URAIAN ANALISA ALAT DUMP TRUCK

No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 3 - 4 M3
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4.0 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 360,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 36,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 42,735.19 Rupiah
W

b. Asuransi, dll = 0.002 x B F 360.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 43,095.19 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (10%-12%) x Pw x Ms H 103,376.90 Rupiah

2. Pelumas = (0,25%-0,35%) x Pw x Mp I 9,500.00 Rupiah

Biaya bengkel (2,2% - 2,8%) x B J 5,040.00 Rupiah


W

3. Perawatan dan (6,4 % - 9 %) x B K 11,520.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 26,142.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 20,928.57 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 176,508.33 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 219,603.52 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 26,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 20,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,650.00 Liter
5. Bahan Bakar Solar Ms 10,337.69 Liter
6. Minyak Pelumas Mp 38,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
No. URAIAN KODE KOEF. SATUAN KET.

A. URAIAN PERALATAN
1. Jenis Peralatan DUMP TRUCK 6-8 M3
2. Tenaga Pw 190.0 HP
3. Kapasitas Cp 8.0 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 420,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 42,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26380 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 49,857.72 Rupiah
W

b. Asuransi, dll = 0.002 x B F 420.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 50,277.72 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (10%-12%) x Pw x Ms H 196,416.11 Rupiah

2. Pelumas = (0,25%-0,35%) x Pw x Mp I 18,050.00 Rupiah

Biaya bengkel (2,2% - 2,8%) x B J 5,880.00 Rupiah


W

3. Perawatan dan (6,4 % - 9 %) x B K 13,440.00 Rupiah


perbaikan = W

4. Operator = ( 1 Orang / Jam ) x U1 L 26,142.86 Rupiah


5. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 20,928.57 Rupiah

Biaya Operasi per Jam = (H+I+K+L+M) P 280,857.54 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 331,135.26 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 10.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 26,142.86 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 20,928.57 Rp./Jam
4. Bahan Bakar Bensin Mb 7,650.00 Liter
5. Bahan Bakar Solar Ms 10,337.69 Liter
6. Minyak Pelumas Mp 38,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan