LAPORAN SUMMARY

HASIL SURVEY DI STASIUN SOLO BALAPAN


LINGKUP PEKERJAAN :
1. Jalur Stabling 1 Emplasemen Stasiun Solo Balapan
2. Dari No. Pole 69A s/d No. Pole 83A
LINGKUP PEKERJAAN
PEMASANGAN / INSTALASI PERALATAN :

1. Wiring Messenger Wire = 445,3 m


2. Wiring Contact Wire = 445,3 m
3. Wiring Ground Wire = 433,3 m
4. Wiring Feeder Wire = 493.3 m
5. Hanger Bar = 89 Set
6. Steadying Equipment, Single Trolley = 10 Set
7. Pull Off Equipment, Pulley Type = 1 Set
8. Insulator Insertion = 1 Set
9. Suspension for Messenger Wire = 11 Set
10. Feeding Branch = 2 Set
11. Automatic Tensioning Device, Pulley Type = 2 Set
12. Anchoring Fixed Type = 2 Set
13. Adjusting OHC = 445,3 m
14. Wiring Feeder Wire = 493,3 m
15. Suspension Insulator for Feeder Wire = 17 Set
KONDISI DI LAPANGAN SAAT INI :

1. Pekerjaan Track Spoor Kolong dan Struktur Atap Depo Masih


Belum Selesai
KONDISI DILAPANGAN SAAT INI :

2. Struktur OHC
KONDISI DILAPANGAN SAAT INI :

Struktur OHC
KONDISI DILAPANGAN SAAT INI :

Struktur OHC
KONDISI DILAPANGAN SAAT INI :

Struktur OHC
KONDISI DILAPANGAN SAAT INI :

Struktur OHC
Timeline Penyelesaian
Uraian Pekerjaan 1 2 3 4 5 6 7 Keterangan
1. Wirring
2. Install Peralatan LAA
3. Finishing

Note:
• Pemasangan dapat dilakukan, tetapi akan terhambat pada area
depo karena rel belum tersedia dan untuk pijakan peralatan
kerja akan terhambat karena banyak material sipil yang masih
dikerjakan;
• Lalu untuk adjusting OHC (finishing) belum dapat dilakukan
menunggu rel sudah fix pada posisinya untuk mengukur
deviasi dan gradientnya.