B) TAPAK
NO. BUTIR-BUTIRAN QTY UNIT PRICE TOTAL (RM)
3) Pembinaan :
a) Untuk membina ruang tambahan pada ruangan aktiviti koperasi 1 lot
b) Untuk melakukan kerja penambahan bumbung dan siling
4) Cat :
a) Untuk mengecat keseluruhan bahagian tapak baharu 1 lot
Jumlah 38,000
Discount
TOTAL AMOUNT RM56,000.00
Excluded From Scope of Works :
a. All materials
b. Electricity required to perform the work
c. To liase with authorities, perform any test and commissioning
Terms and Condition :
a. This quotation is valid for 14 days only
b. Term of Payment : 30% down payment upon confirmation of acceptance for this quotation
c. Payment should be made within 14 days
We hope above quotation meet your requirement. Please do not hesitate to contact us if you require further
information or clarification. Thank you!
PREPARED BY : RECEIVED BY :