Pondasi Tapak Beton Type Bujursangkar

Project : Ruko Permata Juanda Surabaya


Client : Mr Bunawan
Engineer Checked Approved

Name Lutfi Ari


Date 5/7/2020 4:15

Data Struktur : Pu

Mu
1 Dimensi Kolom b = 400 mm b
h = 400 mm Muka Tanah
Type Kolom αs = 30
2 Dimensi Pondasi B = 2.40 m ha
L = 2.40 m B=L
ht = 0.40 m
3 Mutu Beton fc' = 20 Mpa ht
4 Mutu Baja fy' = 320 Mpa
5 Besi tulangan D = 19
(dipakai) L
6 BJ Beton γc = 24 KN/m3
L
Data Tanah :

6 Daya dukung tanah σt = 105 Kpa


7 Berat tanah γt = 17.20 KN/m3
8 Tebal tanah diatas ha = 1.20 m
pondasi
h
B
Data Beban :
B=L
9 Beban P ultimate Pult = 384 KN
10 Beban M ultimate Mult = 18.25 KNm

Result
Cek Status Pondasi :

Tegangan yang terjadi pada tanah σmaks = 104.82767 < 105 OK!
σmin = 88.98566 < 105 OK!

Kontrol gaya geser 1 arah Ø.Vc = 422.617


Vu = 168.620 < 422.617 OK!

Kontrol gaya geser 2 arah Ø.Vc = 1007.237


Vu = 508.641 < 1007.237 OK!

Penulangan Pondasi
Arah X = Y D 19 - 219

Author : Lutfi Andrian, WS


WEB : www.kampustekniksipil.co.cc
E-mail : lutfi.andrian@rocketmail.com
CR 2011
SKEMA HITUNGAN PONDASI

Data : tebal fondasi (ht, d, ds), mutu bahan


Mutu Bahan (Fc, Fy)
Beban (Pu, Mu)
Daya dukung tanah (σt)

Penentuan Dimensi Pondasi

Pult Mu,x Mu,y


σ = + + + q ≤ σt
2 2
B x L 1/6 B x L 1/6 B x L

Menghitung tegangan tanah didasar fondasi

Pult Mu,x Mu,y


σmaks = + + + q ≤ σt
2 2
B x L 1/6 B x L 1/6 B x L

Pult Mu,x Mu,y


σmin = - - + q ≤ σt
2 2
B x L 1/6 B x L 1/6 B x L

Kontrol gaya geser 1 arah

σmaks + σa
Vu = a x B
2
Dimana
L - a x σmaks - σmin
σa = σmin +
L
fc'
Vc = x B x d
6
Syarat :
Vu ≤ Ø Vc dengan Ø = 0.75

Kontrol gaya geser 2 arah

σmaks +
Vu = B2 - b + d h + d x
2

Dipilih nilai Vc terkecil dari :

2 fc' bo d
Vc1 = 1 + x
βc 6

αs d fc' bo d
Vc2 = 2 + x
bo 12

1
Vc3 = x fc' bo d
3
Syarat :

Vu ≤ Ø Vc dengan Ø = 0.75

Hitung Penulangan Fondasi

1) ds = 75 + D + D/2
dimana
d = h - ds

2) σx = σmin + B - x x σmaks - σmin

σmaks - σx
3) Mu = 0.5 σx x 2 + x 2
3
Mu
4) K = , b = 1000
Ø x b x d2

382.5 x 0.85 x 600 + fy - 225 x β1


5) Kmaks =
600 + fy 2

2 x K
6) a' = 1 - 1 - d
0.85 x fc'

0.85 x fc' x a x b
7) As(1) =
fy

8) fc' ≤ 31.36 Mpa


maka

1.4 x b x d
As(2) ≥ Pilih "As" yang
fy terbesar

fc' > 31.36 Mpa


maka

fc' x b x d
As(3) =
4 fy

9) Jarak tulangan

0.25 x phi x D 2
s = S
As terpilih
Pilih "s" yang
s ≤ 2 x ht terkecil

s ≤ 450

Cek Kuat Dukung Fondasi

Pu = Ø x 0.85 x fc' x A ..... ( Ø = 0,7 )

Syarat : Pult ≤ Pu

Referensi : Asroni, A., Buku Kolom Fondasi & Balok T Beton Bertulang,
Notasi :

σ = Tegangan yang terjadi pada dasar fondasi ...........


σt = Daya dukung tanah ...........
Pult = Beban axial terfaktor pada kolom...........
B,L = Panjang dan lebar fondasi
Mu,x = Momen terfaktor kolom searah sumbu X ...........
Mu,y = Momen terfaktor kolom searah sumbu Y ...........
q = Beban terbagi rata akibat beban sendiri fondasi
ditambah beban tanah diatas fondasi ...........
ht = Tebal fondasi ≥ 150 mm
(lihat pasal 17.7 SNI 03-2847-2002)
ha = Tebal tanah diatas fondasi ...........
γc = Berat per volume beton ...........
γt = Berat per volume tanah ...........
Vu = Gaya geser pons terfaktor...........
Vc = Gaya geser yang sanggup ditahan oleh beton...........
Ø = Faktor keamanan = 0,7 (lihat SNI)
βc = Rasio dari sisi panjang terhadap sisi pendek pada
kolom, daerah beban terpusat / atau daerah reaksi
bo = Keliling penampang krisis dari fondasi ...........
αs = Suatu konstanta yang digunakan untuk menghitung
Vc , yang nilai tergantung pada letak fondasi,
40 = Kolom dalam
30 = Kolom tepi
20 = Kolom sudut
σmin = Tegangan tanah minimum ...........
σmaks = Tegangan tanah maksimum ...........
σa = Tegangan tanah sejarak "a" dari tepi fondasi ..........
σx = Tegangan tanah sejarak "x" dari tepi fondasi ..........
a = Jarak dari area bidang yang menerima tekanan
keatas dari tanah (area keruntuhan)
fc' = Kuat tekan beton ...........
fy = Mutu beton ...........
ds = decking
minimal = 75 mm (berhubungan dengan tanah)
D = Diameter tulangan ...........
a' = Tinggi blok tegangan beton teka persegi ekivalen
Mu = Momen yang terjadi padafondasi
K, Kmaks = Faktor momen pikul
s = Jarak tulangan ...........
As = Luas besi tulangan yang dibutuhkan ...........
σmin

fc'
ilih "As" yang

ilih "s" yang


(Kpa) atau KN/m2
(Kpa) atau KN/m2
KN
m
KNm
KNm

(KN/m2)
mm

mm
KN/m3
KN/m3
KN
KN

mm

(Kpa) atau KN/m2


(Kpa) atau KN/m2
(Kpa) atau KN/m2
(Kpa) atau KN/m2
mm

Mpa
Mpa
mm

mm
mm

mm
mm2
Job No. Sheet No
1
Program Hitung Pondasi Tapak
Part
Job Title Ref
Ruko Permata Juanda Surabaya Enginner Lutfi Date
Client. Mr Bunawan File Date/time 5/7/2020 4:15

Analisa

q = Berat Fondasi + Berat Tanah


= ht x γc + ha x γt
= 0.40 x 24 + 1.20 x 17.20
= 30.24 KN/m2

Cek Fondasi Terhadap Tegangan Izin Tanah

Tegangan yang terjadi pada tanah

Pult Mult
σmaks = + + q ≤ σt
B x L 1/6 B x L2

384 18.25
= + + 30.24 ≤ 105
2.40 x 2.40 1/6 2.40 x 2.40 2

= 66.666667 + 7.921 + 30.24

= 104.828 ≤ 105 Save!

Pult Mult
σmin = - + q ≤ σt
B x L 1/6 B x L2

384 18.25
= - + 30.24 ≤ 105
2.40 x 2.40 1/6 2.40 x 2.40 2

= 66.666667 - 7.921 + 30.24

= 88.986 ≤ 105 Save!

Kontrol Tegangan Geser 1 Arah

0.40
ds = 75 + D/2
= 75 + 9.50
= 85.00 mm

d = ht - ds
= 400 - 85.00
0.40 = 315.00

L = 2.40 a = B/2 - b/2 - d


= 1200 - 200 - 315.00
2.40 = 685.00 mm
= 0.685 m

σa = σmin + B - a x σmaks - σmin b

= 88.986 + 2.40 - 0.685 x 104.828 - 88.986 2.40


2.40
0.4 = 100.306 KN/m2

Gaya tekan ke atas dari tanah (Vu)

Vu = a x B x σmaks + σa 2
0.4
= 0.685 x 2.40 x 104.828 + 100.306 2

= 168.620 KN
Job No. Sheet No
1
Program Hitung Pondasi Tapak
Part
Job Title Ref
Ruko Permata Juanda Surabaya Enginner Lutfi Date
Client. Mr Bunawan File Date/time 5/7/2020 4:15

0.40 0.315 0.685 Gaya geser yang dapat ditahan oleh beton (Ø.Vc)

fc'
Ø.Vc = Ø x x B x d
6
20
= 0.75 x x 2.40 x 315.00
6
0.315
= 422.617 KN
2.40
Ø.Vc = 422.617 > Vu = 168.620 ......... Save!

σmin σa σmaks
88.986 100.306 104.828

Kontrol Tegangan Geser 2 Arah (Geser Pons)

Dimensi Kolom, b = 400


h = 400

b + d = 400.00 + 315.00 = 715.00 mm = 0.715 m


h + d = 400 + 315.00 = 715.00 mm = 0.715 m

Gaya Tekan Ke Atas (Geser Pons)

σmaks + σmin
Vu = B2 - b + d x h + d x
2

104.828 + 88.986
= 2.40 2 - 0.715 x 0.715 x
2
= 508.64129

hk 400
βc = = = 1.000
Bk 400

bo = 2 x bk + d + hk + d

bo = 2 x 400 + 315.00 + 400 + 315.00

= 2860 mm

Gaya geser yang ditahan oleh beton

2 fc' bo d
Vc1 = 1 + x
βc 6
0.158

2 20 2860 315.00
0.40
Vc1 = 1 + x
1.000 6
0.158

Vc1 = 2014473.641 N
= 2014.474 KN

0.843 0.158 0.40 0.158 0.8425


αs d fc' bo d
Vc2 = 2 + x
bo 12

30 315.00 20 2860 315.00


Vc2 = 2 + x
0.315 2860 12

0.085 Vc2 = 1445114.832 N


2.40 = 1445.115 KN
Job No. Sheet No
1
Program Hitung Pondasi Tapak
Part
Job Title Ref
Ruko Permata Juanda Surabaya Enginner Lutfi Date
Client. Mr Bunawan File Date/time 5/7/2020 4:15

1
Vc3 = x fc' bo d
3
1
σmin Vc3 = x 20 2860 315.00
88.986 σmaks 3
104.828
= 1342982.4273 N
= 1342.982 KN

Jadi

Vc1 = 2014.474
Vc2 = 1445.115 Diambil yang terkecil
Vc3 = 1342.982

Vc = 1342.982 KN
Ø.Vc = 0.75 x 1342.982
= 1007.237 KN

Ø.Vc = 1007.237 > Vu = 508.641 ......... Save!

Hitungan Penulangan Fondasi

0.40 ds = 75 + 19 + 9.5
= 103.500 mm
≈ 0.105 m
1.00
1.20 d = ht - ds
= 0.40 - 0.105
= 0.295 m
0.40 0.295 = 295 mm
0.105
B h
2.40 x = -
2 2

2400 400
x = -
2 2
σmin σx σmaks x = 1000 mm
88.986 98.227 104.828 = 1 m

σx = σmin + B - x x σmaks - σmin B

σx = 88.986 + 2.40 - 1 x 104.828 - 88.986 2.40


`
= 98.227 KN/m3

σmaks - σx
Mu = 0.5 σx x 2 + x 2
3
104.828 - 98.227
= 0.5 98.227 1 2 + 1 2
3
= 51.314 KNm

Mu
K =
Ø x b x d 2

51313696.952
=
0.8 x 1000 x 295 2

= 0.737 Mpa
Job No. Sheet No
1
Program Hitung Pondasi Tapak
Part
Job Title Ref
Ruko Permata Juanda Surabaya Enginner Lutfi Date
Client. Mr Bunawan File Date/time 5/7/2020 4:15

382.5 x 0.85 x 600 + fy - 225 x β1 fc'


Kmaks =
600 + fy 2

382.5 x 0.85 x 600 + 320 - 225 x 0.85 20


Kmaks =
600 + 320 2

= 5.599 Mpa

K < Kmaks
K = 0.737 < Kmaks = 5.599 ......... OK!

2 x K
a' = 1 - 1 - d
0.85 x fc'

2 x 0.737
= 1 - 1 - 295
0.85 x 20

= 13.080 mm

0.85 x fc' x a' x b


As(1) =
fy

0.85 x 20 x 13.080 x 1000


=
320
= 694.877 mm2

Jika
fc' ≤ 31.36 Mpa
maka
1.4 x b x d
As ≥ ........... (R.1)
fy ....... SNI 03-2847-2002 (Pasal 12.5.1)

Jika
fc' > 31.36 Mpa
maka
fc' x b x d
As = ........... (R.2)
4 fy ....... SNI 03-2847-2002 (Pasal 12.5.1)

fc' = 20 < 31.36


maka yang dipakai adalah pers ..................... (R.1)

1.4 x b x d fc' x b x d
As(2) = ....... (R.1) As(2') = ....... (R.2)
fy 4 fy

1.4 x 1000 x 295 0 x 0 x 0


= =
320 4 0

= 1290.625 mm2 ........... As dipakai = #DIV/0! mm2 ........... As tidak Dipakai!

Dipilih yang terbesar dari As(1) dan As(2)......... Sehingga,

As(1) = 694.877 mm2


As = 1290.625 mm2
As(2) = 1290.625 mm2
Job No. Sheet No
1
Program Hitung Pondasi Tapak
Part
Job Title Ref
Ruko Permata Juanda Surabaya Enginner Lutfi Date
Client. Mr Bunawan File Date/time 5/7/2020 4:15
Jarak tulangan,

0.25 x phi x D 2 x S
s =
As

0.25 x 3.14 x 19 2 x 1000


=
1290.625

= 219.572 mm

s ≤ 2 x ht
≤ 2 x 400
≤ 800

s ≤ 450 mm

Dipilih (s) yang terkecil = 219.572 mm

Jadi dipakai tulangan = D 19 - 219


Job No. Sheet No
2
Program Hitung Pondasi Tapak
Part
Job Title Ref
Ruko Permata Juanda Surabaya Enginner Date
Client. Mr Bunawan File Date/time 5/7/2020 4:15

Cek Panjang Penyaluran Tegangan Tulangan

9 x fy x α β x γ x λ
Panjang penyaluran tegangan (λd) = db
c + Ktr
10 fc'
db

9 x 320 x 1 1 x 0.8 x 1
= 19
75 + 0
10 20
19

9 x 320 x 1 1 x 0.8 x 1
= 19

10 20 2.5

= 391.544 mm > 300 mm


≈ 392 mm

B Bk
Panjang Tersedia (λt) = - - 75
2 2

2400 400
= - - 75
2 2

= 925

Panjang Tersedia (λt) > Panjang penyaluran tegangan (λd)


925 > 392 ....... OK!

Kuat Dukung Fondasi

Pu = Ø x 0.85 x fc' x A

= 0.7 x 0.85 x 20 x 160000

= 1904000 N

= 1904 KN

Pu,k = 384 KN

Pu = 1904 > Pu,k = 384 ....... OK!


Job No. Sheet No
2
Program Hitung Pondasi Tapak
Part
Job Title Ref
Ruko Permata Juanda Surabaya Enginner Date
Client. Mr Bunawan File Date/time 5/7/2020 4:15

SKSNI 03-2847-2002
Job No. Sheet No
2
Program Hitung Pondasi Tapak
Part
Job Title Ref
Ruko Permata Juanda Surabaya Enginner Date
Client. Mr Bunawan File Date/time 5/7/2020 4:15
Job No. Sheet No
3
Program Hitung Pondasi Tapak
Part
Job Title Ref
Ruko Permata Juanda Surabaya Enginner Date
Client. Mr Bunawan File Date/time 5/7/2020 4:15

2.40

2.40

D 19 - 219

DETAIL PONDASI
Non Scale

400

D 19 - 219

400 295

105
2400

POTONGAN 1-1
Non Scale

SNI 03-2847-2002 (Pasal 17.4.3)

SNI 03-2847-2002 (Pasal 17.7)

SNI 03-2847-2002 (Pasal 9.7.1)