PERHITUNGAN TARIKAN JECK STRESSING

CCSP W500 L. 18 m

Dia Strand 0.500 : 1.27 mm tahap 2 = 50% Kom : 70%


Break Load : 170 kN 9.63
16.683 F = P
Jacking Force : 194.5 kN A
19.26 ton 9628.71 = P
Rencan Tarik : 77% 40.66
Jumlah Strand : 22 P = 236.83 kg/cm2
Tarikan Total : 326.221 ton 241.333 bar
337.866 bar
alat yang tersedia 108
Mono Jack
Kapasitas P : 29 ton tahap 3 = 7% kom: 77%
29000 kg 1.35
Working Press : 700 bar F = P
bar/10.19 : 713.3 kg/cm2 A
P = F 1348.02 = P
A 40.66
P = 33.16 kg/cm2
29000 = 713.3 kg/cm2 33.7866 bar
A 371.653 bar
= 40.6561 cm2

Terhadap Kapasitas Alat 53%


Proses Stressing = Cek 371.653 < 700
Mono jack OK
tahap 1 = 20% Kom : 20% Tahap tarikan Kom. Tarikan Tekanan Kom.Tekanan
3.85 1 20% 20% 96.53 96.53
F = P 2 50% 70% 241.33 337.87
A 3 7% 77% 33.79 371.65
3851.49 = P
40.66
P = 94.73 kg/cm2
96.5332 bar