ESTIMASI BIAYA PONDASI & STRUKTUR BAWAH

HARGA
NO URAIAN VOL SATUAN HARGA
SATUAN
1 MOBILISASI ALAT 2.00 LS 50,000,000 100,000,000
2 MOBILISASI TP 1.00 LS 87,500,000 87,500,000
2 PENGADAAN TP 40/40 5,040.00 M 704,000 3,548,160,000
3 PEMANCANGAN 5,040.00 M 100,000 504,000,000
4 SAMBUNGAN PANCANG 210.00 TITIK 150,000 31,500,000
5 PECAH TP 210.00 TITIK 90,000 18,900,000
6 GALIAN PILE CAP 98.74 M3 90,000 8,886,240
7 GALIAN SLOOF 284.59 M3 90,000 25,613,280
8 URUGAN PASIR PILE CAP 35.62 M3 325,000 11,575,200
9 URUGAN PASIR SLOOF 22.64 M3 325,000 7,357,350
10 LANTAI KERJA PILE CAP 17.81 M3 775,000 13,801,200
11 LANTAI KERJA SLOOF 11.32 M3 775,000 8,772,225
12 BETON PILE CAP 58.27 M3 4,400,000 256,396,800
13 BETON SLOOF 162.76 M3 4,400,000 716,144,000
14 URUGAN KEMBALI PC 29.62 M3 35,000 1,036,728
15 URUGAN KEMBALI SLOOF 85.38 M3 35,000 2,988,216
16 PEMADATAN TANAH PELAT 1,998.00 M2 30,000 59,940,000
17 URUGAN PASIR PELAT 199.80 M3 325,000 64,935,000
18 PLASTIK SHEET PELAT 1,998.00 M2 7,500 14,985,000
19 BETON PELAT 499.50 M3 4,400,000 2,197,800,000
7,680,291,239
P2 = Pile Cap ukuran 700 x 1400 x 600 – 3 buah Pancang/Bore Pile kedalaman 24 m (8 buah)

P3 = Pile Cap ukuran 1200 x 1200 x 800 – 4 buah Pancang/Bore Pile kedalaman 24 m (24 buah)

P5 = Pile Cap ukuran 1500 x 1800 x 800 – 6 buah Pancang/Bore Pile kedalaman 24 m (15 buah)

Total kebutuhan Tiang Pancang/Bore Pile = (3x24x8) + (4x24x24) + (6x24x15) = 5040 meter