REKAPITULASI

NO

TOTAL BIAYA

URAIAN

(Rp)

BIAYA LANGSUNG PERSONIL

76,902,875.00

II

BIAYA LANGSUNG NON PERSONIL

78,918,000.00
155,820,875.00

JUMLAH

15,582,087.50

PPN 10 %
TOTAL

171,402,962.50

DIBULATKAN

171,400,000.00

TERBILANG :

Manado,
PT.

2012

PEKERJAAN

PERENCANAAN RUAS JALAN TAMAKO - ENEMAWIRA

TAHUN ANGGARAN

2012

BIAYA LANGSUNG PERSONIL


No.
I

Uraian
PROFESIONAL STAF
a. Team Leader / Ahli Jembatan
e. Ahli Survey dan Pengukuran
f. Ahli Estimasi Kuantitas Biaya
Sub Jumlah

III SUPORTING STAFF


a. Administrasi
b. Juru gambar / Drafter
c. Surveyor
d. Operator Komputer
Sub Jumlah
JUMLAH BIAYA LANGSUNG PERSONIL

Satuan

Biaya Satuan
(Rp)

Vol

OB
OB
OB

1
1
1

x 2.00
x 0.50
x 1.00

OB
OB
OB
OB

1
1
2
1

x
x
x
x

2.00
1.00
0.50
2.00

Jumlah Biaya
(Rp)

13,425,000.00
11,948,250.00
11,948,250.00

26,850,000.00
5,974,125.00
11,948,250.00
44,772,375.00

6,175,500.00
6,444,000.00
5,996,500.00
3,669,500.00

12,351,000.00
6,444,000.00
5,996,500.00
7,339,000.00
32,130,500.00
76,902,875.00

BIAYA LANGSUNG NON PERSONIL


No.
1

Uraian

Satuan

Volume

OPERASIONAL KANTOR
ANALISA DATA, DRAWING, COST & QUANTITY
1. Komputer + Printer (Sewa)
Set/Bln
2. ATK dan Bahan Habis Pakai
Bln
Sub Jumlah

x 2.00
2.00

BIAYA PERJALANAN DINAS


a. Perjalanan Tenaga Ahli
c. Perjalanan Supporting Staff
Sub Jumlah

3
2

x
x

BIAYA LAPORAN
Kontrak Perencanaan
Laporan Perencanaan
Gambar Rencana Uk. A3
Dokumen Tender (RKS, EE, BOQ)
Disket / CD
Sub Jumlah

Org/Trip
Org/Trip

Set
Set
Set
Set
Buah

BIAYA TRANSPORTASI & SEWA KENDARAAN


Sewa Kendaraan Roda 4
Buah/bulan
Sewa Kendaraan Roda 2
Buah/bulan
Sub Jumlah

1
1

Harga Satuan
(Rp)

Jumlah Harga
(Rp)

1,611,000.00
2,148,000.00

3,222,000.00
4,296,000.00
7,518,000.00

4
4

150,000.00
150,000.00

1,800,000.00
1,200,000.00
3,000,000.00

5
5
5
5
10

1,250,000.00
300,000.00
250,000.00
250,000.00
50,000.00

6,250,000.00
1,500,000.00
1,250,000.00
1,250,000.00
500,000.00
10,750,000.00

7,500,000.00
1,450,000.00

7,500,000.00
2,900,000.00
10,400,000.00

7,500,000.00
3,500,000.00
750,000.00
5,000,000.00
2,500,000.00
500,000.00
500,000.00
1,000,000.00

7,500,000.00
3,500,000.00
750,000.00
30,000,000.00
2,500,000.00
3,000,000.00

x 1.00
x 2.00

BIAYA PENYELIDIKAN TANAH


a. Mobilisasi
LS
b. Pengukuran Lahan & Kontur
LS
c. Penggambaran
LS
d. Sondir
Ttk
e. Soil Test (SPT)
Ttk
d. Pengambilan Sampel & Penyelidikan Laboratorium
Test
e. Laporan & Rekomendasi
LS
e. Perlengkapan Lapangan
LS
Sub Jumlah

JUMLAH BIAYA LANGSUNG NON PERSONIL

1
1
1
6
1
6
1
1

47,250,000.00
78,918,000.00