METODE KERJA

TRIAL COMPACTION
PROYEK TOL PROBOLINGGO BANYUWANGI STA 17+600 s/d STA 20+200
PT . SARANA BANGUN PUSAKA

RENCANA VARIABLE PASSING UNTUK PELAKSANAAN TRIAL COMPACTION : (1) PENYEDIAAN OPRIT & JALAN AKSES KE RENCANA LOKASI LAJUR
1. LAJUR – 1 , PASSING = 8 ( 2 PASSING VIBROROLLER – 4 PASSING VIBROSHEEP FOOT – 2 PASSING VIBROROLLER ) TRIAL COMPACTION :
2. LAJUR – 2 , PASSING = 10 ( 2 PASSING VIBROROLLER – 5 PASSING VIBROSHEEP FOOT – 3 PASSING VIBROROLLER )
3. LAJUR – 3 , PASSING = 12 ( 2 PASSING VIBROROLLER – 6 PASSING VIBROSHEEP FOOT – 3 PASSING VIBROROLLER ) (2) STAKE OUT AREA LAJUR RENCANA PELAKSANAAN TRIAL
COMPACTION ; PENGAMBILAN DATA UKUR KONDISI EXISTING AREA
No Nama Peralatan / Material Sat Vol Keterangan Tambahan LAJUR RENCANA TRIAL COMPACTION DAN PENYEDIAAN PATOK ACUAN
ELEVASI TRIAL COMPACTION :
1 Material Tanah Urug m3 150 Eks Quarry Curah Suri – IUP OP Solehudin
(3) DIMENSI LAJUR TRIAL COMPACTION PER VARIABLE = ± 3 M X 25 M
2 Excavator PC-200 / Setara unit 1
3 Dozer D-65 unit 1
4 Vibro Roller unit 1
5 Vibro Sheefoot unit 1
6 Total Station & Waterpass Set set 1
7 Sandcone Test ; Spiritus ; Cawan Kecil ; set 1
Timbangan

(4) PENDATAAN VOLUME MATERIAL ON DUMP TRUCK : (6) PENGHAMPARAN & PERATAAN MATERIAL TANAH URUG (7) PENGAMBILAN DATA UKUR HASIL HAMPARAN TANAH URUG
(5) MATERIAL TANAH URUG DITUANG DI MASING – MASING DENGAN BULDOZER DENGAN HAMPARAN TANAH URUG LOOSE (LOOSE) :
LOKASI / LAJUR RENCANA TRIAL COMPACTION : ± 30 CM :

Loose : ± 30 cm Loose : ± 30 cm

(8) PEMADATAN TIMBUNAN ± 30 CM LOOSE - ± 20 CM PADAT , (9) PENGAMBILAN DATA UKUR / PENGECEKKAN ELEVASI HASIL
LAYER PEMADATAN DENGAN VIBRO ROLLER & VIBRO HAMPARAN TANAH URUG (PADAT) :
SHEEPFOOT DENGAN VARIABLE JUMLAH PASSING SESUAI YANG
DIRENCANAKAN PADA TRIAL COMPACTION DI TIAP LOKASI /
HASIL AKHIR :
(10) SANDCONE TEST & PENGETESAN KADAR AIR SEJUMLAH 2 (DUA)
LAJUR YG TELAH DISIAPKAN : (*) PENYIRAMAN AIR KE TITIK PER LOKASI/LAJUR : DENGAN ACUAN PENILAIAN HASIL
PERMUKAAN TIMBUNAN (JIKA DIPERLUKAN) : VARIABLE TRIAL COMPACTION ATAS PEROLEHAN KEPADATAN PENENTUAN VARIABLE PASSING OLEH
MINIMUM DI = 95% PEMBERI KERJA DAN ATAU KONSULTAN
PENGAWAS YANG AKAN DIGUNAKAN
SUBKONTRAKTOR SEBAGAI ACUAN
PELAKSANAAN PEMADATAN TIMBUNAN :

Layer (Padat) : ± 20 cm Layer (Padat) : ±20 cm (*) PERKIRAAN INDEKS MATERIAL CURAH :