Anda di halaman 1dari 70

DIREKTORAT JENDERAL MINYAK DAN

GAS BUMI – KEMENTERIAN ENERGI DAN


SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 2 of 16
JRG4-SI-TJE-GA-RM-001 0

LEMBAR KRONOLOGIS REVISI DOKUMEN

Rev No Date Description

0 09/04/2020 Issued for Approval


DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 3 of 16
JRG4-SI-TJE-GA-RM-001 0

DAFTAR ISI

1. RINGKASAN EXECUTIVE ........................................................................ 4

2. LAPORAN PROGRESS BULANAN .......................................................... 8

3. LAPORAN QA/QC ..................................................................................... 9

4. LAPORAN HSE/K3 .................................................................................... 11

5. REKOMENDASI ......................................................................................... 15

6. LAMPIRAN................................................................................................. 16

- Dashboard Bulanan

- Breakdown Progres Bulanan

- Timesheet

- Punchlist / NCR / Site Memo


DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 4 of 16
JRG4-SI-TJE-GA-RM-001 0

1. RINGKASAN EXECUTIVE

Pencapaian cumulative progres material dan progress fisik Pembangunan Jaringan

Gas Bumi Untuk Rumah Tangga di Tanjung Enim (4.000 SR) untuk periode 10 Maret

2020 - 8 April 2020 adalah 18,44% dari cummulative plan EPC sebesar 4,74%

sehingga terjadi deviasi (+) 13,70%.

Pencapaian progress yang dicapai dalam bulan ini diperoleh dari :

1. Pekerjaan persiapan
a. Sewa Kantor Proyek (Min.150 m2)
b. Penyediaan Banner
c. Sewa Gudang Material (Min. 300 m2)

2. Material on site Jaringan Pipa Induk

3. Jaringan Pipa Distribusi Tekanan Rendah


a. Material on site pipa PE dia. 63 mm dan Fitting
b. Pekerjaan Penggelaran Pipa PE dia. 63 mm

4. Sambungan Kompor (SK)


a. Material on site untuk Sambungan Kompor
b. Konstruksi pemasangan dan pengujian Sambungan Kompor

Deviasi negatif sampai dengan cut of date 8 April 2020, dikarenakan pencapaian dari

beberapa item pekerjaan yang tidak berjalan sesuai dengan plan konstruksi yang

sudah di buat oleh EPC KSO PPS - Dhamma dengan rincian sebagai berikut :

1. Pekerjaan Persiapan
DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 5 of 16
JRG4-SI-TJE-GA-RM-001 0

Cummulative Plan untuk Pekerjaan Persiapan sampai dengan cut of date

tanggal 8 April 2020 adalah 0,34% dan Cummulative Actual adalah 0,31%,

sehingga terdapat deviasi (-) 0,02%.

Hal ini karena EPC, KSO PPS - Dhamma belum selesai/melaksanakan :


- Penyediaan papan nama proyek
- Penvediaan Tanda Pengaman/Rambu-rambu
- Penyediaan Dinding Penahan Galian

2. Pekerjaan Pasca Konstruksi

Cummulative Plan untuk Pekerjaan Pasca Konstruksi sampai dengan cut of

date tanggal 8 April 2020 adalah 0,05% dan Cummulative Actual adalah 0,00%,

sehingga terdapat deviasi (-) 0,05%.

Hal ini karena EPC, KSO PPS - Dhamma belum selesai/melaksanakan

Pengurusan perizinan

Progres Konstruksi sampai dengan cut of date 8 April 2020 adalah sebagai berikut:

1. Status Perijinan

• Izin Prinsip ke Pemkab. : Closed


• Izin Galian ke Pemkab. : Closed
• Izin BPJN : Open
• Izin BBWS (Cross Sungai) : Open
• Izin MRS/RS : Open
Catatan :
- RS 1, 3, dan 4 menunggu Berita Acara di tanda tangan oleh pihak Kelurahan
DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 6 of 16
JRG4-SI-TJE-GA-RM-001 0

- RS 2 yang berlokasi di SMPN 2 Lawang Kidul, masih menunggu pihak


sekolah karena libur.

2. Validasi Calon Pelanggan : 3.358 dari 4.000 Capel


Catatan :
- Terdapat perbedaan antara angka BOQ (4.000) dan list Capel (4.056)
- EPC masih menunggu keputusan berapa Capel yang akan dikerjakan,
sehingga validasi sementara terhenti pada 3.358 Capel.

3. Survey Jalur
• Pipa PE dia. 63 mm
Deviasi Deviasi
FEED BOQ MC 0
Sektor (FEED - MC0) (BOQ - MC0)
(Meter) (Meter) (Meter)
Meter Meter
Sektor 1 15.887,87 N/A 17.711,00 -1.823,13 -
Sektor 2 14.474,65 N/A 14.171,00 303,65 -
Sektor 3 20.699,70 N/A 21.815,00 -1.115,30 -
Sektor 4 17.273,40 N/A 17.957,00 -683,60 -
Total 68.335,62 67.482,00 71.654,00 -3.318,38 -4.172,00

*Catatan : Terjadi selisih 4.172 m antara hasil pengukuran dan BOQ, EPC
mengajukan hal tersebut pada MC 0

• Pipa CS 4 inch : 13.847 m dari 13.837 m


• Pipa PE dia. 125 mm : 4.261 m dari 4.730 m

4. Konstruksi
a. Penggelaran Pipa PE dia. 63 mm
Sektor 1 : 12.522,3 m
Sektor 2 : 11.841,9 m
Sektor 3 : 5.881,8 m
Sektor 4 :0m
Total : 30.246 dari 67.482 m (44,82%)
DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 7 of 16
JRG4-SI-TJE-GA-RM-001 0

Pekerjaan Penyambungan Fitting & Valve PE dia. 63 mm (Electro Fusion) :


501 titik
b. SK - SR
• Sambungan Kompor : 850 Terpasang, 124 Teruji, dari 4.000 Sambungan
• Sambungan Rumah : 500 Terpasang, 0 Teruji, dari 4.000 Sambungan
Catatan :
- Pemasangan Sambungan Rumah (SR) tidak termasuk MGRT, semua
dilaksanakan di Sektor 1
- Untuk sementara pemasangan Sambungan Rumah (SR) di pending
karena banyak ditemukan galian kedalaman SR yang tidak sesuai
prosedur JRG4-KPD-GEN-CN-PR-007

5. Material On site

a. Jaringan Pipa Induk


- Elbow 90, 125 : 4 Pcs
- Elbow 45, 125 : 5 Pcs
- Coupler 125 : 4 Pcs
b. Jaringan Pipa Distribusi Tekanan Rendah
- Pipa PE dia. 63 mm : 72.600 m
- Elbow 90, 63 : 193 Pcs
- Elbow 45, 63 : 8 Pcs
- Tee Equal, 63 : 421 Pcs
- End Cap, 63 : 290 Pcs
- Coupler, 63 : 1.400 Pcs
c. Sambungan Kompor : 2.310 set dari 4.000 set
DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 8 of 16
JRG4-SI-TJE-GA-RM-001 0

2. LAPORAN PROGRESS BULANAN

S-Curve Tanjung Enim Bulan - 1


20.00% 100.00%
18.00% 90.00%
16.00% 80.00%
14.00% 70.00%
12.00% 60.00%
10.00% 50.00%
8.00% 40.00%
6.00% 30.00%
4.00% 20.00%
2.00% 10.00%
0.00% 0.00%
W-1 W-2 W-3 W-4 M-1 M-2 M-3 M-7 M-8 M-9
Plan 0.00% 1.16% 1.56% 2.02% 4.74% 8.58% 4.03% 18.76% 11.04% 5.27%
Act 0.00% 9.20% 1.70% 7.54% 18.44%
Acc Plan 0.00% 1.16% 2.72% 4.74% 4.74% 13.32% 17.35% 83.69% 94.73% 100.00%
Acc Act 0.00% 9.20% 10.90% 18.44% 18.44%
Deviasi 0.00% 8.04% 8.18% 13.70% 13.70%

Maret April 08-Apr Mei Juni Okt Nov Des


Tittle W-1 W-2 W-3 W-4 M-1 M-2 M-3 M-7 M-8 M-9
Plan 0,00% 1,16% 1,56% 2,02% 4,74% 8,58% 4,03% 18,76% 11,04% 5,27%
Acc Plan 0,00% 1,16% 2,72% 4,74% 4,74% 13,32% 17,35% 83,69% 94,73% 100,00%
Act 0,00% 9,20% 1,70% 7,54% 18,44%
Acc Act 0,00% 9,20% 10,90% 18,44% 18,44%
Deviasi 0,00% 8,04% 8,18% 13,70% 13,70%

Progress Bulan ini


No Item Pekerjaan Bobot Sisa Pekerjaan Note
Kum Plan Kum Akt Deviasi
A PEKERJAAN PERSIAPAN 0,58% 0,34% 0,31% -0,02% 0,26%
B JARINGAN PIPA DISTRIBUSI TEKANAN TINGGI 27,90% 0,00% 0,00% 0,00% 27,90%
C JARINGAN PIPA INDUK 4,45% 0,00% 0,01% 0,01% 4,43%
D JARINGAN PIPA DISTRIBUSI TEKANAN RENDAH 24,79% 1,72% 13,15% 11,43% 11,63% Deviasi Negatif, terdapat
E SAMBUNGAN RUMAH 25,13% 0,00% 0,00% 0,00% 25,13% pada pekerjaan
F SAMBUNGAN KOMPOR 10,35% 2,63% 4,96% 2,33% 5,39% persiapan dan pekerjaan
G PENYEDIAAN KOMPOR GAS ALAM 2 TUNGKU DAN SELANG 1,85% 0,00% 0,00% 0,00% 1,85% pasca konstruksi dimana
H PERALATAN UTAMA 2,17% 0,00% 0,00% 0,00% 2,17% didalamnya terdapat
I PEKERJAAN SIPIL 0,14% 0,00% 0,00% 0,00% 0,14% bobot perihal perizinan
J PEKERJAAN PENGUJIAN 0,42% 0,00% 0,00% 0,00% 0,42%
K PEKERJAAN PASCA KONSTRUKSI 2,23% 0,05% 0,00% -0,05% 2,23%
Total 100,00% 4,74% 18,44% 13,70% 81,56%
DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 9 of 16
JRG4-SI-TJE-GA-RM-001 0

3. LAPORAN QA/QC

Report QA/QC
PMC - Tanjung Enim Periode : 10 Maret - 8 April 2020

Total
No. Item Pengerjaan Ketidaksesuaian Rekomendasi Dokumentasi
Inspeksi
1 Inspeksi Material PE 20 109 Roll Ditemukan penyimpanan tidak
Inspeksi Material PE 63 429 Roll Seharusnya pipa PE 63
sesuai dengan prosedur JRG4-
diberi alas palet dan
KPD-GEN-CN-PR-005 Prosedure
ditutup menggunakan
Penanganan, Pengangkutan &
terpal untuk menghindari
Penyimpanan Material Pipa Baja
kontak langsung dengan
dan PE
matahari
PMC/TE/2020/QC/002 (Closed)
2 - Coupler 125m - 4 Pcs
- L90 x 125 mm - 4 Pcs
- L45 x 125 mm - 14 Pcs
- Flange 125 - 2 Pcs
- Equal Tee dia 63 mm - 431 Pcs PMC memberikan saran
- Coupler 63 mm - 1.400 Pcs kepada KPD agar data
Semua material yang datang
- L90 x 63 mm - 226 Pcs barang (pembukuan) yang
sesuai dengan list MIR
- L45 x 63 mm - 136 Pcs keluar dan masuk didata
- N Cap 63 mm - 290 Pcs dengan baik
- Tapping 63 x 20 mm - 4.000 Pcs
- Coupler 20 mm - 4.000 Pcs
- L90 x 20 mm - 4.000 Pcs
- Trasition fitting - 750 Pcs

Sebelum melakukan
pemasangan SK, mandor
- Jarak klam terlalu jauh SK wajib membaca
- Ditemukan tiang SK memotong prosedur sehingga bisa
3 Pemasangan SK 750
tiang MGRT, sehingga MGRT tidak memberikan pengarahan
bisa dipasang cara pemasangan SK yg
baik.
Noted: Repair di tempat

Total Bocor = 1
Segera dilakukan repair
dengan menambahkan
seal tape dan
4 Pneumatic SK 115
mengencangkan drat yg
kurang kencang
Bocor terdapat Pada Socket Noted : Repair di tempat
DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 10 of 16
JRG4-SI-TJE-GA-RM-001 0

Report QA/QC
PMC - Tanjung Enim Periode : 10 Maret - 8 April 2020
Total
No. Item Pengerjaan Ketidaksesuaian Rekomendasi Dokumentasi
Inspeksi
5 Penggalian SR Ditemukan Kedalaman galian tidak sesuai
84 galian SR dengan prosedure JRG4-KPD-
yang kurang EPC harus bisa
GEN-CN-PR-007 Prosedure
dari top pipe menekankan quality pada
Pekerjaan Penggalian Galian
40 cm mandor lapangan yang
Pipa
memegang gallian SR
JRG4-SI-160307-QC-PCHL-001
(Open)

Membetulkan kembali
JRG4-SI-160307-QC-PCHL-001
semua sambungan SR
= 50 SR (OPEN)
agar sesuai dengan
JRG4-SI-160307-QC-PCHL-002
prosedur kedalaman
= 34 SR (OPEN)
galian

Banyak yang tidak menggunakan


elbow Memberikan tool box
JRG4-SI-160307-QC-PCHL-001 meeting kepada pekerja
(Open) galian SR sebelum
memulai pekerjaan di
Kedalaman galian hanya dekat lapangan
dengan lokasi tiang MGRT
*Noted : PMC akan memberikan NCR untuk semua sambungan SR bila ditemukan lebih banyak lagi
sambung SR yang tidak sesuai dengan Prosedure kedalaman galian (top pipe 40 cm)
6 Galian dan Lowering Lowering
jalur 63 di sektor 1

Sebelum melakukan galian


Saat inspeksi ditemukan pipe 63mm, kpd harus
beberapa galian lubang pit yang melakukan tool box
kurang dari top pipe 80cm meeting setiap hari
PMC/TE/2020/QC/001 (Closed) sebelum melakukan
perkerjaan

*Noted : Repair sudah dilakukan


DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 11 of 16
JRG4-SI-TJE-GA-RM-001 0

4. LAPORAN HSE/K3
REPORT INSPECTION KESELAMATAN KESEHATAN KERJA
PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI
UNTUK RUMAH TANGGA
DI TANJUNG ENIM (4000 SR) TA 2020

Kontraktor : KSO PT. Pratiwi Putri Sulung - PT. Dhamma Sumber Pundi Artha
Pengawas : Alkony
Period : 10 Maret s/d 8 April 2020 Page 1 of 3

Tindakan yang di
No Tanggal Item/Pekerjaan Tingkat Resiko Lokasi Dokumentasi
Rekomendasikan
Info ke Mandor galian untuk
merapikan tanah galian yang
berceceran dan memasukan
Pekerjaan Manual
1 20 Maret 2020 Menengah Sektor 01 kedalam karung, untuk
Boring
menghindari jalan menjadi
sempit dan licin apabila terjadi
hujan

Info ke Pengawas Jalur dari


EPC untuk tidak melakukan
Pekerjaan Galian
2 21 Maret 2020 Tinggi Sektor 01 pekerjaan buka pit dua jalur,
Pipa 63mm
untuk menghindari jalan menjadi
macet dan sempit

Info kepekerja dan dan


pengawas dari EPC untuk hati -
hati dalam melakukan pekerjaan
Pegalian Lubang Pit jika terdapat instalasi lain
3 22 Maret 2020 Rendah Sektor 01
untuk pipa 63mm didalam pit, dan dilarang
merusaknya, karena bisa
menyebabkan pekerjaan ini
terhambat

Untuk peletakan Material Pipa


Penempatan PE 125 mm Agar membuatkan
4 23 Maret 2020 Material pipa PE Menengah Gundang EPC Penyanggah / rak agar pipa
125mm tertata dengan rapi, dan mudah
saat diambil

Info ke pekerja Operator Joint


untuk tidak menarik kabel
sambungan melewati jalan yang
Joint Taping Sadle
5 24 Maret 2020 Tinggi Sektor 01 banyak kendaraan melintas,
dan joint Coupler
karna bisa menyebabkan
pengedara Sepeda Motor
terjatuh akibat terlilit oleh Kabel

Untuk pekerjaan galian Open


Pekerjaan Galian Cut, tanah galian secepatnya
6 25 Maret 2020 Pipa 63mm Open Menengah Sektor 01 dirapikan dan ditimbun agar
Cut tidak terjadi kemacetan pada
kendaraan yang melintas

Info kepekerja dan dan


pengawas dari EPC, untuk tidak
melakukan pekerjaan galian dua
jalur, untuk menghindari
Pekerjaan Galian
7 26 Maret 2020 Menengah Sektor 01 banyaknya lubang Pit yang
Pipa 63mm
terbuka dengan kondisi jalan
sempit, bisa menyebabkan
kendaraan yang melintas
terjatuh kedalam lubang galian
DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 12 of 16
JRG4-SI-TJE-GA-RM-001 0

REPORT INSPECTION KESELAMATAN KESEHATAN KERJA


PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI
UNTUK RUMAH TANGGA
DI TANJUNG ENIM (4000 SR) TA 2020

Kontraktor : KSO PT. Pratiwi Putri Sulung - PT. Dhamma Sumber Pundi Artha
Pengawas : Alkony
Period : 10 Maret s/d 8 April 2020 Page 2 of 3

Tindakan yang di
No Tanggal Item/Pekerjaan Tingkat Resiko Lokasi Dokumentasi
Rekomendasikan
Info ke Pengawas EPC dan CM
Untuk Menghindari Pipa PVC
Pekerjaan Galian Pipa PDAM rusak atau bocor
8 27 Maret 2020 Rendah Sektor 01
PE 63mm digalian pit, EPC harus
mobilisasi air untuk pekerja
galian

Info kepekerja SK untuk selalu


Fabrikasi Pipa Galvanis mengunakan APD dalam
9 28 Maret 2020 Menengah Sektor 01
Sambungan Kompor melakukan pekerjaan
pemotongan pipa

Info ke Pengawas EPC dan CM


jika ingin melakukan pekerjaan
Manual Boring Pipa malam wajib menyediakan
10 29 Maret 2020 Tinggi Sektor 02
63mm pada Malam Hari penerangan, untuk menghindari
kecelakaan kerja pada pekerja
dan kendaraan yang melintas

Info ke Pengawas Jalur EPC


Proses galian Pit Pipa untuk memasang rambu -
11 30 Maret 2020 Menengah Sektor 01
63mm rambu tanda pengaman
pekerjaan

Info ke Pengawas Jalur dan


pekerja agar tidak merusak
utilitas lain yang terdapat
12 31 Maret 2020 Pengalian Lubang Pit Menengah Sektor 01
didalam galian pit, dan berhati
hati dalam melakukan
pekerjaan

Pipa PE 63mm yang selesai


dilowering sebaiknya ditimbun,
Pipa PE 63 mm yang
13 01-Apr-20 Menengah Sektor 02 agar lebh aman, untuk
belum ditimbun
menghindari pipa tertabrak oleh
pengendara

Info ke Pengawas Jalur dan CM


Proses galian Pit Pipa dari EPC untuk memasang
14 02-Apr-20 Menengah Sektor 02
63mm Banner / papan tanda
pengaman galian
DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 13 of 16
JRG4-SI-TJE-GA-RM-001 0

REPORT INSPECTION KESELAMATAN KESEHATAN KERJA


PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI
UNTUK RUMAH TANGGA
DI TANJUNG ENIM (4000 SR) TA 2020

Kontraktor : KSO PT. Pratiwi Putri Sulung - PT. Dhamma Sumber Pundi Artha
Pengawas : Alkony
Period : 10 Maret s/d 8 April 2020 Page 3 of 3

Tindakan yang di
No Tanggal Item/Pekerjaan Tingkat Resiko Lokasi Dokumentasi
Rekomendasikan

Info ke Pengawas Jalur dari


EPC untuk segera menimbun
Galian Lubang Pit
lubang galian untuk
15 03-Apr-20 setelah dilowering pipa Rendah Sektor 01
menghindari pengendara dan
63mm
pejalan kaki masuk kedalam
lubang galian

Info ke Pengawas Jalur dari


EPC untuk untuk melakukan
penyisiran bekas karung yang
16 04-Apr-20 House Kepping Menengah Sektor 01
beserakan didekat lubang pit
yang selesai di back feeling /
ditimbun

Info ke Pengawas Jalur untuk


secepatnya merapikan tanah
galian dan ditimbun karena
Galian Lubang Pit pipa
17 05-Apr-20 Tinggi Sektor 03 posisi lubang pas dengan
63mm
belokan jalan utama, untuk
menghindari bahaya dari
kedaraan yang melintas
Info ke CM dari EPC untuk
memasang papan tanda
pengaman pekerjaan galian,
Proses Pekerjaan
untuk memudahkan
18 06-Apr-20 Galian untuk pipa Menengah Sektor 03
pengedara yang melintas
ditribusi 63mm
mengetahui bahwa ada
pekerjaan galian dan berhati -
hati

Info ke Pengawas Jalur


Flushing untuk memasang
Inject tekanan degan Safety Wire guna menghindari
19 07-Apr-20 Menengah Sektor 01
kompresor AIR MAN Hose compressor terlepas
mengenai pekerja dan
masyarakat sekitar

Info ke pengawas yang


bertanggung jawab dengan
Flushing partial pipa
20 08-Apr-20 Tinggi Sektor 02 kerjaaan flushing untuk
63mm
memasang baricade / safety
line di area inject
DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 14 of 16
JRG4-SI-TJE-GA-RM-001 0

` HSE MONTHLY REPORT

PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI


UNTUK RUMAH TANGGA
DI TANJUNG ENIM ( 4000 SR ) TA 2020

Pemilik Proyek : Kementrian ESDM Periode : 10 Maret - 8 April 2020


Departemen : HSE Bulan : 01 (Satu )

A. MANPOWER
LAST MONTH THIS MONTH
NO. COMPANY
TANJUNG ENIM TANJUNG ENIM
1 KSO PPS - DHAMMA 270
2 PT. SURVEYOR INDONESIA 5
TOTAL MAN POWER 275

B. MAN HOURS
LAST MONTH THIS MONTH
NO. COMPANY COMULATIVE
TANJUNG ENIM TANJUNG ENIM
1 KSO PPS - DHAMMA - 64800 64800
2 PT. SURVEYOR INDONESIA - 1200 1200
TOTAL MAN HOURS - 66000 66000

C. HSE STATISTIK
LAST MONTH THIS MONTH
NO. DESKRIPSI KETERANGAN
TANJUNG ENIM TANJUNG ENIM
1 FATALITY 0 0 0
2 LOST TIME INJURY (LTI) 0 0 0
3 MEDICAL TREATMENT CASE 0 0 0
4 FIRST AID CASE 0 0 0
5 ENVIROMENT INCIDEN 0 0 0
6 NEAR MISS 0 0 0
7 VEHICLE/TRAFFIC ACCIDENT 0 0 0
8 FIRE ACCIDENT 0 0 0
9 PROPERTY DAMAGE 0 0 0
10 SECURITY INCIDENT 0 0 0
DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 15 of 16
JRG4-SI-TJE-GA-RM-001 0

5. REKOMENDASI

a) Segera menindaklanjuti rekomendasi QA/QC dan HSE/K3.

b) Segera repair dan close pekerjaan yang tidak sesuai spesifikasi berdasar

site memo, punch list yang dikeluarkan oleh PMC.

c) Segera lakukan koordinasi perihal perizinan dengan pemerintah daerah

dan Lembaga terkait.

d) Melanjutkan pekerjaan pemasangan Sambungan Rumah dan Sambungan

Kompor sesuai target dengan meningkatkan pengawasan/supervisi

lapangan.

e) Melanjutkan material on site sesuai plan.

f) Agar segera disiapkan tim QC dan Humas dikarenakan lot pekerjaan yang

semakin tinggi.
DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI – KEMENTERIAN ENERGI DAN
SUMBER DAYA MINERAL REPUBLIK
INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : 10 MARET - 8 APRIL 2020
Nomor Dokumen Rev.
Page 16 of 16
JRG4-SI-TJE-GA-RM-001 0

LAMPIRAN
SURVEYOR /AIDONES/A
DIREKTORAT PERENCANAAN & PEMBANGUNAN JARINGAN GAS BUMI RUMAH TANGGA Status: 8 April 2020
PEMBANGUNAN INFRASTRUKTUR MIGAS
TANJUNG ENIM 4.000 SR
S-Curve Tanggal 8 April 2020
PROGRESS FISIK
Profil Proyek RENCANA REALISASI DEVIASI
❑ Obyektif Proyek: 4,47 18,44 13,70
Pembangunan Jargas untuk Rumah
❑ PROGRESS Month – 1 (10 Maret – 8 April 2020)
Tangga di Ogan Komering Ulu dan A. Status Perizinan
Muara Enim 1. Izin Prinsip : Closed
2. Izin Galian : Closed
❑ Ruang Lingkup : 3. Izin BPJN : Open
13.044 SR 4. Izin BBWS : Open
❑Durasi Proyek : 5. Izin MRS/RS
B. Material onsite
: Open

10 Maret 2020 s/d 5 Des 2020 1. Pipa CS 4” : 0 meter dari 13.837 meter (0%)
❑ Kontraktor Pelaksana: 2. Pipa CS 125 mm : 0 meter dari 4.730 meter (0%)
3. Pipa PE 63 mm : 67.482 meter dari 67.482 meter (100,00%)
• KSO PRATIWI-DHAMMA 4. MGRT : 0 set dari 4.000 set (0%)
❑Nilai Kontrak Kontraktor : C. Kontruksi Lapangan
1. Konstruksi Pipa CS 4” : 0 meter dari 13.837 meter (0%)
Rp. 202.513.937.474 2. Pengujian Pipa CS 4” : 0 meter dari 13.837 meter (0%)
❑PMC: 3. Konstruksi Pipa CS 125 : 0 meter dari 4.730 meter (0%)
• PT SURVEYOR INDONESIA 4. Pengujian Pipa CS 125 : 0 meter dari 4.730 meter (0%)
5. Konstruksi Pipa PE 63 : 30.246 meter dari 67.482 meter
❑ Nilai Kontrak PMC : (44,82%)
Rp. 5.748.624.145 6. Pengujian Pipa PE 63 : 0 meter dari 67.482 meter (0%)
7. Konstruksi SK : 850 SK dari 4.000 SK (21,25%)
8. Pengujian SK : 80 SK dari 4.000 SK (2,00%)
9. Konstruksi SR : 500 SR dari 4.000 SR (12,50%)
10. Pengujian SR : 0 SR dari 4.000 SR (0%)
D. Manpower
1. Penggalian PE 63 : 240 orang
2. Penyambungan PE 63 : 6 Tim
3. Pemasangan SK : 20 orang
E. MC-0
1. Survey Calon Pelanggan
• Sektor 1 : 878 dari 1.240 capel
• Sektor 2 : 501 dari 561 capel
• Sektor 3 : 579 dari 685 capel
• Sektor 4 : 1.400 dari 1.570 capel
• Total : 3.358 dari 4000 capel (83,95%)
2. Survey Jalur Pipa 63 mm
• Sektor 1 : 17.711 meter
• Sektor 2 : 14.171 meter
• Sektor 3 : 21.815 meter
• Sektor 4 : 17.957 meter
- Tanjung Enim : 4.000 SR • Total : 71.654 dari 67.482 meter (106,18%)
3. Survey Jalur Pipa CS 4” : 13.847 meter dari 13.837 meter
4. Survey Jalur Pipa CS 125 mm : 4.261 meter dari 4.730 meter
F. Issue
- Personil EPC belum lengkap (QC, Humas)
- Perizinan sedang dalam progress
- Material CS, Casing, belum onsite
Inspeksi Galian PE 63 Mock Up Pressure Gauge Pemasangan dan Pengujian SK
- Semua Manpower EPC belum onsite dikarenakan lockdown
PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM TA 2020
BREAKDOWN PROGRESS BULAN KE-1
PMC - TANJUNG ENIM

Bulan ke-1
No Jenis Barang/Jasa Satuan Unit Volume Bobot Volume Bobot
Yang Lalu Saat Ini Akumulasi Yang Lalu Saat Ini Akumulasi
A PEKERJAAN PERSIAPAN
Penyediaan Papan Nama Provek (kayu & cat semprot) Buah 1 0,001% - - - 0,00% 0,00% 0,00%
Sewa Kantor Proyek (Min.150m2) Ls 1 0,23% - 1,00 1,00 0,00% 0,23% 0,23%
Penyediaan Banner Unit 40 0,06% - 40,00 40,00 0,00% 0,06% 0,06%
Penvediaan Tanda Pengaman/Rambu-rambu Unit 30 0,01% - - - 0,00% 0,00% 0,00%
Penyediaan Dinding Penahan Galian m2 120 0,02% - - - 0,00% 0,00% 0,00%
Sewa Gudang Material (Min. 300m2) Ls 8 0,19% - 1,00 1,00 0,00% 0,02% 0,02%
Pembuatan Gambar Kerja Konstruksi Ls 1 0,07% - - - 0,00% 0,00% 0,00%
Subtotal (A) 0,00% 0,31% 0,31%
B JARINGAN PIPA DISTRIBUSI TEKANAN TINGGI
1 PENGADAAN MATERIAL
Pipa
4, API 5L Gr.B, PSL 2, ERW/LSAW,Sch 40, DRL (L=12m),
Meter 13.837 15,37% - - - 0,00% 0,00% 0,00%
3LPE, t=2mm
Fitting
Flange 4 150# WNRF, Sch. 40, CS,LR,WPB,BW Buah 7 0,00% - - - 0,00% 0,00% 0,00%
Blind Flange 4 150# WNRF, Sch. 40, CS,LR,WPB,BW Buah 1 0,00% - - - 0,00% 0,00% 0,00%
4 Tee Equal Sch. 40, CS,LR,WPB,BW Buah 1 0,00% - - - 0,00% 0,00% 0,00%
4 Elbow 90 Deg Sch. 40, CS,LR,WPB,BW Buah 6 0,00% - - - 0,00% 0,00% 0,00%
4 Elbow 45 Deg Sch. 40, CS,LR,WPB,BW Buah 46 0,02% - - - 0,00% 0,00% 0,00%
Gasket 4 150# SWG RF ,IR 316SS, B 16.5, Filler Graphite
Buah 13 0,00% - - - 0,00% 0,00% 0,00%
Hoop 316SS
Stud Bolt & Nut, 3/4x 110mm c/w washer & ring Set 13 0,00% - - - 0,00% 0,00% 0,00%
Valve 1 0,00% 0,00% 0,00% 0,00%
Ball Valve, 4 API 6D, #150, full bore, trunnion mounted,
double piston A250 LF2, Gear Operated, fully welded body Buah 3 0,21% - - - 0,00% 0,00% 0,00%
untuk future connection
Ball Valve, 1 for venting Buah 3 0,02% - - - 0,00% 0,00% 0,00%
Pipa Casing 1 0,00% 0,00% 0,00% 0,00%
Pipa Casing 8 Galvanis (SNI Medium BS3907) Meter 310 0,37% - - - 0,00% 0,00% 0,00%
2 KONSTRUKSI 1 0,00% 0,00% 0,00% 0,00%
Welding c/w production test Pipa 4 inch Joint 1.326 1,81% - - - 0,00% 0,00% 0,00%
NDT Joint 1.326 0,91% - - - 0,00% 0,00% 0,00%
Field Joint Coating Joint 1.154 0,92% - - - 0,00% 0,00% 0,00%
Holiday Test Meter 13.837 0,29% - - - 0,00% 0,00% 0,00%
Cathodic Protection termasuk ( pengadaan material,
Set 45 0,20% - - - 0,00% 0,00% 0,00%
pemasangan dan accessories)
- High Potential Prepacked Magnesium Anode NWT @7,7
kg c/w 3m x 6mm2 XLPE cable tail. ( @ 500 meter)
- T&R T3 Basic Test Station Black Shockguard type c/w
5(five) terminals.
Pekerjaan Manual Boring Pipa CS dia 4 (termasuk entry/exit
Meter 310 0,50% - - - 0,00% 0,00% 0,00%
pit dan reinstatement)
Pekerjaan Open Cut
a. Pekerjaan Galian Pipa CS dia. 4 (Jalan Nasional) Meter 13.350 2,96% - - - 0,00% 0,00% 0,00%
b. Pekerjaan Stringing & Lowering Pipa CS dia. 4 Meter 13.837 2,20% - - - 0,00% 0,00% 0,00%
c. Pekerjaan Pengurugan Pipa CS dia. 4
- Pasir Landasan dan Penutup Pipa Meter 13.350 0,52% - - - 0,00% 0,00% 0,00%
- Marker Tape Meter 13.350 0,08% - - - 0,00% 0,00% 0,00%
- Penimbunan dan pemadatan Kembali Galian Dengan
Meter 13.350 0,96% - - - 0,00% 0,00% 0,00%
Tanah Pipa CS dia. 4
Pekerjaan Perlintasan Sungai (Pengadaan sinker,
Pemasangan Casing serta sinker, dan termasuk Meter 177 0,33% - - - 0,00% 0,00% 0,00%
reinstatement)
Pekerjaan Box Valve Pipa CS Buah 3 0,12% - - - 0,00% 0,00% 0,00%
Papan Nama Jalur Gas Pipa Tekanan Tinggi Buah 28 0,07% - - - 0,00% 0,00% 0,00%
Pekerjaan Patok Gas Type A (@50m) Pipa Tekanan Tinggi Buah 139 0,03% - - - 0,00% 0,00% 0,00%
Subtotal (B) 0,00% 0,00% 0,00%
C JARINGAN PIPA INDUK
1 PENGADAAN MATERIAL
Pipa
Pipa PE 125 mm, PE 80/PE 100, SDR 11 Meter 4.730 2,19% - - - 0,00% 0,00% 0,00%
Fitting
Elbow 90, 125 mm PE 80/PE 100 SDR 11 ISO 4437 Buah 16 0,02% - 4,00 4,00 0,00% 0,01% 0,01%
Elbow 45, 125 mm PE 80/PE 100 SDR 11 ISO 4437 Buah 5 0,01% - 5,00 5,00 0,00% 0,01% 0,01%
Tee Equal , PE 80/PE 100 SDR 11 ISO 4437 125 mm x 125
Buah 4 0,01% - - - 0,00% 0,00% 0,00%
mm
End Cap, 125 mm, PE 80/PE 100 SDR 11 ISO 4437 Buah 1 0,00% - - - 0,00% 0,00% 0,00%
Coupler 125 mm, PE 80/PE 100 SDR 11 ISO 4437 Buah 164 0,08% - 4,00 4,00 0,00% 0,00% 0,00%
Valve
Ball Valve 125 mm , compact design,Floating Ball, full bore,
Buah 3 0,06% - - - 0,00% 0,00% 0,00%
PE 80/PE 100 SDR 11 (Isolated / Future Valve)
Pipa Casing
Pipa Casing 6 Galvanis Meter 143 0,17% - - - 0,00% 0,00% 0,00%
2 KONSTRUKSI
Pekerjaan Penggelaran Pipa PE dia. 125 mm Meter 4.730 0,05% - - - 0,00% 0,00% 0,00%
Pekerjaan Penyambungan Pipa PE dia. 125 mm Butt Fusion ttk 395 0,17% - - - 0,00% 0,00% 0,00%
Pekerjaan Penyambungan Pipa PE dia. 125 mm Electro
ttk 193 0,09% - - - 0,00% 0,00% 0,00%
Fusion
Pekerjaan Manual Boring Pipa PE dia. 125 mm (termasuk
Meter 3.391 1,02% - - - 0,00% 0,00% 0,00%
entry/exit pit dan reinstatement)
PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM TA 2020
BREAKDOWN PROGRESS BULAN KE-1
PMC - TANJUNG ENIM

Bulan ke-1
No Jenis Barang/Jasa Satuan Unit Volume Bobot Volume Bobot
Yang Lalu Saat Ini Akumulasi Yang Lalu Saat Ini Akumulasi
Pekerjaan Open Cut
a. Pekerjaan Pembongkaran Jalur Pipa
- Pembongkaran Aspal Meter 474 0,02% - - - 0,00% 0,00% 0,00%
b. Pekerjaan Galian Meter 1.196 0,19% - - - 0,00% 0,00% 0,00%
c. Pekerjaan Lowering Pipa PE dia. 125 mm Meter 1.196 0,02% - - - 0,00% 0,00% 0,00%
d. Pekerjaan Pengurugan Pipa PE dia. 125 mm
- Pasir Landasan dan Penutup Pipa Meter 1.196 0,05% - - - 0,00% 0,00% 0,00%
- Batako Pengaman Pipa meter 1.196 0,02% - - - 0,00% 0,00% 0,00%
- Marker Tape Meter 1.196 0,01% - - - 0,00% 0,00% 0,00%
- Pekerjaan Penimbunan (Dengan pemadatan per 20 cm) Meter 1.196 0,09% - - - 0,00% 0,00% 0,00%
e. Pekerjaan Perbaikan Jalur Pipa
- Perbaikan Aspal PE Dia 125 Meter 474 0,03% - - - 0,00% 0,00% 0,00%
Pekerjaan Manual Boring Perlintasan Jalan Pipa PE dia. 125
mm (termasuk penyambungan pipa PE 125 mm dan casing, Meter 143 0,11% - - - 0,00% 0,00% 0,00%
aksesoris, entry/exit pit dan reinstatement)
Pekerjaan Sifon untuk Sinker Pipa 125mm Buah 1 0,00% - - - 0,00% 0,00% 0,00%
Pekerjaan Box Valve Pipa PE dia. 125 mm Buah 3 0,03% - - - 0,00% 0,00% 0,00%
Papan Nama Jalur Gas (@500m) Pipa Tekanan Menengah Buah 9 0,02% - - - 0,00% 0,00% 0,00%

Pekerjaan Patok Gas Type A (@100m) Tekanan Menengah Buah 48 0,01% - - - 0,00% 0,00% 0,00%
Subtotal (C) 0,00% 0,01% 0,01%
D JARINGAN PIPA DISTRIBUSI TEKANAN RENDAH
1 PENGADAAN MATERIAL
Pipa
63 mm , Pipe PE 80/PE 100, SDR 11 Meter 67.482 8,17% - 67.482,00 67.482,00 0,00% 8,17% 8,17%
Fitting
Elbow 90, 63 mm, PE 80/PE 100 SDR 11 ISO 4437 buah 193 0,07% - 193,00 193,00 0,00% 0,07% 0,07%
Elbow 45, 63 mm, PE 80/PE 100 SDR 11 ISO 4437 buah 8 0,00% - 8,00 8,00 0,00% 0,00% 0,00%
Tee Equal, PE 80/PE 100 SDR 11 ISO 4437, 63 mm x 63
buah 421 0,15% - 421,00 421,00 0,00% 0,15% 0,15%
mm x 63 mm
End Cap Pipa 63 mm, PE 80/PE 100 SDR 11 ISO 4437 buah 308 0,11% - 290,00 290,00 0,00% 0,10% 0,10%
Coupler 63 mm, PE 80/PE 100 SDR 11 ISO 4437 buah 2.308 0,43% - 1.400,00 1.400,00 0,00% 0,26% 0,26%
Valve 1 0,00% 0,00% 0,00% 0,00%
Ball Valve 63 mm , compact design,Floating Ball, full bore,
Buah 14 0,12% - - - 0,00% 0,00% 0,00%
PE 80/PE 100 SDR 11 (Isolated / Future Valve)
Pipa Casing
Pipa Casing 4 Galvanis Meter 1.920 0,89% - - - 0,00% 0,00% 0,00%
2 KONSTRUKSI
Pekerjaan Penggelaran Pipa PE dia. 63 mm Meter 67.482 0,17% - 30.246,00 30.246,00 0,00% 0,07% 0,07%
Pekerjaan Penyambungan Pipa PE dia. 63 mm (Electro
Titik 2.308 0,90% - - - 0,00% 0,00% 0,00%
Fusion)
Pekerjaan Penyambungan Fitting & Valve PE dia. 63 mm
Titik 3.252 1,27% - 501,00 501,00 0,00% 0,20% 0,20%
(Electro Fusion)
Pekerjaan Manual Boring Pipa PE dia. 63 mm (termasuk
Meter 57.588 7,87% - 30.246,00 30.246,00 0,00% 4,13% 4,13%
entry/exit pit dan reinstatement)
Pekerjaan Open Cut
a. Pekerjaan Pembongkaran Jalur Pipa PE dia. 63 mm
- Pembongkaran Aspal Meter 6.992 0,23% - - - 0,00% 0,00% 0,00%
- Pembongkaran Beton Meter 190 0,01% - - - 0,00% 0,00% 0,00%
b. Pekerjaan Galian Meter 7.947 0,62% - - - 0,00% 0,00% 0,00%
c. Pekerjaan Lowering Pipa PE dia. 63 mm Meter 7.947 0,02% - - - 0,00% 0,00% 0,00%
d. Pekerjaan Pengurugan
- Pasir Landasan dan Penutup Pipa Meter 7.947 0,31% - - - 0,00% 0,00% 0,00%
- Batako Pengaman Pipa Meter 7.947 0,11% - - - 0,00% 0,00% 0,00%
- Marker Tape Meter 7.947 0,04% - - - 0,00% 0,00% 0,00%
- Pekerjaan Penimbunan Meter 7.947 0,37% - - - 0,00% 0,00% 0,00%
e. Pekerjaan Perbaikan Jalur Pipa
- Jalan Aspal Meter 6.992 1,67% - - - 0,00% 0,00% 0,00%
- Jalan Beton Meter 190 0,04% - - - 0,00% 0,00% 0,00%
Pekerjaan Manual Boring Perlintasan Jalan Pipa PE dia 63
mm (termasuk penyambungan pipa PE 63 mm dan casing, Meter 1.920 0,60% - - - 0,00% 0,00% 0,00%
aksesoris, entry/exit pit dan reinstatement)
Pekerjaan Perlintasan Sungai (Pengadaan sinker,
Pemasangan Casing serta sinker, dan termasuk Meter 27 0,01% - - - 0,00% 0,00% 0,00%
reinstatement)
Pekerjaan Sifon Pipa 63 Buah 1 0,00% - - - 0,00% 0,00% 0,00%
Papan Nama Jalur Gas (@500m) Pipa Distribusi Tekanan
Buah 135 0,36% - - - 0,00% 0,00% 0,00%
Rendah (DTR)
Pekerjaan Box Valve Pipa PE dia. 63 mm ea 14 0,11% - - - 0,00% 0,00% 0,00%
Patok Gas Type B (@100m) Tekanan Rendah Buah 675 0,13% - - - 0,00% 0,00% 0,00%
Subtotal (D) 0,00% 13,15% 13,15%
E SAMBUNGAN RUMAH (SR)
1 MATERIAL SR Ls 4.000 22,97% - - - 0,00% 0,00% 0,00%
Tapping Saddle 63 mm x 20 mm, PE 80/PE 100 SDR 11 ISO
4437
Coupler, PE 80/PE 100, 20 mm
Pipa PE 80/PE 100, SDR 11, Dia 20 mm
Elbow, PE 80/PE 100, 20 mm
Female Transition Fitting PE 80/PE 100 20mm x 3/4 BSP
Threaded/ Mechanical Connection
Pipa Galvanize 3/4 / Three-layer CS PE Coating
Ball Valves 3/4 Gas Specification
Long Elbow 3/4 Male/Female / Flexible SS Pipe
Double Nipple galvanize 3/4
Regulator RT (Tekanan Rendah )
Meter Rumah Tangga (Meter RT) Pre Paid Inlet/Outlet size
3/4 (Include Coupling Meter)
PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM TA 2020
BREAKDOWN PROGRESS BULAN KE-1
PMC - TANJUNG ENIM

Bulan ke-1
No Jenis Barang/Jasa Satuan Unit Volume Bobot Volume Bobot
Yang Lalu Saat Ini Akumulasi Yang Lalu Saat Ini Akumulasi
2 KONSTRUKSI SR Ls 4.000 2,15% - - - 0,00% 0,00% 0,00%
Pemasangan Pipa SR (termasuk meter rumah tangga dan
pondasi beton)
Perbaikan Halaman (rekondisi lahan/ jalur pipa PE 20 mm)
Pekerjaan Pengujian Pneumatik Instalasi Sambungan
Rumah
Subtotal (E) 0,00% 0,00% 0,00%
F SAMBUNGAN KOMPOR (SK)
1 MATERIAL SK LS 4.000 8,53% - 2.310,00 2.310,00 0,00% 4,92% 4,92%
Elbow 3/4 to 1/2 Male Female
Pipa 1/2 Hot Dip Galvanized/Multilayer Pipa ke Kompor
Elbow 1/2
Ball Valve 1/2 (Certified WOG) + Nipple Slang 1/2
Klem Pipa
SockDraft, Galvanis Dia 1/2 inch
2 KONSTRUKSI SK Ls 4.000 1,83% - 80,00 80,00 0,00% 0,04% 0,04%
Pemasangan Pipa SK (dari meter rumah tangga ke kompor,
warna kuning)
Pekerjaan Pengujian Instalasi Sambungan Kompor
Subtotal (F) 0,00% 4,96% 4,96%
PENYEDIAAN KOMPOR GAS ALAM 2 TUNGKU DAN
G
SELANG
Pengadaan Kompor Ls 4.000 1,85% - - - 0,00% 0,00% 0,00%
Kompor Gas Alam 2 tungku (Body SNI)
Selang
Aksesoris (klem,dll)
Subtotal (G) 0,00% 0,00% 0,00%
H PERALATAN UTAMA
RSI Induk 3/3, 8 BarG/4 BarG - 4 BarG/2 BarG
1 Set 1 1,02% - - - 0,00% 0,00% 0,00%
(Spesifikasi sesuai P & ID dan Data Sheet RS)
Termasuk Pengujian FAT dan SAT, Pengiriman ke Site dan
pemasangan Instalasi
PIPE 4, ERW, API 5L GR. B, SCH STD, 3LPE COATED
CASING PVC 6, AW, 10 BAR
INSULATION JOINT 4, CS, #150, AS PER DATA SHEET
FLANGE 4, #150, ASTM A105, WN, RF, SCH STD, ASME
B16.5
GASKET 4, SPIRAL WOUND, SS, #150, ASME B16.20
BOLTS & NUTS, A193-B7 C/W A194-2H, ASME B18.2.1 &
B18.2.2
EQUAL TEE 4, ASTM A234 WPB, SCH. STD, BW, ASME
B16.9
90DEG ELBOW 4, ASTM A234 WPB, SCH.STD, LR, BW,
ASME B16.9
BALL VALVE 4, CS, #150 FE/FE, AS PER DATA SHEET
SOCKOLET 4x 1/2, ASTM A105, #3000, SW, MSS SP-97
BALL VALVE 1/2, CS, #150 FE/FE, AS PER DATA SHEET
PLUG 1/2, NPT-F, ASTM A105, #3000, MSS SP-97
FULL COUPLING 1/2, ASTM A105, #3000, SW, ASME
B16.11
PRESSURE INDICATOR, DIA. 4, GLYCERIN, 1/2
connection
REGULATOR VALVE 4, SELF ACTING, DIAPRAGM
PSV 1/2x1, DIRECT OPERATED
STUB END FLANGE 125 mm, ASTM A105, #150
CONCENTRIC REDUCER 180x125 mm, PE 100, HDPE,
SDR-11, EF
Enclosure
REGULATING STATION 2 inch/2 inch-4barg/2barg-
2 0,5barg/0,3barg-100m3/jam (Spesifikasi sesuai P & ID Set 4 1,16% - - - 0,00% 0,00% 0,00%
dan Data Sheet RS)
Cabinet R/S Sektor
Pressure Indikator c/w valves 1/2 0 - 5 Bar (inlet)
Pressure Indikator c/w valves 1/2 0 - 1000 mBar (outlet)
Regulator Sektor ( R/S Sektor ) integrated safety cutt off
valve 2
PRV ( Pressure Reliev Valve ) + Venting 1/2
Ball Valve CS 2
Bypass line & Needle Valve 1
Fabrication (2 stream with 1 standby line C/W dummy spool
for regulator)
Subtotal (H) 0,00% 0,00% 0,00%
I PEKERJAAN SIPIL
1 KONSTRUKSI DUDUKAN RS
Pondasi dan Pagar pengaman Unit 4 0,08% - - - 0,00% 0,00% 0,00%
Marka Tanda RS Unit 4 0,01% - - - 0,00% 0,00% 0,00%
Perbaikan / Rekondisi Lahan LS 4 0,01% - - - 0,00% 0,00% 0,00%
2 KONSTRUKSI DUDUKAN RS INDUK
Pondasi dan Pagar pengaman Unit 1 0,04% - - - 0,00% 0,00% 0,00%
Marka Tanda MRS Unit 1 0,00% - - - 0,00% 0,00% 0,00%
Perbaikan / Rekondisi Lahan LS 1 0,00% - - - 0,00% 0,00% 0,00%
Subtotal (I) 0,00% 0,00% 0,00%
SURVEYOR /AIDONES/A
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 10 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Survey Jalur Keterangan : Survey Jalur
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Survey Jalur Keterangan : Survey Jalur


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 11 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Survey Jalur Keterangan : Survey Jalur
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Survey Jalur Keterangan : Survey Jalur


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 12 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Survey Jalur Keterangan : Survey Jalur


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 13 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 14 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 15 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 2 Lokasi : Sektor 2
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 16 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 2 Lokasi : Sektor 2

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 2 Lokasi : Sektor 2
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 17 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 3 Lokasi : Sektor 3

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 3 Lokasi : Sektor 3
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 18 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 3 Lokasi : Sektor 3

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 4 Lokasi : Sektor 4
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 19 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 4 Lokasi : Sektor 4

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 4 Lokasi : Sektor 4

Keterangan : Inspeksi Penggalian Jalur Pipa PE 63 Keterangan : Fitting Electrofusion Pipa PE 63


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 20 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 4 Lokasi : Sektor 4

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 4 Lokasi : Sektor 4

Keterangan : Manual Boring Pipa PE 63 Keterangan : Inspeksi Penggalian Jalur Pipa PE 63


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 21 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 4 Lokasi : Sektor 4

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 4 Lokasi : Sektor 4

Keterangan : Lowering Pipa PE 63 Keterangan : Manual Boring Pipa PE 63


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 22 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 4 Lokasi : Sektor 4

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 4 Lokasi : Sektor 4

Keterangan : Lowering Pipa PE 63 Keterangan : Pemasangan Pipa SR


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 23 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 4 Lokasi : Sektor 4

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 4 Lokasi : Sektor 4

Keterangan : Lowering Pipa PE 63 Keterangan : Fitting Electrofusion PE 63


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 24 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Validasi Capel Keterangan : Validasi Capel
Lokasi : Sektor 4 Lokasi : Sektor 4

Keterangan : Validasi Capel Keterangan : Validasi Capel


Lokasi : Sektor 2 Lokasi : Sektor 2

Keterangan : Lowering Pipa PE 63 Keterangan : Inspeksi Kedalaman Galian PE 63


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 25 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Tes Pneumatic SK Keterangan : Tes Pneumatic SK
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Lowering Pipa PE 63 Keterangan : Persiapan Pipa SK


Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Inspeksi Material Keterangan : Fitting Electrofusion PE 63


Lokasi : Gudang EPC Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 26 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Lowering Pipa PE 63 Keterangan : Inspeksi Kedalaman Galian PE 63
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Lowering Pipa PE 63 Keterangan : Fitting Electrofusion Pipa PE 63


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 27 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Pemasangan SR Keterangan : Lowering Pipa PE 63
Lokasi : Sektor 1 Lokasi : Sektor 2

Keterangan : Fitting Electrofusion PE 63 Keterangan : Fitting Electrofusion Pipa PE 63


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 28 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Persiapan Pipa SK Keterangan : Instalasi Pipa SK
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Lowering Pipa PE 63 Keterangan : Inspeksi Penggalian Jalur Pipa PE 63


Lokasi : Sektor 1 Lokasi : Sektor 2

Keterangan : Fitting Electrofusion Pipa PE 63 Keterangan : Fitting Electrofusion Pipa PE 63


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 29 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Survey Jalur Pipa CS 4" Keterangan : Survey Jalur Pipa CS 4"
Lokasi : RSI - Tie In Lokasi : RSI - Tie In

Keterangan : Lowering Pipa PE 63 Keterangan : Inspeksi Penggalian Jalur Pipa PE 63


Lokasi : Sektor 2 Lokasi : Sektor 2
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 30 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Manual Boring Pipa PE 63 Keterangan : Lowering Pipa PE 63
Lokasi : Sektor 2 Lokasi : Sektor 2

Keterangan : Persiapan Pipa SK Keterangan : Instalasi Pipa SK


Lokasi : Sektor 1 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 31 MARET 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Lowering Pipa PE 63 Keterangan : Instalasi Pipa SK
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Manual Boring Pipa PE 63 Keterangan : Fitting Electrofusion Pipa PE 63


Lokasi : Sektor 2 Lokasi : Sektor 2
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 1 APRIL 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Instalasi Pipa SK Keterangan : Manual Boring Pipa PE 63
Lokasi : Sektor 1 Lokasi : Sektor 2

Keterangan : Fitting Electrofusion Pipa PE 63 Keterangan : Fitting Electrofusion Pipa PE 63


Lokasi : Sektor 2 Lokasi : Sektor 2
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 2 APRIL 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Manual Boring Pipa PE 63 Keterangan : Inspeksi Kedalaman Galian PE 63
Lokasi : Sektor 2 Lokasi : Sektor 1

Keterangan : Fitting Electrofusion Pipa PE 63 Keterangan : Lowering Pipa PE 63


Lokasi : Sektor 2 Lokasi : Sektor 1
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 3 APRIL 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Instalasi Pipa SK Keterangan : Tes Pneumatic SK
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Fitting Electrofusion Pipa PE 63 Keterangan : Lowering Pipa PE 63


Lokasi : Sektor 2 Lokasi : Sektor 3
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 4 APRIL 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Instalasi Pipa SK Keterangan : Tes Pneumatic SK
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Fitting Electrofusion Pipa PE 63 Keterangan : Lowering Pipa PE 63


Lokasi : Sektor 2 Lokasi : Sektor 2
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 5 APRIL 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Manual Boring Pipa PE 63 Keterangan : Inspeksi Galian Pipa PE 63
Lokasi : Sektor 3 Lokasi : Sektor 3

Keterangan : Fitting Electrofusion Pipa PE 63 Keterangan : Lowering Pipa PE 63


Lokasi : Sektor 2 Lokasi : Sektor 3
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 6 APRIL 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Manual Boring Pipa PE 63 Keterangan : Lowering Pipa PE 63
Lokasi : Sektor 3 Lokasi : Sektor 3

Keterangan : Fitting Electrofusion Pipa PE 63 Keterangan : Lowering Pipa PE 63


Lokasi : Sektor 3 Lokasi : Sektor 3
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 7 APRIL 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Tes Pneumatic SK Keterangan : Tes Pneumatic SK
Lokasi : Sektor 1 Lokasi : Sektor 1

Keterangan : Fitting Electrofusion Pipa PE 63 Keterangan : Lowering Pipa PE 63


Lokasi : Sektor 3 Lokasi : Sektor 3
DIREKTORAT JENDERAL MINYAK DAN GAS BUMI –
KEMENTERIAN ENERGI DAN SUMBER DAYA MINERAL
REPUBLIK INDONESIA

LAPORAN BULANAN
PMC PENGAWASAN PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA
KAB. OGAN KOMERING ULU DAN KAB. MUARA ENIM
PERIODE : MARET - APRIL 2020

Proyek : Pembangunan Jaringan Gas Bumi untuk Rumah Tangga Pelaksana : KSO PPS - DHAMMA

Kabupaten Muara Enim (Tanjung Enim) TA 2020 Tanggal : 8 APRIL 2020

GAMBAR PEKERJAAN KONSTRUKSI


Keterangan : Tes Pneumatic SK Keterangan : Inspeksi Galian Pipa PE 63
Lokasi : Sektor 1 Lokasi : Sektor 3

Keterangan : Flushing Partial Test Keterangan : Lowering Pipa PE 63


Lokasi : Sektor 1 Lokasi : Sektor 3
SURVEYOR /AIDONES/A
SURVEYOR /AIDONES/A
PUNCH LIST

PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA KAB. OGAN KOMERING ULU DAN
KAB. MUARA ENIM 2020

INSPECTION : JALUR / SK / SR REPORT NO : JRG4-SI-160307-QC-PCHL-001


AREA/LOCATION/SECTOR
: Tanjung Enim/Sektor 1 SHEET : 01 of 05
TEST METHOD : Open Cut SR DATE : 06-Apr-20
DOKUMENTASI FOTO
No Finding STATUS TARGET CLOSE
BEFORE AFTER

Pemasangan sambungan pipa SR yang tidak sesuai


1 TGR 752 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


2 TGR 226 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


3 TGR 220 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


4 TGR 221 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


5 TGR 222 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


6 TGR 217 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


7 TGR 229 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


8 TGR 200 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


9 TGR 198 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


10 TGR 199 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

SPECIAL COMMENTS IF ANY : DOKUMENTASI AFTER REPAIR DILAMPIRKAN ( FOTO NO REGISTER DAN KEDALAMAN SAMBUNGAN SR)
PUNCH LIST

PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA KAB. OGAN KOMERING ULU DAN
KAB. MUARA ENIM 2020

INSPECTION : JALUR / SK / SR REPORT NO : JRG4-SI-160307-QC-PCHL-001


AREA/LOCATION/SECTOR
: Tanjung Enim/Sektor 1 SHEET : 02 of 05
TEST METHOD : Open Cut SR DATE : 06-Apr-20
DOKUMENTASI FOTO
No Finding STATUS TARGET CLOSE
BEFORE AFTER

Pemasangan sambungan pipa SR yang tidak sesuai


11 TGR 196 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


12 TGR 197 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


13 TGR 173 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


14 TGR 171 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


15 TGR 175 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


16 TGR 167 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


17 TGR 166 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


18 TGR 1122 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


19 TGR 1120 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


20 TGR 1125 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

SPECIAL COMMENTS IF ANY : DOKUMENTASI AFTER REPAIR DILAMPIRKAN ( FOTO NO REGISTER DAN KEDALAMAN SAMBUNGAN SR)
PUNCH LIST

PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA KAB. OGAN KOMERING ULU DAN
KAB. MUARA ENIM 2020

INSPECTION : JALUR / SK / SR REPORT NO : JRG4-SI-160307-QC-PCHL-001

AREA/LOCATION/SECTOR
: Tanjung Enim/Sektor 1 SHEET : 03 of 05
TEST METHOD : Open Cut SR DATE : 06-Apr-20

DOKUMENTASI FOTO
No Finding STATUS TARGET CLOSE
BEFORE AFTER

Pemasangan sambungan pipa SR yang tidak sesuai


21 TGR 1126 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


22 TGR 1128 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


23 TGR 1127 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


24 TGR 754 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


25 TGR 163 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


26 TGR 140 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


27 TGR 013 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


28 TGR 382 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


29 TGR 554 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


30 TGR 239 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

SPECIAL COMMENTS IF ANY : DOKUMENTASI AFTER REPAIR DILAMPIRKAN ( FOTO NO REGISTER DAN KEDALAMAN SAMBUNGAN SR)
PUNCH LIST

PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA KAB. OGAN KOMERING ULU DAN
KAB. MUARA ENIM 2020

INSPECTION : JALUR / SK / SR REPORT NO : JRG4-SI-160307-QC-PCHL-001

AREA/LOCATION/SECTOR
: Tanjung Enim/Sektor 1 SHEET : 04 of 05
TEST METHOD : Open Cut SR DATE : 06-Apr-20

DOKUMENTASI FOTO
No Finding STATUS TARGET CLOSE
BEFORE AFTER

Pemasangan sambungan pipa SR yang tidak sesuai


31 TGR 1089 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


32 TGR 1085 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


33 TGR 1031 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


34 TGR 1026 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


35 TGR 1021 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


36 TGR 1020 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


37 TGR 1017 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


38 TGR 219 13-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


39 dengan prosedure. Kedalaman galian crossing hanya TGR 1003 13-Apr-20
10cm dan tidak menggunakan casing.

Pemasangan sambungan pipa SR yang tidak sesuai


40 dengan prosedure. Kedalaman galian crossing hanya TGR 1004 13-Apr-20
10cm dan tidak menggunakan casing.

SPECIAL COMMENTS IF ANY : DOKUMENTASI AFTER REPAIR DILAMPIRKAN ( FOTO NO REGISTER DAN KEDALAMAN SAMBUNGAN SR)
SURVEYOR /AIDONES/A
PUNCH LIST

PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA KAB. OGAN KOMERING ULU DAN
KAB. MUARA ENIM 2020

INSPECTION : JALUR / SK / SR REPORT NO : JRG4-SI-160307-QC-PCHL-002


AREA/LOCATION/SECTOR
: Tanjung Enim/Sektor 1 SHEET : 01 of 04
TEST METHOD : Open Cut SR DATE : 07-Apr-20
DOKUMENTASI FOTO
No Finding STATUS TARGET CLOSE
BEFORE AFTER

Pemasangan sambungan pipa SR yang tidak sesuai


1 TGR 586 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


2 TGR 588 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


3 TGR 587 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


4 TGR 639 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


5 TGR 638 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


6 TGR 641 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


7 TGR 642 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


8 TGR 640 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


9 TGR 584 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


10 TGR 585 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

SPECIAL COMMENTS IF ANY : DOKUMENTASI AFTER REPAIR DILAMPIRKAN ( FOTO NO REGISTER DAN KEDALAMAN SAMBUNGAN SR)
PUNCH LIST

PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA KAB. OGAN KOMERING ULU DAN
KAB. MUARA ENIM 2020

INSPECTION : JALUR / SK / SR REPORT NO : JRG4-SI-160307-QC-PCHL-002


AREA/LOCATION/SECTOR
: Tanjung Enim/Sektor 1 SHEET : 02 of 04
TEST METHOD : Open Cut SR DATE : 07-Apr-20
DOKUMENTASI FOTO
No Finding STATUS TARGET CLOSE
BEFORE AFTER

Pemasangan sambungan pipa SR yang tidak sesuai


11 TGR 634 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


12 TGR 632 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


13 TGR 633 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


14 TGR 644 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


15 TGR 643 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


16 TGR 583 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


17 TGR 628 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


18 TGR 582 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


19 TGR 573 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


20 TGR 571 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

SPECIAL COMMENTS IF ANY : DOKUMENTASI AFTER REPAIR DILAMPIRKAN ( FOTO NO REGISTER DAN KEDALAMAN SAMBUNGAN SR)
PUNCH LIST

PEMBANGUNAN JARINGAN GAS BUMI UNTUK RUMAH TANGGA KAB. OGAN KOMERING ULU DAN
KAB. MUARA ENIM 2020

INSPECTION : JALUR / SK / SR REPORT NO : JRG4-SI-160307-QC-PCHL-002


AREA/LOCATION/SECTOR
: Tanjung Enim/Sektor 1 SHEET : 03 of 04
TEST METHOD : Open Cut SR DATE : 07-Apr-20
DOKUMENTASI FOTO
No Finding STATUS TARGET CLOSE
BEFORE AFTER

Pemasangan sambungan pipa SR yang tidak sesuai


21 TGR 631 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


22 TGR 572 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


23 TGR 570 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


24 TGR 568 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


25 TGR 569 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


26 TGR 563 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


27 TGR 565 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


28 TGR 564 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


29 TGR 566 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

Pemasangan sambungan pipa SR yang tidak sesuai


30 TGR 567 14-Apr-20
dengan procedure. (kedalaman tidak sesuai procedure)

SPECIAL COMMENTS IF ANY : DOKUMENTASI AFTER REPAIR DILAMPIRKAN ( FOTO NO REGISTER DAN KEDALAMAN SAMBUNGAN SR)

Anda mungkin juga menyukai