Anda di halaman 1dari 26

1.

IDENTIFIKASI KENDALA

JENIS MESIN TV = 50Q KOMP= 28Q


MESIN PEMOTONG 120 160
MESIN PERAKIT 200 280
MESIN PENYELESAIAN 210 110

MASALAH DITEMUKAN PADA KELEBIHAN PENGGUNAAN MENIT PADA MESIN PERAKIT

SOLUSI: MENGURANGI JUMLAH PRODUKSI

2. BAURAN PRODUK OPTIMUM


TV KOMPUTER
HARGA JUAL PER UNIT 1,200 1,840
By. Produksi Per unit 500 1,000
TROUGHPUT PER UNIT 700 840

PENDEKATAN TRADISIONAL
TROUGHPUT DRIVER: MENIT TKL
TV KOMPUTER
TROUGHPUT PER UNIT 700 840
MENIT TKL PER UNIT 100 100
TROUGHPUT PER MENIT TKL 7.00 8.40

BAURAN PRODUK OPTIMUM:


TV 30Q 120
KOMPUTER 28Q 280
400

PENDEKATAN TEORI KENDALA (TOC)


TROUGHPUT DRIVER: MENIT MESIN PERAKIT

TV KOMPUTER
TROUGHPUT PER UNIT 700 840
MENIT MESIN PERAKIT PER UNIT 4 10
TROUGHPUT PER MENIT MESIN PERAKIT 175.00 84.00

BAURAN PRODUK OPTIMUM:


TV 50Q 200
KOMPUTER 20Q 200
400

3. LAPORAN LABA RUGI


PENDEKATAN TRADISIONAL
PENJUALAN : TV 36,000
KOMPUTER 51,520
TOTAL PENJUALAN 87,520
BIAYA PRODUKSI : TV 15,000
KOMPUTER 28,000
TOTAL BIAYA PRODUKSI 43,000
LABA KOTOR 44,520
BIAYA PEMASARAN 10,000
LABA BERSIH 34,520

PENDEKATAN TEORI KENDALA (TOC)


PENJUALAN : TV 60,000
KOMPUTER 36,800
TOTAL PENJUALAN 96,800
BIAYA PRODUKSI : TV 25,000
KOMPUTER 20,000
TOTAL BIAYA PRODUKSI 45,000
LABA KOTOR 51,800
BIAYA PEMASARAN 10,000
LABA BERSIH 41,800

4. DARI ANALISIS DATA, MAKA DISARANKAN PERSH MENGGUNAKAN BAURAN PRODUK MENU
PENDEKATAN TOC, YAITU 50Q TV DAN 20Q KOMP SETIAP HARI, KARENA LABA YG DIHASIL
BESAR DARI BAURAN PRODUK OPTIMUM MENURUT PEND. TRADISIONAL.
TOTAL KAPASITAS SELISIH PERSEN (%)
280 400 120 70
480 400 (80) 120 kendala ada pada mesin Perakit
320 400 80 80

ENIT PADA MESIN PERAKIT

OMPUTER

OMPUTER

4 50TV = 200 M 30
10 28 Komp = 280 M
KAPASITA K

OMPUTER

20
KAPASITAS

30Q TV
28Q KOMP

(-)

50Q TV
20Q KOMP

(-)

AKAN BAURAN PRODUK MENURUT


RI, KARENA LABA YG DIHASILKAN LEBIH
RADISIONAL.
A

JENIS BIAYA PRODUKSI

BIAYA BAHAN BAKU (100% VC)


250,000

BIAYA TENAGA KERJA LANGSUNG (VC & FC)


100,000

BIAYA OVERHEAD PABRIK (FC & VC)


75,000

FORMAT LAPORAN LABA RUGI:


PENJUALAN XXX
HARGA POKOK PENJUALAN (HPP) XXX (-)
LABA KOTOR XXX
BEBAN2X (PEMASARAN, ADM & UMUM) XXX (-)
LABA BERSIH XXX

FORMAT PERHITUNGAN HARGA POKOK PENJUALAN

Persediaan Awal BBL 1/1 xxxx


Pembelian BBL xxxx (+)
BBL siap digunakan xxxx
Persediaan Akhir BBL 31/12 xxxx (-)
BBL yang digunakan xxxx
TKL xxxx
BOP xxxx
Barang Dalam Proses (BDP) xxxx
Persediaan Awal BDP 1/1 xxxx
BDP Periode Berjalan xxxx
Persediaan Akhir BDP 31/12 xxxx
Barang Jadi xxxx
Persediaan Awal BJ 1/1 xxxx
Barang Jadi Siap Jual xxxx
Persediaan Akhir BJ 31/12 xxxx
Harga Pokok Penjualan (HPP) XXXX

Biaya produk per unit:


Biaya BBL Per Unit (BBB/Q) xxx
Biaya TKL Per Unit (TKL/Q) xxx
Biaya Overhead Pabrik Per Unit (BOP/Q) xxx (+)
Biaya produk per unit: xxx

Pendekatan Konvensional
Biaya produk per unit: X Y
Biaya BBL Per Unit (BBB/Q) xxx xxx
Biaya TKL Per Unit (TKL/Q) xxx xxx
Biaya Overhead Pabrik Per Unit (BOP/Q) xxx xxx
Biaya produk per unit: xxx xxx

Pendekatan ABC
Biaya produk per unit: X Y
Biaya BBL Per Unit (BBB/Q) xxx xxx
Biaya TKL Per Unit (TKL/Q) xxx xxx
Biaya Overhead Pabrik Per Unit (BOP/Q) ?? ??
By Penyus & Pemelih/Q aa aa
By Penerimaan Pesanan/Q bb bb
By Produksi /Q cc cc
By. Set-Up Mesin/Q dd dd
By. Inspeksi/Q ee ee
Total BOP/Q vvv xxx
Biaya produk per unit: xxx xxx
ARUS BIAYA DALAM PROSES PRODUKSI

T
250,000

BARANG JADI

FC) BARANG DALAM PROSES


100,000 250,000 425,000
100,000
75,000 HARGA POKOK PENJU

75,000
PENGADAAN

BBL

TKL

BOP

SELESAI PROSES PRODUKSI

UALAN BJ

(+)
(+)

(-)

(+)

(-)

Z
xxx
xxx
xxx ??????
xxx

Z
xxx
xxx
?? ??
aa
bb
cc
dd
ee
xxx
xxx
SI

TRANSAKSI PENJUALAN

BARANG JADI PENJUALAN


425,000 425,000 1,250,000

HARGA POKOK PENJUALAN KAS/PIUTANG


425,000 1,250,000

ENGADAAN DIBEBANKAN KE PROSES PRODUKSI


DEBET KREDIT DEBET KREDIT
100,000 BDP 250,000
KAS 100,000 BBL 250,000

250,000 BDP 100,000


KAS 250,000 TKL 100,000

75,000 BDP 75,000


KAS 75,000 BOP 75,000

ELESAI PROSES PRODUKSI


JLH PROD 500
425,000
BDP 425,000 BY. PROD/Q = 425.000/250 = 1.700/ HARGA JUAL 2.500/Q
PROSES PRODUKSI SELESAI DIJUAL SEHARGA RP. 1.250.000
DEBET KREDIT
BARANG JADI (TAHU/TEM 425,000 TRANSAKSI PENJUALAN:
DBP 425,000 KAS / PIUTANG DAGANG 1,250,000
PENJUALAN
HARGA POKOK PENJUAL 425,000
BARANG JADI 425,000

JUMLAH PRODUKSI = 250 POTONG

BY PROD PER PTG TAHU = TOTAL BY PROD / JUMLAH PRO 1700


GA JUAL 2.500/Q
1,250,000
TAHAPAN PENYELESAIAN: BERAPA BIAY
PENDEKATAN
1. MENENTUKAN COST DRIVER (PENGGERAK BIAYA) 1

2. MENGHITUNG BIAYA PER COST DRIVER 2

3. MENGHITUNG TOTAL BIAYA UTK SETIAP JENIS PRODUK 3

4. MENGHITUNG BIAYA PER UNIT PER JENIS PRODUK 4

Total Biaya 43,500


A 4,350
B 4,350 BERAPA BIAY
Total Jam TKL (A+B) 8,700 PENDEKATAN
5 1

4
BERAPA BIAY
PENDEKATAN
1

Man Reg 2020 kls A & B:


Proyek FEB: Pemindahkan Kursi Gedung A - B
Jumlah Kursi : 10.000 == Cost Driver
Dana = 10.000.000 === Dana ini disiapkan utk Kegiatan apa???
Jumlah Mahasiswa = 100 orang
Jam Kerja = 24 JK

Berapa jumlah dana yang diterima per mahasiswa???? Rp. 100.000,-

Biaya Per Kursi = 10.000.000/10.000 = Rp. 1.000/kursi 50,000 A


25,000 B
75,000 C
A =50 105,000 D
B=25
C=75
D=105
BERAPA BIAYA PENANGANAN BAHAN ($43.500)PER UNIT UNTUK PRODUK A & B?
PENDEKATAN TRADISIONAL/KONVENSIONAL
COST DRIVER = JAM TKL PER UNIT

BIAYA PENANGANAN BAHAN PER JAM TKL = $ 5 / JAM TKL


= $43.500/((435x10)+(435x10))

TOTAL BIAYA PENANGANAN BAHAN UNTUK:


A= $5 X (435X10) 21,750
B= $5 X (435X10) 21,750
BIAYA PENANGANAN BAHAN PER UNIT UNTUK PRODUK:
A = $21.750 : 10 2,175 Per Unit
B = $21.750 : 10 2,175 Per Unit

BERAPA BIAYA PERUBAHAN RANCANG TEKNIK PER UNIT UNTUK PRODUK C + D?


PENDEKATAN TRADISIONAL/KONVENSIONAL
COST DRIVER = JAM MESIN PER UNIT : 2 JM/Q

BIAYA PERUBAHAN RANCANG TEKNIK PER JAM MESIN = $ 4,0625/JM


= (($500X10)+($500X3))/((2X400)+(2X400)) 6,500
4.0625 1,600
TOTAL BIAYA RANCANG TEKNIK UNTUK:
C= $4,0625 X (2 X 400) 3,250
D= $4,0625 X (2 X 400) 3,250

BIAYA PERUBAHAN RANCANG TEHNIK PER UNIT UNTUK PRODUK:


C = $3.250 : 400 8.125
D = $3,250 : 400 8.125
BERAPA BIAYA SET-UP MESIN PER UNIT UNTUK PRODUK E & F? $ 8.800
PENDEKATAN TRADISIONAL
COST DRIVER = JAM MESIN PER UNIT : 2 JM/Q

BIAYA SET-UP MESIN PER JAM MESIN = $ 4,00/JM


= $8.800/((2 X 1.000)+(2 X 100)) 2200
4.00
TOTAL BIAYA SET-UP MESIN UNTUK:
E= $4 X (2 X 1.000) 8,000
F= $4 X (2 X 100) 800

BIAYA SET-UP MESIN PER UNIT UNTUK PRODUK:


E = $8.000 : 1.000 8.00 Per Unit
F = $800 : 100 8.00 Per Unit
UNIT UNTUK PRODUK A & B? (Konvensional & ABC)
PENDEKATAN ACTIVITY BASED COSTING (ABC)
1. COST DRIVER = PERPINDAHAN BAHAN

JAM TKL 2. BIAYA PENANGANAN BAHAN PER PERPINDAHAN BAHAN =


8700 =$43.500/((3X10)+(7X10)) 100
5 435
3 TOTAL BIAYA PENANGANAN BAHAN UNTUK:
A = $435 X (3X10) 13,050
B = $435 X (7X10) 30,450
4 BIAYA PENANGANAN BAHAN PER UNIT UNTUK PRODUK:
A = $13.050 : 10 1,305
B = $30.450 : 10 3,045

R UNIT UNTUK PRODUK C + D?


PENDEKATAN ACTIVITY BASED COSTING/ABC
1. COST DRIVER = PERUBAHAN RANCANG TEKNIK PER LINI P

MESIN = $ 4,0625/JM 2. BY PERUBHN RANCANG TEKNIK PER 1X PERUBAHAN RANC

3 TOTAL BIAYA PERUBAHAN RANCANG TEKNIK UNTUK:


C= $500 X 10 5,000
D= $500 X 3 1,500

UNTUK PRODUK: 4 BIAYA PERUBAHAN RANCANG TEKNIK PER UNIT UNTUK PR


C = $5.000 : 400 12.50
D = $1.500 : 400 3.75
ODUK E & F? $ 8.800
PENDEKATAN ACTIVITY BASED COSTING
1. COST DRIVER = JAM SET UP MESIN PER LINI PRODUK

2. BY SET-UP MESIN PER JAM SET-UP MESIN = $880/JAM SET-


= $8.800 / (5+5) 880

3 TOTAL BIAYA SET-UP MESIN UNTUK:


E= $880 X 5 4,400
F= $880 X 5 4,400

4 BIAYA SET-UP MESIN PER UNIT UNTUK PRODUK:


E = $4.400 : 1.000 4.40 Per Unit
F = $4.400 : 100 44.00 Per Unit
DAHAN BAHAN = $ 435 / PERPINDAHAN BAHAN

NTUK PRODUK:

EKNIK PER LINI PRODUK

ERUBAHAN RANCANG TEKNIK = $500/1X PERBH RT

NIK UNTUK:

R UNIT UNTUK PRODUK:


INI PRODUK

N = $880/JAM SET-UP MESIN

RODUK:
JENIS BIAYA PRODUKSI

BIAYA BAHAN BAKU BDP PESANAN 101


XXX 240,000 Pers Awal 345,000
50,000
75,000
87,500
557,500

BIAYA TENAGA KERJA LANGSUNG BDP PESANAN 102


XXX 260,000 Pers Awal 275,000
40,000
30,000
15,000
360,000

BIAYA OVERHEAD PABRIK BDP PESANAN 103


300,000 180,000 Pers Awal 227,500
400,000 20,000
700,000 Selisih 520,000 55,000
27,500
330,000

FORMAT LAPORAN LABA RUGI: BDP PESANAN 104


PENJUAL XXX 130,000
HPP XXX (-) 100,000
A KOTOR XXX 50,000
BEBAN2X XXX (-)
BERSIH XXX
FORMAT PERHITUNGAN HARGA POKOK PENJUALAN

Persediaan xxxx
Pembelian xxxx (+)
BBL siap d xxxx
Persediaan xxxx (-)
digunakan xxxx
TKL xxxx
BOP xxxx (+)
ARUS BIAYA DALAM PROSES PRODUKSI

NAN 101 TRANSAKSI PENJ


557,500

BARANG JADI
1,247,500

NAN 102
360,000

HARGA POKOK PENJUALAN


917,500

NAN 103
330,000

LAPORAN LABA RUGI BLN JANUARI (3)


PENJUALAN
HPP
LABA KOTOR
BEBAN2X (PEMASARAN, ADM & UMUM
NAN 104 Kelebihan BOP Actual
LABA BERSIH
NO

TRANSAKSI PENJUALAN

DI PENJUALAN
917,500

NJUALAN KAS/PIUTANG

LN JANUARI (3)
1,600,000
917,500 (-)
682,500
265,000 (-)
520,000 (-)
(102,500)
JURNAL UMUM
NO KET Ref D K
1 BDP 101 50,000
BDP 102 40,000
BDP 103 20,000
BDP 104 130,000
BAHAN BAKU 240,000

2.a BDP 101 75,000


BDP 102 30,000
BDP 103 55,000
BDP 104 100,000
TKL 260,000

2.b BOP Bahan Penolong 300,000


BOP TKTL 400,000
Biaya TK Pemasaran 125,000
Biaya TK adm & umum 140,000
Kas 965,000

3 BDP 101 87,500


BDP 102 15,000
BDP 103 27,500
BDP 104 50,000
BOP Dibebankan 180,000

4.a Barang Jadi 1,247,500


BDP: 101 557,500
BDP: 102 360,000
BDP: 103 330,000

4.b Kas 1,600,000


Penjualan 1,600,000

HPP 917,500
Barang jadi 917,500

Unfavorable = BOP yang dibebankan lebih kecil dari actual


Favorable = BOP yang dibebankan lebih besar dari actual
PERHIT BOP:
P. 101 175
P. 102 30
P. 103 55
P. 104 100
360