METHODE ERECTION
STRUCTUR BAJA - BETAINE PLANT

No. 003/MKKP/Sunshine/I/2022
Rev. No :
Lian Juan Engineering Sdh.Bhd

Page |1

METHOD STATEMENT FOR STEELL ERECTION

PT. MITRA KHARISMA KONSTRUKSI PRIMA

PROYEK ERECTION BAJA

NOMOR :

WAKTU PENGAJUAN : 09 April 2022

WAKTU PELAKSANAAN :

ESTIMASI PEKERJAAN :

AREA KERJA : Betain Construction Area


PT. MKKP PT. LJE PT. UOI

PREPARED REVIEW CHECKED Review BY CHECKED APPROVED APPROVE


REV DESCRIPTION DATE BY BY BY SHE Engineering BY SHE BY PT.UOI D BY
PT.MKKP PT.MKKP PT.LJE PT. LJE PT.UOI PT.UOI
Work Method
DAFTAR ISI

1. Lembar Persetujuan.................................................................................................................1
2. Daftar Isi………………………………………………………………………………………………………………………………2
3. Survey Assesment Area Kerja……………………………………………………………………………………………….3
4. Informasi Material………………………………………………………………………………………………………………..17
5. Alat yang digunakan……………………………………………………………………………………………………………..17
6. List Peralatan………………………………………………………………………………………………………………………..17
7. List Manpower………………………………………………………………………………………………………………………17
8. Peralatan Safety yang digunakan………………………………………………………………………………………….18
9. List APD………………………………………………………………………………………………………………………………..18
10. Tahap – Tahap Working Method………………………………………………………………………………………….19
11. Analisa Safety……………………………………………………………………………………………………………………...21
12. Pernyataan Safety, Kolom Komentar dan Catatan Safety PT. UOI………………………………………..30

METHOD STATEMENT FOR STEELL ERECTION


1. LOKASI PEKERJAAN
 Pelaksanaan Pekerjaan : PT. Mitra Kharisma Konstruksi Prima
 Lokasi : 9 Hektar Project Sunshine Betain
 Hari/ Tanggal : Selasa, 18 Januari 2022
 Waktu Pelaksanaan : 08.00 s/d Selesai
2. Lingkup Kerja
1. Pekerjaan ini meliputi Unloading dan Lifting Struktur Baja Betaine
2. Survey Assesment Area Kerja

3. Persiapan Pekerjaan
1. Pembuatan program kerja( Work Plan ) termasuk Metode Kerja, Time Line,
Peralatan,Personil Kerja dan gambar kerja yang akan digunakan untuk memperoleh
persetujuan dari pihak Pemilik Kerja dan atau Konsultan sebelum pekerjaan.
2. Memberitahu kepada pemilik kerja atau konsultan secara tertulis.

4. Uraian Pekerjaan
Persiapan Alat kerja menggunakan Crane
1. Jenis : Rought Terrain Crane
2. Pabrik Pembuatan : Kobelco
3. Tahun Pembuat : 2016
4. Merk / Model : Kobelco / RK250 - 3
5. No Serial : EZ 06212
6. Untuk Mengangkut : Lifting Structur H – Beam
7. Kapasitas Angkat : 25.000 Kg
8. Tinggi Angkat : 25 Meter
9. Jenis Motor Penggerak : Motor Diesel Mitsubishi 6D16-TL 184 KW
10. Kecepatan Angkat : 107 m/mnt
11. Tinggi Angkat : 25 Meter
12. Diameter TKB Utama : 16 mm, IWRC, RRL
13. Alat – alat Perlengkapan : Kunci Roda, segel dan Sling,Tools set
14. Alat – alat perlengkapan : Fire nextinguisher, Load Moment Limiter,leght
Sensor, angel sensor & Press sensor, roll out,
Hydraulick system Device.
14. Alat- alat Pengamat : Racun Api ( APAR ) P3K
15. Lain – lain : B 2439 XAU.

5. Peralatan dan Perlengkapan


Peralatan
No Alat Cap Unit

1 Webbing Sling 3 Ton Panjang 6 Meter 2 Unit

2 Wire Rope Sling 16”

3 Shakel 7/8 “ ( 6,5 Ton ) 2 Unit

4 Full Boddy Harnes absorber 4 Pcs

5 Tag Line 10 mm 1 Pcs

6 Life line load test (terberat 12 mm 4 Pcs


80kg/orang)

Alat yang digunakan

Alat Qty (pcs)

Mobile crane RK 250 , 25 Ton 1

Boom lift / Cherry Picker 1

Palu 1

6. Persiapan area kerja di 9 Hektar


1. Toolbox Meeting sebelum melakukan pekerjaan dan melakukan pre Job Analysis untuk menentukan
metode yang akan dilakukan,hambatan saat bekerja dan resiko pada saat melakukan pekerjaan.
2. Mempersiapkan barricade dan signboard disekitar area kerja
3. Memastikan area kerja tidak ada pekerja lain yang tidak berwenang
4. Memastikan alat angkat crane sudah dilakukan pemeriksaan sebelum digunakan
5. Memastikan pekerja sudah memakai alat pelindung diri yang tepat dan benar
6. Memastikan cuaca dalam keadaan baik
7. Isolasi atau tidak dibenarkan pekerja lain yang berada tepat dibawah atau disekitar
area lifting dengan jarak radius ± 30 - 50 mtr.
8. Pastikan posisi penempatan Kobelco telah ditentukan dan sudah koordinasi dengan
pihak Owner
9. Pastikan area tempat yang akan dijadikan tempat penurunan material yang dipasang
telah dalam kondisi aman dan telah mendapat persetujuan dari Pihak PT. Unilever
Olechemical Indonesia
10. Isolasi atau tidak dibenarkan pekerja lain yang tidak bersangkutan berada tepat
dibawah atau disekitar area penurunan Kontainer
11. Baricade area pekerjaan dan pasang Rambu- rambu peringatan bahwa sedang dalam
aktifitas pekerjaan Lifting Stuktur H- Beam dengan menggunakan Mobile Crane
12. Lakukan pemeriksaan peralatan Crane sebelum dilakukan pengangkatan, peralatan
Crane dalam kondisi baik
13. Pekerjaan Menggunakan Mobile Crane dengan kapasitas Crane 25 Ton.
14. Pastikan semua peralatan pendukung ( Webing sling dan Shackle ) sudah diinspeksi
dan layak pakai
15. Penempatan lokasi Kobelco yang akan di erection sudah disetujui oleh pihak PT.
Unilever
16. Berikan Sign Board dan safety Line Penurunan Kontainer sementara sebelum
ditinggalkan

7. Tahap – tahap Working Method


a. Persiapan Material, alat dan area kerja
 Melakukan Pre Job Analysis untuk menentukan metode yang akan dilakukan, hambatan
saat
Bekerja, dan resiko pada saat melakukan pekerjaan
 Marking Material agar mengetahui posisi dari material tersebut melalui drawing.
 Lakukan Persiapan alat kerja seperti webbing Sling 3 ton, Shackle 6.5 T dan tali pengarah
 Harus dilakukan pemeriksaan terhadap lifting gear sebelum dimulai pekerjaan, tidak ada
peralatan rusak yang digunakan dan memastikan sertifikat Crane masih berlaku, Rigger
memiliki lisensi yang masih berlaku.
 Persiapkan cherry picker untuk diparkir di dekat area kerja
 Lakukan pembersihan area, hindari kabel power yang melintas di daerah kerja dan
mengamankan agar tidak ada orang yang melintas.
 Pekerjaan dilakukan apabila assessment area dan pembersihan seluruh hambatan telah
selesai
dilakukan.
 Pastikan outrigger crane terbuka penuh dan dudukan outrigger dipastikan kokoh.
 Pastikan safety tools sudah terpasang .
b. Erection Struktur baja
 Posisikan mobile Crane pada lokasi yang di tentukan sesuai gambar.
 Ikat struktur baja yang akan di erection menggunakan metode Coker menggunakan 2
Webbing sling 3 ton (lihat gambar).
 Pastikan semua lifting gears di lindungi dengan pengaman (webbing sling di proteksi dari
ujung tajam) , mengambil teknik penanganan secara manual yang tepat ketika
pemasangan lifting gears.
 Jarak Crane dengan laydown material ± 11 meter ( lihat gambar layout area kerja )
 Pemasangan dan pengangkatan menggunakan Crane dan posisikan struktur baja pada
pondasi
yang sesuai dengan drawing.
 Urutan pengangkatan sesuai dengan instruksi dari foreman
 Pastikan struktur baja terkunci/ terikat dengan baik dan benar dan di lakukan juru ikat
yang berkompeten.
 Mobile Crane ketika mengangkat/menurunkan beban sampai area posisi akhir dengan
perlahan dalam posisi yang aman (sebelum memulai lifting pastikan barricade semua
area lifting, tampilkan Tanda Peringatan, menjaga semua pekerja yang tidak
berkepentingan masuk kearea lifting) , gunakan pluit untuk peringatan orang lain bahwa
lifting sedang berlangsung dan area lifting bebas dari hambatan.
 Melepaskan lifting gears dari struktur baja dengan cherry picker/boom lift dan
memasang baut dan mur pada girder beam (perhatikan tangan anda dari titik jepit dan
menggunakan sarung tangan ketika melepaskan lifting Gears, selalu gunakan body
harness lengkap ketika bekerja di ketinggian dan dilakukan pekerja yang kompeten.
 Bila aktivitas pengangkatan dan pemasangan sudah selesai dilanjutkan ke struktur baja
yang berikutnya.

C. Assessment Area Kerja


Mengamankan Area Tersebut dari lalu lalang Orang, di karenakan pekerja PT. MB dan
PT. EKKN Juga beraktifitas di Satu Site dan mengamankan jalan dikarenakan banyak lalu lalang
kendaraan proyek

Assessment area kerja dilakukan oleh :

 HSE PT. MKKP : _______________________ ________________________

 Site Eng. PT. MKKP : Hardhika Novantana

 Eng. PT. UOI : ________________________________________________


 SHE PT. UOI : ________________________________________________

Catatan :
___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________

d. Informasi Material

COLUMN COILS Jangkauan TERJAUH Jangkauan TERDEKAT


Berat Material : 881 kg 1096 kg 1644 Kg
Tinggi : 6.43 M 8M 12 M
Lebar : 35 cm 35 cm 36 c m

e. Personil
 Pelaksana : 1 Orang
 Petugas K3 : 2 Orang
 Operator Crane : 1 Orang
 Rigger : 1 Orang
 Scafolder : 3 Orang
 Welder : 2 Orang
 Foreman : 2 Orang
 Semi Skill : 2 Orang
 TKBT : 7 Orang
 Helper : 6 Orang
Total Manpower : 27 Orang
f. Peralatan Safety yang digunakan
 Barricade tape Merah Putih
 Baricade Tape Kuning Hitam
 Safety Cone
 Kotak P3K
 Handy Talky
g. List Safety Sign
 Dilarang Melintas ( 2 pcs)
 Hati – hati area pengangkatan barang (2 pcs)
 Bahaya barang terjatuh dari atas (2 pcs)
h. List APD
 Sepatu Safety
 Rompi
 Kacamata Safety
 Masker
 Sarung Tangan
 Safety Helmet
 Full body harness double hook

a. I Lay Out Area Kerja ( Beban ringan dengan radius terjauh 258kg )

Posisi crane
Simulasi 3D (Beban ringan dengan radius terjauh 258kg)
Swing Radius, Ketinggian Angkatan dan Bukaan Bom yang Digunakan

Boom jangkauan beban ringan dengan radius terjauh 258kg

A = Jarak katrol ke elevasi crane


C B = Radius Crane
A C = Bentangan Boom crane

C = √ A²+B²
B C = √ 24,2²+19² 3M
C = √ 585+361
C=
√946 30,7 M
C = 30,7 m

5,2 M

17 M

19 M

Perhitungan Beban ringan dengan radius terjauh 258kg

Radius 19 m
Bukaan Boom 30,6 m
Tinggi Angkat 25,2 m
Daya Angkat 2450 kg
Beban Angkat 258 kg
Perhitungan beban
SF = Daya Angkat
Beban Angkat

PERHITUNGAN Beban ringan dengan radius terjauh


258kg
Safety Factor (Crane) = 2450
258
9,4 ( Aman )

Survey Assesment Area Kerja

Lay Out Area Kerja ( Beban sedang dengan radius terjauh 833kg )
Simulasi 3D (Beban sedang dengan radius terjauh 833kg)
Swing Radius, Ketinggian Angkatan dan Bukaan Bom yang Digunakan

Boom jangkauan beban sedang dengan radius terjauh 833kg

A = Jarak katrol ke elevasi crane


C B = Radius Crane
A C = Bentangan Boom crane

C = √ A²+B²
B C = √ 11²+17² 3M
C = √ 121+289
C=
√ 410 20,2 M
C = 20,2 m

6,13 M

1M
17 M

Perhitungan Jangkauan beban sedang dengan radius terjauh


833kg
Radius 17 m
Bukaan Boom 20,2 m
Tinggi Angkat 11 m
Daya Angkat 2800 kg
Beban Angkat 833 kg

Perhitungan beban
SF = Daya Angkat
Beban Angkat

PERHITUNGAN Jangkauan beban sedang dengan


radius terjauh 833kg
Safety Factor (Crane) = 2800
833
3,36 ( Aman )
Survey Assesment Area Kerja
Lay Out Area Kerja ( Beban berat dengan radius terjauh 1632 kg)

Simulasi 3D (Beban berat dengan radius terjauh 1632 kg)


Swing Radius, Ketinggian Angkatan dan Bukaan Bom yang Digunakan

Boom Jangkauan Beban berat dengan radius terjauh 1632 kg

A = Jarak katrol ke elevasi crane


C B = Radius Crane
A C = Bentangan Boom crane

C = √ A²+B²
B C = √ 17²+17² 4M
C = √ 289+289
C=
√578 24 M
C = 24 m
12 M

1M

17 M

Perhitungan Beban berat dengan radius terjauh 1632 kg

Radius 17 m
Bukaan Boom 24 m
Tinggi Angkat 17 m
Daya Angkat 3150 kg
Beban Angkat 1632 kg

Perhitungan beban
SF = Daya Angkat
Beban Angkat
PERHITUNGAN Beban berat dengan radius terjauh
1632 kg
Safety Factor (Crane) = 3150
1632
1,8 ( Aman )

Survey Assesment Area Kerja


Lay Out Area Kerja ( Beban berat dengan radius terdekat 1632 kg )
Simulasi 3D (Beban berat dengan radius terdekat 1632 kg)
Swing Radius, Ketinggian Angkatan dan Bukaan Bom yang Digunakan

Boom Jangkauan Beban berat dengan radius terdekat 1632 kg

A = Jarak katrol ke elevasi crane


C B = Radius Crane
A C = Bentangan Boom crane

C = √ A²+B²
B C = √ 17²+7² 4M
C = √ 289+49
C=
√338 18,3 M
C = 18,3 m

12 M

1M

7M

Perhitungan Jangkauan Terdekat beban terberat

Radius 7m
Bukaan Boom 18,3 m
Tinggi Angkat 17 m
Daya Angkat 9700 kg
Beban Angkat 1632 kg
Perhitungan beban
SF = Daya Angkat
Beban Angkat

PERHITUNGAN Jangkauan Terjauh

Safety Factor (Crane) = 9700


1632
5,9 ( Aman )

i. Gambar ikatan dengan sistem choker


j. Lampiran Foto Kondisi Lapangan
k. Analisa Safety

Nilai faktor sudut ( M ) Jenis pengikatan :


 Choker Lift = 2
 Choke Lift = 0,8

Webing Sling yang digunakan 3 ton dan pengikatan menggunakan Choke Lift , Jadi
Daya Angkat Maksimum = 2.400 kg x 2
= 4.800 kg
Safety Faktor pengangkatan Column

SF (Sling) = Daya angkat Maksimum


( Beban Angkat )
Jumlah Sling

Safety Faktor untuk Sling

Safety Beban ringan dengan Beban sedang Beban berat Beban berat dengan
Factor radius terjauh dengan radius terjauh dengan radius radius terdekat
(Sling) terjauh
= 4800 = 4800 = 4800 = 4800
(258) (833) (1632) (1632)
2 2 2 2

= 4800 = 4800 = 4800 = 4800


129 416,5 816 816

37,2 (OK) 11,5 (OK) 5,8 (OK) 5,9 (OK)

Safety Faktor untuk wire sling

Webbing seling yang digunakan, seling wayer (seling baja ) ¾ TC dan pengikatan menggunakan Choke
life
Jadi daya angkat Maksimum

D² x 8 = ¾ inch x ¾ inch x 8
= 9/16inch x 8
= 4,5 ton
Jadi

4,5 x 2 = 9 ton
Choke life = 9000 - 20%
= 7200 kg

Safety Factor Pengangkatan Wire Sling Jarak Terjauh, Beban terberat, Tiang tertinggi

SF = Daya Angkat Maksimal


( Beban Angkat )
Jumlah Seling
= 7.200 / (1.632/2 )
= 8,82 ( Aman )

Safety Factor Wire Sling Jarak Terjauh, Beban terberat, Tiang tertinggi
(Wire Sling)
= 7.200
1.632
2

= 7.29 (OK)

Safety Factor Pengangkatan Jarak Terjauh, Tiang tertinggi

SF = Daya Angkat Maksimal


( Beban Angkat )
Jumlah Seling
= 7.200 / (258/2 )
= 55,818 ( Aman )
Safety Factor Wire Sling Pengangkatan Jarak Terjauh, Tiang tertinggi
(Wire Sling)
= 7.200
258
2

= 55,818 (OK)

Safety Factor Pengangkatan Jarak Terjauh, beban terberat

SF = Daya Angkat Maksimal


( Beban Angkat )
Jumlah Seling
= 7.200 / (833/2 )
= 17,28 ( Aman )
Safety Factor Wire Sling Pengangkatan Jarak Terjauh, beban terberat
(Wire Sling)
= 7.200
833
2

= 17,28 (OK)

Safety Factor Pengangkatan Jarak Terdekat, beban terberat

SF = Daya Angkat Maksimal


( Beban Angkat )
Jumlah Seling
= 7.200 / (1.632/2 )
= 8,82 ( Aman )
Safety Factor Wire Sling Pengangkatan Jarak Terdekat, beban terberat
(Wire Sling)

= 7.200
1.632
2

= 8,82 (OK)
l. Perhitungan Safety Faktor Crane

Load Chart
Terdekat

Terjauh

Pernyataan Safety, Kolom Komentar dan Catatan Safety PT. UOI


Dengan ini kami menyatakan bahwa seluruh perencana yang tertera di dalam working method
Ini telah menyesuaikan dengan peraturan – peraturan dan standarisasi PT. UOI yang tercantum
Dalam SHE Requirements :
1. Program Wajib HSE.
 PPE ( Helm, kacamata, sarung tangan, sepatu safety, baju lengan panjang,rompi safety,
Full Body-harness double hook )
 Kualifikasi Personel
 Spanduk / Alat Bantu Visual K.3
 Barikade
 Pemeriksaan Kesehatan
 Izin Kerja
 Kerapian / Housekeeping

2. Instruksi SHE Khusus


PACKING LIST
DAFTAR BERAT BEBAN KOLOM & BALOK STRUKTUR BETAINE PLANT Halaman 1 / 4
 Perkakas BERAT TINGGI/ TOTAL
NO. URAIAN PER M' PANJANG BERAT Keterangan
 Peralatan Crane dan Lifting (KG) (M') (KG)
1 KOLOM / TIANG BAJA
1,1  Bekerja di Ketinggian
KOLOM BAJA kolom bawah GL 1 A B8 : 350 x 350 136 6,13 833,68
kolom atas GL 1 A B1 : 346 x 174 41,4 9,07 375,50
 Hanya orang yang berkepentingan saja yang bekerja
kolom bawah GL 1 B B8 : 350 x 350 136 6,13 833,68
kolom atas GL 1 B B1 : 346 x 174 41,4 9,07 375,50
Adapun Instruksi Khusus yang dapat membantu untuk menyempurnakan working method ini
kolom bawah GL 1 C B8 : 350 x 350 136 6,13 833,68
kolom atas GL 1 C B1 : 346 x 174 41,4 9,07 375,50
dapat kolom bawah GL 1 D B8 : 350 x 350 136 6,13 833,68
kolom atas GL 1 D B1 : 346 x 174 41,4 9,07 375,50 ( tinggi kolom / tiang = 6.13 m)
Dituangkan ke dalam bentuk catatan di bawah ini :
kolom bawah GL 1 E B8 : 350 x 350 136 6,13 833,68 jarak terjauh, beban terberat
kolom atas GL 1 E B1 : 346 x 174 41,4 9,07 375,50
kolom bawah GL 1 F B1 : 346 x 174 41,4 12 496,80
------------------------------------------------------------------------------------------------------------------------------------
kolom atas GL 1 F B1 : 346 x 174 41,4 3,5 144,90

1,2 KOLOM BAJA kolom bawah


Inspeksi semua alatGL
kolom atas
2 A
( tools)
GL 2 A
B8 : 350 x 350
sebelum 136
digunakan
B1 : 346 x 174 41,4
12
4,47
1.632,00
185,06
------------------------------------------------------
kolom bawah GL 2 B B8 : 350 x 350 136 12 1.632,00
kolom atas GL 2 B B1 : 346 x 174 41,4 4,47 185,06
Baricade area
kolom bawah GL 2 C B8 : 350 x 350 136 12 1.632,00
kolom atas GL 2 C B1 : 346 x 174 41,4 4,47 185,06
------------------------------------------------------------------------------------------------------
kolom bawah GL 2 D B8 : 350 x 350 136 9,13 1.241,68
kolom atas GL 2 D B1 : 346 x 174 41,4 7,04 291,46
Pengawan SPV dan GL
kolom bawah SHE2 Epada B8saat aktifitas
: 350 x 350 berlangsung
136 9,13 1.241,68
kolom atas GL 2 E B1 : 346 x 174 41,4 7,04 291,46 (tinggi kolom / tiang = 12 m)
--------------------------------------------------
kolom bawah GL 2 F B8 : 350 x 350 136 12 1.632,00 jarak terjauh, beban terberat, tiang tertinggi
kolom atas GL 2 F B1 : 346 x 174 41,4 4,47 185,06

------------------------------------------------------------------------------------------------------------------------------------
1,3 KOLOM BAJA kolom bawah GL 3 A B8 : 350 x 350 136 12 1.632,00
kolom atas GL 3 A B1 : 346 x 174 41,4 4,47 185,06 (tinggi kolom / tiang = 12 m)
kolom bawah GL 3 B B8 : 350 x 350 136 12 1.632,00 jarak terdekat, beban terberat
kolom atas GL 3 B B1 : 346 x 174 41,4 4,47 185,06
------------------------------------------------------------------------------------------------------------------------------------
kolom bawah GL 3 C B8 : 350 x 350 136 12 1.632,00
kolom atas GL 3 C B1 : 346 x 174 41,4 4,47 185,06
(______________________________)
kolom bawah GL 3 D B8 : 350 x 350 136 9,13 1.241,68
kolom atas GL 3 D B1 : 346 x 174 41,4 7,04 291,46
kolom bawah GL 3 E B8 : 350 x 350 136 11,7 1.591,20

1,4 KOLOM BAJA kolom bawah GL 4 A B1 : 346 x 174 41,4 11,7 484,38
kolom bawah GL 4 B B1 : 346 x 174 41,4 11,7 484,38

1,5 KOLOM BAJA kolom bawah GL 5 A B1 : 346 x 174 41,4 11,7 484,38
kolom atas GL 5 A B1 : 346 x 174 41,4 3,5 144,90
kolom bawah GL 5 B B1 : 346 x 174 41,4 11,7 484,38
kolom atas GL 5 B B1 : 346 x 174 41,4 3,5 144,90
kolom bawah GL 5 C B8 : 350 x 350 136 6,13 833,68
kolom atas GL 5 C B1 : 346 x 174 41,4 9,07 375,50
kolom bawah GL 5 D B8 : 350 x 350 136 6,13 833,68
kolom atas GL 5 D B1 : 346 x 174 41,4 9,07 375,50
kolom bawah GL 5 E B2 : 150 x 125 29,6 4,7 139,12

2 BALOK BAJA GRID 1


LEVEL +2M --> GL 1 E/F B2 : 250 x 125 29,6 3 88,80
LEVEL + 5 M GL 1 A/B B4 : 350 x 175 49,6 6,25 310,00
GL 1 B/C B4 : 350 x 175 49,6 6,25 310,00
GL 1 C/D B7 : 588 x 300 151 6,25 943,75
GL 1 D/E B6 : 400 x 200 66 6,25 412,50
GL 1 E/F B2 : 250 x 125 29,6 3 88,80

LEVEL + 6.6M GL 1 E / F B2 : 250 x 125 29,6 3 88,80

LEVEL + 8M GL 1 A/B B7 : 588 x 300 151 6,25 943,75


GL 1 B/C B4 : 350 x 175 49,6 6,25 310,00
GL 1 C/D B7 : 588 x 300 151 6,25 943,75
GL 1 D/E B4 : 350 x 175 49,6 6,25 310,00
GL 1 E/F B2 : 250 x 125 29,6 3 88,80
PACKING LIST
DAFTAR BERAT BEBAN KOLOM & BALOK STRUKTUR BETAINE PLANT Halaman 2 / 4
BERAT TINGGI/ TOTAL
NO. URAIAN PER M' PANJANG BERAT Keterangan
(KG) (M') (KG)
LEVEL + 10M GL 1 E / F B2 : 250 x 125 29,6 3 88,80

LEVEL + 12M GL 1 A/B B4 : 350 x 175 49,6 6,25 310,00


GL 1 B/C B4 : 350 x 175 49,6 6,25 310,00
GL 1 C/D B4 : 350 x 175 49,6 6,25 310,00
GL 1 D/E B4 : 350 x 175 49,6 6,25 310,00
GL 1 E/F B2 : 250 x 125 29,6 3 88,80

LEVEL + 15 GL 1 A/B B4 : 350 x 175 49,6 6,25 310,00


GL 1 B/C B4 : 350 x 175 49,6 6,25 310,00
GL 1 C/D B4 : 350 x 175 49,6 6,25 310,00
GL 1 D/E B4 : 350 x 175 49,6 6,25 310,00
GL 1 E/F B2 : 250 x 125 29,6 3 88,80

BALOK BAJA GRID 2


LEVEL + 5 M GL 2 A/B B4 : 350 x 175 49,6 6,25 310,00
GL 2 B/C B4 : 350 x 175 49,6 6,25 310,00
GL 2 C/D B7 : 588 x 300 151 6,25 943,75
GL 2 D/E B6 : 400 x 200 66 6,25 412,50
GL 2 E/F B2 : 250 x 125 29,6 3 88,80

LEVEL + 8M GL 2 A/B B7 : 588 x 300 151 6,25 943,75


GL 2 B/C B7 : 588 x 300 151 6,25 943,75
GL 2 C/D B7 : 588 x 300 151 6,25 943,75
GL 2 E/F B2 : 250 x 125 29,6 3 88,80

LEVEL + 12M GL 2 A/B B6 : 400 x 200 66 6,25 412,50


GL 2 B/C B6 : 400 x 200 66 6,25 412,50
GL 2 C/D B6 : 400 x 200 66 6,25 412,50
GL 2 D/E B6 : 400 x 200 66 6,25 412,50
GL 2 E/F B2 : 250 x 125 29,6 3 88,80

LEVEL + 16.47M GL 2 A/B B4 : 350 x 175 49,6 6,25 310,00


GL 2 B/C B4 : 350 x 175 49,6 6,25 310,00
GL 2 C/D B4 : 350 x 175 49,6 6,25 310,00
GL 2 D/E B4 : 350 x 175 49,6 6,25 310,00
GL 2 E/F B2 : 250 x 125 29,6 3 88,80

BALOK BAJA GRID 3


LEVEL + 5 M GL 3 A/B B4 : 350 x 175 49,6 6,25 310,00
GL 3 B/C B3 : 300 x 150 36,7 6,25 229,38
GL 3 C/D B3 : 300 x 150 36,7 6,25 229,38
GL 3 D/E B6 : 400 x 200 66 6,25 412,50

LEVEL + 6 GL 3 D / E B2 : 250 x 125 29,6 6,25 185,00

LEVEL + 8M GL 3 A/B B7 : 588 x 300 151 6,25 943,75


GL 3 B/C B7 : 588 x 300 151 6,25 943,75
GL 3 C/D B6 : 400 x 200 66 6,25 412,50
GL 3 D/E B4 : 350 x 175 49,6 6,25 310,00

LEVEL + 12M GL 3 A/B B6 : 400 x 200 66 6,25 412,50


GL 3 B/C B6 : 400 x 200 66 6,25 412,50
GL 3 C/D B6 : 400 x 200 66 6,25 412,50
GL 3 D/E B4 : 350 x 175 49,6 6,25 310,00

LEVEL + 16.47M GL 3 A / B B4 : 350 x 175 49,6 6,25 310,00


GL 3 B / C B4 : 350 x 175 49,6 6,25 310,00
GL 3 C / D B4 : 350 x 175 49,6 6,25 310,00

BALOK BAJA GRID 4


LEVEL + 5 M GL 4 A / B B4 : 350 x 175 49,6 6,25 310,00
LEVEL + 8M GL 4 A / B B3 : 300 x 150 36,7 6,25 229,38
LEVEL + 12M GL 4 A / B B3 : 300 x 150 36,7 6,25 229,38
PACKING LIST
DAFTAR BERAT BEBAN KOLOM & BALOK STRUKTUR BETAINE PLANT Halaman 3 / 4
BERAT TINGGI/ TOTAL
NO. URAIAN PER M' PANJANG BERAT Keterangan
(KG) (M') (KG)
BALOK BAJA GRID 5
LEVEL + 5 M GL 5 A / B B4 : 350 x 175 49,6 6,25 310,00
GL 5 B / C B4 : 350 x 175 49,6 6,25 310,00
GL 5 C / D B4 : 350 x 175 49,6 6,25 310,00
GL 5 D / E B2 : 250 x 125 29,6 6,25 185,00

LEVEL + 8M GL 5 A / B B4 : 350 x 175 49,6 6,25 310,00


GL 5 B / C B4 : 350 x 175 49,6 6,25 310,00
GL 5 C / D B4 : 350 x 175 49,6 6,25 310,00

LEVEL + 12M GL 5 A / B B4 : 350 x 175 49,6 6,25 310,00


GL 5 B / C B4 : 350 x 175 49,6 6,25 310,00
GL 5 C / D B4 : 350 x 175 49,6 6,25 310,00

LEVEL + 15.5M GL 5 A / B B4 : 350 x 175 49,6 6,25 310,00


GL 5 B / C B4 : 350 x 175 49,6 6,25 310,00
GL 5 C / D B4 : 350 x 175 49,6 6,25 310,00

BALOK BAJA GRID A


LEVEL + 2.6M GL A 4 / 5 B2 : 250 x 125 29,6 2,654 78,56

LEVEL + 5 M GL A 1/ 2 B4 : 350 x 175 49,6 5,15 255,44


GL A 2/ 3 B4 : 350 x 175 49,6 5,15 255,44
GL A 3/ 4 B9 : 200 x 100 21,30 2,15 45,84
GL A 4/ 5 B9 : 200 x 100 21,30 2,65 56,45

LEVEL + 6M GL A 1 / 2 B4 : 350 x 175 49,6 5,15 255,44


GL A 2 / 3 B4 : 350 x 175 49,6 5,15 255,44

LEVEL + 6.6M GL A 4 / 5 B2 : 250 x 125 29,6 2,65 78,44

LEVEL + 8M GL A 1/ 2 B4 : 350 x 175 49,6 5,15 255,44


GL A 2/ 3 B4 : 350 x 175 49,6 5,15 255,44
GL A 3/ 4 B9 : 200 x 100 21,30 2,15 45,84
GL A 4/ 5 B9 : 200 x 100 21,30 2,65 56,45

LEVEL + 10M GL A 4 / 5 B2 : 250 x 125 29,6 2,654 78,56

LEVEL + 12M GL A 1/ 2 B4 : 350 x 175 49,6 5,15 255,44


GL A 2/ 3 B4 : 350 x 175 49,6 5,15 255,44
GL A 3/ 4 B9 : 200 x 100 21,30 2,15 45,84
GL A 4/ 5 B9 : 200 x 100 21,30 2,65 56,45

LEVEL + 16.47M GL A 1 / 2 B4 : 350 x 175 49,6 5,22 258,91


GL A 2 / 3 B4 : 350 x 175 49,6 5,22 258,91
GL A 3 / 5 B4 : 350 x 175 49,6 5,22 258,91

BALOK BAJA GRID B


LEVEL + 5 M GL B 1/ 2 B4 : 350 x 175 49,6 5,15 255,44
GL B 2/ 3 B4 : 350 x 175 49,6 5,15 255,44
GL B 3/ 4 B9 : 200 x 100 21,30 2,15 45,84
GL B 4/ 5 B9 : 200 x 100 21,30 2,65 56,45

LEVEL + 8M GL B 1/ 2 B4 : 350 x 175 49,6 5,15 255,44


GL B 2/ 3 B4 : 350 x 175 49,6 5,15 255,44
GL B 3/ 4 B4 : 350 x 175 49,6 2,15 106,74
GL B 4/ 5 B4 : 350 x 175 49,6 2,65 131,44

LEVEL + 12M GL B 1/ 2 B4 : 350 x 175 49,6 5,15 255,44


GL B 2/ 3 B4 : 350 x 175 49,6 5,15 255,44
GL B 3/ 4 B4 : 350 x 175 49,6 2,15 106,74
GL B 4/ 5 B4 : 350 x 175 49,6 2,65 131,44

LEVEL + 16.47M GL B 1 / 2 B4 : 350 x 175 49,6 5,22 258,91


GL B 2 / 3 B4 : 350 x 175 49,6 5,22 258,91
GL B 3 / 5 B4 : 350 x 175 49,6 5,22 258,91
PACKING LIST
DAFTAR BERAT BEBAN KOLOM & BALOK STRUKTUR BETAINE PLANT Halaman 4 / 4
BERAT TINGGI/ TOTAL
NO. URAIAN PER M' PANJANG BERAT Keterangan
(KG) (M') (KG)
BALOK BAJA GRID C
LEVEL + 5 M GL C 1 / 2 B4 : 350 x 175 49,6 5,15 255,44
GL C 2 / 3 B4 : 350 x 175 49,6 5,15 255,44
GL C 3 / 5 B4 : 350 x 175 49,6 5,15 255,44

LEVEL + 8M GL C 1 / 2 B4 : 350 x 175 49,6 5,15 255,44


GL C 2 / 3 B4 : 350 x 175 49,6 5,15 255,44
GL C 3 / 5 B4 : 350 x 175 49,6 5,15 255,44

LEVEL + 12M GL C 1 / 2 B4 : 350 x 175 49,6 5,15 255,44


GL C 2 / 3 B4 : 350 x 175 49,6 5,15 255,44
GL C 3 / 5 B4 : 350 x 175 49,6 5,15 255,44

LEVEL + 16.47M GL C 1 / 2 B4 : 350 x 175 49,6 5,22 258,91


GL C 2 / 3 B4 : 350 x 175 49,6 5,22 258,91
GL C 3 / 5 B4 : 350 x 175 49,6 5,22 258,91

BALOK BAJA GRID D


LEVEL + 5 M GL D 1 / 2 B7 : 588 x 300 151 5,15 777,65
GL D 2 / 3 B6 : 400 x 200 66 5,15 339,90
GL D 3 / 5 B6 : 400 x 200 66 5,15 339,90

LEVEL + 8M GL D 1 / 2 B4 : 350 x 175 49,6 5,15 255,44


GL D 2 / 3 B4 : 350 x 175 49,6 5,15 255,44
GL D 3 / 5 B4 : 350 x 175 49,6 5,15 255,44

LEVEL + 12M GL D 1 / 2 B4 : 350 x 175 49,6 5,15 255,44


GL D 2 / 3 B4 : 350 x 175 49,6 5,15 255,44
GL D 3 / 5 B4 : 350 x 175 49,6 5,15 255,44

LEVEL + 16.47M GL D 1 / 2 B4 : 350 x 175 49,6 5,22 258,91


GL D 2 / 3 B4 : 350 x 175 49,6 5,22 258,91
GL D 3 / 5 B4 : 350 x 175 49,6 5,22 258,91

BALOK BAJA GRID E


LEVEL + 5 M GL E 1 / 2 B7 : 588 x 300 151 5,15 777,65
GL E 2 / 3 B6 : 400 x 200 66 5,15 339,90
GL E 3 / 5 B2 : 250 x 125 29,6 5,2 153,92

LEVEL + 8M GL E 1 / 2 B4 : 350 x 175 49,6 5,15 255,44

LEVEL + 12M GL E 1 / 2 B1 : 346 x 174 41,4 5,15 213,21


GL E 2 / 3 B4 : 350 x 175 49,6 5,15 255,44
GL E 3 / 5 B4 : 350 x 175 49,6 1,825 90,52

LEVEL + 16.47M GL E 1 / 2 B4 : 350 x 175 49,6 5,22 258,91

BALOK BAJA GRID F


LEVEL + 5 M GL F 1 / 2 B2 : 250 x 125 29,6 5,15 152,44

LEVEL + 8M GL F 1 / 2 B2 : 250 x 125 29,6 5,15 152,44

LEVEL + 12M GL F 1 / 2 B2 : 250 x 125 29,6 5,15 152,44


(panjang rafter/ kuda-kuda = 5.22m)
LEVEL + 16.47M GL F 1 / 2 B4 : 350 x 175 49,6 5,22 258,91 jarak terjauh, lifting tertinggi, beban terberat