MAKO LANAL TAHAP I

• PT. PRIMA PILAR PERKASA


• KTR/03/03-83/X/2008/SORONG TGL.
07 OKTOBER 2008
• WAKTU 85 HARI
• NILAI KONTRAK Rp 3.758.741.000,-

MAKO LANAL TAHAP II


• PT. BANGUN KONSTRUKSI PERSADA
• KTR/17/02-47/IV/2011/FASLAN TANGGAL 15
APRIL 2011
• WAKTU 120 HARI
• NILAI KONTRAK Rp 6.075.510.000,-

1
MAKO LANAL TAHAP III
• KEMAJUAN PEKERJAAN MINGGU INI 100 %
• PT. BANGUN KONSTRUKSI PERSADA
• KTR/24/02-50/VI/2014/FASLAN TGL 3 JUNI 2014
• WAKTU 180 HARI
• NILAI KONTRAK Rp 14.460.868.000,-

2
MAKO LANTAMAL XIV

TAHAP II
TAHAP III TAHAP III
TAHAP I

PEMBANGUNAN MAKO KA & KI

3
PEMBANGNAN DERMAGA LANTAMAL XIV SORONG

TAHAP I
• NO KTR/51/02-47/VI/2010 TGL 02 JUNI 2010
• PT. DUTA TRISNA ADIYASA
• NILAI Rp. 3.501.270.000,-
• WAKTU 195 HARI ADENDUM 7 HARI

TAHAP II
• NO KTR/58/02-47/VII/2010 TGL 12 JULI 2011
• PT. JAYA ETIKA TEKNIK
• NILAI Rp. 11.339.611.000,-
• WAKTU 150 HARI ADENDUM 90 HARI

TAHAP III
• NO KTR/02/02-47/IV/2012 TGL 18 APR 2012
• PT. TIARA MULTI TEKNIK
• NILAI Rp. 9.486.707.000,-
• WAKTU 180 HARI

4
TAHAP IV
• NO KTR/21/02-50/IV/2013 TGL 11 NOV 2013
• PT. TARA MULTI TEKNIK
• NILAI Rp. 9.000.689.000,-
• WAKTU 255 HARI

TAHAP V
• NO KTR/115/02-50/VI/2015 TGL 11 JUNI 2015
• ADENDUM NOKTR/115/02-50/VI/2015/FASLAN
• TANGGAL26 NOVEMBER 2015
• PT. TARA MULTI TEKNIK
• NILAI Rp. 25.213.441.000,-
• WAKTU 205 HARI

TAHAP VI
• NO KTR/23/02-50/I/2016 TGL 7 JANUARI 2016
• PT. TARA MULTI TEKNIK
• NILAI Rp. 48.119.000.000,-
• WAKTU 240 HARI

5
TAHAP VI TAHAP IV
116 M
24 M 18,2 M
6,8 M 18,6M • PENGERJAAN S.D TAHAP VI
• TAHAP I : CAUSEWAY 75 M
(Rp. 3.501.270.000,-)
TAHAP III • TAHAP II : CAUSEWAY BETON 60 M
(Rp. 11.399.611.000,-)
• TAHAP • TAHAP III : PLAT BETON
I : CAUSEWAY 75 M (T)
(Rp. 9.486.707.000)
TAHAP• II TAHAP II : CAUSEWAY BETON 60 M
292,8 M • TAHAP • TAHAP IV :BETON
III : PLAT (T) KIRI(T)
KANAN
(Rp. 9.000.689.000,-)
• TAHAP IV : (T) KIRI KANAN
• TAHAP V : (REDESAIN) 24 M X 12 M

TAHAP I TAHAP V : KIRI (Rp.24.905.540.000)
. TAHAP VI : PLAT BETON 116 M
( Rp.48.119.000.000)

6
TAMPAK SAMPING KIRI ATAS

7
MAKO LANTAMAL XIV SORONG TAHAP I
(PEMATANGAN DAN PEMANCANGAN)

8
MAKO LANTAMAL XIV SORONG
TAHAP II

9
MAKO LANTAMAL XIV SORONG
TAHAP III