RENCANA ANGGARAN BIAYA

NAMA PROYEK : PEMBANGUNAN GEDUNG RA NURUL HIKHMAH


PEMILIK : YAYASAN BIRRUL MUNADI
LOKASI : DESA KEPONGPONGAN KEC. TALUN KAB. CIREBON

NO ITEM PEKERJAAN
HARGA PEK. (RP) PERSEN BOBOT PEK.(%)
I.1 Pengukuran dan pemasangan bouwplank 6049780.5888 0.211757350822397
I.2 Pembuatan steiger dari bambu 5129280 0.179537543301509
I.3 Membongkar Bangunan (Mushola, WC, Tembok ) 4200000 0.147010434576848
PEKERJAAN LANTAI 1
II PEKERJAAN PONDASI TAPAK
II.1 Galian Tanah 1928445.3 0.0675
II.2 Urugan Pasir 1927920 0.067482
Membuat Pondasi Tapak
Pembesian 155736525 5.451165
Bekisting 9,463,860.00 0.331259
Beton AD. 1:2:3 9473906.50625 0.33161
II.3 Pasangan Batu AD 1:5 2656583.9230392 0.092987
II.4 Urugan kembali bekas galian 6088549.56372001 0.213114
III PEKERJAAN BETON/PEMBESIAN
III.1 SLOOF (S1 & S2)
III.1.1 Pembesian 183225939.6 6.413363
III.1.2 Bekisting 3321325.35 0.116255
III.1.3 Beton AD. 1:2:3 10639523.69295 0.37241
III.2 KOLOM (K1)
III.2.1 Pembesian 274280194.365517 9.600488
III.2.2 Bekisting 42323916.2337931 1.481442
III.4.3 Beton AD. 1:2:3 74161.92 0.002596
III.3 KOLOM (K2)
III.3.1 Pembesian 9873542.25 0.345599
III.3.2 Bekisting 4062871.8 0.142211
III.3.3 Beton AD. 1:2:3 87156.81 0.003051
III.4 KOLOM (K3)
III.4.1 Pembesian 8647666.66666667 0.30269
III.4.2 Bekisting 2992829.2 0.104756
III.4.3 Beton AD. 1:2:3 74161.92 0.002596
IV PEKERJAAN PASANGAN DINDING BATA
IV.1 Pasangan Dinding Bata AD. 1:5 26956901.125 0.943559
IV.2 Plesteran Dinding Bata AD. 1:5 25414945.78 0.889586
IV.3 Pasang Roster / Bata terawang 4186170 0.146526
V PLAT BETON/CANOPY
V.4.1 Pembesian 494633520 17.3134
V.4.2 Bekisting 115260212.966 4.034394
V.4.3 Beton AD. 1:2:3 28722271.0355 1.005351
III.8 TANGGA
III.8.1 Pembesian 37131270 1.299687
III.8.2 Bekisting 5097102.013 0.178411
III.8.3 Beton AD. 1:2:3 2156130.44625 0.07547
V PEKERJAAN KUSEN PINTU DAN JENDELA
V.1 P1 1462611.86 0.051195
V.2 P2 10386251.12 0.363545
V.3 P3 3420000 0.119708
V.4 J1 1117298.28 0.039108
V.5 J2 1245698.28 0.043603
V.6 B1 2166750 0.075842
VII PEKERJAAN LANTAI
VII.1 Urugan tanah (t = 40 cm) 25284869.376 0.885033
VII.2 Urugan Pasir (t = 5 cm) 1537350 0.053811
VII.3 Beton tumbuk lantai AD. 1:3:6 4325312.5 0.151397
VII.4 Pasangan lantai Keramik 40 x 40 cm 18733840 0.655731
VIII PEKERJAAN KAMAR MANDI
VIII.1 Pasangan closet duduk INA 1,408,050.00 0.049285
VIII.2 Pasangan keramik lantai KM 20x20 cm 1638851 0.057364
VIII.3 Pasangan keramik Dinding KM 20x25 cm 5490015 0.192164
VIII.4 Instalasi air bersih 1200000 0.042003
VIII.5 Instalasi air kotor 1600000 0.056004
VIII.6 Pasangan kran air Dia. 1/2" 498000 0.017431
VIII.7 Pembuatan septictank dan rembesan 1647368.73165 0.057662
VIII.8 Pengadaan pompa air listrik 500000 0.017501
VIII.9 Pengadaan reservoir/tandon air 650000 0.022752
PEKERJAAN LANTAI 2
III.2.1 KOLOM (K1)
III.2.1.1 Pembesian 144357997.034483 5.052889
III.2.2.1 Bekisting 22275745.3862069 0.779706
III.2.3.1 Beton AD. 1:2:3 1274292.67034483 0.044603
III.3.1 KOLOM (K2)
III.3.1.1 Pembesian 3949416.9 0.138239
III.3.2.1 Bekisting 1625148.72 0.056884
III.3.3.1 Beton AD. 1:2:3 34862.724 0.00122
III.4.1 KOLOM (K3)
III.4.1.1 Pembesian 17295333.3333333 0.60538
III.4.2.1 Bekisting 5985658.4 0.209513
III.4.3.1 Beton AD. 1:2:3 148323.84 0.005192
III. 5 BALOK (B1)
III.5.1 Pembesian 458402270 16.04522
III.5.2 Bekisting 91298707.242 3.195682
III.5.3 Beton AD. 1:2:3 26618410.41825 0.93171
III.6 BALOK (B2)
III.6.1 Pembesian 118685041.2 4.154271
III.6.2 Bekisting 29009323.084 1.015398
III.6.3 Beton AD. 1:2:3 6891776.95365 0.241229
IV.1 PEKERJAAN PASANGAN DINDING BATA
IV.1.1 Pasangan Dinding Bata AD. 1:5 26956901.125 0.943559
IV.2.1 Plesteran Dinding Bata AD. 1:5 25414945.78 0.889586
IV.3.1 Pasang Roster / Bata terawang 4186170 0.146526
V.1 PEKERJAAN KUSEN PINTU DAN JENDELA
V.1.1 P1 1462611.86 0.051195
V.2.1 P2 10386251.12 0.363545
V.3.1 P3 3420000 0.119708
V.4.1 J1 5586491.4 0.195541
V.5.1 J2 5605642.26 0.196211
V.6.1 B1 2166750 0.075842
PEKERJAAN KUDA-KUDA/ATAP
VI.1 Pasang Rangka Atap Baja Ringan 49976064 1.749286
VI.2 Pasang Genteng Press Beton 51624262.682 1.806977
VI.3 Pasang Nok Genteng 3609082.1 0.126327
VI.4 Pasangan langit-langit rangka Plafond holo 2/4 (GRC) 50676199.1111111 1.773793
VI.5 Pasangan list keliling gypsum 8988278.675 0.314612
VII.1 PEKERJAAN LANTAI
VII.1.1 Urugan tanah (t = 40 cm) 25284869.376 0.885033
VII.2.1 Urugan Pasir (t = 5 cm) 1537350 0.053811
VII.3.1 Beton tumbuk lantai AD. 1:3:6 4325312.5 0.151397
VII.4.1 Pasangan lantai Keramik 40 x 40 cm 18733840 0.655731
VIII.1 PEKERJAAN KAMAR MANDI
VIII.1.1 Pasangan closet duduk INA 1,408,050.00 0.049285
VIII.2.1 Pasangan keramik lantai KM 20x20 cm 1638851 0.057364
VIII.3.1 Pasangan keramik Dinding KM 20x25 cm 5490015 0.192164
VIII.4.1 Instalasi air bersih 1200000 0.042003
VIII.5.1 Instalasi air kotor 1600000 0.056004
VIII.6.1 Pasangan kran air Dia. 1/2" 498000 0.017431
VIII.7.1 Pembuatan septictank dan rembesan 1647368.73165 0.057662
VIII.8.1 Pengadaan pompa air listrik 500000 0.017501
VIII.9.1 Pengadaan reservoir/tandon air 650000 0.022752
IX PEKERJAAN MENGECAT
IX.1 Pengecatan tembok dan langit-langit 20076937.25 0.702743
X PEKERJAAN LISTRIK
X.1 Pemasangan listrik baru 1300 Watt 2000000 0.070005
X.2 Pemasangan titik saklar 362120 0.012675
X.2 Pemasangan titik saklar ganda 1810600 0.063375
X.3 Pemasangan titik stop kontak 1458880 0.051064
X.4 Pemasangan lampu downlight (lengkap) 18476760 0.646733
XI PEKERJAAN LAIN
XII.1 Pemasangan Pagar besi 9450000 0.330773
XII.2 Pembersihan Pekerjaan 800000 0.028002
2856940061.49237 100