KURSI
F-305
(1)
ANALISIS MRP
TABEL 1
DAFTAR KESELURUHAN MATERIAL KURSI
TABEL 3
DATA KOMPONEN KURSI
PART LEND TIME MAKE (M) OR
LEVEL DESCRIPTION
NUMBER (WEEK) BUY (B)
0 F-305 KURSI 1 M
1 S-311 KAKI KURSI 1 B
SANDARAN
1 P-313 1 B
TANGAN
1 A-315 JOK 2 M
2 S-322 RANGKA JOK 2 B
2 R-424 BUSA 1 B
2 R-425 KAIN JOK 2 B
TABEL 4
PENERIMAAN YANG
DIRENCANAKAN
PART
SCHEDULED DUE
NUMER
(WEEK) DATA
RECEIPT
S-311 50 1
P-313 300 2
300 6
S-322 120 1
R-424 100 1
TABEL 5
DATA PERSEDIAAN
CURRENT
PART ALLOCATED
INVENTORY
NUMBER (UNIT)
(UNIT)
F-305 30 10
S-322 80 0
R-425 50 10
TABEL 6
ANALISIS KEBUTUHAN KOMPONEN
ITEM: KURSI PART N0. F-305
WEEK 0 1 2 3 4 5 6 7 8 9
GR 150 170
SR
OI 20 20 20 20 20 20
NR 130 170
PO 130 170
TABEL 7
ANALISIS KEBUTUHAN KOMPONEN
ITEM: KAKI KURSI PART N0. S-311
WEEK 0 1 2 3 4 5 6 7 8 9
GR TABEL 8 520 680
SR 50
ANALISIS KEBUTUHAN KOMPONEN
OI 50 50 50 50
NR 470 680
PO 470 680
TABEL 8
ANALISIS KEBUTUHAN KOMPONEN
ITEM: SANDARAN TANGAN PART N0. P-313
WEEK 0 1 2 3 4 5 6 7 8 9
GR 910 1190
SR 300 300
OI 300 300 300 300 300
NR
PO 610 890
TABEL 9
ANALISIS KEBUTUHAN KOMPONEN
ITEM: JOK KURSI PART N0. A-315
WEEK 0 1 2 3 4 5 6 7 8 9
GR 1170 1530
SR
OI
NR 1170 1530
PO 1170 1530
TABEL 10
ANALISIS KEBUTUHAN KOMPONEN
ITEM: RANGKA JOK PART N0. S-322
WEEK 0 1 2 3 4 5 6 7 8 9
GR 3510 4590
SR 120
OI 80 200 200
NR 3310 4590
PO 3310 4590
TABEL 11
ANALISIS KEBUTUHAN KOMPONEN
ITEM: BUSA PART N0. A-424
WEEK 0 1 2 3 4 5 6 7 8 9
GR 3510 4590
SR 100
OI 100 100
NR 3410 4590
PO 3410 4590
TABEL 12
ANALISIS KEBUTUHAN KOMPONEN
ITEM: KAIN JOK PART N0. R-425
WEEK 0 1 2 3 4 5 6 7 8 9
GR 7020 9180
SR
OI 40 40 40
NR 6980 9180
PO 6980 9180