Anda di halaman 1dari 1

REKAPITULASI

PERKIRAAN HARGA PEKERJAAN

PPK : PROVINSI JAWA JAWA TIMUR


NAMA PAKET : PRESERVASI JALAN DAN JEMBATAN TANJUNG BUMI - PAMEKASAN - SUMENEP
PROVINSI : JAWA TIMUR

JUMLAH HARGA PEKERJAAN (RP)

TOTAL JUMLAH HARGA PRESERVASI JALAN


NO. DIVISI URAIAN
PEKERJAAN (RP.)
REHABILITASI REHABILITASI PEMELIHARAAN
REKONSTRUKSI PELEBARAN
MINOR MAYOR BERKALA JEMBATAN

1 Umum 683.721.000,00 - - - 683.721.000,00 -


2 Drainase 8.199.317.039,34 2.666.291.830,00 450.155.750,00 1.969.411.110,00 3.113.458.349,34 -
3 Pekerjaan Tanah Dan Geosintetik 496.155.009,20 12.217.900,00 6.108.950,00 121.749.338,00 232.026.120,00 124.052.701,20
4 Pekerjaan Preventif - - - - - -
5 Pekerasan Berbutir Dan Perkerasan Beton Semen 4.145.959.697,20 555.234.060,00 129.124.200,00 275.464.960,00 3.161.365.777,20 24.770.700,00
6 Perkerasan Aspal 21.593.219.465,28 6.619.650.074,94 2.212.199.806,32 3.510.667.678,49 8.709.099.554,50 541.602.351,04
7 Struktur 1.204.607.651,97 96.053.089,44 73.323.261,38 194.783.434,88 293.837.432,42 546.610.433,85
8 Rehabilitasi Jembatan 450.577.874,97 - - - - 450.577.874,97
9 Pekerjaan Harian Dan Pekerjaan Lain-Lain 953.102.584,43 397.503.921,90 100.769.496,00 100.720.344,40 286.859.247,76 67.249.574,37
10 Pekerjaan Pemeliharaan Kinerja 460.403.835,34 123.247.223,80 36.698.490,50 62.512.772,20 90.949.248,84 146.996.100,00

(A) Jumlah Harga Pekerjaan ( termasuk Biaya Umum dan Keuntungan ) 38.187.064.157,73 10.470.198.100,08 3.008.379.954,20 6.235.309.637,97 16.571.316.730,06 1.901.859.735,43
(B) Pajak Pertambahan Nilai ( PPN ) = 10% x (A) 3.818.706.415,77 1.047.019.810,01 300.837.995,42 623.530.963,80 1.657.131.673,01 190.185.973,54
(C) JUMLAH TOTAL HARGA PEKERJAAN = (A) + (B) 42.005.770.573,51 11.517.217.910,09 3.309.217.949,62 6.858.840.601,77 18.228.448.403,06 2.092.045.708,97
(C) JUMLAH TOTAL HARGA PEKERJAAN ( dibulatkan ) 42.005.770.500,00 11.517.217.900,00 3.309.217.900,00 6.858.840.600,00 18.228.448.400,00 2.092.045.700,00
Terbilang : Empat Puluh Dua Milyar Lima Juta Tujuh Ratus Tujuh Puluh Ribu Lima Ratus Tujuh Puluh Empat Rupiah
- 42.005.770.500,00
42.013.536.000,00 11.517.584.000,00 3.316.610.000,00 6.858.842.000,00 18.228.454.000,00 2.092.046.000,00
7.765.500,00 366.100,00 7.392.100,00 1.400,00 5.600,00 300,00
Surabaya, 15 Desember 2021
Pejabat Pembuat Komitmen 3.1
Provinsi Jawa Timur

Candra Hervin Subandriyo, ST


NIP. 19840323 201012 1 001