PERENCANANAA TEMBOK PENAHAN TANAH

Data Perencanaan
Parameter Data Tanah Geometrik Tembok
Jenis Tanah = Tanah Pasir Tinggi Tembok
Berat Isi Tanah Timbun Ys = 19 kN/m3 H = 7.00 m
Sudut geser tanah f = 35 o H1 = 6.20
koef gesekan m = 0.5 H2 = 0.80
Daya dukung izin qa = 150 kPa L1 = 0.40
Mutu Bahan Beton L2 = 1.00
Berat Jenis Beton Yc = 25 kN/m3 L3 = 0.80
Mutu Beton fc = 30 N/mm2 L4 = 2.20
Mutu Baja fy = 460 N/mm2 B = 4.00
Diameter tulangan utama D = 20 mm
Diameter tulangan susut D = 16 mm
Tebal penutup beton d = 40 mm

Beban Tambahan q = 10 kPa

0.4 beban tambahan q = 10 kPa

Data tanah urug


Ys = 19 kN/m3
f = 35 o
d = 0.5
7.00 6.20

0.80
data tanah asli
0.80 Ys = 18 kN/m3
0.4 f = 35 o
1.00 2.20 CU = 20 Kpa

4.00 qa = 150 kPa

Geometri Crossection Tembok Penahan


Perhitungan Kestabilan Tembok
Perhitungan Tekanan Tanah urug dibelakang tembok
Tekanan Tanah Aktif
koefisisen tekanan aktif Rankine Ka= 0.27
akibat beban terbagi rata dan tanah dibelakang tembok
pada kedalaman z=0 Pa 0 = q*Ka = 2.71 kN/m2
pada kedalaman z= 6.20 34.63 kN/m4 pot 1-1
pada kedalaman z= 7.00 38.75 kN/m5

0.4 beban terbagi rata q = kN/m2


Wq

7.00 6.20 Wc2 Ws


Wc1 Pa1
Pa2

1 1

0.80 Wc3

0.80 q*Ka Y*Ka*H


0.4 akibat beban q akibat tanah dibelakang tembok
1.00 2.20 gambar diagram tekanan tanah aktif

4.00

Pehitungan berat tembok dan tanah dibelakang tembok


Pias Berat Arm Momen
1 Wc1 31.00 1.27 39.27
2 Wc2 62.00 1.80 111.60
3 Wc3 80.00 2.00 160.00
4 Ws 259.16 2.90 751.56
5 Wq 22.00 2.90 63.80
6 Pa1 18.97 3.50 66.393
7 Pa2 126.15 2.33 294.34
SV 454.16 SMo 1126.2 Momen Penahan Guling

SPa 145.12 SMr 360.73 Momen Penyebab Guling

a Stabilitas Terhadap Guling


SMo
FG Guling = = 3.12 OK
SMr
b Stabilitas terhadap geseran cd*B+SVtan db= 398.01 kN
cd*B+SVtan db
FG Geser = = 2.74 OK
SPa
c Kestabilan terhadap daya dukung
Momen Penahan SMo = 1126.2
Momen Penggerak= SMr/1.4 257.6664
perhitungan excentrisitas beban e= B/2 - X = x= SM0-SMr/SV= 1.91 m
e = 0.09 m
<B/6= 0.67 m OK tidak ada tegangan negatif

Besarnya distribusi tegangan tanah dibawah tapak


q max =SV/B(1+6e/B) 128.45 kN/m2 < qa, OK 150 kN/m2

q min =SV/B(1-6e/B) 98.63 kN/m2 >0, OK

0.4
WQ

WC2
7.00 6.20 WS
WC1

a b pot a-b
Tekanan tanah setinggi dinding
0.80
a b untuk analisa penulangan tembok
0.80
0.4
1.00 2.20
4.00

qmin= 98.63 kN/m2 ,


qax= 128.45 kN/m2 ,

q2= 115.03 kN/m2 ,


q1= 120.99 kN/m2 , Gambar Distribusi Tegangan Tanah
b
a 2.20
1.00 Wq+Ws 128

Wc 20 Wc 20
148 Wq+Ws+Wc
qmax-Wc 108.45 b 49.17 Wq+Ws+Wc-qmin
qmax-Wc 108.45

a q2+Ws+Wc-qmin= 32.77
q1-Wc= 100.99

analisa bidang D dan Momen pada tapak


akibat tegangan tanah dan berat tembok
PENULANGAN DINDING TEGAK DAN TAPAK PONDASI TEMBOK
Bidang D
Va-a = 1.4 146.61 kN/m tapak depan/toe
Vb-b = 1.4 126.18 kN/m tapak belakang/heel
Va-b = 1.4 162.07 kN/m tekanan setinggi steam

Bidang Momen
Ma-a = 1.4 50.50 + 4.97 = 77.65 kNm tapak depan/toe
Mb-b = 1.4 79.30 + 26.46 = 148.06 kNm tapak belakang/heel
Ma-b = 1.4 52.08 + 204.52 = 359.24 kNm tekanan setinggi steam

PENULANGAN Pada dinding tegak (STEAM)

Mu 359.24 kNm
lebar per m' b= 1000 mm
tinggi slab h= 500 mm
selimut beton d= 40 mm
tulangan diameter f= 20 mm
beugel f= 10 mm
tinggi slab efektif d= 450 mm
Mutu Beton f'c = 30 Mpa
Mutu Baja fy = 460 Mpa
b1 = 0.85
Mu 359.24 kNm
Tebal dinding 450.00
Selimut 40.00
Tinggi efektif 400.00
rb =b*0.85*fc/fy*600/(600+fy) = 0.0267
f = 1.0
Rmax = 0.75*rb*fy*[1-*0.75*rb*fy/(0.85*fc)] = 7.541
Ru = Mn*106/(b*d2 ) = 2.245
Ru < Rmax (OK)
r =fc/fy*[1- {12*Rn/(0.85*fc)}] = 0.0060
rmin = 0.0030
r= 0.0060
As = r*b*d = 2,408.09 mm2
D 22 mm
s = p/4*D2*b/As = 158 mm
smax = 200 mm
s= 158 mm
Tualngan Utama
rencana digunakan tulangan, D 22 - 150
Luas tulangan terpakai, As = p/4*D2*b/s = 2,534.22 mm2
OK As terpakai > As tersedia

Tualngan Susut
Luas Tulangan Susu0.2%*b*h 800.00 mm2
digunakan tulangan D16 - 200
( 1,005 mm2 )
OK As terpakai > As tersedia
Kontrol Geser Gaya V = 162.07 kN/m
v=V/bd = 0.36 N/mm2

Vc =0.79*(100As/bd)^1/3(400/d)^1/4/Ym
100*As/bd = 0.563
Vc = 0.63 N/mm2
Kontrol = OK Vc>V

PENULANGAN Pada tapak depan (TOE)


Mu 77.65 kNm
lebar per m' b= 1000 mm
tinggi slab h= 800 mm
selimut beton d= 40 mm
tulangan diameter f= 20 mm
beugel f= 10 mm
tinggi slab efektif d= 750 mm
Mutu Beton f'c = 30 Mpa
Mutu Baja fy = 460 Mpa
b1 = 0.85
Mu 77.65 kNm
Tebal dinding 750.00
Selimut 40.00
Tinggi efektif 700.00
rb =b*0.85*fc/fy*600/(600+fy) = 0.0267
f = 1.0
Rmax = 0.75*rb*fy*[1-*0.75*rb*fy/(0.85*fc)] = 7.541
Ru = Mn*106/(b*d2 ) = 0.158
Ru < R max (OK)
r =fc/fy*[1- {12*Rn/(0.85*fc)}] = 0.0004
rmin = 0.0030
r= 0.0030
As = r*b*d = 2,130.43 mm2
D 22 mm
s = p/4*D2*b/As = 178 mm
smax = 200 mm
s= 178 mm
Tualngan Utama
rencana digunakan tulangan, D 22 - 170
Luas tulangan terpakai, As = p/4*D *b/s =
2
2,236.07 mm2
OK As terpakai > As tersedia

Tualngan Susut
Luas Tulangan Susu0.2%*b*h 1,400.00 mm2
digunakan tulangan D16 - 200
( 1,005 mm2 )
OK As terpakai > As tersedia

Kontrol Geser Gaya V = 146.61 kN/m


v=V/bd = 0.20 N/mm2

Vc =0.79*(100As/bd)^1/3(400/d)^1/4/Ym
100*As/bd = 0.298
Vc = 0.45 N/mm2
Kontrol = OK Vc>V

PENULANGAN Pada tapak belakang (HEEL)


Mu 148.06 kNm
lebar per m' b= 1000 mm
tinggi slab h= 800 mm
selimut beton d= 40 mm
tulangan diameter f= 20 mm
beugel f= 10 mm
tinggi slab efektif d= 750 mm
Mutu Beton f'c = 30 Mpa
Mutu Baja fy = 460 Mpa
b1 = 0.85
Mu 148.06 kNm
Tebal dinding 750.00
Selimut 40.00
Tinggi efektif 700.00
rb =b*0.85*fc/fy*600/(600+fy) = 0.0267
f = 1.0
Rmax = 0.75*rb*fy*[1-*0.75*rb*fy/(0.85*fc)] = 7.541
Ru = Mn*106/(b*d2 ) = 0.302
Ru < Rmax (OK)
r =fc/fy*[1- {12*Rn/(0.85*fc)}] = 0.0008
rmin = 0.0030
r= 0.0030
As = r*b*d = 2,130.43 mm2
D 22 mm
s = p/4*D2*b/As = 178 mm
smax = 200 mm
s= 178 mm
Tualngan Utama
rencana digunakan tulangan, D 22 - 170
Luas tulangan terpakai, As = p/4*D2*b/s = 2,236.07 mm2
OK As terpakai > As tersedia

Tualngan Susut
Luas Tulangan Susu0.2%*b*h 1,400.00 mm2
digunakan tulangan D16 - 200
( 1,005 mm2 )
OK As terpakai > As tersedia
Kontrol Geser
Gaya V = 126.18 kN/m
v=V/bd = 0.168 N/mm2

Vc =0.79*(100As/bd)^1/3(400/d)^1/4/Ym
100*As/bd = 0.298
Vc = 0.45 N/mm2
Kontrol = OK Vc>V

Penulangan Retaining Wall

D 22 - 150
tul utama STEAM
D D16 - 200
tul susut
tul susut
D 14 - 150 D 22 - 170
D 22 - 170 tul utama HEEL
tul utama TOE D 14 - 100
tul susut
DATA PERENCANAAN TEKNINS RETAINING WALL

DIMENSI KONSTRUKSI
H1 = 6.2 m
T1 beban hidup, q H2 = 0.8 m
10 kN/m2 H tot = 7.0 m
T1 = 0.4 m
T2 = 0.4 m
T3 = 1.0 m
T4 = 2.2 m
B = 4.0 m
PARAMETER TANAH
H1 TANAH TIMBUN
H tot Y1 = 19 t/m3
f1 = 35 derajat
C1 = t/m2

H2
PARAMETER TANAH
TANAH ASLI
T3 T2 T1 T4 Y2 = 18 t/m3
f2 = 30 derajat
B C2 = 20 t/m2
TEKANAN TANAH
TEGANGAN TANAH koef tekanan tanah aktif
p1 = 2.71
p2 = 36.04 Spah = 0,5*H^2*Yb*Ka + q*H*Ka

TEKANAN TANAH AKTIF


Tekanan Tanah Aktif Total, Pa Jarak dari O Momen ke O
(kN) (m) (kNm)
Pa1 = 18.9693 3.50 66.393
Pa2 = 126.146 2.33 294.340
145.115 360.733
GAYA VERTIKAL DAN MOMEN AKIBAT BEBAN MATI
NO Berat, W, kN Jarak dari O, m Momen , kNm
1 62.00 1.60 99.20
2 31.00 1.27 39.27
3 80.00 2.00 160.00
4 259.16 2.90 751.56
q 22.00 2.90 63.80
SW 454.16 SM 1113.83
STABILITAS TERHADAP PENGGESERAN
db = f cd = c2 Rh = cd*B + Swtandb 342.209 kN/m

342.209
FK trhdp geser SRh/SPh = = 2.35819
145.115 >1,5, OK

STABILITAS TERHADAP GULING


1113.83
FK trhdp guling SMw/SMgl = 3.08769
360.733 >1,5, OK

STABILITAS TERHADAP DAYA DUKUNG TANAH PONDASI


Tegangan Kontak Di Bawah Tapak
e = B/2 - X 0.34 m <B/6, OK 0.67
X = (Mo-Mr/V) 1.66 m

q max = (SV/B)*(1+6e/B) 171.748 t/m2


q min = (SV/B)*(1-6e/B) 55.3317 t/m2
terjadi tegangan yang merata di sepanjang tapak

A= B'*1 m 3.3 m

DAYA DUKUNG ULTIMIT DIHITUNG DENGAN PERSAMAAN HANSEN

Q ult c*Nc*Sc*Dc*ic + q*Nq*Sq*Dq*iq+0,5*Y*NY*SY*DY*iY


karena pondasi diletakkan di atas permukaan tanah, maka faktor kedalaman dc=dq=Dy =1
demikian juga faktor bentuk, Sc=Sq=SY =1

maka persamaan mmenjadi , qult = c*Nc*ic + 0,5*Y*Ny*iY

kator inclinasi
^0,5
0,5*H
ic = 1 - =
V + A'*ca*cot f
ic =iq (1-(0.5*E36)/(G44+G65*U25*TANH(U24)))^5

^0,5
0,7*H
icY = 1 - =
V + A'*ca*cot f
0.3
dari tabel diperoleh, Nc = 33.30
Nq = 46.12
NY = 48.03

maka q ultimit 314.361 + 0 = 511.0237 = 825.384 kN/m2

FK daya dukung = Qult/q maks 4.81 >3, OK


Htot = 7.0 m

t/m3 Pa1
derajat
t/m2
Pa2

Y2

t/m3
derajat
t/m2

= 0.27099
= 0.472

G65*U25*TANH(U24)))^5

= 0.338
- 100