RAB Rumah 1 Unit Dan Time Schedule - Proyeksipil - Blogspot.co - Id
RAB Rumah 1 Unit Dan Time Schedule - Proyeksipil - Blogspot.co - Id
proyeksipil.blogspot.com
Daftar Harga Bahan dan Upah
Proyek : Rumah 1 Unit
Lokasi : Indonesia
B. Harga Upah
No. Uraian Satuan Harga Satuan (Rp.)
1 Mandor m3 120,000
2 Kepala tukang m3 100,000
3 Tukang batu kg 90,000
4 Tukang kayu m3 90,000
5 Tukang besi / tukang las ltr 90,000
6 Pekerja tak terlatih kg 65,000
Analisa Harga Satuan Bahan dan Upah
Proyek : Rumah 1 Unit
Lokasi : Indonesia
16,800.00
57,600.00
260.00
6,500.00
9,000.00
1,000.00
600.00
74,660.00 17,100.00 91,760.00
39,000.00
7,200.00
- 46,200.00 46,200.00
108,000.00
19,500.00
1,200.00
108,000.00 20,700.00 128,700.00
960,000.00
19,500.00
2,000.00
1,338,750.00
40,500.00
403,200.00
54,000.00
214,650.00
344,500.00
24,750.00
117,000.00
94,500.00
26,200.00
31,800.00
3,032,600.00 638,750.00 3,671,350.00
``
No. Uraian Pekerjaan Jumlah Harga [Rp.]
Terbilang : Delapan Puluh Juta Tiga Ratus Empat Belas Ribu Rupiah
proyeksipil.blogspot.com
WAKTU PELAKSANAAN (TIME SCHEDULE)
PROYEK PEMBANGUNAN ………
JUMLAH
BOBOT
NO URAIAN PEKERJAAN HARGA
(RP.) (%)
A PEKERJAAN PENDAHULUAN 26,651,680.00 7.50
B PEKERJAAN PONDASI 53,663,264.00 15.10
C PEKERJAAN STRUKTUR 100,000,000.00 28.14
D PEKERJAAN DINDING BATA 40,000,000.00 11.26
E PEK. KUSEN, PINTU, JENDELA, DAN AKSESORIS 30,000,000.00 8.44
F PEKERJAAN INSTALASI LISTRIK 15,000,000.00 4.22
G PEKERJAAN SANITAIR 15,000,000.00 4.22
H PEKERJAAN ATAP BETON 55,000,000.00 15.48
I PEKERJAAN FINISHING 20,000,000.00 5.63
JUMLAH = 355,314,944.00 100.00
proyeksipil.blogspot.co.id
WAKTU PELAKSANAAN (TIME SCHEDULE)
PROYEK PEMBANGUNAN ………
JUMLAH W
BOBOT
NO URAIAN PEKERJAAN HARGA MARET 2017
(RP.) (%) 1 2 3
A PEKERJAAN PENDAHULUAN 26,651,680.00 7.50
IN
B PEKERJAAN PONDASI 53,663,264.00 15.10
SE
C PEKERJAAN STRUKTUR 100,000,000.00 28.14 RT
D PEKERJAAN DINDING BATA 40,000,000.00 11.26 -
8.44
IN
E PEK. KUSEN, PINTU, JENDELA, DAN AKSESORIS 30,000,000.00
SE
F PEKERJAAN INSTALASI LISTRIK 15,000,000.00 4.22
RT
G PEKERJAAN SANITAIR 15,000,000.00 4.22 SH
H PEKERJAAN ATAP BETON 55,000,000.00 15.48 EE
5.63
T
I PEKERJAAN FINISHING 20,000,000.00
RO
JUMLAH = 355,314,944.00 100.00 W
WAKTU PELAKSANAAN PEKERJAAN = 4 BULAN
ARET 2017 APRIL 2017 MEI 2017 JUNI 2017 KET.
4 1 2 3 4 1 2 3 4 1 2 3 4
proyeksipil.blogspot.co.id
WAKTU PELAKSANAAN (TIME SCHEDULE)
PROYEK PEMBANGUNAN ………
JUMLAH W
BOBOT
NO URAIAN PEKERJAAN HARGA MARET 2017
(RP.) (%) 1 2 3
A PEKERJAAN PENDAHULUAN 26,651,680.00 7.50 3.75 3.75
5.03 5.03
5.03 12.07 11.26 11.26 12.39 8.45 5.63 5.63 5.35 5.35 2.26 1.65 1.13
17.57 29.64 40.90 52.16 64.54 72.99 78.63 84.26 89.61 94.96 97.22 98.87 100.0
proyeksipil.blogspot.co.id
WAKTU PELAKSANAAN (TIME SCHEDULE)
PROYEK PEMBANGUNAN ………
JUMLAH W
BOBOT
NO URAIAN PEKERJAAN HARGA MARET 2017
(RP.) (%) 1 2 3
A PEKERJAAN PENDAHULUAN 26,651,680.00 7.50 3.75 3.75
5.03 5.03
80
7.04 7.04 7.04 7.04
5.03 12.07 11.26 11.26 12.39 8.45 5.63 5.63 5.35 5.35 2.26 1.65 1.13
17.57 29.64 40.90 52.16 64.54 72.99 78.63 84.26 89.61 94.96 97.22 98.87 100.0