Anda di halaman 1dari 22

PT.

DENKI ENGINEERING
Electrical & Mechanical Contractor

LAPORAN
OJT
(On the JobTraining)

Judul:
Analisa dan Pemeriksaan Sistim Proteksi Petir
Guna Peningkatan Kehandalan dan Keselamatan
di Gedung Kantor PT. Denki Engineering – Bekasi, Jawa Barat

Disusun dalam rangka syarat Sertifkasi Ahli K3


Listrik dari Kementerian Ketenagakerjaan RI

Oleh:

M. Sidrata, ST
NIP : 07150094

PT Denki Engineering
Electrical & Mechanical Contractor
Bekasi – Jawa Barat
2019
LEMBAR PENGESAHAN
LAPORAN OJT
SERTIFIKASI AHLI K3 LISTRIK

Judul:
Analisa dan Pemeriksaan Sistim Proteksi Petir
Guna Peningkatan Dalam Kehandalan dan Keselamatan
di Gedung Baru Kantor PT. Denki Engineering – Bekasi, Jawa Barat

Keterangan:

Pelatihan dan Sertifikasi Ahli K3 Listrik


tanggal 15 Juli - 07 Agustus 2019
di Bevos Training Center – Cikarang

Bekasi, 15 Agustus 2019

Disusun oleh :
Project Manager

M. Sidrata
NIP : 07150094

Mengetahui,

Direktur Manager Operasional

H. Umar Hamdan, ST Adhari Supriyatna, SE


NIP : 07070001 NIP : 07070002

Hal-1
ABSTRAK

Kesehatan dan keselamatan kerja (K3) merupakan hal yang paling penting dalam dunia kerja, baik
K3 secara umum maupun K3 bidang listrik. Hal ini sudah disimbolkan dalam slogan “Utamakan
Keselamatan” atau “Safety First”. Kaitan dengan K3 bidang listrik, pada Permenaker No 12 tahun 2015
tentang Keselamatan & Kesehatan Kerja Listrik di Tempat Kerja disebutkan bahwa perencanaan,
pemasangan, perubahan, dan pemeliharaan dilakukan oleh Ahli K3 Listrik. PT Denki Engineering
mengirimkan personil untuk mengikuti pelatihan dan sertifikasi Ahli K3 Listrik.

Salah satu tahapan pada sertifikasi Ahli K3 Listrik adalah melakukan On the Job Training (OJT) di
tempat kerja masing-masing selama satu bulan setelah training teori . Pada penulisan ini OJT dilakukan
pada gedung baru kantor PT Denki Engineering. Pada OJT ini dilakukan pemeriksaan dari gambar aktual
akhir (as-built drawing) dengan instalasi terpasang, dan pengukuran serta dilakukan analisa yang dilengkapi
rekomendasi.

Hal-2
DAFTAR ISI
LEMBAR PENGESAHAAN ................................................................................................................ 1
ABSTRAK.......................................................................................................................................... 2
DAFTAR ISI ...................................................................................................................................... 3
KATA PENGANTAR .......................................................................................................................... 4
BIODATA PENULIS .......................................................................................................................... 5

BAB I. PENDAHULUAN .................................................................................................................... 6


BAB I.1. LATAR BELAKANG ............................................................................................................. 6
BAB I.2. TUJUAN ............................................................................................................................. 6
BAB I.3. RUANG LINGKUP ............................................................................................................... 6

BAB II. SEKILAS PERUSAHAAN ........................................................................................................ 7


BAB II.1. RIWAYAT SINGKAT PERUSAHAAN ................................................................................... 7
BAB II.2. VISI DAN MISI PERUSAHAAN ........................................................................................... 13
BAB II.3. LOKASI PERUSAHAAN ...................................................................................................... 14

BAB III. PEMERIKSAAN, PENGUJIAN DAN PENGUKURAN PROTEKSI PETIR .................................... 15

BAB III.1. Proteksi atau Penangkal Petir .......................................................................................... 39


BAB III.1.1. Spesifikasi Proteksi Petir dan Pentanahan …................................................................. 39
BAB III.1.2. Hasil Pengukuran Pentanahan Sistim Proteksi Petir ….................................................. 41

BAB IV. KESIMPULAN ....................................................................................................................... 42

DAFTAR PUSTAKA ............................................................................................................................ 43

Hal-3
KATA PENGANTAR

Dengan mengucap Syukur Alhamdulillah penulis panjatkan kehadirat Allah SWT sehingga penulis
dapat mengikuti pelaksanaan pelatihan dan sertifikasi Ahli K3 Listrik di Hotel Ibis Cawang – Jakarta Timur
pada tanggal 17-29 Juli 2017 serta menyelesaikan tugas OJT di tempat kerja dengan baik. Selanjutnya
ucapan terima kasih juga penulis sampaikan kepada:

a. Bapak H. Umar Hamdan, ST (Direktur PT. Denki Engineering)


b. Bapak Adhari Supriyatna, SE (Manager Operasional PT. Denki Engineering)
c. Bapak Teguh Widiantoro, SH (Manager HSE PT. Denki Engineering)
d. Bapak Ir. Ganjar Budiarto (PT. BPSI Jakarta dan Pelaksana Kemenaker RI)
e. Bapak dan Ibu Tenaga Pengajar Ahli K3 Listrik BPSI dan Geo Mandiri Kreasi (GMK)
f. Tim PT. Building and Plant Safety Institute (BPSI)
g. Rekan-rekan seperjuangan Sertifikasi Ahli K3 Listrik dari BPSI Angkatan 4
h. Rekan-rekan kerja di MRTJ CP104 & CP105 Project
i. Istri dan anak tercinta Ani Irawati, SE (istri), Gita Irdina Lasmi (Anak ke-1),
dan Kenji Aryaguna Haryanto (anak ke-2)
j. Ayah dan Ibu tercinta Alm. Bapak Togin Sugianto dan Ibu Kuningsih

Semoga bantuan dan dukungan dari seluruh pihak dapat menjadi amal ibadah. Terimakasih atas
kerjasamanya.

Bekasi, 11 Nopember 2017

Erik Haryanto, ST
NIP. 07150094

Hal-4
BIODATA PENULIS

Nama : Erik Haryanto, ST


TTL : Cirebon / 30 Agustus 1978
Alamat : Mustika Emerald Town House Blok B No.3
Jl. Raya Mustikasari RT/RW 003/03 Kel. Mustikasari, Kec. Mustika Jaya
Bekasi Kota 17157 – Jawa Barat
Email : erik@ptdenki.com atau haryantoerik@gmail.com
Status : Menikah / Anak 2
Pendidikan Terakhir : S1 Teknik Elektro Institut Sains & Teknologi Akprind Yogyakarta
Pekerjaan : Karyawan PT. Denki Engineering
Jabatan Saat Ini : M/E Project Manajer

PENGALAMAN KERJA
2002 – 2006 : Laboratorium Institut Sains & Teknologi Akprind Yogyakarta
Sebagai Asisten Laboran Motor dan Kontrol Listrik Arus Kuat
2006 – 2013 : PT. Kinden Indonesia – Jakarta (Japanesse M/E constructions company)
Sebagai Electrical Engineer dan Electrical Senior Engineer
2013 – Sekarang : PT. Denki Engineering – Bekasi (Nasional M/E constructions company)

Hal-5
BAB I
PENDAHULUAN

I.1. LATAR BELAKANG


Kebutuhan akan keselamatan dan kesehatan kerja (K3) di lingkungan bekerja merupakan
hal yang mutlak di penuhi, sehingga bukan hanya sebagai keinginan atau simbolis saja tapi suatu
kebutuhan. Hal ini sudah disosialisasikan di seluruh perusahan di Indonesia bahkan Dunia melalui
slogan “Safety First” atau “Utamakan Keselamatan”. Ada banyak aspek yang berkaitan dengan K3,
salah satunya adalah K3 bidang listrik. Pekerjaan bidang kelistrikan memiliki banyak potensi
bahaya yang harus teridentifikasi dan dikendalikan sehingga butuh pengawasan ekstra pada saat
bekerja. Potensi bahaya bisa ditimbulkan dari penyebab langsung maupun tidak langsung. Sesuai
perundangan-undangan dan peraturan yang berlaku di Indonesia, setiap pekerjaan bidang listrik
harus dilakukan oleh orang yang memiliki kompetensi bidang listrik yang tersertifikasi.
Perundangan-undangan dan peraturan yang terkait dengan K3 termasuk bidang listrik adalah sbb:
a. UU No 1 Tahun 1970 - Keselamatan Kerja
b. UU No 13 Tahun 2003 - Ketenagakerjaan
c. Permenaker No 02 Tahun 1992 - Tata Cara Penunjukan Kewajiban&Wewenang Ahli K3
d. Permenaker No 12 Tahun 2015 - Keselamatan & Kesehatan Kerja Listrik di Tempat Kerja
e. Kepdirjen No 47 Tahun 2015 - Pembinaan Calon Ahli K3 Bidang Listrik
f. Kepdirjen No 48 Tahun 2015 - Pembinaan Teknisi K3 Listrik
PT. Denki Engineering yang merupakan kontraktor di bidang elektrikal dan mekanikal
berskala nasional mengirimkan personil yang memiliki kompetensi bidang listrik untuk dapat
mengikuti pelatihan dan sertifikasi Ahli K3 Listrik yang terselenggara di Hotel Ibis Cawang, Jakarta
Timur pada tanggal 17-29 Juli 2017.

I.2. TUJUAN
Perusahaan mengirimkan personil bidang kelistirikan untuk dapat mengikuti pelatihan dan
sertifikasi Ahli K3 Listrik dengan tujuan sbb :
a. Dapat meningkatkan kemampuan dan keterampilan dalam hal K3 terutama bidang listrik.
b. Dapat melaksanakan perencanaan, pemasangan, penggunaan, perubahan, pemeliharaan,
pemeriksaan dan pengujian bidang listrik di tempat kerja.
c. Dapat berupaya meningkatkan instalasi yang aman, handal dan memberikan keselamatan
bangunan beserta isinya di tempat kerja.
d. Dapat menciptakan tempat kerja yang selamat dan sehat untuk mendorong produktivitas.
e. Dapat melakukan pembinaan K3 di lingkungan kerja.

I.3. RUANG LINGKUP


On Job Training atau OJT ini dilakukan di gedung baru Kantor PT. Denki Engineering
selama bulan Agustus 2017 dengan ruang lingkup kerja adalah pemeriksaan serta analisa
instalasi kelistrikan tegangan rendah dan proteksi petir terpasang.

Hal-6
BAB II
SEKILAS PERUSAHAAN

II.1. RIWAYAT SINGKAT PERUSAHAAN


PT. Denki Engineering adalah suatu perusahaan jasa konstruksi di bidang mekanikal dan
elektrikal serta permesinan. Didirikan oleh H. Umar Hamdan, ST yang mana beliau berpengalaman
sebelumnya di perusahaan jepang konstruksi mekanikal dan elektrikal yaitu Kyudenko Corp.
Japan, PT. Rakintam, dan PT. Kinden Indonesia.
Berdiri pada tahun 2007 dimulai sebagai kontraktor umum dan pemasok (general
contractor & suppliers) diberbagai proyek gedung komersial dan industri atau pabrik (commercial
building and industry or factory), yang beralamatkan ;

Office : Sentra Niaga Kalimalang


Jl. Jend. Ahmad Yani Blok B1 No. 29 Kayuringin – Bekasi Selatan
Bekasi Kota 17144 – Jawa Barat
Workshop : Kampung Kali Pandan RT/RW 003/01 Teluk Jambe – Karawang Barat

Seiring berjalannya waktu perkembangan perusahaan semakin maju, pelanggan (customers or


clients) makin banyak dan karyawan makin bertambah serta sudah bersertifikasi ISO 9001:2008,
maka pada tahun 2016 bulan Oktober, PT. Denki Engineering menempati kantor baru,
yang beralamatkan ;

Office : Gedung Denki Engineering


Jl. Jend. Sudirman KM.32 No. 18A Kota Bekasi 17144 – Jawa Barat
Workshop : Kampung Kali Pandan RT/RW 003/01 Teluk Jambe – Karawang Barat

PT. Denki Engineering semakin memantapkan bisnisnya dibidang konstruksi berskala


nasional dibidang pekerjaan Elektrikal, Mekanikal, dan Permesinan, dengan bisnis utama atau
kegiatan usaha adalah sebagai berikut ;

1. LAYANAN EVALUASI PROYEK


 Desain, Teknik dan konsultasi konstruksi
 Analisis Pertimbangan Lingkungan

2. DESAIN dan JASA KONSTRUKSI


 Pekerjaan Elektrical (Electrical Works)
- Incoming 20 kV System
- Sub Station System
- Generator Sets System
- Main Feeder System
- Lighting & Receptacle System
- Sound or Public Address System
- Fire Alarm System
- Telephone & LAN System
- MATV System
- Security System
- Power Supply Mechanical System

Hal-7
- Outdoor Lighting System
- Lighting Protection System
- Instrumentation and Control System
- Building Automation System

 Pekerjaan Mekanical (Mekanical Works)


- Water Supply System
- Waste and Soil Water Drainage System
- Sanitary Fixture System
- Heating Ventilation &Air Conditioning System
- Hot and Cold Water System
- Boiler and Steam Supply System
- Fire Fighting System
- Swimming Pool and SPA System
- Gas System
- Installation and Setting Machinery System

 Pekerjaan Permesinan (Machinery Works)


- Machining System
- Spare Part For Furnace System
- Jig Fixture System
- Precision Part System
- Automation System
- Design Machinery System

PT. Denki Engineering berkomitmen terhadap keunggulan profesional, yang mana telah
memungkinkan untuk mencapainya, bahkan seringkali melebihi harapan pelanggan atau klien.
Pemanfaatan sumber daya manusia dan teknis yang efisien, juga memungkinkan menyelesaikan
suatu proyek dalam kerangka waktu dan anggaran yang ditetapkan, sambil mematuhi persyaratan
kinerja yang ketat serta didukung oleh kualitas, kecepatan, keamanan, efektivitas biaya dan teknisi
profesional.
Berikut adalah beberapa produk jasa konstruksi serta layanan evaluasi proyek yang telah
diselesaikan oleh segenap karyawan perusahaan PT. Denki Engineering dari tahun 2009 sampai
dengan 2017 sebagai berikut ;

Hal-8
NO. YEAR CUSTOMER NAME PROJECT NAME DETAIL SCOPE OF WORK

1 2009 PT. DENSO INDONESIA DENSO SUNTER Design, Installation Power Machine

Installation Electrical Utility (MVMDB, TR, LVMDB, Cable


2 2009 PT. TAIKISHA INDONESIA ENGINEERING PT. KOBELCO INDONESIA Feeder, Lighting Receptacle, Sound System, Fire Alarm,
Telephone, Lightning Protection

3 2009 PT. KAYABA INDONESIA PT. KAYABA INDONESIA Design, Installation for Sub Station (MVMDB, TR, LVMDB)

4 2009 PT. IW ATANI INDUSTRIAL GAS INDONESIA PT. IW ATANI INDUSTRIAL GAS INDONESIA Design, Installation Power Machine

5 2009 PT. AE AUTOMOTION INDONESIA PT. INDONESIA PRATAMA Design, Installation Power Machine

6 2009 PT. RINNAI INDONESIA PT. RINNAI INDONESIA Design, Installation Power Machine

7 2009 PT. MIYUKI INDONESIA PT. MIYUKI INDONESIA Design, Installation Power Machine

8 2009 PT. SANYO JAYA COMPONENTS INDONESIA PT. SANYO JAYA COMPONENTS INDONESIA Design, Installation Power Machine

9 2009 PT. SUMCO INDONESIA PT. SUMCO INDONESIA Design, Installation Fire Alarm System

10 2009 PT. SUPRAMAS SAKTI PT. CABININDO INDONESIA Design, Installation for Electrical (Lighting, Receptacle, LAN)

11 2009 PT. KYOTO THERM INDONESIA PT. KYOTO THERM INDONESIA Design, Installation for Electrical (Lighting, Receptacle, Power
Machine)

Design, Installation for M&E (Lighting, Receptacle, LAN, Fire


1 2010 PT. KATSUSHIRO INDONESIA PT. KATSUSHIRO INDONESIA
Alarm, TEL, Sound, A/C, Fan)

2 2010 PT. DENSO INDONESIA DENSO CIBITUNG PLANT Design, Installation Power Machine

3 2010 PT. KAYABA INDONESIA PT. KAYABA INDONESIA Design, Installation Ventilation System

4 2010 PT. INDONESIA NIPPON STEEL PIPE PT. INDONESIA NIPPON STEEL PIPE Design, Installation Ventilation System & Power Machine

5 2010 PT. KIMBERLY CLARK INDONESIA PT. KIMBERLY CLARK INDONESIA Design, Installation Ventilation System & Power Machine

6 2010 PT. SHIBATAYA ENGINEERING PT. KYOEI DENKI INDONESIA Design, Installation for Sub Station (MVMDB, TR, LVMDB)

7 2010 PT. DYNAPLAST PT. DYNAPLAST Design, Installation Ventilation System & Power Machine

8 2010 PT. ORBIT ENGINEERING INDONESIA PT. NESINAK INDONESIA Design, Installation Power Machine

1 2011 PT. PANASONIC SEMICONDUCTOR INDONESIA PT. PANASONIC SEMICONDUCTOR INDONESIA Design, Installation Power Machine

2 2011 PT. LANGGENG MULTI USAHA PT. LANGGENG MULTI USAHA Design, Installation Power Machine

3 2011 PT. SUMBER PIRANTI PAYLYA (PAM) Design, Installation Power Machine

Design, Installation for Electrical (Lighting, Receptacle, Power


4 2011 PT. FUJI TECHANICA INDONESIA PT. FUJI TECHANICA INDONESIA
Machine)
Installation Electrical Utility (MVMDB, TR, LVMDB, Cable
5 2011 PT. SHINRYO INDONESIA PT. NIPRO INDONESIA Feeder, Lighting Receptacle, Sound System, Fire Alarm,
Telephone, Lightning Protection

Design, Installation for Electrical (Lighting, Receptacle, Power


6 2011 PT. UNIVANCE INDONESIA PT. UNIVANCE INDONESIA
Machine)
Design, Installation for M&E(Lighting, Receptacle, LAN, TEL,
7 2011 SHIMIZU CORPORATION P&G PROJECT
A/C, Fan)

1 2012 PT. DENSO INDONESIA DENSO SUNTER Design, Installation Power Machine

Design, Installation for Electrical (Lighting, Receptacle, Power


2 2012 PP TAISEI INDONESIA CONSTRUCTION PT. TD AUTOMOTIVE COMPRESSSOR INDONESIA
Machine)
Design, Installation for Electrical (Lighting, Receptacle, Power
3 2012 PT. PANASONIC SEMICONDUCTOR INDONESIA PT. PANASONIC SEMICONDUCTOR INDONESIA
Machine)

4 2012 PT. INDONESIA NIPPON STEEL PIPE PT. INDONESIA NIPPON STEEL PIPE Design, Installation Ventilation System & Power Machine

5 2012 PT. KIMBERLY CLARK INDONESIA PT. KIMBERLY CLARK INDONESIA Design, Installation Power Machine

Hal-9
NO. YEAR CUSTOMER NAME PROJECT NAME DETAIL SCOPE OF WORK

Design, Installation for Electrical (Lighting, Receptacle, Power


6 2012 PT. AU AUTOMOTIVE COMPRESSOR INDONESIA PT. TD AUTOMOTIVE COMPRESSSOR INDONESIA
Machine)

7 2012 PT. UNIVANCE INDONESIA PT. UNIVANCE INDONESIA Design, Installation Power Machine

8 2012 PT. DJK INDONESIA PT. DJK INDONESIA Design, Installation Power Machine

Design, Installation M&E W orks (Sub-Station, Main Feeder,


Lighting Receptacle, Sound, Fire Alarm, TEL, CCTV, Lightning
1 2013 PT. INTI GRAHA SEMBADA PT. METAL ART ASTRA INDONESIA
Protection, A/C, Ventilation, Fire Hydrant, W ater supply, Cooling
Tower, Compressor)

Design, Installation Electrical Works (Sub-Station, Main


2 2013 JO. SHIMIZU-BANGUN CIPTA KONTRAKTOR PT. USUI INTERNATIONAL Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL, MATV,
Lightning Protection)

Design, Installation Electrical W orks (Sub-Station, Main


3 2013 JO. TECHNO RYOWA-GRAHA BARATA PT. INDO JAPAN STEEL CENTER Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL, MATV,
Lightning Protection)
Design, Installation Electrical Works (Sub-Station, Main Feeder,
4 2013 JO. TECHNO RYOWA-GRAHA BARATA PT. ARAYA STEEL TUBE Lighting Receptacle, Sound, Fire Alarm, TEL, Lightning
Protection)

Design, Installation Electrical Works (Sub-Station, Main


5 2013 JO. TECHNO RYOWA-GRAHA BARATA PT. SEIREN INDONESIA Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL,
Lightning Protection)

Design, Installation M&E W orks (Sub-Station, Main Feeder,


6 2013 JO. TECHNO RYOWA-GRAHA BARATA PT. MARIMO APARTMENT SERVICE Lighting Receptacle, Sound, Fire Alarm, TEL, MATV, CCTV,
ACESS CARD, Lightning Protection)

Design, Installation Electrical Works (Sub-Station, Main


7 2013 PT. ITO TAKA CONSTRUCTION PT. INTI KERTASINDO Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL,
Lightning Protection)

Design, Installation M&E W orks (Sub-Station, Main Feeder,


1 2014 PT. SWADAYA INDO PRIMA PT. SWADAYA INDO PRIMA Lighting Receptacle, Sound, Fire Alarm, TEL, Lightning
Protection, A/C, Ventilation, Water supply)

Design, Installation Electrical W orks (Sub-Station, Main


2 2014 JO. TECHNO RYOWA-GRAHA BARATA PT. UNITED CAN COMPANY Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL, CCTV,
Lightning Protection)
Design, Installation for Electrical (Lighting, Receptacle, Power
3 2014 PT. KATSUYAMASEIKI KKB INDONESIA KATSUYAMASEIKI KKB INDONESIA
Machine)

Design, Installation Electrical W orks (Sub-Station, Main


4 2014 JO. TECHNO RYOWA-GRAHA BARATA PT. TOP TUBE INDONESIA Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL, MATV,
Lightning Protection)

Design, Installation for Electrical (Lighting, Receptacle, Power


5 2014 PT. TAIHO NUSANTARA TAIHO NUSANTARA SAFETY
Machine)

Design, Installation Electrical W orks (Sub-Station, Main


6 2014 PT. ITO TAKA CONSTRUCTION PT. SASAHARA INDONESIA Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL,
Lightning Protection)

Design, Installation Electrical W orks (Sub-Station, Main


7 2014 JO. TECHNO RYOWA-GRAHA BARATA PT. F - TECH INDONESIA Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL,
Lightning Protection, Power Machine)

8 2014 JO. SHIMIZU-OBAYASHI-W IKA-JAKON MRT JAKARTA SOWJ SITE OFFICE Design, E le c t ric a l Installation W orks (Main Feeder, Lighting
Receptacle)

Design, Installation Electrical Works (Sub-Station, Main


9 2014 JO. TECHNO RYOWA-GRAHA BARATA PT. MITSUI KINZOKU ACT Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL,
Lightning Protection)
Installation Electrical Utility (MVMDB, TR, LVMDB, Cable
10 2014 PT. SHINRYO INDONESIA PT. TANABE INDONESIA Feeder, Lighting Receptacle, Sound System, Fire Alarm,
Telephone, Lightning Protection

11 2014 PT. DJABESMEN DJABESMEN Design, Installation Ventilation System

DENSO CIBITUNG PLANT-2 dan Plant 3, Design, Installation for Electrical (Lighting, Receptacle, Power
12 2014 PT. DENSO INDONESIA
DENSO SUNTER PLANT-1 Machine)
Design, Installation Electrical W orks (Main Feeder, Lighting
13 2014 SHIMIZU CORPORATION SHIMIZU NEW OFFICE
Receptacle, TEL)

14 2014 PT. KIMBERLY-CLARK INDONESIA KIMBERLY Design, Installation Power Machine

Design, Installation Electrical W orks (Main Feeder, Lighting


15 2014 JO. SHIMIZU-BANGUN CIPTA KONTRAKTOR JFE STEEL INDONESIA CGL Receptacle, Sound, Fire Alarm, TEL, LAN, Lightning
Protection)

H a l - 10
NO. YEAR CUSTOMER NAME PROJECT NAME DETAIL SCOPE OF WORK

16 2014 PT. TSKEI MOLDING INDONESIA PT. TSKEI MOLDING INDONESIA Design, Installation Power Machine

17 2014 PT. KINDEN INDONESIA PT. SUMCO INDONESIA Design, Installation Power Machine

17 2014 PT. KINDEN INDONESIA PT. SUMCO INDONESIA Design, Installation Power Machine

18 2014 PT. FRINA LESTARI NUSANTARA PT. FRINA LESTARI NUSANTARA Design, Installation Fire Alarm System

Design, Installation M&E W orks (Sub-Station, Main Feeder,


19 2014 PT. YAMATE METAL INDONESIA PT. YAMATE METAL INDONESIA Lighting Receptacle, TEL, Lightning Protection, Compressor ,

Design, Installation Electrical W orks (Main Feeder, Lighting


20 2014 JO. KANDENKO-HAMANROKO PT. TIGER SASH INDONESIA
Receptacle, Sound, Fire Alarm, TEL)

1 2015 CV. SINAR ALAM CEMERLANG PT. BENTOEL MALANG Design, Installation Mechanical & Electrical W orks

Design, Installation Mechanical & Electrical W orks (Sub-


2 2015 HAZAMA ANDO - MURINDA JO MITSUBA Station, Main Feeder, Lighting Receptacle)
Design, Installation Electrical W orks (Sub-Station, Main
3 2015 JO. SECM - DENKI MENARA ASTRA Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL,
Lightning Protection)

4 2015 JO. SHIMIZU TOTAL MENARA ASTRA Design, Installation Electrical W orks (temporary office)

Design, Supply and Installation of Electrical Work for Jakarta


5 2015 SHIMIZU-OBAYASHI-W IKA-JAKON JV (SOW J JV) MRT JAKARTA CP104 & CP105 MRT Project Underground Section

Design, Installation Electrical W orks (Sub-Station, Main


6 2015 JO. TECHNO RYOWA-GRAHA BARATA MEIJI RUBBER Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL, CCTV,
Lightning Protection)

Design, Installation Mechanical &Electrical W orks (Sub -


7 2015 JO. TECHNO RYOWA-GRAHA BARATA MESCO/MKAI Station, Main Feeder, Lighting Receptacle, Lightning
Protection)

Design, Installation Mechanical & Electrical W orks (Sub-Station,


8 2015 JO. TECHNO RYOWA-GRAHA BARATA SATO NAGATOMI SURABAYA Main Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL,
CCTV, Lightning Protection)

Design, Installation Electrical W orks (Sub-Station, Main


9 2015 JO. TECHNO RYOWA-GRAHA BARATA NISHO SOLUTION Feeder, Lighting Receptacle, Lightning Protection)
Design, Installation Electrical W orks (Sub-Station, Main
10 2015 JO. TECHNO RYOWA-GRAHA BARATA SHARP Feeder, Lighting Receptacle, chiller, Lightning Protection)

11 2015 JO. KANDENKO-DENKI MRT JAKARTA TEMPORARY WORKS Design, Installation Electrical W orks (MRT temporary)

Design, Installation Electrical W orks (Sub-Station, Main


12 2015 PT. BEST SINAR NUSANTARA ENSO HOTEL Feeder, Lighting Receptacle, Sound, Fire Alarm, TEL, AC,
Hydrant, Hot Water, Lightning Protection)

13 2015 PT. INDOIT TECHNOTRADE & CONSULTING PIRELLI Design, Installation Mechanical & Electrical W orks

Design, Installation M&E W orks (Sub-Station, Main Feeder,


14 2015 PT. INTI GRAHA SEMBADA EVOTY
Lighting Receptacle, Sound, Fire Alarm, TEL, Lightning

15 2015 PT. KAMIYA SAW & KNIFE INDONESIA PT. KAMIYA SAW & KNIFE INDONESIA Design, Installation Mechanical & Electrical W orks

Design, Installation Smoke detector, A larm,Power Analizer,


16 2015 PT. KIMBERLY-CLARK INDONESIA KIMBERLY Grounding Sytem

17 2015 PT. DJK INDONESIA PT. DJK INDONESIA Design, Installation Power Machine

18 2015 PT. DENSO INDONESIA DENSO SUNTER, CIBITUNG Design, Installation Power Machine & Maintenance

19 2015 PT. INDONESIA NIPPON STEEL PIPE PT. INDONESIA NIPPON STEEL PIPE Design, Installation Power Machine & Maintenance

20 2015 PT. DNP PT. DNP Design, Installation Power Machine & Maintenance

21 2015 PT. METALART ASTRA INDONESIA PT. METALART ASTRA INDONESIA Design, Installation Power Machine & Maintenance

22 2015 PT. KOKUSEI INDUSTRY INDONESIA PT. KOKUSEI INDUSTRY INDONESIA Design, Installation Mechanical & Electrical W orks

23 2015 PT. MARUSHIN INDONESIA PT. MARUSHIN INDONESIA Design, Installation Electrical W orks (Compressor & Air Dryer)

Design, Installation Electrical W orks (Lighting system,


24 2015 PT. O W ELL INDONESIA PT. O W ELL INDONESIA Lightning Protection)
Design, Installation Mechanical W orks (Plumbing System),
25 2015 PT. SHIMIZU BANGUN CIPTA KONTRAKTOR HPPM Services & relocation AC

26 2015 PT. SHIMIZU BANGUN CIPTA KONTRAKTOR MIURA Receptacle Work, Cable, Wiring Device, Cable Duct Floor

Design, Installation Electrical Works,Insurance Fee, Rental


27 2015 PT. SETSUYO ASTEC MUSASHI Lifter Hydrolic,Temporary Facility

H a l - 11
NO. YEAR CUSTOMER NAME PROJECT NAME DETAIL SCOPE OF WORK

1 2016 PT. DENSO INDONESIA DENSO 2ND PLANT Design, Installation Power Machine

2 2016 PT. DNP INDONESIA DNP INDONESIA Design, Installation Power Machine & Maintenance

3 2016 HAZAMA ANDO-MURINDA J.O MITSUBA INDONESIA Design, Installation Power Machine & Maintenance

4 2016 CV SINAR ALAM CEMERLANG MERAPI BENTOEL Design, Installation Power Machine & Maintenance

5 2016 PT.SHOWA WORKS INDONESIA PT. SHOWA WORKS INDONESIA Design, Installation Power Machine & Maintenance

6 2016 PT. METALART ASTRA INDONESIA METALART ASTRA INDONESIA Design, Installation Power Machine & Maintenance

7 2016 PT. INDONESIA NIPPON STEEL PIPE INP Design, Installation Power Machine & Maintenance

8 2016 PT. DAIHO INDONESIA PT. DAIHO INDONESIA Design, Installation Power Machine & Maintenance

9 2016 JO. TECHNO RYOWA-GRAHA BARATA EAST INDUSTRIAL 67-4 (61D1) Design, Installation Power Machine & Maintenance

10 2016 PT. YKK ZIPCO INDONESIA PT YKK ZIPCO INDONESIA Design, Installation Power Machine & Maintenance

Design, Installation M&E W orks (Sub-Station, Main Feeder,


Lighting Receptacle, Sound, Fire Alarm, TEL, Lightning
11 2016 PT. INTI GRAHA SEMBADA METAL ART ASTRA INDONESIA
Protection, A/C, Ventilation, Fire Hydrant, W ater supply,
Cooling Tower, Compressor)

12 2016 PT. KIMBERLY - CLARK INDONESIA PT. KIMBERLY - CLARK INDONESIA Design, Installation Mechanical & Electrical W orks

13 2016 PT. SHIMIZU BANGUN CIPTA KONTRAKTOR TOKIO MARINE LIFE INSURANCE ( HEAD OFFICE ) Design, Installation Mechanical & Electrical W orks

14 2016 PT. NECCO MANUFACTURING INDONESIA PT. NECCO MANUFACTURING INDONESIA Design, Installation Mechanical & Electrical W orks

15 2016 BUT. NTT FACILITIES INC. REPLACEMENT OUT DOOR LIGHTING Design, Installation Mechanical & Electrical W orks

16 2016 JO. SHIMIZU - TOTAL MENARA ASTRA PROJECT Design, Installation Mechanical & Electrical W orks

17 2016 PT. SHARP ELECTRONICS INDONESIA SHARP Design, Installation Mechanical & Electrical W orks

18 2016 KANDENKO - DENKI ENGINEERING JO PT. TIGER SASH INDONESIA Design, Installation Mechanical & Electrical W orks

HINO MOTOR MANUFACTURING INDONESIA


19 2016 PT. HAZAMA ANDO-MURINDA (KAIZEN BUILDING ) Design, Installation Mechanical & Electrical W orks

20 2016 PT. FUJI SHOKO INDONESIA PT FUJI SHOKO INDONESIA Design, Installation Mechanical & Electrical W orks

21 2016 PT. CLEVER TRADING INDONESIA PT. CLEVER TRADING INDONESIA Design, Installation Mechanical & Electrical W orks

22 2016 PT. DENSO SALES INDONESIA DENSO SALES SUNTER PLANT Design, Installation Mechanical & Electrical W orks

23 2016 PT. SMCC UTAMA INDONESIA MAXXIS PROJECT Design, Installation Mechanical & Electrical W orks

24 2016 PT. SWADAYA INDO PRIMA SWADAYA INDO PRIMA Design, Installation Mechanical & Electrical W orks

25 2016 PT. GLOBAL SHINSEI INDONESIA GLOBAL SHINSEI INDONESIA Design, Installation Mechanical & Electrical W orks

26 2016 PT. INDOIT TECHNOTRADE AND CONSULTING PT. PIRELI Design, Installation Mechanical & Electrical W orks

27 2016 PT. GIFU HITEC INDONESIA GIFU HITEC Design, Installation Mechanical & Electrical W orks

28 2016 BUT. SHIMIZU CORPORATION NEW JAKARTA OFFICE - 6TH FLOOR Design, Installation Mechanical & Electrical W orks

29 2016 PT. TECHNO RYOWA ENGINEERING PT.AJINOMOTO KKIC ( SAJIKU FACTORY ) Design, Installation Mechanical & Electrical W orks

30 2016 PT. JFE TECHNO RYOWA ENGINEERING JFE STEEL GALVANIZING INDONESIA Design, Installation Mechanical & Electrical W orks

31 2016 JO. KANDENKO - HAMANROKO OFFICE BUILDING AT SCBD LOT-10 Design, Installation Mechanical & Electrical W orks

32 2016 BUT. SUMITOMO CORPORATION PT. MUSASHI AUTO PARTS FEMS Design, Installation Mechanical & Electrical W orks

33 2016 PT. BENTOEL INTERNATIONAL INVESTAMA TBK. PT. BENTOEL Design, Installation Mechanical & Electrical W orks

34 2016 PT. USUI INTERNATIONAL INDONESIA USUI Design, Installation Mechanical & Electrical W orks

H a l - 12
NO. YEAR CUSTOMER NAME PROJECT NAME DETAIL SCOPE OF WORK

35 2016 PT. JAYA OBAYASHI (LEGE FACTORY) Design, Installation Mechanical & Electrical W orks

36 2016 PT. SHINRYO INDONESIA AEON MALL INDONESIA - SUNTER Design, Installation Mechanical & Electrical W orks

37 2016 PT. OGAWA INDONESIA PT. OGAWA INDONESIA Gen-Set installation work

38 2016 PT. NSK BEARINGS MANUFACTURING INDONESIA NSK Maintenance, Installation Mechanical & Electrical W orks

39 2016 PT. UDAKA ENGINEERING INDONESIA PT. UDAKA ENGINEERING INDONESIA Design, Installation Mechanical & Electrical W orks

40 2016 PT. TRANS REKREASINDO TRANS STUDIO MINI YOGYAKARTA Design, Installation Mechanical & Electrical W orks

41 2016 PT. NPR MANUFACTURING INDONESIA PT. NPR MANUFACTURING INDONESIA Design, Installation Mechanical & Electrical W orks

42 2016 PT. AJINOMOTO INDONESIA PT. AJINOMOTO INDONESIA - KARAWANG P L A N T Design, Installation Mechanical & Electrical W orks

43 2016 PT. TOA PLATING INDONESIA PT. TOA PLATING INDONESIA Design, Installation Mechanical & Electrical W orks

RAILWAY ELECTRIFICATION AND DOUBLE -


44 2016 MITSUBISHI-SUMITOMO JOINT OPERATION Design Mechanical & Electrical W orks
DOUBLE TRACKING OF JAVA MAIN LINE PROJECT

45 2016 PT. SETSUYO ASTEC LACEMENT PATLIGHT ATSUMITEC PROJECT 2ND ST Design, Installation Mechanical & Electrical W orks

Design, Supply and Installation of Electrical & M e c h a n i c a l


46 2016 TOKYU-OBAYASHI-W IKA-JAKON JV (TOW J JV) MRT JAKARTA CP101 & CP102 Work for Jakarta MRT Project E le va te d Section

Design, Supply and Installation of Electrical & M e c h a n i c a l


47 2016 OBAYASHI-SHIMZ-JAKON JV (OSJ JV) MRT JAKARTA CP103 Work for Jakarta MRT Project E le va te d Section

1 2017 PT. TIRTA INVESTAMA EXTENSION FACTORY AT SOLOK PLANT Design, Installation Mechanical & Electrical W orks

2 2017 PT. POIN INDUSTRIA MONITORING SISTEM PT. TUNG PEY INDONESIA Design, Installation Mechanical & Electrical W orks

3 2017 PT. HINO MOTOR MANUFACTURING INDONESIA PT. HINO INDONESIA Design, Installation Mechanical & Electrical W orks

4 2017 PT.CAP MOLD ENGINEERING INDONESIA PT.CAP MOLD ENGINEERING INDONESIA Design, Installation Mechanical & Electrical W orks

RAILWAY ELECTRIFICATION AND DOUBLE -


5 2017 MITSUBISHI-SUMITOMO JOINT OPERATION (MSJO) Installation of Mechanical & Electrical W orks
DOUBLE TRACKING OF JAVA MAIN LINE PROJECT

6 2017 PT. TIRTA INVESTAMA RE-LAYOUT MACHINES AT SENTUL PLANT Design, Installation Mechanical & Electrical W orks

II.2. VISI DAN MISI PERUSAHAAN


a. Visi Perusahaan
Perusahaan yang kompetitif dan andal, mampu melakukan sinergi dengan orang lain, dan
berusaha menjadi perusahaan konstruksi global. membuat karyawan makmur, berdedikasi
dan integritas tinggi, dan karyawan profesional yang dekat dengan teknologinya. Memiliki
lingkungan kerja yang harmonis, transparan dan kondusif untuk meningkatkan kreativitas dan
pemberdayaan karyawan.

b. Misi Perusahaan
Menyediakan layanan perdagangan dan teknis secara profesional untuk kepuasan pelanggan
dan kemakmuran pemangku kepentingan kami.

H a l - 13
II.3. LOKASI PERUSAHAAN

H a l - 14
BAB III
PEMERIKSAAN, PENGUJIAN DAN PENGUKURAN
PROTEKSI PETIR

III.1. PROTEKSI / PENANGKAL PETIR

III.1.1. SPESIFIKASI PROTEKSI PETIR DAN PENTANAHAN

a. Unit : Head Lightning Protection


b Lokasi : Roof Area
c. Fungsi : Pengamaan gedung dan peralatan didalamnya dari sambaran petir
Secara langsung
d Merk : Kurn R.80
e Tipe : Electrostatis Radius 80 meters
f. Tinggi Tiang : 5 meter
g. Tinggi Bangunan : ± 15 meter
h Detail Teknis : Lihat Skema Gambar Proteksi Petir

H a l - 15
a. Unit : Earthing Rod / Pipa Pentanahan dan Kabel Penyaluran
b. Lokasi : Kontrol Bok Mechanical Room
c. Fungsi : Media penyaluran tegangan sambaran petir ke tanah
d. Jenis Elektroda : Besi Ulir Dia.15mm
e. Panjang Elektroda : ± 2 meter
f. Jenis Penyaluran : Kabel NYA 70mm2
g. Kontrol Box : Concrete 400mm x 400mm x 500mm

H a l -18
4040
III.1.2. Hasil Pengukuran Pentanahan untuk Sistim Proteksi Petir
Oleh : Wahyu dan Staff Lapangan
Lokasi : Ruangan Mechanical Basement
Metoda : Pengukuran dan pengambilan data pada bok pentanahan

Spesifikasi Alat Yang Digunakan:


Alat : Digital Earth Tester
Merk : Kyoritsu
Tipe : 4105A
Kalibrasi : Manufacturer Calibration Tahun 2017
Metode Pengukuran : 3 Wire (2 wire untuk rod tester bantu dengan jarak 10 meters
Per-wire rod bantu dan 1 wire untuk rod sistim)
Mengukur : Tahanan Pentanahan sistim listrik (Ohm) dengan Range 20 Ohm

H a l -18
4141
Hasil Pengukuran 1 :
- Nilai Tahanan (Ohm) : Normal 1,39 Ohm (dibawah standar maksimum yang diizinkan 5 Ohm).

Hasil Pengukuran 2 :
- Nilai Tahanan (Ohm) : Normal 2,00 Ohm (dibawah standar maksimum yang diizinkan 5 Ohm).

H a l -18
4242
Hasil Pengukuran 3 :
- Nilai Tahanan (Ohm) : Normal 2,00 Ohm (dibawah standar maksimum yang diizinkan 5 Ohm).

Tabel hasil pengukuran pembumian dengan kedaleman ± 2 meter

Kedalaman (m) Pengukuran 1 (Ω) Pengukuran 2 (Ω) Pengukuran 3 (Ω) Modus (Ω)

2 1.99 2.00 2.00 2.00

H a l -18
4343
BAB IV
KESIMPULAN

Dari hasil OJT yang dilakukan di Gedung Kantor PT Denki Engineering dengan ruang lingkup kerja pada
Analisa Proteksi Petir, maka didapatkan kesimpulan sbb :

Dari hasil pengukuran pentanahan proteksi petir elektroda besi yang dipakai saat ini sudah
cukup baik karena didapatkan hasil 2 Ohm.
Jika memungkinkan rekomendasi kami dikarenakan posisi bak kontrol didalam ruangan dan
tempatnya sangat terbatas maka sebaiknya dibuatkan titik baru di area luar untuk penanaman
elektroda

H a l -18
4444
DAFTAR PUSTAKA

Kementerian Tenaga Kerja RI. 2014. Himpunan Peraturan Perundangan-undangan Keselamatan dan
Kesehatan Kerja.
Kementerian Ketenagakerjaan RI. 2014. Materi Pembinaan Ahli Keselamatan dan Kesehatan Kerja
(K3) Listrik
Modul BPSI Consultant. 2017. Sertifikasi Ahli K3 Listrik.
Badan Standarisasi Nasional. 2000. Persyaratan Umum Instalasi Listrik 2000 (PUIL 2000).
Badan Standarisasi Nasional. 2011. Persyaratan Umum Instalasi Listrik 2011 (PUIL 2011).

Anda mungkin juga menyukai