SUMMARY
JUMLAH KONTRAK PERIODE PROGRES KOMULATIF
PERMASALAHAN
1
2
3
###
WAKTU TERPAKAI : 63 HARI KALENDER ###
SISA WAKTU PELAKSANAAN : 57 HARI KALENDER ###
RENCANA : 23.60 %
REALISASI : 4.22 %
DEVIASI : 19.38 %
PEMERINTAH KABUPATEN MANGGARAI
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
Jalan Adi Sucipto N0. 01, Telp. (0385) 21398, Fax : )0385) 21506 Ruteng
SERTIFIKATE BULANAN MC 02
A N
Div. II PEKERJAAN DRAINASE R - - -
PO
LA
Div. III PEKERJAAN TANAH 19,301,469.00 11,819,262.00 3.30
TERBILANG : Sembilan Juta Tujuh Ratus Tiga Puluh Tujuh Ribu Lima Ratus Rupiah
BULAN LALU 0.00 %
PROSENTASI KEMAJUAN PEKERJAAN BULAN INI 4.22 %
S/D BULAN INI 4.22 %
DIBUAT OLEH :
KONSULTAN PENGAWAS
CV. INDO DESIGN KONSULTAN
HERIBERTUS S. JEMADU, ST
SITE ENGINEER
RINGKASAN KEMAJUAN PEKERJAAN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN MANGGARAI
DATA PROYEK RINGKASAN PROGRES STATUS PROYEK
PROGRAM LINGKUP DINAS PEKERJAAN UMUM KABUPATEN MANGGARAI
PENINGKATAN JALAN
WAKTU TERPAKAI 63 HARI -
PEKERJAAN PENGAWASAN PENANGANAN JALAN SUMBER DANA ALOKASI
UMUM (DAU) PAKET 2 W
KONTRAKTOR CV. SCN A WAKTU TERPAKAI TERHADAP PROBLEM DAN
NOMOR KONTRAK PUPR.600.762/601/VIII/2020, Tanggal 19 Agustus 2020 K MASALAH
TANGGAL KONTRAK 19-Aug-20 T - KONTRAK AWAL 70.00 %
TANGGAL ADD I - - KONTRAK REVISI %
PAKET PENINGKATAN JALAN WONTONG-RABOK-TAGOL-LOCE
(LAPEN+TELFORD) KEC. REOK BARAT (LADA-MAKI-RABOK-
LOCE)
KANTOR DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
KABUPATEN MANGGARAI
PEMIMPIN KEGIATAN J RENCANA PROGRES KOMULATIF 23.60 %
KONTRAKTOR CV. SCN U
KONSULTAN SUPERVISI CV. INDO DESIGN KONSULTAN M REALISASI PROGRES KOMULATIF 4.22 %
PENYERAHAN LAPANGAN 19 AGUSTUS 2020 L
AKTIFITAS LAPANGAN
SURAT PERINTAH MULAI KERJA 19 AGUSTUS 2020 A SELISIH (19.38) %
AKHIR MASA PELAKSANAAN 16 DESEMBER 2020 H
MASA PELAKSANAAN PEKERJAAN 120 HARI KALENDER PROGRES BULAN INI 4.22 %
MASA PEMELIHARAAN 365 HARI KALENDER
MASA KONTRAK 120 HARI KALENDER
JUMLAH NILAI KONTRAK Rp394,359,000.00 DROPING MATERIAL UNTUK PEKERJAAN
ADDENDUM NO. - LAPEN
TOTAL NILAI KONTRAK Rp394,359,000.00
100
KANTOR : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN MANGGARAI
PROGRAM/KEGIATAN : LINGKUP DINAS PEKERJAAN UMUM KABUPATEN MANGGARAI
PEKERJAAN : PENGAWASAN PENANGANAN JALAN SUMBER DANA ALOKASI UMUM (DAU) PAKET 2
LOKASI : KECAMATAN REOK
KONTRAKTOR : CV. SCN Bulan ke : 2 (Dua)
NOMOR KONTRAK : PUPR.600.762/601/VIII/2020, Tanggal 19 Agustus 2020 Periode : 21 Agustus S/D 20 September
NMOR KONTRK ADD :
KONSULTAN : CV. INDO DESIGN KONSULTAN
NOMOR KONTRAK : PUPR.600.762/628/PWSN.DAU-BM/VIII/2020, Tgl, 19 Agustus 2020
TAHUN ANGGARAN : 2020
A UMUM
Mobilisasi 12,750,000.00 12,293,500.00 16.94 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 0.81 100
B PEKERJAAN DRAINASE -
Galian untuk selokan drainase dan saluran air - 1,338,258.60 1.84 0.92 0.92
Pasangan Batu dengan mortar - 22,933,001.54 31.60 7.90 7.90 7.90 7.90 75
C PEKERJAAN TANAH -
Galian Biasa (Dibuang Sekitar Lokasi Galian) - 220,964.80 0.30 - 0.30 - - -
Galian Batu -
Galian Struktur dengan Kedalaman 0 - 2 meter 1,117,989.00 2,715,300.00 3.74 1.87 1.87 50
Pembersihan DAMIJA 5,461.00 - RENCANA- -
D PERKERASAN BERBUTIR -
Lapis pondasi Atas (LPA) 5/7 30,696,540.00 132,972,249.15 183.24 30.54 30.54 30.54 30.54 30.54 30.54
0Pasangan Batu dengan mortar UNIT 31.60 3.95 3.95 3.95 3.95 3.95 3.95 3.95 3.95
50
#REF! #REF! UNIT #REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! UNIT #REF! #REF! #REF! #REF! #REF! #REF! #REF!
0
JUMLAH #REF!
RENCANA KEMAJUAN BULANAN - - - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
KONTRAK ASLI KUMULATIF BULANAN - - - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
REALISASI KEMAJUAN BULANAN - - 4.50 6.18 7.52 7.53 7.50 3.55 #REF! #REF!
KONTRAK ASLI KUMULATIF BULANAN 3.03 3.03 7.53 13.71 21.23 29.06 36.56 40.11 #REF! #REF!
KEMAJUAN BULANAN
RENCANA ADD I
KUMULATIF BULANAN
KEMAJUAN BULANAN
REALISASI ADD I
KUMULATIF BULANAN
DEVIASI KUMULATIF BULANAN 3.03 3.03 7.53 13.71 #REF! #REF! #REF! #REF! #REF! #REF!
Dibuat Oleh
Konsultan Supervisi
CV. Bina Cipta Utama
Riky Rikar Ho
Site Engineer
LAPORAN BULANAN
KANTOR : DINAS PEKERJAAN UMUM DAN PENATAAN RUANG KABUPATEN MANGGARAI Bulan Ke : 2 ( Duaa )
PROGRAM/KEGIATAN : LINGKUP DINAS PEKERJAAN UMUM KABUPATEN MANGGARAI Periode 30 Agustus s/d 26 September
PEKERJAAN : PENGAWASAN PENANGANAN JALAN SUMBER DANA ALOKASI UMUM (DAU) PAKET 2
TARGET CCO :
LOKASI : KECAMATAN REOK
KONTRAKTOR : CV. SCN
NOMOR KONTRAK : PUPR.600.762/601/VIII/2020, Tanggal 19 Agustus 2020
NOMOR KONTRAK ADD 1 :
KONSULTAN : CV. INDO DESIGN KONSULTAN
NOMOR KONTRAK : PUPR.600.762/628/PWSN.DAU-BM/VIII/2020, Tgl, 19 Agustus 2020
TAHUN ANGGARAN : 2020
Dibuat Oleh
Konsultan Supervisi
CV. Bina Cipta Utama
Riky Rikar Ho
Site Engineer
LAPORAN MINGGUAN
PROGRAM/ KEGIATAN : PEMBANGUNAN JALAN BIDANG BINA MARGA, SUMBER DANA ALOKASI UMUM ( DAU ) T.A 2014 Minggu Ke : 6 ( Enam )
PAKET : PENINGKATAN JALAN RPH KAROT - RPH MENA, LAPEN, KEC. LANGKE REMBONG Periode 21 Agustus s/d 27 Agustus
TARGET AWAL : 1,0 KM
TARGET CCO : 1.30 KM
LOKASI : KEC. LANGKE REMBONG
KONTRAKTOR : CV. DAVIDTIANO PUTRA
NOMOR KONTRAK : KU.02.09/1274/VI/2014 TGL 16 JULI 2014
NOMOR KONTRAK ADD 1 : ADD 1.KU.02.09/1557/VIII/2014 TGL 21 AGUSTUS 2014
KONSULTAN : CV. BINA CIPTA UTAMA
TAHUN ANGGARAN : 2014
IDENTIFIKASI KONTRAK Kemajuan Fisik PROSENT.YG DICAPAI
KONTRAK ADDENDUM REALISASI
Kontrak Awal Bobot Volume THSP VOL. TERHADAP
KEUANGAN
No Harga Jumlah Harga Jumlah S/d Bulan lalu Bulan lalu Bulan lalu Seluruh
Uraian Pekerjaan Sat Volume Volume Satuan Harga Seluruh (Rp) Volume Volume Volume
Satuan Harga % Bobot (%) Bobot (%) Bobot (%) % Bobot %
1 2 3 4 5 6 7 8 9 10 11 12
A UMUM
1 Mobilisasi dan demobilisasi LS 1.00 12,293,500.00 12,293,500.00 1.00 12,293,500.00 12,293,500.00 1.55 3,073,375.00 0.20 0.31 0.05 0.08 0.25 0.39 25.00 0.39
Div. I UMUM
1.2 Mobilisasi 12,750,000.00 3.56 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 0.21 100
1.19 Keselamatan dan Kesehatan Kerja 3,814,545.45 1.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
3.2 (3) Penyiapan Badan Jln. pada Galian Biasa atau Perk. Lama Rusak 13,761,720.00 3.84 1.28 1.28 1.28
5.2(3) Lapis pondasi Atas (LPA) 5/7 30,696,540.00 8.56 2.14 2.14 2.14 2.14
- -
Div. III PEKERJAAN TANAH
3.1 (1.a) Galian Biasa (Dibuang Sekitar Lokasi Galian) M3 - - - - - - - - - - - -
3.1.(1) Galian Batu M3 - - - - - - - - - - -
3.1 (3) Galian Struktur dengan Kedalaman 0 - 2 meter M3 13.50 82,814.00 1,117,989.00 0.31 - - - - - - - -
3.2 (1) Timbunan Biasa dari Selain Galian Sumber Bahan M3 - - - - - - - - - -
3.2 (2) Timbunan Pilihan M3 - - - - - - - - - - -
3.2 (3) Penyiapan Badan Jln. pada Galian Biasa atau Perk. Lama Rusak M2 2,520.00 5,461.00 13,761,720.00 3.84 - - - - - - - -
3.3b Pembersihan DAMIJA M2 840.00 5,264.00 4,421,760.00 1.23 - - - - - - - -
19,301,469.00 5.38 - - - - -
Div. V PERKERASAN BERBUTIR
5.2(2) Lapis pondasi bawah (LPB) M3 198.00 576,373.00 114,121,854.00 31.83 - - - - - - - -
5.2(3) Lapis pondasi Atas (LPA) 5/7 M3 60.00 511,609.00 30,696,540.00 8.56 - - - - - - - -
- -
144,818,394.00 40.39
Div. VI PERKERASAN ASPAL
6.6 Lapis Penetrasi Macadam (Permukaan) M3 60.00 2,497,093.00 149,825,580.00 41.79 - - - - - - -
149,825,580.00 41.79 - - - - -
Div. VII STRUKTUR
7.1(5) Beton K - 250 M3 2.40 1,417,251.00 3,401,402.40 0.95 - - - - - - -
7.3(1) Baja Tulangan U24 Polos KG 309.60 17,142.00 5,307,163.20 1.48 - - - - - - -
7.9 Pasangan Batu M3 19.69 979,691.00 19,290,115.79 5.38 - - - - - - - -
7.1 Beton K - 175 M3 - - - - - - - - - - - -
27,998,681.39 7.81 - - - - -
JUMLAH 358,508,669.84 100.00 -
PPN 10% 35,850,866.98 -
TOTAL 394,359,536.82 -
TOTAL DIBULATKAN 394,359,000.00
REALISASI FISIK - - - -
R E N C A N A 0.27
D E V I A S I (0.27)
149,825,580.00 41.79 - - - - -
Div. VII STRUKTUR
7.1(5) Beton K - 250 M3 2.40 1,417,251.00 3,401,402.40 0.95 - - - - - - - - -
7.3(1) Baja Tulangan U24 Polos KG 309.60 17,142.00 5,307,163.20 1.48 - - - - - - - - -
7.9 Pasangan Batu M3 19.69 979,691.00 19,290,115.79 5.38 - - - - - - - - -
7.1 Beton K - 175 M3 - - - - - - - - - - - - -
27,998,681.39 7.81 - - - - -
JUMLAH 358,508,669.84 100.00 -
PPN 10% 35,850,866.98 -
TOTAL 394,359,536.82 -
TOTAL DIBULATKAN 394,359,000.00
REALISASI FISIK - - - -
R E N C A N A 1.78
D E V I A S I (1.78)
149,825,580.00 41.79 - - - - -
Div. VII STRUKTUR
7.1(5) Beton K - 250 M3 2.40 1,417,251.00 3,401,402.40 0.95 - - - - - - - - -
7.3(1) Baja Tulangan U24 Polos KG 309.60 17,142.00 5,307,163.20 1.48 - - - - - - - - -
7.9 Pasangan Batu M3 19.69 979,691.00 19,290,115.79 5.38 - - - - - - - - -
7.10 Beton K - 175 M3 - - - - - - - - - - - - -
27,998,681.39 7.81 - - - - -
JUMLAH 358,508,669.84 100.00 -
PPN 10% 35,850,866.98 -
TOTAL 394,359,536.82 -
TOTAL DIBULATKAN 394,358,600.00
REALISASI FISIK - - - -
R E N C A N A 3.33
D E V I A S I (3.33)
149,825,580.00 41.79 - - - - -
Div. VII STRUKTUR
7.1(5) Beton K - 250 M3 2.40 1,417,251.00 3,401,402.40 0.95 - - - - - - - - -
7.3(1) Baja Tulangan U24 Polos KG 309.60 17,142.00 5,307,163.20 1.48 - - - - - - - - -
7.9 Pasangan Batu M3 19.69 979,691.00 19,290,115.79 5.38 - - - - - - - - -
7.10 Beton K - 175 M3 - - - - - - - - - - - - -
27,998,681.39 7.81 - - - - -
JUMLAH 358,508,669.84 100.00 -
PPN 10% 35,850,866.98 -
TOTAL 394,359,536.82 -
TOTAL DIBULATKAN 394,358,600.00
REALISASI FISIK - - - -
R E N C A N A 4.88
D E V I A S I (4.88)
149,825,580.00 41.79 - - - - -
Div. VII STRUKTUR
7.1(5) Beton K - 250 M3 2.40 1,417,251.00 3,401,402.40 0.95 - - - - - - - - -
7.3(1) Baja Tulangan U24 Polos KG 309.60 17,142.00 5,307,163.20 1.48 - - - - - - - - -
7.9 Pasangan Batu M3 19.69 979,691.00 19,290,115.79 5.38 - - - - - - - - -
7.10 Beton K - 175 M3 - - - - - - - - - - - - -
27,998,681.39 7.81 - - - - -
JUMLAH 358,508,669.84 100.00 -
PPN 10% 35,850,866.98 -
TOTAL 394,359,536.82 -
TOTAL DIBULATKAN 394,358,600.00
REALISASI FISIK 0.00 0.00 0.00 0.00
R E N C A N A 6.74
D E V I A S I (6.74)
149,825,580.00 41.79 - - - - -
Div. VII STRUKTUR
7.1(5) Beton K - 250 M3 2.40 1,417,251.00 3,401,402.40 0.95 - - - - - - - - -
7.3(1) Baja Tulangan U24 Polos KG 309.60 17,142.00 5,307,163.20 1.48 - - - - - - - - -
7.9 Pasangan Batu M3 19.69 979,691.00 19,290,115.79 5.38 - - - - - - - - -
7.10 Beton K - 175 M3 - - - - - - - - - - - - -
27,998,681.39 7.81 - - - - -
JUMLAH 358,508,669.84 100.00 -
PPN 10% 35,850,866.98 -
TOTAL 394,359,536.82 -
TOTAL DIBULATKAN 394,358,600.00
REALISASI FISIK 0.00 0.00 0.00 0.00
R E N C A N A 9.70
D E V I A S I (9.70)
149,825,580.00 41.79 - - - - -
Div. VII STRUKTUR
7.1(5) Beton K - 250 M3 2.40 1,417,251.00 3,401,402.40 0.95 - - - - - - - - -
7.3(1) Baja Tulangan U24 Polos KG 309.60 17,142.00 5,307,163.20 1.48 - - - - - - - - -
7.9 Pasangan Batu M3 19.69 979,691.00 19,290,115.79 5.38 - - - - - - - - -
7.10 Beton K - 175 M3 - - - - - - - - - - - - -
27,998,681.39 7.81 - - - - -
JUMLAH 358,508,669.84 100.00 -
PPN 10% 35,850,866.98 -
TOTAL 394,359,536.82 -
TOTAL DIBULATKAN 394,358,600.00
REALISASI FISIK 0.00 0.00 0.00 0.00
R E N C A N A 12.67
D E V I A S I (12.67)
149,825,580.00 41.79 - - - - -
Div. VII STRUKTUR
7.1(5) Beton K - 250 M3 2.40 1,417,251.00 3,401,402.40 0.95 - - - - - - - - -
7.3(1) Baja Tulangan U24 Polos KG 309.60 17,142.00 5,307,163.20 1.48 - - - - - - - - -
7.9 Pasangan Batu M3 19.69 979,691.00 19,290,115.79 5.38 - - - - - - - - -
7.10 Beton K - 175 M3 - - - - - - - - - - - - -
27,998,681.39 7.81 - - - - -
JUMLAH 358,508,669.84 100.00 7,111,498.55
PPN 10% 35,850,866.98 711,149.85
TOTAL 394,359,536.82 7,822,648.40
TOTAL DIBULATKAN 394,358,600.00
REALISASI FISIK 0.00 1.98 1.98 1.98
R E N C A N A 15.37
D E V I A S I (13.38)
149,825,580.00 41.79 - - - - -
Div. VII STRUKTUR
7.1(5) Beton K - 250 M3 2.40 1,417,251.00 3,401,402.40 0.95 - - - - - - - - -
7.3(1) Baja Tulangan U24 Polos KG 309.60 17,142.00 5,307,163.20 1.48 - - - - - - - - -
7.9 Pasangan Batu M3 19.69 979,691.00 19,290,115.79 5.38 - - - - - - - - -
7.10 Beton K - 175 M3 - - - - - - - - - - - - -
27,998,681.39 7.81 - - - - -
JUMLAH 358,508,669.84 100.00 15,132,171.09
PPN 10% 35,850,866.98 1,513,217.11
TOTAL 394,359,536.82 16,645,388.20
TOTAL DIBULATKAN 394,358,600.00
REALISASI FISIK 1.98 2.24 4.22 4.22
R E N C A N A 23.60
D E V I A S I (19.38)
149,825,580.00 41.79 - - - - -
Div. VII STRUKTUR
7.1(5) Beton K - 250 M3 2.40 1,417,251.00 3,401,402.40 0.95 - - - - - - - - -
7.3(1) Baja Tulangan U24 Polos KG 309.60 17,142.00 5,307,163.20 1.48 - - - - - - - - -
7.9 Pasangan Batu M3 19.69 979,691.00 19,290,115.79 5.38 - - - - - - - - -
7.10 Beton K - 175 M3 - - - - - - - - - - - - -
27,998,681.39 7.81 - - - - -
JUMLAH 358,508,669.84 100.00 64,751,947.08
PPN 10% 35,850,866.98 6,475,194.71
TOTAL 394,359,536.82 71,227,141.79
TOTAL DIBULATKAN 394,358,600.00
REALISASI FISIK 4.22 13.84 18.06 18.06
R E N C A N A 31.83
D E V I A S I (13.77)
- - - -
Div. III PEKERJAAN TANAH
.1 (1.a) Galian Biasa (Dibuang Sekitar Lokasi Galian) M3 - - - - - - - - - - -
3.1.(1) Galian Batu M3 - - - - - - -
3.1 (3) Galian Struktur dengan Kedalaman 0 - 2 meter M3 13.50 82,814.00 1,117,989.00 0.31 - - - - - - -
3.2 (1) Timbunan Biasa dari Selain Galian Sumber Bahan M3 - - - - - - -
3.2 (2) Timbunan Pilihan M3 - - - -
3.2 (3) Penyiapan Badan Jln. pada Galian Biasa atau Perk. Lama Rusak M2 2,520.00 5,461.00 13,761,720.00 3.84 8,945,118.00 1,638.00 2.50 1,638.00 2.50 65.00 2.50
3.3b Pembersihan DAMIJA M2 840.00 5,264.00 4,421,760.00 1.23 2,874,144.00 546.00 0.80 546.00 0.80 65.00 0.80
19,301,469.00 5.38 11,819,262.00 - 3.30 3.30 3.30
Div. V PERKERASAN BERBUTIR
5.2(2) Lapis pondasi bawah (LPB) M3 198.00 576,373.00 114,121,854.00 31.83 - - - - - - -
5.2(3) Lapis pondasi Atas (LPA) 5/7 M3 60.00 511,609.00 30,696,540.00 8.56 - - -
144,818,394.00 40.39 - - -
Div. VI PERKERASAN ASPAL
6.6 Lapis Penetrasi Macadam (Permukaan) M3 60.00 2,497,093.00 149,825,580.00 41.79 - - - - - - -
149,825,580.00 41.79 - - - - -
Div. VII STRUKTUR
7.1(5) Beton K - 250 M3 2.40 1,417,251.00 3,401,402.40 0.95 - - -
7.3(1) Baja Tulangan U24 Polos KG 309.60 17,142.00 5,307,163.20 1.48 - - -
7.9 Pasangan Batu M3 19.69 979,691.00 19,290,115.79 5.38 - - - - - - -
7.1 Beton K - 175 M3 - - - - - - - - - - - -
27,998,681.39 7.81 - - - - -
JUMLAH 358,508,669.84 100.00 15,132,171.09
PPN 10% 35,850,866.98 1,513,217.11
TOTAL 394,359,536.82 16,645,388.20
TOTAL DIBULATKAN 394,359,000.00
REALISASI FISIK 4.22
R E N C A N A 23.60
D E V I A S I (19.38)
Sesuaikan sel yang berwarna merah dengan Sel yang akan ditulis terbilang pada Sheet anda
0
1
2
3
4
5
6
7
8
9
9737500 9737500
Satu
Dua Lima Ratus Milyaran
Tiga Tujuh Ribu 9 Jutaan
Empat Tiga Puluh 737 Ribuan
Lima Tujuh Ratus 500 Ratusan
Enam Sembilan Juta
Tujuh
Delapan
Sembilan