Anda di halaman 1dari 1

PERENCANAAN GEDUNG MA'HAD ALY STAIN BATU SANGKAR

TAHUN 2015

1 Biaya Perencanaan Upah Kerja (15%) Total


Rp133,432,000.00 Rp20,014,800.00 Rp20,014,800.00

2 Pinjaman
Rp12,500,000.00 Rp12,500,000.00
Sisa Yang Harus Dibayarkan Rp7,514,800.00

PERECANAAN IGD ADNAAN WD PAYAKUMBUH

1 Biaya Perencanaan Upah Kerja (30%) Total


Rp126,468,000.00 Rp37,940,400.00 Rp37,940,400.00

2 Pinjaman
Rp5,500,000.00 Rp5,500,000.00
Total Rp32,440,400.00
Retensi (20%) Rp6,488,080.00
Sisa Yang Harus Dibayarkan Rp25,952,320.00

REKAPITULASI
YANG HARUS DIBAYARKAN

No Pekerjaaan Jumlah Total


1 Ma'ad Aly BT Sangkar Rp7,514,800.00 Rp7,514,800.00

2 IGD Adnaan Wd Payakumbu Rp25,952,320.00 Rp25,952,320.00

Total Rp33,467,120.00
Total Yang Harus DibayarkanRp33,467,120.00