
JASA 10 % 2,964.50 - 2,964.50
JUMLAH 32,609.50 - 32,609.50
DIBULATKAN 32,609.00 - 32,609.00
H.2A 1.0000 m2 Pas. genteng beton besar Warna ( isi 9 / m2 ) untuk r. tingkat
9.0000 bh Genteng beton Warna @ Rp. -
0.1000 org Tukang batu @ Rp. 77,000.00 7,700.00
0.0100 org Kep. Tk. Batu @ Rp. 82,500.00 825.00
0.3000 org Pekerja @ Rp. 66,000.00 19,800.00
0.0150 org Mandor @ Rp. 88,000.00 1,320.00
JUMLAH ( BELUM PPN ) 29,645.00 - 29,645.00
JASA 10 % 2,964.50 - 2,964.50
JUMLAH 32,609.50 - 32,609.50
DIBULATKAN 32,609.00 - 32,609.00
SNI 1.0000 m2 Pasang atap genteng metal zinc alume type prima roof
03-3436-2002 1.0200 m2 Genteng metal @ Rp. -
6.32 0.2000 kg Paku anti karat @ Rp. -
0.1000 org Tukang kayu @ Rp. 82,500.00 8,250.00
0.0100 org Kepala tukang kayu @ Rp. 88,000.00 880.00
0.2000 org Pekerja @ Rp. 66,000.00 13,200.00
0.0010 org Mandor @ Rp. 88,000.00 88.00
JUMLAH ( BELUM PPN ) 22,418.00 - 22,418.00
JASA 10 % 2,241.80 - 2,241.80
JUMLAH 24,659.80 - 24,659.80
DIBULATKAN 24,659.00 - 24,659.00
1.0000 m3 Mengangkut hasil galian dan bongkaran dengan dump truck jarak angkut 5 km
org Pekerja @ Rp. -
org Mandor @ Rp. -
0.2400 jam Dump truck @ Rp. 224,770.92 53,945.02
JUMLAH ( BELUM PPN ) - 53,945.02 53,945.02
JASA 10 % - 5,394.50 5,394.50
JUMLAH - 59,339.52
DIBULATKAN - 59,339.00
PEKERJAAN PELESTERAN
1.0000 m2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
0.1000 kg Plamir tembok @ Rp. 18,227.00 1,822.70
0.1000 kg Cat dasar @ Rp. 104,363.00 10,436.30
0.2600 kg Cat penutup 2 x @ Rp. 104,363.00 27,134.38
0.0630 org Tukang cat @ Rp. 77,000.00 4,851.00
0.0063 org Kepala tukang cat @ Rp. 82,500.00 519.75
0.0200 org Pekerja @ Rp. 66,000.00 1,320.00
0.0025 org Mandor @ Rp. 88,000.00 220.00
JUMLAH ( BELUM PPN ) 6,910.75 39,393.38 46,304.13
JASA 10 % 691.08 3,939.34 4,630.41
ANALISA SATUAN PEKERJAAN
PEKERJAAN PERSIAPAN
1.000 bh Membuat papan nama proyek
6.000 m' kayu meranti @ Rp. 19,000.00 114,000.00
1.000 unit Cetak banner @ Rp. 50,000.00 50,000.00
0.600 kg paku @ Rp. 22,202.00 13,321.20
16.800 kg PC @ Rp. 1,031.25 17,325.00
0.027 m3 Pasir beton @ Rp. 208,000.00 5,616.00
0.041 m3 kerikil bton @ Rp. 281,250.00 11,390.63
0.018 oh Tukang batu @ Rp. 60,000.00 1,050.00
0.500 oh Tukang kayu @ Rp. 60,000.00 30,000.00
1.000 oh Pekerja @ Rp. 52,000.00 52,000.00
0.018 oh Mandor @ Rp. 65,000.00 1,137.50
JUMLAH ( BELUM PPN ) 84,187.50 211,652.83 295,840.33
JASA 10 % 29,584.03
JUMLAH 325,424.36
DIBULATKAN 325,424.00
AN 1.1 Pekerjaan Galian Tanah
2 1.000 m3 Menggali tanah biasa sedalam 2 meter
SNI-2007 0.900 oh Pekerja @ Rp. 52,000.00 46,800.00
0.045 oh Mandor @ Rp. 65,000.00 2,925.00
jUMLAH ( BELUM PPN ) 49,725.00 - 49,725.00
JASA 10 % 4,972.50
jUMLAH 54,697.50
DIBULATKAN 54,697.00
AN 2.2
8 1.000 m3 Pekerjaan Urug kembali bekas galian
SNI-2002 0.192 oh Pekerja @ Rp. 52,000.00 9,984.00
0.019 oh Mandor @ Rp. 65,000.00 1,235.00
jUMLAH ( BELUM PPN ) 11,219.00 11,219.00
jASA 10 % 560.95
jUMLAH 11,779.95
DIBULATKAN 11,779.00
AN 2.3 10.000 m2 Pekerjaan Bongkaran lantai
SNI-2007
0.500 oh Pekerja @ Rp. 52,000.00 26,000.00
0.025 oh Mandor @ Rp. 65,000.00 1,625.00
JUMLAH ( BELUM PPN ) 27,625.00 - 27,625.00
JASA 10 % 2,762.50
JUMLAH 30,387.50
DIBULATKAN 30,387.00
AN 17.2 Keramik skualitas Mulia (300x300)
36 1.000 m2 keramik lantai
SNI-2007 1.068 m2 Lantai Roman Gress @ Rp. 38,500.00 41,118.00
10.000 kg Portland Cement @ Rp. 1,031.25 10,312.50
0.045 m3 Pasir Pasang @ Rp. 208,000.00 9,360.00
1.500 kg Semen warna @ Rp. 8,500.00 12,750.00
0.700 oh Pekerja @ Rp. 52,000.00 36,400.00
0.350 oh Tukang batu @ Rp. 60,000.00 21,000.00
0.035 oh Kepala tukang @ Rp. 62,500.00 2,187.50
0.035 oh Mandor @ Rp. 65,000.00 2,275.00
JUMLAH ( BELUM PPN ) 61,862.50 73,540.50 135,403.00
jASA 10 % 6,770.15
JUMLAH 142,173.15
DIBULATKAN 142,173.00
AN 18.2 Cat Interior
11 1.000 m2 Pengecatan Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup )
SNI-2002 0.100 Kg Plamir tembok @ Rp. 20,700.00 2,070.00
0.100 Kg Cat dasar @ Rp. 23,760.00 2,376.00
0.260 Kg Cat penutup 2 x @ Rp. 23,760.00 6,177.60
0.020 oh Pekerja @ Rp. 52,000.00 1,040.00
0.063 oh Tukang Cat @ Rp. 60,000.00 3,780.00
0.006 oh Kepala tukang @ Rp. 62,500.00 393.75
0.003 oh Mandor @ Rp. 65,000.00 162.50
JUMLAH ( BELUM TERMASUK PPN ) 5,376.25 10,623.60 15,999.85
jASA 10 % 799.99
JUMLAH 16,799.84
DIBULATKAN 16,799.00
PEKERJAAN SANITAIR
AN 13.3 1.000 bh Memasang Wastafel
SNI-2002 1.000 bh Wastafel @ Rp. 2,900,000.00 2,900,000.00
0.010 x Harga wastafel (Perlengkapan) @ Rp. - -
0.001 kg PC @ Rp. - -
0.001 m3 Pasir pasang @ Rp. - -
0.001 oh Pekerja @ Rp. 52,000.00 52.00
0.014 oh Tukang batu @ Rp. - -
0.015 oh Kepala tukang batu @ Rp. - -
0.010 oh Mandor @ Rp. - -
JUMLAH ( BELUM TERMASUK PPN ) 52.00 2,900,000.00 2,900,052.00
JASA 10 % 290,005.20
JUMLAH 3,190,057.20
DIBULATKAN 3,190,000.00
AN 13.7 1.000 bh Memasang Kran Ø ¾" atau ½"
SNI-2002 1.000 bh Kran air @ Rp. 45,000.00 45,000.00
0.025 bh Seal tape @ Rp. 2,500.00 62.50
0.010 oh Pekerja @ Rp. 52,000.00 520.00
0.100 oh Tukang batu @ Rp. 60,000.00 6,000.00
0.010 oh Kepala tukang batu @ Rp. 62,500.00 625.00
0.005 oh Mandor @ Rp. 65,000.00 325.00
JUMLAH ( BELUM TERMASUK PPN ) 7,470.00 45,062.50 52,532.50
jASA 10 % 5,253.25
JUMLAH 57,785.75
DIBULATKAN 57,785.00
PEKERJAAN PLUMBING
AN 14.1 1.000 m1 Memasang Pipa PVC Ø 3/4"
SNI-2002 1.200 m1 Pipa galvanis @ Rp. 21,000.00 25,200.00
0.350 x Harga pipa (Perlengkapan) @ Rp. 21,000.00 7,350.00
0.054 oh Pekerja @ Rp. 52,000.00 2,808.00
0.090 oh Tukang batu @ Rp. 60,000.00 5,400.00
0.009 oh Kepala tukang batu @ Rp. 62,500.00 562.50
0.027 oh Mandor @ Rp. 65,000.00 1,755.00
JUMLAH ( BELUM TERMASUK PPN ) 10,525.50 32,550.00 43,075.50
jASA 10 % 4,307.55
JUMLAH 47,383.05
DIBULATKAN 47,383.00
AN 14.4 1.000 m1 Memasang Pipa PVC tipe AW Ø 1"
SNI-2002 1.200 m1 Pipa PVC @ Rp. 9,342.50 11,211.00
0.350 x Harga pipa (Perlengkapan) @ Rp. 9,342.50 3,269.88
0.036 oh Pekerja @ Rp. 52,000.00 1,872.00
0.060 oh Tukang batu @ Rp. 60,000.00 3,600.00
0.006 oh Kepala tukang batu @ Rp. 62,500.00 375.00
0.002 oh Mandor @ Rp. 65,000.00 117.00
JUMLAH ( BELUM TERMASUK PPN ) 5,964.00 14,480.88 20,444.88
jASA 10 % 2,044.49
JUMLAH 22,489.36
DIBULATKAN 22,489.00
AN 14.5 1.000 m1 Memasang Pipa PVC tipe AW Ø 3"
SNI-2002 1.200 m1 Pipa PVC @ Rp. 20,625.00 24,750.00
0.350 x Harga pipa (Perlengkapan) @ Rp. 20,625.00 7,218.75
0.081 oh Pekerja @ Rp. 52,000.00 4,212.00
0.135 oh Tukang batu @ Rp. 60,000.00 8,100.00
0.014 oh Kepala tukang batu @ Rp. 62,500.00 843.75
0.004 oh Mandor @ Rp. 65,000.00 266.50
JUMLAH ( BELUM TERMASUK PPN ) 13,422.25 31,968.75 45,391.00
JASA 10 % 4,539.10
JUMLAH 49,930.10
DIBULATKAN 49,930.00
PEKERJAAN PERSIAPAN
AK 100.00 m2 Pekerjaan Pengukuran Gedung
8.0000 org Pekerja @ Rp. 52,520.00 420,160.00 -
2.0000 org Mandor @ Rp. 77,500.00 155,000.00 -
0.5000 org Pengawas @ Rp. 83,500.00 41,750.00 -
2.0000 org Asisten Ahli Ukur @ Rp. 250,000.00 500,000.00 -
1.0000 hr Sewa alat ukur @ Rp. 75,000.00 75,000.00 -
JUMLAH ( BELUM PPN ) 1,191,910.00 - 1,191,910.00
JASA 10 % 119,191.00 119,191.00
JUMLAH 1,311,101.00 1,311,101.00
DIBULATKAN 1,311,101.00 1,311,101.00
SNI 1.0000 m1 Pengukuran dan pemasangan bouwplank untuk gedung dan saluran
6.4 0.0120 m3 Kayu meranti 5/7 @ Rp. 2,000,000.00 24,000.00
03-2835-2002 0.0200 kg Paku reng @ Rp. 22,743.00 454.86
0.0070 m3 Kayu meranti papan 3/20 @ Rp. 2,000,000.00 14,000.00
0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00
0.0100 org Kepala tukang kayu @ Rp. 73,150.00 731.50
0.1000 org Pekerja @ Rp. 52,520.00 5,252.00
0.0050 org Mandor @ Rp. 77,500.00 387.50
JUMLAH ( BELUM PPN ) 11,871.00 38,454.86 50,325.86
JASA 10 % 1,187.10 3,845.49 5,032.59
JUMLAH 13,058.10 42,300.35 55,358.45
DIBULATKAN 13,058.00 42,300.00 55,358.00
SNI 1.0000 m1 Pembuatan pagar sementara dari seng gelombang tinggi 2 meter
6.2 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 15,000.00 18,750.00
03-2835-2002 2.5000 kg PC @ Rp. 1,650.00 4,125.00
1.2000 lbr Seng gelombang 2"-5" BJLS 24 @ Rp. 20,000.00 24,000.00
0.0050 m3 Pasir beton @ Rp. 133,000.00 665.00
0.0090 m3 Kerikil beton @ Rp. 121,000.00 1,089.00
0.0250 m3 Kaso 5/7 kayu meranti @ Rp. 2,000,000.00 50,000.00
0.0600 kg Paku biasa 2" - 5" @ Rp. 193,030.00 11,581.80
0.4000 kg Meni besi @ Rp. 24,090.00 9,636.00
0.2000 org Tukang kayu @ Rp. 55,000.00 11,000.00
0.0200 org Kepala tukang kayu @ Rp. 73,150.00 1,463.00
0.4000 org Pekerja @ Rp. 52,520.00 21,008.00
0.0200 org Mandor @ Rp. 77,500.00 1,550.00
JUMLAH ( BELUM PPN ) 35,021.00 119,846.80 154,867.80
JASA 10 % 3,502.10 11,984.68 15,486.78
JUMLAH 38,523.10 131,831.48 170,354.58
DIBULATKAN 38,523.00 131,831.00 170,354.00
PEKERJAAN TANAH
SNI 1.0000 m3 Galian tanah biasa sedalam sampai 1 meter
6.1 0.4000 org Pekerja @ Rp. 52,520.00 21,008.00
0.0400 org Mandor @ Rp. 77,500.00 3,100.00
JUMLAH ( BELUM PPN ) 24,108.00 - 24,108.00
JASA 10 % 2,410.80 2,410.80
JUMLAH 26,518.80 26,518.80
DIBULATKAN 26,518.00 26,518.00
PEKERJAAN PASANGAN
PEKERJAAN BETON
SNI 1.0000 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr -
6.13 336.0000 kg PC @ Rp. 1,650.00 554,400.00
0.5400 m3 Pasir beton @ Rp. 133,000.00 71,820.00
0.8100 m3 Kerikil beton @ Rp. 121,000.00 98,010.00
0.3500 org Tukang batu @ Rp. 63,800.00 22,330.00
0.0350 org Kepala tukang batu @ Rp. 71,500.00 2,502.50
2.0000 org Pekerja @ Rp. 52,520.00 105,040.00
0.1000 org Mandor @ Rp. 77,500.00 7,750.00
JUMLAH ( BELUM PPN ) 137,622.50 724,230.00 861,852.50
JASA 10 % 13,762.25 72,423.00 86,185.25
JUMLAH 151,384.75 796,653.00 948,037.75
DIBULATKAN 151,384.00 796,653.00 948,037.00
PEKERJAAN PELESTERAN
PEKERJAAN KERAMIK
An. 1.0000 m2 Pasang ubin porselin
G.69.c 1.0000 m2 Tegel porselin @ Rp. 55,000.00 55,000.00
4.6800 kg PC @ Rp. 1,650.00 7,722.00
0.0090 m3 Pasir pasang @ Rp. 133,000.00 1,197.00
1.0000 kg Semen putih @ Rp. 2,250.00 2,250.00
0.5000 org Tukang batu @ Rp. 63,800.00 31,900.00
0.0500 org Kep. Tk. Batu @ Rp. 71,500.00 3,575.00
0.2500 org Pekerja @ Rp. 52,520.00 13,130.00
0.0125 org Mandor @ Rp. 77,500.00 968.75
JUMLAH ( BELUM PPN ) 49,573.75 66,169.00 115,742.75
JASA 10 % 4,957.38 6,616.90 11,574.28
JUMLAH 54,531.13 72,785.90 127,317.03
DIBULATKAN 54,531.00 72,785.00 127,317.00
PEKERJAAN CONBLOCK
AK 1.0000 m2 Pasang usuk 5/7 kayu jati, reng 2/3 kayu bengkirai
2.2000 m1 Usuk kayu jati 5/7 @ Rp. 70,000.00 154,000.00
5.0000 m1 Reng kayu bengkirai 2/3 @ Rp. 4,500.00 22,500.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00
0.0100 org Kep. Tk. Kayu @ Rp. 73,150.00 731.50
0.1000 org Pekerja @ Rp. 52,520.00 5,252.00
0.0025 org Mandor @ Rp. 77,500.00 193.75
JUMLAH ( BELUM PPN ) 11,677.25 182,104.60 193,781.85
JASA 10 % 1,167.73 18,210.46 19,378.19
JUMLAH 12,844.98 200,315.06 213,160.04
DIBULATKAN 12,844.00 200,315.00 213,160.00
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu jati
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 26,250.00 57,750.00
5.0000 m1 Reng jati 2/3 @ Rp. 12,000.00 60,000.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00
0.0100 org Kep. Tk. Kayu @ Rp. 73,150.00 731.50
0.1000 org Pekerja @ Rp. 52,520.00 5,252.00
0.0025 org Mandor @ Rp. 77,500.00 193.75
JUMLAH ( BELUM PPN ) 11,677.25 123,354.60 135,031.85
JASA 10 % 1,167.73 12,335.46 13,503.19
JUMLAH 12,844.98 135,690.06 148,535.04
DIBULATKAN 12,844.00 135,690.00 148,535.00
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu bengkirai
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 26,250.00 57,750.00
5.0000 m1 Reng kayu bengkirai 2/3 @ Rp. 4,500.00 22,500.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00
0.0100 org Kep. Tk. Kayu @ Rp. 73,150.00 731.50
0.1000 org Pekerja @ Rp. 52,520.00 5,252.00
0.0025 org Mandor @ Rp. 77,500.00 193.75
JUMLAH ( BELUM PPN ) 11,677.25 85,854.60 97,531.85
JASA 10 % 1,167.73 8,585.46 9,753.19
JUMLAH 12,844.98 94,440.06 107,285.04
DIBULATKAN 12,844.00 94,440.00 107,285.00
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu jati lokal
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 26,250.00 57,750.00
4.0000 m1 Reng kayu jati 3/4 lokal @ Rp. 9,600.00 38,400.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00
0.0100 org Kep. Tk. Kayu @ Rp. 73,150.00 731.50
0.1000 org Pekerja @ Rp. 52,520.00 5,252.00
0.0025 org Mandor @ Rp. 77,500.00 193.75
JUMLAH ( BELUM PPN ) 11,677.25 101,754.60 113,431.85
JASA 10 % 1,167.73 10,175.46 11,343.19
JUMLAH 12,844.98 111,930.06 124,775.04
DIBULATKAN 12,844.00 111,930.00 124,775.00
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu bengkirai
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 26,250.00 57,750.00
4.0000 m1 Reng kayu bengkirai 3/4 @ Rp. 9,000.00 36,000.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00
0.0100 org Kep. Tk. Kayu @ Rp. 73,150.00 731.50
0.1000 org Pekerja @ Rp. 52,520.00 5,252.00
0.0025 org Mandor @ Rp. 77,500.00 193.75
JUMLAH ( BELUM PPN ) 11,677.25 99,354.60 111,031.85
JASA 10 % 1,167.73 9,935.46 11,103.19
JUMLAH 12,844.98 109,290.06 122,135.04
DIBULATKAN 12,844.00 109,290.00 122,135.00
SNI 1.0000 m2 Pasang pintu teakwood rangkap, rangka kayu jati lokal
6.19 0.0196 m3 Papan kayu jati lokal @ Rp. 8,200,000.00 160,720.00
03-3434-2002 0.0300 kg Paku biasa 1/2" - 1" @ Rp. 22,743.00 682.29
0.3000 kg Lem kayu @ Rp. 15,000.00 4,500.00
1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp. 69,500.00 69,500.00
2.0000 org Tukang kayu @ Rp. 55,000.00 110,000.00
0.2000 org Kepala tukang kayu @ Rp. 73,150.00 14,630.00
0.6000 org Pekerja @ Rp. 52,520.00 31,512.00
0.0300 org Mandor @ Rp. 77,500.00 2,325.00
JUMLAH ( BELUM PPN ) 158,467.00 235,402.29 393,869.29
JASA 10 % 15,846.70 23,540.23 39,386.93
JUMLAH 174,313.70 258,942.52 433,256.22
DIBULATKAN 174,313.00 258,942.00 433,256.00
SNI 1.0000 m2 Pasang pintu dan jendela kaca kayu jati lokal
6.9 0.0350 m3 Papan kayu jati lokal @ Rp. 8,200,000.00 287,000.00
03-3434-2002 2.0000 org Tukang kayu @ Rp. 55,000.00 110,000.00
0.2000 org Kepala tukang kayu @ Rp. 73,150.00 14,630.00
0.8000 org Pekerja @ Rp. 52,520.00 42,016.00
0.0400 org Mandor @ Rp. 77,500.00 3,100.00
JUMLAH ( BELUM PPN ) 169,746.00 287,000.00 456,746.00
JASA 10 % 16,974.60 28,700.00 45,674.60
JUMLAH 186,720.60 315,700.00 502,420.60
DIBULATKAN 186,720.00 315,700.00 502,420.00
SNI 1.0000 m2 Mengerjakan daun pintu / jendela panil kayu jati lokal
6.7 0.0400 m3 Kayu jati papan lokal @ Rp. 8,200,000.00 328,000.00
03-3434-2002 2.5000 org Tukang kayu @ Rp. 55,000.00 137,500.00
0.2500 org Kepala tukang kayu @ Rp. 73,150.00 18,287.50
1.0000 org Pekerja @ Rp. 52,520.00 52,520.00
0.0500 org Mandor @ Rp. 77,500.00 3,875.00
JUMLAH ( BELUM PPN ) 212,182.50 328,000.00 540,182.50
JASA 10 % 21,218.25 32,800.00 54,018.25
JUMLAH 233,400.75 360,800.00 594,200.75
DIBULATKAN 233,400.00 360,800.00 594,200.00
PEKERJAAN PLAFOND
SNI 1.0000 m2 Pasang rangka langit-langit (1,00 x 1,00) m, kayu lama
03-3434-2002 0.1000 kg Paku biasa 2" - 5" @ Rp. 22,202.00 2,220.20
0.2500 org Tukang kayu @ Rp. 55,000.00 13,750.00
0.0250 org Kepala tukang kayu @ Rp. 73,150.00 1,828.75
0.1500 org Pekerja @ Rp. 52,520.00 7,878.00
0.0075 org Mandor @ Rp. 77,500.00 581.25
JUMLAH ( BELUM PPN ) 24,038.00 2,220.20 26,258.20
JASA 10 % 2,403.80 222.02 2,625.82
JUMLAH 26,441.80 2,442.22 28,884.02
DIBULATKAN 26,441.00 2,442.00 28,884.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kamper tanpa plepet
0.0120 m3 Kayu kamper balok @ Rp. 7,500,000.00 90,000.00
03-2838-2002 0.0600 kg Paku biasa @ Rp. 23,000.00 1,380.00
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 16,775.00 18,452.50
0.3200 org Tukang kayu @ Rp. 55,000.00 17,600.00
0.0320 org Kepala tukang kayu @ Rp. 73,150.00 2,340.80
0.1800 org Pekerja @ Rp. 52,520.00 9,453.60
0.0090 org Mandor @ Rp. 77,500.00 697.50
JUMLAH ( BELUM PPN ) 30,091.90 109,832.50 139,924.40
JASA 10 % 3,009.19 10,983.25 13,992.44
JUMLAH 33,101.09 120,815.75 153,916.84
DIBULATKAN 33,101.00 120,815.00 153,916.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kruing tanpa plepet
0.0120 m3 Kayu kruing balok @ Rp. 6,302,000.00 75,624.00
03-2838-2002 0.0600 kg Paku biasa @ Rp. 23,000.00 1,380.00
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 16,775.00 18,452.50
0.3200 org Tukang kayu @ Rp. 55,000.00 17,600.00
0.0320 org Kepala tukang kayu @ Rp. 73,150.00 2,340.80
0.1800 org Pekerja @ Rp. 52,520.00 9,453.60
0.0090 org Mandor @ Rp. 77,500.00 697.50
JUMLAH ( BELUM PPN ) 30,091.90 95,456.50 125,548.40
JASA 10 % 3,009.19 9,545.65 12,554.84
JUMLAH 33,101.09 105,002.15 138,103.24
DIBULATKAN 33,101.00 105,002.00 138,103.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka bengkirai tanpa plepet
0.0120 m3 Kayu bengkirai balok @ Rp. 7,500,000.00 90,000.00
03-2838-2002 0.0600 kg Paku biasa @ Rp. 23,000.00 1,380.00
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 16,775.00 18,452.50
0.3200 org Tukang kayu @ Rp. 55,000.00 17,600.00
0.0320 org Kepala tukang kayu @ Rp. 73,150.00 2,340.80
0.1800 org Pekerja @ Rp. 52,520.00 9,453.60
0.0090 org Mandor @ Rp. 77,500.00 697.50
JUMLAH ( BELUM PPN ) 30,091.90 109,832.50 139,924.40
JASA 10 % 3,009.19 10,983.25 13,992.44
JUMLAH 33,101.09 120,815.75 153,916.84
DIBULATKAN 33,101.00 120,815.00 153,916.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kayu lama dg plepet
03-2838-2002 0.0600 kg Paku biasa @ Rp. 23,000.00 1,380.00
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 16,775.00 18,452.50
2.6000 m1 Plepet kayu @ Rp. 4,500.00 11,700.00
0.0100 kg Paku eternit @ Rp. 22,743.00 227.43
0.0100 kg Paku plepet @ Rp. 23,000.00 230.00
0.3200 org Tukang kayu @ Rp. 55,000.00 17,600.00
0.0320 org Kepala tukang kayu @ Rp. 73,150.00 2,340.80
0.1800 org Pekerja @ Rp. 52,520.00 9,453.60
0.0090 org Mandor @ Rp. 77,500.00 697.50
JUMLAH ( BELUM PPN ) 30,091.90 31,989.93 62,081.83
JASA 10 % 3,009.19 3,198.99 6,208.18
JUMLAH 33,101.09 35,188.92 68,290.01
DIBULATKAN 33,101.00 35,188.00 68,290.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kayu kamper dg plepet
0.0120 m3 Kayu kamper balok @ Rp. 7,500,000.00 90,000.00
03-2838-2002 0.0600 kg Paku biasa @ Rp. 23,000.00 1,380.00
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 16,775.00 18,452.50
2.6000 m1 Plepet kayu @ Rp. 4,500.00 11,700.00
0.0100 kg Paku eternit @ Rp. 22,743.00 227.43
0.0100 kg Paku plepet @ Rp. 23,000.00 230.00
0.3200 org Tukang kayu @ Rp. 55,000.00 17,600.00
0.0320 org Kepala tukang kayu @ Rp. 73,150.00 2,340.80
0.1800 org Pekerja @ Rp. 52,520.00 9,453.60
0.0090 org Mandor @ Rp. 77,500.00 697.50
JUMLAH ( BELUM PPN ) 30,091.90 121,989.93 152,081.83
JASA 10 % 3,009.19 12,198.99 15,208.18
JUMLAH 33,101.09 134,188.92 167,290.01
DIBULATKAN 33,101.00 134,188.00 167,290.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kayu kruing dg plepet
0.0120 m3 Kayu kruing balok @ Rp. 6,302,000.00 75,624.00
03-2838-2002 0.0600 kg Paku biasa @ Rp. 23,000.00 1,380.00
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. 16,775.00 18,452.50
2.6000 m1 Plepet kayu @ Rp. 4,500.00 11,700.00
0.0100 kg Paku eternit @ Rp. 22,743.00 227.43
0.0100 kg Paku plepet @ Rp. 23,000.00 230.00
0.3200 org Tukang kayu @ Rp. 55,000.00 17,600.00
0.0320 org Kepala tukang kayu @ Rp. 73,150.00 2,340.80
0.1800 org Pekerja @ Rp. 52,520.00 9,453.60
0.0090 org Mandor @ Rp. 77,500.00 697.50
JUMLAH ( BELUM PPN ) 30,091.90 107,613.93 137,705.83
JASA 10 % 3,009.19 10,761.39 13,770.58
JUMLAH 33,101.09 118,375.32 151,476.41
DIBULATKAN 33,101.00 118,375.00 151,476.00
6.13 1.0000 m2 Langit2 gypsum t;l 9 mm, rangka 60 x 120 kayu kruing
0.0130 m3 Kayu kruing @ Rp. 6,302,000.00 81,926.00
0.3600 lbr Gypsum board 9 mm @ Rp. 75,000.00 27,000.00
0.0500 roll Kasa gypsum @ Rp. 12,500.00 625.00
0.4500 kg Tepung gypsum @ Rp. 6,000.00 2,700.00
0.0030 kg Alkasit @ Rp. 350,000.00 1,050.00
0.0500 kg Paku gypsum @ Rp. 25,000.00 1,250.00
0.1200 kg Paku usuk @ Rp. 22,202.00 2,664.24
0.3700 org Tukang kayu @ Rp. 55,000.00 20,350.00
0.0370 org Kepala tukang kayu @ Rp. 73,150.00 2,706.55
0.2400 org Pekerja @ Rp. 52,520.00 12,604.80
0.0120 org Mandor @ Rp. 77,500.00 930.00
JUMLAH ( BELUM PPN ) 36,591.35 117,215.24 153,806.59
JASA 10 % 3,659.14 11,721.52 15,380.66
JUMLAH 40,250.49 128,936.76 169,187.25
DIBULATKAN 40,250.00 128,936.00 169,187.00
6.13 1.0000 m2 Langit2 kalsiboard t;l 3.5 mm, rangka 60 x 120 ky kruing
0.0130 m3 Kayu kruing @ Rp. 6,302,000.00 81,926.00
0.3600 lbr Kalsiboard 3.5 mm @ Rp. 65,000.00 23,400.00
0.0500 roll Kasa gypsum @ Rp. 12,500.00 625.00
0.4500 kg Tepung gypsum @ Rp. 6,000.00 2,700.00
0.0030 kg Alkasit @ Rp. 350,000.00 1,050.00
0.0500 kg Paku gypsum @ Rp. 25,000.00 1,250.00
0.1200 kg Paku usuk @ Rp. 22,202.00 2,664.24
0.3700 org Tukang kayu @ Rp. 55,000.00 20,350.00
0.0370 org Kepala tukang kayu @ Rp. 73,150.00 2,706.55
0.2400 org Pekerja @ Rp. 52,520.00 12,604.80
0.0120 org Mandor @ Rp. 77,500.00 930.00
JUMLAH ( BELUM PPN ) 36,591.35 113,615.24 150,206.59
JASA 10 % 3,659.14 11,361.52 15,020.66
JUMLAH 40,250.49 124,976.76 165,227.25
DIBULATKAN 40,250.00 124,976.00 165,227.00
PEKERJAAN LISPLANG
1.0000 m1 Pasang lisplank ukuran (2 x 20) cm, kayu jati
0.0048 m3 Kayu jati papan @ Rp. 22,000,000.00 105,600.00
0.0600 kg Paku biasa 2" - 5" @ Rp. 22,743.00 1,364.58
0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00
0.0100 org Kepala tukang kayu @ Rp. 73,150.00 731.50
0.1000 org Pekerja @ Rp. 52,520.00 5,252.00
0.0050 org Mandor @ Rp. 77,500.00 387.50
JUMLAH ( BELUM PPN ) 11,871.00 106,964.58 118,835.58
JASA 10 % 1,187.10 10,696.46 11,883.56
JUMLAH 13,058.10 117,661.04 130,719.14
DIBULATKAN 13,058.00 117,661.00 130,719.00
PEKERJAAN TALANG
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu kamper
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 45,000.00 22,500.00
0.0150 kg Paku biasa 1/2" - 1" @ Rp. 22,743.00 341.15
0.0096 m3 Kayu kamper papan @ Rp. 9,000,000.00 86,400.00
0.2500 kg Flincoat @ Rp. 40,000.00 10,000.00
0.4000 org Tukang kayu @ Rp. 55,000.00 22,000.00
0.0250 org Kepala tukang kayu @ Rp. 73,150.00 1,828.75
0.1500 org Pekerja @ Rp. 52,520.00 7,878.00
0.0013 org Mandor @ Rp. 77,500.00 96.88
JUMLAH ( BELUM PPN ) 31,803.63 119,241.15 151,044.77
JASA 10 % 3,180.36 11,924.11 15,104.48
JUMLAH 34,983.99 131,165.26 166,149.25
DIBULATKAN 34,983.00 131,165.00 166,149.00
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu kruing
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 45,000.00 22,500.00
0.0150 kg Paku biasa 1/2" - 1" @ Rp. 22,743.00 341.15
0.0096 m3 Kayu kruing papan @ Rp. 6,500,000.00 62,400.00
0.2500 kg Flincoat @ Rp. 40,000.00 10,000.00
0.4000 org Tukang kayu @ Rp. 55,000.00 22,000.00
0.0250 org Kepala tukang kayu @ Rp. 73,150.00 1,828.75
0.1500 org Pekerja @ Rp. 52,520.00 7,878.00
0.0013 org Mandor @ Rp. 77,500.00 96.88
JUMLAH ( BELUM PPN ) 31,803.63 95,241.15 127,044.77
JASA 10 % 3,180.36 9,524.11 12,704.48
JUMLAH 34,983.99 104,765.26 139,749.25
DIBULATKAN 34,983.00 104,765.00 139,749.00
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu bengkirai
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 45,000.00 22,500.00
0.0150 kg Paku biasa 1/2" - 1" @ Rp. 22,743.00 341.15
0.0096 m3 Kayui bengkirai papan @ Rp. 9,000,000.00 86,400.00
0.2500 kg Flincoat @ Rp. 40,000.00 10,000.00
0.4000 org Tukang kayu @ Rp. 55,000.00 22,000.00
0.0250 org Kepala tukang kayu @ Rp. 73,150.00 1,828.75
0.1500 org Pekerja @ Rp. 52,520.00 7,878.00
0.0013 org Mandor @ Rp. 77,500.00 96.88
JUMLAH ( BELUM PPN ) 31,803.63 119,241.15 151,044.77
JASA 10 % 3,180.36 11,924.11 15,104.48
JUMLAH 34,983.99 131,165.26 166,149.25
DIBULATKAN 34,983.00 131,165.00 166,149.00
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu kamper
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 45,000.00 22,500.00
0.0150 kg Paku biasa 1/2" - 1" @ Rp. 22,743.00 341.15
0.0190 m3 Kayu kamper papan @ Rp. 9,000,000.00 171,000.00
0.2500 kg Flincoat @ Rp. 40,000.00 10,000.00
0.4000 org Tukang kayu @ Rp. 55,000.00 22,000.00
0.0250 org Kepala tukang kayu @ Rp. 73,150.00 1,828.75
0.0400 org Pekerja @ Rp. 52,520.00 2,100.80
0.0013 org Mandor @ Rp. 77,500.00 96.88
JUMLAH ( BELUM PPN ) 26,026.43 203,841.15 229,867.57
JASA 10 % 2,602.64 20,384.11 22,986.76
JUMLAH 28,629.07 224,225.26 252,854.33
DIBULATKAN 28,629.00 224,225.00 252,854.00
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu kruing
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 45,000.00 22,500.00
0.0150 kg Paku biasa 1/2" - 1" @ Rp. 22,743.00 341.15
0.0190 m3 Kayu kruing papan @ Rp. 6,500,000.00 123,500.00
0.2500 kg Flincoat @ Rp. 40,000.00 10,000.00
0.4000 org Tukang kayu @ Rp. 55,000.00 22,000.00
0.0250 org Kepala tukang kayu @ Rp. 73,150.00 1,828.75
0.0400 org Pekerja @ Rp. 52,520.00 2,100.80
0.0013 org Mandor @ Rp. 77,500.00 96.88
JUMLAH ( BELUM PPN ) 26,026.43 156,341.15 182,367.57
JASA 10 % 2,602.64 15,634.11 18,236.76
JUMLAH 28,629.07 171,975.26 200,604.33
DIBULATKAN 28,629.00 171,975.00 200,604.00
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu bengkirai
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. 45,000.00 22,500.00
0.0150 kg Paku biasa 1/2" - 1" @ Rp. 22,743.00 341.15
0.0190 m3 Kayu bengkirai papan @ Rp. 9,000,000.00 171,000.00
0.2500 kg Flincoat @ Rp. 40,000.00 10,000.00
0.4000 org Tukang kayu @ Rp. 55,000.00 22,000.00
0.0250 org Kepala tukang kayu @ Rp. 73,150.00 1,828.75
0.0400 org Pekerja @ Rp. 52,520.00 2,100.80
0.0013 org Mandor @ Rp. 77,500.00 96.88
JUMLAH ( BELUM PPN ) 26,026.43 203,841.15 229,867.57
JASA 10 % 2,602.64 20,384.11 22,986.76
JUMLAH 28,629.07 224,225.26 252,854.33
DIBULATKAN 28,629.00 224,225.00 252,854.00
SNI 1.0000 m2 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper
03-3434-2002 0.0195 m3 Kayu kamper balok @ Rp. 7,500,000.00 146,250.00
6.56 0.0070 m3 Kayu kamper papan @ Rp. 9,000,000.00 63,000.00
0.1000 kg Paku biasa 2" - 5" @ Rp. 193,030.00 19,303.00
0.5600 kg Lem kayu @ Rp. 15,000.00 8,400.00
1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp. 69,500.00
0.4500 org Tukang kayu @ Rp. 55,000.00 24,750.00
0.0450 org Kepala tukang kayu @ Rp. 73,150.00 3,291.75
0.1500 org Pekerja @ Rp. 52,520.00 7,878.00
0.0750 org Mandor @ Rp. 77,500.00 5,812.50
JUMLAH ( BELUM PPN ) 41,732.25 236,953.00 278,685.25
JASA 10 % 4,173.23 23,695.30 27,868.53
JUMLAH 45,905.48 260,648.30 306,553.78
DIBULATKAN 45,905.00 260,648.00 306,553.00
PEKERJAAN ATAP
H.2A 1.0000 m2 Pas. genteng beton besar Natural ( isi 9 / m2 ) untuk r. tingkat
9.0000 bh Genteng beton natural @ Rp. 4,500.00 40,500.00
0.1000 org Tukang batu @ Rp. 63,800.00 6,380.00
0.0100 org Kep. Tk. Batu @ Rp. 71,500.00 715.00
0.3000 org Pekerja @ Rp. 52,520.00 15,756.00
0.0150 org Mandor @ Rp. 77,500.00 1,162.50
JUMLAH ( BELUM PPN ) 24,013.50 40,500.00 64,513.50
JASA 10 % 2,401.35 4,050.00 6,451.35
JUMLAH 26,414.85 44,550.00 70,964.85
DIBULATKAN 26,414.00 44,550.00 70,964.00
H.2A 1.0000 m2 Pas. genteng beton besar Warna ( isi 9 / m2 ) untuk r. tingkat
9.0000 bh Genteng beton Warna @ Rp. 5,700.00 51,300.00
0.1000 org Tukang batu @ Rp. 63,800.00 6,380.00
0.0100 org Kep. Tk. Batu @ Rp. 71,500.00 715.00
0.3000 org Pekerja @ Rp. 52,520.00 15,756.00
0.0150 org Mandor @ Rp. 77,500.00 1,162.50
JUMLAH ( BELUM PPN ) 24,013.50 51,300.00 75,313.50
JASA 10 % 2,401.35 5,130.00 7,531.35
JUMLAH 26,414.85 56,430.00 82,844.85
DIBULATKAN 26,414.00 56,430.00 82,844.00
SNI 1.0000 m2 Pasang atap genteng metal zinc alume type prima roof
03-3436-2002 1.0200 m2 Genteng metal @ Rp. 119,250.00 121,635.00
6.32 0.2000 kg Paku anti karat @ Rp. 25,000.00 5,000.00
0.1000 org Tukang kayu @ Rp. 55,000.00 5,500.00
0.0100 org Kepala tukang kayu @ Rp. 73,150.00 731.50
0.2000 org Pekerja @ Rp. 52,520.00 10,504.00
0.0010 org Mandor @ Rp. 77,500.00 77.50
JUMLAH ( BELUM PPN ) 16,813.00 126,635.00 143,448.00
JASA 10 % 1,681.30 12,663.50 14,344.80
JUMLAH 18,494.30 139,298.50 157,792.80
DIBULATKAN 18,494.00 139,298.00 157,792.00
PEKERJAAN CAT-CATAN
SNI 1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
6.8 0.2000 kg Cat meni @ Rp. 15,000.00 3,000.00
0.1500 kg Plamir @ Rp. 18,227.00 2,734.05
0.1700 kg Cat dasar @ Rp. 67,643.00 11,499.31
0.2600 kg Cat penutup @ Rp. 67,643.00 17,587.18
0.0900 org Tukang cat @ Rp. 62,700.00 5,643.00
0.0060 org Kepala tukang cat @ Rp. 69,300.00 415.80
0.0700 org Pekerja @ Rp. 52,520.00 3,676.40
0.0025 org Mandor @ Rp. 77,500.00 193.75
JUMLAH ( BELUM PPN ) 9,928.95 34,820.54 44,749.49
JASA 10 % 992.90 3,482.05 4,474.95
JUMLAH 10,921.85 38,302.59 49,224.44
DIBULATKAN 10,921.00 38,302.00 49,224.00
SNI 1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
6.9 0.2000 kg Cat meni @ Rp. 15,000.00 3,000.00
0.1500 kg Plamir @ Rp. 18,227.00 2,734.05
0.1700 kg Cat dasar @ Rp. 67,643.00 11,499.31
0.3500 kg Cat penutup @ Rp. 67,643.00 23,675.05
0.1050 org Tukang cat @ Rp. 62,700.00 6,583.50
0.0040 org Kepala tukang cat @ Rp. 69,300.00 277.20
0.0700 org Pekerja @ Rp. 52,520.00 3,676.40
0.0025 org Mandor @ Rp. 77,500.00 193.75
JUMLAH ( BELUM PPN ) 10,730.85 40,908.41 51,639.26
JASA 10 % 1,073.09 4,090.84 5,163.93
JUMLAH 11,803.94 44,999.25 56,803.19
DIBULATKAN 11,803.00 44,999.00 56,803.00
SNI 1.0000 m2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
6.14 0.1000 kg Plamir tembok @ Rp. 15,000.00 1,500.00
0.1000 kg Cat dasar @ Rp. 20,872.60 2,087.26
0.2600 kg Cat penutup 2 x @ Rp. 20,872.60 5,426.88
0.0630 org Tukang cat @ Rp. 62,700.00 3,950.10
0.0063 org Kepala tukang cat @ Rp. 69,300.00 436.59
0.0200 org Pekerja @ Rp. 52,520.00 1,050.40
0.0025 org Mandor @ Rp. 77,500.00 193.75
JUMLAH ( BELUM PPN ) 5,630.84 9,014.14 14,644.98
JASA 10 % 563.08 901.41 1,464.50
JUMLAH 6,193.92 9,915.55 16,109.47
DIBULATKAN 6,193.00 9,915.00 16,109.00
SNI 1.0000 m2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
6.15 0.1200 kg Cat dasar @ Rp. 20,872.60 2,504.71
0.1800 kg Cat penutup 2 x @ Rp. 20,872.60 3,757.07
0.0420 org Tukang cat @ Rp. 62,700.00 2,633.40
0.0042 org Kepala tukang cat @ Rp. 69,300.00 291.06
0.0280 org Pekerja @ Rp. 52,520.00 1,470.56
0.0025 org Mandor @ Rp. 77,500.00 193.75
JUMLAH ( BELUM PPN ) 4,588.77 6,261.78 10,850.55
JASA 10 % 458.88 626.18 1,085.06
JUMLAH 5,047.65 6,887.96 11,935.61
DIBULATKAN 5,047.00 6,887.00 11,935.00
SNI 1.0000 m2 Pengecatan tembok tidak terlindung dari panas dan hujan
6.14 0.1000 kg Cat alkali resisting primer @ Rp. 30,000.00 3,000.00
0.3600 kg Cat ICI Weathershield @ Rp. 55,000.00 19,800.00
0.0630 org Tukang cat @ Rp. 62,700.00 3,950.10
0.0063 org Kepala tukang cat @ Rp. 69,300.00 436.59
0.0200 org Pekerja @ Rp. 52,520.00 1,050.40
0.0025 org Mandor @ Rp. 77,500.00 193.75
JUMLAH ( BELUM PPN ) 5,630.84 22,800.00 28,430.84
JASA 10 % 563.08 2,280.00 2,843.08
JUMLAH 6,193.92 25,080.00 31,273.92
DIBULATKAN 6,193.00 25,080.00 31,273.00
SNI 1.0000 m2 Melabur tembok lama dengan kapur sirih (untuk pemeliharaan)
6.18 0.0020 m3 Perancah kayu @ Rp. 1,500,000.00 3,000.00
0.3000 kg Kapur sirih @ Rp. 600.00 180.00
0.0050 org Tukang cat @ Rp. 62,700.00 313.50
0.0005 org Kepala tukang cat @ Rp. 69,300.00 34.65
0.0400 org Pekerja @ Rp. 52,520.00 2,100.80
0.0025 org Mandor @ Rp. 77,500.00 193.75
JUMLAH ( BELUM PPN ) 2,642.70 3,180.00 5,822.70
JASA 10 % 264.27 318.00 582.27
JUMLAH 2,906.97 3,498.00 6,404.97
DIBULATKAN 2,906.00 3,498.00 6,404.00
SNI 1.0000 m2 Pengecacatan permukaan baja dengan meni besi memakai perancah
6.21 0.1000 kg Meni besi sinkromat @ Rp. 24,090.00 2,409.00
0.0100 bh Kuas @ Rp. 8,000.00 80.00
0.0020 m3 Perancah kayu @ Rp. 1,500,000.00 3,000.00
0.2250 org Tukang cat @ Rp. 62,700.00 14,107.50
0.0225 org Kepala tukang cat @ Rp. 69,300.00 1,559.25
0.2250 org Pekerja @ Rp. 52,520.00 11,817.00
0.0075 org Mandor @ Rp. 77,500.00 581.25
JUMLAH ( BELUM PPN ) 28,065.00 5,489.00 33,554.00
JASA 10 % 2,806.50 548.90 3,355.40
JUMLAH 30,871.50 6,037.90 36,909.40
DIBULATKAN 30,871.00 6,037.00 36,909.00
PEKERJAAN BONGKARAN
L.12 1.0000 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi
6.0000 org Tukang kayu @ Rp. 55,000.00 330,000.00
0.6000 org Kep. Tk. Kayu @ Rp. 73,150.00 43,890.00
4.0000 org Pekerja @ Rp. 52,520.00 210,080.00
0.2000 org Mandor @ Rp. 77,500.00 15,500.00
JUMLAH ( BELUM PPN ) 599,470.00 - 599,470.00
JASA 10 % 59,947.00 - 59,947.00
JUMLAH 659,417.00 - 659,417.00
DIBULATKAN 659,417.00 - 659,417.00
1.0000 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi
1.0000 org Pekerja @ Rp. 52,520.00 52,520.00
0.2000 org Mandor @ Rp. 77,500.00 15,500.00
JUMLAH ( BELUM PPN ) 68,020.00 - 68,020.00
JASA 10 % 6,802.00 - 6,802.00
JUMLAH 74,822.00 - 74,822.00
DIBULATKAN 74,822.00 - 74,822.00
ANALISA SUPLEMEN
PEKERJAAN SANITASI
SNI 1.0000 bh Memasang kloset duduk/monoblock
1.0000 bh Kloset duduk / monoblock @ Rp. 1,500,000.00 1,500,000.00
6.1 6% x Harga kloset (Perlengkapan) @ Rp. 1,500,000.00 90,000.00
1.1000 org Tukang batu @ Rp. 63,800.00 70,180.00
0.0010 org Kepala tukang batu @ Rp. 71,500.00 71.50
3.3000 org Pekerja @ Rp. 52,520.00 173,316.00
0.1600 org Mandor @ Rp. 77,500.00 12,400.00
JUMLAH ( BELUM PPN ) 255,967.50 1,590,000.00 1,845,967.50
JASA 10 % 25,596.75 159,000.00 184,596.75
JUMLAH 281,564.25 1,749,000.00 2,030,564.25
DIBULATKAN 281,564.00 1,749,000.00 2,030,564.00
SNI 1.0000 bh Memasang bak kontrol pas.bata (30 x 30) cm, tinggi 35 cm
87.0000 bh Batu bata @ Rp. 750.00 65,250.00
6.16 44.0000 kg PC @ Rp. 1,650.00 72,600.00
0.0700 m3 Pasir pasang @ Rp. 133,000.00 9,310.00
0.0700 m3 Batu kerikil @ Rp. 100,000.00 7,000.00
1.6000 kg Besi beton @ Rp. 10,110.00 16,176.00
0.0600 m3 Pasir beton @ Rp. 133,000.00 7,980.00
1.0150 org Tukang batu @ Rp. 63,800.00 64,757.00
0.0015 org Kepala tukang batu @ Rp. 71,500.00 107.25
3.2000 org Pekerja @ Rp. 52,520.00 168,064.00
0.0160 org Mandor @ Rp. 77,500.00 1,240.00
JUMLAH ( BELUM PPN ) 234,168.25 178,316.00 412,484.25
JASA 10 % 23,416.83 17,831.60 41,248.43
JUMLAH 257,585.08 196,147.60 453,732.68
Analisa Gedung - 442
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
DIBULATKAN 257,585.00 196,147.00 453,732.00
SNI 1.0000 bh Memasang bak kontrol pas. bata (45 x 45) cm, tinggi 50 cm
150.0000 bh Batu bata @ Rp. 750.00 112,500.00
6.17 77.0000 kg PC @ Rp. 1,650.00 127,050.00
0.1300 m3 Pasir pasang @ Rp. 133,000.00 17,290.00
0.0200 m3 Batu kerikil @ Rp. 100,000.00 2,000.00
2.6000 kg Besi beton @ Rp. 10,110.00 26,286.00
0.0900 m3 Pasir beton @ Rp. 133,000.00 11,970.00
0.4730 org Tukang batu @ Rp. 63,800.00 30,177.40
0.0470 org Kepala tukang batu @ Rp. 71,500.00 3,360.50
1.4200 org Pekerja @ Rp. 52,520.00 74,578.40
0.0710 org Mandor @ Rp. 77,500.00 5,502.50
JUMLAH ( BELUM PPN ) 113,618.80 297,096.00 410,714.80
JASA 10 % 11,361.88 29,709.60 41,071.48
JUMLAH 124,980.68 326,805.60 451,786.28
DIBULATKAN 124,980.00 326,805.00 451,786.00
SNI 1.0000 bh Memasang bak kontrol pas. bata (60 x 60) cm, tingg 65 cm
222.0000 bh Batu bata @ Rp. 750.00 166,500.00
6.18 114.0000 kg PC @ Rp. 1,650.00 188,100.00
0.1840 m3 Pasir pasang @ Rp. 133,000.00 24,472.00
0.0330 m3 Batu kerikil @ Rp. 100,000.00 3,300.00
4.8500 kg Besi beton @ Rp. 10,110.00 49,033.50
0.1200 m3 Pasir beton @ Rp. 133,000.00 15,960.00
0.7200 org Tukang batu @ Rp. 63,800.00 45,936.00
0.0720 org Kepala tukang batu @ Rp. 71,500.00 5,148.00
2.1600 org Pekerja @ Rp. 52,520.00 113,443.20
0.1000 org Mandor @ Rp. 77,500.00 7,750.00
JUMLAH ( BELUM PPN ) 172,277.20 447,365.50 619,642.70
JASA 10 % 17,227.72 44,736.55 61,964.27
JUMLAH 189,504.92 492,102.05 681,606.97
DIBULATKAN 189,504.00 492,102.00 681,606.00
TERBILANG :
Dua Milyar Dua Ratus Dua Puluh Satu Juta Seratus Enam Puluh Dua Ribu Rupiah
Dibuat oleh
Konsultan Perencana
Direktur
HIMPUNAN REKAPITULASI
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PENETAPAN KEBIJAKAN, STRATEGI DAN PROGRAM PERKOTAAN
PEKERJAAN : PENYUSUNAN DOKUMEN TEKNIS PENATAAN LINGKUNGAN ( DTPL )
LOKASI : PADUKUHAN BANARAN
TAHUN ANGGARAN : 2017
JUMLAH HARGA
NO. URAIAN PEKERJAAN
( Rp. )
I PERSIAPAN Rp 4,177,000.00
II PEMBUATAN JEMBATAN Rp 413,259,000.00
III PAVING BLOCK JALAN LINGKUNGAN Rp 352,913,000.00
IV PEMBUATAN GUDANG Rp 79,268,000.00
V PEMBUATAN RTH Rp 274,791,000.00
VI PEMBUATAN BANK SAMPAH Rp 28,898,000.00
VII PEMBUATAN GAPURA Rp 31,202,000.00
VIII PEMBUATAN ATAP KANOPI MAKAM Rp 16,843,000.00
IX PENERANGAN JALAN Rp 32,613,000.00
X PEMBUATAN SIGNAGE Rp 16,036,000.00
JUMLAH TOTAL 1,250,000,000.00
TERBILANG :
Satu Milyar Dua Ratus Lima Puluh Juta Rupiah
Dibuat oleh
Konsultan Perencana
Direktur
ANALISA SATUAN PEKERJAAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
PEKERJAAN PERSIAPAN
1.0000 m 2
Pekerjaan Pengukuran
0.01 x - - -
SNI 1.0000 m1 Pengukuran dan pemasangan bouwplank untuk gedung dan saluran
6.4 0.0120 m3 Kayu meranti 5/7 @ Rp. 4,440,000.00 53,280.00
03-2835-2002 0.0200 kg Paku reng @ Rp. 22,700.00 454.00
0.0070 m3 Kayu meranti papan 3/20 @ Rp. 5,040,000.00 35,280.00
0.1000 org Tukang kayu @ Rp. 90,000.00 9,000.00
0.0100 org Kepala tukang kayu @ Rp. 96,000.00 960.00
0.1000 org Pekerja @ Rp. 72,000.00 7,200.00
0.0050 org Mandor @ Rp. 96,000.00 480.00
JUMLAH ( BELUM PPN ) 17,640.00 89,014.00 106,654.00
JASA 10 % 1,764.00 8,901.40 10,665.40
JUMLAH 19,404.00 97,915.40 117,319.40
DIBULATKAN 19,404.00 97,915.00 117,319.00
SNI 1.0000 m 2
Membersihkan lapangan dan perataan
6.8 0.1000 org Pekerja @ Rp. 72,000.00 7,200.00
03-2835-2002 0.0500 org Mandor @ Rp. 96,000.00 4,800.00
JUMLAH ( BELUM PPN ) 12,000.00 - 12,000.00
JASA 10 % 1,200.00 1,200.00
JUMLAH 13,200.00 13,200.00
DIBULATKAN 13,200.00 13,200.00
SNI 1.0000 m1 Pembuatan pagar sementara dari seng gelombang tinggi 2 meter
6.2 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 12,500.00 15,625.00
03-2835-2002 2.5000 kg PC @ Rp. 1,452.00 3,630.00
1.2000 lbr Seng gelombang 2"-5" BJLS 24 @ Rp. 73,300.00 87,960.00
0.0050 m3 Pasir beton @ Rp. 104,400.00 522.00
0.0090 m3 Kerikil beton @ Rp. 309,400.00 2,784.60
0.0250 m3 Kaso 5/7 kayu meranti @ Rp. 4,440,000.00 111,000.00
0.0600 kg Paku biasa 2" - 5" @ Rp. 22,200.00 1,332.00
0.4000 kg Meni besi @ Rp. 24,100.00 9,640.00
0.2000 org Tukang kayu @ Rp. 90,000.00 18,000.00
0.0200 org Kepala tukang kayu @ Rp. 96,000.00 1,920.00
0.4000 org Pekerja @ Rp. 72,000.00 28,800.00
0.0200 org Mandor @ Rp. 96,000.00 1,920.00
JUMLAH ( BELUM PPN ) 50,640.00 232,493.60 283,133.60
JASA 10 % 5,064.00 23,249.36 28,313.36
JUMLAH 55,704.00 255,742.96 311,446.96
DIBULATKAN 55,704.00 255,742.00 311,446.00
PEKERJAAN TANAH
SNI 1.0000 m3 Galian tanah biasa sedalam sampai 1 meter
6.1 0.4000 org Pekerja @ Rp. 72,000.00 28,800.00
0.0400 org Mandor @ Rp. 96,000.00 3,840.00
JUMLAH ( BELUM PPN ) 32,640.00 - 32,640.00
JASA 10 % 3,264.00 3,264.00
JUMLAH 35,904.00 35,904.00
DIBULATKAN 35,904.00 35,904.00
SNI 1.0000 m 3
Galian tanah biasa sedalam 2 - 3 meter
6.3 0.7350 org Pekerja @ Rp. 72,000.00 52,920.00
0.0735 org Mandor @ Rp. 96,000.00 7,056.00
JUMLAH ( BELUM PPN ) 59,976.00 - 59,976.00
JASA 10 % 5,997.60 5,997.60
JUMLAH 65,973.60 65,973.60
DIBULATKAN 65,973.00 65,973.00
PEKERJAAN PASANGAN
SNI 1.0000 m 3
Pasangan pondasi 1 Pc : 3 Kp : 10 Ps
6.12 1.1000 m3 Batu belah (hitam) 15/20 cm @ Rp. 265,100.00 291,610.00
03-2835-2002 61.0000 kg PC @ Rp. 1,452.00 88,572.00
0.1470 m3 Kapurr pasang @ Rp. -
0.4920 m3 Pasir pasang @ Rp. 200,000.00 98,400.00
0.6000 org Tukang batu @ Rp. 84,000.00 50,400.00
0.0600 org Kepala tukang batu @ Rp. 96,000.00 5,760.00
1.5000 org Pekerja @ Rp. 72,000.00 108,000.00
0.0750 org Mandor @ Rp. 96,000.00 7,200.00
JUMLAH ( BELUM PPN ) 171,360.00 478,582.00 649,942.00
JASA 10 % 17,136.00 47,858.20 64,994.20
JUMLAH 188,496.00 526,440.20 714,936.20
DIBULATKAN 188,496.00 526,440.00 714,936.00
PEKERJAAN BETON
SNI 1.0000 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr
6.13 336.0000 kg PC @ Rp. 1,452.00 487,872.00
0.5400 m3 Pasir beton @ Rp. 244,000.00 131,760.00
0.8100 m3 Kerikil beton / koral @ Rp. 292,600.00 237,006.00
0.3500 org Tukang batu @ Rp. 84,000.00 29,400.00
0.0350 org Kepala tukang batu @ Rp. 96,000.00 3,360.00
2.0000 org Pekerja @ Rp. 72,000.00 144,000.00
0.1000 org Mandor @ Rp. 96,000.00 9,600.00
JUMLAH ( BELUM PPN ) 186,360.00 856,638.00 1,042,998.00
JASA 10 % 18,636.00 85,663.80 104,299.80
JUMLAH 204,996.00 942,301.80 1,147,297.80
DIBULATKAN 204,996.00 942,301.00 1,147,297.00
PEKERJAAN PELESTERAN
SNI 1.0000 m 2
Plesteran siar adukan 1 Pc : 2 Ps
6.35 4.3200 kg PC @ Rp. 1,452.00 6,272.64
03-2837-2002 0.0160 m3 Pasir pasang @ Rp. 200,000.00 3,200.00
0.0700 org Tukang batu @ Rp. 84,000.00 5,880.00
0.0070 org Kepala tukang batu @ Rp. 96,000.00 672.00
0.1500 org Pekerja @ Rp. 72,000.00 10,800.00
0.0080 org Mandor @ Rp. 96,000.00 768.00
JUMLAH ( BELUM PPN ) 18,120.00 9,472.64 27,592.64
JASA 10 % 1,812.00 947.26 2,759.26
JUMLAH 19,932.00 10,419.90 30,351.90
DIBULATKAN 19,932.00 10,419.00 30,351.00
PEKERJAAN KERAMIK
AK 1.0000 m 2
Pasang tegel keramik 20/20 dan 30/30
1.0000 m2 Tegel keramik (std) @ Rp. 46,500.00 46,500.00
4.0800 kg PC @ Rp. 1,452.00 5,924.16
0.0090 m3 Pasir pasang @ Rp. 200,000.00 1,800.00
0.6000 kg Semen putih @ Rp. -
0.5000 org Tukang batu @ Rp. 84,000.00 42,000.00
0.0500 org Kep. Tk. Batu @ Rp. 96,000.00 4,800.00
0.2500 org Pekerja @ Rp. 72,000.00 18,000.00
0.0125 org Mandor @ Rp. 96,000.00 1,200.00
JUMLAH ( BELUM PPN ) 66,000.00 54,224.16 120,224.16
JASA 10 % 6,600.00 5,422.42 12,022.42
JUMLAH 72,600.00 59,646.58 132,246.58
DIBULATKAN 72,600.00 59,646.00 132,246.00
SNI 1.0000 m 1
Pasang plint keramik ukuran 10 x 40 cm
6.24 0.2300 m2 Keramik 40/40 @ Rp. -
1.2000 kg PC @ Rp. 1,452.00 1,742.40
0.0030 m3 Pasir pasang @ Rp. 200,000.00 600.00
0.1000 kg Semen warna @ Rp. -
0.0300 org Tukang batu @ Rp. 84,000.00 2,520.00
0.0030 org Kepala tukang batu @ Rp. 96,000.00 288.00
0.0600 org Pekerja @ Rp. 72,000.00 4,320.00
0.0030 org Mandor @ Rp. 96,000.00 288.00
JUMLAH ( BELUM TERMASUK PPN ) 7,416.00 2,342.40 9,758.40
JASA 10 % 741.60 234.24 975.84
JUMLAH 8,157.60 2,576.64 10,734.24
DIBULATKAN 8,157.00 2,576.00 10,734.00
PEKERJAAN CONBLOCK
AK 1.0000 m 2
Pasang conblock tipe segi-enam abu-abu 6 cm, K-200
1.0000 m2 Conblock @ Rp. 45,800.00 45,800.00
0.0500 m3 Pasir urug @ Rp. 144,100.00 7,205.00
0.2500 org Tukang batu @ Rp. 84,000.00 21,000.00
0.0250 org Kep. Tk. Batu @ Rp. 96,000.00 2,400.00
0.5000 org Pekerja @ Rp. 72,000.00 36,000.00
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.0250 org Mandor @ Rp. 96,000.00 2,400.00
JUMLAH ( BELUM PPN ) 61,800.00 53,005.00 114,805.00
JASA 10 % 6,180.00 5,300.50 11,480.50
JUMLAH 67,980.00 58,305.50 126,285.50
DIBULATKAN 67,980.00 58,305.00 126,285.00
AK 1.0000 m2 Pasang usuk 5/7 kayu jati, reng 2/3 kayu bengkirai
2.2000 m1 Usuk kayu jati 5/7 @ Rp. -
5.0000 m1 Reng kayu bengkirai 2/3 @ Rp. -
0.1500 kg Paku usuk @ Rp. 22,200.00 3,330.00
0.1000 kg Paku reng @ Rp. 22,700.00 2,270.00
0.1000 org Tukang kayu @ Rp. 90,000.00 9,000.00
0.0100 org Kep. Tk. Kayu @ Rp. 96,000.00 960.00
0.1000 org Pekerja @ Rp. 72,000.00 7,200.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 17,400.00 5,600.00 23,000.00
JASA 10 % 1,740.00 560.00 2,300.00
JUMLAH 19,140.00 6,160.00 25,300.00
DIBULATKAN 19,140.00 6,160.00 25,300.00
AK 1.0000 m 2
Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu jati
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. -
5.0000 m1 Reng jati 2/3 @ Rp. -
0.1500 kg Paku usuk @ Rp. 22,200.00 3,330.00
0.1000 kg Paku reng @ Rp. 22,700.00 2,270.00
0.1000 org Tukang kayu @ Rp. 90,000.00 9,000.00
0.0100 org Kep. Tk. Kayu @ Rp. 96,000.00 960.00
0.1000 org Pekerja @ Rp. 72,000.00 7,200.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 17,400.00 5,600.00 23,000.00
JASA 10 % 1,740.00 560.00 2,300.00
JUMLAH 19,140.00 6,160.00 25,300.00
DIBULATKAN 19,140.00 6,160.00 25,300.00
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu bengkirai
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. -
5.0000 m 1
Reng kayu bengkirai 2/3 @ Rp. -
0.1500 kg Paku usuk @ Rp. 22,200.00 3,330.00
0.1000 kg Paku reng @ Rp. 22,700.00 2,270.00
0.1000 org Tukang kayu @ Rp. 90,000.00 9,000.00
0.0100 org Kep. Tk. Kayu @ Rp. 96,000.00 960.00
0.1000 org Pekerja @ Rp. 72,000.00 7,200.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 17,400.00 5,600.00 23,000.00
JASA 10 % 1,740.00 560.00 2,300.00
JUMLAH 19,140.00 6,160.00 25,300.00
DIBULATKAN 19,140.00 6,160.00 25,300.00
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu jati lokal
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. -
4.0000 m1 Reng kayu jati 3/4 lokal @ Rp. -
0.1500 kg Paku usuk @ Rp. 22,200.00 3,330.00
0.1000 kg Paku reng @ Rp. 22,700.00 2,270.00
0.1000 org Tukang kayu @ Rp. 90,000.00 9,000.00
0.0100 org Kep. Tk. Kayu @ Rp. 96,000.00 960.00
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.1000 org Pekerja @ Rp. 72,000.00 7,200.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 17,400.00 5,600.00 23,000.00
JASA 10 % 1,740.00 560.00 2,300.00
JUMLAH 19,140.00 6,160.00 25,300.00
DIBULATKAN 19,140.00 6,160.00 25,300.00
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu bengkirai
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. -
4.0000 m1 Reng kayu bengkirai 3/4 @ Rp. -
0.1500 kg Paku usuk @ Rp. 22,200.00 3,330.00
0.1000 kg Paku reng @ Rp. 22,700.00 2,270.00
0.1000 org Tukang kayu @ Rp. 90,000.00 9,000.00
0.0100 org Kep. Tk. Kayu @ Rp. 96,000.00 960.00
0.1000 org Pekerja @ Rp. 72,000.00 7,200.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 17,400.00 5,600.00 23,000.00
JASA 10 % 1,740.00 560.00 2,300.00
JUMLAH 19,140.00 6,160.00 25,300.00
DIBULATKAN 19,140.00 6,160.00 25,300.00
SNI 1.0000 m2 Pasang pintu teakwood rangkap, rangka kayu jati lokal
6.19 0.0196 m3 Papan kayu jati lokal @ Rp. -
03-3434-2002 0.0300 kg Paku biasa 1/2" - 1" @ Rp. -
0.3000 kg Lem kayu @ Rp. -
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp. -
2.0000 org Tukang kayu @ Rp. 90,000.00 180,000.00
0.2000 org Kepala tukang kayu @ Rp. 96,000.00 19,200.00
0.6000 org Pekerja @ Rp. 72,000.00 43,200.00
0.0300 org Mandor @ Rp. 96,000.00 2,880.00
JUMLAH ( BELUM PPN ) 245,280.00 - 245,280.00
JASA 10 % 24,528.00 - 24,528.00
JUMLAH 269,808.00 - 269,808.00
DIBULATKAN 269,808.00 - 269,808.00
SNI 1.0000 m2 Pasang pintu dan jendela kaca kayu jati lokal
6.9 0.0350 m3 Papan kayu jati lokal @ Rp. -
03-3434-2002 2.0000 org Tukang kayu @ Rp. 90,000.00 180,000.00
0.2000 org Kepala tukang kayu @ Rp. 96,000.00 19,200.00
0.8000 org Pekerja @ Rp. 72,000.00 57,600.00
0.0400 org Mandor @ Rp. 96,000.00 3,840.00
JUMLAH ( BELUM PPN ) 260,640.00 - 260,640.00
JASA 10 % 26,064.00 - 26,064.00
JUMLAH 286,704.00 - 286,704.00
DIBULATKAN 286,704.00 - 286,704.00
SNI 1.0000 m2 Mengerjakan daun pintu / jendela panil kayu jati lokal
6.7 0.0400 m3 Kayu jati papan lokal @ Rp. -
03-3434-2002 2.5000 org Tukang kayu @ Rp. 90,000.00 225,000.00
0.2500 org Kepala tukang kayu @ Rp. 96,000.00 24,000.00
1.0000 org Pekerja @ Rp. 72,000.00 72,000.00
0.0500 org Mandor @ Rp. 96,000.00 4,800.00
JUMLAH ( BELUM PPN ) 325,800.00 - 325,800.00
JASA 10 % 32,580.00 - 32,580.00
JUMLAH 358,380.00 - 358,380.00
DIBULATKAN 358,380.00 - 358,380.00
SNI 1.0000 m 2
Mengerjakan daun pintu / jendela panil kayu kamper
6.8 0.0400 m3 Kayu kamper papan @ Rp. -
03-3434-2002 2.5000 org Tukang kayu @ Rp. 90,000.00 225,000.00
0.2500 org Kepala tukang kayu @ Rp. 96,000.00 24,000.00
1.0000 org Pekerja @ Rp. 72,000.00 72,000.00
0.0500 org Mandor @ Rp. 96,000.00 4,800.00
JUMLAH ( BELUM PPN ) 325,800.00 - 325,800.00
JASA 10 % 32,580.00 - 32,580.00
JUMLAH 358,380.00 - 358,380.00
DIBULATKAN 358,380.00 - 358,380.00
SNI 1.0000 m 2
Mengerjakan daun pintu / jendela panil kayu kruing
0.0400 m3 Kayu kruing papan @ Rp. -
03-3434-2002 2.5000 org Tukang kayu @ Rp. 90,000.00 225,000.00
0.2500 org Kepala tukang kayu @ Rp. 96,000.00 24,000.00
1.0000 org Pekerja @ Rp. 72,000.00 72,000.00
0.0500 org Mandor @ Rp. 96,000.00 4,800.00
JUMLAH ( BELUM PPN ) 325,800.00 - 325,800.00
JASA 10 % 32,580.00 - 32,580.00
JUMLAH 358,380.00 - 358,380.00
DIBULATKAN 358,380.00 - 358,380.00
PEKERJAAN PLAFOND
SNI 1.0000 m2 Pasang rangka langit-langit (1,00 x 1,00) m, kayu lama
03-3434-2002 0.1000 kg Paku biasa 2" - 5" @ Rp. -
0.2500 org Tukang kayu @ Rp. 90,000.00 22,500.00
0.0250 org Kepala tukang kayu @ Rp. 96,000.00 2,400.00
0.1500 org Pekerja @ Rp. 72,000.00 10,800.00
0.0075 org Mandor @ Rp. 96,000.00 720.00
JUMLAH ( BELUM PPN ) 36,420.00 - 36,420.00
JASA 10 % 3,642.00 - 3,642.00
JUMLAH 40,062.00 - 40,062.00
DIBULATKAN 40,062.00 - 40,062.00
1.0000 m 2
Pasang rangka langit-langit (60 x 120) m, kayu bengkirai
0.0130 m3 Kayu bengkirai @ Rp. -
0.1200 kg Paku @ Rp. -
0.2700 org Tukang kayu @ Rp. 90,000.00 24,300.00
0.0270 org Kep. Tk. Kayu @ Rp. 96,000.00 2,592.00
0.1700 org Pekerja @ Rp. 72,000.00 12,240.00
0.0085 org Mandor @ Rp. 96,000.00 816.00
JUMLAH ( BELUM PPN ) 39,948.00 - 39,948.00
JASA 10 % 3,994.80 - 3,994.80
JUMLAH 43,942.80 - 43,942.80
DIBULATKAN 43,942.00 - 43,942.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kamper tanpa plepet
0.0120 m3 Kayu kamper balok @ Rp. -
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
0.3200 org Tukang kayu @ Rp. 90,000.00 28,800.00
0.0320 org Kepala tukang kayu @ Rp. 96,000.00 3,072.00
0.1800 org Pekerja @ Rp. 72,000.00 12,960.00
0.0090 org Mandor @ Rp. 96,000.00 864.00
JUMLAH ( BELUM PPN ) 45,696.00 - 45,696.00
JASA 10 % 4,569.60 - 4,569.60
JUMLAH 50,265.60 - 50,265.60
DIBULATKAN 50,265.00 - 50,265.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kruing tanpa plepet
0.0120 m3 Kayu kruing balok @ Rp. -
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
0.3200 org Tukang kayu @ Rp. 90,000.00 28,800.00
0.0320 org Kepala tukang kayu @ Rp. 96,000.00 3,072.00
0.1800 org Pekerja @ Rp. 72,000.00 12,960.00
0.0090 org Mandor @ Rp. 96,000.00 864.00
JUMLAH ( BELUM PPN ) 45,696.00 - 45,696.00
JASA 10 % 4,569.60 - 4,569.60
JUMLAH 50,265.60 - 50,265.60
DIBULATKAN 50,265.00 - 50,265.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka bengkirai tanpa plepet
0.0120 m3 Kayu bengkirai balok @ Rp. -
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
0.3200 org Tukang kayu @ Rp. 90,000.00 28,800.00
0.0320 org Kepala tukang kayu @ Rp. 96,000.00 3,072.00
0.1800 org Pekerja @ Rp. 72,000.00 12,960.00
0.0090 org Mandor @ Rp. 96,000.00 864.00
JUMLAH ( BELUM PPN ) 45,696.00 - 45,696.00
JASA 10 % 4,569.60 - 4,569.60
JUMLAH 50,265.60 - 50,265.60
DIBULATKAN 50,265.00 - 50,265.00
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kayu lama dg plepet
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
2.6000 m1 Plepet kayu @ Rp. -
0.0100 kg Paku eternit @ Rp. -
0.0100 kg Paku plepet @ Rp. -
0.3200 org Tukang kayu @ Rp. 90,000.00 28,800.00
0.0320 org Kepala tukang kayu @ Rp. 96,000.00 3,072.00
0.1800 org Pekerja @ Rp. 72,000.00 12,960.00
0.0090 org Mandor @ Rp. 96,000.00 864.00
JUMLAH ( BELUM PPN ) 45,696.00 - 45,696.00
JASA 10 % 4,569.60 - 4,569.60
JUMLAH 50,265.60 - 50,265.60
DIBULATKAN 50,265.00 - 50,265.00
SNI 1.0000 m 2
Langit2 asbes (1,00 x 1,00) m, rangka kayu kamper dg plepet
0.0120 m3 Kayu kamper balok @ Rp. -
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
2.6000 m1 Plepet kayu @ Rp. -
0.0100 kg Paku eternit @ Rp. -
0.0100 kg Paku plepet @ Rp. -
0.3200 org Tukang kayu @ Rp. 90,000.00 28,800.00
0.0320 org Kepala tukang kayu @ Rp. 96,000.00 3,072.00
0.1800 org Pekerja @ Rp. 72,000.00 12,960.00
0.0090 org Mandor @ Rp. 96,000.00 864.00
JUMLAH ( BELUM PPN ) 45,696.00 - 45,696.00
JASA 10 % 4,569.60 - 4,569.60
JUMLAH 50,265.60 - 50,265.60
DIBULATKAN 50,265.00 - 50,265.00
SNI 1.0000 m 2
Langit2 asbes (1,00 x 1,00) m, rangka kayu kruing dg plepet
0.0120 m3 Kayu kruing balok @ Rp. -
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
2.6000 m1 Plepet kayu @ Rp. -
0.0100 kg Paku eternit @ Rp. -
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.0100 kg Paku plepet @ Rp. -
0.3200 org Tukang kayu @ Rp. 90,000.00 28,800.00
0.0320 org Kepala tukang kayu @ Rp. 96,000.00 3,072.00
0.1800 org Pekerja @ Rp. 72,000.00 12,960.00
0.0090 org Mandor @ Rp. 96,000.00 864.00
JUMLAH ( BELUM PPN ) 45,696.00 - 45,696.00
JASA 10 % 4,569.60 - 4,569.60
JUMLAH 50,265.60 - 50,265.60
DIBULATKAN 50,265.00 - 50,265.00
6.13 1.0000 m2 Langit2 gypsum t;l 9 mm, rangka 60 x 120 kayu kruing
0.0130 m3 Kayu kruing @ Rp. -
0.3600 lbr Gypsum board 9 mm @ Rp. -
0.0500 roll Kasa gypsum @ Rp. -
0.4500 kg Tepung gypsum @ Rp. -
0.0030 kg Alkasit @ Rp. -
0.0500 kg Paku gypsum @ Rp. -
0.1200 kg Paku usuk @ Rp. -
0.3700 org Tukang kayu @ Rp. 90,000.00 33,300.00
0.0370 org Kepala tukang kayu @ Rp. 96,000.00 3,552.00
0.2400 org Pekerja @ Rp. 72,000.00 17,280.00
0.0120 org Mandor @ Rp. 96,000.00 1,152.00
JUMLAH ( BELUM PPN ) 55,284.00 - 55,284.00
JASA 10 % 5,528.40 - 5,528.40
JUMLAH 60,812.40 - 60,812.40
DIBULATKAN 60,812.00 - 60,812.00
6.13 1.0000 m2 Langit2 kalsiboard t;l 3.5 mm, rangka 60 x 120 ky kruing
0.0130 m3 Kayu kruing @ Rp. -
0.3600 lbr Kalsiboard 3.5 mm @ Rp. -
0.0500 roll Kasa gypsum @ Rp. -
0.4500 kg Tepung gypsum @ Rp. -
0.0030 kg Alkasit @ Rp. -
0.0500 kg Paku gypsum @ Rp. -
0.1200 kg Paku usuk @ Rp. -
0.3700 org Tukang kayu @ Rp. 90,000.00 33,300.00
0.0370 org Kepala tukang kayu @ Rp. 96,000.00 3,552.00
0.2400 org Pekerja @ Rp. 72,000.00 17,280.00
0.0120 org Mandor @ Rp. 96,000.00 1,152.00
JUMLAH ( BELUM PPN ) 55,284.00 - 55,284.00
JASA 10 % 5,528.40 - 5,528.40
JUMLAH 60,812.40 - 60,812.40
DIBULATKAN 60,812.00 - 60,812.00
PEKERJAAN LISPLANG
1.0000 m1 Pasang lisplank ukuran (2 x 20) cm, kayu jati
0.0048 m3 Kayu jati papan @ Rp. -
0.0600 kg Paku biasa 2" - 5" @ Rp. -
0.1000 org Tukang kayu @ Rp. 90,000.00 9,000.00
0.0100 org Kepala tukang kayu @ Rp. 96,000.00 960.00
0.1000 org Pekerja @ Rp. 72,000.00 7,200.00
0.0050 org Mandor @ Rp. 96,000.00 480.00
JUMLAH ( BELUM PPN ) 17,640.00 - 17,640.00
JASA 10 % 1,764.00 - 1,764.00
JUMLAH 19,404.00 - 19,404.00
DIBULATKAN 19,404.00 - 19,404.00
PEKERJAAN TALANG
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu kamper
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0096 m3 Kayu kamper papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 90,000.00 36,000.00
0.0250 org Kepala tukang kayu @ Rp. 96,000.00 2,400.00
0.1500 org Pekerja @ Rp. 72,000.00 10,800.00
0.0013 org Mandor @ Rp. 96,000.00 120.00
JUMLAH ( BELUM PPN ) 49,320.00 - 49,320.00
JASA 10 % 4,932.00 - 4,932.00
JUMLAH 54,252.00 - 54,252.00
DIBULATKAN 54,252.00 - 54,252.00
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu kruing
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0096 m3 Kayu kruing papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 90,000.00 36,000.00
0.0250 org Kepala tukang kayu @ Rp. 96,000.00 2,400.00
0.1500 org Pekerja @ Rp. 72,000.00 10,800.00
0.0013 org Mandor @ Rp. 96,000.00 120.00
JUMLAH ( BELUM PPN ) 49,320.00 - 49,320.00
JASA 10 % 4,932.00 - 4,932.00
JUMLAH 54,252.00 - 54,252.00
DIBULATKAN 54,252.00 - 54,252.00
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu bengkirai
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0096 m3 Kayui bengkirai papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 90,000.00 36,000.00
0.0250 org Kepala tukang kayu @ Rp. 96,000.00 2,400.00
0.1500 org Pekerja @ Rp. 72,000.00 10,800.00
0.0013 org Mandor @ Rp. 96,000.00 120.00
JUMLAH ( BELUM PPN ) 49,320.00 - 49,320.00
JASA 10 % 4,932.00 - 4,932.00
JUMLAH 54,252.00 - 54,252.00
DIBULATKAN 54,252.00 - 54,252.00
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu kamper
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0190 m3 Kayu kamper papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 90,000.00 36,000.00
0.0250 org Kepala tukang kayu @ Rp. 96,000.00 2,400.00
0.0400 org Pekerja @ Rp. 72,000.00 2,880.00
0.0013 org Mandor @ Rp. 96,000.00 120.00
JUMLAH ( BELUM PPN ) 41,400.00 - 41,400.00
JASA 10 % 4,140.00 - 4,140.00
JUMLAH 45,540.00 - 45,540.00
DIBULATKAN 45,540.00 - 45,540.00
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu kruing
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0190 m3 Kayu kruing papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 90,000.00 36,000.00
0.0250 org Kepala tukang kayu @ Rp. 96,000.00 2,400.00
0.0400 org Pekerja @ Rp. 72,000.00 2,880.00
0.0013 org Mandor @ Rp. 96,000.00 120.00
JUMLAH ( BELUM PPN ) 41,400.00 - 41,400.00
JASA 10 % 4,140.00 - 4,140.00
JUMLAH 45,540.00 - 45,540.00
DIBULATKAN 45,540.00 - 45,540.00
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu bengkirai
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.0190 m3 Kayu bengkirai papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. 90,000.00 36,000.00
0.0250 org Kepala tukang kayu @ Rp. 96,000.00 2,400.00
0.0400 org Pekerja @ Rp. 72,000.00 2,880.00
0.0013 org Mandor @ Rp. 96,000.00 120.00
JUMLAH ( BELUM PPN ) 41,400.00 - 41,400.00
JASA 10 % 4,140.00 - 4,140.00
JUMLAH 45,540.00 - 45,540.00
DIBULATKAN 45,540.00 - 45,540.00
SNI 1.0000 m2 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper
03-3434-2002 0.0195 m3 Kayu kamper balok @ Rp. -
6.56 0.0070 m3 Kayu kamper papan @ Rp. -
0.1000 kg Paku biasa 2" - 5" @ Rp. -
0.5600 kg Lem kayu @ Rp. -
1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp.
0.4500 org Tukang kayu @ Rp. 90,000.00 40,500.00
0.0450 org Kepala tukang kayu @ Rp. 96,000.00 4,320.00
0.1500 org Pekerja @ Rp. 72,000.00 10,800.00
0.0750 org Mandor @ Rp. 96,000.00 7,200.00
JUMLAH ( BELUM PPN ) 62,820.00 - 62,820.00
JASA 10 % 6,282.00 - 6,282.00
JUMLAH 69,102.00 - 69,102.00
DIBULATKAN 69,102.00 - 69,102.00
H.2A 1.0000 m2 Pas. genteng beton besar Natural ( isi 9 / m2 ) untuk r. tingkat
9.0000 bh Genteng beton natural @ Rp. -
0.1000 org Tukang batu @ Rp. -
0.0100 org Kep. Tk. Batu @ Rp. -
0.3000 org Pekerja @ Rp. 72,000.00 21,600.00
0.0150 org Mandor @ Rp. 96,000.00 1,440.00
JUMLAH ( BELUM PPN ) 23,040.00 - 23,040.00
JASA 10 % 2,304.00 - 2,304.00
JUMLAH 25,344.00 - 25,344.00
DIBULATKAN 25,344.00 - 25,344.00
H.2A 1.0000 m2 Pas. genteng beton besar Warna ( isi 9 / m2 ) untuk r. tingkat
9.0000 bh Genteng beton Warna @ Rp. -
0.1000 org Tukang batu @ Rp. -
0.0100 org Kep. Tk. Batu @ Rp. -
0.3000 org Pekerja @ Rp. 72,000.00 21,600.00
0.0150 org Mandor @ Rp. 96,000.00 1,440.00
JUMLAH ( BELUM PPN ) 23,040.00 - 23,040.00
JASA 10 % 2,304.00 - 2,304.00
JUMLAH 25,344.00 - 25,344.00
DIBULATKAN 25,344.00 - 25,344.00
SNI 1.0000 m 2
Pasang atap genteng metal zinc alume type prima roof
03-3436-2002 1.0200 m2 Genteng metal @ Rp. -
6.32 0.2000 kg Paku anti karat @ Rp. -
0.1000 org Tukang kayu @ Rp. 90,000.00 9,000.00
0.0100 org Kepala tukang kayu @ Rp. 96,000.00 960.00
0.2000 org Pekerja @ Rp. 72,000.00 14,400.00
0.0010 org Mandor @ Rp. 96,000.00 96.00
JUMLAH ( BELUM PPN ) 24,456.00 - 24,456.00
JASA 10 % 2,445.60 - 2,445.60
JUMLAH 26,901.60 - 26,901.60
DIBULATKAN 26,901.00 - 26,901.00
PEKERJAAN CAT-CATAN
SNI 1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
6.8 0.2000 kg Cat meni @ Rp. -
0.1500 kg Plamir @ Rp. -
0.1700 kg Cat dasar @ Rp. -
0.2600 kg Cat penutup @ Rp. -
0.0900 org Tukang cat @ Rp. -
0.0060 org Kepala tukang cat @ Rp. -
0.0700 org Pekerja @ Rp. 72,000.00 5,040.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 5,280.00 - 5,280.00
JASA 10 % 528.00 - 528.00
JUMLAH 5,808.00 - 5,808.00
DIBULATKAN 5,808.00 - 5,808.00
SNI 1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
6.9 0.2000 kg Cat meni @ Rp. -
0.1500 kg Plamir @ Rp. -
0.1700 kg Cat dasar @ Rp. -
0.3500 kg Cat penutup @ Rp. -
0.1050 org Tukang cat @ Rp. -
0.0040 org Kepala tukang cat @ Rp. -
0.0700 org Pekerja @ Rp. 72,000.00 5,040.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 5,280.00 - 5,280.00
JASA 10 % 528.00 - 528.00
JUMLAH 5,808.00 - 5,808.00
DIBULATKAN 5,808.00 - 5,808.00
SNI 1.0000 m2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
6.14 0.1000 kg Plamir tembok @ Rp. 18,200.00 1,820.00
0.1000 kg Cat dasar @ Rp. 52,800.00 5,280.00
0.2600 kg Cat penutup 2 x @ Rp. 105,600.00 27,456.00
0.0630 org Tukang cat @ Rp. 85,000.00 5,355.00
0.0063 org Kepala tukang cat @ Rp. 90,000.00 567.00
0.0200 org Pekerja @ Rp. 72,000.00 1,440.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 7,602.00 34,556.00 42,158.00
JASA 10 % 760.20 3,455.60 4,215.80
JUMLAH 8,362.20 38,011.60 46,373.80
DIBULATKAN 8,362.00 38,011.00 46,373.00
SNI 1.0000 m2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
6.15 0.1200 kg Cat dasar @ Rp. -
0.1800 kg Cat penutup 2 x @ Rp. -
0.0420 org Tukang cat @ Rp. -
0.0042 org Kepala tukang cat @ Rp. -
0.0280 org Pekerja @ Rp. 72,000.00 2,016.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 2,256.00 - 2,256.00
JASA 10 % 225.60 - 225.60
JUMLAH 2,481.60 - 2,481.60
DIBULATKAN 2,481.00 - 2,481.00
SNI 1.0000 m2 Pengecatan tembok tidak terlindung dari panas dan hujan
6.14 0.1000 kg Cat alkali resisting primer @ Rp. -
0.3600 kg Cat ICI Weathershield @ Rp. -
0.0630 org Tukang cat @ Rp. -
0.0063 org Kepala tukang cat @ Rp. -
0.0200 org Pekerja @ Rp. 72,000.00 1,440.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 1,680.00 - 1,680.00
JASA 10 % 168.00 - 168.00
JUMLAH 1,848.00 - 1,848.00
DIBULATKAN 1,848.00 - 1,848.00
SNI 1.0000 m2 Melabur tembok lama dengan kapur sirih (untuk pemeliharaan)
6.18 0.0020 m3 Perancah kayu @ Rp. -
0.3000 kg Kapur sirih @ Rp. -
0.0050 org Tukang cat @ Rp. -
0.0005 org Kepala tukang cat @ Rp. -
0.0400 org Pekerja @ Rp. 72,000.00 2,880.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 3,120.00 - 3,120.00
JASA 10 % 312.00 - 312.00
JUMLAH 3,432.00 - 3,432.00
DIBULATKAN 3,432.00 - 3,432.00
SNI 1.0000 m 2
Pengecatan bidang besi ( 3 x )
6.9 0.1670 kg Cat meni besi @ Rp. 24,100.00 4,024.70
0.2000 kg Cat besi @ Rp. 52,800.00 10,560.00
0.1500 ltr Thinner @ Rp. 1,800.00 270.00
0.1050 org Tukang cat @ Rp. 85,000.00 8,925.00
0.0040 org Kepala tukang cat @ Rp. 90,000.00 360.00
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.0700 org Pekerja @ Rp. 72,000.00 5,040.00
0.0025 org Mandor @ Rp. 96,000.00 240.00
JUMLAH ( BELUM PPN ) 14,565.00 14,854.70 29,419.70
JASA 10 % 1,456.50 1,485.47 2,941.97
JUMLAH 16,021.50 16,340.17 32,361.67
DIBULATKAN 16,021.00 16,340.00 32,361.00
SNI 1.0000 m2 Pengecacatan permukaan baja dengan meni besi memakai perancah
6.21 0.1000 kg Meni besi sinkromat @ Rp. -
0.0100 bh Kuas @ Rp. -
0.0020 m3 Perancah kayu @ Rp. -
0.2250 org Tukang cat @ Rp. -
0.0225 org Kepala tukang cat @ Rp. -
0.2250 org Pekerja @ Rp. 72,000.00 16,200.00
0.0075 org Mandor @ Rp. 96,000.00 720.00
JUMLAH ( BELUM PPN ) 16,920.00 - 16,920.00
JASA 10 % 1,692.00 - 1,692.00
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
JUMLAH 18,612.00 - 18,612.00
DIBULATKAN 18,612.00 - 18,612.00
PEKERJAAN BONGKARAN
AK 1.0000 m 3
Membongkar Perkerasan
2.0000 org Pekerja @ Rp. 72,000.00 144,000.00
JUMLAH ( BELUM PPN ) 144,000.00 - 144,000.00
JASA 10 % 14,400.00 - 14,400.00
JUMLAH 158,400.00 - 158,400.00
DIBULATKAN 158,400.00 - 158,400.00
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
L.12 1.0000 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi
6.0000 org Tukang kayu @ Rp. 90,000.00 540,000.00
0.6000 org Kep. Tk. Kayu @ Rp. 96,000.00 57,600.00
4.0000 org Pekerja @ Rp. 72,000.00 288,000.00
0.2000 org Mandor @ Rp. 96,000.00 19,200.00
JUMLAH ( BELUM PPN ) 904,800.00 - 904,800.00
JASA 10 % 90,480.00 - 90,480.00
JUMLAH 995,280.00 - 995,280.00
DIBULATKAN 995,280.00 - 995,280.00
1.0000 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi
1.0000 org Pekerja @ Rp. 72,000.00 72,000.00
0.2000 org Mandor @ Rp. 96,000.00 19,200.00
JUMLAH ( BELUM PPN ) 91,200.00 - 91,200.00
JASA 10 % 9,120.00 - 9,120.00
JUMLAH 100,320.00 - 100,320.00
DIBULATKAN 100,320.00 - 100,320.00
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
L.14 1.0000 m3 Mengerjakan kembali bangunan kayu yang telah dibongkar
12.0000 org Tukang kayu @ Rp. 90,000.00 1,080,000.00
1.2000 org Kep. Tk. Kayu @ Rp. 96,000.00 115,200.00
4.0000 org Pekerja @ Rp. 72,000.00 288,000.00
0.2000 org Mandor @ Rp. 96,000.00 19,200.00
JUMLAH ( BELUM PPN ) 1,502,400.00 - 1,502,400.00
JASA 10 % 150,240.00 - 150,240.00
JUMLAH 1,652,640.00 - 1,652,640.00
DIBULATKAN 1,652,640.00 - 1,652,640.00
ANALISA SUPLEMEN
3 1.0000 m Pengelasan Single ( las listrik )
3.0000 kg Kawat las @ Rp. -
1.0000 hari Peralatan las @ Rp. -
0.5000 org Tukang las @ Rp. -
0.0500 org Kepala tukang las @ Rp. -
1.0000 Org Pekerja @ Rp. 72,000.00 72,000.00
1.0000 Org Mandor @ Rp. 96,000.00 96,000.00
JUMLAH ( BELUM PPN ) 168,000.00 - 168,000.00
JASA 10 % 16,800.00 - 16,800.00
JUMLAH 184,800.00 - 184,800.00
DIBULATKAN 184,800.00 - 184,800.00
PEKERJAAN SANITASI
SNI 1.0000 bh Memasang kloset duduk/monoblock
1.0000 bh Kloset duduk / monoblock @ Rp. -
6.1 6% x Harga kloset (Perlengkapan) @ Rp. -
1.1000 org Tukang batu @ Rp. 84,000.00 92,400.00
0.0010 org Kepala tukang batu @ Rp. 96,000.00 96.00
3.3000 org Pekerja @ Rp. 72,000.00 237,600.00
0.1600 org Mandor @ Rp. 96,000.00 15,360.00
JUMLAH ( BELUM PPN ) 345,456.00 - 345,456.00
JASA 10 % 34,545.60 - 34,545.60
JUMLAH 380,001.60 - 380,001.60
DIBULATKAN 380,001.00 - 380,001.00
SNI 1.0000 m 1
Memasang pipa beton, diameter 15 cm - 20 cm
1.1000 bh Pipa beton @ Rp. -
6.14 16.0000 bh Batu bata @ Rp. -
3.9200 kg PC @ Rp. -
0.0560 m3 Pasir pasang @ Rp. -
0.0240 m3 Pasir urug @ Rp. -
0.0700 org Tukang batu @ Rp. 84,000.00 5,880.00
0.0070 org Kepala tukang batu @ Rp. 96,000.00 672.00
0.1400 org Pekerja @ Rp. 72,000.00 10,080.00
0.0070 org Mandor @ Rp. 96,000.00 672.00
JUMLAH ( BELUM PPN ) 17,304.00 - 17,304.00
JASA 10 % 1,730.40 - 1,730.40
JUMLAH 19,034.40 - 19,034.40
DIBULATKAN 19,034.00 - 19,034.00
SNI 1.0000 bh Memasang bak kontrol pas.bata (30 x 30) cm, tinggi 35 cm
87.0000 bh Batu bata @ Rp. -
6.16 44.0000 kg PC @ Rp. -
0.0700 m3 Pasir pasang @ Rp. -
0.0700 m3 Batu kerikil @ Rp. -
1.6000 kg Besi beton @ Rp. -
0.0600 m3 Pasir beton @ Rp. -
1.0150 org Tukang batu @ Rp. 84,000.00 85,260.00
0.0015 org Kepala tukang batu @ Rp. 96,000.00 144.00
3.2000 org Pekerja @ Rp. 72,000.00 230,400.00
0.0160 org Mandor @ Rp. 96,000.00 1,536.00
JUMLAH ( BELUM PPN ) 317,340.00 - 317,340.00
JASA 10 % 31,734.00 - 31,734.00
JUMLAH 349,074.00 - 349,074.00
DIBULATKAN 349,074.00 - 349,074.00
SNI 1.0000 bh Memasang bak kontrol pas. bata (45 x 45) cm, tinggi 50 cm
150.0000 bh Batu bata @ Rp. -
6.17 77.0000 kg PC @ Rp. -
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.1300 m3 Pasir pasang @ Rp. -
0.0200 m3 Batu kerikil @ Rp. -
2.6000 kg Besi beton @ Rp. -
0.0900 m3 Pasir beton @ Rp. -
0.4730 org Tukang batu @ Rp. 84,000.00 39,732.00
0.0470 org Kepala tukang batu @ Rp. 96,000.00 4,512.00
1.4200 org Pekerja @ Rp. 72,000.00 102,240.00
0.0710 org Mandor @ Rp. 96,000.00 6,816.00
JUMLAH ( BELUM PPN ) 153,300.00 - 153,300.00
JASA 10 % 15,330.00 - 15,330.00
JUMLAH 168,630.00 - 168,630.00
DIBULATKAN 168,630.00 - 168,630.00
SNI 1.0000 bh Memasang bak kontrol pas. bata (60 x 60) cm, tingg 65 cm
222.0000 bh Batu bata @ Rp. -
6.18 114.0000 kg PC @ Rp. -
0.1840 m 3
Pasir pasang @ Rp. -
0.0330 m3 Batu kerikil @ Rp. -
4.8500 kg Besi beton @ Rp. -
0.1200 m3 Pasir beton @ Rp. -
0.7200 org Tukang batu @ Rp. 84,000.00 60,480.00
0.0720 org Kepala tukang batu @ Rp. 96,000.00 6,912.00
2.1600 org Pekerja @ Rp. 72,000.00 155,520.00
0.1000 org Mandor @ Rp. 96,000.00 9,600.00
JUMLAH ( BELUM PPN ) 232,512.00 - 232,512.00
JASA 10 % 23,251.20 - 23,251.20
JUMLAH 255,763.20 - 255,763.20
DIBULATKAN 255,763.00 - 255,763.00
SNI 1.0000 m 1
Memasang pipa PVC tipe AW diameter 2"
1.2000 m1 Pipa PVC @ Rp. -
6.29 35% x Harga pipa (Perlengkapan) @ Rp. -
0.0900 org Tukang batu @ Rp. 84,000.00 7,560.00
0.0090 org Kepala tukang batu @ Rp. 96,000.00 864.00
0.0544 org Pekerja @ Rp. 72,000.00 3,916.80
0.0027 org Mandor @ Rp. 96,000.00 259.20
JUMLAH ( BELUM PPN ) 12,600.00 - 12,600.00
JASA 10 % 1,260.00 - 1,260.00
JUMLAH 13,860.00 - 13,860.00
DIBULATKAN 13,860.00 - 13,860.00
6.17 1.0000 m 2
Pasang kaca, tebal 5 mm
1.1000 m2 Kaca polos @ Rp. -
0.1500 org Tukang kayu @ Rp. 90,000.00 13,500.00
0.0150 org Kepala tukang kayu @ Rp. 96,000.00 1,440.00
0.0150 org Pekerja @ Rp. 72,000.00 1,080.00
0.0008 org Mandor @ Rp. 96,000.00 72.00
JUMLAH ( BELUM PPN ) 16,092.00 - 16,092.00
JASA 10 % 1,609.20 - 1,609.20
JUMLAH 17,701.20 - 17,701.20
DIBULATKAN 17,701.00 - 17,701.00
6.20 1.0000 m 2
Pasang kaca cermin, tebal 5 mm
1.1000 m2 Kaca cermin @ Rp. -
0.1500 org Tukang kayu @ Rp. 90,000.00 13,500.00
0.0150 org Kepala tukang kayu @ Rp. 96,000.00 1,440.00
0.0150 org Pekerja @ Rp. 72,000.00 1,080.00
0.0008 org Mandor @ Rp. 96,000.00 72.00
JUMLAH ( BELUM PPN ) 16,092.00 - 16,092.00
JASA 10 % 1,609.20 - 1,609.20
JUMLAH 17,701.20 - 17,701.20
DIBULATKAN 17,701.00 - 17,701.00
PEKERJAAN JALAN
100.000 ton/hari Produksi Lataston HRS (Lapis Aspal Tipis Aspal Beton )
1.000 Mandor @ Rp. 96,000.00 96,000.00
4.000 Tenaga @ Rp. 72,000.00 288,000.00
6,324.000 Kg Aspal curah @ Rp. -
32.310 M3 Pasir ayak untuk beton @ Rp. -
27.500 M3 Batu pecah 9.5 - 19 mm @ Rp. -
7,480.000 Kg Filler @ Rp. -
1.000 Set Alat bantu @ Rp. -
4.000 jam Wheel Loader 115 HP @ Rp. -
4.000 jam Asphalt Mixing Plant 30 Ton/Jam @ Rp. -
42.000 jam Dump Truck 5,0 Ton @ Rp. -
tiap1ton - 384,000.00 384,000.00
0.0100 x 3,840.00
Bj HRS 2,3 t/m3 2.30 JUMLAH (BELUM JASA) 3,840.00
per 1m2 tebal 1.00 100 88.32
1.000 m2 Lataston HRS-BC5 cm padat (Lapis Aspal Tipis Aspal Beton ) - Leveling
tebal Lapis Aspal Resap Pengikat Prime Coat 576.00
5.000 cm Lataston HRS-BC5 cm padat (Lapis Aspal Tipis Aspal Beton ) - Leveling 441.60
Menghampar HRS 213.33
JUMLAH : 1,230.93
JASA 10 % : 123.09
JUMLAH ( BELUM TERMASUK PPN ) : 1,354.03
DIBULATKAN : 1,354.00
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PENATAAN KAWASAN KUMUH
PEKERJAAN : PENYUSUNAN DOKUMEN TEKNIS PENATAAN LINGKUNGAN (DPTL)
LOKASI : PADUKUHAN SUMBERAN RT 02 RW 21
TAHUN ANGGARAN : 2017
I Pekerjaan Persiapan
1 Pembersihan Lahan 1.00 Ls 1,500,000.00 1,500,000.00
2 Pemasangan Bowplank 1.00 Ls 450,000.00 450,000.00
IV Pekerjaan Dinding
1 Pasangan Batu Bata Ringan 19.60 m2 101,611.00 1,991,575.60
2 Plesteran Tembok Batu Bata 39.20 m2 38,358.00 1,503,633.60
3 Acian dinding Batu bata Ringan 39.20 m2 14,901.00 584,119.20
5 pasang Papan GRC 1,5x122x244cm 67.20 m2 200,043.00 13,442,889.60
6 Pengecetan Dinding 106.40 m2 46,373.00 4,934,087.20
V Pekerjaan Atap
1 Rangka Baja Ringan 39.40 m2 159,226.00 6,273,504.40
2 Petutup atap galvalum 34.40 m2 200,085.00 6,882,924.00
3 List Plang GRC Out Door 25.20 m2 200,043.00 5,041,083.60
4 Bubungan Atap 3.00 m' 119,823.00 359,469.00
VI Pekerjaan Lantai
1 Pasir urug 10 cm 2.58 m3 215,028.00 555,632.35
2 Pemasangan Keramik 40x40 cm 25.84 m2 132,246.00 3,417,236.64
IV Pekerjaan Dinding
1 Pasangan Batu Bata Ringan 28.00 0.70 19.60 m2
2 Plesteran Tembok Batu Bata 28.00 0.70 2.00 19.60 39.20 m2
3 Acian dinding Batu bata Ringan 39.20 m2
4 Dinding rangka baja ringan Metal Stuf 100x35x0.75 50.27 m2
Dinding Baja Ringan Metal Stud 100x35x0,75mm 7.00 2.40 2.00 33.60
Dinding Baja Ringan Metal Stud 100x35x0,75mm 4.00 2.40 9.60
Dinding Baja Ringan Metal Stud 100x35x0,75mm 2.23 2.40 5.35
Dinding Baja Ringan Metal Stud 100x35x0,75mm 0.97 1.77 1.72
5 pasang Papan GRC 1,5x122x244cm 28.00 2.40 67.20 m2
6 Pengecetan Dinding 106.40 m2
V Pekerjaan Atap
Rangka Baja Ringan 39.40
1 Kuda-Kuda Baja Ringan75x35x0,75mm 2.00 2.80 5.60 m2
2 setengah Kuda-Kuda Baja Ringan 75x35x0,75mm 2.00 2.80 5.60 m2
3 Petutup atap galvalum 8.60 4.00 0.20 34.40 m2
4 List Plang GRC Out Door 8.60 4.00 0.20 25.20 m2
5 Bubungan Atap 3.00 3.00 m'
Lokasi 1
1 Pembongkaran Paving Lama 176.40 m2 158,400.00 27,941,760.00
2 Pemadatan dan perataaan tanah bekas bongkaran 176.40 m2 13,992.00 2,468,188.80
3 Galian Tanah Canstin 1.47 m3 35,904.00 52,778.88
4 Pasang paving polos, t=8 cm K 200 130.20 m2 139,595.00 18,175,269.00
5 Pasang paving Warna, t=8 cm K 200 46.20 m2 151,530.00 7,000,686.00
6 Pengadaan dan Pemasangan Canstin (TEGAK) 98.00 m' 75,251.00 7,374,598.00
7 Pengecatan Canstin 60 x 25 x 22 x18 14.70 m2 73,961.00 1,087,226.70
Lokasi 2
1 Pembongkaran Paving Lama 62.81 m2 158,400.00 9,949,500.00
2 Pemadatan dan perataaan tanah bekas bongkaran 62.81 m2 13,992.00 878,872.50
3 Pasang paving polos, t=6 cm K 200 54.70 m2 126,285.00 6,908,105.21
4 Pasang paving Warna, t=6 cm K 200 8.11 m2 138,385.00 1,122,302.35
5 Cor Beton Pengunci Campuran 1Pc : 3Ps : 5Sp 2.25 m3 932,643.00 2,098,446.75
Lokasi 3
1 Pembongkaran Paving Lama 70.00 m2 158,400.00 11,088,000.00
2 Pemadatan dan perataaan tanah bekas bongkaran 70.00 m2 13,992.00 979,440.00
0 Galian Tanah Canstin 1.05 m3 35,904.00 37,699.20
3 Pasang paving polos, t=6 cm K 200 63.15 m2 126,285.00 7,974,897.75
4 Pasang paving Warna, t=6 cm K 200 6.85 m2 138,385.00 947,937.25
5 Pengadaan dan Pemasangan Canstin (TEGAK) 70.00 m' 53,284.00 3,729,880.00
6 Pengecatan Canstin 40x20x15x10cm 10.50 m2 73,961.00 776,590.50
Lokasi 4
1 Pembongkaran Paving Lama 66.24 m2 158,400.00 10,492,416.00
2 Pemadatan dan perataaan tanah bekas bongkaran 66.24 m2 13,992.00 926,830.08
3 Pasang paving polos, t=6 cm K 200 57.99 m2 126,285.00 7,323,267.15
4 Pasang paving Warna, t=6 cm K 200 8.25 m2 138,385.00 1,141,676.25
5 Cor Beton Pengunci Campuran 1Pc : 3Ps : 5Sp 2.21 m3 932,643.00 2,059,275.74
Lokasi 5
1 Pembongkaran Paving Lama 50.00 m2 158,400.00 7,920,000.00
2 Pemadatan dan perataaan tanah bekas bongkaran 50.00 m2 13,992.00 699,600.00
3 Pasang paving polos, t=6 cm K 200 44.98 m2 126,285.00 5,680,299.30
4 Pasang paving Warna, t=6 cm K 200 5.02 m2 138,385.00 694,692.70
5 Cor Beton Pengunci Campuran 1Pc : 3Ps : 5Sp 0.75 m3 932,643.00 699,482.25
Lokasi 6
1 Pembongkaran Paving Lama 384.12 m2 158,400.00 60,844,608.00
2 Pemadatan dan perataaan tanah bekas bongkaran 384.12 m2 13,992.00 5,374,607.04
3 Pasang paving polos, t=6 cm K 200 286.48 m2 126,285.00 36,177,495.38
4 Pasang paving Warna, t=6 cm K 200 97.65 m2 138,385.00 13,512,603.33
5 Cor Beton Pengunci Campuran 1Pc : 3Ps : 5Sp 6.40 m3 932,643.00 5,970,780.49
HARGA SAT. JUMLAH HARGA
NO. URAIAN PEKERJAAN VOL. SAT
( Rp. ) ( Rp. )
Pengerjaan SPAH
1 Cor Beton Selimut Buis Beton 25.01 m3 932,643.00 23,325,849.10
2 Memasang Buis Beton Ø 30 cm 100.30 m' 70,510.00 7,072,153.00
3 Plat Beton K175 Tutup Bak Kontrol
a Beton Mutu, f'c=14,5 Mpa (K175), Menggunakan Molen 1.22 m3 1,147,297.00 1,400,849.64
b Pembesian dengan besi polos 143.93 Kg 23,211.00 3,340,846.50
c Bekisting Beton Biasa dengan Multiplex 9 mm 14.96 m2 110,009.00 1,645,734.64
d Bongkar Bekisting Secara Hati hati (pakai ulang 2 kali) 14.96 m2 79,200.00 1,184,832.00
4 Pasang Grill Besi Cor 40 x 60 x 3 cm 8.00 bh 369,600.00 2,956,800.00
Pekerjaan Sumur Resapan
1 Sumur Resapan Buis Beton D-80 cm 18.00 m' 393,333.00 7,079,994.00
2 Memasanag lapisan ijuk 40.00 bh 62,960.00 2,518,400.00
II Pekerjaan Lain-Lain
1 Uji Lab Paving Polos dan Merah t : 8 cm K-200 1.00 Ls 25,000.00 25,000.00
2 Uji Lab Paving Polos dan Merah t : 6 cm K-200 1.00 Ls 25,000.00 25,000.00
3 Uji Hammer Test Tutup SPAH K-175 1.00 Ls 45,000.00 45,000.00
4 Uji Lab Beton SPAH K-175 1.00 Ls 25,000.00 25,000.00
5 Uji Tarik Besi Ø 10mm 1.00 Ls 75,000.00 75,000.00
320,830,271.47
320,830,271.47
JUMLAH 320,830,271.47
PPN ( 10 % ) 32,083,027.15
JML TOTAL 352,913,298.62
DIBULATKAN 352,913,000.00
PEKERJAAN PAVING
No. URAIAN PEKERJAAN Panjang Lebar Tinggi kedalaman jumlah luas volume Satuan V.Tot
I Pekerjaan Jalan Lingkungan
Lokasi 1
1 Pembongkaran Paving Lama 49.00 3.60 176.40 m2
2 Pemadatan dan perataaan tanah bekas bongkaran 49.00 3.60 176.40 m2
3 Galian Tanah Canstin 49.00 0.15 0.10 2.00 0.74 1.47 m3
4 Pasang paving polos, t=8 cm K 200 49.00 3.60 176.40 130.20 m2
5 Pasang paving Warna, t=8 cm K 200 46.20 46.20 m2
6 Pengadaan dan Pemasangan Canstin (TEGAK) 49.00 2.00 98.00 m'
7 Pengecatan Canstin 60 x 25 x 22 x18 0.15 14.70 m2
Lokasi 2
1 Pembongkaran Paving Lama 37.50 1.68 62.81 m2
2 Pemadatan dan perataaan tanah bekas bongkaran 37.50 1.68 62.81 m2
3 Pasang paving polos, t=6 cm K 200 37.50 1.68 54.70 m2
4 Pasang paving Warna, t=6 cm K 200 37.50 1.68 8.11 m2
5 Cor Beton Pengunci Campuran 1Pc : 3Ps : 5Sp 75.00 0.15 0.20 2.25 m3
Lokasi 3
1 Pembongkaran Paving Lama 35.00 2.00 70.00 m2
2 Pemadatan dan perataaan tanah bekas bongkaran 35.00 2.00 70.00 m2
Galian Tanah Canstin 35.00 0.15 0.10 2.00 0.53 1.05 m3
3 Pasang paving polos, t=6 cm K 200 35.00 2.00 63.15 m2
4 Pasang paving Warna, t=6 cm K 200 35.00 2.00 6.85 m2
5 Pengadaan dan Pemasangan Canstin (TEGAK) 35.00 2.00 70.00 m'
6 Pengecatan Canstin 40x20x15x10cm 0.15 10.50 m2
Lokasi 4
1 Pembongkaran Paving Lama 36.8 1.80 66.24 m2
2 Pemadatan dan perataaan tanah bekas bongkaran 36.8 1.80 66.24 m2
3 Pasang paving polos, t=6 cm K 200 36.8 1.80 57.99 m2
4 Pasang paving Warna, t=6 cm K 200 36.8 1.80 8.25 m2
5 Cor Beton Pengunci Campuran 1Pc : 3Ps : 5Sp 73.6 0.15 0.20 2.21 m3
Lokasi 5
1 Pembongkaran Paving Lama 25 2.00 50.00 m2
2 Pemadatan dan perataaan tanah bekas bongkaran 25 2.00 50.00 m2
3 Pasang paving polos, t=6 cm K 200 25 2.00 44.98 m2
4 Pasang paving Warna, t=6 cm K 200 25 2.00 5.02 m2
5 Cor Beton Pengunci Campuran 1Pc : 3Ps : 5Sp 25 0.15 0.20 0.75 m3
Lokasi 6
1 Pembongkaran Paving Lama 106.7 3.60 384.12 m2
2 Pemadatan dan perataaan tanah bekas bongkaran 106.7 3.60 384.12 m2
3 Pasang paving polos, t=6 cm K 200 106.7 3.60 286.48 m2
4 Pasang paving Warna, t=6 cm K 200 106.7 3.60 97.65 m2
5 Cor Beton Pengunci Campuran 1Pc : 3Ps : 5Sp 106.7 0.15 0.20 2.00 3.20 6.40 m3
Pengerjaan SPAH
1 Cor Beton Selimut Buis Beton 106.7 0.60 0.60 13.40 25.01 m3
2 Memasang Buis Beton Ø 30 cm 106.7 100.30 m'
3 Plat Beton K175 Tutup Bak Kontrol
a Beton Mutu, f'c=14,5 Mpa (K175), Menggunakan Molen 1.10 1.10 8.00 0.15 1.22 m3
b Pembesian dengan besi polos 1.10 1.10 8.00 17.99 143.93 Kg
c Bekisting Beton Biasa dengan Multiplex 9 mm 1.1 1.10 0.15 8.00 1.87 14.96 m2
d Bongkar Bekisting Secara Hati hati (pakai ulang 2 kali) 14.96 m2
4 Pasang Grill Besi Cor 40 x 60 x 3 cm 8.00 8.00 bh
Pekerjaan Sumur Resapan
1 Sumur Resapan Buis Beton D-80 cm 8.00 18.00 m'
2 Memasanag lapisan ijuk 40.00 40.00 bh
Lokasi 7
II Pekerjaan Lain-Lain
1 Uji Lab Paving Polos dan Merah t : 8 cm K-200 1.00 Ls
2 Uji Lab Paving Polos dan Merah t : 6 cm K-200 1.00 Ls
3 Uji Hammer Test Tutup SPAH K-175 1.00 Ls
4 Uji Lab Beton SPAH K-175 1.00 Ls
5 Uji Tarik Besi Ø 10mm 1.00 Ls
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PENETAPAN KEBIJAKAN, STRATEGI DAN PROGRAM PERKOTAAN
PEKERJAAN : PENYUSUNAN DOKUMEN TEKNIS PENATAAN LINGKUNGAN (DPTL)
LOKASI : RT 01 DUSUN SUMBERAN
TAHUN ANGGARAN : 2017
I Pekerjaan Persiapan
1 Pemasangan Bowplang 1.00 Ls 450,000 450,000.00
2 Pembersihan Lahan 2.00 m2 1,000,000 2,000,000.00
IV Pekerjaan Dinding
1 Pasangan Dinding Batu Bata 44.80 m2 101,611 4,552,172.80
2 Pekerjaan Acian 89.60 m2 14,901 1,335,129.60
3 Pekerjaan Plester 89.60 m2 38,358 3,436,876.80
a Pembesian Ring Balk 15x20 68.98 Kg
b Pembetonan Ring Balk 15x20 0.48 m3 1,147,297 550,702.56
V Pekerjaan Atap
1 Kuda-Kuda Baja Ringan 16.22 m2 159,226 2,583,043.79
2 Atap Galvalum 16.22 m2 200,085 3,245,878.91
VI Pekerjaan Lantai
1 Pasir urug 10 cm 0.71 m3 215,028 153,153.69
2 Lantai Kerja Rabat Beton t : 5 cm 0.36 m3 932,643 332,137.49
3 Acian permukaan lantai 7.12 m2 14,901 106,132.37
26,270,981.07
JUMLAH 26,270,981.07
PPN ( 10 % ) 2,627,098.11
JML TOTAL 28,898,079.17
DIBULATKAN 28,898,000.00
PEKERJAAN GAPURA
No. URAIAN PEKERJAAN Panjang Lebar Tinggi kedalaman jumlah luas volume Satuan V.Tot
I Pekerjaan Persiapan
1 Pemasangan Bowplang 4 2 1.00 Ls
2 Pembersihan Lahan 2.00 m2
IV Pekerjaan Dinding
1 Pasangan Dinding Batu Bata 16 2.80 44.80 m2
2 Pekerjaan Acian 16 2.80 2.00 89.60 m2
3 Pekerjaan Plester 89.60 m2
4 Pengecetan 89.60 m2
5 Pekerjan Ring Balk
a Pembesian Ring Balk 15x20 68.98 Kg
Tulangan Pokok 16 39.49
Tulangan Begel 16 29.49
b Pembetonan Ring Balk 15x20 16 0.15 0.20 0.48 m3
c Pemasangan Begisiting 16 0.20 3.20 m2
d Pembongakran Begisting 16 0.20 3.20 m2
V Pekerjaan Atap
1 Kuda-Kuda Baja Ringan 5.15 3.15 16.22 m2
2 Atap Galvalum 5.15 3.15 16.22 m2
VI Pekerjaan Lantai
1 Pasir urug 10 cm 3.85 1.85 0.10 0.71 m3
2 Lantai Kerja Rabat Beton t : 5 cm 3.85 1.85 0.05 0.36 m3
3 Acian permukaan lantai 3.85 1.85 7.12 m2
II Pekerjaan Fondasi
1 Pasangan batu Kali 1 : 4 Pcs 3.55 m3 884,010 3,137,351.49
2 Pondasi Foot Plat
a Pembesian Fondasi Foot Plat 106.62 Kg 23,211 2,474,701.11
b Pengecoran Fondasi Foot Plat K-200 0.19 m3 1,147,297 223,034.54
c Pemasangan Begisting 0.96 m2 110,009 105,608.64
d Bongkar Begisitng 0.96 m2 79,200 76,032.00
28,365,888.44
JUMLAH 28,365,888.44
PPN ( 10 % ) 2,836,588.84
JML TOTAL 31,202,477.29
DIBULATKAN 31,202,000.00
PEKERJAAN GAPURA
No. URAIAN PEKERJAAN Panjang Lebar Tinggi kedalaman jumlah luas volume Satuan V.Tot
I Pekerjaan Tanah dan Pasir
1 Galian tanah pondasi batu kali 2 1.3 0.80 2.00 2.08 4.16 m3
2 galian tanah pondasi foot plat 0.9 0.9 0.55 2.00 0.45 0.89 m3
3 Urug Pasir Bawah Pondasi batu kali t : 10cm 2 1.3 0.10 2.00 0.26 0.52 m3
4 Urug Pasir Bawah Pondasi Foot plat t : 10cm 0.9 0.9 0.10 2.00 0.08 0.16 m3
5 Urug tanah kembali pondasi 1.31 m3
II Pekerjaan Fondasi
1 Pasangan batu Kali 1 : 4 Pcs 1.95 1.3 0.70 2.00 1.77 3.55 m3
2 Pondasi Foot Plat
a Pembesian Fondasi Foot Plat 0.9 0.9 0.12 2.00 53.31 106.62 Kg
b Pengecoran Fondasi Foot Plat K-200 0.9 0.90 0.12 2.00 0.10 0.19 m3
c Pemasangan Begisting 4 0.12 2.00 0.48 0.96 m2
d Bongkar Begisitng 0.96 m2
X Acian
1 Luas Acian 2.8 0.65 4 7.28 m2
2 Luas Acian 2.8 0.8 4 8.96 m2
3 Luas Acian 3.84 0.34 4 5.2224 m2 Luas Acian 21.4624
XI Batu Tempel
1 Batu Tempel 0.6 1.36 4 3.264 m2
2 Batu Tempel 0.75 1.36 4 4.08 m2 Batu Tempel 7.344
XIII Wiremesh
Wiremesh ∅8 2.03 0.5 4 2.03 m2
Wiremesh ∅8 1.11 0.2 4 0.888 m2 Wiremesh ∅8 2.918
XVII Bekisting
1 Bekisting atap gapura 5.66 0.1 2 1.132 m2
2 Bekisting atap gapura 0.5 0.57 2 0.57 m2
64.08 kg
118.7032 kg
20.1292 kg
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PENETAPAN KEBIJAKAN, STRATEGI DAN PROGRAM PERKOTAAN
PEKERJAAN : PENYUSUNAN DOKUMEN TEKNIS PENATAAN LINGKUNGAN (DPTL)
LOKASI : DUSUN BANARAN
TAHUN ANGGARAN : 2017
I PEKERJAAN REGOL
1 Pipa Galvanis Dim 1" 42.75 m1 78,131 3,340,100.25
3 Pipa Galvanis Dim 2" 16.38 m1 155,247 2,542,953.61
2 Reng Pipa Galvanis 1" 63.27 m' 78,131 4,943,348.37
3 Atap Galvalum 24.25 Ls 159,226 3,861,787.79
4 Besi Ornamen 5.33 Kg 23,211 123,668.21
II Pekerjaan Lain-Lain
Finishing 1.00 ls 500,000 500,000.00
15,311,858.23
JUMLAH 15,311,858.23
PPN ( 10 % ) 1,531,185.82
JML TOTAL 16,843,044.06
DIBULATKAN 16,843,000.00
PEKERJAAN PAVING
No. URAIAN PEKERJAAN Panjang Lebar Tinggi kedalaman jumlah luas volume Satuan V.Tot
I PEKERJAAN REGOL
1 Pembuatan Bak Adukan ( 40x 50x20 ) cm 1.00 1.00 bh
2 Pipa Galvanis Dim 1" 42.75 m'
3 Pipa Galvanis Dim 2" 2.73 6.00 16.38 m1
Pipa Besi 1" 1.12 10.00 11.20 m1
Pipa Besi 1" 2.91 5.00 14.55 m1
Pipa Besi 1" 0.15 20.00 3.00 m1
Pipa Besi 1" 0.26 15.00 3.90 m1
Pipa Besi 1" 0.48 10.00 4.80 m1
Pipa Besi 1" 1.06 5.00 5.30 m1 Pipa Besi 1" 106.02 m1
4 Reng Pipa Galvanis 1" 7.03 9.00 63.27 m1
5 Atap Galvalum 24.25 m2
Atap Galvalum 7.03 1.14 2.00 16.03 m2
Atap Galvalum 7.03 1.17 8.23 m2 Atap Galvalum 24.2535
6 Besi Ornamen
Besi Ornamen 1" 1 6.00 5.33 Kg
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PENETAPAN KEBIJAKAN, STRATEGI DAN PROGRAM PERKOTAAN
PEKERJAAN : PENYUSUNAN DOKUMEN TEKNIS PENATAAN LINGKUNGAN (DPTL)
LOKASI : RT 01 DUSUN SUMBERAN
TAHUN ANGGARAN : 2017
I PEKERJAAN SPAH
1 Membongkar Paving untuk dipasang kembali 18.00 titik 158,400 2,851,200.00
2 Membuat Sumur Buis Beton D-80 cm 18.00 m2 393,333 7,079,994.00
3 Tutup SPAH 45.00 m1 -
a Membuat Beton f’c = 14,5 MPa (K 175) 1.56 m3 1,147,297 1,793,750.18
b Pembesian dengan besi polos 184.14 kg 23,211 4,273,973.27
c Cetakan beton / begisting memakai papan 23.86 m2 110,009 2,625,168.92
d Membongkar cetakan 1.56 m3 79,200 123,825.84
4 Bak Kontrol 4.00 bh -
a Galian Tanah 0.84 m3 35,904 30,159.36
b Pasir Urug tebal 10 cm 0.14 m3 215,028 30,103.92
c Pasangan bata merah 1 Pc : 4 Ps 3.00 m2 111,251 333,753.00
d Plesteran 1 Pc : 4 Ps 3.00 m2 38,358 115,074.00
e Membuat Beton f’c = 14,5 MPa (K 175) 0.23 m3 1,147,297 268,467.50
f Pembesian dengan besi polos 40.84 kg 23,211 947,825.83
g Cetakan beton / begisting memakai papan 0.90 m2 110,009 99,008.10
h Membongkar cetakan 0.23 m3 79,200 18,532.80
5 Memasang Grill Besi Profil 22.00 bh -
6 Memasang Pipa PVC diameter 4" 203.00 m1 24,644 5,002,732.00
7 Memasang lapisan Ijuk 18.00 unit -
8 Membuang tanah bekas galian 33.41 m3 46,147 1,541,865.07
II Pekerjaan Sapitank
1 Membongkar Paving Pasang Kembali
2 Pekerjaan Tanah Galian 72.00 m2 158,400 11,404,800.00
3 Pekerjaan Dinding Sapitank 144.00 m3 35,904 5,170,176.00
a Pembesian Dinding Sapitank 8,292.48 Kg 23,211 192,476,753.28
b Pembetonan Dinding Sapitank 75.60 m3 1,147,297 86,735,653.20
Pemasangan Bekisting 792.00 m2 110,009 87,127,128.00
Bongkar Bekisting 792.00 m2 79,200 62,726,400.00
Plester Dinding Dalam Sapitank 432.00 m2 38,358 16,570,656.00
Jumlah Sapitank 18.00 bh
II PEKERJAAN FINISHING
1 Pembersihan lokasi dan Pengembalian Fasilitas Umum
1.00 Ls 750,000 750,000.00
JUMLAH 490,097,000.26
PPN 10% 49,009,700.03
JUMLAH TOTAL 539,106,700.29
DIBULATKAN 539,106,000.00
PEKERJAAN GAPURA
No. URAIAN PEKERJAAN Panjang Lebar Tinggi kedalaman jumlah luas volume Satuan V.Tot
I PEKERJAAN SPAH
1 Membongkar Paving untuk dipasang kembali 18.00 titik
2 Membuat Sumur Buis Beton D-80 cm 1.00 1.00 18.00 18.00 m2
3 Tutup SPAH 45.00 m1
a Membuat Beton f’c = 14,5 MPa (K 175) 1.00 0.12 18.00 1.56 m3
b Pembesian dengan besi polos 1.00 - 184.14 kg
c Cetakan beton / begisting memakai papan 1.00 - 23.86 m2
d Membongkar cetakan 0.30 18.00 1.56 m3
4 Bak Kontrol 4.00 4.00 bh
a Galian Tanah 0.70 0.60 0.50 0.84 m3
b Pasir Urug tebal 10 cm 0.70 0 0.14 m3
c Pasangan bata merah 1 Pc : 4 Ps 2.50 0.30 3.00 m2
d Plesteran 1 Pc : 4 Ps 3.00 m2
e Membuat Beton f’c = 14,5 MPa (K 175) 3.00 0.23 m3
f Pembesian dengan besi polos 2.60 0.60 40.84 kg
g Cetakan beton / begisting memakai papan 2.60 0.60 0.90 m2
h Membongkar cetakan 2.60 0.23 m3
5 Memasang Grill Besi Profil 22.00 bh
6 Memasang Pipa PVC diameter 4" 203 203.00 m1
7 Memasang lapisan Ijuk 18.00 18.00 unit
8 Membuang tanah ke luar lokasi sejauh 5 km 33.41 m3
II Pekerjaan Sapitank
1 Membongkar Paving Pasang Kembali 2.00 2.00 18.00 72.00 m2
2 Pekerjaan Tanah Galian 2.00 2.00 2.00 18.00 144.00 m3
3 Pekerjaan Dinding Sapitank
a Pembesian Dinding Sapitank 8,292.48 Kg
b Pembetonan Dinding Sapitank 75.60 m3
Pemasangan Bekisting 792.00 m2
Bongkar Bekisting 792.00 m2
Plester Dinding Dalam Sapitank 432.00 m2
Jumlah Sapitank 18.00 bh
II PEKERJAAN FINISHING
1 Pembersihan lokasi dan Pengembalian Fasilitas Umum 1.00 Ls
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PENETAPAN KEBIJAKAN, STRATEGI DAN PROGRAM PERKOTAAN
PEKERJAAN : PENYUSUNAN DOKUMEN TEKNIS PENATAAN LINGKUNGAN (DPTL)
LOKASI : RT 01 DUSUN SUMBERAN
TAHUN ANGGARAN : 2017
I Pekerjaan Galian
1 Galian tanah pondasi 0.59 m3 35,904 21,326.98
No. URAIAN PEKERJAAN Panjang Lebar Tinggi kedalaman jumlah luas volume Satuan V.Tot
I Pekerjaan Galian
1 Galian tanah pondasi 0.3 0.3 0.60 11.00 0.05 0.59 m3
I Pekerjaan Galian
1 Galian tanah pondasi 0.59 m3 35,904 21,326.98
No. URAIAN PEKERJAAN Panjang Lebar Tinggi kedalaman jumlah luas volume Satuan V.Tot
I Pekerjaan Galian
1 Galian tanah pondasi 0.3 0.3 0.60 11.00 0.05 0.59 m3
I Bongkaran
1 Bongkaran batu bata 86.40 m2 79,200 6,842,880.00
II PEKERJAAN PASANGAN
1 Pasangan Batu Bata 72.56 m2 111,251 8,072,728.56
2 Pasangan Batu Tempel 34.00 m2 261,526 8,891,884.00
IV PEKERJAAN LAIN-LAIN
1 Pembersihan Lokasi dan Pengembalian Fasilitas Umum 1.00 ls 1,500,000 1,500,000.00
31,574,792.56
JUMLAH 31,574,792.56
PPN ( 10 % ) 3,157,479.26
JML TOTAL 34,732,271.82
DIBULATKAN 34,732,000.00
No. URAIAN PEKERJAAN Panjang Lebar Tinggi kedalaman jumlah luas volume Satuan V.Tot
I PEKERJAAN PERSIAPAN
1 Membuat Papan Nama Proyek 60x120 cm (bahan flexi) 1.00 1.00 bh
2 Mobilisasi dan Demobilisasi Alat 1.00 1.00 Ls
3 Pembuatan Bak Adukan ( 40x 50x20 ) cm 1.00 1.00 bh
II Bongkaran
1 Bongkaran batu bata 3.6 1.00 40.00 72.00 m3
2 Bongkaran batu bata 1.2 0.3 40.00 14.40 m3 Bongkaran batu bata 86.40
VI Tanaman Hias
Tanaman Hias 6 40.00 240.00 bh
m3
m2
no jenis pekerjaan sta letak panjang
1 galian tanah talud 0.00 kanan sungai 26.66
kiri sungai 17.33
0.25 - 0.50 kanan sungai 42.09
kiri sungai 58.51
bawah jembatan 2.50
bawah jembatan 2.95
0.50 - 0.75 kanan sungai 23.56
kiri sungai 20.00
1.00 - 1.25 kanan sungai 1 40.70
kanan sungai 2 47.85
kanan sungai 3 43.25
kiri sungai 42.48
1.50 - 1.75 kanan sungai 1 46.37
kanan sungai 2 48.63
kanan sungai 3 38.83
kanan sungai 4 34.22
kiri sungai 57.14
1.75 - 1.93 kanan sungai 1 26.18
kanan sungai 2 31.80
kiri sungai 14.48
I Pekerjaan Talud
1 Galian Tanah Talud 1-2 meter 597.10 m3 47,213 28,191,106.40
2 Pasangan Batu Kali 1,408.71 m3 884,010 1,245,314,080.70
3 Urukan Tanah Kembali 18.33 m3 17,212 315,446.05
4 Pasang paving blok 412.66 m2 126,285 52,112,768.10
5 Plester siar timbul 947.34 m2 69,381 65,727,417.35
6 Plester dan acian 126.13 m2 45,045 5,681,480.81
7 Pekerjaan Suling-Suling D2" 236.84 m2 155,247 36,768,046.99
II Pekerjaan Lain-Lain
Finishing dan Pembersihan Lokasi 1.00 Ls 500,000 500,000.00
JUMLAH 1,434,610,346.40
PPN 10% 143,461,034.64
JUMLAH TOTAL 1,578,071,381.04
DIBULATKAN 1,578,071,000.00
No. Panjang Lebar Tinggi kedalaman
I JARINGAN HYDRANT
1 Pipa Jaringan Hydrant
a Bongkar Paving Block Untuk Dipasang Kembali
258.00 0.30
h Pengembalian Conblock
80% bongkar paving
d Siemese Connection
e Plesteran 1 Pc:3 Kp:10 Ps, tebal 15 mm
0.40 0.35
f Acian
c Pillar Hydrant
e Acian
5 Acian
jumlah luas volume
77.4 m2
77.4
34.83 m3
34.83
0.6708 m3
129.00 0.6708
258 m1
258
64.5 m2
64.5
32.1328727 m3
32.1328727
0.9675 m3
0.9675
58.05 m2
58.05
19.35 m2
19.35
0.024 m3
4.00 0.024
0.048 m3
4.00 0.048
0.32 m2
4.00 0.32
4 unit
4.00 4
0.56 m2
4.00 0.56
0.56 m2
0.56
0.024 m3
4.00 0.024
0.032 m3
4.00 0.032
4 unit
4.00 4
0.08 m2
4.00 0.08
0.08 m2
0.08
0.0245 m3
1.00 0.0245
0.0735 m3
1.00 0.0735
1 unit
1.00 1
0.665 m2
1.00 0.42
1.00 0.245
0.665 m2
0.665
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PENETAPAN KEBIJAKAN, STRATEGI DAN PROGRAM PERKOTAAN
PEKERJAAN : PENYUSUNAN DOKUMEN TEKNIS PENATAAN LINGKUNGAN (DPTL)
LOKASI : RT 01 DUSUN SUMBERAN
TAHUN ANGGARAN : 2017
Pekerjaan lain-Lain
1 Pengembalian Fasilitas Umum 1.00 ls 500,000.00 500,000.00
-
JUMLAH 62,957,404.03
62,957,404.03
JUMLAH 62,957,404.03
PPN ( 10 % ) 6,295,740.40
JML TOTAL 69,253,144.44
DIBULATKAN 69,253,000.00
No. URAIAN PEKERJAAN Panjang Lebar Tinggi kedalaman jumlah luas volume Satuan V.Tot
1 Pekerjaan CUT & FILL
galian tanah potongan 1 2.04 0.33 0.67 m3
galian tanah potongan 2 3.00 1.47 4.40 m3
galian tanah potongan 3 9.43 5.05 47.57 m3
galian tanah potongan 4 8.86 1.13 10.01 m3
galian tanah potongan 5 31.90 1.92 61.38 m3
124.03
pemadatan tanah potongan 1 1.10 2.82 3.10 m3
pemadatan tanah potongan 2 2.42 2.08 5.03 m3
pemadatan tanah potongan 4 9.66 1.80 17.39 m3
pemadatan tanah potongan 5 3.30 0.74 2.45 m3
27.97
2 Pekerjaan talud pembatas RTH
galian tanah talud 51.20 1.57 80.38 m3
pasangan talud batu kali 51.20 1.71 87.55 m3
Plester siar timbul 51.20 2.00 102.40 m2
Plester siar top 51.20 0.30 15.36 m2
Pekerjaan Suling-Suling 12.80 m2
9 Pekerjaan taman
Galian tanah pondasi 29.68 0.15 0.20 0.89 m3
Pasangan batu kali pondasi 29.68 0.10 0.15 0.45 m3
urug tanah 29.68 0.05 0.05 0.07 m3
Pemasangan batu bata taman kecil 2.00 0.15 24 7.20 m2
Pemasangan batu bata taman besar 0.45 0.20 56 5.04 m2
plesteran 12.24 m2
acian 12.24 m2
urug tanah subur 29.68 0.10 0.35 1.04 m3
penanaman tanaman biola cantik 14.00 unit
penanaman tanaman kucai (mandogras) 12.00 unit
10 Gazebo RTH
galian tanah 1.00 1.00 0.50 4 2.00 m3
urug pasir 1.00 1.00 0.10 4 0.40 m3
pasangan pondasi batu kali sebagai umpak 0.60 0.60 0.85 4 1.22 m3
urug tanah kembali 0.15 0.15 0.40 4 0.04 m3
Gazebo Kayu 1.00 Bh
11 Pergola RTH
A Pergola Tipe 1
galian tanah pondasi 1.05 0.25 0.35 3 0.28 m3
pasangan pondasi batu kali 1.00 0.20 0.30 3 0.18 m3
urug pasir 1.05 0.20 0.10 3 0.06 m3
urug tanah 1.00 0.05 0.05 3 0.01 m3
rabat beton lantai 1pc:3ps:5kr 1.00 2.55 0.10 0.26 m3
pembesian bangku dan meja dengan tulangan Ø8-100 11.00 3.00 5.46 kg
begesting bangku dan meja 0.73 m2
bongkar begesting bangku dan meja 0.73 m2
cor beton plat meja dan kursi 1.10 0.30 0.10 0.03 m3
pasangan batu bata dinding 0.60 0.60 2 0.72 m2
pasangan batu bata penyangga kursi 0.30 0.30 4 0.36 m2
pasangan batu bata penyangga meja 0.50 0.20 2 0.20 m2
acian 0.56 m2
plesteran 0.56 m2
pembesian pergola pipa galvanis Ø3'' 1.20 4 4.80 m1
pembesian atap pergola pipa galvanis Ø2'' 2.85 4 11.40 m1
penutup atap kasa galvanis Ø5mm-50mm 7.20 m2
penanaman sirih belanda 1.00 ls
B Pergola Tipe 2
pasangan batu bata bangku 1pc:4ps 0.40 0.40 4 0.64 m2
acian 0.40 0.40 8 1.28 m2
pembesian besi Ø8-150mm 1.17 0.40 2 8.16 kg
cor beton plat bangku k-175 1.17 0.40 0.12 2 0.11 m3
finishing acian bangku cor 1.17 0.40 2 0.94 m2
pembesian pergola pipa galvanis Ø2'' 1.77 4 7.08 m1
pembesian besi ornamen pergola Ø8mm 0.84 8 6.70 m1
pembesian penutup pergola pipa galvanis Ø2'' 1.37 2 2.74 m1
pembesian penutup pergola pipa galvanis Ø1'' 2.70 3 8.10 m1
Penutup kawat wiremesh M5 2.70 1.37 3.70 m2
penanaman sirih belanda 1.00 ls
IX Pekerjaan taman
Galian tanah pondasi 0.89 m3 35,904.00 31,968.92
Pasangan batu kali pondasi 0.45 m3 884,010.00 393,561.25
urug tanah 0.07 m3 17,212.00 1,277.13
Pemasangan batu bata taman kecil 7.20 m2 101,611.00 731,599.20
Pemasangan batu bata taman besar 5.04 m2 111,251.00 560,705.04
plesteran 12.24 m2 38,358.00 469,501.92
acian 12.24 m2 14,901.00 182,388.24
urug tanah subur 1.04 m3 17,212.00 17,879.83
X Gazebo RTH
galian tanah 2.00 m3 35,904.00 71,808.00
urug pasir 0.40 m3 215,028.00 86,011.20
pasangan pondasi batu kali sebagai umpak 1.22 m3 884,010.00 1,082,028.24
urug tanah kembali 0.04 m3 17,212.00 619.63
Gazebo Kayu 1.00 Bh 14,500,000.00 14,500,000.00
XI Pergola RTH
1 Pergola Tipe 1
galian tanah pondasi 0.28 m3 35,904.00 9,896.04
pasangan pondasi batu kali 0.18 m3 884,010.00 159,121.80
urug pasir 0.06 m3 215,028.00 13,546.76
urug tanah 0.01 m3 17,212.00 129.09
rabat beton lantai 1pc:3ps:5kr 0.26 m3 932,643.00 237,823.97
pembesian bangku dan meja dengan tulangan Ø8-100 5.46 kg 23,211.00 126,732.06
begesting bangku dan meja 0.73 m2 110,009.00 80,306.57
bongkar begesting bangku dan meja 0.73 m2 79,200.00 57,816.00
cor beton plat meja dan kursi 0.03 m3 884,010.00 29,172.33
pasangan batu bata dinding 0.72 m2 111,251.00 80,100.72
pasangan batu bata penyangga kursi 0.36 m2 111,251.00 40,050.36
pasangan batu bata penyangga meja 0.20 m2 111,251.00 22,250.20
acian 0.56 m2 14,901.00 8,344.56
plesteran 0.56 m2 38,358.00 21,480.48
pembesian pergola pipa galvanis Ø3'' 4.80 m1 23,211.00 111,412.80
pembesian atap pergola pipa galvanis Ø2'' 11.40 m1 23,211.00 264,605.40
2 Pergola Tipe 2 -
pasangan batu bata bangku 1pc:4ps 0.64 m2 111,251.00 71,200.64
acian 1.28 m2 38,358.00 49,098.24
pembesian besi Ø8-150mm 8.16 kg 23,211.00 189,494.60
cor beton plat bangku k-175 0.11 m3 1,147,297.00 128,864.40
finishing acian bangku cor 0.94 m2 14,901.00 13,947.34
pembesian pergola pipa galvanis Ø2'' 7.08 m1 23,211.00 164,333.88
pembesian besi ornamen pergola Ø8mm 6.70 m1 23,211.00 155,513.70
pembesian penutup pergola pipa galvanis Ø2'' 2.74 m1 23,211.00 63,598.14
pembesian penutup pergola pipa galvanis Ø1'' 8.10 m1 23,211.00 188,009.10
-
XII Pagar Pengaman RTH -
1 pipa galvanis Ø3'' 26.00 m1 190,232.06 4,946,033.47
XIII Permainan RTH -
1 Ayunan Gapura 1.00 unit 1,000,000.00 1,000,000.00
2 Halang Rintang 1.00 unit 1,000,000.00 1,000,000.00
3 Dock 1.00 unit 1,000,000.00 1,000,000.00
4 Mangakok Putar 2.00 unit 1,500,000.00 3,000,000.00
5 Jungkitan 1.00 unit 1,500,000.00 1,500,000.00
HARGA SAT. JUMLAH HARGA
NO. URAIAN PEKERJAAN VOL. SAT
( Rp. ) ( Rp. )
XIII Pekerjaan Lain - Lain -
1 Pengembalian Fasilitas Umum 1.00 ls 500,000.00 500,000.00
-
JUMLAH 249,810,293.60
249,810,293.60
JUMLAH 249,810,293.60
PPN ( 10 % ) 24,981,029.36
JML TOTAL 274,791,322.96
DIBULATKAN 274,791,000.00
PEKERJAAN JEMBATAN
No. URAIAN PEKERJAAN Panjang Lebar Tinggi jumlah luas volume Satuan V.Tot
I PEKERJAAN PERSIAPAN
1 Membuat Papan Nama Proyek 60x120 cm (bahan flexi) 1.00 1.00 bh
2 Mobilisasi dan Demobilisasi Alat 1.00 1.00 Ls
3 Pembuatan Bak Adukan ( 40x 50x20 ) cm 1.00 1.00 bh
II Bongkaran
1 Bongkaran Tembok 1 0.15 1.16 - 0.17 m2
2 Bongkaran Tembok 1 0.15 1.25 - 0.19 m3 Bongkaran Tembok
3 Bongkaran Beton Jembatan 12.22 2.10 0.30 7.70 m3
4 Bongkaran Beton Pagar Jembatan 0.15 0.15 1.20 18.00 0.49 m3 Bongkaran Beton
5 Bongkaran Besi Pagar Jembatan 12.18 0.08 0.08 4.00 0.311808 m3
Bongkaran total
III Mengankut Hasil Bongkaran
1 Mengankut Hasil Bongkaran Sejauh 5 km 8.857908 m3
III Galian
1 Galian tanah fondasi pasangan batu kali 3.26 4.50 0.46 2.00 6.7482 m3
2 Galian tanah fondasi pasangan batu kali 2.5 5.00 0.80 2.00 20 m3 Galian tanah fondasi pasangan batu kali
3 Galian Fondasi Sumuran 4.5 1.70 2.25 2.00 34.425 m3
IV Timbunan
1 Timbunan Tanah 3.71 5.00 0.54 5.0085 m3
V Cor Beton
1 Cor beton K250 0.79 3.70 0.10 2.00 0.5846 m3
2 Cor beton K250 0.94 3.70 0.20 2.00 1.3912 m3
3 Cor beton K250 0.45 3.70 0.20 2.00 0.666 m3
4 Cor beton K200 2 3.70 0.20 2.00 2.96 m3
5 Cor beton K250 12 5.00 0.20 12 m3
6 Cor beton K250 Pagar Jembatan 0.15 0.15 0.88 18.00 0.3564 m3
7 Cor beton K250 Pagar Jembatan 0.56 0.15 0.32 18.00 0.24192 m3 Cor beton K250
8 Cor beton K175 Trotoar 12.4 0.85 0.20 2.00 4.216 m3
VI Pagar PipaGalvanis
1 Pagar PipaGalvanis 3" 12.18 4.00 48.72 m1
X Batu Hias
1 Batu Hias 4.00 4 bh
XI Lampu LED
1 Lampu LED 4.00 4 bh
XII Cansteen
1 Cansteen 42X20X15X10 12.5 2.00 25 m1
XIV Baut
1 Baut ∅25 541.00 541 bh
XV Shear Connector
1 Shear Connector 72.00 72 bh
XIX Bekisting
1 Bekisting Papan plat jembatan 12 5.00 60 m2
2 Bekisting pagar jembatan 1.4 0.66 9.00 8.316 m2
3 Bekisting Papan jembatan 0.94 0.30 4.00 1.128 m2
4 Bekisting Papan jembatan 0.45 0.20 4.00 0.36 m2
5 Bekisting Papan jembatan 3.7 0.20 2.00 1.48 m2
6 Bekisting Papan jembatan 3.7 0.74 2.00 5.476 m2
7 Bekisting Papan jembatan 3.7 0.94 2.00 6.956 m2
8 Bekisting Papan jalan 14 0.20 2.8 m2 Bekisting
XX Urug Tanah
1 Urug Tanah 2.86 5.00 0.34 2.00 4.862 m2
2 Urug Tanah 1.58 5.00 0.20 2.00 1.58 m2 Urug Tanah
0.36
8.18
8.86
26.7482
18.20012
42.96
4645.181 kg
86.516
6.442
RENCANA ANGGARAN BIAYA (RAB)
KEGIATAN : PENETAPAN KEBIJAKAN, STRATEGI DAN PROGRAM PERKOTAAN
PEKERJAAN : PENYUSUNAN DOKUMEN TEKNIS PENATAAN LINGKUNGAN (DPTL)
LOKASI : DUSUN BANARAN
TAHUN ANGGARAN : 2017
PEKERJAAN LAIN-LAIN -
1 Pembersihan Lokasi dan Pengembalian Fasilitas Umum 1.00 ls 500,000 500,000.00
-
375,690,711.63
JUMLAH 375,690,711.63
PPN ( 10 % ) 37,569,071.16
JML TOTAL 413,259,782.79
DIBULATKAN 413,259,000.00
BACK UP VOLUME
II Pekerjaan Sapitank
1 Membongkar Paving Pasang Kembali 72.000 m2
2 Pekerjaan Tanah Galian 144.000 m3
3 Pekerjaan Dinding Sapitank
a Pembesian Dinding Sapitank 8,292.480 Kg
b Pembetonan Dinding Sapitank 75.600 m3
Pemasangan Bekisting 792.000 m2
Bongkar Bekisting 792.000 m2
Plester Dinding Dalam Sapitank 432.000 m2
Jumlah Sapitank 18.000 bh
II PEKERJAAN FINISHING
1 Pembersihan lokasi dan Pengembalian Fasilitas Umum 1.000 Ls
ANALISA SATUAN PEKERJAAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
PEKERJAAN PERSIAPAN
SNI 1.0000 m1 Pengukuran dan pemasangan bouwplank untuk gedung dan saluran
6.4 0.0120 m3 Kayu meranti 5/7 @ Rp. 19,000.00 228.00
03-2835-2002 0.0200 kg Paku reng @ Rp. 22,743.00 454.86
0.0070 m3 Kayu meranti papan 3/20 @ Rp. 32,500.00 227.50
0.1000 org Tukang kayu @ Rp. Err:509 Err:509
0.0100 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1000 org Pekerja @ Rp. Err:509 Err:509
0.0050 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 910.36 Err:509
JASA 10 % Err:509 91.04 Err:509
JUMLAH Err:509 1,001.40 Err:509
DIBULATKAN Err:509 1,001.00 Err:509
SNI 1.0000 m1 Pembuatan pagar sementara dari seng gelombang tinggi 2 meter
6.2 1.2500 btg Dolken kayu Ø 8 - 10/400 cm @ Rp. 12,500.00 15,625.00
03-2835-2002 2.5000 kg PC @ Rp. 1,580.00 3,950.00
1.2000 lbr Seng gelombang 2"-5" BJLS 24 @ Rp. 73,333.00 87,999.60
0.0050 m3 Pasir beton @ Rp. 208,000.00 1,040.00
0.0090 m3 Kerikil beton @ Rp. 281,250.00 2,531.25
0.0250 m3 Kaso 5/7 kayu meranti @ Rp. 5,442,700.00 136,067.50
0.0600 kg Paku biasa 2" - 5" @ Rp. 22,202.00 1,332.12
0.4000 kg Meni besi @ Rp. 24,090.00 9,636.00
0.2000 org Tukang kayu @ Rp. Err:509 Err:509
0.0200 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.4000 org Pekerja @ Rp. Err:509 Err:509
0.0200 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 258,181.47 Err:509
JASA 10 % Err:509 25,818.15 Err:509
JUMLAH Err:509 283,999.62 Err:509
DIBULATKAN Err:509 283,999.00 Err:509
PEKERJAAN TANAH
SNI 1.0000 m3 Galian tanah biasa sedalam sampai 1 meter
6.1 0.4000 org Pekerja @ Rp. Err:509 Err:509
0.0400 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 Err:509
JUMLAH Err:509 Err:509
DIBULATKAN Err:509 Err:509
A14 1.0000 m3 Mengangkut hasil galian dan bongkaran dengan dump truck jarak angkut 5 km
org Pekerja @ Rp. -
org Mandor @ Rp. -
0.2400 jam Dump truck @ Rp. 224,770.92 53,945.02
JUMLAH ( BELUM PPN ) - 53,945.02 53,945.02
JASA 10 % - 5,394.50 5,394.50
JUMLAH - 59,339.52
DIBULATKAN - 59,339.00
A14 1.0000 m3 Mengangkut hasil galian dan bongkaran dengan dump truck jarak angkut 5 km
1.0000 org Sopir @ Rp. Err:509 Err:509
1.0000 org Kemet @ Rp. Err:509 Err:509
2.4000 lt Solar industri @ Rp. 8,500.00 20,400.00
0.2400 jam Dump truck @ Rp. 224,770.92 53,945.02
JUMLAH ( BELUM PPN ) 74,345.02 Err:509 Err:509
JASA 10 % 7,434.50 Err:509 Err:509
JUMLAH 81,779.52 Err:509
DIBULATKAN 81,779.00 Err:509
1.0000 m2 Membongkar Paving untuk di pergunakan lagi
0.1000 org Pekerja @ Rp. Err:509 Err:509
0.0500 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
AK 1.0000 m2 Pasang Kembali Paving bekas bongkaran
1.0000 m2 Paving @ Rp. -
0.0500 m3 Pasir urug @ Rp. 131,000.00 6,550.00
0.2500 org Tukang batu @ Rp. Err:509 Err:509
0.0250 org Kep. Tk. Batu @ Rp. Err:509 Err:509
0.5000 org Pekerja @ Rp. Err:509 Err:509
0.0250 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 6,550.00 Err:509
JASA 10 % Err:509 655.00 Err:509
JUMLAH Err:509 7,205.00 Err:509
DIBULATKAN Err:509 7,205.00 Err:509
PEKERJAAN PASANGAN
PEKERJAAN BETON
SNI 1.0000 m3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr -
6.13 336.0000 kg PC @ Rp. 1,580.00 530,880.00
0.5400 m3 Pasir beton @ Rp. 208,000.00 112,320.00
0.8100 m3 Kerikil beton / koral @ Rp. 266,000.00 215,460.00
0.3500 org Tukang batu @ Rp. Err:509 Err:509
0.0350 org Kepala tukang batu @ Rp. Err:509 Err:509
2.0000 org Pekerja @ Rp. Err:509 Err:509
0.1000 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 858,660.00 Err:509
JASA 10 % Err:509 85,866.00 Err:509
JUMLAH Err:509 944,526.00 Err:509
DIBULATKAN Err:509 944,526.00 Err:509
PEKERJAAN PELESTERAN
PEKERJAAN KERAMIK
PEKERJAAN CONBLOCK
AK 1.0000 m2 Pasang usuk 5/7 kayu jati, reng 2/3 kayu bengkirai
2.2000 m1 Usuk kayu jati 5/7 @ Rp. -
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
5.0000 m1 Reng kayu bengkirai 2/3 @ Rp. 6,400.00 32,000.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. Err:509 Err:509
0.0100 org Kep. Tk. Kayu @ Rp. Err:509 Err:509
0.1000 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 37,604.60 Err:509
JASA 10 % Err:509 3,760.46 Err:509
JUMLAH Err:509 41,365.06 Err:509
DIBULATKAN Err:509 41,365.00 Err:509
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu jati
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 37,000.00 81,400.00
5.0000 m1 Reng jati 2/3 @ Rp. -
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. Err:509 Err:509
0.0100 org Kep. Tk. Kayu @ Rp. Err:509 Err:509
0.1000 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 87,004.60 Err:509
JASA 10 % Err:509 8,700.46 Err:509
JUMLAH Err:509 95,705.06 Err:509
DIBULATKAN Err:509 95,705.00 Err:509
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 2/3 kayu bengkirai
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 37,000.00 81,400.00
5.0000 m1 Reng kayu bengkirai 2/3 @ Rp. 6,400.00 32,000.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. Err:509 Err:509
0.0100 org Kep. Tk. Kayu @ Rp. Err:509 Err:509
0.1000 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 119,004.60 Err:509
JASA 10 % Err:509 11,900.46 Err:509
JUMLAH Err:509 130,905.06 Err:509
DIBULATKAN Err:509 130,905.00 Err:509
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu jati lokal
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 37,000.00 81,400.00
4.0000 m1 Reng kayu jati 3/4 lokal @ Rp. -
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. Err:509 Err:509
0.0100 org Kep. Tk. Kayu @ Rp. Err:509 Err:509
0.1000 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 87,004.60 Err:509
JASA 10 % Err:509 8,700.46 Err:509
JUMLAH Err:509 95,705.06 Err:509
DIBULATKAN Err:509 95,705.00 Err:509
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu bengkirai
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 37,000.00 81,400.00
4.0000 m1 Reng kayu bengkirai 3/4 @ Rp. 6,400.00 25,600.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 kg Paku reng @ Rp. 22,743.00 2,274.30
0.1000 org Tukang kayu @ Rp. Err:509 Err:509
0.0100 org Kep. Tk. Kayu @ Rp. Err:509 Err:509
0.1000 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 112,604.60 Err:509
JASA 10 % Err:509 11,260.46 Err:509
JUMLAH Err:509 123,865.06 Err:509
DIBULATKAN Err:509 123,865.00 Err:509
AK 1.0000 m2 Pasang usuk 5/7 kayu bengkirai, reng 3/4 kayu bengkirai
2.2000 m1 Usuk kayu bengkirai 5/7 @ Rp. 37,000.00 81,400.00
0.1500 kg Paku usuk @ Rp. 22,202.00 3,330.30
0.1000 org Tukang kayu @ Rp. Err:509 Err:509
0.0100 org Kep. Tk. Kayu @ Rp. Err:509 Err:509
0.1000 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 84,730.30 Err:509
JASA 10 % Err:509 8,473.03 Err:509
JUMLAH Err:509 93,203.33 Err:509
DIBULATKAN Err:509 93,203.00 Err:509
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
SNI 1.0000 m2 Pasang pintu teakwood rangkap, rangka kayu jati lokal
6.19 0.0196 m3 Papan kayu jati lokal @ Rp. -
03-3434-2002 0.0300 kg Paku biasa 1/2" - 1" @ Rp. -
0.3000 kg Lem kayu @ Rp. -
1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp. -
2.0000 org Tukang kayu @ Rp. Err:509 Err:509
0.2000 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.6000 org Pekerja @ Rp. Err:509 Err:509
0.0300 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m2 Pasang pintu dan jendela kaca kayu jati lokal
6.9 0.0350 m3 Papan kayu jati lokal @ Rp. 12,604,000.00 441,140.00
03-3434-2002 2.0000 org Tukang kayu @ Rp. Err:509 Err:509
0.2000 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.8000 org Pekerja @ Rp. Err:509 Err:509
0.0400 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 441,140.00 Err:509
JASA 10 % Err:509 44,114.00 Err:509
JUMLAH Err:509 485,254.00 Err:509
DIBULATKAN Err:509 485,254.00 Err:509
SNI 1.0000 m2 Mengerjakan daun pintu / jendela panil kayu jati lokal
6.7 0.0400 m3 Kayu jati papan lokal @ Rp. 12,604,000.00 504,160.00
03-3434-2002 2.5000 org Tukang kayu @ Rp. Err:509 Err:509
0.2500 org Kepala tukang kayu @ Rp. Err:509 Err:509
1.0000 org Pekerja @ Rp. Err:509 Err:509
0.0500 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 504,160.00 Err:509
JASA 10 % Err:509 50,416.00 Err:509
JUMLAH Err:509 554,576.00 Err:509
DIBULATKAN Err:509 554,576.00 Err:509
PEKERJAAN PLAFOND
SNI 1.0000 m2 Pasang rangka langit-langit (1,00 x 1,00) m, kayu lama
03-3434-2002 0.1000 kg Paku biasa 2" - 5" @ Rp. -
0.2500 org Tukang kayu @ Rp. Err:509 Err:509
0.0250 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1500 org Pekerja @ Rp. Err:509 Err:509
0.0075 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kamper tanpa plepet
0.0120 m3 Kayu kamper balok @ Rp. 8,880,200.00 106,562.40
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
0.3200 org Tukang kayu @ Rp. Err:509 Err:509
0.0320 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1800 org Pekerja @ Rp. Err:509 Err:509
0.0090 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 106,562.40 Err:509
JASA 10 % Err:509 10,656.24 Err:509
JUMLAH Err:509 117,218.64 Err:509
DIBULATKAN Err:509 117,218.00 Err:509
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kruing tanpa plepet
0.0120 m3 Kayu kruing balok @ Rp. 6,302,000.00 75,624.00
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
0.3200 org Tukang kayu @ Rp. Err:509 Err:509
0.0320 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1800 org Pekerja @ Rp. Err:509 Err:509
0.0090 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 75,624.00 Err:509
JASA 10 % Err:509 7,562.40 Err:509
JUMLAH Err:509 83,186.40 Err:509
DIBULATKAN Err:509 83,186.00 Err:509
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka bengkirai tanpa plepet
0.0120 m3 Kayu bengkirai balok @ Rp. 10,598,900.00 127,186.80
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
0.3200 org Tukang kayu @ Rp. Err:509 Err:509
0.0320 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1800 org Pekerja @ Rp. Err:509 Err:509
0.0090 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 127,186.80 Err:509
JASA 10 % Err:509 12,718.68 Err:509
JUMLAH Err:509 139,905.48 Err:509
DIBULATKAN Err:509 139,905.00 Err:509
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kayu lama dg plepet
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
2.6000 m1 Plepet kayu @ Rp. -
0.0100 kg Paku eternit @ Rp. -
0.0100 kg Paku plepet @ Rp. -
0.3200 org Tukang kayu @ Rp. Err:509 Err:509
0.0320 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1800 org Pekerja @ Rp. Err:509 Err:509
0.0090 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kayu kamper dg plepet
0.0120 m3 Kayu kamper balok @ Rp. 8,880,200.00 106,562.40
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
2.6000 m1 Plepet kayu @ Rp. -
0.0100 kg Paku eternit @ Rp. -
0.0100 kg Paku plepet @ Rp. -
0.3200 org Tukang kayu @ Rp. Err:509 Err:509
0.0320 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1800 org Pekerja @ Rp. Err:509 Err:509
0.0090 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 106,562.40 Err:509
JASA 10 % Err:509 10,656.24 Err:509
JUMLAH Err:509 117,218.64 Err:509
DIBULATKAN Err:509 117,218.00 Err:509
SNI 1.0000 m2 Langit2 asbes (1,00 x 1,00) m, rangka kayu kruing dg plepet
0.0120 m3 Kayu kruing balok @ Rp. 6,302,000.00 75,624.00
03-2838-2002 0.0600 kg Paku biasa @ Rp. -
1.1000 lbr Asbes 1,00 x 1,00 m @ Rp. -
2.6000 m1 Plepet kayu @ Rp. -
0.0100 kg Paku eternit @ Rp. -
0.0100 kg Paku plepet @ Rp. -
0.3200 org Tukang kayu @ Rp. Err:509 Err:509
0.0320 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1800 org Pekerja @ Rp. Err:509 Err:509
0.0090 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 75,624.00 Err:509
JASA 10 % Err:509 7,562.40 Err:509
JUMLAH Err:509 83,186.40 Err:509
DIBULATKAN Err:509 83,186.00 Err:509
6.13 1.0000 m2 Langit2 gypsum t;l 9 mm, rangka 60 x 120 kayu kruing
0.0130 m3 Kayu kruing @ Rp. 6,302,000.00 81,926.00
0.3600 lbr Gypsum board 9 mm @ Rp. -
0.0500 roll Kasa gypsum @ Rp. -
0.4500 kg Tepung gypsum @ Rp. -
0.0030 kg Alkasit @ Rp. -
0.0500 kg Paku gypsum @ Rp. -
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.1200 kg Paku usuk @ Rp. -
0.3700 org Tukang kayu @ Rp. Err:509 Err:509
0.0370 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.2400 org Pekerja @ Rp. Err:509 Err:509
0.0120 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 81,926.00 Err:509
JASA 10 % Err:509 8,192.60 Err:509
JUMLAH Err:509 90,118.60 Err:509
DIBULATKAN Err:509 90,118.00 Err:509
6.13 1.0000 m2 Langit2 kalsiboard t;l 3.5 mm, rangka 60 x 120 ky kruing
0.0130 m3 Kayu kruing @ Rp. 6,302,000.00 81,926.00
0.3600 lbr Kalsiboard 3.5 mm @ Rp. -
0.0500 roll Kasa gypsum @ Rp. -
0.4500 kg Tepung gypsum @ Rp. -
0.0030 kg Alkasit @ Rp. -
0.0500 kg Paku gypsum @ Rp. -
0.1200 kg Paku usuk @ Rp. -
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.3700 org Tukang kayu @ Rp. Err:509 Err:509
0.0370 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.2400 org Pekerja @ Rp. Err:509 Err:509
0.0120 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 81,926.00 Err:509
JASA 10 % Err:509 8,192.60 Err:509
JUMLAH Err:509 90,118.60 Err:509
DIBULATKAN Err:509 90,118.00 Err:509
PEKERJAAN LISPLANG
1.0000 m1 Pasang lisplank ukuran (2 x 20) cm, kayu jati
0.0048 m3 Kayu jati papan @ Rp. -
0.0600 kg Paku biasa 2" - 5" @ Rp. -
0.1000 org Tukang kayu @ Rp. Err:509 Err:509
0.0100 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1000 org Pekerja @ Rp. Err:509 Err:509
0.0050 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
PEKERJAAN TALANG
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu kamper
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0096 m3 Kayu kamper papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. Err:509 Err:509
0.0250 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1500 org Pekerja @ Rp. Err:509 Err:509
0.0013 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu kruing
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0096 m3 Kayu kruing papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. Err:509 Err:509
0.0250 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1500 org Pekerja @ Rp. Err:509 Err:509
0.0013 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m1 Pasang talang datar, seng BJLS 28, papan kayu bengkirai
6.18 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0096 m3 Kayui bengkirai papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. Err:509 Err:509
0.0250 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1500 org Pekerja @ Rp. Err:509 Err:509
0.0013 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu kamper
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0190 m3 Kayu kamper papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. Err:509 Err:509
0.0250 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.0400 org Pekerja @ Rp. Err:509 Err:509
0.0013 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu kruing
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0190 m3 Kayu kruing papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. Err:509 Err:509
0.0250 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.0400 org Pekerja @ Rp. Err:509 Err:509
0.0013 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m1 Pasang talang miring, seng BJLS 28, papan kayu bengkirai
6.19 0.5000 lbr Seng plat 3' x 6' BJLS 28 @ Rp. -
0.0150 kg Paku biasa 1/2" - 1" @ Rp. -
0.0190 m3 Kayu bengkirai papan @ Rp. -
0.2500 kg Flincoat @ Rp. -
0.4000 org Tukang kayu @ Rp. Err:509 Err:509
0.0250 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.0400 org Pekerja @ Rp. Err:509 Err:509
0.0013 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m2 Pasang dinding pemisah teakwood rangkap, rangka kayu kamper
03-3434-2002 0.0195 m3 Kayu kamper balok @ Rp. -
6.56 0.0070 m3 Kayu kamper papan @ Rp. -
0.1000 kg Paku biasa 2" - 5" @ Rp. -
0.5600 kg Lem kayu @ Rp. -
1.0000 lbr Teakwood 4' x 8' x 4 mm @ Rp.
0.4500 org Tukang kayu @ Rp. Err:509 Err:509
0.0450 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.1500 org Pekerja @ Rp. Err:509 Err:509
0.0750 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
PEKERJAAN ATAP
H.2A 1.0000 m2 Pas. genteng beton besar Natural ( isi 9 / m2 ) untuk r. tingkat
9.0000 bh Genteng beton natural @ Rp. -
0.1000 org Tukang batu @ Rp. Err:509 Err:509
0.0100 org Kep. Tk. Batu @ Rp. Err:509 Err:509
0.3000 org Pekerja @ Rp. Err:509 Err:509
0.0150 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
H.2A 1.0000 m2 Pas. genteng beton besar Warna ( isi 9 / m2 ) untuk r. tingkat
9.0000 bh Genteng beton Warna @ Rp. -
0.1000 org Tukang batu @ Rp. Err:509 Err:509
0.0100 org Kep. Tk. Batu @ Rp. Err:509 Err:509
0.3000 org Pekerja @ Rp. Err:509 Err:509
0.0150 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m2 Pasang atap genteng metal zinc alume type prima roof
03-3436-2002 1.0200 m2 Genteng metal @ Rp. -
6.32 0.2000 kg Paku anti karat @ Rp. -
0.1000 org Tukang kayu @ Rp. Err:509 Err:509
0.0100 org Kepala tukang kayu @ Rp. Err:509 Err:509
0.2000 org Pekerja @ Rp. Err:509 Err:509
0.0010 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
PEKERJAAN CAT-CATAN
SNI 1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
6.8 0.2000 kg Cat meni @ Rp. -
0.1500 kg Plamir @ Rp. -
0.1700 kg Cat dasar @ Rp. -
0.2600 kg Cat penutup @ Rp. -
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
0.0900 org Tukang cat @ Rp. -
0.0060 org Kepala tukang cat @ Rp. -
0.0700 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
6.9 0.2000 kg Cat meni @ Rp. -
0.1500 kg Plamir @ Rp. -
0.1700 kg Cat dasar @ Rp. -
0.3500 kg Cat penutup @ Rp. -
0.1050 org Tukang cat @ Rp. -
0.0040 org Kepala tukang cat @ Rp. -
0.0700 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
6.14 0.1000 kg Plamir tembok @ Rp. -
0.1000 kg Cat dasar @ Rp. -
0.2600 kg Cat penutup 2 x @ Rp. -
0.0630 org Tukang cat @ Rp. -
0.0063 org Kepala tukang cat @ Rp. -
0.0200 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
6.15 0.1200 kg Cat dasar @ Rp. -
0.1800 kg Cat penutup 2 x @ Rp. -
0.0420 org Tukang cat @ Rp. -
0.0042 org Kepala tukang cat @ Rp. -
0.0280 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m2 Pengecatan tembok tidak terlindung dari panas dan hujan
6.14 0.1000 kg Cat alkali resisting primer @ Rp. -
0.3600 kg Cat ICI Weathershield @ Rp. -
0.0630 org Tukang cat @ Rp. -
0.0063 org Kepala tukang cat @ Rp. -
0.0200 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m2 Melabur tembok lama dengan kapur sirih (untuk pemeliharaan)
6.18 0.0020 m3 Perancah kayu @ Rp. -
0.3000 kg Kapur sirih @ Rp. -
0.0050 org Tukang cat @ Rp. -
0.0005 org Kepala tukang cat @ Rp. -
0.0400 org Pekerja @ Rp. Err:509 Err:509
0.0025 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 m2 Pengecacatan permukaan baja dengan meni besi memakai perancah
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
6.21 0.1000 kg Meni besi sinkromat @ Rp. -
0.0100 bh Kuas @ Rp. -
0.0020 m3 Perancah kayu @ Rp. -
0.2250 org Tukang cat @ Rp. -
0.0225 org Kepala tukang cat @ Rp. -
0.2250 org Pekerja @ Rp. Err:509 Err:509
0.0075 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
PEKERJAAN BONGKARAN
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
AK 1.0000 m3 Membongkar pasangan batu kali
4.0000 org Tukang batu @ Rp. Err:509 Err:509
0.4000 org Pekerja @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
L.12 1.0000 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi
6.0000 org Tukang kayu @ Rp. Err:509 Err:509
0.6000 org Kep. Tk. Kayu @ Rp. Err:509 Err:509
4.0000 org Pekerja @ Rp. Err:509 Err:509
0.2000 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
1.0000 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi
1.0000 org Pekerja @ Rp. Err:509 Err:509
0.2000 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
ANALISA SUPLEMEN
3 1.0000 m Pengelasan Single ( las listrik )
3.0000 kg Kawat las @ Rp. -
1.0000 hari Peralatan las @ Rp. -
0.5000 org Tukang las @ Rp. -
0.0500 org Kepala tukang las @ Rp. -
1.0000 Org Pekerja @ Rp. Err:509 Err:509
1.0000 Org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
PEKERJAAN SANITASI
SNI 1.0000 bh Memasang kloset duduk/monoblock
1.0000 bh Kloset duduk / monoblock @ Rp. -
6.1 6% x Harga kloset (Perlengkapan) @ Rp. -
1.1000 org Tukang batu @ Rp. Err:509 Err:509
0.0010 org Kepala tukang batu @ Rp. Err:509 Err:509
3.3000 org Pekerja @ Rp. Err:509 Err:509
0.1600 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 bh Memasang bak kontrol pas.bata (30 x 30) cm, tinggi 35 cm
87.0000 bh Batu bata @ Rp. -
6.16 44.0000 kg PC @ Rp. -
0.0700 m3 Pasir pasang @ Rp. -
0.0700 m3 Batu kerikil @ Rp. -
1.6000 kg Besi beton @ Rp. -
0.0600 m3 Pasir beton @ Rp. -
1.0150 org Tukang batu @ Rp. Err:509 Err:509
0.0015 org Kepala tukang batu @ Rp. Err:509 Err:509
3.2000 org Pekerja @ Rp. Err:509 Err:509
0.0160 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
SNI 1.0000 bh Memasang bak kontrol pas. bata (45 x 45) cm, tinggi 50 cm
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
150.0000 bh Batu bata @ Rp. 649.00 97,350.00
6.17 77.0000 kg PC @ Rp. 1,580.00 121,660.00
0.1300 m3 Pasir pasang @ Rp. 208,000.00 27,040.00
0.0200 m3 Batu kerikil @ Rp. 266,000.00 5,320.00
2.6000 kg Besi beton @ Rp. 17,000.00 44,200.00
0.0900 m3 Pasir beton @ Rp. 208,000.00 18,720.00
0.4730 org Tukang batu @ Rp. Err:509 Err:509
0.0470 org Kepala tukang batu @ Rp. Err:509 Err:509
1.4200 org Pekerja @ Rp. Err:509 Err:509
0.0710 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 314,290.00 Err:509
JASA 10 % Err:509 31,429.00 Err:509
JUMLAH Err:509 345,719.00 Err:509
DIBULATKAN Err:509 345,719.00 Err:509
SNI 1.0000 bh Memasang bak kontrol pas. bata (60 x 60) cm, tingg 65 cm
222.0000 bh Batu bata @ Rp. -
6.18 114.0000 kg PC @ Rp. -
0.1840 m3 Pasir pasang @ Rp. -
0.0330 m3 Batu kerikil @ Rp. -
4.8500 kg Besi beton @ Rp. -
0.1200 m3 Pasir beton @ Rp. -
0.7200 org Tukang batu @ Rp. Err:509 Err:509
0.0720 org Kepala tukang batu @ Rp. Err:509 Err:509
2.1600 org Pekerja @ Rp. Err:509 Err:509
0.1000 org Mandor @ Rp. Err:509 Err:509
JUMLAH ( BELUM PPN ) Err:509 - Err:509
JASA 10 % Err:509 - Err:509
JUMLAH Err:509 - Err:509
DIBULATKAN Err:509 - Err:509
PEKERJAAN JALAN
100.000 ton/hari Produksi Lataston HRS (Lapis Aspal Tipis Aspal Beton )
1.000 Mandor @ Rp. Err:509 Err:509
4.000 Tenaga @ Rp. Err:509 Err:509
6,324.000 Kg Aspal curah @ Rp. -
32.310 M3 Pasir ayak untuk beton @ Rp. -
27.500 M3 Batu pecah 9.5 - 19 mm @ Rp. -
7,480.000 Kg Filler @ Rp. -
1.000 Set Alat bantu @ Rp. -
4.000 jam Wheel Loader 115 HP @ Rp. -
4.000 jam Asphalt Mixing Plant 30 Ton/Jam @ Rp. -
42.000 jam Dump Truck 5,0 Ton @ Rp. -
tiap1ton - Err:509 Err:509
0.0100 x Err:509
Bj HRS 2,3 t/m3 2.30 JUMLAH (BELUM JASA) Err:509
per 1m2 tebal 1.00 100 Err:509
1.000 m2 Lataston HRS-BC5 cm padat (Lapis Aspal Tipis Aspal Beton ) - Leveling
tebal Lapis Aspal Resap Pengikat Prime Coat Err:509
5.000 cm Lataston HRS-BC5 cm padat (Lapis Aspal Tipis Aspal Beton ) - Leveling Err:509
Menghampar HRS Err:509
JUMLAH : Err:509
JASA 10 % : Err:509
JUMLAH ( BELUM TERMASUK PPN ) : Err:509
DIBULATKAN : Err:509
JUMLAH : 2,235,000.00
A PEKERJAAN TANAH
1 Bongkar Perkerasan Aspal - m2 9,250.00 -
2 Galian Tanah Biasa Sedalam 1-2m 90.63 m3 #REF! #REF!
3 Timbunan Pasir Sebagai Bahan Pengisi - m3 #REF! #REF!
4 Timbunan Sirtu Sebagai Bahan Pengisi 105.93 m1 #REF! #REF!
5 Timbunan Tanah atau Urugan Kembali 1.03 m2 #REF! #REF!
6 Pemadatan Pasir dan Sirtu 105.93
7 Mengangkut Hasil Galian dan Bongkaran Dengan Dump Truck Jarak Angkut 5 km 89.60
JUMLAH : #REF!
B PEKERJAAN SAH
1 Langsiran Box Culvert 60 x 60 cm 1.00 m3 #REF! #REF!
2 Box Culvert 60 x 60 cm Gandar 20 T 42.80 m3 #REF! #REF!
3 Upah Pasang Box Culvert 60 x 60 cm Gandar 20 T 42.80 m3 #REF! #REF!
4 Cor Beton K-175 Balok Landasan 15 x 15 x 30 cm 0.72 m3 #REF! #REF!
JUMLAH : #REF!
C PEKERJAAN SUMUR RESAPAN
1 Beton BertulangDinding SAH K175 1.63 m3 #REF! #REF!
2 Beton Mutu, f'c=14,5 Mpa (K175), Menggunakan Molen 140.68 m3 #REF! #REF!
3 Pembesian dengan besi polos 19.80 m3 #REF! #REF!
4 Bekisting Beton Biasa dengan Multiplex 9 mm 19.80 m3 #REF! #REF!
5 Bongkar Bekisting Secara Hati hati (pakai ulang 2 kali) - m3 #REF! #REF!
6 Beton Bertulang Plat SAH K175 (Landasan Manhole) 2.97 m2 #REF! #REF!
7 Beton Mutu, f'c=14,5 Mpa (K175), Menggunakan Molen 175.75 m2 #REF! #REF!
8 Pembesian dengan besi polos 2.20 m' #REF! #REF!
9 Bekisting Beton Biasa dengan Multiplex 9 mm 2.20 Unit 342,500,000.00 753,500,000.00
10 Bongkar Bekisting Secara Hati hati (pakai ulang 2 kali) 20.25 Paket 3,000,000.00 60,750,000.00
11 Sumur Resapan D-60 cm kedalaman 2.25 m - Paket 5,000,000.00 -
12 (Termasuk Buang Tanah) 9.00 Unit 2,500,000.00 22,500,000.00
13 Pasang Tutup Bak Kontrol / Manhole Besi Ceper 60 x 60 x 1 cm berat 43 kg - m' #REF! #REF!
-
JUMLAH : #REF!
D PEKERJAAN PENGEMBALIAN TROTOAR
1 Masang acian 6.53 m3 #REF! #REF!
2 Sirtu 4.71 m3 #REF! #REF!
JUMLAH : -
E PEKERJAAN LAIN-LAIN
1 Test / Uji Hammer Test Untuk Box Culvert 3.00 ls 1,000,000.00 3,000,000.00
2 Pembersihan Lokasi dan Pengembalian Fasilitas Umum 1.00
JUMLAH : 3,000,000.00
JUMLAH #REF!
PPN ( 10 % ) #REF!
JUMLAH TOTAL #REF!
DIBULATKAN #REF!
Terbilang :
#REF!
Dibuat
PT. TRI PATRA KONSULTAN
#REF!
1 1 M2 #REF! #REF! #REF! #REF!
2 1 M1 #REF! #REF! #REF! #REF!
3 1 M2 #REF! #REF! #REF! #REF!
4 1 buah #REF! #REF! #REF! #REF!
5 1 M2 #REF! #REF! #REF! #REF!
6 1 M2 #REF! #REF! #REF! #REF!
7 1 M1 #REF! #REF! #REF! #REF!
#REF!
1 1 M3 #REF! #REF! #REF! #REF!
2 1 M3 #REF! #REF! #REF! #REF!
3 1 M3 #REF! #REF! #REF! #REF!
4 1 M3 #REF! #REF! #REF! #REF!
5 1 M3 #REF! #REF! #REF! #REF!
6 1 M3 #REF! #REF! #REF! #REF!
7 1 M1 #REF! #REF! #REF! #REF!
8 1 M3 #REF! #REF! #REF! #REF!
9 1 M3 #REF! #REF! #REF! #REF!
10 1 M3 #REF! #REF! #REF! #REF!
11 1 M3 #REF! #REF! #REF! #REF!
12 1 M2 #REF! #REF! #REF! #REF!
13 1 M3 #REF! #REF! #REF! #REF!
14 1 M3 #REF! #REF! #REF! #REF!
15 1 M3 #REF! #REF! #REF! #REF!
16 1 M3 #REF! #REF! #REF! #REF!
17 1 M2 #REF! #REF! #REF! #REF!
#REF!
1 1 M3 #REF! #REF! #REF! #REF!
2 1 M3 #REF! #REF! #REF! #REF!
3 1 M3 #REF! #REF! #REF! #REF!
4 1 M3 #REF! #REF! #REF! #REF!
5 1 M3 #REF! #REF! #REF! #REF!
6 1 M2 #REF! #REF! #REF! #REF!
7 1 M2 #REF! #REF! #REF! #REF!
8 1 M2 #REF! #REF! #REF! #REF!
9 1 M2 #REF! #REF! #REF! #REF!
10 1 M2 #REF! #REF! #REF! #REF!
11 1 M2 #REF! #REF! #REF! #REF!
#REF!
1 1 M3 #REF! #REF! #REF! #REF!
2 1 M3 #REF! #REF! #REF! #REF!
3 1 M3 #REF! #REF! #REF! #REF!
4 1 M3 #REF! #REF! #REF! #REF!
5 1 M3 #REF! #REF! #REF! #REF!
6 1 M3 #REF! #REF! #REF! #REF!
7 1 M3 #REF! #REF! #REF! #REF!
8 1 kg #REF! #REF! #REF! #REF!
9 1 kg #REF! #REF! #REF! #REF!
10 1 M2 #REF! #REF! #REF! #REF!
11 1 M2 #REF! #REF! #REF! #REF!
12 1 M3 #REF! #REF! #REF! #REF!
Rekapitulasi - 630
HARGA HARGA JUMLAH
NO. SATUAN MACAM PEKERJAAN
UPAH BAHAN HARGA
13 1 M3 #REF! #REF! #REF! #REF!
14 1 M3 #REF! #REF! #REF! #REF!
15 1 M3 #REF! #REF! #REF! #REF!
16 1 M3 #REF! #REF! #REF! #REF!
17 1 M3 #REF! #REF! #REF! #REF!
18 1 M3 #REF! #REF! #REF! #REF!
19 1 M3 #REF! #REF! #REF! #REF!
20 1 M3 #REF! #REF! #REF! #REF!
21 1 M3 #REF! #REF! #REF! #REF!
22 1 M3 #REF! #REF! #REF! #REF!
23 1 M3 #REF! #REF! #REF! #REF!
24 1 M3 #REF! #REF! #REF! #REF!
25 1 M3 #REF! #REF! #REF! #REF!
26 1 M3 #REF! #REF! #REF! #REF!
27 1 M3 #REF! #REF! #REF! #REF!
28 1 M3 #REF! #REF! #REF! #REF!
29 1 M3 #REF! #REF! #REF! #REF!
#REF!
1 1 M2 #REF! #REF! #REF! #REF!
2 1 M2 #REF! #REF! #REF! #REF!
3 1 M2 #REF! #REF! #REF! #REF!
4 1 M2 #REF! #REF! #REF! #REF!
5 1 M1 #REF! #REF! #REF! #REF!
6 1 M2 #REF! #REF! #REF! #REF!
7 1 M2 #REF! #REF! #REF! #REF!
8 1 M2 #REF! #REF! #REF! #REF!
9 1 M2 #REF! #REF! #REF! #REF!
#REF!
1 1 M2 #REF! #REF! #REF! #REF!
2 1 M2 #REF! #REF! #REF! #REF!
#REF!
1 1 M2 #REF! #REF! #REF! #REF!
2 1 M2 #REF! #REF! #REF! #REF!
3 1 M2 #REF! #REF! #REF! #REF!
4 1 M2 #REF! #REF! #REF! #REF!
5 1 M2 #REF! #REF! #REF! #REF!
6 1 M1 #REF! #REF! #REF! #REF!
7 1 M1 #REF! #REF! #REF! #REF!
8 1 M1 #REF! #REF! #REF! #REF!
9 1 M1 #REF! #REF! #REF! #REF!
10 1 M2 #REF! #REF! #REF! #REF!
#REF!
1 1 M2 #REF! #REF! #REF! #REF!
2 1 M2 #REF! #REF! #REF! #REF!
3 1 M2 #REF! #REF! #REF! #REF!
4 1 M2 #REF! #REF! #REF! #REF!
5 1 M2 #REF! #REF! #REF! #REF!
6 1 M2 #REF! #REF! #REF! #REF!
7 1 M2 #REF! #REF! #REF! #REF!
8 1 M2 #REF! #REF! #REF! #REF!
9 1 M2 #REF! #REF! #REF! #REF!
10 1 M2 #REF! #REF! #REF! #REF!
11 1 bh #REF! #REF! #REF! #REF!
Rekapitulasi - 631
HARGA HARGA JUMLAH
NO. SATUAN MACAM PEKERJAAN
UPAH BAHAN HARGA
#REF!
1 1 M3 #REF! #REF! #REF! #REF!
2 1 M3 #REF! #REF! #REF! #REF!
3 1 M3 #REF! #REF! #REF! #REF!
4 1M3 #REF! #REF! #REF! #REF!
5 1M3 #REF! #REF! #REF! #REF!
6 1M3 #REF! #REF! #REF! #REF!
7 1M2 #REF! #REF! #REF! #REF!
8 1 M2 #REF! #REF! #REF! #REF!
9 1 M2 #REF! #REF! #REF! #REF!
10 1 M2 #REF! #REF! #REF! #REF!
11 1 M2 #REF! #REF! #REF! #REF!
12 1 M2 #REF! #REF! #REF! #REF!
13 1 M2 #REF! #REF! #REF! #REF!
14 1 M2 #REF! #REF! #REF! #REF!
15 1 M3 #REF! #REF! #REF! #REF!
16 1 M3 #REF! #REF! #REF! #REF!
17 1 M3 #REF! #REF! #REF! #REF!
18 1 M3 #REF! #REF! #REF! #REF!
19 1 M3 #REF! #REF! #REF! #REF!
20 1 M2 #REF! #REF! #REF! #REF!
21 1 M2 #REF! #REF! #REF! #REF!
22 1 M2 #REF! #REF! #REF! #REF!
23 1 M2 #REF! #REF! #REF! #REF!
24 1 M2 #REF! #REF! #REF! #REF!
25 1 M2 #REF! #REF! #REF! #REF!
26 1 M2 #REF! #REF! #REF! #REF!
27 1 M2 #REF! #REF! #REF! #REF!
28 1 M2 #REF! #REF! #REF! #REF!
29 1 M2 #REF! #REF! #REF! #REF!
30 1 M2 #REF! #REF! #REF! #REF!
31 1 M2 #REF! #REF! #REF! #REF!
32 1 M2 #REF! #REF! #REF! #REF!
33 1 M2 #REF! #REF! #REF! #REF!
34 1 M2 #REF! #REF! #REF! #REF!
35 1 M2 #REF! #REF! #REF! #REF!
36 1 M2 #REF! #REF! #REF! #REF!
37 1 M2 #REF! #REF! #REF! #REF!
38 1 M2 #REF! #REF! #REF! #REF!
39 1 M2 #REF! #REF! #REF! #REF!
40 1 M2 #REF! #REF! #REF! #REF!
41 1 M2 #REF! #REF! #REF! #REF!
42 1 M2 #REF! #REF! #REF! #REF!
43 1 M2 #REF! #REF! #REF! #REF!
44 1 M2 #REF! #REF! #REF! #REF!
45 1 M2 #REF! #REF! #REF! #REF!
46 1 M2 #REF! #REF! #REF! #REF!
47 1 M2 #REF! #REF! #REF! #REF!
48 1 M2 #REF! #REF! #REF! #REF!
49 1 M2 #REF! #REF! #REF! #REF!
50 1 M2 #REF! #REF! #REF! #REF!
51 1 M2 #REF! #REF! #REF! #REF!
52 1 M2 #REF! #REF! #REF! #REF!
53 1 M2 #REF! #REF! #REF! #REF!
54 1 M2 #REF! #REF! #REF! #REF!
55 1 M2 #REF! #REF! #REF! #REF!
56 1 M2 #REF! #REF! #REF! #REF!
57 1 M2 #REF! #REF! #REF! #REF!
58 1 M2 #REF! #REF! #REF! #REF!
59 1 M2 #REF! #REF! #REF! #REF!
Rekapitulasi - 632
HARGA HARGA JUMLAH
NO. SATUAN MACAM PEKERJAAN
UPAH BAHAN HARGA
60 1 M2 #REF! #REF! #REF! #REF!
61 1 M2 #REF! #REF! #REF! #REF!
62 1 M2 #REF! #REF! #REF! #REF!
63 1 M1 #REF! #REF! #REF! #REF!
64 1 M1 #REF! #REF! #REF! #REF!
65 1 M1 #REF! #REF! #REF! #REF!
66 1 M1 #REF! #REF! #REF! #REF!
67 1 M1 #REF! #REF! #REF! #REF!
68 1 M1 #REF! #REF! #REF! #REF!
69 1 M1 #REF! #REF! #REF! #REF!
70 1 M1 #REF! #REF! #REF! #REF!
71 1 M1 #REF! #REF! #REF! #REF!
72 1 M1 #REF! #REF! #REF! #REF!
73 1 M1 #REF! #REF! #REF! #REF!
74 1 M1 #REF! #REF! #REF! #REF!
75 1 M1 #REF! #REF! #REF! #REF!
76 1 M2 #REF! #REF! #REF! #REF!
77 1 M2 #REF! #REF! #REF! #REF!
78 1 M2 #REF! #REF! #REF! #REF!
79 1 M1 #REF! #REF! #REF! #REF!
80 1 M1 #REF! #REF! #REF! #REF!
81 1 M1 #REF! #REF! #REF! #REF!
82 1 M1 #REF! #REF! #REF! #REF!
83 1 M1 #REF! #REF! #REF! #REF!
84 1 M1 #REF! #REF! #REF! #REF!
85 1 M1 #REF! #REF! #REF! #REF!
86 1 M1 #REF! #REF! #REF! #REF!
87 1 M1 #REF! #REF! #REF! #REF!
88 1 M1 #REF! #REF! #REF! #REF!
89 1 M1 #REF! #REF! #REF! #REF!
90 1 M2 #REF! #REF! #REF! #REF!
91 1 M2 #REF! #REF! #REF! #REF!
92 1 M2 #REF! #REF! #REF! #REF!
#REF!
1 1 M2 #REF! #REF! #REF! #REF!
2 1 M2 #REF! #REF! #REF! #REF!
3 1 M2 #REF! #REF! #REF! #REF!
4 1 M2 #REF! #REF! #REF! #REF!
5 1 M2 #REF! #REF! #REF! #REF!
6 1 M2 #REF! #REF! #REF! #REF!
7 1 M2 #REF! #REF! #REF! #REF!
8 1 M1 #REF! #REF! #REF! #REF!
9 1 M1 #REF! #REF! #REF! #REF!
10 1 M1 #REF! #REF! #REF! #REF!
11 1 M2 #REF! #REF! #REF! #REF!
12 1 M2 #REF! #REF! #REF! #REF!
13 1 M2 #REF! #REF! #REF! #REF!
14 1 M2 #REF! #REF! #REF! #REF!
15 1 M2 #REF! #REF! #REF! #REF!
16 1 M2 #REF! #REF! #REF! #REF!
17 1 M2 #REF! #REF! #REF! #REF!
18 1 M2 #REF! #REF! #REF! #REF!
19 1 M2 #REF! #REF! #REF! #REF!
20 1 M2 #REF! #REF! #REF! #REF!
21 1 M2 #REF! #REF! #REF! #REF!
22 1 M1 #REF! #REF! #REF! #REF!
Rekapitulasi - 633
HARGA HARGA JUMLAH
NO. SATUAN MACAM PEKERJAAN
UPAH BAHAN HARGA
23 1 M1 #REF! #REF! #REF! #REF!
24 1 M1 #REF! #REF! #REF! #REF!
25 1 M1 #REF! #REF! #REF! #REF!
26 1 M1 #REF! #REF! #REF! #REF!
27 1 M2 #REF! #REF! #REF! #REF!
28 1 M2 #REF! #REF! #REF! #REF!
#REF!
1 1 M2 #REF! #REF! #REF! #REF!
2 1 M2 #REF! #REF! #REF! #REF!
3 1 M2 #REF! #REF! #REF! #REF!
#REF!
1 1 M3 #REF! #REF! #REF! #REF!
2 1 M3 #REF! #REF! #REF! #REF!
3 1 M3 #REF! #REF! #REF! #REF!
4 1 M2 #REF! #REF! #REF! #REF!
5 1 M2 #REF! #REF! #REF! #REF!
6 1 M2 #REF! #REF! #REF! #REF!
7 1 M2 #REF! #REF! #REF! #REF!
8 1 M2 #REF! #REF! #REF! #REF!
9 1 M2 #REF! #REF! #REF! #REF!
10 1 M3 #REF! #REF! #REF! #REF!
#REF!
1 1 M1 #REF! #REF! #REF! #REF!
#REF!
2 1 bh #REF! #REF! #REF! #REF!
3 1 bh #REF! #REF! #REF! #REF!
4 1 bh #REF! #REF! #REF! #REF!
5 1 bh #REF! #REF! #REF! #REF!
6 1 bh #REF! #REF! #REF! #REF!
7 1 bh #REF! #REF! #REF! #REF!
8 1 bh #REF! #REF! #REF! #REF!
9 1 M1 #REF! #REF! #REF! #REF!
10 1 M1 #REF! #REF! #REF! #REF!
Rekapitulasi - 634
HARGA HARGA JUMLAH
NO. SATUAN MACAM PEKERJAAN
UPAH BAHAN HARGA
11 1 bh #REF! #REF! #REF! #REF!
12 1 bh #REF! #REF! #REF! #REF!
13 1 bh #REF! #REF! #REF! #REF!
14 1 M1 #REF! #REF! #REF! #REF!
15 1 M1 #REF! #REF! #REF! #REF!
16 1 M1 #REF! #REF! #REF! #REF!
17 1 M1 #REF! #REF! #REF! #REF!
18 1 M1 #REF! #REF! #REF! #REF!
19 1 M1 #REF! #REF! #REF! #REF!
20 1 M1 #REF! #REF! #REF! #REF!
21 1 M1 #REF! #REF! #REF! #REF!
22 1 M1 #REF! #REF! #REF! #REF!
23 1 M1 #REF! #REF! #REF! #REF!
24 1 M1 #REF! #REF! #REF! #REF!
25 1 M1 #REF! #REF! #REF! #REF!
26 1 bh #REF! #REF! #REF! #REF!
27 1 bh #REF! #REF! #REF! #REF!
28 1 bh #REF! #REF! #REF! #REF!
#REF!
1 1 kg #REF! #REF! #REF! #REF!
2 1 M2 #REF! #REF! #REF! #REF!
3 1 M2 #REF! #REF! #REF! #REF!
4 1 M2 #REF! #REF! #REF! #REF!
5 1 M2 #REF! #REF! #REF! #REF!
6 1 M2 #REF! #REF! #REF! #REF!
7 1 M2 #REF! #REF! #REF! #REF!
8 1 M2 #REF! #REF! #REF! #REF!
9 1 M2 #REF! #REF! #REF! #REF!
10 1 M2 #REF! #REF! #REF! #REF!
11 1 M2 #REF! #REF! #REF! #REF!
#REF!
1 1 bh #REF! #REF! #REF! #REF!
2 1 bh #REF! #REF! #REF! #REF!
3 1 bh #REF! #REF! #REF! #REF!
4 1 bh #REF! #REF! #REF! #REF!
5 1 bh #REF! #REF! #REF! #REF!
6 1 bh #REF! #REF! #REF! #REF!
7 1 bh #REF! #REF! #REF! #REF!
8 1 bh #REF! #REF! #REF! #REF!
9 1 bh #REF! #REF! #REF! #REF!
10 1 bh #REF! #REF! #REF! #REF!
11 1 bh #REF! #REF! #REF! #REF!
12 1 bh #REF! #REF! #REF! #REF!
13 1 bh #REF! #REF! #REF! #REF!
14 1 bh #REF! #REF! #REF! #REF!
15 1 bh #REF! #REF! #REF! #REF!
16 1 M2 #REF! #REF! #REF! #REF!
17 1 M2 #REF! #REF! #REF! #REF!
18 1 M2 #REF! #REF! #REF! #REF!
19 1 M2 #REF! #REF! #REF! #REF!
Rekapitulasi - 635
DAFTAR SATUAN UPAH
TENAGA
1 Tukang kayu hari 55,000.00
2 Kepala tukang kayu hari 73,150.00
3 Tukang batu hari 63,800.00
4 Kepala tukang batu hari 71,500.00
5 Tukang besi hari 67,650.00
6 Kepala tukang besi hari 71,500.00
7 Tukang las hari 63,800.00
8 Kepala tukang las hari 73,150.00
9 Tukang cat hari 62,700.00
10 Kepala tukang cat hari 69,300.00
11 Tukang plitur hari 62,700.00
12 Kepala tukang plitur hari 69,300.00
13 Tukang bor hari 97,350.00
14 Kepala tukang bor hari 71,500.00
15 Tukang listrik hari 69,300.00
16 Tukanng pipa ledeng hari 72,050.00
17 Tukang kapur hari 63,800.00
18 Pekerja hari 52,520.00
19 Mandor hari 77,500.00
20 Pengawas / Ahli Teknik hari 83,500.00
21 Ahli ukur hari 200,000.00
22 Asisten ahli ukur hari 250,000.00
23 Sopir hari 72,050.00
24 Masinis hari 75,900.00
25 Kernet / pembantu sopir hari 66,000.00
26 Mekanik terlatih hari 81,950.00
27 Operator tak terlatih hari 66,000.00
28 Operator terlatih hari 75,900.00
29 Operator semi terlatih hari 69,300.00
30 Butuh terlatih hari 66,000.00
31 Buruh semi terlatih hari 60,000.00
32 Buruh tak terlatih hari 55,000.00
33 Tukang gali hari 52,520.00
34 Juru godog aspal hari 72,050.00
35 Penjaga hari 52,250.00
36 Penyemprot hari 69,300.00
37 Tukang Sungging hari 62,700.00
38 Kepala Tukang Sungging hari 69,300.00
39 Tukang Ukir hari 55,000.00
40 Kepala Tukang Ukir hari 73,150.00
41 Tukang Prodo hari 62,700.00
42 Kepala Tukang Prodo hari 69,300.00
43 Tukang Gambar hari 83,500.00
44 Tukang Grouting hari 75,000.00
45 Kepala tukang Grouting hari 70,000.00
46 Operator mesin sondir hari 100,000.00
47 Analis test sondir hari 150,000.00
Bahan - 636
ANALISA KPUT
No. Macam Pekerjaan Upah Bahan Jumlah
(1) (2) (3) (4) (5)
KPUT 100.0000 m2 Perkerasan lapis pondasi bawah (sub base) tebal 20 cm padat
10.8 5.0000 m3 Pasair pasang @ Rp. #REF! #REF!
23.0000 m3 Batu belah 15/20 @ Rp. #REF! #REF!
3.0000 m3 Batu pecah 5/7 cm @ Rp. #REF! #REF!
6.5000 m3 Pasir urug @ Rp. #REF! #REF!
26.0000 m3 Isi batu berkerasan @ Rp. #REF! #REF!
6.5000 Tng Menyawur pasir @ Rp. #REF! #REF!
JUMLAH ( BELUM TERMASUK PPN ) #REF! #REF! #REF!
DIBULATKAN #REF!
Tiap m2
1/100 x #REF! + #REF! #REF! #REF!
Biaya menggilas
1/200 x #REF! + #REF! #REF! #REF!
Sewa motor walls
1/200 x #NAME? #NAME?
JUMLAH ( BELUM TERMASUK PPN ) #NAME? #REF! #REF!
JASA 10 % #REF!
JUMLAH #REF!
DIBULATKAN #REF!
Tiap m2
1/100 x #REF! + #REF! #REF! #REF!
Biaya menggilas
1/200 x #REF! + #REF! #REF! #REF!
Sewa motor walls
1/200 x #NAME? #NAME?
JUMLAH ( BELUM TERMASUK PPN ) #NAME? #REF! #REF!
JASA 10 % #REF!
JUMLAH #REF!
DIBULATKAN #REF!
Tiap m2
1/100 x #REF! + #REF! #REF! #REF!
Biaya menggilas
1/150 x #REF! + #REF! #REF! #REF!
Sewa motor walls
1/150 x #NAME? #NAME?
JUMLAH ( BELUM TERMASUK PPN ) #NAME? #REF! #REF!
JASA 10 % #REF!
JUMLAH #REF!
DIBULATKAN #REF!
Tiap m2
1/100 x #REF! + #REF! #REF! #REF!
Biaya menggilas
4/12,5/200 x #REF! + #REF! #REF! #REF!
Sewa motor walls
1/200 x #NAME? #NAME?
JUMLAH ( BELUM TERMASUK PPN ) #NAME? #REF! #REF!
JASA 10 % #REF!
JUMLAH #REF!
DIBULATKAN #REF!
Tiap m2
Aspal sand sheet 2 cm jereng (1 cm padat)
2/100 x #REF! + #REF! #REF! #REF!
Biaya menggilas
1/500 x #REF! + #REF! #REF! #REF!
Sewa motor walls
1/500 x #NAME? #NAME?
Aspal untuk lem 0,5 kg
0.5000 x #REF! #REF!
JUMLAH ( BELUM TERMASUK PPN ) #NAME? #REF! #REF!
JASA 10 % #REF!
JUMLAH #REF!
DIBULATKAN #REF!
Tiap m2
Aspal sand sheet 3 cm jereng (2 cm padat)
3/100 x #REF! + #REF! #REF! #REF!
Biaya menggilas
1/500 x #REF! + #REF! #REF! #REF!
Sewa motor walls
1/500 x #NAME? #NAME?
Aspal untuk lem 0,5 kg
0.5000 x #REF! #REF!
JUMLAH ( BELUM TERMASUK PPN ) #NAME? #REF! #REF!
JASA 10 % #REF!
JUMLAH #REF!
DIBULATKAN #REF!
KPUT 100.0000 m2 Pengaspalan sand sheet (latasir) tanpa aspal, tebal 1 cm jereng
M.8 - kg Aspal #REF! #REF!
1.0000 m3 Pasair pasang @ Rp. #REF! #REF!
0.9000 m3 Kayu bakar @ Rp. #REF! #REF!
0.2500 org Juru godog aspal @ Rp. #REF! #REF!
8.1000 org Pekerja @ Rp. #REF! #REF!
0.4000 org Mandor @ Rp. #REF! #REF!
JUMLAH ( BELUM TERMASUK PPN ) #REF! #REF! #REF!
DIBULATKAN #REF!
Tiap m2
Aspal sand sheet 2 cm jereng (1 cm padat) tanpa aspal
2/100 x #REF! + #REF! #REF! #REF!
Biaya menggilas
1/500 x #REF! + #REF! #REF! #REF!
Sewa motor walls
1/500 x #NAME? #NAME?
Aspal untuk lem 0,5 kg
- x #REF! #REF!
JUMLAH ( BELUM TERMASUK PPN ) #NAME? #REF! #REF!
JASA 10 % #REF!
JUMLAH #REF!
DIBULATKAN #REF!
Tiap m2
Aspal sand sheet 3 cm jereng (2 cm padat) tanpa aspal
3/100 x #REF! + #REF! #REF! #REF!
Biaya menggilas
1/500 x #REF! + #REF! #REF! #REF!
Sewa motor walls
1/500 x #NAME? #NAME?
Aspal untuk lem 0,5 kg
- x #REF! #REF!
JUMLAH ( BELUM TERMASUK PPN ) #NAME? #REF! #REF!
JASA 10 % #REF!
JUMLAH #REF!
DIBULATKAN #REF!
25. 1.0000 set Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son + pengetesan dan penyalaan
0.5000 org Pekerja @ Rp. #REF! #REF!
0.5000 org Tukang Listrik @ Rp. #REF! #REF!
1.2500 org Pengawas @ Rp. #REF! #REF!
0.5000 org Mandor @ Rp. #REF! #REF!
JUMLAH (A) #REF! - #REF!
27. 1.0000 set Pasang Stang Ornamen 6 meter + Lampu SRP 822/250 Watt Son
0.8750 org Pekerja @ Rp. #REF! #REF!
0.8750 org Tukang Listrik @ Rp. #REF! #REF!
1.8033 org Pengawas @ Rp. #REF! #REF!
0.7413 org Mandor @ Rp. #REF! #REF!
JUMLAH (C) #REF! - #REF!
28. 1.0000 set Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son
0.5000 org Pekerja @ Rp. #REF! #REF!
0.5000 org Tukang Listrik @ Rp. #REF! #REF!
1.2500 org Pengawas @ Rp. #REF! #REF!
0.5000 org Mandor @ Rp. #REF! #REF!
JUMLAH (D) #REF! - #REF!
29. 1.0000 set Pasang Tiang Octogonal Cabang 1, h= 7 meter+ lampu SRP 822/250 Watt Son
0.4200 m3 Pondasi Tiang Beton bertulang 1:2:3 @ Rp. #REF! #REF!
2.8500 org Pekerja @ Rp. #REF! #REF!
2.8500 org Tukang Listrik @ Rp. #REF! #REF!
2.0075 org Pengawas @ Rp. #REF! #REF!
1.0000 org Mandor @ Rp. #REF! #REF!
JUMLAH (E) #REF! #REF! #REF!
30. 1.0000 set Pasang Tiang Octogonal Cabang 1, h= 9 meter + lampu SRP 822/250 Watt Son
0.4200 m3 Pondasi Tiang Beton bertulang 1:2:3 @ Rp. #REF! #REF!
3.1000 org Pekerja @ Rp. #REF! #REF!
3.1000 org Tukang Listrik @ Rp. #REF! #REF!
2.5000 org Pengawas @ Rp. #REF! #REF!
1.2100 org Mandor @ Rp. #REF! #REF!
JUMLAH (F) #REF! #REF! #REF!
31. 1.0000 set Pasang Tiang Octogonal Cabang 2, h= 9 meter+ lampu SRP 822/250 Watt Son
0.4200 m3 Pondasi Tiang Beton bertulang 1:2:3 @ Rp. #REF! #REF!
3.3000 org Pekerja @ Rp. #REF! #REF!
3.3000 org Tukang Listrik @ Rp. #REF! #REF!
2.5782 org Pengawas @ Rp. #REF! #REF!
1.2433 org Mandor @ Rp. #REF! #REF!
JUMLAH (G) #REF! #REF! #REF!
32. 1.0000 set Pasang Tiang Octogonal Cabang 3, h= 9 m+ lampu SRP 822/250 Watt Son
0.4200 m3 Pondasi Tiang Beton bertulang 1:2:3 @ Rp. #REF! #REF!
3.8100 org Pekerja @ Rp. #REF! #REF!
3.8100 org Tukang Listrik @ Rp. #REF! #REF!
2.6626 org Pengawas @ Rp. #REF! #REF!
1.2650 org Mandor @ Rp. #REF! #REF!
JUMLAH (H) #REF! #REF! #REF!
33. 1.0000 set Pasang Tiang Octogonal Cabang 3, h= 11 m+ lampu SRP 822/250 Watt Son
0.4200 m3 Pondasi Tiang Beton bertulang 1:2:3 @ Rp. #REF! #REF!
4.2500 org Pekerja @ Rp. #REF! #REF!
4.2500 org Tukang Listrik @ Rp. #REF! #REF!
2.9287 org Pengawas @ Rp. #REF! #REF!
1.2939 org Mandor @ Rp. #REF! #REF!
JUMLAH (I) #REF! #REF! #REF!
34. 1.0000 set Bongkar armatur pada stang ornamen existing + pasang lampu SRP 822/150 Watt Son + return
0.9000 org Pekerja @ Rp. #REF! #REF!
0.9000 org Tukang Listrik @ Rp. #REF! #REF!
2.1044 org Pengawas @ Rp. #REF! #REF!
0.8418 org Mandor @ Rp. #REF! #REF!
0.0500 unit Retur material existing @ Rp. #REF! #REF!
JUMLAH (J) #REF! - #REF!
35. 1.0000 set Bongkar armatur pada stang ornamen existing + pasang Lampu SRP 822/250 Watt Son + retur
0.8750 org Pekerja @ Rp. #REF! #REF!
0.8750 org Tukang Listrik @ Rp. #REF! #REF!
1.6995 org Pengawas @ Rp. #REF! #REF!
0.6798 org Mandor @ Rp. #REF! #REF!
0.0500 unit Retur material existing @ Rp. #REF! #REF!
JUMLAH (K) #REF! - #REF!
36. 1.0000 set Bongkar armatur pada tang existing + pasang Lampu SRP 822/250 Watt Son + retur
0.9000 org Pekerja @ Rp. #REF! #REF!
0.9000 org Tukang Listrik @ Rp. #REF! #REF!
2.1044 org Pengawas @ Rp. #REF! #REF!
0.8418 org Mandor @ Rp. #REF! #REF!
0.0500 unit Retur material existing @ Rp. #REF! #REF!
JUMLAH (L) #REF! - #REF!
37. 1.0000 set Bongkar komponen lama existing + pasang komponen Lampu SRP 822/250 Watt Son + retur
0.8500 org Pekerja @ Rp. #REF! #REF!
0.8500 org Tukang Listrik @ Rp. #REF! #REF!
1.9554 org Pengawas @ Rp. #REF! #REF!
0.7822 org Mandor @ Rp. #REF! #REF!
0.0500 unit Retur material existing @ Rp. #REF! #REF!
JUMLAH (M) #REF! - #REF!
I URAIAN PERALATAN
1 Jenis Peralatan ASPHALT MIXING PLANT E01
2 Tenaga Pw 150.00 HP
3 Kapasitas Cp 50.00 Ton/jam
4 Alat Baru : a. Umur Ekonomis A 10.00 Tahun
b. Jam Kerja dalam 1 Tahun W 1,500.00 Jam
c. Harga Alat B 7,500,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 10.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 1,500.00 Jam Alat Baru
c. Harga Alat B' 7,500,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan ASPHALT FINISHER E02
2 Tenaga Pw 47.00 HP
3 Kapasitas Cp 6.00 Ton
4 Alat Baru : a. Umur Ekonomis A 6.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000 Jam
c. Harga Alat B 715,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 6.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 715,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan ASPHALT SPRAYER E03
2 Tenaga Pw 15.00 HP
3 Kapasitas Cp 800.00 Liter
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000 Jam
c. Harga Alat B 145,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 145,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan BULLDOZER 100 -150 HP E04
2 Tenaga Pw 140.00 HP
3 Kapasitas Cp Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000 Jam
c. Harga Alat B 700,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 700,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan COMPRESSOR 4000 - 6500 L/M E05
2 Tenaga Pw 80.00 HP
3 Kapasitas Cp Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000 Jam
c. Harga Alat B 175,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 175,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan WHEEL LOADER 1,0 - 1,6 M3 E15
2 Tenaga Pw 105.00 HP
3 Kapasitas Cp 1.50 Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 840,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 840,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan TANDEM ROLLER 6 - 8 T E17
2 Tenaga Pw 50.00 HP
3 Kapasitas Cp 8.00 Ton
4 Alat Baru a Umur Ekonomis A 5.00 Tahun
b Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c Harga Alat B 460,000,000.00 Rupiah
5 Alat yang dipakai a Umur Ekonomis A' 5.00 Tahun Alat Baru
b Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c Harga Alat B' 460,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan PNEUMATIC TYRE ROLLER 8 - 10 T E18
2 Tenaga Pw 60.00 HP
3 Kapasitas Cp 10.00 Ton
4 Alat Baru a Umur Ekonomis A 5.00 Tahun
b Jam Kerja dalam 1 Tahun W 1,800.00 Jam
c Harga Alat B 510,000,000.00 Rupiah
5 Alat yang dipakai a Umur Ekonomis A' 5.00 Tahun Alat Baru
b Jam Kerja dalam 1 Tahun W' 1,800.00 Jam Alat Baru
c Harga Alat B' 510,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan DUMP TRUCK E09
2 Tenaga Pw 125.00 HP
3 Kapasitas Cp 8.00 Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 145,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 145,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan GENERATOR SET E12
2 Tenaga Pw 175.00 HP
3 Kapasitas Cp 125.00 KVA
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 440,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 440,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan MOTOR GRADER > 100 HP E12
2 Tenaga Pw 125.00 HP
3 Kapasitas Cp - -
4 Alat Baru a Umur Ekonomis A 5.00 Tahun
b Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c Harga Alat B 880,000,000.00 Rupiah
5 Alat yang dipakai a Umur Ekonomis A' 5.00 Tahun Alat Baru
b Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c Harga Alat B' 880,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan VIBRATORY ROLLER 5 - 8 T E19
2 Tenaga Pw 75.00 HP
3 Kapasitas Cp 7.00 Ton
4 Alat Baru Umur Ekonomis A 4.00 Tahun
Jam Kerja dalam 1 Tahun W 2,000.00 Jam
Harga Alat B 500,000,000.00 Rupiah
5 Alat yang dipakai a Umur Ekonomis A' 4.00 Tahun Alat Baru
b Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c Harga Alat B' 500,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan WATER TANK TRUCK 3000 - 4000 L E23
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 4,000.00 Liter
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 50,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 50,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan JACK HAMMER E26
2 Tenaga Pw 3.00 HP
3 Kapasitas Cp - Liter
4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun
b. Jam Kerja dalam 1 Tahun W 1,000.00 Jam
c. Harga Alat B 3,500,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 1,000.00 Jam Alat Baru
c. Harga Alat B' 3,500,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan TAMPER E25
2 Tenaga Pw 5.00 HP
3 Kapasitas Cp 0.170 Ton
4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun
b. Jam Kerja dalam 1 Tahun W 1,000.00 Jam
c. Harga Alat B 3,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 1,000.00 Jam Alat Baru
c. Harga Alat B' 3,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan STONE CRUSHER E21
2 Tenaga Pw 220.00 HP
3 Kapasitas Cp 50.00 Ton/Jam
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 491,500,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 491,500,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan THREE WHEEL ROLLER 6 - 8 T E16
2 Tenaga Pw 55.00 HP
3 Kapasitas Cp 8.00 Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 125,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 125,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan CONCRETE VIBRATOR E20
2 Tenaga Pw 10.00 HP
3 Kapasitas Cp - -
4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun
b. Jam Kerja dalam 1 Tahun W 1,000.00 Jam
c. Harga Alat B 12,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 1,000.00 Jam Alat Baru
c. Harga Alat B' 12,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan CONCRETE MIXER 0.3 - 0.6 M3 E06
2 Tenaga Pw 15.00 HP
3 Kapasitas Cp 500.00 Liter
4 Alat Baru : a. Umur Ekonomis A 4.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 45,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 4.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 45,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan CRANE 10 - 15 TON E07
2 Tenaga Pw 150.00 HP
3 Kapasitas Cp 15.00 Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 300,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 300,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan DUMP TRUCK 3 - 4 M3 E08
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 6.00 Ton
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 100,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 100,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan EXCAVATOR 80 - 140 HP E10
2 Tenaga Pw 80.00 HP
3 Kapasitas Cp 0.50 M3
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 250,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 250,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan FLAT BED TRUCK 3 - 4 M3 E11
2 Tenaga Pw 100.00 HP
3 Kapasitas Cp 4.00 M3
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 250,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 250,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan WATER PUMP 70 - 100 mm E22
2 Tenaga Pw 6.00 HP
3 Kapasitas Cp - -
4 Alat Baru : a. Umur Ekonomis A 2.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 5,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 2.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 5,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan FULVI MIXER E27
2 Tenaga Pw 75.00 HP
3 Kapasitas Cp - -
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 100,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 100,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
I URAIAN PERALATAN
1 Jenis Peralatan TRACK LOADER 75 - 100 HP E14
2 Tenaga Pw 90.00 HP
3 Kapasitas Cp 1.60 M3
4 Alat Baru : a. Umur Ekonomis A 5.00 Tahun
b. Jam Kerja dalam 1 Tahun W 2,000.00 Jam
c. Harga Alat B 300,000,000.00 Rupiah
5 Alat Yang Dipakai : a. Umur Ekonomis A' 5.00 Tahun Alat Baru
b. Jam Kerja dalam 1 Tahun W' 2,000.00 Jam Alat Baru
c. Harga Alat B' 300,000,000.00 Rupiah Alat Baru
V LAIN LAIN
1 Tingkat suku bunga (i) 20.00 % / Tahun
2 Upah Operator / Sopir U1 #REF! Rp / Jam
3 Upah Pembantu Operator / Pembantu Sopir U2 #REF! Rp / Jam
4 Bahan bakar bensin Mb #REF! Liter
5 Bahan bakar solar Ms #REF! Liter
6 Minyak Pelumas Mp #REF! Liter
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.0113 #REF! #REF!
2 Mandor ( L 03 ) Jam 0.0016 #REF! #REF!
B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.0121 #REF! #REF!
2 Agregat Halus ( M 04 ) M3 0.0232 #REF! #REF!
3 Filler ( M 05 ) Kg 4.8004 #REF! #REF!
4 Aspal ( M 10 ) Kg 5.2962 #REF! #REF!
C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0011 #NAME? #NAME?
2 AMP ( E 01 ) Jam 0.0016 #NAME? #NAME?
3 Genset ( E 12 ) Jam 0.0016 #NAME? #NAME?
4 Dump Truck ( E 09 ) Jam 0.0143 #NAME? #NAME?
5 Aspal Finisher ( E 02 ) Jam 0.0020 #NAME? #NAME?
6 Tandem Roller ( E 17 ) Jam 0.0017 #NAME? #NAME?
7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0013 #NAME? #NAME?
8 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH #NAME?
JASA 10 % #NAME?
JUMLAH ( BELUM TERMASUK PPN ) #NAME?
DIBULATKAN #NAME?
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )
dan biaya biaya lainnya
Analisa - E 675
URAIAN ANALISA HARGA SATUAN LATASTON ( HRS )
SATUAN : M2 Analisa EI - 633
I ASUMSI
1 Menggunakan alat berat ( cara mekanik )
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km
5 Tebal lapisan padat t 0.03 m
6 Jam kerja efektif 1 hari Tk 7.00 Jam
7 Faktor kehilangan material
- Agregat Fh 1 1.10 -
- Aspal Fh 2 1.05 -
II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat
langsung ke dalam Dump Truck dan diangkut ke lokasi pekerjaan.
3 Campuran panas HRS dihampar dengan Finisher dan dipadatakan dengan
Tandem dan Peneumatic Tire Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu
2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50 m3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu siklus Ts 1
- Muat T1 1.50 menit
- Lain lain T2 0.50 menit
Ts 1 2.00 menit
Analisa - E 676
No URAIAN KODE KOEF. SATUAN KET.
d Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 8.00 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata rata bermuatan v1 40.00 km / jam
Kecepatan rata rata kosong v2 50.00 km / jam
Kapasitas AMP batch Q2 b 0.50 ton
Waktu menyiapkan 1 batch HRS Tb 1.00 menit
Waktu Siklus Ts2
- Mengisi bak = ( V : Q2b ) x Tb T1 16.00 menit
- Angkut = ( L : v1 ) x 60 menit T2 30.00 menit
- Tunggu + Dumping + Putar T3 15.00 menit
- Kembali = ( L : v2 ) x 60 menit T4 24.00 menit
Ts2 85.00 menit
e Finisher ( E 02 )
Kapasitas produksi V 40.00 km / jam
Faktor efisiensi alat Fa 0.83 -
f Tandem Roller ( E 17 )
Kecepatan rata rata alat v 3.50 km/jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 6.00 lintasan
Faktor efisiensi alat Fa 0.83 -
Analisa - E 677
No URAIAN KODE KOEF. SATUAN KET.
h Alat Bantu
Diperlukan :
- Kereta dorong = 2 bh Lump sum
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan
3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 617.56 m2 / jam
Produksi HRS / hari = Tk x Q2 Qt 4,322.92 m2
Kebutuhan tenaga
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Rp #NAME? / M2
Analisa - E 678
FORMULIR STANDAR UNTUK PEREKAMAN ANALISA
MASING MASING HARGA SATUAN
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.0217 #REF! #REF!
2 Mandor ( L 03 ) Jam 0.0022 #REF! #REF!
B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.0336 #REF! #REF!
2 Agregat Halus ( M 04 ) M3 0.0149 #REF! #REF!
3 Filler ( M 05 ) Kg 4.8015 #REF! #REF!
4 Aspal ( M 10 ) Kg 6.6150 #REF! #REF!
C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0015 #NAME? #NAME?
2 AMP ( E 01 ) Jam 0.0022 #NAME? #NAME?
3 Genset ( E 12 ) Jam 0.0022 #NAME? #NAME?
4 Dump Truck ( E 09 ) Jam 0.0348 #NAME? #NAME?
5 Aspal Finisher ( E 02 ) Jam 0.0027 #NAME? #NAME?
6 Tandem Roller ( E 17 ) Jam 0.0016 #NAME? #NAME?
7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0023 #NAME? #NAME?
8 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH #NAME?
JASA 10 % #NAME?
JUMLAH ( BELUM TERMASUK PPN ) #NAME?
DIBULATKAN #NAME?
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )
dan biaya biaya lainnya
Analisa - E 679
URAIAN ANALISA HARGA SATUAN LASTON ( AC )
SATUAN : M2 Analisa EI - 634
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km
5 Tebal lapisan ( AC ) padat t 0.04 m
6 Jam kerja efektif 1 hari Tk 7.00 Jam
7 Faktor kehilangan material
- Agregat Fh 1 1.10 -
- Aspal Fh 2 1.05 -
II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat
langsung ke dalam Dump Truck dan diangkut ke lapangan
3 Campuran panas AC dihampar dengan Finisher dan dipadatakan dengan
Tandem dan Tire Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu
2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50 m3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu siklus Ts 1
- Muat T1 1.50 menit
- Lain lain T2 0.50 menit
Ts 1 2.00 menit
Analisa - E 680
No URAIAN KODE KOEF. SATUAN KET.
d Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 4.00 m3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata rata bermuatan v1 40.00 km / jam
Kecepatan rata rata kosong v2 50.00 km / jam
Kapasitas AMP batch Q2 b 0.50 ton
Waktu menyiapkan 1 batch AC Tb 1.00 menit
Waktu Siklus Ts2
- Mengisi bak = ( V : Q2b ) x Tb T1 8.00 menit
- Angkut = ( L : v1 ) x 60 menit T2 29.99 menit
- Tunggu + Dumping + Putar T3 15.00 menit
- Kembali = ( L : v2 ) x 60 menit T4 23.99 menit
Ts2 76.98 menit
e Finisher ( E 02 )
Kapasitas produksi V 40.00 ton / jam
Faktor efisiensi alat Fa 0.83 -
f Tandem Roller ( E 17 )
Kecepatan rata rata alat v 2.50 km / jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 4.00 lintasan
Faktor efisiensi alat Fa 0.83 -
Analisa - E 681
No URAIAN KODE KOEF. SATUAN KET.
h Alat Bantu
Diperlukan :
- Rambu = 2 bh
- Kereta dorong = 2 bh Lump sum
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan
3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 461.11 m2 / jam
Produksi AC / hari = Tk x Q2 Qt 3,227.78 m2
Kebutuhan tenaga
- Pekerja P 10.00 orang
- Mandor M 1.00 orang
Rp #NAME? / M2
Analisa - E 682
FORMULIR STANDAR UNTUK PEREKAMAN ANALISA
MASING MASING HARGA SATUAN
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.3880 #REF! #REF!
2 Mandor ( L 03 ) Jam 0.0554 #REF! #REF!
B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.7028 #REF! #REF!
2 Agregat Halus ( M 04 ) M3 0.5341 #REF! #REF!
3 Filler ( M 05 ) Kg 139.2 #REF! #REF!
4 Aspal ( M 10 ) Kg 157.0 #REF! #REF!
C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0380 #NAME? #NAME?
2 AMP ( E 01 ) Jam 0.0554 #NAME? #NAME?
3 Genset ( E 12 ) Jam 0.0554 #NAME? #NAME?
4 Dump Truck ( E 09 ) Jam 0.4906 #NAME? #NAME?
5 Aspal Finisher ( E 02 ) Jam 0.0767 #NAME? #NAME?
6 Tandem Roller ( E 17 ) Jam 0.0430 #NAME? #NAME?
7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0321 #NAME? #NAME?
8 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH #NAME?
JASA 10 % #NAME?
JUMLAH ( BELUM TERMASUK PPN ) #NAME?
DIBULATKAN #NAME?
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )
dan biaya biaya lainnya
Analisa - E 683
URAIAN ANALISA HARGA SATUAN ASPHALT TREATED BASE ( ATB )
I ASUMSI
1 Menggunakan alat berat ( Cara mekanik )
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km
5 Tebal lapisan ( ATB ) padat t 0.04 m
6 Jam kerja efektif 1 hari Tk 7.00 Jam
7 Faktor kehilangan material
- Agregat Fh 1 1.10 -
- Aspal Fh 2 1.05 -
II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat
langsung ke dalam Dump truck dan diangkut ke lokasi pekerjaan
3 Campuran panas ATB dihampar dengan Finisher dan dipadatakan dengan
Tandem dan Pneumatic Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu
2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50 m3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu siklus Ts 1
- Muat T1 1.50 menit
- Lain lain T2 0.50 menit
Ts 1 2.00 menit
Analisa - E 684
No URAIAN KODE KOEF. SATUAN KET.
d Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 8.00 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata rata bermuatan v1 40.00 km / jam
Kecepatan rata rata kosong v2 50.00 km / jam
Kapasitas AMP batch Q2 b 0.50 ton
Waktu menyiapkan 1 batch ATB Tb 1.00 menit
Waktu Siklus Ts2
- Mengisi bak = ( V : Q2b ) x Tb T1 16.00 menit
- Angkut = ( L : v1 ) x 60 menit T2 29.99 menit
- Tunggu + Dumping + Putar T3 15.00 menit
- Kembali = ( L : v2 ) x 60 menit T4 23.99 menit
Ts2 84.99 menit
e Finisher
Kapasitas produksi V 40.00 ton/jam
Faktor efisiensi alat Fa 0.75 -
f Tandem Roller ( E 17 )
Kecepatan rata rata alat v 3.50 km / jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 6.00 lintasan
Faktor efisiensi alat Fa 0.83 -
Analisa - E 685
No URAIAN KODE KOEF. SATUAN KET.
h Alat Bantu
Diperlukan :
- Kereta dorong = 2 bh Lump sum
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan
3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 18.04 m3 / jam
Produksi ATB / hari = Tk x Q2 Qt 126.30 m3
Kebutuhan tenaga
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Rp #NAME? / M3
Analisa - E 686
FORMULIR STANDAR UNTUK PEREKAMAN ANALISA
MASING MASING HARGA SATUAN
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.0301 #REF! #REF!
2 Mandor ( L 03 ) Jam 0.0060 #REF! #REF!
B BAHAN
1 Aspal ( M 10 ) ( M 10 ) Kg 0.6417 #REF! #REF!
2 Karosene ( M 11 ) ( M 11 ) Liter 0.4889 #REF! #REF!
C PERALATAN
1 Asphalt Sprayer ( E 03 ) Jam 0.0030 #NAME? #NAME?
2 Compresor ( E 05 ) Jam 0.0031 #NAME? #NAME?
3 Dump Truck ( E 08 ) Jam 0.0030 #NAME? #NAME?
JUMLAH #NAME?
JASA 10 % #NAME?
JUMLAH ( BELUM TERMASUK PPN ) #NAME?
DIBULATKAN #NAME?
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )
dan biaya biaya lainnya
Analisa - E 687
URAIAN ANALISA HARGA SATUAN LAPIS RESAP PENGIKAT
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.00 Km
4 Jam kerja efektif 1 hari Tk 7.00 Jam
5 Faktor kehilangan material Fh 1.10 -
6 Komposisi campuran AC ( Spesifikasi )
- Aspal AC - 10 atau AC - 20 AS 56 % 100 Bagian
- Minyak Flux / pencair K 44 % 80 Bagian
8 Bahan dasar ( aspal dan minyak pencair ) semuanya diterima di Lokasi Pekerjaan
II METODA KERJA
1 Aspal dan minyak Flux dicampur dan dipanaskan sehingga menjadi campuran aspal cair
2 Permukaan yang akan dilapis dibersihkan dari debu dan kotoran dg air kompresor
3 Campuran aspal cair disemprotkan dg aspahalt sprayer ke atas permukaan yg akan dilapis
4 Angkutan aspal dan minyak Flux menggunakan Dump truck
2 ALAT
a Asphalt Sprayer ( E 03 )
Kapasitas alat V 800.00 liter
Faktor efisiensi alat Fa 0.83 -
Waktu siklus ( termasuk proses pemanasan ) Ts 2.00 jam
b Air Compresor ( E 05 )
Kapasitas alat -----------> Diambil V 400.00 m2 / jam
Aplikasi Lapis Resap Pengikat Rata rata ( Spesifikasi ) Ap 0.80 liter / m2
Analisa - E 688
No URAIAN KODE KOEF. SATUAN KET.
c Dump Truk ( DT ) ( E 08 )
Sebagai alat pengangkut bahan di lokasi pekerjaan Dump Truck melayani alat
Asphalt Sprayer
3 TENAGA
Produksi menentukan : ASPALT FINISHER Q4 332.00 Liter
Produksi Lapis Resap Pengikat / hari = Tk x Q4 Qt 2,324.00 Liter
Kebutuhan tenaga
- Pekerja P 10.00 orang
- Mandor M 2.00 orang
Rp #NAME? / LITER
Analisa - E 689
FORMULIR STANDAR UNTUK PEREKAMAN ANALISA
MASING MASING HARGA SATUAN
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.4373 #REF! #REF!
2 Mandor ( L 03 ) Jam 0.0625 #REF! #REF!
B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.7680 #REF! #REF!
2 Agregat Halus ( M 04 ) M3 0.4320 #REF! #REF!
C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0625 #NAME? #NAME?
2 Dump Truck ( E 09 ) Jam 0.1994 #NAME? #NAME?
3 Motor Grader ( E 13 ) Jam 0.0117 #NAME? #NAME?
4 Vibratory Roller ( E 19 ) Jam 0.0178 #NAME? #NAME?
5 Pneumatic Tyre Roller ( E 18 ) Jam 0.0043 #NAME? #NAME?
6 Water Tank Truck ( E 23 ) Jam 0.0211 #NAME? #NAME?
7 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH #NAME?
JASA 10 % #NAME?
JUMLAH ( BELUM TERMASUK PPN ) #NAME?
DIBULATKAN #NAME?
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )
dan biaya biaya lainnya
Analisa - E 690
URAIAN ANALISA HARGA SATUAN LAPIS PONDASI AGREGAT KLAS A
I ASUMSI
1 Menggunakan alat berat Cara mekanik
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km
5 Tebal Agregat padat t 0.15 m
6 Faktor kembang material ( padat - lepas ) Fk 1.20
7 Jam kerja efektif per hari Tk 7.00 Jam
8 Proporsi campuran
- Agregat Kasar Ak 64.00 % Tabel; 5.1.2 (a)
- Agregat halus Ah 36.00 %
II METODA KERJA
1 WHEEL LOADER mencampur dan memuat agregat ke dalam Dump Truck di
Base camp
2 Dump Truck mengangkut Agregat ke lokasi pekerjaan dan dihampar dg motor
Grader
3 Hamparan Agregat di basahi dengan Water Tank Truck sebelum dipadatkan
dengan Tandem Roller & PTR
4 Selama pemadatan sekelompok pekerja akan merapikan tepi hamparan dan level
permukaan dengan menggunakan alat bantu
2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50 m3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu siklus Ts 1
- Mencampur T1 2.50 menit
- Memuat dan Lain lain T2 1.00 menit
Ts 1 3.50 menit
b Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 6.00 m3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata rata bermuatan v1 45.00 km / jam
Kecepatan rata rata kosong v2 60.00 km / jam
Waktu Siklus Ts2
- Waktu tempuh isi = ( L : v1 ) x 60 menit T1 26.65 menit
- Waktu tempuh kosong = ( L : v2 ) x 60 menit T2 19.99 menit
- lain lain termasuk menurunkan Agregat T3 3.00 menit
Analisa - E 691
No URAIAN KODE KOEF. SATUAN KET.
c Motor Grader ( E 13 )
Panjang hamparan Lh 50.00 m
Lebar efektif kerja blade b 2.40 m
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata rata alat v 4.00 km / jam
Jumlah lintasan n 6.00 Lintas 3 x pp
Waktu siklus Ts 3
- Perataan 1 Lintasan = Lh : ( v x 1000 x 60 menit ) T1 0.75 menit
- Lain lain T2 1.00 menit
Ts 3 1.75 menit
d Vibratory Roller ( E 19 )
Kecepatan rata rata alat v 3.00 km / jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 8.00 lintasan
Faktor efisiensi alat Fa 0.83 -
Analisa - E 692
No URAIAN KODE KOEF. SATUAN KET.
g Alat Bantu
Diperlukan :
3 TENAGA
Produksi menentukan : WHEEL LOADER Q1 16.01 m3 / jam
Produksi Agregat / hari = Tk x Q1 Qt 112.05 m3
Kebutuhan tenaga
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Rp #NAME? / M2
Analisa - E 693
FORMULIR STANDAR UNTUK PEREKAMAN ANALISA
MASING MASING HARGA SATUAN
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.4373 #REF! #REF!
2 Mandor ( L 03 ) Jam 0.0625 #REF! #REF!
B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.7080 #REF! #REF!
2 Agregat Halus ( M 04 ) M3 0.4920 #REF! #REF!
C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0625 #NAME? #NAME?
2 Dump Truck ( E 09 ) Jam 0.1994 #NAME? #NAME?
3 Motor Grader ( E 13 ) Jam 0.0117 #NAME? #NAME?
4 Vibratory Roller ( E 19 ) Jam 0.0178 #NAME? #NAME?
5 Pneumatic Tyre Roller ( E 18 ) Jam 0.0043 #NAME? #NAME?
6 Water Tank Truck ( E 23 ) Jam 0.0211 #NAME? #NAME?
7 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH #NAME?
JASA 10 % #NAME?
JUMLAH ( BELUM TERMASUK PPN ) #NAME?
DIBULATKAN #NAME?
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )
dan biaya biaya lainnya
Analisa - E 694
URAIAN ANALISA HARGA SATUAN LAPIS PONDASI AGREGAT KLAS B
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0 Km
5 Tebal Agregat padat t 0.15 m
6 Faktor kembang material ( padat - lepas ) Fk 1.20
7 Jam kerja efektif per hari Tk 7.00 Jam
8 Proporsi campuran
- Agregat Kasar Ak 59.00 % Tabel; 5.1.2 (a)
- Agregat halus Ah 41.00 %
II METODA KERJA
1 WHEEL LOADER mencampur dan memuat agregat ke dalam Dump Truck di
Base camp
2 Dump Truck mengangkut Agregat ke lokasi pekerjaan dan dihampar dengan
motor Grader
3 Hamparan Agregat di basahi dengan Water Tank Truck sebelum dipadatkan
dengan Tandem Roller & PTR
4 Selama pemadatan sekelompok pekerja akan merapikan tepi hamparan dan level
permukaan dengan menggunakan alat bantu
2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50 m3
Faktor bucket Fb 0.90 -
Faktor efisiensi alat Fa 0.83 -
Waktu siklus Ts 1
- Mencampur T1 2.50 menit
- Memuat dan Lain lain T2 1.00 menit
Ts 1 3.50 menit
b Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 6.00 m3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata rata bermuatan v1 45.00 km / jam
Kecepatan rata rata kosong v2 60.00 km / jam
Waktu Siklus Ts2
- Waktu tempuh isi = ( L : v1 ) x 60 menit T1 26.65 menit
- Waktu tempuh kosong = ( L : v2 ) x 60 menit T2 19.99 menit
- lain lain termasuk menurunkan Agregat T3 3.00 menit
Analisa - E 695
No URAIAN KODE KOEF. SATUAN KET.
c Motor Grader ( E 13 )
Panjang hamparan Lh 50.00 m
Lebar efektif kerja blade b 2.40 m
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata rata alat v 4.00 km / jam
Jumlah lintasan n 6.00 Lintas 3 x pp
Waktu siklus Ts 3
- Perataan 1 Lintasan = ( Lh x 60 ) : ( v x 1000 ) T1 0.75 menit
- Lain lain T2 1.00 menit
Ts 3 1.75 menit
d Vibratory Roller ( E 17 )
Kecepatan rata rata alat v 3.00 km / jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 8.00 lintasan
Faktor efisiensi alat Fa 0.83 -
Analisa - E 696
No URAIAN KODE KOEF. SATUAN KET.
g Alat Bantu
Diperlukan :
3 TENAGA
Produksi menentukan : WHEEL LOADER Q1 16.01 m3 / jam
Produksi Agregat / hari = Tk x Q1 Qt 112.05 m3 / jam
Kebutuhan tenaga
- Pekerja P 7.00 orang
- Mandor M 1.00 orang
Rp #NAME? / M2
Analisa - E 697
FORMULIR STANDAR UNTUK PEREKAMAN ANALISA
MASING MASING HARGA SATUAN
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.0301 #REF! #REF!
2 Mandor ( L 03 ) Jam 0.0060 #REF! #REF!
B BAHAN
1 Aspal ( M 10 ) Kg 0.8880 #REF! #REF!
2 Kerosene ( M 11 ) Liter 0.2530 #REF! #REF!
C PERALATAN
1 Asphalt Sprayer ( E 03 ) Jam 0.0030 #NAME? #NAME?
2 Compresor ( E 05 ) Jam 0.0063 #NAME? #NAME?
3 Dump Truck ( E 08 ) Jam 0.0030 #NAME? #NAME?
JUMLAH #NAME?
JASA 10 % #NAME?
JUMLAH ( BELUM TERMASUK PPN ) #NAME?
DIBULATKAN #NAME?
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )
dan biaya biaya lainnya
Analisa - E 698
URAIAN ANALISA HARGA SATUAN LAPIS PEREKAT
I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.00 Km
4 Jam kerja efektif 1 hari Tk 7.00 Jam
5 Faktor kehilangan material Fh 1.10 -
6 Komposisi campuran ( Spesifikasi )
- Aspal AC - 10 atau AC - 20 AS 77 % 100 Bagian
- Minyak Flux / pencair K 23 % 30 Bagian
II METODA KERJA
1 Aspal dan minyak Flux dicampur dan dipanaskan sehingga menjadi campuran
aspal cair
2 Permukaan yang akan dilapis dibersihkan dari debu dan kotoran dg air
kompresor
3 Campuran aspal cair disemprotkan dg aspahalt sprayer ke atas permukaan yg
akan dilapis
4 Angkutan aspal dan minyak Flux menggunakan Dump truck
2 ALAT
a Asphalt Sprayer ( E 03 )
Kapasitas alat V 800.00 Liter
Faktor efisiensi alat Fa 0.83 -
Waktu siklus ( termasuk proses pemanasan ) Ts 2.00 Jam
b Air Compresor ( E 05 )
Kapasitas alat . . . . . Diambil V 400.00 m2 / jam
Aplikasi Lapis Resap Pengikat Rata rata ( Spesifikasi ) Ap 0.40 Liter / m2
Analisa - E 699
No URAIAN KODE KOEF. SATUAN KET.
c Dump Truk ( DT ) ( E 08 )
Sebagai alat pengangkut bahan di lokasi pekerjaan Dump Truck melayani alat
Asphalt Sprayer
3 TENAGA
Produksi menentukan : ASPALT FINISHER Q4 332.00 Liter
Produksi Lapis Perekat / hari = Tk x Q4 Qt 2,324.00 Liter
Kebutuhan tenaga
- Pekerja P 10.00 orang
- Mandor M 2.00 orang
Rp #NAME? / Liter
Analisa - E 700
FORMULIR STANDAR UNTUK PEREKAMAN ANALISA
MASING MASING HARGA SATUAN
HARGA JUMLAH
NO KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)
A TENAGA
1 Pekerja ( L 01 ) Jam 0.0161 #REF! #REF!
2 Mandor ( L 02 ) Jam 0.0040 #REF! #REF!
B BAHAN
C PERALATAN
1 Motor Grader ( E 13 ) Jam 0.0025 #NAME? #NAME?
2 Vibratory Roller ( E 19 ) Jam 0.0040 #NAME? #NAME?
3 Water Tank Truck ( E 23 ) Jam 0.0105 #NAME? #NAME?
4 Alat Bantu Ls 1.0000 500.00 500.00
JUMLAH #REF!
JASA 10 % #REF!
JUMLAH ( BELUM TERMASUK PPN ) #REF!
DIBULATKAN #REF!
1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembayaran
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar dari kontrak )
dan biaya biaya lainnya
Analisa - E 701
URAIAN ANALISA HARGA SATUAN PENYIAPAN BADAN JALAN
( PEMADATAN DAN PERATAAN )
SATUAN : M2 Analisa EI - 33
I ASUMSI
1 Pekerjaan dilakukan pada hanya pada tanah galian
2 Pekerjaan dilakukan secara mekanis
3 Lokasi pekerjaan : sepanjang jalan
4 Kondisi jalan : jelek / belum padat
5 Jam kerja efektif per hari Tk 7.00 Jam
II URUTAN KERJA
1 Motor Grader meratakan permukaan hasil galian
2 Vibro Roller memadatkan permukaan jalan yang telah diratakan oleh Motor grader
3 Sekelompok pekerja akan membanru meratakan badan jalan dengan alat bantu
permukaan dengan menggunakan alat bantu
2 ALAT
a Motor Grader ( E 13 )
Panjang hamparan Lh 50.00 m
Lebar efektif kerja blade b 2.40 m
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata rata alat v 2.00 km / jam
Jumlah lintasan n 6.00 Lintas 3 x pp
Waktu siklus Ts 1
- Perataan 1 Lintasan = Lh : ( v x 1000 x 60 menit ) T1 1.50 menit
- Lain lain T2 1.00 menit
Ts 1 2.50 menit
b Vibratory Roller ( E 19 )
Kecepatan rata rata alat v 2.00 km / jam
Lebar efektif pemadatan b 1.20 m
Jumlah lintasan n 8.00 lintasan
Faktor efisiensi alat Fa 0.83 -
Analisa - E 702
No URAIAN KODE KOEF. SATUAN KET.
g Alat Bantu
Diperlukan :
3 TENAGA
Produksi menentukan : VIBRATORY ROLLER Q2 249.00 m3 / jam
Produksi Pekerjaan / hari = Tk x Q2 Qt 1,743.00 m3
Kebutuhan tenaga
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Rp #REF! / M2
Analisa - E 703