CORPORATE PRESENTATION
PT WIJAYA KARYA (Persero) Tbk.

HARBOUR
ROAD
PENGEMBANGAN JALAN TOL Ir.WIYOTO WIYONO Msc. (HBR II) ANCOL TIMUR- PLUIT

PEKERJAAN PERSIAPAN
R.E Martadinata & Lodan Raya

MAR
2021
DAFTAR ISI
General Informasi

Trase

Lokasi Kerja

Metode Kerja

Traffic Management

Aset Terdampak
GENERAL INFORMATION

OWNER
•CITRA MARGA NUSAPHALA
Nama Proyek : PROYEK PENGEMBANGAN JALAN TOL
Ir. Wiyoto Wiyono
Section Harbour Road Ii
CONSULTAN FS (Evelated)
& BASIC
DESIGN Pemilik Proyek : PT CITRA MARGA NUSAPHALA PERSADA
•MULTI PHI BETA
•VIRAMA KARYA
Length : 8.97 KM
•INDOTEK KONSULTAN Area : Ancol – Pluit, Jakarta Utara
: Tol Elevated
UTAMA
Structure Type
: 1095 HARI
CONSULTAN DED
•CIPTA GRAHA ABADI
Duration

CONTRACTOR
•WIJAYA KARYA
•GIRDER INDONESIA
KONSEP

Harbour Road II
INFORMASI PROYEK 2
3 HBR I
HBR II HBR II HBR II HBR II
HBR I

3 2
Stadion JIS

4
1
4
HBR II
HBR II HBR I
HBR II HBR I HBR II

Spesifikasi Teknis
Kecepatan Rencana : 80 Km/jam
Jumah Lajur :2x3
Lebar Lajur : 3.5 m
Bahu Dalam : 0.5 m
Bahu Luar : 2.5 m
Jumlah Ramp :4
(On R.E Martadianata, On Ancol, Off Ancol, & On Pluit)
LOKASI PROYEK

WILAYAH ADMINISTRASI
• 1 Kota KEC. PADEMANGAN
• 3 Kecamatan • Kel. Ancol
• 7 Kelurahan • Kel. Pademangan Barat

KEC. TANJUNG PRIOK KEC. PENJARINGAN


• Kel. Papanggo • Kel. Pejagalan
• Kel. Tanjung Priok • Kel. Penjaringan
• Kel. Sunter Agung
Kelurahan Sunter Agung

Kel. Sunter Agung


Kelurahan Pademangan Barat

Kel. Pademangan Barat


Kelurahan Ancol

Kel. Ancol
3D VIEW
3D View

EKSISTING Pek. Persiapan FINAL

Pek. Persiapan :
Test Pit
Identifikasi Utilitas
Soil Investigasi
Pekerjaan Persiapan
R.E Martadinata & Lodan Raya
AREA PRIORITAS
Lodan dan RE Martadinata
Area Prioritas
R.E Martadinata

Jl. Martadinata

P33S P30S

Start Selatan
7m

Arah Pluit

Jl. Martadinata

P61S

6.5 m

Arah Pluit

Tahap 1 (Area Prioritas)


Area Prioritas
R.E Martadinata
Jl. Martadinata

P75S 7m

Arah Pluit

Jl. Martadinata

7m
P105S

Arah Pluit

Tahap 1 (Area Prioritas)


Area Prioritas
Lodan Raya
P147N Jl. Lodan Raya

P141S

P137N
7m

Arah Priok
Arah Pluit
P125S Tahap 1 (Area Prioritas)

Jl. R. Martadinata
P30S – P125S Resume
Jumlah Pier : 95 Pier
Jumlah Pier

Jl. Lodan Raya 105


P137N – P147N
Jumlah Pier : 10 Pier Pier
TRAFFIC MANAGEMENT
MANAJEMEN LALULINTAS

PENEMPATAN RAMBU
SEMENTARA PEMELIHARAAN
LALU LINTAS PLAN PEKERJAAN
PADA LAJUR KIRI
LIGHT ROPE

Lokasi Pekerjaan

MCB + Pagar

Rubber Cone + Lampu untuk


Pekerjaan Malam hari

Rambu-Rambu :

Perbaikan Jalan Batas Kec. Maks Hati - hati


Rottary Lamp
LIGHT ROPE

Rubber Cone
Penyempitan Kiri Batas Kec. Maks Akhir Larangan

5m MCB Dilarang Mendahului Arah yg Diwajibkan


Traffic Management
R.E Martadinata & Lodan Raya
Tahap 1
Tahap 2

TAHAP KE 2

TAHAP KE 1

KONDISI EKSISTING SELAMA KONSTRUKSI

Pagar Proyek

*Detail lebar jalan dan rambu ada dilampiran


Traffic Management
R.E Martadinata & Lodan Raya
Tahap 1
Tahap 2

TAHAP KE 2

TAHAP KE 1

KONDISI EKSISTING SELAMA KONSTRUKSI

AKSES
JALAN
DITUTUP

Pagar Proyek
Traffic Management
R.E Martadinata & Lodan Raya
Tahap 1
Tahap 2

TAHAP KE 2

TAHAP KE 1

KONDISI EKSISTING SELAMA KONSTRUKSI

Pagar Proyek
Leader in sustainable investments & EPC
for better quality of life

Dimanapun engkau berada selalulah menjadi yang terbaik


dan berikan yang terbaik dari yang bisa kita berikan

- B.J. HABIBIE -
DETAIL TRAFFIC MANAGEMENT
Lodan dan RE Martadinata
TRAFFIC MANAGEMENT
DETAIL PER ZONA
STA 0+050 - STA 0+600 STA 0+600 - STA 0+750

ZONA 1

STA 0+050 - STA 0+750

Jl. Ketel
Jl. R.E Martadinata
Jl. R.E Martadinata
TRAFFIC MANAGEMENT
DETAIL PER ZONA
STA 0+750 - STA 2+150
ZONA 1

STA 0+750 - STA 2+150

Jl. R.E Martadinata


Jl. Ketel

Jl. R.E Martadinata


TRAFFIC MANAGEMENT
DETAIL PER ZONA
STA 2+200 - STA 3+500

STA 2+200 - STA 3+500

Jl. R.E Martadinata

Jl. R.E Martadinata Jl. Lodan


Raya
TRAFFIC MANAGEMENT
DETAIL PER ZONA

STA 3+500 - STA 3+700 ZONA 2

STA 3+500 - STA 3+700

Jl. Lodan Raya


Jl. R.E Martadinata
Jl. R.E Martadinata
TRAFFIC MANAGEMENT
DETAIL PER ZONA
STA 5+000 - STA 6+000
ZONA 3

STA 5+000 - STA 6+000


TRAFFIC MANAGEMENT
ASPEK KESELAMATAN

TRAFFIC CONTROL EQUIPMENT


PENGAMANAN TRAFFIC SAAT MALAM HARI
No Equipment
1 Unic crane, Crane Lorry
2 Pick up
3 Moveable barrier
4 Sign board
5 Safety cone
6 PPE for flagman
TRAFFIC MANAGEMENT
RAMBU LALULINTAS PROYEK

1600 mm

SPESIFIKASI RAMBU
HINDARI RUAS JALAN UKURAN PANEL: 1200 MM X 1600 MM

R.E MARTADINATA HURUP : MENGACU PADA STANDARD ALPHABETS


FOR HIGHWAY SIGNS AND PAVEMENT
1200 mm

ADA PEKERJAAN HURUP


MARKINGS – FHWA, 1993
: SERI ( HINDARI RUAS JALAN )

PEMBANGUNAN WARNA : DASAR = BIRU REFLEKTIF


TULISAN = PUTIH REFLEKTIF

TOLL HARBOUR ROAD II TEPI = PUTIH REFLEKTIF

RADIUS PELENGKUNG : 50 MM
SUDUT

CONTOH RAMBU INFORMASI PROYEK


TRAFFIC MANAGEMENT
RAMBU LALULINTAS PROYEK

1600 mm

SPESIFIKASI RAMBU

UKURAN PANEL: 1200 MM X 1600 MM

HATI - HATI HURUP : MENGACU PADA STANDARD ALPHABETS


1200 mm

FOR HIGHWAY SIGNS AND PAVEMENT

500 M LAGI MENDEKATI HURUP


MARKINGS – FHWA, 1993
: SERI D ( HINDARI RUAS JALAN )

PROYEK PEMBANGUNAN WARNA : DASAR


TULISAN
= KUNING REFLEKTIF
= HITAM NON REFLEKTIF

TOLL HARBOUR ROAD II TEPI = HITAM NON REFLEKTIF

RADIUS PELENGKUNG : 50 MM
SUDUT

CONTOH RAMBU PERINGATAN PROYEK


TRAFFIC MANAGEMENT
RAMBU LALULINTAS PROYEK
TRAFFIC MANAGEMENT
RAMBU LALULINTAS PROYEK
DETAIL ASET & UTILTIAS TERDAMPAK
Lodan dan RE Martadinata
Aset Terdampak
R.E Martadinata & Lodan Raya

No Item Pekerjaan Satuan Jumlah No Item Pekerjaan Satuan Jumlah


1 Pembersihan Area Kerja m2 48133 31 Pembongkaran Reklame unit 35
2 Pembongkaran Pasangan Batu m3 160 32 Pembongkaran Baliho unit 5
3 Pembongkaran Kerb (Kiri-Kanan Berm dan Median) m1 6400
33 Pembongkaran Plang / Papan Nama unit 3
4 Pembongkaran Pedestrian Stampconcreat m2 3768
34 Pembongkaran Pagar Pas Bata m 603
5 Pembongkaran Pedestrian Rabat Beton m2 2412.4
6 Pembongkaran Pedestrian Paving m2 3432
35 Pembongkaran Pintu Gerbang Bangunan / Gudang unit 17
7 Pembongkaran Taman m2 553 36 Pembongkaran Pagar ROW KAI m1 2727
8 Pembongkaran Sparator Pejan Kaki unit 27 37 Pembongkaran Pagar ROW Type BRC m1 710 Jl. R. Martadinata
9 Pembongkaran Pot Bunga unit 2 38 Pembongkaran Type Panel Beton m1 600
P30S – P125S
10 Pembongkaran Halte Bus unit 7 39 Pembongkaran Pagar Besi m 120
11 Pembongkaran Kursi Taman Unit 31
Jumlah Pier : 95 Pier
40 Pembongkaran Pos Jaga unit 30
12 Pembongkaran Reksisting Guard Rail m' 100 41 Pembongkaran Bangunan Jembatan Penyebrangan (JPO) m2 173
13 Pembongkaran Perkerasan Jalan Asphalt m3 618.8 42 Pembongkaran Bangunan Private m2 334 Jl. Lodan Raya
14 Pembongkaran Perkerasan Jalan Beton (Rigid Eksisting pd m3 4298 P137N – P147N
43 Pembongkaran Bangunan Semi Permanen m2 3639
15 Pembongkaran Saluran Terbuka m 540
16 Pembongkaran Saluran Tertutup m 3500
44 Pembongkaran Ekisting Parapet m 150 Jumlah Pier : 10 Pier
17 Pembongkaran Saluran Box Culvert Eksisting 1 m x 1,2 m m 480 45 Pembongkaran Utilitas PGN 24 in titik 11
18 Pembongkaran Tali Air unit 1200 46 Pembongkaran Utilitas PGN 16 in titik 4 Resume
19 Pembongkaran Rambu Kupu-Kupu unit 36 47 Pembongkaran Utilitas Pertagas 24 in titik 11 Jumlah Pier
20 Pembongkaran Rambu Petunjuk Type A (tiang F) unit 18 48 Pembongkaran Pipa Aetra 16" titik 58
21
22
Pembongkaran Rambu Petunjuk Type B
Pembongkaran Rambu Petunjuk Type D
unit
unit
4
2
49
50
Pembongkaran Pipa Palija 16''
Pembongkaran Pipa Palija 10''
titik
titik
33
6
105
23
24
Pembongkaran Panel PLN/PJU
Pembongkaran Tiang Listrik Beton( PLN )
unit
unit
19
1
51
52
Pembongkaran Pipa Palija 8''
Pembongkaran Kabel SKTT
titik
m
11
20160
Pier
25 Pembongkaran Tiang Optik unit 69
53 Pembongkaran Kabel SKTM Udara KAI m 2560
26 Pembongkaran Tiang Listrik ( PLN ) unit 70
27 Pembongkaran Tiang Listrik ( PJU ) unit 144
54 Pembongkaran Kabel SKTM m 8600
28 Pembongkaran Tiang Listrik Power Kereta (KRL/KAI) unit 46 55 Crossing SUTT unit 1
29 Pembongkaran Tiang BTS ( Telekomunikasi ) unit 4 56 Pembongkaran Pemasangan Tiang SUTT unit 1
30 Pembongkaran Trafik Light unit 5 57 Crossing Jembatan unit 1
Layout Lokasi Kerja
R.E Martadinata & Lodan Raya

Posisi Pagar Proyek


Traffic Arah Priok
Traffic Arah Pluit
Layout Lokasi Kerja
R.E Martadinata & Lodan Raya

Posisi Pagar Proyek


Traffic Arah Priok
Traffic Arah Pluit
Layout Lokasi Kerja
R.E Martadinata & Lodan Raya

Posisi Pagar Proyek


Traffic Arah Priok
Traffic Arah Pluit
Layout Lokasi Kerja
R.E Martadinata & Lodan Raya

Posisi Pagar Proyek


Traffic Arah Priok
Traffic Arah Pluit
Layout Lokasi Kerja
R.E Martadinata & Lodan Raya

Posisi Pagar Proyek


Traffic Arah Priok
Traffic Arah Pluit
Layout Lokasi Kerja
R.E Martadinata & Lodan Raya

Posisi Pagar Proyek


Traffic Arah Priok
Traffic Arah Pluit
Layout Lokasi Kerja
R.E Martadinata & Lodan Raya

Posisi Pagar Proyek


Traffic Arah Priok
Traffic Arah Pluit
Layout Lokasi Kerja
R.E Martadinata & Lodan Raya

Posisi Pagar Proyek


Traffic Arah Priok
Traffic Arah Pluit
Layout Lokasi Kerja
R.E Martadinata & Lodan Raya

Posisi Pagar Proyek


Traffic Arah Priok
Traffic Arah Pluit
Layout Lokasi Kerja
R.E Martadinata & Lodan Raya

Posisi Pagar Proyek


Traffic Arah Priok
Traffic Arah Pluit
Layout Lokasi Kerja
R.E Martadinata & Lodan Raya