LANGKAH LANGKAH PENGERJAAN:

A. KRP = kill rate pressure ( psi )


1. Mskkan harga OMW = 12 ppg
2. Mskkan harga pump 1 ( for low rate ) : 650 psi @ 35 spm
3. Mskkan harga pump 1 ( for high rate ) : 850 psi @ 45 spm
4. Mskkan harga pump 2 ( for low rate ) : 650 psi @ 35 spm
5. Mskkan harga pump 2( for high rate ) : 850 psi @ 45 spm

B. Masukkan harga PO = pump output ( 0.12 bbl/stk ) baik utk pump 1 dan pump 2
C. Masukkan harga DPC = DP capacity : 0,172 bbl/ft ( klu ke 3 pipa baik DP,HWDP & DC tinggal kamu jumlahkan )
D. Masukkan harga SIDPP ( Shut In DP Press ) : 580 psi
E. Masukkan harga SICP ( Shut In Casing Press ) : 870 psi
F. Masukkan harga Pit Gain : 15 bbl
G. Masukkan harga bit TVD : 11850 ft ; harga bit MD : 11850 ft
H. Masukkan harga shoe TVD : 8800 ft; harga bit MD : 11850 ft

KEMUDIAN TINGGAL KAMU HITUNG APA YG DITANYAKAN


JAWABAN :
1. KMW = SIDPP ÷ BIT TVD ÷ 0,052 + OMW = 12,9 ppg
2. Utk no 2 spi 6 tinggal dimasukkan sesuai dg yg diminta yaitu : ICP, FCP, STB, STS dan Total stroke
3. Utk Drill pipe schedule, misalkan ambil N = 100 stks, sehingga pressure drop (psi)/ N stk dicari dg rumus spt
sheet 2 shg bias didptkan harga pressure drop (psi)/ N stk

4.SELAMAT MENCOBA