NAMA PAKET : Pembangunan Jembatan Kuranji Bypass

PROP / KAB / KODYA : Sumatera Barat / Padang

Durasi Perkiraan Harga Satuan


No. Uraian Satuan Jumlah Harga
(hari) Kuantitas (Rupiah)

a b c d e f = (d x

Div. 1 UMUM
1.1 Mobilisasi dan Demobilisasi Ls 9 1.00 1,384,125,000.00
1.2 Manajemen dan Safety Ls 192 1.00 28,250,000.00

Div. 3 PEKERJAAN TANAH


3.1 Galian Biasa m3 1 Err:509 Err:509
3.2 Galian Struktur Kedalaman 0 - 2 meter m3 1 Err:509 Err:509
3.3 Galian Struktur Kedalaman 2 - 4 meter m3 1 Err:509 Err:509
3.4 Timbunan Biasa m3 1 Err:509 Err:509
3.5 Timbunan Pilihan m3 2 Err:509 Err:509

Div. 5 PEKERJAAN BERBUTIR


5.1 Lapis Fondasi Agregat Kelas A m3 1 Err:509 Err:509
5.2 Lapis Fondasi Agregat Kelas B m3 1 Err:509 Err:509

Div. 6 PEKERJAAN PERKERASAN ASPAL


6.1 Lapis Resap Pengikat (Prime Coat) Liter 1 Err:509 Err:509
6.2 Lapis Pengikat (Tack Coat) Liter 2 142.24 14,936.96
6.3 Asphaltic Concrete - Wearing Course (AC-WC) Ton 1 41.43 1,500,113.38
6.4 Asphaltic Concrete - Binder Course (AC-BC) Ton 1 Err:509 Err:509
6.5 Asphaltic Concrete - Base (AC-Base) Ton 1 Err:509 Err:509
6.6 Bahan Anti Pengelupasan Liter 3 6.70 75,000.00

Div. 7 PEKERJAAN STRUKTUR


7.1 Beton Struktur dengan fc' 30 Mpa Kekuatan K-350 m3 23 1359.79 2,461,961.60
a. Pekerjaan Abutment m3 4 251.00
b. Pekerjaan Pier m3 7 439.00
c. Pekerjaan Approach Slab m3 1 28.50
d. Pekerjaan Lantai Jembatan m3 8 498.96
e. Pekerjaan Sandaran Jembatan m3 3 142.33
7.2 Beton Struktur dengan fc' 25 Mpa Kekuatan K-175 m3 1 47.52 Err:509
7.3 Beton Struktur dengan fc' 10 Mpa Kekuatan K-125 m3 3 18.80 Err:509
a. Lantai Kerja Abutment m3 1
b. Lantai Kerja Pier m3 1
c. Lantai Kerja Approach Slab m3 1
7.4 Unit Pracetak Gelagar I Bentang 40 meter Balok I.210-40 Unit 16 12.00 Err:509
a. Pengadaan Girder I bentang 40 meter Unit 14
b Pemasangan Girder I bentang 40 meter Unit 2
7.5 Unit Pracetak Gelagar I Bentang 50 meter Balok I.210-50 Unit 7 7.00 499,324,940.86
a. Pengadaan Girder I bentang 50 meter Unit 6
b. Pemasangan Girder I bentang 50 meter Unit 1
7.6 Edge dan Midle Diafragm Span :40 Meter (I Girder) Unit 5 70.00 Err:509
7.7 Edge dan Midle Diafragm Span :50 Meter (I Girder) Unit 4 54.00 Err:509
7.8 Slab Deck Span : 40 Meter Unit 11 410.00 551,088.79
7.9 Slab Deck Span : 50 Meter Unit 8 306.00 Err:509
7.10 Baja Tulangan BJ 39 Ulir Kg 73 142227.57 22,088.88
a. Pekerjaan Abutment Kg 15 28417.49
b. Pekerjaan Pier Kg 21 41441.67
c. Pekerjaan Approach Slab Kg 2 3582.35
d. Pekerjaan Lantai Jembatan Kg 26 51110.95
e. Pekerjaan Sandaran Jembatan Kg 9 17675.11
7.11 Fondasi Bor Pile Diameter 1000 mm m 49 600.00 Err:509
7.12 Expantion Joint Tipe Asphaltig Plug m 3 32.00 1,858,648.42
7.13 Bearing Pad (Elastomer) Unit 2 38.00 1,632,145.57

Div. 8 PEKERJAAN RINGAN


8.1 Marka Jalan Tipe Termoplastis m2 1 64.84 563,235.81
8.2 Kereb Pracetak Unit 3 220.00 236,915.49
Total
Rencana Bobot Kumulatif
Komulatif Rencana Harian
Realisasi Bobot Harian
Komulatif Realisasi
1

Jumlah Harga (Rupiah) Bobot (%)


0.9

f = (d x e) 1 2 3 4 5 6 7 8 9 10 11

1,384,125,000.00 Err:509 Err:509 Err:509 Err:509


28,250,000.00 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
0.8

Err:509 Err:509 Err:509


Err:509 Err:509 Err:509
Err:509 Err:509 Err:509
Err:509 Err:509
Err:509 Err:509
0.7

Err:509 Err:509
Err:509 Err:509

Err:509 Err:509
0.6
2,124,633.68 Err:509
62,145,797.12 Err:509
Err:509 Err:509
0.6

Err:509 Err:509
502,611.84 Err:509

0.5
3,347,750,761.08 Err:509

Err:509 0.4
Err:509
Err:509 Err:509

Err:509 Err:509
0.3

3,495,274,586.03 Err:509

Err:509 Err:509
Err:509 Err:509
225,946,401.87 Err:509
0.2
Err:509 Err:509
3,141,647,726.42 Err:509

0.1
0.1
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
59,476,749.43 Err:509
62,021,531.52 Err:509

36,518,801.86 Err:509
52,121,408.58 Err:509
0
Err:509 Err:509 0
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
42 43 44 45 46 47 48 49 50 51 52 53 54 55 56

Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509
Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

50
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
57 58 59 60 61 62 63 64 65 66 67 68 69 70 71

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
72 73 74 75 76 77 78 79 80 81 82 83 84 85 86

Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509


Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
HARI KE-

87 88 89 90 91 92 93 94 95 96 97 98 99 100 101

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509
Err:509 Err:509

Err:509
Err:509
Err:509

Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509

Err:509 Err:509
100
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
102 103 104 105 106 107 108 109 110 111 112 113 114 115 116

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509


Err:509
Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
00
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
117 118 119 120 121 122 123 124 125 126 127 128 129 130 131

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
132 133 134 135 136 137 138 139 140 141 142 143 144 145 146

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
147 148 149 150 151 152 153 154 155 156 157 158 159 160 161

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

150
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
162 163 164 165 166 167 168 169 170 171 172 173 174 175 176

Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509
Err:509 Err:509

Err:509
Err:509
Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509


Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
177 178 179 180 181 182 183 184 185 186 187 188 189 190 191

Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509

Err:509
Err:509

Err:509 Err:509 Err:509


Err:509
Err:509 Err:509 Err:509 Err:509

Err:509 Err:509 Err:509

Err:509
Err:509 Err:509 Err:509

Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
KETERANGAN

192

100
Err:509
Err:509

90

80

70
70

60

50

40

30

20
10

0
200
Err:509
Err:509
No Item Pekerjaan Uraian

5. pekerjaan struktur
5.1 beton k-350 Perhitungan volume Plat Lantai
plat lantai dan trotoar Plat Lantai 1
- panjang plat lantai 35 m
350 100 7000 100 350
- lebar plat lantai 7.6 m
- tinggi plat lantai 0.2 m
Volume Plat = 53.2 m3

Volume Total Plat Lantai = 53.2 m3

Perhitungan Volume Trotoar


- panjang trotoar = 35 m
- lebar trotoar = 0.5 m
- tinggi trotoar = 0.2 m
Volume Trotoar = 3.5 m3
1850 1850 1850 1850

Concrete Barrier

500 350 panjang bentang 1 =


Luas total =
Volume concrete barrier (kiri) = Luas total x panjang =
Volume concrete barrier total (kiri-kanan) =
500
180 50 200
500 350

500
250 180 50 200
panjang bentang 2 =
Luas total =
Volume concrete barrier (kiri) = Luas total x panjang =
Volume concrete barrier total (kiri-kanan) =

No Item Pekerjaan Uraian

Diafrgama

Dimensi Span Span Jumlah Dimensi


(m) (n) (bh) P
35 1 20 1.65

Volume Total
diafragma 20 buah

Dimensi Span Span Jumlah Dimensi

(m) (n) (bh) P


15.8 2 12 1.68

Volume Total
diafragma 12 buah
Detail Diafragma untuk Span 35 dan 15,8 m
No
Item Pekerjaan Uraian

5.2 Pengadaan I Girder Kebutuhan I Girder untuk Span 35 m = 5

5.2 Pengadaan I Girder Kebutuhan I Girder untuk Span 15,8 m = 5

: 5.9a.Pengadaan Bearing Pad

Kebutuhan bearing pad di Abutment = 5


Kebutuhan bearing pad di Pier = 5
Kebutuhan total bearing pad pada konstruksi jembatan adalah =

Bearing Pad Plan pada Pier

: 5.8. Pengadaan Expansion Joint (Asphaltig Plug) Kebutuhan Expnasion Joint


- sambungan pada pembangunan jembatan =
- panjang expansion join pada tiap sambungan =
Kebutuhan total expansion joint =
Detail Expansion Joint Tipe Asphaltig Plug

No
Item Pekerjaan Uraian

: 5.6. Baja Tulangan BJ 39 Ulir Perhitungan Penulangan Plat Lantai span 1

tulangan atas D16-250 tulangan atas D16-250 tulangan atas D16-250 tulangan atas D16-250 tulangan atas D16-250

tulangan bagi D 16-250

tulangan atas D16-100 tulangan atas D16-100 tulangan atas D16-100 tulangan atas D16-100 tulangan atas D16-100

tulangan pokok D 16-100

Slab Detail (Span 35 meter)


Kode Type DIA Ukuran

(mm) a b c
S1 16 9200 15 8
S2 16 900 15 8
S3 16 34500 39 15
S4 16 34500 39 15
S5 10 15 5 -

Slab Detail besi D16


besi D10
No
Item Pekerjaan Uraian

Baja Tulangan BJ 39 Ulir Perhitungan Penulangan Plat Lantai 2

tulangan atas D16-250 tulangan atas D16-250 tulangan atas D16-250 tulangan atas D16-250 tulangan atas D16-250

tulangan bagi D 16-250

tulangan atas D16-100 tulangan atas D16-100 tulangan atas D16-100 tulangan atas D16-100 tulangan atas D16-100

tulangan pokok D 16-100

Slab Detail (Span 35 meter)

Kode Type DIA Ukuran

(mm) a b c
S1 16 9200 15 8
S2 16 900 15 8
S3 16 15300 39 15
S4 16 15300 39 15
S5 10 15 5 -

Slab Detail besi D16


besi D10

No
Item Pekerjaan Uraian

Concrete railing Perhitungan Penulangan Concrete Barrier span 1

Plat Baja T 25 mm Kode Type DIA Ukuran (cm)

Pipa C.7 63 cm
Plat Baja T 25 mm

(mm) a b c
S6 10 48 39 20
Pipa C.7 63 cm S7 10 45 30 6.5
S8 13 15 5
S9 10 20 5 -
Plat Baja T 25 mm
S10 13 3450 39 15

D 10 200/ 450
S9
Total Penulangan Concrete B
D 13 100
S6
D 10 250
Total Penulangan Concrete Barr
S8 D 13 200
S10

D 13 100
S7

Concrete railing Perhitungan Penulangan Concrete Barrier span 1

Plat Baja T 25 mm Kode Type DIA Ukuran (cm)

(mm) a b c
S6 10 48 39 20
S7 10 45 30 6.5
Pipa C.7 63 cm
S8 13 15 5
S9 10 20 5 -
Plat Baja T 25 mm S10 13 3450 39 15

D 10 200/ 450
S9
D 13 100
S6
D 10 250
S8 D 13 200
S10
Pipa C.7 63 cm

Plat Baja T 25 mm

D 10 200/ 450
Total Penulangan Concrete B
S9
D 13 100
Total Penulangan Concrete Barr
S6
D 10 250
S8 D 13 200
S10

D 13 100
S7

Item
No Pekerjaan Uraian

Diafragma Perhitungan Penulangan Diafragma span 1


Kode Type DIA Ukuran

(mm) a b c
lebar
1,6 m A1 13 1750 30 30
A2 13 1500 150 30

Total Penulangan 1 Diaf


tulangan diafragma Total Penulangan 20 Dia

Perhitungan Penulangan Diafragma span 2

Kode Type DIA Ukuran

(mm) a b c
lebar
1,6 m A1 13 1750 5 5
A2 13 700 700 15
Total Penulangan 1 Diaf
Total Penulangan 20 Dia

tulangan diafragma

No
Item Pekerjaan Uraian

6 Pekerjaan Pengembalian Kondisi dan Minor


6.1 Pekerjaan Kereb Jalan Perhitungan Volume 1 Kereb Jalan

- panjang = 60 cm
- lebar alas = 25 cm
- lebar atas = 18 cm
- tinggi = 30 cm

"Volume Kereb = " "(Lebar Alas + Lebar Atas)" /"2" "× tinggi × panjang"

"= " "(25 + 18)" /"2" " × 30 × 60"

= 38700 cm3
TAMPAK DEPAN TAMPAK SAMPING
= 0.0387 m3 (Volume 1 Unit)

Detail Kereb Volume Pekerjaan Kereb Jalan Mutu Beton K-300 adalah
6.2 Pekerjaan Marka Jalan Perhitungan Volume Marka Jalan

Untuk Garis Putus- Putus

7 meter - panjang jalan = 50.4 m


- lebar marka = 0.15 m
- panjang marka = 3m
- spasi antar marka = 5m
- perbandingan = 3/8 m

Panjang Total Marka = 18.9 meter


Kuantitas Pekerjaan = 10.24 m2

182 meter
Jadi total volume pekerjaan marka jalan adalah

Detail Marka Jalan


No
Item Pekerjaan Uraian

Perhitungan jumla
bentang 1
5.5a Slab Deck Span : 35 Meter
Ukuran Panjang : = 1 meter
lebar : = 1.25 meter
tebal : = 0.2 meter

panjang bentang : = 35 meter


jumlah deck slap : = 140 buah

Perhitungan jumla
bentang 1
5.5b. : Slab Deck Span : 15,8 Meter
Ukuran Panjang : = 1 meter
lebar : = 1.25 meter
tebal : = 0.2 meter

panjang bentang : = 15.8 meter


jumlah deck slap : = 63.2 buah

6. Deck Slab Perhitungan Penulan

b
a
b
a

Kode Type DIA Ukuran


100

(mm) a b c
Span
25,4 m A 10 1150 30 30
A 8 950 30 30
B 8 80 240 80
Total Penulangan 1 Deck Slab unt
Total Penulangan 75 Deck Slab un

120
Uraian Kuantitas Satuan

Plat Lantai 2
- panjang plat lantai 15.8 m
- lebar plat lantai 7.6 m
- tinggi plat lantai 0.2 m
Volume Plat = 24.016 m3

Volume Total Plat Lantai = 24.016 m3

Perhitungan Volume Trotoar


- panjang trotoar = 15.8 m
- lebar trotoar = 0.5 m
- tinggi trotoar = 0.2 m
Volume Trotoar = 1.58 m3
TOTAL 82.296 m3

35 m
0.19375 m2 (area by AutoCad)
6.78125 m3
13.5625 m3
15.8 m
0.19375 m2 (area by AutoCad)
3.06125 m3
6.1225 m3

TOTAL 19.685 m3

Uraian Kuantitas Satuan

luas jajar
luas jajar
Luas genjang
genjang Total Luas Tebal Volume
atas
L (m2) Atas Bawah (m2) (m) (m3)
0.88 1.452 0.162 0.3375 1.9515 0.2 0.3903

0.3903
7.806

luas jajar
luas jajar
Luas genjang
genjang Total Luas Tebal Volume
atas

L (m2) Atas Bawah (m2) (m) (m3)


0.53 0.8904 0.1272 0.159 1.1766 0.2 0.23532

0.23532
2.82384

TOTAL 2 10.62984 m3
Kuantitas Satuan
Uraian

buah (1 Span) 5 Girder

buah (1 Span) 5 Girder

buah
buah
mbatan adalah = 20 buah

TOTAL 38 buah

3 buah
7 meter
21 meter
TOTAL 21 m

Kuantitas Satuan
Uraian
Panjang Berat Per Jumlah Berat
Total Meter Potongan Total
d e f g (m) (kg/m') (buah) (kg)
92.39 1.044 351 33855.8
9.39 1.044 351 3440.91
345.7 1.044 39 14219.9
345.7 1.044 39 14219.9
0.3 0.618 351 65.0754

besi D16 65736.44136


besi D10 65.0754
TOTAL 131603.03 kg
Kuantitas Satuan
Uraian

Panjang Berat Per Jumlah Berat


Total Meter Potongan Total
d e f g (m) (kg/m') (buah) (kg)
92.39 1.044 159 15336.4
9.39 1.044 159 1558.7
153.7 1.044 39 6322.23
153.7 1.044 39 6322.23
0.3 0.618 159 29.4786

besi D16 29539.54152


besi D10 29.4786
TOTAL 59138.04 kg

Kuantitas Satuan
Uraian

an 1

Panjang Berat Per Jumlah Berat


Ukuran (cm)
Total Meter Potongan Total
d e f g (m) (kg/m') (buah) (kg)
15 5 64 1.91 0.618 351 414.313
0.815 0.618 351 176.788
0.2 1.044 1404 293.155
0.25 0.618 176 27.192
35.04 1.044 11 402.399

Total Penulangan Concrete Barrier Kiri 1313.85


tal Penulangan Concrete Barrier Kiri - Kanan 2627.7

TOTAL 5255.39244 kg
an 1

Panjang Berat Per Jumlah Berat


Ukuran (cm)
Total Meter Potongan Total
d e f g (m) (kg/m') (buah) (kg)
15 5 64 1.91 0.618 159 187.68
0.815 0.618 159 80.0835
0.2 1.044 636 132.797
0.25 0.618 80 12.36
35.04 1.044 11 402.399
Total Penulangan Concrete Barrier Kiri 815.32
tal Penulangan Concrete Barrier Kiri - Kanan 1630.64

TOTAL 3261.28044 kg

Kuantitas Satuan
Panjang Berat Per Jumlah Berat
Total Meter Potongan Total
d e f g (mm) (kg/m') (buah) (kg)
- - - 1810 1.04 8 15.0798
30 - - 1710 1.04 10 17.8083

Total Penulangan 1 Diafragma 32.8881


Total Penulangan 20 Diafragma 657.761
657.761
TOTAL 657.76103 kg

Panjang Berat Per Jumlah Berat


Total Meter Potongan Total
d e f g (mm) (kg/m') (buah) (kg)
- - - 1760 1.04 8 14.6632
15 - - 1430 1.04 10 14.8923
Total Penulangan 1 Diafragma 29.5555
Total Penulangan 20 Diafragma 591.11
591.11

TOTAL 591.110134 kg
Kuantitas Satuan
Uraian

Kebutuhan Kereb untuk Jembatan (unit)

- panjang jembatan = 50.4 m


- lebar kereb = 0.6 m
Kebutuhan Kereb = 84 unit

/"2" "× tinggi × panjang"

(Volume 1 Unit)

3.2508 m3

TOTAL 3.2508 m3
Untuk Garis Tepi

- panjang jalan = 50 m
- lebar marka = 0.15 m

Panjang Total Marka 7.5 meter


Kuantitas Pekerjaan 2 Sisi = 15 m2

25.24 m2

TOTAL 25.24 m2
Kuantitas Satuan
Uraian

Perhitungan jumlah Deck Slab

total 140 buah


Perhitungan jumlah Deck Slab
total 63.2 buah

Perhitungan Penulangan Deck Slab

b c
a c
a
b

b c
a c
a

Panjang Berat Per Jumlah Berat


Total Meter Potongan Total
d e f g (mm) (kg/m') (buah) (kg)
1210 0.62 6 4.47379
1010 0.39 6 2.38997
400 0.39 1 0.15775
tal Penulangan 1 Deck Slab untuk Span 25,4 m 7.02151
tal Penulangan 75 Deck Slab untuk Span 25,4 m 526.614

total 1053.22712 kg
Tabel 3.1 Perhitungan Kuantitas Pekerjaan

NO Item Pekerjaan Uraian Kuantitas Satuan

4 Perkerasan Beraspal
4.2. Tack Coat
7 meter

Pemakaian per meter luas (H) 0.4 liter


Panjang Jalan (P) 50.8 meter
Lebar jalan (L) 7 meter
Volume = P x L x H 142.24 Liter TOTAL 142.24 Liter

Catatan : Pemakaian permeter luas (H) diperoleh dari Spesifikasi Umum 2010

182 meter
4.3. AC-WC (Asphaltic Concrete Wearing Couse)

7m
Panjang Jalan (P) 50.8 meter
Tebal Hamparan (T) 0.05 meter
Lebar (L) 7 meter
BJ Hotmix 2.33 Ton/m3
Volume (V) = P x L x T 17.78 m3
Volume = V x BJ Hotmix 41.43 Ton
TOTAL 41.43 Ton
0.04 m
NO Kuantitas Satuan
Item Pekerjaan Uraian

4.6. Aspal Semen Komposisi Aspal Pada AC - WC (asp1) 5.5 %


Komposisi Aspal Pada AC - BC (asp2) 5.1 %
Komposisi Aspal Pada AC - Base (asp3) 4.5 %
Volume AC - WC 41.43 Ton

Kuantitas
Pada AC -WC = asp1 x Volume AC- WC) 2.279 Ton 2.279 Ton

TOTAL 2.279 0

4.7. Filler / Bahan Pengisi


Komposisi Pemakaian Dalam 1 Ton Hotmix Pada :
AC - WC 2% Volume AC -WC (V1) 41.43 Ton

Kuantitas
Pada AC - WC = AC - WC * V1 0.829 Ton 0.829 Ton

828.548 Liter

4.8. Bahan Adiktif Anti Pengelupasan


Komposisi Campuan (K) 0.3 % dari Berat Aspal BJ Aspal 1.02
Berat Aspal Total Yang dibutuhkan (Tasp) 2.28 Ton
Kuantitas Anti Striping = (K*Tasp)/BJ Aspal*1000 7 Liter TOTAL 7 Liter
NO Kuantitas Satuan
Item Pekerjaan Uraian

4.6 Bahan Adiktif Anti Pengelupasan Komposisi Aspal Pada AC - WC (asp1) 5.5 %
Komposisi Aspal Pada AC - BC (asp2) 5.1 %
Komposisi Aspal Pada AC - Base (asp3) 4.5 %
Volume AC - WC 41.43 Ton

Kuantitas
Pada AC -WC = asp1 x Volume AC- WC) 2.279 Ton 2.279 Ton

TOTAL 2.279 0

Komposisi Campuan (K) 0.3 % dari Berat Aspal BJ Aspal 1.02


Berat Aspal Total Yang dibutuhkan (Tasp) 2.28 Ton
Kuantitas Anti Striping = (K*Tasp)*BJ Aspal 7 Liter TOTAL 7 Liter
3.4 Rencana Anggaran Pelaksanaan
Dari perhitungan volume dan analisa harga satuan pekerjaan diperoleh Biaya Anggaran Pelaksanaan struktur atas yang
direncanakan dengan 2 bentang.

Tabel 3.5 Rekap Rencana Anggaran Biaya Pelaksanaan

NO. ITEM PEKERJAAN SATUAN KUANTITAS HARGA SATUAN TOTAL BIAYA

1 PERKERJAAN PENDAHULUAN
: 1.1. : Mobilisasi/Demobilisasi : Ls 1.00 1,384,125,000.00 1,384,125,000.00
: 1.2. : Manajemen dan Safety : Ls 1.00 28,250,000.00 28,250,000.00

4 PEKERJAAN PERKERASAN ASPAL


: 4.2. : Lapis Pengikat (Tack Coat) : Liter 142.24 14,936.96 2,124,633.68
: 4.3. : Asphaltic Concrete - Wearing Course (AC-WC)(Fine/Coarse) : Ton 41.43 1,500,113.38 62,145,797.12
: 4.7. : Bahan Anti Pengelupasan : Liter 6.70 75,000.00 502,611.84

5 PEKERJAAN STRUKTUR
: 5.1. : Beton Struktur dengan fc' 30 Mpa Kekuatan K-350 : m3 112.61 2,461,961.60 277,243,563.58
5.3a. : Unit Pracetak Gelagar I Bentang 15,8 meter Balok I.90-15,8 : Unit 5.00 242,513,480.26 1,212,567,401.32
: 5.3b. : Unit Pracetak Gelagar I Bentang 35 meter Balok I.210-35 : Unit 5.00 499,324,940.86 2,496,624,704.31
: 5.4a. : Diafragma span 35 meter : Buah 20.00 2,594,403.50 51,888,070.00
:5.4b. : Diafragma span 15.8 meter : Buah 12.00 2,328,548.12 27,942,577.41
: 5.5a. : Slab Deck Span : 35 Meter : Unit 140.00 551,088.79 77,152,429.91
: 5.5b. : Slab Deck Span : 15,8 Meter : Unit 63 551,088.79 34,828,811.22
: 5.6. : Baja Tulangan BJ 39 Ulir : Kg 200,506.62 22,088.88 4,428,966,619.87
: 5.8. : Expantion Joint Tipe Asphaltig Plug : m' 21.00 1,858,648.42 39,031,616.82
: 5.9a. : Bearing Pad (Elastomer) : Unit 38.00 1,632,145.57 62,021,531.52

6 PEKERJAAN RINGAN
: 6.1. : Marka Jalan Tipe Termoplastis : m2 25.24 563,235.81 14,216,071.86
: 6.2. : Kereb Pra Cetak Tipe 4 : Unit 84.00 236,915.49 19,900,901.46

TOTAL BIAYA KESELURUHAN 10,219,532,341.90


ITEM PEMBAYARAN NO. : 1.1.
JENIS PEKERJAAN : Mobilisasi/Demobilisasi

No. U RAIAN SATUAN VOL.

A. Sewa Tanah M2 500

B. PERALATAN
Periksa lembar 1.2-2

C. FASILITAS KONTRAKTOR
1 Base Camp M2 100
2 Kantor M2 80
3 Barak M2 60
4 Bengkel M2 60
5 Gudang, dan lain-lain M2 40
6 ...................... ....

D. FASILITAS LABORATORIUM
1 Ruang Laboratorium (sesuai Gambar) M2 60

2 Soil & Aggregate Testing


Compaction Test Set 1.00
CBR Test Set 1.00
Specific Gravity Set 1.00
Atterberg Limits Set 1.00
Grain Size Analysis Set 1.00
Field Density Test by Sand Cone Methode Set 1.00
Moisture Content Set 1.00
Abrasion of Aggregate by Los Angeles Machine Bln 1.00

3 Bituminous Testing
Marshall Asphalt Test Set 1.00
Specific Gravity for Coarse Aggregate Set 1.00
Specific Gravity for Fine Aggregate Set 1.00
Core Drill Set 1.00
Penetration Test Bln 1.00

4 Concrete Testing
Slump Cone Set 1.00
Cylinder/Cube Mould for Compressive Strength Set 1.00

5 Pendukung
(Sewa Mobil Pick Up ,Beli Komputer + Printer 1 set)
6 Operasional
(Teknisi Lab dan Tenaga Kerja Trampil)
E. MOBILISASI LAINNYA
E.I. PEKERJAAN DARURAT
1 Perkuatan Jembatan Lama LS
2 Pemeliharaan Jalan Kerja / Samping LS
3 ...................... ....
4 ...................... ....

E.II. LAIN-LAIN
1 Komunikasi Lapangan Lengkap Set 1
2 Pengadaan Kendaraan roda 4 unit 2.00
3 ...................... ....

F. DEMOBILISASI LS 1

Total Biaya Mobilisasi

Catatan : Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
Lembar 1.2-1
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

Rp 7,250.00 Rp 3,625,000.00

Rp 10,000,000.00 Rp 10,000,000.00

Rp 750,000.00 Rp 75,000,000.00
Rp 750,000.00 Rp 60,000,000.00
Rp 500,000.00 Rp 30,000,000.00
Rp 500,000.00 Rp 30,000,000.00
Rp 350,000.00 Rp 14,000,000.00

Rp 500,000.00 Rp 30,000,000.00

Rp 15,000,000.00 Rp 15,000,000.00
Rp 20,000,000.00 Rp 20,000,000.00
Rp 5,000,000.00 Rp 5,000,000.00
Rp 5,000,000.00 Rp 5,000,000.00
Rp 12,500,000.00 Rp 12,500,000.00
Rp 6,500,000.00 Rp 6,500,000.00
Rp 6,000,000.00 Rp 6,000,000.00
Rp 5,000,000.00 Rp 5,000,000.00

Rp 20,000,000.00 Rp 20,000,000.00
Rp 9,000,000.00 Rp 9,000,000.00
Rp 9,000,000.00 Rp 9,000,000.00
Rp 15,000,000.00 Rp 15,000,000.00
Rp 1,000,000.00 Rp 1,000,000.00

Rp 500,000.00 Rp 500,000.00
Rp 10,000,000.00 Rp 10,000,000.00

Rp 21,000,000.00

Rp 56,000,000.00
Rp 100,000,000.00 Rp 100,000,000.00
Rp 100,000,000.00 Rp 100,000,000.00

Rp 5,000,000.00 Rp 5,000,000.00
Rp 350,000,000.00 Rp 700,000,000.00

Rp 10,000,000.00 Rp 10,000,000.00

Rp 1,384,125,000.00

masuk over-head dan laba


ITEM PEMBAYARAN NO. : 1.1.
JENIS PEKERJAAN : Mobilisasi/Demobilisasi

KODE
No. JENIS ALAT ALAT SATUAN VOL.

B. PERALATAN

1 Asphalt Finisher E02 Unit 1.00


2 Compressor 4000-6500 L\M E05 Unit 1.00
3 Generator Set E12 Unit 4.00
4 Motor Grader >100 Hp E13 Unit 1.00
5 Wheel Loader 1.0-1.6 M3 E15 Unit 1.00
6 Tandem Roller 6-8 T. E17 Unit 1.00
7 Tire Roller 8-10 T. E18 Unit 1.00
8 Vibratory Roller 5-8 T. E19 Unit 1.00
9 Stone Crusher E21 Unit 1.00
10 Water Pump 70-100 Mm E22 Unit 1.00
11 Jack Hammer E26 Unit 1.00
12 Crane On Track 35 Ton E31 Unit 2.00
13 Bore Pile Machine E33 Unit 1.00
14 Asphalt Distribution E41 Unit 1.00
15 Concrete Pan Mixer E43 Unit 1.00
16 Concrete Mixer (350) E47 Unit 3.00

Total untuk Item B pada Lembar 1

ITEM PEMBAYARAN NO. : 1.2.


JENIS PEKERJAAN : Manajemen dan Safety
SATUAN PEMBAYARAN : Ls
KODE
No. JENIS ALAT ALAT SATUAN VOL.

A. PETUGAS

1 Biaya Pengamanan Lalu Lintas oleh Aparat OH 50.00


2 Biaya Pengamanan Lalu Lintas oleh (Pembantu) OH 50.00
3 - Helem Buah 20.00
4 - Rompi Buah 20.00
5 - Sepatu Buah 20.00

B. BAHAN

1 - Spanduk Buah 2.00


2 - Police Line Rol 15.00
3 - Traffic Cone Buah 30.00
4 - Rambu Pengaman Buah 6.00
Total untuk Item B pada Lembar 1

Catatan : Jumlah yang tercantum pada masing-masing item mobilisasi di atas sudah termasuk over-head dan laba
serta seluruh pajak dan bea (kecuali PPn), dan pengeluaran lainnya.
Lembar 1.2-2
HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

Rp 500,000.00 Rp 500,000.00
Rp 250,000.00 Rp 250,000.00
Rp 500,000.00 Rp 2,000,000.00
Rp 500,000.00 Rp 500,000.00
Rp 500,000.00 Rp 500,000.00
Rp 500,000.00 Rp 500,000.00
Rp 500,000.00 Rp 500,000.00
Rp 500,000.00 Rp 500,000.00
Rp 500,000.00 Rp 500,000.00
Rp 100,000.00 Rp 100,000.00
Rp 100,000.00 Rp 100,000.00
Rp 750,000.00 Rp 1,500,000.00
Rp 750,000.00 Rp 750,000.00
Rp 500,000.00 Rp 500,000.00
Rp 1,000,000.00 Rp 1,000,000.00
Rp 100,000.00 Rp 300,000.00

Rp 10,000,000.00

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

Rp 150,000.00 Rp 7,500,000.00
Rp 65,000.00 Rp 3,250,000.00
Rp 50,000.00 Rp 1,000,000.00
Rp 35,000.00 Rp 700,000.00
Rp 350,000.00 Rp 7,000,000.00

Rp 500,000.00 Rp 1,000,000.00
Rp 100,000.00 Rp 1,500,000.00
Rp 150,000.00 Rp 4,500,000.00
Rp 300,000.00 Rp 1,800,000.00
Rp 28,250,000.00

masuk over-head dan laba


NO DESKRIPSI KETERANGAN

1 PROYEK : JEMBATAN CAMPAGO KABUPATEN PADANG PARIAMAN


2 NO. PAKET KONTRAK :
3 ITEM PEKERJAAN : Pembangunan Jembatan
5 KOTA : Kabupaten Padang Pariaman

6 LAMA KONTRAK Hari Kalender atau


Bulan

7 JARAK RATA-RATA BASE CAMP KE PROYEK 18.00 km


L = { (c+a/2)*a + (c+b/2)*b } / (a+b) 7.65

15 km 1 km 11 km
A C B

D Base
Lokasi Quarry
- Gravel Camp
- Batu Kali
Quarry - Batu Belah
- Pasir jarak Basecamp ke Lokasi Pengerjaan 16.259 16.3 km
-Tanah timbunan

8 JAM KERJA EFEKTIF DALAM 1 HARI 7 jam

OVERHEAD DAN PROFIT 10 % x BIAYA LANGSUNG

INTEREST RATE OF EQUIPMENT INVESMENT 15 % x BIAYA AWAL

9 PANJANG JEMBATAN
a. BENTANG 1 35 METER
b. BENTANG 2 15.8 METER

10
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Asphalt Mixing Plant
2. Tenaga Pw 294.0 HP
3. Kapasitas Cp 60.0 T/Jam
4. Alat a. Umur Ekonomis A 10.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 3,135,000,000.0 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 313,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.19925 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 374,793.13 Rupiah
W

b. Asuransi, dll = 0.002 x B F 4,180.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 378,973.13 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H1 298,116.00 Rupiah


Bahan Bakar Pemanasan Material = 12 X 0.7 Cp X Ms H2 4,258,800.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 257,250.00 Rupiah

3. Biaya bengkel (6.25% dan 8.75%) x B J 130,625 Rupiah


W

4. Biaya perbaikan = (12,5 % - 17,5 %) x B K 261,250.00 Rupiah


dan perawatan W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 3 Orang / Jam ) x U2 M 31,080.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 5,261,121.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) T 5,640,094.13 Rupiah


E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E01

Alat Baru

Khusus AMP
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Asphalt Finisher
2. Tenaga Pw 72.4 HP
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 7.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 2,205,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 220,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.24036 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 198,747.98 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,837.50 Rupiah


W

Biaya Pasti per Jam = (E+F) G 200,585.48 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 73,413.60 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 63,350.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 57,422 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 114,843.75 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 343,389.23 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 543,974.70 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E02
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Bulldozer 100-150 Hp
2. Tenaga Pw 155.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 900,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 90,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 89,179.96 Rupiah
W

b. Asuransi, dll = 0.002 x B F 750.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 89,929.96 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 157,170.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 135,625.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 23,438 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 46,875.00 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 397,467.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 487,397.46 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E04
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Compressor 4000-6500 L\M
2. Tenaga Pw 60.0 HP
3. Kapasitas Cp 5,000.0 CPM/(L/m)
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 110,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 11,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 14,766.62 Rupiah
W

b. Asuransi, dll = 0.002 x B F 110.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 14,876.62 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 60,840.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 52,500.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 3,438 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 6,875.00 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 158,012.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 172,889.12 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E05
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Crane 10-15 Ton
2. Tenaga Pw 138.0 HP
3. Kapasitas Cp 15.0 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 1,488,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 148,800,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 147,444.19 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,240.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 148,684.19 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 139,932.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 120,750.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 38,750 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 77,500.00 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 411,292.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 559,976.19 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E07
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Dump Truck 8-10 M3
2. Tenaga Pw 190.0 HP
3. Kapasitas Cp 10.0 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 360,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 36,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 35,671.98 Rupiah
W

b. Asuransi, dll = 0.002 x B F 300.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 35,971.98 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 192,660.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 166,250.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 9,375 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 18,750.00 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 421,395.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 457,366.98 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir / Mekanik U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir / Pmb.Mekanik U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E09
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Excavator 80-140 Hp
2. Tenaga Pw 133.0 HP
3. Kapasitas Cp 0.90 M3
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 850,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 85,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 84,225.51 Rupiah
W

b. Asuransi, dll = 0.002 x B F 708.33 Rupiah


W

Biaya Pasti per Jam = (E+F) G 84,933.85 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 134,862.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 116,375.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 22,135 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 44,270.83 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 352,003.25 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 436,937.10 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E10
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Generator Set
2. Tenaga Pw 180.0 HP
3. Kapasitas Cp 135.0 KVA
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 207,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 20,700,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 20,511.39 Rupiah
W

b. Asuransi, dll = 0.002 x B F 172.50 Rupiah


W

Biaya Pasti per Jam = (E+F) G 20,683.89 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 182,520.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 157,500.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 5,391 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 10,781.25 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 390,551.88 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 411,235.76 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E12
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Motor Grader >100 Hp
2. Tenaga Pw 135.0 HP
3. Kapasitas Cp 10,800.0 -
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 676,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 67,600,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 66,984.06 Rupiah
W

b. Asuransi, dll = 0.002 x B F 563.33 Rupiah


W

Biaya Pasti per Jam = (E+F) G 67,547.39 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 136,890.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 118,125.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 17,604 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 35,208.33 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 342,187.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 409,734.89 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E13
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Wheel Loader 1.0-1.6 M3
2. Tenaga Pw 96.0 HP
3. Kapasitas Cp 1.5 M3
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 564,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 56,400,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 55,886.11 Rupiah
W

b. Asuransi, dll = 0.002 x B F 470.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 56,356.11 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 97,344.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 84,000.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 14,688 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 29,375.00 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 259,766.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 316,122.61 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E15
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Tandem Roller 6-8 T.
2. Tenaga Pw 82.0 HP
3. Kapasitas Cp 8.1 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 1,195,425,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 119,542,500 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 133,730.20 Rupiah
W

b. Asuransi, dll = 0.002 x B F 996.19 Rupiah


W

Biaya Pasti per Jam = (E+F) G 134,726.39 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 83,148.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 71,750.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 31,131 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 62,261.72 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 282,650.58 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 417,376.97 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E17
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Tire Roller 8-10 T.
2. Tenaga Pw 100.5 HP
3. Kapasitas Cp 9.0 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 900,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 90,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 89,179.96 Rupiah
W

b. Asuransi, dll = 0.002 x B F 750.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 89,929.96 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 101,907.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 87,937.50 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 23,438 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 46,875.00 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 294,517.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 384,446.96 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E18
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Vibratory Roller 5-8 T.
2. Tenaga Pw 82.0 HP
3. Kapasitas Cp 7.100 Ton
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 918,787,500 Rupiah

B. BIAYA PASTI PER JAM KERJA BIAYA PASTI PER JAM KERJA
1. Nilai Sisa Alat = 10 % x B C 91,878,750 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 102,783.23 Rupiah
W

b. Asuransi, dll = 0.002 x B F 765.66 Rupiah


W

Biaya Pasti per Jam = (E+F) G 103,548.88 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 83,148.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 71,750.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 23,927 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 47,853.52 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 261,038.27 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 364,587.15 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E19
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Concrete Vibrator
2. Tenaga Pw 5.5 HP
3. Kapasitas Cp 25.0 -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 800.0 Jam
c. Harga Alat B 4,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 400,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 1,342.42 Rupiah
W

b. Asuransi, dll = 0.002 x B F 10.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 1,352.42 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 5,577.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 4,812.50 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 313 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 625.00 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 45,687.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 47,039.42 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E20
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Stone Crusher
2. Tenaga Pw 220.0 HP
3. Kapasitas Cp 50.0 T/Jam
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 1,010,989,671 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 101,098,967 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 113,097.73 Rupiah
W

b. Asuransi, dll = 0.002 x B F 842.49 Rupiah


W

Biaya Pasti per Jam = (E+F) G 113,940.22 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 223,080.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 192,500.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 26,328 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 52,655.71 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 2 Orang / Jam ) x U2 M 20,720.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 539,283.57 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 653,223.79 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E21
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Water Pump 70-100 Mm
2. Tenaga Pw 6.0 HP
3. Kapasitas Cp - -
4. Alat Baru : a. Umur Ekonomis A 3.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 5,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.43798 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 985.45 Rupiah
W

b. Asuransi, dll = 0.002 x B F 5.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 990.45 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 6,084.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 5,250.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 156 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 312.50 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 46,162.75 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 47,153.20 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E22
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Water Tanker 3000-4500 L.
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 4,000.0 Liter
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 105,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 10,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 10,404.33 Rupiah
W

b. Asuransi, dll = 0.002 x B F 87.50 Rupiah


W

Biaya Pasti per Jam = (E+F) G 10,491.83 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 101,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 87,500.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 2,734 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 5,468.75 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 231,463.13 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 241,954.95 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E23
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Jack Hammer
2. Tenaga Pw 0.7 HP
3. Kapasitas Cp 1,330.000 -
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 35,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 3,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 3,915.39 Rupiah
W

b. Asuransi, dll = 0.002 x B F 29.17 Rupiah


W

Biaya Pasti per Jam = (E+F) G 3,944.56 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 709.80 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 612.50 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 911 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 1,822.92 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 38,416.68 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 42,361.23 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E26
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Concrete Pump
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 8.00 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 112,500,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 11,250,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 12,585.19 Rupiah
W

b. Asuransi, dll = 0.002 x B F 93.75 Rupiah


W

Biaya Pasti per Jam = (E+F) G 12,678.94 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 101,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 87,500.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 2,930 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 5,859.38 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 232,049.06 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 244,728.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E28
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Trailer 20 Ton
2. Tenaga Pw 175.0 HP
3. Kapasitas Cp 20.00 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 600,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 60,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 59,453.30 Rupiah
W

b. Asuransi, dll = 0.002 x B F 500.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 59,953.30 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 177,450.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 153,125.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 15,625 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 31,250.00 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 411,810.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 471,763.30 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E29
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Crane On Track 35 Ton
2. Tenaga Pw 125.0 HP
3. Kapasitas Cp 35.00 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 850,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 85,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 101,070.62 Rupiah
W

b. Asuransi, dll = 0.002 x B F 850.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 101,920.62 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 126,750.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 109,375.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 26,563 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 53,125.00 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 350,172.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 452,093.12 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E31
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Welding Set
2. Tenaga Pw 40.0 HP
3. Kapasitas Cp 250.00 Amp
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 17,500,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 1,750,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 1,957.70 Rupiah
W

b. Asuransi, dll = 0.002 x B F 14.58 Rupiah


W

Biaya Pasti per Jam = (E+F) G 1,972.28 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 40,560.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 35,000.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 456 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 911.46 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 111,287.19 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 113,259.47 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E32
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Bore Pile Machine
2. Tenaga Pw 150.0 HP
3. Kapasitas Cp 2,000.00 Meter
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 2,250,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 225,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 222,949.89 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,875.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 224,824.89 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 152,100.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 131,250.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 58,594 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 117,187.50 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 493,491.25 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 718,316.14 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E37
TENAGA KAPASITAS HARGA ALAT YANG DIPA
ALAT ALAT ALAT JAM
UMUR KERJA
ALAT 1 TAHUN

(HP) - (Tahun) (Tahun) (Jam)


No. JENIS PERALATAN KODE
ALAT

HP Cp B A W
1 2 2a 3 4 5 6 7

1 Asphalt Mixing Plant E01 294.0 60.0 T/jam 3,135,000,000 10.0 1,500.0
2 Asphalt Finisher E02 72.4 10.0 Ton 2,205,000,000 7.0 2,400.0
3 Bulldozer 100-150 Hp E04 155.0 - 900,000,000 6.0 2,400.0
4 Compressor 4000-6500 L\M E05 60.0 5,000.0 CPM/(L/m) 110,000,000 5.0 2,000.0
5 Crane 10-15 Ton E07 138.0 15.0 Ton 1,488,000,000 6.0 2,400.0
6 Dump Truck 8-10 M3 E09 190.0 10.0 Ton 360,000,000 6.0 2,400.0
7 Excavator 80-140 Hp E10 133.0 0.9 M3 850,000,000 6.0 2,400.0
8 Flat Bed Truck 3-4 M3 E11 100.0 10.0 Ton 330,800,000 6.0 2,400.0
9 Generator Set E12 180.0 135.0 KVA 207,000,000 6.0 2,400.0
10 Motor Grader >100 Hp E13 135.0 10,800.0 - 676,000,000 6.0 2,400.0
11 Wheel Loader 1.0-1.6 M3 E15 96.0 1.5 M3 564,000,000 6.0 2,400.0
12 Tandem Roller 6-8 T. E17 82.0 8.1 Ton 1,195,425,000 5.0 2,400.0
13 Tire Roller 8-10 T. E18 100.5 9.0 Ton 900,000,000 6.0 2,400.0
14 Vibratory Roller 5-8 T. E19 82.0 7.1 Ton 918,787,500 5.0 2,400.0
15 Concrete Vibrator E20 5.5 25.0 - 4,000,000 5.0 800.0
16 Stone Crusher E21 220.0 50.0 T/Jam 1,010,989,671 5.0 2,400.0
17 Water Pump 70-100 Mm E22 6.0 - 5,000,000 3.0 2,000.0
18 Water Tanker 3000-4500 L. E23 100.0 4,000.0 Liter 105,000,000 6.0 2,400.0
19 Jack Hammer E26 0.7 1,330.0 - 35,000,000 5.0 2,400.0
20 Concrete Pump E28 100.0 8.0 M3 112,500,000 5.0 2,400.0
21 Trailer 20 Ton E29 175.0 20.0 Ton 600,000,000 6.0 2,400.0
22 Crane On Track 35 Ton E31 125.0 35.0 Ton 850,000,000 6.0 2,000.0
23 Welding Set E32 40.0 250.0 Amp 17,500,000 5.0 2,400.0
24 Bore Pile Machine E37 150.0 2,000.0 meter 2,250,000,000 6.0 2,400.0
25 Asphalt Distributor E41 115.0 4,000.0 liter 395,000,000 6.0 2,000.0
26 Concrete Pan Mixer (Batching Plan) E43 134.0 600.0 liter 1,000,000,000 10.0 1,500.0
27 Concrete Mixer E47 20.0 350.0 liter 35,000,000 2.0 2,000.0
28 Truck Mixer E49 220.0 5.0 M3 750,000,000 5.0 2,000.0
29 Blending Equipment E52 50.0 30.0 Ton 500,000,000 10.0 1,500.0

KETERANGAN : 1 Tingkat Suku Bunga =


2 Upah Operator / Sopir / Mekanik =
3 Upah Pembantu Operator/Sopir/Mekanik =
4 Harga Bahan Bakar Bensin =
5 Harga Bahan Bakar Solar =
6 Minyak Pelumas =
7 Pajak Pertambahan Nilai (PPN) diperhitungkan pada Lembar Rekapitulasi Biaya P
8 Khusus AMP, biaya bahan bakar ditambah (untuk pemanasan material) sebesar : 12
ANALISA BIAYA SEWA PERALATAN PER JAM KERJA

ALAT YANG DIPAKAI NILAI FAKTOR BIAYA PASTI PER JAM


SISA PENGEM- BIAYA ASURANSI TOTAL BAHAN BAKAR & PELUMAS
HARGA ALAT BALIAN PENGEM- DAN BIAYA BAHAN MINYAK
ALAT MODAL BALIAN LAIN-LAIN PASTI / JAM BAKAR PELUMAS BIAYA
MODAL
(Rp.) (Rp.) - (Rp.) (Rp.) (Rp.) % % (Rp.)
f1 x HP x
i(1+i)^A (B - C) x D 0.002 x B 12 2.5 Harga BBM
(10% X B) ----------- ----------- ----------- (e1 + e2) s/d s/d +
(1+i)^A-1 W W 15 3 f2 x HP x
Harga Olie
B C D e1 e2 E f1 f2 F
8 9 10 11 12 13 14 15 16

3,135,000,000 313,500,000 0.19925 374,793.13 4,180.00 378,973.13 0.1200 0.0250 4,814,166.00


2,205,000,000 220,500,000 0.24036 198,747.98 1,837.50 200,585.48 0.1200 0.0250 136,763.60
900,000,000 90,000,000 0.26424 89,179.96 750.00 89,929.96 0.1200 0.0250 292,795.00
110,000,000 11,000,000 0.29832 14,766.62 110.00 14,876.62 0.1200 0.0250 113,340.00
1,488,000,000 148,800,000 0.26424 147,444.19 1,240.00 148,684.19 0.1200 0.0250 260,682.00
360,000,000 36,000,000 0.26424 35,671.98 300.00 35,971.98 0.1200 0.0250 358,910.00
850,000,000 85,000,000 0.26424 84,225.51 708.33 84,933.85 0.1200 0.0250 251,237.00
330,800,000 33,080,000 0.26424 32,778.59 275.67 33,054.25 0.1200 0.0250 188,900.00
207,000,000 20,700,000 0.26424 20,511.39 172.50 20,683.89 0.1200 0.0250 340,020.00
676,000,000 67,600,000 0.26424 66,984.06 563.33 67,547.39 0.1200 0.0250 255,015.00
564,000,000 56,400,000 0.26424 55,886.11 470.00 56,356.11 0.1200 0.0250 181,344.00
1,195,425,000 119,542,500 0.29832 133,730.20 996.19 134,726.39 0.1200 0.0250 154,898.00
900,000,000 90,000,000 0.26424 89,179.96 750.00 89,929.96 0.1200 0.0250 189,844.50
918,787,500 91,878,750 0.29832 102,783.23 765.66 103,548.88 0.1200 0.0250 154,898.00
4,000,000 400,000 0.29832 1,342.42 10.00 1,352.42 0.1200 0.0250 10,389.50
1,010,989,671 101,098,967 0.29832 113,097.73 842.49 113,940.22 0.1200 0.0250 415,580.00
5,000,000 500,000 0.43798 985.45 5.00 990.45 0.1200 0.0250 11,334.00
105,000,000 10,500,000 0.26424 10,404.33 87.50 10,491.83 0.1200 0.0250 188,900.00
35,000,000 3,500,000 0.29832 3,915.39 29.17 3,944.56 0.1200 0.0250 1,322.30
112,500,000 11,250,000 0.29832 12,585.19 93.75 12,678.94 0.1200 0.0250 188,900.00
600,000,000 60,000,000 0.26424 59,453.30 500.00 59,953.30 0.1200 0.0250 330,575.00
850,000,000 85,000,000 0.26424 101,070.62 850.00 101,920.62 0.1200 0.0250 236,125.00
17,500,000 1,750,000 0.29832 1,957.70 14.58 1,972.28 0.1200 0.0250 75,560.00
2,250,000,000 225,000,000 0.26424 222,949.89 1,875.00 224,824.89 0.1200 0.0250 283,350.00
395,000,000 39,500,000 0.26424 46,968.11 395.00 47,363.11 0.1200 0.0250 217,235.00
1,000,000,000 100,000,000 0.19925 119,551.24 1,333.33 120,884.57 0.1200 0.0250 253,126.00
35,000,000 3,500,000 0.61512 9,688.08 35.00 9,723.08 0.1200 0.0250 37,780.00
750,000,000 75,000,000 0.298315552 100,681.50 750.00 101,431.50 0.1200 0.0250 415,580.00
500,000,000 50,000,000 0.199252063 59,775.62 666.67 60,442.29 0.1200 0.0250 94,450.00

15.00 % per-tahun
24,000 Rupiah per-orang/jam
10,360 Rupiah per-orang/jam
6,200 Rupiah per-liter
8,450 Rupiah per-liter
35,000 Rupiah per-liter
Rekapitulasi Biaya Pekerjaan
material) sebesar : 12 Liter x (Kapasitas AMP Riil = 0.7 x Kapasitas AMP/Jam) x Harga BBM Solar , (kolom 16)
A

BIAYA OPERASI PER JAM KERJA TOTAL


WORKSHOP PERBAIKAN & PERAWATAN UPAH TOTAL BIAYA
OPERATOR PEMBANTU BIAYA SEWA ALAT
KOEF. BIAYA KOEF. BIAYA / SOPIR OPERATOR OPERASI PER
/ SOPIR / JAM JAM KERJA
- (Rp.) - (Rp.) (Rp.) (Rp.) (Rp.) (Rp.) KET.
1 Orang 1 Orang
0.0625 (g1 x B') 0.125 (g1 x B') Per Per
s/d ----- s/d ----------- Jam Kerja Jam Kerja F+G+H+I E+J
0.0875 W 0.175 W = =
Rp24,000.0 Rp10,360.0
g1 G g1 G H I J K L
17 18 17 18 19 20 21 22 23

0.0625 130,625 0.1250 261,250.00 24,000.00 31,080.00 5,261,121.00 5,640,094.13 Alat Baru
0.0625 57,421.88 0.1250 114,843.75 24,000.00 10,360.00 343,389.23 543,974.70 Alat Baru
0.0625 23,437.50 0.1250 46,875.00 24,000.00 10,360.00 397,467.50 487,397.46 Alat Baru
0.0625 3,437.50 0.1250 6,875.00 24,000.00 10,360.00 158,012.50 172,889.12 Alat Baru
0.0625 38,750.00 0.1250 77,500.00 24,000.00 10,360.00 411,292.00 559,976.19 Alat Baru
0.0625 9,375.00 0.1250 18,750.00 24,000.00 10,360.00 421,395.00 457,366.98 Alat Baru
0.0625 22,135.42 0.1250 44,270.83 24,000.00 10,360.00 352,003.25 436,937.10 Alat Baru
0.0625 8,614.58 0.1250 17,229.17 24,000.00 10,360.00 249,103.75 282,158.00 Alat Baru
0.0625 5,390.63 0.1250 10,781.25 24,000.00 10,360.00 390,551.88 411,235.76 Alat Baru
0.0625 17,604.17 0.1250 35,208.33 24,000.00 10,360.00 342,187.50 409,734.89 Alat Baru
0.0625 14,687.50 0.1250 29,375.00 24,000.00 10,360.00 259,766.50 316,122.61 Alat Baru
0.0625 31,130.86 0.1250 62,261.72 24,000.00 10,360.00 282,650.58 417,376.97 Alat Baru
0.0625 23,437.50 0.1250 46,875.00 24,000.00 10,360.00 294,517.00 384,446.96 Alat Baru
0.0625 23,926.76 0.1250 47,853.52 24,000.00 10,360.00 261,038.27 364,587.15 Alat Baru
0.0625 312.50 0.1250 625.00 24,000.00 10,360.00 45,687.00 47,039.42 Alat Baru
0.0625 26,327.86 0.1250 52,655.71 24,000.00 20,720.00 539,283.57 653,223.79 Alat Baru
0.0625 156.25 0.1250 312.50 24,000.00 10,360.00 46,162.75 47,153.20 Alat Baru
0.0625 2,734.38 0.1250 5,468.75 24,000.00 10,360.00 231,463.13 241,954.95 Alat Baru
0.0625 911.46 0.1250 1,822.92 24,000.00 10,360.00 38,416.68 42,361.23 Alat Baru
0.0625 2,929.69 0.1250 5,859.38 24,000.00 10,360.00 232,049.06 244,728.00 Alat Baru
0.0625 15,625.00 0.1250 31,250.00 24,000.00 10,360.00 411,810.00 471,763.30 Alat Baru
0.0625 26,562.50 0.1250 53,125.00 24,000.00 10,360.00 350,172.50 452,093.12 Alat Baru
0.0625 455.73 0.1250 911.46 24,000.00 10,360.00 111,287.19 113,259.47 Alat Baru
0.0625 58,593.75 0.1250 117,187.50 24,000.00 10,360.00 493,491.25 718,316.14 Alat Baru
0.0625 12,343.75 0.1250 24,687.50 24,000.00 10,360.00 288,626.25 335,989.36 Alat Baru
0.0625 41,666.67 0.1250 83,333.33 24,000.00 10,360.00 412,486.00 533,370.57 Alat Baru
0.0625 1,093.75 0.1250 2,187.50 24,000.00 10,360.00 75,421.25 85,144.33 Alat Baru
0.0625 23,437.50 0.1250 46,875.00 24,000.00 10,360.00 520,252.50 621,684.00 Alat Baru
0.0625 20,833.33 0.1250 41,666.67 24,000.00 10,360.00 191,310.00 251,752.29 Alat Baru
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Flat Bed Truck
2. Tenaga Pw 100.0 HP
3. Kapasitas Cp 10.00 Ton
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,400.0 Jam
c. Harga Alat B 330,800,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 33,080,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 32,778.59 Rupiah
W

b. Asuransi, dll = 0.002 x B F 275.67 Rupiah


W

Biaya Pasti per Jam = (E+F) G 33,054.25 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 101,400.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 87,500.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 8,615 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 17,229.17 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 249,103.75 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 282,158.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E11
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Asphalt Distributor
2. Tenaga Pw 115.0 HP
3. Kapasitas Cp 4,000.00 liter
4. Alat Baru : a. Umur Ekonomis A 6.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 395,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 39,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.26424 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 46,968.11 Rupiah
W

b. Asuransi, dll = 0.002 x B F 395.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 47,363.11 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 116,610.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 100,625.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 12,344 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 24,687.50 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 288,626.25 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 335,989.36 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E41
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Concrete Pan Mixer
2. Tenaga Pw 134.0 HP
3. Kapasitas Cp 600.00 liter
4. Alat Baru : a. Umur Ekonomis A 10.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 1,000,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 100,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.19925 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 119,551.24 Rupiah
W

b. Asuransi, dll = 0.002 x B F 1,333.33 Rupiah


W

Biaya Pasti per Jam = (E+F) G 120,884.57 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 135,876.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 117,250.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 41,667 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 83,333.33 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 412,486.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 533,370.57 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E43
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Concrete Mixer
2. Tenaga Pw 20.0 HP
3. Kapasitas Cp 350.00 liter
4. Alat Baru : a. Umur Ekonomis A 2.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 35,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 3,500,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.61512 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 9,688.08 Rupiah
W

b. Asuransi, dll = 0.002 x B F 35.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 9,723.08 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 20,280.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 17,500.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 1,094 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 2,187.50 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 75,421.25 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 85,144.33 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E47
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Truck Mixer
2. Tenaga Pw 220.0 HP
3. Kapasitas Cp 5.00 M3
4. Alat Baru : a. Umur Ekonomis A 5.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 2,000.0 Jam
c. Harga Alat B 750,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 75,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.29832 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 100,681.50 Rupiah
W

b. Asuransi, dll = 0.002 x B F 750.00 Rupiah


W

Biaya Pasti per Jam = (E+F) G 101,431.50 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 223,080.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 192,500.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 23,438 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 46,875.00 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 520,252.50 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 621,684.00 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E49
URAIAN ANALISA ALAT

No. U RAIAN KODE KOEF. SATUAN

A. URAIAN PERALATAN
1. Jenis Peralatan Blending Equipment
2. Tenaga Pw 50.0 HP
3. Kapasitas Cp 30.00 ton
4. Alat Baru : a. Umur Ekonomis A 10.0 Tahun
b. Jam Kerja Dalam 1 Tahun W 1,500.0 Jam
c. Harga Alat B 500,000,000 Rupiah

B. BIAYA PASTI PER JAM KERJA


1. Nilai Sisa Alat = 10 % x B C 50,000,000 Rupiah

2. Faktor Angsuran Modal = i x (1 + i)^A D 0.19925 -


(1 + i)^A - 1
3. Biaya Pasti per Jam :
a. Biaya Pengembalian Modal = (B-C)xD E 59,775.62 Rupiah
W

b. Asuransi, dll = 0.002 x B F 666.67 Rupiah


W

Biaya Pasti per Jam = (E+F) G 60,442.29 Rupiah

C. BIAYA OPERASI PER JAM KERJA

1. Bahan Bakar = (12%-15%) x Pw x Ms H 50,700.00 Rupiah

2. Pelumas = (2.5%-3%) x Pw x Mp I 43,750.00 Rupiah

3. Biaya bengkel = (6.25% dan 8.75%) x B J 20,833 Rupiah


W

4. Perawatan dan (12,5 % - 17,5 %) x B K 41,666.67 Rupiah


perbaikan = W

5. Operator = ( 1 Orang / Jam ) x U1 L 24,000.00 Rupiah


6. Pembantu Operator = ( 1 Orang / Jam ) x U2 M 10,360.00 Rupiah

Biaya Operasi per Jam = (H+I+J+K+L+M) P 191,310.00 Rupiah

D. TOTAL BIAYA SEWA ALAT / JAM = ( G + P ) S 251,752.29 Rupiah

E. LAIN - LAIN
1. Tingkat Suku Bunga i 15.00 % / Tahun
2. Upah Operator / Sopir U1 24,000.00 Rp./Jam
3. Upah Pembantu Operator / Pmb.Sopir U2 10,360.00 Rp./Jam
4. Bahan Bakar Bensin Mb 6,200.00 Liter
5. Bahan Bakar Solar Ms 8,450.00 Liter
6. Minyak Pelumas Mp 35,000.00 Liter
7. PPN diperhitungkan pada lembar Rekapitulasi
Biaya Pekerjaan
URAIAN ANALISA ALAT

KET.

E52
DAFTAR ALAT YANG DIGUNAKAN

No. Jenis Alat Kode HP Kapasitas

1 Asphalt Mixing Plant E01 294.00 60 T/jam


2 Asphalt Finisher E02 72.40 10 Ton
3 Bulldozer 100-150 HP E04 155.00 -
4 Compressor 4000-6500 L\M E05 60.00 5000 CPM/(L/m)
5 Crane 10-15 Ton E07 138.00 15 Ton
6 Dump Truck 10 Ton E09 190.00 10 Ton
7 Excavator 80-140 Hp E10 133.00 0.9 M3
8 Flat Bed Truck E11 100.00 10 Ton
9 Generator Set E12 180.00 135 KVA
10 Motor Grader >100 Hp E13 135.00 10800 -
11 Wheel Loader 1.0-1.6 M3 E15 96.00 1.5 M3
12 Tandem Roller 6-8 T. E17 82.00 8.1 Ton
13 Tire Roller 8-10 T. E18 100.50 9 Ton
14 Vibratory Roller 5-8 T. E19 82.00 7.1 Ton
15 Concrete Vibrator E20 5.50 25 -
16 Stone Crusher E21 220.00 50 T/Jam
17 Water Pump 70-100 Mm E22 6.00 -
18 Water Tanker 3000-4500 L. E23 100.00 4000 Liter
19 Jack Hammer E26 0.70 1330
20 Concrete Pump E28 100.00 8 M3
21 Trailer 20 Ton E29 175.00 20 Ton
22 Crane On Track 35 Ton E31 125.00 35 Ton
23 Welding Set E32 40.00 250 Amp
24 Bore Pile Machine E33 150.00 2000 meter
25 Asphalt Distributor E41 115.00 4000 liter
26 Concrete Pan Mixer E43 134.00 600 liter
27 Concrete Mixer E47 20.00 350 liter
28 Truck Mixer E49 220 5 M3
Catatan : Harga Alat yang digunakan merupakan Alat yang diperoleh dari Owner Estimate
KAN

Harga
yang Keterangan
digunakan

3,135,000,000 Alat Baru


2,205,000,000 Alat Baru
900,000,000 Alat Baru
110,000,000 Alat Baru
1,488,000,000 Alat Baru
360,000,000 Alat Baru
850,000,000 Alat Baru
330,800,000 Alat Baru
207,000,000 Alat Baru
676,000,000 Alat Baru
564,000,000 Alat Baru
1,195,425,000 Alat Baru
900,000,000 Alat Baru
918,787,500 Alat Baru
4,000,000 Alat Baru
1,010,989,671 Alat Baru
5,000,000 Alat Baru
105,000,000 Alat Baru
35,000,000 Alat Baru
112,500,000 Alat Baru
600,000,000 Alat Baru
850,000,000 Alat Baru
17,500,000 Alat Baru
2,250,000,000 Alat Baru
395,000,000 Alat Baru
1,000,000,000 Alat Baru
35,000,000 Alat Baru
750,000,000 Alat Baru
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M01 - Pasir Pasang
Lokasi : Quarry
Tujuan : Base Camp

No. URAIAN KODE KOEF.

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi Base Camp L 28.00
4 Harga satuan pasir di Quarry RpM01 1.00
5 Harga Satuan Dasar Excavator RpE10 1.00
6 Harga Satuan Dasar Dump Truck RpE09 1.00
7 Berat volume pasir Bil 1.42

II. URUTAN KERJA


1 Pasir digali dengan Excavator
2 Excavator sekaligus memuat pasir hasil
galian ke dalam Dump Truck
3 Dump Truck mengangkut pasir ke lokasi
Base Camp

III. PERHITUNGAN

EXCAVATOR (E10)
Kapasitas Bucket V 0.90
Faktor Bucket Fb 0.90
Faktor Efisiensi alat Fa 0.83
Waktu siklus Ts1
- Menggali / memuat T1 0.50
- Lain-lain T2 0.50
Ts1 1.00
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 40.338
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 10,831.90

DUMP TRUCK (E09)


Kapasitas bak V 10.00
Faktor efisiensi alat Fa 0.83
Kecepatan rata-rata bermuatan v1 40.00
Kecepatan rata-rata kosong v2 60.00
Waktu siklus Ts2
- Muat = (V x 60)/Q1 x Bil) T1 10.47
- Waktu tempuh isi = (L/v1) x 60 T2 42.00
- Waktu tempuh kosong = (L/v2) x 60 T3 28.00
- Lain-lain T4 11.11
Ts2 91.59

Kapasitas Produksi / Jam =


V x Fa x 60 Q2 3.83
Ts2 x Bil

Biaya Dump Truck / M3 = (1 : Q2) x RpE09 Rp2 119,440.83

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI BASE CAMP

Harga Satuan Dasar Pasir =

( RpM01 + Rp1 + Rp2 ) M01 185,272.72

Dibulatkan : M01 185,300.00


ALISA HARGA DASAR SATUAN BAHAN

HARGA
SATUAN SATUAN
(Rp.)

Km
M3 55,000.00
Jam 436,937.10
Jam 457,366.98
ton/m3

M3
-
-

menit
menit
menit

M3 / Jam

Rupiah

m3
-
KM/Jam
KM/Jam
menit
menit
menit
menit
menit

M3 / Jam

Rupiah

Rupiah

Rupiah
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M02 - Batu Kali
Lokasi : Quarry
Tujuan : Base Camp

No. URAIAN KODE KOEF.

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke Base Camp L 41.00
4 Harga satuan batu kali di Quarry RpM02 1.00
5 Harga Satuan Dasar Excavator RpE10 1.00
6 Harga Satuan Dasar Dump Truck RpE09 1.00
7 Berat volume batu kali Bil 1.44

II. URUTAN KERJA


1 Batu kali digali dengan Excavator
2 Excavator sekaligus memuat batu kali
hasil galian ke dalam Dump Truck
3 Dump Truck mengangkut batu kali ke
base camp

III. PERHITUNGAN

EXCAVATOR (E10)
Kapasitas Bucket V 0.90
Faktor Bucket Fb 0.75
Faktor Efisiensi alat Fa 0.83
Waktu siklus Ts1
- Menggali / memuat T1 0.75
- Lain-lain T2 0.50
Ts1 1.25
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 26.892
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 16,247.85

DUMP TRUCK (E09)


Kapasitas bak V 10.00
Faktor efisiensi alat Fa 0.83
Kecepatan rata-rata bermuatan v1 40.00
Kecepatan rata-rata kosong v2 60.00
Waktu siklus Ts2
- Muat = (V x 60)/(Q1 x Bil) T1 15.49
- Waktu tempuh isi = (L/v1) x 60 T2 61.50
- Waktu tempuh kosong = (L/v2) x 60 T3 41.00
- Lain-lain T4 13.89
Ts2 131.88

Kapasitas Produksi / Jam =


V x Fa x 60 Q2 2.62
Ts2 x Bil

Biaya Dump Truck / M3 = (1 : Q2) x RpE09 Rp2 174,416.13

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga Satuan Dasar Batu kali =

( RpM02 + Rp1 + Rp2 ) M02 244,663.98

Dibulatkan : M02 244,700.00


ALISA HARGA DASAR SATUAN BAHAN

HARGA
SATUAN SATUAN
(Rp.)

Km
M3 54,000.00
Jam 436,937.10
Jam 457,366.98
ton/m3

M3
-
-

menit
menit
menit

M3 / Jam

Rupiah

m3
-
KM/Jam
KM/Jam
menit
menit
menit
menit
menit

M3 / Jam

Rupiah

Rupiah

Rupiah
HARGA & JARAK RATA-RATA
DARI SUMBER BAHAN (QUARRY)
HARGA
No. URAIAN SATUAN ROYALTY
(Rp)

1. M01 - P a s i r Pasang M3 55,000.00

2. M02 - Batu M3 54,000.00

4 M08 - Tanah Timbunan Biasa M3 40,000.00

5 M09 - Timbunan Material Pilihan M3 60,500.00

6 M16 - Sirtu M3 75,000.00

7 M44 - Pasir Urug M3 80,000.00

Sumber : Harga Royalty disesuaikan dengan Enginnering Estimate

Catatan : Harga Royalty sudah ditambah biaya retribusi sebesar Rp. 300,-/m3

Quarry Kayu Tanam


Jarak lokasi ke Base Camp 41 KM
Granular Material (50% Stone and 50% Sand Grav
Digunakan untuk Material Perkerasan dan Campur

Quarry Lubuk Alung


Jarak lokasi ke Base Camp 28 KM
Pasir digunakan untuk Bahan Campuran pada Beton dan
pasir urugan

Borrow Pit Lubuk Minturun


End of Project KM 26+500 Jarak Quarry ke Lokasi Pekerjaan 22 KM
Digunakan untuk Bahan Timbunan Biasa
Base Camp
KM 25
Borrow Pit Lubuk Minturun
Jarak Quarry ke Lokasi Pekerjaan 22 KM
Digunakan untuk Bahan Timbunan Biasa
Base Camp
KM 25
KM 19

KM 8+741,81
Lokasi Jembatan Kuranji

KM 4+800
Start of Project KM 00+000

Borrow Pit Indarung


Jarak Quarry ke Lokasi Pekerjaan 19 KM
Digunakan untuk Bahan Timbunan Pilihan dan
Sirtu
HARGA & JARAK RATA-RATA
DARI SUMBER BAHAN (QUARRY)
JARAK
QUARRY KET.
( Km )

28.00 Ke Base Camp

41.00 Ke Base Camp

22.00 Ke Lokasi Kerja

19.00 Ke Lokasi Kerja

19.00 Ke Base Camp

28.00 Ke Base Camp

Quarry Kayu Tanam


Jarak lokasi ke Base Camp 41 KM
Granular Material (50% Stone and 50% Sand Gravel)
Digunakan untuk Material Perkerasan dan Campuran Beton

Quarry Lubuk Alung


Jarak lokasi ke Base Camp 28 KM
Pasir digunakan untuk Bahan Campuran pada Beton dan
pasir urugan

Borrow Pit Lubuk Minturun


Jarak Quarry ke Lokasi Pekerjaan 22 KM
Digunakan untuk Bahan Timbunan Biasa
Borrow Pit Lubuk Minturun
Jarak Quarry ke Lokasi Pekerjaan 22 KM
Digunakan untuk Bahan Timbunan Biasa

KM 8+741,81
Lokasi Jembatan Kuranji

Borrow Pit Indarung


Jarak Quarry ke Lokasi Pekerjaan 19 KM
Digunakan untuk Bahan Timbunan Pilihan dan
Sirtu
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M16 - Sirtu
Lokasi : Quarry
Tujuan: Lokasi Pekerjaan

No. URAIAN KODE KOEF.

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi Base Camp L 19.00
4 Harga satuan Sirtu di Quarry RpM16 1.00
5 Harga Satuan Dasar Excavator RpE10 1.00
6 Harga Satuan Dasar Dump Truck RpE09 1.00
7 Berat volume sirtu Bil 1.51

II. URUTAN KERJA


1 Sirtu digali dengan Excavator
2 Excavator sekaligus memuat sirtu hasil
galian ke dalam Dump Truck
3 Dump Truck mengangkut sirtu ke lokasi
Base Camp

III. PERHITUNGAN

EXCAVATOR (E10)
Kapasitas Bucket V 0.90
Faktor Bucket Fb 0.90
Faktor Efisiensi alat Fa 0.83
Waktu siklus Ts1
- Menggali / memuat T1 0.50
- Lain-lain T2 0.50
Ts1 1.00
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 40.338
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 10,831.90

DUMP TRUCK (E09)


Kapasitas bak V 10.00
Faktor efisiensi alat Fa 0.83
Kecepatan rata-rata bermuatan v1 20.00
Kecepatan rata-rata kosong v2 30.00
Waktu siklus Ts2
- Muat = (V x 60)/(Q1 x Bil) T1 9.85
- Waktu tempuh isi = (L/v1) x 60 T2 57.00
- Waktu tempuh kosong = (L/v2) x 60 T3 38.00
- Lain-lain T4 11.11
Ts2 115.96
ALISA HARGA DASAR SATUAN BAHAN

HARGA
SATUAN SATUAN
(Rp.)

Km
M3 75,000.00
Jam 436,937.10
Jam 457,366.98
ton/m3

M3
-
-

menit
menit
menit

M3 / Jam

Rupiah

m3
-
KM/Jam
KM/Jam
menit
menit
menit
menit
menit

Bersambung
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M16 - Sirtu
Lokasi : Quarry
Tujuan: Lokasi Pekerjaan

No. URAIAN KODE KOEF.

Kapasitas Produksi / Jam =


V x Fa x 60 Q2 2.84
Ts2 x Bil

Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 160,815.09

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga Satuan Dasar Sirtu =

( RpM16 + Rp1 + Rp2 ) M16 246,646.99

Dibulatkan : M16 246,600.00


ALISA HARGA DASAR SATUAN BAHAN

Lanjutan
HARGA
SATUAN SATUAN
(Rp.)

M3 / Jam

Rupiah

Rupiah

Rupiah
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M44 - Pasir Urug
Lokasi : Quarry
Tujuan: Lokasi Pekerjaan

No. URAIAN KODE KOEF.

I. ASUMSI
1 Menggunakan alat berat
2 Kondisi Jalan : baik
3 Jarak Quarry ke lokasi pekerjaan L 28.00
4 Harga satuan pasir urug di Quarry RpM44 1.00
5 Harga Satuan Dasar Excavator RpE10 1.00
6 Harga Satuan Dasar Dump Truck RpE09 1.00
7 Berat volume pasir urug Bil 1.42

II. URUTAN KERJA


1 pasir urug digali dengan Excavator
2 Excavator sekaligus memuat pasir urug
hasil galian ke dalam Dump Truck
3 Dump Truck mengangkut pasir urug
ke lokasi pekerjaan

III. PERHITUNGAN

EXCAVATOR (E10)
Kapasitas Bucket V 0.90
Faktor Bucket Fb 0.90
Faktor Efisiensi alat Fa 0.83
Waktu siklus Ts1
- Menggali / memuat T1 0.50
- Lain-lain T2 0.50
Ts1 1.00
Kap. Prod. / jam =
V x Fb x Fa x 60 Q1 40.338
Ts1

Biaya Excavator / M3 = (1 : Q1) x RpE10 Rp1 10,831.90

DUMP TRUCK (E09)


Kapasitas bak V 10.00
Faktor efisiensi alat Fa 0.83
Kecepatan rata-rata bermuatan v1 20.00
Kecepatan rata-rata kosong v2 30.00
Waktu siklus Ts2
- Muat = (V x 60)/(Q1 x Bil) T1 10.47
- Waktu tempuh isi = (L/v1) x 60 T2 84.00
- Waktu tempuh kosong = (L/v2) x 60 T3 56.00
- Lain-lain T4 11.11
Ts2 161.59
ALISA HARGA DASAR SATUAN BAHAN

HARGA
SATUAN SATUAN
(Rp.)

Km
M3 80,000.00
Jam 436,937.10
Jam 457,366.98
ton/m3

M3
-
-

menit
menit
menit

M3 / Jam

Rupiah

m3
-
KM/Jam
KM/Jam

menit
menit
menit
menit
menit

Bersambung
ANALISA HARGA DASAR SATUAN BAHAN
Jenis : M44 - Pasir Urug
Lokasi : Quarry
Tujuan: Lokasi Pekerjaan

No. URAIAN KODE KOEF.

Kapasitas Produksi / Jam =


V x Fa x 60 Q2 2.17
Ts2 x Bil

Biaya Dump Truck / M3 = (1 : Q2) x RpE08 Rp2 210,730.54

IV. HARGA SATUAN DASAR BAHAN


DI LOKASI PEKERJAAN

Harga Satuan Dasar pasir urug =

( RpM44 + Rp1 + Rp2 ) M44 301,562.44

Dibulatkan : M44 301,600.00


ALISA HARGA DASAR SATUAN BAHAN

Lanjutan
HARGA
SATUAN SATUAN
(Rp.)

M3 / Jam

Rupiah

Rupiah

Rupiah
ITEM PEMBAYARAN : AGREGAT KASAR & HALUS
JENIS PEKERJAAN : PENGADAAN AGREGAT KASAR & HALUS
SATUAN PEMBAYARAN : M3

No. URAIAN

I ASUMSI
1 Bahan dasar (Batu dan Pasir) diterima di lokasi Alat
Pemecah Batu (di Base Camp)
2 Kegiatan dilakukan di dalam lokasi Base Camp
3 Hasil produksi Alat Pemecah Batu : - Agregat Halus
- Agregat Kasar
4 Berat Isi Bahan : - Batu / Gravel
- Pasir
- Batu Pecah
5 Harga Satuan Bahan Dasar : - Batu Kali
- Pasir
6 Biaya Operasi Alat : - Pemecah Batu (Stone Crusher)
- Wheel Loader
7 Kapasitas Alat : - Pemecah Batu (Stone Crusher)
- Wheel Loader
8 Faktor Efisiensi Alat : - Pemecah Batu (Stone Crusher)
- Wheel Loader
9 Faktor Kehilangan Material
10 Agregat Halus masih perlu dicampur dengan pasir

II METHODE PELAKSANAAN

1 Wheel Loader mengangkut batu/gravel dari tumpukan


dan menuangkannya ke Alat Pemecah Batu.

2 Batu/gravel dipecah dengan Alat Pemecah Batu


(Stone Crusher) sehingga menghasilkan Agregat Batu
Pecah Kasar dan Halus.

3 Agregat Halus dicampur dengan pasir menggunakan Loader

III PERHITUNGAN
III.1. HARGA SATUAN AGREGAT PRODUKSI ST. CRUSHER

1.a. Kerja Stone Crusher memecah gravel :


- Waktu kerja Stone Crusher
- Produksi Stone Crusher 1 jam = (Fa1 x Cp1) x D3
- Kebutuhan batu/gravel 1 jam = (Fa1 x Cp1) x D1

1.b. Kerja Wheel Loader melayani Stone Crusher :


- Kap. Angkut / rit = (Fa2 x Cp2) x D1
- Waktu Siklus (Muat, Tuang, Tunggu, dll)
- Waktu kerja W.Loader memasok gravel
= {(Qg : Ka) x Ts} : 60 menit

1.c. Biaya Produksi Batu Pecah / Ton


= {(Tst x Rp3) + (Tw x Rp4)} : Qb

1.d. Harga Satuan Batu Pecah Produksi St.Crusher / M3


= {(Qg : Qb) x Fh x Rp1} + Bp

III.2. HARGA SATUAN AGREGAT PECAH MESIN 5-10 & 10-20 mm


( berlaku juga untuk Aggregat 20-30 mm dan Agregat 30-40 mm)
Agregat Kasar Produksi Stone Crusher = 70%
(Tertahan saringan # 4 = 4,75mm)
Harga Satuan Agregat Kasar / M3 = (K x HSb) / K

III.3. HARGA SATUAN AGREGAT PECAH MESIN 0-5 mm


(Agregat Halus)

Dianggap aggregat produksi stone crusher yang lolos saringan #4


(4,75 mm) belum memenuhi spesifikasi sehingga perlu dicampur lagi
dengan pasir sebanyak =

3.a. Agregat Halus Produksi Stone Crusher = 30%


Harga Agregat Halus Prod. Stone Crsh.= (H x HSb) / H
3.b. Pasir tambahan = Pst x Rp2
3.c. Waktu pencampuran (blending) dengan wheel loader
3.d. Biaya pencampuran = (1+Pst) M3 x Tc x Rp4

Harga Satuan Agregat Halus / M3


= (Hs1 + Hs2 + Hs3)
EGAT KASAR & HALUS
URAIAN ANALISA HARGA SATUAN

KODE KOEFISIEN SATUAN KETERANGAN

H 30.00 %
K 70.00 %
D1 1.20 Ton/M3 Berongga
D2 1.40 Ton/M3 Berongga
D3 1.35 Ton/M3 Berongga
Rp1 244,700.00 Rp./M3
Rp2 185,300.00 Rp./M3
Rp3 653,223.79 Rp./Jam
Rp4 316,122.61 Rp./Jam
Cp1 50.00 Ton/Jam
Cp2 1.50 M3 Kap. Bucket
Fa1 0.70 -
Fa2 0.83 -
Fh 1.10 -
Tst 1.00 Jam
Qb 47.25 Ton/Jam Batu pecah
Qg 42.00 Ton/Jam

Ka 1.49 ton
Ts 5.00 menit

Tw 2.34 Jam

Bp 29,498.53 Rp./ton

HSb 268,760.75 Rp./ton

K 70.00 %

HSAk 268,760.75 Rupiah Di Luar PPN

Pst 25.00 %

H 30.00 %
Hs1 268,760.75 Rupiah per 1 ton
Hs2 46,325.00 Rupiah per (Pst) M3
Tc 0.03 Jam/m3
Hs3 13,171.78 Rupiah
HSAh 328,257.53 Rupiah Di Luar PPN
ITEM PEMBAYARAN : AGREGAT KELAS A (kondisi lepas)
JENIS PEKERJAAN : PENGADAAN AGREGAT KELAS A
SATUAN PEMBAYARAN : M3 URAIAN ANA

No. URAIAN KODE KOEFISIEN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 18.00
5 Tebal lapis agregat padat t 0.15
6 Berat isi padat Bip 1.81
7 Jam kerja efektif per-hari Tk 7.00
8 Proporsi Campuran : - Agregat Pecah Mesin 20 - 30 mm 20-30 35.00
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 40.00
- Sirtu PU 25.00
9 Berat Isi Agregat (lepas) Bil 1.51
10 Faktor kehilangan - Agregat Pecah Mesin 20 - 30 mm Fh1 1.05
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm Fh2 1.05
- Sirtu Fh3 1.05

II. URUTAN KERJA


1 Wheel Loader memuat material bahan campuran dari
stockpile ke alat blending
2 Blending equipment melakukan pencampuran (blending)
Aggregat kasar, aggregat halus dan pasir alam menjadi
Aggregat A

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
- Agr 20-30 = "20-30" x 1 M3 x Fh1 M93 0.3675
- Agr 5 - 10 & 10 - 20 = "5-10 & 10-20" x 1 M3 x Fh2 M92 0.4200
- Sirtu = PU x 1 M3 x Fh3 M44 0.2625

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50
Faktor bucket Fb 0.85
Faktor Efisiensi alat Fa 0.83
Waktu Siklus :
- Waktu pemuatan alat blending T1 2.00

Ts1 2.00

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 31.75


Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0315

2.b. BLENDING EQIPMENT (E52)


Kapasitas V 25.00
Faktor effesiensi alat Fa 0.83
Kap. Prod. / jam = V x Fa Q2 20.75

Koefisien Alat / M3 = 1 : Q2 0.0482

3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 31.75
Produksi Agregat / hari = Tk x Q1 Qt 222.23
Kebutuhan tenaga :
- Pekerja P 2.00
- Mandor M 1.00

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0630
- Mandor = (Tk x M) : Qt (L03) 0.0315
URAIAN ANALISA HARGA SATUAN

SATUAN KETERANGAN

KM
M
-
jam
% Gradasi harus
% memenuhi Spec.
%
ton/m3

M3
M3
M3

M3 (lepas)
- kondisi sedang
-

menit jarak 50 meter

menit

M3 padat

jam

M3/jam
M3

jam

M3/Jam
M3

orang
orang

Jam
Jam
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : Padang Bypass Capacity Expansion Project


No. PAKET KONTRAK : KU.08.08/KTR.06.PPK-12-PJNII/IV/2014
NAMA PAKET : Pembangunan Jembatan Kuranji Bypass
PROP / KAB / KODYA : Padang
ITEM PEMBAYARAN NO. : AGREGAT KELAS A (kondisi lepas)
JENIS PEKERJAAN : PENGADAAN AGREGAT KELAS A
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.0630 10,360.00


2. Mandor (L03) jam 0.0315 15,000.00

JUMLAH HARGA TENAGA

B. BAHAN

1. Agregat 20-30 M93 M3 0.3675 268,760.75


2. Agregat 5-10 & 10-20 M92 M3 0.4200 268,760.75
3 Sirtu M16 M3 0.2625 246,600.00

JUMLAH HARGA BAHAN

C. PERALATAN
1. Wheel Loader (E15) jam 0.0315 316,122.61
2. Blending Equpment (E52) jam 0.0482 251,752.29
3 Alat Bantu Ls 1.0000

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/a
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satu
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diu
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Pes
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak te
yang dibayar dari kontrak) dan biaya-biaya lainnya.
RMULIR STANDAR UNTUK
ALISA MASING-MASING HARGA SATUAN

:
:
:

JUMLAH
HARGA
(Rp.)

652.65
472.48

1,125.13

98,769.58
112,879.52
64,732.50

276,381.59

9,957.40
12,132.64
0.00

22,090.04

299,596.76
operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

erkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan


a Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
si/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
termasuk bahan bakar, bahan habis dipakai dan operator.
luaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : Padang Bypass Capacity Expansion Project


No. PAKET KONTRAK : KU.08.08/KTR.06.PPK-12-PJNII/IV/2014
NAMA PAKET : Pembangunan Jembatan Kuranji Bypass
PROP / KAB / KODYA : Padang
ITEM PEMBAYARAN NO. : AGREGAT KELAS B (kondisi lepas)
JENIS PEKERJAAN : PENGADAAN AGREGAT KELAS B
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA
NO. KOMPONEN SATUAN KUANTITAS SATUAN
(Rp.)

A. TENAGA

1. Pekerja (L01) jam 0.0630 10,360.00


2. Mandor (L03) jam 0.0315 15,000.00

JUMLAH HARGA TENAGA

B. BAHAN

1. Aggregat 20-30 M93 M3 0.2625 268,760.75


2. Agg 5 - 10 & 10 - 20 M92 M3 0.4200 268,760.75
3 Pasir Urug M44 M3 0.3675 301,600.00

JUMLAH HARGA BAHAN

C. PERALATAN
1. Wheel Loader (E15) jam 0.0315 316,122.61
2. Blending Equpment (E52) jam 0.0482 251,752.29
3 Alat Bantu Ls 1.0000

JUMLAH HARGA PERALATAN

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C )


Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau u
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan p
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak terma
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ORMULIR STANDAR UNTUK
ALISA MASING-MASING HARGA SATUAN

:
:
:

JUMLAH
HARGA
(Rp.)

652.65
472.48

1,125.13

70,549.70
112,879.52
110,838.00

294,267.21

9,957.40
12,132.64
0.00

22,090.04

317,482.38
erasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran

raan setiap komponen untuk menyelesaikan satu satuan pekerjaan


atuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
eskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
masuk bahan bakar, bahan habis dipakai dan operator.
ran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
ITEM PEMBAYARAN : AGREGAT KELAS B (kondisi lepas)
JENIS PEKERJAAN : PENGADAAN AGREGAT KELAS B
SATUAN PEMBAYARAN : M3 URAIAN ANA

No. URAIAN KODE KOEFISIEN

I ASUMSI
1 Bahan Agregat Halus & Kasar diterima di lokasi
Base Camp
2 Jarak dari stockpile ke alat blending l 50.00
3 Jam kerja effektif perhari Tk 7.00
4 Kegiatan dilakukan di dalam lokasi Base Camp
5 Berat isi padat Bip 1.81
6 Jam kerja efektif per-hari Tk 7.00
8 Proporsi Campuran : - Agregat Pecah Mesin 20 - 30 mm 20-30 25.00
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 40.00
- Pasir Urug St 35.00
9 Berat volume agregat (lepas) Bil 1.51
- Agregat Pecah Mesin 20 - 30 mm Fh1 1.05
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm Fh2 1.05
- Pasir Urug Fh3 1.05

II URUTAN PEKERJAAN

1 Wheel Loader memuat material bahan campuran dari


stockpile ke alat blending
2 Blending equipment melakukan pencampuran (blending)
Aggregat kasar, aggregat halus dan pasir alam menjadi
Aggregat B

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
- Agr 20-30 = "20-30" x 1 M3 x Fh1 M93 0.2625
- Agr 5 - 10 & 10 - 20 = "5-10 & 10-20" x 1 M3 x Fh2 M92 0.4200
- Psir Urug = St x 1 M3 x Fh3 M16 0.3675

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50
Faktor bucket Fb 0.85
Faktor Efisiensi alat Fa 0.83
Waktu Siklus :
- Waktu pemuatan alat belending T1 2.00

Ts1 2.00

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 31.75


(Bip/Bil) x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0315

2.b. BLENDING EQUIPMENT (E52)


Kapasitas V 25.00
Faktor effesiensi alat Fa 0.83

Kap. Prod. / jam = V x Fa Q2 20.75


Koefisien Alat / M3 = 1 : Q2 0.0482

3. TENAGA
Produksi menentukan : WHEEL LOADER Q1 31.75
Produksi Agregat / hari = Tk x Q1 Qt 222.23
Kebutuhan tenaga :
- Pekerja P 2.00
- Mandor M 1.00

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0630
- Mandor = (Tk x M) : Qt (L03) 0.0315
URAIAN ANALISA HARGA SATUAN

SATUAN KETERANGAN

M
jam

jam
% Gradasi harus
% memenuhi
% Spesifikasi
ton/m3

M3
M3
M3

M3 (lepas)
- kondisi sedang
-

menit jarak 50 meter

menit

M3 padat

jam

M3/jam

M3
jam

M3/Jam
M3

orang
orang

Jam
Jam
ITEM PEMBAYARAN NO. : 3.1 (1) Analisa EI-311
JENIS PEKERJAAN : Galian Biasa
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Berat volume tanah (lepas) D 1.60 ton/m3 1.40 - 1.80

II. URUTAN KERJA


1 Tanah yang dipotong umumnya berada disisi fondasi struktur
2 Penggalian dilakukan dengan menggunakan Excavator
3 Selanjutnya Excavator menuangkan material hasil
galian kedalam Dump Truck
4 Dump Truck membuang material hasil galian keluar
lokasi jalan sejauh L 5.00 Km

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
Tidak ada bahan yang diperlukan

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.90 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.83
Faktor konversi , kedalaman < 40 % Fv 0.90 lihat panduan
Waktu siklus Ts1 menit
- Menggali / memuat (standar) T1 0.320 menit

Waktu siklus = T1 x Fv Ts1 0.29 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 129.69 M3/Jam


Ts1 x Fk

Koefisien Alat / M3 = 1 : Q1 (E10) 0.0077 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 10.00 ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktu siklus Ts2 menit
- Muat = (V x 60)/(D x Q1 x Fk) T1 2.41 menit
- Waktu tempuh isi = (L : v1) x 60 T2 7.50 menit
- Waktu tempuh kosong = (L : v2) x 60 T3 5.00 menit
- Lain-lain T4 2.00 menit
Ts2 16.91 menit

Kapasitas Produksi / Jam = V x Fa x 60 Q2 15.34 M3/Jam


D x Fk x Ts2

Koefisien Alat / M3 = 1 : Q2 (E08) 0.0652 Jam

2.d. ALAT BANTU


Diperlukan alat-alat bantu kecil Lump Sump
- Sekop
- Keranjang

Berlanjut ke halaman berikut


Analisa EI-311

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : JEMBATAN CAMPAGO KABUPATEN PADANG PARIAMAN


No. PAKET KONTRAK :
NAMA PAKET : Pembangunan Jembatan
PROP / KAB / KODYA : Kabupaten Padang Pariaman
ITEM PEMBAYARAN NO. : 3.1 (1)
JENIS PEKERJAAN : Galian Biasa
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0154 10,360.00 159.77


2. Mandor (L03) Jam 0.0077 15,000.00 115.66

JUMLAH HARGA TENAGA 275.43

B. BAHAN

JUMLAH HARGA BAHAN 0.00

C. PERALATAN

1. Excavator (E10) Jam 0.0077 436,937.10 3,369.15


2. Dump Truck (E08) Jam 0.0652 457,366.98 29,817.49
3. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 33,186.64

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 33,462.07


E. OVERHEAD & PROFIT 10.0 % x D 3,346.21
F. HARGA SATUAN PEKERJAAN ( D + E ) 36,808.28
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 3.1 (1) Analisa EI-311
JENIS PEKERJAAN : Galian Biasa
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

3. TENAGA
Produksi menentukan : EXCAVATOR Q1 129.69 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 907.81 M3
Kebutuhan tenaga :
- Pekerja P 2.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0154 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0077 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 36,808.28 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
Analisa EI-313

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : JEMBATAN CAMPAGO KABUPATEN PADANG PARIAMAN


No. PAKET KONTRAK :
NAMA PAKET : Pembangunan Jembatan
PROP / KAB / KODYA : Kabupaten Padang Pariaman
ITEM PEMBAYARAN NO. : 3.1 (3)
JENIS PEKERJAAN : Galian Struktur dengan Kedalaman 0 - 2 meter
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0308 10,360.00 319.54


2. Mandor (L03) Jam 0.0077 15,000.00 115.66

JUMLAH HARGA TENAGA 435.20

B. BAHAN

JUMLAH HARGA BAHAN 0.00

C. PERALATAN
1. Excavator (E10) Jam 0.0077 436,937.10 3,369.15
2. Bulldozer (E04) Jam 0.014502 487,397.46 7,068.46
3. Alat bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 10,437.61

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 10,872.81


E. OVERHEAD & PROFIT 10.0 % x D 1,087.28
F. HARGA SATUAN PEKERJAAN ( D + E ) 11,960.09
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 3.1 (3) Analisa EI-313
JENIS PEKERJAAN : Galian Struktur dengan Kedalaman 0 - 2 meter
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanik
2 Lokasi pekerjaan : sekitar jembatan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -

II. METHODE PELAKSANAAN


1 Tanah yang dipotong berada disekitar lokasi jembatan
2 Penggalian dilakukan dengan menggunakan alat
Excavator
3 Bulldozer mengangkut/mengusur hasil galian ke tempat
pembuangan di sekitar lokasi pekerjaan L 0.1000 Km

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.90 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.83 -
Faktor konversi (kedalaman < 40 %) Fv 0.90 -
Berat isi material Bim 0.85 -
Waktu siklus
- Menggali, memuat, lain-lain (standar) T1 0.32 menit
Waktu siklus = T1 x Fv Ts1 0.29 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 129.69 M3/Jam


Ts1 x Fk

Koefisien Alat / M3 = 1 : Q1 (E10) 0.0077 Jam

2.a. BULLDOZER (E04)


Faktor pisau (blade) Fb 1.00 -
Faktor efisiensi kerja Fa 0.83 -
Kecepatan mengupas Vf 3.00 Km/Jam
Kecepatan mundur Vr 5.00 Km/Jam
Kapasitas pisau q 5.40 M3
` Faktor kemiringan (grade) Fm 1.00

Waktu Siklus Ts
- Waktu gusur = (L x 60) : Vf T1 2.0 menit
- Waktu kembali = (L x 60) : Vr T2 1.2 menit
- Waktu lain-lain T3 0.05 menit
Ts 3.25 menit

Kapasitas Produksi / Jam = q x Fb x Fm x Fa x 60/Ts Q2 68.95 M3


Fk

Koefisien Alat / M3 = 1 : Q2 (E04) 0.014502 Jam

2.d. ALAT BANTU


Diperlukan alat-alat bantu kecil Lump Sump
- Pacul = 2 buah
- Sekop = 2 buah

Berlanjut ke halaman berikut


ITEM PEMBAYARAN NO. : 3.1 (3) Analisa EI-313
JENIS PEKERJAAN : Galian Struktur dengan Kedalaman 0 - 2 meter
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

3. TENAGA
Produksi menentukan : EXCAVATOR Q1 129.69 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 907.81 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0308 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0077 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 11,960.09 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
Analisa EI-314

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : JEMBATAN CAMPAGO KABUPATEN PADANG PARIAMAN


No. PAKET KONTRAK :
NAMA PAKET : Pembangunan Jembatan
PROP / KAB / KODYA : Kabupaten Padang Pariaman
ITEM PEMBAYARAN NO. : 3.1 (4)
JENIS PEKERJAAN : Galian Struktur dengan Kedalaman 2 - 4 meter
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.1658 10,360.00 1,717.94


2. Mandor (L03) Jam 0.0166 15,000.00 248.74

JUMLAH HARGA TENAGA 1,966.68

B. BAHAN

1. Bahan pengaman tebing Ls 1.000 468,180.00 468,180.00

JUMLAH HARGA BAHAN 468,180.00

C. PERALATAN
1. Excavator (E10) Jam 0.0166 436,937.10 7,245.49
2. Bulldozer (E04) Jam 0.029005 487,397.46 14,136.92
3. Alat bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 21,382.41

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 491,529.09


E. OVERHEAD & PROFIT 10.0 % x D 49,152.91
F. HARGA SATUAN PEKERJAAN ( D + E ) 540,682.00
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 3.1 (4) Analisa EI-314
JENIS PEKERJAAN : Galian Struktur dengan Kedalaman 2 - 4 meter
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanik
2 Lokasi pekerjaan : sekitar jembatan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Faktor pembayaran Fp 2.00 1.5 - 2

II. METHODE PELAKSANAAN


1 Tanah yang dipotong berada disekitar jembatan
2 Penggalian dilakukan dengan menggunakan alat
Excavator
3 Bulldozer mengangkut/mengusur hasil galian ke tempat
pembuangan di sekitar lokasi pekerjaan L 0.1000 Km
4 Bahan pengaman tebing galian (bahan kayu)

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
- Bahan pengaman tebing galian 0,2 - 0,4 M3 (kayu) 0.20 M3

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.93 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.83 -
Faktor konversi (kedalaman 40 - 75%) Fv 1.00 -
Berat isi material Bim 0.85 -
Waktu siklus
- Menggali / memuat, lain lain, standar T1 0.32 menit

Waktu Siklus = T1 x Fv Ts1 0.32 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 60.30 M3/Jam


Ts1 x Fk x Fp

Koefisien Alat / M3 = 1 : Q1 (E10) 0.0166 Jam

2.a. BULLDOZER (E04)


Faktor pisau (blade) Fb 1.00 -
Faktor efisiensi kerja Fa 0.83 -
Kecepatan mengupas Vf 3.00 Km/Jam
Kecepatan mundur Vr 5.00 Km/Jam
Kapasitas pisau q 5.40 M3 panduan =datar
` Faktor kemiringan (grade) Fm 1.00

Waktu Siklus Ts
- Waktu gusur = (L x 60) : Vf T1 2.0 menit
- Waktu kembali = (L x 60) : Vr T2 1.2 menit
- Waktu lain-lain T3 0.05 menit
Ts 3.25 menit

Kapasitas Produksi / Jam = q x Fb x Fm x Fa x 60/Ts Q2 34.48 M3


Fk x Fp

Koefisien Alat / M3 = 1 : Q2 (E04) 0.0290 Jam

Berlanjut ke halaman berikut


ITEM PEMBAYARAN NO. : 3.1 (4) Analisa EI-314
JENIS PEKERJAAN : Galian Struktur dengan Kedalaman 2 - 4 meter
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.d. ALAT BANTU


Diperlukan alat-alat bantu kecil Lump Sump
- Pacul = 2 buah
- Sekop = 2 buah

3. TENAGA
Produksi menentukan : EXCAVATOR Q1 60.30 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 422.13 M3
Kebutuhan tenaga :
- Pekerja P 10.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.1658 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0166 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 540,682.00 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 3.2 (1) Analisa EI-321
JENIS PEKERJAAN : Timbunan Biasa
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Lokasi pekerjaan : bagian oprit jembatan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Tebal hamparan padat t 0.15 M
7 Berat volume bahan (lepas) D 1.60 Ton/M3

II. URUTAN KERJA


1 Excavator menggali dan memuat ke dalam dump truck
2 Dump Truck mengangkut ke lapangan dengan jarak
quari ke lapangan L 22.00 Km
3 Material diratakan dengan menggunakan Motor Grader
4 Material dipadatkan menggunakan Vibratory Roller
5 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
1.a. Bahan timbunan = 1 x Fk (M08) 1.20 M3

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.90 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi Alat Fa 0.83 -
Faktor Konversi Fv 0.90 Lihat panduan
Waktu sklus Ts1
- Muat T1 0.32 menit
Waktu Siklus = T1 x Fv Ts1 0.29 menit

Kapasitas Produksi / Jam = V x Fb x Fa x 60 Q1 129.69 M3


Fk x Ts1

Koefisien alat / M3 = 1 : Q1 (E10) 0.0077 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 10.00 Ton
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 KM/Jam
Kecepatan rata-rata kosong v2 60.00 KM/Jam
Waktusiklus : Ts2
- Waktu muat = (V x 60)/(D x Q1) T1 1.46 menit
- Waktu tempuh isi = (L : v1) x 60 T2 33.00 menit
- Waktu tempuh kosong = (L : v2) x 60 T3 22.00 menit
- Lain-lain T4 2.00 menit
Ts2 58.46 menit

Kapasitas Produksi / Jam = V x Fa x 60 Q2 5.32 M3


D x Ts2

Koefisien Alat / M3 = 1 : Q2 (E08) 0.1878 Jam

Berlanjut ke halaman berikut


Analisa EI-321

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : JEMBATAN CAMPAGO KABUPATEN PADANG PARIAMAN


No. PAKET KONTRAK :
NAMA PAKET : Pembangunan Jembatan
PROP / KAB / KODYA : Kabupaten Padang Pariaman
ITEM PEMBAYARAN NO. : 3.2 (1)
JENIS PEKERJAAN : Timbunan Biasa
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0524 10,360.00 542.35


2. Mandor (L02) Jam 0.0131 15,000.00 196.31

JUMLAH HARGA TENAGA 738.66

B. BAHAN

1. Bahan timbunan (M08) M3 1.2000 40,000.00 48,000.00

JUMLAH HARGA BAHAN 48,000.00

C. PERALATAN
1. Excavator (E15) Jam 0.0077 436,937.10 3,369.15
2. Dump Truck (E08) Jam 0.1878 457,366.98 85,904.17
3. Motor Grader (E13) Jam 0.0131 409,734.89 5,362.45
4. Vibro Roller (E19) Jam 0.0109 364,587.15 3,957.31
5. Water Tanker (E23) Jam 0.0141 241,954.95 3,400.97
6. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 101,994.06

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 150,732.73


E. OVERHEAD & PROFIT 10.0 % x D 15,073.27
F. HARGA SATUAN PEKERJAAN ( D + E ) 165,806.00
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 3.2 (1) Analisa EI-321
JENIS PEKERJAAN : Timbunan Biasa
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar Overlap bo 0.30 M
Faktor Efisiensi kerja Fa 0.80 -
Kecepatan rata-rata alat v 4.00 Km / Jam
Jumlah lintasan n 7 lintasan
Lebar pisau effektif b 2.6 M
Waktu siklus Ts3
- Perataan 1 kali lintasan Lh x 60 T1 0.75 menit
- Lain-lain v x 1000 T2 1.00 menit
Ts3 1.75 menit

Kapasitas Prod / Jam = Lh x ((b-bo)+bo) x t x Fa x 60 Q3 76.41 M3


Ts3 x n

Koefisien Alat / M3 = 1 : Q3 (E13) 0.0131 Jam

2.d. VIBRATOR ROLLER (E19)


Kecepatan rata-rata alat v 4.00 Km / Jam
Lebar efektif pemadatan b 1.48 M
Jumlah lintasan n 8.00 lintasan
Faktor efisiensi alat Fa 0.83 -

Kapasitas Prod./Jam = (v x 1000) x b x t x Fa Q4 92.13 M3


n

Koefisien Alat / M3 = 1 : Q4 (E19) 0.0109 Jam

2.e. WATER TANK TRUCK (E23)


Volume tangki air V 4.00 M3
Kebutuhan air/M3 material padat Wc 0.07 M3
Kapasitas pompa air pa 100.00 liter/menit
Faktor efisiensi alat Fa 0.83

Kapasitas Prod./Jam = pa x Fa x 60 Q5 71.14 M3


1000 x Wc

Koefisien Alat / M3 = 1 : Q5 0.0141 jam

2.f. ALAT BANTU


Diperlukan alat-alat bantu kecil Lump Sump
- Sekop = 3 buah

3. TENAGA
Produksi menentukan : MOTOR GRADER Q3 76.41 M3/Jam
Produksi Timbunan / hari = Tk x Q1 Qt 534.86 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0524 Jam
- Mandor = (Tk x M) : Qt (L02) 0.0131 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

Berlanjut ke halaman berikut


ITEM PEMBAYARAN NO. : 3.2 (1) Analisa EI-321
JENIS PEKERJAAN : Timbunan Biasa
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 165,806.00 / M3

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
Analisa EI-322

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : JEMBATAN CAMPAGO KABUPATEN PADANG PARIAMAN


No. PAKET KONTRAK :
NAMA PAKET : Pembangunan Jembatan
PROP / KAB / KODYA : Kabupaten Padang Pariaman
ITEM PEMBAYARAN NO. : 3.2 (2)
JENIS PEKERJAAN : Timbunan Pilihan
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0524 10,360.00 542.35


2. Mandor (L03) Jam 0.0131 15,000.00 196.31

JUMLAH HARGA TENAGA 738.66

B. BAHAN

1. Bahan pilihan (M09) (M09) M3 1.2000 60,500.00 72,600.00

JUMLAH HARGA BAHAN 72,600.00

C. PERALATAN
1. Excavator (E10) Jam 0.0077 316,122.61 2,437.57
2. Dump Truck (E08) Jam 0.1683 457,366.98 76,986.90
3. Motor Grader (E13) Jam 0.0131 409,734.89 5,362.45
3. Vibrator Roller (E19) Jam 0.0109 364,587.15 3,957.31
4. Water Tanker (E23) Jam 0.0070 241,954.95 1,700.49
5. Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 90,444.72

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 163,783.38


E. OVERHEAD & PROFIT 10.0 % x D 16,378.34
F. HARGA SATUAN PEKERJAAN ( D + E ) 180,161.72
Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 3.2 (2) Analisa EI-322
JENIS PEKERJAAN : Timbunan Pilihan
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Pekerjaan dilakukan secara mekanis
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi Jalan : baik
4 Jam kerja efektif per-hari Tk 7.00 Jam
5 Faktor pengembangan bahan Fk 1.20 -
6 Tebal hamparan padat t 0.15 M
7 Berat volume bahan (lepas) D 1.60 Ton/M3

II. URUTAN KERJA


1 Excavator menggali dan memuat ke dalam Dump Truck
2 Dump Truck mengangkut ke lapangan dengan jarak
quari ke lapangan L 19.00 Km
3 Material dihampar dengan menggunakan Motor Grader
4 Hamparan material disiram air dengan Watertank Truck
(sebelum pelaksanaan pemadatan) dan dipadatkan
dengan menggunakan Tandem Roller
5 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
1.a. Bahan pilihan = 1 x Fk (M09) 1.20 M3

2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.90 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi Alat Fa 0.83 -
Faktor Konversi Fv 0.90 Lihat Panduan
Waktu sklus Ts1 menit
- Muat T1 0.32 menit
Waktu Siklus = T1 x Fv Ts1 0.288
V x Fb x Fa x 60 M3
Kapasitas Produksi / Jam = Fk x Ts1 Q1 129.6875

Koefisienalat / M3 = = 1 : Q1 (E10) 0.0077 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 10.00 M3
Faktor efisiensi alat Fa 0.83 -
Kecepatan rata-rata bermuatan v1 40.00 Km / Jam
Kecepatan rata-rata kosong v2 60.00 Km / Jam
Waktusiklus : Ts2
- Waktu muat = = (V x 60)/(D x Q1) T1 2.89 menit
- Waktu tempuh isi = (L : v1) x 60 T2 28.50 menit
- Waktu tempuh kosong = (L : v2) x 60 T3 19.00 menit
- Lain-lain T4 2.00 menit
Ts2 52.39 menit

Kapasitas Produksi / Jam = V x Fa x 60 Q2 5.94 M3


D x Ts2

Koefisien Alat / m3 = 1 : Q2 (E08) 0.1683 Jam

Berlanjut ke halaman berikut


ITEM PEMBAYARAN NO. : 3.2 (2) Analisa EI-322
JENIS PEKERJAAN : Timbunan Pilihan
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 m
Lebar Efektif kerja Blade b 2.60 m
Lebar overlap bo 0.30 m Panduan
Faktor Efisiensi Alat Fa 0.80 -
Kecepatan rata-rata alat v 4.00 Km / Jam
Jumlah lintasan n 7.00 lintasan
Waktu siklus Ts3
- Perataan 1 kali lintasan = Lh : (v x 1000) x 60 T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kapasitas Produksi/Jam = Lh x (n(b-bo)+bo) x t x Fa x 60 Q3 76.41 M3


Ts3 x n

Koefisien Alat / m3 = 1 : Q3 (E13) 0.0131 Jam

2.d. VIBRATOR ROLLER (E19)


Kecepatan rata-rata alat v 4.00 Km / jam
Lebar efektif pemadatan b 1.48 M
Jumlah lintasan n 8.00 lintasan
Faktor efisiensi alat Fa 0.83 -
Kapasitas Prod./Jam = (v x 1000) x b x t x Fa Q4 92.13 M3
n

Koefisien Alat / m3 = 1 : Q4 (E17) 0.0109 Jam

2.e. WATER TANK TRUCK (E23)


Volume tangki air V 4.00 M3
Kebutuhan air / M3 material padat Wc 0.07 M3
Kapasitas pompa air pa 200.00 liter/menit
Faktor efisiensi alat Fa 0.83 -

Kapasitas Produksi / Jam = pa x Fa x 60 Q5 142.29 M3


1000 x Wc

Koefisien Alat / m3 = 1 : Q5 (E23) 0.0070 Jam

2.f. ALAT BANTU


Diperlukan alat-alat bantu kecil Lump Sump
- Sekop = 3 buah

3. TENAGA
Produksi menentukan : MOTOR GRADER Q3 76.41 M3/Jam
Produksi Timbunan / hari = Tk x Q1 Qt 534.86 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0524 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0131 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

Berlanjut ke halaman berikut


ITEM PEMBAYARAN NO. : 3.2 (2) Analisa EI-322
JENIS PEKERJAAN : Timbunan Pilihan
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 180,161.72 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 5.1 (1) Analisa EI-511
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas A
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 16.30 KM
5 Tebal lapis Agregat padat t 0.20 M
6 Berat isi padat Bip 1.81 -
7 Jam kerja efektif per-hari Tk 7.00 Jam
8 Lebar bahu jalan Lb 1.00 M
9 Proporsi Campuran : - Agregat Pecah Mesin 30 - 40 mm 30-40 35.00 % Gradasi harus
- Agregat Pecah Mesin 20 - 30 mm 20-30 10.00 % memenuhi Spec.
- Agregat Pecah Mesin 5 - 10 & 10 - 20 mm 5-10&10-20 20.00 %
- Pasir 0-5 mm PU 35.00 %
10 Berat Isi Agregat (lepas) Bil 1.51 ton/m3
Faktor kehilangan - Agregat A Fh 1.05

II. URUTAN KERJA


1 Wheel Loader mencampur & memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaan dan dihampar dengan Motor Grader
3 Hamparan Agregat dibasahi dengan Water Tank Truck
sebelum dipadatkan dengan Vibratory Roller
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
- Bahan Agreagat Base Kelas A M26 1.00000 M3

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3 (lepas)
Faktor bucket Fb 0.85 - kondisi sedang
Faktor Efisiensi alat Fa 0.83 -
Waktu Siklus :
- Memuat dan lain-lain T1 0.45 menit panduan

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 117.71 M3


(Bip/Bil) x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0085 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 10.00 ton
Faktor Efisiensi alat Fa 0.80 -
Kecepatan rata-rata bermuatan v1 40.00 KM / Jam
Kecepatan rata-rata kosong v2 60.00 KM / Jam
Waktu Siklus :
- Waktu memuat = (V x 60)/(Q1 x Bil) T1 3.38 menit
- Waktu tempuh isi = (L : v1) x 60 menit T2 24.45 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T3 16.30 menit
- Lain-lain termasuk menurunkan Agregat T4 2.00 menit
Ts2 46.13 menit

Kap. Prod./jam = V x Fa x 60 Q2 5.75 M3


bip x Ts2
Koefisien Alat / M3 = 1 = 1 : Q2 (E08) 0.1739 Jam

Berlanjut ke halaman berikut


Analisa EI-511

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : JEMBATAN CAMPAGO KABUPATEN PADANG PARIAMAN


No. PAKET KONTRAK :
NAMA PAKET : Pembangunan Jembatan
PROP / KAB / KODYA : Kabupaten Padang Pariaman
ITEM PEMBAYARAN NO. : 5.1 (1)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas A
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0492 10,360.00 509.68


2. Mandor (L03) Jam 0.0070 15,000.00 105.42

JUMLAH HARGA TENAGA 615.10

B. BAHAN

1. Bahan Agreagat Base Kelas A M26 M3 1.0000 299,596.76 299,596.76

JUMLAH HARGA BAHAN 299,596.76

C. PERALATAN

1 Wheel Loader E15 Jam 0.0085 316,122.61 2,685.53


2 Dump Truck E08 Jam 0.1739 457,366.98 79,550.70
3 Motor Grader E13 Jam 0.0070 409,734.89 2,879.66
4 Vibrator Roller E19 Jam 0.0081 364,587.15 2,967.98
5 Water Tanker E23 Jam 0.0141 241,954.95 3,400.97
6 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 91,484.85

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 391,696.72


E. OVERHEAD & PROFIT 10.0 % x D 39,169.67
F. HARGA SATUAN PEKERJAAN ( D + E ) 430,866.39

Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 5.1 (1) Analisa EI-511
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas A
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.c. MOTOR GRADER (E13)


Panjang hamparan Lh 50.00 M
Lebar efektif kerja blade b 1.00 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM / Jam
Jumlah lintasan n 2.00 lintasan 1 x pp
Waktu Siklus Ts3
- Perataan 1 lintasan = (Lh x 60) : (v x 1000) T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap.Prod. / jam = Lh x b x t x Fa x 60 Q3 142.29 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0070 Jam

2.d. VIBRATOR ROLLER 0


Kecepatan rata-rata v 4.00 KM / Jam
Lebar efektif pemadatan b 1.48 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = (v x 1000) x b x t x Fa Q4 122.84 M3


n
Koefisien Alat / M3 = 1 : Q4 (E17) 0.0081 Jam

2.e. WATERTANK TRUCK (E23)


Volume tangki air V 4.00 M3
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Kapasitas pompa air pa 100.00 liter/menit
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod. / jam = pa x Fa x 60 Q5 71.14 M3


1000 x Wc
Koefisien Alat / M3 = 1 : Q5 (E23) 0.0141 Jam

2.g. ALAT BANTU


diperlukan : Lump Sum
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

3. TENAGA
Produksi menentukan : MOTOR GRADER Q4 142.29 M3/Jam
Produksi Agregat / hari = Tk x Q1 Qt 996.00 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0492 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0070 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

Berlanjut ke halaman berikut


ITEM PEMBAYARAN NO. : 5.1 (1) Analisa EI-511
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas A
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 430,866.39 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
Analisa EI-512

FORMULIR STANDAR UNTUK


PEREKAMAN ANALISA MASING-MASING HARGA SATUAN

PROYEK : JEMBATAN CAMPAGO KABUPATEN PADANG PARIAMAN


No. PAKET KONTRAK :
NAMA PAKET : Pembangunan Jembatan
PROP / KAB / KODYA : Kabupaten Padang Pariaman
ITEM PEMBAYARAN NO. : 5.1 (2)
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas B
SATUAN PEMBAYARAN : M3

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA

1. Pekerja (L01) Jam 0.0281 10,360.00 291.24


2. Mandor (L03) Jam 0.0040 15,000.00 60.24

JUMLAH HARGA TENAGA 351.49

B. BAHAN

1. Bahan Agregat Base Kelas B M27 M3 1.0000 317,482.38 317,482.38

JUMLAH HARGA BAHAN 317,482.38

C. PERALATAN

1 Wheel Loader E15 Jam 0.0085 316,122.61 2,685.53


2 Dump Truck E08 Jam 0.1739 457,366.98 79,550.70
3 Motor Grader E13 Jam 0.0040 409,734.89 1,645.52
4 Vibrator Roller E17 Jam 0.0047 364,587.15 1,695.99
5 Water Tanker E23 Jam 0.0141 241,954.95 3,400.97
6 Alat Bantu Ls 1.0000 0.00 0.00

JUMLAH HARGA PERALATAN 88,978.72

D. JUMLAH HARGA TENAGA, BAHAN DAN PERALATAN ( A + B + C ) 406,812.59


E. OVERHEAD & PROFIT 10.0 % x D 40,681.26
F. HARGA SATUAN PEKERJAAN ( D + E ) 447,493.85

Note: 1 SATUAN dapat berdasarkan atas jam operasi untuk Tenaga Kerja dan Peralatan, volume dan/atau ukuran
berat untuk bahan-bahan.
2 Kuantitas satuan adalah kuantitas perkiraan setiap komponen untuk menyelesaikan satu satuan pekerjaan
dari nomor mata pembayaran. Harga Satuan yang disampaikan Penyedia Jasa tidak dapat diubah kecuali
terdapat Penyesuaian Harga (Eskalasi/Deskalasi) sesuai ketentuan dalam Instruksi Kepada Peserta Lelang
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator.
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan (tetapi tidak termasuk PPN
yang dibayar dari kontrak) dan biaya-biaya lainnya.
ITEM PEMBAYARAN NO. : 5.1 (2) Analisa EI-512
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas B
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN

No. URAIAN KODE KOEF. SATUAN KETERANGAN

I. ASUMSI
1 Menggunakan alat berat (cara mekanik)
2 Lokasi pekerjaan : sepanjang jalan
3 Kondisi existing jalan : sedang
4 Jarak rata-rata Base Camp ke lokasi pekerjaan L 16.30 KM
5 Tebal lapis Agregat padat t 0.35 M
6 Berat isi padat Bip 1.81
7 Jam kerja efektif per-hari Tk 7.00 Jam
8 Lebar bahu jalan Lb 1.00 M
9 Proporsi Campuran : - Agregat Pecah Mesin 30 - 40 mm 30-40 10.00 % Gradasi harus
- Agregat Pecah Mesin 20 - 30 mm 20-30 20.00 % memenuhi
- Agregat Pecah Mesin 10 - 20 mm 10-20 15.00 % Spesifikasi
- Granular Material 0 - 50 mm 0-50 20.00
- Pasir PU 35.00 %
10 Berat volume agregat (lepas) Bil 1.51 ton/m3
- Agregat B Fh 1.05

II. URUTAN KERJA


1 Wheel Loader mencampur & memuat Agregat ke
dalam Dump Truck di Base Camp
2 Dump Truck mengangkut Agregat ke lokasi
pekerjaan dan dihampar dengan Motor Grader
3 Hamparan Agregat dibasahi dengan Water Tank Truck
sebelum dipadatkan dengan Vibratory Roller
4 Selama pemadatan sekelompok pekerja akan
merapikan tepi hamparan dan level permukaan
dengan menggunakan alat bantu

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA


1. BAHAN
- Bahan Agregat Base Kelas B M27 1.0000 M3

2. ALAT
2.a. WHEEL LOADER (E15)
Kapasitas bucket V 1.50 M3
Faktor bucket Fb 0.85 - Pemuatan lepas
Faktor Efisiensi alat Fa 0.83 - sedang
Waktu siklus Ts1
- Memuat dan lain-lain T1 0.45 menit panduan

Ts1 0.45 menit

Kap. Prod. / jam = V x Fb x Fa x 60 Q1 117.71 M3


(Bip/Bil) x Ts1
Koefisien Alat / M3 = 1 : Q1 (E15) 0.0085 Jam

2.b. DUMP TRUCK (E08)


Kapasitas bak V 10.00 ton
Faktor Efisiensi alat Fa 0.80 -
Kecepatan rata-rata bermuatan v1 40.00 KM / Jam
Kecepatan rata-rata kosong v2 60.00 KM / Jam
Waktu Siklus :
- Waktu memuat = (V x 60)/(Q1 x Bil) T1 3.38 menit
- Waktu tempuh isi = (L : v1) x 60 menit T2 24.45 menit
- Waktu tempuh kosong = (L : v2) x 60 menit T3 16.30 menit
- Lain-lain termasuk menurunkan Agregat T4 2.00 menit
Ts2 46.13 menit

Kap. Prod. / Jam = V x Fa x 60 Q2 5.75 M3


Ts2 x Bip
Koefisien Alat / M3 = 1 : Q2 (E08) 0.1739 Jam

Berlanjut ke halaman berikut


ITEM PEMBAYARAN NO. : 5.1 (2) Analisa EI-512
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas B
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

2.c. MOTOR GRADER (E13)


Panjang hamparaan Lh 50.00 M
Lebar efektif kerja blade b 1.00 M
Faktor Efisiensi alat Fa 0.83 -
Kecepatan rata-rata alat v 4.00 KM / Jam
Jumlah lintasan n 2.00 lintasan 1 x pp
Waktu Siklus Ts3
- Perataan 1 lintasan = (Lh x 60) : (v x 1000) T1 0.75 menit
- Lain-lain T2 1.00 menit
Ts3 1.75 menit

Kap.Prod. / jam = Lh x b x t x Fa x 60 Q3 249.00 M3


n x Ts3
Koefisien Alat / M3 = 1 : Q3 (E13) 0.0040 Jam

2.d. VIBRATOR ROLLER (E19)


Kecepatan rata-rata v 4.00 KM / Jam
Lebar efektif pemadatan b 1.48 M
Jumlah lintasan n 8.00 lintasan
Faktor Efisiensi alat Fa 0.83 -

Kap.Prod./jam = (v x 1000) x b x t x Fa Q4 214.97 M3


n
Koefisien Alat / M3 = 1 : Q4 (E17) 0.0047 Jam

2.e. WATER TANKER (E23)


Volume Tangki air V 4.00 M3 Lump Sum
Kebutuhan air / M3 agregat padat Wc 0.07 M3
Kapasitas pompa air pa 100.00 liter/menit
Faktor efisiensi alat Fa 0.83 -

Kap. Prod. / Jam = pa x Fa x 60 Q5 71.14 M3


1000 x Wc

Koefisien Alat / M3 = 1 : Q5 (E23) 0.0141 Jam

ALAT BANTU
diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah

3. TENAGA
Produksi menentukan : MOTO GRADER Q1 249.00 M3/Jam
Produksi Agregat / hari = Tk x Q1 Qt 1,743.00 M3
Kebutuhan tenaga :
- Pekerja P 7.00 orang
- Mandor M 1.00 orang

Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0281 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0040 Jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

Berlanjut ke halaman berikut


ITEM PEMBAYARAN NO. : 5.1 (2) Analisa EI-512
JENIS PEKERJAAN : Lapis Pondasi Agregat Kelas B
SATUAN PEMBAYARAN : M3 URAIAN ANALISA HARGA SATUAN
Lanjutan

No. URAIAN KODE KOEF. SATUAN KETERANGAN

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 447,493.85 / M3.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
ITEM PEMBAYARAN NO. : 6.3 (7a)
JENIS PEKERJAAN : Laston Lapis Pondasi (AC-Base)
SATUAN PEMBAYARAN : Ton

No. URAIAN KODE

2.h. ALAT BANTU


diperlukan :
- Kereta dorong = 2 buah
- Sekop = 3 buah
- Garpu = 2 buah
- Tongkat Kontrol ketebalan hanparan

3. TENAGA
Produksi menentukan : AMP Q2
Produksi AC-BC / hari = Tk x Q5 Qt
Kebutuhan tenaga :
- Pekerja P
- Mandor M

Koefisien Tenaga / M3 :
- Pekerja = (Tk x P) / Qt (L01)
- Mandor = (Tk x M) / Qt (L03)

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,292,410.54 / Ton.

6. WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M3
Analisa EI-637a

URAIAN ANALISA HARGA SATUAN


Lanjutan

KOEF. SATUAN KETERANGAN

Lump Sum

21.47 M3
150.26 M3

10.00 orang
1.00 orang

0.4659 Jam
0.0466 Jam
ITEM PEMBAYARAN NO. : 7.12 (2)
JENIS PEKERJAAN : Perletakan Elastomerik Jenis 2 (300 x 300 x 60)
SATUAN PEMBAYARAN : Buah

No. URAIAN KODE KOEF.

I. ASUMSI
1 Menggunakan alat (cara mekanik)
2 Lokasi pekerjaan di lokasi jembatan
3 Bahan / material diterima seluruhnya di lokasi
pekerjaan proyek
4 Jarak rata-rata Base camp ke lokasi pekerjaan L 16.30
5 Jam kerja efektif per-hari Tk 7.00

II. URUTAN KERJA


1 Material dan peralatan disiapkan
2 Elastomer dipasang dengan seksama
3 Penyelesaian dan perapihan setelah pemasangan

III. PEMAKAIAN BAHAN, ALAT DAN TENAGA

1. BAHAN
1.a. Elastomer per buah 1.000
1.b. Bahan Leveling Mortar (1 Semen : 2 Pasir) 0.006
- Semen 2.667
- Pasir 0.004

2. ALAT
2.a. Alat pertukangan dan lain-lain

3. TENAGA
Produksi pasang Elastomer dalam 1 hari
= Tk x Q1 = Qt 4.00

Kebutuhan tenaga : - Mandor M 1.00


- Tukang Tb 1.00
- Pekerja P 4.00

Koefisien Tenaga / M3 :
- Mandor = (Tk x M) : Qt (L03) 1.7500
- Tukang = (Tk x Tb) : Qt (L02) 1.7500
- Pekerja = (Tk x P) : Qt (L01) 7.0000
4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT
Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKEMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 1,632,146 / M2

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : ............

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 M1
Analisa EI-7122

URAIAN ANALISA HARGA SATUAN

SATUAN KETERANGAN

KM
jam

Buah
M3 untuk 1 Unit
Kg
M3

buah

orang
orang
orang

jam
jam
jam
ITEM PEMBAYARAN NO. : 8.4.(10)
JENIS PEKERJAAN : Kerb Pracetak
SATUAN PEMBAYARAN : M URAIAN ANALISA HARGA SATU

No. URAIAN KODE KOEF. SATUAN

Koefisien Tenaga / Bh :
- Mandor = (Tk x M) : Qt (L03) 0.0778 jam
- Tukang = (Tk x Tb) : Qt (L02) 0.1556 jam
- Pekerja = (Tk x P) : Qt (L01) 0.3891 jam

4. HARGA DASAR SATUAN UPAH, BAHAN DAN ALAT


Lihat lampiran.

5. ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam FORMULIR STANDAR UNTUK
PEREKAMAN ANALISA MASING-MASING HARGA
SATUAN.
Didapat Harga Satuan Pekerjaan :

Rp. 74,346.93 / Meter

6. MASA PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan : . . . . . . . . . . . bulan

7. VOLUME PEKERJAAN YANG DIPERLUKAN


Volume pekerjaan : 0.00 Buah
Analisa EI-8410

URAIAN ANALISA HARGA SATUAN


Lanjutan

KETERANGAN