KEMENTERIAN PEKERJAAN UMUM DAN PERUMAHAN RAKYAT

DIREKTORAT JENDERAL BINA MARGA


BALAI BESAR PELAKSANAAN JALAN NASIONAL VI
SATKER PELAKSANAAN JALAN NASIONAL WILAYAH 1 BANTEN

INFORMASI KEGIATAN
PEMBANGUNAN OVERPASS KEMANG B

PENYEDIA JASA :
PT BUMI DUTA PERSADA
PPK 1.1 PJN WILAYAH 1
KONSULTAN PENGAWAS : BANTEN
PT. DAKSINAPATI KONSULTINDO TAHUN ANGGARAN 2020
DATA UMUM PROYEK
PAKET PEMBANGUNAN OVERPASS KEMANG B
PAKET PEKERJAAN : PEMBANGUNAN OVERPASS KEMANG B
PPK : PPK 1.1 PJN I BANTEN
PENYEDIA JASA : PT. BUMI DUTA PERSADA
KONSULTAN PENGAWAS : PT. DAKSINAPATI KONSULTINDO
NOMOR KONTRAK : PB.0201/KTR/PJNW I-BTN/PPK1.1/02/2020
TANGGAL KONTRAK : 24 JANUARI 2020
NILAI KONTRAK : Rp. 46.067.175.930,-
NOMOR KONTRAK ADD-01 : PB.0201/KTR/ADD-1/PJNW I-BTN/PPK1.1/02/2020
TANGGAL KONTRAK : 10 MARET 2020
NILAI KONTRAK : Rp. 46.067.175.930,-
NOMOR KONTRAK ADD-02 : PB.0201/KTR/ADD-2/PJNW I-BTN/PPK1.1/02/2020
TANGGAL KONTRAK : 26 MARET 2020
NILAI KONTRAK : Rp. 46.067.175.930,-
NOMOR KONTRAK ADD-03 : PB.0201/KTR/ADD-3/PJNW I-BTN/PPK1.1/02/2020
TANGGAL KONTRAK : 27 MEI 2020
NILAI KONTRAK : Rp. 37.684.521.000,-
NOMOR KONTRAK ADD-04 : PB.0201/KTR/ADD-4/PJNW I-BTN/PPK1.1/02/2020
TANGGAL KONTRAK : 01 OKTOBER 2020
NILAI KONTRAK : Rp. 46.067.175.930,-
NOMOR KONTRAK ADD-05 : PB.0201/KTR/ADD-5/PJNW I-BTN/PPK1.1/02/2020
TANGGAL KONTRAK : 11 NOVEMBER 2020
NILAI KONTRAK : Rp. 46.067.175.930,-
PROGRESS FISIK & PROGRESS KEUANGAN

PAKET PEKERJAAN : PEMBANGUNAN OVERPASS KEMANG B


PPK : PPK 1.1 PJN I BANTEN

PENYEDIA JASA : PT. BUMI DUTA PERSADA


KONSULTAN PENGAWAS : PT. DAKSINAPATI KONSULTINDO

LAPORAN KEMAJUAN PEKERJAAN PERIODE 26 NOVEMBER 2020


PROGRESS FISIK MYC PROGRESS KEUANGAN
RENCANA : 71.60 % UANG MUKA : 20.00 %
REALISASI : 90.34 % MC : 89.47%
DEVIASI : 18.73 %

PROGRESS FISIK SYC WAKTU PELAKSANAAN


RENCANA : 79.11 % RENCANA : 420 HK
REALISASI : 92.51 % REALISASI : 300 HK
DEVIASI : 13.40 % SISA : 120 HK
PPK 1.1
PJN I BANTEN
PETA LOKASI KEGIATAN PAKET OVERPASS KEMANG B

Rencana Overpass Kemang B

LOKASI
Kota   Serang Timur
Kecamatan   Cipocok Jaya
Desa   Kemang

KOORDINAT

Awal x 631222.3910
  y 9323404.630
Akhir x 631865.7580

  y 9323398.959
LAYOUT OVERPASS KEMANG B

STA
AWAL STA
AKHIR
LAYOUT OVERPASS KEMANG B
A1 ABT 1 ABT 2 A2
OPRIT 1 OPRIT 2

POTONGAN MEMANJANG
KONSTRUKSI BANGUNAN BAWAH

DENAH DENAH
DENAH FOOTING DENAH
FOOTING
FOOTING ABT 2 FOOTING
ABT 1
A1 A2
KONSTRUKSI BANGUNAN BAWAH

FOOTING FOOTING
ABT1 ABT2 FOOTING
FOOTING A2
A1
KONSTRUKSI BANGUNAN BAWAH

A1
A1
ABT1 ABT2
KONSTRUKSI BANGUNAN ATAS

STEEL BOX
CSP
GIRDER
CSP
DATA TEKNIS
DOKUMENTASI PEKERJAAN

Erection Steel Box Girder


DOKUMENTASI PEKERJAAN

Erection Steel Box Girder


DOKUMENTASI PEKERJAAN

Pemasangan Savety Net


DOKUMENTASI PEKERJAAN

Pemasangan Savety Net dan Impaction Diafragma


DOKUMENTASI PEKERJAAN

Assembling Corrugated Steel Plate ABT 1 Timbunan Pilihan Layer 1 Abt 1


DOKUMENTASI PEKERJAAN

Pembesian dan pemasangan bekisting separator mortar busa abt 1


DOKUMENTASI PEKERJAAN

Pembesian Slab lantai jembatan


DOKUMENTASI PEKERJAAN

Pekerjaan Mortar Busa ABT.1


DOKUMENTASI PEKERJAAN

Pengecoran Lantai Kerja Optrit


DOKUMENTASI PEKERJAAN

Pembesian Optrit Beton Fc’45


DOKUMENTASI PEKERJAAN

Pengecoran Beton FC’45 Optrit Jembatan