5 .000 ×5 × 2. 500
Bahan baku Rp2.083.333,33
30
5 .000 ×2 . 500
Upah langsung Rp416.666,67
30
15.000. 000
Biaya pemasaran Rp500.000
30
Biaya administrasi dan 10.000.000
Rp333.333,33
umum 30
Total Rp3.333.333,33
2.
Total
Biaya
3.
EOQ=
√2×R×S
C
=
√2 ×100.000 kg × Rp100.000
Rp 250
=8.944,27 = 8.944(Dibulatkan)
Reorder Point = Safety Stock + Kebutuhan Selama Lead Time
= 1500 + (10 : 360 x 100.000)
= 4.277,77 = 4.278(Dibulatkan)