A Unit Filtrasi
1 Lampu 40 10
2 Pompa Feed 836 1
3 Pompa Mikrofilter 370 1
4 Pompa Filtrasi ke Hopper 660 1
5 Conductivity TDS Monitor 33 4
B Unit Filling
1 Lampu Neon 40 4
2 Lampu LED 18 2
3 Blower 126 2
4 AC 1660 2
5 Kompressor 5592.75 1
6 Seperangkat Unit Alat Filling 3800 1
7 Mesin Penutup Botol 380 1
8 Ozone Generator 140 1
9 Uv light 20 1
C Unit Packaging
1 Conveyor 370 1
2 Lampu Neon 40 4
3 Lampu LED 18 1
D Unit Analisa
1 Timbangan 4 1
2 Lampu neon 40 1
3 Mikroskop 20 1
4 Autoclave 2000 1
TOTAL PEMAKAIAN LISTRIK
1 Air Minum
Hasil Produksi Botol Kecil 0.33 499
2 Botol + Tutup 1 499
3 Label 1 499
4 Lakban 0.94 21
5 Selotip 0.03 499
6 Kardus 1 21
7 Stiker 1 499
8 Media Bakteri 0.0045 1
9 Aquadest 0.375 1
10 Ongkos angkut 1 21
Total
Total Per Botol
1 Air Minum
Air Reject 0.33 1
2 Botol + Tutup 1 1
Total Reject
1 420000000 5
Gaji Pekerja per Botol 1500
Unit Filtrasi
Pompa penampung IDR 689,000.00 IDR 180,000.00
Pompa umpan IDR 975,000.00 IDR 315,000.00
filtration set IDR 25,000,000.00 IDR 20,000,000.00
Filling
Ozone Generator IDR 3,950,000.00 IDR 1,250,000.00
Uv light IDR 1,100,000.00 IDR 900,000.00
Unit Alat Filling IDR 205,000,000.00 IDR 188,351,500.00
kompressor IDR 68,200,000.00 IDR 58,700,000.00
mesin penutup botol IDR 5,585,000.00 IDR 485,000.00
AC IDR 3,300,000.00 IDR 2,261,000.00
blower IDR 1,717,000.00 IDR 1,080,500.00
Packing
konveyor IDR 6,900,000.00 IDR 5,540,700.00
Analisa
Autoclave IDR 70,000,000.00 IDR 60,500,000.00
mikroskop IDR 3,700,000.00 IDR 3,000,000.00
Neraca Analitik IDR 18,600,000.00 IDR 3,850,000.00
Total
4
40
20
2000
18710.75
Umur alat
depresiasi/tahun depresiasi/jam
(tahun)
A Unit Filtrasi
1 Lampu 40
2 Pompa Feed 836
3 Pompa Mikrofilter 370
4 Pompa Filtrasi ke Hopper 660
5 Conductivity TDS Monitor 33
B Unit Filling
1 Lampu Neon 40
2 Lampu LED 18
3 Blower 126
4 AC 1660
5 Kompressor 5592.75
6 Seperangkat Unit Alat Filling 3800
7 Mesin Penutup Botol 380
8 Ozone Generator 140
9 Uv light 20
C Unit Packaging
1 Conveyor 370
2 Lampu Neon 40
3 Lampu LED 18
D Unit Analisa
1 Timbangan 4
2 Lampu neon 40
Mikroskop 20
3
4 Autoclave 2000
TOTAL PEMAKAIAN LISTRIK
1 Air Minum
Hasil Produksi Botol Kecil 0.33
2 Botol + Tutup 1
3 Label 1
4 Lakban 0.94
5 Selotip 0.03
6 Kardus 1
7 Stiker 1
8 Media Bakteri 0.0045
9 Aquadest 0.375
10 Ongkos angkut 1
Total
Total Per Botol
1 Air Minum
Air Reject 0.33
2 Botol + Tutup 1
Total Reject
1 420000000 5
Gaji Pekerja per Botol 300
Unit Filtrasi
Pompa penampung IDR 689,000.00
Pompa umpan IDR 975,000.00
filtration set IDR 25,000,000.00
Filling
Ozone Generator IDR 3,950,000.00
Uv light IDR 1,100,000.00
Unit Alat Filling IDR 205,000,000.00
kompressor IDR 68,200,000.00
mesin penutup botol IDR 5,585,000.00
AC IDR 3,300,000.00
blower IDR 1,717,000.00
Packing
konveyor IDR 6,900,000.00
Analisa
Autoclave IDR 70,000,000.00
mikroskop IDR 3,700,000.00
Neraca Analitik IDR 18,600,000.00
Total
1 4
1 40
1 20
1 2000
18710.75
Jumlah Total Satuan Harga per satuan (Rp.) Biaya total (Rp)
Jumlah Total Satuan Harga per satuan (Rp.) Biaya total (Rp)
kWh
jam
botol
jam