Data Struktur : Pu
Mu
1 Dimensi Kolom b = 700 mm b
h = 400 mm Muka Tanah
Type Kolom αs = 30
2 Dimensi Pondasi B = 2.40 m ha
L = 2.40 m B=L
ht = 0.40 m
3 Mutu Beton fc' = 20 Mpa ht
4 Mutu Baja fy' = 320 Mpa
5 Besi tulangan D = 19
(dipakai) L
6 BJ Beton γc = 24 KN/m3
L
Data Tanah :
Result
Cek Status Pondasi :
Tegangan yang terjadi pada tanah σmaks = 104.82767 < 105 OK!
σmin = 88.98566 < 105 OK!
Penulangan Pondasi
Arah X = Y D 19 - 219
σmaks + σa
Vu = a x B
2
Dimana
L - a x σmaks - σmin
σa = σmin +
L
fc'
Vc = x B x d
6
Syarat :
Vu ≤ Ø Vc dengan Ø = 0.75
Kontrol gaya geser 2 arah
σmaks +
Vu = B2 - b + d h + d x
2
2 fc' bo d
Vc1 = 1 + x
βc 6
αs d fc' bo d
Vc2 = 2 + x
bo 12
1
Vc3 = x fc' bo d
3
Syarat :
Vu ≤ Ø Vc dengan Ø = 0.75
1) ds = 75 + D + D/2
dimana
d = h - ds
σmaks - σx
3) Mu = 0.5 σx x 2 + x 2
3
Mu
4) K = , b = 1000
Ø x b x d2
2 x K
6) a' = 1 - 1 - d
0.85 x fc'
0.85 x fc' x a x b
7) As(1) =
fy
1.4 x b x d
As(2) ≥ Pilih "As" yang
fy terbesar
fc' x b x d
As(3) =
4 fy
9) Jarak tulangan
0.25 x phi x D 2
s = S
As terpilih
Pilih "s" yang
s ≤ 2 x ht terkecil
s ≤ 450
Syarat : Pult ≤ Pu
Referensi : Asroni, A., Buku Kolom Fondasi & Balok T Beton Bertulang,
Notasi :
fc'
ilih "As" yang
(KN/m2)
mm
mm
KN/m3
KN/m3
KN
KN
mm
Mpa
Mpa
mm
mm
mm
mm
mm2
Program Hitung Pondasi Tapak
Job Title
Ruko Permata Juanda Surabaya
Client. Mr Bunawan
Analisa
Pult Mult
σmaks = + + q
B x L 1/6 B x L2
384 18.25
= + + 30.24
2.40 x 2.40 1/6 2.40 x 2.40 2
Pult Mult
σmin = - + q
B x L 1/6 B x L 2
384 18.25
= - + 30.24
2.40 x 2.40 1/6 2.40 x 2.40 2
0.40
ds = 75 + D/2
= 75 + 9.50
= 85.00 mm
d = ht - ds
= 400 - 85.00
0.40 = 315.00
σa = σmin + B
= 88.986 + 2.40
2.40
0.7 = 100.306 KN/m2
Vu = a x B
0.4
= 0.685 x 2.40
= 168.620 KN
0.40 0.315 0.685 Gaya geser yang dapat ditahan oleh beton (Ø.Vc)
Ø.Vc = Ø x
= 0.75 x
0.315
= 422.617 KN
2.40
Ø.Vc = 422.617 >
σmin σa σmaks
88.986 100.306 104.828
Vu = B2 - b + d x h + d
104.828 + 88.986
= 2.40 2 - 1.015 x 0.715 x
2
= 487.85481
hk 700
βc = = = 1.750
Bk 400
bo = 2 x bk + d + hk + d
= 3460 mm
0.40
Vc1 = 1 +
0.158
Vc1 = 1740778.920
= 1740.779
Vc2 = 2 +
Vc2 = 2 +
0.315
Jadi
Vc1 = 1740.779
Vc2 = 1515.551 Diambil yang terkecil
Vc3 = 1624.727
Vc = 1515.551 KN
Ø.Vc = 0.75 x 1515.551
= 1136.663 KN
0.40 ds = 75 + 19
= 103.500 mm
≈ 0.105 m
1.00
1.20 d = ht - ds
= 0.40 - 0.105
= 0.295 m
0.40 0.295 = 295 mm
0.105
B h
2.40 x = -
2 2
2400 700
x = -
2 2
σmin σx σmaks x = 850 mm
88.986 99.217 104.828 = 0.85 m
Mu
K =
Ø x b x d 2
37193373.700
=
0.8 x 1000 x 295 2
= 0.534 Mpa
382.5 x 0.85 x 600 + fy - 225 x
Kmaks =
600 + fy 2
= 5.599 Mpa
K < Kmaks
K = 0.534 < Kmaks = 5.599 ......... OK!
2 x K
a' = 1 - 1 - d
0.85 x fc'
2 x 0.534
= 1 - 1 - 295
0.85 x 20
= 9.421 mm
Jika
fc' ≤ 31.36 Mpa
maka
1.4 x b x d
As ≥ ........... (R.1)
fy ....... SNI 03-2847-2002 (Pasal 12.5.1)
Jika
fc' > 31.36 Mpa
maka
fc' x b x d
As = ........... (R.2)
4 fy ....... SNI 03-2847-2002 (Pasal 12.5.1)
0.25 x phi x D 2 x S
s =
As
= 219.572 mm
s ≤ 2 x ht
≤ 2 x 400
≤ 800
s ≤ 450 mm
Part
Ref
Enginner Lutfi Date
File Date/time 9/23/2022 11:21
≤ σt
≤ 105
≤ σt
≤ 105
- d
- 315.00
- a x σmaks - σmin b
x σmaks + σa 2
x 104.828 + 100.306 2
n (Ø.Vc)
fc'
x B x d
6
20
x 2.40 x 315.00
6
mm = 1.015 m
mm = 0.715 m
σmaks + σmin
x
2
2 fc' bo d
x
βc 6
2 20 3460 315.00
x
1.750 6
N
KN
αs d fc' bo d
x
bo 12
N
KN
bo d
3460 315.00
+ 9.5
2
2
β1 fc'
0.85 20
x b x d
....... (R.2)
4 fy
x 0 x 0
4 0
9 x fy x α β x γ x λ
Panjang penyaluran tegangan (λ d) = db
c + Ktr
10 fc'
db
9 x 320 x 1 1 x 0.8 x 1
= 19
75 + 0
10 20
19
9 x 320 x 1 1 x 0.8 x 1
= 19
10 20 2.5
B Bk
Panjang Tersedia (λt) = - - 75
2 2
2400 700
= - - 75
2 2
= 775
Pu = Ø x 0.85 x fc' x A
= 3332000 N
= 3332 KN
Pu,k = 384 KN
2.40
2.40
D 19 - 219
DETAIL PONDASI
Non Scale
400
D 19 - 219
400 295
105
2400
POTONGAN 1-1
Non Scale