TIME SCHEDULE

PEMBANGUNAN GEDUNG PERTEMUAN 3 LANTAI DI GROBOGAN


TAHUN 2017
BULAN KE 1 BULAN KE 2 BULAN KE 3 BULAN KE 4 BULAN KE 5
NO URAIAN PEKERJAAN HARGA
VOL SAT.PEK
JUMLAH BOBOT (%) DURASI keterangan
I II III IV I II III IV I II III IV I II III IV I II

I PEKERJAAN PERSIAPAN 430.72 60,837,872.88 3.901 2 1.951 1.951 100.00


II PEKERJAAN TANAH 554.31 # 58,992,080.15 3.783 1 3.783
III PEKERJAAN BETON LANTAI 1 205.57 314,145,904.86 20.144 3 6.715 6.715 6.715
IV PEKERJAAN BETON LANTAI 2 373.19 314,145,904.86 20.144 3 6.715 6.715 6.715
V PEKERJAAN BETON LANTAI 3 370.91 300,148,031.08 19.247 3 6.416 6.416 6.416
VI PEKERJAAN ATAP 363.65 260,619,248.66 16.712 3 5.571 5.571 5.571
VII PEKERJAAN DINDING 232.38 64,769,275.05 4.153 1 4.153
VIII PEKERJAAN LANTAI 270.1 48,935,735.30 3.138 1 3.138
IX PEKERJAAN PLAFOND 566.3 89,298,431.25 5.726 1 5.726
X PEKERJAAN KUSEN,DAUN PIMTU & JENDELA 19 15,893,641.50 1.019 1 1.019
XI PEKERJAAN SANITASI AIR 38.75 17,663,119.10 1.133 1 1.133
XII PEKERJAAN PENGECATAN 262.67 8,368,407.43 0.537 1 0.536618978
XIII PEKERJAAN PENGGANTUNG & PENGUNCI 104 3,651,500.00 0.234 1 0.234150191
XIV PEKERJAAN LAIN-LAIN 2 2,000,000.00 0.128 1 0.12824877
Jumlah 1,559,469,152.12 100.000

Rencana Kemajuan Pekerjaan 1.951 1.951 3.783 6.715 6.715 6.715 6.715 6.715 6.715 6.416 6.416 6.416 5.571 5.571 5.571 9.443 5.726 0.899 100.00

Rencana Kemajuan Komulatif 1.951 3.901 7.684 14.399 21.114 27.828 34.543 41.258 47.973 54.388 60.804 67.220 72.790 78.361 83.932 93.375 99.101 100.000 100.00