IMPLEMENTASI BIM

Pada Proyek Konstruksi

By SALMAN
Manager BIM Ops PT.PP (persero) Tbk
THE OUTLINE
PT.PP Profil

What & Why BIM ?

Tujuan Penggunaan BIM

Tantangan Penggunaan BIM

BIM by Level & Dimension

Penggunaan BIM Pada Proyek


PT PP - Milestones

2011
2004 Diversification 2014 2016
1971 Employee to EPC and Diversification to Diversification to
Changed Management PP Investment PP Equipment PP Energy and
status to a Buy-Out PP Infra Subsidiaries
- Share RI 51%
State Owned
Enterprise - Share KKSPP 49%

1953 1971 1991 2004 2010 2011 2012 2014 2015 2016 2017

2010
PT PP (Persero) Tbk 2017
1991 IPO PP Presisi
Diversification to IPO
1953 Property and 2012 2015
Establishment Realty Diversification PP Property
of the NV. PP to PP Precast IPO

2
INTEGRATION of PP’s 7 Business Lines

UPSTREAM MIDSTREAM DOWNSTREAM

PROPERTY ENERGY INFRASTRUCTURE CONSTRUCTION EPC PRECAST EQUIPMENT

▪ COMMERCIAL ▪ POWER PLANT ▪ TOLL ROAD ▪ POWER PLANT ▪ CONSTRUCTION ▪ FOUNDATION


▪ HIGH RISE
▪ RESIDENTIAL ▪ GAS ▪ PORT ▪ OIL & GAS ▪ PRECAST CONSTRUCTION
BUILDING
▪ HOSPITALITY ▪ AIRPORT ▪ MINING FACTORY ▪ ASPHALT MIXING
▪ ROADS & BRIDGES
▪ HIGH RISE PLANT
▪ PORT
PRECAST ▪ READY-MIX
▪ DAM
▪ BUILDING PLANT
MANAGEMENT ▪ EQUIPMENT
RENTAL

INVESTMENT CONSTRUCTION
3
What’s & Why BIM ?
Building Information Modeling

4
“ ..What is BIM …. ?”
BIM (Building Information Modeling) adalah proses berbasis
teknologi untuk membuat model dari bangunan dengan
akurat secara digital. Sistem ini mensupport desain dalam
setiap siklus bangunan dan memberikan analisis dan kontrol
yang lebih baik daripada proses manual.

Model yang dibentuk menghasilkan geometri dan data yang


tepat yang diperlukan untuk mendukung perencanaan,
konstruksi, pabrikasi, aktivitas procurement dan pengelolaan
bangunan”

BIM bukan software….

BIM adalah suatu metode dalam memodelkan suatu


bangunan secara 3D s.d 6D, dengan menggunakan software
dan equipment digital.

5
“ ..What is BIM …. ?”

Information
BIM bukan hanya untuk Building

BIM bukan software


Building Modeling
BIM bukan sekedar 3D

BIM

6
“ ..What is BIM …. ?”

Optus stadium, Aussie

RENCANA REALISASI

7
Built before We Build
“ ..What is BIM …. ?”
Current Construction Coordination Expected Digital Construction Coordination

8
Why BIM.. ?
Data perencanaan antar disiplin (Struktur, Arsitek, MEP) umumnya tidak
saling terkoordinasi menyebabkan kebingungan dalam pelaksanaan dan
menyebabkan pelaksanaan terhambat.

Design Koordinasi Manual BIM Design Koordinasi

9
Why BIM.. ?
Desain Konstruksi yang semakin rumit dan unik

10
“ ..What is BIM …. ?”

11
Tujuan Penggunaan BIM
Building Information Modeling

12
Tujuan Penggunaan BIM

▪ Peningkatan Produktivitas dan Efisiensi


Proses Konstruksi
▪ Kolaborasi semua stakeholder Konstruksi
(Investor, perencana, kontraktor dan
manufaktur)
▪ Peningkatan Mutu, Biaya dan Waktu dari
Proyek-Proyek Konstruksi Indonesia
▪ Regulator Memberikan Approval,
Memonitor, dan Supervisi Progres
Pekerjaan Konstruksi Secara Digital
Sebagaimana Negara Maju Lainnya.

13
Tantangan Penggunaan BIM
Building Information Modeling

14
Tantangan Penggunaan BIM

Belum adanya Regulasi yang


mengatur Penerapan Sistem BIM
di proyek Konstruksi

Merubah habit kalangan pelaksana


konstruksi yang sudah nyaman
dengan sistem konvensional

SDM yang belum mumpuni dan belum


siap di Era Disruption saat ini

15
BIM by Level & Dimension
Building Information Modeling

16
Level of BIM
Tingkat Implementasi BIM (Maturity Level)

17
Dimension of BIM

3D 4D 5D 6D 7D
3D Building data & Project Schedule &
Informasi Phasing Conceptual Cost Planning Energy analysis Building Life Cycles
Existing model Data Just in Time schedule Quantity Extraction to Green Building Element BIM as built data
cost estimation
Data Prefabrikasi BIM Installation schedule Green Building BIM cost operation&
Trade Verification certification Tracking Maintenance
Reinforcement & struktur Payment Visual Approval
analysis Value Engineering Green Building Point BIM Digital lend lease
Last Planner schedule.
Field layout & civil data Prefabrication tracking. planning
Critical Point

Fungsi dan Benefits BIM

18
Benefit of BIM : Design & Shopdrawing Coordination BIM 3D

Proyek Jembatan Kendari

19
Benefit of BIM : Scheduling & Sequencing BIM 4D

Proyek Stadion Papua


Proyek Gedung BI Gorontalo

Jalan Tol Pandaan Malang

20
Benefit of BIM : Clash Detection BIM 4D

Ada GAP 3 m terhadap


dermaga Ferry

21
Benefit of BIM : Quantity Take Off BIM 5D

ASDP Bakauheni Port Project

Tol Pandaan Malang Project

22
Benefit of BIM : Cost Estimation BIM 5D
Cost Planner

23
Benefit of BIM : Energy Simulation BIM 6D

BNI 46 Pejompongan Building – Green Building Design & Build

Energy analysis Computational Flow Diagram


Green Building Element
Green Building Certification Tracking

24
BIM di Proyek Infrastruktur
Building Information Modeling

25
BUILDING INDORMATION MODELLING

PIDEKSO DAM

26 Penggunaan BIM Pada Proyek Infrastruktur


JUARA TEKLA INDONESIA AWARD 2022

27
SEKILAS
Proyek Waduk PIDEKSO merupakan salah
satu proyek strategis nasional yang terletak di
provinsi Jawa Tengah, di kabuapaten/kota
Wonogiri tepatnya di desa Pidekso.
Proyek ini dibawahi oleh Balai Besar Wilayah
Sungai Bengawan Solo dengan menggandeng
konsultan perencana PT.Mettana. Proses
pengerjaan Waduk PIDEKSO ini dilaksanakan
oleh PT.PP sebagai kontraktor tunggal.
Pelaksanaan proyek ini dimulai pada tanggal
2 Januari 2015 hingga 30 Juni 2021 dan
memakan waktu kurang lebih 2.549 hari
kalender dengan masa pemeliharaan selama
365 hari kalender. Proses pelaksanaan efektif
bagian bendungan dimulai pada pertengahan
tahun 2018.
Waduk PIDEKSO diharapkan dapat membantu
sebagai bahan baku air bersih 300 liter/detik,
irigasi seluas 1500 hektar, pengendali banjir
dan juga sebagai lokasi konservasi dan
pariwisata sehingga dapat membantu
meningkatkan kesejahteraan masyarakat
sekitar.

28
29
30
31
32
BIM IMPLEMENTATION
TEKLA STRUCTURES

33
SMART TECHNOLOGY
Geolistrik

34
SMART TECHNOLOGY
Early Warning System

35
SMART TECHNOLOGY
Drone Technology

36
37 Trimble SX 10
38
Overview - TRIMBLE 3D LASER SCANNER SX-10
BIM di Proyek Gedung
Building Information Modeling

39
40
41
42
43
44
45
BIM di Proyek Jembatan
Building Information Modeling

46
Penggunaan BIM Pada Proyek Jembatan Teluk Kendari

Bahteramas Bridge - Kendari

PIER P3

PYLON P1

47
Penggunaan BIM Pada Proyek Jembatan Teluk Kendari
Detailing..

Detailing Main Span

48
Penggunaan BIM Pada Proyek Jembatan Teluk Kendari
Detailing..

BAHTERAMAS BRIDGE - KENDARI PIER P2CAP


CABLE

49
Penggunaan BIM Pada Proyek Jembatan Teluk Kendari
Rebar Detailing..

PIER P2 Rebar
Rebar Detailing
Detailing
-- Quantity
Quantity take
Quantity takeoff
take off
off
-- BBS
BBS
-- Visualitation
Visualitation

50
Penggunaan BIM Pada Proyek Jembatan Teluk Kendari
DESAIN HAMMER PDA

Pembesian Pipa Post Cooling Beton


2044,35 Kg 16,7 m 9.86 m³

Penggunaan software Tekla Structure untuk pemodelan Hammer PDA tes (struktur pendukung), pemodelan yang
dilakukan diantaranya yaitu pembesian, beton dan perletakkan pipa post cooling sekaligus sebagai mock-up

51
Penggunaan BIM Pada Proyek Jembatan Teluk Kendari
Realisasi di lapangan

52
Penggunaan BIM Pada Proyek PP lainnya
Proyek Pelabuhan Sibolga Tahap 1

53
Penggunaan BIM Pada Proyek PP lainnya
Proyek KA Solo-Adisumarno - Elevated

54
Penggunaan BIM Pada Proyek PP lainnya

Box Traffic – Tol Balsam

55
Penggunaan BIM Pada Proyek PP lainnya
Proyek Bendungan - Tender

56
Penggunaan BIM Pada Proyek PP lainnya
Proyek Underpas - Tender
Faster quantity take-off

57