Method Statement N2 Purging

SENTOSA AIR
SOLUSINDO

Document No. Nitrogen Purging Services Rev. : 0


SAS 001-03/X/2023 Sheet No.
1 of 9
v

COMPANY : PT MASINDO MARINE INDONESIA


CONTRACTOR : PT SENTOSA AIR SOLUSINDO
PROJECT : NITROGEN PURGING
LOCATION : SITE PERTAMINA EP FIELD PANGKALAN SUSU,
SUMATERA UTARA

1A 23/10/2023 Issued for Review EP AN IBC


PRE CHK APP CHK APP APP
REV. DATE DESCRIPTION PT SENTOSA AIR SOLUSINDO PKT
Method Statement N2 Purging
SENTOSA AIR
SOLUSINDO

Document No. Nitrogen Purging Services Rev. : 0


SAS 001-03/X/2023 Sheet No.
2 of 9
v

REVISION SHEET

No Revision Date Remarks


Method Statement N2 Purging
SENTOSA AIR
SOLUSINDO

Document No. Nitrogen Purging Services Rev. : 0


SAS 001-03/X/2023 Sheet No.
3 of 9

1. PROSES PERSIAPAN N2 PURGING ......................................................................6

2. PROSES PELAKSANAAN N2 PURGING..................................................................7

3. HOUSE KEEPING / PEMBERSIHAN ............................................................... 9


Method Statement N2 Purging
SENTOSA AIR
SOLUSINDO

Document No. Nitrogen Purging Services Rev. : 0


SAS 001-03/X/2023 Sheet No.
4 of 9

1. Metode Kerja
2. Mengadakan Pertemuan / Meeting untuk membahas pekerjaan yang akan
dilakukan dan dampak keselamatan pada pekerjaan tersebut.

B. Peralatan Kerja

Jenis-jenis peralatan yang digunakan untuk mendukung pekerjaan ini adalah:


1. Genset / Listrik (Jika ada pekerjaan malam)
2. Iso Tank (Stand by 1 unit 5000 Gall)
3. Evaporator (1 unit 1500 Nm3 )
4. Pressure gauge
5. Fitting connection
6. Flexible hose Rubber & Metal
7. O2 Detector untuk Object
8. O2 detector ( Untuk Manpower )
9. Manual Valve / ball balve
10. Hand Tools (Wrench)
11. Blind Flange C/W, Bolt and Nut, Gasket
12. Whip check
13. HT (Handy Talky)
Method Statement N2 Purging
SENTOSA AIR
SOLUSINDO

Document No. Nitrogen Purging Services Rev. : 0


SAS 001-03/X/2023 Sheet No.
5 of 9

C. Penggunaan Alat Pelindung Diri (APD)

Pada saat akan melakukan pekerjaan dan memasuki daerah lokasi kerja, semua karyawan yang

terlibat wajib menggunakan Alat Pelindung Diri (APD) yang sesuai dengan Standar

Keselamatan Kerja, seperti :

3. Helm Safety ( Safety Helmet ) dan Tali dagu

4. Kaca Mata Keselamatan ( Safety Google Glass Clear )

5. Sepatu Keselamatan ( Safety Shoes )

6. Baju Kerja (uniform)

7. Sarung Tangan

8. Face Shield

9. Masker Respirator / N95

10. Ear muff/Ear plug


Method Statement N2 Purging
SENTOSA AIR
SOLUSINDO

Document No. Nitrogen Purging Services Rev. : 0


SAS 001-03/X/2023 Sheet No.
6 of 9

1. PROSES PERSIAPAN N2 PURGING

 Sebelum kegiatan persiapan N2 Purging sudah dilakukan Punch list dan Box Up.
 Pasang Baricade & sign / rambu2 diarea kerja dan Penempatan Material.
 Pasang selang di Titik Inject
 Pasang Pressure Gauge di Titik Inject.
 Loading & Unloading equipment N2 Purging dengan menggunakan crane 25 ton
Method Statement N2 Purging
SENTOSA AIR
SOLUSINDO

Document No. Nitrogen Purging Services Rev. : 0


SAS 001-03/X/2023 Sheet No.
7 of 9

 Lakukan pemasangan flexible hose dari isotank ke evaporator


 Lakukan pemasangan flexible hose dari Evaporator ke titik inject

Dibutuhkan 3 Orang SDM di lokasi Dari Pihak Pertamina, dalam hal pelaksanaan Purging Yang di lengkapi
(Handy Talky) Jumlah Orang menyesuaikan kebutuhan. Untuk fungtional kerja sbb :

1. Indentifikasi Object ( pastikan dalam keadaan Baik ) Sebelum dilakukan Purging


2. Proses Purging biasanya dilakukan dalam 3 tahap , ( Menyesuaikan Kondisi Tangki)
3. Membantu Buka tutup Valve saat Proses Purging di lakukan.

2. PROSES PELAKSANAAN N2 PURGING PIPING

 Pastikan Semua Valve tertutup


 Inject Nitrogen menggunakan Isotank dan evaporator yang telah tersambung dengan
pressure hose dan flexible hose dan Setel laju aliran sesuai dengan tekanan yang dibutuhkan.

 Proses Purging dengan Tekanan yang dibutuhkan, untuk selanjutnya lakukan pengecekan tekanan.secara
berkala. Jika tekanan melebihi MAWP tangki segera release tekanan

 Cek O2 content secara berkala di lokasi venting, release dengan pelan

 Lakukan Berulang sampai O2 content telah tercapai sesuai target

3. HOUSE KEEPING/PEMBERSIHAN.

Jika pekerjaan N2 Purging sudah selesai, maka semua lokasi pekerjaan harus dibersihkan yang ada
disekitar lokasi dan semua sampah harus dibuang pada tempatnya serta disesuaikan dengan jenis
sampahnya. Tata dan atur semua material dan Peralatan pada tempatnya agar tidak mempersempit
lokasi kerja dan tidak mengganggu akses keluar- masuk lokasi.