= 1%
M-3 O-3 P = = =101
Wp = 12 menit
PERHITUNGAN JUMLAH MESIN
𝑡 𝑃
DIMANA :
= waktu proses
𝑁𝑖= ×
P= bahan baku
D= jam kerja mesin
E = efisiensi mesin (0,8 – 0,9)
=1,17 = 2 MESIN
=2,8 = 3 MESIN
MENGHITUNG UMUR MESIN
MESIN 1
HARGA = 10.000.000
10 juta
UMUR = 5 TAHUN
PERAWATAN = 500.000/BULAN
1 TAHUN = 250 HARI KERJA 500 ribu
SISA = 2.000.000 0 5
1 2 3 4
10.000.000 – 2.000.000 = 8.000.000
PENYUSUTAN → 8.000.000/5 TAHUN = 1.600.000
2 juta
PERAWATAN = 500.000 +
TOTAL = 2.100.000
PERAWATAN = 600.000 +
TOTAL = 3.000.000
PERAWATAN = 400.000 +
TOTAL = 2.000.000
Baban pembantu
2 baut =Rp750
2 mur =Rp750
Total = 2 x 750 = Rp1500
OVERHEAD COST
M1 = 800 WATT X 8 X 20 = 128.000 (128 KW)
M2 = 200 WATT X 8 X 20 = 32.000 (32 KW)
M3 = 500 WATT X 8 X 20 = 80.000 (80 KW)
1 KWH = 4000
M1 = 4000 X 128 = 512.000
M2 = 4000 X 32 = 128.000
M3 = 4000 X 80 = 320.000 +
TOTAL = 960.000/ BULAN
KAPASITAS = 100 X 20 HARI = 2.000 UNIT
Onkos overheat = = 480/ unit