METODE

PELAPORAN
KINERJA K3LMP &
5R

Jakarta, OKTOBER 2018


MATERI PELAPORAN BUJT

1 MAPPING PERSONIL K3L

2 CATATAN & PENILAIAN KINERJA K3L

3 PERMASALAHAN & TINDAKAN PERBAIKAN K3L

4 TINDAKLANJUT HASIL AUDIT/INSPEKSI K3L

5 USULAN IMPROVEMENT
MAPPING PERSONIL K3L
PT. CITRA WASPPHUTOWA
PROYEK TOL DEPOK-ANTASARI

PERIODE : OKTOBER 2018


STRUKTUR ORGANISASI PT. CITRA WASPPHUTOWA
STRUKTUR ORGANISASI KONSULTAN PENGAWAS

Ir. Nuli Hapsari


Risk management Specialist
Ir. Yahmanto Djaja Sudjana
Geodetic Eng. - 18 Chief Surv.
Ebo Yusup Bohari

Garnia Suhandar
Yusuf Suhendar

Ir. Titik Mardiyati


Dedy Sopyan
Surveyor (1)

Surveyor (2)

Surveyor (3)

Surveyor (4)

Landscape Eng.
TO BE NAMED
Traffic Eng.
TO BE NAMED
Constr./Proj. Manag. Eng.
Ir. Zaedadin R. TO BE NAMED
Facility (Mech Electrical) Eng. Ass. Facility (Mech Electrical) Eng.
Hendri Prabowo, ST Wawin Hendarwin, ST
Drainage Eng. 1. Ass. Drainage Eng.
Chief Review Design Eng.
Ir. Budhi Haryono, MSc

TO BE NAMED TO BE NAMED
3. Structure Eng. (3) - 13 3. Ass. Structure Eng. (3)
Ir. Sarmayenti Sali Andri Wahyudi, ST
2. Structure Eng. (2) 2. Ass. Structure Eng. (2)
Ir. Hanofik TO BE NAMED
1. Structure Eng. (1) 1. Ass. Structure Eng. (1)
TO BE NAMED TO BE NAMED
2. Highway Eng. (2) 2. Ass. Highway Eng. (2)
Ir. Sutikna
TO BE NAME
1. Highway Eng. (1)
1. Ass. Highway Eng. (1)

Ronald Alfred S.,ST


EWPav Insp. (2)
Ir. Alice Kiswani D., MM Unik Sugiono, SE
Environmental Spec. Ass. Environmental Spec. - 18
Ir. Agus Salam A. Surbakti
Cost Control Eng. (Doc. Spec.)
Chief Engineer/Team Leader

Ass. Cost Control Eng.


Ir. M. Teguh Wiyono

(Highway Eng.)

EWPav Insp. (2)


Nofria Effendi
EWPav Insp. (2)
Suparan
TO BE NAMED
2. Quantity Eng. (2)
Rina Ratnasari SST
2. Quantity Surv. (2)
Ir. Agus Salam
1. Quantity Eng. (1)
Aprilia Wardah, SKt

Eko Chandra, ST

Wahyu Setiawan
EWPav Insp. (1)
EWPav Insp. (1)
1. Quantity Surv. (1)

Landscape Insp. (3)


Rohmat Agus Solihin

TO BE NAMED
Lab Technician (1)

Landscape Insp. (3)


Sugeng

TO BE NAMED
Plant Inspector (1) (2)
Ir. Elipen
Ir. Mamik Radyantono,MT
Quality (Soil, Mat & Pav) Eng.

Passa Prihandono
Chief Supervision Eng. +

Struc. Insp. (2)


Aulia Rahman
Andi Nugroho

Struc. Insp. (2)


Lab Technician (3)

M/E Inspector (1) - (2)


Syarif Usman, ST

TO BE NAMED
SMK3L
Teguh Brotowijoyo, ST Lab Technician (2)
Project Control Eng.

M/E Inspector (1) - (2)


TO BE NAMED

Ahmad Ibrahim
Struc. Insp. (1)
Struc. Insp. (1)
Lili Sutardi
Ir. Wandoyo Sukardi
2. Chief Inspector (2)
Fajar Darajat, ST
1. Chief Inspector (1)
STRUKTUR ORGANISASI KONTRAKTOR PELAKSANA
STRUKTUR ORGANISASI K3 KONTRAKTOR PELAKSANA
PT. GIRDER INDONESIA
STRUKTUR ORGANISASI K3L
PT. GIRDER INDONESIA
PROYEK PEMBANGUNAN JALAN TOL DEPOK - ANTASARI

GERARD SONDAKH
GENERAL MANAGER

EDRIE
KOORDINATOR

DUDIK INRASMORO ZULFIANTO


CONSTRUCTION & RESOURCES SAFETY PATROL

SANDY SUNDARGO YUSUF


OFFICER OFFICER OFFICER
ADMINISTRASI

LEWIS RIDWAN AGUNG


SUPERVISOR SUPERVISOR SUPERVISOR

FLAGMAN FLAGMAN FLAGMAN FLAGMAN


BISNIS PROSES PT. CITRA WASPPHUTOWA
KEBIJAKAN, VISI MISI PT. CITRA WASPPHUTOWA

Visi Perseroan

 Menjadi Badan Usaha Jalan Tol (BUJT) utama di dalam Citra Group,
yaitu entitas anak PT Citra Marga Nusaphala Persada Tbk. Yang
mampu menjadi Jakarta Intra Urbans Toll (JIUT) Successor.

Menjadi JIUT Successor berarti mampu mewarisi atau melanjutkan kisah sukses Perusahaan
Jalan Tol Ir. Wiyoto Wiyono MSc serta menggantikan kontribusi besaran pendapatan tol dari
JIUT setelah selesainya masa konsesi di tahun 2025, dengan membangun koridor Jadebowi
yang kelak menjadi Jagorawi kedua (second Jagorawi) bahkan akan mampu mewarisi atau
melanjutkan kisah sukses Pengusahaan Jalan Tol Jagorawi.

Misi Perseroan

 Mewujudkan Tol Koridor Jadebowi.

Menjadi JIUT Successor berarti mampu mewarisi atau melanjutkan kisah sukses Perusahaan
Jalan Tol Ir. Wiyoto Wiyono MSc serta menggantikan kontribusi besaran pendapatan tol dari
JIUT setelah selesainya masa konsesi di tahun 2025, dengan membangun koridor Jadebowi
yang kelak menjadi Jagorawi kedua (second Jagorawi) bahkan akan mampu mewarisi atau
melanjutkan kisah sukses Pengusahaan Jalan Tol Jagorawi.
MAPPING PERSONIL K3L PT. GIRDER INDONESIA
MAPPING PERSONEL FLAG MAN
CATATAN & PENILAIAN KINERJA K3L
PT. CITRA WASPPHUTOWA
PROYEK TOL DEPOK-ANTASARI

PERIODE : OKTOBER 2018


CATATAN KINERJA K3L PT. CITRA WASPPHUTOWA
LAPORAN KINERJA K3
KECELAKAAN / INSIDEN / SAKIT / MASALAH LINGKUNGAN

Periode : Oktober 2018


Proyek : Pembangunan Tol Depok Antasari

AKUMULASI CATATAN BULAN INI AKUMULASI SAMPAI


NO KETERANGAN SATUAN
PERIODE LALU AUG SEP OKT DENGAN BULAN INI
1 Jumlah Total Jam Kerja Orang Jam Orang 1.590.600 234.960 146.817 140.712 2.113.089
2 Jumlah Total Tenaga Kerja Jam Orang 4.262 669 560 533 6.024
3 Jumlah kasus 33 - - 1 34
A. Hampir Celaka (nearmiss) 9 - - - 9
B. Kecelakaan (Accident)
B.1 Luka Ringan (FAC) 28 - - 1 29
B.2 Perawatan Dokter (MTC) Jam Orang 5 - - - 5
B.3 Kehilangan Hari Kerja (LTI) - - - - -
B.4 Kecelakaan Fatal (FATALITY)
a. Cacat Permanen - - - - -
b. Meninggal - - - - -
4 Total jumlah hari yang hilang hari 16 - - - 16
5 FREQUANCY RATE 20,75 - - 7,11 16,09
6 Kecelakaan Terakhir Tgl/Bln/Thn 19-Apr-18 13-Jul N/A N/A N/A
7 Kecelakaan Fatal Terakhir Tgl/Bln/Thn 02-Jan-18 02-Jan-18 02-Jan-18 02-Jan-18 02-Jan-18
8 Jumlah Total Orang
a. Cacat Permanen Orang - - - - -
b. Meninggal - - - - -
9 Hari Tanpa Kecelakaan Fatal sejak
Hari 210 241 271 302 302
Kecelakaan Fatal Terakhir
CATATAN KINERJA K3L PT. CITRA WASPPHUTOWA
MANPOWER HISTOGRAM
PROYEK PEMBANGUNAN TOL DEPOK - ANTASARI
PERIODE s.d OKTEBER 2018
1400 1227 1245
1217 1223 1181
1200
Num of Manpover

1000 916
853 795
800
560 533
600
400
200
0
Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18
Num Of MP PT. GI 145 155 155 156 155 155 164 165 153 154
Num Of MP Sub Kon 622 622 623 677 643 462 433 347 182 174
Num Of MP Mandor 450 450 445 348 447 299 256 283 225 205
Total Manpower 1217 1227 1223 1181 1245 916 853 795 560 533

Project Month
PERMASALAHAN DAN TINDAKAN
PERBAIKAN K3L
PT. CITRA WASPPHUTOWA
PROYEK TOL DEPOK-ANTASARI

PERIODE : OKTOBER 2018


PERMASALAHAN & TINDAKAN PERBAIKAN K3L
PT. DEPOK-ANTASARI
DAFTAR KELUHAN / COMPLAINT

Bulan : Oktober 2018


Proyek : Tol Depok Antasari

TANGGAL SELESAI
NO Tanggal ISI KELUHAN / COMPLAINT FOTO KELUHAN TINDAK PENYELESAIAN FOTO PERBAIKAN PIC STATUS
TARGET REALISASI
1 20-Okt-18 Permintaan penggantian barier pembatas Pemasangan Barier Pembatas beton HSE - GI 24-Okt-18 25-Okt-18 Closed
plastik dengan barier beton

1 24-Okt-18 Permintaan perbaikan pagar pengaman proyek Perbaikan pagar pengaman proyek HSE - GI 24-Okt-18 24-Okt-18 Closed

3 30-Okt-18 Adanya penumpukan sampah pada saluran pembuangan Pembersihan sampah saluran pembuangan HSE - GI 30-Okt-18 30-Okt-18 Closed

4 11-Okt-18 Pekerja tidak menggunakan APD sesuai dengan SOP Pekerja telah menggunakan APD sesuai HSE - GI 11-Okt-18 11-Okt-18 Closed
untuk bekerja di Ketinggian SOP untuk bekerja di Ketinggian
TINDAKLANJUT HASIL INSPEKSI K3L
PT. CITRA WASPPHUTOWA
PROYEK TOL DEPOK-ANTASARI

PERIODE : OKTOBER 2018


TINDAKLANJUT HASIL INSPEKSI PT CW & KONSULTAN
Tindakan
No Tanggal No. Memo Temuan Foto kejadian Lokasi Resiko Penyebab Foto Perbaikan Status
perbaikan
1 11/10/2018 MVI /1S/X/2018/01 Terdapat beda tinggi antara rigid dengan Main Road Sedang pengecoran rigid yang segera perbaiki posisi - Open
steel grating STA 3+200 tidak rata dengan elevasi steel grating sejajar
kanan steel grating berpotensi dengan rigid
mobil bumping /
melompat ketika
melewati steel grating
tersebut, dan
menyulitkan aliran air ke
man hole

2 25/10/2018 MVI /1S/X/2018/02 Tiang SUTT di dekat lokasi proyek tidak Main Road Sedang Banyak alat berat dan Segera pasang pagar Closed
diproteksi dengan pagar STA 8+800 kiri kendaraan proyek yang pengaman dan spanduk
beroperasi di sekitar peringatan pada tiang
tiang SUTT sehingga SUTT
berpotensi tertabrak.

3 25/10/2018 MVI /1S/X/2018/03 Pertemuan jalan arteri Brigif dengan off Arteri Jalan Sedang Adanya persimpangan Pasang rambu "Hati - - Open
ramp Brigif minim rambu Brigif jalan atreri dengan jalan hati keluar/masuk
tol ditambah lagi kendaraan proyek" dan
kendaraan dari proyek rambu dilarang masuk
berpotensi terjadi
kecalakaan
USULAN PERBAIKAN K3L PT CITRA WASPPHUTOWA
PROGRAM KERJA HSE

PERENCANAAN
TARGET HSE INDUCTION HSE SAFETY TALK HSE PATROL HSE MEETING TRAINING HSE HOUSE KEEPING AUDIT HSE
HSE
HSE PLAN TARGET : ZERO PEKERJA BARU : SETIAP HARI SETIAP DUA KALI SETIAP DUA DASAR-DASAR - LINGKUNGAN 6 BULAN SEKALI
ACCIDENT PERUSAHAAN, SEMINGGU DI HARI MINGGU SEKALI DI HSE, P3K, KERJA BERSIH,
TAMU, SUBKON, SELASA DAN HARI KAMIS PEMADAMAN API, RAPI DAN SEHAT
MANDOR JUMAT TANGGAP - PEMBERSIHAN
DARURAT, MASAL SETIAP
LATIHAN JUMAT (RUTIN)
KEBAKARAN
PERENCANAAN PETUNJUK/GAMBARAN PELAKSANAAN K3 DI AREA PROYEK (SAFETY PLAN) HSE PATROL PATROLI RUTIN YANG DILAKUKAN SETIAP DUA KALI SEMINGGU DI HARI SELASA
DAN JUMAT MULAI JAM 09.00 - SELESAI. DENGAN TUJUAN UNTUK MEMONITOR
KEGIATAN PEKERJAAN DI LAPANGAN

TARGET ZERO ACCIDENT HSE MEETING MEETING INTERNAL DILAKSANAKAN HARI KAMIS JAM 10.00 - SELESAI. GUNA
MEMBAHAS MASALAH YANG MUNGKIN TERJADI DAN TINDAKAN
PENCEGAHANNYA SERTA MELAPORKAN KECELAKAAN YANG TERJADI DAN
LANGKAH-LANGKAH PERBAIKANNYA.

HSE INDUCTION PENDEKATAN DAN PENGARAHAN TENTANG HSE, HOUSE KEEPING DAN TRAINING HSE TRAINING HSE KEPADA KARYAWAN, MANDOR, SUB-KONTRAKTOR TENTANG
KETERTIBAN PROYEK KEPADA PEKERJA BARU DAN KEPADA PEKERJA SEBELUM DASAR-DASAR HSE, P3K, CARA PEMADAMAN API DAN TANGGAP DARURAT SERTA
MELAKUKAKN PEKERJAAN YANG BERPOTENSI BAHAYA TINGGI LATIHAN KEBAKARAN SATU BULAN SEKALI

HSE SAFETY TALK PENGARAHAN SINGKAT TENTANG HSE DAN KONDISI PROYEK KEPADA SELURUH HOUSE KEEPING TARGET LINGKUNGAN KERJA BERSIH, RAPI DAN SEHAT
PEKERJA SEBELUM PEKERJAAN DIMULAI, DILAKUKAKN SETIAP HARI JAM 07.30 -
08.00 WIB
HSE INSPEKSI INSPEKSI YANG DILAKUKAN UNTUK MEMONITOR PELAKSANAAN HSE DAN UNTUK AUDIT HSE AUDIT PELAKSANAAN DAN PENERAPAN HSE SETIAP 6 BULAN SEKALI
(CAMPAIGN) MENJAGA KONSISTENSI PENERAPAN HSE DI PROYEK. HSE INSPEKSI DILAKUKAN
SETIAP DUA MINGGU SEKALI DI HARI RABU
SIMULASI TANGGAP DARURAT

Simulasi Tanggap Darurat penanganan


kecelakaan di jalan tol untuk melatih
kecakapan personil K3.