Anda di halaman 1dari 279

BADAN PENDAPATAN PENGELOLAAN

KEUANGAN DAN ASET (BPPKA)


PEMERINTAH KOTA MOJOKERTO

TAHUN ANGGARAN

Harga Satuan Pokok Kegiatan (HSPK)


dan Analisa Standar Belanja (ASB)
Pemerintah Kota Mojokerto
DAFTAR ISI

PERWALI MOJOKERTO
DAFTAR ISI ..................................................................................................................................................................................................................................... i
STANDART BIAYA UMUM (SBU) ............................................................................................................................................................................................ 1
PENJELASAN .......................................................................................................................................................................................................................... 58
REKAP HSPK................................................................................................................................................................................................................................... 68
HSPK .................................................................................................................................................................................................................................................. 80
2.01 HSPK FISIK - KONSTRUKSI.......................................................................................................................................................................................... 80
2.01.01 BANGUNAN GEDUNG .............................................................................................................................................................................................. 80
2.01.01.01 PEKERJAAN PERSIAPAN DAN TANAH ....................................................................................................................................................... 80
2.01.01.01.01 PEKERJAAN PERSIAPAN ........................................................................................................................................................................... 80
2.01.01.01.01.002 Pekerjaan Pembuatan Pagar Sementara Seng Gelombang Tinggi 2 m .......................................................................... 80
2.01.01.01.01.003 Pekerjaan Pembuatan Pagar Sementara Kawat Duri Tinggi 1.8 m ................................................................................. 80
2.01.01.01.01.004 Pekerjaan Pengukuran dan Pemasangan Bouwplank.......................................................................................................... 80
2.01.01.01.01.008 Pekerjaan Pembersihan Lapangan "Ringan" dan Perataan ............................................................................................... 81
2.01.01.01.01.020 Pekerjaan Pembersihan Lapangan "Berat" dan Perataan .................................................................................................. 81
2.01.01.01.01.010 Pekerjaan Pembuatan Jalan Sementara ..................................................................................................................................... 81
2.01.01.01.01.011 Pekerjaan Pembongkaran Beton Bertulang ............................................................................................................................. 81
2.01.01.01.01.013 Pekerjaan Pembongkaran Pasangan Batu Kali ....................................................................................................................... 81
2.01.01.01.01.015 Pekerjaan Pembongkaran Tembok Batu Bata......................................................................................................................... 82
2.01.01.01.01.016 Pekerjaan Pembongkaran Penutup Atap Tidak Dipakai Kembali ................................................................................... 82
2.01.01.01.01.017 Pekerjaan Pembongkaran Penutup Atap dan Dipakai Kembali................................................................................. 82
2.01.01.01.01.018 Pekerjaan Pembongkaran Paving Tidak Dipakai Kembali........................................................................................... 82
2.01.01.01.01.021 Pekerjaan Pembongkaran Paving dan Dipakai Kembali............................................................................................... 82
2.01.01.01.02 PEKERJAAN TANAH .................................................................................................................................................................................... 83
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa ................................................................................................................................................. 83
2.01.01.01.02.004 Pekerjaan Galian Tanah Keras ....................................................................................................................................................... 83
2.01.01.01.02.005 Pekerjaan Galian Tanah Cadas ...................................................................................................................................................... 83
2.01.01.01.02.006 Pekerjaan Galian Tanah Lumpur .................................................................................................................................................. 83
2.01.01.01.02.007 Pekerjaan Stripping Tebing Setinggi 1 m .................................................................................................................................. 83
2.01.01.01.02.008 Pekerjaan Pembuangan Hasil Galian Sejauh 30 m ................................................................................................................ 84
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa ............................................................................................................ 84
2.01.01.01.02.016 Pekerjaan Pemadatan Tanah dengan Alat ................................................................................................................................ 84
2.01.01.01.02.017 Pekerjaan Pemasangan Pudel Campuran 1 Kp : 3 Pp : 7 Tl ......................................................................................... 84
2.01.01.01.02.018 Pekerjaan Pemasangan Lapisan Ijuk Tebal 10 cm untuk Bidang Resapan ........................................................... 84
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug ........................................................................................................................................ 85
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat ....................................................................................................................................... 85
2.01.01.01.02.022 Pekerjaan Pengurugan dengan Tanah Urug ...................................................................................................................... 85
2.01.01.01.02.023 Pekerjaan Pengurugan dengan Tanah Taman .................................................................................................................. 85
2.01.01.02 PEKERJAAN PONDASI ...................................................................................................................................................................................... 85
2.01.01.02.01 PEKERJAAN PONDASI ................................................................................................................................................................................ 85
2.01.01.02.01.001 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 3 Pp) ...................................................... 85
2.01.01.02.01.002 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 4 Pp) ...................................................... 86
2.01.01.02.01.003 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 5 Pp) ...................................................... 86
2.01.01.02.01.007 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1/4 Pc : 1 Kp : 4 Pp) .................................... 86
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) .................................................................................................... 87
2.01.01.02.01.011 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 20 cm Sedalam 3 m ........................................................... 87
2.01.01.02.01.012 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 30 cm Sedalam 3 m ........................................................... 87
2.01.01.03 PEKERJAAN STRUKTUR UTAMA .................................................................................................................................................................. 87
2.01.01.03.01 PEKERJAAN BETON ..................................................................................................................................................................................... 87
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 ......................................................................................................................... 87
2.01.01.03.01.002 Pekerjaan Pembuatan Beton K-100 ...................................................................................................................................... 88
2.01.01.03.01.003 Pekerjaan Pembuatan Beton K-125 ...................................................................................................................................... 88
2.01.01.03.01.004 Pekerjaan Pembuatan Beton K-150 ...................................................................................................................................... 88
2.01.01.03.01.005 Pekerjaan Pembuatan Beton K-175 ...................................................................................................................................... 89
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 ...................................................................................................................................... 89
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 ...................................................................................................................................... 89
2.01.01.03.01.008 Pekerjaan Pembuatan Beton K-250 ...................................................................................................................................... 90
2.01.01.03.01.009 Pekerjaan Pembuatan Beton K-275 ...................................................................................................................................... 90
2.01.01.03.01.010 Pekerjaan Pembuatan Beton K-300 ...................................................................................................................................... 90
2.01.01.03.01.011 Pekerjaan Pembuatan Beton K-325 ...................................................................................................................................... 90
2.01.01.03.01.012 Pekerjaan Pembuatan Beton K-350 ...................................................................................................................................... 91
2.01.01.03.01.013 Pekerjaan Pembesian dengan Besi Polos/Ulir.................................................................................................................. 91
2.01.01.03.01.015 Pekerjaan Pemasangan Wiremesh ........................................................................................................................................ 91

i
2.01.01.03.01.016 Pekerjaan Pembuatan Pondasi Beton Bertulang (150 kg Besi + Bekisting) ......................................................... 92
2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) ............................................................... 92
2.01.01.03.01.018 Pekerjaan Pembuatan Kolom Beton Bertulang (300 kg Besi + Bekisting) ............................................................ 92
2.01.01.03.01.019 Pekerjaan Pembuatan Balok Beton Bertulang (200 kg Besi + Bekisting) .............................................................. 93
2.01.01.03.01.020 Pekerjaan Pembuatan Plat Beton Bertulang (150 kg Besi + Bekisting) ................................................................. 93
2.01.01.03.01.021 Pekerjaan Pembuatan Dinding Beton Bertulang (150 kg Besi + Bekisting) ......................................................... 94
2.01.01.03.01.022 Pekerjaan Pembuatan Dinding Beton Bertulang (200 kg Besi + Bekisting) ......................................................... 94
2.01.01.03.01.023 Pekerjaan Pembuatan Kolom Praktis Beton Bertulang 11x11 cm ........................................................................... 95
2.01.01.03.01.024 Pekerjaan Pembuatan Ring Balok Beton Bertulang 10x15 cm .................................................................................. 95
2.01.01.03.02 PEKERJAAN CETAKAN BETON (BEKISTING) .................................................................................................................................. 96
2.01.01.03.02.001 Pekerjaan Pasang Bekisting untuk Pondasi ....................................................................................................................... 96
2.01.01.03.02.002 Pekerjaan Pasang Bekisting untuk Sloof ............................................................................................................................. 96
2.01.01.03.02.003 Pekerjaan Pasang Bekisting untuk Kolom .......................................................................................................................... 96
2.01.01.03.02.004 Pekerjaan Pasang Bekisting untuk Balok ........................................................................................................................... 97
2.01.01.03.02.005 Pekerjaan Pasang Bekisting untuk Lantai .......................................................................................................................... 97
2.01.01.03.02.006 Pekerjaan Pasang Bekisting untuk Dinding ....................................................................................................................... 97
2.01.01.03.02.007 Pekerjaan Pasang Bekisting untuk Tangga ........................................................................................................................ 98
2.01.01.04 PEKERJAAN PASANGAN DINDING DAN PLESTERAN .......................................................................................................................... 98
2.01.01.04.01 PEKERJAAN PASANGAN DINDING ........................................................................................................................................................ 98
2.01.01.04.01.001 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 2 Ps) ........................................................................................ 98
2.01.01.04.01.002 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 2 Ps) ................................................................................... 98
2.01.01.04.01.003 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 3 Ps) ........................................................................................ 99
2.01.01.04.01.004 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 3 Ps) ................................................................................... 99
2.01.01.04.01.013 Pekerjaan Pasangan Dinding Bata Ringan Tebal 7,5 cm dengan Mortar Siap Pakai ......................................... 99
2.01.01.04.01.014 Pekerjaan Pasangan Dinding Bata Ringan Tebal 10 cm dengan Mortar Siap Pakai .......................................... 99
2.01.01.04.01.015 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 4 Ps) ........................................................................................ 100
2.01.01.04.01.016 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 4 Ps) ................................................................................... 100
2.01.01.04.01.017 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 5 Ps) ........................................................................................ 100
2.01.01.04.01.018 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 5 Ps) ................................................................................... 101
2.01.01.04.01.019 Pekerjaan Pemasangan Dinding Bata Expose tbl 1 Bata (1 Pc : 3 Ps) ..................................................................... 101
2.01.01.04.02 PEKERJAAN PLESTERAN ......................................................................................................................................................................... 101
2.01.01.04.02.001 Pekerjaan Plesteran 1 Pc : 1 Ps tbl 15 mm ......................................................................................................................... 101
2.01.01.04.02.002 Pekerjaan Plesteran 1 Pc : 2 Ps tbl 15 mm ......................................................................................................................... 101
2.01.01.04.02.003 Pekerjaan Plesteran 1 Pc : 3 Ps tbl 15 mm ......................................................................................................................... 102
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm ......................................................................................................................... 102
2.01.01.04.02.005 Pekerjaan Plesteran 1 Pc : 5 Ps tbl 15 mm ......................................................................................................................... 102
2.01.01.04.02.014 Pekerjaan Plesteran Skoning 1 Pc : 3 Ps lebar 10 cm..................................................................................................... 103
2.01.01.04.02.015 Pekerjaan Benangan ................................................................................................................................................................... 103
2.01.01.04.02.016 Pekerjaan Plesteran Ciprat 1 Pc : 2 Ps ................................................................................................................................. 103
2.01.01.04.02.020 Pekerjaan Acian ............................................................................................................................................................................ 103
2.01.01.05 PEKERJAAN PENUTUP LANTAI DAN DINDING ..................................................................................................................................... 104
2.01.01.05.01 PEKERJAAN PENUTUP LANTAI ............................................................................................................................................................. 104
2.01.01.05.01.001 Pekerjaan Pemasangan Lantai Granit Uk. 60x60 cm...................................................................................................... 104
2.01.01.05.01.002 Pekerjaan Pemasangan Lantai Granit Uk. 40x40 cm...................................................................................................... 104
2.01.01.05.01.013 Pekerjaan Pemasangan Lantai Granit Uk. 30x30 cm...................................................................................................... 104
2.01.01.05.01.003 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 40x40 cm ..................................................................................... 105
2.01.01.05.01.004 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 30x30 cm ..................................................................................... 105
2.01.01.05.01.005 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 20x20 cm ..................................................................................... 105
2.01.01.05.01.006 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 40x40 cm ..................................................................................... 105
2.01.01.05.01.007 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 30x30 cm ..................................................................................... 106
2.01.01.05.01.008 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 20x20 cm ..................................................................................... 106
2.01.01.05.01.009 Pekerjaan Pemasangan Lantai Marmer Uk. 100x100 cm............................................................................................. 106
2.01.01.05.01.011 Pekerjaan Pemasangan Lantai Kayu (Parquet) ................................................................................................................ 107
2.01.01.05.01.012 Pekerjaan Pemasangan Lantai Karpet + Underlayer (Pelapis Bawah Karpet) .................................................... 107
2.01.01.05.02 PEKERJAAN PENUTUP DINDING .......................................................................................................................................................... 107
2.01.01.05.02.001 Pekerjaan Pemasangan Dinding Keramik Polos Uk. 20x25 cm.................................................................................. 107
2.01.01.05.02.002 Pekerjaan Pemasangan Dinding Keramik Polos Uk. 20x20 cm.................................................................................. 108
2.01.01.05.02.003 Pekerjaan Pemasangan Dinding Keramik Polos Uk. 10x20 cm.................................................................................. 108
2.01.01.05.02.004 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x25 cm .................................................................................. 108
2.01.01.05.02.005 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x20 cm .................................................................................. 109
2.01.01.05.02.006 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 10x20 cm .................................................................................. 109
2.01.01.05.02.007 Pekerjaan Pemasangan Plint Keramik 10x20 cm ............................................................................................................ 109
2.01.01.05.02.011 Pekerjaan Pemasangan Batu Palimanan ............................................................................................................................. 109
2.01.01.05.02.013 Pekerjaan Pemasangan Batu Ampyang ............................................................................................................................... 110
2.01.01.05.02.015 Pekerjaan Pemasangan Batu Gilang ..................................................................................................................................... 110
2.01.01.05.02.018 Pekerjaan Pemasangan Wallpaper........................................................................................................................................ 110
2.01.01.06 PEKERJAAN KAYU ............................................................................................................................................................................................. 111
ii
2.01.01.06.01 PEKERJAAN KUSEN, PINTU, JENDELA, DAN JALUSI ..................................................................................................................... 111
2.01.01.06.01.001 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas I (Jati) .................................................................. 111
2.01.01.06.01.002 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas II (Kamper) ....................................................... 111
2.01.01.06.01.003 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas III (Kruing)........................................................ 111
2.01.01.06.01.004 Pembuatan dan Pemasangan Pintu Klamp Kayu Kelas I (Jati) ................................................................................... 111
2.01.01.06.01.005 Pembuatan dan Pemasangan Pintu Klamp Kayu Kelas II (Kamper) ........................................................................ 112
2.01.01.06.01.006 Pembuatan dan Pemasangan Pintu Klamp Kayu Kelas III (Kruing)......................................................................... 112
2.01.01.06.01.007 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Kelas I (Jati) ......................................................................... 112
2.01.01.06.01.008 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Kelas II (Kamper) .............................................................. 113
2.01.01.06.01.009 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Kelas III (Kruing)............................................................... 113
2.01.01.06.01.010 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas I (Jati) ..................................................................... 113
2.01.01.06.01.011 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas II (Kamper) .......................................................... 113
2.01.01.06.01.012 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas III (Kruing) ........................................................... 114
2.01.01.06.01.013 Pembuatan dan Pemasangan Pintu/Jendela Jalusi Kayu Kelas I (Jati).................................................................... 114
2.01.01.06.01.014 Pembuatan dan Pemasangan Pintu/Jendela Jalusi Kayu Kelas II (Kamper)......................................................... 114
2.01.01.06.01.015 Pembuatan dan Pemasangan Pintu/Jendela Jalusi Kayu Kelas III (Kruing) ......................................................... 114
2.01.01.06.01.016 Pembuatan dan Pemasangan Pintu Plywood Rangkap, Rangka Kayu Kelas I (Jati) .......................................... 115
2.01.01.06.01.017 Pembuatan dan Pemasangan Pintu Plywood Rangkap, Rangka Kayu Kelas II (Kamper) ............................... 115
2.01.01.06.01.018 Pembuatan dan Pemasangan Pintu Plywood Rangkap, Rangka Kayu Kelas III (Kruing) ................................ 115
2.01.01.06.01.019 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas I (Jati)....................................... 116
2.01.01.06.01.020 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas II (Kamper)............................ 116
2.01.01.06.01.021 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas III (Kruing) ............................ 116
2.01.01.06.01.022 Pembuatan dan Pemasangan Pintu Triplek Rangkap, Rangka Kayu Kelas I (Jati) ............................................. 116
2.01.01.06.01.023 Pembuatan dan Pemasangan Pintu Triplek Rangkap, Rangka Kayu Kelas II (Kamper) .................................. 117
2.01.01.06.01.025 Pembuatan dan Pemasangan Pintu Triplek Rangkap, Rangka Kayu Kelas III (Kruing) ................................... 117
2.01.01.06.01.026 Pekerjaan Pemasangan Pintu PVC (Polyvinyl Chloride)............................................................................................... 117
2.01.01.06.01.027 Pekerjaan Pemasangan Pintu HPL (High Pressure Laminated) ................................................................................ 117
2.01.01.06.02 PEKERJAAN KUDA-KUDA DAN RANGKA ATAP............................................................................................................................... 118
2.01.01.06.02.001 Pekerjaan Pemasangan Kuda-kuda Kayu Kelas I (Jati) ................................................................................................. 118
2.01.01.06.02.002 Pekerjaan Pemasangan Kuda-kuda Kayu Kelas II (Kamper) ...................................................................................... 118
2.01.01.06.02.003 Pekerjaan Pemasangan Kuda-kuda Kayu Kelas III (Kruing & Meranti) ................................................................. 118
2.01.01.06.02.005 Pekerjaan Pemasangan Gording Kayu Kelas I (Jati) ....................................................................................................... 119
2.01.01.06.02.006 Pekerjaan Pemasangan Gording Kayu Kelas II (Kamper) ............................................................................................ 119
2.01.01.06.02.007 Pekerjaan Pemasangan Gording Kayu Kelas III (Kruing & Meranti) ....................................................................... 119
2.01.01.06.02.009 Pekerjaan Pemasangan Rangka Atap Kayu Kelas III - Genteng Kodok ................................................................... 120
2.01.01.06.02.010 Pekerjaan Pemasangan Rangka Atap Kayu Kelas III - Genteng Keramik ............................................................... 120
2.01.01.06.02.011 Pekerjaan Pemasangan Rangka Atap Kayu Kelas III - Genteng Beton .................................................................... 120
2.01.01.06.03 PEKERJAAN RANGKA LANGIT-LANGIT DAN LISTPLANK........................................................................................................... 121
2.01.01.06.03.004 Pekerjaan Pemasangan Rangka Langit-langit Kayu Kelas II (Kamper) 100x100 ............................................... 121
2.01.01.06.03.005 Pekerjaan Pemasangan Rangka Langit-langit Kayu Kelas II (Kamper) 50x100 .................................................. 121
2.01.01.06.03.006 Pekerjaan Pemasangan Rangka Langit-langit Kayu Kelas II (Kamper) 60x60 .................................................... 121
2.01.01.06.03.014 Pekerjaan Pemasangan Listplank Kayu Kelas II (Kamper) 3/20 .............................................................................. 121
2.01.01.06.03.016 Pekerjaan Pemasangan Listplank Kayu Kelas II (Kamper) 3/30 .............................................................................. 122
2.01.01.06.04 PEKERJAAN DINDING PARTISI .............................................................................................................................................................. 122
2.01.01.06.04.011 Pekerjaan Partisi Double Gypsum Rangka Kayu Kelas II (Kamper) ........................................................................ 122
2.01.01.06.04.012 Pekerjaan Partisi Double Plywood Rangka Kayu Kelas II (Kamper) ....................................................................... 122
2.01.01.06.04.013 Pekerjaan Partisi Multiplek Finishing HPL Rangka Kayu Kelas II (Kamper)........................................................ 123
2.01.01.06.04.014 Pekerjaan Partisi Double Gypsum Rangka Metal Stud .................................................................................................. 123
2.01.01.06.04.015 Pekerjaan Partisi Double Plywood Rangka Metal Stud ................................................................................................. 123
2.01.01.06.04.016 Pekerjaan Partisi Multiplek Finishing HPL Rangka Metal Stud ................................................................................. 123
2.01.01.06.04.017 Pekerjaan Partisi Kalsiboard Rangka Hollow ................................................................................................................... 124
2.01.01.07 PEKERJAAN FINISHING................................................................................................................................................................................... 124
2.01.01.07.01 PEKERJAAN FINISHING PENUTUP ATAP DAN LANGIT LANGIT .............................................................................................. 124
2.01.01.07.01.001 Pekerjaan Pemasangan Penutup Atap Genteng Tanah Liat (Karang Pilang) ....................................................... 124
2.01.01.07.01.003 Pekerjaan Pemasangan Penutup Atap Genteng Tanah Liat (Plentong, Kodok) Glazur .................................... 124
2.01.01.07.01.005 Pekerjaan Pemasangan Penutup Atap Genteng Keramik Glazur .............................................................................. 125
2.01.01.07.01.009 Pekerjaan Pemasangan Penutup Atap Seng Gelombang .............................................................................................. 125
2.01.01.07.01.010 Pekerjaan Pemasangan Penutup Atap Roof Light Fiberglass ..................................................................................... 125
2.01.01.07.01.044 Pekerjaan Pemasangan Penutup Atap Galvalum ............................................................................................................. 125
2.01.01.07.01.011 Pekerjaan Pemasangan Penutup Atap Asbes Gelombang Tebal 5 mm ................................................................... 126
2.01.01.07.01.016 Pekerjaan Pemasangan Penutup Atap Asbes Gelombang Tebal 4 mm ................................................................... 126
2.01.01.07.01.020 Pekerjaan Pemasangan Bubungan Genteng Tanah Liat (Karang Pilang) .............................................................. 126
2.01.01.07.01.021 Pekerjaan Pemasangan Bubungan Genteng Tanah Liat (Plentong, Kodok) Glazur ........................................... 126
2.01.01.07.01.022 Pekerjaan Pemasangan Bubungan Genteng Keramik Glazur ..................................................................................... 127
2.01.01.07.01.023 Pekerjaan Pemasangan Nok Genteng Beton...................................................................................................................... 127
2.01.01.07.01.045 Pekerjaan Pemasangan Nok Galvalum ................................................................................................................................ 127
2.01.01.07.01.026 Pekerjaan Pemasangan Nok Seng .......................................................................................................................................... 128
iii
2.01.01.07.01.031 Pekerjaan Pemasangan Bubungan Steel Gelombang Kecil .......................................................................................... 128
2.01.01.07.01.046 Pekerjaan Pemasangan Insulation Alumunium Foil ...................................................................................................... 128
2.01.01.07.01.032 Pekerjaan Waterproofing Membrane (Liquid)................................................................................................................. 128
2.01.01.07.01.033 Pekerjaan Waterproofing Coating ......................................................................................................................................... 129
2.01.01.07.01.034 Pekerjaan Pemasangan Langit-langit Asbes Tebal 4 mm, 5 mm, 6 mm.................................................................. 129
2.01.01.07.01.038 Pekerjaan Pemasangan Langit-langit Tripleks Tebal 3 mm, 4 mm, 6 mm............................................................. 129
2.01.01.07.01.041 Pekerjaan Pemasangan Langit-langit Gypsum Board Tebal 9 mm ........................................................................... 129
2.01.01.07.01.042 Pekerjaan Pemasangan Lis Langit-langit Kayu................................................................................................................. 130
2.01.01.07.01.043 Pekerjaan Pemasangan Lis Langit-langit Gypsum .......................................................................................................... 130
2.01.01.07.02 PEKERJAAN SANITAIR .............................................................................................................................................................................. 130
2.01.01.07.02.001 Pekerjaan Pemasangan Kloset Duduk ................................................................................................................................. 130
2.01.01.07.02.002 Pekerjaan Pemasangan Kloset Jongkok Porselain .......................................................................................................... 131
2.01.01.07.02.004 Pekerjaan Pemasangan Urinoir .............................................................................................................................................. 131
2.01.01.07.02.005 Pekerjaan Pemasangan Wastafel ........................................................................................................................................... 131
2.01.01.07.02.006 Pekerjaan Pemasangan Bak Mandi Fiberglass ................................................................................................................. 131
2.01.01.07.02.009 Pekerjaan Pemasangan Bak Cuci Piring Stainless Steel + Accesories...................................................................... 132
2.01.01.07.02.010 Pekerjaan Pemasangan Floor Drain...................................................................................................................................... 132
2.01.01.07.02.011 Pekerjaan Pemasangan Bak Kontrol Pasangan Batu Bata Merah ............................................................................. 132
2.01.01.07.02.014 Pekerjaan Pemasangan Pipa Galvanis Diameter 1/2 inch ........................................................................................... 133
2.01.01.07.02.015 Pekerjaan Pemasangan Pipa Galvanis Diameter 3/4 inch ........................................................................................... 133
2.01.01.07.02.016 Pekerjaan Pemasangan Pipa Galvanis Diameter 1 inch ................................................................................................ 133
2.01.01.07.02.017 Pekerjaan Pemasangan Pipa Galvanis Diameter 1 1/2 inch ....................................................................................... 133
2.01.01.07.02.018 Pekerjaan Pemasangan Pipa Galvanis Diameter 3 inch ................................................................................................ 134
2.01.01.07.02.019 Pekerjaan Pemasangan Pipa Galvanis Diameter 4 inch ................................................................................................ 134
2.01.01.07.02.020 Pekerjaan Pemasangan Kran Air............................................................................................................................................ 134
2.01.01.07.02.021 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1/2 inch ................................................................................ 134
2.01.01.07.02.022 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 3/4 inch ................................................................................ 135
2.01.01.07.02.023 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1 inch ..................................................................................... 135
2.01.01.07.02.024 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1 1/2 inch............................................................................. 135
2.01.01.07.02.025 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 2 inch ..................................................................................... 135
2.01.01.07.02.026 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 2 1/2 inch............................................................................. 136
2.01.01.07.02.027 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 3 inch ..................................................................................... 136
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch ..................................................................................... 136
2.01.01.07.02.036 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 6 inch ..................................................................................... 136
2.01.01.07.02.029 Pekerjaan Pemasangan Pipa PVC Type D Diameter 2 inch.......................................................................................... 137
2.01.01.07.02.030 Pekerjaan Pemasangan Pipa PVC Type D Diameter 3 inch.......................................................................................... 137
2.01.01.07.02.031 Pekerjaan Pemasangan Pipa PVC Type D Diameter 4 inch.......................................................................................... 137
2.01.01.07.02.032 Pekerjaan Pemasangan Shower Set ...................................................................................................................................... 137
2.01.01.07.02.037 Pekerjaan Pemasangan Tee Pipa PVC Type D Diameter 4 inch ................................................................................. 138
2.01.01.07.02.038 Pekerjaan Pemasangan Elbow Pipa PVC Type D Diameter 4 inch............................................................................ 138
2.01.01.07.02.039 Pekerjaan Pemasangan Socket Pipa PVC Type D Diameter 4 inch ........................................................................... 138
2.01.01.07.02.040 Pekerjaan Pemasangan Valve Pipa PVC Type D Diameter 4 inch ............................................................................. 138
2.01.01.07.02.041 Pekerjaan Pemasangan Blank Flanged Diameter 4 inch............................................................................................... 139
2.01.01.07.03 PEKERJAAN BESI DAN ALUMUNIUM .................................................................................................................................................. 139
2.01.01.07.03.001 Pekerjaan Pemasangan Besi Profil ........................................................................................................................................ 139
2.01.01.07.03.004 Pekerjaan Perakitan Besi Profil .............................................................................................................................................. 139
2.01.01.07.03.005 Pekerjaan Pengelasan dengan Las Listrik .......................................................................................................................... 139
2.01.01.07.03.006 Pekerjaan Pemasangan Rangka Hollow Dinding Partisi............................................................................................... 140
2.01.01.07.03.007 Pekerjaan Pembuatan Kusen Alumunium 4 inch ............................................................................................................ 140
2.01.01.07.03.008 Pekerjaan Pembuatan Kusen Alumunium 3 inch ............................................................................................................ 140
2.01.01.07.03.009 Pekerjaan Pemasangan Rangka Atap Galvalum Genteng Asbes/Spandek ............................................................ 140
2.01.01.07.03.010 Pekerjaan Pemasangan Rangka Atap Galvalum Genteng Biasa/Metal ................................................................... 141
2.01.01.07.03.011 Pekerjaan Pemasangan Rangka Hollow Plafon ................................................................................................................ 141
2.01.01.07.03.012 Pekerjaan Pemasangan Pintu Kaca Rangka Alumunium .............................................................................................. 141
2.01.01.07.03.013 Pekerjaan Pemasangan Pintu Alumunium Strip .............................................................................................................. 142
2.01.01.07.03.014 Pekerjaan Pemasangan Rolling Door Besi/Galvalum .................................................................................................... 142
2.01.01.07.03.015 Pekerjaan Pemasangan Rolling Door Alumunium .......................................................................................................... 142
2.01.01.07.03.016 Pekerjaan Pemasangan Folding Door Besi/Galvalum ................................................................................................... 142
2.01.01.07.03.034 Pekerjaan Pemasangan Folding Door Alumunium ......................................................................................................... 143
2.01.01.07.03.035 Pekerjaan Pemasangan Folding Door PVC ......................................................................................................................... 143
2.01.01.07.03.017 Pekerjaan Pemasangan Jendela Nako dan Teralis .......................................................................................................... 143
2.01.01.07.03.018 Pekerjaan Pemasangan Terali Besi Strip ............................................................................................................................ 143
2.01.01.07.03.019 Pekerjaan Pemasangan Talang Datar/Jurai Seng ............................................................................................................ 144
2.01.01.07.03.020 Pekerjaan Pemasangan Talang Miring Seng ...................................................................................................................... 144
2.01.01.07.03.021 Pekerjaan Pemasangan Talang 1/2 Lingkarang .............................................................................................................. 144
2.01.01.07.03.023 Pekerjaan Pemasangan Sunscreen........................................................................................................................................ 145
2.01.01.07.03.024 Pekerjaan Pemasangan Vertical/Venetion Blind............................................................................................................. 145
iv
2.01.01.07.03.025 Pekerjaan Pemasangan Kawat Nyamuk .............................................................................................................................. 145
2.01.01.07.03.026 Pekerjaan Pemasangan Pagar Besi BRC .............................................................................................................................. 145
2.01.01.07.03.027 Pekerjaan Pemasangan Tiang Pagar Besi BRC ................................................................................................................. 146
2.01.01.07.03.028 Pekerjaan Pemasangan Daun Pintu Besi BRC Swing Ganda........................................................................................ 146
2.01.01.07.03.029 Pekerjaan Pemasangan Railling Tangga Besi Hollow .................................................................................................... 146
2.01.01.07.03.030 Pekerjaan Pemasangan Kanopi Rangka Besi Hollow Penutup Atap Polycarbonate.......................................... 146
2.01.01.07.03.031 Pekerjaan Pembuatan dan Pemasangan Pagar Besi Hollow ....................................................................................... 147
2.01.01.07.03.032 Pekerjaan Pembuatan dan Pemasangan Pagar Besi Tempa........................................................................................ 147
2.01.01.07.04 PEKERJAAN KUNCI DAN KACA .............................................................................................................................................................. 147
2.01.01.07.04.002 Pekerjaan Pemasangan Kunci Tanam Biasa ...................................................................................................................... 147
2.01.01.07.04.004 Pekerjaan Pemasangan Kunci Silinder ................................................................................................................................ 147
2.01.01.07.04.005 Pekerjaan Pemasangan Engsel Panel ................................................................................................................................... 148
2.01.01.07.04.006 Pekerjaan Pemasangan Engsel Kupu-kupu ....................................................................................................................... 148
2.01.01.07.04.011 Pekerjaan Pemasangan Door Closer ..................................................................................................................................... 148
2.01.01.07.04.012 Pekerjaan Pemasangan Grendel............................................................................................................................................. 148
2.01.01.07.04.013 Pekerjaan Pemasangan Door Holder.................................................................................................................................... 149
2.01.01.07.04.014 Pekerjaan Pemasangan Door Stopper.................................................................................................................................. 149
2.01.01.07.04.015 Pekerjaan Pemasangan Sliding Door Rail ........................................................................................................................... 149
2.01.01.07.04.016 Pekerjaan Pemasangan Kaca Tebal 3 mm .......................................................................................................................... 149
2.01.01.07.04.017 Pekerjaan Pemasangan Kaca Tebal 5 mm .......................................................................................................................... 150
2.01.01.07.04.018 Pekerjaan Pemasangan Kaca Tebal 8 mm .......................................................................................................................... 150
2.01.01.07.05 PEKERJAAN PENGECATAN...................................................................................................................................................................... 150
2.01.01.07.05.001 Pekerjaan Mengerok Cat Lama Permukaan Kayu ........................................................................................................... 150
2.01.01.07.05.002 Pekerjaan Mendempul dan Menggosok Kayu ................................................................................................................... 150
2.01.01.07.05.003 Pekerjaan Pengecatan Bidang Kayu Lama ......................................................................................................................... 151
2.01.01.07.05.004 Pekerjaan Pengecatan Bidang Kayu Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Penutup) ................................ 151
2.01.01.07.05.005 Pekerjaan Pengecatan Bidang Kayu Baru (1 Lps. Plamir, 1 Lps. Dasar, 3 Lps. Penutup) ................................ 151
2.01.01.07.05.006 Pekerjaan Pelaburan Bidang Kayu dengan Politur ......................................................................................................... 152
2.01.01.07.05.007 Pekerjaan Pelaburan Bidang Kayu dengan Cat Residu/Teer ...................................................................................... 152
2.01.01.07.05.008 Pekerjaan Pelaburan Bidang Kayu dengan Vernis .......................................................................................................... 152
2.01.01.07.05.009 Pekerjaan Mengerok Cat Lama Permukaan Tembok ..................................................................................................... 153
2.01.01.07.05.010 Pekerjaan Pencucian Bidang Permukaan Tembok yang Pernah Dicat ................................................................... 153
2.01.01.07.05.011 Pekerjaan Mengapur Dinding Tembok Baru ..................................................................................................................... 153
2.01.01.07.05.012 Pekerjaan Mengapur Dinding Tembok Lama.................................................................................................................... 153
2.01.01.07.05.013 Pekerjaan Pengecatan Bidang Tembok Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Interior) ........................... 154
2.01.01.07.05.014 Pekerjaan Pengecatan Bidang Tembok Lama (1 Lps. Dasar, 2 Lps. Interior)....................................................... 154
2.01.01.07.05.015 Pekerjaan Pengecatan Tembok Exterior............................................................................................................................. 154
2.01.01.07.05.023 Pekerjaan Pengecatan Plafon .................................................................................................................................................. 155
2.01.01.07.05.025 Pekerjaan Pengecatan Pohon .................................................................................................................................................. 155
2.01.01.07.05.024 Pekerjaan Pengecatan Outdoor Antislip ............................................................................................................................. 155
2.01.01.07.06 PEKERJAAN INSTALASI LISTRIK .......................................................................................................................................................... 155
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak .................................................................................................................................... 156
2.01.01.07.06.002 Pekerjaan Pemasangan Titik Lampu .................................................................................................................................... 156
2.01.01.07.06.004 Pekerjaan Pemasangan Saklar Tunggal............................................................................................................................... 156
2.01.01.07.06.005 Pekerjaan Pemasangan Saklar Ganda .................................................................................................................................. 156
2.01.01.07.06.006 Pekerjaan Pemasangan Lampu TL 18 watt........................................................................................................................ 157
2.01.01.07.06.007 Pekerjaan Pemasangan Lampu TL 36 watt........................................................................................................................ 157
2.01.01.07.06.008 Pekerjaan Pemasangan Lampu SL 18 watt ........................................................................................................................ 157
2.01.01.07.06.009 Pekerjaan Pemasangan Lampu SL 36 watt ........................................................................................................................ 157
2.01.01.07.06.010 Pekerjaan Pemasangan Lampu LED 18 watt..................................................................................................................... 157
2.01.01.07.06.011 Pekerjaan Pemasangan Lampu LED 36 watt..................................................................................................................... 158
2.01.01.07.06.012 Pekerjaan Pemasangan Lampu Downlight ........................................................................................................................ 158
2.01.01.07.06.013 Pekerjaan Pemasangan Panel Box ......................................................................................................................................... 158
2.01.01.07.06.014 Pekerjaan Pemasangan Panel Phase 2200 VA .................................................................................................................. 158
2.01.02.01.03 PEKERJAAN DRAINASE............................................................................................................................................................................. 159
2.01.02.01.03.001 Pekerjaan Galian untuk Selokan Drainase dan Saluran Air ......................................................................................... 159
2.01.02.01.03.002 Pekerjaan Pasangan Batu dengan Mortar .......................................................................................................................... 159
2.01.02.01.03.003 Bahan Porous untuk Filter........................................................................................................................................................ 159
2.01.02.01.03.004 Pekerjaan Pemasangan Lubang Drainase........................................................................................................................... 160
2.01.02.01 PAVING DAN PERKERASAN JALAN ............................................................................................................................................................ 160
2.01.02.01.02 PEKERJAAN PENGADAAN AGREGAT .................................................................................................................................................. 160
2.01.02.01.02.001 Pembuatan Agregat Kelas A ..................................................................................................................................................... 160
2.01.02.01.02.002 Pembuatan Agregat Kelas B ..................................................................................................................................................... 160
2.01.02.01.02.003 Pembuatan Agregat Kelas S ..................................................................................................................................................... 161
2.01.02.01.02.004 Pembuatan Lapis Pondasi Agregat (CBR 60%) ................................................................................................................ 161
2.01.02.01.02.005 Pembuatan Lapis Permukaan Agregat (CBR 60%) ......................................................................................................... 161
2.01.02.01.01 PEKERJAAN PAVING .................................................................................................................................................................................. 161
v
2.01.02.01.01.001 Pekerjaan Pemasangan Tegel Trotoar ................................................................................................................................. 161
2.01.02.01.01.002 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Segi Enam) ................................................................................... 162
2.01.02.01.01.003 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Segi Enam - Warna) ................................................................. 162
2.01.02.01.01.004 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Persegi Panjang ......................................................................... 162
2.01.02.01.01.005 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Persegi Panjang - Warna) ...................................................... 163
2.01.02.01.01.006 Pekerjaan Pemasangan Paving Stone tebal 6 cm (Persegi Panjang ......................................................................... 163
2.01.02.01.01.007 Pekerjaan Pemasangan Paving Stone tebal 6 cm (Persegi Panjang - Warna) ...................................................... 163
2.01.02.01.01.013 Pekerjaan Pemasangan Kanstin ............................................................................................................................................. 163
2.01.02.01.01.014 Pekerjaan Pemasangan Stopper/Uskup.............................................................................................................................. 164
2.01.02.01.01.015 Pekerjaan Tegel Batu Ampyang.............................................................................................................................................. 164
2.01.02.01.04 PEKERJAAN TANAH ................................................................................................................................................................................... 164
2.01.02.01.04.001 Pekerjaan Galian Biasa + Pembuangan Sisa Galian ........................................................................................................ 164
2.01.02.01.04.003 Pekerjaan Galian Batu + Pembuangan Sisa Galian .......................................................................................................... 164
2.01.02.01.04.004 Pekerjaan Galian Struktur dengan Kedalaman 0-2 m.................................................................................................... 165
2.01.02.01.04.005 Pekerjaan Galian Struktur dengan Kedalaman 2-4 m.................................................................................................... 165
2.01.02.01.04.006 Pekerjaan Galian Struktur dengan Kedalaman 4-6 m.................................................................................................... 165
2.01.02.01.04.007 Pekerjaan Galian Perkerasan Beraspal dengan Cold Milling
Machine ............................................................................................................................................................................................ 165
2.01.02.01.04.008 Pekerjaan Galian Perkerasan Beraspal Tanpa Cold Milling
Machine ............................................................................................................................................................................................ 166
2.01.02.01.04.010 Pekerjaan Pemotongan Pohon Pilihan Diameter 15-30 cm ........................................................................................ 166
2.01.02.01.04.011 Pekerjaan Pemotongan Pohon Pilihan Diameter 30-50 cm ........................................................................................ 166
2.01.02.01.04.012 Pekerjaan Pemotongan Pohon Pilihan Diameter 50-75 cm ........................................................................................ 166
2.01.02.01.04.013 Pekerjaan Pemotongan Pohon Pilihan Diameter >75 cm ............................................................................................ 167
2.01.02.01.04.014 Pekerjaan Galian Perkerasan Berbutir (Tanpa Lapis Penutup
Aspal) ................................................................................................................................................................................................ 167
2.01.02.01.04.015 Pekerjaan Pemasangan Geotextile ........................................................................................................................................ 167
2.01.02.01.04.016 Pekerjaan Galian Perkerasan Beton ..................................................................................................................................... 167
2.01.02.01.05 PEKERJAAN PELABURAN PERKERASAN DAN BAHU JALAN ..................................................................................................... 168
2.01.02.01.05.001 Pekerjaan Lapis Pondasi Agregat Kelas A .......................................................................................................................... 168
2.01.02.01.05.002 Pekerjaan Lapis Pondasi Agregat Kelas B .......................................................................................................................... 168
2.01.02.01.05.004 Pekerjaan Lapis Pondasi Semen Tanah ............................................................................................................................... 168
2.01.02.01.05.005 Bahan Agregat Penutup Burtu ................................................................................................................................................ 169
2.01.02.01.05.006 Bahan Aspal untuk Pekerjaan Pelaburan ........................................................................................................................... 169
2.01.02.01.05.007 Pekerjaan Lapis Resap Pengikat............................................................................................................................................. 169
2.01.02.01.05.008 Pekerjaan Lapis Pondasi Agregat Kelas S ........................................................................................................................... 169
2.01.02.01.05.009 Pekerjaan Lapis Perkerasan 5-10 cm (Padat Digilas).................................................................................................... 170
2.01.02.01.06 PEKERJAAN PELABURAN PERKERASAN NON ASPAL ................................................................................................................. 170
2.01.02.01.06.001 Pekerjaan Lapis Pondasi Agregat Kelas A .......................................................................................................................... 170
2.01.02.01.06.002 Pekerjaan Lapis Pondasi Agregat Kelas B .......................................................................................................................... 170
2.01.02.01.06.007 Pekerjaan Lapis Pondasi Atas Bersemen (Cement Treated Based-CTB) ............................................................... 171
2.01.02.01.06.008 Pekerjaan Lapis Pondasi Bawah (Cement Treated Sub-Based-
CTSB) ................................................................................................................................................................................................ 171
2.01.02.01.06.009 Pekerjaan Lapis Pondasi Agregat Tanpa Penutup Aspal .............................................................................................. 171
2.01.02.01.07 PEKERJAAN PELABURAN PERKERASAN ASPAL ............................................................................................................................ 172
2.01.02.01.07.001 Lapis Resap Pengikat - Aspal Cair.......................................................................................................................................... 172
2.01.02.01.07.002 Lapis Perekat - Aspal Cair ......................................................................................................................................................... 172
2.01.02.01.07.003 Bahan Agregat Penutup Burtu ................................................................................................................................................ 172
2.01.02.01.07.004 Bahan Agregat Penutup Burda ............................................................................................................................................... 173
2.01.02.01.07.007 Bahan Lataston Lapis Aus (HRS-WC) ................................................................................................................................... 173
2.01.02.01.07.008 Bahan Lataston Lapis Aus Perata (HRS-WC L) ................................................................................................................. 173
2.01.02.01.07.009 Bahan Lataston Lapis Pondasi (HRS-BASE) ...................................................................................................................... 174
2.01.02.01.07.010 Bahan Lataston Lapis Pondasi Perata (HRS-BASE L) .................................................................................................... 174
2.01.02.01.07.011 Bahan Laston Lapis Aus (AC-WC) .......................................................................................................................................... 174
2.01.02.01.07.012 Bahan Laston Lapis Aus Perata (AC-WC L) ........................................................................................................................ 175
2.01.02.01.07.013 Bahan Laston Lapis Antara (AC-BC) ..................................................................................................................................... 175
2.01.02.01.07.014 Bahan Laston Lapis Antara Perata (AC-BC L) ................................................................................................................... 176
2.01.02.01.07.015 Bahan Laston Lapis Pondasi (AC-BASE) ............................................................................................................................. 176
2.01.02.01.07.016 Bahan Laston Lapis Pondasi Perata (AC-BASE L) ........................................................................................................... 177
2.01.02.01.07.017 Pekerjaan Campuran Aspal Dingin untuk Pelapisan ...................................................................................................... 177
2.01.02.01.07.018 Pekerjaan Lapis Permukaan Penetrasi Macadam ........................................................................................................... 177
2.01.02.01.07.019 Pekerjaan Lapis Pondasi/Perata Penetrasi Macadam ................................................................................................... 178
2.01.02.01.07.020 Lapis Resep Pengikat - Aspal Emulsi .................................................................................................................................... 178
2.01.02.01.07.021 Lapis Perekat - Aspal Emulsi ................................................................................................................................................... 178
2.01.02.01.07.022 Aspal untuk Pekerjaan Pelaburan ......................................................................................................................................... 178
2.01.02.01.07.023 Lapis Perekat - Aspal Cair (Manual) ..................................................................................................................................... 179
2.01.02.01.07.024 Bahan Laston Lapis Aus (AC-WC) (Manual) ...................................................................................................................... 179
vi
2.01.02.01.07.025 Bahan Laston Lapis Antara (AC-BC) (Manual) ................................................................................................................. 179
2.01.02.01.08 PEKERJAAN STRUKTUR ........................................................................................................................................................................... 180
2.01.02.01.08.001 Beton Mutu Tinggi Fc'=45 Mpa............................................................................................................................................... 180
2.01.02.01.08.002 Beton Mutu Tinggi Fc'=35 Mpa............................................................................................................................................... 180
2.01.02.01.08.003 Beton Mutu Sedang Fc'=30 Mpa ............................................................................................................................................. 180
2.01.02.01.08.004 Beton Mutu Sedang Fc'=25 Mpa ............................................................................................................................................. 181
2.01.02.01.08.005 Beton Mutu Sedang Fc'=20 Mpa ............................................................................................................................................. 181
2.01.02.01.08.006 Beton Mutu Rendah Fc'=15 Mpa ............................................................................................................................................ 181
2.01.02.01.08.007 Beton Siklop Fc'=15 Mpa........................................................................................................................................................... 182
2.01.02.01.08.008 Beton Mutu Rendah Fc'=10 Mpa ............................................................................................................................................ 182
2.01.02.01.09 PEKERJAAN BAHAN AGREGAT UNTUK PEKERJAAN MINOR .................................................................................................... 182
2.01.02.01.09.001 Pekerjaan Lapis Pondasi Agregat Kelas A untuk Pekerjaan
Minor ................................................................................................................................................................................................. 182
2.01.02.01.09.002 Pekerjaan Lapis Pondasi Agregat Kelas B untuk Pekerjaan Minor........................................................................... 183
2.01.02.01.09.003 Agregat Lapis Pondasi Jalan Tanpa Penutup Aspal untuk
Pekerjaan Minor ........................................................................................................................................................................... 183
2.01.02.01.09.004 Pekerjaan Waterbound Macadam untuk Pekerjaan Minor ......................................................................................... 183
2.01.02.01.09.005 Pekerjaan Lapis Pondasi Agregat Kelas S untuk Pekerjaan
Minor ................................................................................................................................................................................................. 184
2.01.02.01.09.006 Pekerjaan Campuran Aspal Panas untuk Pekerjaan Minor ......................................................................................... 184
2.01.02.01.09.007 Pekerjaan Penetrasi Macadam untuk Pekerjaan Minor ................................................................................................ 184
2.01.02.01.09.008 Pekerjaan Campuran Aspal Dingin untuk Pekerjaan Minor........................................................................................ 185
2.01.02.01.09.009 Bahan Residu Bitumen untuk Pekerjaan Minor ............................................................................................................... 185
2.01.02.01.09.010 Pekerjaan Pemasangan Patok Pengarah ............................................................................................................................. 185
2.01.02.01.09.011 Pekerjaan Pemasangan Patok Kilometer ............................................................................................................................ 185
2.01.02.01.09.012 Pekerjaan Pemasangan Patok Hektometer ........................................................................................................................ 186
2.01.02.01.09.013 Pekerjaan Pemasangan Paku Jalan (Solar Road Stud)................................................................................................... 186
2.01.02.02 PEKERJAAN PENGAIRAN................................................................................................................................................................................ 187
2.01.02.02.02 PEKERJAAN PENGERUKAN DAN GALIAN ......................................................................................................................................... 187
2.01.02.02.02.002 Pekerjaan Pengerukan Saluran (Alat Berat) ..................................................................................................................... 187
2.01.02.02.02.003 Pekerjaan Galian Tanah Berbatu (Semi-Mechanic) ........................................................................................................ 187
2.01.02.02.02.004 Pekerjaan Galian Batu (Semi-Mechanic)............................................................................................................................. 187
2.01.02.02.02.005 Pekerjaan Galian Tanah Cadas (Semi-Mechanic) ............................................................................................................ 187
2.01.02.02.02.006 Pekerjaan Galian Lumpur (Semi-Mechanic)...................................................................................................................... 187
2.01.02.02.02.007 Pekerjaan Sumur Bor Chasing 2.5 " ...................................................................................................................................... 188
2.01.02.02.02.008 Pekerjaan Sumur Bor Chasing 3" ........................................................................................................................................... 188
2.01.02.02.04 PEKERJAAN CERUCUK DAN TURAP .................................................................................................................................................... 188
2.01.02.02.04.006 Pekerjaan Pemasangan Turap Bambu Tinggi 1,5 m....................................................................................................... 188
2.01.02.02.04.007 Pekerjaan Pemasangan Turap Bambu Tinggi 2,75 m .................................................................................................... 189
2.01.02.02.04.008 Pekerjaan Pemancangan Tiang Pancang 30/30............................................................................................................... 189
2.02 HSPK FISIK NON KONSTRUKSI................................................................................................................................................................................. 189
2.02.03 SARANA DAN PRASARANA KOTA ..................................................................................................................................................................... 189
2.02.03.01 PEKERJAAN PENERANGAN JALAN UMUM .............................................................................................................................................. 189
2.02.03.01.01 PEKERJAAN ELEKTRIKAL DAN PENERANGAN JALAN UMUM
(PJU) .................................................................................................................................................................................................. 189
2.02.03.01.01.004 Pekerjaan Pemasangan Konektor Kabel ............................................................................................................................. 189
2.02.03.01.01.005 Pekerjaan Penarikan Kabel ...................................................................................................................................................... 189
2.02.03.01.01.006 Pekerjaan Penarikan Kabel Bawah Tanah (Bore Machine) ......................................................................................... 190
2.02.03.01.01.007 Pekerjaan Pemasangan Panel Meter/Panel Lampu PJU ............................................................................................... 190
2.02.03.01.01.008 Pekerjaan Pemasangan Pipa untuk Kabel Tanam ........................................................................................................... 190
2.02.03.01.01.015 Pekerjaan Instalasi Tarikan Kabel Udara ........................................................................................................................... 190
2.02.03.01.01.020 Roll Pipa 1,5 inch .......................................................................................................................................................................... 190
2.02.03.01.01.021 Roll Pipa 2 inch ............................................................................................................................................................................. 191
2.02.03.01.01.022 Roll Pipa 3 inch ............................................................................................................................................................................. 191
2.02.03.01.01.023 Roll Pipa 4 inch ............................................................................................................................................................................. 191
2.02.03.01.01.024 Pekerjaan Pemasangan Ornamen Tiang Panjang 1,5 m................................................................................................ 191
2.02.03.01.01.025 Pekerjaan Pemasangan Ornamen Tiang Panjang 2 m ................................................................................................... 192
2.02.03.01.01.026 Pekerjaan Pemasangan Ornamen Tiang Panjang 3 m ................................................................................................... 192
2.02.03.01.01.027 Pekerjaan Pemasangan Ornamen Tiang Panjang 6 m ................................................................................................... 192
2.02.03.01.01.028 Pekerjaan Pemasangan Panel Lampu PJU 1 Phase 4400 VA ....................................................................................... 192
2.02.03.01.01.029 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 6600 VA ....................................................................................... 193
2.02.03.01.01.030 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 10600 VA .................................................................................... 193
2.02.03.01.01.031 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 13200 VA .................................................................................... 194
2.02.03.01.01.032 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 16500 VA .................................................................................... 194
2.02.03.01.01.033 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 23000 VA .................................................................................... 195
2.02.03.01.01.034 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 33000 VA .................................................................................... 195
2.02.03.01.01.035 Pekerjaan Pengecatan Tiang PJU ........................................................................................................................................... 196
vii
2.02.03.01.01.036 Pekerjaan Pemasangan Tiang Biasa 5 m Cabang 1 ......................................................................................................... 196
2.02.03.01.01.037 Pekerjaan Pemasangan Tiang Biasa 7 m Cabang 1 ......................................................................................................... 196
2.02.03.01.01.038 Pekerjaan Pemasangan Tiang Biasa 5 m Cabang 2 ......................................................................................................... 197
2.02.03.01.01.039 Pekerjaan Pemasangan Tiang Biasa 7 m Cabang 2 ......................................................................................................... 197
2.02.03.01.01.040 Pekerjaan Pemasangan Tiang Biasa 7 m Cabang 4 ......................................................................................................... 197
2.02.03.01.01.041 Pekerjaan Pondasi Biasa PJU ................................................................................................................................................... 197
2.02.03.01.01.042 Pekerjaan Pondasi Strouss PJU ............................................................................................................................................... 198
2.02.03.01.01.043 Pekerjaan Pemasangan Tiang Oktagonal 5 m Single HDG ........................................................................................... 198
2.02.03.01.01.044 Pekerjaan Pemasangan Tiang Oktagonal 5 m Double HDG ......................................................................................... 198
2.02.03.01.01.045 Pekerjaan Pemasangan Tiang Oktagonal 7 m Single HDG ........................................................................................... 199
2.02.03.01.01.046 Pekerjaan Pemasangan Tiang Oktagonal 7 m Double HDG ......................................................................................... 199
2.02.03.01.01.047 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 5 m Cabang 1 ............................................................. 199
2.02.03.01.01.048 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 5 m Cabang 2 ............................................................. 200
2.02.03.01.01.049 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Cabang 1 ............................................................. 200
2.02.03.01.01.050 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Cabang 2 ............................................................. 200
2.02.03.01.01.051 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Cabang 4 ............................................................. 201
2.02.03.01.01.052 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Dekoratif............................................................. 201
2.02.03.01.01.053 Pemasangan Lampu HPS 150W/220V Lengkap .............................................................................................................. 202
2.02.03.01.01.054 Pemasangan Lampu HPS 250W/220V Lengkap .............................................................................................................. 202
2.02.03.01.01.055 Pemasangan Lampu HPS 400W/220V Lengkap .............................................................................................................. 202
2.02.03.01.01.056 Pemasangan Lampu LED 150W/220V Lengkap .............................................................................................................. 203
2.02.03.01.01.058 Pemasangan Lampu Mercury HPLN 150W/220V Lengkap ........................................................................................ 203
2.02.03.01.01.059 Pemasangan Lampu Mercury HPLN 250W/220V Lengkap ........................................................................................ 203
2.02.03.02 PEKERJAAN SARANA LALU LINTAS........................................................................................................................................................... 203
2.02.03.02.01 PEKERJAAN RAMBU RAMBU LALU LINTAS ..................................................................................................................................... 203
2.02.03.02.01.009 Pekerjaan Pemasangan Lampu Jalan Bulat (Tampered) .............................................................................................. 203
2.02.03.02.01.010 Pekerjaan Pemasangan Lampu Jalan Alumunium Solar Stud ..................................................................................... 204
2.02.03.02.01.014 Pekerjaan Cat Besi ....................................................................................................................................................................... 204
2.02.03.02.01.016 Pekerjaan Pengecatan Marka Jalan (Manual) ................................................................................................................... 204
2.02.03.02.01.017 Pekerjaan Marka Jalan Thermoplastic ................................................................................................................................. 204
2.02.03.02.01.018 Pekerjaan Marka Jalan Coldplastic ........................................................................................................................................ 205
2.02.03.02.01.044 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 90 cm .................................................................................... 205
2.02.03.02.01.045 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 75 cm .................................................................................... 205
2.02.03.02.01.046 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 60 cm .................................................................................... 206
2.02.03.02.01.047 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 45 cm .................................................................................... 206
2.02.03.03 PEKERJAAN TAMAN DAN KEBERSIHAN .................................................................................................................................................. 206
2.02.03.03.01 PEKERJAAN TAMAN ................................................................................................................................................................................... 206
2.02.03.03.01.030 Penanaman Rumput Taman .................................................................................................................................................... 206
2.02.03.03.01.031 Penanaman Semak Hias............................................................................................................................................................. 206
2.02.03.03.01.032 Penanaman Pohon Diameter > 15 cm Batang Tunggal ................................................................................................. 207
2.02.03.03.01.036 Penanaman Pohon Diameter < 15 cm Batang Tunggal ................................................................................................. 207
2.02.03.03.01.033 Penyiapan Media Tanam ........................................................................................................................................................... 207
2.02.03.03.01.034 Pekerjaan Pasangan Batu Refleksi ........................................................................................................................................ 207
2.02.03.03.01.035 Pekerjaan Pasangan Lantai Batu Andesit ........................................................................................................................... 208
REKAP ASB FISIK.......................................................................................................................................................................................................................... 209
ASB FISIK ......................................................................................................................................................................................................................................... 212
3.01 ASB FISIK ............................................................................................................................................................................................................................ 212
3.01.01.01.01 BANGUNAN GEDUNG DAN RUMAH NEGARA .................................................................................................................................. 212
3.01.01.01.01.001 Pembangunan Gedung Negara Sederhana ......................................................................................................................... 212
3.01.01.01.01.002 Pembangunan Gedung Negara Tidak Sederhana ............................................................................................................ 213
3.01.01.01.01.003 Pembangunan Rumah Negara - Type A ............................................................................................................................... 215
3.01.01.01.01.004 Pembangunan Rumah Negara - Type B ............................................................................................................................... 216
3.01.01.01.01.005 Pembangunan Rumah Negara - Type C ............................................................................................................................... 218
3.01.01.01.01.008 Pekerjaan Pagar Bata Expose Desain Majapahit Tinggi 1.5 m, Tebal 1 Bata ........................................................ 219
3.01.01.01.01.009 Pekerjaan Pagar Bata Expose Desain Majapahit Tinggi 2 m, Tebal 1 Bata ............................................................ 219
3.01.02.01.01 DRAINASE DAN SALURAN ....................................................................................................................................................................... 219
3.01.02.01.01.001 Pekerjaan Saluran U-ditch 30.40.120 Gandar 5 Ton ..................................................................................................... 219
3.01.02.01.01.002 Pekerjaan Saluran U-ditch 40.50.120 Gandar 5 Ton ..................................................................................................... 220
3.01.02.01.01.003 Pekerjaan Saluran U-ditch 40.60.120 Gandar 5 Ton ..................................................................................................... 220
3.01.02.01.01.004 Pekerjaan Saluran U-ditch 50.50.120 Gandar 5 Ton ..................................................................................................... 220
3.01.02.01.01.005 Pekerjaan Saluran U-ditch 50.60.120 Gandar 5 Ton ..................................................................................................... 220
3.01.02.01.01.006 Pekerjaan Saluran U-ditch 50.70.120 Gandar 5 Ton ..................................................................................................... 220
3.01.02.01.01.007 Pekerjaan Saluran U-ditch 60.60.120 Gandar 5 Ton ..................................................................................................... 220
3.01.02.01.01.008 Pekerjaan Saluran U-ditch 60.70.120 Gandar 5 Ton ..................................................................................................... 220
3.01.02.01.01.009 Pekerjaan Saluran U-ditch 60.80.120 Gandar 5 Ton ..................................................................................................... 221
3.01.02.01.01.010 Pekerjaan Saluran U-ditch 80.80.120 Gandar 5 Ton ..................................................................................................... 221
3.01.02.01.01.011 Pekerjaan Saluran U-ditch 80.100.120 Gandar 5 Ton .................................................................................................. 221
viii
3.01.02.01.01.012 Pekerjaan Saluran U-ditch 40.60.120 Gandar 10 Ton .................................................................................................. 221
3.01.02.01.01.013 Pekerjaan Saluran U-ditch 50.50.120 Gandar 10 Ton .................................................................................................. 221
3.01.02.01.01.014 Pekerjaan Saluran U-ditch 50.60.120 Gandar 10 Ton .................................................................................................. 221
3.01.02.01.01.015 Pekerjaan Saluran U-ditch 50.70.120 Gandar 10 Ton .................................................................................................. 221
3.01.02.01.01.016 Pekerjaan Saluran U-ditch 60.60.120 Gandar 10 Ton .................................................................................................. 221
3.01.02.01.01.017 Pekerjaan Saluran U-ditch 60.70.120 Gandar 10 Ton .................................................................................................. 222
3.01.02.01.01.018 Pekerjaan Saluran U-ditch 60.80.120 Gandar 10 Ton .................................................................................................. 222
3.01.02.01.01.019 Pekerjaan Saluran U-ditch 80.80.120 Gandar 10 Ton .................................................................................................. 222
3.01.02.01.01.020 Pekerjaan Saluran U-ditch 80.100.120 Gandar 10 Ton................................................................................................ 222
3.01.02.01.01.021 Pekerjaan Saluran U-ditch 100.120.120 Gandar 10 Ton ............................................................................................. 222
3.01.02.01.01.022 Pekerjaan Saluran U-ditch 80.100.120 Gandar 20 Ton................................................................................................ 222
3.01.02.01.01.023 Pekerjaan Saluran U-ditch 100.120.120 Gandar 20 Ton ............................................................................................. 222
3.01.02.01.01.024 Pekerjaan Cover U-ditch 30.8.120 Gandar 5 Ton ........................................................................................................... 223
3.01.02.01.01.025 Pekerjaan Cover U-ditch 40.10.120 Gandar 5 Ton......................................................................................................... 223
3.01.02.01.01.026 Pekerjaan Cover U-ditch 40.12.120 Gandar 10 Ton ...................................................................................................... 223
3.01.02.01.01.027 Pekerjaan Cover U-ditch 50.10.120 Gandar 5 Ton......................................................................................................... 223
3.01.02.01.01.028 Pekerjaan Cover U-ditch 50.12.120 Gandar 10 Ton ...................................................................................................... 223
3.01.02.01.01.029 Pekerjaan Cover U-ditch 60.12.120 Gandar 5 Ton......................................................................................................... 223
3.01.02.01.01.030 Pekerjaan Cover U-ditch 60.14.120 Gandar 10 Ton ...................................................................................................... 223
3.01.02.01.01.031 Pekerjaan Cover U-ditch 80.10.120 Gandar 5 Ton......................................................................................................... 223
3.01.02.01.01.032 Pekerjaan Cover U-ditch 80.12.120 Gandar 10 Ton ...................................................................................................... 223
3.01.02.01.01.033 Pekerjaan Cover U-ditch 80.15.120 Gandar 20 Ton ...................................................................................................... 223
3.01.02.01.01.034 Pekerjaan Cover U-ditch 100.12.120 Gandar 10 Ton ................................................................................................... 223
3.01.02.01.01.035 Pekerjaan Cover U-ditch 100.15.120 Gandar 20 Ton ................................................................................................... 223
3.01.02.01.01.036 Pekerjaan Saluran Box Culvert 100/100 Gandar 20 Ton............................................................................................ 223
3.01.02.01.01.037 Pekerjaan Saluran Box Culvert 200/200 Gandar 20 Ton............................................................................................ 223
3.01.02.01.01.038 Pekerjaan Saluran Box Culvert 250/250 Gandar 20 Ton............................................................................................ 224
3.01.02.01.01.039 Pekerjaan Saluran Box Culvert 400/200 Gandar 20 Ton............................................................................................ 224
3.01.02.01.01.040 Pekerjaan Saluran Batu Kali 40/60 + Tutup Precast ..................................................................................................... 224
3.01.02.01.01.041 Pekerjaan Saluran Batu Kali 60/80 + Tutup Precast ..................................................................................................... 224
3.01.02.01.01.042 Pekerjaan Saluran Batu Kali 80/100 + Tutup Precast ................................................................................................... 224
3.01.02.01.01.043 Pekerjaan Saluran Batu Kali 100/120 + Tutup Precast ................................................................................................ 224
3.01.02.01.01.044 Pekerjaan Pembuatan Lubang Biopori Sedalam 1 m ..................................................................................................... 225
3.01.02.01.01.045 Pekerjaan Pembuatan Lubang Biopori Sedalam 2 m ..................................................................................................... 225
3.01.02.01.01.046 Pekerjaan Pembuatan Sumur Resapan Sedalam 3 m + Tutup
Plat ..................................................................................................................................................................................................... 225
3.01.02.01.01.047 Pekerjaan Saluran Buis Beton Ø 30....................................................................................................................................... 225
3.01.02.01.01.048 Pekerjaan Saluran Buis Beton Ø 40....................................................................................................................................... 225
3.01.02.01.01.049 Pekerjaan Saluran Buis Beton Ø 50....................................................................................................................................... 225
3.01.02.01.01.050 Pekerjaan Saluran Buis Beton Ø 60....................................................................................................................................... 225
3.01.02.01.01.051 Pekerjaan Saluran Buis Beton Ø 80....................................................................................................................................... 226
3.01.02.01.01.052 Pekerjaan Saluran Buis Beton Ø 100 .................................................................................................................................... 226
3.01.02.02.01 JALAN DAN KELENGKAPAN LALU LINTAS ....................................................................................................................................... 226
3.01.02.02.01.001 Pekerjaan Perkerasan Jalan Beton (Rigid Pavement).................................................................................................... 226
3.01.02.02.01.002 Pembangunan Halte / Shelter Angkutan Umum.............................................................................................................. 226
3.01.02.02.01.003 Pemasangan PJU Cabang 1 Lampu LED 150W/220V .................................................................................................... 227
3.01.02.02.01.004 Pemasangan PJU Cabang 2 Lampu LED 150W/220V .................................................................................................... 227
3.01.02.02.01.005 Pekerjaan Pemasangan Lampu Peringatan (Warning Light) Tiang Lengkung + Solar Cell ............................ 227
3.01.02.02.01.006 Pekerjaan Pemasangan Lampu Peringatan (Warning Light) Tiang
L + Solar Cell................................................................................................................................................................................... 227
3.01.02.02.01.012 Pekerjaan Pemasangan Rambu Lalu Lintas 90 cm.......................................................................................................... 228
3.01.02.02.01.011 Pekerjaan Pemasangan Rambu Lalu Lintas 75 cm.......................................................................................................... 228
3.01.02.02.01.010 Pekerjaan Pemasangan Rambu Lalu Lintas 60 cm.......................................................................................................... 228
3.01.02.02.01.009 Pekerjaan Pemasangan Rambu Lalu Lintas 45 cm.......................................................................................................... 228
3.01.02.02.01.013 Pekerjaan Pemasangan Pagar Pengamanan Jalan (Terminal End Fish Tail) - Panjang 4 m ........................... 228
3.01.02.02.01.024 Pekerjaan Pemasangan Pagar Pengamanan Jalan (Terminal End Buffer) - Panjang 4 m ................................ 228
3.01.02.02.01.014 Pekerjaan Lataston Lapis Aus (HRS-WC) ........................................................................................................................... 229
3.01.02.02.01.015 Pekerjaan Lataston Lapis Perata (HRS-WC L) .................................................................................................................. 229
3.01.02.02.01.016 Pekerjaan Lataston Lapis Pondasi (HRS-BASE) ............................................................................................................... 229
3.01.02.02.01.017 Pekerjaan Lataston Lapis Pondasi Perata (HRS-BASE L) ............................................................................................. 229
3.01.02.02.01.018 Pekerjaan Laston Lapis Aus (AC-WC) .................................................................................................................................. 229
3.01.02.02.01.019 Pekerjaan Laston Lapis Aus Perata (AC-WC L) ................................................................................................................ 229
3.01.02.02.01.020 Pekerjaan Laston Lapis Antara (AC-BC) ............................................................................................................................. 229
3.01.02.02.01.021 Pekerjaan Laston Lapis Antara Perata (AC-BC L) ............................................................................................................ 229
3.01.02.02.01.022 Pekerjaan Laston Lapis Pondasi (AC-BASE) ...................................................................................................................... 229
3.01.02.02.01.023 Pekerjaan Laston Lapis Pondasi Perata(AC-BASE L) ..................................................................................................... 229
3.01.02.02.01.025 Pekerjaan Pemasangan Patok Pengaman (Delineator)................................................................................................. 229
ix
3.01.02.02.01.026 Pekerjaan Pemasangan Cermin Tikungan.......................................................................................................................... 229
3.01.02.02.01.027 Pekerjaan Pemasangan RPPJ 120 x 180 (Overhead) ..................................................................................................... 229
3.01.02.02.01.028 Pekerjaan Pemasangan RPPJ 120 x 240 (Overhead) ..................................................................................................... 230
3.01.02.02.01.029 Pekerjaan Pemasangan ATCS 3 Simpang............................................................................................................................ 230
3.01.02.02.01.030 Pekerjaan Pemasangan ATCS 4 Simpang............................................................................................................................ 230
3.01.02.02.01.031 Pekerjaan Overlay Jalan (Manual) ......................................................................................................................................... 230
3.01.02.03.01 ELEKTRIKAL DAN INSTALASI JARINGAN ......................................................................................................................................... 230
3.01.02.03.01.001 Pekerjaan Pemasangan Kabel NYFGBY 4 x 2.5 mm ........................................................................................................ 230
3.01.02.03.01.002 Pekerjaan Pemasangan Kabel NYFGBY 4 x 4 mm ........................................................................................................... 230
3.01.02.03.01.003 Pekerjaan Pemasangan Kabel NYFGBY 4 x 6 mm ........................................................................................................... 230
3.01.02.03.01.004 Pekerjaan Pemasangan Kabel NYFGBY 4 x 10 mm ......................................................................................................... 230
3.01.02.03.01.005 Pekerjaan Pemasangan Kabel NYFGBY 4 x 16 mm ......................................................................................................... 231
3.01.02.03.01.006 Pekerjaan Pemasangan Kabel NYY 4 x 2.5 mm ................................................................................................................ 231
3.01.02.03.01.007 Pekerjaan Pemasangan Kabel NYY 4 x 4 mm .................................................................................................................... 231
3.01.02.03.01.008 Pekerjaan Pemasangan Kabel NYY 4 x 6 mm .................................................................................................................... 231
3.01.02.03.01.009 Pekerjaan Pemasangan Kabel NYY 4 x 10 mm ................................................................................................................. 231
3.01.02.03.01.010 Pekerjaan Pemasangan Kabel NYY 4 x 16 mm ................................................................................................................. 231
3.01.02.03.01.011 Pekerjaan Pemasangan Kabel NYY 4 x 25 mm ................................................................................................................. 231
3.01.02.03.01.012 Pekerjaan Pemasangan Kabel NYY 4 x 35 mm ................................................................................................................. 231
3.01.02.03.01.013 Pekerjaan Pemasangan Kabel NYM 2 x 1.5 mm ............................................................................................................... 231
3.01.02.03.01.014 Pekerjaan Pemasangan Kabel NYM 2 x 2.5 mm ............................................................................................................... 231
3.01.02.03.01.015 Pekerjaan Pemasangan Kabel Twisted 2 x 10 mm ......................................................................................................... 232
3.01.02.03.01.016 Pekerjaan Pemasangan Kabel Twisted 2 x 16 mm ......................................................................................................... 232
3.01.02.03.01.017 Pekerjaan Pemasangan Kabel Twisted 4 x 16 mm ......................................................................................................... 232
3.01.02.04.01 BANGUNAN MASYARAKAT DAN LINGKUNGAN ............................................................................................................................. 232
3.01.02.04.01.001 Septictank Pasasangan Bata Kapasitas 3 m3 + Rembesan........................................................................................... 232
3.01.02.04.01.002 Septictank Pasasangan Bata Kapasitas 6 m3 + Rembesan........................................................................................... 232
3.01.02.04.01.003 Pemasangan Pipa Saluran Air Bersih Ø 4" ......................................................................................................................... 232
3.01.02.04.01.004 Pemasangan IPAL Komunal Panjang 7 m, Diameter 3 m ............................................................................................. 233
3.01.02.04.01.005 Pemasangan Septictank Komunal Tinggi 3.5 m, Diameter 2 m ................................................................................. 234
3.01.02.04.01.007 Pekerjaan Pembuatan Taman Aktif ...................................................................................................................................... 235
3.01.02.04.01.011 Pekerjaan Pembuatan Trotoar dengan Tegel Batu Ampyang..................................................................................... 235
REKAP ASB NON FISIK 236
ASB NON FISIK .............................................................................................................................................................................................................................. 237
3.02 ASB NON FISIK 237
3.02.01 ANALISIS STANDAR BELANJA NON FISIK ....................................................................................................................................................... 237
3.02.01.01 KEGIATAN PERENCANAAN ........................................................................................................................................................................... 237
3.02.01.01.01 PENELITIAN/KAJIAN ................................................................................................................................................................................. 237
3.02.01.01.01.001 Kegiatan Penelitian / Kajian Tipe 1 ...................................................................................................................................... 237
3.02.01.01.01.002 Kegiatan Penelitian / Kajian Tipe 2 ...................................................................................................................................... 237
3.02.01.01.02.001 Kegiatan Penyusunan Rumusan Kebijakan Tipe 1.......................................................................................................... 237
3.02.01.01.02.002 Kegiatan Penyusunan Rumusan Kebijakan Tipe 2.......................................................................................................... 238
3.02.01.02 KEGIATAN PELAKSANAAN ............................................................................................................................................................................ 238
3.02.01.02.01 KEGIATAN SOSIALISASI / PENYULUHAN ......................................................................................................................................... 238
3.02.01.02.01.001 Kegiatan Sosialisasi / Penyuluhan Tipe 1........................................................................................................................... 238
3.02.01.02.01.004 Kegiatan Sosialisasi / Penyuluhan Tipe 1........................................................................................................................... 239
3.02.01.02.01.002 Kegiatan Sosialisasi / Penyuluhan Tipe 2........................................................................................................................... 239
3.02.01.02.01.005 Kegiatan Sosialisasi / Penyuluhan Tipe 2........................................................................................................................... 241
3.02.01.02.01.003 Kegiatan Sosialisasi / Penyuluhan Tipe 3........................................................................................................................... 242
3.02.01.02.01.006 Kegiatan Sosialisasi / Penyuluhan Tipe 3........................................................................................................................... 242
3.02.01.02.02 Kegiatan Pelatihan / Bimtek / Workshop.......................................................................................................................................... 243
3.02.01.02.02.001 Kegiatan Pelatihan / Bimtek / Workshop Tipe 1 ............................................................................................................ 243
3.02.01.02.02.002 Kegiatan Pelatihan / Bimtek / Workshop Tipe 2 ............................................................................................................ 244
3.02.01.02.02.005 Kegiatan Pelatihan / Bimtek / Workshop Tipe 2 ............................................................................................................ 245
3.02.01.02.02.003 Kegiatan Pelatihan / Bimtek / Workshop Tipe 3 ............................................................................................................ 245
3.02.01.02.02.004 Kegiatan Pelatihan / Bimtek / Workshop Tipe 4 ............................................................................................................ 246
3.02.01.02.02.006 Kegiatan Pelatihan / Bimtek / Workshop Tipe 4 ............................................................................................................ 247
3.02.01.02.03 Kegiatan Pagelaran / Festival / Pawai ................................................................................................................................................ 247
3.02.01.02.03.001 Kegiatan Pagelaran / Festival / Pawai Tipe 1 ................................................................................................................... 247
3.02.01.02.03.002 Kegiatan Pagelaran / Festival / Pawai Tipe 2 ................................................................................................................... 248
3.02.01.02.03.003 Kegiatan Pagelaran / Festival / Pawai Tipe 3 ................................................................................................................... 249
3.02.01.02.04 Kegiatan Pameran / Expo......................................................................................................................................................................... 249
3.02.01.02.04.001 Kegiatan Pameran / Expo Tipe 1 ........................................................................................................................................... 249
3.02.01.02.04.002 Kegiatan Pameran / Expo Tipe 2 ........................................................................................................................................... 250
3.02.01.02.04.003 Kegiatan Pameran / Expo Tipe 3 ........................................................................................................................................... 250
3.02.01.02.04.004 Kegiatan Pameran / Expo Tipe 4 ........................................................................................................................................... 251
3.02.01.02.05 Kegiatan Lomba ........................................................................................................................................................................................... 251
x
3.02.01.02.05.001 Kegiatan Lomba Tipe 1 .............................................................................................................................................................. 251
3.02.01.02.05.002 Kegiatan Lomba Tipe 2 .............................................................................................................................................................. 252
3.02.01.02.05.003 Kegiatan Lomba Tipe 3 .............................................................................................................................................................. 252

xi
PEMERINTAH KOTA
MOJOKERTO

um
m
U
ya
ia
U
rB
S B
a
nd
S
ta

TAHUN ANGGARAN
2020
KODE BARANG NAMA BARANG SPESIFIKASI SATUAN BIAYA
(a) (b) (c) (d) (e)
1.10 Standart Biaya Umum
1.10.28 Satuan Honorarium, Upah/Jasa, Biaya Operasional
1.10.28.01 Honorarium Umum
1.10.28.01.01 Honorarium Penanggungjawab Pengelola Keuangan/Pengelola Barang
1.10.28.01.01.001 Honorarium Penanggung Jawab Pengelola/Pengguna Barang
1.10.28.01.01.001.001 Pemegang Kekuasaan Pengelola BMD Walikota OB 2,500,000
1.10.28.01.01.001.002 Pengelola Barang Sekda OB 2,000,000
1.10.28.01.01.001.003 Pejabat Penatausahaan Barang PPKD OB 1,500,000
1.10.28.01.01.001.004 Pengurus Barang Pengelola PPKD OB 950,000
1.10.28.01.01.001.005 Pengguna Barang Kepala OPD OB 1,000,000
Honorarium Penanggung Jawab Pengelola
1.10.28.01.01.001.006 Pembantu Pengurus Barang Pengelola OB 850,000
Barang
Honorarium Penanggung Jawab Pengguna
1.10.28.01.01.001.007 Pembantu Pengurus Barang Pengguna OB 400,000
Barang
1.10.28.01.01.001.008 Pengurus Barang Pembantu UPT OB 300,000

1.10.28.01.01.002 Honorarium Pejabat Pengelola Keuangan Daerah (PPKD) / Pejabat Penatausahaan

Honorarium Pejabat Pengelola Keuangan


1.10.28.01.01.002.001 PPKD/PPB Daerah (PPKD) / Pejabat Penatausahaan OB 1,875,000
Barang
1.10.28.01.01.002.002 Pemegang Kekuasaan Pengelola BMD Walikota OB 30,950,000
1.10.28.01.01.002.003 Pengelola Barang Sekda OB 27,080,000
1.10.28.01.01.002.004 Pejabat Penatausahaan Barang PPKD OB 11,600,000
1.10.28.01.01.002.005 Pengurus Barang Pengelola PPKD OB 5,800,000

1.10.28.01.01.003 Honorarium Pengguna Anggaran/Pengguna Barang (PA/PB)

Honorarium Pengguna Anggaran/Pengguna


1.10.28.01.01.003.001 Nilai pagu dana sd. Rp. 100 juta OB 1,040,000
Barang (PA/PB)
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.003.002 OB 1,250,000
Barang (PA/PB) 250 juta
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.003.003 OB 1,450,000
Barang (PA/PB) 500 juta
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.003.004 OB 1,660,000
Barang (PA/PB) 1 miliar
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.003.005 OB 1,970,000
Barang (PA/PB) 2,5 miliar
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.003.006 OB 2,280,000
Barang (PA/PB) Rp. 5 miliar
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.003.007 OB 2,590,000
Barang (PA/PB) 10 miliar
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.003.008 OB 3,010,000
Barang (PA/PB) Rp. 25 miliar
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.003.009 OB 3,420,000
Barang (PA/PB) Rp. 50 miliar
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.003.010 OB 3,840,000
Barang (PA/PB) Rp.75 miliar
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp.75 miliar sd.
1.10.28.01.01.003.011 OB 4,250,000
Barang (PA/PB) Rp.100 miliar
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp.100 miliar sd.
1.10.28.01.01.003.012 OB 4,770,000
Barang (PA/PB) Rp. 250 miliar
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 250 miliar sd.
1.10.28.01.01.003.013 OB 5,290,000
Barang (PA/PB) Rp. 500 miliar

1
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 500 miliar sd.
1.10.28.01.01.003.014 OB 5,810,000
Barang (PA/PB) Rp. 750 miliar
Honorarium Pengguna Anggaran/Pengguna Nilai pagu dana di atas Rp. 750 miliar sd.
1.10.28.01.01.003.015 OB 6,330,000
Barang (PA/PB) Rp. 1 triliun
Honorarium Pengguna Anggaran/Pengguna
1.10.28.01.01.003.016 Nilai pagu dana di atas Rp. 1 triliun OB 7,370,000
Barang (PA/PB)

1.10.28.01.01.004 Honorarium Kuasa Pengguna Anggaran/Kuasa Pengguna Barang (KPA/KPB)

Honorarium Kuasa Pengguna


1.10.28.01.01.004.001 Anggaran/Kuasa Pengguna Barang Nilai pagu dana sd. Rp. 100 juta OB 1,040,000
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.004.002 Anggaran/Kuasa Pengguna Barang OB 1,250,000
250 juta
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.004.003 Anggaran/Kuasa Pengguna Barang OB 1,450,000
500 juta
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.004.004 Anggaran/Kuasa Pengguna Barang OB 1,660,000
1 miliar
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.004.005 Anggaran/Kuasa Pengguna Barang OB 1,970,000
2,5 miliar
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.004.006 Anggaran/Kuasa Pengguna Barang OB 2,280,000
Rp. 5 miliar
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.004.007 Anggaran/Kuasa Pengguna Barang OB 2,590,000
10 miliar
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.004.008 Anggaran/Kuasa Pengguna Barang OB 3,010,000
Rp. 25 miliar
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.004.009 Anggaran/Kuasa Pengguna Barang OB 3,420,000
Rp. 50 miliar
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.004.010 Anggaran/Kuasa Pengguna Barang OB 3,840,000
Rp.75 miliar
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp.75 miliar sd. Rp.
1.10.28.01.01.004.011 Anggaran/Kuasa Pengguna Barang OB 4,250,000
100 miliar
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp.100 miliar sd.
1.10.28.01.01.004.012 Anggaran/Kuasa Pengguna Barang OB 4,770,000
Rp. 250 miliar
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 250 miliar sd.
1.10.28.01.01.004.013 Anggaran/Kuasa Pengguna Barang OB 5,290,000
Rp. 500 miliar
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 500 miliar sd.
1.10.28.01.01.004.014 Anggaran/Kuasa Pengguna Barang OB 5,810,000
Rp. 750 miliar
(KPA/KPB)
Honorarium Kuasa Pengguna
Nilai pagu dana di atas Rp. 750 miliar sd.
1.10.28.01.01.004.015 Anggaran/Kuasa Pengguna Barang OB 6,330,000
Rp. 1 triliun
(KPA/KPB)

2
Honorarium Kuasa Pengguna
1.10.28.01.01.004.016 Anggaran/Kuasa Pengguna Barang Nilai pagu dana di atas Rp. 1 triliun OB 7,370,000
(KPA/KPB)
Honorarium Pejabat Pembuat Komitmen (PPK) - (Diberikan tiap bulan per paket pekerjaan selama masa pelaksanaan
1.10.28.01.01.005
pekerjaan)
Honorarium Pejabat Pembuat Komitmen
1.10.28.01.01.005.001 Nilai pagu dana sd. Rp. 100 juta OB 1,010,000
(PPK)
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.005.002 OB 1,210,000
(PPK) 250 juta
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.005.003 OB 1,410,000
(PPK) 500 juta
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.005.004 OB 1,610,000
(PPK) 1 miliar
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.005.005 OB 1,910,000
(PPK) 2,5 miliar
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.005.006 OB 2,210,000
(PPK) Rp. 5 miliar
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.005.007 OB 2,520,000
(PPK) 10 miliar
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.005.008 OB 2,920,000
(PPK) Rp. 25 miliar
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.005.009 OB 3,320,000
(PPK) Rp. 50 miliar
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.005.010 OB 3,720,000
(PPK) Rp.75 miliar
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp.75 miliar sd. Rp.
1.10.28.01.01.005.011 OB 4,130,000
(PPK) 100 miliar
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp.100 miliar sd.
1.10.28.01.01.005.012 OB 4,630,000
(PPK) Rp. 250 miliar
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 250 miliar sd.
1.10.28.01.01.005.013 OB 5,130,000
(PPK) Rp. 500 miliar
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 500 miliar sd.
1.10.28.01.01.005.014 OB 5,640,000
(PPK) Rp. 750 miliar
Honorarium Pejabat Pembuat Komitmen Nilai pagu dana di atas Rp. 750 miliar sd.
1.10.28.01.01.005.015 OB 6,140,000
(PPK) Rp. 1 triliun
Honorarium Pejabat Pembuat Komitmen
1.10.28.01.01.005.016 Nilai pagu dana di atas Rp. 1 triliun OB 7,140,000
(PPK)

1.10.28.01.01.006 Honorarium Pejabat Penguji Tagihan dan Penandatangan Surat Perintah Membayar

Honorarium Pejabat Penguji Tagihan dan


1.10.28.01.01.006.001 Nilai pagu dana sd. Rp. 100 juta OB 400,000
Penandatangan Surat Perintah Membayar
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.006.002 OB 480,000
Penandatangan Surat Perintah Membayar 250 juta
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.006.003 OB 570,000
Penandatangan Surat Perintah Membayar 500 juta
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.006.004 OB 660,000
Penandatangan Surat Perintah Membayar 1 miliar
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.006.005 OB 770,000
Penandatangan Surat Perintah Membayar 2,5 miliar
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.006.006 OB 880,000
Penandatangan Surat Perintah Membayar Rp. 5 miliar
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.006.007 OB 990,000
Penandatangan Surat Perintah Membayar 10 miliar
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.006.008 OB 1,250,000
Penandatangan Surat Perintah Membayar Rp. 25 miliar

3
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.006.009 OB 1,520,000
Penandatangan Surat Perintah Membayar Rp. 50 miliar
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.006.010 OB 1,780,000
Penandatangan Surat Perintah Membayar Rp.75 miliar
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp.75 miliar sd. Rp.
1.10.28.01.01.006.011 OB 2,040,000
Penandatangan Surat Perintah Membayar 100 miliar
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 100 miliar sd.
1.10.28.01.01.006.012 OB 2,440,000
Penandatangan Surat Perintah Membayar Rp. 250 miliar
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 250 miliar sd.
1.10.28.01.01.006.013 OB 2,830,000
Penandatangan Surat Perintah Membayar Rp. 500 miliar
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 500 miliar sd.
1.10.28.01.01.006.014 OB 3,230,000
Penandatangan Surat Perintah Membayar Rp. 750 miliar
Honorarium Pejabat Penguji Tagihan dan Nilai pagu dana di atas Rp. 750 miliar sd.
1.10.28.01.01.006.015 OB 3,620,000
Penandatangan Surat Perintah Membayar Rp. 1 triliun
Honorarium Pejabat Penguji Tagihan dan
1.10.28.01.01.006.016 Nilai pagu dana di atas Rp. 1 triliun OB 4,420,000
Penandatangan Surat Perintah Membayar
Honorarium Pejabat Pelaksana Teknis Kegiatan (PPTK) - (Diberikan tiap bulan per rekening kegiatan selama masa
1.10.28.01.01.007
pelaksanaan pekerjaan)
Honorarium Pejabat Pelaksana Teknis
1.10.28.01.01.007.001 Nilai pagu dana sd. Rp. 100 juta OK 462,500
Kegiatan (PPTK)
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.007.002 OK 575,000
Kegiatan (PPTK) 250 juta
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.007.003 OK 700,000
Kegiatan (PPTK) 500 juta
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.007.004 OK 812,500
Kegiatan (PPTK) 1 miliar
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.007.005 OK 900,000
Kegiatan (PPTK) 2,5 miliar
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.007.006 OK 1,037,500
Kegiatan (PPTK) Rp. 5 miliar
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.007.007 OK 1,187,500
Kegiatan (PPTK) 10 miliar
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.007.008 OK 1,487,500
Kegiatan (PPTK) Rp. 25 miliar
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.007.009 OK 1,887,500
Kegiatan (PPTK) Rp. 50 miliar
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.007.010 OK 2,237,500
Kegiatan (PPTK) Rp.75 miliar
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp.75 miliar sd. Rp.
1.10.28.01.01.007.011 OK 2,587,500
Kegiatan (PPTK) 100 miliar
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 100 miliar sd.
1.10.28.01.01.007.012 OK 3,112,500
Kegiatan (PPTK) Rp. 250 miliar
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 250 miliar sd.
1.10.28.01.01.007.013 OK 3,637,500
Kegiatan (PPTK) Rp. 500 miliar
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 500 miliar sd.
1.10.28.01.01.007.014 OK 4,162,500
Kegiatan (PPTK) Rp. 750 miliar
Honorarium Pejabat Pelaksana Teknis Nilai pagu dana di atas Rp. 750 miliar sd.
1.10.28.01.01.007.015 OK 4,625,000
Kegiatan (PPTK) Rp. 1 triliun
Honorarium Pejabat Pelaksana Teknis
1.10.28.01.01.007.016 Nilai pagu dana di atas Rp. 1 triliun OK 5,675,000
Kegiatan (PPTK)

1.10.28.01.01.008 Honorarium Pejabat Penatausahaan Keuangan (PPK-SKPD/PPK-PPKD)

Honorarium Pejabat Penatausahaan


1.10.28.01.01.008.001 Nilai pagu dana sd. Rp. 100 juta OB 250,000
Keuangan (PPK-SKPD/PPK-PPKD)

4
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.008.002 OB 300,000
Keuangan (PPK-SKPD/PPK-PPKD) 250 juta
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.008.003 OB 350,000
Keuangan (PPK-SKPD/PPK-PPKD) 500 juta
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.008.004 OB 400,000
Keuangan (PPK-SKPD/PPK-PPKD) 1 miliar
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.008.005 OB 500,000
Keuangan (PPK-SKPD/PPK-PPKD) 2,5 miliar
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.008.006 OB 550,000
Keuangan (PPK-SKPD/PPK-PPKD) Rp. 5 miliar
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.008.007 OB 625,000
Keuangan (PPK-SKPD/PPK-PPKD) 10 miliar
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.008.008 OB 800,000
Keuangan (PPK-SKPD/PPK-PPKD) Rp. 25 miliar
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.008.009 OB 950,000
Keuangan (PPK-SKPD/PPK-PPKD) Rp. 50 miliar
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.008.010 OB 1,125,000
Keuangan (PPK-SKPD/PPK-PPKD) Rp.75 miliar
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp.75 miliar sd. Rp.
1.10.28.01.01.008.011 OB 1,275,000
Keuangan (PPK-SKPD/PPK-PPKD) 100 miliar
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 100 miliar sd.
1.10.28.01.01.008.012 OB 1,525,000
Keuangan (PPK-SKPD/PPK-PPKD) Rp. 250 miliar
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 250 miliar sd.
1.10.28.01.01.008.013 OB 1,800,000
Keuangan (PPK-SKPD/PPK-PPKD) Rp. 500 miliar
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 500 miliar sd.
1.10.28.01.01.008.014 OB 2,000,000
Keuangan (PPK-SKPD/PPK-PPKD) Rp. 750 miliar
Honorarium Pejabat Penatausahaan Nilai pagu dana di atas Rp. 750 miliar sd.
1.10.28.01.01.008.015 OB 2,250,000
Keuangan (PPK-SKPD/PPK-PPKD) Rp. 1 triliun
Honorarium Pejabat Penatausahaan
1.10.28.01.01.008.016 Nilai pagu dana di atas Rp. 1 triliun OB 2,750,000
Keuangan (PPK-SKPD/PPK-PPKD)

1.10.28.01.01.009 Honorarium Bendahara Pengeluaran Pembantu

Honorarium Bendahara Pengeluaran


1.10.28.01.01.009.001 Nilai pagu dana sd. Rp. 100 juta OB 260,000
Pembantu
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.009.002 OB 310,000
Pembantu 250 juta
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.009.003 OB 370,000
Pembantu 500 juta
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.009.004 OB 430,000
Pembantu 1 miliar
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.009.005 OB 500,000
Pembantu 2,5 miliar
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.009.006 OB 570,000
Pembantu Rp. 5 miliar
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.009.007 OB 640,000
Pembantu 10 miliar
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.009.008 OB 810,000
Pembantu Rp. 25 miliar
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.009.009 OB 980,000
Pembantu Rp. 50 miliar
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.009.010 OB 1,150,000
Pembantu Rp.75 miliar
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp.75 miliar sd. Rp.
1.10.28.01.01.009.011 OB 1,330,000
Pembantu 100 miliar

5
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 100 miliar sd.
1.10.28.01.01.009.012 OB 1,580,000
Pembantu Rp. 250 miliar
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 250 miliar sd.
1.10.28.01.01.009.013 OB 1,840,000
Pembantu Rp. 500 miliar
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 500 miliar sd.
1.10.28.01.01.009.014 OB 2,090,000
Pembantu Rp. 750 miliar
Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 750 miliar sd.
1.10.28.01.01.009.015 OB 2,350,000
Pembantu Rp. 1 triliun
Honorarium Bendahara Pengeluaran
1.10.28.01.01.009.016 Nilai pagu dana di atas Rp. 1 triliun OB 2,860,000
Pembantu

1.10.28.01.01.010 Honorarium Staf Pengelola/Pembuat Dokumen/Pembantu Bendahara Pengeluaran

Honorarium Staf Pengelola/Pembuat


1.10.28.01.01.010.001 Nilai pagu dana sd. Rp. 100 juta OK 250,000
Dokumen/Pembantu Bendahara Pengeluaran

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.010.002 OK 300,000
Dokumen/Pembantu Bendahara Pengeluaran 250 juta

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.010.003 OK 362,500
Dokumen/Pembantu Bendahara Pengeluaran 500 juta

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.010.004 OK 425,000
Dokumen/Pembantu Bendahara Pengeluaran 1 miliar

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.010.005 OK 500,000
Dokumen/Pembantu Bendahara Pengeluaran 2,5 miliar

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.010.006 OK 562,500
Dokumen/Pembantu Bendahara Pengeluaran Rp. 5 miliar

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.010.007 OK 637,500
Dokumen/Pembantu Bendahara Pengeluaran 10 miliar

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.010.008 OK 800,000
Dokumen/Pembantu Bendahara Pengeluaran Rp. 25 miliar

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.010.009 OK 975,000
Dokumen/Pembantu Bendahara Pengeluaran Rp. 50 miliar

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.010.010 OK 1,150,000
Dokumen/Pembantu Bendahara Pengeluaran Rp.75 miliar

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp.75 miliar sd. Rp.
1.10.28.01.01.010.011 OK 1,325,000
Dokumen/Pembantu Bendahara Pengeluaran 100 miliar

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 100 miliar sd.
1.10.28.01.01.010.012 OK 1,575,000
Dokumen/Pembantu Bendahara Pengeluaran Rp. 250 miliar

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 250 miliar sd.
1.10.28.01.01.010.013 OK 1,837,500
Dokumen/Pembantu Bendahara Pengeluaran Rp. 500 miliar

Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 500 miliar sd.
1.10.28.01.01.010.014 OK 2,087,500
Dokumen/Pembantu Bendahara Pengeluaran Rp. 750 miliar

6
Honorarium Staf Pengelola/Pembuat Nilai pagu dana di atas Rp. 750 miliar sd.
1.10.28.01.01.010.015 OK 2,350,000
Dokumen/Pembantu Bendahara Pengeluaran Rp. 1 triliun

Honorarium Staf Pengelola/Pembuat


1.10.28.01.01.010.016 Nilai pagu dana di atas Rp. 1 triliun OK 2,850,000
Dokumen/Pembantu Bendahara Pengeluaran

1.10.28.01.01.011 Honorarium Bendahara Penerimaan


1.10.28.01.01.011.001 Honorarium Bendahara Penerimaan Target pendapatan sd. 500 juta OB 500,000
Target pendapatan diatas 500 juta sd. 1
1.10.28.01.01.011.002 Honorarium Bendahara Penerimaan OB 570,000
Miliar
Target pendapatan diatas 1 Milliar sd. 5
1.10.28.01.01.011.003 Honorarium Bendahara Penerimaan OB 730,000
Milliar
1.10.28.01.01.011.004 Honorarium Bendahara Penerimaan Target pendapatan diatas 5 Milliar OB 1,030,000
1.10.28.01.01.012 Honorarium Bendahara Penerimaan Pembantu

Honorarium Bendahara Penerimaan


1.10.28.01.01.012.001 Target pendapatan sd. 500 juta OB 156,300
Pembantu
Honorarium Bendahara Penerimaan Target pendapatan diatas 500 juta sd. 1
1.10.28.01.01.012.002 OB 218,800
Pembantu Miliar
Honorarium Bendahara Penerimaan Target pendapatan diatas 1 Milliar sd. 5
1.10.28.01.01.012.003 OB 312,500
Pembantu Milliar
Honorarium Bendahara Penerimaan
1.10.28.01.01.012.004 Target pendapatan diatas 5 Milliar OB 375,000
Pembantu
1.10.28.01.01.013 Honorarium Pengurus Gaji

1.10.28.01.01.013.001 Honorarium Pengurus Gaji Nilai pagu dana sd. Rp. 100 juta OB 340,000
Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.013.002 Honorarium Pengurus Gaji OB 420,000
250 juta
Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.013.003 Honorarium Pengurus Gaji OB 500,000
500 juta
Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.013.004 Honorarium Pengurus Gaji OB 570,000
1 miliar
Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.013.005 Honorarium Pengurus Gaji OB 670,000
2,5 miliar
Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.013.006 Honorarium Pengurus Gaji OB 770,000
Rp. 5 miliar
Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.013.007 Honorarium Pengurus Gaji OB 860,000
10 miliar
Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.013.008 Honorarium Pengurus Gaji OB 1,090,000
Rp. 25 miliar
Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.013.009 Honorarium Pengurus Gaji OB 1,320,000
Rp. 50 miliar
Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.013.010 Honorarium Pengurus Gaji OB 1,550,000
Rp.75 miliar
Nilai pagu dana di atas Rp.75 miliar sd. Rp.
1.10.28.01.01.013.011 Honorarium Pengurus Gaji OB 1,780,000
100 miliar
Nilai pagu dana di atas Rp. 100 miliar sd.
1.10.28.01.01.013.012 Honorarium Pengurus Gaji OB 2,120,000
Rp. 250 miliar
Nilai pagu dana di atas Rp. 250 miliar sd.
1.10.28.01.01.013.013 Honorarium Pengurus Gaji OB 2,470,000
Rp. 500 miliar
Nilai pagu dana di atas Rp. 500 miliar sd.
1.10.28.01.01.013.014 Honorarium Pengurus Gaji OB 2,810,000
Rp. 750 miliar
Nilai pagu dana di atas Rp. 750 miliar sd.
1.10.28.01.01.013.015 Honorarium Pengurus Gaji OB 3,160,000
Rp. 1 triliun
1.10.28.01.01.013.016 Honorarium Pengurus Gaji Nilai pagu dana di atas Rp. 1 triliun OB 3,840,000

7
Honorarium Direksi Lapangan/Pengawas Lapangan - (Diberikan tiap bulan per paket pekerjaan selama masa
1.10.28.01.01.014
pengawasan pekerjaan)

Honorarium Direksi Lapangan/Pengawas


1.10.28.01.01.014.001 Nilai pagu dana sd. Rp. 100 juta OB 312,500
Lapangan
Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.014.002 OB 437,500
Lapangan 250 juta
Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.014.003 OB 562,500
Lapangan 500 juta
Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.014.004 OB 687,500
Lapangan 1 miliar
Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.014.005 OB 750,000
Lapangan 2,5 miliar
Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.014.006 OB 875,000
Lapangan Rp. 5 miliar
Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.014.007 OB 1,000,000
Lapangan 10 miliar
Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.014.008 OB 1,125,000
Lapangan Rp. 25 miliar
Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.014.009 OB 1,250,000
Lapangan Rp. 50 miliar
Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.014.010 OB 1,750,000
Lapangan Rp.75 miliar
Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp.75 miliar sd. Rp.
1.10.28.01.01.014.011 OB 2,000,000
Lapangan 100 miliar
Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp. 100 miliar sd.
1.10.28.01.01.014.012 OB 2,500,000
Lapangan Rp. 250 miliar
1.10.28.01.01.014.013 Honorarium Direksi Lapangan/Pengawas Nilai pagu dana di atas Rp. 250 miliar sd. OB 3,125,000
1.10.28.01.01.015 Honorarium Pejabat Pemeriksa Hasil Pekerjaan

1.10.28.01.01.015.001 Pejabat Pemeriksa Hasil Pekerjaan (PjPHP) OB 450,000

1.10.28.01.01.016 Panitia Penerima Hasil Pekerjaan/Pengadaan Barang/Jasa

Panitia Penerima Hasil Pekerjaan/Pengadaan


1.10.28.01.01.016.001 OP 450,000
Barang/Jasa

1.10.28.01.01.017 Honorarium Bendahara Pengeluaran

1.10.28.01.01.008.001 Honorarium Bendahara Pengeluaran Nilai pagu dana sd. Rp. 100 juta OB 340,000
Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.008.002 Honorarium Bendahara Pengeluaran OB 420,000
250 juta
Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.008.003 Honorarium Bendahara Pengeluaran OB 500,000
500 juta
Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.008.004 Honorarium Bendahara Pengeluaran OB 570,000
1 miliar
Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.008.005 Honorarium Bendahara Pengeluaran OB 670,000
2,5 miliar
Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.008.006 Honorarium Bendahara Pengeluaran OB 770,000
Rp. 5 miliar
Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.008.007 Honorarium Bendahara Pengeluaran OB 860,000
10 miliar
Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.008.008 Honorarium Bendahara Pengeluaran OB 1,090,000
Rp. 25 miliar
Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.008.009 Honorarium Bendahara Pengeluaran OB 1,320,000
Rp. 50 miliar
Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.008.010 Honorarium Bendahara Pengeluaran OB 1,550,000
Rp.75 miliar

8
Nilai pagu dana di atas Rp.75 miliar sd. Rp.
1.10.28.01.01.008.011 Honorarium Bendahara Pengeluaran OB 1,780,000
100 miliar
Nilai pagu dana di atas Rp. 100 miliar sd.
1.10.28.01.01.008.012 Honorarium Bendahara Pengeluaran OB 2,120,000
Rp. 250 miliar
Nilai pagu dana di atas Rp. 250 miliar sd.
1.10.28.01.01.008.013 Honorarium Bendahara Pengeluaran OB 2,470,000
Rp. 500 miliar
Nilai pagu dana di atas Rp. 500 miliar sd.
1.10.28.01.01.008.014 Honorarium Bendahara Pengeluaran OB 2,810,000
Rp. 750 miliar
Nilai pagu dana di atas Rp. 750 miliar sd.
1.10.28.01.01.008.015 Honorarium Bendahara Pengeluaran OB 3,160,000
Rp. 1 triliun
1.10.28.01.01.008.016 Honorarium Bendahara Pengeluaran Nilai pagu dana di atas Rp. 1 triliun OB 3,840,000

1.10.28.01.01.018 Honorarium Pengurus Barang Pengguna

1.10.28.01.01.008.001 Honorarium Pengurus Barang Pengguna Nilai pagu dana sd. Rp. 100 juta OB 260,000
Nilai pagu dana di atas Rp. 100 juta sd. Rp.
1.10.28.01.01.008.002 Honorarium Pengurus Barang Pengguna OB 310,000
250 juta
Nilai pagu dana di atas Rp. 250 juta sd. Rp.
1.10.28.01.01.008.003 Honorarium Pengurus Barang Pengguna OB 370,000
500 juta
Nilai pagu dana di atas Rp. 500 juta sd. Rp.
1.10.28.01.01.008.004 Honorarium Pengurus Barang Pengguna OB 430,000
1 miliar
Nilai pagu dana di atas Rp. 1 miliar sd. Rp.
1.10.28.01.01.008.005 Honorarium Pengurus Barang Pengguna OB 500,000
2,5 miliar
Nilai pagu dana di atas Rp. 2,5 miliar sd.
1.10.28.01.01.008.006 Honorarium Pengurus Barang Pengguna OB 570,000
Rp. 5 miliar
Nilai pagu dana di atas Rp. 5 miliar sd. Rp.
1.10.28.01.01.008.007 Honorarium Pengurus Barang Pengguna OB 640,000
10 miliar
Nilai pagu dana di atas Rp. 10 miliar sd.
1.10.28.01.01.008.008 Honorarium Pengurus Barang Pengguna OB 810,000
Rp. 25 miliar
Nilai pagu dana di atas Rp. 25 miliar sd.
1.10.28.01.01.008.009 Honorarium Pengurus Barang Pengguna OB 980,000
Rp. 50 miliar
Nilai pagu dana di atas Rp. 50 miliar sd.
1.10.28.01.01.008.010 Honorarium Pengurus Barang Pengguna OB 1,150,000
Rp.75 miliar
Nilai pagu dana di atas Rp.75 miliar sd.
1.10.28.01.01.008.011 Honorarium Pengurus Barang Pengguna OB 1,330,000
Rp.100 miliar
Nilai pagu dana di atas Rp.100 miliar sd.
1.10.28.01.01.008.012 Honorarium Pengurus Barang Pengguna OB 1,580,000
Rp. 250 miliar
Nilai pagu dana di atas Rp. 250 miliar sd.
1.10.28.01.01.008.013 Honorarium Pengurus Barang Pengguna OB 1,840,000
Rp. 500 miliar
Nilai pagu dana di atas Rp. 500 miliar sd.
1.10.28.01.01.008.014 Honorarium Pengurus Barang Pengguna OB 2,090,000
Rp. 750 miliar
Nilai pagu dana di atas Rp. 750 miliar sd.
1.10.28.01.01.008.015 Honorarium Pengurus Barang Pengguna OB 2,350,000
Rp. 1 triliun
1.10.28.01.01.008.016 Honorarium Pengurus Barang Pengguna Nilai pagu dana di atas Rp. 1 triliun OB 2,860,000
1.10.28.01.02 Honorarium Penanggungjawab Pengelola Keuangan Pada Satker Yang Khusus Mengelola Belanja Pegawai
1.10.28.01.03 Honorarium Pengadaan Barang dan Jasa - (1 Orang Pejabat Pengadaan mendapatkan satu honor per bulan)

1.10.28.01.03.001 Honorarium Pejabat Pengadaaan Barang dan Jasa

Pagu dana adalah pagu pengadaan


Honorarium Pejabat Pengadaaan Barang dan
1.10.28.01.03.001.001 langsung yang dikelola oleh Pejabat OB 680,000
Jasa
Pengadaan
1.10.28.01.03.099 Honorarium Pengadaan Barang dan Jasa Lainnya
1.10.28.01.04 Honorarium Perangkat Unit Layanan Pengadaan (ULP)

1.10.28.01.04.001 Honorarium Perangkat Unit Layanan Pengadaan (ULP)

Honorarium Perangkat Unit Layanan


1.10.28.01.04.001.001 Kepala ULP OB 1,000,000
Pengadaan (ULP)

9
Honorarium Perangkat Unit Layanan
1.10.28.01.04.001.002 Sekretaris OB 750,000
Pengadaan (ULP)
Honorarium Perangkat Unit Layanan
1.10.28.01.04.001.003 Staf Pendukung ULP OB 750,000
Pengadaan (ULP)

1.10.28.01.04.002 Honorarium Kelompok Kerja Unit Layanan Pengadaan (ULP) - Konstruksi

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan sampai dengan
1.10.28.01.04.002.001 OP 680,000
Pengadaan (ULP) - Konstruksi Rp.200 juta
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 200 juta
1.10.28.01.04.002.002 OP 850,000
Pengadaan (ULP) - Konstruksi sd. Rp. 500 juta
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 500 juta
1.10.28.01.04.002.003 OP 1,020,000
Pengadaan (ULP) - Konstruksi sd. Rp. 1 miliar
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 1 milyar
1.10.28.01.04.002.004 OP 1,270,000
Pengadaan (ULP) - Konstruksi sd. Rp. 2,5 miliar
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 2,5 miliar
1.10.28.01.04.002.005 OP 1,520,000
Pengadaan (ULP) - Konstruksi sd. Rp. 5 miliar
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 5 miliar
1.10.28.01.04.002.006 OP 1,780,000
Pengadaan (ULP) - Konstruksi sd. Rp. 10 miliar
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 10 miliar
1.10.28.01.04.002.007 OP 2,120,000
Pengadaan (ULP) - Konstruksi sd. Rp. 25 miliar
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 25 miliar
1.10.28.01.04.002.008 OP 2,450,000
Pengadaan (ULP) - Konstruksi sd. Rp. 50 miliar
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 50 miliar
1.10.28.01.04.002.009 OP 2,790,000
Pengadaan (ULP) - Konstruksi sd. Rp. 75 miliar
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 75 miliar
1.10.28.01.04.002.010 OP 3,130,000
Pengadaan (ULP) - Konstruksi sd. Rp. 100 miliar
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 100
1.10.28.01.04.002.011 OP 3,580,000
Pengadaan (ULP) - Konstruksi miliar sd Rp. 250 miliar
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 250
1.10.28.01.04.002.012 OP 4,030,000
Pengadaan (ULP) - Konstruksi miliar sd. Rp. 500 milyar
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 500
1.10.28.01.04.002.013 OP 4,490,000
Pengadaan (ULP) - Konstruksi miliar sd. Rp. 750 milyar
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 750
1.10.28.01.04.002.014 OP 4,940,000
Pengadaan (ULP) - Konstruksi miliar sd. Rp. 1 trilyun
Honorarium Kelompok Kerja Unit Layanan
1.10.28.01.04.002.015 Nilai pagu pengadaan di atas Rp. 1 triliun OP 5,560,000
Pengadaan (ULP) - Konstruksi

1.10.28.01.04.003 Honorarium Kelompok Kerja Unit Layanan Pengadaan (ULP) – Non Konstruksi

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan sampai dengan
1.10.28.01.04.003.001 OP 760,000
Pengadaan (ULP) – Non Konstruksi Rp.200 juta

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 200 juta
1.10.28.01.04.003.002 OP 760,000
Pengadaan (ULP) – Non Konstruksi sd. Rp. 500 juta

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 500 juta
1.10.28.01.04.003.003 OP 920,000
Pengadaan (ULP) – Non Konstruksi sd. Rp. 1 miliar

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 1 milyar
1.10.28.01.04.003.004 OP 1,140,000
Pengadaan (ULP) – Non Konstruksi sd. Rp. 2,5 miliar

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 2,5 miliar
1.10.28.01.04.003.005 OP 1,370,000
Pengadaan (ULP) – Non Konstruksi sd. Rp. 5 miliar

10
Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 5 miliar
1.10.28.01.04.003.006 OP 1,600,000
Pengadaan (ULP) – Non Konstruksi sd. Rp. 10 miliar

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 10 miliar
1.10.28.01.04.003.007 OP 1,910,000
Pengadaan (ULP) – Non Konstruksi sd. Rp. 25 miliar

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 25 miliar
1.10.28.01.04.003.008 OP 2,210,000
Pengadaan (ULP) – Non Konstruksi sd. Rp. 50 miliar

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 50 miliar
1.10.28.01.04.003.009 OP 2,520,000
Pengadaan (ULP) – Non Konstruksi sd. Rp. 75 miliar

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 75 miliar
1.10.28.01.04.003.010 OP 2,820,000
Pengadaan (ULP) – Non Konstruksi sd. Rp. 100 miliar

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 100
1.10.28.01.04.003.011 OP 3,230,000
Pengadaan (ULP) – Non Konstruksi miliar sd Rp. 250 miliar

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 250
1.10.28.01.04.003.012 OP 3,640,000
Pengadaan (ULP) – Non Konstruksi miliar sd. Rp. 500 milyar

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 500
1.10.28.01.04.003.013 OP 4,040,000
Pengadaan (ULP) – Non Konstruksi miliar sd. Rp. 750 milyar

Honorarium Kelompok Kerja Unit Layanan Nilai pagu pengadaan di atas Rp. 750
1.10.28.01.04.003.014 OP 4,450,000
Pengadaan (ULP) – Non Konstruksi miliar sd. Rp. 1 trilyun

Honorarium Kelompok Kerja Unit Layanan


1.10.28.01.04.003.015 Nilai pagu pengadaan di atas Rp. 1 triliun OP 5,010,000
Pengadaan (ULP) – Non Konstruksi

1.10.28.01.04.004 Honorarium Kelompok Kerja Jasa lainnya dan Konsultansi Unit Layanan Pengadaan (ULP) – Non Konstruksi

Honorarium Kelompok Kerja Jasa lainnya


Nilai pagu pengadaan jasa konsultansi di
1.10.28.01.04.004.001 dan Konsultansi Unit Layanan Pengadaan OP 450,000
atas Rp. 50 juta sd. Rp. 200 juta
(ULP) – Non Konstruksi
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.002 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp. 200 juta sd. Rp.250 OP 480,000
(ULP) – Non Konstruksi juta
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.003 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp.250 juta sd. OP 600,000
(ULP) – Non Konstruksi Rp.500juta
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.004 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp.500 juta sd. Rp. 1 OP 720,000
(ULP) – Non Konstruksi miliar
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.005 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp. 1 milyar sd. Rp.2,5 OP 910,000
(ULP) – Non Konstruksi miliar
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.006 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp.2,5 miliar sd. Rp.5 OP 1,090,000
(ULP) – Non Konstruksi miliar
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.007 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp. 5 miliar sd. Rp. 10 OP 1,270,000
(ULP) – Non Konstruksi miliar

11
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.008 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp. 10 miliar sd. Rp.25 OP 1,510,000
(ULP) – Non Konstruksi miliar
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.009 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp.25 miliar sd. Rp.50 OP 1,750,000
(ULP) – Non Konstruksi miliar
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.010 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp.50 miliar sd. Rp.75 OP 1,990,000
(ULP) – Non Konstruksi miliar
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.011 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp.75 miliar sd. Rp100 OP 2,230,000
(ULP) – Non Konstruksi miliar
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.012 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp100 miliar sd Rp250 OP 2,560,000
(ULP) – Non Konstruksi miliar
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.013 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp250 miliar sd. Rp. OP 2,880,000
(ULP) – Non Konstruksi 500 milyar
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.014 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp 500 miliar sd. OP 3,200,000
(ULP) – Non Konstruksi Rp.750 milyar
Honorarium Kelompok Kerja Jasa lainnya Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.015 dan Konsultansi Unit Layanan Pengadaan jasa lainnya di atas Rp 750 miliar sd. Rp. 1 OP 3,520,000
(ULP) – Non Konstruksi trilyun
Honorarium Kelompok Kerja Jasa lainnya
Nilai pagu pengadaan jasa konsultansi/
1.10.28.01.04.004.016 dan Konsultansi Unit Layanan Pengadaan OP 3,960,000
jasa lainnya di atas Rp. 1 triliun
(ULP) – Non Konstruksi
1.10.28.01.09 Honorarium Tim Pelaksana Kegiatan

1.10.28.01.09.001 Honorarium Tim Pelaksana Kegiatan - ditetapkan oleh Walikota

Honorarium Tim Pelaksana Kegiatan -


1.10.28.01.09.001.001 Pengarah 1 OK 750,000
ditetapkan oleh Walikota
Honorarium Tim Pelaksana Kegiatan -
1.10.28.01.09.001.002 Pengarah 2 OK 725,000
ditetapkan oleh Walikota
Honorarium Tim Pelaksana Kegiatan -
1.10.28.01.09.001.003 Pengarah 3 OK 725,000
ditetapkan oleh Walikota
Honorarium Tim Pelaksana Kegiatan -
1.10.28.01.09.001.004 Penanggung Jawab/Koordinator OK 700,000
ditetapkan oleh Walikota
Honorarium Tim Pelaksana Kegiatan -
1.10.28.01.09.001.005 Ketua OK 650,000
ditetapkan oleh Walikota
Honorarium Tim Pelaksana Kegiatan -
1.10.28.01.09.001.006 Wakil Ketua OK 600,000
ditetapkan oleh Walikota
Honorarium Tim Pelaksana Kegiatan -
1.10.28.01.09.001.007 Sekretaris OK 500,000
ditetapkan oleh Walikota
Anggota - (Koordinator Bidang/Urusan - Honorarium Tim Pelaksana Kegiatan -
1.10.28.01.09.001.008 OK 500,000
apabila diperlukan ditetapkan oleh Walikota

1.10.28.01.09.003 Honorarium Sekretariat Tim Pelaksana Kegiatan

Honorarium Sekretariat Tim Pelaksana


1.10.28.01.09.003.001 Ketua/Wakil OK 250,000
Kegiatan
Honorarium Sekretariat Tim Pelaksana
1.10.28.01.09.003.002 Anggota OK 220,000
Kegiatan

1.10.28.01.09.004 Honorarium Tim Anggaran Pemerintah Kota Mojokerto

Honorarium Tim Anggaran Pemerintah


1.10.28.01.09.004.001 Pengarah 1 OK 3,600,000
Kota Mojokerto

12
Honorarium Tim Anggaran Pemerintah
1.10.28.01.09.004.002 Pengarah 2 OK 3,500,000
Kota Mojokerto
Honorarium Tim Anggaran Pemerintah
1.10.28.01.09.004.003 Ketua OK 3,300,000
Kota Mojokerto
Honorarium Tim Anggaran Pemerintah
1.10.28.01.09.004.004 Wakil Ketua OK 3,200,000
Kota Mojokerto
Honorarium Tim Anggaran Pemerintah
1.10.28.01.09.004.005 Sekretaris OK 3,100,000
Kota Mojokerto
Honorarium Tim Anggaran Pemerintah
1.10.28.01.09.004.006 Anggota OK 3,000,000
Kota Mojokerto
1.10.28.01.09.005 Honorarium Sekretariat Tim Anggaran Pemerintah Kota Mojokerto
Honorarium Sekretariat Tim Anggaran
1.10.28.01.09.005.001 Koordinator OK 1,400,000
Pemerintah Kota Mojokerto
Honorarium Sekretariat Tim Anggaran
1.10.28.01.09.005.002 Sekretaris OK 1,000,000
Pemerintah Kota Mojokerto
Honorarium Sekretariat Tim Anggaran
1.10.28.01.09.005.003 Anggota OK 1,000,000
Pemerintah Kota Mojokerto

Honorarium Tim Pembahasan, Penetapan Rancangan Prioritas, Plafon Anggaran Sementara Anggaran Pendapatan,
1.10.28.01.09.006
dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


Rancangan Prioritas, Plafon Anggaran
1.10.28.01.09.006.001 Pengarah OK 2,100,000
Sementara Anggaran Pendapatan, dan
Belanja Daerah
Honorarium Tim Pembahasan, Penetapan
Rancangan Prioritas, Plafon Anggaran
1.10.28.01.09.006.002 Penanggung Jawab OK 2,000,000
Sementara Anggaran Pendapatan, dan
Belanja Daerah
Honorarium Tim Pembahasan, Penetapan
Rancangan Prioritas, Plafon Anggaran
1.10.28.01.09.006.003 Koordinator OK 1,900,000
Sementara Anggaran Pendapatan, dan
Belanja Daerah
Honorarium Tim Pembahasan, Penetapan
Rancangan Prioritas, Plafon Anggaran
1.10.28.01.09.006.004 Ketua OK 1,800,000
Sementara Anggaran Pendapatan, dan
Belanja Daerah
Honorarium Tim Pembahasan, Penetapan
Rancangan Prioritas, Plafon Anggaran
1.10.28.01.09.006.005 Wakil Ketua OK 1,700,000
Sementara Anggaran Pendapatan, dan
Belanja Daerah
Honorarium Tim Pembahasan, Penetapan
Rancangan Prioritas, Plafon Anggaran
1.10.28.01.09.006.006 Sekretaris OK 1,600,000
Sementara Anggaran Pendapatan, dan
Belanja Daerah
Honorarium Tim Pembahasan, Penetapan
Rancangan Prioritas, Plafon Anggaran
1.10.28.01.09.006.007 Anggota OK 1,500,000
Sementara Anggaran Pendapatan, dan
Belanja Daerah

1.10.28.01.09.007 Honorarium Tim Pembahasan, Penetapan Rancangan Kebijakan Umum Anggaran Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.007.001 Pengarah Rancangan Kebijakan Umum Anggaran OK 2,100,000
Pendapatan, dan Belanja Daerah

13
Honorarium Tim Pembahasan, Penetapan
1.10.28.01.09.007.002 Penanggung Jawab Rancangan Kebijakan Umum Anggaran OK 2,000,000
Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.007.003 Koordinator Rancangan Kebijakan Umum Anggaran OK 1,900,000
Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.007.004 Ketua Rancangan Kebijakan Umum Anggaran OK 1,800,000
Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.007.005 Wakil Ketua Rancangan Kebijakan Umum Anggaran OK 1,700,000
Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.007.006 Sekretaris Rancangan Kebijakan Umum Anggaran OK 1,600,000
Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.007.007 Anggota Rancangan Kebijakan Umum Anggaran OK 1,500,000
Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan Rancangan Peraturan Daerah tentang Anggaran Pendapatan, dan Belanja
1.10.28.01.09.008
Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.008.001 Pengarah Rancangan Peraturan Daerah tentang OK 3,600,000
Anggaran Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.008.002 Penanggung Jawab Rancangan Peraturan Daerah tentang OK 3,500,000
Anggaran Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.008.003 Koordinator Rancangan Peraturan Daerah tentang OK 3,400,000
Anggaran Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.008.004 Ketua Rancangan Peraturan Daerah tentang OK 3,300,000
Anggaran Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.008.005 Wakil Ketua Rancangan Peraturan Daerah tentang OK 3,200,000
Anggaran Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.008.006 Sekretaris Rancangan Peraturan Daerah tentang OK 3,100,000
Anggaran Pendapatan, dan Belanja Daerah

Honorarium Tim Pembahasan, Penetapan


1.10.28.01.09.008.007 Anggota Rancangan Peraturan Daerah tentang OK 3,000,000
Anggaran Pendapatan, dan Belanja Daerah

14
Honorarium Tim Pembahasan, dan Penetapan Rancangan Peraturan Daerah tentang Laporan Keterangan
1.10.28.01.09.009
Pertanggungjawaban Walikota

Honorarium Tim Pembahasan, dan


Penetapan Rancangan Peraturan Daerah
1.10.28.01.09.009.001 Pengarah OK 3,600,000
tentang Laporan Keterangan
Pertanggungjawaban Walikota
Honorarium Tim Pembahasan, dan
Penetapan Rancangan Peraturan Daerah
1.10.28.01.09.009.002 Penanggung Jawab OK 3,500,000
tentang Laporan Keterangan
Pertanggungjawaban Walikota
Honorarium Tim Pembahasan, dan
Penetapan Rancangan Peraturan Daerah
1.10.28.01.09.009.003 Koordinator OK 3,400,000
tentang Laporan Keterangan
Pertanggungjawaban Walikota
Honorarium Tim Pembahasan, dan
Penetapan Rancangan Peraturan Daerah
1.10.28.01.09.009.004 Ketua OK 3,300,000
tentang Laporan Keterangan
Pertanggungjawaban Walikota
Honorarium Tim Pembahasan, dan
Penetapan Rancangan Peraturan Daerah
1.10.28.01.09.009.005 Wakil Ketua OK 3,200,000
tentang Laporan Keterangan
Pertanggungjawaban Walikota
Honorarium Tim Pembahasan, dan
Penetapan Rancangan Peraturan Daerah
1.10.28.01.09.009.006 Sekretaris OK 3,100,000
tentang Laporan Keterangan
Pertanggungjawaban Walikota
Honorarium Tim Pembahasan, dan
Penetapan Rancangan Peraturan Daerah
1.10.28.01.09.009.007 Anggota OK 3,000,000
tentang Laporan Keterangan
Pertanggungjawaban Walikota

1.10.28.01.09.010 Honorarium Tim Pokja Kegiatan

1.10.28.01.09.010.006 Ketua Pokja/Program Honorarium Tim Pokja Kegiatan OK 525,000


1.10.28.01.09.010.007 Wakil Ketua Pokja/Program Honorarium Tim Pokja Kegiatan OK 500,000
1.10.28.01.09.010.008 Anggota Honorarium Tim Pokja Kegiatan OK 500,000

Honorarium Tim Penyusunan, Penetapan, dan Perubahan Rencana Kerja Pembangunan Daerah (RKPD) Kota
1.10.28.01.09.012
Mojokerto

Honorarium Tim Penyusunan, Penetapan,


dan Perubahan Rencana Kerja
1.10.28.01.09.012.001 Pembina I OK 2,000,000
Pembangunan Daerah (RKPD) Kota
Mojokerto
Honorarium Tim Penyusunan, Penetapan,
dan Perubahan Rencana Kerja
1.10.28.01.09.012.002 Pembina II OK 1,750,000
Pembangunan Daerah (RKPD) Kota
Mojokerto
Honorarium Tim Penyusunan, Penetapan,
dan Perubahan Rencana Kerja
1.10.28.01.09.012.003 Ketua OK 1,500,000
Pembangunan Daerah (RKPD) Kota
Mojokerto
Honorarium Tim Penyusunan, Penetapan,
dan Perubahan Rencana Kerja
1.10.28.01.09.012.004 Sekretaris OK 1,250,000
Pembangunan Daerah (RKPD) Kota
Mojokerto

15
Honorarium Tim Penyusunan, Penetapan,
dan Perubahan Rencana Kerja
1.10.28.01.09.012.005 Anggota OK 1,000,000
Pembangunan Daerah (RKPD) Kota
Mojokerto

1.10.28.01.09.013 Honorarium Tim Pelaksana kegiatan Fasilitasi Penyelesaian Perselisihan Hubungan Industrial

Honorarium Tim Pelaksana kegiatan


1.10.28.01.09.013.001 Penanggungjawab Tim Mediasi Fasilitasi Penyelesaian Perselisihan Orang/Kasus 500,000
Hubungan Industrial
Honorarium Tim Pelaksana kegiatan
1.10.28.01.09.013.002 Mediator Hubungan Industrial Fasilitasi Penyelesaian Perselisihan Orang/Kasus 400,000
Hubungan Industrial
Honorarium Tim Pelaksana kegiatan
1.10.28.01.09.013.003 Anggota Tim Mediasi Fasilitasi Penyelesaian Perselisihan Orang/Kasus 300,000
Hubungan Industrial
1.10.28.01.09.014 Honorarium Tim Pembahasan dan Penetapan Raperda Kota Mojokerto
Honorarium Tim Pembahasan dan
1.10.28.01.09.014.001 Pengarah OK 3,600,000
Penetapan Raperda Kota Mojokerto
Honorarium Tim Pembahasan dan
1.10.28.01.09.014.002 Penanggung Jawab OK 3,500,000
Penetapan Raperda Kota Mojokerto
Honorarium Tim Pembahasan dan
1.10.28.01.09.014.003 Koordinator OK 3,400,000
Penetapan Raperda Kota Mojokerto
Honorarium Tim Pembahasan dan
1.10.28.01.09.014.004 Ketua OK 3,300,000
Penetapan Raperda Kota Mojokerto
Honorarium Tim Pembahasan dan
1.10.28.01.09.014.005 Wakil Ketua OK 3,200,000
Penetapan Raperda Kota Mojokerto
Honorarium Tim Pembahasan dan
1.10.28.01.09.014.006 Sekretaris OK 3,100,000
Penetapan Raperda Kota Mojokerto
Honorarium Tim Pembahasan dan
1.10.28.01.09.014.007 Anggota OK 3,000,000
Penetapan Raperda Kota Mojokerto

1.10.28.01.09.015 Honorarium Tim Penyusunan Jurnal/Buletin/Majalah/Tabloid

Honorarium Tim Penyusunan


1.10.28.01.09.015.001 Penanggung Jawab Oter 500,000
Jurnal/Buletin/Majalah/Tabloid
Honorarium Tim Penyusunan
1.10.28.01.09.015.002 Redaktur Oter 400,000
Jurnal/Buletin/Majalah/Tabloid
Honorarium Tim Penyusunan
1.10.28.01.09.015.003 Penyunting/Editor Oter 300,000
Jurnal/Buletin/Majalah/Tabloid
Honorarium Tim Penyusunan
1.10.28.01.09.015.004 Desain Grafis Oter 180,000
Jurnal/Buletin/Majalah/Tabloid
Honorarium Tim Penyusunan
1.10.28.01.09.015.005 Fotografer Oter 180,000
Jurnal/Buletin/Majalah/Tabloid
Honorarium Tim Penyusunan
1.10.28.01.09.015.006 Sekretariat Oter 150,000
Jurnal/Buletin/Majalah/Tabloid
Honorarium Tim Penyusunan
1.10.28.01.09.015.007 Pembuat artikel Halaman 200,000
Jurnal/Buletin/Majalah/Tabloid

1.10.28.01.09.016 Honorarium Tim Pengelola Website Pemerintah Kota Mojokerto

Honorarium Tim Pengelola Website


1.10.28.01.09.016.001 Penanggung Jawab OB 500,000
Pemerintah Kota Mojokerto
Honorarium Tim Pengelola Website
1.10.28.01.09.016.002 Redaktur OB 450,000
Pemerintah Kota Mojokerto
Honorarium Tim Pengelola Website
1.10.28.01.09.016.003 Editor OB 400,000
Pemerintah Kota Mojokerto
Honorarium Tim Pengelola Website
1.10.28.01.09.016.004 Web Admin OB 350,000
Pemerintah Kota Mojokerto

16
Honorarium Tim Pengelola Website
1.10.28.01.09.016.005 Web Developer OB 300,000
Pemerintah Kota Mojokerto
Honorarium Tim Pengelola Website
1.10.28.01.09.016.006 Pembuat Artikel Halaman 100,000
Pemerintah Kota Mojokerto
1.10.28.01.09.017 Honorarium Panitia Seleksi Terbuka Jabatan Pimpinan Tinggi Pratama
Honorarium Panitia Seleksi Terbuka
1.10.28.01.09.017.001 Ketua OK 2,500,000
Jabatan Pimpinan Tinggi Pratama
Honorarium Panitia Seleksi Terbuka
1.10.28.01.09.017.002 Sekretaris OK 2,400,000
Jabatan Pimpinan Tinggi Pratama
Honorarium Panitia Seleksi Terbuka
1.10.28.01.09.017.003 Anggota OK 2,300,000
Jabatan Pimpinan Tinggi Pratama
1.10.28.01.09.020 Honorarium Tim Penilai Angka kredit

1.10.28.01.09.020.001 Ketua Honorarium Tim Penilai Angka kredit Per Semester 500,000
1.10.28.01.09.020.002 Wakil Ketua Honorarium Tim Penilai Angka kredit Per Semester 400,000
1.10.28.01.09.020.003 Sekretaris Honorarium Tim Penilai Angka kredit Per Semester 300,000
1.10.28.01.09.020.004 Anggota Honorarium Tim Penilai Angka kredit Per Semester 250,000

1.10.28.01.09.021 Honor Unit Saber Pungli

1.10.28.01.09.021.001 Penanggung Jawab Unit Saber Pungli OK 1,500,000


1.10.28.01.09.021.002 Pendamping Penanggung Jawab I Unit Saber Pungli OK 1,500,000
1.10.28.01.09.021.003 Pendamping Penanggung Jawab II Unit Saber Pungli OK 1,500,000
1.10.28.01.09.021.004 Pendamping Penanggung Jawab III Unit Saber Pungli OK 1,500,000
1.10.28.01.09.021.005 Ketua Unit Saber Pungli OK 1,300,000
1.10.28.01.09.021.006 Wakil Ketua I Unit Saber Pungli OK 1,200,000
1.10.28.01.09.021.007 Wakil Ketua II Unit Saber Pungli OK 1,200,000
1.10.28.01.09.021.008 Sekretaris Unit Saber Pungli OK 1,000,000
1.10.28.01.09.021.009 Bidang Operasional Unit Saber Pungli OK 900,000
1.10.28.01.09.021.010 Bidang Logistik Unit Saber Pungli OK 900,000
1.10.28.01.09.021.011 Bidang Administrasi Umum I Unit Saber Pungli OK 900,000
1.10.28.01.09.021.012 Bidang Administrasi Umum II Unit Saber Pungli OK 900,000
1.10.28.01.09.021.013 Bidang Keuangan Unit Saber Pungli OK 900,000
1.10.28.01.09.021.014 Bidang Informasi Unit Saber Pungli OK 900,000
1.10.28.01.09.021.015 Bidang Publikasi Umum Unit Saber Pungli OK 900,000
Ketua Pokja Unit Intelejen, Unit
1.10.28.01.09.021.016 Pencegahan, Unit Penindakan Dan Unit Unit Saber Pungli OK 1,000,000
Yustisi
Anggota Pokja Unit Intelejen, Unit
1.10.28.01.09.021.017 Pencegahan, Unit Penindakan Dan Unit Unit Saber Pungli OK 900,000
Yustisi
1.10.28.01.09.022 Honorarium Perangkat Layanan Pengadaan Secara Elektronik (LPSE)

Honorarium Perangkat Layanan


1.10.28.01.09.022.001 Kepala LPSE OB 1,000,000
Pengadaan Secara Elektronik (LPSE)
Honorarium Perangkat Layanan
1.10.28.01.09.022.002 Administrasi Agensi OB 600,000
Pengadaan Secara Elektronik (LPSE)
Honorarium Perangkat Layanan
1.10.28.01.09.022.003 Administrasi Helpdesk OB 600,000
Pengadaan Secara Elektronik (LPSE)
Honorarium Perangkat Layanan
1.10.28.01.09.022.003 Administrasi PPE OB 600,000
Pengadaan Secara Elektronik (LPSE)
1.10.28.01.09.039 Satuan Biaya Pemeriksaan Khusus TP4D

1.10.28.01.09.039.001 Pengarah OK 650,000


1.10.28.01.09.039.002 Ketua 1 OK 600,000
1.10.28.01.09.039.003 Ketua 2 OK 550,000
1.10.28.01.09.039.004 Wakil Ketua OK 500,000

17
1.10.28.01.09.039.005 Sekretaris OK 500,000
1.10.28.01.09.039.006 Anggota OK 400,000
1.10.28.01.09.039.007 Anggota Pendukung OK 400,000

1.10.28.01.09.099 Honorarium Tim Pelaksana Kegiatan Lainnya

OPD yang mempunyai Kader (masyarakat)


1.10.28.01.09.099.001 Honor kader motivator OB 100,000
dilingkup kegiatannya
1.10.28.01.09.099.002 Honor Pelindung Kegiatan PSN OB 750,000
Kegiatan FKKS (Forum Komunikasi Kota
1.10.28.01.09.099.003 Ketua OB 300,000
Sehat)
Kegiatan FKKS (Forum Komunikasi Kota
1.10.28.01.09.099.004 Sekretaris OB 280,000
Sehat)
Kegiatan FKKS (Forum Komunikasi Kota
1.10.28.01.09.099.005 Bendahara OB 250,000
Sehat)
1.10.28.01.09.099.006 Ketua Kegiatan Pokja Kelurahan Sehat OB 275,000
1.10.28.01.09.099.007 Sekretaris Kegiatan Pokja Kelurahan Sehat OB 250,000
1.10.28.01.09.099.008 Bendahara Kegiatan Pokja Kelurahan Sehat OB 225,000
1.10.28.01.99 Honorarium Umum Lainnya

1.10.28.01.99.001 Honorarium Tenaga Kerja Non Pegawai Negeri Sipil

1.10.28.01.99.001.001 Tenaga Administrasi Umum Jasa Tenaga Kerja (Non ASN) OB 2,200,000

1.10.28.01.99.003 Vakasi & Honorarium Penyelenggaraan Ujian

siswa/mata
1.10.28.01.99.003.001 Pemeriksaan Hasil Ujian Vakasi - (Pendidikan Dasar) 5,000
ujian
siswa/mata
1.10.28.01.99.003.002 Pemeriksaan Hasil Ujian Vakasi - (Pendidikan Menengah) 7,500
ujian
Honorarium Penyelenggaraan Ujian - naskah/pelaja
1.10.28.01.99.003.003 Penyusunan/pembuatan bahan Ujian 150,000
(Pendidikan Dasar) ran
Honorarium Penyelenggaraan Ujian -
1.10.28.01.99.003.004 Pengawas Ujian OH 240,000
(Pendidikan Dasar)
Honorarium Penyelenggaraan Ujian - naskah/pelaja
1.10.28.01.99.003.005 Penyusunan/pembuatan bahan Ujian 190,000
(Pendidikan Menengah) ran
Honorarium Penyelenggaraan Ujian -
1.10.28.01.99.003.006 Pengawas Ujian OH 270,000
(Pendidikan Menengah)
1.10.28.01.99.004 Honorarium Pengajar Diklat
1.10.28.01.99.004.001 Pengajar dari dalam SKPD Honorarium Pengajar Diklat OJ 200,000
1.10.28.01.99.004.002 Pengajar dari luar SKPD (Internal PEMDA) Honorarium Pengajar Diklat OJ 300,000
1.10.28.01.99.004.003 Penyusun Materi/Naskah Honorarium Pengajar Diklat per materi 150,000

1.10.28.01.99.005 Honorarium Penunjang Penelitian / Perekayasaan

Honorarium Penunjang Penelitian /


1.10.28.01.99.005.001 Peneliti Utama ( Maksimum 4 Jam / hari ) OJ 60,000
Perekayasaan
Honorarium Penunjang Penelitian /
1.10.28.01.99.005.002 Peneliti Madya ( Maksimum 4 Jam / hari ) OJ 50,000
Perekayasaan
Honorarium Penunjang Penelitian /
1.10.28.01.99.005.003 Peneliti Muda ( Maksimum 4 Jam / hari ) OJ 40,000
Perekayasaan
Honorarium Penunjang Penelitian /
1.10.28.01.99.005.004 Peneliti Pertama ( Maksimum 4 Jam / hari ) OJ 35,000
Perekayasaan
Honorarium Penunjang Penelitian /
1.10.28.01.99.005.005 Peneliti (Non Fungsional Peneliti) OJ 30,000
Perekayasaan
Honorarium Penunjang Penelitian /
1.10.28.01.99.005.006 Pembantu Peneliti/Perekayasa OJ 25,000
Perekayasaan
Honorarium Penunjang Penelitian /
1.10.28.01.99.005.007 Koordinator Peneliti/Perekayasa OB 420,000
Perekayasaan

18
Honorarium Penunjang Penelitian /
1.10.28.01.99.005.008 Sekretariat Penelitian/Perekayasa OB 300,000
Perekayasaan
Honorarium Penunjang Penelitian /
1.10.28.01.99.005.009 Pengolah Data penelitian 1,540,000
Perekayasaan
Honorarium Penunjang Penelitian / orang/respon
1.10.28.01.99.005.010 Petugas Survey 8,000
Perekayasaan den
Honorarium Penunjang Penelitian /
1.10.28.01.99.005.011 Pembantu Lapangan OH 80,000
Perekayasaan
1.10.28.01.99.006 Honorarium Koordinator Aplikasi Keuangan Pada Satuan Kerja Perangkat Daerah
Koordinator pemerintah Kota Mojokerto
1.10.28.01.99.006.001 OB 700,000
(SKPKD)
Wakil Koordinator pemerintah Kota
1.10.28.01.99.006.002 OB 600,000
Mojokerto (SKPKD)
1.10.28.01.99.006.003 Koordinator Aplikasi Keuangan Pada Satuan Kerja Perangkat Daerah (Operator SIMDA) OB 750,000
1.10.28.01.99.006.004 Anggota pada SKPD (tidak boleh melebihi bendahara pengeluaran/bendahara OB 400,000
1.10.28.01.99.007 Honorarium Unit Kerja Sekretariat DPRD Kota Mojokerto
Honorarium Unit Kerja Sekretariat DPRD
1.10.28.01.99.007.001 Honorarium Tenaga Ahli DPRD OB 2,750,000
Kota Mojokerto
Honorarium Pengukuh Sumpah/Pejabat yang Honorarium Unit Kerja Sekretariat DPRD
1.10.28.01.99.007.002 OK 1,500,000
melantik Kota Mojokerto
Honorarium Unit Kerja Sekretariat DPRD
1.10.28.01.99.007.003 Honorarium Rohaniawan OK 500,000
Kota Mojokerto
Honorarium Tenaga Administrasi Pimpinan Honorarium Unit Kerja Sekretariat DPRD
1.10.28.01.99.007.004 OB 2,500,000
DPRD Kota Mojokerto
1.10.28.01.99.099 Honorarium Umum Lain - lain
1.10.28.01.99.099.001 Tunjangan Kebakaran PMK OB 400,000
1.10.28.01.99.099.002 Uang jaga/piket Hari Raya OK 100,000

1.10.28.01.99.099.003 Uang kejadian kebakaran regu/kegiatan 1,000,000

1.10.28.01.99.099.004 Honorarium Pengawas Pengangkut Sampah OB 250,000

1.10.28.01.99.099.005 Honorarium Pengawas Penyapu Jalan OB 250,000


1.10.28.01.99.099.006 Honorarium Pengawas Pemelihara Taman OB 250,000
1.10.28.01.99.099.007 Honorarium Pemelihara PJU OB 250,000
1.10.28.01.99.099.008 Honorarium Pengawas Pemelihara Saluran OB 250,000
1.10.28.02 Upah/Jasa
1.10.28.02.01 Upah/Jasa Sektor Fisik
1.10.28.02.01.001 Upah/Jasa Tenaga Kerja Terampil (Terlatih)
1.10.28.02.01.001.001 Upah Mandor OH 180,000
1.10.28.02.01.001.002 Upah Kepala Tukang OH 150,000
1.10.28.02.01.001.003 Upah Surveyor Geodesi OH 120,000
1.10.28.02.01.001.004 Tukang Kayu OH 110,000
1.10.28.02.01.001.005 Tukang Cat OH 150,000
1.10.28.02.01.001.006 Tukang Batu OH 110,000
1.10.28.02.01.001.007 Tukang Aspal OH 110,000
1.10.28.02.01.001.008 Tukang Besi OH 110,000
1.10.28.02.01.001.009 Tukang Pipa OH 110,000
1.10.28.02.01.001.010 Tukang Gali Tanah OH 110,000
1.10.28.02.01.001.011 Tukang Gali Jalan OH 110,000
1.10.28.02.01.001.012 Tukang Gali Lumpur OH 110,000
1.10.28.02.01.001.013 Tukang Las OH 110,000
1.10.28.02.01.001.014 Tukang Taman OH 110,000
1.10.28.02.01.001.015 Upah Operator Alat Berat OH 110,000
1.10.28.02.01.001.016 Upah Sopir OH 110,000
1.10.28.02.01.001.017 Upah Bor Master OH 110,000

19
1.10.28.02.01.001.018 Upah Mekanik OH 100,000
1.10.28.02.01.001.019 Upah Juru ukur OH 100,000
1.10.28.02.01.001.020 Upah Colter dan Kalibrasi OH 425,000
1.10.28.02.01.001.021 Upah Operator Alat Ringan OH 85,000
1.10.28.02.01.001.022 Tukang Listrik OH 110,000
1.10.28.02.01.002 Upah/Jasa Tenaga Kerja Tak Terampil (Tidak Terlatih)
Operator Pompa, Pembantu Sopir,
Pembantu Mekanik, Pembantu Juru Ukur,
1.10.28.02.01.002.001 Upah Pekerja (Tak Terampil) OH 150,000
Pembantu Operator Alat Berat, Pembantu
Surveyor, dan Sejenisnya

1.10.28.02.01.002.002 Upah Pekerja (Tak Terampil) Biaya Pasang Backdrop, banner, spanduk m' 10,000

1.10.28.02.01.003 Upah/Jasa Kegiatan Pemeliharaan


Ganti Kompresor AC Windows 1 PK (Jasa
1.10.28.02.01.003.001 Pemeliharaan AC unit 1,000,000
dan Isi Freon)
Ganti Kompresor AC Windows 1,5 PK (
1.10.28.02.01.003.002 Pemeliharaan AC unit 2,000,000
Jasa dan Isi Freon)
Ganti Kompresor AC Windows 2 PK (Jasa
1.10.28.02.01.003.003 Pemeliharaan AC unit 4,000,000
dan Isi Freon)
1.10.28.02.01.003.004 Pemeliharaan AC Isi Freon AC Split 1/2 - 1 PK unit 150,000
1.10.28.02.01.003.005 Pemeliharaan AC Isi Freon AC Split 1,5 – 2 PK unit 200,000
1.10.28.02.01.003.006 Pemeliharaan AC Isi Freon AC Split 2 – 2,5 PK unit 350,000
1.10.28.02.01.003.007 Pemeliharaan AC Isi Freon AC Split 5 PK unit 400,000
1.10.28.02.01.003.008 Pemeliharaan AC Isi Freon AC Cassete, sentral, Standing per PK 200,000
1.10.28.02.01.003.009 Pemeliharaan AC Isi Freon AC Split Inverter 1/2 - 2 PK unit 300,000
1.10.28.02.01.003.010 Pemeliharaan AC Isi Freon AC Window 1 PK unit 1,000,000
1.10.28.02.01.003.011 Pemeliharaan AC Tambah freon AC Split 1/2 - 2 PK unit 150,000
Tambah freon AC Cassete, sentral,
1.10.28.02.01.003.012 Pemeliharaan AC per PK 150,000
Standing

1.10.28.02.01.003.013 Pemeliharaan AC Tambah freon AC Split Inverter 1/2 - 2 PK unit 250,000

1.10.28.02.01.003.014 Pemeliharaan AC Cleaning / Cuci AC Split 1/2 - 1 unit 50,000


1.10.28.02.01.003.015 Pemeliharaan AC Cleaning / Cuci AC Split 2 – 2,5 PK unit 70,000
Cleaning / Cuci AC Cassete, sentral,
1.10.28.02.01.003.016 Pemeliharaan AC per PK 100,000
Standing
1.10.28.02.01.003.017 Pemeliharaan AC Pemeriksaan / Cek AC Split 1/2 - 2 PK unit 100,000
Pemeriksaan / Cek AC Cassete, sentral,
1.10.28.02.01.003.018 Pemeliharaan AC unit 150,000
Standing
Jasa ganti sparepart kecil semua jenis/tipe
1.10.28.02.01.003.019 Pemeliharaan AC unit 150,000
AC
Jasa ganti sparepart besar semua jenis/tipe
1.10.28.02.01.003.020 Pemeliharaan AC unit 200,000
AC
1.10.28.02.01.003.021 Pemeliharaan AC Jasa ganti kompresor 1/2 - 2 PK unit 500,000
1.10.28.02.01.003.022 Pemeliharaan AC Jasa ganti kompresor 3 - 5 PK unit 1,500,000
1.10.28.02.01.003.023 Pemeliharaan AC las per titik semua jenis/tipe AC titik 100,000
1.10.28.02.01.003.024 Pemeliharaan AC Jasa Pasang AC 1/2 - 2 PK unit 250,000
1.10.28.02.01.003.025 Pemeliharaan AC Jasa Pasang AC 3 - 5 PK unit 1,500,000
1.10.28.02.01.003.026 Pemeliharaan AC Jasa Bongkar AC 1/2 - 2 PK unit 200,000
1.10.28.02.01.003.027 Pemeliharaan AC Jasa Bongkar AC 3 - 5 PK unit 500,000
1.10.28.02.01.003.028 Pemeliharaan AC Bobokan 1/2 - 1 PK per titik/m' 100,000
1.10.28.02.01.003.029 Pemeliharaan AC Penggantian Capasitor 1,5 - 2 PK unit 275,000
1.10.28.02.01.003.030 Pemeliharaan AC Penggantian Capasitor 3 - 5 PK unit 325,000

1.10.28.02.01.003.031 Pemeliharaan AC Penggantian Overload semua jenis/tipe AC unit 375,000

20
Penggantian Termistor semua jenis/tipe
1.10.28.02.01.003.032 Pemeliharaan AC unit 175,000
AC
Service Komputer/Pengecekan PC semua
1.10.28.02.01.003.033 Pemeliharaan Komputer unit/kali 100,000
jenis PC + jasa
1.10.28.02.01.003.034 Pemeliharaan Komputer Jasa Back Up Data unit 100,000
1.10.28.02.01.003.035 Pemeliharaan Komputer Jasa Update Antivirus/Cleaning Virus unit 75,000
1.10.28.02.01.003.036 Pemeliharaan Komputer Jasa Pembersihan PC dari debu unit 50,000
Install Windows + Software Standar semua
1.10.28.02.01.003.037 Pemeliharaan Komputer unit/kali 150,000
jenis PC + jasa
Install Windows + Software Standar +
1.10.28.02.01.003.038 Pemeliharaan Komputer unit/kali 200,000
Setting Outlook semua jenis PC + jasa
Install Windows + Software Standart +
1.10.28.02.01.003.039 Pemeliharaan Komputer unit/kali 230,000
Back Up Data Data < 50 Gb + jasa
Install Windows + Software Standart +
1.10.28.02.01.003.040 Pemeliharaan Komputer unit/kali 250,000
Back Up Data Data 50 - 60 Gb + jasa

Install Windows+Software Standart+Back


1.10.28.02.01.003.041 Pemeliharaan Komputer unit/kali 310,000
Up Data Data 60 - 80 Gb + jasa

Install Windows + Software Standart +


1.10.28.02.01.003.042 Pemeliharaan Komputer unit/kali 330,000
Back Up Data Data > 80 Gb + jasa
1.10.28.02.01.003.043 Pemeliharaan Komputer Install Program Desain - PHOTOSHOP unit/kali 75,000
1.10.28.02.01.003.044 Pemeliharaan Komputer Install Program Desain - CORELDRAW unit/kali 75,000
1.10.28.02.01.003.045 Pemeliharaan Komputer Install Program Desain - ACAD unit/kali 80,000
1.10.28.02.01.003.046 Pemeliharaan Komputer Install Program Desain - 3D MAX unit/kali 80,000
Service Laptop / Pengecekan + Bongkar
1.10.28.02.01.003.047 Pemeliharaan Komputer unit/kali 150,000
Semua jenis laptop + Jasa
Service + Ganti fun Semua jenis laptop +
1.10.28.02.01.003.048 Pemeliharaan Komputer unit/kali 350,000
Jasa
Install Windows + Software Standar semua
1.10.28.02.01.003.049 Pemeliharaan Komputer unit/kali 150,000
jenis PC + jasa
Install Windows + Software Standar +
1.10.28.02.01.003.050 Pemeliharaan Komputer unit/kali 200,000
Setting Outlook semua jenis PC + jasa

Install Windows+Software Standart+Back


1.10.28.02.01.003.051 Pemeliharaan Komputer unit/kali 230,000
Up Data Data < 50 Gb + jasa

Install Windows+Software Standart+Back


1.10.28.02.01.003.052 Pemeliharaan Komputer unit/kali 250,000
Up Data Data 50 - 60 Gb + jasa

Install Windows+Software Standart+Back


1.10.28.02.01.003.053 Pemeliharaan Komputer unit/kali 310,000
Up Data Data 60 - 80 Gb + jasa

Install Windows+Software Standart+Back


1.10.28.02.01.003.054 Pemeliharaan Komputer unit/kali 330,000
Up Data Data > 80 Gb + jasa

Setting LAN dan Sharing data - Printer


1.10.28.02.01.003.055 Pemeliharaan Komputer/Printer unit 125,000
Semua jenis PC
Instalasi LAN dan Sharing data - Printer
1.10.28.02.01.003.056 Pemeliharaan Komputer/Printer unit 350,000
Semua jenis PC
Ganti Busi, Setara Honda Accord Type
1.10.28.02.01.003.057 Pemeliharaan Kendaraan (Service Rutin) unit 2,230,800
CP3 3500cc
Ganti Filter Bensin, Setara Honda Accord
1.10.28.02.01.003.058 Pemeliharaan Kendaraan (Service Rutin) unit 764,500
Type CP3 3500cc
Ganti Filter Udara, Setara Honda Accord
1.10.28.02.01.003.059 Pemeliharaan Kendaraan (Service Rutin) unit 359,700
Type CP3 3500cc

21
Ganti O. Injektor, Setara Honda Accord
1.10.28.02.01.003.060 Pemeliharaan Kendaraan (Service Rutin) unit 928,400
Type CP3 3500cc
Ganti Filter AC, Setara Honda Accord
1.10.28.02.01.003.061 Pemeliharaan Kendaraan (Service Rutin) unit 300,300
Type CP3 3500cc
Ganti Busi, Setara Honda CR-V Type RE3
1.10.28.02.01.003.062 Pemeliharaan Kendaraan (Service Rutin) unit 101,200
2400cc
Ganti Filter Bensin, Setara Honda CR-V
1.10.28.02.01.003.063 Pemeliharaan Kendaraan (Service Rutin) unit 1,008,700
Type RE3 2400cc
Ganti Filter Udara, Setara Honda CR-V
1.10.28.02.01.003.064 Pemeliharaan Kendaraan (Service Rutin) unit 199,100
Type RE3 2400cc
Ganti O. Injektor, Setara Honda CR-V
1.10.28.02.01.003.065 Pemeliharaan Kendaraan (Service Rutin) unit 325,600
Type RE3 2400cc
Ganti Filter AC, Setara Honda CR-V Type
1.10.28.02.01.003.066 Pemeliharaan Kendaraan (Service Rutin) unit 300,300
RE3 2400cc
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.067 Biaya Jasa+Part; Setara Avanza unit 849,000
Per 10.000/70.000/90.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.068 Biaya Jasa+Part; Setara Avanza unit 888,000
Per 20.000/60.000/140.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.069 Biaya Jasa+Part; Setara Avanza unit 849,000
Per 30.000/50.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.070 Biaya Jasa+Part; Setara Avanza unit 1,544,000
Per 40.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.071 Biaya Jasa+Part; Setara Avanza unit 1,640,000
Per 80.000/240.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.072 Biaya Jasa+Part; Setara Avanza unit 1,248,000
Per 100.000/300.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.073 Biaya Jasa+Part; Setara Rush unit 996,000
Per 10.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.074 Biaya Jasa+Part; Setara Rush unit 1,155,000
Per 20.000/100.000/300.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.075 Biaya Jasa+Part; Setara Rush unit 2,489,000
Per 30.000/50.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.076 Biaya Jasa+Part; Setara Rush unit 1,816,000
Per 40.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.077 Biaya Jasa+Part; Setara Rush unit 1,861,000
Per 60.000/140.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.078 Biaya Jasa+Part; Setara Rush unit 2,844,000
Per 70.000/90.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.079 Biaya Jasa+Part; Setara Rush unit 2,649,000
Per 80.000/240.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.080 Biaya Jasa+Part; Setara Innova unit 1,249,000
Per 10.000/30.000/50.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.081 Biaya Jasa+Part; Setara Innova unit 1,409,000
Per 20.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.082 Biaya Jasa+Part; Setara Innova unit 2,278,000
Per 40.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.083 Biaya Jasa+Part; Setara Innova unit 1,440,000
Per 60.000/140.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.084 Biaya Jasa+Part; Setara Innova unit 1,283,000
Per 70.000/90.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.085 Biaya Jasa+Part; Setara Innova unit 2,658,000
Per 80.000/240.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.086 Biaya Jasa+Part; Setara Innova unit 1,611,000
Per 100.000/300.000 KM

22
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.087 Biaya Jasa+Part; Setara Fortuner unit 1,724,000
Per 10.000/30.000/50.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.088 Biaya Jasa+Part; Setara Fortuner unit 1,906,000
Per 20.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.089 Biaya Jasa+Part; Setara Fortuner unit 2,847,000
Per 40.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.090 Biaya Jasa+Part; Setara Fortuner unit 1,937,000
Per 60.000/140.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.091 Biaya Jasa+Part; Setara Fortuner unit 1,758,000
Per 70.000/90.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.092 Biaya Jasa+Part; Setara Fortuner unit 3,367,000
Per 80.000/240.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.093 Biaya Jasa+Part; Setara Fortuner unit 1,611,000
Per 100.000/300.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.094 Biaya Jasa+Part; Setara Camry unit 1,683,000
Per 10.000/30.000/50.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.095 Biaya Jasa+Part; Setara Camry unit 1,869,000
Per 20.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.096 Biaya Jasa+Part; Setara Camry unit 2,363,000
Per 40.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.097 Biaya Jasa+Part; Setara Camry unit 1,859,000
Per 60.000/140.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.098 Biaya Jasa+Part; Setara Camry unit 1,673,000
Per 70.000/90.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.099 Biaya Jasa+Part; Setara Camry unit 3,223,000
Per 80.000/240.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.100 Biaya Jasa+Part; Setara Camry unit 2,991,000
Per 100.000/300.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.101 Biaya Jasa+Part; Setara Hilux unit 1,108,000
Per 10.000/30.000/50.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.102 Biaya Jasa+Part; Setara Hilux unit 1,185,000
Per 20.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.103 Biaya Jasa+Part; Setara Hilux unit 2,198,000
Per 40.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.104 Biaya Jasa+Part; Setara Hilux unit 1,265,000
Per 60.000/100.000/140.000/300.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.105 Biaya Jasa+Part; Setara Hilux unit 1,133,000
Per 70.000/90.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.106 Biaya Jasa+Part; Setara Hilux unit 2,464,000
Per 80.000/240.000 KM
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Clutch (Jasa+Part); Setara
1.10.28.02.01.003.107 unit 2,003,000
Cadang Avanza
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Depan 1 Sisi
1.10.28.02.01.003.108 unit 1,221,000
Cadang (Jasa+Part); Setara Avanza
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Belakang 1
1.10.28.02.01.003.109 unit 552,000
Cadang Sisi (Jasa+Part); Setara Avanza
Pemeliharaan Kendaraan - Penggantian Suku
1.10.28.02.01.003.110 Biaya Ganti Clutch (Jasa+Part); Setara Rush unit 2,003,000
Cadang
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Depan 1 Sisi
1.10.28.02.01.003.111 unit 1,381,000
Cadang (Jasa+Part); Setara Rush
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Belakang 1
1.10.28.02.01.003.112 unit 609,000
Cadang Sisi (Jasa+Part); Setara Rush
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Clutch (Jasa+Part); Setara
1.10.28.02.01.003.113 unit 4,055,000
Cadang Innova

23
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Depan 1 Sisi
1.10.28.02.01.003.114 unit 2,214,000
Cadang (Jasa+Part); Setara Innova
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Belakang 1
1.10.28.02.01.003.115 unit 559,000
Cadang Sisi (Jasa+Part); Setara Innova
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Clutch (Jasa+Part); Setara
1.10.28.02.01.003.116 unit 4,473,000
Cadang Fortuner
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Depan 1 Sisi
1.10.28.02.01.003.117 unit 2,408,000
Cadang (Jasa+Part); Setara Fortuner
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Belakang 1
1.10.28.02.01.003.118 unit 662,000
Cadang Sisi (Jasa+Part); Setara Fortuner
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Clutch (Jasa+Part); Setara
1.10.28.02.01.003.119 unit 3,934,000
Cadang Camry
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Depan 1 Sisi
1.10.28.02.01.003.120 unit 2,978,000
Cadang (Jasa+Part); Setara Camry
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Belakang 1
1.10.28.02.01.003.121 unit 3,243,000
Cadang Sisi (Jasa+Part); Setara Camry
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Clutch (Jasa+Part); Setara
1.10.28.02.01.003.122 unit 4,283,000
Cadang Hilux
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Depan 1 Sisi
1.10.28.02.01.003.123 unit 2,135,000
Cadang (Jasa+Part); Setara Hilux
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Belakang 1
1.10.28.02.01.003.124 unit 477,000
Cadang Sisi (Jasa+Part); Setara Hilux

Pemeliharaan Kendaraan - Service Berkala


1.10.28.02.01.003.125 Biaya Jasa+Part; Setara Vios unit 1,109,000
Per 10.000/30.000/50.000/70.000/90.000 KM

Pemeliharaan Kendaraan - Service Berkala


1.10.28.02.01.003.126 Biaya Jasa+Part; Setara Vios unit 1,160,000
Per 20.000/60.000/140.000/100.000/300.000 KM

Pemeliharaan Kendaraan - Service Berkala


1.10.28.02.01.003.127 Biaya Jasa+Part; Setara Vios unit 1,847,000
Per 40.000 KM
Pemeliharaan Kendaraan - Service Berkala
1.10.28.02.01.003.128 Biaya Jasa+Part; Setara Vios unit 2,217,000
Per 80.000/240.000 KM
Pemeliharaan Kendaraan - Penggantian Suku
1.10.28.02.01.003.129 Biaya Ganti Clutch (Jasa+Part); Setara Vios unit 4,344,000
Cadang
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Depan 1 Sisi
1.10.28.02.01.003.130 unit 2,211,000
Cadang (Jasa+Part); Setara Vios
Pemeliharaan Kendaraan - Penggantian Suku Biaya Ganti Shock Absorber Belakang 1
1.10.28.02.01.003.131 unit 1,348,000
Cadang Sisi (Jasa+Part); Setara Vios
Biaya Service Fingerprint semua jenis non
1.10.28.02.01.003.132 Pemeliharaan Fingerprint unit 250,000
transport
Biaya Backup Mesin Absen semua jenis
1.10.28.02.01.003.133 Pemeliharaan Fingerprint unit 300,000
non transport
Biaya Penggantian Sparepart Casing
1.10.28.02.01.003.134 Pemeliharaan Fingerprint unit 800,000
Fingerprint (Include Jasa+Part)
1.10.28.02.01.003.135 Pemeliharaan Alat Vitek 2 Compact unit 7,567,560
1.10.28.02.01.003.136 Refil catridge tipe 85A, 83A, 35A + Jasa Pemeliharaan Printer unit 69,000
1.10.28.02.01.003.137 Refil catridge tipe 49A, 05A, 80A + Jasa Pemeliharaan Printer unit 115,000
1.10.28.02.01.003.138 Refil catridge tipe HL 1000 + Jasa Pemeliharaan Printer unit 143,750
1.10.28.02.01.003.139 Refil catridge tipe DR 2255 + Jasa Pemeliharaan Printer unit 172,500

1.10.28.02.01.003.140 Refil catridge tipe ML1915, 3155, 1660 + Jasa Pemeliharaan Printer unit 149,500

1.10.28.02.01.003.141 Refil catridge tipe CP1025 + Jasa Pemeliharaan Printer unit 201,250
1.10.28.02.01.003.142 Refil catridge tipe PRO200 + Jasa Pemeliharaan Printer unit 316,250
1.10.28.02.01.003.143 Refil catridge tipe 26A + Jasa Pemeliharaan Printer unit 143,750
1.10.28.02.01.003.144 Refil catridge tipe 17A + Jasa Pemeliharaan Printer unit 115,000

24
Pemeliharaan Tabung Pemadam
1.10.28.02.01.003.145 Refill Dry Chemical Powder kg 40,000
Kebakaran
Pemeliharaan Tabung Pemadam
1.10.28.02.01.003.146 Refill Carbon Dioxide (CO2) kg 45,000
Kebakaran
Pemeliharaan Tabung Pemadam
1.10.28.02.01.003.147 Refill Foam (AFFF) AB dan liquid kg 40,000
Kebakaran
Pemeliharaan Tabung Pemadam
1.10.28.02.01.003.148 Refill Liquid Gas HCFC kg 275,000
Kebakaran

1.10.28.02.01.003.149 Pemeliharaan Genset lebih kecil dari 50 KVa unit/tahun 7,190,000

1.10.28.02.01.003.150 Pemeliharaan Genset 75 KVA unit/tahun 8,640,000


1.10.28.02.01.003.151 Pemeliharaan Genset 100 KVA unit/tahun 10,150,000
1.10.28.02.01.003.152 Pemeliharaan Genset 125 KVA unit/tahun 10,780,000
1.10.28.02.01.003.153 Pemeliharaan Genset 150 KVA unit/tahun 13,260,000
1.10.28.02.01.003.154 Pemeliharaan Genset 175 KVA unit/tahun 14,810,000
1.10.28.02.01.003.155 Pemeliharaan Genset 200 KVA unit/tahun 15,850,000
1.10.28.02.01.003.156 Pemeliharaan Genset 250 KVA unit/tahun 16,790,000
1.10.28.02.01.003.157 Pemeliharaan Genset 275 KVA unit/tahun 17,760,000
1.10.28.02.01.003.158 Pemeliharaan Genset 300 KVA unit/tahun 20,960,000
1.10.28.02.01.003.159 Pemeliharaan Genset 350 KVA unit/tahun 22,960,000
1.10.28.02.01.003.160 Pemeliharaan Genset 450 KVA unit/tahun 25,620,000
1.10.28.02.01.003.161 Pemeliharaan Genset 500 KVA unit/tahun 31,770,000
Pengisian Ulang Alat Pemadam Kebakaran Pemeliharaan Tabung Pemadam
1.10.28.02.01.003.162 kg 750,000
Halotron 1 Kebakaran
Pengisian Ulang Alat Pemadam Kebakaran Pemeliharaan Tabung Pemadam
1.10.28.02.01.003.163 kg 650,000
AF11 Kebakaran
Perbaikan Alat Autoclave (tekanan pada alat
1.10.28.02.01.003.164 Pemeliharaan Alat Kesehatan unit 2,000,000
tidak bisa naik)
Perbaikan Alat Hot Plate (pemanas tidak
1.10.28.02.01.003.165 Pemeliharaan Alat Kesehatan unit 2,000,000
berfungsi)

1.10.28.02.01.003.166 Perbaikan Alat Kulkas( isi freon dan service) Pemeliharaan Alat Kesehatan unit 2,000,000

Perbaikan Alat Turbidimeter (alat tidak bisa


1.10.28.02.01.003.167 Pemeliharaan Alat Kesehatan unit 2,000,000
membaca sampel)
Perbaikan Alat Waterbath (suhu alat tidak
1.10.28.02.01.003.168 Pemeliharaan Alat Kesehatan unit 2,000,000
berfungsi)
1.10.28.02.01.003.169 Pemeliharaan Meubelair Perbaikan / plitur meja kursi kantor Unit / set 150,000
1.10.28.02.01.003.170 Pemeliharaan Meubelair Pasang Bekled (Jok) Kursi Unit / buah 400,000
1.10.28.02.01.003.171 Pemeliharaan service sound system Peralatan Kantor unit 250,000
1.10.28.02.01.003.172 Pemeliharaan service RIG, HT, Repiter Peralatan Kantor unit 150,000
1.10.28.02.01.003.173 Pemeliharaan service mesin ketik Peralatan Kantor unit 150,000
Pemeliharaan service mesin penghancur
1.10.28.02.01.003.174 Peralatan Kantor unit 150,000
kertas
1.10.28.02.01.003.175 Pemeliharaan service mesin fax Peralatan Kantor unit 250,000
1.10.28.02.01.003.176 Pemeliharaan service mesin fotocopy Peralatan Kantor unit 350,000
1.10.28.02.01.003.177 Pemeliharaan service kamera digital Peralatan Kantor unit 500,000
Pemeliharaan/Perawatan Videotron LED Regular checking, maintenance dan
1.10.28.02.01.003.178 tahun 30,000,000
Display trouble shooting
Pemeliharaan Peralatan Jaringan dan
1.10.28.02.01.003.179 Instalasi Jaringan Titik 500,000
Telekomunikasi
1.10.28.02.01.003.180 Pemeliharaan Smoke Tester Alat Uji Kendaraan unit/tahun 10,000,000
1.10.28.02.01.003.181 Pemeliharaan Gas Analizer Alat Uji Kendaraan unit/tahun 10,000,000
1.10.28.02.01.003.182 Pemeliharaan Side Slip Tester Alat Uji Kendaraan unit/tahun 10,000,000
1.10.28.02.01.003.183 Pemeliharaan Head Lamp Tester Alat Uji Kendaraan unit/tahun 6,000,000
1.10.28.02.01.003.184 Pemeliharaan Loadcell Tester Alat Uji Kendaraan unit/tahun 11,000,000

25
1.10.28.02.01.003.185 Pemeliharaan Break Tester Alat Uji Kendaraan unit/tahun 11,000,000
1.10.28.02.01.003.186 Pemeliharaan Spidometer Tester Alat Uji Kendaraan unit/tahun 9,000,000
1.10.28.02.01.003.187 Pemeliharaan Sound Level Tester Alat Uji Kendaraan unit/tahun 5,000,000
1.10.28.02.01.003.188 Pemeliharaan Playditector Alat Uji Kendaraan unit/tahun 8,000,000
1.10.28.02.01.003.189 Pemeliharaan Pintu Kaca Otomatis Alat Uji Kendaraan unit 6,000,000
1.10.28.02.01.003.190 Pemeliharaan Televisi Alat Uji Kendaraan unit 5,000,000
Pemeliharaan / Service Kunci / Gembok
1.10.28.02.01.003.191 Pemeliharaan Meubelair unit 250,000
Pintu
1.10.28.02.01.004 Satuan Biaya Kegiatan Pengujian
Smoke Tester, Gas Analizer, Head Lamp
Tester, Side Slip Tester, Loadcell Tester,
1.10.28.02.01.004.001 Biaya Kalibrasi Alat Uji Kendaraan unit 1,000,000
Break Tester, Spidometer Tester, Sound
Level Tester
Jasa + Bahan Uji (parameter yang diuji:
Biaya Pengujian Emisi Sumber Tidak
1.10.28.02.01.004.002 SO2, Debu,Opasitas dan Laju Air Titik 4,050,000
Bergerak (Cerobong)
(pengukuran 15 menit)
Jasa + Bahan Uji (Pengujian selama 24jam;
O3, NO2, Debu TSP, NH3, H25, HC, SO2,
1.10.28.02.01.004.003 Biaya Pengujian Udara Ambien Sampel 2,725,000
Pb, Kecepatan angin, Temperatur dan
kelembapan)

Jasa + Bahan Uji Air sungai, Air Danau,


Air Embung, Air Badan Air (Parameter
yang diuji; Suhu, TSS, TDS, pH, BOD,
1.10.28.02.01.004.004 Biaya Pengujian Air Badan Air COD, DO, PO4, NO3, NO2, NH4, Co, Cd, Sampel 1,683,500
Cr6+, Cu, Fe, Pb, Mn, Hg, Zn, Cl-, CN, F,
SO4, H2S, Cl2 bebas, Detergen, Fenol,
Minyak Lemak, Fecal dan TotalColiform)

Uji TCLP (Cu, Cr 6+, Cd, Pb, Hg, Zn, F,


1.10.28.02.01.004.005 Biaya Pengujian Limbah Padat/Slugde Sampel 2,178,000
NO3, NO2, CN, Ni, Fe, Mn, Cr tot, Co)
Biaya Pengujian Air Limbah Industri (Inlet Jasa + Bahan Uji (Air Limbah Domestik;
1.10.28.02.01.004.006 Sampel 1,500,000
dan Outlet) pH, TSS, BOD, Minyak Lemak)
1.10.28.02.01.004.007 Biaya Pengujian Air Hujan Konduktifitas, SO4, NO3, Cr, NH4 total Titik 1,400,000
1.10.28.02.01.004.008 Biaya Kalibrasi Alat Inkubator unit 800,000
1.10.28.02.01.004.009 Biaya Kalibrasi Alat Autoclave unit 900,000
1.10.28.02.01.004.010 Biaya Kalibrasi Alat Timbangan Analitik unit 600,000
1.10.28.02.01.004.011 Biaya Kalibrasi Alat Waterbath unit 750,000
1.10.28.02.01.004.012 Biaya Kalibrasi Alat Oven unit 800,000
1.10.28.02.01.004.013 Biaya Kalibrasi Alat Thermoreaktor unit 700,000
1.10.28.02.01.004.014 Biaya Kalibrasi Alat pH Meter unit 600,000
1.10.28.02.01.004.015 Biaya Kalibrasi Alat DHL unit 2,000,000
1.10.28.02.01.004.016 Biaya Kalibrasi Alat Thermohygrometer unit 900,000
1.10.28.02.01.004.017 Biaya Kalibrasi Alat Thermometer raksa unit 800,000
1.10.28.02.01.004.018 Biaya Kalibrasi Alat Thermometer digital unit 800,000
1.10.28.02.01.004.019 Biaya Kalibrasi Alat Spektrofotometer UV-Vis unit 5,000,000
1.10.28.02.01.004.020 Biaya Kalibrasi Alat Anak Timbangan unit 1,000,000
1.10.28.02.01.004.021 Biaya Kalibrasi Alat Turbidimeter unit 2,000,000
1.10.28.02.01.004.022 Biaya Kalibrasi Alat Centrifuge unit 990,000
1.10.28.02.01.004.023 Biaya Kalibrasi Alat Tensimeter Raksa unit 950,000
1.10.28.02.01.004.024 Biaya Kalibrasi Alat Tensimeter Digital unit 950,000
1.10.28.02.01.004.025 Biaya Kalibrasi Alat Timbangan Badan unit 1,100,000
1.10.28.02.01.004.026 Biaya Kalibrasi Alat Lemari Es unit 1,100,000
1.10.28.02.01.004.027 Biaya Kalibrasi Alat Lux Meter unit 2,160,000
1.10.28.02.01.004.028 Biaya Kalibrasi Alat Sound Level Meter unit 3,300,000
1.10.28.02.01.004.029 Biaya Kalibrasi Alat Buret unit 685,000

26
1.10.28.02.01.004.030 Pemeriksaan Kimia Air Bersih Sampel 500,000
1.10.28.02.01.004.031 Pemeriksaan Mikrobiologi Air Bersih Sampel 150,000
1.10.28.02.01.004.032 Pemeriksaan Mikrobiologi Air Limbah MPN kuman gol. Coli Tinja/Faecal Coli Sampel 143,000
1.10.28.02.01.004.033 Pemeriksaan Mikrobiologi Air Limbah MPN kuman gol. Coli/Total Coliform Sampel 176,000
1.10.28.02.01.004.034 Pemeriksaan Usap Alat Medis Sampel 74,000
1.10.28.02.01.004.035 Pemeriksaan Usap Lantai/Dinding Sampel 74,000
1.10.28.02.01.004.036 Pemeriksaan Udara Ruang Sampel 400,000
Pemeriksaan Mutu Eksternal atau Uji
1.10.28.02.01.004.037 Profisiensi Pelayanan Laboratorium Kimia klinik paket 1,100,000
Kesehatan
Pemeriksaan Mutu Eksternal atau Uji
1.10.28.02.01.004.038 Profisiensi Pelayanan Laboratorium Hematologi paket 1,100,000
Kesehatan
Pemeriksaan Mutu Eksternal atau Uji
1.10.28.02.01.004.039 Profisiensi Pelayanan Laboratorium Urinalisa paket 900,000
Kesehatan
Pemeriksaan Mutu Eksternal atau Uji
1.10.28.02.01.004.040 Profisiensi Pelayanan Laboratorium Mikroskopis BTA paket 600,000
Kesehatan
Pemeriksaan Mutu Eksternal atau Uji
1.10.28.02.01.004.041 Profisiensi Pelayanan Laboratorium Mikroskopis telur cacing paket 350,000
Kesehatan
Pemeriksaan Mutu Eksternal atau Uji
1.10.28.02.01.004.042 Profisiensi Pelayanan Laboratorium Anti HIV paket 1,400,000
Kesehatan
Pemeriksaan Mutu Eksternal atau Uji
1.10.28.02.01.004.043 Profisiensi Pelayanan Laboratorium Syphilis paket 1,400,000
Kesehatan
Pemeriksaan Mutu Eksternal atau Uji
1.10.28.02.01.004.044 Profisiensi Pelayanan Laboratorium HbsAg paket 1,300,000
Kesehatan
Pemeriksaan Mutu Eksternal atau Uji
1.10.28.02.01.004.045 Profisiensi Pelayanan Laboratorium Anti HCV paket 1,300,000
Kesehatan
Pemeriksaan Mutu Eksternal atau Uji
1.10.28.02.01.004.046 Profisiensi Pelayanan Laboratorium Kimia air paket 2,200,000
Kesehatan
Pemeriksaan Mutu Eksternal atau Uji
1.10.28.02.01.004.047 Profisiensi Pelayanan Laboratorium Kimia air terbatas paket 900,000
Kesehatan
1.10.28.02.01.004.048 Jasa Uji Mutu Obat Organoleptik Sampel 30,000
1.10.28.02.01.004.049 Jasa Uji Mutu Obat Penetapan kadar Sampel 500,000
1.10.28.02.01.004.050 Jasa Uji Mutu Obat Keseragaman kandungan Sampel 500,000
1.10.28.02.01.004.051 Jasa Uji Mutu Obat Uji dissolusi (spektrofotometri) Sampel 500,000
1.10.28.02.01.004.052 Jasa Uji Mutu Obat Keragaman bobot Sampel 60,000
1.10.28.02.01.004.053 Jasa Uji Mutu Obat pH Sampel 50,000
1.10.28.02.01.004.054 Jasa Uji Mutu Obat Volume Terpindahkan Sampel 60,000
1.10.28.02.01.004.055 Sampel Bahan Uji Lab Aspal Sampel 250,000
Uji Profisiensi Pemeriksaan Air Minum dan
1.10.28.02.01.004.056 Sampel 3,831,800
Air Limbah

1.10.28.02.01.004.057 Uji Profisiensi Pemeriksaan Mutu Eksternal Pelayanan Labkes (Kimia Klinik) Sampel 1,500,000

1.10.28.02.01.004.058 Uji Profisiensi Pemeriksaan Mutu Eksternal Pelayanan Labkes (Hematologi) Sampel 1,900,000

27
1.10.28.02.01.004.059 Uji Profisiensi Pemeriksaan Mutu Eksternal Pelayanan Labkes (Urinalisa) Sampel 1,500,000

1.10.28.02.01.004.060 Uji Profisiensi Pemeriksaan Mutu Eksternal Pelayanan Labkes (Mikros BTA) Sampel 750,000

1.10.28.02.01.004.061 Uji Profisiensi Pemeriksaan Mutu Eksternal Pelayanan Labkes (Telur Cacing) Sampel 750,000

1.10.28.02.01.004.062 Jasa Uji Sampel Kain Sampel 2,500,000


1.10.28.02.01.004.063 Biaya Pengujian Emisi Asap Incenerator Sampel 4,500,000
Biaya Pengujian Air Limbah Industri (Inlet Jasa + Bahan Uji (Air Lindi/TPA; COD,
1.10.28.02.01.004.064 Sampel
dan Outlet) pH, TSS, BOD, Cd, Hg, N Total)
Biaya Pengujian Air Limbah Industri (Inlet Jasa + Bahan Uji (Air Limbah Rumah Sakit;
1.10.28.02.01.004.065 Sampel
dan Outlet) Fisika, Kimia, Bakteriologi)

Jasa + Bahan Uji (Air Limbah Industri;


Suhu, TDS, TSS, pH, Fe, Mn, Cu, Zn, Cr6+,
Biaya Pengujian Air Limbah Industri (Inlet
1.10.28.02.01.004.066 Cr tot, Cd, Hg, Pb, Ni, Co, Cn, H2S, F, CL2 Sampel
dan Outlet)
Bebas, NH4. NO3, NO2, BOD, COD,
Detergen, Fenol, Minyak Lemak)

Jasa + Bahan Uji (Air Limbah Industri


kegiatan Laboratorium Klinik; Suhu, TSS,
Biaya Pengujian Air Limbah Industri (Inlet
1.10.28.02.01.004.067 pH, BOD, COD, NH4, PO4 Ortho, CL2 Sampel
dan Outlet)
Bebas, Kuman Golongan Koli Tinja,
Detergen, Fenol, Minyak Lemak)
Jasa + Bahan Uji (Air Limbah Kawasan
Biaya Pengujian Air Limbah Industri (Inlet Industri; Suhu, TSS, pH, COD, H2S, BOD,
1.10.28.02.01.004.068 Sampel
dan Outlet) NH4, Cd, Cr6+, Cr tot, Cu, Pb, Ni, Zn,
Detergen, Fenol, Minyak Lemak)
1.10.28.02.01.004.069 Biaya Pengujian Limbah Padat/Slugde Plankton dan Bentos Sampel 591,000

1.10.28.02.01.004.070 Biaya Pengujian Limbah Padat/Slugde Jasa Pengambilan Contoh Uji/Sampel/Titik Sampel 450,000

Jasa + Bahan Uji (Pengujian udara setiap


1jam; SO2, CO, NO2, O3, TSP, NH3, H2S,
1.10.28.02.01.004.071 Biaya Pengujian Udara Ambien Sampel
HC, Pb, Kecepatan angin, Temperatur dan
kelembapan)

1.10.28.02.01.005 Satuan Biaya Kegiatan Fisik Konstruksi


1.10.28.02.01.005.001 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 100 Jt paket 5,000,000
1.10.28.02.01.005.002 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 250 Jt paket 10,000,000
1.10.28.02.01.005.003 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 500 Jt paket 20,000,000
1.10.28.02.01.005.004 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 750 Jt paket 30,000,000
1.10.28.02.01.005.005 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 1 milliar paket 40,000,000
1.10.28.02.01.005.006 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 1,50 milliar paket 45,000,000
1.10.28.02.01.005.007 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 2 milliar paket 60,000,000
1.10.28.02.01.005.008 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 2,50 milliar paket 75,000,000
1.10.28.02.01.005.009 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 3 milliar paket 90,000,000
1.10.28.02.01.005.010 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 3,50 milliar paket 105,000,000
1.10.28.02.01.005.011 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 4 milliar paket 120,000,000
1.10.28.02.01.005.012 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 4,50 milliar paket 135,000,000
1.10.28.02.01.005.013 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 5 milliar paket 150,000,000
1.10.28.02.01.005.014 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 5,50 milliar paket 165,000,000
1.10.28.02.01.005.015 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 6 milliar paket 180,000,000
1.10.28.02.01.005.016 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 6,50 milliar paket 195,000,000
1.10.28.02.01.005.017 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 7 milliar paket 210,000,000
1.10.28.02.01.005.018 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 8,50 milliar paket 255,000,000
1.10.28.02.01.005.019 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 9 milliar paket 270,000,000

28
1.10.28.02.01.005.020 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 9,50 milliar paket 285,000,000
1.10.28.02.01.005.021 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 10 milliar paket 300,000,000
1.10.28.02.01.005.022 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 20 milliar paket 600,000,000
1.10.28.02.01.005.023 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 30 milliar paket 900,000,000
1.10.28.02.01.005.024 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 40 milliar paket 1,200,000,000
1.10.28.02.01.005.025 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan s.d 50 milliar paket 1,500,000,000
1.10.28.02.01.005.026 Biaya Perencanaan Teknis Konstruksi Nilai Pekerjaan diatas 50 milliar paket 3,000,000,000
1.10.28.02.01.005.027 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 100 Jt paket 4,000,000
1.10.28.02.01.005.028 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 250 Jt paket 7,500,000
1.10.28.02.01.005.029 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 500 Jt paket 15,000,000
1.10.28.02.01.005.030 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 750 Jt paket 22,500,000
1.10.28.02.01.005.031 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 1 milliar paket 30,000,000
1.10.28.02.01.005.032 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 1,50 milliar paket 30,000,000
1.10.28.02.01.005.033 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 2 milliar paket 40,000,000
1.10.28.02.01.005.034 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 2,50 milliar paket 50,000,000
1.10.28.02.01.005.035 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 3 milliar paket 60,000,000
1.10.28.02.01.005.036 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 3,50 milliar paket 70,000,000
1.10.28.02.01.005.037 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 4 milliar paket 80,000,000
1.10.28.02.01.005.038 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 4,50 milliar paket 90,000,000
1.10.28.02.01.005.039 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 5 milliar paket 100,000,000
1.10.28.02.01.005.040 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 5,50 milliar paket 110,000,000
1.10.28.02.01.005.041 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 6 milliar paket 120,000,000
1.10.28.02.01.005.042 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 6,50 milliar paket 130,000,000
1.10.28.02.01.005.043 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 7 milliar paket 140,000,000
1.10.28.02.01.005.044 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 8,50 milliar paket 170,000,000
1.10.28.02.01.005.045 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 9 milliar paket 180,000,000
1.10.28.02.01.005.046 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 9,50 milliar paket 190,000,000
1.10.28.02.01.005.047 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 10 milliar paket 200,000,000
1.10.28.02.01.005.048 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 20 milliar paket 400,000,000
1.10.28.02.01.005.049 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 30 milliar paket 600,000,000
1.10.28.02.01.005.050 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 40 milliar paket 800,000,000
1.10.28.02.01.005.051 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan s.d 50 milliar paket 1,000,000,000
1.10.28.02.01.005.052 Biaya Pengawasan Teknis Konstruksi Nilai Pekerjaan diatas 50 milliar paket 2,000,000,000
1.10.28.02.01.005.053 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 100 Jt paket 5,000,000
1.10.28.02.01.005.054 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 250 Jt paket 10,000,000
1.10.28.02.01.005.055 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 500 Jt paket 20,000,000
1.10.28.02.01.005.056 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 750 Jt paket 30,000,000
1.10.28.02.01.005.057 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 1 milliar paket 40,000,000
1.10.28.02.01.005.058 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 1,50 milliar paket 45,000,000
1.10.28.02.01.005.059 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 2 milliar paket 60,000,000
1.10.28.02.01.005.060 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 2,50 milliar paket 75,000,000
1.10.28.02.01.005.061 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 3 milliar paket 90,000,000
1.10.28.02.01.005.062 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 3,50 milliar paket 105,000,000
1.10.28.02.01.005.063 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 4 milliar paket 120,000,000
1.10.28.02.01.005.064 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 4,50 milliar paket 135,000,000
1.10.28.02.01.005.065 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 5 milliar paket 150,000,000
1.10.28.02.01.005.066 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 5,50 milliar paket 165,000,000
1.10.28.02.01.005.067 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 6 milliar paket 180,000,000
1.10.28.02.01.005.068 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 6,50 milliar paket 195,000,000
1.10.28.02.01.005.069 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 7 milliar paket 210,000,000
1.10.28.02.01.005.070 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 8,50 milliar paket 255,000,000
1.10.28.02.01.005.071 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 9 milliar paket 270,000,000
1.10.28.02.01.005.072 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 9,50 milliar paket 285,000,000
1.10.28.02.01.005.073 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 10 milliar paket 300,000,000
1.10.28.02.01.005.074 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 20 milliar paket 600,000,000

29
1.10.28.02.01.005.075 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 30 milliar paket 900,000,000
1.10.28.02.01.005.076 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 40 milliar paket 1,200,000,000
1.10.28.02.01.005.077 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan s.d 50 milliar paket 1,500,000,000
1.10.28.02.01.005.078 Biaya Administrasi Kegiatan Konstruksi Nilai Pekerjaan diatas 50 milliar paket 3,000,000,000
1.10.28.02.01.099 Upah/Jasa Sektor Fisik Lain - lain
1.10.28.02.02 Upah/Jasa Sektor Non Fisik
1.10.28.02.02.001 Upah/Jasa dengan Satuan (Orang/Bulan)
1.10.28.02.02.001.001 Jasa Pengemudi/Sopir OB 2,200,000
Jasa Petugas Kebersihan, Petugas
1.10.28.02.02.001.002 Jasa Petugas Kebersihan Kebersihan Kantor, Pengemudi, OB 2,200,000
Pramubakti
1.10.28.02.02.001.003 Jasa Penyusun Naskah Sambutan Humas dan Protokol OB 300,000
1.10.28.02.02.001.004 Jasa Koordinator Humas dan Protokol OB 600,000
1.10.28.02.02.001.005 Jasa Anggota Humas dan Protokol OB 500,000
1.10.28.02.02.001.006 Jasa Pembuat naskah Pidato Kepala Daerah Humas dan Protokol OB 350,000
1.10.28.02.02.001.007 Jasa Penyusun Release Humas dan Protokol OB 350,000
1.10.28.02.02.001.008 Jasa Pengelola Media Sosial Humas dan Protokol OB 350,000
1.10.28.02.02.001.009 Jasa Pengelola Videotrone Humas dan Protokol OB 350,000
1.10.28.02.02.001.010 Jasa Pemilah Arsip Petugas Arsip OB 350,000
1.10.28.02.02.001.011 Petugas tindak lanjut pelayanan kesehatan Jasa Petugas Kesehatan OB 2,260,000
1.10.28.02.02.001.012 Tenaga Komunikator Jasa Petugas Kesehatan OB 2,260,000
1.10.28.02.02.001.013 Tenaga Verifikator Jasa Petugas Kesehatan OB 2,260,000
1.10.28.02.02.001.014 Jasa Peliputan Kegiatan Humas dan Protokol OB 500,000
1.10.28.02.02.001.015 Jasa Technical Support Network Minimal Ijasah SMK OB 2,260,000
1.10.28.02.02.001.016 Jasa Network Administrator Ijasah S1 OB 3,500,000
1.10.28.02.02.001.017 Jasa Petugas penjaga TMP OB 2,260,000
1.10.28.02.02.001.019 Jasa Petugas Keamanan OB 2,260,000
1.10.28.02.02.001.020 Jasa Laundry Kesehatan OB 2,260,000
1.10.28.02.02.001.021 Jasa Juru Masak Rawat Inap OB 2,260,000
1.10.28.02.02.001.022 Jasa TAGANA ( Tanggap Bencana ) OB 200,000
1.10.28.02.02.001.023 Jasa Petugas Sandi OB 300,000
1.10.28.02.02.001.025 Jasa Pengawas Lapangan TPS OB 150,000
Jasa Petugas Analisa Data Base (ADB)
1.10.28.02.02.001.026 OB 350,000
Kependudukan
1.10.28.02.02.001.028 Jasa Administrator Website OB 400,000
1.10.28.02.02.001.030 Jasa Tutor paket C OB 300,000
1.10.28.02.02.001.031 Jasa Tutor paket B OB 250,000
1.10.28.02.02.001.032 Jasa Pengelola Paket B/C OB 200,000
1.10.28.02.02.001.033 Jasa Penyelenggara Paket B/C OB 175,000
Memiliki kompetensi penguji kendaraan
Jasa Tenaga Kerja Pembantu Penguji bermotor dari Dirjen perhubungan darat,
1.10.28.02.02.001.034 OB 2,000,000
Kendaraan Bermotor (Non PNS) lulusan DII/DIII Pengujian Kendaraan
bermotor Rp. 2.300.000
1.10.28.02.02.001.035 Jasa Tenaga Kerja Operator ATCS OB 2,260,000
Honorarium Teknisi Listrik untuk
1.10.28.02.02.001.036 Jasa Tenaga Kerja Teknisi Perbengkelan OB 1,800,000
Rusunawa
1.10.28.02.02.001.037 Jasa Petugas Juru Parkir OB 400,000
1.10.28.02.02.001.038 Upah/Jasa Manajer Telecenter OB 2,260,000
Ijazah Min SMA/SMK; Kemampuan
1.10.28.02.02.001.039 Upah/Jasa Sekretaris Telecenter bidang aplikasi perkantoran (MS Office OB 2,260,000
dan Internet)
Ijazah Min SMA/SMK; Kemampuan
Upah/Jasa Tenaga Kerja Bagian
1.10.28.02.02.001.040 bidang aplikasi perkantoran (MS Office OB 2,260,000
Pengembangan dan Pelayanan Telecenter
dan Internet)

30
Ijazah Min SMA/SMK; Kemampuan
Upah/Jasa Tenaga Kerja Bagian Teknologi
1.10.28.02.02.001.041 bidang aplikasi perkantoran (MS Office OB 2,260,000
Informasi Telecenter
dan Internet)
1.10.28.02.02.001.042 Honor Kader KB PPKBK OB 75,000
1.10.28.02.02.001.043 Honor Sub Kader KB PPKBK OB 50,000
1.10.28.02.02.001.045 Honor Pengelola PIK OB 50,000
1.10.28.02.02.001.046 Honor Pembina Pramuka/Ekstra OB 300,000
1.10.28.02.02.001.047 Tenaga Kerja Perawatan Tanaman OB 750,000
1.10.28.02.02.001.048 Jasa Dokter Umum PTT Provinsi OB 3,000,000
1.10.28.02.02.001.049 Jasa Analisa Pemberitaan Media Massa bulan 16,500,000

Guru TPQ, Guru Sekolah Minggu, Coster,


1.10.28.02.02.001.050 Upah/Jasa Tenaga Kerja dibidang Keagamaan Mudin, Muadzin, Takmir Masjid/Mushola, OB 125,000
Pemandi Jenazah, Penjaga Makam

1.10.28.02.02.001.051 Jurnalis OB 2,000,000


1.10.28.02.02.001.052 Reporter OB 2,750,000
1.10.28.02.02.001.053 Video Editor OB 2,750,000
1.10.28.02.02.001.054 Honor pembantu penerima pkb bulan/orang 312,500
1.10.28.02.02.001.055 Pengendali Teknis Tenaga Fasilitator Lapangan (TFL) bulan 3,200,000
Tenaga Kesejahteraan Sosial, Relawan
1.10.28.02.02.001.056 Honor Pekerja Sosial Profesional OB 300,000
Sosial
1.10.28.02.02.001.057 Petugas Pelayanan SLRT Fasilitator SLRT OB 200,000
1.10.28.02.02.001.058 Petugas Pelayanan SLRT Manajer SLRT OB 1,000,000
1.10.28.02.02.001.059 Petugas Pelayanan SLRT Petugas Front Office / Back Office SLRT OB 500,000
1.10.28.02.02.001.060 Honor Tim P2TP2A Ketua Tim OB 500,000
1.10.28.02.02.001.061 Honor Tim P2TP2A Anggota Tim OB 150,000
1.10.28.02.02.001.062 Honor Tim P2TP2A Tenaga Ahli Psikologi OB 400,000
1.10.28.02.02.002 Upah/Jasa dengan Satuan (Orang/Hari)
Jasa Pendukung Kegiatan Seminar/ Rakor/
1.10.28.02.02.002.001 Moderator Sosialisasi/ Diseminasi / FGD / Bintek OH 700,000
(Kegiatan Sejenis)
Jasa Pendukung Kegiatan Seminar/ Rakor/
1.10.28.02.02.002.002 Pembawa Acara Sosialisasi/ Diseminasi / FGD / Bintek OH 400,000
(Kegiatan Sejenis)
Jasa Pendukung Kegiatan Seminar/ Rakor/
1.10.28.02.02.002.003 Pembaca Doa Sosialisasi/ Diseminasi / FGD / Bintek OH 200,000
(Kegiatan Sejenis)
1.10.28.02.02.002.004 Uang Saku Atlet OH 100,000
1.10.28.02.02.002.005 Uang Saku Official OH 200,000
1.10.28.02.02.002.006 Jasa Juri Profesional / Juri Propinsi OH 1,000,000
1.10.28.02.02.002.007 Jasa Juri Internal Pemda OH 350,000
Jasa Anggota Satgas Pengamanan Kepolisian
1.10.28.02.02.002.008 OH 100,000
/ TNI
1.10.28.02.02.002.009 Jasa Pengamanan Linmas (Hansip) OH 75,000
1.10.28.02.02.002.010 Jasa Pelatih Paskibra OH 400,000
1.10.28.02.02.002.011 Jasa Asst. Pelatih Paskibra OH 150,000
1.10.28.02.02.002.012 Jasa Petugas Seleksi Paskibra OH 150,000
1.10.28.02.02.002.013 Jasa Pembina Purna Paskibra OH 100,000
1.10.28.02.02.002.014 Jasa Pengawal/Patwal OH 100,000
1.10.28.02.02.002.015 Jasa Komandan Upacara OH 150,000
1.10.28.02.02.002.016 Jasa Perwira Upacara OH 200,000
1.10.28.02.02.002.017 Jasa Bendel Arsip Petugas Arsip OH 35,000
1.10.28.02.02.002.018 Jasa Angkut Arsip Petugas Arsip OH 35,000
1.10.28.02.02.002.019 Tenaga Paramedis Jasa Petugas Kesehatan OH 50,000

31
Pelayanan Kesehatan Masyarakat Miskin
1.10.28.02.02.002.020 Jasa Petugas Kesehatan OH 50,000
(Jamkesmas) - APBN
Pelayanan Kesehatan Masyarakat Miskin
1.10.28.02.02.002.021 Jasa Petugas Kesehatan OH 35,000
(Jamkesmas) - APBD
1.10.28.02.02.002.022 Dokter umum Jasa Petugas Kesehatan OH 150,000
1.10.28.02.02.002.023 Dokter Kejiwaan Jasa Petugas Kesehatan OH 200,000
1.10.28.02.02.002.024 Perawat Umum Jasa Petugas Kesehatan OH 100,000
1.10.28.02.02.002.025 Perawat Jiwa Jasa Petugas Kesehatan OH 125,000
Jasa Peliputan Inspeksi Mendadak dan
1.10.28.02.02.002.026 OH 150,000
Jumpa Pers
1.10.28.02.02.002.027 Jasa Pemandu Bahasa Asing OH 250,000
1.10.28.02.02.002.028 Jasa Surveyor OH 50,000
1.10.28.02.02.002.029 Jasa Pembantu Surveyor OH 40,000

1.10.28.02.02.002.030 Jasa Verifikasi Nota Pertimbangan Pangkat OH 50,000

1.10.28.02.02.002.031 Jasa Petugas Kebersihan Kegiatan OH 50,000


1.10.28.02.02.002.033 Jasa Pramusaji OH 50,000
1.10.28.02.02.002.034 Jasa Sopir Angkutan Orang (Rental) OH 150,000
Kegiatan Pelatihan menggunakan Alat
1.10.28.02.02.002.035 Jasa Asisten Narasumber OH 250,000
Peraga/Bahan Praktek
1.10.28.02.02.002.036 Jasa Petugas korsik OH 250,000
1.10.28.02.02.002.037 Jasa Petugas Koor OH 100,000
1.10.28.02.02.002.038 Jasa Petugas keamanan OH 100,000
1.10.28.02.02.002.039 Jasa Petugas Kesehatan OH 100,000
1.10.28.02.02.002.040 Jasa Petugas Kebersihan OH 50,000
1.10.28.02.02.002.041 Jasa Petugas Pengibar Bendera OH 100,000
1.10.28.02.02.002.042 Jasa Komandan Upacara & Dan Kompi OH 150,000
1.10.28.02.02.002.043 Jasa Pengatur Barisan OH 100,000
Jasa Pembaca UUD 1945/Panca Prasetya
1.10.28.02.02.002.044 OH 100,000
KORPRI
1.10.28.02.02.002.045 Buruh Tani OH 50,000
1.10.28.02.02.002.046 Tenaga Kerja Potong Jerami OH 80,000
1.10.28.02.02.002.047 Tenaga Kerja Penyemprotan OH 200,000
1.10.28.02.02.002.048 Jasa Tenaga Assesor OH 500,000
1.10.28.02.02.003 Upah/Jasa dengan Satuan (Orang/Jam)
Jasa Narasumber Kegiatan Seminar/ Rakor/
Menteri / pejabat setingkat Menteri/
1.10.28.02.02.003.001 Sosialisasi/ Diseminasi / FGD / Bintek OJ 2,500,000
Pejabat Negara Lainnya/yang disetarakan
(Kegiatan Sejenis)
Jasa Narasumber Kegiatan Seminar/ Rakor/
1.10.28.02.02.003.002 Sosialisasi/ Diseminasi / FGD / Bintek Pejabat Eselon I / yang disetarakan OJ 1,750,000
(Kegiatan Sejenis)
Jasa Narasumber Kegiatan Seminar/ Rakor/
1.10.28.02.02.003.003 Sosialisasi/ Diseminasi / FGD / Bintek Pejabat Eselon II / yang disetarakan OJ 1,000,000
(Kegiatan Sejenis)
Jasa Narasumber Kegiatan Seminar/ Rakor/
Pejabat Eselon III ke bawah / yang
1.10.28.02.02.003.004 Sosialisasi/ Diseminasi / FGD / Bintek OJ 900,000
disetarakan
(Kegiatan Sejenis)
Jasa Narasumber Kegiatan Seminar/ Rakor/
Pakar/Praktisi/Pembicara Khusus/Tenaga
1.10.28.02.02.003.005 Sosialisasi/ Diseminasi / FGD / Bintek OJ 1,700,000
Ahli
(Kegiatan Sejenis)
Jasa Pendukung Kegiatan Seminar/ Rakor/
1.10.28.02.02.003.006 Penyuluh Sosialisasi/ Diseminasi / FGD / Bintek OJ 250,000
(Kegiatan Sejenis)
1.10.28.02.02.003.007 Jasa Pelatih Seni OJ 300,000
1.10.28.02.02.003.008 Jasa Pelatih Olah Raga OJ 300,000

32
Kegiatan Batikku Batikmu, Pemilihan Gus
1.10.28.02.02.003.009 Jasa Juri Profesional dan Yuk (Duta Wisata), Pemilihan Gus, OJ 1,250,000
dan Yuk Cilik
1.10.28.02.02.003.010 Jasa Penyiar Radio OJ 30,000
1.10.28.02.02.003.011 Jasa Pelatih Petugas Keamanan OJ 300,000
1.10.28.02.02.004 Upah/Jasa dengan Satuan (Orang/Kegiatan)
1.10.28.02.02.004.001 Jasa Master of Ceremony (MC) Profesional per acara 500,000
Jasa Master of Ceremony (MC) Non
1.10.28.02.02.004.002 per acara 250,000
Profesional
1.10.28.02.02.004.003 Jasa Pembaca Al Qur'an per acara 150,000
Instruktur pelatihan/ Narasumber/ Jasa
1.10.28.02.02.004.004 Jasa Instruktur Senam OK 300,000
Tenaga Ahli

per
1.10.28.02.02.004.005 Wasit Per Paket Pertandingan 300,000
pertandingan

Tim Wasit ( lbh dr satu orang pada per


1.10.28.02.02.004.006 Jasa Wasit Perorangan 300,000
perlombaan atletik ) pertandingan

1.10.28.02.02.004.007 Biaya Make Up & Sanggul orang 350,000

1.10.28.02.02.004.008 Biaya Make Up & Sanggul Untuk Pengantin orang 750,000

1.10.28.02.02.004.009 Rias Pengantin Bentuk Basahan orang 1,000,000


1.10.28.02.02.004.010 Rias Pengantin Bentuk Solo orang 1,000,000
1.10.28.02.02.004.011 Rias Pengantin Bentuk Muslim orang 1,000,000
1.10.28.02.02.004.012 Rias Karakter Pekohan orang 350,000
1.10.28.02.02.004.013 Rias Cantik Bersanggul orang 400,000
1.10.28.02.02.004.014 Rias Cantik Tanpa Sanggul orang 300,000
1.10.28.02.02.004.015 Tenaga Kurir per kegiatan 35,000
Kepala/Supervisor Regu Penyemprotan orang
1.10.28.02.02.004.016 Jasa Petugas Kesehatan 100,000
Nyamuk/Lalat kegiatan
orang
1.10.28.02.02.004.017 Petugas Epidemologi Jasa Petugas Kesehatan 75,000
kegiatan
1.10.28.02.02.004.018 Jasa Petugas Penyemprotan Nyamuk/Lalat Jasa Tenaga Kesehatan/Penyemprot orang hari 75,000
1.10.28.02.02.004.019 Fasilitator Jasa Petugas Kesehatan OK 700,000
Dokter Spesialis (Keg. Penyuluhan &
1.10.28.02.02.004.020 Jasa Petugas Kesehatan OK 2,000,000
Pemeriksaan)
1.10.28.02.02.004.021 Jasa Juri Internal Pawai Pembangunan OK 500,000
1.10.28.02.02.004.022 Tenaga Bumbun OK 1,500,000
1.10.28.02.02.004.023 Tenaga Klentek OK 700,000
1.10.28.02.02.004.024 Tenaga Pengolahan Lahan 0,5 Ha OK 1,800,000
1.10.28.02.02.004.025 Biaya Borongan Pengairan OK 1,000,000
1.10.28.02.02.004.026 Tenaga potong bibit tebu dan tanam OK 1,500,000
1.10.28.02.02.005 Upah/Jasa dengan Satuan Lainnya
1.10.28.02.02.005.001 Jasa Kurir Barang per alamat 5,000
1.10.28.02.02.005.002 Jasa Pos Luar Kota Luar Propinsi Surat 3,500
1.10.28.02.02.005.003 Jasa Pos Dalam Kota Surat 2,000
1.10.28.02.02.005.004 Jasa Kurir Surat per alamat 750
1.10.28.02.02.005.005 Jasa Instalasi, setting dan pointing radio per radio 2,500,000

1.10.28.02.02.005.006 Jasa Pemasangan dan Pembongkaran Tower per meter 100,000

1.10.28.02.02.005.007 Jasa Pengecatan Tower Monopole Upah dan Bahan per meter 75,000
Jasa Pengecetan Tower Triangle beton ulir 13
1.10.28.02.02.005.008 Upah dan Bahan per meter 125,000
SII
Jasa Penggantian Kawat Seling Tower
1.10.28.02.02.005.009 Upah dan Bahan per meter 175,000
Monopole

33
Jasa Penggantian Kawat Seling Tower
1.10.28.02.02.005.010 Upah dan Bahan per meter 250,000
Triangle
1.10.28.02.02.005.011 Jasa Entry Data Honorarium Operator E-Mon DAK bulan 500,000
1.10.28.02.02.005.012 Jasa Surveyor orang titik 8,000
1.10.28.02.02.005.013 Jasa Dokter Terapis SLB/Berkebutuhan Khusus orang/anak 850,000
1.10.28.02.02.005.014 Biaya Jahit Pakaian potong 100,000
1.10.28.02.02.005.015 Biaya Jahit Pakaian stell 200,000
1.10.28.02.02.005.016 Jasa Laundry Cuci + Setrika kg 7,300
1.10.28.02.02.005.017 Jasa Cucian Korden m' 7,300
1.10.28.02.02.005.018 Jasa Scan dokumen/arsip lembar 2,500

Pemasangan selang monito; Pemasangan


lembar penutup; Pemasangan Sand Snake;
Pengukuran Vol.Komoditas; Penentuan
1.10.28.02.02.005.019 Jasa Fumigasi jumlah Fumigan; Pendistribusian m2 45,000
Fumigan; Deteksi Kebocoran Gas;
Pembebasan ruang fumigasi dr fumigan;
Pengemasan Alat dan bahan

1.10.28.02.02.005.020 Ongkos Jahit Staf orang 100,000


1.10.28.02.02.005.021 Ongkos Jahit Eselon IV orang 150,000
1.10.28.02.02.005.022 Ongkos Jahit Eselon III orang 200,000
1.10.28.02.02.005.023 Ongkos Jahit Eselon II orang 250,000
1.10.28.02.02.005.024 Jasa Karikatur Dimensi wajah/lukisan per edisi 380,000
1.10.28.02.02.005.025 Petugas penempel per edisi 100,000
1.10.28.02.02.005.026 Design / Layout per hal 25,000
1.10.28.02.02.005.027 Jasa MOP/ MOW pasien 2,800,000
per lubang
1.10.28.02.02.005.028 Tenaga borongan lubang tanam 3,000
tanam
1.10.28.02.02.005.029 Pemeliharaan dan perbaikan biling system paket 3,500,000
orang/kunjun
1.10.28.02.02.005.030 Dokter Spesialis 500,000
gan
orang/kunjun
1.10.28.02.02.005.031 Psikolog 500,000
gan
1.10.28.02.02.005.032 Jasa Layanan Juru Parkir tahun 200,000
Duurasi 2-4 menit, 1080 HD, Frame Width
1.10.28.02.02.005.033 Jasa Pembuatan Video dokumen 5,000,000
1280, Frame Height 720,
1.10.28.02.02.005.034 Jasa Surveyor laporan 25,000
1.10.28.02.02.005.035 Jasa Pengemudi/Sopir Jasa Sedot Tinja (IPAL KOMUNAL) m3 500,000
1.10.28.02.02.005.036 Pengelasan cm 3,036
1.10.28.02.03 Upah/Jasa Konsultansi
1.10.28.02.03.001 Tenaga Ahli Fisik
1.10.28.02.03.001.001 AHLI MUDA S1 (Pengalaman Kerja) 1 Th OB 16,280,000
1.10.28.02.03.001.002 AHLI MUDA S1 (Pengalaman Kerja) 2 Th OB 17,600,000
1.10.28.02.03.001.003 AHLI MUDA S1 (Pengalaman Kerja) 3 Th OB 18,920,000
1.10.28.02.03.001.004 AHLI MUDA S1 (Pengalaman Kerja) 4 Th OB 20,240,000
1.10.28.02.03.001.005 AHLI MUDA S1 (Pengalaman Kerja) 5 Th OB 21,560,000
1.10.28.02.03.001.006 AHLI MUDA S1 (Pengalaman Kerja) 6 Th OB 22,880,000
1.10.28.02.03.001.007 AHLI MUDA S1 (Pengalaman Kerja) 7 Th OB 24,200,000
1.10.28.02.03.001.008 AHLI MUDA S1 (Pengalaman Kerja) 8 Th OB 25,520,000
1.10.28.02.03.001.009 AHLI MUDA S1 (Pengalaman Kerja) 9 Th OB 26,840,000
1.10.28.02.03.001.010 AHLI MUDA S1 (Pengalaman Kerja) 10 Th OB 28,160,000
1.10.28.02.03.001.011 AHLI MUDA S1 (Pengalaman Kerja) 11 Th OB 29,480,000
1.10.28.02.03.001.012 AHLI MUDA S1 (Pengalaman Kerja) 12 Th OB 30,800,000
1.10.28.02.03.001.013 AHLI MUDA S1 (Pengalaman Kerja) 13 Th OB 32,120,000
1.10.28.02.03.001.014 AHLI MUDA S1 (Pengalaman Kerja) 14 Th OB 33,440,000

34
1.10.28.02.03.001.015 AHLI MUDA S1 (Pengalaman Kerja) 15 Th OB 34,760,000
1.10.28.02.03.001.016 AHLI MUDA S1 (Pengalaman Kerja) 16 Th OB 36,080,000
1.10.28.02.03.001.017 AHLI MUDA S1 (Pengalaman Kerja) 17 Th OB 37,400,000
1.10.28.02.03.001.018 AHLI MUDA S1 (Pengalaman Kerja) 18 Th OB 38,720,000
1.10.28.02.03.001.019 AHLI MUDA S1 (Pengalaman Kerja) 19 Th OB 40,040,000
1.10.28.02.03.001.020 AHLI MUDA S1 (Pengalaman Kerja) 20 Th OB 41,360,000
1.10.28.02.03.001.021 AHLI MUDA S1 (Pengalaman Kerja) 21 Th OB 42,680,000
1.10.28.02.03.001.022 AHLI MUDA S1 (Pengalaman Kerja) 22 Th OB 44,000,000
1.10.28.02.03.001.023 AHLI MUDA S1 (Pengalaman Kerja) 23 Th OB 45,320,000
1.10.28.02.03.001.024 AHLI MUDA S2 (Pengalaman Kerja) 1 Th OB 23,980,000
1.10.28.02.03.001.025 AHLI MUDA S2 (Pengalaman Kerja) 2 Th OB 25,740,000
1.10.28.02.03.001.026 AHLI MUDA S2 (Pengalaman Kerja) 3 Th OB 27,280,000
1.10.28.02.03.001.027 AHLI MUDA S2 (Pengalaman Kerja) 4 Th OB 28,820,000
1.10.28.02.03.001.028 AHLI MUDA S2 (Pengalaman Kerja) 5 Th OB 30,580,000
1.10.28.02.03.001.029 AHLI MUDA S2 (Pengalaman Kerja) 6 Th OB 32,120,000
1.10.28.02.03.001.030 AHLI MUDA S2 (Pengalaman Kerja) 7 Th OB 33,660,000
1.10.28.02.03.001.031 AHLI MUDA S2 (Pengalaman Kerja) 8 Th OB 35,420,000
1.10.28.02.03.001.032 AHLI MUDA S2 (Pengalaman Kerja) 9 Th OB 36,960,000
1.10.28.02.03.001.033 AHLI MUDA S2 (Pengalaman Kerja) 10 Th OB 38,500,000
1.10.28.02.03.001.034 AHLI MUDA S2 (Pengalaman Kerja) 11 Th OB 40,260,000
1.10.28.02.03.001.035 AHLI MUDA S2 (Pengalaman Kerja) 12 Th OB 41,800,000
1.10.28.02.03.001.036 AHLI MUDA S2 (Pengalaman Kerja) 13 Th OB 43,340,000
1.10.28.02.03.001.037 AHLI MUDA S2 (Pengalaman Kerja) 14 Th OB 45,100,000
1.10.28.02.03.001.038 AHLI MUDA S2 (Pengalaman Kerja) 15 Th OB 46,640,000
1.10.28.02.03.001.039 AHLI MUDA S2 (Pengalaman Kerja) 16 Th OB 48,180,000
1.10.28.02.03.001.040 AHLI MUDA S2 (Pengalaman Kerja) 17 Th OB 49,940,000
1.10.28.02.03.001.041 AHLI MUDA S2 (Pengalaman Kerja) 18 Th OB 51,480,000
1.10.28.02.03.001.042 AHLI MUDA S2 (Pengalaman Kerja) 19 Th OB 53,020,000
1.10.28.02.03.001.043 AHLI MUDA S2 (Pengalaman Kerja) 20 Th OB 54,780,000
1.10.28.02.03.001.044 AHLI MUDA S2 (Pengalaman Kerja) 21 Th OB 56,320,000
1.10.28.02.03.001.045 AHLI MUDA S2 (Pengalaman Kerja) 22 Th OB 57,860,000
1.10.28.02.03.001.046 AHLI MUDA S2 (Pengalaman Kerja) 23 Th OB 59,620,000
1.10.28.02.03.001.047 AHLI MUDA S3 (Pengalaman Kerja) 1 Th OB 30,140,000
1.10.28.02.03.001.048 AHLI MUDA S3 (Pengalaman Kerja) 2 Th OB 31,900,000
1.10.28.02.03.001.049 AHLI MUDA S3 (Pengalaman Kerja) 3 Th OB 33,660,000
1.10.28.02.03.001.050 AHLI MUDA S3 (Pengalaman Kerja) 4 Th OB 35,420,000
1.10.28.02.03.001.051 AHLI MUDA S3 (Pengalaman Kerja) 5 Th OB 37,180,000
1.10.28.02.03.001.052 AHLI MUDA S3 (Pengalaman Kerja) 6 Th OB 38,940,000
1.10.28.02.03.001.053 AHLI MUDA S3 (Pengalaman Kerja) 7 Th OB 40,700,000
1.10.28.02.03.001.054 AHLI MUDA S3 (Pengalaman Kerja) 8 Th OB 42,460,000
1.10.28.02.03.001.055 AHLI MUDA S3 (Pengalaman Kerja) 9 Th OB 44,220,000
1.10.28.02.03.001.056 AHLI MUDA S3 (Pengalaman Kerja) 10 Th OB 45,980,000
1.10.28.02.03.001.057 AHLI MUDA S3 (Pengalaman Kerja) 11 Th OB 47,740,000
1.10.28.02.03.001.058 AHLI MUDA S3 (Pengalaman Kerja) 12 Th OB 49,500,000
1.10.28.02.03.001.059 AHLI MUDA S3 (Pengalaman Kerja) 13 Th OB 51,260,000
1.10.28.02.03.001.060 AHLI MUDA S3 (Pengalaman Kerja) 14 Th OB 53,020,000
1.10.28.02.03.001.061 AHLI MUDA S3 (Pengalaman Kerja) 15 Th OB 54,780,000
1.10.28.02.03.001.062 AHLI MUDA S3 (Pengalaman Kerja) 16 Th OB 56,540,000
1.10.28.02.03.001.063 AHLI MUDA S3 (Pengalaman Kerja) 17 Th OB 58,300,000
1.10.28.02.03.001.064 AHLI MUDA S3 (Pengalaman Kerja) 18 Th OB 60,060,000
1.10.28.02.03.001.065 AHLI MUDA S3 (Pengalaman Kerja) 19 Th OB 61,820,000
1.10.28.02.03.001.066 AHLI MUDA S3 (Pengalaman Kerja) 20 Th OB 63,580,000
1.10.28.02.03.001.067 AHLI MUDA S3 (Pengalaman Kerja) 21 Th OB 65,340,000
1.10.28.02.03.001.068 AHLI MUDA S3 (Pengalaman Kerja) 22 Th OB 67,100,000
1.10.28.02.03.001.069 AHLI MUDA S3 (Pengalaman Kerja) 23 Th OB 68,860,000

35
1.10.28.02.03.001.070 AHLI MADYA S1 (Pengalaman Kerja) 1 Th OB 18,920,000
1.10.28.02.03.001.071 AHLI MADYA S1 (Pengalaman Kerja) 2 Th OB 20,240,000
1.10.28.02.03.001.072 AHLI MADYA S1 (Pengalaman Kerja) 3 Th OB 21,560,000
1.10.28.02.03.001.073 AHLI MADYA S1 (Pengalaman Kerja) 4 Th OB 22,880,000
1.10.28.02.03.001.074 AHLI MADYA S1 (Pengalaman Kerja) 5 Th OB 24,200,000
1.10.28.02.03.001.075 AHLI MADYA S1 (Pengalaman Kerja) 6 Th OB 25,520,000
1.10.28.02.03.001.076 AHLI MADYA S1 (Pengalaman Kerja) 7 Th OB 26,840,000
1.10.28.02.03.001.077 AHLI MADYA S1 (Pengalaman Kerja) 8 Th OB 28,160,000
1.10.28.02.03.001.078 AHLI MADYA S1 (Pengalaman Kerja) 9 Th OB 29,480,000
1.10.28.02.03.001.079 AHLI MADYA S1 (Pengalaman Kerja) 10 Th OB 30,800,000
1.10.28.02.03.001.080 AHLI MADYA S1 (Pengalaman Kerja) 11 Th OB 32,120,000
1.10.28.02.03.001.081 AHLI MADYA S1 (Pengalaman Kerja) 12 Th OB 33,440,000
1.10.28.02.03.001.082 AHLI MADYA S1 (Pengalaman Kerja) 13 Th OB 34,760,000
1.10.28.02.03.001.083 AHLI MADYA S1 (Pengalaman Kerja) 14 Th OB 36,080,000
1.10.28.02.03.001.084 AHLI MADYA S1 (Pengalaman Kerja) 15 Th OB 37,400,000
1.10.28.02.03.001.085 AHLI MADYA S1 (Pengalaman Kerja) 16 Th OB 38,720,000
1.10.28.02.03.001.086 AHLI MADYA S1 (Pengalaman Kerja) 17 Th OB 40,040,000
1.10.28.02.03.001.087 AHLI MADYA S1 (Pengalaman Kerja) 18 Th OB 41,360,000
1.10.28.02.03.001.088 AHLI MADYA S1 (Pengalaman Kerja) 19 Th OB 42,680,000
1.10.28.02.03.001.089 AHLI MADYA S1 (Pengalaman Kerja) 20 Th OB 44,000,000
1.10.28.02.03.001.090 AHLI MADYA S1 (Pengalaman Kerja) 21 Th OB 45,320,000
1.10.28.02.03.001.091 AHLI MADYA S2 (Pengalaman Kerja) 1 Th OB 27,280,000
1.10.28.02.03.001.092 AHLI MADYA S2 (Pengalaman Kerja) 2 Th OB 28,820,000
1.10.28.02.03.001.093 AHLI MADYA S2 (Pengalaman Kerja) 3 Th OB 30,580,000
1.10.28.02.03.001.094 AHLI MADYA S2 (Pengalaman Kerja) 4 Th OB 32,120,000
1.10.28.02.03.001.095 AHLI MADYA S2 (Pengalaman Kerja) 5 Th OB 33,660,000
1.10.28.02.03.001.096 AHLI MADYA S2 (Pengalaman Kerja) 6 Th OB 35,420,000
1.10.28.02.03.001.097 AHLI MADYA S2 (Pengalaman Kerja) 7 Th OB 36,960,000
1.10.28.02.03.001.098 AHLI MADYA S2 (Pengalaman Kerja) 8 Th OB 38,500,000
1.10.28.02.03.001.099 AHLI MADYA S2 (Pengalaman Kerja) 9 Th OB 40,260,000
1.10.28.02.03.001.100 AHLI MADYA S2 (Pengalaman Kerja) 10 Th OB 41,800,000
1.10.28.02.03.001.101 AHLI MADYA S2 (Pengalaman Kerja) 11 Th OB 43,340,000
1.10.28.02.03.001.102 AHLI MADYA S2 (Pengalaman Kerja) 12 Th OB 45,100,000
1.10.28.02.03.001.103 AHLI MADYA S2 (Pengalaman Kerja) 13 Th OB 46,640,000
1.10.28.02.03.001.104 AHLI MADYA S2 (Pengalaman Kerja) 14 Th OB 48,180,000
1.10.28.02.03.001.105 AHLI MADYA S2 (Pengalaman Kerja) 15 Th OB 49,940,000
1.10.28.02.03.001.106 AHLI MADYA S2 (Pengalaman Kerja) 16 Th OB 51,480,000
1.10.28.02.03.001.107 AHLI MADYA S2 (Pengalaman Kerja) 17 Th OB 53,020,000
1.10.28.02.03.001.108 AHLI MADYA S2 (Pengalaman Kerja) 18 Th OB 54,780,000
1.10.28.02.03.001.109 AHLI MADYA S2 (Pengalaman Kerja) 19 Th OB 56,320,000
1.10.28.02.03.001.110 AHLI MADYA S2 (Pengalaman Kerja) 20 Th OB 57,860,000
1.10.28.02.03.001.111 AHLI MADYA S2 (Pengalaman Kerja) 21 Th OB 59,620,000
1.10.28.02.03.001.112 AHLI MADYA S3 (Pengalaman Kerja) 1 Th OB 33,660,000
1.10.28.02.03.001.113 AHLI MADYA S3 (Pengalaman Kerja) 2 Th OB 35,420,000
1.10.28.02.03.001.114 AHLI MADYA S3 (Pengalaman Kerja) 3 Th OB 37,180,000
1.10.28.02.03.001.115 AHLI MADYA S3 (Pengalaman Kerja) 4 Th OB 38,940,000
1.10.28.02.03.001.116 AHLI MADYA S3 (Pengalaman Kerja) 5 Th OB 40,700,000
1.10.28.02.03.001.117 AHLI MADYA S3 (Pengalaman Kerja) 6 Th OB 42,460,000
1.10.28.02.03.001.118 AHLI MADYA S3 (Pengalaman Kerja) 7 Th OB 44,220,000
1.10.28.02.03.001.119 AHLI MADYA S3 (Pengalaman Kerja) 8 Th OB 45,980,000
1.10.28.02.03.001.120 AHLI MADYA S3 (Pengalaman Kerja) 9 Th OB 47,740,000
1.10.28.02.03.001.121 AHLI MADYA S3 (Pengalaman Kerja) 10 Th OB 49,500,000
1.10.28.02.03.001.122 AHLI MADYA S3 (Pengalaman Kerja) 11 Th OB 51,260,000
1.10.28.02.03.001.123 AHLI MADYA S3 (Pengalaman Kerja) 12 Th OB 53,020,000
1.10.28.02.03.001.124 AHLI MADYA S3 (Pengalaman Kerja) 13 Th OB 54,780,000

36
1.10.28.02.03.001.125 AHLI MADYA S3 (Pengalaman Kerja) 14 Th OB 56,540,000
1.10.28.02.03.001.126 AHLI MADYA S3 (Pengalaman Kerja) 15 Th OB 58,300,000
1.10.28.02.03.001.127 AHLI MADYA S3 (Pengalaman Kerja) 16 Th OB 60,060,000
1.10.28.02.03.001.128 AHLI MADYA S3 (Pengalaman Kerja) 17 Th OB 61,820,000
1.10.28.02.03.001.129 AHLI MADYA S3 (Pengalaman Kerja) 18 Th OB 63,580,000
1.10.28.02.03.001.130 AHLI MADYA S3 (Pengalaman Kerja) 19 Th OB 65,340,000
1.10.28.02.03.001.131 AHLI MADYA S3 (Pengalaman Kerja) 20 Th OB 67,100,000
1.10.28.02.03.001.132 AHLI MADYA S3 (Pengalaman Kerja) 21 Th OB 68,860,000
1.10.28.02.03.001.133 AHLI UTAMA S1 (Pengalaman Kerja) 1 Th OB 22,880,000
1.10.28.02.03.001.134 AHLI UTAMA S1 (Pengalaman Kerja) 2 Th OB 24,200,000
1.10.28.02.03.001.135 AHLI UTAMA S1 (Pengalaman Kerja) 3 Th OB 25,520,000
1.10.28.02.03.001.136 AHLI UTAMA S1 (Pengalaman Kerja) 4 Th OB 26,840,000
1.10.28.02.03.001.137 AHLI UTAMA S1 (Pengalaman Kerja) 5 Th OB 28,160,000
1.10.28.02.03.001.138 AHLI UTAMA S1 (Pengalaman Kerja) 6 Th OB 29,480,000
1.10.28.02.03.001.139 AHLI UTAMA S1 (Pengalaman Kerja) 7 Th OB 30,800,000
1.10.28.02.03.001.140 AHLI UTAMA S1 (Pengalaman Kerja) 8 Th OB 32,120,000
1.10.28.02.03.001.141 AHLI UTAMA S1 (Pengalaman Kerja) 9 Th OB 33,440,000
1.10.28.02.03.001.142 AHLI UTAMA S1 (Pengalaman Kerja) 10 Th OB 34,760,000
1.10.28.02.03.001.143 AHLI UTAMA S1 (Pengalaman Kerja) 11 Th OB 36,080,000
1.10.28.02.03.001.144 AHLI UTAMA S1 (Pengalaman Kerja) 12 Th OB 37,400,000
1.10.28.02.03.001.145 AHLI UTAMA S1 (Pengalaman Kerja) 13 Th OB 38,720,000
1.10.28.02.03.001.146 AHLI UTAMA S1 (Pengalaman Kerja) 14 Th OB 40,040,000
1.10.28.02.03.001.147 AHLI UTAMA S1 (Pengalaman Kerja) 15 Th OB 41,360,000
1.10.28.02.03.001.148 AHLI UTAMA S1 (Pengalaman Kerja) 16 Th OB 42,680,000
1.10.28.02.03.001.149 AHLI UTAMA S1 (Pengalaman Kerja) 17 Th OB 44,000,000
1.10.28.02.03.001.150 AHLI UTAMA S1 (Pengalaman Kerja) 18 Th OB 45,320,000
1.10.28.02.03.001.151 AHLI UTAMA S2 (Pengalaman Kerja) 1 Th OB 32,120,000
1.10.28.02.03.001.152 AHLI UTAMA S2 (Pengalaman Kerja) 2 Th OB 33,660,000
1.10.28.02.03.001.153 AHLI UTAMA S2 (Pengalaman Kerja) 3 Th OB 35,420,000
1.10.28.02.03.001.154 AHLI UTAMA S2 (Pengalaman Kerja) 4 Th OB 36,960,000
1.10.28.02.03.001.155 AHLI UTAMA S2 (Pengalaman Kerja) 5 Th OB 38,500,000
1.10.28.02.03.001.156 AHLI UTAMA S2 (Pengalaman Kerja) 6 Th OB 40,260,000
1.10.28.02.03.001.157 AHLI UTAMA S2 (Pengalaman Kerja) 7 Th OB 41,800,000
1.10.28.02.03.001.158 AHLI UTAMA S2 (Pengalaman Kerja) 8 Th OB 43,340,000
1.10.28.02.03.001.159 AHLI UTAMA S2 (Pengalaman Kerja) 9 Th OB 45,100,000
1.10.28.02.03.001.160 AHLI UTAMA S2 (Pengalaman Kerja) 10 Th OB 46,640,000
1.10.28.02.03.001.161 AHLI UTAMA S2 (Pengalaman Kerja) 11 Th OB 48,180,000
1.10.28.02.03.001.162 AHLI UTAMA S2 (Pengalaman Kerja) 12 Th OB 49,940,000
1.10.28.02.03.001.163 AHLI UTAMA S2 (Pengalaman Kerja) 13 Th OB 51,480,000
1.10.28.02.03.001.164 AHLI UTAMA S2 (Pengalaman Kerja) 14 Th OB 53,020,000
1.10.28.02.03.001.165 AHLI UTAMA S2 (Pengalaman Kerja) 15 Th OB 54,780,000
1.10.28.02.03.001.166 AHLI UTAMA S2 (Pengalaman Kerja) 16 Th OB 56,320,000
1.10.28.02.03.001.167 AHLI UTAMA S2 (Pengalaman Kerja) 17 Th OB 57,860,000
1.10.28.02.03.001.168 AHLI UTAMA S2 (Pengalaman Kerja) 18 Th OB 59,620,000
1.10.28.02.03.001.169 AHLI UTAMA S3 (Pengalaman Kerja) 1 Th OB 38,940,000
1.10.28.02.03.001.170 AHLI UTAMA S3 (Pengalaman Kerja) 2 Th OB 40,700,000
1.10.28.02.03.001.171 AHLI UTAMA S3 (Pengalaman Kerja) 3 Th OB 42,460,000
1.10.28.02.03.001.172 AHLI UTAMA S3 (Pengalaman Kerja) 4 Th OB 44,220,000
1.10.28.02.03.001.173 AHLI UTAMA S3 (Pengalaman Kerja) 5 Th OB 45,980,000
1.10.28.02.03.001.174 AHLI UTAMA S3 (Pengalaman Kerja) 6 Th OB 47,740,000
1.10.28.02.03.001.175 AHLI UTAMA S3 (Pengalaman Kerja) 7 Th OB 49,500,000
1.10.28.02.03.001.176 AHLI UTAMA S3 (Pengalaman Kerja) 8 Th OB 51,260,000
1.10.28.02.03.001.177 AHLI UTAMA S3 (Pengalaman Kerja) 9 Th OB 53,020,000
1.10.28.02.03.001.178 AHLI UTAMA S3 (Pengalaman Kerja) 10 Th OB 54,780,000
1.10.28.02.03.001.179 AHLI UTAMA S3 (Pengalaman Kerja) 11 Th OB 56,540,000

37
1.10.28.02.03.001.180 AHLI UTAMA S3 (Pengalaman Kerja) 12 Th OB 58,300,000
1.10.28.02.03.001.181 AHLI UTAMA S3 (Pengalaman Kerja) 13 Th OB 60,060,000
1.10.28.02.03.001.182 AHLI UTAMA S3 (Pengalaman Kerja) 14 Th OB 61,820,000
1.10.28.02.03.001.183 AHLI UTAMA S3 (Pengalaman Kerja) 15 Th OB 63,580,000
1.10.28.02.03.001.184 AHLI UTAMA S3 (Pengalaman Kerja) 16 Th OB 65,340,000
1.10.28.02.03.001.185 AHLI UTAMA S3 (Pengalaman Kerja) 17 Th OB 67,100,000
1.10.28.02.03.001.186 AHLI UTAMA S3 (Pengalaman Kerja) 18 Th OB 68,860,000
1.10.28.02.03.002 Tenaga Ahli Non Fisik
1.10.28.02.03.002.001 AHLI MUDA S1 (Pengalaman Kerja) 1 Th OB 4,070,000
1.10.28.02.03.002.002 AHLI MUDA S1 (Pengalaman Kerja) 2 Th OB 4,400,000
1.10.28.02.03.002.003 AHLI MUDA S1 (Pengalaman Kerja) 3 Th OB 4,730,000
1.10.28.02.03.002.004 AHLI MUDA S1 (Pengalaman Kerja) 4 Th OB 5,060,000
1.10.28.02.03.002.005 AHLI MUDA S1 (Pengalaman Kerja) 5 Th OB 5,390,000
1.10.28.02.03.002.006 AHLI MUDA S1 (Pengalaman Kerja) 6 Th OB 5,720,000
1.10.28.02.03.002.007 AHLI MUDA S1 (Pengalaman Kerja) 7 Th OB 6,050,000
1.10.28.02.03.002.008 AHLI MUDA S1 (Pengalaman Kerja) 8 Th OB 6,380,000
1.10.28.02.03.002.009 AHLI MUDA S1 (Pengalaman Kerja) 9 Th OB 6,710,000
1.10.28.02.03.002.010 AHLI MUDA S1 (Pengalaman Kerja) 10 Th OB 7,040,000
1.10.28.02.03.002.011 AHLI MUDA S1 (Pengalaman Kerja) 11 Th OB 7,370,000
1.10.28.02.03.002.012 AHLI MUDA S1 (Pengalaman Kerja) 12 Th OB 7,700,000
1.10.28.02.03.002.013 AHLI MUDA S1 (Pengalaman Kerja) 13 Th OB 8,030,000
1.10.28.02.03.002.014 AHLI MUDA S1 (Pengalaman Kerja) 14 Th OB 8,360,000
1.10.28.02.03.002.015 AHLI MUDA S1 (Pengalaman Kerja) 15 Th OB 8,690,000
1.10.28.02.03.002.016 AHLI MUDA S1 (Pengalaman Kerja) 16 Th OB 9,020,000
1.10.28.02.03.002.017 AHLI MUDA S1 (Pengalaman Kerja) 17 Th OB 9,350,000
1.10.28.02.03.002.018 AHLI MUDA S1 (Pengalaman Kerja) 18 Th OB 9,680,000
1.10.28.02.03.002.019 AHLI MUDA S1 (Pengalaman Kerja) 19 Th OB 10,010,000
1.10.28.02.03.002.020 AHLI MUDA S1 (Pengalaman Kerja) 20 Th OB 10,340,000
1.10.28.02.03.002.021 AHLI MUDA S1 (Pengalaman Kerja) 21 Th OB 10,670,000
1.10.28.02.03.002.022 AHLI MUDA S1 (Pengalaman Kerja) 22 Th OB 11,000,000
1.10.28.02.03.002.023 AHLI MUDA S1 (Pengalaman Kerja) 23 Th OB 11,330,000
1.10.28.02.03.002.024 AHLI MUDA S2 (Pengalaman Kerja) 1 Th OB 5,995,000
1.10.28.02.03.002.025 AHLI MUDA S2 (Pengalaman Kerja) 2 Th OB 6,435,000
1.10.28.02.03.002.026 AHLI MUDA S2 (Pengalaman Kerja) 3 Th OB 6,820,000
1.10.28.02.03.002.027 AHLI MUDA S2 (Pengalaman Kerja) 4 Th OB 7,205,000
1.10.28.02.03.002.028 AHLI MUDA S2 (Pengalaman Kerja) 5 Th OB 7,645,000
1.10.28.02.03.002.029 AHLI MUDA S2 (Pengalaman Kerja) 6 Th OB 8,030,000
1.10.28.02.03.002.030 AHLI MUDA S2 (Pengalaman Kerja) 7 Th OB 8,415,000
1.10.28.02.03.002.031 AHLI MUDA S2 (Pengalaman Kerja) 8 Th OB 8,855,000
1.10.28.02.03.002.032 AHLI MUDA S2 (Pengalaman Kerja) 9 Th OB 9,240,000
1.10.28.02.03.002.033 AHLI MUDA S2 (Pengalaman Kerja) 10 Th OB 9,625,000
1.10.28.02.03.002.034 AHLI MUDA S2 (Pengalaman Kerja) 11 Th OB 10,065,000
1.10.28.02.03.002.035 AHLI MUDA S2 (Pengalaman Kerja) 12 Th OB 10,450,000
1.10.28.02.03.002.036 AHLI MUDA S2 (Pengalaman Kerja) 13 Th OB 10,835,000
1.10.28.02.03.002.037 AHLI MUDA S2 (Pengalaman Kerja) 14 Th OB 11,275,000
1.10.28.02.03.002.038 AHLI MUDA S2 (Pengalaman Kerja) 15 Th OB 11,660,000
1.10.28.02.03.002.039 AHLI MUDA S2 (Pengalaman Kerja) 16 Th OB 12,045,000
1.10.28.02.03.002.040 AHLI MUDA S2 (Pengalaman Kerja) 17 Th OB 12,485,000
1.10.28.02.03.002.041 AHLI MUDA S2 (Pengalaman Kerja) 18 Th OB 12,870,000
1.10.28.02.03.002.042 AHLI MUDA S2 (Pengalaman Kerja) 19 Th OB 13,255,000
1.10.28.02.03.002.043 AHLI MUDA S2 (Pengalaman Kerja) 20 Th OB 13,695,000
1.10.28.02.03.002.044 AHLI MUDA S2 (Pengalaman Kerja) 21 Th OB 14,080,000
1.10.28.02.03.002.045 AHLI MUDA S2 (Pengalaman Kerja) 22 Th OB 14,465,000
1.10.28.02.03.002.046 AHLI MUDA S2 (Pengalaman Kerja) 23 Th OB 14,905,000
1.10.28.02.03.002.047 AHLI MUDA S3 (Pengalaman Kerja) 1 Th OB 7,535,000

38
1.10.28.02.03.002.048 AHLI MUDA S3 (Pengalaman Kerja) 2 Th OB 7,975,000
1.10.28.02.03.002.049 AHLI MUDA S3 (Pengalaman Kerja) 3 Th OB 8,415,000
1.10.28.02.03.002.050 AHLI MUDA S3 (Pengalaman Kerja) 4 Th OB 8,855,000
1.10.28.02.03.002.051 AHLI MUDA S3 (Pengalaman Kerja) 5 Th OB 9,295,000
1.10.28.02.03.002.052 AHLI MUDA S3 (Pengalaman Kerja) 6 Th OB 9,735,000
1.10.28.02.03.002.053 AHLI MUDA S3 (Pengalaman Kerja) 7 Th OB 10,175,000
1.10.28.02.03.002.054 AHLI MUDA S3 (Pengalaman Kerja) 8 Th OB 10,615,000
1.10.28.02.03.002.055 AHLI MUDA S3 (Pengalaman Kerja) 9 Th OB 11,055,000
1.10.28.02.03.002.056 AHLI MUDA S3 (Pengalaman Kerja) 10 Th OB 11,495,000
1.10.28.02.03.002.057 AHLI MUDA S3 (Pengalaman Kerja) 11 Th OB 11,935,000
1.10.28.02.03.002.058 AHLI MUDA S3 (Pengalaman Kerja) 12 Th OB 12,375,000
1.10.28.02.03.002.059 AHLI MUDA S3 (Pengalaman Kerja) 13 Th OB 12,815,000
1.10.28.02.03.002.060 AHLI MUDA S3 (Pengalaman Kerja) 14 Th OB 13,255,000
1.10.28.02.03.002.061 AHLI MUDA S3 (Pengalaman Kerja) 15 Th OB 13,695,000
1.10.28.02.03.002.062 AHLI MUDA S3 (Pengalaman Kerja) 16 Th OB 14,135,000
1.10.28.02.03.002.063 AHLI MUDA S3 (Pengalaman Kerja) 17 Th OB 14,575,000
1.10.28.02.03.002.064 AHLI MUDA S3 (Pengalaman Kerja) 18 Th OB 15,015,000
1.10.28.02.03.002.065 AHLI MUDA S3 (Pengalaman Kerja) 19 Th OB 15,455,000
1.10.28.02.03.002.066 AHLI MUDA S3 (Pengalaman Kerja) 20 Th OB 15,895,000
1.10.28.02.03.002.067 AHLI MUDA S3 (Pengalaman Kerja) 21 Th OB 16,335,000
1.10.28.02.03.002.068 AHLI MUDA S3 (Pengalaman Kerja) 22 Th OB 16,775,000
1.10.28.02.03.002.069 AHLI MUDA S3 (Pengalaman Kerja) 23 Th OB 17,215,000
1.10.28.02.03.002.070 AHLI MADYA S1 (Pengalaman Kerja) 1 Th OB 4,730,000
1.10.28.02.03.002.071 AHLI MADYA S1 (Pengalaman Kerja) 2 Th OB 5,060,000
1.10.28.02.03.002.072 AHLI MADYA S1 (Pengalaman Kerja) 3 Th OB 5,390,000
1.10.28.02.03.002.073 AHLI MADYA S1 (Pengalaman Kerja) 4 Th OB 5,720,000
1.10.28.02.03.002.074 AHLI MADYA S1 (Pengalaman Kerja) 5 Th OB 6,050,000
1.10.28.02.03.002.075 AHLI MADYA S1 (Pengalaman Kerja) 6 Th OB 6,380,000
1.10.28.02.03.002.076 AHLI MADYA S1 (Pengalaman Kerja) 7 Th OB 6,710,000
1.10.28.02.03.002.077 AHLI MADYA S1 (Pengalaman Kerja) 8 Th OB 7,040,000
1.10.28.02.03.002.078 AHLI MADYA S1 (Pengalaman Kerja) 9 Th OB 7,370,000
1.10.28.02.03.002.079 AHLI MADYA S1 (Pengalaman Kerja) 10 Th OB 7,700,000
1.10.28.02.03.002.080 AHLI MADYA S1 (Pengalaman Kerja) 11 Th OB 8,030,000
1.10.28.02.03.002.081 AHLI MADYA S1 (Pengalaman Kerja) 12 Th OB 8,360,000
1.10.28.02.03.002.082 AHLI MADYA S1 (Pengalaman Kerja) 13 Th OB 8,690,000
1.10.28.02.03.002.083 AHLI MADYA S1 (Pengalaman Kerja) 14 Th OB 9,020,000
1.10.28.02.03.002.084 AHLI MADYA S1 (Pengalaman Kerja) 15 Th OB 9,350,000
1.10.28.02.03.002.085 AHLI MADYA S1 (Pengalaman Kerja) 16 Th OB 9,680,000
1.10.28.02.03.002.086 AHLI MADYA S1 (Pengalaman Kerja) 17 Th OB 10,010,000
1.10.28.02.03.002.087 AHLI MADYA S1 (Pengalaman Kerja) 18 Th OB 10,340,000
1.10.28.02.03.002.088 AHLI MADYA S1 (Pengalaman Kerja) 19 Th OB 10,670,000
1.10.28.02.03.002.089 AHLI MADYA S1 (Pengalaman Kerja) 20 Th OB 11,000,000
1.10.28.02.03.002.090 AHLI MADYA S1 (Pengalaman Kerja) 21 Th OB 11,330,000
1.10.28.02.03.002.091 AHLI MADYA S2 (Pengalaman Kerja) 1 Th OB 6,820,000
1.10.28.02.03.002.092 AHLI MADYA S2 (Pengalaman Kerja) 2 Th OB 7,205,000
1.10.28.02.03.002.093 AHLI MADYA S2 (Pengalaman Kerja) 3 Th OB 7,645,000
1.10.28.02.03.002.094 AHLI MADYA S2 (Pengalaman Kerja) 4 Th OB 8,030,000
1.10.28.02.03.002.095 AHLI MADYA S2 (Pengalaman Kerja) 5 Th OB 8,415,000
1.10.28.02.03.002.096 AHLI MADYA S2 (Pengalaman Kerja) 6 Th OB 8,855,000
1.10.28.02.03.002.097 AHLI MADYA S2 (Pengalaman Kerja) 7 Th OB 9,240,000
1.10.28.02.03.002.098 AHLI MADYA S2 (Pengalaman Kerja) 8 Th OB 9,625,000
1.10.28.02.03.002.099 AHLI MADYA S2 (Pengalaman Kerja) 9 Th OB 10,065,000
1.10.28.02.03.002.100 AHLI MADYA S2 (Pengalaman Kerja) 10 Th OB 10,450,000
1.10.28.02.03.002.101 AHLI MADYA S2 (Pengalaman Kerja) 11 Th OB 10,835,000
1.10.28.02.03.002.102 AHLI MADYA S2 (Pengalaman Kerja) 12 Th OB 11,275,000

39
1.10.28.02.03.002.103 AHLI MADYA S2 (Pengalaman Kerja) 13 Th OB 11,660,000
1.10.28.02.03.002.104 AHLI MADYA S2 (Pengalaman Kerja) 14 Th OB 12,045,000
1.10.28.02.03.002.105 AHLI MADYA S2 (Pengalaman Kerja) 15 Th OB 12,485,000
1.10.28.02.03.002.106 AHLI MADYA S2 (Pengalaman Kerja) 16 Th OB 12,870,000
1.10.28.02.03.002.107 AHLI MADYA S2 (Pengalaman Kerja) 17 Th OB 13,255,000
1.10.28.02.03.002.108 AHLI MADYA S2 (Pengalaman Kerja) 18 Th OB 13,695,000
1.10.28.02.03.002.109 AHLI MADYA S2 (Pengalaman Kerja) 19 Th OB 14,080,000
1.10.28.02.03.002.110 AHLI MADYA S2 (Pengalaman Kerja) 20 Th OB 14,465,000
1.10.28.02.03.002.111 AHLI MADYA S2 (Pengalaman Kerja) 21 Th OB 14,905,000
1.10.28.02.03.002.112 AHLI MADYA S3 (Pengalaman Kerja) 1 Th OB 8,415,000
1.10.28.02.03.002.113 AHLI MADYA S3 (Pengalaman Kerja) 2 Th OB 8,855,000
1.10.28.02.03.002.114 AHLI MADYA S3 (Pengalaman Kerja) 3 Th OB 9,295,000
1.10.28.02.03.002.115 AHLI MADYA S3 (Pengalaman Kerja) 4 Th OB 9,735,000
1.10.28.02.03.002.116 AHLI MADYA S3 (Pengalaman Kerja) 5 Th OB 10,175,000
1.10.28.02.03.002.117 AHLI MADYA S3 (Pengalaman Kerja) 6 Th OB 10,615,000
1.10.28.02.03.002.118 AHLI MADYA S3 (Pengalaman Kerja) 7 Th OB 11,055,000
1.10.28.02.03.002.119 AHLI MADYA S3 (Pengalaman Kerja) 8 Th OB 11,495,000
1.10.28.02.03.002.120 AHLI MADYA S3 (Pengalaman Kerja) 9 Th OB 11,935,000
1.10.28.02.03.002.121 AHLI MADYA S3 (Pengalaman Kerja) 10 Th OB 12,375,000
1.10.28.02.03.002.122 AHLI MADYA S3 (Pengalaman Kerja) 11 Th OB 12,815,000
1.10.28.02.03.002.123 AHLI MADYA S3 (Pengalaman Kerja) 12 Th OB 13,255,000
1.10.28.02.03.002.124 AHLI MADYA S3 (Pengalaman Kerja) 13 Th OB 13,695,000
1.10.28.02.03.002.125 AHLI MADYA S3 (Pengalaman Kerja) 14 Th OB 14,135,000
1.10.28.02.03.002.126 AHLI MADYA S3 (Pengalaman Kerja) 15 Th OB 14,575,000
1.10.28.02.03.002.127 AHLI MADYA S3 (Pengalaman Kerja) 16 Th OB 15,015,000
1.10.28.02.03.002.128 AHLI MADYA S3 (Pengalaman Kerja) 17 Th OB 15,455,000
1.10.28.02.03.002.129 AHLI MADYA S3 (Pengalaman Kerja) 18 Th OB 15,895,000
1.10.28.02.03.002.130 AHLI MADYA S3 (Pengalaman Kerja) 19 Th OB 16,335,000
1.10.28.02.03.002.131 AHLI MADYA S3 (Pengalaman Kerja) 20 Th OB 16,775,000
1.10.28.02.03.002.132 AHLI MADYA S3 (Pengalaman Kerja) 21 Th OB 17,215,000
1.10.28.02.03.002.133 AHLI UTAMA S1 (Pengalaman Kerja) 1 Th OB 5,720,000
1.10.28.02.03.002.134 AHLI UTAMA S1 (Pengalaman Kerja) 2 Th OB 6,050,000
1.10.28.02.03.002.135 AHLI UTAMA S1 (Pengalaman Kerja) 3 Th OB 6,380,000
1.10.28.02.03.002.136 AHLI UTAMA S1 (Pengalaman Kerja) 4 Th OB 6,710,000
1.10.28.02.03.002.137 AHLI UTAMA S1 (Pengalaman Kerja) 5 Th OB 7,040,000
1.10.28.02.03.002.138 AHLI UTAMA S1 (Pengalaman Kerja) 6 Th OB 7,370,000
1.10.28.02.03.002.139 AHLI UTAMA S1 (Pengalaman Kerja) 7 Th OB 7,700,000
1.10.28.02.03.002.140 AHLI UTAMA S1 (Pengalaman Kerja) 8 Th OB 8,030,000
1.10.28.02.03.002.141 AHLI UTAMA S1 (Pengalaman Kerja) 9 Th OB 8,360,000
1.10.28.02.03.002.142 AHLI UTAMA S1 (Pengalaman Kerja) 10 Th OB 8,690,000
1.10.28.02.03.002.143 AHLI UTAMA S1 (Pengalaman Kerja) 11 Th OB 9,020,000
1.10.28.02.03.002.144 AHLI UTAMA S1 (Pengalaman Kerja) 12 Th OB 9,350,000
1.10.28.02.03.002.145 AHLI UTAMA S1 (Pengalaman Kerja) 13 Th OB 9,680,000
1.10.28.02.03.002.146 AHLI UTAMA S1 (Pengalaman Kerja) 14 Th OB 10,010,000
1.10.28.02.03.002.147 AHLI UTAMA S1 (Pengalaman Kerja) 15 Th OB 10,340,000
1.10.28.02.03.002.148 AHLI UTAMA S1 (Pengalaman Kerja) 16 Th OB 10,670,000
1.10.28.02.03.002.149 AHLI UTAMA S1 (Pengalaman Kerja) 17 Th OB 11,000,000
1.10.28.02.03.002.150 AHLI UTAMA S1 (Pengalaman Kerja) 18 Th OB 11,330,000
1.10.28.02.03.002.151 AHLI UTAMA S2 (Pengalaman Kerja) 1 Th OB 8,030,000
1.10.28.02.03.002.152 AHLI UTAMA S2 (Pengalaman Kerja) 2 Th OB 8,415,000
1.10.28.02.03.002.153 AHLI UTAMA S2 (Pengalaman Kerja) 3 Th OB 8,855,000
1.10.28.02.03.002.154 AHLI UTAMA S2 (Pengalaman Kerja) 4 Th OB 9,240,000
1.10.28.02.03.002.155 AHLI UTAMA S2 (Pengalaman Kerja) 5 Th OB 9,625,000
1.10.28.02.03.002.156 AHLI UTAMA S2 (Pengalaman Kerja) 6 Th OB 10,065,000
1.10.28.02.03.002.157 AHLI UTAMA S2 (Pengalaman Kerja) 7 Th OB 10,450,000

40
1.10.28.02.03.002.158 AHLI UTAMA S2 (Pengalaman Kerja) 8 Th OB 10,835,000
1.10.28.02.03.002.159 AHLI UTAMA S2 (Pengalaman Kerja) 9 Th OB 11,275,000
1.10.28.02.03.002.160 AHLI UTAMA S2 (Pengalaman Kerja) 10 Th OB 11,660,000
1.10.28.02.03.002.161 AHLI UTAMA S2 (Pengalaman Kerja) 11 Th OB 12,045,000
1.10.28.02.03.002.162 AHLI UTAMA S2 (Pengalaman Kerja) 12 Th OB 12,485,000
1.10.28.02.03.002.163 AHLI UTAMA S2 (Pengalaman Kerja) 13 Th OB 12,870,000
1.10.28.02.03.002.164 AHLI UTAMA S2 (Pengalaman Kerja) 14 Th OB 13,255,000
1.10.28.02.03.002.165 AHLI UTAMA S2 (Pengalaman Kerja) 15 Th OB 13,695,000
1.10.28.02.03.002.166 AHLI UTAMA S2 (Pengalaman Kerja) 16 Th OB 14,080,000
1.10.28.02.03.002.167 AHLI UTAMA S2 (Pengalaman Kerja) 17 Th OB 14,465,000
1.10.28.02.03.002.168 AHLI UTAMA S2 (Pengalaman Kerja) 18 Th OB 14,905,000
1.10.28.02.03.002.169 AHLI UTAMA S3 (Pengalaman Kerja) 1 Th OB 9,735,000
1.10.28.02.03.002.170 AHLI UTAMA S3 (Pengalaman Kerja) 2 Th OB 10,175,000
1.10.28.02.03.002.171 AHLI UTAMA S3 (Pengalaman Kerja) 3 Th OB 10,615,000
1.10.28.02.03.002.172 AHLI UTAMA S3 (Pengalaman Kerja) 4 Th OB 11,055,000
1.10.28.02.03.002.173 AHLI UTAMA S3 (Pengalaman Kerja) 5 Th OB 11,495,000
1.10.28.02.03.002.174 AHLI UTAMA S3 (Pengalaman Kerja) 6 Th OB 11,935,000
1.10.28.02.03.002.175 AHLI UTAMA S3 (Pengalaman Kerja) 7 Th OB 12,375,000
1.10.28.02.03.002.176 AHLI UTAMA S3 (Pengalaman Kerja) 8 Th OB 12,815,000
1.10.28.02.03.002.177 AHLI UTAMA S3 (Pengalaman Kerja) 9 Th OB 13,255,000
1.10.28.02.03.002.178 AHLI UTAMA S3 (Pengalaman Kerja) 10 Th OB 13,695,000
1.10.28.02.03.002.179 AHLI UTAMA S3 (Pengalaman Kerja) 11 Th OB 14,135,000
1.10.28.02.03.002.180 AHLI UTAMA S3 (Pengalaman Kerja) 12 Th OB 14,575,000
1.10.28.02.03.002.181 AHLI UTAMA S3 (Pengalaman Kerja) 13 Th OB 15,015,000
1.10.28.02.03.002.182 AHLI UTAMA S3 (Pengalaman Kerja) 14 Th OB 15,455,000
1.10.28.02.03.002.183 AHLI UTAMA S3 (Pengalaman Kerja) 15 Th OB 15,895,000
1.10.28.02.03.002.184 AHLI UTAMA S3 (Pengalaman Kerja) 16 Th OB 16,335,000
1.10.28.02.03.002.185 AHLI UTAMA S3 (Pengalaman Kerja) 17 Th OB 16,775,000
1.10.28.02.03.002.186 AHLI UTAMA S3 (Pengalaman Kerja) 18 Th OB 17,215,000
1.10.28.02.03.007 Tenaga Pendukung Biaya Langsung Personil (Untuk Supporting Staff)
1.10.28.02.03.007.001 Office Manager OB 9,900,000
1.10.28.02.03.007.002 Site Office Manager/Administrator OB 8,932,000
1.10.28.02.03.007.003 Bilingual Secretary OB 9,768,000
1.10.28.02.03.007.004 Secretary OB 6,072,000
1.10.28.02.03.007.005 Computer Operator / Typist OB 5,368,000
1.10.28.02.03.007.006 Drafter (Manual) OB 5,016,000
1.10.28.02.03.007.007 Messenger OH 3,784,000
1.10.28.02.03.007.008 Office Boy OH 3,520,000
1.10.28.02.03.007.009 Driver OH 4,048,000
1.10.28.02.03.007.010 Office Guard / Security Office OH 3,740,000
1.10.28.02.03.008 Tenaga Pendukung Biaya Langsung Personil (Untuk Tenaga Sub Profesional)
D3 / SO Pendidikan dan Pengalaman lebih
1.10.28.02.03.008.001 Software Programer / Implementer OB 11,044,000
dari 3 Th
1.10.28.02.03.008.002 Software Programer / Implementer S1 Pendidikan dan Pengalaman 0 - 3 Th OB 11,044,000
1.10.28.02.03.008.003 Software Programer / Implementer S2 Pendidikan dan Pengalaman 0 - 1 Th OB 11,044,000
D3 / SO Pendidikan dan Pengalaman lebih
1.10.28.02.03.008.004 Hardware Technician OB 9,416,000
dari 3 Th
1.10.28.02.03.008.005 Hardware Technician S1 Pendidikan dan Pengalaman 0 - 3 Th OB 9,416,000
1.10.28.02.03.008.006 Hardware Technician S2 Pendidikan dan Pengalaman 0 - 1 Th OB 9,416,000
Ijazah Min S1; Sertifikasi MTCNA;
1.10.28.02.03.008.007 Jasa Technical Support Network OB 3,000,000
Pengalaman lebih dari 2 th
Ijazah Min SMA/SMK; Sertifikasi
1.10.28.02.03.008.008 Jasa Technical Support Network OB 2,500,000
MTCNA; Pengalaman 0-2 th
Ijazah Min SMA/SMK; Sertifikasi
1.10.28.02.03.008.009 Jasa Technical Support Network OB 3,000,000
MTCNA; Pengalaman lebih dari 2 th

41
Ijazah Min S1 Komputer; Sertifikasi
1.10.28.02.03.008.010 Jasa Network Administrator OB 5,000,000
MTCNA; Pengalaman 2 th
Ijazah Min D3 Komputer; Sertifikasi
1.10.28.02.03.008.011 Jasa Network Administrator OB 3,500,000
MTCNA; Pengalaman 0-2 th
Ijazah Min D3 Komputer; Sertifikasi
1.10.28.02.03.008.012 Jasa Network Administrator OB 4,500,000
MTCNA; Pengalaman lebih dari 2 th
Ijazah Min S1 Komputer; Pengalaman 0 - 3
1.10.28.02.03.008.013 Jasa System Administrator OB 5,000,000
th
Ijazah Min S1 Komputer; Pengalaman
1.10.28.02.03.008.014 Jasa System Administrator OB 8,000,000
lebih dari 3 th
Ijazah Min S1 Komputer; Pengalaman 0 - 3
1.10.28.02.03.008.015 Analis Sistem OB 3,500,000
th
Ijazah Min S1 Komputer; Pengalaman
1.10.28.02.03.008.016 Analis Sistem OB 4,500,000
lebih dari 3 th
1.10.28.02.04 Upah/Jasa Lainnya
1.10.28.02.04.001 Satuan Biaya Penerjemahan Dan Pengetikan

Satuan Biaya Penerjemahan Dan Pengetikan -


1.10.28.02.04.001.001 Bahasa Inggris ke Bahasa Indonesia halaman jadi 250,000
(Dari Bahasa Asing Ke Indonesia)

Satuan Biaya Penerjemahan Dan Pengetikan -


1.10.28.02.04.001.002 Dari Bahasa Jepang halaman jadi 400,000
(Dari Bahasa Asing Ke Indonesia)

Satuan Biaya Penerjemahan Dan Pengetikan -


1.10.28.02.04.001.003 Dari Bahasa Mandarin, Belanda halaman jadi 450,000
(Dari Bahasa Asing Ke Indonesia)

Satuan Biaya Penerjemahan Dan Pengetikan -


1.10.28.02.04.001.004 Dari Bahasa Prancis, Jerman halaman jadi 414,000
(Dari Bahasa Asing Ke Indonesia)

Satuan Biaya Penerjemahan Dan Pengetikan -


1.10.28.02.04.001.005 Dari Bahasa Asing Lainnya halaman jadi 300,000
(Dari Bahasa Asing Ke Indonesia)

Satuan Biaya Penerjemahan Dan Pengetikan -


1.10.28.02.04.001.006 Dari Bahasa Indonesia halaman jadi 250,000
(Dari Bahasa Indonesia Ke Asing)

Satuan Biaya Penerjemahan Dan Pengetikan -


1.10.28.02.04.001.007 Ke Bahasa Jepang halaman jadi 400,000
(Dari Bahasa Indonesia Ke Asing)

Satuan Biaya Penerjemahan Dan Pengetikan -


1.10.28.02.04.001.008 Ke Bahasa Mandarin, Belanda halaman jadi 450,000
(Dari Bahasa Indonesia Ke Asing)

Satuan Biaya Penerjemahan Dan Pengetikan -


1.10.28.02.04.001.009 Ke Bahasa Prancis, Jerman halaman jadi 414,000
(Dari Bahasa Indonesia Ke Asing)

Satuan Biaya Penerjemahan Dan Pengetikan -


1.10.28.02.04.001.010 Ke Bahasa Asing Lainnya halaman jadi 300,000
(Dari Bahasa Indonesia Ke Asing)

Satuan Biaya Penerjemahan Dan Pengetikan -


1.10.28.02.04.001.011 (Dari Bahasa Indonesia Ke Bahasa halaman jadi 174,000
Daerah/Lokal dan sebaliknya)
1.10.28.02.04.002 Satuan Biaya Diklat
1.10.28.02.04.002.001 Diklat Teknis Biaya Fasilitasi per orang 10,000,000
1.10.28.02.04.002.002 Diklat Fungsional Biaya Fasilitasi per orang 10,000,000
1.10.28.02.04.002.003 Diklatpim II Biaya Fasilitasi per orang 35,000,000
1.10.28.02.04.002.004 Diklatpim III Biaya Fasilitasi per orang 25,000,000
1.10.28.02.04.002.005 Diklatpim IV Biaya Fasilitasi per orang 20,000,000

42
1.10.28.02.04.002.006 Diklat Prajabatan Gol III Biaya Fasilitasi per orang 10,000,000
1.10.28.02.04.002.007 Diklat Prajabatan Gol II Biaya Fasilitasi per orang 8,000,000
1.10.28.02.04.002.008 Diklat / Diklat Honorer Biaya Fasilitasi per orang 5,000,000
1.10.28.02.04.002.009 Assesment bagi Staf Biaya Uji Kompetensi per orang 2,500,000
1.10.28.02.04.002.010 Assesment bagi Eselon IV Biaya Uji Kompetensi per orang 3,000,000
1.10.28.02.04.002.011 Assesment bagi Eselon III Biaya Uji Kompetensi per orang 3,500,000
1.10.28.02.04.002.012 Assesment bagi Eselon II Biaya Uji Kompetensi per orang 4,000,000
1.10.28.02.04.002.013 Assesment Job Target (seleksi Terbuka) Biaya Uji Kompetensi per orang 10,000,000
1.10.28.02.04.099 Upah/Jasa Lain - lain
1.10.28.02.04.099.001 Tambal Ban buah 25,000
Pemain keyboard, pemain gendang Jawa,
1.10.28.02.04.099.002 Campursari pemain ketipung dangdut, penyanyi, MC, paket 8,500,000
sound system
1.10.28.03 Satuan Biaya Operasional Kegiatan
1.10.28.03.01 Satuan Biaya Operasional Kegiatan Umum
1.10.28.03.01.001 Satuan Biaya Uang Lembur Dan Uang Makan Lembur PNS
1.10.28.03.01.001.001 Uang Lembur Golongan I OJ 13,000
1.10.28.03.01.001.002 Uang Lembur Golongan II OJ 17,000
1.10.28.03.01.001.003 Uang Lembur Golongan III OJ 20,000
1.10.28.03.01.001.004 Uang Lembur Golongan IV OJ 25,000
1.10.28.03.01.001.005 Uang Makan Lembur Golongan I dan II OH 35,000
1.10.28.03.01.001.006 Uang Makan Lembur Golongan III OH 37,000
1.10.28.03.01.001.007 Uang Makan Lembur Golongan IV OH 41,000
1.10.28.03.01.001.008 Uang Lembur Non ASN OJ 20,000
1.10.28.03.01.001.009 Uang Makan Lembur Non ASN OH 31,000
Satpam, Pengemudi, Petugas Kebersihan,
1.10.28.03.01.001.010 Uang Lembur OJ 13,000
dan Pramubakti
Satpam, Pengemudi, Petugas Kebersihan,
1.10.28.03.01.001.011 Uang Makan Lembur OH 30,000
dan Pramubakti
1.10.28.03.01.002 Satuan Biaya Perjalanan Dinas - Uang Representasi
1.10.28.03.01.002.001 Uang Representasi Walikota/Wakil Walikota OH 250,000
Sekretaris Daerah (Eselon II A)/Pimpinan
1.10.28.03.01.002.002 Uang Representasi OH 250,000
DPRD
1.10.28.03.01.002.003 Uang Representasi Anggota DPRD OH 250,000
1.10.28.03.01.002.004 Uang Representasi Eselon II B OH 150,000
1.10.28.03.01.003 Satuan Biaya Perjalanan Dinas - Uang Harian Study Banding
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.001 Walikota OH 1,700,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.002 Wakil Walikota OH 1,400,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.003 Sekda/Ketua DPRD OH 1,200,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.004 Wakil Ketua DPRD OH 1,150,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.

43
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.005 Ketua Komisi DPRD OH 1,050,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.006 Wakil Ketua Komisi OH 1,000,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.007 Sekretaris Komisi DPRD OH 950,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya Anggota Komisi DPRD / Anggota
1.10.28.03.01.003.008 OH 900,000
disediakan oleh Penyelenggara Luar Kota DPRD/Eselon II b
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.009 Eselon III/Kepala SKPD/Kabag/Camat OH 650,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya Eselon III/Bukan Kepala SKPD/auditor
1.10.28.03.01.003.010 OH 450,000
disediakan oleh Penyelenggara Luar Kota madya
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.011 Eselon IV/Lurah/auditor muda OH 400,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.012 Eselon V/auditor pertama OH 300,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.013 Gol III dan IV OH 250,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.014 Gol I dan II OH 200,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.015 Non PNS Daerah/Masyarakat OH 150,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.016 Instansi vertikal OH 750,000
disediakan oleh Penyelenggara Luar Kota
Dalam Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.017 Walikota OH 2,700,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.

44
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.018 Wakil Walikota OH 2,400,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.019 Sekda/Ketua DPRD OH 2,300,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.020 Wakil Ketua DPRD OH 2,200,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.021 Ketua Komisi DPRD OH 1,900,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.022 Wakil Ketua Komisi OH 1,800,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.023 Sekretaris Komisi DPRD OH 1,750,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya Anggota Komisi DPRD / Anggota
1.10.28.03.01.003.024 OH 1,700,000
disediakan oleh Penyelenggara Luar Kota DPRD/Eselon II b
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.025 Eselon III/Kepala SKPD/Kabag/Camat OH 1,300,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya Eselon III/Bukan Kepala SKPD/auditor
1.10.28.03.01.003.026 OH 1,150,000
disediakan oleh Penyelenggara Luar Kota madya
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.027 Eselon IV/Lurah/auditor muda OH 900,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.028 Eselon V/auditor pertama OH 800,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.029 Gol III dan IV OH 700,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.030 Gol I dan II OH 600,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.

45
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.031 Non PNS Daerah/Masyarakat OH 500,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
Uang Harian Study Banding/Kegiatan yang
Fasilitas Penginapan dan Konsumsi nya
1.10.28.03.01.003.032 Instansi vertikal OH 1,700,000
disediakan oleh Penyelenggara Luar Kota
Luar Prov.
1.10.28.03.01.004 Satuan Biaya Perjalanan Dinas - Uang Saku Diklat
1.10.28.03.01.004.001 Uang Saku Diklat - Luar Kota Dalam Prov. Walikota/ Wakil Walikota/ Sekda OH 250,000
1.10.28.03.01.004.002 Uang Saku Diklat - Luar Kota Dalam Prov. Eselon II b OH 150,000
Eselon III/Kepala
1.10.28.03.01.004.003 Uang Saku Diklat - Luar Kota Dalam Prov. SKPD/Kabag/Camat/Bukan Kepala OH 150,000
SKPD/auditor madya
1.10.28.03.01.004.004 Uang Saku Diklat - Luar Kota Dalam Prov. Eselon IV/Lurah/auditor muda OH 150,000
1.10.28.03.01.004.005 Uang Saku Diklat - Luar Kota Dalam Prov. Eselon V/auditor pertama OH 150,000
1.10.28.03.01.004.006 Uang Saku Diklat - Luar Kota Dalam Prov. Gol I dan II/ Gol III dan IV OH 150,000
1.10.28.03.01.004.007 Uang Saku Diklat - Luar Kota Dalam Prov. Non PNS Daerah/ Masyarakat OH 150,000
1.10.28.03.01.004.008 Uang Saku Diklat - Luar Prov. Walikota/ Wakil Walikota/ Sekda OH 300,000
1.10.28.03.01.004.009 Uang Saku Diklat - Luar Prov. Eselon II b OH 200,000
Eselon III/Kepala
1.10.28.03.01.004.010 Uang Saku Diklat - Luar Prov. SKPD/Kabag/Camat/Bukan Kepala OH 200,000
SKPD/auditor madya
1.10.28.03.01.004.011 Uang Saku Diklat - Luar Prov. Eselon IV/Lurah/auditor muda OH 200,000
1.10.28.03.01.004.012 Uang Saku Diklat - Luar Prov. Eselon V/auditor pertama OH 200,000
1.10.28.03.01.004.013 Uang Saku Diklat - Luar Prov. Gol I dan II/ Gol III dan IV OH 200,000
1.10.28.03.01.004.014 Uang Saku Diklat - Luar Prov. Non PNS Daerah/ Masyarakat OH 200,000
1.10.28.03.01.004.015 Uang Saku Diklat - Dalam Kota Eselon II b OH 100,000
Eselon III/Kepala
1.10.28.03.01.004.016 Uang Saku Diklat - Dalam Kota SKPD/Kabag/Camat/Bukan Kepala OH 100,000
SKPD/auditor madya
1.10.28.03.01.004.017 Uang Saku Diklat - Dalam Kota Eselon IV/Lurah/auditor muda OH 100,000
1.10.28.03.01.004.018 Uang Saku Diklat - Dalam Kota Eselon V/auditor pertama OH 100,000
1.10.28.03.01.004.019 Uang Saku Diklat - Dalam Kota Gol I dan II/ Gol III dan IV OH 100,000
1.10.28.03.01.004.020 Uang Saku Diklat - Dalam Kota Non PNS Daerah/ Masyarakat OH 100,000
1.10.28.03.01.006 Satuan Biaya Perjalanan Dinas - Biaya Transportasi
Peserta Pelatihan/ Sosialisasi/ Bintek dan
1.10.28.03.01.006.006 Biaya Transportasi Di Dalam Kota Mojokerto orang 75,000
Sejenis nya/Masyarakat

Anggota DPRD yang tidak menggunakan


1.10.28.03.01.006.007 Biaya Transportasi Di Dalam Kota Mojokerto orang 100,000
kendaraan dinas roda empat

Biaya Transportasi Luar Kota Mojokerto Di


1.10.28.03.01.006.008 Eselon III ( bukan Ka. SKPD) orang 242,400
Jawa Timur ZONA A
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.009 Eselon IV orang 242,400
Jawa Timur ZONA A
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.010 Golongan III dan IV orang 242,400
Jawa Timur ZONA A
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.011 Golongan II dan I orang 242,400
Jawa Timur ZONA A
Biaya Transportasi Luar Kota Mojokerto Di Personil Honorer dan peserta Pelatihan/
1.10.28.03.01.006.012 orang 242,400
Jawa Timur ZONA A Sosialisasi/ Bintek / Masyarakat

Biaya Transportasi Luar Kota Mojokerto Di Anggota DPRD yang tidak menggunakan
1.10.28.03.01.006.013 orang 242,400
Jawa Timur ZONA A kendaraan dinas roda empat

46
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.014 Eselon III ( bukan Ka. SKPD) orang 405,800
Jawa Timur ZONA B
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.015 Eselon IV orang 405,800
Jawa Timur ZONA B
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.016 Golongan III dan IV orang 405,800
Jawa Timur ZONA B
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.017 Golongan II dan I orang 405,800
Jawa Timur ZONA B
Biaya Transportasi Luar Kota Mojokerto Di Personil Honorer dan peserta Pelatihan/
1.10.28.03.01.006.018 orang 405,800
Jawa Timur ZONA B Sosialisasi/ Bintek / Masyarakat

Biaya Transportasi Luar Kota Mojokerto Di Anggota DPRD yang tidak menggunakan
1.10.28.03.01.006.019 orang 405,800
Jawa Timur ZONA B kendaraan dinas roda empat

Biaya Transportasi Luar Kota Mojokerto Di


1.10.28.03.01.006.020 Eselon III ( bukan Ka. SKPD) orang 405,400
Jawa Timur ZONA C
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.021 Eselon IV orang 405,400
Jawa Timur ZONA C
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.022 Golongan III dan IV orang 405,400
Jawa Timur ZONA C
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.023 Golongan II dan I orang 405,400
Jawa Timur ZONA C
Biaya Transportasi Luar Kota Mojokerto Di Personil Honorer dan peserta Pelatihan/
1.10.28.03.01.006.024 orang 405,400
Jawa Timur ZONA C Sosialisasi/ Bintek / Masyarakat

Biaya Transportasi Luar Kota Mojokerto Di Anggota DPRD yang tidak menggunakan
1.10.28.03.01.006.025 orang 405,400
Jawa Timur ZONA C kendaraan dinas roda empat

Biaya Transportasi Luar Kota Mojokerto Di


1.10.28.03.01.006.026 Eselon III ( bukan Ka. SKPD) orang 408,500
Jawa Timur ZONA D
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.027 Eselon IV orang 408,500
Jawa Timur ZONA D
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.028 Golongan III dan IV orang 408,500
Jawa Timur ZONA D
Biaya Transportasi Luar Kota Mojokerto Di
1.10.28.03.01.006.029 Golongan II dan I orang 408,500
Jawa Timur ZONA D
Biaya Transportasi Luar Kota Mojokerto Di Personil Honorer dan peserta Pelatihan/
1.10.28.03.01.006.030 orang 408,500
Jawa Timur ZONA D Sosialisasi/ Bintek / Masyarakat

Biaya Transportasi Luar Kota Mojokerto Di Anggota DPRD yang tidak menggunakan
1.10.28.03.01.006.031 orang 408,500
Jawa Timur ZONA D kendaraan dinas roda empat

Satuan Biaya Perjalanan Dinas - Biaya Penginapan (Satuan Biaya Penginapan Merupakan Alokasi Biaya Tertinggi
1.10.28.03.01.007
Penginapan - At Cost)
Biaya Penginapan Luar Kota Di Dalam
1.10.28.03.01.007.001 Eselon I/Kepala Daerah/Ketua DPRD orang 4,400,000
Propinsi Jawa Timur
Biaya Penginapan Luar Kota Di Dalam
1.10.28.03.01.007.002 Eselon II/Anggota DPRD orang 1,605,000
Propinsi Jawa Timur
Biaya Penginapan Luar Kota Di Dalam
1.10.28.03.01.007.003 Eselon III/Gol IV orang 1,076,000
Propinsi Jawa Timur
Biaya Penginapan Luar Kota Di Dalam
1.10.28.03.01.007.004 Eselon IV/Gol III orang 664,000
Propinsi Jawa Timur
Biaya Penginapan Luar Kota Di Dalam
1.10.28.03.01.007.005 Gol II/I orang 664,000
Propinsi Jawa Timur
Biaya Penginapan Di Luar Jawa Timur Di
1.10.28.03.01.007.006 Eselon I/Kepala Daerah/Ketua DPRD orang 5,725,000
Pulau Jawa
Biaya Penginapan Di Luar Jawa Timur Di
1.10.28.03.01.007.007 Eselon II/Anggota DPRD orang 2,373,000
Pulau Jawa

47
Biaya Penginapan Di Luar Jawa Timur Di
1.10.28.03.01.007.008 Eselon III/Gol IV orang 1,000,000
Pulau Jawa
Biaya Penginapan Di Luar Jawa Timur Di
1.10.28.03.01.007.009 Eselon IV/Gol III orang 718,000
Pulau Jawa
Biaya Penginapan Di Luar Jawa Timur Di
1.10.28.03.01.007.010 Gol II/I orang 718,000
Pulau Jawa
Biaya Penginapan Di D.K.I Jakarta/Luar
1.10.28.03.01.007.011 Eselon I/Kepala Daerah/Ketua DPRD orang 8,720,000
Pulau Jawa
Biaya Penginapan Di D.K.I Jakarta/Luar
1.10.28.03.01.007.012 Eselon II/Anggota DPRD orang 1,490,000
Pulau Jawa
Biaya Penginapan Di D.K.I Jakarta/Luar
1.10.28.03.01.007.013 Eselon III/Gol IV orang 992,000
Pulau Jawa
Biaya Penginapan Di D.K.I Jakarta/Luar
1.10.28.03.01.007.014 Eselon IV/Gol III orang 610,000
Pulau Jawa
Biaya Penginapan Di D.K.I Jakarta/Luar
1.10.28.03.01.007.015 Gol II/I orang 610,000
Pulau Jawa
1.10.28.03.01.008 Satuan Biaya Perjalanan Dinas - Uang Harian
1.10.28.03.01.008.001 Uang Harian - Dalam Prov. Walikota OH 1,800,000
1.10.28.03.01.008.002 Uang Harian - Dalam Prov. Wakil Walikota OH 1,500,000
1.10.28.03.01.008.003 Uang Harian - Dalam Prov. Sekda/Ketua DPRD OH 1,300,000
1.10.28.03.01.008.004 Uang Harian - Dalam Prov. Wakil Ketua DPRD OH 1,250,000
1.10.28.03.01.008.005 Uang Harian - Dalam Prov. Ketua Komisi DPRD OH 1,150,000
1.10.28.03.01.008.006 Uang Harian - Dalam Prov. Wakil Ketua Komisi OH 1,100,000
1.10.28.03.01.008.007 Uang Harian - Dalam Prov. Sekretaris Komisi DPRD OH 1,050,000
Anggota Komisi DPRD / Anggota
1.10.28.03.01.008.008 Uang Harian - Dalam Prov. OH 1,000,000
DPRD/Eselon II b
1.10.28.03.01.008.009 Uang Harian - Dalam Prov. Eselon III/Kepala SKPD/Kabag/Camat OH 750,000
Eselon III/Bukan Kepala SKPD/auditor
1.10.28.03.01.008.010 Uang Harian - Dalam Prov. OH 550,000
madya
1.10.28.03.01.008.011 Uang Harian - Dalam Prov. Eselon IV/Lurah/auditor muda OH 500,000
1.10.28.03.01.008.012 Uang Harian - Dalam Prov. Eselon V/auditor pertama OH 400,000
1.10.28.03.01.008.013 Uang Harian - Dalam Prov. Gol III dan IV OH 350,000
1.10.28.03.01.008.014 Uang Harian - Dalam Prov. Gol I dan II OH 300,000
1.10.28.03.01.008.015 Uang Harian - Dalam Prov. Non PNS Daerah/Masyarakat OH 250,000
1.10.28.03.01.008.016 Uang Harian - Dalam Prov. Instansi Vertikal OH 850,000
1.10.28.03.01.008.017 Uang Harian - Luar Prov. Walikota OH 2,800,000
1.10.28.03.01.008.018 Uang Harian - Luar Prov. Wakil Walikota OH 2,500,000
1.10.28.03.01.008.019 Uang Harian - Luar Prov. Sekda/Ketua DPRD OH 2,400,000
1.10.28.03.01.008.020 Uang Harian - Luar Prov. Wakil Ketua DPRD OH 2,300,000
1.10.28.03.01.008.021 Uang Harian - Luar Prov. Ketua Komisi DPRD OH 2,000,000
1.10.28.03.01.008.022 Uang Harian - Luar Prov. Wakil Ketua Komisi OH 1,900,000
1.10.28.03.01.008.023 Uang Harian - Luar Prov. Sekretaris Komisi DPRD OH 1,850,000
Anggota Komisi DPRD / Anggota
1.10.28.03.01.008.024 Uang Harian - Luar Prov. OH 1,800,000
DPRD/Eselon II b
1.10.28.03.01.008.025 Uang Harian - Luar Prov. Eselon III/Kepala SKPD/Kabag/Camat OH 1,400,000
Eselon III/Bukan Kepala SKPD/auditor
1.10.28.03.01.008.026 Uang Harian - Luar Prov. OH 1,250,000
madya
1.10.28.03.01.008.027 Uang Harian - Luar Prov. Eselon IV/Lurah/auditor muda OH 1,000,000
1.10.28.03.01.008.028 Uang Harian - Luar Prov. Eselon V/auditor pertama OH 900,000
1.10.28.03.01.008.029 Uang Harian - Luar Prov. Gol III dan IV OH 800,000
1.10.28.03.01.008.030 Uang Harian - Luar Prov. Gol I dan II OH 700,000
1.10.28.03.01.008.031 Uang Harian - Luar Prov. Non PNS Daerah/Masyarakat OH 600,000
1.10.28.03.01.008.032 Uang Harian - Luar Prov. Instansi Vertikal OH 1,800,000
1.10.28.03.01.010 Satuan Biaya Makanan Penambah Daya Tahan Tubuh/Ekstra Puding

48
Satuan Biaya Makanan Penambah Daya
1.10.28.03.01.010.001 OH 19,000
Tahan Tubuh/Ekstra Puding
1.10.28.03.01.011 Bantuan Uang Transport dalam Kegiatan

1.10.28.03.01.011.001 Uang Transport Pemateri Pemerintah Pusat Bantuan Uang Transport dalam Kegiatan OH 1,000,000

1.10.28.03.01.011.002 Uang Transport Pemateri Pemprov Bantuan Uang Transport dalam Kegiatan OH 400,000

1.10.28.03.01.011.003 Uang Transport Pemateri Pihak Ketiga Bantuan Uang Transport dalam Kegiatan OH 300,000

1.10.28.03.01.011.004 Transport Peserta (Dalam Kota) Bantuan Uang Transport dalam Kegiatan OH 80,000

1.10.28.03.01.011.005 Transport Peserta (Luar Kota) Bantuan Uang Transport dalam Kegiatan OH 100,000

1.10.28.03.01.011.006 Transport Tim seleksi Bantuan Uang Transport dalam Kegiatan OH 100,000

1.10.28.03.01.012 Satuan Biaya Diklat Pimpinan/ Struktural


peserta/angka
1.10.28.03.01.012.001 Satuan Biaya Diklat Pimpinan/ Struktural Diklat Pimpinan Tk. II 32,000,000
tan
peserta/angka
1.10.28.03.01.012.002 Satuan Biaya Diklat Pimpinan/ Struktural Diklat Pimpinan Tk. III 22,000,000
tan
peserta/angka
1.10.28.03.01.012.003 Satuan Biaya Diklat Pimpinan/ Struktural Diklat Pimpinan Tk. IV 18,000,000
tan
peserta/angka
1.10.28.03.01.012.004 Satuan Biaya Latihan Prajabatan Golongan I dan Golongan II 8,000,000
tan
peserta/angka
1.10.28.03.01.012.005 Satuan Biaya Latihan Prajabatan Golongan III 9,500,000
tan
1.10.28.03.01.013 Satuan Biaya Bantuan Beasiswa Program Gelar/Non-Gelar Dalam Negeri
Biaya Hidup dan Biaya Operasional - Satuan Biaya Bantuan Beasiswa Program
1.10.28.03.01.013.001 OT 16,070,000
Diploma I dan Diploma III Gelar/Non-Gelar Dalam Negeri
Biaya Hidup dan Biaya Operasional - Satuan Biaya Bantuan Beasiswa Program
1.10.28.03.01.013.002 OT 17,010,000
Diploma IV dan Strata I Gelar/Non-Gelar Dalam Negeri
Uang buku dan Referensi per tahun - Satuan Biaya Bantuan Beasiswa Program
1.10.28.03.01.013.003 OT 1,330,000
Diploma I Gelar/Non-Gelar Dalam Negeri
Uang buku dan Referensi per tahun - Satuan Biaya Bantuan Beasiswa Program
1.10.28.03.01.013.004 OT 1,590,000
Diploma III Gelar/Non-Gelar Dalam Negeri
Uang buku dan Referensi per tahun - Satuan Biaya Bantuan Beasiswa Program
1.10.28.03.01.013.005 OT 1,850,000
Diploma IV dan Strata I Gelar/Non-Gelar Dalam Negeri
Biaya Hidup dan Biaya Operasional - Strata 2 Satuan Biaya Bantuan Beasiswa Program
1.10.28.03.01.013.006 OT 20,690,000
dan Spesialis 1 Gelar/Non-Gelar Dalam Negeri
Biaya Hidup dan Biaya Operasional - Strata 3 Satuan Biaya Bantuan Beasiswa Program
1.10.28.03.01.013.007 OT 21,320,000
dan Spesialis 2 Gelar/Non-Gelar Dalam Negeri
Uang buku dan Referensi per tahun - Strata 2 Satuan Biaya Bantuan Beasiswa Program
1.10.28.03.01.013.008 OT 2,120,000
dan Spesialis 1 Gelar/Non-Gelar Dalam Negeri
Uang buku dan Referensi per tahun - Strata 3 Satuan Biaya Bantuan Beasiswa Program
1.10.28.03.01.013.009 OT 2,380,000
dan Spesialis 2 Gelar/Non-Gelar Dalam Negeri
1.10.28.03.01.014 Biaya Tarif Dasar Listrik dan Biaya Tambah Daya Listrik
1.10.28.03.01.014.001 Pasang Listrik Baru 1300 KWh (Belum termasuk b. Instalasi) paket 1,107,600
1.10.28.03.01.014.002 Pasang Listrik Baru paket 1,874,500
Dari 450 KWh ke 900 KWh (sudah
1.10.28.03.01.014.003 Biaya Tambah Daya Listrik paket 450,000
termasuk biaya instalasi)
Dari 900 KWh ke 1300 KWh (sudah
1.10.28.03.01.014.004 Biaya Tambah Daya Listrik paket 800,000
termasuk biaya instalasi)
Dari 1300 KWh ke 2200 KWh (sudah
1.10.28.03.01.014.005 Biaya Tambah Daya Listrik paket 1,200,000
termasuk biaya instalasi)

49
Dari 2200 KWh ke 3500 Kwh (sudah
1.10.28.03.01.014.006 Biaya Tambah Daya Listrik paket 1,499,000
termasuk biaya instalasi)
1.10.28.03.01.014.007 Tarif Dasar Listrik P-1/TR 450 VA Rp/kWh 685
1.10.28.03.01.014.008 Tarif Dasar Listrik P-1/TR 900 VA Rp/kWh 760
1.10.28.03.01.014.009 Tarif Dasar Listrik P-1/TR 1300 VA Rp/kWh 1,049
1.10.28.03.01.014.010 Tarif Dasar Listrik P-1/TR 2200 VA Rp/kWh 1,076
1.10.28.03.01.014.011 Tarif Dasar Listrik P-1/TR 3500 VA Rp/kWh 1,076
1.10.28.03.01.014.012 Tarif Dasar Listrik P-1/TR 4400 VA Rp/kWh 1,076
1.10.28.03.01.014.013 Tarif Dasar Listrik P-1/TR 5500 VA Rp/kWh 1,076
1.10.28.03.01.014.014 Tarif Dasar Listrik P-1/TR 6600 VA s.d 200 kVA Rp/kWh 1,467
1.10.28.03.01.014.015 Tarif Dasar Listrik P-2/TM diatas 200 kVA Rp/kWh 1,115
1.10.28.03.01.014.016 Tarif Dasar Listrik P-3/TR Rp/kWh 1,467
1.10.28.03.02 Satuan Biaya Operasional Lainnya
1.10.28.03.02.001 Upah Konstruksi Pekerjaan Dinas Perhubungan
1.10.28.03.02.001.001 Pasang dan Stel 1 pesawat Kontroller buah 247,800
1.10.28.03.02.001.002 Erection RPPJ Portal unit 4,383,700
1.10.28.03.02.001.003 Biaya Penyambungan PLN unit 2,577,700
1.10.28.03.02.001.004 Pengecatan RPPJ Portal Gapura unit 1,108,800
1.10.28.03.02.001.005 Biaya Programming set 2,158,800
1.10.28.03.02.002 Satuan Biaya Tiket Kereta Api dan Tiket Pesawat
1.10.28.03.02.002.001 Tiket Kereta Api ke Jakarta orang 650,000
1.10.28.03.02.002.002 Tiket Kereta Api ke Solo orang 390,000
1.10.28.03.02.002.003 Tiket Kereta Api ke Bandung orang 620,000
1.10.28.03.02.002.004 Tiket Kereta Api ke Semarang orang 490,000
1.10.28.03.02.002.005 Tiket Kereta Api ke Malang orang 290,000
1.10.28.03.02.002.006 Tiket Kereta Api ke Jember orang 255,000
1.10.28.03.02.002.007 Tiket Kereta Api ke Surabaya orang 250,000
1.10.28.03.02.002.008 Tiket Kereta Api ke Banyuwangi orang 285,000
1.10.28.03.02.002.009 Tiket Kereta Api ke Jogjakarta orang 295,000
1.10.28.03.02.002.010 Tiket Kereta Api ke Blitar orang 18,000
1.10.28.03.02.002.011 Tiket Kereta Api ke Kediri orang 15,000
1.10.28.03.02.002.027 Tiket Pesawat Surabaya ke Jakarta Bisnis orang 5,466,000
1.10.28.03.02.002.028 Tiket Pesawat Surabaya ke Bandung Bisnis orang 4,824,000
1.10.28.03.02.002.029 Tiket Pesawat Surabaya ke Aceh Bisnis orang 10,985,000
1.10.28.03.02.002.030 Tiket Pesawat Surabaya ke Medan Bisnis orang 10,739,000
1.10.28.03.02.002.031 Tiket Pesawat Surabaya ke Batam Bisnis orang 8,600,000
1.10.28.03.02.002.032 Tiket Pesawat Surabaya ke Padang Bisnis orang 9,199,000
1.10.28.03.02.002.033 Tiket Pesawat Surabaya ke Lampung Bisnis orang 6,386,000
1.10.28.03.02.002.034 Tiket Pesawat Surabaya ke Palembang Bisnis orang 7,690,000
1.10.28.03.02.002.035 Tiket Pesawat Surabaya ke Jambi Bisnis orang 7,883,000
1.10.28.03.02.002.036 Tiket Pesawat Surabaya ke Pangkal Pinang Bisnis orang 7,284,000
1.10.28.03.02.002.037 Tiket Pesawat Surabaya ke Pekanbaru Bisnis orang 9,241,000
1.10.28.03.02.002.038 Tiket Pesawat Surabaya ke Pontianak Bisnis orang 8,140,000
1.10.28.03.02.002.039 Tiket Pesawat Surabaya ke Balikpapan Bisnis orang 10,889,000
1.10.28.03.02.002.040 Tiket Pesawat Surabaya ke Banjarmasin Bisnis orang 8,942,000
1.10.28.03.02.002.041 Tiket Pesawat Surabaya ke Palangkaraya Bisnis orang 8,696,000
1.10.28.03.02.002.042 Tiket Pesawat Surabaya ke Makasar Bisnis orang 5,936,000
1.10.28.03.02.002.043 Tiket Pesawat Surabaya ke Manado Bisnis orang 9,937,000
1.10.28.03.02.002.044 Tiket Pesawat Surabaya ke Palu Bisnis orang 6,878,000
1.10.28.03.02.002.045 Tiket Pesawat Surabaya ke Kendari Bisnis orang 11,103,000
1.10.28.03.02.002.046 Tiket Pesawat Surabaya ke Ambon Bisnis orang 8,803,000
1.10.28.03.02.002.047 Tiket Pesawat Surabaya ke Denpasar Bisnis orang 3,198,000
1.10.28.03.02.002.048 Tiket Pesawat Surabaya ke Mataram Bisnis orang 3,829,000
1.10.28.03.02.002.049 Tiket Pesawat Surabaya ke Kupang Bisnis orang 6,749,000
1.10.28.03.02.002.050 Tiket Pesawat Surabaya ke Jayapura Bisnis orang 12,675,000

50
1.10.28.03.02.002.051 Tiket Pesawat Surabaya ke Biak Bisnis orang 12,782,000
1.10.28.03.02.002.052 Tiket Pesawat Surabaya ke Timika Bisnis orang 11,295,000
1.10.28.03.02.002.053 Tiket Pesawat Surabaya ke Jakarta Ekonomi orang 2,674,000
1.10.28.03.02.002.054 Tiket Pesawat Surabaya ke Bandung Ekonomi orang 2,856,000
1.10.28.03.02.002.055 Tiket Pesawat Surabaya ke Aceh Ekonomi orang 5,744,000
1.10.28.03.02.002.056 Tiket Pesawat Surabaya ke Medan Ekonomi orang 5,134,000
1.10.28.03.02.002.057 Tiket Pesawat Surabaya ke Batam Ekonomi orang 4,300,000
1.10.28.03.02.002.058 Tiket Pesawat Surabaya ke Padang Ekonomi orang 4,364,000
1.10.28.03.02.002.059 Tiket Pesawat Surabaya ke Lampung Ekonomi orang 3,123,000
1.10.28.03.02.002.060 Tiket Pesawat Surabaya ke Palembang Ekonomi orang 3,744,000
1.10.28.03.02.002.061 Tiket Pesawat Surabaya ke Jambi Ekonomi orang 3,915,000
1.10.28.03.02.002.062 Tiket Pesawat Surabaya ke Pangkal Pinang Ekonomi orang 3,626,000
1.10.28.03.02.002.063 Tiket Pesawat Surabaya ke Pekanbaru Ekonomi orang 4,407,000
1.10.28.03.02.002.064 Tiket Pesawat Surabaya ke Pontianak Ekonomi orang 4,204,000
1.10.28.03.02.002.065 Tiket Pesawat Surabaya ke Balikpapan Ekonomi orang 5,113,000
1.10.28.03.02.002.066 Tiket Pesawat Surabaya ke Banjarmasin Ekonomi orang 4,385,000
1.10.28.03.02.002.067 Tiket Pesawat Surabaya ke Palangkaraya Ekonomi orang 4,385,000
1.10.28.03.02.002.068 Tiket Pesawat Surabaya ke Makasar Ekonomi orang 3,433,000
1.10.28.03.02.002.069 Tiket Pesawat Surabaya ke Manado Ekonomi orang 5,262,000
1.10.28.03.02.002.070 Tiket Pesawat Surabaya ke Palu Ekonomi orang 3,883,000
1.10.28.03.02.002.071 Tiket Pesawat Surabaya ke Kendari Ekonomi orang 5,466,000
1.10.28.03.02.002.072 Tiket Pesawat Surabaya ke Ambon Ekonomi orang 4,845,000
1.10.28.03.02.002.073 Tiket Pesawat Surabaya ke Denpasar Ekonomi orang 1,979,000
1.10.28.03.02.002.074 Tiket Pesawat Surabaya ke Mataram Ekonomi orang 2,321,000
1.10.28.03.02.002.075 Tiket Pesawat Surabaya ke Kupang Ekonomi orang 3,722,000
1.10.28.03.02.002.076 Tiket Pesawat Surabaya ke Jayapura Ekonomi orang 7,231,000
1.10.28.03.02.002.077 Tiket Pesawat Surabaya ke Biak Ekonomi orang 7,081,000
1.10.28.03.02.002.078 Tiket Pesawat Surabaya ke Timika Ekonomi orang 6,589,000
1.10.28.03.02.002.281 Tiket Pesawat Surabaya ke Tarakan Ekonomi orang 2,552,500
1.10.28.03.02.002.282 Tiket Pesawat Surabaya ke Tarakan Ekonomi orang 2,903,400
1.10.28.03.02.002.283 Tiket Pesawat Surabaya ke Tarakan Ekonomi orang 4,433,500
1.10.28.03.02.003 Satuan Biaya Tarif Internet, Hot Spot/Wifi ID, Fiber Optik, IP Address
Indihome Paket Deluxe - Triple Play (10
1.10.28.03.02.003.001 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 435,000
UseeTV; Movin basic)
Indihome Paket Premium - Triple Play (20
1.10.28.03.02.003.002 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 555,000
UseeTV; Movin basic)
Indihome Paket Premium - Triple Play (30
1.10.28.03.02.003.003 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 735,000
UseeTV; Movin basic)
Indihome Paket Premium - Triple Play (40
1.10.28.03.02.003.004 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 930,000
UseeTV; Movin basic)
Indihome Paket Premium - Triple Play (50
1.10.28.03.02.003.005 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 1,225,000
UseeTV; Movin basic)
Indihome Paket Premium - Triple Play
1.10.28.03.02.003.006 Tarif Internet (100 mps; 1000 menit nelpon bulan 1,890,000
lokal/interlokal; UseeTV; Movin basic)
1.10.28.03.02.003.007 Biaya Pasang Baru Internet Indihome - Triple Play per kegiatan 75,000
Indihome Paket Netizen I - Dual Play (10
1.10.28.03.02.003.008 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 320,000
Movin basic)

51
Indihome Paket Netizen I - Dual Play (20
1.10.28.03.02.003.009 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 380,000
Movin basic)
Indihome Paket Netizen I - Dual Play (30
1.10.28.03.02.003.010 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 525,000
Movin basic)
Indihome Paket Netizen I - Dual Play (40
1.10.28.03.02.003.011 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 675,000
Movin basic)
Indihome Paket Netizen II - Dual Play (10
1.10.28.03.02.003.012 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 346,500
Movin basic)
Indihome Paket Netizen II - Dual Play (20
1.10.28.03.02.003.013 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 420,000
Movin basic)
Indihome Paket Netizen II - Dual Play (30
1.10.28.03.02.003.014 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 565,000
Movin basic)
Indihome Paket Netizen II - Dual Play (40
1.10.28.03.02.003.015 Tarif Internet mps; 1000 menit nelpon lokal/interlokal; bulan 742,500
Movin basic)
1.10.28.03.02.003.016 Biaya Pasang Baru Internet Indihome - Dual Play per kegiatan 150,000
1.10.28.03.02.003.017 Hot Spot / Wifi ID Telkom bulan 550,000
1.10.28.03.02.003.018 ISP Fiber Optik 2 Mbps bulan 4,059,000
1.10.28.03.02.003.019 ISP Fiber Optik 20 Mbps bulan 7,360,732
1.10.28.03.02.003.020 ISP Fiber Optik 100 Mbps bulan 95,287,500
1.10.28.03.02.003.021 ISP Fiber Optik 150 Mbps Internasional bulan 140,250,000
1.10.28.03.02.003.022 IP Address /24 tahun 9,072,000
1.10.28.03.02.003.023 Biaya Instalasi Pemasangan IP Address kali 2,000,000
1.10.28.03.02.003.024 Biaya Telepon Tarif Telpon Biasa menit 300
1.10.28.03.02.003.025 Langganan Biznet Metronet 1A 50 Mbps, Belum termasuk PPN 10% bulan 1,000,000
1.10.28.03.02.003.026 Langganan Biznet Metronet 2A 90 Mbps, Belum termasuk PPN 10% bulan 1,700,000
1.10.28.03.02.003.027 Langganan Biznet Metronet 3A 150 Mbps, Belum termasuk PPN 10% bulan 2,700,000
1.10.28.03.02.003.028 Langganan Biznet Dedicated 30 Mbps, Belum termasuk PPN 10% bulan 4,500,000
1.10.28.03.02.003.029 Langganan Biznet Dedicated 40 Mbps, Belum termasuk PPN 10% bulan 6,000,000
1.10.28.03.02.003.030 Langganan Biznet Dedicated 50 Mbps, Belum termasuk PPN 10% bulan 7,500,000
1.10.28.03.02.004 Satuan Biaya Perpanjangan STNK dan Uji Kir
Jenis Sedan: Toyota Corolla,Honda Accord/
1.10.28.03.02.004.001 Biaya Perpanjangan STNK unit/tahun 2,350,000
sekelas
Jenis MPV: Toyota Innova,
1.10.28.03.02.004.002 Biaya Perpanjangan STNK unit/tahun 1,350,000
Avanza,Daihatsu /sekelas
Jenis SUV: Toyota Fortuner, Nissan
1.10.28.03.02.004.003 Biaya Perpanjangan STNK unit/tahun 1,950,000
Xtrail/sekelas
Jenis Van/Mini Bus: Suzuki APV,
1.10.28.03.02.004.004 Biaya Perpanjangan STNK unit/tahun 750,000
Carry/sekelas
Jenis Pick Up: Toyota Hiluk, Suzuki
1.10.28.03.02.004.005 Biaya Perpanjangan STNK unit/tahun 750,000
Carry/sekelas
1.10.28.03.02.004.006 Biaya Perpanjangan STNK Jenis Roda 2: Standart semua tipe unit/tahun 300,000
Kendaraan Bermotor JBB tidak melebihi
1.10.28.03.02.004.007 Biaya Uji Kir unit 80,000
3500 kg
Kendaraan Bermotor JBB lebih dari 3500
1.10.28.03.02.004.008 Biaya Uji Kir unit 100,000
kg
Rusak, JBB kurang dari sama dengan 3500
1.10.28.03.02.004.009 Biaya Pembuatan buku Uji Kir buku 30,000
kg
1.10.28.03.02.004.010 Biaya Pembuatan buku Uji Kir Rusak, JBB lebih dari 3500 kg buku 35,000

52
Hilang, JBB kurang dari sama dengan 3500
1.10.28.03.02.004.011 Biaya Pembuatan buku Uji Kir buku 50,000
kg
1.10.28.03.02.004.012 Biaya Pembuatan buku Uji Kir Hilang, JBB lebih dari 3500 kg buku 60,000
1.10.28.03.02.004.013 Biaya Pembuatan buku Uji Kir Habis masa berlakunya buku 25,000
Rusak, JBB kurang dari sama dengan 3500
1.10.28.03.02.004.014 Biaya Tanda Uji buku 15,000
kg
1.10.28.03.02.004.015 Biaya Tanda Uji Rusak, JBB lebih dari 3500 kg buku 20,000
Hilang, JBB kurang dari sama dengan 3500
1.10.28.03.02.004.016 Biaya Tanda Uji buku 20,000
kg
1.10.28.03.02.004.017 Biaya Tanda Uji Hilang, JBB lebih dari 3500 kg buku 30,000
1.10.28.03.02.004.018 Biaya Tanda Samping Uji Rusak, Hilang, Habis masa berlakunya buku 30,000
1.10.28.03.02.012 Satuan Biaya Premi Asuransi
1.10.28.03.01.004.001 Biaya Premi Asuransi BPJS Ketenagakerjaan bulan 156,000
1.10.28.03.01.004.002 Biaya Premi Asuransi BPJS Kesehatan bulan 105,000
1.10.28.03.02.004.003 Premi Asuransi Kebakaran Untuk OPD Pasar tahun 50,000,000
1.10.28.03.02.005 Satuan Biaya Berlangganan (Surat Kabar, Majalah, Tabloid dan buku Bahan Bacaan)
1.10.28.03.02.005.001 Berlangganan Surat Kabar Koran Harian(Jawa Pos) eksemplar 150,000
1.10.28.03.02.005.009 Berlangganan Majalah Majalah Mingguan (Tempo) buah 200,000
1.10.28.03.02.005.011 Berlangganan Tabloid PC Plus mingguan 20,000
1.10.28.03.01.005.012 Berlangganan Majalah Majalah mingguan-Bobo (13.000/edisi) eksemplar 13,000
Majalah bulanan-Sains Kuark (26.000 per
1.10.28.03.01.005.013 Berlangganan Majalah eksemplar 26,000
tingkatan edisi)
1.10.28.03.02.006 Satuan Biaya Pemasangan dan Berlangganan TV Kabel
1.10.28.03.02.007 Satuan Biaya Tarif Dasar Air minum, Pemeliharaan, Administrasi, Pemasangan PDAM

1.10.28.03.02.007.001 Biaya Tarif Air minum PDAM Kode tarif IV; Blok Pemakaian (0 - 10) m3 m3 1,675

1.10.28.03.02.007.002 Biaya Tarif Air minum PDAM Kode tarif IV; Blok Pemakaian (11 - 20) m3 m3 2,230

1.10.28.03.02.007.003 Biaya Tarif Air minum PDAM Kode tarif IV; Blok Pemakaian (21 - 30) m3 m3 3,345

Kode tarif IV; Blok Pemakaian diatas 30


1.10.28.03.02.007.004 Biaya Tarif Air minum PDAM m3 5,575
m3
Biaya Pemeliharaan Meter dan Biaya
1.10.28.03.02.007.005 Golongan Instansi Pemerintah unit 12,000
Administrasi
Biaya Pemasangan Sambungan Pelanggan
1.10.28.03.02.007.006 Golongan Instansi Pemerintah paket 850,000
Baru/Pipa Dinas
1.10.28.03.02.008 Satuan Biaya Jaminan Kesehatan Total Coverage - Dinas Kesehatan
Pelayanan Kesehatan Semesta (Total
1.10.28.03.02.008.001 Dinas Kesehatan premi/org 2,305,000
Coverage)
1.10.28.03.02.009 Satuan Biaya Kepesertaan
Biaya Kontribusi Pelatihan BCLS (bagi
1.10.28.03.02.009.001 Biaya Kepesertaan orang/paket 1,000,000
perawat)
Biaya Kontribusi Pelatihan ACLS (bagi
1.10.28.03.02.009.002 Biaya Kepesertaan orang/paket 3,250,000
dokter umum)
Biaya Kontribusi Pelatihan ACLS (bagi
1.10.28.03.02.009.003 Biaya Kepesertaan orang/paket 1,400,000
perawat)
1.10.28.03.02.009.004 Biaya Kepesertaan Biaya Kontribusi Pelatihan ATLS orang/paket 5,000,000
1.10.28.03.02.009.005 Biaya Kepesertaan Biaya Kontribusi Pelatihan PPGD orang/paket 2,500,000
Biaya Kontribusi Pelatihan Manajemen
1.10.28.03.02.009.006 Biaya Kepesertaan orang/paket 4,800,000
Puskesmas
Biaya Kontribusi Pelatihan Akreditasi
1.10.28.03.02.009.007 Biaya Kepesertaan orang/paket 3,600,000
Puskesmas
Biaya Kontribusi Pelatihan Pendamping
1.10.28.03.02.009.008 Biaya Kepesertaan orang/paket 5,400,000
Akreditasi FKTP

53
Biaya Kontribusi Pelaksanaan Survailan
1.10.28.03.02.009.009 Biaya Kepesertaan orang/paket 3,500,000
Akreditasi Lab
1.10.28.03.02.009.010 Biaya Kepesertaan Iuran Akreditasi KAN tahun 1,000,000
1.10.28.03.02.009.011 Biaya Kepesertaan Pelatihan PPGDON paket 12,900,000
1.10.28.03.02.009.012 Biaya Kepesertaan Pelatihan ICU paket 48,000,000
1.10.28.03.02.009.013 Biaya Kepesertaan Pelatihan ICCU paket 16,900,000
1.10.28.03.02.009.014 Biaya Kepesertaan Pelatihan NICU paket 17,400,000
1.10.28.03.02.009.015 Biaya Kepesertaan Pelatihan ANESTESI paket 29,200,000
1.10.28.03.02.009.016 Biaya Kepesertaan Pelatihan HEMODIALISA paket 36,000,000

1.10.28.03.02.009.017 Biaya Kepesertaan Pelatihan INSTRUMEN KMR OPERASI paket 43,400,000

1.10.28.03.02.009.018 Biaya Kepesertaan Pelatihan K3 paket 21,800,000


1.10.28.03.02.009.019 Biaya Kepesertaan Pelatihan PLEBOTOMY paket 12,800,000
1.10.28.03.02.009.020 Biaya Kepesertaan Survei Simulasi Akreditasi paket 50,000,000
1.10.28.03.02.009.021 Biaya Kepesertaan Pelatihan PPI Lanjutan paket 7,400,000
1.10.28.03.02.009.022 Biaya Kepesertaan Pelatihan Loundry paket 7,800,000
1.10.28.03.02.009.023 Biaya Kepesertaan Pelatihan PPGD paket 14,135,000
1.10.28.03.02.009.024 Biaya Kepesertaan Pelatihan Bedah Mata paket 20,450,000

1.10.28.03.02.009.025 Biaya Kepesertaan Pelatihan Teknik Analisa Mikrobiologi Air per orang 7,000,000

1.10.28.03.02.009.026 Biaya Kepesertaan Pelatihan Jaminan Mutu Hasil Pengujian per orang 5,000,000

1.10.28.03.02.009.027 Biaya Kepesertaan Pelatihan Mikrobiologi Klinik per orang 4,500,000


Konstribusi dan Akomodasi Pelatihan
1.10.28.03.02.009.028 Biaya Kepesertaan orang/kali 5,000,000
Teknis Subtantif
Rapat Koordinasi Teknis (Rakontek) Dak
1.10.28.03.02.009.029 Biaya Kepesertaan orang/paket 1,686,000
Bidang Kesehatan
1.10.28.03.02.010 Satuan Biaya Taksi Perjalanan Dinas Dalam Negeri
1.10.28.03.02.010.001 Satuan Biaya Taksi Aceh orang/kali 123,000
1.10.28.03.02.010.002 Satuan Biaya Taksi Sumatera Utara orang/kali 232,000
1.10.28.03.02.010.003 Satuan Biaya Taksi Riau orang/kali 94,000
1.10.28.03.02.010.004 Satuan Biaya Taksi Kepulauan Riau orang/kali 137,000
1.10.28.03.02.010.005 Satuan Biaya Taksi Jambi orang/kali 147,000
1.10.28.03.02.010.006 Satuan Biaya Taksi Sumatera Barat orang/kali 190,000
1.10.28.03.02.010.007 Satuan Biaya Taksi Sumatera Selatan orang/kali 128,000
1.10.28.03.02.010.008 Satuan Biaya Taksi Lampung orang/kali 167,000
1.10.28.03.02.010.009 Satuan Biaya Taksi Bengkulu orang/kali 109,000
1.10.28.03.02.010.010 Satuan Biaya Taksi Bangka Belitung orang/kali 90,000
1.10.28.03.02.010.011 Satuan Biaya Taksi Banten orang/kali 446,000
1.10.28.03.02.010.012 Satuan Biaya Taksi Jawa Barat orang/kali 166,000
1.10.28.03.02.010.013 Satuan Biaya Taksi DKI Jakarta orang/kali 256,000
1.10.28.03.02.010.014 Satuan Biaya Taksi Jawa Tengah orang/kali 90,000
1.10.28.03.02.010.015 Satuan Biaya Taksi DI Jogjakarta orang/kali 118,000
1.10.28.03.02.010.016 Satuan Biaya Taksi Jawa Timur orang/kali 194,000
1.10.28.03.02.010.017 Satuan Biaya Taksi Bali orang/kali 159,000
1.10.28.03.02.010.018 Satuan Biaya Taksi Nusa Tenggara Barat orang/kali 231,000
1.10.28.03.02.010.019 Satuan Biaya Taksi Nusa Tenggara Timur orang/kali 108,000
1.10.28.03.02.010.020 Satuan Biaya Taksi Kalimantan Barat orang/kali 135,000
1.10.28.03.02.010.021 Satuan Biaya Taksi Kalimantan Tengah orang/kali 111,000
1.10.28.03.02.010.022 Satuan Biaya Taksi Kalimantan Selatan orang/kali 150,000
1.10.28.03.02.010.023 Satuan Biaya Taksi Kalimantan Timur orang/kali 450,000
1.10.28.03.02.010.024 Satuan Biaya Taksi Kalimantan Utara orang/kali 218,000
1.10.28.03.02.010.025 Satuan Biaya Taksi Sulawesi Utara orang/kali 313,000
1.10.28.03.02.010.026 Satuan Biaya Taksi Gorontalo orang/kali 240,000
1.10.28.03.02.010.027 Satuan Biaya Taksi Sulawesi Barat orang/kali 313,000

54
1.10.28.03.02.010.028 Satuan Biaya Taksi Sulawesi Selatan orang/kali 145,000
1.10.28.03.02.010.029 Satuan Biaya Taksi Sulawesi Tengah orang/kali 165,000
1.10.28.03.02.010.030 Satuan Biaya Taksi Sulawesi Tenggara orang/kali 171,000
1.10.28.03.02.010.031 Satuan Biaya Taksi Maluku orang/kali 240,000
1.10.28.03.02.010.032 Satuan Biaya Taksi Maluku Utara orang/kali 215,000
1.10.28.03.02.010.033 Satuan Biaya Taksi Papua orang/kali 431,000
1.10.28.03.02.010.034 Satuan Biaya Taksi Papua Barat orang/kali 182,000
1.10.28.03.02.011 Satuan Biaya Uang Pembinaan Perlombaan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.001 Perorangan paket 5,000,000
Bidang Olahraga Tingkat Kelurahan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.002 Perorangan paket 10,000,000
Bidang Olahraga Tingkat Kecamatan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.003 Perorangan paket 15,000,000
Bidang Olahraga Tingkat Kota

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.004 Beregu paket 10,000,000
Bidang Olahraga Tingkat Kelurahan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.005 Beregu paket 20,000,000
Bidang Olahraga Tingkat Kecamatan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.006 Beregu paket 30,000,000
Bidang Olahraga Tingkat Kota

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.007 Perorangan paket 4,000,000
Bidang Seni Budaya Tingkat Kelurahan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.008 Perorangan paket 8,000,000
Bidang Seni Budaya Tingkat Kecamatan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.009 Perorangan paket 12,000,000
Bidang Seni Budaya Tingkat Kota

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.010 Beregu paket 6,000,000
Bidang Seni Budaya Tingkat Kelurahan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.011 Beregu paket 12,000,000
Bidang Seni Budaya Tingkat Kecamatan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.012 Beregu paket 18,000,000
Bidang Seni Budaya Tingkat Kota

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.013 Perorangan paket 3,000,000
Bidang Umum Tingkat Kelurahan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.014 Perorangan paket 4,000,000
Bidang Umum Tingkat Kecamatan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.015 Perorangan paket 5,000,000
Bidang Umum Tingkat Kota

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.016 Beregu paket 5,000,000
Bidang Umum Tingkat Kelurahan

55
Uang Pembinaan Perlombaan Non Akademik
1.10.28.03.02.011.017 Beregu paket 7,000,000
Bidang Umum Tingkat Kecamatan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.018 Beregu paket 10,000,000
Bidang Umum Tingkat Kota

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.019 paket 10,000,000
Bidang Umum Tingkat Kelurahan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.020 paket 20,000,000
Bidang Umum Tingkat Kecamatan

Uang Pembinaan Perlombaan Non Akademik


1.10.28.03.02.011.021 paket 50,000,000
Bidang Umum Tingkat Kota
Uang Pembinaan Perlombaan Akademik
1.10.28.03.02.011.022 Perorangan paket 1,500,000
Tingkat PAUD
Uang Pembinaan Perlombaan Akademik
1.10.28.03.02.011.023 Beregu paket 5,000,000
Tingkat PAUD
Uang Pembinaan Perlombaan Akademik
1.10.28.03.02.011.024 Perorangan paket 2,500,000
Tingkat SD/MI
Uang Pembinaan Perlombaan Akademik
1.10.28.03.02.011.025 Beregu paket 10,000,000
Tingkat SD/MI
Uang Pembinaan Perlombaan Akademik
1.10.28.03.02.011.026 Perorangan paket 5,000,000
Tingkat SMP/MTS/SMA/SMK/MA
Uang Pembinaan Perlombaan Akademik
1.10.28.03.02.011.027 Beregu paket 15,000,000
Tingkat SMP/MTS/SMA/SMK/MA
1.10.28.03.02.099 Satuan Biaya Operasional Lain - lain
Pemberian Jaminan Sosial bagi Disabilitas
1.10.28.03.02.099.001 Kegiatan Dinas Sosial OB 700,000
Berat
1.10.28.03.02.099.002 Uang saku wartawan jumpa pers OH 150,000
Uang saku wartawan peliputan inspeksi
1.10.28.03.02.099.003 OH 150,000
mendadak
kegiatan/tahu
1.10.28.03.02.099.006 Biaya Kontribusi APEKSI 30,000,000
n
Biaya Operasional Pemeliharaan Dashboard
1.10.28.03.02.099.007 paket/tahun 65,000,000
Monitoring E Transchool Mojo
1.10.28.03.02.099.008 Langganan Domain Domain : COM, NET,ORG/ sejenisnya paket/tahun 135,000
1.10.28.03.02.099.009 Langganan Domain Domain : ID paket/tahun 250,000
1.10.28.03.02.099.010 Biaya Operasional RT/RW OB 200,000
1.10.28.03.02.099.011 Transport Sidak / Jumpa pers Wartawan OK 1,500,000
Jasa Pelayanan Angkutan Sekolah Gratis hari/kendaraa
1.10.28.03.02.099.012 82,500
Memakai Mikrolet n/kali
1.10.28.03.02.099.013 Bea Balik Nama (BNN) Bus Mini unit 25,000,000
Biaya Penilaian Perluasan Ruang Lingkup
1.10.28.03.02.099.014 paket 5,000,000
Lab
Paket Executive : Pemeriksaan Fisik,
1.10.28.03.02.099.015 General Check-up Rontgen Foto Thorax, THT,Mata, Gigi, orang/tahun 1,500,000
USG,EKG,Pemeriksaan Laboratorium.
kegiatan/tahu
1.10.28.03.02.099.016 Biaya Kontribusi FORSESDASI 10,000,000
n
1.10.28.03.02.099.017 PMT Posyandu Barang diserahkan ke Masyarakat bulan 100,000
Biaya Pengelolaan Sampah Medis dan
1.10.28.03.02.099.018 kg 16,500
Limbah B3
1.10.28.03.02.099.019 Biaya Pajak PBB Aset Pemkot Mojokerto tahun 49,980,000

1.10.28.03.02.099.021 Langganan Cloudflare PRO Professional website, blogs and portfolio paket 270,000

56
Business Advanced security and
1.10.28.03.02.099.022 Langganan Cloudflare BUSINESS paket 2,700,000
performance
1.10.28.03.02.099.023 Langganan SSL Standart tahun 2,362,500
1.10.28.03.02.099.024 Langganan SSL Wildcare tahun 8,032,500
Bagi Hasil Retribusi Parkir Berlangganan
1.10.28.03.02.099.025 tahun 798,228,000
Konvensional
1.10.28.03.02.099.026 Biaya Pengganti buku Cek Bank Jatim buku 125,000
Sudah termasuk Pengurusan Paspor dan
1.10.28.03.02.099.027 Biaya Pemberangkatan UMROH orang 50,000,000
Chek Up kesehatan
1.10.28.03.02.099.028 Biaya Sertifikat Tanah Asset m2 300
1.10.28.03.01.099.029 Retribusi Sampah DLH bulan 25,000
1.10.28.03.01.099.030 Biaya Pengisian E-Toll Kali 50,000

SATUAN BIAYA e-TOLL (PERJALANAN DINAS)


PEMERINTAH KOTA MOJOKERTO TA 2020

NO. ASAL TUJUAN P HARGA PP


1 Mojokerto Surabaya 29,000 58,000.00
2 Mojokerto Bandara Juanda 37,000 74,000.00
3 Mojokerto Sidoarjo 32,500 65,000.00
4 Mojokerto Malang 50,000 100,000.00
5 Mojokerto Gresik 40,500 81,000.00
6 Mojokerto Pasuruan 62,500 125,000.00
7 Mojokerto Probolinggo 102,000 204,000.00
8 Mojokerto Jombang 34,500 69,000.00
9 Mojokerto Kertosono 51,500 103,000.00
10 Mojokerto Madiun 119,500 239,000.00
11 Mojokerto Kab. Ngawi 139,500 279,000.00
12 Mojokerto Kab. Sragen 190,500 381,000.00
13 Mojokerto Solo 225,500 451,000.00
14 Mojokerto Boyolali 234,500 469,000.00
15 Mojokerto Salatiga 243,000 486,000.00
16 Mojokerto Semarang 276,000 552,000.00
17 Mojokerto Kab. Batang 351,000 702,000.00
18 Mojokerto Kab. Pemalang 386,000 772,000.00
19 Mojokerto Kab. Pejagan 443,500 887,000.00
20 Mojokerto Cirebon 472,500 945,000.00
21 Mojokerto Karawang 634,500 1,269,000.00
22 Mojokerto Kab. Purwakarta 633,500 1,267,000.00
23 Mojokerto Bandung 631,500 1,263,000.00
24 Mojokerto Bekasi 642,000 1,284,000.00
25 Mojokerto Jakarta 646,500 1,293,000.00
26 Mojokerto Bogor 653,000 1,306,000.00
27 Mojokerto Kab. Ciawi 659,500 1,319,000.00
28 Mojokerto Tangerang 652,000 1,304,000.00
29 Mojokerto Pelabuhan Merak 693,000 1,386,000.00

57
PENJELASAN STANDAR BIAYA UMUM
YANG BERFUNGSI SEBAGAI BATAS TERTINGGI

NO. URAIAN
1 HONORARIUM PENANGGUNG JAWAB PENGELOLA KEUANGAN/BARANG
1.1. HONORARIUM PENANGGUNG JAWAB PENGELOLA BARANG
1.1. Pengelola Barang/Pengguna Barang
Pengelola Barang adalah Sekretaris Daerah Kota yang diberikan honorarium per orang tiap-tiap
bulan.
Pengguna Barang adalah Kepala Badan/Dinas di SKPD/SKPKD yang diberikan honorarium per
orang tiap-tiap bulan.
1.2. Pengurus Barang Pengelola

Pengurus Barang Pengelola adalah Kepala Bidang yang mengelola aset pada SKPKD (Satuan Kerja
Pengelola Keuangan Daerah) yang diberikan honorarium per orang tiap-tiap bulan.

1.3. Pembantu Pengurus Barang Pengelola


Pembantu Pengurus Barang Pengelola adalah staf yang ditunjuk untuk membantu pengurus
barang pengelola yang diberikan honorarium per orang tiap-tiap bulan.

1.2. PENGGUNA ANGGARAN (PA) / PENGGUNA BARANG (PB)


a. Honorarium PA/PB diberikan dengan anggaran yang dikelola
b. Apabila PA/PB ikut dalam Tim Pelaksana Kegiatan maka PA/PB dapat menerima Honorarium
tersebut
c. Honorarium diberikan tiap-tiap bulan berdasarkan besaran nilai aset yang tercantum pada Neraca
SKPD berkenaan.

1.3. KUASA PENGGUNA ANGGARAN (KPA) / KUASA PENGGUNA BARANG (KPB)


a. Honorarium KPA/KPB diberikan dengan anggaran yang dikelola

b. Apabila KPA/KPB ikut dalam Tim Pelaksana Kegiatan maka KPA/KPB dapat menerima Honorarium
tersebut

c. Honorarium diberikan tiap-tiap bulan berdasarkan besaran nilai aset yang tercantum pada Neraca
SKPD berkenaan.

1.4. PEJABAT PENGELOLA KEUANGAN DAERAH (PPKD) /PEJABAT PENATAUSAHAAN


BARANG(PPB)
a. Kepala satuan kerja pengelola keuangan daerah yang mempunyai tugas melaksanakan pengelolaan
APBD dan bertindak sebagai bedahara umum daerah, yang diberikan honorarium per orang tiap-
tiap bulan.

1.5. PEJABAT PEMBUAT KOMITMEN (PPK)


a. PPK dapat diberikan honorarium setiap bulan sesuai dengan paket pekerjaan yang dikelola selama
masa pelaksanaan pekerjaan, dengan tetap memegang prinsip efisiensi anggaran.
b. Apabila PPK dijabat oleh PA/KPA maka honorarium PPK tidak dapat diberikan
1.6. DIREKSI LAPANGAN / PENGAWAS LAPANGAN

58
a. Direksi Lapangan / Pengawas Lapangan ditetapkan dengan Ketetapan Pejabat yang berwenang,
dapat diberikan honorarium setiap bulan sesuai dengan Paket Pekerjaan yang diawasi dengan tetap
memegang prinsip efisiensi anggaran

1.7. PEJABAT PELAKSANA TEKNIS KEGIATAN (PPTK) dan STAF PENGELOLA


a. PPTK dan staf pengelola kegiatan ditetapkan dengan keputusan pejabat yang berwenang, untuk
melaksanakan 1 (satu) atau beberapa kegiatan.

1.8. PEJABAT PENATAUSAHAAN KEUANGAN SKPD/PPKD (PPK-SKPD/PPKD)


a. PPK-SKPD/PPKD dapat diberikan honorarium setiap bulan sesuai dengan pagu anggaran yang
dikelola SKPD
b. Dalam hal PPK-SKPD/PPKD bertindak sebagai Tim Pelaksana Kegiatan tetap dapat menerima tim
tersebut

1.9. BENDAHARA PENGELUARAN

a. Bendahara Pengeluaran dapat diberikan honorarium setiap bulan sesuai dengan pagu anggaran yang
dikelola

b. Dalam hal bendahara pengeluaran bertindak sebagai anggota tim pelaksana kegiatan tetap dapat
diberikan honorarium tim tersebut
c. Bendahara Pengeluaran adalah Pejabat fungsional yang ditunjuk untuk menerima, menyimpan,
membayarkan, menatausahakan dan mempertanggungjawabkan uang untuk keperluan belanja
daerah dalam rangka pelaksanaan APBD pada SKPD.

1.10. BENDAHARA PENGELUARAN PEMBANTU


a. Bendahara Pengeluaran Pembantu dapat diberikan honorarium setiap bulan sesuai dengan pagu
anggaran yang dikelola KPA.
b. Dalam hal Bendahara Pengeluaran Pembantu bertindak sebagai anggota tim pelaksana kegiatan
tetap dapat diberikan honorarium tim tersebut.

2 HONORARIUM PENGADAAN BARANG/JASA/ ULP


a. Honorarium diberikan kepada pegawai negeri yang diangkat oleh Pengguna/Kuasa Pengguna
Barang/Jasa untuk melaksanakan pemilihan penyedia barang/jasa melalui penunjukkan
langsung/pengadaan langsung untuk paket pengadaan barang/pekerjaan konstruksi/jasa lainnya
yang bernilai paling tinggi Rp. 200.000.000; (dua ratus juta rupiah). Untuk paket pengadaan jasa
konsultasi yang bernilai paling tinggi Rp. 100.000.000; (seratus juta rupiah).

b. Susunan keanggotaan perangkat unit layanan pengadaan barang/jasa ditetapkan oleh walikota, yang
terdiri dari kepala ULP, sekretaris ULP, dan kelompok kerja ULP

c. Honorarium diberikan tiap-tiap bulan kepada kelompok kerja ULP yang ditugaskan oleh kepala
ULP untuk melaksanakan pemilihan penyedian barang/jasa sesuai dengan ketentuan yang berlaku.

59
Catatan :

Dalam hal pejabat / pengadaan barang / jasa dan kelompok kerja ULP telah ditetapkan sebagai jabatan
fungsional dan telah diberikan tunjangan jabatan fungsionalnya, maka pemberian honorarium untuk
Pejabat Pengadaan Barang/Jasa dan Kelompok Kerja ULP dinyatakan tidak berlaku.

3 HONORARIUM PENERIMA HASIL PEKERJAAN


Honorarium diberikan kepada pegawai negeri yang ditunjuk oleh PA/KPA untuk melakukan penilaian
terhadap hasil pekerjaan yang telah diselesaikan dan menerima penyerahan pekerjaan setelah seluruh
hasil pekerjaan dilaksanakan sesuai dengan ketentuan kontrak. Honorarium Pejabat Penerima Hasil
Pekerjaan diberikan per bulan, sedangkan honorarium Panitia Penerima Hasil Pekerjaan diberikan per
paket pekerjaan.

Satu orang Pejabat Penerima Hasil Pekerjaan hanya dapat menerima 1 (satu) Honor dalam 1 (satu) bulan
dalam satu SKPD dapat ditunjuk sebanyak-banyak nya 3 (tiga) orang Pejabat Penerima Hasil Pekerjaan.

4 HONORARIUM PENGELOLAAN BARANG MILIK DAERAH


Honorarium Pengelolaan Barang Milik Daerah diberikan kepada pejabat/pegawai di lingkungan
pengguna barang dan kuasa pengguna barang yang melakukan tugas rutin selaku pengurus/penyimpan
barang berdasarkan surat keputusan pengguna barang.

5 PENGURUS GAJI
Membantu tugas perbendaharaan pada bendahara pengeluaran dalam pengurusan gaji yang diberikan
honorarium per orang tiap-tiap bulan berdasarkan nilai pagu anggaran.

6 BENDAHARA PENERIMAAN
Pegawai Negeri Sipil yang ditetapkan oleh Walikota untuk Menerima, menyimpan, menyetorkan,
menatausahakan, dan mempertanggungjawabkan uang pendapatan daerah yang diberikan honorarium
per orang tiap-tiap bulan berdasarkan nilai target pendapatan.

7 BENDAHARA PENERIMAAN PEMBANTU


Pegawai Negeri Sipil yang ditetapkan oleh Walikota untuk Membantu tugas perbendaharaan pada
bendahara penerimaan yang diberikan honorarium per orang tiap-tiap bulan berdasarkan nilai target
pendapatan.

8 HONORARIUM PENUNJANG PENELITIAN / PEREKAYASAAN


Honorarium peneliti dberikan kepada pegawai negeri dan non pegawai negeri yang terdiri dari
pembantu peneliti/perekayasa, coordinator peneliti/perekayasa, secretariat peneliti/perekayasaan,
pengolah data, petugas survey, pembantu lapangan yang berdasarkan surat perintah pejabat yang
berwenang diberi tugas untuk menunjang kegiatan penelitian /perekayasaan yang dilakukan oleh
fungsional peneliti/perekayasa.
Terhadap pembantu peneliti/perekayasa sebagaimana tersebut diatas yang berstatus pegawai negeri
tidak diberikan uang lembur dan uang makan lembur.

60
1. Dalam hal penelitian/perekayasaan dilakukan bersama-sama dengan pegawai negeri (non fungsional
peneliti/perekayasa), kepada pegawai negeri (non fungsional peneliti/perekayasa) atas penugasan
penelitian yang dilakukan di luar jam kerja normal diberikan honorarium paling tinggi sebesar 85%
(delapan puluh lima persen) dari honorarium kelebihan jam. perekayasaan untuk perekayasa
pertama.

2. Honorarium penunjang penelitian / perekayasaan diberikan secara selektif dengan


mempertimbangkan prinsip efisiensi dan efektifitas.

HONORARIUM NARASUMBER SEMINAR/RAKOR/SOSIALISASI/DISEMINASI/ FOCUS


9
GROUP DISCUSSION/ KEGIATAN SEJENIS
a. Honorarium Narasumber Pakar/Praktisi/Pembicara Khusus/Tenaga ahli
Honorarium narasumber dapat diberikan kepada PNS dengan melihat kemampuan yang bersangkutan
memberikan informasi / pengetahuan kepada pegawai negeri lainnya/masyarakat dengan ketentuan
sebagai berikut:
1) Berasal dari luar lingkup SKPD penyelenggara; dan
2) Berasal dari lingkup SKPD penyelenggara sepanjang peserta yang menjadi sasaran utama
kegiatan berasal dari luar lingkup SKPD penyelenggara / masyarakat.
Honorarium narasumber Pakar/Praktisi/Pembicara Khusus/Tenaga ahli diberikan kepada Non PNS
dengan melihat kemampuan yang bersangkutan.
b. Honorarium Moderator
Honorarium moderator diberikan kepada pegawai negeri/non pegawai negeri yang melaksanakan tugas
sebagai moderator pada kegiatan seminar /rakor / sosialisasi/ diseminasi / focus group discussion /
kegiatan sejenis.
Pelaksanaan kegiatan seminar /rakor / sosialisasi/ diseminasi / focus group discussion / kegiatan sejenis
dapat menggunakan jasa moderator dalam hal diperlukan.
Catatan :
Satuan jam yang digunakan untuk kegiatan seminar /rakor / sosialisasi/ diseminasi / focus group
discussion / kegiatan sejenis, setara dengan jam pelajaran, paling kurang 60 (enam puluh) menit.

HONORARIUM PANITIA SEMINAR/RAKOR/SOSIALISASI/DISEMINASI/ FOCUS GROUP


10
DISCUSSION/ KEGIATAN SEJENIS
Honorarium dapat diberikan kepada pegawai negeri yang diberi tugas sebagai panitia untuk
melaksanakan kegiatan Seminar/Rakor/Sosialisasi/Diseminasi/ Focus Group Discussion/ Kegiatan
Sejenis sepanjang peserta yang menjadi sasaran utama kegiatan berasal dari luar lingkup unit SKPD
penyelenggara/masyarakat.
Dalam hal pelaksanaan kegiatan Seminar/Rakor/Sosialisasi/Diseminasi/ Focus Group Discussion/
Kegiatan Sejenis non pegawai memerlukan tambahan panitia yang berasal dari non pegawai negeri
harus dilakukan secara selektif dengan mempertimbangkan urgensi, dengan besaran honorarium
mengacu pada besaran honorarium untuk anggota panitia.

11 HONORARIUM PENYULUH NON PEGAWAI NEGERI


Honorarium diberikan kepada non pegawai negeri yang ditunjuk untuk melakukan penyuluhan
berdasarkan surat keputusan pejabat yang berwenang.

61
Honorarium diberikan sebagai pengganti upah kerja kepada Nonpegawai Negeri Sipil yang diangkat
untuk melakukan penyuluhan berdasarkan surat keputusan pejabat yang berwenang.

12 HONORARIUM TIM PELAKSANA KEGIATAN


1) Honorarium tim pelaksana kegiatan dapat diberikan kepada pegawai negeri atau non pegawai yang
diberi tugas untuk melaksanakan kegiatan berdasarkan surat keputusan Walikota/ PA/ KPA.
Ketentuan pembentukan tim adalah sebagai berikut :
a) Mempunyai keluaran (output) jelas dan terukur;
b) Bersifat koordinatif baik internal maupun eksternal SKPD;
c) Bersifat temporer, pelaksanaannya perlu diprioritaskan atau di luar jam kerja;
d) Merupakan perangkapan fungsi atau tugas tertentu kepada pegawai negeri di samping tugas
pokoknya sehari-hari;
e) Dilakukan secara selektif, efektif, dan efisien.
2) Honorarium Sekretariat Tim Pelaksana Kegiatan
Honorarium diberikan kepada pegawai negeri/non pegawai negeri yang diberi tugas untuk
melaksanakan kegiatan administratif yang berfungsi untuk menunjang kegiatan tim pelaksana
kegiatan. Sekretariat hanya dapat dibentuk untuk menunjang tim pelaksana kegiatan yang
ditetapkan oleh Walikota/ PA/ KPA.

13 HONORARIUM TIM PENYUSUNAN JURNAL


Honorarium tim penyusunan jurnal dapat diberikan kepada Pegawai Aparatur Sipil Negara/Anggota
Polri/TNI dan Pegawai Non Aparatur Sipil Negara yang diberi tugas untuk menyusun dan menerbitkan
jurnal berdasarkan surat keputusan pejabat yang berwenang. Unsur sekretariat adalah pembantu
umum, pelaksana dan yang sejenis, dan tidak berupa struktur organisasi tersendiri.

14 HONORARIUM TIM PENYUSUNAN BULETIN/MAJALAH


Honorarium tim penyusunan jurnal dapat diberikan kepada Pegawai Aparatur Sipil Negara/Anggota
Polri/TNI dan Pegawai Non Aparatur Sipil Negara yang diberi tugas untuk menyusun dan menerbitkan
buletin/majalah, berdasarkan surat keputusan pejabat yang berwenang.
Majalah adalah terbitan berkala yang isinya berbagai liputan jurnalistik, pandangan tentang topik
aktual yang patut diketahui pembaca.

Buletin adalah media cetak berupa selebaran atau majalah berisi warta singkat atau pernyataan tertulis
yang diterbitkan secara periodik yang ditujukan untuk lembaga atau kelompok profesi tertentu.

15 HONORARIUM TIM PENGELOLA WEBSITE PEMERINTAH KOTA MOJOKERTO


Honorarium tim pengelola website dapat diberikan kepada Pegawai Aparatur Sipil Negara/Anggota
Polri/TNI yang diberi tugas untuk mengelola website berdasarkan surat keputusan pejabat yang
berwenang. Website yang dimaksud di sini adalah yang dikelola oleh Pemerintah Kota Mojokerto

16 VAKASI PENYELENGGARA UJIAN

62
Vakasi/honorarium penyelenggara ujian pada tingkat pendidikan dasar dan menengah, tidak diberikan
untuk penyelenggaraan ujian yang bersifat latihan dan ujian lokal. Satuan biaya pengawas ujian untuk
pengawas ujian tingkat pendidikan dasar dan menengah sudah termasuk uang transport. Vakasi
penyelenggara ujian pada tingkat pendidikan tinggi diberikan untuk ujian semester dan ujian akhir.

Honorarium penguji pendadaran/skripsi diberikan kepada dosen penguji skripsi.

SATUAN BIAYA UANG LEMBUR DAN UANG MAKAN BAGI PEGAWAI APARATUR SIPIL
17
NEGARA (ASN)
a. Uang Lembur merupakan kompensasi bagi pegawai aparatur sipil negara yang melakukan kerja
lembur berdasarkan surat perintah dari pejabat yang berwenang.
Kerja lembur adalah segala pekerjaan yang harus dilakukan oleh Pegawai Negeri Sipil pada waktu –
waktu tertentu di luar waktu jam kerja sebagaimana telah ditetapkan bagi tiap-tiap instansi dan
kantor Pemerintah.
Kerja lembur tiap – tiap kali selama paling sedikit 1 (satu) jam penuh dapat diberikan uang lembur.
b. Uang makan diberikan setelah kerja lembur minimal 2 (dua) jam berturut – turut dan diberikan
maksimal 1 (satu) kali dalam hal kerja lembur dilaksanakan 8 (delapan) jam atau lebih dalam sehari.
Uang lembur pada hari libur kerja sebesar 200% (dua ratus persen) dari besarnya uang lembur.

SATUAN BIAYA LEMBUR DAN UANG MAKAN BAGI PEGAWAI NON APARATUR SIPIL
18
NEGARA (ASN), SATPAM, PENGEMUDI, PETUGAS KEBERSIHAN , DAN PRAMUBAKTI

a. Uang Lembur merupakan kompensasi bagi pegawai non aparatur sipil negara yang melakukan kerja
rutin kementerian negara/lembaga, Satpam, Pengemudi, Petugas Kebersihan, dan Pramubakti yang
melakukan kerja lembur berdasarkan surat perintah dari pejabat yang berwenang.

b. Uang makan diberikan setelah kerja lembur minimal 2 (dua) jam berturut – turut dan diberikan
maksimal 1 (satu) kali sehari.

19 HONORARIUM SATPAM, PENGEMUDI, PETUGAS KEBERSIHAN, DAN PRAMUBAKTI


Satuan biaya honorarium diperuntukkan bagi non pegawai negeri yang ditunjuk untuk melakukan
kegiatan sesuai dengan tugas dan fungsinya, berdasarkan surat keputusan pejabat yang
berwenang/kontrak kerja. Upah Minimum Kabupaten/Kota sebagaimana yang dimaksud sudah diatur
dalam Keputusan Gubernur Jawa Timur 188/665/KPTS/013/2018.

20 SATUAN BIAYA DIKLAT PIMPINAN/STRUKTURAL


Satuan biaya yang digunakan untuk perencanaan kebutuhan biaya diklat penjenjangan untuk
pejabat/pegawai yang akan/telah menduduki jabatan tertentu. Satuan biaya sudah termasuk biaya
observasi lapangan, namun belum termasuk biaya perjalanan dinas peserta. Apabila dalam pelaksanaan
anggaran terjadi perubahan tarif biaya diklat pimpinan, satuan biaya dapat mengacu pada Peraturan
Pemerintah yang mengatur tentang tarif diklat pimpinan tersebut.

21 SATUAN BIAYA LATIHAN PRAJABATAN

63
Satuan biaya latihan prajabatan merupakan satuan biaya yang digunakan untuk perencanaan
kebutuhan biaya latihan prajabatan bagi calon pegawai negeri sebagai syarat untuk diangkat sebagai
pegawai negeri. Satuan biaya ini sudah termasuk biaya observasi lapangan, namun belum ternmasuk
biaya perjalanan dinas peserta.

22 SATUAN BIAYA PEMELIHARAAN SARANA KANTOR


Satuan biaya pemeliharaan sarana kantor digunakan untuk mempertahankan barang
inventaris/peralatan kantor (yang digunakan langsung oleh pegawai, khususnya meja dan kursi),
personal computer/Notebook, Printer, AC Split, dan Genset agar berada dalam kondisi normal
(beroperasi dengan baik).
Untuk biaya pemeliharaan genset belum termasuk kebutuhan bahan bakar minyak.

23 SATUAN BIAYA PEMELIHARAAN KENDARAAN


Satuan biaya pemeliharaan dan operasional kendaraan dinas digunakan untuk mempertahankan
kendaraan dinas agar tetap dalam kondisi normal dan siap pakai sesuai dengan peruntukannya
termasuk biaya bahan bakar. Satuan biaya tersebut belum termasuk biaya pengurusan Surat Tanda
Nomor Kendaraan (STNK).
Catatan:
Yang dimaksud kendaraan operasional dalam lingkungan kantor adalah kendaraan yang digunakan
hanya terbatas dalam lingkungan kantor.

24 SATUAN BIAYA PENERJEMAHAN DAN PENGETIKAN


Satuan biaya yang digunakan untuk perencanaan kebutuhan biaya penerjemahan dan pengetikan,
dibayarkan kepada pihak/orang yang menerjemahkan naskah asli ke dalam bahasa yang diinginkan.

25 SATUAN BIAYA BANTUAN BEASISWA PROGRAM GELAR / NON-GELAR DALAM NEGERI

Satuan biaya bantuan beasiswa program gelar/non gelar dalam negeri merupakan satuan biaya yang
digunakan untuk perencanaan kebutuhan biaya bantuan mahasiswa program gelar / non gelar dalam
negeri bagi pegawai negeri yang ditugaskan untuk melanjutkan pendidikan Diploma I, Diploma III,
Diploma IV, atau Strata I (satu), dan pendidikan Pasca Sarjana ( Strata 2 (dua) atau Strata 3 (tiga) ) yang
terdiri dari biaya hidup dan biaya operasional, uang buku dan referensi per tahun. Biaya untuk
pendidikan ditanggung oleh pemerintah secara at cost sedangkan untuk biaya riset program dapat
dialokasikan bantuan biaya riset sesuai kemampuan keuangan Kota Mojokerto masing-masing, yang
dalam pengusulannya dilampiri dengan Terms of Reference (TOR), Rincian Anggaran Biaya (RAB), dan
Surat Pernyataan Tanggung Jawab Mutlak (SPTJM).

Khusus tenaga pengajar biasa pada perguruan tinggi yang ditugaskan mengikuti pendidikan fakultas
pasca sarjana, besaran tunjangan tugas belajar merujuk Keputusan Presiden Nomor 57 tahun 1986
tentang Tunjangan Belajar Bagi Tenaga Pengajar Biasa Pada Perguruan Tinggi Yang Ditugaskan
Mengikuti Pendidikan Pada Fakultas Pasca Sarjana.

26 SATUAN BIAYA MAKANAN PENAMBAH DAYA TAHAN TUBUH/EKSTRA PUDING

64
Satuan biaya yang digunakan untuk perencanaan kebutuhan biaya pengadaan makanan/minuman bagi
pegawai negeri sebagai penambah daya tahan tubuh, hanya diberikan kepada pegawai negeri yang jenis
pekerjaannya dapat memberikan dampak buruk bagi kesehatan pegawai tersebut.

27 SATUAN BIAYA KONSUMSI RAPAT


Satuan biaya yang digunakan untuk perencanaan kebutuhan biaya pengadaan konsumsi makanan
termasuk minuman dan kudapan untuk rapat/pertemuan yang diselenggarakan di kantor.
Rapat Koordinasi Tingkat Menteri/SKPD/Tamu-tamu dari Luar Daerah/FORPIMDA adalah rapat
koordinasi yang pesertanya Rapat Koordinasi Tingkat Menteri/SKPD /Tamu-tamu dari Luar/
FORPIMDA.

28 SATUAN BIAYA PEMELIHARAAN GEDUNG/BANGUNAN DALAM NEGERI


Satuan biaya digunakan untuk pemeliharaan rutin dengan maksud menjaga/ mempertahankan gedung
dan bangunan kantor di dalam negeri agar tetap dalam kondisi semula atau perbaikan dengan tingkat
kerusakan kurang dari atau sama dengan 2% (dua persen).

29 SATUAN BIAYA PENGADAAN PAKAIAN DINAS DAN/ATAU PAKAIAN KERJA


Satuan biaya yang digunakan untuk perencanaan kebutuhan biaya pengadaan pakaian dinas, pakaian
seragam dan/atau kerja resmi.
a. Satuan Biaya Pakaian Dinas Dokter
Satuan biaya pakaian dinas dokter diperuntukkan bagi dokter dan penyediaannya secara selektif.
Pakaian dinas dapat diberikan berupa 1 (satu) potong jas untuk dokter Satuan biaya tersebut sudah
termasuk ongkos jahit.
b. Satuan Biaya Pakaian Dinas dan/atau Kerja Resmi Pegawai/Perawat
Hanya dapat dialokasikan dengan ketentuan:

1) Bagi satuan kerja yang pada awal pembentukannya terdapat ketentuan yang mewajibkan
penggunaan pakaian seragam (pengaturannya setingkat Peraturan Presiden), pakaian dinas dapat
dialokasikan meskipun belum memiliki ijin prinsip dari Menteri Pendayagunaan Aparatur Negara
dan Reformasi Birokrasi;

2) Bagi satuan kerja yang pada awal pembentukannya tidak terdapat ketentuan yang mewajibkan
penggunaan pakaian seragam (setingkat Peraturan Presiden) tetapi mempunyai tugas dan fungsi
berkaitan dengan pelayanan langsung kepada masyarakat, keamanan, penegak keadilan, atau
pemeriksaan dapat mengalokasikan biaya untuk pakaian dinas setelah memiliki ijin prinsip dari
Menteri Pendayagunaan Aparatur Negara dan Reformasi Birokrasi;
3) diberikan paling banyak 2 (dua) stel per tahun;
4) pakaian perawat di peruntukkan bagi perawat dan penyediaannya secara selektif. Pakaian
dimaksud diberikan 1 (satu) stel per tahun.
c. Satuan Biaya Pakaian Kerja Sopir/Pesuruh
Satuan biaya pakaian sopir/pesuruh diperuntukkan bagi sopir/pesuruh yang diangkat berdasarkan
surat keputusan pejabat yang berwenang. Pakaian sopir/pesuruh dapat diberikan paling banyak 2
(dua) stel per tahun. Satuan biaya tersebut sudah termasuk ongkos jahit.
d. Satuan Biaya Pakaian Kerja Satpam

65
Pakaian satpam sudah termasuk perlengkapannya (sepatu, baju PDL, kopel, ikat pinggang, tali kurt
dan peluit, kaos kaki, topi, kaos security dan atribut lainnya). Pakaian satpam dapat diberikan paling
banyak 2 (dua) stel per tahun.

30 SATUAN BIAYA PERJALANAN DINAS DALAM NEGERI DAN UANG REPRESENTASI


a. Satuan biaya uang harian perjalanan dinas dalam negeri merupakan penggantian biaya keperluan
sehari-hari Pejabat Negara/Pegawai Aparatur Sipil Negara/Anggota Polri/TNI/Pihak Lain dalam
menjalankan perintah perjalanan dinas di dalam negeri.
b. Uang representasi hanya diberikan kepada pejabat negara (ketua/wakil ketua dan anggota lembaga
tinggi negara, Menteri serta setingkat Menteri), pejabat eselon I dan pejabat eselon II yang
melaksanakan perjalanan dinas jabatan dalam rangka pelaksanaan tugas dan fungsi yang melekat
padajabatan sebagaimana diatur dalam Peraturan Menteri Keuangan mengenai perjalanan dinas
dalam negeri bagi pejabat negara, pegawai negeri, dan pegawai tidak tetap .
c. Uang harian diklat diberikan kepada Pegawai Aparatur SipilNegara/ Anggota Polri/TNI/Pihak
Lain yang diberikan tugas untuk mengikuti kegiatan pendidikan dan pelatihan yang
diselenggarakan didalam kota yang melebihi 8 (delapan) jam atau diselenggarakan di luar kota.

31 ZONA PERJALANAN DINAS


a. Zona A meliputi: Kabupaten Mojokerto, Kabupaten Jombang, Kabupaten Sidoarjo, Kota Surabaya,
Kabupaten Gresik.
b. Zona B meliputi: Kabupaten Lamongan, Kabupaten Nganjuk, Kabupaten Kediri, Kota Kediri,
Kabupaten Pasuruan, Kota Pasuruan, Kabupaten Malang, Kota Malang, Kota Batu, Kabupaten
Madiun, Kota Madiun.
c. Zona C meliputi: Kabupaten Blitar, Kota Blitar, Kabupaten Tulungagung, Kabupaten Probolinggo,
Kota Probolinggo, Kabupaten Tuban, Kabupaten Bojonegoro, Kabupaten Ponorogo, Kabupaten
Magetan, Kabupaten Ngawi.
d. Zona D meliputi: Kabupaten Trenggalek, Kabupaten Lumajang, Kabupaten Jember, Kabupaten
Bondowoso, Kabupaten SituBondo, Kabupaten Banyuwangi, Kabupaten Bangkalan, Kabupaten
Sampang, Kabupaten Pamekasan, Kabupaten Sumenep, Pacitan.

32 SATUAN BIAYA E-TOLL


Satuan biaya yang digunakan untuk biaya perjalanan dinas malalui jalan tol dari Badan Pengatur Jalan
Tol (BPJT). Keberadaan BPJT diamanatkan oleh Undang-undang No. 38 tahun 2004 tentang Jalan,
diatur dalam Peraturan Pemerintah No. 15 tahun 2005 tentang Jalan Tol dan ditetapkan melalui
Peraturan Menteri Pekerjaan Umum No.295/PRT/M/2005 tentang Badan Pengatur Jalan Tol.

66
Biaya Pengisian e-Toll adalah biaya nominal minimum pengisian kartu elektronik untuk mesin Toll
yang akan digunakan perangkat daerah terkait dalam melakukan perjalanan dinas dalam negeri dalam
lingkup pulau Jawa.
Nominal minimum ini diberlakukan untuk satu kali pengisian dan berlaku kelipatan menyesuaikan
kebutuhan dan tujuan perjalanan dinas perangkat daerah terkait yang melewati satu ataupun beberapa
ruas Toll atau tujuan tertentu.
Patokan tarif untuk penganggaran Biaya Pengisian E-Toll mengacu pada tabel asal-tujuan yang besaran
tarifnya mengacu pada tarif aktual gardu Toll yang berlaku di setiap tujuan perjalanan dinas.
Asumsi asal perjalanan dinas adalah Kota Mojokerto dan asumsi tujuan mengikuti kota tujuan di pulau
Jawa yang dihubungkan jaringan Toll hingga tahun 2019

67
PEMERINTAH KOTA
MOJOKERTO

n
ta
a
gi
Ke
k
ko
Po
K
n
ua
SP
t
Sa
ga
H
ar
H

REKAP

TAHUN ANGGARAN
2020
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.01 HSPK FISIK - KONSTRUKSI
2.01.01 BANGUNAN GEDUNG
2.01.01.01 PEKERJAAN PERSIAPAN DAN TANAH
2.01.01.01.01 PEKERJAAN PERSIAPAN
2.01.01.01.01.002 Pekerjaan Pembuatan Pagar Sementara Seng Gelombang Tinggi 2 m m' 389,732
2.01.01.01.01.003 Pekerjaan Pembuatan Pagar Sementara Kawat Duri Tinggi 1.8 m m' 141,437
2.01.01.01.01.004 Pekerjaan Pengukuran dan Pemasangan Bouwplank m' 145,360
2.01.01.01.01.008 Pekerjaan Pembersihan Lapangan "Ringan" dan Perataan m2 10,000
2.01.01.01.01.020 Pekerjaan Pembersihan Lapangan "Berat" dan Perataan m2 20,000
2.01.01.01.01.010 Pekerjaan Pembuatan Jalan Sementara m2 151,353
2.01.01.01.01.011 Pekerjaan Pembongkaran Beton Bertulang m3 1,466,600
2.01.01.01.01.013 Pekerjaan Pembongkaran Pasangan Batu Kali m3 245,800
2.01.01.01.01.015 Pekerjaan Pembongkaran Tembok Batu Bata m3 733,300
2.01.01.01.01.016 Pekerjaan Pembongkaran Penutup Atap Tidak Dipakai Kembali m2 11,000
2.01.01.01.01.017 Pekerjaan Pembongkaran Penutup Atap dan Dipakai Kembali m2 22,000
2.01.01.01.01.018 Pekerjaan Pembongkaran Paving Tidak Dipakai Kembali m2 2,000
2.01.01.01.01.021 Pekerjaan Pembongkaran Paving dan Dipakai Kembali m2 4,000
2.01.01.01.02 PEKERJAAN TANAH
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa m3 80,000
2.01.01.01.02.004 Pekerjaan Galian Tanah Keras m3 106,400
2.01.01.01.02.005 Pekerjaan Galian Tanah Cadas m3 162,000
2.01.01.01.02.006 Pekerjaan Galian Tanah Lumpur m3 129,000
2.01.01.01.02.007 Pekerjaan Stripping Tebing Setinggi 1 m m2 10,500
2.01.01.01.02.008 Pekerjaan Pembuangan Hasil Galian Sejauh 30 m m3 35,000
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa m3 60,000
2.01.01.01.02.016 Pekerjaan Pemadatan Tanah dengan Alat m3 82,480
2.01.01.01.02.017 Pekerjaan Pemasangan Pudel Campuran 1 Kp : 3 Pp : 7 Tl m3 361,149
2.01.01.01.02.018 Pekerjaan Pemasangan Lapisan Ijuk Tebal 10 cm untuk Bidang Resapan m2 213,600
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug m3 254,600
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat m3 299,760
2.01.01.01.02.022 Pekerjaan Pengurugan dengan Tanah Urug m3 241,880
2.01.01.01.02.023 Pekerjaan Pengurugan dengan Tanah Taman m3 266,960
2.01.01.02 PEKERJAAN PONDASI
2.01.01.02.01 PEKERJAAN PONDASI
2.01.01.02.01.001 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 3 Pp) m3 780,273
2.01.01.02.01.002 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 4 Pp) m3 747,566
2.01.01.02.01.003 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 5 Pp) m3 724,881
2.01.01.02.01.007 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1/4 Pc : 1 Kp : 4 Pp) m3 640,371
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) m3 432,606
2.01.01.02.01.011 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 20 cm Sedalam 3 m titik 192,720
2.01.01.02.01.012 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 30 cm Sedalam 3 m titk 207,264
2.01.01.03 PEKERJAAN STRUKTUR UTAMA
2.01.01.03.01 PEKERJAAN BETON
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 m3 729,451

68
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.01.01.03.01.002 Pekerjaan Pembuatan Beton K-100 m3 803,529
2.01.01.03.01.003 Pekerjaan Pembuatan Beton K-125 m3 827,493
2.01.01.03.01.004 Pekerjaan Pembuatan Beton K-150 m3 846,661
2.01.01.03.01.005 Pekerjaan Pembuatan Beton K-175 m3 869,019
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 m3 890,439
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 m3 906,467
2.01.01.03.01.008 Pekerjaan Pembuatan Beton K-250 m3 917,022
2.01.01.03.01.009 Pekerjaan Pembuatan Beton K-275 m3 936,061
2.01.01.03.01.010 Pekerjaan Pembuatan Beton K-300 m3 941,594
2.01.01.03.01.011 Pekerjaan Pembuatan Beton K-325 m3 1,025,613
2.01.01.03.01.012 Pekerjaan Pembuatan Beton K-350 m3 1,033,146
2.01.01.03.01.013 Pekerjaan Pembesian dengan Besi Polos/Ulir kg 13,352
2.01.01.03.01.015 Pekerjaan Pemasangan Wiremesh kg 12,131
2.01.01.03.01.016 Pekerjaan Pembuatan Pondasi Beton Bertulang (150 kg Besi + Bekisting) m3 4,671,766
2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) m3 5,828,054
2.01.01.03.01.018 Pekerjaan Pembuatan Kolom Beton Bertulang (300 kg Besi + Bekisting) m3 10,378,596
2.01.01.03.01.019 Pekerjaan Pembuatan Balok Beton Bertulang (200 kg Besi + Bekisting) m3 8,232,995
2.01.01.03.01.020 Pekerjaan Pembuatan Plat Beton Bertulang (150 kg Besi + Bekisting) m3 7,678,812
2.01.01.03.01.021 Pekerjaan Pembuatan Dinding Beton Bertulang (150 kg Besi + Bekisting) m3 7,296,126
2.01.01.03.01.022 Pekerjaan Pembuatan Dinding Beton Bertulang (200 kg Besi + Bekisting) m3 7,322,586
2.01.01.03.01.023 Pekerjaan Pembuatan Kolom Praktis Beton Bertulang 11x11 cm m' 83,912
2.01.01.03.01.024 Pekerjaan Pembuatan Ring Balok Beton Bertulang 10x15 cm m' 121,081
2.01.01.03.02 PEKERJAAN CETAKAN BETON (BEKISTING)
2.01.01.03.02.001 Pekerjaan Pasang Bekisting untuk Pondasi m2 355,126
2.01.01.03.02.002 Pekerjaan Pasang Bekisting untuk Sloof m2 386,036
2.01.01.03.02.003 Pekerjaan Pasang Bekisting untuk Kolom m2 711,455
2.01.01.03.02.004 Pekerjaan Pasang Bekisting untuk Balok m2 635,058
2.01.01.03.02.005 Pekerjaan Pasang Bekisting untuk Lantai m2 712,655
2.01.01.03.02.006 Pekerjaan Pasang Bekisting untuk Dinding m2 617,575
2.01.01.03.02.007 Pekerjaan Pasang Bekisting untuk Tangga m2 548,791
2.01.01.04 PEKERJAAN PASANGAN DINDING DAN PLESTERAN
2.01.01.04.01 PEKERJAAN PASANGAN DINDING
2.01.01.04.01.001 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 2 Ps) m2 268,884
2.01.01.04.01.002 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 2 Ps) m2 131,282
2.01.01.04.01.003 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 3 Ps) m2 260,312
2.01.01.04.01.004 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 3 Ps) m2 127,062
2.01.01.04.01.013 Pekerjaan Pasangan Dinding Bata Ringan Tebal 7,5 cm dengan Mortar Siap Pakai m2 385,707
2.01.01.04.01.014 Pekerjaan Pasangan Dinding Bata Ringan Tebal 10 cm dengan Mortar Siap Pakai m2 413,780
2.01.01.04.01.015 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 4 Ps) m2 254,271
2.01.01.04.01.016 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 4 Ps) m2 124,731
2.01.01.04.01.017 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 5 Ps) m2 251,540
2.01.01.04.01.018 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 5 Ps) m2 123,271
2.01.01.04.01.019 Pekerjaan Pemasangan Dinding Bata Expose tbl 1 Bata (1 Pc : 3 Ps) m2 1,099,504
2.01.01.04.02 PEKERJAAN PLESTERAN

69
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.01.01.04.02.001 Pekerjaan Plesteran 1 Pc : 1 Ps tbl 15 mm m2 76,131
2.01.01.04.02.002 Pekerjaan Plesteran 1 Pc : 2 Ps tbl 15 mm m2 71,570
2.01.01.04.02.003 Pekerjaan Plesteran 1 Pc : 3 Ps tbl 15 mm m2 69,661
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm m2 68,305
2.01.01.04.02.005 Pekerjaan Plesteran 1 Pc : 5 Ps tbl 15 mm m2 67,609
2.01.01.04.02.014 Pekerjaan Plesteran Skoning 1 Pc : 3 Ps lebar 10 cm m' 77,637
2.01.01.04.02.015 Pekerjaan Benangan m' 54,899
2.01.01.04.02.016 Pekerjaan Plesteran Ciprat 1 Pc : 2 Ps m2 54,899
2.01.01.04.02.020 Pekerjaan Acian m2 41,750
2.01.01.05 PEKERJAAN PENUTUP LANTAI DAN DINDING
2.01.01.05.01 PEKERJAAN PENUTUP LANTAI
2.01.01.05.01.001 Pekerjaan Pemasangan Lantai Granit Uk. 60x60 cm m2 513,621
2.01.01.05.01.002 Pekerjaan Pemasangan Lantai Granit Uk. 40x40 cm m2 489,356
2.01.01.05.01.013 Pekerjaan Pemasangan Lantai Granit Uk. 30x30 cm m2 334,331
2.01.01.05.01.003 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 40x40 cm m2 254,259
2.01.01.05.01.004 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 30x30 cm m2 229,635
2.01.01.05.01.005 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 20x20 cm m2 219,491
2.01.01.05.01.006 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 40x40 cm m2 310,931
2.01.01.05.01.007 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 30x30 cm m2 289,143
2.01.01.05.01.008 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 20x20 cm m2 276,791
2.01.01.05.01.009 Pekerjaan Pemasangan Lantai Marmer Uk. 100x100 cm m2 558,324
2.01.01.05.01.011 Pekerjaan Pemasangan Lantai Kayu (Parquet) m2 218,660
2.01.01.05.01.012 Pekerjaan Pemasangan Lantai Karpet + Underlayer (Pelapis Bawah Karpet) m2 182,230
2.01.01.05.02 PEKERJAAN PENUTUP DINDING
2.01.01.05.02.001 Pekerjaan Pemasangan Dinding Keramik Polos Uk. 20x25 cm m2 289,670
2.01.01.05.02.002 Pekerjaan Pemasangan Dinding Keramik Polos Uk. 20x20 cm m2 280,980
2.01.01.05.02.003 Pekerjaan Pemasangan Dinding Keramik Polos Uk. 10x20 cm m2 300,061
2.01.01.05.02.004 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x25 cm m2 289,670
2.01.01.05.02.005 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x20 cm m2 338,280
2.01.01.05.02.006 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 10x20 cm m2 300,061
2.01.01.05.02.007 Pekerjaan Pemasangan Plint Keramik 10x20 cm m' 53,432
2.01.01.05.02.011 Pekerjaan Pemasangan Batu Palimanan m2 320,683
2.01.01.05.02.013 Pekerjaan Pemasangan Batu Ampyang m2 254,383
2.01.01.05.02.015 Pekerjaan Pemasangan Batu Gilang m2 349,753
2.01.01.05.02.018 Pekerjaan Pemasangan Wallpaper m2 116,158
2.01.01.06 PEKERJAAN KAYU
2.01.01.06.01 PEKERJAAN KUSEN, PINTU, JENDELA, DAN JALUSI
2.01.01.06.01.001 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas I (Jati) m3 27,773,310
2.01.01.06.01.002 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas II (Kamper) m3 13,118,630
2.01.01.06.01.003 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas III (Kruing) m3 12,444,230
2.01.01.06.01.004 Pembuatan dan Pemasangan Pintu Klamp Kayu Kelas I (Jati) m2 1,067,084
2.01.01.06.01.005 Pembuatan dan Pemasangan Pintu Klamp Kayu Kelas II (Kamper) m2 527,576
2.01.01.06.01.006 Pembuatan dan Pemasangan Pintu Klamp Kayu Kelas III (Kruing) m2 460,136
2.01.01.06.01.007 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Kelas I (Jati) m2 1,470,174

70
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.01.01.06.01.008 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Kelas II (Kamper) m2 930,666
2.01.01.06.01.009 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Kelas III (Kruing) m2 863,226
2.01.01.06.01.010 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas I (Jati) m2 1,003,104
2.01.01.06.01.011 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas II (Kamper) m2 679,400
2.01.01.06.01.012 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas III (Kruing) m2 638,936
2.01.01.06.01.013 Pembuatan dan Pemasangan Pintu/Jendela Jalusi Kayu Kelas I (Jati) m2 1,982,708
2.01.01.06.01.014 Pembuatan dan Pemasangan Pintu/Jendela Jalusi Kayu Kelas II (Kamper) m2 1,119,496
2.01.01.06.01.015 Pembuatan dan Pemasangan Pintu/Jendela Jalusi Kayu Kelas III (Kruing) m2 1,011,592
2.01.01.06.01.016 Pembuatan dan Pemasangan Pintu Plywood Rangkap, Rangka Kayu Kelas I (Jati) m2 1,092,546
2.01.01.06.01.017 Pembuatan dan Pemasangan Pintu Plywood Rangkap, Rangka Kayu Kelas II (Kamper) m2 755,354
2.01.01.06.01.018 Pembuatan dan Pemasangan Pintu Plywood Rangkap, Rangka Kayu Kelas III (Kruing) m2 713,204
2.01.01.06.01.019 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas I (Jati) m2 1,031,966
2.01.01.06.01.020 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas II (Kamper) m2 694,774
2.01.01.06.01.021 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas III (Kruing) m2 652,624
2.01.01.06.01.022 Pembuatan dan Pemasangan Pintu Triplek Rangkap, Rangka Kayu Kelas I (Jati) m2 1,048,866
2.01.01.06.01.023 Pembuatan dan Pemasangan Pintu Triplek Rangkap, Rangka Kayu Kelas II (Kamper) m2 711,674
2.01.01.06.01.025 Pembuatan dan Pemasangan Pintu Triplek Rangkap, Rangka Kayu Kelas III (Kruing) m2 669,524
2.01.01.06.01.026 Pekerjaan Pemasangan Pintu PVC (Polyvinyl Chloride) unit 473,100
2.01.01.06.01.027 Pekerjaan Pemasangan Pintu HPL (High Pressure Laminated) unit 545,500
2.01.01.06.02 PEKERJAAN KUDA-KUDA DAN RANGKA ATAP
2.01.01.06.02.001 Pekerjaan Pemasangan Kuda-kuda Kayu Kelas I (Jati) m3 26,335,680
2.01.01.06.02.002 Pekerjaan Pemasangan Kuda-kuda Kayu Kelas II (Kamper) m3 11,499,210
2.01.01.06.02.003 Pekerjaan Pemasangan Kuda-kuda Kayu Kelas III (Kruing & Meranti) m3 10,881,010
2.01.01.06.02.005 Pekerjaan Pemasangan Gording Kayu Kelas I (Jati) m3 25,311,260
2.01.01.06.02.006 Pekerjaan Pemasangan Gording Kayu Kelas II (Kamper) m3 10,474,790
2.01.01.06.02.007 Pekerjaan Pemasangan Gording Kayu Kelas III (Kruing & Meranti) m3 9,856,590
2.01.01.06.02.009 Pekerjaan Pemasangan Rangka Atap Kayu Kelas III - Genteng Kodok m2 116,957
2.01.01.06.02.010 Pekerjaan Pemasangan Rangka Atap Kayu Kelas III - Genteng Keramik m2 369,745
2.01.01.06.02.011 Pekerjaan Pemasangan Rangka Atap Kayu Kelas III - Genteng Beton m2 511,367
2.01.01.06.03 PEKERJAAN RANGKA LANGIT-LANGIT DAN LISTPLANK
2.01.01.06.03.004 Pekerjaan Pemasangan Rangka Langit-langit Kayu Kelas II (Kamper) 100x100 m2 167,685
2.01.01.06.03.005 Pekerjaan Pemasangan Rangka Langit-langit Kayu Kelas II (Kamper) 50x100 m2 204,706
2.01.01.06.03.006 Pekerjaan Pemasangan Rangka Langit-langit Kayu Kelas II (Kamper) 60x60 m2 204,797
2.01.01.06.03.014 Pekerjaan Pemasangan Listplank Kayu Kelas II (Kamper) 3/20 m2 130,993
2.01.01.06.03.016 Pekerjaan Pemasangan Listplank Kayu Kelas II (Kamper) 3/30 m2 131,557
2.01.01.06.04 PEKERJAAN DINDING PARTISI
2.01.01.06.04.011 Pekerjaan Partisi Double Gypsum Rangka Kayu Kelas II (Kamper) m2 329,071
2.01.01.06.04.012 Pekerjaan Partisi Double Plywood Rangka Kayu Kelas II (Kamper) m2 423,104
2.01.01.06.04.013 Pekerjaan Partisi Multiplek Finishing HPL Rangka Kayu Kelas II (Kamper) m2 777,820
2.01.01.06.04.014 Pekerjaan Partisi Double Gypsum Rangka Metal Stud m2 263,377
2.01.01.06.04.015 Pekerjaan Partisi Double Plywood Rangka Metal Stud m2 303,673
2.01.01.06.04.016 Pekerjaan Partisi Multiplek Finishing HPL Rangka Metal Stud m2 658,389
2.01.01.06.04.017 Pekerjaan Partisi Kalsiboard Rangka Hollow m2 204,245
2.01.01.07 PEKERJAAN FINISHING

71
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.01.01.07.01 PEKERJAAN FINISHING PENUTUP ATAP DAN LANGIT LANGIT
2.01.01.07.01.001 Pekerjaan Pemasangan Penutup Atap Genteng Tanah Liat (Karang Pilang) m2 73,050
2.01.01.07.01.003 Pekerjaan Pemasangan Penutup Atap Genteng Tanah Liat (Plentong, Kodok) Glazur m2 89,050
2.01.01.07.01.005 Pekerjaan Pemasangan Penutup Atap Genteng Keramik Glazur m2 541,770
2.01.01.07.01.009 Pekerjaan Pemasangan Penutup Atap Seng Gelombang m2 86,848
2.01.01.07.01.010 Pekerjaan Pemasangan Penutup Atap Roof Light Fiberglass m2 198,369
2.01.01.07.01.044 Pekerjaan Pemasangan Penutup Atap Galvalum m2 144,148
2.01.01.07.01.011 Pekerjaan Pemasangan Penutup Atap Asbes Gelombang Tebal 5 mm m2 82,788
2.01.01.07.01.016 Pekerjaan Pemasangan Penutup Atap Asbes Gelombang Tebal 4 mm m2 75,694
2.01.01.07.01.020 Pekerjaan Pemasangan Bubungan Genteng Tanah Liat (Karang Pilang) m' 121,554
2.01.01.07.01.021 Pekerjaan Pemasangan Bubungan Genteng Tanah Liat (Plentong, Kodok) Glazur m' 72,204
2.01.01.07.01.022 Pekerjaan Pemasangan Bubungan Genteng Keramik Glazur m' 177,604
2.01.01.07.01.023 Pekerjaan Pemasangan Nok Genteng Beton m' 161,914
2.01.01.07.01.045 Pekerjaan Pemasangan Nok Galvalum m' 64,120
2.01.01.07.01.026 Pekerjaan Pemasangan Nok Seng m' 44,620
2.01.01.07.01.031 Pekerjaan Pemasangan Bubungan Steel Gelombang Kecil m' 172,465
2.01.01.07.01.046 Pekerjaan Pemasangan Insulation Alumunium Foil m2 32,935
2.01.01.07.01.032 Pekerjaan Waterproofing Membrane (Liquid) m2 89,015
2.01.01.07.01.033 Pekerjaan Waterproofing Coating m2 130,955
2.01.01.07.01.034 Pekerjaan Pemasangan Langit-langit Asbes Tebal 4 mm, 5 mm, 6 mm m2 126,652
2.01.01.07.01.038 Pekerjaan Pemasangan Langit-langit Tripleks Tebal 3 mm, 4 mm, 6 mm m2 63,919
2.01.01.07.01.041 Pekerjaan Pemasangan Langit-langit Gypsum Board Tebal 9 mm m2 50,462
2.01.01.07.01.042 Pekerjaan Pemasangan Lis Langit-langit Kayu m' 145,142
2.01.01.07.01.043 Pekerjaan Pemasangan Lis Langit-langit Gypsum m' 183,595
2.01.01.07.02 PEKERJAAN SANITAIR
2.01.01.07.02.001 Pekerjaan Pemasangan Kloset Duduk unit 2,017,800
2.01.01.07.02.002 Pekerjaan Pemasangan Kloset Jongkok Porselain unit 601,998
2.01.01.07.02.004 Pekerjaan Pemasangan Urinoir unit 3,555,808
2.01.01.07.02.005 Pekerjaan Pemasangan Wastafel unit 956,150
2.01.01.07.02.006 Pekerjaan Pemasangan Bak Mandi Fiberglass unit 1,949,300
2.01.01.07.02.009 Pekerjaan Pemasangan Bak Cuci Piring Stainless Steel + Accesories unit 333,358
2.01.01.07.02.010 Pekerjaan Pemasangan Floor Drain unit 28,100
2.01.01.07.02.011 Pekerjaan Pemasangan Bak Kontrol Pasangan Batu Bata Merah unit 474,305
2.01.01.07.02.014 Pekerjaan Pemasangan Pipa Galvanis Diameter 1/2 inch m' 84,731
2.01.01.07.02.015 Pekerjaan Pemasangan Pipa Galvanis Diameter 3/4 inch m' 100,593
2.01.01.07.02.016 Pekerjaan Pemasangan Pipa Galvanis Diameter 1 inch m' 138,335
2.01.01.07.02.017 Pekerjaan Pemasangan Pipa Galvanis Diameter 1 1/2 inch m' 210,269
2.01.01.07.02.018 Pekerjaan Pemasangan Pipa Galvanis Diameter 3 inch m' 426,115
2.01.01.07.02.019 Pekerjaan Pemasangan Pipa Galvanis Diameter 4 inch m' 591,629
2.01.01.07.02.020 Pekerjaan Pemasangan Kran Air unit 85,298
2.01.01.07.02.021 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1/2 inch m' 26,959
2.01.01.07.02.022 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 3/4 inch m' 29,826
2.01.01.07.02.023 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1 inch m' 33,973
2.01.01.07.02.024 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1 1/2 inch m' 57,856

72
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.01.01.07.02.025 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 2 inch m' 75,798
2.01.01.07.02.026 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 2 1/2 inch m' 101,778
2.01.01.07.02.027 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 3 inch m' 131,848
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch m' 177,921
2.01.01.07.02.029 Pekerjaan Pemasangan Pipa PVC Type D Diameter 2 inch m' 47,123
2.01.01.07.02.030 Pekerjaan Pemasangan Pipa PVC Type D Diameter 3 inch m' 87,595
2.01.01.07.02.031 Pekerjaan Pemasangan Pipa PVC Type D Diameter 4 inch m' 110,496
2.01.01.07.02.020 Pekerjaan Pemasangan Shower Set unit 275,995
2.01.01.07.02.037 Pekerjaan Pemasangan Tee Pipa PVC Type D Diameter 4 inch unit 156,640
2.01.01.07.02.038 Pekerjaan Pemasangan Elbow Pipa PVC Type D Diameter 4 inch unit 116,490
2.01.01.07.02.039 Pekerjaan Pemasangan Socket Pipa PVC Type D Diameter 4 inch unit 101,310
2.01.01.07.02.040 Pekerjaan Pemasangan Valve Pipa PVC Type D Diameter 4 inch unit 226,349
2.01.01.07.02.041 Pekerjaan Pemasangan Blank Flanged Diameter 4 inch unit 203,773
2.01.01.07.03 PEKERJAAN BESI DAN ALUMUNIUM
2.01.01.07.03.001 Pekerjaan Pemasangan Besi Profil kg 37,085
2.01.01.07.03.004 Pekerjaan Perakitan Besi Profil 100 kg 53,640
2.01.01.07.03.005 Pekerjaan Pengelasan dengan Las Listrik cm 2,766
2.01.01.07.03.006 Pekerjaan Pemasangan Rangka Hollow Dinding Partisi m2 132,880
2.01.01.07.03.007 Pekerjaan Pembuatan Kusen Alumunium 4 inch m' 204,380
2.01.01.07.03.008 Pekerjaan Pembuatan Kusen Alumunium 3 inch m' 108,780
2.01.01.07.03.009 Pekerjaan Pemasangan Rangka Atap Galvalum Genteng Asbes/Spandek m2 222,020
2.01.01.07.03.010 Pekerjaan Pemasangan Rangka Atap Galvalum Genteng Biasa/Metal m2 263,900
2.01.01.07.03.011 Pekerjaan Pemasangan Rangka Hollow Plafon m2 163,750
2.01.01.07.03.012 Pekerjaan Pemasangan Pintu Kaca Rangka Alumunium m2 973,879
2.01.01.07.03.013 Pekerjaan Pemasangan Pintu Alumunium Strip m2 1,401,728
2.01.01.07.03.014 Pekerjaan Pemasangan Rolling Door Besi/Galvalum m2 712,600
2.01.01.07.03.015 Pekerjaan Pemasangan Rolling Door Alumunium m2 808,900
2.01.01.07.03.016 Pekerjaan Pemasangan Folding Door Besi/Galvalum m2 561,000
2.01.01.07.03.034 Pekerjaan Pemasangan Folding Door Alumunium m2 506,000
2.01.01.07.03.035 Pekerjaan Pemasangan Folding Door PVC m2 2,156,000
2.01.01.07.03.017 Pekerjaan Pemasangan Jendela Nako dan Teralis m2 2,203,498
2.01.01.07.03.018 Pekerjaan Pemasangan Terali Besi Strip m2 637,463
2.01.01.07.03.019 Pekerjaan Pemasangan Talang Datar/Jurai Seng m' 184,115
2.01.01.07.03.020 Pekerjaan Pemasangan Talang Miring Seng m' 184,115
2.01.01.07.03.021 Pekerjaan Pemasangan Talang 1/2 Lingkarang m' 90,020
2.01.01.07.03.023 Pekerjaan Pemasangan Sunscreen m2 472,810
2.01.01.07.03.024 Pekerjaan Pemasangan Vertical/Venetion Blind m2 255,005
2.01.01.07.03.025 Pekerjaan Pemasangan Kawat Nyamuk m2 276,198
2.01.01.07.03.026 Pekerjaan Pemasangan Pagar Besi BRC m2 400,190
2.01.01.07.03.027 Pekerjaan Pemasangan Tiang Pagar Besi BRC titik 422,000
2.01.01.07.03.028 Pekerjaan Pemasangan Daun Pintu Besi BRC Swing Ganda m2 388,388
2.01.01.07.03.029 Pekerjaan Pemasangan Railling Tangga Besi Hollow m' 261,889
2.01.01.07.03.030 Pekerjaan Pemasangan Kanopi Rangka Besi Hollow Penutup Atap Polycarbonate m2 900,590
2.01.01.07.03.031 Pekerjaan Pembuatan dan Pemasangan Pagar Besi Hollow m2 479,988

73
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.01.01.07.03.032 Pekerjaan Pembuatan dan Pemasangan Pagar Besi Tempa m2 676,430
2.01.01.07.04 PEKERJAAN KUNCI DAN KACA
2.01.01.07.04.002 Pekerjaan Pemasangan Kunci Tanam Biasa unit 157,600
2.01.01.07.04.004 Pekerjaan Pemasangan Kunci Silinder unit 151,000
2.01.01.07.04.005 Pekerjaan Pemasangan Engsel Panel unit 77,350
2.01.01.07.04.006 Pekerjaan Pemasangan Engsel Kupu-kupu unit 35,400
2.01.01.07.04.011 Pekerjaan Pemasangan Door Closer unit 262,200
2.01.01.07.04.012 Pekerjaan Pemasangan Grendel unit 49,200
2.01.01.07.04.013 Pekerjaan Pemasangan Door Holder unit 129,700
2.01.01.07.04.014 Pekerjaan Pemasangan Door Stopper unit 40,500
2.01.01.07.04.015 Pekerjaan Pemasangan Sliding Door Rail unit 325,600
2.01.01.07.04.016 Pekerjaan Pemasangan Kaca Tebal 3 mm m2 110,926
2.01.01.07.04.017 Pekerjaan Pemasangan Kaca Tebal 5 mm m2 165,156
2.01.01.07.04.018 Pekerjaan Pemasangan Kaca Tebal 8 mm m2 215,594
2.01.01.07.05 PEKERJAAN PENGECATAN
2.01.01.07.05.001 Pekerjaan Mengerok Cat Lama Permukaan Kayu m2 16,895
2.01.01.07.05.002 Pekerjaan Mendempul dan Menggosok Kayu m2 36,525
2.01.01.07.05.003 Pekerjaan Pengecatan Bidang Kayu Lama m2 45,646
2.01.01.07.05.004 Pekerjaan Pengecatan Bidang Kayu Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Penutup) m2 59,123
2.01.01.07.05.005 Pekerjaan Pengecatan Bidang Kayu Baru (1 Lps. Plamir, 1 Lps. Dasar, 3 Lps. Penutup) m2 80,735
2.01.01.07.05.006 Pekerjaan Pelaburan Bidang Kayu dengan Politur m2 55,906
2.01.01.07.05.007 Pekerjaan Pelaburan Bidang Kayu dengan Cat Residu/Teer m2 39,398
2.01.01.07.05.008 Pekerjaan Pelaburan Bidang Kayu dengan Vernis m2 55,906
2.01.01.07.05.009 Pekerjaan Mengerok Cat Lama Permukaan Tembok m2 16,895
2.01.01.07.05.010 Pekerjaan Pencucian Bidang Permukaan Tembok yang Pernah Dicat m2 16,775
2.01.01.07.05.011 Pekerjaan Mengapur Dinding Tembok Baru m2 29,825
2.01.01.07.05.012 Pekerjaan Mengapur Dinding Tembok Lama m2 19,995
2.01.01.07.05.013 Pekerjaan Pengecatan Bidang Tembok Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Interior) m2 49,338
2.01.01.07.05.014 Pekerjaan Pengecatan Bidang Tembok Lama (1 Lps. Dasar, 2 Lps. Interior) m2 33,705
2.01.01.07.05.015 Pekerjaan Pengecatan Tembok Exterior m2 35,776
2.01.01.07.05.023 Pekerjaan Pengecatan Plafon m2 38,693
2.01.01.07.05.024 Pekerjaan Pengecatan Outdoor Antislip m2 53,403
2.01.01.07.06 PEKERJAAN INSTALASI LISTRIK
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak titik 184,890
2.01.01.07.06.002 Pekerjaan Pemasangan Titik Lampu titik 226,950
2.01.01.07.06.004 Pekerjaan Pemasangan Saklar Tunggal titik 55,600
2.01.01.07.06.005 Pekerjaan Pemasangan Saklar Ganda titik 57,800
2.01.01.07.06.006 Pekerjaan Pemasangan Lampu TL 18 watt unit 116,050
2.01.01.07.06.007 Pekerjaan Pemasangan Lampu TL 36 watt unit 150,850
2.01.01.07.06.008 Pekerjaan Pemasangan Lampu SL 18 watt unit 48,550
2.01.01.07.06.009 Pekerjaan Pemasangan Lampu SL 36 watt unit 96,450
2.01.01.07.06.010 Pekerjaan Pemasangan Lampu LED 18 watt unit 96,700
2.01.01.07.06.011 Pekerjaan Pemasangan Lampu LED 36 watt unit 157,750
2.01.01.07.06.012 Pekerjaan Pemasangan Lampu Downlight unit 108,250

74
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.01.01.07.06.013 Pekerjaan Pemasangan Panel Box titik 793,100
2.01.01.07.06.014 Pekerjaan Pemasangan Panel Phase 2200 VA unit 2,884,490
2.01.02.01 PAVING DAN PERKERASAN JALAN
2.01.02.01.02 PEKERJAAN PENGADAAN AGREGAT
2.01.02.01.02.001 Pembuatan Agregat Kelas A m3 287,272
2.01.02.01.02.002 Pembuatan Agregat Kelas B m3 295,547
2.01.02.01.02.003 Pembuatan Agregat Kelas S m3 319,397
2.01.02.01.02.004 Pembuatan Lapis Pondasi Agregat (CBR 60%) m3 297,989
2.01.02.01.02.005 Pembuatan Lapis Permukaan Agregat (CBR 60%) m3 232,938
2.01.02.01.03 PEKERJAAN DRAINASE
2.01.02.01.03.001 Pekerjaan Galian untuk Selokan Drainase dan Saluran Air m3 36,850
2.01.02.01.03.002 Pekerjaan Pasangan Batu dengan Mortar m3 499,170
2.01.02.01.03.003 Bahan Porous untuk Filter m3 348,996
2.01.02.01.03.004 Pekerjaan Pemasangan Lubang Drainase unit 25,705
2.01.02.01.01 PEKERJAAN PAVING
2.01.02.01.01.001 Pekerjaan Pemasangan Tegel Trotoar m2 116,185
2.01.02.01.01.002 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Segi Enam) m2 243,845
2.01.02.01.01.003 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Segi Enam - Warna) m2 258,830
2.01.02.01.01.004 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Persegi Panjang) m2 243,845
2.01.02.01.01.005 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Persegi Panjang - Warna) m2 258,830
2.01.02.01.01.006 Pekerjaan Pemasangan Paving Stone tebal 6 cm (Persegi Panjang) m2 228,860
2.01.02.01.01.007 Pekerjaan Pemasangan Paving Stone tebal 6 cm (Persegi Panjang - Warna) m2 234,855
2.01.02.01.01.013 Pekerjaan Pemasangan Kanstin m' 211,971
2.01.02.01.01.014 Pekerjaan Pemasangan Stopper/Uskup m' 164,756
2.01.02.01.01.015 Pekerjaan Tegel Batu Ampyang m2 208,060
2.01.02.01.04 PEKERJAAN TANAH
2.01.02.01.04.001 Pekerjaan Galian Biasa + Pembuangan Sisa Galian m3 38,802
2.01.02.01.04.003 Pekerjaan Galian Batu + Pembuangan Sisa Galian m3 94,670
2.01.02.01.04.004 Pekerjaan Galian Struktur dengan Kedalaman 0-2 m m3 7,896
2.01.02.01.04.005 Pekerjaan Galian Struktur dengan Kedalaman 2-4 m m3 23,626
2.01.02.01.04.006 Pekerjaan Galian Struktur dengan Kedalaman 4-6 m m3 24,194
2.01.02.01.04.007 Pekerjaan Galian Perkerasan Beraspal dengan Cold Milling Machine m3 78,087
2.01.02.01.04.008 Pekerjaan Galian Perkerasan Beraspal Tanpa Cold Milling Machine m3 902,128
2.01.02.01.04.010 Pekerjaan Pemotongan Pohon Pilihan Diameter 15-30 cm unit 184,289
2.01.02.01.04.011 Pekerjaan Pemotongan Pohon Pilihan Diameter 30-50 cm unit 193,984
2.01.02.01.04.012 Pekerjaan Pemotongan Pohon Pilihan Diameter 50-75 cm unit 213,373
2.01.02.01.04.013 Pekerjaan Pemotongan Pohon Pilihan Diameter >75 cm unit 297,628
2.01.02.01.04.014 Pekerjaan Galian Perkerasan Berbutir (Tanpa Lapis Penutup Aspal) m3 133,959
2.01.02.01.04.015 Pekerjaan Pemasangan Geotextile m2 42,107
2.01.02.01.04.016 Pekerjaan Galian Perkerasan Beton m3 171,491
2.01.02.01.05 PEKERJAAN PELABURAN PERKERASAN DAN BAHU JALAN
2.01.02.01.05.001 Pekerjaan Lapis Pondasi Agregat Kelas A m3 352,185
2.01.02.01.05.002 Pekerjaan Lapis Pondasi Agregat Kelas B m3 351,646
2.01.02.01.05.004 Pekerjaan Lapis Pondasi Semen Tanah m3 666,833

75
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.01.02.01.05.005 Bahan Agregat Penutup Burtu m2 6,407
2.01.02.01.05.006 Bahan Aspal untuk Pekerjaan Pelaburan liter 9,430
2.01.02.01.05.007 Pekerjaan Lapis Resap Pengikat liter 13,620
2.01.02.01.05.008 Pekerjaan Lapis Pondasi Agregat Kelas S m3 336,327
2.01.02.01.05.009 Pekerjaan Lapis Perkerasan 5-10 cm (Padat Digilas) m2 62,498
2.01.02.01.06 PEKERJAAN PELABURAN PERKERASAN NON ASPAL
2.01.02.01.06.001 Pekerjaan Lapis Pondasi Agregat Kelas A m3 351,209
2.01.02.01.06.002 Pekerjaan Lapis Pondasi Agregat Kelas B m3 367,687
2.01.02.01.06.007 Pekerjaan Lapis Pondasi Atas Bersemen (Cement Treated Based-CTB) m3 536,836
2.01.02.01.06.008 Pekerjaan Lapis Pondasi Bawah (Cement Treated Sub-Based-CTSB) m3 564,684
2.01.02.01.06.009 Pekerjaan Lapis Pondasi Agregat Tanpa Penutup Aspal m3 344,425
2.01.02.01.07 PEKERJAAN PELABURAN PERKERASAN ASPAL
2.01.02.01.07.001 Lapis Resap Pengikat - Aspal Cair liter 12,074
2.01.02.01.07.002 Lapis Perekat - Aspal Cair liter 10,715
2.01.02.01.07.003 Bahan Agregat Penutup Burtu m2 12,899
2.01.02.01.07.004 Bahan Agregat Penutup Burda m2 25,028
2.01.02.01.07.007 Bahan Lataston Lapis Aus (HRS-WC) ton 955,879
2.01.02.01.07.008 Bahan Lataston Lapis Aus Perata (HRS-WC L) ton 955,879
2.01.02.01.07.009 Bahan Lataston Lapis Pondasi (HRS-BASE) ton 831,493
2.01.02.01.07.010 Bahan Lataston Lapis Pondasi Perata (HRS-BASE L) ton 831,493
2.01.02.01.07.011 Bahan Laston Lapis Aus (AC-WC) ton 853,037
2.01.02.01.07.012 Bahan Laston Lapis Aus Perata (AC-WC L) ton 853,037
2.01.02.01.07.013 Bahan Laston Lapis Antara (AC-BC) ton 807,252
2.01.02.01.07.014 Bahan Laston Lapis Antara Perata (AC-BC L) ton 807,252
2.01.02.01.07.015 Bahan Laston Lapis Pondasi (AC-BASE) ton 741,856
2.01.02.01.07.016 Bahan Laston Lapis Pondasi Perata (AC-BASE L) ton 741,856
2.01.02.01.07.017 Pekerjaan Campuran Aspal Dingin untuk Pelapisan m3 2,131,393
2.01.02.01.07.018 Pekerjaan Lapis Permukaan Penetrasi Macadam m3 1,373,348
2.01.02.01.07.019 Pekerjaan Lapis Pondasi/Perata Penetrasi Macadam m3 1,455,135
2.01.02.01.07.020 Lapis Resep Pengikat - Aspal Emulsi liter 11,762
2.01.02.01.07.021 Lapis Perekat - Aspal Emulsi liter 11,757
2.01.02.01.07.022 Aspal untuk Pekerjaan Pelaburan liter 9,416
2.01.02.01.07.023 Lapis Perekat - Aspal Cair (Manual) liter 10,640
2.01.02.01.07.024 Bahan Laston Lapis Aus (AC-WC) (Manual) ton 701,769
2.01.02.01.07.025 Bahan Laston Lapis Antara (AC-BC) (Manual) ton 659,221
2.01.02.01.08 PEKERJAAN STRUKTUR
2.01.02.01.08.001 Beton Mutu Tinggi Fc'=45 Mpa m3 3,633,883
2.01.02.01.08.002 Beton Mutu Tinggi Fc'=35 Mpa m3 3,541,313
2.01.02.01.08.003 Beton Mutu Sedang Fc'=30 Mpa m3 3,488,191
2.01.02.01.08.004 Beton Mutu Sedang Fc'=25 Mpa m3 2,205,577
2.01.02.01.08.005 Beton Mutu Sedang Fc'=20 Mpa m3 2,163,035
2.01.02.01.08.006 Beton Mutu Rendah Fc'=15 Mpa m3 1,484,513
2.01.02.01.08.007 Beton Siklop Fc'=15 Mpa m3 921,948
2.01.02.01.08.008 Beton Mutu Rendah Fc'=10 Mpa m3 1,152,781

76
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.01.02.01.09 PEKERJAAN BAHAN AGREGAT UNTUK PEKERJAAN MINOR
2.01.02.01.09.001 Pekerjaan Lapis Pondasi Agregat Kelas A untuk Pekerjaan Minor m3 390,487
2.01.02.01.09.002 Pekerjaan Lapis Pondasi Agregat Kelas B untuk Pekerjaan Minor m3 389,600
2.01.02.01.09.003 Agregat Lapis Pondasi Jalan Tanpa Penutup Aspal untuk Pekerjaan Minor m3 341,470
2.01.02.01.09.004 Pekerjaan Waterbound Macadam untuk Pekerjaan Minor m3 307,148
2.01.02.01.09.005 Pekerjaan Lapis Pondasi Agregat Kelas S untuk Pekerjaan Minor m3 370,131
2.01.02.01.09.006 Pekerjaan Campuran Aspal Panas untuk Pekerjaan Minor m3 2,106,787
2.01.02.01.09.007 Pekerjaan Penetrasi Macadam untuk Pekerjaan Minor m3 1,320,927
2.01.02.01.09.008 Pekerjaan Campuran Aspal Dingin untuk Pekerjaan Minor m3 1,960,110
2.01.02.01.09.009 Bahan Residu Bitumen untuk Pekerjaan Minor liter 10,876
2.01.02.01.09.010 Pekerjaan Pemasangan Patok Pengarah unit 402,484
2.01.02.01.09.011 Pekerjaan Pemasangan Patok Kilometer unit 402,484
2.01.02.01.09.012 Pekerjaan Pemasangan Patok Hektometer unit 181,316
2.01.02.01.09.013 Pekerjaan Pemasangan Paku Jalan (Solar Road Stud) unit 296,040
2.01.02.02 PEKERJAAN PENGAIRAN
2.01.02.02.02 PEKERJAAN PENGERUKAN DAN GALIAN
2.01.02.02.02.002 Pekerjaan Pengerukan Saluran (Alat Berat) m3 2,641
2.01.02.02.02.003 Pekerjaan Galian Tanah Berbatu (Semi-Mechanic) m3 80,450
2.01.02.02.02.004 Pekerjaan Galian Batu (Semi-Mechanic) m3 172,900
2.01.02.02.02.005 Pekerjaan Galian Tanah Cadas (Semi-Mechanic) m3 64,850
2.01.02.02.02.006 Pekerjaan Galian Lumpur (Semi-Mechanic) m3 55,007
2.01.02.02.02.007 Pekerjaan Sumur Bor Chasing 2.5 " m' 167,475
2.01.02.02.02.008 Pekerjaan Sumur Bor Chasing 3" m' 190,755
2.01.02.02.04 PEKERJAAN CERUCUK DAN TURAP
2.01.02.02.04.006 Pekerjaan Pemasangan Turap Bambu Tinggi 1,5 m m' 167,125
2.01.02.02.04.007 Pekerjaan Pemasangan Turap Bambu Tinggi 2,75 m m' 312,078
2.01.02.02.04.008 Pekerjaan Pemancangan Tiang Pancang 30/30 m' 313,866

2.02 HSPK FISIK NON KONSTRUKSI

2.02.03 SARANA DAN PRASARANA KOTA

2.02.03.01 PEKERJAAN PENERANGAN JALAN UMUM

2.02.03.01.01 PEKERJAAN ELEKTRIKAL DAN PENERANGAN JALAN UMUM (PJU)


2.02.03.01.01.004 Pekerjaan Pemasangan Konektor Kabel Unit 31,800
2.02.03.01.01.006 Pekerjaan Penarikan Kabel m' 5,000
2.02.03.01.01.006 Pekerjaan Penarikan Kabel Bawah Tanah (Bore Machine) m' 430,300
2.02.03.01.01.007 Pekerjaan Pemasangan Panel Meter/Panel Lampu PJU Unit 243,600
2.02.03.01.01.008 Pekerjaan Pemasangan Pipa untuk Kabel Tanam m' 100,975
2.02.03.01.01.015 Pekerjaan Instalasi Tarikan Kabel Udara m' 99,540
2.02.03.01.01.020 Roll Pipa 1,5 inch unit 120,805
2.02.03.01.01.021 Roll Pipa 2 inch unit 130,165
2.02.03.01.01.022 Roll Pipa 3 inch unit 171,000
2.02.03.01.01.023 Roll Pipa 4 inch unit 223,500
2.02.03.01.01.024 Pekerjaan Pemasangan Ornamen Tiang Panjang 1,5 m unit 612,167
2.02.03.01.01.025 Pekerjaan Pemasangan Ornamen Tiang Panjang 2 m unit 685,614
2.02.03.01.01.026 Pekerjaan Pemasangan Ornamen Tiang Panjang 3 m unit 1,244,656

77
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.02.03.01.01.027 Pekerjaan Pemasangan Ornamen Tiang Panjang 6 m unit 1,863,362
2.02.03.01.01.028 Pekerjaan Pemasangan Panel Lampu PJU 1 Phase 4400 VA unit 3,021,340
2.02.03.01.01.029 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 6600 VA unit 5,256,640
2.02.03.01.01.030 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 10600 VA unit 5,256,640
2.02.03.01.01.031 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 13200 VA unit 5,337,640
2.02.03.01.01.032 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 16500 VA unit 5,337,640
2.02.03.01.01.033 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 23000 VA unit 6,096,240
2.02.03.01.01.034 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 33000 VA unit 6,335,640
2.02.03.01.01.035 Pekerjaan Pengecatan Tiang PJU unit 321,839
2.02.03.01.01.036 Pekerjaan Pemasangan Tiang Biasa 5 m Cabang 1 unit 1,607,975
2.02.03.01.01.037 Pekerjaan Pemasangan Tiang Biasa 7 m Cabang 1 unit 2,096,975
2.02.03.01.01.038 Pekerjaan Pemasangan Tiang Biasa 5 m Cabang 2 unit 1,718,215
2.02.03.01.01.039 Pekerjaan Pemasangan Tiang Biasa 7 m Cabang 2 unit 2,239,575
2.02.03.01.01.040 Pekerjaan Pemasangan Tiang Biasa 7 m Cabang 4 unit 2,475,895
2.02.03.01.01.041 Pekerjaan Pondasi Biasa PJU unit 1,108,536
2.02.03.01.01.042 Pekerjaan Pondasi Strouss PJU unit 1,514,192
2.02.03.01.01.043 Pekerjaan Pemasangan Tiang Oktagonal 5 m Single HDG unit 2,602,175
2.02.03.01.01.044 Pekerjaan Pemasangan Tiang Oktagonal 5 m Double HDG unit 2,961,875
2.02.03.01.01.045 Pekerjaan Pemasangan Tiang Oktagonal 7 m Single HDG unit 2,776,375
2.02.03.01.01.046 Pekerjaan Pemasangan Tiang Oktagonal 7 m Double HDG unit 3,315,875
2.02.03.01.01.047 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 5 m Cabang 1 unit 2,530,326
2.02.03.01.01.048 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 5 m Cabang 2 unit 2,825,883
2.02.03.01.01.049 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Cabang 1 unit 3,120,888
2.02.03.01.01.050 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Cabang 2 unit 3,416,445
2.02.03.01.01.051 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Cabang 4 unit 4,006,673
2.02.03.01.01.052 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Dekoratif unit 3,981,112
2.02.03.01.01.053 Pemasangan Lampu HPS 150W/220V Lengkap unit 248,700
2.02.03.01.01.054 Pemasangan Lampu HPS 250W/220V Lengkap unit 269,200
2.02.03.01.01.055 Pemasangan Lampu HPS 400W/220V Lengkap unit 312,500
2.02.03.01.01.056 Pemasangan Lampu LED 150W/220V Lengkap unit 3,744,800
2.02.03.01.01.058 Pemasangan Lampu Mercury HPLN 150W/220V Lengkap unit 2,480,400
2.02.03.01.01.059 Pemasangan Lampu Mercury HPLN 250W/220V Lengkap unit 2,677,100
2.02.03.02 PEKERJAAN SARANA LALU LINTAS
2.02.03.02.01 PEKERJAAN RAMBU RAMBU LALU LINTAS
2.02.03.02.01.009 Pekerjaan Pemasangan Lampu Jalan Bulat (Tampered) Unit 311,368
2.02.03.02.01.010 Pekerjaan Pemasangan Lampu Jalan Alumunium Solar Stud Unit 578,368
2.02.03.02.01.014 Pekerjaan Cat Besi m2 128,535
2.02.03.02.01.016 Pekerjaan Pengecatan Marka Jalan (Manual) m' 96,565
2.02.03.02.01.017 Pekerjaan Marka Jalan Thermoplastic m2 502,917
2.02.03.02.01.018 Pekerjaan Marka Jalan Coldplastic m2 626,543
2.02.03.02.01.044 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 90 cm unit 1,090,586
2.02.03.02.01.045 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 75 cm unit 879,893
2.02.03.02.01.046 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 60 cm unit 663,564
2.02.03.02.01.047 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 45 cm unit 516,538

78
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
2.02.03.03 PEKERJAAN TAMAN DAN KEBERSIHAN
2.02.03.03.01 PEKERJAAN TAMAN
2.02.03.03.01.030 Penanaman Rumput Taman m2 34,300
2.02.03.03.01.031 Penanaman Semak Hias m2 18,500
2.02.03.03.01.032 Penanaman Pohon Diameter > 15 cm Batang Tunggal batang 22,250
2.02.03.03.01.036 Penanaman Pohon Diameter < 15 cm Batang Tunggal batang 14,000
2.02.03.03.01.033 Penyiapan Media Tanam m3 426,720
2.02.03.03.01.034 Pekerjaan Pasangan Batu Refleksi m2 283,300
2.02.03.03.01.035 Pekerjaan Pasangan Lantai Batu Andesit m2 338,271

79
PEMERINTAH KOTA
MOJOKERTO

an
at
gi
Ke
k
ko
Po
K
n
ua
SP
t
Sa
ga
H
ar
H

TAHUN ANGGARAN
2020
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01 HSPK FISIK - KONSTRUKSI
2.01.01 BANGUNAN GEDUNG
2.01.01.01 PEKERJAAN PERSIAPAN DAN TANAH
2.01.01.01.01 PEKERJAAN PERSIAPAN
2.01.01.01.01.002 Pekerjaan Pembuatan Pagar Sementara Seng Gelombang Tinggi 2 m m' 389,732
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.020 OH 200,000 4,000
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.004 Tukang Kayu 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.400 OH 100,000 40,000
Jumlah Harga Tenaga Kerja 77,000
Bahan
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 6.250 batang 25,300 158,125
1.1.7.01.01.01.007.00002 Seng Gelombang - BJLS 30 Uk. 80 x 240 cm, tbl. 3 - 5 mm 1.200 lembar 101,200 121,440
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 2.500 kg 1,000 2,500
1.1.7.01.01.01.004.00001 Pasir Beton 0.005 m3 230,400 1,152
1.1.7.01.01.01.005.00009 Koral Beton 0.009 m3 224,800 2,023
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.060 kg 20,200 1,212
1.1.7.01.01.01.006.00006 Cat Meni Besi 0.450 kg 58,400 26,280
Jumlah Harga Bahan 312,732
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 389,732
2.01.01.01.01.003 Pekerjaan Pembuatan Pagar Sementara Kawat Duri Tinggi 1.8 m m' 141,437
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.020 OH 200,000 4,000
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.004 Tukang Kayu 0.300 OH 150,000 45,000
1.10.28.02.01.002.001 Pekerja 0.200 OH 100,000 20,000
Jumlah Harga Tenaga Kerja 72,000
Bahan
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 1.000 batang 25,300 25,300
1.1.7.01.01.05.001.00021 Kawat Duri 0.625 roll 60,400 37,750
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 2.000 kg 1,000 2,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.005 m3 230,400 1,152
1.1.7.01.01.01.005.00009 Koral Beton 0.009 m3 224,800 2,023
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.060 kg 20,200 1,212
Jumlah Harga Bahan 69,437
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 141,437
2.01.01.01.01.004 Pekerjaan Pengukuran dan Pemasangan Bouwplank m' 145,360
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.004 Tukang Kayu 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 27,500
Bahan
1.1.7.01.01.05.002.00036 Kayu Kelas III - Balok Usuk (Meranti) Uk. 5 x 7 cm, 400 cm 0.012 m3 6,181,900 74,183
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.020 kg 20,200 404
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan Uk. 3/20 0.007 m3 6,181,900 43,273

80
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Bahan 117,860
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 145,360
2.01.01.01.01.008 Pekerjaan Pembersihan Lapangan "Ringan" dan Perataan m2 10,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.025 OH 200,000 5,000
1.10.28.02.01.002.001 Pekerja 0.050 OH 100,000 5,000
Jumlah Harga Tenaga Kerja 10,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 10,000
2.01.01.01.01.020 Pekerjaan Pembersihan Lapangan "Berat" dan Perataan m2 20,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 20,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 20,000
2.01.01.01.01.010 Pekerjaan Pembuatan Jalan Sementara m2 151,353
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 101,000
Bahan
1.1.7.01.01.01.005.00006 Batu Belah 0.150 m3 168,600 25,290
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.090 m3 258,500 23,265
1.1.7.01.01.01.004.00002 Pasir Pasang 0.010 m3 179,800 1,798
Jumlah Harga Bahan 50,353
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 151,353
2.01.01.01.01.011 Pekerjaan Pembongkaran Beton Bertulang m3 1,466,600
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.666 OH 200,000 133,200
1.10.28.02.01.002.001 Pekerja 13.334 OH 100,000 1,333,400
Jumlah Harga Tenaga Kerja 1,466,600
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,466,600
2.01.01.01.01.013 Pekerjaan Pembongkaran Pasangan Batu Kali m3 245,800
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.205 OH 200,000 41,000
1.10.28.02.01.002.001 Pekerja 2.048 OH 100,000 204,800
Jumlah Harga Tenaga Kerja 245,800

81
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 245,800
2.01.01.01.01.015 Pekerjaan Pembongkaran Tembok Batu Bata m3 733,300
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.333 OH 200,000 66,600
1.10.28.02.01.002.001 Pekerja 6.667 OH 100,000 666,700
Jumlah Harga Tenaga Kerja 733,300
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 733,300
2.01.01.01.01.016 Pekerjaan Pembongkaran Penutup Atap Tidak Dipakai Kembali m2 11,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 11,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 11,000
2.01.01.01.01.017 Pekerjaan Pembongkaran Penutup Atap dan Dipakai Kembali m2 22,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.010 OH 200,000 2,000
1.10.28.02.01.002.001 Pekerja 0.200 OH 100,000 20,000
Jumlah Harga Tenaga Kerja 22,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 22,000
2.01.01.01.01.018 Pekerjaan Pembongkaran Paving Tidak Dipakai Kembali m2 2,000
Tenaga Kerja
1.10.28.02.01.002.001 Pekerja 0.020 OH 100,000 2,000
Jumlah Harga Tenaga Kerja 2,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 2,000
2.01.01.01.01.021 Pekerjaan Pembongkaran Paving dan Dipakai Kembali m2 4,000
Tenaga Kerja
1.10.28.02.01.002.001 Pekerja 0.040 OH 100,000 4,000
Jumlah Harga Tenaga Kerja 4,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan

82
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Harga Satuan Pokok Kegiatan 4,000
2.01.01.01.02 PEKERJAAN TANAH
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa m3 80,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.025 OH 200,000 5,000
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 80,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 80,000
2.01.01.01.02.004 Pekerjaan Galian Tanah Keras m3 106,400
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.032 OH 200,000 6,400
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 106,400
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 106,400
2.01.01.01.02.005 Pekerjaan Galian Tanah Cadas m3 162,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.060 OH 200,000 12,000
1.10.28.02.01.002.001 Pekerja 1.500 OH 100,000 150,000
Jumlah Harga Tenaga Kerja 162,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 162,000
2.01.01.01.02.006 Pekerjaan Galian Tanah Lumpur m3 129,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.045 OH 200,000 9,000
1.10.28.02.01.002.001 Pekerja 1.200 OH 100,000 120,000
Jumlah Harga Tenaga Kerja 129,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 129,000
2.01.01.01.02.007 Pekerjaan Stripping Tebing Setinggi 1 m m2 10,500
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.002.001 Pekerja 0.005 OH 100,000 500
Jumlah Harga Tenaga Kerja 10,500
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 10,500

83
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.01.02.008 Pekerjaan Pembuangan Hasil Galian Sejauh 30 m m3 35,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.010 OH 200,000 2,000
1.10.28.02.01.002.001 Pekerja 0.330 OH 100,000 33,000
Jumlah Harga Tenaga Kerja 35,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 35,000
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa m3 60,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.002.001 Pekerja 0.500 OH 100,000 50,000
Jumlah Harga Tenaga Kerja 60,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 60,000
2.01.01.01.02.016 Pekerjaan Pemadatan Tanah dengan Alat m3 82,480
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.002.001 Pekerja 0.500 OH 100,000 50,000
Jumlah Harga Tenaga Kerja 60,000
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00018 Stamper 0.050 hari 449,600 22,480
Jumlah Harga Peralatan 22,480
Harga Satuan Pokok Kegiatan 82,480
2.01.01.01.02.017 Pekerjaan Pemasangan Pudel Campuran 1 Kp : 3 Pp : 7 Tl m3 361,149
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.080 OH 200,000 16,000
1.10.28.02.01.001.002 Kepala Tukang 0.040 OH 150,000 6,000
1.10.28.02.01.001.004 Tukang 0.400 OH 150,000 60,000
1.10.28.02.01.002.001 Pekerja 0.800 OH 100,000 80,000
Jumlah Harga Tenaga Kerja 162,000
Bahan
1.1.7.01.01.01.002.00014 Kapur Padam 0.135 kg 108,900 14,702
1.1.7.01.01.01.004.00002 Pasir Pasang 0.400 m3 179,800 71,920
1.1.7.01.01.01.004.00006 Tanah Liat 0.948 m3 118,700 112,528
Jumlah Harga Bahan 199,149
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 361,149
2.01.01.01.02.018 Pekerjaan Pemasangan Lapisan Ijuk Tebal 10 cm untuk Bidang Resapan m2 213,600
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 18,000
Bahan

84
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.022.00470 Ijuk 6.000 kg 32,600 195,600
Jumlah Harga Bahan 195,600
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 213,600
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug m3 254,600
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.010 OH 200,000 2,000
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 32,000
Bahan
1.1.7.01.01.01.004.00003 Pasir Urug 1.200 m3 185,500 222,600
Jumlah Harga Bahan 222,600
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 254,600
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat m3 299,760
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.025 OH 200,000 5,000
1.10.28.02.01.002.001 Pekerja 0.250 OH 100,000 25,000
Jumlah Harga Tenaga Kerja 30,000
Bahan
1.1.7.01.01.01.004.00004 Pasir Sirtu 1.200 m3 224,800 269,760
Jumlah Harga Bahan 269,760
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 299,760
2.01.01.01.02.022 Pekerjaan Pengurugan dengan Tanah Urug m3 241,880
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.010 OH 200,000 2,000
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 32,000
Bahan
1.1.7.01.01.01.004.00005 Tanah Urug 1.200 m3 174,900 209,880
Jumlah Harga Bahan 209,880
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 241,880
2.01.01.01.02.023 Pekerjaan Pengurugan dengan Tanah Taman m3 266,960
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.010 OH 200,000 2,000
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 32,000
Bahan
1.1.7.01.01.01.004.00008 Tanah Taman 1.200 m3 195,800 234,960
Jumlah Harga Bahan 234,960
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 266,960
2.01.01.02 PEKERJAAN PONDASI
2.01.01.02.01 PEKERJAAN PONDASI
2.01.01.02.01.001 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 3 Pp) m3 780,273

85
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.075 OH 150,000 11,250
1.10.28.02.01.001.006 Tukang Batu 0.750 OH 150,000 112,500
1.10.28.02.01.002.001 Pekerja 1.500 OH 100,000 150,000
Jumlah Harga Tenaga Kerja 288,750
Bahan
1.1.7.01.01.01.005.00006 Batu Belah - 15/20 cm 1.200 m3 168,600 202,320
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 202 kg 1,000 202,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.485 m3 179,800 87,203
Jumlah Harga Bahan 491,523
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 780,273
2.01.01.02.01.002 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 4 Pp) m3 747,566
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.075 OH 150,000 11,250
1.10.28.02.01.001.006 Tukang Batu 0.750 OH 150,000 112,500
1.10.28.02.01.002.001 Pekerja 1.500 OH 100,000 150,000
Jumlah Harga Tenaga Kerja 288,750
Bahan
1.1.7.01.01.01.005.00006 Batu Belah - 15/20 cm 1.200 m3 168,600 202,320
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 163 kg 1,000 163,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.520 m3 179,800 93,496
Jumlah Harga Bahan 458,816
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 747,566
2.01.01.02.01.003 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 5 Pp) m3 724,881
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.075 OH 150,000 11,250
1.10.28.02.01.001.006 Tukang Batu 0.750 OH 150,000 112,500
1.10.28.02.01.002.001 Pekerja 1.500 OH 100,000 150,000
Jumlah Harga Tenaga Kerja 288,750
Bahan
1.1.7.01.01.01.005.00006 Batu Belah - 15/20 cm 1.200 m3 168,600 202,320
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 136 kg 1,000 136,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.544 m3 179,800 97,811
Jumlah Harga Bahan 436,131
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 724,881
2.01.01.02.01.007 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1/4 Pc : 1 Kp : 4 Pp) m3 640,371
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.075 OH 150,000 11,250
1.10.28.02.01.001.006 Tukang Batu 0.750 OH 150,000 112,500
1.10.28.02.01.002.001 Pekerja 1.500 OH 100,000 150,000
Jumlah Harga Tenaga Kerja 288,750
Bahan

86
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.005.00006 Batu Belah - 15/20 cm 1.200 m3 168,600 202,320
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 41 kg 1,000 41,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.523 m3 179,800 94,035
1.1.7.01.01.01.002.00015 Kapur Pasang 0.131 m3 108,900 14,266
Jumlah Harga Bahan 351,621
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 640,371
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) m3 432,606
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.039 OH 200,000 7,800
1.10.28.02.01.001.002 Kepala Tukang 0.039 OH 150,000 5,850
1.10.28.02.01.001.006 Tukang Batu 0.390 OH 150,000 58,500
1.10.28.02.01.002.001 Pekerja 0.780 OH 100,000 78,000
Jumlah Harga Tenaga Kerja 150,150
Bahan
1.1.7.01.01.01.005.00006 Batu Belah - 15/20 cm 1.200 m3 168,600 202,320
1.1.7.01.01.01.004.00003 Pasir Urug 0.432 m3 185,500 80,136
Jumlah Harga Bahan 282,456
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 432,606
2.01.01.02.01.011 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 20 cm Sedalam 3 m titik 192,720
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.060 OH 200,000 12,000
1.10.28.02.01.002.001 Pekerja 1.200 OH 100,000 120,000
Jumlah Harga Tenaga Kerja 132,000
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00034 Sewa Alat Bantu Strouss Pile 1.200 jam 50,600 60,720
Jumlah Harga Peralatan 60,720
Harga Satuan Pokok Kegiatan 192,720
2.01.01.02.01.012 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 30 cm Sedalam 3 m titik 207,264
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.072 OH 200,000 14,400
1.10.28.02.01.002.001 Pekerja 1.200 OH 100,000 120,000
Jumlah Harga Tenaga Kerja 134,400
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00034 Sewa Alat Bantu Strouss Pile 1.440 jam 50,600 72,864
Jumlah Harga Peralatan 72,864
Harga Satuan Pokok Kegiatan 207,264
2.01.01.03 PEKERJAAN STRUKTUR UTAMA
2.01.01.03.01 PEKERJAAN BETON
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 m3 729,451
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.060 OH 200,000 12,000
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.006 Tukang Batu 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 1.200 OH 100,000 120,000

87
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Tenaga Kerja 165,000
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 230 kg 1,000 230,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.638 m3 230,400 146,962
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.571 m3 258,500 147,488
1.1.7.01.01.01.022.00468 Air 200 liter 200 40,000
Jumlah Harga Bahan 564,451
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 729,451
2.01.01.03.01.002 Pekerjaan Pembuatan Beton K-100 m3 803,529
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.083 OH 200,000 16,600
1.10.28.02.01.001.002 Kepala Tukang 0.028 OH 150,000 4,200
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.002.001 Pekerja 1.650 OH 100,000 165,000
Jumlah Harga Tenaga Kerja 227,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 247 kg 1,000 247,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.621 m3 230,400 143,012
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.555 m3 258,500 143,468
1.1.7.01.01.01.022.00468 Air 215 liter 200 43,000
Jumlah Harga Bahan 576,479
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 803,529
2.01.01.03.01.003 Pekerjaan Pembuatan Beton K-125 m3 827,493
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.083 OH 200,000 16,600
1.10.28.02.01.001.002 Kepala Tukang 0.028 OH 150,000 4,200
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.002.001 Pekerja 1.650 OH 100,000 165,000
Jumlah Harga Tenaga Kerja 227,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 276 kg 1,000 276,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.591 m3 230,400 136,166
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.562 m3 258,500 145,277
1.1.7.01.01.01.022.00468 Air 215 liter 200 43,000
Jumlah Harga Bahan 600,443
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 827,493
2.01.01.03.01.004 Pekerjaan Pembuatan Beton K-150 m3 846,661
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.083 OH 200,000 16,600
1.10.28.02.01.001.002 Kepala Tukang 0.028 OH 150,000 4,200
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.002.001 Pekerja 1.650 OH 100,000 165,000
Jumlah Harga Tenaga Kerja 227,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 299 kg 1,000 299,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.571 m3 230,400 131,558

88
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.565 m3 258,500 146,053
1.1.7.01.01.01.022.00468 Air 215 liter 200 43,000
Jumlah Harga Bahan 619,611
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 846,661
2.01.01.03.01.005 Pekerjaan Pembuatan Beton K-175 m3 869,019
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.083 OH 200,000 16,600
1.10.28.02.01.001.002 Kepala Tukang 0.028 OH 150,000 4,200
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.002.001 Pekerja 1.650 OH 100,000 165,000
Jumlah Harga Tenaga Kerja 227,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 326 kg 1,000 326,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.543 m3 230,400 125,107
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.572 m3 258,500 147,862
1.1.7.01.01.01.022.00468 Air 215 liter 200 43,000
Jumlah Harga Bahan 641,969
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 869,019
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 m3 890,439
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.083 OH 200,000 16,600
1.10.28.02.01.001.002 Kepala Tukang 0.028 OH 150,000 4,200
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.002.001 Pekerja 1.650 OH 100,000 165,000
Jumlah Harga Tenaga Kerja 227,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 352 kg 1,000 352,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.522 m3 230,400 120,269
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.573 m3 258,500 148,121
1.1.7.01.01.01.022.00468 Air 215 liter 200 43,000
Jumlah Harga Bahan 663,389
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 890,439
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 m3 906,467
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.083 OH 200,000 16,600
1.10.28.02.01.001.002 Kepala Tukang 0.028 OH 150,000 4,200
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.002.001 Pekerja 1.650 OH 100,000 165,000
Jumlah Harga Tenaga Kerja 227,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 371 kg 1,000 371,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.499 m3 230,400 114,970
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.582 m3 258,500 150,447
1.1.7.01.01.01.022.00468 Air 215 liter 200 43,000
Jumlah Harga Bahan 679,417
Peralatan

89
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 906,467
2.01.01.03.01.008 Pekerjaan Pembuatan Beton K-250 m3 917,022
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.083 OH 200,000 16,600
1.10.28.02.01.001.002 Kepala Tukang 0.028 OH 150,000 4,200
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.002.001 Pekerja 1.650 OH 100,000 165,000
Jumlah Harga Tenaga Kerja 227,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 384 kg 1,000 384,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.494 m3 230,400 113,818
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.577 m3 258,500 149,155
1.1.7.01.01.01.022.00468 Air 215 liter 200 43,000
Jumlah Harga Bahan 689,972
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 917,022
2.01.01.03.01.009 Pekerjaan Pembuatan Beton K-275 m3 936,061
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.083 OH 200,000 16,600
1.10.28.02.01.001.002 Kepala Tukang 0.028 OH 150,000 4,200
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.002.001 Pekerja 1.650 OH 100,000 165,000
Jumlah Harga Tenaga Kerja 227,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 406 kg 1,000 406,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.489 m3 230,400 112,666
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.570 m3 258,500 147,345
1.1.7.01.01.01.022.00468 Air 215 liter 200 43,000
Jumlah Harga Bahan 709,011
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 936,061
2.01.01.03.01.010 Pekerjaan Pembuatan Beton K-300 m3 941,594
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.083 OH 200,000 16,600
1.10.28.02.01.001.002 Kepala Tukang 0.028 OH 150,000 4,200
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.002.001 Pekerja 1.650 OH 100,000 165,000
Jumlah Harga Tenaga Kerja 227,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 413 kg 1,000 413,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.486 m3 230,400 111,974
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.567 m3 258,500 146,570
1.1.7.01.01.01.022.00468 Air 215 liter 200 43,000
Jumlah Harga Bahan 714,544
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 941,594
2.01.01.03.01.011 Pekerjaan Pembuatan Beton K-325 m3 1,025,613
Tenaga Kerja

90
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.001 Mandor 0.105 OH 200,000 21,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.006 Tukang Batu 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 2.100 OH 100,000 210,000
Jumlah Harga Tenaga Kerja 288,750
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 439 kg 1,000 439,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.479 m3 230,400 110,362
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.559 m3 258,500 144,502
1.1.7.01.01.01.022.00468 Air 215 liter 200 43,000
Jumlah Harga Bahan 736,863
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,025,613
2.01.01.03.01.012 Pekerjaan Pembuatan Beton K-350 m3 1,033,146
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.105 OH 200,000 21,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.006 Tukang Batu 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 2.100 OH 100,000 210,000
Jumlah Harga Tenaga Kerja 288,750
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 448 kg 1,000 448,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.476 m3 230,400 109,670
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.556 m3 258,500 143,726
1.1.7.01.01.01.022.00468 Air 215 liter 200 43,000
Jumlah Harga Bahan 744,396
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,033,146
2.01.01.03.01.013 Pekerjaan Pembesian dengan Besi Polos/Ulir kg 13,352
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0004 OH 200,000 80
1.10.28.02.01.001.002 Kepala Tukang 0.0007 OH 150,000 105
1.10.28.02.01.001.006 Tukang Batu 0.007 OH 150,000 1,050
1.10.28.02.01.002.001 Pekerja 0.007 OH 100,000 700
Jumlah Harga Tenaga Kerja 1,935
Bahan
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 1.050 kg 10,500 11,025
1.1.7.01.01.05.001.00018 Kawat Beton 0.015 kg 26,100 392
Jumlah Harga Bahan 11,417
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 13,352
2.01.01.03.01.015 Pekerjaan Pemasangan Wiremesh kg 12,131
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.00010 OH 200,000 20
1.10.28.02.01.001.002 Kepala Tukang 0.00025 OH 150,000 38
1.10.28.02.01.001.006 Tukang Batu 0.00250 OH 150,000 375
1.10.28.02.01.002.001 Pekerja 0.00250 OH 100,000 250
Jumlah Harga Tenaga Kerja 683
Bahan

91
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.008.00049 Wiremesh M-6 0.029 lembar 393,400 11,318
1.1.7.01.01.05.001.00018 Kawat Beton 0.005 kg 26,100 131
Jumlah Harga Bahan 11,448
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 12,131
2.01.01.03.01.016 Pekerjaan Pembuatan Pondasi Beton Bertulang (150 kg Besi + Bekisting) m3 4,671,766
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.265 OH 200,000 53,000
1.10.28.02.01.001.002 Kepala Tukang 0.262 OH 150,000 39,300
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.001.004 Tukang Kayu 1.300 OH 150,000 195,000
1.10.28.02.01.001.008 Tukang Besi 1.050 OH 150,000 157,500
1.10.28.02.01.002.001 Pekerja 5.300 OH 100,000 530,000
Jumlah Harga Tenaga Kerja 1,016,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 336 kg 1,000 336,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.540 m3 230,400 124,416
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.810 m3 258,500 209,385
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 1.500 kg 20,200 30,300
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 157.500 kg 10,500 1,653,750
1.1.7.01.01.05.001.00018 Kawat Beton 2.250 kg 26,100 58,725
1.1.7.01.01.04.002.00001 Minyak Bekisting 0.400 liter 16,900 6,760
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.200 m3 6,181,900 1,236,380
Jumlah Harga Bahan 3,655,716
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 4,671,766
2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) m3 5,828,054
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.283 OH 200,000 56,600
1.10.28.02.01.001.002 Kepala Tukang 0.323 OH 150,000 48,450
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.001.004 Tukang Kayu 1.560 OH 150,000 234,000
1.10.28.02.01.001.008 Tukang Besi 1.400 OH 150,000 210,000
1.10.28.02.01.002.001 Pekerja 5.650 OH 100,000 565,000
Jumlah Harga Tenaga Kerja 1,155,300
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 336 kg 1,000 336,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.540 m3 230,400 124,416
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.810 m3 258,500 209,385
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 2.000 kg 20,200 40,400
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 210 kg 10,500 2,205,000
1.1.7.01.01.05.001.00018 Kawat Beton 3.000 kg 26,100 78,300
1.1.7.01.01.04.002.00001 Minyak Bekisting 0.600 liter 16,900 10,140
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.270 m3 6,181,900 1,669,113
Jumlah Harga Bahan 4,672,754
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 5,828,054
2.01.01.03.01.018 Pekerjaan Pembuatan Kolom Beton Bertulang (300 kg Besi + Bekisting) m3 10,378,596
Tenaga Kerja

92
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.001 Mandor 0.353 OH 200,000 70,600
1.10.28.02.01.001.002 Kepala Tukang 0.403 OH 150,000 60,450
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.001.004 Tukang Kayu 1.650 OH 150,000 247,500
1.10.28.02.01.001.008 Tukang Besi 2.100 OH 150,000 315,000
1.10.28.02.01.002.001 Pekerja 7.050 OH 100,000 705,000
Jumlah Harga Tenaga Kerja 1,439,800
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 336 kg 1,000 336,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.540 m3 230,400 124,416
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.810 m3 258,500 209,385
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 4.000 kg 20,200 80,800
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 315 kg 10,500 3,307,500
1.1.7.01.01.05.001.00018 Kawat Beton 4.500 kg 26,100 117,450
1.1.7.01.01.04.002.00001 Minyak Bekisting 2.000 liter 16,900 33,800
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.400 m3 6,181,900 2,472,760
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok 0.150 m3 7,867,900 1,180,185
1.1.7.01.01.05.007.00022 Plywood - Uk. 9 mm 3.500 lembar 163,000 570,500
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 20 batang 25,300 506,000
Jumlah Harga Bahan 8,938,796
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 10,378,596
2.01.01.03.01.019 Pekerjaan Pembuatan Balok Beton Bertulang (200 kg Besi + Bekisting) m3 8,232,995
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.318 OH 200,000 63,600
1.10.28.02.01.001.002 Kepala Tukang 0.333 OH 150,000 49,950
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.001.004 Tukang Kayu 1.650 OH 150,000 247,500
1.10.28.02.01.001.008 Tukang Besi 1.400 OH 150,000 210,000
1.10.28.02.01.002.001 Pekerja 6.350 OH 100,000 635,000
Jumlah Harga Tenaga Kerja 1,247,300
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 336 kg 1,000 336,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.540 m3 230,400 124,416
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.810 m3 258,500 209,385
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 3.200 kg 20,200 64,640
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 210 kg 10,500 2,205,000
1.1.7.01.01.05.001.00018 Kawat Beton 3.000 kg 26,100 78,300
1.1.7.01.01.04.002.00001 Minyak Bekisting 1.600 liter 16,900 27,040
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.320 m3 6,181,900 1,978,208
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok 0.140 m3 7,867,900 1,101,506
1.1.7.01.01.05.007.00022 Plywood - Uk. 9 mm 2.800 lembar 163,000 456,400
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 16 batang 25,300 404,800
Jumlah Harga Bahan 6,985,695
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 8,232,995
2.01.01.03.01.020 Pekerjaan Pembuatan Plat Beton Bertulang (150 kg Besi + Bekisting) m3 7,678,812
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.265 OH 200,000 53,000
1.10.28.02.01.001.002 Kepala Tukang 0.265 OH 150,000 39,750

93
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.001.004 Tukang Kayu 1.300 OH 150,000 195,000
1.10.28.02.01.001.008 Tukang Besi 1.050 OH 150,000 157,500
1.10.28.02.01.002.001 Pekerja 5.300 OH 100,000 530,000
Jumlah Harga Tenaga Kerja 1,016,500
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 336 kg 1,000 336,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.540 m3 230,400 124,416
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.810 m3 258,500 209,385
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 3.200 kg 20,200 64,640
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 157.5 kg 10,500 1,653,750
1.1.7.01.01.05.001.00018 Kawat Beton 2.250 kg 26,100 58,725
1.1.7.01.01.04.002.00001 Minyak Bekisting 1.600 liter 16,900 27,040
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.320 m3 6,181,900 1,978,208
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok 0.120 m3 7,867,900 944,148
1.1.7.01.01.05.007.00022 Plywood - Uk. 9 mm 2.800 lembar 163,000 456,400
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 32 batang 25,300 809,600
Jumlah Harga Bahan 6,662,312
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 7,678,812
2.01.01.03.01.021 Pekerjaan Pembuatan Dinding Beton Bertulang (150 kg Besi + Bekisting) m3 7,296,126
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.265 OH 200,000 53,000
1.10.28.02.01.001.002 Kepala Tukang 0.262 OH 150,000 39,300
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.001.004 Tukang Kayu 1.300 OH 150,000 195,000
1.10.28.02.01.001.008 Tukang Besi 1.050 OH 150,000 157,500
1.10.28.02.01.002.001 Pekerja 5.300 OH 100,000 530,000
Jumlah Harga Tenaga Kerja 1,016,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 336 kg 1,000 336,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.540 m3 230,400 124,416
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.810 m3 258,500 209,385
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 3.200 kg 20,200 64,640
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 157.5 kg 10,500 1,653,750
1.1.7.01.01.05.001.00018 Kawat Beton 2.250 kg 26,100 58,725
1.1.7.01.01.04.002.00001 Minyak Bekisting 1.600 liter 16,900 27,040
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.240 m3 6,181,900 1,483,656
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok 0.160 m3 7,867,900 1,258,864
1.1.7.01.01.05.007.00022 Plywood - Uk. 9 mm 2.800 lembar 163,000 456,400
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 24 batang 25,300 607,200
Jumlah Harga Bahan 6,280,076
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 7,296,126
2.01.01.03.01.022 Pekerjaan Pembuatan Dinding Beton Bertulang (200 kg Besi + Bekisting) m3 7,322,586
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.283 OH 200,000 56,600
1.10.28.02.01.001.002 Kepala Tukang 0.323 OH 150,000 48,450
1.10.28.02.01.001.006 Tukang Batu 0.275 OH 150,000 41,250
1.10.28.02.01.001.004 Tukang Kayu 1.560 OH 150,000 234,000

94
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.008 Tukang Besi 1.400 OH 150,000 210,000
1.10.28.02.01.002.001 Pekerja 5.650 OH 100,000 565,000
Jumlah Harga Tenaga Kerja 1,155,300
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 336 kg 1,000 336,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.540 m3 230,400 124,416
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.810 m3 258,500 209,385
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 3.000 kg 20,200 60,600
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 210 kg 10,500 2,205,000
1.1.7.01.01.05.001.00018 Kawat Beton 3.000 kg 26,100 78,300
1.1.7.01.01.04.002.00001 Minyak Bekisting 1.200 liter 16,900 20,280
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.250 m3 6,181,900 1,545,475
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok 0.105 m3 7,867,900 826,130
1.1.7.01.01.05.007.00022 Plywood - Uk. 9 mm 2.500 lembar 163,000 407,500
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 14 batang 25,300 354,200
Jumlah Harga Bahan 6,167,286
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 7,322,586
2.01.01.03.01.023 Pekerjaan Pembuatan Kolom Praktis Beton Bertulang 11x11 cm m' 83,912
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.009 OH 200,000 1,800
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 900
1.10.28.02.01.001.006 Tukang Batu 0.020 OH 150,000 3,000
1.10.28.02.01.001.004 Tukang Kayu 0.020 OH 150,000 3,000
1.10.28.02.01.001.008 Tukang Besi 0.020 OH 150,000 3,000
1.10.28.02.01.002.001 Pekerja 0.180 OH 100,000 18,000
Jumlah Harga Tenaga Kerja 29,700
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 4.000 kg 1,000 4,000
1.1.7.01.01.01.004.00001 Pasir Beton 0.006 m3 230,400 1,382
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.009 m3 258,500 2,327
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.073 kg 20,200 1,465
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 3.000 kg 10,500 31,500
1.1.7.01.01.05.001.00018 Kawat Beton 0.045 kg 26,100 1,175
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.002 m3 6,181,900 12,364
Jumlah Harga Bahan 54,212
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 83,912
2.01.01.03.01.024 Pekerjaan Pembuatan Ring Balok Beton Bertulang 10x15 cm m' 121,081
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.006 Tukang Batu 0.033 OH 150,000 4,950
1.10.28.02.01.001.004 Tukang Kayu 0.033 OH 150,000 4,950
1.10.28.02.01.001.008 Tukang Besi 0.033 OH 150,000 4,950
1.10.28.02.01.002.001 Pekerja 0.297 OH 100,000 29,700
Jumlah Harga Tenaga Kerja 49,050
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 5.500 kg 1,000 5,500
1.1.7.01.01.01.004.00001 Pasir Beton 0.009 m3 230,400 2,074

95
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.015 m3 258,500 3,878
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.145 kg 20,200 2,929
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 3.600 kg 10,500 37,800
1.1.7.01.01.05.001.00018 Kawat Beton 0.050 kg 26,100 1,305
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.003 m3 6,181,900 18,546
Jumlah Harga Bahan 72,031
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 121,081
2.01.01.03.02 PEKERJAAN CETAKAN BETON (BEKISTING)
2.01.01.03.02.001 Pekerjaan Pasang Bekisting untuk Pondasi m2 355,126
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.026 OH 200,000 5,200
1.10.28.02.01.001.002 Kepala Tukang 0.026 OH 150,000 3,900
1.10.28.02.01.001.004 Tukang Kayu 0.260 OH 150,000 39,000
1.10.28.02.01.002.001 Pekerja 0.520 OH 100,000 52,000
Jumlah Harga Tenaga Kerja 100,100
Bahan
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.040 m3 6,181,900 247,276
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.300 kg 20,200 6,060
1.1.7.01.01.04.002.00001 Minyak Bekisting 0.100 liter 16,900 1,690
Jumlah Harga Bahan 255,026
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 355,126
2.01.01.03.02.002 Pekerjaan Pasang Bekisting untuk Sloof m2 386,036
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.026 OH 200,000 5,200
1.10.28.02.01.001.002 Kepala Tukang 0.026 OH 150,000 3,900
1.10.28.02.01.001.004 Tukang Kayu 0.260 OH 150,000 39,000
1.10.28.02.01.002.001 Pekerja 0.520 OH 100,000 52,000
Jumlah Harga Tenaga Kerja 100,100
Bahan
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.045 m3 6,181,900 278,186
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.300 kg 20,200 6,060
1.1.7.01.01.04.002.00001 Minyak Bekisting 0.100 liter 16,900 1,690
Jumlah Harga Bahan 285,936
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 386,036
2.01.01.03.02.003 Pekerjaan Pasang Bekisting untuk Kolom m2 711,455
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.083 OH 200,000 16,600
1.10.28.02.01.001.002 Kepala Tukang 0.028 OH 150,000 4,200
1.10.28.02.01.001.004 Tukang Kayu 0.275 OH 150,000 41,250
1.10.28.02.01.002.001 Pekerja 1.650 OH 100,000 165,000
Jumlah Harga Tenaga Kerja 227,050
Bahan
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.040 m3 6,181,900 247,276
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.400 kg 20,200 8,080
1.1.7.01.01.04.002.00001 Minyak Bekisting 0.200 Liter 16,900 3,380
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok 0.015 m3 7,867,900 118,019

96
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.05.007.00022 Plywood - Uk. 9 mm 0.350 Lbr 163,000 57,050
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 2.000 Batang 25,300 50,600
Jumlah Harga Bahan 484,405
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 711,455
2.01.01.03.02.004 Pekerjaan Pasang Bekisting untuk Balok m2 635,058
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.033 OH 200,000 6,600
1.10.28.02.01.001.002 Kepala Tukang 0.033 OH 150,000 4,950
1.10.28.02.01.001.004 Tukang Kayu 0.330 OH 150,000 49,500
1.10.28.02.01.002.001 Pekerja 0.660 OH 100,000 66,000
Jumlah Harga Tenaga Kerja 127,050
Bahan
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.040 m3 6,181,900 247,276
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.400 kg 20,200 8,080
1.1.7.01.01.04.002.00001 Minyak Bekisting 0.200 Liter 16,900 3,380
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok 0.018 m3 7,867,900 141,622
1.1.7.01.01.05.007.00022 Plywood - Uk. 9 mm 0.350 Lbr 163,000 57,050
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 2.000 Batang 25,300 50,600
Jumlah Harga Bahan 508,008
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 635,058
2.01.01.03.02.005 Pekerjaan Pasang Bekisting untuk Lantai m2 712,655
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.033 OH 200,000 6,600
1.10.28.02.01.001.002 Kepala Tukang 0.033 OH 150,000 4,950
1.10.28.02.01.001.004 Tukang Kayu 0.330 OH 150,000 49,500
1.10.28.02.01.002.001 Pekerja 0.660 OH 100,000 66,000
Jumlah Harga Tenaga Kerja 127,050
Bahan
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.040 m3 6,181,900 247,276
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.400 kg 20,200 8,080
1.1.7.01.01.04.002.00001 Minyak Bekisting 0.200 Liter 16,900 3,380
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok 0.015 m3 7,867,900 118,019
1.1.7.01.01.05.007.00022 Plywood - Uk. 9 mm 0.350 Lbr 163,000 57,050
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 6.000 Batang 25,300 151,800
Jumlah Harga Bahan 585,605
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 712,655
2.01.01.03.02.006 Pekerjaan Pasang Bekisting untuk Dinding m2 617,575
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.033 OH 200,000 6,600
1.10.28.02.01.001.002 Kepala Tukang 0.033 OH 150,000 4,950
1.10.28.02.01.001.004 Tukang Kayu 0.330 OH 150,000 49,500
1.10.28.02.01.002.001 Pekerja 0.660 OH 100,000 66,000
Jumlah Harga Tenaga Kerja 127,050
Bahan
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.030 m3 6,181,900 185,457
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.400 kg 20,200 8,080

97
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.04.002.00001 Minyak Bekisting 0.200 Liter 16,900 3,380
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok 0.020 m3 7,867,900 157,358
1.1.7.01.01.05.007.00022 Plywood - Uk. 9 mm 0.350 Lbr 163,000 57,050
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 3.000 Batang 25,300 75,900
1.1.7.01.01.01.022.00514 Penjaga Jarak Bekisting - Spacer 4.000 Buah 825 3,300
Jumlah Harga Bahan 490,525
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 617,575
2.01.01.03.02.007 Pekerjaan Pasang Bekisting untuk Tangga m2 548,791
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.033 OH 200,000 6,600
1.10.28.02.01.001.002 Kepala Tukang 0.033 OH 150,000 4,950
1.10.28.02.01.001.004 Tukang Kayu 0.330 OH 150,000 49,500
1.10.28.02.01.002.001 Pekerja 0.660 OH 100,000 66,000
Jumlah Harga Tenaga Kerja 127,050
Bahan
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.030 m3 6,181,900 185,457
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.400 kg 20,200 8,080
1.1.7.01.01.04.002.00001 Minyak Bekisting 0.150 Liter 16,900 2,535
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok 0.015 m3 7,867,900 118,019
1.1.7.01.01.05.007.00022 Plywood - Uk. 9 mm 0.350 Lbr 163,000 57,050
1.1.7.01.01.05.002.00054 Dolken Kayu - Dia. 8-10/400 cm 2.000 Batang 25,300 50,600
Jumlah Harga Bahan 421,741
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 548,791
2.01.01.04 PEKERJAAN PASANGAN DINDING DAN PLESTERAN
2.01.01.04.01 PEKERJAAN PASANGAN DINDING
2.01.01.04.01.001 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 2 Ps) m2 268,884
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.030 OH 200,000 6,000
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.006 Tukang Batu 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.600 OH 100,000 60,000
Jumlah Harga Tenaga Kerja 99,000
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 44 kg 1,000 43,500
1.1.7.01.01.01.005.00010 Bata Merah 140 buah 800 112,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.080 m3 179,800 14,384
Jumlah Harga Bahan 169,884
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 268,884
2.01.01.04.01.002 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 2 Ps) m2 131,282
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.006 Tukang Batu 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 49,500
Bahan

98
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 18.950 kg 1,000 18,950
1.1.7.01.01.01.005.00010 Bata Merah 70 buah 800 56,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.038 m3 179,800 6,832
Jumlah Harga Bahan 81,782
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 131,282
2.01.01.04.01.003 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 3 Ps) m2 260,312
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.030 OH 200,000 6,000
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.006 Tukang Batu 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.600 OH 100,000 60,000
Jumlah Harga Tenaga Kerja 99,000
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 32.950 kg 1,000 32,950
1.1.7.01.01.01.005.00010 Bata Merah 140 buah 800 112,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.091 m3 179,800 16,362
Jumlah Harga Bahan 161,312
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 260,312
2.01.01.04.01.004 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 3 Ps) m2 127,062
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.006 Tukang Batu 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 49,500
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 14.370 kg 1,000 14,370
1.1.7.01.01.01.005.00010 Bata Merah 70 buah 800 56,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.040 m3 179,800 7,192
Jumlah Harga Bahan 77,562
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 127,062
2.01.01.04.01.013 Pekerjaan Pasangan Dinding Bata Ringan Tebal 7,5 cm dengan Mortar Siap Pakai m2 385,707
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.130 OH 150,000 19,500
1.10.28.02.01.001.006 Tukang Batu 1.300 OH 150,000 195,000
1.10.28.02.01.002.001 Pekerja 1.020 OH 100,000 102,000
Jumlah Harga Tenaga Kerja 317,100
Bahan
1.1.7.01.01.01.005.00015 Bata Ringan - Tbl. 7,5 cm 0.075 m3 786,800 59,157
1.1.7.01.01.01.002.00016 Mortar 0.063 zak 150,000 9,450
Jumlah Harga Bahan 68,607
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 385,707
2.01.01.04.01.014 zak m2 413,780

99
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.130 OH 150,000 19,500
1.10.28.02.01.001.006 Tukang Batu 1.300 OH 150,000 195,000
1.10.28.02.01.002.001 Pekerja 1.050 OH 100,000 105,000
Jumlah Harga Tenaga Kerja 320,100
Bahan
1.1.7.01.01.01.005.00015 Bata Ringan - Tbl. 7,5 cm 0.100 m3 786,800 78,680
1.1.7.01.01.01.002.00016 Mortar 0.100 kg 150,000 15,000
Jumlah Harga Bahan 93,680
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 413,780
2.01.01.04.01.015 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 4 Ps) m2 254,271
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.030 OH 200,000 6,000
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.006 Tukang Batu 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.600 OH 100,000 60,000
Jumlah Harga Tenaga Kerja 99,000
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 26.550 kg 1,000 26,550
1.1.7.01.01.01.005.00010 Bata Merah 140 buah 800 112,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.093 m3 179,800 16,721
Jumlah Harga Bahan 155,271
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 254,271
2.01.01.04.01.016 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 4 Ps) m2 124,731
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.006 Tukang Batu 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 49,500
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 11.500 kg 1,000 11,500
1.1.7.01.01.01.005.00010 Bata Merah 70 buah 800 56,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.043 m3 179,800 7,731
Jumlah Harga Bahan 75,231
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 124,731
2.01.01.04.01.017 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 5 Ps) m2 251,540
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.030 OH 200,000 6,000
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.006 Tukang Batu 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.600 OH 100,000 60,000
Jumlah Harga Tenaga Kerja 99,000
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 22.200 kg 1,000 22,200

100
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.005.00010 Bata Merah 140 buah 800 112,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.102 m3 179,800 18,340
Jumlah Harga Bahan 152,540
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 251,540
2.01.01.04.01.018 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 5 Ps) m2 123,271
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.006 Tukang Batu 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 49,500
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.680 kg 1,000 9,680
1.1.7.01.01.01.005.00010 Bata Merah 70 buah 800 56,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.045 m3 179,800 8,091
Jumlah Harga Bahan 73,771
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 123,271
2.01.01.04.01.019 Pekerjaan Pemasangan Dinding Bata Expose tbl 1 Bata (1 Pc : 3 Ps) m2 1,099,504
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.015 OH 150,000 2,250
1.10.28.02.01.001.006 Tukang Batu 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 57,750
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 14.000 kg 1,000 14,000
1.1.7.01.01.01.008.00088 Hollow Brick 140 buah 7,300 1,022,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.032 m3 179,800 5,754
Jumlah Harga Bahan 1,041,754
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,099,504
2.01.01.04.02 PEKERJAAN PLESTERAN
2.01.01.04.02.001 Pekerjaan Plesteran 1 Pc : 1 Ps tbl 15 mm m2 76,131
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.015 OH 150,000 2,250
1.10.28.02.01.001.006 Tukang Batu 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 57,750
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 15.504 kg 1,000 15,504
1.1.7.01.01.01.004.00002 Pasir Pasang 0.016 m3 179,800 2,877
Jumlah Harga Bahan 18,381
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 76,131
2.01.01.04.02.002 Pekerjaan Plesteran 1 Pc : 2 Ps tbl 15 mm m2 71,570

101
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.015 OH 150,000 2,250
1.10.28.02.01.001.006 Tukang Batu 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 57,750
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 10.224 kg 1,000 10,224
1.1.7.01.01.01.004.00002 Pasir Pasang 0.020 m3 179,800 3,596
Jumlah Harga Bahan 13,820
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 71,570
2.01.01.04.02.003 Pekerjaan Plesteran 1 Pc : 3 Ps tbl 15 mm m2 69,661
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.015 OH 150,000 2,250
1.10.28.02.01.001.006 Tukang Batu 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 57,750
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 7.776 kg 1,000 7,776
1.1.7.01.01.01.004.00002 Pasir Pasang 0.023 m3 179,800 4,135
Jumlah Harga Bahan 11,911
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 69,661
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm m2 68,305
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.015 OH 150,000 2,250
1.10.28.02.01.001.006 Tukang Batu 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 57,750
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 6.240 kg 1,000 6,240
1.1.7.01.01.01.004.00002 Pasir Pasang 0.024 m3 179,800 4,315
Jumlah Harga Bahan 10,555
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 68,305
2.01.01.04.02.005 Pekerjaan Plesteran 1 Pc : 5 Ps tbl 15 mm m2 67,609
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.015 OH 150,000 2,250
1.10.28.02.01.001.006 Tukang Batu 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 57,750
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 5.184 kg 1,000 5,184
1.1.7.01.01.01.004.00002 Pasir Pasang 0.026 m3 179,800 4,675
Jumlah Harga Bahan 9,859

102
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 67,609
2.01.01.04.02.014 Pekerjaan Plesteran Skoning 1 Pc : 3 Ps lebar 10 cm m' 77,637
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.040 OH 150,000 6,000
1.10.28.02.01.001.006 Tukang Batu 0.400 OH 150,000 60,000
1.10.28.02.01.002.001 Pekerja 0.080 OH 100,000 8,000
Jumlah Harga Tenaga Kerja 74,800
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 0.500 kg 1,000 500
1.1.7.01.01.01.004.00002 Pasir Pasang 0.013 m3 179,800 2,337
Jumlah Harga Bahan 2,837
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 77,637
2.01.01.04.02.015 Pekerjaan Benangan m' 54,899
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.040 OH 200,000 8,000
1.10.28.02.01.001.006 Tukang Batu 0.040 OH 150,000 6,000
1.10.28.02.01.002.001 Pekerja 0.080 OH 100,000 8,000
Jumlah Harga Tenaga Kerja 22,000
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 0.500 kg 1,000 500
1.1.7.01.01.01.004.00002 Pasir Pasang 0.013 m3 179,800 2,337
Jumlah Harga Bahan 2,837
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 24,837
2.01.01.04.02.016 Pekerjaan Plesteran Ciprat 1 Pc : 2 Ps m2 54,899
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.006 Tukang Batu 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 49,500
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 4.320 kg 1,000 4,320
1.1.7.01.01.01.004.00002 Pasir Pasang 0.006 m3 179,800 1,079
Jumlah Harga Bahan 5,399
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 54,899
2.01.01.04.02.020 Pekerjaan Acian m2 41,750
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.010 OH 200,000 2,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.006 Tukang Batu 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.200 OH 100,000 20,000
Jumlah Harga Tenaga Kerja 38,500
Bahan

103
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 3.250 kg 1,000 3,250
Jumlah Harga Bahan 3,250
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 41,750
2.01.01.05 PEKERJAAN PENUTUP LANTAI DAN DINDING
2.01.01.05.01 PEKERJAAN PENUTUP LANTAI
2.01.01.05.01.001 Pekerjaan Pemasangan Lantai Granit Uk. 60x60 cm m2 513,621
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.012 OH 200,000 2,400
1.10.28.02.01.001.002 Kepala Tukang 0.012 OH 150,000 1,800
1.10.28.02.01.001.004 Tukang 0.120 OH 150,000 18,000
1.10.28.02.01.002.001 Pekerja 0.240 OH 100,000 24,000
Jumlah Harga Tenaga Kerja 46,200
Bahan
1.1.7.01.01.01.013.00039 Granit - Uk. 60 x 60 cm 1.050 m2 399,600 419,580
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.600 kg 1,000 9,600
1.1.7.01.01.01.004.00002 Pasir Pasang 0.045 m3 179,800 8,091
1.1.7.01.01.01.002.00007 Semen Warna - Nat 1.500 kg 20,100 30,150
Jumlah Harga Bahan 467,421
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 513,621
2.01.01.05.01.002 Pekerjaan Pemasangan Lantai Granit Uk. 40x40 cm m2 489,356
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.013 OH 200,000 2,600
1.10.28.02.01.001.002 Kepala Tukang 0.013 OH 150,000 1,950
1.10.28.02.01.001.004 Tukang 0.125 OH 150,000 18,750
1.10.28.02.01.002.001 Pekerja 0.250 OH 100,000 25,000
Jumlah Harga Tenaga Kerja 48,300
Bahan
1.1.7.01.01.01.013.00036 Granit - Uk. 40 x 40 cm 1.050 m2 374,300 393,015
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.800 kg 1,000 9,800
1.1.7.01.01.01.004.00002 Pasir Pasang 0.045 m3 179,800 8,091
1.1.7.01.01.01.002.00007 Semen Warna - Nat 1.500 kg 20,100 30,150
Jumlah Harga Bahan 441,056
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 489,356
2.01.01.05.01.013 Pekerjaan Pemasangan Lantai Granit Uk. 30x30 cm m2 334,331
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.013 OH 200,000 2,600
1.10.28.02.01.001.002 Kepala Tukang 0.013 OH 150,000 1,950
1.10.28.02.01.001.004 Tukang 0.130 OH 150,000 19,500
1.10.28.02.01.002.001 Pekerja 0.260 OH 100,000 26,000
Jumlah Harga Tenaga Kerja 50,050
Bahan
1.1.7.01.01.01.013.00034 Granit - Uk. 30 x 30 cm 1.050 m2 224,800 236,040
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 10.000 kg 1,000 10,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.045 m3 179,800 8,091
1.1.7.01.01.01.002.00007 Semen Warna - Nat 1.500 kg 20,100 30,150
Jumlah Harga Bahan 284,281

104
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 334,331
2.01.01.05.01.003 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 40x40 cm m2 254,259
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.004 Tukang 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 134,750
Bahan
1.1.7.01.01.01.013.00012 Keramik Putih - Uk. 40 x 40 cm 1.120 m2 67,400 75,488
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.800 kg 1,000 9,800
1.1.7.01.01.01.004.00002 Pasir Pasang 0.045 m3 179,800 8,091
1.1.7.01.01.01.002.00007 Semen Warna - Nat 1.300 kg 20,100 26,130
Jumlah Harga Bahan 119,509
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 254,259
2.01.01.05.01.004 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 30x30 cm m2 229,635
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.004 Tukang 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 134,750
Bahan
1.1.7.01.01.01.013.00010 Keramik Putih - Uk. 30 x 30 cm 1.080 m2 61,800 66,744
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 10.000 kg 1,000 10,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.045 m3 179,800 8,091
1.1.7.01.01.01.002.00007 Semen Warna - Nat 0.500 kg 20,100 10,050
Jumlah Harga Bahan 94,885
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 229,635
2.01.01.05.01.005 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 20x20 cm m2 219,491
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.004 Tukang 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 134,750
Bahan
1.1.7.01.01.01.013.00013 Keramik Putih - Uk. 20 x 20 cm 1.000 m2 56,200 56,200
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 10.400 kg 1,000 10,400
1.1.7.01.01.01.004.00002 Pasir Pasang 0.045 m3 179,800 8,091
1.1.7.01.01.01.002.00007 Semen Warna - Nat 0.500 kg 20,100 10,050
Jumlah Harga Bahan 84,741
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 219,491
2.01.01.05.01.006 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 40x40 cm m2 310,931

105
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.004 Tukang 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 134,750
Bahan
1.1.7.01.01.01.013.00008 Keramik Motif - Uk. 40 x 40 cm 1.120 m2 118,000 132,160
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.800 kg 1,000 9,800
1.1.7.01.01.01.004.00002 Pasir Pasang 0.045 m3 179,800 8,091
1.1.7.01.01.01.002.00007 Semen Warna - Nat 1.300 kg 20,100 26,130
Jumlah Harga Bahan 176,181
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 310,931
2.01.01.05.01.007 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 30x30 cm m2 289,143
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.004 Tukang 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 134,750
Bahan
1.1.7.01.01.01.013.00007 Keramik Motif - Uk. 30 x 30 cm 1.080 m2 116,900 126,252
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 10.000 kg 1,000 10,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.045 m3 179,800 8,091
1.1.7.01.01.01.002.00007 Semen Warna - Nat 0.500 kg 20,100 10,050
Jumlah Harga Bahan 154,393
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 289,143
2.01.01.05.01.008 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 20x20 cm m2 276,791
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.004 Tukang 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 134,750
Bahan
1.1.7.01.01.01.013.00001 Keramik Motif - Uk. 20 x 20 cm 1.000 m2 113,500 113,500
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 10.400 kg 1,000 10,400
1.1.7.01.01.01.004.00002 Pasir Pasang 0.045 m3 179,800 8,091
1.1.7.01.01.01.002.00007 Semen Warna - Nat 0.500 kg 20,100 10,050
Jumlah Harga Bahan 142,041
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 276,791
2.01.01.05.01.009 Pekerjaan Pemasangan Lantai Marmer Uk. 100x100 cm m2 558,324
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.006 Tukang Batu 0.350 OH 150,000 52,500

106
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 134,750
Bahan
1.1.7.01.01.01.013.00044 Marmer - Uk. 100 x 100 cm 1.000 m2 404,600 404,600
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 8.190 kg 1,000 8,190
1.1.7.01.01.01.004.00002 Pasir Pasang 0.045 m3 179,800 8,091
1.1.7.01.01.01.002.00007 Semen Warna - Nat 0.134 kg 20,100 2,693
Jumlah Harga Bahan 423,574
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 558,324
2.01.01.05.01.011 Pekerjaan Pemasangan Lantai Kayu (Parquet) m2 218,660
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.004 Tukang 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 134,750
Bahan
1.1.7.01.01.05.002.00047 Lantai Kayu (Parquet) - Bengkirei 1.050 m2 67,400 70,770
1.1.7.01.01.01.022.00270 Lem Kayu 0.600 kg 21,900 13,140
Jumlah Harga Bahan 83,910
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 218,660
2.01.01.05.01.012 Pekerjaan Pemasangan Lantai Karpet + Underlayer (Pelapis Bawah Karpet) m2 182,230
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.009 OH 200,000 1,800
1.10.28.02.01.001.002 Kepala Tukang 0.017 OH 150,000 2,550
1.10.28.02.01.001.004 Tukang 0.170 OH 150,000 25,500
1.10.28.02.01.002.001 Pekerja 0.170 OH 100,000 17,000
Jumlah Harga Tenaga Kerja 46,850
Bahan
1.1.7.01.01.01.022.00239 Karpet 1.050 m2 23,500 24,675
1.1.7.01.01.01.022.00242 Underlayer / Rubber Corrugated 1.050 m2 76,600 80,430
1.1.7.01.01.01.022.00279 Lem Karpet 0.350 kg 86,500 30,275
Jumlah Harga Bahan 135,380
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 182,230
2.01.01.05.02 PEKERJAAN PENUTUP DINDING
2.01.01.05.02.001 Pekerjaan Pemasangan Dinding Keramik Polos Uk. 20x25 cm m2 289,670
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.045 OH 200,000 9,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.004 Tukang 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.900 OH 100,000 90,000
Jumlah Harga Tenaga Kerja 173,250
Bahan
1.1.7.01.01.01.013.00019 Keramik Dinding - Uk. 20 x 25 cm 1.050 m2 61,800 64,890
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.300 kg 1,000 9,300
1.1.7.01.01.01.004.00002 Pasir Pasang 0.018 m3 179,800 3,236

107
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.002.00007 Semen Warna - Nat 1.940 kg 20,100 38,994
Jumlah Harga Bahan 116,420
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 289,670
2.01.01.05.02.002 Pekerjaan Pemasangan Dinding Keramik Polos Uk. 20x20 cm m2 280,980
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.045 OH 200,000 9,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.004 Tukang 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.900 OH 100,000 90,000
Jumlah Harga Tenaga Kerja 173,250
Bahan
1.1.7.01.01.01.013.00013 Keramik Dinding - Uk. 20 x 20 cm 1.000 m2 56,200 56,200
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.300 kg 1,000 9,300
1.1.7.01.01.01.004.00002 Pasir Pasang 0.018 m3 179,800 3,236
1.1.7.01.01.01.002.00007 Semen Warna - Nat 1.940 kg 20,100 38,994
Jumlah Harga Bahan 107,730
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 280,980
2.01.01.05.02.003 Pekerjaan Pemasangan Dinding Keramik Polos Uk. 10x20 cm m2 300,061
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.045 OH 200,000 9,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.004 Tukang 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.900 OH 100,000 90,000
Jumlah Harga Tenaga Kerja 173,250
Bahan
1.1.7.01.01.01.013.00046 Keramik Dinding Motif - Uk. 10 x 20 cm 1.000 m2 59,000 59,000
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.300 kg 1,000 9,300
1.1.7.01.01.01.004.00002 Pasir Pasang 0.018 m3 179,800 3,236
1.1.7.01.01.01.002.00007 Semen Warna - Nat 2.750 kg 20,100 55,275
Jumlah Harga Bahan 126,811
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 300,061
2.01.01.05.02.004 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x25 cm m2 289,670
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.045 OH 200,000 9,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.004 Tukang 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.900 OH 100,000 90,000
Jumlah Harga Tenaga Kerja 173,250
Bahan
1.1.7.01.01.01.013.00019 Keramik Dinding Motif - Uk. 20 x 25 cm 1.050 m2 61,800 64,890
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.300 kg 1,000 9,300
1.1.7.01.01.01.004.00002 Pasir Pasang 0.018 m3 179,800 3,236
1.1.7.01.01.01.002.00007 Semen Warna - Nat 1.940 kg 20,100 38,994
Jumlah Harga Bahan 116,420
Peralatan
Jumlah Harga Peralatan

108
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Harga Satuan Pokok Kegiatan 289,670
2.01.01.05.02.005 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x20 cm m2 338,280
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.045 OH 200,000 9,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.004 Tukang 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.900 OH 100,000 90,000
Jumlah Harga Tenaga Kerja 173,250
Bahan
1.1.7.01.01.01.013.00001 Keramik Dinding Motif - Uk. 20 x 20 cm 1.000 m2 113,500 113,500
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.300 kg 1,000 9,300
1.1.7.01.01.01.004.00002 Pasir Pasang 0.018 m3 179,800 3,236
1.1.7.01.01.01.002.00007 Semen Warna - Nat 1.940 kg 20,100 38,994
Jumlah Harga Bahan 165,030
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 338,280
2.01.01.05.02.006 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 10x20 cm m2 300,061
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.045 OH 200,000 9,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.006 Tukang Batu 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.900 OH 100,000 90,000
Jumlah Harga Tenaga Kerja 173,250
Bahan
1.1.7.01.01.01.013.00046 Keramik Dinding Motif - Uk. 10 x 20 cm 1.000 m2 59,000 59,000
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.300 kg 1,000 9,300
1.1.7.01.01.01.004.00002 Pasir Pasang 0.018 m3 179,800 3,236
1.1.7.01.01.01.002.00007 Semen Warna - Nat 2.750 kg 20,100 55,275
Jumlah Harga Bahan 126,811
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 300,061
2.01.01.05.02.007 Pekerjaan Pemasangan Plint Keramik 10x20 cm m' 53,432
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.004 Tukang 0.090 OH 150,000 13,500
1.10.28.02.01.002.001 Pekerja 0.090 OH 100,000 9,000
Jumlah Harga Tenaga Kerja 28,750
Bahan
1.1.7.01.01.01.013.00026 Plint Keramik - Uk. 10 x 20 cm 5.000 buah 4,500 22,500
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 1.140 kg 1,000 1,140
1.1.7.01.01.01.004.00002 Pasir Pasang 0.003 m3 179,800 539
1.1.7.01.01.01.002.00007 Semen Warna - Nat 0.025 kg 20,100 503
Jumlah Harga Bahan 24,682
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 53,432
2.01.01.05.02.011 Pekerjaan Pemasangan Batu Palimanan m2 320,683
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000

109
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.006 Tukang Batu 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 129,500
Bahan
1.1.7.01.01.01.005.00024 Batu Dinding - Palimanan 1.100 m2 157,400 173,140
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 11.750 kg 1,000 11,750
1.1.7.01.01.01.004.00002 Pasir Pasang 0.035 m3 179,800 6,293
Jumlah Harga Bahan 191,183
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 320,683
2.01.01.05.02.013 Pekerjaan Pemasangan Batu Ampyang m2 254,383
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.006 Tukang Batu 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.620 OH 100,000 62,000
Jumlah Harga Tenaga Kerja 121,500
Bahan
1.1.7.01.01.01.005.00043 Batu Lantai - Ampyang (Carport) Multi Warna 1.100 m2 104,400 114,840
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 11.750 kg 1,000 11,750
1.1.7.01.01.01.004.00002 Pasir Pasang 0.035 m3 179,800 6,293
Jumlah Harga Bahan 132,883
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 254,383
2.01.01.05.02.015 Pekerjaan Pemasangan Batu Gilang m2 349,753
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.006 Tukang Batu 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.620 OH 100,000 62,000
Jumlah Harga Tenaga Kerja 121,500
Bahan
1.1.7.01.01.01.005.00016 Batu Dinding - Gilang Berbagai Profil 1.100 m2 191,100 210,210
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 11.750 kg 1,000 11,750
1.1.7.01.01.01.004.00002 Pasir Pasang 0.035 m3 179,800 6,293
Jumlah Harga Bahan 228,253
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 349,753
2.01.01.05.02.018 Pekerjaan Pemasangan Wallpaper m2 116,158
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.002 OH 200,000 400
1.10.28.02.01.001.004 Tukang 0.175 OH 150,000 26,250
1.10.28.02.01.002.001 Pekerja 0.350 OH 100,000 35,000
Jumlah Harga Tenaga Kerja 61,650
Bahan
1.1.7.01.01.01.022.00243 Wallpaper - lbr. 50 cm 0.200 m' 211,900 42,380
1.1.7.01.01.01.022.00506 Lem Wallpaper 0.250 kg 48,510 12,128
Jumlah Harga Bahan 54,508
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 116,158

110
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.06 PEKERJAAN KAYU
2.01.01.06.01 PEKERJAAN KUSEN, PINTU, JENDELA, DAN JALUSI
2.01.01.06.01.001 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas I (Jati) m3 27,773,310
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.350 OH 200,000 70,000
1.10.28.02.01.001.002 Kepala Tukang 2.100 OH 150,000 315,000
1.10.28.02.01.001.004 Tukang Kayu 21.000 OH 150,000 3,150,000
1.10.28.02.01.002.001 Pekerja 7.000 OH 100,000 700,000
Jumlah Harga Tenaga Kerja 4,235,000
Bahan
1.1.7.01.01.05.002.00001 Kayu Kelas I - Balok (Jati) Uk. 6/12, 400 cm 1.100 m3 21,355,600 23,491,160
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 10 cm 1.250 kg 20,200 25,250
1.1.7.01.01.01.022.00270 Lem Kayu 1.000 kg 21,900 21,900
Jumlah Harga Bahan 23,538,310
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 27,773,310
2.01.01.06.01.002 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas II (Kamper) m3 13,118,630
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.300 OH 200,000 60,000
1.10.28.02.01.001.002 Kepala Tukang 1.800 OH 150,000 270,000
1.10.28.02.01.001.004 Tukang Kayu 18.000 OH 150,000 2,700,000
1.10.28.02.01.002.001 Pekerja 6.000 OH 100,000 600,000
Jumlah Harga Tenaga Kerja 3,630,000
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok (Kamper) Uk. 6/12, 400 cm 1.200 m3 7,867,900 9,441,480
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 10 cm 1.250 kg 20,200 25,250
1.1.7.01.01.01.022.00270 Lem Kayu 1.000 kg 21,900 21,900
Jumlah Harga Bahan 9,488,630
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 13,118,630
2.01.01.06.01.003 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas III (Kruing) m3 12,444,230
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.300 OH 200,000 60,000
1.10.28.02.01.001.002 Kepala Tukang 1.800 OH 150,000 270,000
1.10.28.02.01.001.004 Tukang Kayu 18.000 OH 150,000 2,700,000
1.10.28.02.01.002.001 Pekerja 6.000 OH 100,000 600,000
Jumlah Harga Tenaga Kerja 3,630,000
Bahan
1.1.7.01.01.05.002.00019 Kayu Kelas III - Balok (Kruing) Uk. 6/12, 400 cm 1.200 m3 7,305,900 8,767,080
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 10 cm 1.250 kg 20,200 25,250
1.1.7.01.01.01.022.00270 Lem Kayu 1.000 kg 21,900 21,900
Jumlah Harga Bahan 8,814,230
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 12,444,230
2.01.01.06.01.004 Pembuatan dan Pemasangan Pintu Klamp Kayu Kelas I (Jati) m2 1,067,084
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.018 OH 200,000 3,600
1.10.28.02.01.001.002 Kepala Tukang 0.105 OH 150,000 15,750
1.10.28.02.01.001.004 Tukang Kayu 1.050 OH 150,000 157,500

111
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.002.001 Pekerja 0.350 OH 100,000 35,000
Jumlah Harga Tenaga Kerja 211,850
Bahan
1.1.7.01.01.05.002.00002 Kayu Kelas I - Papan (Jati) Uk. 2 x 20 x 400 cm 0.040 m3 21,355,600 854,224
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.050 kg 20,200 1,010
Jumlah Harga Bahan 855,234
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,067,084
2.01.01.06.01.005 Pembuatan dan Pemasangan Pintu Klamp Kayu Kelas II (Kamper) m2 527,576
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.018 OH 200,000 3,600
1.10.28.02.01.001.002 Kepala Tukang 0.105 OH 150,000 15,750
1.10.28.02.01.001.004 Tukang Kayu 1.050 OH 150,000 157,500
1.10.28.02.01.002.001 Pekerja 0.350 OH 100,000 35,000
Jumlah Harga Tenaga Kerja 211,850
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Papan (Kamper) Uk. 2 x 20 x 400 cm 0.040 m3 7,867,900 314,716
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.050 kg 20,200 1,010
Jumlah Harga Bahan 315,726
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 527,576
2.01.01.06.01.006 Pembuatan dan Pemasangan Pintu Klamp Kayu Kelas III (Kruing) m2 460,136
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.018 OH 200,000 3,600
1.10.28.02.01.001.002 Kepala Tukang 0.105 OH 150,000 15,750
1.10.28.02.01.001.004 Tukang Kayu 1.050 OH 150,000 157,500
1.10.28.02.01.002.001 Pekerja 0.350 OH 100,000 35,000
Jumlah Harga Tenaga Kerja 211,850
Bahan
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan (Kruing) Uk. 2 x 20 x 400 cm 0.040 m3 6,181,900 247,276
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.050 kg 20,200 1,010
Jumlah Harga Bahan 248,286
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 460,136
2.01.01.06.01.007 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Kelas I (Jati) m2 1,470,174
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.001.002 Kepala Tukang 0.300 OH 150,000 45,000
1.10.28.02.01.001.004 Tukang Kayu 3.000 OH 150,000 450,000
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 605,000
Bahan
1.1.7.01.01.05.002.00002 Kayu Kelas I - Papan (Jati) Uk. 2 x 20 x 400 cm 0.040 m3 21,355,600 854,224
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 21,900 10,950
Jumlah Harga Bahan 865,174
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,470,174
2.01.01.06.01.008 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Kelas II (Kamper) m2 930,666

112
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.001.002 Kepala Tukang 0.300 OH 150,000 45,000
1.10.28.02.01.001.004 Tukang Kayu 3.000 OH 150,000 450,000
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 605,000
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Papan (Kamper) Uk. 2 x 20 x 400 cm 0.040 m3 7,867,900 314,716
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 21,900 10,950
Jumlah Harga Bahan 325,666
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 930,666
2.01.01.06.01.009 Pembuatan dan Pemasangan Daun Pintu Panel Kayu Kelas III (Kruing) m2 863,226
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.001.002 Kepala Tukang 0.300 OH 150,000 45,000
1.10.28.02.01.001.004 Tukang Kayu 3.000 OH 150,000 450,000
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 605,000
Bahan
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan (Kruing) Uk. 2 x 20 x 400 cm 0.040 m3 6,181,900 247,276
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 21,900 10,950
Jumlah Harga Bahan 258,226
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 863,226
2.01.01.06.01.010 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas I (Jati) m2 1,003,104
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.040 OH 200,000 8,000
1.10.28.02.01.001.002 Kepala Tukang 0.240 OH 150,000 36,000
1.10.28.02.01.001.004 Tukang Kayu 2.400 OH 150,000 360,000
1.10.28.02.01.002.001 Pekerja 0.800 OH 100,000 80,000
Jumlah Harga Tenaga Kerja 484,000
Bahan
1.1.7.01.01.05.002.00002 Kayu Kelas I - Papan (Jati) Uk. 2 x 20 x 400 cm 0.024 m3 21,355,600 512,534
1.1.7.01.01.01.022.00270 Lem Kayu 0.300 kg 21,900 6,570
Jumlah Harga Bahan 519,104
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,003,104
2.01.01.06.01.011 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas II (Kamper) m2 679,400
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.040 OH 200,000 8,000
1.10.28.02.01.001.002 Kepala Tukang 0.240 OH 150,000 36,000
1.10.28.02.01.001.004 Tukang Kayu 2.400 OH 150,000 360,000
1.10.28.02.01.002.001 Pekerja 0.800 OH 100,000 80,000
Jumlah Harga Tenaga Kerja 484,000
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Papan (Kamper) Uk. 2 x 20 x 400 cm 0.024 m3 7,867,900 188,830
1.1.7.01.01.01.022.00270 Lem Kayu 0.300 kg 21,900 6,570
Jumlah Harga Bahan 195,400

113
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 679,400
2.01.01.06.01.012 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas III (Kruing) m2 638,936
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.040 OH 200,000 8,000
1.10.28.02.01.001.002 Kepala Tukang 0.240 OH 150,000 36,000
1.10.28.02.01.001.004 Tukang Kayu 2.400 OH 150,000 360,000
1.10.28.02.01.002.001 Pekerja 0.800 OH 100,000 80,000
Jumlah Harga Tenaga Kerja 484,000
Bahan
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan (Kruing) Uk. 2 x 20 x 400 cm 0.024 m3 6,181,900 148,366
1.1.7.01.01.01.022.00270 Lem Kayu 0.300 kg 21,900 6,570
Jumlah Harga Bahan 154,936
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 638,936
2.01.01.06.01.013 Pembuatan dan Pemasangan Pintu/Jendela Jalusi Kayu Kelas I (Jati) m2 1,982,708
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.001.002 Kepala Tukang 0.300 OH 150,000 45,000
1.10.28.02.01.001.004 Tukang Kayu 3.000 OH 150,000 450,000
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 605,000
Bahan
1.1.7.01.01.05.002.00002 Kayu Kelas I - Papan (Jati) Uk. 2 x 20 x 400 cm 0.064 m3 21,355,600 1,366,758
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 21,900 10,950
Jumlah Harga Bahan 1,377,708
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,982,708
2.01.01.06.01.014 Pembuatan dan Pemasangan Pintu/Jendela Jalusi Kayu Kelas II (Kamper) m2 1,119,496
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.001.002 Kepala Tukang 0.300 OH 150,000 45,000
1.10.28.02.01.001.004 Tukang Kayu 3.000 OH 150,000 450,000
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 605,000
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Papan (Kamper) Uk. 2 x 20 x 400 cm 0.064 m3 7,867,900 503,546
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 21,900 10,950
Jumlah Harga Bahan 514,496
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,119,496
2.01.01.06.01.015 Pembuatan dan Pemasangan Pintu/Jendela Jalusi Kayu Kelas III (Kruing) m2 1,011,592
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.001.002 Kepala Tukang 0.300 OH 150,000 45,000
1.10.28.02.01.001.004 Tukang Kayu 3.000 OH 150,000 450,000
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 605,000

114
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan (Kruing) Uk. 2 x 20 x 400 cm 0.064 m3 6,181,900 395,642
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 21,900 10,950
Jumlah Harga Bahan 406,592
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,011,592
2.01.01.06.01.016 Pembuatan dan Pemasangan Pintu Plywood Rangkap, Rangka Kayu Kelas I (Jati) m2 1,092,546
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.210 OH 150,000 31,500
1.10.28.02.01.001.004 Tukang Kayu 2.100 OH 150,000 315,000
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 423,500
Bahan
1.1.7.01.01.05.007.00019 Plywood - Uk. 122 x 244 cm, tbl. 4 mm 1.000 lembar 123,600 123,600
1.1.7.01.01.05.002.00002 Kayu Kelas I - Papan (Jati) Uk. 2 x 20 x 400 cm 0.025 m3 21,355,600 533,890
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 21,900 10,950
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.030 kg 20,200 606
Jumlah Harga Bahan 669,046
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,092,546
2.01.01.06.01.017 Pembuatan dan Pemasangan Pintu Plywood Rangkap, Rangka Kayu Kelas II (Kamper) m2 755,354
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.210 OH 150,000 31,500
1.10.28.02.01.001.004 Tukang Kayu 2.100 OH 150,000 315,000
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 423,500
Bahan
1.1.7.01.01.05.007.00019 Plywood - Uk. 122 x 244 cm, tbl. 4 mm 1.000 lembar 123,600 123,600
1.1.7.01.01.05.002.00013 Kayu Kelas II - Papan (Kamper) Uk. 2 x 20 x 400 cm 0.025 m3 7,867,900 196,698
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 21,900 10,950
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.030 kg 20,200 606
Jumlah Harga Bahan 331,854
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 755,354
2.01.01.06.01.018 Pembuatan dan Pemasangan Pintu Plywood Rangkap, Rangka Kayu Kelas III (Kruing) m2 713,204
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.210 OH 150,000 31,500
1.10.28.02.01.001.004 Tukang Kayu 2.100 OH 150,000 315,000
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 423,500
Bahan
1.1.7.01.01.05.007.00019 Plywood - Uk. 122 x 244 cm, tbl. 4 mm 1.000 lembar 123,600 123,600
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan (Kruing) Uk. 2 x 20 x 400 cm 0.025 m3 6,181,900 154,548
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 21,900 10,950
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.030 kg 20,200 606
Jumlah Harga Bahan 289,704

115
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 713,204
2.01.01.06.01.019 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas I (Jati) m2 1,031,966
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.210 OH 150,000 31,500
1.10.28.02.01.001.004 Tukang Kayu 2.100 OH 150,000 315,000
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 423,500
Bahan
1.1.7.01.01.05.007.00034 Taekwood - Uk. 122 x 244 cm, tbl. 4 mm 1.000 lembar 67,400 67,400
1.1.7.01.01.05.002.00002 Kayu Kelas I - Papan (Jati) Uk. 2 x 20 x 400 cm 0.025 m3 21,355,600 533,890
1.1.7.01.01.01.022.00270 Lem Kayu 0.300 kg 21,900 6,570
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.030 kg 20,200 606
Jumlah Harga Bahan 608,466
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,031,966
2.01.01.06.01.020 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas II (Kamper) m2 694,774
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.210 OH 150,000 31,500
1.10.28.02.01.001.004 Tukang Kayu 2.100 OH 150,000 315,000
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 423,500
Bahan
1.1.7.01.01.05.007.00034 Taekwood - Uk. 122 x 244 cm, tbl. 4 mm 1.000 lembar 67,400 67,400
1.1.7.01.01.05.002.00013 Kayu Kelas II - Papan (Kamper) Uk. 2 x 20 x 400 cm 0.025 m3 7,867,900 196,698
1.1.7.01.01.01.022.00270 Lem Kayu 0.300 kg 21,900 6,570
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.030 kg 20,200 606
Jumlah Harga Bahan 271,274
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 694,774
2.01.01.06.01.021 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas III (Kruing) m2 652,624
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.210 OH 150,000 31,500
1.10.28.02.01.001.004 Tukang Kayu 2.100 OH 150,000 315,000
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 423,500
Bahan
1.1.7.01.01.05.007.00034 Taekwood - Uk. 122 x 244 cm, tbl. 4 mm 1.000 lembar 67,400 67,400
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan (Kruing) Uk. 2 x 20 x 400 cm 0.025 m3 6,181,900 154,548
1.1.7.01.01.01.022.00270 Lem Kayu 0.300 kg 21,900 6,570
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.030 kg 20,200 606
Jumlah Harga Bahan 229,124
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 652,624
2.01.01.06.01.022 Pembuatan dan Pemasangan Pintu Triplek Rangkap, Rangka Kayu Kelas I (Jati) m2 1,048,866

116
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.210 OH 150,000 31,500
1.10.28.02.01.001.004 Tukang Kayu 2.100 OH 150,000 315,000
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 423,500
Bahan
1.1.7.01.01.05.007.00007 Triplek - Uk. 122 x 244 cm, tbl. 4 mm 1.000 lembar 84,300 84,300
1.1.7.01.01.05.002.00002 Kayu Kelas I - Papan (Jati) Uk. 2 x 20 x 400 cm 0.025 m3 21,355,600 533,890
1.1.7.01.01.01.022.00270 Lem Kayu 0.300 kg 21,900 6,570
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.030 kg 20,200 606
Jumlah Harga Bahan 625,366
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,048,866
2.01.01.06.01.023 Pembuatan dan Pemasangan Pintu Triplek Rangkap, Rangka Kayu Kelas II (Kamper) m2 711,674
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.210 OH 150,000 31,500
1.10.28.02.01.001.004 Tukang Kayu 2.100 OH 150,000 315,000
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 423,500
Bahan
1.1.7.01.01.05.007.00007 Triplek - Uk. 122 x 244 cm, tbl. 4 mm 1.000 lembar 84,300 84,300
1.1.7.01.01.05.002.00013 Kayu Kelas II - Papan (Kamper) Uk. 2 x 20 x 400 cm 0.025 m3 7,867,900 196,698
1.1.7.01.01.01.022.00270 Lem Kayu 0.300 kg 21,900 6,570
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.030 kg 20,200 606
Jumlah Harga Bahan 288,174
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 711,674
2.01.01.06.01.025 Pembuatan dan Pemasangan Pintu Triplek Rangkap, Rangka Kayu Kelas III (Kruing) m2 669,524
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.035 OH 200,000 7,000
1.10.28.02.01.001.002 Kepala Tukang 0.210 OH 150,000 31,500
1.10.28.02.01.001.004 Tukang Kayu 2.100 OH 150,000 315,000
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 423,500
Bahan
1.1.7.01.01.05.007.00007 Triplek - Uk. 122 x 244 cm, tbl. 4 mm 1.000 lembar 84,300 84,300
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan (Kruing) Uk. 2 x 20 x 400 cm 0.025 m3 6,181,900 154,548
1.1.7.01.01.01.022.00270 Lem Kayu 0.300 kg 21,900 6,570
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.030 kg 20,200 606
Jumlah Harga Bahan 246,024
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 669,524
2.01.01.06.01.026 Pekerjaan Pemasangan Pintu PVC (Polyvinyl Chloride) unit 473,100
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.030 OH 200,000 6,000
1.10.28.02.01.001.002 Kepala Tukang 0.030 OH 150,000 4,500
1.10.28.02.01.001.004 Tukang Kayu 0.600 OH 150,000 90,000

117
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.002.001 Pekerja 0.600 OH 100,000 60,000
Jumlah Harga Tenaga Kerja 160,500
Bahan
1.1.7.01.01.01.022.00058 Pintu PVC - Uk. 80 x 200 cm (pre-fabricated) 1.000 buah 312,600 312,600
Jumlah Harga Bahan 312,600
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 473,100
2.01.01.06.01.027 Pekerjaan Pemasangan Pintu HPL (High Pressure Laminated) unit 545,500
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.030 OH 200,000 6,000
1.10.28.02.01.001.002 Kepala Tukang 0.030 OH 150,000 4,500
1.10.28.02.01.001.004 Tukang Kayu 0.600 OH 150,000 90,000
1.10.28.02.01.002.001 Pekerja 0.600 OH 100,000 60,000
Jumlah Harga Tenaga Kerja 160,500
Bahan
1.1.7.01.01.01.022.00515 Pintu HPL - Uk. 80 x 200 cm (pre-fabricated) 1.000 buah 385,000 385,000
Jumlah Harga Bahan 385,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 545,500
2.01.01.06.02 PEKERJAAN KUDA-KUDA DAN RANGKA ATAP
2.01.01.06.02.001 Pekerjaan Pemasangan Kuda-kuda Kayu Kelas I (Jati) m3 26,335,680
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.200 OH 200,000 40,000
1.10.28.02.01.001.002 Kepala Tukang 1.200 OH 150,000 180,000
1.10.28.02.01.001.004 Tukang Kayu 12.000 OH 150,000 1,800,000
1.10.28.02.01.002.001 Pekerja 4.000 OH 100,000 400,000
Jumlah Harga Tenaga Kerja 2,420,000
Bahan
1.1.7.01.01.05.002.00001 Kayu Kelas I - Balok (Jati) Uk. 8/12, 400 cm 1.100 m3 21,355,600 23,491,160
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 12 cm 15.000 kg 20,200 303,000
1.1.7.01.01.01.008.00072 Besi Strip - Tbl. 5 mm 5.600 kg 21,700 121,520
Jumlah Harga Bahan 23,915,680
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 26,335,680
2.01.01.06.02.002 Pekerjaan Pemasangan Kuda-kuda Kayu Kelas II (Kamper) m3 11,499,210
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.200 OH 200,000 40,000
1.10.28.02.01.001.002 Kepala Tukang 1.200 OH 150,000 180,000
1.10.28.02.01.001.004 Tukang Kayu 12.000 OH 150,000 1,800,000
1.10.28.02.01.002.001 Pekerja 4.000 OH 100,000 400,000
Jumlah Harga Tenaga Kerja 2,420,000
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok (Kamper) Uk. 8/12, 400 cm 1.100 m3 7,867,900 8,654,690
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 12 cm 15.000 kg 20,200 303,000
1.1.7.01.01.01.008.00072 Besi Strip - Tbl. 5 mm 5.600 kg 21,700 121,520
Jumlah Harga Bahan 9,079,210
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 11,499,210

118
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.06.02.003 Pekerjaan Pemasangan Kuda-kuda Kayu Kelas III (Kruing & Meranti) m3 10,881,010
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.200 OH 200,000 40,000
1.10.28.02.01.001.002 Kepala Tukang 1.200 OH 150,000 180,000
1.10.28.02.01.001.004 Tukang Kayu 12.000 OH 150,000 1,800,000
1.10.28.02.01.002.001 Pekerja 4.000 OH 100,000 400,000
Jumlah Harga Tenaga Kerja 2,420,000
Bahan
1.1.7.01.01.05.002.00019 Kayu Kelas III - Balok (Kruing & Meranti) Uk. 8/12, 400 cm 1.100 m3 7,305,900 8,036,490
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 12 cm 15.000 kg 20,200 303,000
1.1.7.01.01.01.008.00072 Besi Strip - Tbl. 5 mm 5.600 kg 21,700 121,520
Jumlah Harga Bahan 8,461,010
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 10,881,010
2.01.01.06.02.005 Pekerjaan Pemasangan Gording Kayu Kelas I (Jati) m3 25,311,260
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.120 OH 200,000 24,000
1.10.28.02.01.001.002 Kepala Tukang 0.720 OH 150,000 108,000
1.10.28.02.01.001.004 Tukang Kayu 7.200 OH 150,000 1,080,000
1.10.28.02.01.002.001 Pekerja 2.400 OH 100,000 240,000
Jumlah Harga Tenaga Kerja 1,452,000
Bahan
1.1.7.01.01.05.002.00001 Kayu Kelas I - Balok (Jati) Uk. 8/12, 400 cm 1.100 m3 21,355,600 23,491,160
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 12 cm 15.000 kg 20,200 303,000
1.1.7.01.01.01.008.00072 Besi Strip - Tbl. 5 mm 3.000 kg 21,700 65,100
Jumlah Harga Bahan 23,859,260
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 25,311,260
2.01.01.06.02.006 Pekerjaan Pemasangan Gording Kayu Kelas II (Kamper) m3 10,474,790
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.120 OH 200,000 24,000
1.10.28.02.01.001.002 Kepala Tukang 0.720 OH 150,000 108,000
1.10.28.02.01.001.004 Tukang Kayu 7.200 OH 150,000 1,080,000
1.10.28.02.01.002.001 Pekerja 2.400 OH 100,000 240,000
Jumlah Harga Tenaga Kerja 1,452,000
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok (Kamper) Uk. 8/12, 400 cm 1.100 m3 7,867,900 8,654,690
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 12 cm 15.000 kg 20,200 303,000
1.1.7.01.01.01.008.00072 Besi Strip - Tbl. 5 mm 3.000 kg 21,700 65,100
Jumlah Harga Bahan 9,022,790
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 10,474,790
2.01.01.06.02.007 Pekerjaan Pemasangan Gording Kayu Kelas III (Kruing & Meranti) m3 9,856,590
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.120 OH 200,000 24,000
1.10.28.02.01.001.002 Kepala Tukang 0.720 OH 150,000 108,000
1.10.28.02.01.001.004 Tukang Kayu 7.200 OH 150,000 1,080,000
1.10.28.02.01.002.001 Pekerja 2.400 OH 100,000 240,000
Jumlah Harga Tenaga Kerja 1,452,000

119
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
1.1.7.01.01.05.002.00019 Kayu Kelas III - Balok (Kruing & Meranti) Uk. 8/12, 400 cm 1.100 m3 7,305,900 8,036,490
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 12 cm 15.000 kg 20,200 303,000
1.1.7.01.01.01.008.00072 Besi Strip - Tbl. 5 mm 3.000 kg 21,700 65,100
Jumlah Harga Bahan 8,404,590
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 9,856,590
2.01.01.06.02.009 Pekerjaan Pemasangan Rangka Atap Kayu Kelas III - Genteng Kodok m2 116,957
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.006 OH 200,000 1,200
1.10.28.02.01.001.002 Kepala Tukang 0.012 OH 150,000 1,800
1.10.28.02.01.001.004 Tukang Kayu 0.120 OH 150,000 18,000
1.10.28.02.01.002.001 Pekerja 0.120 OH 100,000 12,000
Jumlah Harga Tenaga Kerja 33,000
Bahan
1.1.7.01.01.05.002.00025 Kayu Kelas III - Balok Reng (Kruing) Uk. 2/3, 400 cm 0.012 m3 6,743,900 80,927
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.150 kg 20,200 3,030
Jumlah Harga Bahan 83,957
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 116,957
2.01.01.06.02.010 Pekerjaan Pemasangan Rangka Atap Kayu Kelas III - Genteng Keramik m2 369,745
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.004 Tukang Kayu 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 27,500
Bahan
1.1.7.01.01.05.002.00025 Kayu Kelas III - Balok Usuk (Kruing) Uk. 5/7, 400 cm 0.014 m3 6,743,900 94,415
1.1.7.01.01.05.002.00025 Kayu Kelas III - Balok Reng (Kruing) Uk. 2/3, 400 cm 0.036 m3 6,743,900 242,780
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.250 kg 20,200 5,050
Jumlah Harga Bahan 342,245
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 369,745
2.01.01.06.02.011 Pekerjaan Pemasangan Rangka Atap Kayu Kelas III - Genteng Beton m2 511,367
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.004 Tukang Kayu 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 27,500
Bahan
1.1.7.01.01.05.002.00025 Kayu Kelas III - Balok Usuk (Kruing) Uk. 5/7, 400 cm 0.014 m3 6,743,900 94,415
1.1.7.01.01.05.002.00025 Kayu Kelas III - Balok Reng (Kruing) Uk. 2/3, 400 cm 0.057 m3 6,743,900 384,402
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.250 kg 20,200 5,050
Jumlah Harga Bahan 483,867
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 511,367

120
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.06.03 PEKERJAAN RANGKA LANGIT-LANGIT DAN LISTPLANK
2.01.01.06.03.004 Pekerjaan Pemasangan Rangka Langit-langit Kayu Kelas II (Kamper) 100x100 m2 167,685
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.025 OH 150,000 3,750
1.10.28.02.01.001.004 Tukang Kayu 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 71,250
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok Usuk (Kamper) Uk. 5/7, 400 cm 0.012 m3 7,867,900 94,415
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.100 kg 20,200 2,020
Jumlah Harga Bahan 96,435
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 167,685
2.01.01.06.03.005 Pekerjaan Pemasangan Rangka Langit-langit Kayu Kelas II (Kamper) 50x100 m2 204,706
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.030 OH 150,000 4,500
1.10.28.02.01.001.004 Tukang Kayu 0.300 OH 150,000 45,000
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 79,500
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok Usuk (Kamper) Uk. 5/7, 400 cm 0.015 m3 7,867,900 121,166
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.200 kg 20,200 4,040
Jumlah Harga Bahan 125,206
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 204,706
2.01.01.06.03.006 Pekerjaan Pemasangan Rangka Langit-langit Kayu Kelas II (Kamper) 60x60 m2 204,797
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.010 OH 200,000 2,000
1.10.28.02.01.001.002 Kepala Tukang 0.030 OH 150,000 4,500
1.10.28.02.01.001.004 Tukang Kayu 0.300 OH 150,000 45,000
1.10.28.02.01.002.001 Pekerja 0.200 OH 100,000 20,000
Jumlah Harga Tenaga Kerja 71,500
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok Usuk (Kamper) Uk. 5/7, 400 cm 0.016 m3 7,867,900 128,247
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.250 kg 20,200 5,050
Jumlah Harga Bahan 133,297
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 204,797
2.01.01.06.03.014 Pekerjaan Pemasangan Listplank Kayu Kelas II (Kamper) 3/20 m2 130,993
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.004 Tukang Kayu 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 44,000
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Papan (Kamper) Uk. 2 x 20 x 400 cm 0.011 m3 7,867,900 84,973

121
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.100 kg 20,200 2,020
Jumlah Harga Bahan 86,993
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 130,993
2.01.01.06.03.016 Pekerjaan Pemasangan Listplank Kayu Kelas II (Kamper) 3/30 m2 131,557
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.004 Tukang Kayu 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 44,000
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Papan (Kamper) Uk. 2 x 20 x 400 cm 0.011 m3 7,867,900 86,547
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.050 kg 20,200 1,010
Jumlah Harga Bahan 87,557
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 131,557
2.01.01.06.04 PEKERJAAN DINDING PARTISI
2.01.01.06.04.011 Pekerjaan Partisi Double Gypsum Rangka Kayu Kelas II (Kamper) m2 329,071
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.004 Tukang Kayu 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 104,250
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok (Kamper) Uk. 5/7, 400 cm 0.020 m3 7,867,900 153,424
1.1.7.01.01.01.022.00073 Gypsum Board - Uk. 120 x 240 cm 0.690 lembar 65,200 44,988
1.1.7.01.01.01.022.00087 Paku Asbes - Uk. 4 inch. 0.224 kg 61,800 13,843
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.080 kg 20,200 1,616
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 21,900 10,950
Jumlah Harga Bahan 224,821
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 329,071
2.01.01.06.04.012 Pekerjaan Partisi Double Plywood Rangka Kayu Kelas II (Kamper) m2 423,104
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.004 Tukang Kayu 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 104,250
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok (Kamper) Uk. 5/7, 400 cm 0.020 m3 7,867,900 153,424
1.1.7.01.01.05.007.00019 Plywood - Uk. 122 x 244 cm, tbl. 4 mm 0.690 lembar 123,600 85,284
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.170 kg 20,200 3,434
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 153,424 76,712
Jumlah Harga Bahan 318,854
Peralatan
Jumlah Harga Peralatan

122
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Harga Satuan Pokok Kegiatan 423,104
2.01.01.06.04.013 Pekerjaan Partisi Multiplek Finishing HPL Rangka Kayu Kelas II (Kamper) m2 777,820
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.004 Tukang Kayu 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 104,250
Bahan
1.1.7.01.01.05.002.00013 Kayu Kelas II - Balok (Kamper) Uk. 5/7, 400 cm 0.020 m3 7,867,900 153,424
1.1.7.01.01.05.007.00058 Multiplek Finishing HPL 1.100 m2 400,000 440,000
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.170 kg 20,200 3,434
1.1.7.01.01.01.022.00270 Lem Kayu 0.500 kg 153,424 76,712
Jumlah Harga Bahan 673,570
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 777,820
2.01.01.06.04.014 Pekerjaan Partisi Double Gypsum Rangka Metal Stud m2 263,377
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.004 Tukang Kayu 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 104,250
Bahan
1.1.7.01.01.01.022.00507 Metal Stud - MS 92 Uk. 34 x 92 mm, tbl. 0.4 - 1.0 mm 0.016 m3 5,385,710 86,171
1.1.7.01.01.01.022.00073 Gypsum Board - Uk. 120 x 240 cm 0.690 lembar 65,200 44,988
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.224 kg 67,400 15,098
1.1.7.01.01.01.022.00526 Skrup Metal Stud 0.120 kg 107,250 12,870
Jumlah Harga Bahan 159,127
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 263,377
2.01.01.06.04.015 Pekerjaan Partisi Double Plywood Rangka Metal Stud m2 303,673
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.004 Tukang Kayu 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 104,250
Bahan
1.1.7.01.01.01.022.00507 Metal Stud - MS 92 Uk. 34 x 92 mm, tbl. 0.4 - 1.0 mm 0.016 m3 5,385,710 86,171
1.1.7.01.01.05.007.00019 Plywood - Uk. 122 x 244 cm, tbl. 4 mm 0.690 lembar 123,600 85,284
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.224 kg 67,400 15,098
1.1.7.01.01.01.022.00526 Skrup Metal Stud 0.120 kg 107,250 12,870
Jumlah Harga Bahan 199,423
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 303,673
2.01.01.06.04.016 Pekerjaan Partisi Multiplek Finishing HPL Rangka Metal Stud m2 658,389
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000

123
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.004 Tukang Kayu 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 104,250
Bahan
1.1.7.01.01.01.022.00507 Metal Stud - MS 92 Uk. 34 x 92 mm, tbl. 0.4 - 1.0 mm 0.016 m3 5,385,710 86,171
1.1.7.01.01.05.007.00058 Multiplek Finishing HPL 1.100 m2 400,000 440,000
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.224 kg 67,400 15,098
1.1.7.01.01.01.022.00526 Skrup Metal Stud 0.120 kg 107,250 12,870
Jumlah Harga Bahan 554,139
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 658,389
2.01.01.06.04.017 Pekerjaan Partisi Kalsiboard Rangka Hollow m2 204,245
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.002 Kepala Tukang 0.045 OH 150,000 6,750
1.10.28.02.01.001.008 Tukang Besi 0.450 OH 150,000 67,500
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 104,250
Bahan
1.1.7.01.01.01.022.00220 Rangka Hollow - Uk. 40 x 40 x 2 mm 0.900 batang 33,700 30,330
1.1.7.01.01.01.022.00079 Kalsiboard - Uk. 120 x 240 cm, tbl. 6 mm 0.365 lembar 149,500 54,568
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.224 kg 67,400 15,098
Jumlah Harga Bahan 99,995
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 204,245
2.01.01.07 PEKERJAAN FINISHING
2.01.01.07.01 PEKERJAAN FINISHING PENUTUP ATAP DAN LANGIT LANGIT
2.01.01.07.01.001 Pekerjaan Pemasangan Penutup Atap Genteng Tanah Liat (Karang Pilang) m2 73,050
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.004 Tukang Kayu 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 29,050
Bahan
1.1.7.01.01.01.014.00015 Genteng Tanah Liat - Karang Pilang Uk. 19.5 x 23.5 cm 20.000 buah 2,200 44,000
Jumlah Harga Bahan 44,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 73,050
2.01.01.07.01.003 Pekerjaan Pemasangan Penutup Atap Genteng Tanah Liat (Plentong, Kodok) Glazur m2 89,050
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.004 Tukang Kayu 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 29,050
Bahan
1.1.7.01.01.01.014.00019 Genteng Tanah Liat - Plentong, Kodok Uk. 23 x 29 cm 25.000 buah 2,400 60,000

124
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Bahan 60,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 89,050
2.01.01.07.01.005 Pekerjaan Pemasangan Penutup Atap Genteng Keramik Glazur m2 541,770
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.004 Tukang Kayu 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 29,050
Bahan
1.1.7.01.01.01.014.00023 Genteng Keramik - Uk. 31 x 34 cm 13.600 buah 37,700 512,720
Jumlah Harga Bahan 512,720
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 541,770
2.01.01.07.01.009 Pekerjaan Pemasangan Penutup Atap Seng Gelombang m2 86,848
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.006 OH 200,000 1,200
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 900
1.10.28.02.01.001.004 Tukang Kayu 0.060 OH 150,000 9,000
1.10.28.02.01.002.001 Pekerja 0.120 OH 100,000 12,000
Jumlah Harga Tenaga Kerja 23,100
Bahan
1.1.7.01.01.01.007.00002 Seng Gelombang - BJLS 30 Uk. 80 x 240 cm, tbl. 2.5 - 3 mm 0.550 lembar 101,200 55,660
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.120 kg 67,400 8,088
Jumlah Harga Bahan 63,748
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 86,848
2.01.01.07.01.010 Pekerjaan Pemasangan Penutup Atap Roof Light Fiberglass m2 198,369
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.007 OH 200,000 1,400
1.10.28.02.01.001.002 Kepala Tukang 0.007 OH 150,000 1,050
1.10.28.02.01.001.004 Tukang Kayu 0.067 OH 150,000 10,050
1.10.28.02.01.002.001 Pekerja 0.120 OH 100,000 12,000
Jumlah Harga Tenaga Kerja 24,500
Bahan
1.1.7.01.01.01.022.00518 Roof Light Fiberglass - Uk. 90 x 180 cm 1.050 m2 159,170 167,129
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.100 kg 67,400 6,740
Jumlah Harga Bahan 173,869
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 198,369
2.01.01.07.01.044 Pekerjaan Pemasangan Penutup Atap Galvalum m2 144,148
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.007 OH 200,000 1,400
1.10.28.02.01.001.002 Kepala Tukang 0.007 OH 150,000 1,050
1.10.28.02.01.001.004 Tukang Kayu 0.067 OH 150,000 10,050
1.10.28.02.01.002.001 Pekerja 0.140 OH 100,000 14,000
Jumlah Harga Tenaga Kerja 26,500

125
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
1.1.7.01.01.01.022.00517 Plat Galvalum - BJLS 30 Uk. 1.219 x 1 m, 4.12 kg 0.830 lembar 132,000 109,560
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.120 kg 67,400 8,088
Jumlah Harga Bahan 117,648
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 144,148
2.01.01.07.01.011 Pekerjaan Pemasangan Penutup Atap Asbes Gelombang Tebal 5 mm m2 82,788
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.004 Tukang Kayu 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.140 OH 100,000 14,000
Jumlah Harga Tenaga Kerja 28,050
Bahan
1.1.7.01.01.01.022.00014 Asbes Gelombang - Uk. 0.92 x 2.5 m, tbl. 5 mm 0.500 lembar 93,300 46,650
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.120 kg 67,400 8,088
Jumlah Harga Bahan 54,738
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 82,788
2.01.01.07.01.016 Pekerjaan Pemasangan Penutup Atap Asbes Gelombang Tebal 4 mm m2 75,694
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.004 Tukang Kayu 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.140 OH 100,000 14,000
Jumlah Harga Tenaga Kerja 28,050
Bahan
1.1.7.01.01.01.022.00009 Asbes Gelombang - Uk. 1.05 x 2.4 m, tbl. 4 mm 0.440 lembar 89,900 39,556
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.120 kg 67,400 8,088
Jumlah Harga Bahan 47,644
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 75,694
2.01.01.07.01.020 Pekerjaan Pemasangan Bubungan Genteng Tanah Liat (Karang Pilang) m' 121,554
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.004 Tukang Kayu 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 29,050
Bahan
1.1.7.01.01.01.014.00009 Bubungan Genteng Tanah Liat - Karang Pilang Uk. 20 x 33 cm 3.500 buah 22,500 78,750
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 8.000 kg 1,000 8,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.032 m3 179,800 5,754
Jumlah Harga Bahan 92,504
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 121,554
2.01.01.07.01.021 Pekerjaan Pemasangan Bubungan Genteng Tanah Liat (Plentong, Kodok) Glazur m' 72,204
Tenaga Kerja

126
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.004 Tukang Kayu 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 29,050
Bahan
1.1.7.01.01.01.014.00002 Bubungan Genteng Tanah Liat - Plentong, Kodok Uk. 20 x 33 cm 3.500 buah 8,400 29,400
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 8.000 kg 1,000 8,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.032 m3 179,800 5,754
Jumlah Harga Bahan 43,154
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 72,204
2.01.01.07.01.022 Pekerjaan Pemasangan Bubungan Genteng Keramik Glazur m' 177,604
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.004 Tukang Kayu 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 29,050
Bahan
1.1.7.01.01.01.014.00028 Bubungan Genteng Keramik - Uk. 21 x 29.5 cm 4.000 buah 33,700 134,800
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 8.000 kg 1,000 8,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.032 m3 179,800 5,754
Jumlah Harga Bahan 148,554
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 177,604
2.01.01.07.01.023 Pekerjaan Pemasangan Nok Genteng Beton m' 161,914
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.020 OH 200,000 4,000
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.004 Tukang Kayu 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.400 OH 100,000 40,000
Jumlah Harga Tenaga Kerja 77,000
Bahan
1.1.7.01.01.01.014.00027 Nok Genteng Beton - Uk. 27 x 35 cm 3.500 buah 13,500 47,250
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 10.800 kg 1,000 10,800
1.1.7.01.01.01.002.00007 Semen Warna - Nat 1.000 kg 20,100 20,100
1.1.7.01.01.01.004.00002 Pasir Pasang 0.032 m3 179,800 5,754
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.050 kg 20,200 1,010
Jumlah Harga Bahan 84,914
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 161,914
2.01.01.07.01.045 Pekerjaan Pemasangan Nok Galvalum m' 64,120
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.006 OH 200,000 1,200
1.10.28.02.01.001.002 Kepala Tukang 0.007 OH 150,000 1,050
1.10.28.02.01.001.004 Tukang Kayu 0.070 OH 150,000 10,500
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 27,750

127
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
1.1.7.01.01.01.014.00032 Nok Galvalum - BJLS 30 Uk. 30 x 300 cm 0.300 lembar 110,000 33,000
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.050 kg 67,400 3,370
Jumlah Harga Bahan 36,370
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 64,120
2.01.01.07.01.026 Pekerjaan Pemasangan Nok Seng m' 44,620
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.006 OH 200,000 1,200
1.10.28.02.01.001.002 Kepala Tukang 0.007 OH 150,000 1,050
1.10.28.02.01.001.004 Tukang Kayu 0.070 OH 150,000 10,500
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 27,750
Bahan
1.1.7.01.01.01.014.00031 Nok Seng Plat - BJLS 30, Uk. 3 x 6 inch 300 cm 0.300 lembar 45,000 13,500
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.050 kg 67,400 3,370
Jumlah Harga Bahan 16,870
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 44,620
2.01.01.07.01.031 Pekerjaan Pemasangan Bubungan Steel Gelombang Kecil m' 172,465
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.013 OH 150,000 1,950
1.10.28.02.01.001.004 Tukang Kayu 0.125 OH 150,000 18,750
1.10.28.02.01.002.001 Pekerja 0.084 OH 100,000 8,400
Jumlah Harga Tenaga Kerja 29,900
Bahan
1.1.7.01.01.01.022.00031 Bubungan Steel Gelombang - Uk. 108 cm, tbl. 6 mm 2.050 lembar 67,900 139,195
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.050 kg 67,400 3,370
Jumlah Harga Bahan 142,565
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 172,465
2.01.01.07.01.046 Pekerjaan Pemasangan Insulation Alumunium Foil m2 32,935
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.004 Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 24,850
Bahan
1.1.7.01.01.01.022.00477 Alumunium Foil Paper - Sisalation 1.050 m2 7,700 8,085
Jumlah Harga Bahan 8,085
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 32,935
2.01.01.07.01.032 Pekerjaan Waterproofing Membrane (Liquid) m2 89,015
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.004 Tukang 0.075 OH 150,000 11,250

128
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.002.001 Pekerja 0.050 OH 100,000 5,000
Jumlah Harga Tenaga Kerja 31,250
Bahan
1.1.7.01.01.01.022.00203 Waterproofing Membrane - Liquid 1.050 kg 39,300 41,265
Jumlah Harga Bahan 41,265
Peralatan
9.1.2.10.07.01.001.00129 Sprayer Waterproofing 0.500 jam 33,000 16,500
Jumlah Harga Peralatan 16,500
Harga Satuan Pokok Kegiatan 89,015
2.01.01.07.01.033 Pekerjaan Waterproofing Coating m2 130,955
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.075 OH 200,000 15,000
1.10.28.02.01.001.004 Tukang 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.050 OH 100,000 5,000
Jumlah Harga Tenaga Kerja 31,250
Bahan
1.1.7.01.01.01.022.00202 Waterproofing Coat - Polymer 1.050 kg 55,100 57,855
1.1.7.01.01.01.022.00522 Serat Fiber Mat - Uk. 25 x 30 cm 13.500 lembar 3,100 41,850
Jumlah Harga Bahan 99,705
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 130,955
2.01.01.07.01.034 Pekerjaan Pemasangan Langit-langit Asbes Tebal 4 mm, 5 mm, 6 mm m2 126,652
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.007 OH 150,000 1,050
1.10.28.02.01.001.004 Tukang Kayu 0.070 OH 150,000 10,500
1.10.28.02.01.002.001 Pekerja 0.030 OH 100,000 3,000
Jumlah Harga Tenaga Kerja 15,350
Bahan
1.1.7.01.01.01.022.00076 Plafon Asbes Eternit - Tbl. 4 mm, 5 mm, 6 mm 1.100 m2 101,000 111,100
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.010 kg 20,200 202
Jumlah Harga Bahan 111,302
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 126,652
2.01.01.07.01.038 Pekerjaan Pemasangan Langit-langit Tripleks Tebal 3 mm, 4 mm, 6 mm m2 63,919
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.004 Tukang Kayu 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 27,500
Bahan
1.1.7.01.01.05.007.00008 Plafon Tripleks - Uk. 120 x 240 cm, Tbl. 3 mm, 4mm, 6 mm 0.375 lembar 95,500 35,813
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.030 kg 20,200 606
Jumlah Harga Bahan 36,419
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 63,919
2.01.01.07.01.041 Pekerjaan Pemasangan Langit-langit Gypsum Board Tebal 9 mm m2 50,462
Tenaga Kerja

129
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.004 Tukang Kayu 0.050 OH 150,000 7,500
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 19,250
Bahan
1.1.7.01.01.01.022.00073 Plafon Gypsum Board - Uk. 122 x 244 cm, Tbl. 9 mm 0.365 lembar 65,200 23,798
1.1.7.01.01.01.022.00088 Skrup Asbes - Uk. 4 inch. 0.110 kg 67,400 7,414
Jumlah Harga Bahan 31,212
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 50,462
2.01.01.07.01.042 Pekerjaan Pemasangan Lis Langit-langit Kayu m' 145,142
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.004 Tukang Kayu 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.500 OH 100,000 50,000
Jumlah Harga Tenaga Kerja 126,350
Bahan
1.1.7.01.01.05.002.00055 Lis Plafon Kayu - Pjg. 200 cm 1.100 m' 16,900 18,590
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.010 kg 20,200 202
Jumlah Harga Bahan 18,792
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 145,142
2.01.01.07.01.043 Pekerjaan Pemasangan Lis Langit-langit Gypsum m' 183,595
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 900
1.10.28.02.01.001.004 Tukang Kayu 0.600 OH 150,000 90,000
1.10.28.02.01.002.001 Pekerja 0.600 OH 100,000 60,000
Jumlah Harga Tenaga Kerja 151,500
Bahan
1.1.7.01.01.01.022.00074 Lis Plafon Gypsum 1.100 m' 28,100 30,910
1.1.7.01.01.01.022.00083 Tepung Gypsum 0.150 kg 7,900 1,185
Jumlah Harga Bahan 32,095
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 183,595
2.01.01.07.02 PEKERJAAN SANITAIR
2.01.01.07.02.001 Pekerjaan Pemasangan Kloset Duduk unit 2,017,800
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.160 OH 200,000 32,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.006 Tukang Batu 1.100 OH 150,000 165,000
1.10.28.02.01.002.001 Pekerja 3.300 OH 100,000 330,000
Jumlah Harga Tenaga Kerja 528,500
Bahan
1.1.7.01.01.01.022.00144 Kloset Duduk/Monoblock 1.060 buah 1,405,000 1,489,300
Jumlah Harga Bahan 1,489,300
Peralatan

130
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 2,017,800
2.01.01.07.02.002 Pekerjaan Pemasangan Kloset Jongkok Porselain unit 601,998
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.160 OH 200,000 32,000
1.10.28.02.01.001.002 Kepala Tukang 0.150 OH 150,000 22,500
1.10.28.02.01.001.006 Tukang Batu 1.500 OH 150,000 225,000
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 379,500
Bahan
1.1.7.01.01.01.022.00154 Kloset Jongkok 1.000 unit 214,700 214,700
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 6.000 kg 1,000 6,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.010 m3 179,800 1,798
Jumlah Harga Bahan 222,498
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 601,998
2.01.01.07.02.004 Pekerjaan Pemasangan Urinoir unit 3,555,808
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.001.002 Kepala Tukang 0.100 OH 150,000 15,000
1.10.28.02.01.001.004 Tukang 1.000 OH 150,000 150,000
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 275,000
Bahan
1.1.7.01.01.01.022.00160 Urinoir 1.300 unit 2,517,700 3,273,010
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 6.000 kg 1,000 6,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.010 m3 179,800 1,798
Jumlah Harga Bahan 3,280,808
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 3,555,808
2.01.01.07.02.005 Pekerjaan Pemasangan Wastafel unit 956,150
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.060 OH 200,000 12,000
1.10.28.02.01.001.002 Kepala Tukang 0.150 OH 150,000 22,500
1.10.28.02.01.001.004 Tukang 1.450 OH 150,000 217,500
1.10.28.02.01.002.001 Pekerja 1.200 OH 100,000 120,000
Jumlah Harga Tenaga Kerja 372,000
Bahan
1.1.7.01.01.01.022.00172 Wastafel 1.120 unit 514,600 576,352
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 6.000 kg 1,000 6,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.010 m3 179,800 1,798
Jumlah Harga Bahan 584,150
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 956,150
2.01.01.07.02.006 Pekerjaan Pemasangan Bak Mandi Fiberglass unit 1,949,300
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.900 OH 200,000 180,000
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.004 Tukang 4.500 OH 150,000 675,000

131
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.002.001 Pekerja 3.000 OH 100,000 300,000
Jumlah Harga Tenaga Kerja 1,162,500
Bahan
1.1.7.01.01.01.022.00191 Bak Mandi Fiberglass - Vol. 1 m3 1.120 unit 702,500 786,800
Jumlah Harga Bahan 786,800
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,949,300
2.01.01.07.02.009 Pekerjaan Pemasangan Bak Cuci Piring Stainless Steel + Accesories unit 333,358
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.015 OH 200,000 3,000
1.10.28.02.01.001.002 Kepala Tukang 0.030 OH 150,000 4,500
1.10.28.02.01.001.004 Tukang 0.300 OH 150,000 45,000
1.10.28.02.01.002.001 Pekerja 0.030 OH 100,000 3,000
Jumlah Harga Tenaga Kerja 55,500
Bahan
1.1.7.01.01.01.022.00188 Bak Cuci Piring Stainless Steel - 1 bowl + wing Uk. 95 x 45 cm 1.000 unit 222,500 222,500
1.1.7.01.01.01.022.00194 Water Drain 1.000 set 10,700 10,700
1.1.7.01.01.01.022.00346 Kran Air Stainless Steel - Dia. 1/2 - 3/4 inch. 1.000 set 33,100 33,100
1.1.7.01.01.01.022.00471 Sealtape 0.025 buah 3,900 98
1.1.7.01.01.01.022.00268 Silicon Sealant Netral - 300 ml 0.300 kg 38,200 11,460
Jumlah Harga Bahan 277,858
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 333,358
2.01.01.07.02.010 Pekerjaan Pemasangan Floor Drain unit 28,100
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.004 Tukang 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.010 OH 100,000 1,000
Jumlah Harga Tenaga Kerja 18,500
Bahan
1.1.7.01.01.01.022.00195 Floor Drain Stainless Steel - Uk. 11.5 x 11.5 cm 1.000 unit 9,600 9,600
Jumlah Harga Bahan 9,600
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 28,100
2.01.01.07.02.011 Pekerjaan Pemasangan Bak Kontrol Pasangan Batu Bata Merah unit 474,305
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.011 OH 200,000 2,200
1.10.28.02.01.001.002 Kepala Tukang 0.072 OH 150,000 10,800
1.10.28.02.01.001.006 Tukang Batu 0.720 OH 150,000 108,000
1.10.28.02.01.002.001 Pekerja 2.160 OH 100,000 216,000
Jumlah Harga Tenaga Kerja 337,000
Bahan
1.1.7.01.01.01.005.00010 Bata Merah 40.000 buah 800 32,000
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 44.000 kg 1,000 44,000
1.1.7.01.01.01.004.00002 Pasir Pasang 0.070 m3 179,800 12,586
1.1.7.01.01.01.004.00001 Pasir Beton 0.060 m3 230,400 13,824
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.070 m3 258,500 18,095
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 1.600 kg 10,500 16,800

132
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Bahan 137,305
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 474,305
2.01.01.07.02.014 Pekerjaan Pemasangan Pipa Galvanis Diameter 1/2 inch m' 84,731
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.027 OH 200,000 5,400
1.10.28.02.01.001.002 Kepala Tukang 0.009 OH 150,000 1,350
1.10.28.02.01.001.009 Tukang Pipa 0.090 OH 150,000 13,500
1.10.28.02.01.002.001 Pekerja 0.054 OH 100,000 5,400
Jumlah Harga Tenaga Kerja 25,650
Bahan
1.1.7.02.02.07.001.00001 Pipa Galvanis - Medium Dia. 1/2 inch. Pjg. 600 cm, tbl. 2.6 mm 0.258 batang 228,700 59,081
Jumlah Harga Bahan 59,081
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 84,731
2.01.01.07.02.015 Pekerjaan Pemasangan Pipa Galvanis Diameter 3/4 inch m' 100,593
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.027 OH 200,000 5,400
1.10.28.02.01.001.002 Kepala Tukang 0.009 OH 150,000 1,350
1.10.28.02.01.001.009 Tukang Pipa 0.090 OH 150,000 13,500
1.10.28.02.01.002.001 Pekerja 0.054 OH 100,000 5,400
Jumlah Harga Tenaga Kerja 25,650
Bahan
1.1.7.02.02.07.001.00002 Pipa Galvanis - Medium Dia. 3/4 inch. Pjg. 600 cm, tbl. 2.6 mm 0.258 batang 290,100 74,943
Jumlah Harga Bahan 74,943
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 100,593
2.01.01.07.02.016 Pekerjaan Pemasangan Pipa Galvanis Diameter 1 inch m' 138,335
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.027 OH 200,000 5,400
1.10.28.02.01.001.002 Kepala Tukang 0.009 OH 150,000 1,350
1.10.28.02.01.001.009 Tukang Pipa 0.090 OH 150,000 13,500
1.10.28.02.01.002.001 Pekerja 0.054 OH 100,000 5,400
Jumlah Harga Tenaga Kerja 25,650
Bahan
1.1.7.02.02.07.001.00003 Pipa Galvanis - Medium Dia. 1 inch. Pjg. 600 cm, tbl. 3.2 mm 0.258 batang 436,200 112,685
Jumlah Harga Bahan 112,685
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 138,335
2.01.01.07.02.017 Pekerjaan Pemasangan Pipa Galvanis Diameter 1 1/2 inch m' 210,269
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.018 OH 150,000 2,700
1.10.28.02.01.001.009 Tukang Pipa 0.180 OH 150,000 27,000
1.10.28.02.01.002.001 Pekerja 0.108 OH 100,000 10,800
Jumlah Harga Tenaga Kerja 41,500
Bahan
1.1.7.02.02.07.001.00005 Pipa Galvanis - Medium Dia. 1 1/2 inch. Pjg. 600 cm, tbl. 3.2 mm 0.258 batang 653,300 168,769

133
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Bahan 168,769
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 210,269
2.01.01.07.02.018 Pekerjaan Pemasangan Pipa Galvanis Diameter 3 inch m' 426,115
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.007 OH 200,000 1,400
1.10.28.02.01.001.002 Kepala Tukang 0.023 OH 150,000 3,450
1.10.28.02.01.001.009 Tukang Pipa 0.225 OH 150,000 33,750
1.10.28.02.01.002.001 Pekerja 0.135 OH 100,000 13,500
Jumlah Harga Tenaga Kerja 52,100
Bahan
1.1.7.02.02.07.001.00008 Pipa Galvanis - Medium Dia. 3 inch. Pjg. 600 cm, tbl. 4 mm 0.258 batang 1,447,800 374,015
Jumlah Harga Bahan 374,015
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 426,115
2.01.01.07.02.019 Pekerjaan Pemasangan Pipa Galvanis Diameter 4 inch m' 591,629
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.007 OH 200,000 1,400
1.10.28.02.01.001.002 Kepala Tukang 0.023 OH 150,000 3,450
1.10.28.02.01.001.009 Tukang Pipa 0.225 OH 150,000 33,750
1.10.28.02.01.002.001 Pekerja 0.135 OH 100,000 13,500
Jumlah Harga Tenaga Kerja 52,100
Bahan
1.1.7.02.02.07.001.00009 Pipa Galvanis - Medium Dia. 4 inch. Pjg. 600 cm, tbl. 4.5 mm 0.258 batang 2,088,500 539,529
Jumlah Harga Bahan 539,529
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 591,629
2.01.01.07.02.020 Pekerjaan Pemasangan Kran Air unit 85,298
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.007 OH 200,000 1,400
1.10.28.02.01.001.002 Kepala Tukang 0.023 OH 150,000 3,450
1.10.28.02.01.001.009 Tukang Pipa 0.225 OH 150,000 33,750
1.10.28.02.01.002.001 Pekerja 0.135 OH 100,000 13,500
Jumlah Harga Tenaga Kerja 52,100
Bahan
1.1.7.01.01.01.022.00346 Kran Air Stainless Steel - Dia. 1/2 - 3/4 inch. 1.000 unit 33,100 33,100
1.1.7.01.01.01.022.00471 Sealtape 0.025 buah 3,900 98
Jumlah Harga Bahan 33,198
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 85,298
2.01.01.07.02.021 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1/2 inch m' 26,959
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.002 OH 200,000 400
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 900
1.10.28.02.01.001.009 Tukang Pipa 0.060 OH 150,000 9,000
1.10.28.02.01.002.001 Pekerja 0.036 OH 100,000 3,600
Jumlah Harga Tenaga Kerja 13,900
Bahan

134
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.02.02.06.001.00001 Pipa PVC - Type AW Dia. 1/2 inch. pjg. 400 cm 0.388 batang 33,700 13,059
Jumlah Harga Bahan 13,059
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 26,959
2.01.01.07.02.022 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 3/4 inch m' 29,826
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.002 OH 200,000 400
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 900
1.10.28.02.01.001.009 Tukang Pipa 0.060 OH 150,000 9,000
1.10.28.02.01.002.001 Pekerja 0.036 OH 100,000 3,600
Jumlah Harga Tenaga Kerja 13,900
Bahan
1.1.7.02.02.06.001.00002 Pipa PVC - Type AW Dia. 3/4 inch. pjg. 400 cm 0.388 batang 41,100 15,926
Jumlah Harga Bahan 15,926
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 29,826
2.01.01.07.02.023 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1 inch m' 33,973
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.002 OH 200,000 400
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 900
1.10.28.02.01.001.009 Tukang Pipa 0.060 OH 150,000 9,000
1.10.28.02.01.002.001 Pekerja 0.036 OH 100,000 3,600
Jumlah Harga Tenaga Kerja 13,900
Bahan
1.1.7.02.02.06.001.00003 Pipa PVC - Type AW Dia. 1 inch. pjg. 400 cm 0.388 batang 51,800 20,073
Jumlah Harga Bahan 20,073
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 33,973
2.01.01.07.02.024 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1 1/2 inch m' 57,856
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.009 OH 150,000 1,350
1.10.28.02.01.001.009 Tukang Pipa 0.090 OH 150,000 13,500
1.10.28.02.01.002.001 Pekerja 0.054 OH 100,000 5,400
Jumlah Harga Tenaga Kerja 20,850
Bahan
1.1.7.02.02.06.001.00005 Pipa PVC - Type AW Dia. 1 1/2 inch. pjg. 400 cm 0.388 batang 95,500 37,006
Jumlah Harga Bahan 37,006
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 57,856
2.01.01.07.02.025 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 2 inch m' 75,798
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.009 OH 150,000 1,350
1.10.28.02.01.001.009 Tukang Pipa 0.090 OH 150,000 13,500
1.10.28.02.01.002.001 Pekerja 0.054 OH 100,000 5,400
Jumlah Harga Tenaga Kerja 20,850
Bahan

135
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.02.02.06.001.00006 Pipa PVC - Type AW Dia. 2 inch. pjg. 400 cm 0.388 batang 141,800 54,948
Jumlah Harga Bahan 54,948
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 75,798
2.01.01.07.02.026 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 2 1/2 inch m' 101,778
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.014 OH 150,000 2,025
1.10.28.02.01.001.009 Tukang Pipa 0.135 OH 150,000 20,250
1.10.28.02.01.002.001 Pekerja 0.081 OH 100,000 8,100
Jumlah Harga Tenaga Kerja 31,175
Bahan
1.1.7.02.02.06.001.00007 Pipa PVC - Type AW Dia. 2 1/2 inch. pjg. 400 cm 0.388 batang 182,200 70,603
Jumlah Harga Bahan 70,603
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 101,778
2.01.01.07.02.027 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 3 inch m' 131,848
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.014 OH 150,000 2,025
1.10.28.02.01.001.009 Tukang Pipa 0.135 OH 150,000 20,250
1.10.28.02.01.002.001 Pekerja 0.081 OH 100,000 8,100
Jumlah Harga Tenaga Kerja 31,175
Bahan
1.1.7.02.02.06.001.00008 Pipa PVC - Type AW Dia. 3 inch. pjg. 400 cm 0.388 batang 259,800 100,673
Jumlah Harga Bahan 100,673
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 131,848
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch m' 177,921
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.014 OH 150,000 2,025
1.10.28.02.01.001.009 Tukang Pipa 0.135 OH 150,000 20,250
1.10.28.02.01.002.001 Pekerja 0.081 OH 100,000 8,100
Jumlah Harga Tenaga Kerja 31,175
Bahan
1.1.7.02.02.06.001.00009 Pipa PVC - Type AW Dia. 4 inch. pjg. 400 cm 0.388 batang 378,700 146,746
Jumlah Harga Bahan 146,746
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 177,921
2.01.01.07.02.036 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 6 inch m' 337,068
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.014 OH 150,000 2,025
1.10.28.02.01.001.009 Tukang Pipa 0.135 OH 150,000 20,250
1.10.28.02.01.002.001 Pekerja 0.081 OH 100,000 8,100
Jumlah Harga Tenaga Kerja 31,175
Bahan

136
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.02.02.06.001.00011 Pipa PVC - Type AW Dia. 6 inch. pjg. 400 cm 0.388 batang 789,400 305,893
Jumlah Harga Bahan 305,893
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 337,068
2.01.01.07.02.029 Pekerjaan Pemasangan Pipa PVC Type D Diameter 2 inch m' 47,123
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.009 OH 150,000 1,350
1.10.28.02.01.001.009 Tukang Pipa 0.090 OH 150,000 13,500
1.10.28.02.01.002.001 Pekerja 0.054 OH 100,000 5,400
Jumlah Harga Tenaga Kerja 20,850
Bahan
1.1.7.02.02.06.001.00040 Pipa PVC - Type D Dia. 2 inch. pjg. 400 cm 0.388 batang 67,800 26,273
Jumlah Harga Bahan 26,273
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 47,123
2.01.01.07.02.030 Pekerjaan Pemasangan Pipa PVC Type D Diameter 3 inch m' 87,595
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.014 OH 150,000 2,025
1.10.28.02.01.001.009 Tukang Pipa 0.135 OH 150,000 20,250
1.10.28.02.01.002.001 Pekerja 0.081 OH 100,000 8,100
Jumlah Harga Tenaga Kerja 31,175
Bahan
1.1.7.02.02.06.001.00042 Pipa PVC - Type D Dia. 3 inch. pjg. 400 cm 0.388 batang 145,600 56,420
Jumlah Harga Bahan 56,420
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 87,595
2.01.01.07.02.031 Pekerjaan Pemasangan Pipa PVC Type D Diameter 4 inch m' 110,496
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.014 OH 150,000 2,025
1.10.28.02.01.001.009 Tukang Pipa 0.135 OH 150,000 20,250
1.10.28.02.01.002.001 Pekerja 0.081 OH 100,000 8,100
Jumlah Harga Tenaga Kerja 31,175
Bahan
1.1.7.02.02.06.001.00043 Pipa PVC - Type D Dia. 4 inch. pjg. 400 cm 0.388 batang 204,700 79,321
Jumlah Harga Bahan 79,321
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 110,496
2.01.01.07.02.032 Pekerjaan Pemasangan Shower Set unit 275,995
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.007 OH 200,000 1,400
1.10.28.02.01.001.002 Kepala Tukang 0.023 OH 150,000 3,450
1.10.28.02.01.001.009 Tukang Pipa 0.225 OH 150,000 33,750
1.10.28.02.01.002.001 Pekerja 0.135 OH 100,000 13,500
Jumlah Harga Tenaga Kerja 52,100
Bahan

137
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.022.00164 Shower Set Stainless Steel - Shower + Flexi Hose Pipe + Kran Air 1.000 set 223,700 223,700
1.1.7.01.01.01.022.00471 Sealtape 0.050 buah 3,900 195
Jumlah Harga Bahan 223,895
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 275,995
2.01.01.07.02.037 Pekerjaan Pemasangan Tee Pipa PVC Type D Diameter 4 inch unit 156,640
Tenaga Kerja
1.10.28.02.01.001.009 Tukang Pipa 0.017 OH 150,000 2,550
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 77,550
Bahan
1.1.7.02.02.07.001.00227 Tee Pipa PVC - Type D Dia. 4 inch 1.100 unit 67,400 74,140
1.1.7.01.01.01.022.00278 Lem PVC 0.100 tube 49,500 4,950
Jumlah Harga Bahan 79,090
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 156,640
2.01.01.07.02.038 Pekerjaan Pemasangan Elbow Pipa PVC Type D Diameter 4 inch unit 116,490
Tenaga Kerja
1.10.28.02.01.001.009 Tukang Pipa 0.017 OH 150,000 2,550
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 77,550
Bahan
1.1.7.02.02.07.001.00248 Elbow Pipa PVC - Type D Dia. 4 inch 1.100 unit 30,900 33,990
1.1.7.01.01.01.022.00278 Lem PVC 0.100 tube 49,500 4,950
Jumlah Harga Bahan 38,940
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 116,490
2.01.01.07.02.039 Pekerjaan Pemasangan Socket Pipa PVC Type D Diameter 4 inch unit 101,310
Tenaga Kerja
1.10.28.02.01.001.009 Tukang Pipa 0.017 OH 150,000 2,550
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 77,550
Bahan
1.1.7.02.02.07.001.00159 Socket Pipa PVC - Type D Dia. 4 inch 1.100 unit 17,100 18,810
1.1.7.01.01.01.022.00278 Lem PVC 0.100 tube 49,500 4,950
Jumlah Harga Bahan 23,760
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 101,310
2.01.01.07.02.040 Pekerjaan Pemasangan Valve Pipa PVC Type D Diameter 4 inch unit 226,349
Tenaga Kerja
1.10.28.02.01.001.009 Tukang Pipa 0.017 OH 150,000 2,550
1.10.28.02.01.002.001 Pekerja 1.500 OH 100,000 150,000
Jumlah Harga Tenaga Kerja 152,550
Bahan
1.1.7.02.02.06.001.00105 Valve Pipa PVC - Type D Dia. 4 inch 1.100 unit 62,590 68,849
1.1.7.01.01.01.022.00278 Lem PVC 0.100 tube 49,500 4,950
Jumlah Harga Bahan 73,799
Peralatan

138
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 226,349
2.01.01.07.02.041 Pekerjaan Pemasangan Blank Flanged Diameter 4 inch unit 203,773
Tenaga Kerja
1.10.28.02.01.001.009 Tukang Pipa 0.017 OH 150,000 2,550
1.10.28.02.01.002.001 Pekerja 1.100 OH 100,000 110,000
Jumlah Harga Tenaga Kerja 112,550
Bahan
1.1.7.02.02.07.001.00346 Blank Flanged Pipa PVC - Type D Dia. 4 inch 1.100 unit 78,430 86,273
1.1.7.01.01.01.022.00278 Lem PVC 0.100 tube 49,500 4,950
Jumlah Harga Bahan 91,223
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 203,773
2.01.01.07.03 PEKERJAAN BESI DAN ALUMUNIUM
2.01.01.07.03.001 Pekerjaan Pemasangan Besi Profil kg 37,085
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 900
1.10.28.02.01.001.008 Tukang Besi 0.060 OH 150,000 9,000
1.10.28.02.01.002.001 Pekerja 0.060 OH 100,000 6,000
Jumlah Harga Tenaga Kerja 16,500
Bahan
1.1.7.01.01.01.008.00040 Besi Profil 1.150 kg 17,900 20,585
Jumlah Harga Bahan 20,585
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 37,085
2.01.01.07.03.004 Pekerjaan Perakitan Besi Profil 100 kg 53,640
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.001 OH 150,000 150
1.10.28.02.01.001.008 Tukang Besi 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 26,150
Bahan
1.1.7.01.01.04.001.00006 Solar Industri 1.000 liter 8,800 8,800
1.1.7.01.01.04.002.00001 Minyak Pelumas 0.100 liter 16,900 1,690
1.1.7.01.01.01.022.00126 Mur Baut - Uk. 10 cm 10.000 buah 1,700 17,000
Jumlah Harga Bahan 27,490
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 53,640
2.01.01.07.03.005 Pekerjaan Pengelasan dengan Las Listrik cm 2,766
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0002 OH 200,000 40
1.10.28.02.01.001.002 Kepala Tukang 0.0002 OH 150,000 30
1.10.28.02.01.001.008 Tukang Besi 0.002 OH 150,000 300
1.10.28.02.01.002.001 Pekerja 0.004 OH 100,000 400
Jumlah Harga Tenaga Kerja 770
Bahan
1.1.7.01.01.05.001.00019 Kawat Las Elektroda - Dia. 2 mm, pjg. 300 mm 0.040 kg 41,600 1,664

139
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.04.001.00006 Solar Industri 0.030 liter 8,800 264
1.1.7.01.01.04.002.00001 Minyak Pelumas 0.004 liter 16,900 68
Jumlah Harga Bahan 1,996
Peralatan
9.1.2.10.07.01.001.00094 Las Listrik - 900 watt 0.017 jam 110,462 1,878
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 2,766
2.01.01.07.03.006 Pekerjaan Pemasangan Rangka Hollow Dinding Partisi m2 132,880
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.013 OH 200,000 2,600
1.10.28.02.01.001.002 Kepala Tukang 0.025 OH 150,000 3,750
1.10.28.02.01.001.008 Tukang Besi 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.250 OH 100,000 25,000
Jumlah Harga Tenaga Kerja 68,850
Bahan
1.1.7.01.01.01.022.00220 Rangka Hollow - Uk. 40 x 40 x 2 mm 1.900 batang 33,700 64,030
Jumlah Harga Bahan 64,030
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 132,880
2.01.01.07.03.007 Pekerjaan Pembuatan Kusen Alumunium 4 inch m' 204,380
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.002 OH 200,000 400
1.10.28.02.01.001.002 Kepala Tukang 0.004 OH 150,000 600
1.10.28.02.01.001.008 Tukang Besi 0.043 OH 150,000 6,450
1.10.28.02.01.002.001 Pekerja 0.043 OH 100,000 4,300
Jumlah Harga Tenaga Kerja 11,750
Bahan
1.1.7.01.01.01.022.00070 Kusen Alumunium Profil - Uk. 4 inch. 1.000 m' 191,100 191,100
1.1.7.01.01.01.022.00478 Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm 0.015 kg 69,630 1,044
1.1.7.01.01.01.022.00280 Lem Plastic Steel Epoxy - 48 gr 0.003 kg 168,600 486
Jumlah Harga Bahan 192,630
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 204,380
2.01.01.07.03.008 Pekerjaan Pembuatan Kusen Alumunium 3 inch m' 108,780
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.002 OH 200,000 400
1.10.28.02.01.001.002 Kepala Tukang 0.004 OH 150,000 600
1.10.28.02.01.001.008 Tukang Besi 0.043 OH 150,000 6,450
1.10.28.02.01.002.001 Pekerja 0.043 OH 100,000 4,300
Jumlah Harga Tenaga Kerja 11,750
Bahan
1.1.7.01.01.01.022.00069 Kusen Alumunium Profil - Uk. 3 inch. 1.000 m' 95,500 95,500
1.1.7.01.01.01.022.00478 Baut Sekrup - Uk. 1/2 - 3/4 inch. Dia. 3 mm 0.015 kg 69,630 1,044
1.1.7.01.01.01.022.00280 Lem Plastic Steel Epoxy - 48 gr 0.003 kg 168,600 486
Jumlah Harga Bahan 97,030
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 108,780
2.01.01.07.03.009 Pekerjaan Pemasangan Rangka Atap Galvalum Genteng Asbes/Spandek m2 222,020
Tenaga Kerja

140
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.008 Tukang Besi 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.400 OH 100,000 40,000
Jumlah Harga Tenaga Kerja 57,500
Bahan
1.1.7.01.01.01.022.00213 Kanal Galvalum - Profil C75 Uk. 80 x 30 mm, 600 cm 0.600 batang 93,300 55,980
1.1.7.01.01.01.022.00216 Reng Galvalum - T. 30, tbl. 0.45 mm, 600 cm 0.600 batang 46,100 27,660
1.1.7.01.01.01.022.00223 Talang Galvalum - Lbr. 90 cm, tbl. 0.30 mm 0.124 m' 45,000 5,580
1.1.7.01.01.01.022.00521 Sekrup Galvalum - Self Drilling Screw (SDS) 0.600 kg 93,500 56,100
1.1.7.01.01.01.022.00544 Dynabolt 1.600 buah 12,000 19,200
Jumlah Harga Bahan 164,520
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 222,020
2.01.01.07.03.010 Pekerjaan Pemasangan Rangka Atap Galvalum Genteng Biasa/Metal m2 263,900
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.008 Tukang Besi 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.400 OH 100,000 40,000
Jumlah Harga Tenaga Kerja 57,500
Bahan
1.1.7.01.01.01.022.00213 Kanal Galvalum - Profil C75 Uk. 80 x 30 mm, 600 cm 0.600 batang 93,300 55,980
1.1.7.01.01.01.022.00216 Reng Galvalum - T. 30, tbl. 0.45 mm, 600 cm 0.900 batang 46,100 41,490
1.1.7.01.01.01.022.00223 Talang Galvalum - Lbr. 90 cm, tbl. 0.30 mm 0.124 m' 45,000 5,580
1.1.7.01.01.01.022.00521 Sekrup Galvalum - Self Drilling Screw (SDS) 0.900 kg 93,500 84,150
1.1.7.01.01.01.022.00544 Dynabolt 1.600 buah 12,000 19,200
Jumlah Harga Bahan 206,400
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 263,900
2.01.01.07.03.011 Pekerjaan Pemasangan Rangka Hollow Plafon m2 163,750
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.018 OH 200,000 3,600
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.008 Tukang Besi 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.350 OH 100,000 35,000
Jumlah Harga Tenaga Kerja 96,350
Bahan
1.1.7.01.01.01.022.00220 Rangka Hollow - Uk. 40 x 40 x 2 mm 2.000 batang 33,700 67,400
Jumlah Harga Bahan 67,400
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 163,750
2.01.01.07.03.012 Pekerjaan Pemasangan Pintu Kaca Rangka Alumunium m2 973,879
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.009 OH 150,000 1,350
1.10.28.02.01.001.008 Tukang Allumunium/Kaca 0.085 OH 150,000 12,750
1.10.28.02.01.002.001 Pekerja 0.085 OH 100,000 8,500
Jumlah Harga Tenaga Kerja 23,600

141
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
1.1.7.01.01.01.022.00070 Kusen Alumunium Profil - Uk. 4 inch. 4.400 m' 191,100 840,840
1.1.7.01.01.01.003.00005 Kaca Rayben - Tbl. 6 mm 0.680 m2 89,900 61,132
1.1.7.01.01.01.022.00525 Silicone Rubber Sealent 0.270 Tube 178,915 48,307
Jumlah Harga Bahan 950,279
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 973,879
2.01.01.07.03.013 Pekerjaan Pemasangan Pintu Alumunium Strip m2 1,401,728
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0042 OH 200,000 840
1.10.28.02.01.001.002 Kepala Tukang 0.0085 OH 150,000 1,275
1.10.28.02.01.001.008 Tukang Allumunium/Kaca 0.085 OH 150,000 12,750
1.10.28.02.01.002.001 Pekerja 0.085 OH 100,000 8,500
Jumlah Harga Tenaga Kerja 23,365
Bahan
1.1.7.01.01.01.022.00070 Kusen Alumunium Profil - Uk. 4 inch. 4.400 m' 191,100 840,840
1.1.7.01.01.01.022.00476 Alumiunium Strip - Lbr. 8 cm 14.600 m' 36,667 535,338
1.1.7.01.01.01.022.00280 Lem Plastic Steel Epoxy - 48 gr 0.013 kg 168,600 2,185
Jumlah Harga Bahan 1,378,363
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,401,728
2.01.01.07.03.014 Pekerjaan Pemasangan Rolling Door Besi/Galvalum m2 712,600
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.006 OH 200,000 1,200
1.10.28.02.01.001.002 Kepala Tukang 0.120 OH 150,000 18,000
1.10.28.02.01.001.013 Tukang Las 1.200 OH 150,000 180,000
1.10.28.02.01.002.001 Pekerja 1.200 OH 100,000 120,000
Jumlah Harga Tenaga Kerja 319,200
Bahan
1.1.7.01.01.01.022.00045 Rolling Door Besi/Galvalum 1.000 m2 393,400 393,400
Jumlah Harga Bahan 393,400
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 712,600
2.01.01.07.03.015 Pekerjaan Pemasangan Rolling Door Alumunium m2 808,900
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.050 OH 200,000 10,000
1.10.28.02.01.001.002 Kepala Tukang 0.100 OH 150,000 15,000
1.10.28.02.01.001.008 Tukang Allumunium/Kaca 1.000 OH 150,000 150,000
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 275,000
Bahan
1.1.7.01.01.01.022.00046 Rolling Door Alumunium 1.000 m2 533,900 533,900
Jumlah Harga Bahan 533,900
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 808,900
2.01.01.07.03.016 Pekerjaan Pemasangan Folding Door Besi/Galvalum m2 561,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.022 OH 200,000 4,400

142
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.002 Kepala Tukang 0.044 OH 150,000 6,600
1.10.28.02.01.001.004 Tukang 0.440 OH 150,000 66,000
1.10.28.02.01.002.001 Pekerja 0.440 OH 100,000 44,000
Jumlah Harga Tenaga Kerja 121,000
Bahan
1.1.7.01.01.01.022.00497 Folding Door Besi/Galvalum - tbl. 4 mm 1.000 m2 440,000 440,000
Jumlah Harga Bahan 440,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 561,000
2.01.01.07.03.034 Pekerjaan Pemasangan Folding Door Alumunium m2 506,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.022 OH 200,000 4,400
1.10.28.02.01.001.002 Kepala Tukang 0.044 OH 150,000 6,600
1.10.28.02.01.001.004 Tukang 0.440 OH 150,000 66,000
1.10.28.02.01.002.001 Pekerja 0.440 OH 100,000 44,000
Jumlah Harga Tenaga Kerja 121,000
Bahan
1.1.7.01.01.01.022.00496 Folding Door Alumunium - tbl. 6 mm 1.000 m2 385,000 385,000
Jumlah Harga Bahan 385,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 506,000
2.01.01.07.03.035 Pekerjaan Pemasangan Folding Door PVC m2 2,156,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.022 OH 200,000 4,400
1.10.28.02.01.001.002 Kepala Tukang 0.044 OH 150,000 6,600
1.10.28.02.01.001.004 Tukang 0.440 OH 150,000 66,000
1.10.28.02.01.002.001 Pekerja 0.440 OH 100,000 44,000
Jumlah Harga Tenaga Kerja 121,000
Bahan
1.1.7.01.01.01.022.00498 Folding Door PVC Solid 1.000 m2 2,035,000 2,035,000
Jumlah Harga Bahan 2,035,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 2,156,000
2.01.01.07.03.017 Pekerjaan Pemasangan Jendela Nako dan Teralis m2 2,203,498
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 200
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.004 Tukang 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.200 OH 100,000 20,000
Jumlah Harga Tenaga Kerja 53,200
Bahan
1.1.7.01.01.01.022.00500 Jendela Nako - Rangka lbr. 80 cm + Kaca lbr. 10 cm, tbl. 5 mm) 1.100 m2 1,925,000 2,117,500
1.1.7.01.01.01.022.00521 Sekrup Galvalum - Self Drilling Screw (SDS) 0.300 kg 93,500 28,050
1.1.7.01.01.01.008.00027 Besi Strip - Uk. 2 x 3 mm 0.330 m' 14,400 4,748
Jumlah Harga Bahan 2,150,298
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 2,203,498
2.01.01.07.03.018 Pekerjaan Pemasangan Terali Besi Strip m2 637,463

143
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.083 OH 200,000 16,600
1.10.28.02.01.001.002 Kepala Tukang 0.167 OH 150,000 25,050
1.10.28.02.01.001.013 Tukang Las 1.670 OH 150,000 250,500
1.10.28.02.01.002.001 Pekerja 1.670 OH 100,000 167,000
Jumlah Harga Tenaga Kerja 459,150
Bahan
1.1.7.01.01.01.008.00027 Besi Strip - Uk. 2 x 3 mm 6.177 kg 14,400 88,949
2.01.01.07.03.005 Pengelasan 27.080 cm 3,300 89,364
Jumlah Harga Bahan 178,313
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 637,463
2.01.01.07.03.019 Pekerjaan Pemasangan Talang Datar/Jurai Seng m' 184,115
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 200
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.013 Tukang Las 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.200 OH 100,000 20,000
Jumlah Harga Tenaga Kerja 53,200
Bahan
1.1.7.01.01.01.007.00009 Seng Plat - BJLS 28 lbr. 90 cm, tbl. 3 mm 0.260 lembar 50,600 13,156
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.015 kg 20,200 303
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.019 m3 6,181,900 117,456
Jumlah Harga Bahan 130,915
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 184,115
2.01.01.07.03.020 Pekerjaan Pemasangan Talang Miring Seng m' 184,115
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 200
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.013 Tukang Las 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.200 OH 100,000 20,000
Jumlah Harga Tenaga Kerja 53,200
Bahan
1.1.7.01.01.01.007.00009 Seng Plat - BJLS 28 lbr. 90 cm, tbl. 3 mm 0.260 lembar 50,600 13,156
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.015 kg 20,200 303
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.019 m3 6,181,900 117,456
Jumlah Harga Bahan 130,915
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 184,115
2.01.01.07.03.021 Pekerjaan Pemasangan Talang 1/2 Lingkarang m' 90,020
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 200
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000
1.10.28.02.01.001.013 Tukang Las 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.200 OH 100,000 20,000
Jumlah Harga Tenaga Kerja 53,200
Bahan
1.1.7.01.01.01.007.00010 Seng Plat - BJLS 30 1/2 Lingkaran Dia. 15 cm, tbl. 6 mm 0.260 lembar 39,300 10,218

144
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.010 kg 20,200 202
1.1.7.01.01.01.008.00010 Plat Strip - Uk. 0.3 x 2 cm 0.500 kg 52,800 26,400
Jumlah Harga Bahan 36,820
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 90,020
2.01.01.07.03.023 Pekerjaan Pemasangan Sunscreen m2 472,810
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.080 OH 150,000 12,000
1.10.28.02.01.001.004 Tukang 0.800 OH 150,000 120,000
1.10.28.02.01.002.001 Pekerja 0.080 OH 100,000 8,000
Jumlah Harga Tenaga Kerja 140,800
Bahan
1.1.7.01.01.01.003.00018 Sunscreen Alumunium (Pre-fabricated) 1.050 m2 316,200 332,010
Jumlah Harga Bahan 332,010
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 472,810
2.01.01.07.03.024 Pekerjaan Pemasangan Vertical/Venetion Blind m2 255,005
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.018 OH 200,000 3,600
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.004 Tukang 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.350 OH 100,000 35,000
Jumlah Harga Tenaga Kerja 96,350
Bahan
1.1.7.01.01.01.003.00015 Vertical/Venetian Blind Alumunium (Pre-fabricated) 1.050 m2 151,100 158,655
Jumlah Harga Bahan 158,655
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 255,005
2.01.01.07.03.025 Pekerjaan Pemasangan Kawat Nyamuk m2 276,198
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.018 OH 200,000 3,600
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.013 Tukang Las 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.350 OH 100,000 35,000
Jumlah Harga Tenaga Kerja 96,350
Bahan
1.1.7.01.01.05.001.00011 Kawat Nyamuk Alumunium 1.100 m2 47,800 52,580
2.01.01.07.03.005 Pengelasan 11.110 cm 3,300 36,663
1.1.7.01.01.01.008.00010 Plat Strip - Uk. 0.3 x 2 cm 1.716 kg 52,800 90,605
Jumlah Harga Bahan 179,848
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 276,198
2.01.01.07.03.026 Pekerjaan Pemasangan Pagar Besi BRC m2 400,190
Tenaga Kerja
1.10.28.02.01.001.008 Tukang Besi 1.050 OH 150,000 157,500
1.10.28.02.01.002.001 Pekerja 1.050 OH 100,000 105,000
Jumlah Harga Tenaga Kerja 262,500

145
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
1.1.7.01.01.01.022.00061 Panel Pagar Besi BRC - Uk. 240 x 120 cm, dia. 6 mm (Pre-fabricated) 0.350 unit 393,400 137,690
Jumlah Harga Bahan 137,690
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 400,190
2.01.01.07.03.027 Pekerjaan Pemasangan Tiang Pagar Besi BRC titik 422,000
Tenaga Kerja
1.10.28.02.01.001.008 Tukang Besi 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.500 OH 100,000 50,000
Jumlah Harga Tenaga Kerja 125,000
Bahan
1.1.7.02.02.07.001.00347 Pipa Besi BRC - Tinggi 120 cm, dia. 2 inch. (Pre-fabricated) 1.000 unit 297,000 297,000
Jumlah Harga Bahan 297,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 422,000
2.01.01.07.03.028 Pekerjaan Pemasangan Daun Pintu Besi BRC Swing Ganda m2 388,388
Tenaga Kerja
1.10.28.02.01.001.008 Tukang Besi 1.050 OH 150,000 157,500
1.10.28.02.01.002.001 Pekerja 1.050 OH 100,000 105,000
Jumlah Harga Tenaga Kerja 262,500
Bahan
1.1.7.01.01.01.022.00052 Pintu Besi BRC - Doubel Swing Uk. 300 x 120 cm (Pre-fabricated) 0.280 unit 449,600 125,888
Jumlah Harga Bahan 125,888
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 388,388
2.01.01.07.03.029 Pekerjaan Pemasangan Railling Tangga Besi Hollow m' 261,889
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.008 Tukang Besi 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 29,050
Bahan
1.1.7.01.01.01.008.00069 Besi Hollow - Uk. 40 x 40 x 2 mm 1.035 batang 155,400 160,839
1.1.7.01.01.01.022.00126 Mur Baut - Uk. 10 cm 6.000 buah 1,700 10,200
1.1.7.01.01.01.006.00001 Cat Besi 1.000 kg 61,800 61,800
Jumlah Harga Bahan 232,839
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 261,889
2.01.01.07.03.030 Pekerjaan Pemasangan Kanopi Rangka Besi Hollow Penutup Atap Polycarbonate m2 900,590
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.008 Tukang Besi 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 29,050
Bahan
1.1.7.01.01.01.008.00069 Besi Hollow - Uk. 40 x 40 x 2 mm 1.724 batang 155,400 267,910

146
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.022.00291 Polycarbonate Twinlite - 6 mm 1.050 m2 200,600 210,630
1.1.7.01.01.01.022.00087 Skrup Asbes - Uk. 4 inch. (buah) 6.000 buah 61,800 370,800
1.1.7.01.01.01.022.00126 Mur Baut - Uk. 10 cm 6.000 buah 1,700 10,200
1.1.7.01.01.01.022.00544 Dynabolt 1.000 buah 12,000 12,000
Jumlah Harga Bahan 871,540
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 900,590
2.01.01.07.03.031 Pekerjaan Pembuatan dan Pemasangan Pagar Besi Hollow m2 479,988
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.052 OH 200,000 10,400
1.10.28.02.01.001.002 Kepala Tukang 0.105 OH 150,000 15,750
1.10.28.02.01.001.008 Tukang Besi 1.050 OH 150,000 157,500
1.10.28.02.01.002.001 Pekerja 1.050 OH 100,000 105,000
Jumlah Harga Tenaga Kerja 288,650
Bahan
1.1.7.01.01.01.008.00086 Besi Hollow - Uk. 40 x 40 x 1.2 mm 1.824 batang 104,900 191,338
Jumlah Harga Bahan 191,338
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 479,988
2.01.01.07.03.032 Pekerjaan Pembuatan dan Pemasangan Pagar Besi Tempa m2 676,430
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.052 OH 200,000 10,400
1.10.28.02.01.001.002 Kepala Tukang 0.105 OH 150,000 15,750
1.10.28.02.01.001.008 Tukang Besi 1.050 OH 150,000 157,500
1.10.28.02.01.002.001 Pekerja 1.050 OH 100,000 105,000
Jumlah Harga Tenaga Kerja 288,650
Bahan
1.1.7.01.01.01.008.00084 Besi Tempa 1.150 m2 337,200 387,780
Jumlah Harga Bahan 387,780
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 676,430
2.01.01.07.04 PEKERJAAN KUNCI DAN KACA
2.01.01.07.04.002 Pekerjaan Pemasangan Kunci Tanam Biasa unit 157,600
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.004 Tukang 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.010 OH 100,000 1,000
Jumlah Harga Tenaga Kerja 84,500
Bahan
1.1.7.01.01.01.022.00364 Kunci Tanam Biasa - Brass/Alumunium 1.000 buah 73,100 73,100
Jumlah Harga Bahan 73,100
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 157,600
2.01.01.07.04.004 Pekerjaan Pemasangan Kunci Silinder unit 151,000
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500

147
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.004 Tukang 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.005 OH 100,000 500
Jumlah Harga Tenaga Kerja 83,600
Bahan
1.1.7.01.01.01.022.00367 Kunci Silinder - Brass/Alumunium Uk. 60 mm 1.000 buah 67,400 67,400
Jumlah Harga Bahan 67,400
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 151,000
2.01.01.07.04.005 Pekerjaan Pemasangan Engsel Panel unit 77,350
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.015 OH 150,000 2,250
1.10.28.02.01.001.004 Tukang 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.015 OH 100,000 1,500
Jumlah Harga Tenaga Kerja 27,850
Bahan
1.1.7.01.01.01.022.00495 Engsel Panel - Besi/Alumunium 4 inch. 1.000 buah 49,500 49,500
Jumlah Harga Bahan 49,500
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 77,350
2.01.01.07.04.006 Pekerjaan Pemasangan Engsel Kupu-kupu unit 35,400
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.004 Tukang 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.010 OH 100,000 1,000
Jumlah Harga Tenaga Kerja 18,500
Bahan
1.1.7.01.01.01.022.00310 Engsel Kupu-kupu - Besi/Alumunium 2 inch. 1.000 buah 16,900 16,900
Jumlah Harga Bahan 16,900
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 35,400
2.01.01.07.04.011 Pekerjaan Pemasangan Door Closer unit 262,200
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.004 Tukang 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.050 OH 100,000 5,000
Jumlah Harga Tenaga Kerja 88,100
Bahan
1.1.7.01.01.01.022.00384 Door Closer - Besi/Alumunium 90 -180 degree berat pintu 40 - 65 kg 1.000 buah 174,100 174,100
Jumlah Harga Bahan 174,100
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 262,200
2.01.01.07.04.012 Pekerjaan Pemasangan Grendel unit 49,200
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 200
1.10.28.02.01.001.002 Kepala Tukang 0.020 OH 150,000 3,000

148
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.004 Tukang 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.020 OH 100,000 2,000
Jumlah Harga Tenaga Kerja 35,200
Bahan
1.1.7.01.01.01.022.00340 Grendel - Brass/Stainless Steel Uk. 6 inch. 1.000 buah 14,000 14,000
Jumlah Harga Bahan 14,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 49,200
2.01.01.07.04.013 Pekerjaan Pemasangan Door Holder unit 129,700
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.004 Tukang 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.050 OH 100,000 5,000
Jumlah Harga Tenaga Kerja 88,100
Bahan
1.1.7.01.01.01.022.00386 Door Holder - Besi/Alumunium berat pintu 45 - 60 kg 1.000 buah 41,600 41,600
Jumlah Harga Bahan 41,600
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 129,700
2.01.01.07.04.014 Pekerjaan Pemasangan Door Stopper unit 40,500
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.004 Tukang 0.100 OH 150,000 15,000
1.10.28.02.01.002.001 Pekerja 0.010 OH 100,000 1,000
Jumlah Harga Tenaga Kerja 18,500
Bahan
1.1.7.01.01.01.022.00385 Door Stopper - Besi/Alumunium berat pintu 45 - 60 kg 1.000 buah 22,000 22,000
Jumlah Harga Bahan 22,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 40,500
2.01.01.07.04.015 Pekerjaan Pemasangan Sliding Door Rail unit 325,600
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.060 OH 150,000 9,000
1.10.28.02.01.001.004 Tukang 0.600 OH 150,000 90,000
1.10.28.02.01.002.001 Pekerja 0.060 OH 100,000 6,000
Jumlah Harga Tenaga Kerja 105,600
Bahan
1.1.7.01.01.01.022.00527 Sliding Door Rail - Besi/Alumunium pjg. 180 cm 1.000 set 220,000 220,000
Jumlah Harga Bahan 220,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 325,600
2.01.01.07.04.016 Pekerjaan Pemasangan Kaca Tebal 3 mm m2 110,926
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 160
1.10.28.02.01.001.002 Kepala Tukang 0.015 OH 150,000 2,250

149
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.004 Tukang 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.015 OH 100,000 1,500
Jumlah Harga Tenaga Kerja 26,410
Bahan
1.1.7.01.01.01.003.00001 Kaca Polos Bening - tbl. 3 mm 1.100 m2 68,700 75,570
1.1.7.01.01.01.022.00525 Silicone Rubber Sealent 0.05 kg 178,915 8,946
Jumlah Harga Bahan 84,516
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 110,926
2.01.01.07.04.017 Pekerjaan Pemasangan Kaca Tebal 5 mm m2 165,156
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 160
1.10.28.02.01.001.002 Kepala Tukang 0.015 OH 150,000 2,250
1.10.28.02.01.001.004 Tukang 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.015 OH 100,000 1,500
Jumlah Harga Tenaga Kerja 26,410
Bahan
1.1.7.01.01.01.003.00002 Kaca Polos Bening - tbl. 5 mm 1.100 m2 118,000 129,800
1.1.7.01.01.01.022.00525 Silicone Rubber Sealent 0.05 kg 178,915 8,946
Jumlah Harga Bahan 138,746
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 165,156
2.01.01.07.04.018 Pekerjaan Pemasangan Kaca Tebal 8 mm m2 215,594
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 180
1.10.28.02.01.001.002 Kepala Tukang 0.017 OH 150,000 2,550
1.10.28.02.01.001.004 Tukang 0.170 OH 150,000 25,500
1.10.28.02.01.002.001 Pekerja 0.017 OH 100,000 1,700
Jumlah Harga Tenaga Kerja 29,930
Bahan
1.1.7.01.01.01.003.00003 Kaca Polos Bening - tbl. 8 mm 1.100 m2 157,400 173,140
1.1.7.01.01.01.022.00525 Silicone Rubber Sealent 0.07 kg 178,915 12,524
Jumlah Harga Bahan 185,664
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 215,594
2.01.01.07.05 PEKERJAAN PENGECATAN
2.01.01.07.05.001 Pekerjaan Mengerok Cat Lama Permukaan Kayu m2 16,895
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 15,600
Bahan
1.1.7.01.01.01.022.00472 Soda Api - Natrium Hydroxide 500 gr 0.050 kg 25,900 1,295
Jumlah Harga Bahan 1,295
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 16,895
2.01.01.07.05.002 Pekerjaan Mendempul dan Menggosok Kayu m2 36,525
Tenaga Kerja

150
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.002 Kepala Tukang 0.011 OH 150,000 1,650
1.10.28.02.01.001.004 Tukang Kayu 0.110 OH 150,000 16,500
Jumlah Harga Tenaga Kerja 18,150
Bahan
1.1.7.01.01.01.006.00011 Dempul Kayu 0.150 kg 48,300 7,245
1.1.7.01.01.01.006.00036 Plamir Kayu 0.080 kg 31,500 2,520
1.1.7.01.01.01.006.00041 Thinner 0.100 liter 27,800 2,780
Jumlah Harga Bahan 12,545
Peralatan
1.1.7.01.01.01.022.00224 Amplas - No. 240 1.000 lembar 5,500 5,500
1.1.7.01.03.09.007.00014 Pisau Pallet 0.015 buah 22,000 330
Jumlah Harga Peralatan 5,830
Harga Satuan Pokok Kegiatan 36,525
2.01.01.07.05.003 Pekerjaan Pengecatan Bidang Kayu Lama m2 45,646
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.004 Tukang Kayu 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.075 OH 100,000 7,500
Jumlah Harga Tenaga Kerja 20,550
Bahan
1.1.7.01.01.01.006.00014 Cat Kayu - Finishing 0.170 kg 67,400 11,458
1.1.7.01.01.01.006.00036 Plamir Kayu 0.150 kg 31,500 4,725
1.1.7.01.01.01.006.00041 Thinner 0.100 liter 27,800 2,780
Jumlah Harga Bahan 18,963
Peralatan
1.1.7.01.01.01.022.00224 Amplas - No. 240 1.000 lembar 5,500 5,500
1.1.7.01.03.09.007.00014 Pisau Pallet 0.015 buah 22,000 330
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 6,133
Harga Satuan Pokok Kegiatan 45,646
2.01.01.07.05.004 Pekerjaan Pengecatan Bidang Kayu Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Penutup) m2 59,123
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 900
1.10.28.02.01.001.005 Tukang Cat 0.075 OH 150,000 11,250
1.10.28.02.01.002.001 Pekerja 0.070 OH 100,000 7,000
Jumlah Harga Tenaga Kerja 19,750
Bahan
1.1.7.01.01.01.006.00011 Cat Kayu - Primer 0.170 kg 48,300 8,211
1.1.7.01.01.01.006.00014 Cat Kayu - Finishing 0.260 kg 67,400 17,524
1.1.7.01.01.01.006.00036 Plamir Kayu 0.150 kg 31,500 4,725
1.1.7.01.01.01.006.00041 Thinner 0.100 liter 27,800 2,780
Jumlah Harga Bahan 33,240
Peralatan
1.1.7.01.01.01.022.00224 Amplas - No. 240 1.000 lembar 5,500 5,500
1.1.7.01.03.09.007.00014 Pisau Pallet 0.015 buah 22,000 330
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 6,133
Harga Satuan Pokok Kegiatan 59,123
2.01.01.07.05.005 Pekerjaan Pengecatan Bidang Kayu Baru (1 Lps. Plamir, 1 Lps. Dasar, 3 Lps. Penutup) m2 80,735
Tenaga Kerja

151
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.001 Mandor 0.008 OH 200,000 1,600
1.10.28.02.01.001.002 Kepala Tukang 0.010 OH 150,000 1,500
1.10.28.02.01.001.005 Tukang Cat 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.070 OH 100,000 7,000
Jumlah Harga Tenaga Kerja 32,600
Bahan
1.1.7.01.01.01.006.00011 Cat Kayu - Primer 0.170 kg 48,300 8,211
1.1.7.01.01.01.006.00014 Cat Kayu - Finishing 0.390 kg 67,400 26,286
1.1.7.01.01.01.006.00036 Plamir Kayu 0.150 kg 31,500 4,725
1.1.7.01.01.01.006.00041 Thinner 0.100 liter 27,800 2,780
Jumlah Harga Bahan 42,002
Peralatan
1.1.7.01.01.01.022.00224 Amplas - No. 240 1.000 lembar 5,500 5,500
1.1.7.01.03.09.007.00014 Pisau Pallet 0.015 buah 22,000 330
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 6,133
Harga Satuan Pokok Kegiatan 80,735
2.01.01.07.05.006 Pekerjaan Pelaburan Bidang Kayu dengan Politur m2 55,906
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.016 OH 150,000 2,400
1.10.28.02.01.001.005 Tukang Cat 0.060 OH 150,000 9,000
1.10.28.02.01.002.001 Pekerja 0.040 OH 100,000 4,000
Jumlah Harga Tenaga Kerja 16,000
Bahan
1.1.7.01.01.01.006.00049 Politur Kayu 0.370 liter 80,900 29,933
1.1.7.01.01.01.006.00041 Thinner 0.150 liter 27,800 4,170
Jumlah Harga Bahan 34,103
Peralatan
1.1.7.01.01.01.022.00224 Amplas - No. 240 1.000 lembar 5,500 5,500
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 5,803
Harga Satuan Pokok Kegiatan 55,906
2.01.01.07.05.007 Pekerjaan Pelaburan Bidang Kayu dengan Cat Residu/Teer m2 39,398
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.006 OH 200,000 1,200
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 11,200
Bahan
1.1.7.01.01.01.006.00051 Cat Residu/Teer 0.350 kg 79,700 27,895
Jumlah Harga Bahan 27,895
Peralatan
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 303
Harga Satuan Pokok Kegiatan 39,398
2.01.01.07.05.008 Pekerjaan Pelaburan Bidang Kayu dengan Vernis m2 55,906
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.016 OH 150,000 2,400
1.10.28.02.01.001.005 Tukang Cat 0.060 OH 150,000 9,000
1.10.28.02.01.002.001 Pekerja 0.040 OH 100,000 4,000
Jumlah Harga Tenaga Kerja 16,000

152
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
1.1.7.01.01.01.006.00049 Politur Kayu 0.370 liter 80,900 29,933
1.1.7.01.01.01.006.00041 Thinner 0.150 liter 27,800 4,170
Jumlah Harga Bahan 34,103
Peralatan
1.1.7.01.01.01.022.00224 Amplas - No. 240 1.000 lembar 5,500 5,500
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 5,803
Harga Satuan Pokok Kegiatan 55,906
2.01.01.07.05.009 Pekerjaan Mengerok Cat Lama Permukaan Tembok m2 16,895
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 15,600
Bahan
1.1.7.01.01.01.022.00472 Soda Api - Natrium Hydroxide 500 gr 0.050 kg 25,900 1,295
Jumlah Harga Bahan 1,295
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 16,895
2.01.01.07.05.010 Pekerjaan Pencucian Bidang Permukaan Tembok yang Pernah Dicat m2 16,775
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 15,600
Bahan
1.1.7.01.03.07.008.00034 Sabun Detergent 0.050 kg 23,500 1,175
Jumlah Harga Bahan 1,175
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 16,775
2.01.01.07.05.011 Pekerjaan Mengapur Dinding Tembok Baru m2 29,825
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 500
1.10.28.02.01.001.002 Kepala Tukang 0.000 OH 150,000 15
1.10.28.02.01.001.005 Tukang Cat 0.001 OH 150,000 150
1.10.28.02.01.002.001 Pekerja 0.150 OH 100,000 15,000
Jumlah Harga Tenaga Kerja 15,665
Bahan
1.1.7.01.01.01.002.00011 Kapur Pasang (kg) 0.150 kg 3,400 510
1.1.7.01.01.01.022.00470 Ijuk 0.250 ikat 32,600 8,150
Jumlah Harga Bahan 8,660
Peralatan
1.1.7.01.01.01.022.00224 Amplas - No. 240 1.000 lembar 5,500 5,500
Jumlah Harga Peralatan 5,500
Harga Satuan Pokok Kegiatan 29,825
2.01.01.07.05.012 Pekerjaan Mengapur Dinding Tembok Lama m2 19,995
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 500
1.10.28.02.01.001.002 Kepala Tukang 0.001 OH 150,000 75
1.10.28.02.01.001.005 Tukang Cat 0.005 OH 150,000 750
1.10.28.02.01.002.001 Pekerja 0.040 OH 100,000 4,000

153
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Tenaga Kerja 5,325
Bahan
1.1.7.01.01.01.002.00011 Kapur Pasang (kg) 0.300 kg 3,400 1,020
1.1.7.01.01.01.022.00470 Ijuk 0.250 ikat 32,600 8,150
Jumlah Harga Bahan 9,170
Peralatan
1.1.7.01.01.01.022.00224 Amplas - No. 240 1.000 lembar 5,500 5,500
Jumlah Harga Peralatan 5,500
Harga Satuan Pokok Kegiatan 19,995
2.01.01.07.05.013 Pekerjaan Pengecatan Bidang Tembok Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Interior) m2 49,338
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 900
1.10.28.02.01.001.005 Tukang Cat 0.063 OH 150,000 9,450
1.10.28.02.01.002.001 Pekerja 0.020 OH 100,000 2,000
Jumlah Harga Tenaga Kerja 12,950
Bahan
1.1.7.01.01.01.006.00027 Cat Tembok Interior - Primer 0.040 kaleng 127,700 5,108
1.1.7.01.01.01.006.00026 Cat Tembok Interior - Finishing 0.104 kaleng 196,700 20,457
1.1.7.01.01.01.006.00037 Plamir Tembok 0.100 kg 19,100 1,910
1.1.7.01.01.01.006.00041 Thinner 0.100 liter 27,800 2,780
Jumlah Harga Bahan 30,255
Peralatan
1.1.7.01.01.01.022.00224 Amplas - No. 240 1.000 lembar 5,500 5,500
1.1.7.01.03.09.007.00014 Pisau Pallet 0.015 buah 22,000 330
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 6,133
Harga Satuan Pokok Kegiatan 49,338
2.01.01.07.05.014 Pekerjaan Pengecatan Bidang Tembok Lama (1 Lps. Dasar, 2 Lps. Interior) m2 33,705
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.002 Kepala Tukang 0.004 OH 150,000 630
1.10.28.02.01.001.005 Tukang Cat 0.042 OH 150,000 6,300
1.10.28.02.01.002.001 Pekerja 0.028 OH 100,000 2,800
Jumlah Harga Tenaga Kerja 10,330
Bahan
1.1.7.01.01.01.006.00027 Cat Tembok Interior - Primer 0.048 kaleng 127,700 6,130
1.1.7.01.01.01.006.00026 Cat Tembok Interior - Finishing 0.072 kaleng 196,700 14,162
1.1.7.01.01.01.006.00041 Thinner 0.100 liter 27,800 2,780
Jumlah Harga Bahan 23,072
Peralatan
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 303
Harga Satuan Pokok Kegiatan 33,705
2.01.01.07.05.015 Pekerjaan Pengecatan Tembok Exterior m2 35,776
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 945
1.10.28.02.01.001.005 Tukang Cat 0.063 OH 150,000 9,450
1.10.28.02.01.002.001 Pekerja 0.020 OH 100,000 2,000
Jumlah Harga Tenaga Kerja 12,395
Bahan
1.1.7.01.01.01.006.00024 Cat Tembok Exterior - Primer - Weather Shield 0.024 kaleng 143,900 3,454

154
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.006.00022 Cat Tembok Exterior - Finishing - Weather Shield 0.036 kaleng 252,900 9,104
1.1.7.01.01.01.006.00037 Plamir Tembok 0.100 kg 19,100 1,910
1.1.7.01.01.01.006.00041 Thinner 0.100 liter 27,800 2,780
Jumlah Harga Bahan 17,248
Peralatan
1.1.7.01.01.01.022.00224 Amplas - No. 240 1.000 lembar 5,500 5,500
1.1.7.01.03.09.007.00014 Pisau Pallet 0.015 buah 22,000 330
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 6,133
Harga Satuan Pokok Kegiatan 35,776
2.01.01.07.05.023 Pekerjaan Pengecatan Plafon m2 38,693
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 900
1.10.28.02.01.001.005 Tukang Cat 0.060 OH 150,000 9,000
1.10.28.02.01.002.001 Pekerja 0.080 OH 100,000 8,000
Jumlah Harga Tenaga Kerja 18,700
Bahan
1.1.7.01.01.01.006.00027 Cat Tembok Interior - Primer 0.040 kaleng 127,700 5,108
1.1.7.01.01.01.006.00026 Cat Tembok Interior - Finishing 0.060 kaleng 196,700 11,802
1.1.7.01.01.01.006.00041 Thinner 0.100 liter 27,800 2,780
Jumlah Harga Bahan 19,690
Peralatan
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 303
Harga Satuan Pokok Kegiatan 38,693
2.01.01.07.05.025 Pekerjaan Pengecatan Pohon m2 17,903
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.006 OH 150,000 900
1.10.28.02.01.002.001 Pekerja 0.080 OH 100,000 8,000
Jumlah Harga Tenaga Kerja 8,900
Bahan
1.1.7.01.01.01.006.00057 Cat Kayu - Finishing (Eco Green Variant) 0.150 kg 58,000 8,700
Jumlah Harga Bahan 8,700
Peralatan
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 303
Harga Satuan Pokok Kegiatan 17,903
2.01.01.07.05.024 Pekerjaan Pengecatan Outdoor Antislip m2 53,403
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.008 OH 150,000 1,200
1.10.28.02.01.001.005 Tukang Cat 0.050 OH 150,000 7,500
1.10.28.02.01.002.001 Pekerja 0.060 OH 100,000 6,000
Jumlah Harga Tenaga Kerja 14,700
Bahan
1.1.7.01.01.01.006.00056 Cat Court Coating - All Weather 0.240 kg 160,000 38,400
Jumlah Harga Bahan 38,400
Peralatan
1.1.7.01.01.01.022.00260 Kuas Cat 0.015 buah 20,200 303
Jumlah Harga Peralatan 303
Harga Satuan Pokok Kegiatan 53,403
2.01.01.07.06 PEKERJAAN INSTALASI LISTRIK

155
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak titik 184,890
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.022 Tukang Listrik 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.050 OH 100,000 5,000
Jumlah Harga Tenaga Kerja 80,750
Bahan
1.1.7.01.03.08.001.00005 Kabel NYA - 1 x 2.5 mm 15.000 m' 5,100 76,500
1.1.7.02.02.06.001.00069 Pipa PVC - Type C Dia. 5/8 inch. pjg. 400 cm 0.800 m' 8,800 7,040
1.1.7.01.03.08.003.00005 Stop Kontak - Tunggal 1.000 buah 16,700 16,700
1.1.7.01.03.08.012.00016 T Dos PVC 1.000 buah 3,900 3,900
Jumlah Harga Bahan 104,140
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 184,890
2.01.01.07.06.002 Pekerjaan Pemasangan Titik Lampu titik 226,950
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.022 Tukang Listrik 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.300 OH 100,000 30,000
Jumlah Harga Tenaga Kerja 105,750
Bahan
1.1.7.01.03.08.001.00005 Kabel NYA - 1 x 2.5 mm 15.000 m' 5,100 76,500
1.1.7.02.02.06.001.00069 Pipa PVC - Type C Dia. 5/8 inch. pjg. 400 cm 4.000 m' 8,800 35,200
1.1.7.01.03.08.008.00004 Fitting Lampu Plafon 1.000 buah 5,600 5,600
1.1.7.01.03.08.012.00016 T Dos PVC 1.000 buah 3,900 3,900
Jumlah Harga Bahan 121,200
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 226,950
2.01.01.07.06.004 Pekerjaan Pemasangan Saklar Tunggal titik 55,600
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.022 Tukang Listrik 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.001 OH 100,000 100
Jumlah Harga Tenaga Kerja 37,600
Bahan
1.1.7.01.03.08.004.00004 Saklar Dinding - Tunggal 1.000 buah 18,000 18,000
Jumlah Harga Bahan 18,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 55,600
2.01.01.07.06.005 Pekerjaan Pemasangan Saklar Ganda titik 57,800
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.022 Tukang Listrik 0.200 OH 150,000 30,000
1.10.28.02.01.002.001 Pekerja 0.001 OH 100,000 100
Jumlah Harga Tenaga Kerja 37,600
Bahan
1.1.7.01.03.08.004.00001 Saklar Dinding - Ganda 1.000 buah 20,200 20,200
Jumlah Harga Bahan 20,200
Peralatan

156
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 57,800
2.01.01.07.06.006 Pekerjaan Pemasangan Lampu TL 18 watt unit 116,050
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.022 Tukang Listrik 0.050 OH 150,000 7,500
1.10.28.02.01.002.001 Pekerja 0.010 OH 100,000 1,000
Jumlah Harga Tenaga Kerja 9,250
Bahan
1.1.7.01.03.08.002.00045 Lampu TL 18 watt 1.000 buah 106,800 106,800
Jumlah Harga Bahan 106,800
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 116,050
2.01.01.07.06.007 Pekerjaan Pemasangan Lampu TL 36 watt unit 150,850
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.022 Tukang Listrik 0.050 OH 150,000 7,500
1.10.28.02.01.002.001 Pekerja 0.010 OH 100,000 1,000
Jumlah Harga Tenaga Kerja 9,250
Bahan
1.1.7.01.03.08.002.00046 Lampu TL 36 watt 1.000 buah 141,600 141,600
Jumlah Harga Bahan 141,600
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 150,850
2.01.01.07.06.008 Pekerjaan Pemasangan Lampu SL 18 watt unit 48,550
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.022 Tukang Listrik 0.050 OH 150,000 7,500
1.10.28.02.01.002.001 Pekerja 0.010 OH 100,000 1,000
Jumlah Harga Tenaga Kerja 9,250
Bahan
1.1.7.01.03.08.002.00011 Lampu SL 18 watt 1.000 buah 39,300 39,300
Jumlah Harga Bahan 39,300
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 48,550
2.01.01.07.06.009 Pekerjaan Pemasangan Lampu SL 36 watt unit 96,450
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.022 Tukang Listrik 0.050 OH 150,000 7,500
1.10.28.02.01.002.001 Pekerja 0.010 OH 100,000 1,000
Jumlah Harga Tenaga Kerja 9,250
Bahan
1.1.7.01.03.08.002.00030 Lampu SL 36 watt 1.000 buah 87,200 87,200
Jumlah Harga Bahan 87,200
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 96,450
2.01.01.07.06.010 Pekerjaan Pemasangan Lampu LED 18 watt unit 96,700
Tenaga Kerja

157
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.022 Tukang Listrik 0.050 OH 150,000 7,500
1.10.28.02.01.002.001 Pekerja 0.010 OH 100,000 1,000
Jumlah Harga Tenaga Kerja 9,250
Bahan
1.1.7.01.03.08.002.00061 Lampu LED 16 watt 1.000 buah 87,450 87,450
Jumlah Harga Bahan 87,450
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 96,700
2.01.01.07.06.011 Pekerjaan Pemasangan Lampu LED 36 watt unit 157,750
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.022 Tukang Listrik 0.050 OH 150,000 7,500
1.10.28.02.01.002.001 Pekerja 0.010 OH 100,000 1,000
Jumlah Harga Tenaga Kerja 9,250
Bahan
1.1.7.01.03.08.002.00062 Lampu LED 24 watt 1.000 buah 148,500 148,500
Jumlah Harga Bahan 148,500
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 157,750
2.01.01.07.06.012 Pekerjaan Pemasangan Lampu Downlight unit 108,250
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.005 OH 150,000 750
1.10.28.02.01.001.022 Tukang Listrik 0.050 OH 150,000 7,500
1.10.28.02.01.002.001 Pekerja 0.010 OH 100,000 1,000
Jumlah Harga Tenaga Kerja 9,250
Bahan
1.1.7.01.03.08.002.00051 Lampu Downlight LED 18 watt 1.000 buah 99,000 99,000
Jumlah Harga Bahan 99,000
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 108,250
2.01.01.07.06.013 Pekerjaan Pemasangan Panel Box titik 793,100
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 1.000 OH 150,000 150,000
1.10.28.02.01.001.022 Tukang Listrik 1.000 OH 150,000 150,000
1.10.28.02.01.002.001 Pekerja 0.500 OH 100,000 50,000
Jumlah Harga Tenaga Kerja 350,000
Bahan
1.3.2.18.01.01.003.00200 MCB Panel Box - Outbow 4 Grup 1.000 buah 64,100 64,100
1.3.2.18.01.01.003.00036 MCB - 1 Phase 4.5 kA, 6 A 2.000 buah 56,200 112,400
1.3.2.18.01.01.003.00035 MCB - 1 Phase 4.5 kA, 4 A 2.000 buah 65,800 131,600
1.1.7.01.03.08.001.00010 Kabel NYM - 3 x 2.5 mm 6.000 m' 22,500 135,000
Jumlah Harga Bahan 443,100
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 793,100
2.01.01.07.06.014 Pekerjaan Pemasangan Panel Phase 2200 VA unit 2,884,490
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.900 OH 150,000 135,000

158
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.002.001 Pekerja 1.300 OH 100,000 130,000
Jumlah Harga Tenaga Kerja 265,000
Bahan
1.1.7.01.01.01.022.00508 Panel kWh Meter - 1 Phase 1.000 buah 571,300 571,300
1.3.2.18.01.01.003.00047 MCB C60N - 1 Phase, 6 A 4.000 buah 104,000 416,000
1.3.2.18.01.01.003.00049 MCB C60N - 1 Phase, 16 A 2.000 buah 104,000 208,000
1.1.7.01.03.08.012.00028 Magnet Contactor LC1 D12 - 25 A 1.000 buah 278,400 278,400
1.1.7.01.03.08.012.00031 Time Switch SUL 181 D 1.000 buah 523,000 523,000
1.1.7.01.03.08.001.00046 Kabel Gland - PG-7 1.000 buah 1,900 1,900
1.1.7.01.03.08.001.00045 Kabel Gland - PG-21 4.000 buah 7,000 28,000
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm (for ARDE) 0.750 batang 31,400 23,550
1.1.7.02.02.07.001.00258 Elbow Pipa PVC - Type C Dia. 1/2 inch 2.000 buah 11,400 22,800
1.1.7.01.01.01.022.00528 Stainless Tie + Clip + Ring 3.000 buah 14,080 42,240
1.1.7.01.03.08.001.00034 Kabel Twisted - 2 x 10 mm, XLPE 3.000 m' 6,700 20,100
1.3.2.18.01.01.003.00201 Grounding Rod + Steel Wire - Uk. 16 mm (for ARDE) 1.000 buah 396,500 396,500
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 1.000 buah 87,700 87,700
Jumlah Harga Bahan 2,619,490
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 2,884,490
2.01.02.01.03 PEKERJAAN DRAINASE
2.01.02.01.03.001 Pekerjaan Galian untuk Selokan Drainase dan Saluran Air m3 36,850
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.007 OH 200,000 1,400
1.10.28.02.01.002.001 Pekerja 0.226 OH 100,000 22,600
Jumlah Harga Tenaga Kerja 24,000
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.01.01.001.00005 Excavator 0.067 jam 191,785 12,850
9.1.2.09.03.01.001.00097 Dump Truck 0.067 jam 97,531 6,535
Jumlah Harga Peralatan 12,850
Harga Satuan Pokok Kegiatan 36,850
2.01.02.01.03.002 Pekerjaan Pasangan Batu dengan Mortar m3 499,170
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.051 OH 200,000 10,140
1.10.28.02.01.001.006 Tukang Batu 0.151 OH 150,000 22,590
1.10.28.02.01.002.001 Pekerja 0.502 OH 100,000 50,200
Jumlah Harga Tenaga Kerja 82,930
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 161 kg 1,000 161,000
1.1.7.01.01.01.002.00013 Kapur 1.080 m3 41,000 44,280
1.1.7.01.01.01.004.00002 Pasir Pasang 0.483 m3 179,800 86,825
Jumlah Harga Bahan 292,105
Peralatan
9.1.2.09.03.01.001.00008 Concrete Mixer 0.402 jam 309,100 124,135
Jumlah Harga Peralatan 124,135
Harga Satuan Pokok Kegiatan 499,170
2.01.02.01.03.003 Bahan Porous untuk Filter m3 348,996
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.088 OH 200,000 17,500
1.10.28.02.01.002.001 Pekerja 0.350 OH 100,000 35,000

159
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Tenaga Kerja 52,500
Bahan
1.1.7.01.01.01.005.00067 Agregat Kasar 0.550 m3 228,000 125,400
1.1.7.01.01.01.004.00002 Pasir Pasang 0.550 m3 179,800 98,890
Jumlah Harga Bahan 224,290
Peralatan
9.1.2.09.03.01.001.00018 Tamper 0.161 jam 449,600 72,206
Jumlah Harga Peralatan 72,206
Harga Satuan Pokok Kegiatan 348,996
2.01.02.01.03.004 Pekerjaan Pemasangan Lubang Drainase unit 25,705
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 600
1.10.28.02.01.001.006 Tukang Batu 0.060 OH 150,000 9,000
1.10.28.02.01.002.001 Pekerja 0.060 OH 100,000 6,000
Jumlah Harga Tenaga Kerja 15,600
Bahan
1.1.7.02.02.06.001.00040 Pipa PVC - Type D Dia. 2 inch. pjg. 400 cm 0.125 batang 67,800 8,475
1.1.7.01.01.01.022.00470 Ijuk 0.050 kg 32,600 1,630
Jumlah Harga Bahan 10,105
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 25,705
2.01.02.01 PAVING DAN PERKERASAN JALAN
2.01.02.01.02 PEKERJAAN PENGADAAN AGREGAT
2.01.02.01.02.001 Pembuatan Agregat Kelas A m3 287,272
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 786
1.10.28.02.01.002.001 Pekerja 0.008 OH 100,000 780
Jumlah Harga Tenaga Kerja 1,566
Bahan
1.1.7.01.01.01.005.00060 Agregat Pecah Kasar 0.733 m3 260,000 190,684
1.1.7.01.01.01.005.00029 Agregat Halus Lapis Pondasi Kelas A 0.317 m3 224,800 71,172
Jumlah Harga Bahan 261,856
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.032 jam 449,600 14,162
9.1.2.09.03.01.001.00076 Blending Equipment 0.048 jam 201,000 9,688
Jumlah Harga Peralatan 23,851
Harga Satuan Pokok Kegiatan 287,272
2.01.02.01.02.002 Pembuatan Agregat Kelas B m3 295,547
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 786
1.10.28.02.01.002.001 Pekerja 0.008 OH 100,000 780
Jumlah Harga Tenaga Kerja 1,566
Bahan
1.1.7.01.01.01.005.00060 Agregat Pecah Kasar 0.416 m3 260,000 108,108
1.1.7.01.01.01.005.00074 Fraksi Lolos - Scalping Screen 0 - 50 mm 0.634 m3 255,475 162,022
Jumlah Harga Bahan 270,130
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.032 jam 449,600 14,162
9.1.2.09.03.01.001.00076 Blending Equipment 0.048 jam 201,000 9,688
Jumlah Harga Peralatan 23,851
Harga Satuan Pokok Kegiatan 295,547

160
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.02.01.02.003 Pembuatan Agregat Kelas S m3 319,397
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 786
1.10.28.02.01.002.001 Pekerja 0.008 OH 100,000 780
Jumlah Harga Tenaga Kerja 1,566
Bahan
1.1.7.01.01.01.005.00060 Agregat Pecah Kasar 0.189 m3 260,000 49,140
1.1.7.01.01.01.005.00069 Agregat Lolos - Screen 1" 0.192 m3 212,200 40,785
1.1.7.01.01.01.005.00065 Fraksi Lolos - Scalping Screen 0 - 37.5 mm 0.669 m3 237,400 158,797
Jumlah Harga Bahan 248,722
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.032 jam 449,600 14,162
9.1.2.09.03.01.001.00076 Blending Equipment 0.048 jam 201,000 9,688
Jumlah Harga Peralatan 23,851
Harga Satuan Pokok Kegiatan 274,138
2.01.02.01.02.004 Pembuatan Lapis Pondasi Agregat (CBR 60%) m3 297,989
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 786
1.10.28.02.01.002.001 Pekerja 0.008 OH 100,000 780
Jumlah Harga Tenaga Kerja 1,566
Bahan
1.1.7.01.01.01.005.00060 Agregat Pecah Kasar 0.252 m3 260,000 65,520
1.1.7.01.01.01.005.00069 Agregat Lolos - Screen 1" 0.223 m3 212,200 47,321
1.1.7.01.01.01.005.00065 Fraksi Lolos - Scalping Screen 0 - 37.5 mm 0.575 m3 237,400 136,505
Jumlah Harga Bahan 249,346
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.032 jam 449,600 14,162
9.1.2.09.03.01.001.00076 Blending Equipment 0.048 jam 201,000 9,688
Jumlah Harga Peralatan 23,851
Harga Satuan Pokok Kegiatan 274,762
2.01.02.01.02.005 Pembuatan Lapis Permukaan Agregat (CBR 60%) m3 232,938
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 786
1.10.28.02.01.002.001 Pekerja 0.008 OH 100,000 780
Jumlah Harga Tenaga Kerja 1,566
Bahan
1.1.7.01.01.01.005.00066 Agregat - Uk. 5-10 mm / 10-20 mm 0.479 m3 212,200 101,601
1.1.7.01.01.01.004.00003 Pasir Urug 0.571 m3 185,500 105,921
Jumlah Harga Bahan 207,522
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.032 jam 449,600 14,162
9.1.2.09.03.01.001.00076 Blending Equipment 0.048 jam 201,000 9,688
Jumlah Harga Peralatan 23,851
Harga Satuan Pokok Kegiatan 232,938
2.01.02.01.01 PEKERJAAN PAVING
2.01.02.01.01.001 Pekerjaan Pemasangan Tegel Trotoar m2 116,185
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.025 OH 200,000 5,000
1.10.28.02.01.001.006 Tukang Batu 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.500 OH 100,000 50,000
Jumlah Harga Tenaga Kerja 92,500
Bahan

161
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.013.00042 Tegel Trotoar - Uk. 30 x 30 cm 1.050 m2 16,900 17,745
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 3.650 kg 1,000 3,650
1.1.7.01.01.01.004.00002 Pasir Pasang 0.010 m3 179,800 1,798
1.1.7.01.01.01.002.00013 Kapur 0.012 m3 41,000 492
Jumlah Harga Bahan 23,685
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 116,185
2.01.02.01.01.002 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Segi Enam) m2 243,845
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 260
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.006 Tukang Batu 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.250 OH 100,000 25,000
Jumlah Harga Tenaga Kerja 107,760
Bahan
1.1.7.01.01.01.022.00302 Paving Stone - Tbl. 8 cm, Abu - abu, Segi Enam 1.010 m2 114,500 115,645
1.1.7.01.01.01.004.00002 Pasir Pasang 0.050 m3 179,800 8,990
Jumlah Harga Bahan 124,635
Peralatan
1.1.7.01.01.01.022.00302 Peralatan 0.100 unit 114,500 11,450
Jumlah Harga Peralatan 11,450
Harga Satuan Pokok Kegiatan 243,845
2.01.02.01.01.003 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Segi Enam - Warna) m2 258,830
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 260
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.006 Tukang Batu 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.250 OH 100,000 25,000
Jumlah Harga Tenaga Kerja 107,760
Bahan
1.1.7.01.01.01.022.00303 Paving Stone - Tbl. 8 cm, Warna, Segi Enam 1.010 m2 128,000 129,280
1.1.7.01.01.01.004.00002 Pasir Pasang 0.050 m3 179,800 8,990
Jumlah Harga Bahan 138,270
Peralatan
1.1.7.01.01.01.022.00303 Peralatan 0.100 unit 128,000 12,800
Jumlah Harga Peralatan 12,800
Harga Satuan Pokok Kegiatan 258,830
2.01.02.01.01.004 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Persegi Panjang) m2 243,845
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 260
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.006 Tukang Batu 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.250 OH 100,000 25,000
Jumlah Harga Tenaga Kerja 107,760
Bahan
1.1.7.01.01.01.022.00296 Paving Stone - Tbl. 8 cm, Abu - abu, Persegi Panjang 1.010 m2 114,500 115,645
1.1.7.01.01.01.004.00002 Pasir Pasang 0.050 m3 179,800 8,990
Jumlah Harga Bahan 124,635
Peralatan
1.1.7.01.01.01.022.00296 Peralatan 0.100 unit 114,500 11,450
Jumlah Harga Peralatan 11,450

162
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Harga Satuan Pokok Kegiatan 243,845
2.01.02.01.01.005 Pekerjaan Pemasangan Paving Stone tebal 8 cm (Persegi Panjang - Warna) m2 258,830
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 260
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.006 Tukang Batu 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.250 OH 100,000 25,000
Jumlah Harga Tenaga Kerja 107,760
Bahan
1.1.7.01.01.01.022.00297 Paving Stone - Tbl. 8 cm, Warna, Persegi Panjang 1.010 m2 128,000 129,280
1.1.7.01.01.01.004.00002 Pasir Pasang 0.050 m3 179,800 8,990
Jumlah Harga Bahan 138,270
Peralatan
1.1.7.01.01.01.022.00297 Peralatan 0.100 unit 128,000 12,800
Jumlah Harga Peralatan 12,800
Harga Satuan Pokok Kegiatan 258,830
2.01.02.01.01.006 Pekerjaan Pemasangan Paving Stone tebal 6 cm (Persegi Panjang) m2 228,860
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 260
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.006 Tukang Batu 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.250 OH 100,000 25,000
Jumlah Harga Tenaga Kerja 107,760
Bahan
1.1.7.01.01.01.022.00294 Paving Stone - Tbl. 6 cm, Abu - abu, Persegi Panjang 1.010 m2 101,000 102,010
1.1.7.01.01.01.004.00002 Pasir Pasang 0.050 m3 179,800 8,990
Jumlah Harga Bahan 111,000
Peralatan
1.1.7.01.01.01.022.00294 Peralatan 0.100 unit 101,000 10,100
Jumlah Harga Peralatan 10,100
Harga Satuan Pokok Kegiatan 228,860
2.01.02.01.01.007 Pekerjaan Pemasangan Paving Stone tebal 6 cm (Persegi Panjang - Warna) m2 234,855
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 260
1.10.28.02.01.001.002 Kepala Tukang 0.050 OH 150,000 7,500
1.10.28.02.01.001.006 Tukang Batu 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.250 OH 100,000 25,000
Jumlah Harga Tenaga Kerja 107,760
Bahan
1.1.7.01.01.01.022.00295 Paving Stone - Tbl. 6 cm, Warna, Persegi Panjang 1.010 m2 114,500 115,645
1.1.7.01.01.01.004.00002 Pasir Pasang 0.050 m3 179,800 8,990
Jumlah Harga Bahan 115,645
Peralatan
1.1.7.01.01.01.022.00295 Peralatan 0.100 unit 114,500 11,450
Jumlah Harga Peralatan 11,450
Harga Satuan Pokok Kegiatan 234,855
2.01.02.01.01.013 Pekerjaan Pemasangan Kanstin m' 211,971
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.025 OH 200,000 5,000
1.10.28.02.01.001.006 Tukang Batu 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.500 OH 100,000 50,000
Jumlah Harga Tenaga Kerja 130,000

163
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
1.1.7.01.01.01.022.00501 Kanstin - Uk 15 x 25 x 40 cm 2.500 buah 31,500 78,750
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 2.250 kg 1,000 2,250
1.1.7.01.01.01.004.00002 Pasir Pasang 0.005 m3 179,800 971
Jumlah Harga Bahan 81,971
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 211,971
2.01.02.01.01.014 Pekerjaan Pemasangan Stopper/Uskup m' 164,756
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.025 OH 200,000 5,000
1.10.28.02.01.001.006 Tukang Batu 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.500 OH 100,000 50,000
Jumlah Harga Tenaga Kerja 130,000
Bahan
1.1.7.01.01.01.022.00304 Paving Uskup - Tbl. 8 cm 0.367 m2 94,300 34,577
1.1.7.01.01.01.004.00002 Pasir Pasang 0.001 m3 179,800 180
Jumlah Harga Bahan 34,756
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 164,756
2.01.02.01.01.015 Pekerjaan Tegel Batu Ampyang m2 208,060
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.025 OH 200,000 5,000
1.10.28.02.01.001.006 Tukang Batu 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.500 OH 100,000 50,000
Jumlah Harga Tenaga Kerja 92,500
Bahan
1.1.7.01.01.01.005.00043 Batu Lantai - Ampyang (Carport) Multi Warna 1.050 m2 104,400 109,620
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 3.650 kg 1,000 3,650
1.1.7.01.01.01.004.00002 Pasir Pasang 0.010 m3 179,800 1,798
1.1.7.01.01.01.002.00013 Kapur 0.012 m3 41,000 492
Jumlah Harga Bahan 115,560
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 208,060
2.01.02.01.04 PEKERJAAN TANAH
2.01.02.01.04.001 Pekerjaan Galian Biasa + Pembuangan Sisa Galian m3 38,802
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.003 OH 200,000 640
1.10.28.02.01.002.001 Pekerja 0.006 OH 100,000 638
Jumlah Harga Tenaga Kerja 1,278
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.01.01.001.00005 Excavator 0.026 jam 191,785 4,910
9.1.2.09.03.01.001.00097 Dump Truck 0.334 jam 97,531 32,614
Jumlah Harga Peralatan 37,524
Harga Satuan Pokok Kegiatan 38,802
2.01.02.01.04.003 Pekerjaan Galian Batu + Pembuangan Sisa Galian m3 94,670
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.007 OH 200,000 1,380

164
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.002.001 Pekerja 0.056 OH 100,000 5,570
Jumlah Harga Tenaga Kerja 6,950
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00051 Compressor 0.056 jam 202,300 11,288
9.1.2.09.03.01.001.00040 Jack Hammer 0.056 jam 123,600 6,897
9.1.2.09.03.01.001.00029 Wheel Loader 0.056 jam 449,600 25,088
9.1.2.09.01.01.001.00005 Excavator 0.056 jam 191,785 10,702
9.1.2.09.03.01.001.00097 Dump Truck 0.346 jam 97,531 33,746
Jumlah Harga Peralatan 87,720
Harga Satuan Pokok Kegiatan 94,670
2.01.02.01.04.004 Pekerjaan Galian Struktur dengan Kedalaman 0-2 m m3 7,896
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 130
1.10.28.02.01.002.001 Pekerja 0.003 OH 100,000 250
Jumlah Harga Tenaga Kerja 380
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.02.01.001.00001 Bulldozer 0.015 jam 449,600 6,519
9.1.2.09.01.01.001.00005 Excavator 0.005 jam 191,785 997
Jumlah Harga Peralatan 7,516
Harga Satuan Pokok Kegiatan 7,896
2.01.02.01.04.005 Pekerjaan Galian Struktur dengan Kedalaman 2-4 m m3 23,626
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 130
1.10.28.02.01.002.001 Pekerja 0.003 OH 100,000 250
Jumlah Harga Tenaga Kerja 380
Bahan
1.1.7.01.01.01.022.00523 Sheet Pile - U-Shape Uk. 400 x 100 mm 13.000 batang 1,210 15,730
Jumlah Harga Bahan 15,730
Peralatan
9.1.2.09.02.01.001.00001 Bulldozer 0.015 jam 449,600 6,519
9.1.2.09.01.01.001.00005 Excavator 0.005 jam 191,785 997
Jumlah Harga Peralatan 7,516
Harga Satuan Pokok Kegiatan 23,626
2.01.02.01.04.006 Pekerjaan Galian Struktur dengan Kedalaman 4-6 m m3 24,194
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 215
1.10.28.02.01.002.001 Pekerja 0.013 OH 100,000 1,290
Jumlah Harga Tenaga Kerja 1,505
Bahan
1.1.7.01.01.01.022.00523 Sheet Pile - U-Shape Uk. 400 x 100 mm 12.000 m2 1,210 14,520
Jumlah Harga Bahan 14,520
Peralatan
9.1.2.09.02.01.001.00001 Bulldozer 0.015 jam 449,600 6,519
9.1.2.09.01.01.001.00005 Excavator 0.009 jam 191,785 1,649
Jumlah Harga Peralatan 8,169
Harga Satuan Pokok Kegiatan 24,194
2.01.02.01.04.007 Pekerjaan Galian Perkerasan Beraspal dengan Cold Milling Machine m3 78,087
Tenaga Kerja

165
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 925
1.10.28.02.01.002.001 Pekerja 0.009 OH 100,000 926
Jumlah Harga Tenaga Kerja 1,851
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00036 Cold Milling 0.037 jam 828,900 30,669
9.1.2.09.03.01.001.00097 Dump Truck 0.467 jam 97,531 45,566
Jumlah Harga Peralatan 76,236
Harga Satuan Pokok Kegiatan 78,087
2.01.02.01.04.008 Pekerjaan Galian Perkerasan Beraspal Tanpa Cold Milling Machine m3 902,128
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.021 OH 200,000 4,160
1.10.28.02.01.002.001 Pekerja 0.042 OH 100,000 4,166
Jumlah Harga Tenaga Kerja 8,326
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00040 Jack Hammer 2.410 jam 123,600 297,827
9.1.2.09.03.01.001.00051 Compressor 2.410 jam 202,300 487,462
9.1.2.09.03.01.001.00097 Dump Truck 1.113 jam 97,531 108,513
Jumlah Harga Peralatan 893,801
Harga Satuan Pokok Kegiatan 902,128
2.01.02.01.04.010 Pekerjaan Pemotongan Pohon Pilihan Diameter 15-30 cm unit 184,289
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.044 OH 200,000 8,750
1.10.28.02.01.002.001 Pekerja 0.438 OH 100,000 43,750
Jumlah Harga Tenaga Kerja 52,500
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00097 Dump Truck 0.199 jam 97,531 19,389
9.1.2.09.03.01.001.00063 Chainshaw 1.000 jam 112,400 112,400
Jumlah Harga Peralatan 131,789
Harga Satuan Pokok Kegiatan 184,289
2.01.02.01.04.011 Pekerjaan Pemotongan Pohon Pilihan Diameter 30-50 cm unit 193,984
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.044 OH 200,000 8,750
1.10.28.02.01.002.001 Pekerja 0.438 OH 100,000 43,750
Jumlah Harga Tenaga Kerja 52,500
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00097 Dump Truck 0.298 jam 97,531 29,084
9.1.2.09.03.01.001.00063 Chainshaw 1.000 jam 112,400 112,400
Jumlah Harga Peralatan 141,484
Harga Satuan Pokok Kegiatan 193,984
2.01.02.01.04.012 Pekerjaan Pemotongan Pohon Pilihan Diameter 50-75 cm unit 213,373
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.044 OH 200,000 8,750
1.10.28.02.01.002.001 Pekerja 0.438 OH 100,000 43,750
Jumlah Harga Tenaga Kerja 52,500

166
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00097 Dump Truck 0.497 jam 97,531 48,473
9.1.2.09.03.01.001.00063 Chainshaw 1.000 jam 112,400 112,400
Jumlah Harga Peralatan 160,873
Harga Satuan Pokok Kegiatan 213,373
2.01.02.01.04.013 Pekerjaan Pemotongan Pohon Pilihan Diameter >75 cm unit 297,628
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.058 OH 200,000 11,667
1.10.28.02.01.002.001 Pekerja 0.583 OH 100,000 58,334
Jumlah Harga Tenaga Kerja 70,000
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00097 Dump Truck 1.084 jam 97,531 105,753
9.1.2.09.03.01.001.00063 Chainshaw 1.084 jam 112,400 121,875
Jumlah Harga Peralatan 227,628
Harga Satuan Pokok Kegiatan 297,628
2.01.02.01.04.014 Pekerjaan Galian Perkerasan Berbutir (Tanpa Lapis Penutup Aspal) m3 133,959
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.031 OH 200,000 6,250
1.10.28.02.01.002.001 Pekerja 0.188 OH 100,000 18,750
Jumlah Harga Tenaga Kerja 25,000
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00040 Jack Hammer 0.267 jam 123,600 32,964
9.1.2.09.03.01.001.00051 Compressor 0.267 jam 202,300 53,953
9.1.2.09.03.01.001.00097 Dump Truck 0.226 jam 97,531 22,042
Jumlah Harga Peralatan 108,959
Harga Satuan Pokok Kegiatan 133,959
2.01.02.01.04.015 Pekerjaan Pemasangan Geotextile m2 42,107
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.002 OH 200,000 440
1.10.28.02.01.002.001 Pekerja 0.018 OH 100,000 1,768
Jumlah Harga Tenaga Kerja 2,208
Bahan
1.1.7.01.01.01.022.00205 Geotextile Woven - Uk. 4 x 100 m, tbl. 0,8 mm 200 gr 1.050 m2 31,400 32,970
Jumlah Harga Bahan 32,970
Peralatan
9.1.2.08.01.01.001.00053 Flatbed Truck 0.018 jam 391,500 6,930
Jumlah Harga Peralatan 6,930
Harga Satuan Pokok Kegiatan 42,107
2.01.02.01.04.016 Pekerjaan Galian Perkerasan Beton m3 171,491
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.021 OH 200,000 4,166
1.10.28.02.01.002.001 Pekerja 0.125 OH 100,000 12,500
Jumlah Harga Tenaga Kerja 16,666
Bahan
Jumlah Harga Bahan
Peralatan

167
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
9.1.2.09.03.01.001.00040 Jack Hammer 0.402 jam 123,600 49,638
9.1.2.09.03.01.001.00051 Compressor 0.402 jam 202,300 81,244
9.1.2.09.03.01.001.00097 Dump Truck 0.246 jam 97,531 23,944
Jumlah Harga Peralatan 154,825
Harga Satuan Pokok Kegiatan 171,491
2.01.02.01.05 PEKERJAAN PELABURAN PERKERASAN DAN BAHU JALAN
2.01.02.01.05.001 Pekerjaan Lapis Pondasi Agregat Kelas A m3 352,185
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 212
1.10.28.02.01.002.001 Pekerja 0.007 OH 100,000 740
Jumlah Harga Tenaga Kerja 952
Bahan
1.1.7.01.01.01.005.00029 Agregat Kelas A 1.259 m3 224,800 282,933
Jumlah Harga Bahan 282,933
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.009 jam 449,600 3,822
9.1.2.09.03.01.001.00097 Dump Truck 0.504 jam 97,531 49,185
9.1.2.09.02.01.001.00005 Motor Grader 0.009 jam 323,700 3,043
9.1.2.09.03.01.001.00019 Tandem Roller 0.012 jam 449,600 5,350
9.1.2.08.01.01.001.00005 Water Tanker 0.014 jam 489,400 6,901
Jumlah Harga Peralatan 68,300
Harga Satuan Pokok Kegiatan 352,185
2.01.02.01.05.002 Pekerjaan Lapis Pondasi Agregat Kelas B m3 351,646
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 212
1.10.28.02.01.002.001 Pekerja 0.007 OH 100,000 740
Jumlah Harga Tenaga Kerja 952
Bahan
1.1.7.01.01.01.005.00030 Agregat Kelas B 1.259 m3 224,800 282,933
Jumlah Harga Bahan 282,933
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.009 jam 449,600 3,822
9.1.2.09.03.01.001.00097 Dump Truck 0.504 jam 97,531 49,185
9.1.2.09.02.01.001.00005 Motor Grader 0.009 jam 323,700 3,043
9.1.2.09.03.01.001.00019 Tandem Roller 0.011 jam 449,600 4,811
9.1.2.08.01.01.001.00005 Water Tanker 0.014 jam 489,400 6,901
Jumlah Harga Peralatan 67,760
Harga Satuan Pokok Kegiatan 351,646
2.01.02.01.05.004 Pekerjaan Lapis Pondasi Semen Tanah m3 666,833
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.005 OH 200,000 1,000
1.10.28.02.01.002.001 Pekerja 0.679 OH 100,000 67,900
Jumlah Harga Tenaga Kerja 68,900
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 247 kg 1,000 247,000
1.1.7.01.01.01.004.00005 Tanah Urug 1.200 m3 174,900 209,880
Jumlah Harga Bahan 456,880
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.008 jam 449,600 3,597
9.1.2.09.03.01.001.00097 Dump Truck 1.023 jam 97,531 99,764
9.1.2.09.02.01.001.00005 Motor Grader 0.009 jam 323,700 3,043
9.1.2.09.03.01.001.00017 Vibratory Roller 0.027 jam 449,600 12,049

168
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.007 jam 421,500 2,740
9.1.2.09.03.01.001.00036 Cold Milling 0.014 jam 828,900 11,687
9.1.2.08.01.01.001.00005 Water Tanker 0.017 jam 489,400 8,173
Jumlah Harga Peralatan 141,053
Harga Satuan Pokok Kegiatan 666,833
2.01.02.01.05.005 Bahan Agregat Penutup Burtu m2 6,407
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0000 OH 200,000 3
1.10.28.02.01.002.001 Pekerja 0.0003 OH 100,000 30
Jumlah Harga Tenaga Kerja 33
Bahan
1.1.7.01.01.01.005.00072 Batu Pecah - Chipping 0.023 m3 228,000 5,189
Jumlah Harga Bahan 5,189
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.000 jam 449,600 45
9.1.2.09.03.01.001.00097 Dump Truck 0.009 jam 97,531 888
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.001 jam 421,500 253
Jumlah Harga Peralatan 1,185
Harga Satuan Pokok Kegiatan 6,407
2.01.02.01.05.006 Bahan Aspal untuk Pekerjaan Pelaburan liter 9,430
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0000 OH 200,000 3
1.10.28.02.01.002.001 Pekerja 0.0003 OH 100,000 30
Jumlah Harga Tenaga Kerja 33
Bahan
1.1.7.01.01.01.001.00003 Asphalt 1.079 kg 8,400 9,064
1.1.7.01.01.04.001.00008 Minyak Tanah 0.052 liter 5,000 260
Jumlah Harga Bahan 9,324
Peralatan
9.1.2.09.03.01.001.00077 Asphalt Distributor 0.0002 jam 168,600 34
9.1.2.09.03.01.001.00051 Air Compressor 0.0002 jam 202,300 40
Jumlah Harga Peralatan 74
Harga Satuan Pokok Kegiatan 9,430
2.01.02.01.05.007 Pekerjaan Lapis Resap Pengikat liter 13,620
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0001 OH 200,000 10
1.10.28.02.01.002.001 Pekerja 0.0003 OH 100,000 26
Jumlah Harga Tenaga Kerja 36
Bahan
1.1.7.01.01.01.001.00003 Asphalt 0.635 kg 8,400 5,330
1.1.7.01.01.01.001.00015 Kerosene 0.484 liter 16,900 8,180
Jumlah Harga Bahan 13,509
Peralatan
9.1.2.09.03.01.001.00077 Asphalt Distributor 0.0002 jam 168,600 34
9.1.2.09.03.01.001.00051 Air Compressor 0.0002 jam 202,300 40
Jumlah Harga Peralatan 74
Harga Satuan Pokok Kegiatan 13,620
2.01.02.01.05.008 Pekerjaan Lapis Pondasi Agregat Kelas S m3 336,327
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 212
1.10.28.02.01.002.001 Pekerja 0.007 OH 100,000 740
Jumlah Harga Tenaga Kerja 952

169
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
1.1.7.01.01.01.005.00068 Agregat Kelas S 1.259 m3 212,200 267,075
Jumlah Harga Bahan 267,075
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.009 jam 449,600 3,822
9.1.2.09.03.01.001.00097 Dump Truck 0.504 jam 97,531 49,185
9.1.2.09.02.01.001.00005 Motor Grader 0.009 jam 323,700 3,043
9.1.2.09.03.01.001.00019 Tandem Roller 0.012 jam 449,600 5,350
9.1.2.08.01.01.001.00005 Water Tanker 0.014 jam 489,400 6,901
Jumlah Harga Peralatan 68,300
Harga Satuan Pokok Kegiatan 336,327
2.01.02.01.05.009 Pekerjaan Lapis Perkerasan 5-10 cm (Padat Digilas) m2 62,498
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.038 OH 200,000 7,600
1.10.28.02.01.002.001 Pekerja 0.095 OH 100,000 9,500
Jumlah Harga Tenaga Kerja 17,100
Bahan
1.1.7.01.01.01.005.00006 Batu Belah - 15/20 cm 0.100 m3 168,600 16,860
1.1.7.01.01.01.005.00072 Batu Pecah - Chipping 0.040 m3 228,000 9,120
1.1.7.01.01.01.001.00003 Asphalt 1.500 kg 8,400 12,600
Jumlah Harga Bahan 38,580
Peralatan
9.1.2.09.03.01.001.00077 Asphalt Distributor 0.000 jam 168,600 34
9.1.2.09.03.01.001.00051 Air Compressor 0.000 jam 202,300 40
9.1.2.09.03.01.001.00017 Vibratory Roller 0.015 jam 449,600 6,744
Jumlah Harga Peralatan 6,818
Harga Satuan Pokok Kegiatan 62,498
2.01.02.01.06 PEKERJAAN PELABURAN PERKERASAN NON ASPAL
2.01.02.01.06.001 Pekerjaan Lapis Pondasi Agregat Kelas A m3 351,209
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 212
1.10.28.02.01.002.001 Pekerja 0.007 OH 100,000 740
Jumlah Harga Tenaga Kerja 952
Bahan
1.1.7.01.01.01.005.00029 Agregat Kelas A 1.259 m3 224,800 282,933
Jumlah Harga Bahan 282,933
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.009 jam 449,600 3,822
9.1.2.09.03.01.001.00097 Dump Truck 0.504 jam 97,531 49,185
9.1.2.09.02.01.001.00005 Motor Grader 0.004 jam 323,700 1,392
9.1.2.09.03.01.001.00019 Tandem Roller 0.013 jam 449,600 6,025
9.1.2.08.01.01.001.00005 Water Tanker 0.014 jam 489,400 6,901
Jumlah Harga Peralatan 67,323
Harga Satuan Pokok Kegiatan 351,209
2.01.02.01.06.002 Pekerjaan Lapis Pondasi Agregat Kelas B m3 367,687
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 212
1.10.28.02.01.002.001 Pekerja 0.007 OH 100,000 740
Jumlah Harga Tenaga Kerja 952
Bahan
1.1.7.01.01.01.005.00030 Agregat Kelas B 1.259 m3 224,800 282,933
Jumlah Harga Bahan 282,933

170
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.009 jam 449,600 3,822
9.1.2.09.03.01.001.00097 Dump Truck 0.486 jam 97,531 47,410
9.1.2.09.02.01.001.00005 Motor Grader 0.004 jam 323,700 1,392
9.1.2.09.03.01.001.00019 Tandem Roller 0.054 jam 449,600 24,278
9.1.2.08.01.01.001.00005 Water Tanker 0.014 jam 489,400 6,901
Jumlah Harga Peralatan 83,802
Harga Satuan Pokok Kegiatan 367,687
2.01.02.01.06.007 Pekerjaan Lapis Pondasi Atas Bersemen (Cement Treated Based-CTB) m3 536,836
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.019 OH 200,000 3,777
1.10.28.02.01.001.006 Tukang Batu 0.038 OH 150,000 5,648
1.10.28.02.01.002.001 Pekerja 0.132 OH 100,000 13,178
Jumlah Harga Tenaga Kerja 22,602
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 87.125 kg 1,000 87,125
1.1.7.01.01.01.005.00067 Agregat Kasar 1.259 m3 228,000 286,961
Jumlah Harga Bahan 374,086
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.024 jam 449,600 10,970
9.1.2.09.03.01.001.00078 Batching Plant 0.075 jam 950,900 71,603
9.1.2.09.03.01.001.00097 Dump Truck 0.283 jam 97,531 27,611
9.1.2.09.03.01.001.00017 Vibratory Roller 0.005 jam 449,600 2,428
9.1.2.08.01.01.001.00005 Water Tanker 0.042 jam 489,400 20,653
9.1.2.09.03.01.001.00080 Screed Paver 0.010 jam 717,100 6,884
Jumlah Harga Peralatan 140,149
Harga Satuan Pokok Kegiatan 536,836
2.01.02.01.06.008 Pekerjaan Lapis Pondasi Bawah (Cement Treated Sub-Based-CTSB) m3 564,684
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.019 OH 200,000 3,777
1.10.28.02.01.001.006 Tukang Batu 0.038 OH 150,000 5,648
1.10.28.02.01.002.001 Pekerja 0.132 OH 100,000 13,178
Jumlah Harga Tenaga Kerja 22,602
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 112.75 kg 1,000 112,750
1.1.7.01.01.01.005.00067 Agregat Kasar 1.259 m3 228,000 286,961
Jumlah Harga Bahan 399,711
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.024 jam 449,600 10,970
9.1.2.09.03.01.001.00078 Batching Plant 0.075 jam 950,900 71,603
9.1.2.09.03.01.001.00097 Dump Truck 0.283 jam 97,531 27,611
9.1.2.09.03.01.001.00017 Vibratory Roller 0.005 jam 449,600 2,428
9.1.2.08.01.01.001.00005 Water Tanker 0.042 jam 489,400 20,653
9.1.2.09.03.01.001.00080 Screed Paver 0.013 jam 717,100 9,107
Jumlah Harga Peralatan 142,372
Harga Satuan Pokok Kegiatan 564,684
2.01.02.01.06.009 Pekerjaan Lapis Pondasi Agregat Tanpa Penutup Aspal m3 344,425
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 213
1.10.28.02.01.002.001 Pekerja 0.007 OH 100,000 744
Jumlah Harga Tenaga Kerja 956
Bahan

171
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.005.00029 Agregat Kelas A 1.259 m3 224,800 282,933
Jumlah Harga Bahan 282,933
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.009 jam 449,600 3,822
9.1.2.09.03.01.001.00097 Dump Truck 0.486 jam 97,531 47,429
9.1.2.09.02.01.001.00005 Motor Grader 0.003 jam 323,700 1,036
9.1.2.09.03.01.001.00019 Tandem Roller 0.003 jam 449,600 1,349
9.1.2.08.01.01.001.00005 Water Tanker 0.014 jam 489,400 6,901
Jumlah Harga Peralatan 60,536
Harga Satuan Pokok Kegiatan 344,425
2.01.02.01.07 PEKERJAAN PELABURAN PERKERASAN ASPAL
2.01.02.01.07.001 Lapis Resap Pengikat - Aspal Cair liter 12,074
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0001 OH 200,000 10
1.10.28.02.01.002.001 Pekerja 0.0002 OH 100,000 20
Jumlah Harga Tenaga Kerja 30
Bahan
1.1.7.01.01.01.001.00003 Asphalt 0.679 kg 8,400 5,704
1.1.7.01.01.01.001.00015 Kerosene 0.371 liter 16,900 6,267
Jumlah Harga Bahan 11,970
Peralatan
9.1.2.09.03.01.001.00077 Asphalt Distributor 0.0002 jam 168,600 34
9.1.2.09.03.01.001.00051 Air Compressor 0.0002 jam 202,300 40
Jumlah Harga Peralatan 74
Harga Satuan Pokok Kegiatan 12,074
2.01.02.01.07.002 Lapis Perekat - Aspal Cair liter 10,715
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0001 OH 200,000 10
1.10.28.02.01.002.001 Pekerja 0.0002 OH 100,000 20
Jumlah Harga Tenaga Kerja 30
Bahan
1.1.7.01.01.01.001.00003 Asphalt 0.849 kg 8,400 7,129
1.1.7.01.01.01.001.00015 Kerosene 0.206 liter 16,900 3,481
Jumlah Harga Bahan 10,610
Peralatan
9.1.2.09.03.01.001.00077 Asphalt Distributor 0.0002 jam 168,600 34
9.1.2.09.03.01.001.00051 Air Compressor 0.0002 jam 202,300 40
Jumlah Harga Peralatan 74
Harga Satuan Pokok Kegiatan 10,715
2.01.02.01.07.003 Bahan Agregat Penutup Burtu m2 12,899
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0013 OH 200,000 265
1.10.28.02.01.002.001 Pekerja 0.0266 OH 100,000 2,658
Jumlah Harga Tenaga Kerja 2,923
Bahan
1.1.7.01.01.01.005.00072 Batu Pecah - Chipping 0.013 m3 228,000 2,913
Jumlah Harga Bahan 2,913
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.011 jam 449,600 4,766
9.1.2.09.03.01.001.00097 Dump Truck 0.021 jam 97,531 2,087
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.001 jam 421,500 211
Jumlah Harga Peralatan 7,064

172
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Harga Satuan Pokok Kegiatan 12,899
2.01.02.01.07.004 Bahan Agregat Penutup Burda m2 25,028
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0022 OH 200,000 440
1.10.28.02.01.002.001 Pekerja 0.0443 OH 100,000 4,430
Jumlah Harga Tenaga Kerja 4,870
Bahan
1.1.7.01.01.01.005.00072 Batu Pecah - Chipping 0.019 m3 228,000 4,433
Jumlah Harga Bahan 4,433
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.018 jam 449,600 7,958
9.1.2.09.03.01.001.00097 Dump Truck 0.032 jam 97,531 3,131
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.011 jam 421,500 4,637
Jumlah Harga Peralatan 15,725
Harga Satuan Pokok Kegiatan 25,028
2.01.02.01.07.007 Bahan Lataston Lapis Aus (HRS-WC) ton 955,879
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0024 OH 200,000 478
1.10.28.02.01.002.001 Pekerja 0.0167 OH 100,000 1,668
Jumlah Harga Tenaga Kerja 2,145
Bahan
1.1.7.01.01.01.005.00063 Agregat Pecah Mesin - Uk. 5 - 15 mm 0.244 m3 239,600 58,462
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.154 m3 244,100 37,543
1.1.7.01.01.01.004.00002 Pasir Pasang 0.248 m3 179,800 44,608
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 23.100 kg 1,000 23,100
1.1.7.01.01.01.001.00003 Asphalt 75.190 kg 8,400 631,596
Jumlah Harga Bahan 795,309
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.010 jam 449,600 4,316
9.1.2.09.03.01.001.00001 Asphalt Mixing Plant 0.020 jam 4,495,900 90,368
9.1.2.10.04.01.001.00004 Genset 0.020 jam 401,429 8,069
9.1.2.09.03.01.001.00097 Dump Truck 0.370 jam 97,531 36,067
9.1.2.09.03.01.001.00004 Asphalt Finisher 0.019 jam 562,000 10,734
9.1.2.09.03.01.001.00019 Tandem Roller 0.016 jam 449,600 7,059
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.004 jam 421,500 1,812
Jumlah Harga Peralatan 158,425
Harga Satuan Pokok Kegiatan 955,879
2.01.02.01.07.008 Bahan Lataston Lapis Aus Perata (HRS-WC L) ton 955,879
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0024 OH 200,000 478
1.10.28.02.01.002.001 Pekerja 0.0167 OH 100,000 1,668
Jumlah Harga Tenaga Kerja 2,145
Bahan
1.1.7.01.01.01.005.00063 Agregat Pecah Mesin - Uk. 5 - 15 mm 0.244 m3 239,600 58,462
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.154 m3 244,100 37,543
1.1.7.01.01.01.004.00002 Pasir Pasang 0.248 m3 179,800 44,608
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 23.100 kg 1,000 23,100
1.1.7.01.01.01.001.00003 Asphalt 75.190 kg 8,400 631,596
Jumlah Harga Bahan 795,309
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.010 jam 449,600 4,316
9.1.2.09.03.01.001.00001 Asphalt Mixing Plant 0.020 jam 4,495,900 90,368

173
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
9.1.2.10.04.01.001.00004 Genset 0.020 jam 401,429 8,069
9.1.2.09.03.01.001.00097 Dump Truck 0.370 jam 97,531 36,067
9.1.2.09.03.01.001.00004 Asphalt Finisher 0.019 jam 562,000 10,734
9.1.2.09.03.01.001.00019 Tandem Roller 0.016 jam 449,600 7,059
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.004 jam 421,500 1,812
Jumlah Harga Peralatan 158,425
Harga Satuan Pokok Kegiatan 955,879
2.01.02.01.07.009 Bahan Lataston Lapis Pondasi (HRS-BASE) ton 831,493
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0005 OH 200,000 103
1.10.28.02.01.002.001 Pekerja 0.0036 OH 100,000 358
Jumlah Harga Tenaga Kerja 460
Bahan
1.1.7.01.01.01.005.00063 Agregat Pecah Mesin - Uk. 5 - 15 mm 0.296 m3 239,600 70,874
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.140 m3 244,100 34,272
1.1.7.01.01.01.004.00002 Pasir Pasang 0.227 m3 179,800 40,725
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 15.750 kg 1,000 15,750
1.1.7.01.01.01.001.00003 Asphalt 61.800 kg 8,400 519,120
Jumlah Harga Bahan 680,740
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.010 jam 449,600 4,316
9.1.2.09.03.01.001.00001 Asphalt Mixing Plant 0.020 jam 4,495,900 90,368
9.1.2.10.04.01.001.00004 Genset 0.020 jam 401,429 8,069
9.1.2.09.03.01.001.00097 Dump Truck 0.370 jam 97,531 36,067
9.1.2.09.03.01.001.00004 Asphalt Finisher 0.004 jam 562,000 2,304
9.1.2.09.03.01.001.00019 Tandem Roller 0.016 jam 449,600 7,104
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.005 jam 421,500 2,065
Jumlah Harga Peralatan 150,293
Harga Satuan Pokok Kegiatan 831,493
2.01.02.01.07.010 Bahan Lataston Lapis Pondasi Perata (HRS-BASE L) ton 831,493
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0005 OH 200,000 103
1.10.28.02.01.002.001 Pekerja 0.0036 OH 100,000 358
Jumlah Harga Tenaga Kerja 460
Bahan
1.1.7.01.01.01.005.00063 Agregat Pecah Mesin - Uk. 5 - 15 mm 0.296 m3 239,600 70,874
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.140 m3 244,100 34,272
1.1.7.01.01.01.004.00002 Pasir Pasang 0.227 m3 179,800 40,725
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 15.750 kg 1,000 15,750
1.1.7.01.01.01.001.00003 Asphalt 61.800 kg 8,400 519,120
Jumlah Harga Bahan 680,740
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.010 jam 449,600 4,316
9.1.2.09.03.01.001.00001 Asphalt Mixing Plant 0.020 jam 4,495,900 90,368
9.1.2.10.04.01.001.00004 Genset 0.020 jam 401,429 8,069
9.1.2.09.03.01.001.00097 Dump Truck 0.370 jam 97,531 36,067
9.1.2.09.03.01.001.00004 Asphalt Finisher 0.004 jam 562,000 2,304
9.1.2.09.03.01.001.00019 Tandem Roller 0.016 jam 449,600 7,104
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.005 jam 421,500 2,065
Jumlah Harga Peralatan 150,293
Harga Satuan Pokok Kegiatan 831,493
2.01.02.01.07.011 Bahan Laston Lapis Aus (AC-WC) ton 853,037

174
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0025 OH 200,000 503
1.10.28.02.01.002.001 Pekerja 0.0251 OH 100,000 2,510
Jumlah Harga Tenaga Kerja 3,013
Bahan
1.1.7.01.01.01.005.00063 Agregat Pecah Mesin - Uk. 5 - 15 mm 0.298 m3 239,600 71,353
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.352 m3 244,100 85,996
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.870 kg 1,000 9,870
1.1.7.01.01.01.001.00003 Asphalt 62.830 kg 8,400 527,772
Jumlah Harga Bahan 694,991
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.010 jam 449,600 4,316
9.1.2.09.03.01.001.00001 Asphalt Mixing Plant 0.020 jam 4,495,900 90,368
9.1.2.10.04.01.001.00004 Genset 0.020 jam 401,429 8,069
9.1.2.09.03.01.001.00097 Dump Truck 0.370 jam 97,531 36,067
9.1.2.09.03.01.001.00004 Asphalt Finisher 0.014 jam 562,000 7,699
9.1.2.09.03.01.001.00019 Tandem Roller 0.014 jam 449,600 6,070
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.006 jam 421,500 2,445
Jumlah Harga Peralatan 155,033
Harga Satuan Pokok Kegiatan 853,037
2.01.02.01.07.012 Bahan Laston Lapis Aus Perata (AC-WC L) ton 853,037
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0025 OH 200,000 503
1.10.28.02.01.002.001 Pekerja 0.0251 OH 100,000 2,510
Jumlah Harga Tenaga Kerja 3,013
Bahan
1.1.7.01.01.01.005.00063 Agregat Pecah Mesin - Uk. 5 - 15 mm 0.298 m3 239,600 71,353
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.352 m3 244,100 85,996
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.870 kg 1,000 9,870
1.1.7.01.01.01.001.00003 Asphalt 62.830 kg 8,400 527,772
Jumlah Harga Bahan 694,991
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.010 jam 449,600 4,316
9.1.2.09.03.01.001.00001 Asphalt Mixing Plant 0.020 jam 4,495,900 90,368
9.1.2.10.04.01.001.00004 Genset 0.020 jam 401,429 8,069
9.1.2.09.03.01.001.00097 Dump Truck 0.370 jam 97,531 36,067
9.1.2.09.03.01.001.00004 Asphalt Finisher 0.014 jam 562,000 7,699
9.1.2.09.03.01.001.00019 Tandem Roller 0.014 jam 449,600 6,070
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.006 jam 421,500 2,445
Jumlah Harga Peralatan 155,033
Harga Satuan Pokok Kegiatan 853,037
2.01.02.01.07.013 Bahan Laston Lapis Antara (AC-BC) ton 807,252
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0025 OH 200,000 503
1.10.28.02.01.002.001 Pekerja 0.0251 OH 100,000 2,510
Jumlah Harga Tenaga Kerja 3,013
Bahan
1.1.7.01.01.01.005.00064 Agregat Pecah Mesin - Uk. 5 - 20 mm 0.348 m3 236,000 82,152
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.313 m3 244,100 76,330
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.450 kg 1,000 9,450
1.1.7.01.01.01.001.00003 Asphalt 57.680 kg 8,400 484,512
Jumlah Harga Bahan 652,444

175
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.010 jam 449,600 4,316
9.1.2.09.03.01.001.00001 Asphalt Mixing Plant 0.020 jam 4,495,900 90,368
9.1.2.10.04.01.001.00004 Genset 0.020 jam 401,429 8,069
9.1.2.09.03.01.001.00097 Dump Truck 0.370 jam 97,531 36,067
9.1.2.09.03.01.001.00004 Asphalt Finisher 0.011 jam 562,000 6,182
9.1.2.09.03.01.001.00019 Tandem Roller 0.011 jam 449,600 4,856
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.005 jam 421,500 1,939
Jumlah Harga Peralatan 151,796
Harga Satuan Pokok Kegiatan 807,252
2.01.02.01.07.014 Bahan Laston Lapis Antara Perata (AC-BC L) ton 807,252
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0025 OH 200,000 503
1.10.28.02.01.002.001 Pekerja 0.0251 OH 100,000 2,510
Jumlah Harga Tenaga Kerja 3,013
Bahan
1.1.7.01.01.01.005.00064 Agregat Pecah Mesin - Uk. 5 - 20 mm 0.348 m3 236,000 82,152
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.313 m3 244,100 76,330
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.450 kg 1,000 9,450
1.1.7.01.01.01.001.00003 Asphalt 57.680 kg 8,400 484,512
Jumlah Harga Bahan 652,444
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.010 jam 449,600 4,316
9.1.2.09.03.01.001.00001 Asphalt Mixing Plant 0.020 jam 4,495,900 90,368
9.1.2.10.04.01.001.00004 Genset 0.020 jam 401,429 8,069
9.1.2.09.03.01.001.00097 Dump Truck 0.370 jam 97,531 36,067
9.1.2.09.03.01.001.00004 Asphalt Finisher 0.011 jam 562,000 6,182
9.1.2.09.03.01.001.00019 Tandem Roller 0.011 jam 449,600 4,856
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.005 jam 421,500 1,939
Jumlah Harga Peralatan 151,796
Harga Satuan Pokok Kegiatan 807,252
2.01.02.01.07.015 Bahan Laston Lapis Pondasi (AC-BASE) ton 741,856
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0025 OH 200,000 503
1.10.28.02.01.002.001 Pekerja 0.0251 OH 100,000 2,510
Jumlah Harga Tenaga Kerja 3,013
Bahan
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.132 m3 258,500 34,019
1.1.7.01.01.01.005.00064 Agregat Pecah Mesin - Uk. 5 - 20 mm 0.298 m3 236,000 70,352
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.242 m3 244,100 58,975
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.975 kg 1,000 9,975
1.1.7.01.01.01.001.00003 Asphalt 49.440 kg 8,400 415,296
Jumlah Harga Bahan 588,616
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.010 jam 449,600 4,316
9.1.2.09.03.01.001.00001 Asphalt Mixing Plant 0.020 jam 4,495,900 90,368
9.1.2.10.04.01.001.00004 Genset 0.020 jam 401,429 8,069
9.1.2.09.03.01.001.00097 Dump Truck 0.370 jam 97,531 36,067
9.1.2.09.03.01.001.00004 Asphalt Finisher 0.009 jam 562,000 5,170
9.1.2.09.03.01.001.00019 Tandem Roller 0.009 jam 449,600 4,046
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.005 jam 421,500 2,192
Jumlah Harga Peralatan 150,228

176
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Harga Satuan Pokok Kegiatan 741,856
2.01.02.01.07.016 Bahan Laston Lapis Pondasi Perata (AC-BASE L) ton 741,856
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0025 OH 200,000 503
1.10.28.02.01.002.001 Pekerja 0.0251 OH 100,000 2,510
Jumlah Harga Tenaga Kerja 3,013
Bahan
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.132 m3 258,500 34,019
1.1.7.01.01.01.005.00064 Agregat Pecah Mesin - Uk. 5 - 20 mm 0.298 m3 236,000 70,352
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.242 m3 244,100 58,975
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.975 kg 1,000 9,975
1.1.7.01.01.01.001.00003 Asphalt 49.440 kg 8,400 415,296
Jumlah Harga Bahan 588,616
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.010 jam 449,600 4,316
9.1.2.09.03.01.001.00001 Asphalt Mixing Plant 0.020 jam 4,495,900 90,368
9.1.2.10.04.01.001.00004 Genset 0.020 jam 401,429 8,069
9.1.2.09.03.01.001.00097 Dump Truck 0.370 jam 97,531 36,067
9.1.2.09.03.01.001.00004 Asphalt Finisher 0.009 jam 562,000 5,170
9.1.2.09.03.01.001.00019 Tandem Roller 0.009 jam 449,600 4,046
9.1.2.09.03.01.001.00016 Pneumatic Tyre Roller 0.005 jam 421,500 2,192
Jumlah Harga Peralatan 150,228
Harga Satuan Pokok Kegiatan 741,856
2.01.02.01.07.017 Pekerjaan Campuran Aspal Dingin untuk Pelapisan m3 2,131,393
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0104 OH 200,000 2,080
1.10.28.02.01.002.001 Pekerja 0.1250 OH 100,000 12,500
Jumlah Harga Tenaga Kerja 14,580
Bahan
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 1.349 m3 244,100 329,242
1.1.7.01.01.01.001.00005 Asphalt Emultion 153.300 kg 11,200 1,716,960
Jumlah Harga Bahan 2,046,202
Peralatan
9.1.2.09.03.01.001.00008 Concrete Mixer 0.083 jam 309,100 25,757
9.1.2.09.03.01.001.00019 Tandem Roller 0.024 jam 449,600 10,835
9.1.2.09.03.01.001.00097 Dump Truck 0.349 jam 97,531 34,019
Jumlah Harga Peralatan 70,611
Harga Satuan Pokok Kegiatan 2,131,393
2.01.02.01.07.018 Pekerjaan Lapis Permukaan Penetrasi Macadam m3 1,373,348
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0018 OH 200,000 354
1.10.28.02.01.002.001 Pekerja 0.0177 OH 100,000 1,771
Jumlah Harga Tenaga Kerja 2,125
Bahan
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 1.669 m3 258,500 431,437
1.1.7.01.01.01.004.00003 Pasir Urug 0.148 m3 185,500 27,435
1.1.7.01.01.01.001.00003 Asphalt 98.586 kg 8,400 828,120
Jumlah Harga Bahan 1,286,992
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.007 jam 449,600 3,192
9.1.2.09.03.01.001.00097 Dump Truck 0.182 jam 97,531 17,780
9.1.2.09.03.01.001.00014 3-Wheel Roller 0.044 jam 303,900 13,220

177
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
9.1.2.09.03.01.001.00002 Asphalt Sprayer 0.379 jam 132,100 50,039
Jumlah Harga Peralatan 84,231
Harga Satuan Pokok Kegiatan 1,373,348
2.01.02.01.07.019 Pekerjaan Lapis Pondasi/Perata Penetrasi Macadam m3 1,455,135
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0018 OH 200,000 354
1.10.28.02.01.002.001 Pekerja 0.0177 OH 100,000 1,771
Jumlah Harga Tenaga Kerja 2,125
Bahan
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 1.775 m3 258,500 458,734
1.1.7.01.01.01.004.00003 Pasir Urug 0.247 m3 185,500 45,726
1.1.7.01.01.01.001.00003 Asphalt 103 kg 8,400 865,200
Jumlah Harga Bahan 1,369,660
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.007 jam 449,600 3,192
9.1.2.09.03.01.001.00097 Dump Truck 0.182 jam 97,531 17,780
9.1.2.09.03.01.001.00014 3-Wheel Roller 0.041 jam 303,900 12,338
9.1.2.09.03.01.001.00002 Asphalt Sprayer 0.379 jam 132,100 50,039
Jumlah Harga Peralatan 83,350
Harga Satuan Pokok Kegiatan 1,455,135
2.01.02.01.07.020 Lapis Resep Pengikat - Aspal Emulsi liter 11,762
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0001 OH 200,000 10
1.10.28.02.01.002.001 Pekerja 0.0003 OH 100,000 26
Jumlah Harga Tenaga Kerja 36
Bahan
1.1.7.01.01.01.001.00005 Asphalt Emultion 1.040 kg 11,200 11,651
Jumlah Harga Bahan 11,651
Peralatan
9.1.2.09.03.01.001.00077 Asphalt Distributor 0.0002 jam 168,600 34
9.1.2.09.03.01.001.00051 Air Compressor 0.0002 jam 202,300 40
Jumlah Harga Peralatan 74
Harga Satuan Pokok Kegiatan 11,762
2.01.02.01.07.021 Lapis Perekat - Aspal Emulsi liter 11,757
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0001 OH 200,000 10
1.10.28.02.01.002.001 Pekerja 0.0003 OH 100,000 26
Jumlah Harga Tenaga Kerja 36
Bahan
1.1.7.01.01.01.001.00005 Asphalt Emultion 0.520 kg 11,200 5,826
1.1.7.01.01.01.022.00468 Air 1.000 liter 200 200
Jumlah Harga Bahan 6,026
Peralatan
9.1.2.09.03.01.001.00077 Asphalt Distributor 0.0002 jam 168,600 34
9.1.2.09.03.01.001.00051 Air Compressor 0.0002 jam 202,300 40
9.1.2.09.03.01.001.00005 Asphalt Liquid Mixer 0.0250 jam 224,800 5,620
Jumlah Harga Peralatan 5,694
Harga Satuan Pokok Kegiatan 11,757
2.01.02.01.07.022 Aspal untuk Pekerjaan Pelaburan liter 9,416
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0001 OH 200,000 10
1.10.28.02.01.002.001 Pekerja 0.0002 OH 100,000 20

178
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Tenaga Kerja 30
Bahan
1.1.7.01.01.01.001.00003 Asphalt 0.976 kg 8,400 8,198
1.1.7.01.01.01.001.00015 Kerosene 0.066 liter 16,900 1,114
Jumlah Harga Bahan 9,312
Peralatan
9.1.2.09.03.01.001.00077 Asphalt Distributor 0.0002 jam 168,600 34
9.1.2.09.03.01.001.00051 Air Compressor 0.0002 jam 202,300 40
Jumlah Harga Peralatan 74
Harga Satuan Pokok Kegiatan 9,416
2.01.02.01.07.023 Lapis Perekat - Aspal Cair (Manual) liter 10,640
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0001 OH 200,000 10
1.10.28.02.01.002.001 Pekerja 0.0002 OH 100,000 20
Jumlah Harga Tenaga Kerja 30
Bahan
1.1.7.01.01.01.001.00003 Asphalt 0.849 kg 8,400 7,129
1.1.7.01.01.01.001.00015 Kerosene 0.206 liter 16,900 3,481
Jumlah Harga Bahan 10,610
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 10,640
2.01.02.01.07.024 Bahan Laston Lapis Aus (AC-WC) (Manual) ton 701,769
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0025 OH 200,000 503
1.10.28.02.01.001.004 Tukang 0.0251 OH 150,000 3,765
1.10.28.02.01.002.001 Pekerja 0.0251 OH 100,000 2,510
Jumlah Harga Tenaga Kerja 6,778
Bahan
1.1.7.01.01.01.005.00063 Agregat Pecah Mesin - Uk. 5 - 15 mm 0.298 m3 239,600 71,353
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.352 m3 244,100 85,996
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.870 kg 1,000 9,870
1.1.7.01.01.01.001.00003 Asphalt 62.830 kg 8,400 527,772
Jumlah Harga Bahan 694,991
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 701,769
2.01.02.01.07.025 Bahan Laston Lapis Antara (AC-BC) (Manual) ton 659,221
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.0025 OH 200,000 503
1.10.28.02.01.001.004 Tukang 0.0251 OH 150,000 3,765
1.10.28.02.01.002.001 Pekerja 0.0251 OH 100,000 2,510
Jumlah Harga Tenaga Kerja 6,778
Bahan
1.1.7.01.01.01.005.00064 Agregat Pecah Mesin - Uk. 5 - 20 mm 0.348 m3 236,000 82,152
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.313 m3 244,100 76,330
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 9.450 kg 1,000 9,450
1.1.7.01.01.01.001.00003 Asphalt 57.680 kg 8,400 484,512
Jumlah Harga Bahan 652,444
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 659,221

179
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.02.01.08 PEKERJAAN STRUKTUR JALAN
2.01.02.01.08.001 Beton Mutu Tinggi Fc'=45 Mpa m3 3,633,883
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.013 OH 200,000 2,510
1.10.28.02.01.001.006 Tukang Batu 0.226 OH 150,000 33,885
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,040
Jumlah Harga Tenaga Kerja 46,435
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 595.34 kg 1,000 595,340
1.1.7.01.01.01.004.00001 Pasir Beton 0.290 m3 230,400 66,739
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.496 m3 258,500 128,216
1.1.7.01.01.05.002.00028 Kayu Kelas III 0.400 m3 6,181,900 2,472,760
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 4.800 kg 20,200 96,960
Jumlah Harga Bahan 3,360,015
Peralatan
9.1.2.09.03.01.001.00008 Concrete Pan Mixer 0.100 jam 309,100 31,034
9.1.2.09.03.01.001.00079 Truck Mixer 0.316 jam 562,000 177,704
9.1.2.08.01.01.001.00005 Water Tank Truck 0.038 jam 489,400 18,695
Jumlah Harga Peralatan 227,433
Harga Satuan Pokok Kegiatan 3,633,883
2.01.02.01.08.002 Beton Mutu Tinggi Fc'=35 Mpa m3 3,541,313
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.013 OH 200,000 2,510
1.10.28.02.01.001.006 Tukang Batu 0.226 OH 150,000 33,885
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,040
Jumlah Harga Tenaga Kerja 46,435
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 492.34 kg 1,000 492,340
1.1.7.01.01.01.004.00001 Pasir Beton 0.335 m3 230,400 77,169
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.496 m3 258,500 128,216
1.1.7.01.01.05.002.00028 Kayu Kelas III 0.400 m3 6,181,900 2,472,760
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 4.800 kg 20,200 96,960
Jumlah Harga Bahan 3,267,445
Peralatan
9.1.2.09.03.01.001.00008 Concrete Pan Mixer 0.100 jam 309,100 31,034
9.1.2.09.03.01.001.00079 Truck Mixer 0.316 jam 562,000 177,704
9.1.2.08.01.01.001.00005 Water Tank Truck 0.038 jam 489,400 18,695
Jumlah Harga Peralatan 227,433
Harga Satuan Pokok Kegiatan 3,541,313
2.01.02.01.08.003 Beton Mutu Sedang Fc'=30 Mpa m3 3,488,191
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.013 OH 200,000 2,510
1.10.28.02.01.001.006 Tukang Batu 0.226 OH 150,000 33,885
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,040
Jumlah Harga Tenaga Kerja 46,435
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 469.68 kg 1,000 469,680
1.1.7.01.01.01.004.00001 Pasir Beton 0.343 m3 230,400 79,027
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.496 m3 258,500 128,216
1.1.7.01.01.05.002.00028 Kayu Kelas III 0.400 m3 6,181,900 2,472,760
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 3.200 kg 20,200 64,640
Jumlah Harga Bahan 3,214,323

180
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Peralatan
9.1.2.09.03.01.001.00008 Concrete Pan Mixer 0.100 jam 309,100 31,034
9.1.2.09.03.01.001.00079 Truck Mixer 0.316 jam 562,000 177,704
9.1.2.08.01.01.001.00005 Water Tank Truck 0.038 jam 489,400 18,695
Jumlah Harga Peralatan 227,433
Harga Satuan Pokok Kegiatan 3,488,191
2.01.02.01.08.004 Beton Mutu Sedang Fc'=25 Mpa m3 2,205,577
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.013 OH 200,000 2,510
1.10.28.02.01.001.006 Tukang Batu 0.138 OH 150,000 20,708
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,040
Jumlah Harga Tenaga Kerja 33,258
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 469.68 kg 1,000 469,680
1.1.7.01.01.01.004.00001 Pasir Beton 0.340 m3 230,400 78,290
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.496 m3 258,500 128,216
1.1.7.01.01.05.002.00028 Kayu Kelas III 0.200 m3 6,181,900 1,236,380
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 1.600 kg 20,200 32,320
Jumlah Harga Bahan 1,944,886
Peralatan
9.1.2.09.03.01.001.00008 Concrete Pan Mixer 0.100 jam 309,100 31,034
9.1.2.09.03.01.001.00079 Truck Mixer 0.316 jam 562,000 177,704
9.1.2.08.01.01.001.00005 Water Tank Truck 0.038 jam 489,400 18,695
Jumlah Harga Peralatan 227,433
Harga Satuan Pokok Kegiatan 2,205,577
2.01.02.01.08.005 Beton Mutu Sedang Fc'=20 Mpa m3 2,163,035
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.013 OH 200,000 2,510
1.10.28.02.01.001.006 Tukang Batu 0.138 OH 150,000 20,708
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,040
Jumlah Harga Tenaga Kerja 33,258
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 422.30 kg 1,000 422,300
1.1.7.01.01.01.004.00001 Pasir Beton 0.361 m3 230,400 83,128
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.496 m3 258,500 128,216
1.1.7.01.01.05.002.00028 Kayu Kelas III 0.200 m3 6,181,900 1,236,380
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 1.600 kg 20,200 32,320
Jumlah Harga Bahan 1,902,344
Peralatan
9.1.2.09.03.01.001.00008 Concrete Pan Mixer 0.100 jam 309,100 31,034
9.1.2.09.03.01.001.00079 Truck Mixer 0.316 jam 562,000 177,704
9.1.2.08.01.01.001.00005 Water Tank Truck 0.038 jam 489,400 18,695
Jumlah Harga Peralatan 227,433
Harga Satuan Pokok Kegiatan 2,163,035
2.01.02.01.08.006 Beton Mutu Rendah Fc'=15 Mpa m3 1,484,513
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.085 OH 200,000 17,068
1.10.28.02.01.001.006 Tukang Batu 0.171 OH 150,000 25,603
1.10.28.02.01.002.001 Pekerja 0.171 OH 100,000 17,069
Jumlah Harga Tenaga Kerja 59,739
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 327.54 kg 1,000 327,540

181
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.004.00001 Pasir Beton 0.335 m3 230,400 77,161
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.604 m3 258,500 156,005
1.1.7.01.01.05.002.00028 Kayu Kelas III 0.100 m3 6,181,900 618,190
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.800 kg 20,200 16,160
Jumlah Harga Bahan 1,195,056
Peralatan
9.1.2.09.03.01.001.00008 Concrete Pan Mixer 0.683 jam 309,100 211,023
9.1.2.08.01.01.001.00005 Water Tank Truck 0.038 jam 489,400 18,695
Jumlah Harga Peralatan 229,718
Harga Satuan Pokok Kegiatan 1,484,513
2.01.02.01.08.007 Beton Siklop Fc'=15 Mpa m3 921,948
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.085 OH 200,000 17,068
1.10.28.02.01.001.006 Tukang Batu 0.085 OH 150,000 12,801
1.10.28.02.01.002.001 Pekerja 1.024 OH 100,000 102,410
Jumlah Harga Tenaga Kerja 132,278
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 229.28 kg 1,000 229,278
1.1.7.01.01.01.004.00001 Pasir Beton 0.234 m3 230,400 54,021
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.422 m3 258,500 109,208
1.1.7.01.01.01.005.00006 Batu Belah - 15/20 cm 0.652 m3 168,600 109,893
Jumlah Harga Bahan 502,400
Peralatan
9.1.2.09.03.01.001.00008 Concrete Mixer 0.683 jam 309,100 211,023
9.1.2.08.01.01.001.00005 Water Tank Truck 0.038 jam 489,400 18,695
9.1.2.09.03.01.001.00009 Concrete Vibrator 0.683 jam 84,300 57,552
Jumlah Harga Peralatan 287,269
Harga Satuan Pokok Kegiatan 921,948
2.01.02.01.08.008 Beton Mutu Rendah Fc'=10 Mpa m3 1,152,781
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.085 OH 200,000 17,068
1.10.28.02.01.001.006 Tukang Batu 0.171 OH 150,000 25,603
1.10.28.02.01.002.001 Pekerja 0.171 OH 100,000 17,069
Jumlah Harga Tenaga Kerja 59,739
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 311.60 kg 1,000 311,600
1.1.7.01.01.01.004.00001 Pasir Beton 0.341 m3 230,400 78,536
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.604 m3 258,500 156,013
1.1.7.01.01.05.002.00028 Kayu Kelas III 0.050 m3 6,181,900 309,095
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.400 kg 20,200 8,080
Jumlah Harga Bahan 863,324
Peralatan
9.1.2.09.03.01.001.00008 Concrete Pan Mixer 0.683 jam 309,100 211,023
9.1.2.08.01.01.001.00005 Water Tank Truck 0.038 jam 489,400 18,695
Jumlah Harga Peralatan 229,718
Harga Satuan Pokok Kegiatan 1,152,781
2.01.02.01.09 PEKERJAAN BAHAN AGREGAT UNTUK PEKERJAAN MINOR
2.01.02.01.09.001 Pekerjaan Lapis Pondasi Agregat Kelas A untuk Pekerjaan Minor m3 390,487
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 176
1.10.28.02.01.002.001 Pekerja 0.022 OH 100,000 2,215
Jumlah Harga Tenaga Kerja 2,391

182
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
1.1.7.01.01.01.005.00060 Agregat Pecah Kasar 1.259 m3 260,000 327,236
Jumlah Harga Bahan 327,236
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.007 jam 449,600 3,192
9.1.2.09.03.01.001.00097 Dump Truck 0.484 jam 97,531 47,205
9.1.2.09.03.01.001.00012 Pedestrian Roller 0.053 jam 67,600 3,563
9.1.2.08.01.01.001.00005 Water Tank Truck 0.014 jam 489,400 6,901
Jumlah Harga Peralatan 60,860
Harga Satuan Pokok Kegiatan 390,487
2.01.02.01.09.002 Pekerjaan Lapis Pondasi Agregat Kelas B untuk Pekerjaan Minor m3 389,600
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 176
1.10.28.02.01.002.001 Pekerja 0.013 OH 100,000 1,328
Jumlah Harga Tenaga Kerja 1,504
Bahan
1.1.7.01.01.01.005.00060 Agregat Pecah Kasar 1.259 m3 260,000 327,236
Jumlah Harga Bahan 327,236
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.007 jam 449,600 3,192
9.1.2.09.03.01.001.00097 Dump Truck 0.484 jam 97,531 47,205
9.1.2.09.03.01.001.00012 Pedestrian Roller 0.053 jam 67,600 3,563
9.1.2.08.01.01.001.00005 Water Tank Truck 0.014 jam 489,400 6,901
Jumlah Harga Peralatan 60,860
Harga Satuan Pokok Kegiatan 389,600
2.01.02.01.09.003 Agregat Lapis Pondasi Jalan Tanpa Penutup Aspal untuk Pekerjaan Minor m3 341,470
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 212
1.10.28.02.01.002.001 Pekerja 0.016 OH 100,000 1,593
Jumlah Harga Tenaga Kerja 1,805
Bahan
1.1.7.01.01.01.005.00060 Agregat Pecah Kasar 1.200 m3 260,000 312,000
Jumlah Harga Bahan 312,000
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.009 jam 449,600 3,822
9.1.2.09.03.01.001.00097 Dump Truck 0.137 jam 97,531 13,381
9.1.2.09.03.01.001.00012 Pedestrian Roller 0.053 jam 67,600 3,563
9.1.2.08.01.01.001.00005 Water Tank Truck 0.014 jam 489,400 6,901
Jumlah Harga Peralatan 27,666
Harga Satuan Pokok Kegiatan 341,470
2.01.02.01.09.004 Pekerjaan Waterbound Macadam untuk Pekerjaan Minor m3 307,148
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 255
1.10.28.02.01.002.001 Pekerja 0.020 OH 100,000 2,038
Jumlah Harga Tenaga Kerja 2,293
Bahan
1.1.7.01.01.01.005.00060 Agregat Pecah Kasar 0.935 m3 260,000 243,100
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.165 m3 244,100 40,277
Jumlah Harga Bahan 283,377
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.010 jam 449,600 4,586
9.1.2.09.03.01.001.00097 Dump Truck 0.090 jam 97,531 8,749

183
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
9.1.2.09.03.01.001.00014 3-Wheel Roller 0.027 jam 303,900 8,145
Jumlah Harga Peralatan 21,479
Harga Satuan Pokok Kegiatan 307,148
2.01.02.01.09.005 Pekerjaan Lapis Pondasi Agregat Kelas S untuk Pekerjaan Minor m3 370,131
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 213
1.10.28.02.01.002.001 Pekerja 0.007 OH 100,000 743
Jumlah Harga Tenaga Kerja 956
Bahan
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 1.259 m3 244,100 307,224
Jumlah Harga Bahan 307,224
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.009 jam 449,600 3,822
9.1.2.09.03.01.001.00097 Dump Truck 0.486 jam 97,531 47,410
9.1.2.09.02.01.001.00005 Motor Grader 0.004 jam 323,700 1,392
9.1.2.09.03.01.001.00019 Tandem Roller 0.005 jam 449,600 2,428
9.1.2.08.01.01.001.00005 Water Tank Truck 0.014 jam 489,400 6,901
Jumlah Harga Peralatan 61,952
Harga Satuan Pokok Kegiatan 370,131
2.01.02.01.09.006 Pekerjaan Campuran Aspal Panas untuk Pekerjaan Minor m3 2,106,787
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.014 OH 200,000 2,771
1.10.28.02.01.002.001 Pekerja 0.139 OH 100,000 13,855
Jumlah Harga Tenaga Kerja 16,626
Bahan
1.1.7.01.01.01.005.00060 Agregat Pecah Kasar 0.773 m3 260,000 201,006
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.527 m3 244,100 128,665
1.1.7.01.01.01.001.00014 Filler 25.300 kg 4,000 101,200
1.1.7.01.01.01.001.00003 Asphalt 156.975 kg 8,400 1,318,590
Jumlah Harga Bahan 1,749,461
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.030 jam 449,600 13,533
9.1.2.09.03.01.001.00001 Asphalt Mixing Plant 0.055 jam 4,495,900 249,073
9.1.2.10.04.01.001.00004 Genset 0.055 jam 401,429 22,239
9.1.2.09.03.01.001.00097 Dump Truck 0.436 jam 97,531 42,504
9.1.2.09.03.01.001.00012 Pedestrian Roller 0.198 jam 67,600 13,351
Jumlah Harga Peralatan 340,700
Harga Satuan Pokok Kegiatan 2,106,787
2.01.02.01.09.007 Pekerjaan Penetrasi Macadam untuk Pekerjaan Minor m3 1,320,927
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.002 OH 200,000 425
1.10.28.02.01.002.001 Pekerja 0.021 OH 100,000 2,126
Jumlah Harga Tenaga Kerja 2,551
Bahan
1.1.7.01.01.01.005.00060 Agregat Pecah Kasar 1.478 m3 260,000 384,228
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 0.278 m3 244,100 67,811
1.1.7.01.01.01.001.00003 Asphalt 99.273 kg 8,400 833,891
Jumlah Harga Bahan 1,285,930
Peralatan
9.1.2.09.03.01.001.00029 Wheel Loader 0.009 jam 449,600 3,822
9.1.2.09.03.01.001.00097 Dump Truck 0.208 jam 97,531 20,296
9.1.2.09.03.01.001.00014 3-Wheel Roller 0.012 jam 303,900 3,586

184
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
9.1.2.09.03.01.001.00002 Asphalt Sprayer 0.036 jam 132,100 4,742
Jumlah Harga Peralatan 32,446
Harga Satuan Pokok Kegiatan 1,320,927
2.01.02.01.09.008 Pekerjaan Campuran Aspal Dingin untuk Pekerjaan Minor m3 1,960,110
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.024 OH 200,000 4,820
1.10.28.02.01.002.001 Pekerja 0.145 OH 100,000 14,458
Jumlah Harga Tenaga Kerja 19,278
Bahan
1.1.7.01.01.01.005.00062 Agregat Pecah Mesin - Uk. 0 - 5 mm 1.168 m3 244,100 285,182
1.1.7.01.01.01.001.00005 Asphalt Emultion 140.700 kg 11,200 1,575,840
Jumlah Harga Bahan 1,861,022
Peralatan
9.1.2.09.03.01.001.00008 Concrete Mixer 0.096 jam 309,100 29,797
9.1.2.09.03.01.001.00012 Pedestrian Roller 0.198 jam 67,600 13,351
9.1.2.09.03.01.001.00097 Dump Truck 0.376 jam 97,531 36,662
Jumlah Harga Peralatan 79,810
Harga Satuan Pokok Kegiatan 1,960,110
2.01.02.01.09.009 Bahan Residu Bitumen untuk Pekerjaan Minor liter 10,876
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.00004 OH 200,000 8
1.10.28.02.01.002.001 Pekerja 0.00041 OH 100,000 41
Jumlah Harga Tenaga Kerja 50
Bahan
1.1.7.01.01.01.001.00003 Asphalt 0.986 kg 8,400 8,280
1.1.7.01.01.01.001.00015 Kerosene 0.143 liter 16,900 2,417
Jumlah Harga Bahan 10,697
Peralatan
9.1.2.09.03.01.001.00002 Asphalt Sprayer 0.0003 jam 132,100 40
9.1.2.09.03.01.001.00051 Compressor 0.0003 jam 202,300 61
9.1.2.09.03.01.001.00097 Dump Truck 0.0003 jam 97,531 29
Jumlah Harga Peralatan 130
Harga Satuan Pokok Kegiatan 10,876
2.01.02.01.09.010 Pekerjaan Pemasangan Patok Pengarah unit 402,484
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.012 OH 200,000 2,305
1.10.28.02.01.001.006 Tukang Batu 0.046 OH 150,000 6,919
1.10.28.02.01.002.001 Pekerja 0.092 OH 100,000 9,225
Jumlah Harga Tenaga Kerja 18,449
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 11.595 kg 1,000 11,595
1.1.7.01.01.01.004.00001 Pasir Beton 0.012 m3 230,400 2,732
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.021 m3 258,500 5,522
1.1.7.01.01.05.002.00028 Kayu Kelas III 0.004 m3 6,181,900 21,884
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.028 kg 20,200 572
1.1.7.01.01.01.012.00007 Besi Beton 4.651 kg 10,500 48,838
Jumlah Harga Bahan 91,142
Peralatan
9.1.2.09.03.01.001.00097 Dump Truck 0.092 jam 97,531 8,992
Jumlah Harga Peralatan 8,992
Harga Satuan Pokok Kegiatan 118,583
2.01.02.01.09.011 Pekerjaan Pemasangan Patok Kilometer unit 402,484

185
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.013 OH 200,000 2,623
1.10.28.02.01.001.006 Tukang Batu 0.026 OH 150,000 3,932
1.10.28.02.01.002.001 Pekerja 0.066 OH 100,000 6,554
Jumlah Harga Tenaga Kerja 13,108
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 49.524 kg 1,000 49,524
1.1.7.01.01.01.004.00001 Pasir Beton 0.051 m3 230,400 11,668
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.091 m3 258,500 23,589
1.1.7.01.01.05.002.00028 Kayu Kelas III 0.015 m3 6,181,900 93,470
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.121 kg 20,200 2,443
1.1.7.01.01.01.012.00007 Besi Beton 18.900 kg 10,500 198,450
Jumlah Harga Bahan 379,145
Peralatan
9.1.2.09.03.01.001.00097 Dump Truck 0.105 jam 97,531 10,231
Jumlah Harga Peralatan 10,231
Harga Satuan Pokok Kegiatan 402,484
2.01.02.01.09.012 Pekerjaan Pemasangan Patok Hektometer unit 181,316
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.013 OH 200,000 2,623
1.10.28.02.01.001.006 Tukang Batu 0.026 OH 150,000 3,932
1.10.28.02.01.002.001 Pekerja 0.066 OH 100,000 6,554
Jumlah Harga Tenaga Kerja 13,108
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 20.635 kg 1,000 20,635
1.1.7.01.01.01.004.00001 Pasir Beton 0.021 m3 230,400 4,862
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.038 m3 258,500 9,829
1.1.7.01.01.05.002.00028 Kayu Kelas III 0.006 m3 6,181,900 38,946
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.050 kg 20,200 1,018
1.1.7.01.01.01.012.00007 Besi Beton 7.875 kg 10,500 82,688
Jumlah Harga Bahan 157,977
Peralatan
9.1.2.09.03.01.001.00097 Dump Truck 0.105 jam 97,531 10,231
Jumlah Harga Peralatan 10,231
Harga Satuan Pokok Kegiatan 181,316
2.01.02.01.09.013 Pekerjaan Pemasangan Paku Jalan (Solar Road Stud) unit 296,040
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.044 OH 200,000 8,750
1.10.28.02.01.001.006 Tukang Batu 0.088 OH 150,000 13,125
1.10.28.02.01.002.001 Pekerja 0.219 OH 100,000 21,875
Jumlah Harga Tenaga Kerja 43,750
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 20.635 kg 1,000 20,635
1.1.7.01.01.01.004.00001 Pasir Beton 0.021 m3 230,400 4,862
1.1.7.01.01.01.005.00008 Kerikil - Max. 30 mm 0.038 m3 258,500 9,829
1.1.7.01.01.05.002.00028 Kayu Kelas III 0.006 m3 6,181,900 38,946
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.050 kg 20,200 1,018
1.3.2.18.01.01.003.00189 Paku Jalan - Solar Road Stud 1.000 unit 177,000 177,000
Jumlah Harga Bahan 252,290
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 296,040

186
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.02.02 PEKERJAAN PENGAIRAN
2.01.02.02.02 PEKERJAAN PENGERUKAN DAN GALIAN
2.01.02.02.02.002 Pekerjaan Pengerukan Saluran (Alat Berat) m3 2,641
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.001 OH 200,000 290
1.10.28.02.01.002.001 Pekerja 0.015 OH 100,000 1,450
Jumlah Harga Tenaga Kerja 1,740
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00098 Suction Dredger 0.005 jam 191,785 901
Jumlah Harga Peralatan 901
Harga Satuan Pokok Kegiatan 2,641
2.01.02.02.02.003 Pekerjaan Galian Tanah Berbatu (Semi-Mechanic) m3 80,450
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.045 OH 200,000 9,000
1.10.28.02.01.002.001 Pekerja 0.450 OH 100,000 45,000
Jumlah Harga Tenaga Kerja 54,000
Bahan
1.1.7.01.01.04.001.00006 Solar Industri 1.250 liter 8,800 11,000
Jumlah Harga Bahan 11,000
Peralatan
9.1.2.09.03.01.001.00040 Jack Hammer 0.125 jam 123,600 15,450
Jumlah Harga Peralatan 15,450
Harga Satuan Pokok Kegiatan 80,450
2.01.02.02.02.004 Pekerjaan Galian Batu (Semi-Mechanic) m3 172,900
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.100 OH 200,000 20,000
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 120,000
Bahan
1.1.7.01.01.04.001.00006 Solar Industri 2.500 liter 8,800 22,000
Jumlah Harga Bahan 22,000
Peralatan
9.1.2.09.03.01.001.00040 Jack Hammer 0.250 jam 123,600 30,900
Jumlah Harga Peralatan 30,900
Harga Satuan Pokok Kegiatan 172,900
2.01.02.02.02.005 Pekerjaan Galian Tanah Cadas (Semi-Mechanic) m3 64,850
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.032 OH 200,000 6,400
1.10.28.02.01.002.001 Pekerja 0.320 OH 100,000 32,000
Jumlah Harga Tenaga Kerja 38,400
Bahan
1.1.7.01.01.04.001.00006 Solar Industri 1.250 liter 8,800 11,000
Jumlah Harga Bahan 11,000
Peralatan
9.1.2.09.03.01.001.00040 Jack Hammer 0.125 jam 123,600 15,450
Jumlah Harga Peralatan 15,450
Harga Satuan Pokok Kegiatan 64,850
2.01.02.02.02.006 Pekerjaan Galian Lumpur (Semi-Mechanic) m3 55,007
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.024 OH 200,000 4,800

187
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.002.001 Pekerja 0.240 OH 100,000 24,000
Jumlah Harga Tenaga Kerja 28,800
Bahan
1.1.7.01.01.04.001.00006 Solar Industri 0.900 liter 8,800 7,920
Jumlah Harga Bahan 7,920
Peralatan
9.1.2.10.07.01.001.00096 Mud Pumping Machine 0.188 jam 97,531 18,287
Jumlah Harga Peralatan 18,287
Harga Satuan Pokok Kegiatan 55,007
2.01.02.02.02.007 Pekerjaan Sumur Bor Chasing 2.5 " m' 167,475
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.038 OH 200,000 7,500
1.10.28.02.01.001.002 Kepala Tukang 0.063 OH 150,000 9,375
1.10.28.02.01.001.009 Tukang Pipa 0.063 OH 150,000 9,375
1.10.28.02.01.002.001 Pekerja 0.125 OH 100,000 12,500
Jumlah Harga Tenaga Kerja 38,750
Bahan
1.1.7.02.02.06.001.00007 Pipa PVC - Type AW Dia. 2 1/2 inch. pjg. 400 cm 0.300 batang 182,200 54,660
Jumlah Harga Bahan 54,660
Peralatan
9.1.2.09.03.01.001.00034 Sewa Alat Bantu Strouss Pile 0.500 jam 50,600 25,300
9.1.2.10.07.01.001.00096 Mud Pumping Machine 0.500 jam 97,531 48,765
Jumlah Harga Peralatan 74,065
Harga Satuan Pokok Kegiatan 167,475
2.01.02.02.02.008 Pekerjaan Sumur Bor Chasing 3" m' 190,755
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.038 OH 200,000 7,500
1.10.28.02.01.001.002 Kepala Tukang 0.063 OH 150,000 9,375
1.10.28.02.01.001.009 Tukang Pipa 0.063 OH 150,000 9,375
1.10.28.02.01.002.001 Pekerja 0.125 OH 100,000 12,500
Jumlah Harga Tenaga Kerja 38,750
Bahan
1.1.7.02.02.06.001.00008 Pipa PVC - Type AW Dia. 3 inch. pjg. 400 cm 0.300 batang 259,800 77,940
Jumlah Harga Bahan 77,940
Peralatan
9.1.2.09.03.01.001.00034 Sewa Alat Bantu Strouss Pile 0.500 jam 50,600 25,300
9.1.2.10.07.01.001.00096 Mud Pumping Machine 0.500 jam 97,531 48,765
Jumlah Harga Peralatan 74,065
Harga Satuan Pokok Kegiatan 190,755
2.01.02.02.04 PEKERJAAN CERUCUK DAN TURAP
2.01.02.02.04.006 Pekerjaan Pemasangan Turap Bambu Tinggi 1,5 m m' 167,125
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.002 OH 200,000 436
1.10.28.02.01.001.002 Kepala Tukang 0.007 OH 150,000 1,020
1.10.28.02.01.001.004 Tukang Kayu 0.022 OH 150,000 3,270
1.10.28.02.01.002.001 Pekerja 0.273 OH 100,000 27,250
Jumlah Harga Tenaga Kerja 31,976
Bahan
1.1.7.01.01.05.007.00039 Cerucuk Bambu - Dia. 12 cm, pjg. 600 cm 1.500 batang 22,500 33,750
1.1.7.01.01.05.007.00047 Gedeg Guling - Uk. 2 x 4 m 1.650 m2 59,730 98,555
1.1.7.01.01.05.001.00018 Kawat Beton 0.109 kg 26,100 2,845
Jumlah Harga Bahan 135,149

188
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 167,125
2.01.02.02.04.007 Pekerjaan Pemasangan Turap Bambu Tinggi 2,75 m m' 312,078
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.004 OH 200,000 800
1.10.28.02.01.001.002 Kepala Tukang 0.013 OH 150,000 1,875
1.10.28.02.01.001.004 Tukang Kayu 0.040 OH 150,000 6,000
1.10.28.02.01.002.001 Pekerja 0.500 OH 100,000 50,000
Jumlah Harga Tenaga Kerja 58,675
Bahan
1.1.7.01.01.05.007.00039 Cerucuk Bambu - Dia. 12 cm, pjg. 600 cm 3.000 batang 22,500 67,500
1.1.7.01.01.05.007.00047 Gedeg Guling - Uk. 2 x 4 m 3.025 m2 59,730 180,683
1.1.7.01.01.05.001.00018 Kawat Beton 0.200 kg 26,100 5,220
Jumlah Harga Bahan 253,403
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 312,078
2.01.02.02.04.008 Pekerjaan Pemancangan Tiang Pancang 30/30 m' 313,866
Tenaga Kerja
1.10.28.02.01.001.004 Tukang 0.125 OH 150,000 18,750
Jumlah Harga Tenaga Kerja 18,750
Bahan
1.1.7.01.01.01.011.00003 Tiang Pancang - Beton Uk. 30/30 1.000 m' 196,700 196,700
Jumlah Harga Bahan 196,700
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.218 jam 161,150 35,131
9.1.2.09.03.01.001.00042 Sheet Pile Hammer 0.218 jam 290,300 63,285
Jumlah Harga Peralatan 98,416
Harga Satuan Pokok Kegiatan 313,866

2.02 HSPK FISIK NON KONSTRUKSI

2.02.03 SARANA DAN PRASARANA KOTA

2.02.03.01 PEKERJAAN PENERANGAN JALAN UMUM

2.02.03.01.01 PEKERJAAN ELEKTRIKAL DAN PENERANGAN JALAN UMUM (PJU)


2.02.03.01.01.004 Pekerjaan Pemasangan Konektor Kabel Unit 31,800
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.010 OH 150,000 1,500
Jumlah Harga Tenaga Kerja 1,500
Bahan
1.1.7.01.03.08.012.00020 Konektor Kabel 1.000 buah 30,300 30,300
Jumlah Harga Bahan 30,300
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 31,800
2.02.03.01.01.005 Pekerjaan Penarikan Kabel m' 5,000
Tenaga Kerja
1.10.28.02.01.002.001 Pekerja 0.050 OH 100,000 5,000
Jumlah Harga Tenaga Kerja 5,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan

189
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Harga Satuan Pokok Kegiatan 5,000
2.02.03.01.01.006 Pekerjaan Penarikan Kabel Bawah Tanah (Bore Machine) m' 430,300
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 150,000
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00037 Horizntal Direction Drilling (HDD) Machine 0.500 jam 560,600 280,300
Jumlah Harga Peralatan 280,300
Harga Satuan Pokok Kegiatan 430,300
2.02.03.01.01.007 Pekerjaan Pemasangan Panel Meter/Panel Lampu PJU Unit 243,600
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.400 OH 150,000 60,000
1.10.28.02.01.002.001 Pekerja 0.800 OH 100,000 80,000
Jumlah Harga Tenaga Kerja 140,000
Bahan
1.1.7.01.03.08.001.00046 Kabel Gland - PG-7 1.000 buah 1,900 1,900
1.1.7.01.03.08.001.00045 Kabel Gland - PG-21 2.000 buah 7,000 14,000
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 1.000 buah 87,700 87,700
Jumlah Harga Bahan 103,600
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 243,600
2.02.03.01.01.008 Pekerjaan Pemasangan Pipa untuk Kabel Tanam m' 100,975
Tenaga Kerja
1.10.28.02.01.001.009 Tukang Pipa 0.002 OH 150,000 300
1.10.28.02.01.002.001 Pekerja 0.060 OH 100,000 6,000
Jumlah Harga Tenaga Kerja 6,300
Bahan
1.1.7.02.02.06.001.00009 Pipa PVC - Type AW Dia. 4 inch. pjg. 400 cm 0.250 batang 378,700 94,675
Jumlah Harga Bahan 94,675
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 100,975
2.02.03.01.01.015 Pekerjaan Instalasi Tarikan Kabel Udara m' 99,540
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.025 OH 150,000 3,750
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 78,750
Bahan
1.1.7.01.03.08.001.00009 Kabel NYM - 2 x 2.5 mm 1.100 m' 18,900 20,790
Jumlah Harga Bahan 20,790
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 99,540
2.02.03.01.01.020 Roll Pipa 1,5 inch unit 120,805
Tenaga Kerja
1.10.28.02.01.001.008 Tukang Besi 0.107 OH 150,000 16,005
1.10.28.02.01.002.001 Pekerja 0.213 OH 100,000 21,300
Jumlah Harga Tenaga Kerja 37,305

190
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00054 Steel Pipe Bender Machine 1.000 jam 83,500 83,500
Jumlah Harga Peralatan 83,500
Harga Satuan Pokok Kegiatan 120,805
2.02.03.01.01.021 Roll Pipa 2 inch unit 130,165
Tenaga Kerja
1.10.28.02.01.001.008 Tukang Besi 0.133 OH 150,000 19,995
1.10.28.02.01.002.001 Pekerja 0.267 OH 100,000 26,670
Jumlah Harga Tenaga Kerja 46,665
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00054 Steel Pipe Bender Machine 1.000 jam 83,500 83,500
Jumlah Harga Peralatan 83,500
Harga Satuan Pokok Kegiatan 130,165
2.02.03.01.01.022 Roll Pipa 3 inch unit 171,000
Tenaga Kerja
1.10.28.02.01.001.008 Tukang Besi 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.500 OH 100,000 50,000
Jumlah Harga Tenaga Kerja 87,500
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00054 Steel Pipe Bender Machine 1.000 jam 83,500 83,500
Jumlah Harga Peralatan 83,500
Harga Satuan Pokok Kegiatan 171,000
2.02.03.01.01.023 Roll Pipa 4 inch unit 223,500
Tenaga Kerja
1.10.28.02.01.001.008 Tukang Besi 0.400 OH 150,000 60,000
1.10.28.02.01.002.001 Pekerja 0.800 OH 100,000 80,000
Jumlah Harga Tenaga Kerja 140,000
Bahan
Jumlah Harga Bahan
Peralatan
9.1.2.09.03.01.001.00054 Steel Pipe Bender Machine 1.000 jam 83,500 83,500
Jumlah Harga Peralatan 83,500
Harga Satuan Pokok Kegiatan 223,500
2.02.03.01.01.024 Pekerjaan Pemasangan Ornamen Tiang Panjang 1,5 m unit 612,167
Tenaga Kerja
1.10.28.02.01.001.008 Tukang Besi 0.333 OH 150,000 49,950
1.10.28.02.01.002.001 Pekerja 0.667 OH 100,000 66,670
Jumlah Harga Tenaga Kerja 116,620
Bahan
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4 mm 0.250 batang 884,900 221,225
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 0.050 m2 308,440 15,422
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 2.000 buah 87,700 175,400
Jumlah Harga Bahan 412,047
Peralatan
9.1.2.09.03.01.001.00054 Steel Pipe Bender Machine 1.000 jam 83,500 83,500
Jumlah Harga Peralatan 83,500

191
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Harga Satuan Pokok Kegiatan 612,167
2.02.03.01.01.025 Pekerjaan Pemasangan Ornamen Tiang Panjang 2 m unit 685,614
Tenaga Kerja
1.10.28.02.01.001.008 Tukang Besi 0.333 OH 150,000 49,950
1.10.28.02.01.002.001 Pekerja 0.667 OH 100,000 66,670
Jumlah Harga Tenaga Kerja 116,620
Bahan
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4 mm 0.333 batang 884,900 294,672
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 0.050 m2 308,440 15,422
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 2.000 buah 87,700 175,400
Jumlah Harga Bahan 485,494
Peralatan
9.1.2.09.03.01.001.00054 Steel Pipe Bender Machine 1.000 jam 83,500 83,500
Jumlah Harga Peralatan 83,500
Harga Satuan Pokok Kegiatan 685,614
2.02.03.01.01.026 Pekerjaan Pemasangan Ornamen Tiang Panjang 3 m unit 1,244,656
Tenaga Kerja
1.10.28.02.01.001.008 Tukang Besi 0.333 OH 150,000 49,950
1.10.28.02.01.002.001 Pekerja 0.667 OH 100,000 66,670
Jumlah Harga Tenaga Kerja 116,620
Bahan
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4 mm 0.500 batang 884,900 442,450
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 0.050 m2 308,440 15,422
1.1.7.01.01.01.008.00025 Plat Besi - Uk. 30 x 30 cm, Tbl. 15 mm 28.560 kg 14,400 411,264
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 2.000 buah 87,700 175,400
Jumlah Harga Bahan 1,044,536
Peralatan
Steel Pipe Bender Machine 1.000 jam 83,500 83,500
Jumlah Harga Peralatan 83,500
Harga Satuan Pokok Kegiatan 1,244,656
2.02.03.01.01.027 Pekerjaan Pemasangan Ornamen Tiang Panjang 6 m unit 1,863,362
Tenaga Kerja
1.10.28.02.01.001.008 Tukang Besi 0.333 OH 150,000 49,950
1.10.28.02.01.002.001 Pekerja 0.667 OH 100,000 66,670
Jumlah Harga Tenaga Kerja 116,620
Bahan
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4 mm 1.000 batang 884,900 884,900
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 0.050 m2 308,440 15,422
1.1.7.01.01.01.008.00025 Plat Besi - Uk. 30 x 30 cm, Tbl. 15 mm 40.800 kg 14,400 587,520
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 2.000 buah 87,700 175,400
Jumlah Harga Bahan 1,663,242
Peralatan
Steel Pipe Bender Machine 1.000 jam 83,500 83,500
Jumlah Harga Peralatan 83,500
Harga Satuan Pokok Kegiatan 1,863,362
2.02.03.01.01.028 Pekerjaan Pemasangan Panel Lampu PJU 1 Phase 4400 VA unit 3,021,340
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.900 OH 150,000 135,000
1.10.28.02.01.002.001 Pekerja 1.300 OH 100,000 130,000
Jumlah Harga Tenaga Kerja 265,000
Bahan
1.1.7.01.01.01.022.00508 Panel kWh Meter - 1 Phase 1.000 buah 571,300 571,300

192
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.3.2.18.01.01.003.00047 MCB C60N - 1 Phase, 6 A 1.000 buah 104,000 104,000
1.3.2.18.01.01.003.00048 MCB C60N - 1 Phase, 10 A 3.000 buah 104,000 312,000
1.3.2.18.01.01.003.00053 MCB C60N - 1 Phase, 40 A 2.000 buah 137,100 274,200
1.1.7.01.03.08.012.00028 Magnet Contactor LC1 D12 - 25 A 1.000 buah 278,400 278,400
1.1.7.01.03.08.012.00031 Time Switch SUL 181 D 1.000 buah 523,000 523,000
1.1.7.01.03.08.001.00046 Kabel Gland - PG-7 1.000 buah 1,900 1,900
1.1.7.01.03.08.001.00045 Kabel Gland - PG-21 4.000 buah 7,000 28,000
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm (for ARDE) 3.000 batang 31,400 94,200
1.1.7.02.02.07.001.00258 Elbow Pipa PVC - Type C Dia. 1/2 inch 2.000 buah 11,400 22,800
1.1.7.01.01.01.022.00528 Stainless Tie + Clip + Ring 3.000 buah 14,080 42,240
1.1.7.01.03.08.001.00034 Kabel Twisted - 2 x 10 mm, XLPE 3.000 m' 6,700 20,100
1.3.2.18.01.01.003.00201 Grounding Rod + Steel Wire - Uk. 16 mm (for ARDE) 1.000 buah 396,500 396,500
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 1.000 buah 87,700 87,700
Jumlah Harga Bahan 2,756,340
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 3,021,340
2.02.03.01.01.029 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 6600 VA unit 5,256,640
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.900 OH 150,000 135,000
1.10.28.02.01.002.001 Pekerja 1.300 OH 100,000 130,000
Jumlah Harga Tenaga Kerja 265,000
Bahan
1.1.7.01.01.01.022.00509 Panel kWh Meter - 3 Phase 1.000 buah 1,138,500 1,138,500
1.1.7.01.03.08.002.00049 Pilot Lamp 3.000 buah 43,500 130,500
1.3.2.18.01.01.003.00047 MCB C60N - 1 Phase, 6 A 1.000 buah 104,000 104,000
1.3.2.18.01.01.003.00048 MCB C60N - 1 Phase, 10 A 6.000 buah 104,000 624,000
1.3.2.18.01.01.003.00069 MCB C60N - 3 Phase, 25 A 2.000 buah 451,800 903,600
1.1.7.01.03.08.012.00029 Magnet Contactor LC1 D40 - 40 A 1.000 buah 874,600 874,600
1.1.7.01.03.08.012.00031 Time Switch SUL 181 D 1.000 buah 523,000 523,000
1.1.7.01.03.08.001.00046 Kabel Gland - PG-7 1.000 buah 1,900 1,900
1.1.7.01.03.08.001.00045 Kabel Gland - PG-21 4.000 buah 7,000 28,000
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm (for ARDE) 3.000 batang 31,400 94,200
1.1.7.02.02.07.001.00258 Elbow Pipa PVC - Type C Dia. 1/2 inch 2.000 buah 11,400 22,800
1.1.7.01.01.01.022.00528 Stainless Tie + Clip + Ring 3.000 buah 14,080 42,240
1.1.7.01.03.08.001.00034 Kabel Twisted - 2 x 10 mm, XLPE 3.000 m' 6,700 20,100
1.3.2.18.01.01.003.00201 Grounding Rod + Steel Wire - Uk. 16 mm (for ARDE) 1.000 buah 396,500 396,500
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 1.000 buah 87,700 87,700
Jumlah Harga Bahan 4,991,640
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 5,256,640
2.02.03.01.01.030 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 10600 VA unit 5,256,640
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.900 OH 150,000 135,000
1.10.28.02.01.002.001 Pekerja 1.300 OH 100,000 130,000
Jumlah Harga Tenaga Kerja 265,000
Bahan
1.1.7.01.01.01.022.00509 Panel kWh Meter - 3 Phase 1.000 buah 1,138,500 1,138,500
1.1.7.01.03.08.002.00049 Pilot Lamp 3.000 buah 43,500 130,500
1.3.2.18.01.01.003.00047 MCB C60N - 1 Phase, 6 A 1.000 buah 104,000 104,000
1.3.2.18.01.01.003.00049 MCB C60N - 1 Phase, 16 A 6.000 buah 104,000 624,000

193
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.3.2.18.01.01.003.00069 MCB C60N - 3 Phase, 25 A 2.000 buah 451,800 903,600
1.1.7.01.03.08.012.00029 Magnet Contactor LC1 D40 - 40 A 1.000 buah 874,600 874,600
1.1.7.01.03.08.012.00031 Time Switch SUL 181 D 1.000 buah 523,000 523,000
1.1.7.01.03.08.001.00046 Kabel Gland - PG-7 1.000 buah 1,900 1,900
1.1.7.01.03.08.001.00045 Kabel Gland - PG-21 4.000 buah 7,000 28,000
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm (for ARDE) 3.000 batang 31,400 94,200
1.1.7.02.02.07.001.00258 Elbow Pipa PVC - Type C Dia. 1/2 inch 2.000 buah 11,400 22,800
1.1.7.01.01.01.022.00528 Stainless Tie + Clip + Ring 3.000 buah 14,080 42,240
1.1.7.01.03.08.001.00034 Kabel Twisted - 2 x 10 mm, XLPE 3.000 m' 6,700 20,100
1.3.2.18.01.01.003.00201 Grounding Rod + Steel Wire - Uk. 16 mm (for ARDE) 1.000 buah 396,500 396,500
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 1.000 buah 87,700 87,700
Jumlah Harga Bahan 4,991,640
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 5,256,640
2.02.03.01.01.031 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 13200 VA unit 5,337,640
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.900 OH 150,000 135,000
1.10.28.02.01.002.001 Pekerja 1.300 OH 100,000 130,000
Jumlah Harga Tenaga Kerja 265,000
Bahan
1.1.7.01.01.01.022.00509 Panel kWh Meter - 3 Phase 1.000 buah 1,138,500 1,138,500
1.1.7.01.03.08.002.00049 Pilot Lamp 3.000 buah 43,500 130,500
1.3.2.18.01.01.003.00047 MCB C60N - 1 Phase, 6 A 1.000 buah 104,000 104,000
1.3.2.18.01.01.003.00049 MCB C60N - 1 Phase, 16 A 6.000 buah 104,000 624,000
1.3.2.18.01.01.003.00071 MCB C60N - 3 Phase, 40 A 2.000 buah 492,300 984,600
1.1.7.01.03.08.012.00029 Magnet Contactor LC1 D40 - 40 A 1.000 buah 874,600 874,600
1.1.7.01.03.08.012.00031 Time Switch SUL 181 D 1.000 buah 523,000 523,000
1.1.7.01.03.08.001.00046 Kabel Gland - PG-7 1.000 buah 1,900 1,900
1.1.7.01.03.08.001.00045 Kabel Gland - PG-21 4.000 buah 7,000 28,000
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm (for ARDE) 3.000 batang 31,400 94,200
1.1.7.02.02.07.001.00258 Elbow Pipa PVC - Type C Dia. 1/2 inch 2.000 buah 11,400 22,800
1.1.7.01.01.01.022.00528 Stainless Tie + Clip + Ring 3.000 buah 14,080 42,240
1.1.7.01.03.08.001.00034 Kabel Twisted - 2 x 10 mm, XLPE 3.000 m' 6,700 20,100
1.3.2.18.01.01.003.00201 Grounding Rod + Steel Wire - Uk. 16 mm (for ARDE) 1.000 buah 396,500 396,500
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 1.000 buah 87,700 87,700
Jumlah Harga Bahan 5,072,640
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 5,337,640
2.02.03.01.01.032 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 16500 VA unit 5,337,640
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.900 OH 150,000 135,000
1.10.28.02.01.002.001 Pekerja 1.300 OH 100,000 130,000
Jumlah Harga Tenaga Kerja 265,000
Bahan
1.1.7.01.01.01.022.00509 Panel kWh Meter - 3 Phase 1.000 buah 1,138,500 1,138,500
1.1.7.01.03.08.002.00049 Pilot Lamp 3.000 buah 43,500 130,500
1.3.2.18.01.01.003.00047 MCB C60N - 1 Phase, 6 A 1.000 buah 104,000 104,000
1.3.2.18.01.01.003.00049 MCB C60N - 1 Phase, 16 A 6.000 buah 104,000 624,000
1.3.2.18.01.01.003.00071 MCB C60N - 3 Phase, 40 A 2.000 buah 492,300 984,600
1.1.7.01.03.08.012.00029 Magnet Contactor LC1 D40 - 40 A 1.000 buah 874,600 874,600

194
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.03.08.012.00031 Time Switch SUL 181 D 1.000 buah 523,000 523,000
1.1.7.01.03.08.001.00046 Kabel Gland - PG-7 1.000 buah 1,900 1,900
1.1.7.01.03.08.001.00045 Kabel Gland - PG-21 4.000 buah 7,000 28,000
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm (for ARDE) 3.000 batang 31,400 94,200
1.1.7.02.02.07.001.00258 Elbow Pipa PVC - Type C Dia. 1/2 inch 2.000 buah 11,400 22,800
1.1.7.01.01.01.022.00528 Stainless Tie + Clip + Ring 3.000 buah 14,080 42,240
1.1.7.01.03.08.001.00034 Kabel Twisted - 2 x 10 mm, XLPE 3.000 m' 6,700 20,100
1.3.2.18.01.01.003.00201 Grounding Rod + Steel Wire - Uk. 16 mm (for ARDE) 1.000 buah 396,500 396,500
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 1.000 buah 87,700 87,700
Jumlah Harga Bahan 5,072,640
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 5,337,640
2.02.03.01.01.033 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 23000 VA unit 6,096,240
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.900 OH 150,000 135,000
1.10.28.02.01.002.001 Pekerja 1.300 OH 100,000 130,000
Jumlah Harga Tenaga Kerja 265,000
Bahan
1.1.7.01.01.01.022.00509 Panel kWh Meter - 3 Phase 1.000 buah 1,138,500 1,138,500
1.1.7.01.03.08.002.00049 Pilot Lamp 3.000 buah 43,500 130,500
1.3.2.18.01.01.003.00047 MCB C60N - 1 Phase, 6 A 1.000 buah 104,000 104,000
1.3.2.18.01.01.003.00051 MCB C60N - 1 Phase, 25 A 6.000 buah 115,800 694,800
1.3.2.18.01.01.003.00073 MCB C60N - 3 Phase, 63 A 2.000 buah 836,200 1,672,400
1.1.7.01.03.08.012.00029 Magnet Contactor LC1 D40 - 40 A 1.000 buah 874,600 874,600
1.1.7.01.03.08.012.00031 Time Switch SUL 181 D 1.000 buah 523,000 523,000
1.1.7.01.03.08.001.00046 Kabel Gland - PG-7 1.000 buah 1,900 1,900
1.1.7.01.03.08.001.00045 Kabel Gland - PG-21 4.000 buah 7,000 28,000
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm (for ARDE) 3.000 batang 31,400 94,200
1.1.7.02.02.07.001.00258 Elbow Pipa PVC - Type C Dia. 1/2 inch 2.000 buah 11,400 22,800
1.1.7.01.01.01.022.00528 Stainless Tie + Clip + Ring 3.000 buah 14,080 42,240
1.1.7.01.03.08.001.00034 Kabel Twisted - 2 x 10 mm, XLPE 3.000 m' 6,700 20,100
1.3.2.18.01.01.003.00201 Grounding Rod + Steel Wire - Uk. 16 mm (for ARDE) 1.000 buah 396,500 396,500
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 1.000 buah 87,700 87,700
Jumlah Harga Bahan 5,831,240
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 6,096,240
2.02.03.01.01.034 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 33000 VA unit 6,335,640
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.900 OH 150,000 135,000
1.10.28.02.01.002.001 Pekerja 1.300 OH 100,000 130,000
Jumlah Harga Tenaga Kerja 265,000
Bahan
1.1.7.01.01.01.022.00509 Panel kWh Meter - 3 Phase 1.000 buah 1,138,500 1,138,500
1.1.7.01.03.08.002.00049 Pilot Lamp 3.000 buah 43,500 130,500
1.3.2.18.01.01.003.00047 MCB C60N - 1 Phase, 6 A 1.000 buah 104,000 104,000
1.3.2.18.01.01.003.00051 MCB C60N - 1 Phase, 25 A 6.000 buah 115,800 694,800
1.3.2.18.01.01.003.00232 MCB C120N - 3 Phase, 100 A 2.000 buah 955,900 1,911,800
1.1.7.01.03.08.012.00029 Magnet Contactor LC1 D40 - 40 A 1.000 buah 874,600 874,600
1.1.7.01.03.08.012.00031 Time Switch SUL 181 D 1.000 buah 523,000 523,000
1.1.7.01.03.08.001.00046 Kabel Gland - PG-7 1.000 buah 1,900 1,900

195
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.03.08.001.00045 Kabel Gland - PG-21 4.000 buah 7,000 28,000
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm (for ARDE) 3.000 batang 31,400 94,200
1.1.7.02.02.07.001.00258 Elbow Pipa PVC - Type C Dia. 1/2 inch 2.000 buah 11,400 22,800
1.1.7.01.01.01.022.00528 Stainless Tie + Clip + Ring 3.000 buah 14,080 42,240
1.1.7.01.03.08.001.00034 Kabel Twisted - 2 x 10 mm, XLPE 3.000 m' 6,700 20,100
1.3.2.18.01.01.003.00201 Grounding Rod + Steel Wire - Uk. 16 mm (for ARDE) 1.000 buah 396,500 396,500
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 1.000 buah 87,700 87,700
Jumlah Harga Bahan 6,070,640
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 6,335,640
2.02.03.01.01.035 Pekerjaan Pengecatan Tiang PJU unit 321,839
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.040 OH 200,000 8,000
1.10.28.02.01.001.002 Kepala Tukang 0.100 OH 150,000 15,000
1.10.28.02.01.001.005 Tukang Cat 1.000 OH 150,000 150,000
1.10.28.02.01.002.001 Pekerja 0.700 OH 100,000 70,000
Jumlah Harga Tenaga Kerja 243,000
Bahan
1.1.7.01.01.01.006.00006 Cat Meni Besi 0.408 kg 58,400 23,827
1.1.7.01.01.01.006.00001 Cat Besi 0.408 kg 61,800 25,214
1.1.7.01.01.01.006.00041 Thinner 0.004 liter 27,800 97
1.1.7.01.01.01.022.00225 Amplas - No. 500 2.000 lembar 5,600 11,200
1.1.7.01.01.01.022.00249 Kuas - Uk. 4" 1.000 buah 18,500 18,500
Jumlah Harga Bahan 78,839
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 321,839
2.02.03.01.01.036 Pekerjaan Pemasangan Tiang Biasa 5 m Cabang 1 unit 1,607,975
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.250 OH 150,000 37,500
1.10.28.02.01.001.008 Tukang Besi 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 150,000
Bahan
1.3.2.18.01.01.003.00118 Tiang Biasa - Tinggi 5 m, Single Arm 1.000 unit 1,377,400 1,377,400
Jumlah Harga Bahan 1,377,400
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 1,607,975
2.02.03.01.01.037 Pekerjaan Pemasangan Tiang Biasa 7 m Cabang 1 unit 2,096,975
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.250 OH 150,000 37,500
1.10.28.02.01.001.008 Tukang Besi 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 150,000
Bahan
1.3.2.18.01.01.003.00119 Tiang Biasa - Tinggi 7 m, Single Arm 1.000 unit 1,866,400 1,866,400
Jumlah Harga Bahan 1,866,400
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575

196
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 2,096,975
2.02.03.01.01.038 Pekerjaan Pemasangan Tiang Biasa 5 m Cabang 2 unit 1,718,215
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.250 OH 150,000 37,500
1.10.28.02.01.001.008 Tukang Besi 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 150,000
Bahan
1.3.2.18.01.01.003.00235 Tiang Biasa - Tinggi 5 m, Double Arms 1.000 unit 1,487,640 1,487,640
Jumlah Harga Bahan 1,487,640
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 1,718,215
2.02.03.01.01.039 Pekerjaan Pemasangan Tiang Biasa 7 m Cabang 2 unit 2,239,575
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.250 OH 150,000 37,500
1.10.28.02.01.001.008 Tukang Besi 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 150,000
Bahan
1.3.2.18.01.01.003.00121 Tiang Biasa - Tinggi 7 m, Double Arms 1.000 unit 2,009,000 2,009,000
Jumlah Harga Bahan 2,009,000
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 2,239,575
2.02.03.01.01.040 Pekerjaan Pemasangan Tiang Biasa 7 m Cabang 4 unit 2,475,895
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.250 OH 150,000 37,500
1.10.28.02.01.001.008 Tukang Besi 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 150,000
Bahan
1.3.2.18.01.01.003.00236 Tiang Biasa - Tinggi 7 m, Quad Arms 1.000 unit 2,245,320 2,245,320
Jumlah Harga Bahan 2,245,320
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 2,475,895
2.02.03.01.01.041 Pekerjaan Pondasi Biasa PJU unit 1,108,536
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.065 OH 200,000 13,000
1.10.28.02.01.001.002 Kepala Tukang 0.125 OH 150,000 18,750
1.10.28.02.01.001.006 Tukang Batu 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 169,250
Bahan
1.1.7.01.01.01.008.00077 Angkur - Dia. 19 mm, pjg. 60 cm + Mur + Ring 4.000 buah 54,300 217,200
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm 0.500 batang 31,400 15,700
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 2.366 kg 10,500 24,843

197
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.050 m3 6,181,900 309,095
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.500 kg 20,200 10,100
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 145.036 kg 1,000 145,036
1.1.7.01.01.01.004.00001 Pasir Beton 0.337 m3 230,400 77,645
1.1.7.01.01.01.004.00004 Pasir Sirtu 0.096 m3 224,800 21,581
1.1.7.01.01.01.005.00004 Batu Pecah 0.420 m3 264,100 110,922
Jumlah Harga Bahan 932,122
Peralatan
9.1.2.09.03.01.001.00021 Vibro Roller 0.015 jam 168,500 2,528
9.1.2.09.03.01.001.00008 Concrete Mixer 0.015 jam 309,100 4,637
Jumlah Harga Peralatan 7,164
Harga Satuan Pokok Kegiatan 1,108,536
2.02.03.01.01.042 Pekerjaan Pondasi Strouss PJU unit 1,514,192
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.065 OH 200,000 13,000
1.10.28.02.01.001.002 Kepala Tukang 0.125 OH 150,000 18,750
1.10.28.02.01.001.006 Tukang Batu 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 169,250
Bahan
1.1.7.01.01.01.008.00077 Angkur - Dia. 19 mm, pjg. 60 cm + Mur + Ring 4.000 buah 54,300 217,200
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm 0.500 batang 31,400 15,700
1.1.7.01.01.01.012.00007 Besi Beton - Polos/Ulir 25.758 kg 10,500 270,459
1.1.7.01.01.05.002.00030 Kayu Kelas III - Papan 0.050 m3 6,181,900 309,095
1.1.7.01.01.01.022.00104 Paku Biasa - Uk. 2 - 5 inch 0.500 kg 20,200 10,100
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 175.396 kg 1,000 175,396
1.1.7.01.01.01.004.00001 Pasir Beton 0.488 m3 230,400 112,435
1.1.7.01.01.01.004.00004 Pasir Sirtu 0.096 m3 224,800 21,581
1.1.7.01.01.01.005.00004 Batu Pecah 0.420 m3 264,100 110,922
1.1.7.01.01.01.008.00010 Plat Strip - Uk. 0.3 x 2 cm 0.400 batang 52,800 21,120
1.1.7.01.01.05.001.00018 Kawat Beton 0.500 kg 26,100 13,050
Jumlah Harga Bahan 1,277,058
Peralatan
9.1.2.09.03.01.001.00034 Strouss Bore 1.200 jam 50,600 60,720
9.1.2.09.03.01.001.00021 Vibro Roller 0.015 jam 168,500 2,528
9.1.2.09.03.01.001.00008 Concrete Mixer 0.015 jam 309,100 4,637
Jumlah Harga Peralatan 67,884
Harga Satuan Pokok Kegiatan 1,514,192
2.02.03.01.01.043 Pekerjaan Pemasangan Tiang Oktagonal 5 m Single HDG unit 2,602,175
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.250 OH 150,000 37,500
1.10.28.02.01.001.008 Tukang Besi 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 150,000
Bahan
1.3.2.18.01.01.003.00074 Tiang Oktagonal - Single Hot-Dipped Galvanized, Tinggi 5 m 1.000 unit 2,371,600 2,371,600
Jumlah Harga Bahan 2,371,600
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 2,602,175
2.02.03.01.01.044 Pekerjaan Pemasangan Tiang Oktagonal 5 m Double HDG unit 2,961,875

198
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.250 OH 150,000 37,500
1.10.28.02.01.001.008 Tukang Besi 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 150,000
Bahan
1.3.2.18.01.01.003.00075 Tiang Oktagonal - Double Hot-Dipped Galvanized, Tinggi 5 m 1.000 unit 2,731,300 2,731,300
Jumlah Harga Bahan 2,731,300
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 2,961,875
2.02.03.01.01.045 Pekerjaan Pemasangan Tiang Oktagonal 7 m Single HDG unit 2,776,375
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.250 OH 150,000 37,500
1.10.28.02.01.001.008 Tukang Besi 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 150,000
Bahan
1.3.2.18.01.01.003.00076 Tiang Oktagonal - Single Hot-Dipped Galvanized, Tinggi 7 m 1.000 unit 2,545,800 2,545,800
Jumlah Harga Bahan 2,545,800
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 2,776,375
2.02.03.01.01.046 Pekerjaan Pemasangan Tiang Oktagonal 7 m Double HDG unit 3,315,875
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.250 OH 150,000 37,500
1.10.28.02.01.001.008 Tukang Besi 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 150,000
Bahan
1.3.2.18.01.01.003.00077 Tiang Oktagonal - Double Hot-Dipped Galvanized, Tinggi 7 m 1.000 unit 3,085,300 3,085,300
Jumlah Harga Bahan 3,085,300
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 3,315,875
2.02.03.01.01.047 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 5 m Cabang 1 unit 2,530,326
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.500 OH 200,000 100,000
1.10.28.02.01.001.013 Tukang Las 0.625 OH 150,000 93,750
1.10.28.02.01.001.022 Tukang Listrik 0.500 OH 150,000 75,000
1.10.28.02.01.001.005 Tukang Cat 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 2.750 OH 100,000 275,000
Jumlah Harga Tenaga Kerja 581,250
Bahan
1.1.7.01.03.08.012.00030 Terminal Block - 4 Pole, 25 A, 600 V 1.000 Buah 108,675 108,675
1.3.2.18.01.01.003.00233 MCB Fuse Thermal Tripping - 4 Pole, 10 A 1.000 Buah 62,600 62,600
1.1.7.01.01.01.008.00003 Plat Baja - Tbl. 1.2 mm 0.168 Lembar 224,800 37,766
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4.5 mm 0.333 batang 884,900 294,672
1.1.7.02.02.07.001.00008 Pipa Galvanis - Medium Dia. 3 inch. Pjg. 600 cm, tbl. 4 mm 0.333 batang 1,447,800 482,117

199
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.02.02.07.001.00009 Pipa Galvanis - Medium Dia. 4 inch. Pjg. 600 cm, tbl. 4.5 mm 0.333 batang 2,088,500 695,471
1.1.7.01.01.01.008.00025 Plat Besi - Uk. 30 x 30 cm, Tbl. 15 mm 13.000 kg 14,400 187,200
Jumlah Harga Bahan 1,868,501
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 2,530,326
2.02.03.01.01.048 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 5 m Cabang 2 unit 2,825,883
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.500 OH 200,000 100,000
1.10.28.02.01.001.013 Tukang Las 0.625 OH 150,000 93,750
1.10.28.02.01.001.022 Tukang Listrik 0.500 OH 150,000 75,000
1.10.28.02.01.001.005 Tukang Cat 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 2.750 OH 100,000 275,000
Jumlah Harga Tenaga Kerja 581,250
Bahan
1.1.7.01.03.08.012.00030 Terminal Block - 4 Pole, 25 A, 600 V 1.000 Buah 108,675 108,675
1.3.2.18.01.01.003.00233 MCB Fuse Thermal Tripping - 4 Pole, 10 A 1.000 Buah 62,600 62,600
1.1.7.01.01.01.008.00003 Plat Baja - Tbl. 1.2 mm 0.168 Lembar 224,800 37,766
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4.5 mm 0.667 batang 884,900 590,228
1.1.7.02.02.07.001.00008 Pipa Galvanis - Medium Dia. 3 inch. Pjg. 600 cm, tbl. 4 mm 0.333 batang 1,447,800 482,117
1.1.7.02.02.07.001.00009 Pipa Galvanis - Medium Dia. 4 inch. Pjg. 600 cm, tbl. 4.5 mm 0.333 batang 2,088,500 695,471
1.1.7.01.01.01.008.00025 Plat Besi - Uk. 30 x 30 cm, Tbl. 15 mm 13.000 kg 14,400 187,200
Jumlah Harga Bahan 2,164,058
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 2,825,883
2.02.03.01.01.049 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Cabang 1 unit 3,120,888
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.500 OH 200,000 100,000
1.10.28.02.01.001.013 Tukang Las 0.625 OH 150,000 93,750
1.10.28.02.01.001.022 Tukang Listrik 0.500 OH 150,000 75,000
1.10.28.02.01.001.005 Tukang Cat 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 2.750 OH 100,000 275,000
Jumlah Harga Tenaga Kerja 581,250
Bahan
1.1.7.01.03.08.012.00030 Terminal Block - 4 Pole, 25 A, 600 V 1.000 Buah 108,675 108,675
1.3.2.18.01.01.003.00233 MCB Fuse Thermal Tripping - 4 Pole, 10 A 1.000 Buah 62,600 62,600
1.1.7.01.01.01.008.00003 Plat Baja - Tbl. 1.2 mm 0.168 Lembar 224,800 37,766
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4.5 mm 0.333 batang 884,900 294,672
1.1.7.02.02.07.001.00008 Pipa Galvanis - Medium Dia. 3 inch. Pjg. 600 cm, tbl. 4 mm 0.500 batang 1,447,800 723,900
1.1.7.02.02.07.001.00009 Pipa Galvanis - Medium Dia. 4 inch. Pjg. 600 cm, tbl. 4.5 mm 0.500 batang 2,088,500 1,044,250
1.1.7.01.01.01.008.00025 Plat Besi - Uk. 30 x 30 cm, Tbl. 15 mm 13.000 kg 14,400 187,200
Jumlah Harga Bahan 2,459,063
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 3,120,888
2.02.03.01.01.050 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Cabang 2 unit 3,416,445
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.500 OH 200,000 100,000

200
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.10.28.02.01.001.013 Tukang Las 0.625 OH 150,000 93,750
1.10.28.02.01.001.022 Tukang Listrik 0.500 OH 150,000 75,000
1.10.28.02.01.001.005 Tukang Cat 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 2.750 OH 100,000 275,000
Jumlah Harga Tenaga Kerja 581,250
Bahan
1.1.7.01.03.08.012.00030 Terminal Block - 4 Pole, 25 A, 600 V 1.000 Buah 108,675 108,675
1.3.2.18.01.01.003.00233 MCB Fuse Thermal Tripping - 4 Pole, 10 A 1.000 Buah 62,600 62,600
1.1.7.01.01.01.008.00003 Plat Baja - Tbl. 1.2 mm 0.168 Lembar 224,800 37,766
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4.5 mm 0.667 batang 884,900 590,228
1.1.7.02.02.07.001.00008 Pipa Galvanis - Medium Dia. 3 inch. Pjg. 600 cm, tbl. 4 mm 0.500 batang 1,447,800 723,900
1.1.7.02.02.07.001.00009 Pipa Galvanis - Medium Dia. 4 inch. Pjg. 600 cm, tbl. 4.5 mm 0.500 batang 2,088,500 1,044,250
1.1.7.01.01.01.008.00025 Plat Besi - Uk. 30 x 30 cm, Tbl. 15 mm 13.000 kg 14,400 187,200
Jumlah Harga Bahan 2,754,620
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 3,416,445
2.02.03.01.01.051 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Cabang 4 unit 4,006,673
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.500 OH 200,000 100,000
1.10.28.02.01.001.013 Tukang Las 0.625 OH 150,000 93,750
1.10.28.02.01.001.022 Tukang Listrik 0.500 OH 150,000 75,000
1.10.28.02.01.001.005 Tukang Cat 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 2.750 OH 100,000 275,000
Jumlah Harga Tenaga Kerja 581,250
Bahan
1.1.7.01.03.08.012.00030 Terminal Block - 4 Pole, 25 A, 600 V 1.000 Buah 108,675 108,675
1.3.2.18.01.01.003.00233 MCB Fuse Thermal Tripping - 4 Pole, 10 A 1.000 Buah 62,600 62,600
1.1.7.01.01.01.008.00003 Plat Baja - Tbl. 1.2 mm 0.168 Lembar 224,800 37,766
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4.5 mm 1.334 batang 884,900 1,180,457
1.1.7.02.02.07.001.00008 Pipa Galvanis - Medium Dia. 3 inch. Pjg. 600 cm, tbl. 4 mm 0.500 batang 1,447,800 723,900
1.1.7.02.02.07.001.00009 Pipa Galvanis - Medium Dia. 4 inch. Pjg. 600 cm, tbl. 4.5 mm 0.500 batang 2,088,500 1,044,250
1.1.7.01.01.01.008.00025 Plat Besi - Uk. 30 x 30 cm, Tbl. 15 mm 13.000 kg 14,400 187,200
Jumlah Harga Bahan 3,344,848
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
Jumlah Harga Peralatan 80,575
Harga Satuan Pokok Kegiatan 4,006,673
2.02.03.01.01.052 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Dekoratif unit 3,981,112
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.500 OH 200,000 100,000
1.10.28.02.01.001.013 Tukang Las 0.875 OH 150,000 131,250
1.10.28.02.01.001.022 Tukang Listrik 0.500 OH 150,000 75,000
1.10.28.02.01.001.005 Tukang Cat 0.250 OH 150,000 37,500
1.10.28.02.01.002.001 Pekerja 3.250 OH 100,000 325,000
Jumlah Harga Tenaga Kerja 668,750
Bahan
1.1.7.01.03.08.012.00030 Terminal Block - 4 Pole, 25 A, 600 V 1.000 Buah 108,675 108,675
1.3.2.18.01.01.003.00233 MCB Fuse Thermal Tripping - 4 Pole, 10 A 1.000 Buah 62,600 62,600
1.1.7.01.01.01.008.00003 Plat Baja - Tbl. 1.2 mm 0.168 Lembar 224,800 37,766
1.1.7.02.02.07.001.00003 Pipa Galvanis - Medium Dia. 1 inch. Pjg. 600 cm, tbl. 3.2 mm 0.667 batang 436,200 290,945

201
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4.5 mm 0.500 batang 884,900 442,450
1.1.7.02.02.07.001.00008 Pipa Galvanis - Medium Dia. 3 inch. Pjg. 600 cm, tbl. 4 mm 0.500 batang 1,447,800 723,900
1.1.7.02.02.07.001.00009 Pipa Galvanis - Medium Dia. 4 inch. Pjg. 600 cm, tbl. 4.5 mm 0.500 batang 2,088,500 1,044,250
1.1.7.01.01.01.008.00025 Plat Besi - Uk. 30 x 30 cm, Tbl. 15 mm 13.000 kg 14,400 187,200
Jumlah Harga Bahan 2,897,787
Peralatan
9.1.2.09.03.01.001.00095 Crane - 30 ton 0.500 jam 161,150 80,575
9.1.2.09.03.01.001.00054 Steel Pipe Bender Machine 4.000 jam 83,500 334,000
Jumlah Harga Peralatan 414,575
Harga Satuan Pokok Kegiatan 3,981,112
2.02.03.01.01.053 Pemasangan Lampu HPS 150W/220V Lengkap unit 248,700
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.300 OH 150,000 45,000
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 120,000
Bahan
1.1.7.01.03.08.002.00055 Lampu High Pressure Sodium (HPS) - 150 W/220 V 1.000 unit 128,700 128,700
+ Armateur Cap
+ Internal Ignitor and Capacitor
+ Electric Ballast
Jumlah Harga Bahan 128,700
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 248,700
2.02.03.01.01.054 Pemasangan Lampu HPS 250W/220V Lengkap unit 269,200
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.300 OH 150,000 45,000
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 120,000
Bahan
1.1.7.01.03.08.002.00056 Lampu High Pressure Sodium (HPS) - 250 W/220 V 1.000 unit 149,200 149,200
+ Armateur Cap
+ Internal Ignitor and Capacitor
+ Electric Ballast
Jumlah Harga Bahan 149,200
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 269,200
2.02.03.01.01.055 Pemasangan Lampu HPS 400W/220V Lengkap unit 312,500
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.300 OH 150,000 45,000
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 120,000
Bahan
1.1.7.01.03.08.002.00057 Lampu High Pressure Sodium (HPS) - 400 W/220 V 1.000 unit 192,500 192,500
+ Armateur Cap
+ Internal Ignitor and Capacitor
+ Electric Ballast
Jumlah Harga Bahan 192,500
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 312,500

202
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.02.03.01.01.056 Pemasangan Lampu LED 150W/220V Lengkap unit 3,744,800
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.300 OH 150,000 45,000
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 120,000
Bahan
1.1.7.01.03.08.002.00018 Lampu Light Emitting Diode (LED) - 150 W/220 V 1.000 unit 3,624,800 3,624,800
+ Armateur Cap
+ Internal Ignitor and Capacitor
+ Electric Ballast
Jumlah Harga Bahan 3,624,800
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 3,744,800
2.02.03.01.01.058 Pemasangan Lampu Mercury HPLN 150W/220V Lengkap unit 2,480,400
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.300 OH 150,000 45,000
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 120,000
Bahan
1.1.7.01.03.08.002.00019 Lampu Mercury - 150 W/220 V 1.000 unit 2,360,400 2,360,400
+ Armateur Cap
+ Internal Ignitor and Capacitor
+ Electric Ballast
Jumlah Harga Bahan 2,360,400
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 2,480,400
2.02.03.01.01.059 Pemasangan Lampu Mercury HPLN 250W/220V Lengkap unit 2,677,100
Tenaga Kerja
1.10.28.02.01.001.022 Tukang Listrik 0.300 OH 150,000 45,000
1.10.28.02.01.002.001 Pekerja 0.750 OH 100,000 75,000
Jumlah Harga Tenaga Kerja 120,000
Bahan
1.1.7.01.03.08.002.00020 Lampu Mercury - 250 W/220 V 1.000 unit 2,557,100 2,557,100
+ Armateur Cap
+ Internal Ignitor and Capacitor
+ Electric Ballast
Jumlah Harga Bahan 2,557,100
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 2,677,100
2.02.03.02 PEKERJAAN SARANA LALU LINTAS
2.02.03.02.01 PEKERJAAN RAMBU RAMBU LALU LINTAS
2.02.03.02.01.009 Pekerjaan Pemasangan Lampu Jalan Bulat (Tampered) Unit 311,368
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.083 OH 150,000 12,450
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 112,450
Bahan
1.3.2.18.01.01.003.00189 Paku Jalan Bulat (Tampered) - Dia. 100 mm, tbl. 19 mm 1.000 buah 177,000 177,000
1.1.7.01.01.01.022.00280 Lem Mixed Epoxy Adhesive 0.130 kg 168,600 21,918

203
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Bahan 198,918
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 311,368
2.02.03.02.01.010 Pekerjaan Pemasangan Lampu Jalan Alumunium Solar Stud Unit 578,368
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.083 OH 150,000 12,450
1.10.28.02.01.002.001 Pekerja 1.000 OH 100,000 100,000
Jumlah Harga Tenaga Kerja 112,450
Bahan
1.3.2.18.01.01.003.00190 Alumunium Solar Road Stud LED - Uk. 100 x 100 x 20 mm + Baut 1.000 buah 444,000 444,000
1.1.7.01.01.01.022.00280 Lem Mixed Epoxy Adhesive 0.130 kg 168,600 21,918
Jumlah Harga Bahan 465,918
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 578,368
2.02.03.02.01.014 Pekerjaan Cat Besi m2 128,535
Tenaga Kerja
1.10.28.02.01.001.005 Tukang Cat 0.340 OH 150,000 51,000
1.10.28.02.01.002.001 Pekerja 0.200 OH 100,000 20,000
Jumlah Harga Tenaga Kerja 71,000
Bahan
1.1.7.01.01.01.006.00001 Cat Besi 0.425 kg 61,800 26,265
1.1.7.01.01.01.006.00006 Cat Meni Besi 0.125 kg 58,400 7,300
1.1.7.01.01.01.006.00041 Thinner 0.750 liter 27,800 20,850
Jumlah Harga Bahan 54,415
Peralatan
1.1.7.01.01.01.022.00260 Kuas Cat 0.100 buah 20,200 2,020
1.1.7.01.01.01.022.00224 Amplas - No. 240 0.200 lembar 5,500 1,100
Jumlah Harga Peralatan 3,120
Harga Satuan Pokok Kegiatan 128,535
2.02.03.02.01.016 Pekerjaan Pengecatan Marka Jalan (Manual) m' 96,565
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.015 OH 150,000 2,250
1.10.28.02.01.001.005 Tukang Cat 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.100 OH 100,000 10,000
Jumlah Harga Tenaga Kerja 34,750
Bahan
1.1.7.01.01.01.006.00058 Cat Marka - Road Line Paint 0.345 kaleng 155,000 53,475
1.1.7.01.01.01.006.00041 Thinner 0.300 liter 27,800 8,340
Jumlah Harga Bahan 61,815
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 96,565
2.02.03.02.01.017 Pekerjaan Marka Jalan Thermoplastic m2 502,917
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.600 OH 150,000 90,000
1.10.28.02.01.001.005 Tukang Cat 0.225 OH 150,000 33,750
1.10.28.02.01.002.001 Pekerja 0.075 OH 100,000 7,500
Jumlah Harga Tenaga Kerja 131,250
Bahan
1.3.2.18.01.01.003.00176 Cat Thermoplastic 4.500 kg 22,500 101,250

204
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.3.2.18.01.01.003.00175 Micro Glass Bead 1.400 kg 169,700 237,580
1.1.7.01.01.01.006.00041 Thinner 1.050 liter 27,800 29,190
Jumlah Harga Bahan 368,020
Peralatan
9.1.2.10.07.01.001.00095 Mixer 0.075 jam 24,310 1,823
9.1.2.10.07.01.001.00097 Road Marking Machine 0.075 jam 24,310 1,823
Jumlah Harga Peralatan 3,647
Harga Satuan Pokok Kegiatan 502,917
2.02.03.02.01.018 Pekerjaan Marka Jalan Coldplastic m2 626,543
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.600 OH 150,000 90,000
1.10.28.02.01.001.005 Tukang Cat 0.225 OH 150,000 33,750
1.10.28.02.01.002.001 Pekerja 0.075 OH 100,000 7,500
Jumlah Harga Tenaga Kerja 131,250
Bahan
1.3.2.18.01.01.003.00174 Cat Coldplastic 4.500 kg 41,100 184,950
1.3.2.18.01.01.003.00175 Micro Glass Bead 1.400 kg 169,700 237,580
1.1.7.01.01.01.004.00010 Colour Sands 2.500 kg 16,700 41,750
1.1.7.01.01.01.006.00041 Thinner 1.050 liter 27,800 29,190
Jumlah Harga Bahan 493,470
Peralatan
9.1.2.10.07.01.001.00097 Road Marking Machine 0.075 jam 24,310 1,823
Jumlah Harga Peralatan 1,823
Harga Satuan Pokok Kegiatan 626,543
2.02.03.02.01.044 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 90 cm unit 1,090,586
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.500 OH 150,000 75,000
1.10.28.02.01.001.008 Tukang Besi 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 1.500 OH 100,000 150,000
Jumlah Harga Tenaga Kerja 300,000
Bahan
1.1.7.01.01.01.022.00516 Plat Alumunium - Tbl. 2 mm 0.810 m2 440,000 356,400
1.1.7.01.01.01.008.00011 Besi Strip - Uk. 4 x 30 mm 0.225 batang 73,100 16,448
1.1.7.01.01.01.022.00130 Klem Galvanish Rambu + Mur + Baut 2.000 buah 9,000 18,000
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 0.810 m2 308,440 249,836
1.1.7.01.01.01.022.00520 Scotch Light - White, Engineering Grade 0.486 m2 308,440 149,902
Jumlah Harga Bahan 790,586
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 1,090,586
2.02.03.02.01.045 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 75 cm unit 879,893
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.500 OH 150,000 75,000
1.10.28.02.01.001.008 Tukang Besi 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 1.500 OH 100,000 150,000
Jumlah Harga Tenaga Kerja 300,000
Bahan
1.1.7.01.01.01.022.00516 Plat Alumunium - Tbl. 2 mm 0.563 m2 440,000 247,500
1.1.7.01.01.01.008.00011 Besi Strip - Uk. 4 x 30 mm 0.500 m' 73,100 36,550
1.1.7.01.01.01.022.00130 Klem Galvanish Rambu + Mur + Baut 2.000 buah 9,000 18,000
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 0.563 m2 308,440 173,652
1.1.7.01.01.01.022.00520 Scotch Light - White, Engineering Grade 0.338 m2 308,440 104,191

205
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Bahan 579,893
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 879,893
2.02.03.02.01.046 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 60 cm unit 663,564
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.500 OH 150,000 75,000
1.10.28.02.01.001.008 Tukang Besi 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 1.500 OH 100,000 150,000
Jumlah Harga Tenaga Kerja 300,000
Bahan
1.1.7.01.01.01.022.00516 Plat Alumunium - Tbl. 2 mm 0.360 m2 440,000 158,400
1.1.7.01.01.01.008.00011 Besi Strip - Uk. 4 x 30 mm 0.130 batang 73,100 9,503
1.1.7.01.01.01.022.00130 Klem Galvanish Rambu + Mur + Baut 2.000 buah 9,000 18,000
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 0.360 m2 308,440 111,038
1.1.7.01.01.01.022.00520 Scotch Light - White, Engineering Grade 0.216 m2 308,440 66,623
Jumlah Harga Bahan 363,564
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 663,564
2.02.03.02.01.047 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 45 cm unit 516,538
Tenaga Kerja
1.10.28.02.01.001.002 Kepala Tukang 0.500 OH 150,000 75,000
1.10.28.02.01.001.008 Tukang Besi 0.500 OH 150,000 75,000
1.10.28.02.01.002.001 Pekerja 1.500 OH 100,000 150,000
Jumlah Harga Tenaga Kerja 300,000
Bahan
1.1.7.01.01.01.022.00516 Plat Alumunium - Tbl. 2 mm 0.203 m2 440,000 89,100
1.1.7.01.01.01.008.00011 Besi Strip - Uk. 4 x 30 mm 0.130 batang 73,100 9,503
1.1.7.01.01.01.022.00130 Klem Galvanish Rambu + Mur + Baut 2.000 buah 9,000 18,000
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 0.203 m2 308,440 62,459
1.1.7.01.01.01.022.00520 Scotch Light - White, Engineering Grade 0.122 m2 308,440 37,475
Jumlah Harga Bahan 216,538
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 516,538
2.02.03.03 PEKERJAAN TAMAN DAN KEBERSIHAN
2.02.03.03.01 PEKERJAAN TAMAN
2.02.03.03.01.030 Penanaman Rumput Taman m2 34,300
Tenaga Kerja
1.10.28.02.01.001.014 Tukang Taman 0.020 OH 150,000 3,000
1.10.28.02.01.002.001 Pekerja 0.313 OH 100,000 31,300
Jumlah Harga Tenaga Kerja 34,300
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 34,300
2.02.03.03.01.031 Penanaman Semak Hias m2 18,500
Tenaga Kerja
1.10.28.02.01.001.014 Tukang Taman 0.010 OH 150,000 1,500
1.10.28.02.01.002.001 Pekerja 0.170 OH 100,000 17,000

206
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Jumlah Harga Tenaga Kerja 18,500
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 18,500
2.02.03.03.01.032 Penanaman Pohon Diameter > 15 cm Batang Tunggal batang 22,250
Tenaga Kerja
1.10.28.02.01.001.014 Tukang Taman 0.015 OH 150,000 2,250
1.10.28.02.01.002.001 Pekerja 0.200 OH 100,000 20,000
Jumlah Harga Tenaga Kerja 22,250
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 22,250
2.02.03.03.01.036 Penanaman Pohon Diameter < 15 cm Batang Tunggal batang 14,000
Tenaga Kerja
1.10.28.02.01.001.014 Tukang Taman 0.010 OH 150,000 1,500
1.10.28.02.01.002.001 Pekerja 0.125 OH 100,000 12,500
Jumlah Harga Tenaga Kerja 14,000
Bahan
Jumlah Harga Bahan
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 14,000
2.02.03.03.01.033 Penyiapan Media Tanam m3 426,720
Tenaga Kerja
1.10.28.02.01.001.014 Tukang Taman 0.010 OH 150,000 1,500
1.10.28.02.01.002.001 Pekerja 0.250 OH 100,000 25,000
Jumlah Harga Tenaga Kerja 26,500
Bahan
1.1.7.01.01.01.004.00008 Tanah Taman 0.900 m3 195,800 176,220
1.1.7.01.01.12.001.00011 Pupuk Kandang Terolah 40.000 kg 5,600 224,000
Jumlah Harga Bahan 400,220
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 426,720
2.02.03.03.01.034 Pekerjaan Pasangan Batu Refleksi m2 283,300
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.017 OH 200,000 3,400
1.10.28.02.01.001.002 Kepala Tukang 0.015 OH 150,000 2,250
1.10.28.02.01.001.006 Tukang Batu 0.150 OH 150,000 22,500
1.10.28.02.01.002.001 Pekerja 0.350 OH 100,000 35,000
Jumlah Harga Tenaga Kerja 63,150
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 6.260 kg 1,000 6,260
1.1.7.01.01.01.004.00002 Pasir Pasang 0.012 m3 179,800 2,140
1.1.7.01.01.01.005.00073 Batu Refleksi Taman 5.500 zak 38,500 211,750
Jumlah Harga Bahan 220,150
Peralatan
Jumlah Harga Peralatan

207
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
Harga Satuan Pokok Kegiatan 283,300
2.02.03.03.01.035 Pekerjaan Pasangan Lantai Batu Andesit m2 338,271
Tenaga Kerja
1.10.28.02.01.001.001 Mandor 0.030 OH 200,000 6,000
1.10.28.02.01.001.002 Kepala Tukang 0.035 OH 150,000 5,250
1.10.28.02.01.001.006 Tukang Batu 0.350 OH 150,000 52,500
1.10.28.02.01.002.001 Pekerja 0.620 OH 100,000 62,000
Jumlah Harga Tenaga Kerja 125,750
Bahan
1.1.7.01.01.01.002.00003 Semen Portland - 50 kg 17.688 kg 1,000 17,688
1.1.7.01.01.01.004.00002 Pasir Pasang 0.035 m3 179,800 6,293
1.1.7.01.01.01.005.00035 Batu Andesit - Uk. 20 x 20 cm, tbl. 5 cm 1.100 m2 171,400 188,540
Jumlah Harga Bahan 212,521
Peralatan
Jumlah Harga Peralatan
Harga Satuan Pokok Kegiatan 338,271

208
A
A S na
lis
a
B
St F
MOJOKERTO

an I
da S
r I
PEMERINTAH KOTA

Be
la
K
nj
a
Ke
gi
ata
n
Fi
si k
Ko
ns
t ru

2020
TAHUN ANGGARAN
REKAP
ks
i
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
3.01.01.01.01 BANGUNAN GEDUNG DAN RUMAH NEGARA
3.01.01.01.01.001 Pembangunan Gedung Negara Sederhana m2 4,997,750
3.01.01.01.01.002 Pembangunan Gedung Negara Tidak Sederhana m2 5,877,080
3.01.01.01.01.003 Pembangunan Rumah Negara - Type A m2 6,704,796
3.01.01.01.01.004 Pembangunan Rumah Negara - Type B m2 5,961,703
3.01.01.01.01.005 Pembangunan Rumah Negara - Type C m2 5,315,573
3.01.01.01.01.008 Pekerjaan Pagar Bata Expose Desain Majapahit Tinggi 1.5 m, Tebal 1 Bata m' 2,517,530
3.01.01.01.01.009 Pekerjaan Pagar Bata Expose Desain Majapahit Tinggi 2 m, Tebal 1 Bata m' 3,083,451
3.01.02.01.01 DRAINASE DAN SALURAN
3.01.02.01.01.001 Pekerjaan Saluran U-ditch 30.40.120 Gandar 5 Ton unit 622,897
3.01.02.01.01.002 Pekerjaan Saluran U-ditch 40.50.120 Gandar 5 Ton unit 869,138
3.01.02.01.01.003 Pekerjaan Saluran U-ditch 40.60.120 Gandar 5 Ton unit 957,449
3.01.02.01.01.004 Pekerjaan Saluran U-ditch 50.50.120 Gandar 5 Ton unit 964,227
3.01.02.01.01.005 Pekerjaan Saluran U-ditch 50.60.120 Gandar 5 Ton unit 1,057,353
3.01.02.01.01.006 Pekerjaan Saluran U-ditch 50.70.120 Gandar 5 Ton unit 1,165,058
3.01.02.01.01.007 Pekerjaan Saluran U-ditch 60.60.120 Gandar 5 Ton unit 1,179,301
3.01.02.01.01.008 Pekerjaan Saluran U-ditch 60.70.120 Gandar 5 Ton unit 1,093,227
3.01.02.01.01.009 Pekerjaan Saluran U-ditch 60.80.120 Gandar 5 Ton unit 1,190,753
3.01.02.01.01.010 Pekerjaan Saluran U-ditch 80.80.120 Gandar 5 Ton unit 2,036,486
3.01.02.01.01.011 Pekerjaan Saluran U-ditch 80.100.120 Gandar 5 Ton unit 2,061,828
3.01.02.01.01.012 Pekerjaan Saluran U-ditch 40.60.120 Gandar 10 Ton unit 958,760
3.01.02.01.01.013 Pekerjaan Saluran U-ditch 50.50.120 Gandar 10 Ton unit 1,152,801
3.01.02.01.01.014 Pekerjaan Saluran U-ditch 50.60.120 Gandar 10 Ton unit 1,267,743
3.01.02.01.01.015 Pekerjaan Saluran U-ditch 50.70.120 Gandar 10 Ton unit 1,380,308
3.01.02.01.01.016 Pekerjaan Saluran U-ditch 60.60.120 Gandar 10 Ton unit 1,351,108
3.01.02.01.01.017 Pekerjaan Saluran U-ditch 60.70.120 Gandar 10 Ton unit 1,465,158
3.01.02.01.01.018 Pekerjaan Saluran U-ditch 60.80.120 Gandar 10 Ton unit 1,192,676
3.01.02.01.01.019 Pekerjaan Saluran U-ditch 80.80.120 Gandar 10 Ton unit 2,212,900
3.01.02.01.01.020 Pekerjaan Saluran U-ditch 80.100.120 Gandar 10 Ton unit 2,314,922
3.01.02.01.01.021 Pekerjaan Saluran U-ditch 100.120.120 Gandar 10 Ton unit 2,807,819
3.01.02.01.01.022 Pekerjaan Saluran U-ditch 80.100.120 Gandar 20 Ton unit 2,515,283
3.01.02.01.01.023 Pekerjaan Saluran U-ditch 100.120.120 Gandar 20 Ton unit 5,013,124
3.01.02.01.01.024 Pekerjaan Cover U-ditch 30.8.120 Gandar 5 Ton unit 129,060
3.01.02.01.01.025 Pekerjaan Cover U-ditch 40.10.120 Gandar 5 Ton unit 190,674
3.01.02.01.01.026 Pekerjaan Cover U-ditch 40.12.120 Gandar 10 Ton unit 105,613
3.01.02.01.01.027 Pekerjaan Cover U-ditch 50.10.120 Gandar 5 Ton unit 270,000
3.01.02.01.01.028 Pekerjaan Cover U-ditch 50.12.120 Gandar 10 Ton unit 296,406
3.01.02.01.01.029 Pekerjaan Cover U-ditch 60.12.120 Gandar 5 Ton unit 325,296
3.01.02.01.01.030 Pekerjaan Cover U-ditch 60.14.120 Gandar 10 Ton unit 415,800
3.01.02.01.01.031 Pekerjaan Cover U-ditch 80.10.120 Gandar 5 Ton unit 414,720
3.01.02.01.01.032 Pekerjaan Cover U-ditch 80.12.120 Gandar 10 Ton unit 658,800
3.01.02.01.01.033 Pekerjaan Cover U-ditch 80.15.120 Gandar 20 Ton unit 825,120
3.01.02.01.01.034 Pekerjaan Cover U-ditch 100.12.120 Gandar 10 Ton unit 694,440

209
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
3.01.02.01.01.035 Pekerjaan Cover U-ditch 100.15.120 Gandar 20 Ton unit 907,524
3.01.02.01.01.036 Pekerjaan Saluran Box Culvert 100/100 Gandar 20 Ton unit 4,064,893
3.01.02.01.01.037 Pekerjaan Saluran Box Culvert 200/200 Gandar 20 Ton unit 13,237,805
3.01.02.01.01.038 Pekerjaan Saluran Box Culvert 250/250 Gandar 20 Ton unit 18,711,942
3.01.02.01.01.039 Pekerjaan Saluran Box Culvert 400/200 Gandar 20 Ton unit 23,489,528
3.01.02.01.01.040 Pekerjaan Saluran Batu Kali 40/60 + Tutup Precast m' 1,453,287
3.01.02.01.01.041 Pekerjaan Saluran Batu Kali 60/80 + Tutup Precast m' 1,901,391
3.01.02.01.01.042 Pekerjaan Saluran Batu Kali 80/100 + Tutup Precast m' 2,193,105
3.01.02.01.01.043 Pekerjaan Saluran Batu Kali 100/120 + Tutup Precast m' 2,536,769
3.01.02.01.01.044 Pekerjaan Pembuatan Lubang Biopori Sedalam 1 m titik 151,370
3.01.02.01.01.045 Pekerjaan Pembuatan Lubang Biopori Sedalam 2 m titik 267,738
3.01.02.01.01.046 Pekerjaan Pembuatan Sumur Resapan Sedalam 3 m + Tutup Plat titik 3,320,258
3.01.02.01.01.047 Pekerjaan Saluran Buis Beton Ø 30 m' 188,888
3.01.02.01.01.048 Pekerjaan Saluran Buis Beton Ø 40 m' 289,024
3.01.02.01.01.049 Pekerjaan Saluran Buis Beton Ø 50 m' 349,067
3.01.02.01.01.050 Pekerjaan Saluran Buis Beton Ø 60 m' 469,484
3.01.02.01.01.051 Pekerjaan Saluran Buis Beton Ø 80 m' 635,565
3.01.02.01.01.052 Pekerjaan Saluran Buis Beton Ø 100 m' 945,038

3.01.02.02.01 JALAN DAN KELENGKAPAN LALU LINTAS


3.01.02.02.01.001 Pekerjaan Perkerasan Jalan Beton (Rigid Pavement) m2 3,220,760
3.01.02.02.01.002 Pembangunan Halte / Shelter Angkutan Umum unit 3,560,078
3.01.02.02.01.003 Pemasangan PJU Cabang 1 Lampu LED 150W/220V unit 16,469,899
3.01.02.02.01.004 Pemasangan PJU Cabang 2 Lampu LED 150W/220V unit 20,510,256
3.01.02.02.01.005 Pekerjaan Pemasangan Lampu Peringatan (Warning Light) Tiang Lengkung + Solar Cell unit 55,922,408
3.01.02.02.01.006 Pekerjaan Pemasangan Lampu Peringatan (Warning Light) Tiang L + Solar Cell unit 56,851,146
3.01.02.02.01.009 Pekerjaan Pemasangan Rambu Lalu Lintas 45 cm unit 1,197,703
3.01.02.02.01.010 Pekerjaan Pemasangan Rambu Lalu Lintas 60 cm unit 1,344,730
3.01.02.02.01.011 Pekerjaan Pemasangan Rambu Lalu Lintas 75 cm unit 1,561,059
3.01.02.02.01.012 Pekerjaan Pemasangan Rambu Lalu Lintas 90 cm unit 1,771,751
3.01.02.02.01.013 Pekerjaan Pemasangan Pagar Pengamanan Jalan (Terminal End Fish Tail) - Panjang 4 m unit 5,159,776
3.01.02.02.01.014 Pekerjaan Lataston Lapis Aus (HRS-WC) m2 63,948
3.01.02.02.01.015 Pekerjaan Lataston Lapis Perata (HRS-WC L) m2 63,948
3.01.02.02.01.016 Pekerjaan Lataston Lapis Pondasi (HRS-BASE) m2 64,898
3.01.02.02.01.017 Pekerjaan Lataston Lapis Pondasi Perata (HRS-BASE L) m2 64,898
3.01.02.02.01.018 Pekerjaan Laston Lapis Aus (AC-WC) m2 76,091
3.01.02.02.01.019 Pekerjaan Laston Lapis Aus Perata (AC-WC L) m2 76,091
3.01.02.02.01.020 Pekerjaan Laston Lapis Antara (AC-BC) m2 108,010
3.01.02.02.01.021 Pekerjaan Laston Lapis Antara Perata (AC-BC L) m2 108,010
3.01.02.02.01.022 Pekerjaan Laston Lapis Pondasi (AC-BASE) m2 124,075
3.01.02.02.01.023 Pekerjaan Laston Lapis Pondasi Perata(AC-BASE L) m2 124,075
3.01.02.02.01.024 Pekerjaan Pemasangan Pagar Pengamanan Jalan (Terminal End Buffer) - Panjang 4 m unit 5,943,476
3.01.02.02.01.025 Pekerjaan Pemasangan Patok Pengaman (Delineator) unit 623,896
3.01.02.02.01.026 Pekerjaan Pemasangan Cermin Tikungan unit 2,899,921

210
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
3.01.02.02.01.027 Pekerjaan Pemasangan RPPJ 120 x 180 (Overhead) unit 23,557,759
3.01.02.02.01.028 Pekerjaan Pemasangan RPPJ 120 x 240 (Overhead) unit 24,248,862
3.01.02.02.01.029 Pekerjaan Pemasangan ATCS 3 Simpang unit 191,318,000
3.01.02.02.01.030 Pekerjaan Pemasangan ATCS 4 Simpang unit 226,424,400
3.01.02.02.01.031 Pekerjaan Overlay Jalan (Manual) m2 137,934

3.01.02.03.01 ELEKTRIKAL DAN INSTALASI JARINGAN


3.01.02.03.01.001 Pekerjaan Pemasangan Kabel NYFGBY 4 x 2.5 mm m' 57,292
3.01.02.03.01.002 Pekerjaan Pemasangan Kabel NYFGBY 4 x 4 mm m' 57,292
3.01.02.03.01.003 Pekerjaan Pemasangan Kabel NYFGBY 4 x 6 mm m' 87,892
3.01.02.03.01.004 Pekerjaan Pemasangan Kabel NYFGBY 4 x 10 mm m' 116,792
3.01.02.03.01.005 Pekerjaan Pemasangan Kabel NYFGBY 4 x 16 mm m' 160,592
3.01.02.03.01.006 Pekerjaan Pemasangan Kabel NYY 4 x 2.5 mm m' 143,367
3.01.02.03.01.007 Pekerjaan Pemasangan Kabel NYY 4 x 4 mm m' 155,167
3.01.02.03.01.008 Pekerjaan Pemasangan Kabel NYY 4 x 6 mm m' 182,067
3.01.02.03.01.009 Pekerjaan Pemasangan Kabel NYY 4 x 10 mm m' 196,167
3.01.02.03.01.010 Pekerjaan Pemasangan Kabel NYY 4 x 16 mm m' 258,567
3.01.02.03.01.011 Pekerjaan Pemasangan Kabel NYY 4 x 25 mm m' 324,351
3.01.02.03.01.012 Pekerjaan Pemasangan Kabel NYY 4 x 35 mm m' 396,951
3.01.02.03.01.013 Pekerjaan Pemasangan Kabel NYM 2 x 1.5 mm m' 113,800
3.01.02.03.01.014 Pekerjaan Pemasangan Kabel NYM 2 x 2.5 mm m' 121,900
3.01.02.03.01.015 Pekerjaan Pemasangan Kabel Twisted 2 x 10 mm m' 109,700
3.01.02.03.01.016 Pekerjaan Pemasangan Kabel Twisted 2 x 16 mm m' 111,400
3.01.02.03.01.017 Pekerjaan Pemasangan Kabel Twisted 4 x 16 mm m' 130,000

3.01.02.04.01.001 BANGUNAN MASYARAKAT DAN LINGKUNGAN


3.01.02.04.01.001 Septictank Pasasangan Bata Kapasitas 3 m3 + Rembesan unit 6,720,496
3.01.02.04.01.002 Septictank Pasasangan Bata Kapasitas 6 m3 + Rembesan unit 8,955,168
3.01.02.04.01.003 Pemasangan Pipa Saluran Air Bersih Ø 4" m' 615,318
3.01.02.04.01.004 Pemasangan IPAL Komunal Panjang 7 m, Diameter 3 m unit 357,887,785
3.01.02.04.01.005 Pemasangan Septictank Komunal Tinggi 3.5 m, Diameter 2 m unit 145,099,921
3.01.02.04.01.007 Pekerjaan Pembuatan Taman Aktif m2 888,233
3.01.02.04.01.011 Pekerjaan Pembuatan Trotoar dengan Tegel Batu Ampyang m2 286,079

211
A
A S
na
l isa B
St F
MOJOKERTO

an I
da S
r I
PEMERINTAH KOTA

Be
la
K
nj
a
Ke
gi
at
an
Fi
si k
Ko
n st
ru
k

2020
TAHUN ANGGARAN
si
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)

BANGUNAN GEDUNG DAN RUMAH NEGARA


3.01.01.01.01.001 Pembangunan Gedung Negara Sederhana m2 4,997,750
PEKERJAAN TANAH
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.419 m3 80,000 33,520
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.026 m3 60,000 1,560

PEKERJAAN PONDASI
2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.022 m3 5,828,054 128,217
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) 0.130 m3 432,606 56,239
2.01.01.02.01.002 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 4 Pp) 0.019 m3 747,566 14,204
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.008 m3 729,451 5,836

PEKERJAAN BETON STRUKTUR


2.01.01.03.01.020 Pekerjaan Pembuatan Plat Beton Bertulang (150 kg Besi + Bekisting) 0.001 m3 7,678,812 7,679
2.01.01.03.01.018 Pekerjaan Pembuatan Kolom Beton Bertulang (300 kg Besi + Bekisting) 0.021 m3 10,378,596 217,951
2.01.01.03.01.019 Pekerjaan Pembuatan Balok Beton Bertulang (200 kg Besi + Bekisting) 0.030 m3 8,232,995 246,990

PEKERJAAN DINDING
2.01.01.04.01.016 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 4 Ps) 2.132 m2 124,731 265,927
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 3.980 m2 68,305 271,855
2.01.01.04.02.020 Pekerjaan Acian 3.980 m2 41,750 166,165
2.01.01.06.04.014 Pekerjaan Partisi Double Gypsum Rangka Metal Stud 0.120 m2 263,377 31,605

PEKERJAAN LANTAI
2.01.01.05.01.003 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 40x40 cm 1.023 m2 254,259 260,107
2.01.01.05.02.004 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x25 cm 0.193 m2 289,670 55,906

PEKERJAAN DAUN PINTU,JENDELA DAN KUSEN


2.01.01.07.03.007 Pekerjaan Pembuatan Kusen Alumunium 4 inch 3.420 m' 204,380 698,980

PEKERJAAN ATAP DAN PLAFOND


2.01.01.07.01.005 Pekerjaan Pemasangan Penutup Atap Genteng Keramik Glazur 1.672 m2 541,770 905,839
2.01.01.07.03.010 Pekerjaan Pemasangan Rangka Atap Galvalum Genteng Biasa/Metal 1.672 m2 263,900 441,241
2.01.01.07.01.022 Pekerjaan Pemasangan Bubungan Genteng Keramik Glazur 0.316 m' 177,604 56,123
2.01.01.06.03.014 Pekerjaan Pemasangan Listplank Kayu Kelas II (Kamper) 3/20 0.431 m' 130,993 56,458
2.01.01.07.03.019 Pekerjaan Pemasangan Talang Datar/Jurai Seng 0.176 m' 184,115 32,404
2.01.01.06.04.017 Pekerjaan Partisi Kalsiboard Rangka Hollow 1.409 m2 204,245 287,781
2.01.01.07.01.043 Pekerjaan Pemasangan Lis Langit-langit Gypsum 1.187 m' 183,595 217,930

PEKERJAAN PENGECATAN
2.01.01.07.05.013 Pekerjaan Pengecatan Bidang Tembok Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Interior) 3.980 m2 49,338 196,364
2.01.01.07.05.023 Pekerjaan Pengecatan Plafon 1.605 m2 38,693 62,102

PEKERJAAN INSTALASI LISTRIK


LANTAI DASAR
2.01.01.07.06.002 Pekerjaan Pemasangan Titik Lampu 0.155 titik 226,950 35,177
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak 0.076 titik 184,890 14,052
2.01.01.07.06.004 Pekerjaan Pemasangan Saklar Tunggal 0.155 titik 55,600 8,618
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak 0.076 titik 184,890 14,052
2.01.01.07.06.007 Pekerjaan Pemasangan Lampu TL 36 watt 0.067 buah 150,850 10,107
2.01.01.07.06.012 Pekerjaan Pemasangan Lampu Downlight 0.088 buah 108,250 9,526

PEKERJAAN SANITASI AIR KOTOR


3.01.02.04.01.002 Septictank Pasasangan Bata Kapasitas 6 m3 + Rembesan 0.004 unit 8,955,168 35,821

212
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)

TANDON DAN BAK PENAMPUNG AIR


2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.036 m3 80,000 2,880
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 0.009 m3 890,439 8,014
2.01.01.05.01.008 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 20x20 cm 0.038 m2 276,791 10,518
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.002 m3 254,600 509
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 0.003 m3 890,439 2,671

PEKERJAAN INSTALASI AIR


2.01.01.07.02.005 Pekerjaan Pemasangan Wastafel 0.004 unit 956,150 3,825
2.01.01.07.02.020 Pekerjaan Pemasangan Kran Air 0.013 unit 85,298 1,109
2.01.01.07.02.023 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1 inch 0.349 m' 33,973 11,856
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch 0.471 m' 177,921 83,801
2.01.01.07.02.001 Pekerjaan Pemasangan Kloset Duduk 0.013 unit 2,017,800 26,231
3.01.01.01.01.002 Pembangunan Gedung Negara Tidak Sederhana m2 5,877,080
PEKERJAAN TANAH
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.082 m3 80,000 6,560
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 1.150 m3 60,000 69,000
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.016 m3 254,600 4,074

PEKERJAAN PONDASI
2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.029 m3 5,828,054 169,014
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) 0.135 m3 432,606 58,402
2.01.01.02.01.002 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 4 Pp) 0.020 m3 747,566 14,951
2.01.01.03.01.016 Pekerjaan Pembuatan Pondasi Beton Bertulang (150 kg Besi + Bekisting) 0.055 m3 4,671,766 256,947
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.008 m3 729,451 5,836

PEKERJAAN BETON STRUKTUR


LANTAI DASAR
2.01.01.03.01.018 Pekerjaan Pembuatan Kolom Beton Bertulang (300 kg Besi + Bekisting) 0.014 m3 10,378,596 145,300
2.01.01.03.01.020 Pekerjaan Pembuatan Plat Beton Bertulang (150 kg Besi + Bekisting) 0.093 m3 7,678,812 714,130
2.01.01.03.01.019 Pekerjaan Pembuatan Balok Beton Bertulang (200 kg Besi + Bekisting) 0.037 m3 8,232,995 304,621

LANTAI ATAS
2.01.01.03.01.018 Pekerjaan Pembuatan Kolom Beton Bertulang (300 kg Besi + Bekisting) 0.016 m3 10,378,596 166,058
2.01.01.03.01.019 Pekerjaan Pembuatan Balok Beton Bertulang (200 kg Besi + Bekisting) 0.016 m3 8,232,995 131,728
2.01.01.03.01.020 Pekerjaan Pembuatan Plat Beton Bertulang (150 kg Besi + Bekisting) 0.072 m3 7,678,812 552,874

PEKERJAAN DINDING
LANTAI DASAR
2.01.01.04.01.016 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 4 Ps) 0.684 m2 124,731 85,316
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 1.302 m2 68,305 88,933
2.01.01.04.02.020 Pekerjaan Acian 1.302 m2 41,750 54,359
2.01.01.06.04.014 Pekerjaan Partisi Double Gypsum Rangka Metal Stud 0.092 m2 263,377 24,231

LANTAI DASAR
2.01.01.04.01.016 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 4 Ps) 0.998 m2 124,731 124,482
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 1.823 m2 68,305 124,520
2.01.01.04.02.020 Pekerjaan Acian 1.823 m2 41,750 76,110
2.01.01.06.04.014 Pekerjaan Partisi Double Gypsum Rangka Metal Stud 0.088 m2 263,377 23,177

PEKERJAAN LANTAI
LANTAI DASAR
2.01.01.05.01.003 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 40x40 cm 0.717 m2 254,259 182,304

213
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.05.02.004 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x25 cm 0.092 m2 289,670 26,650

LANTAI ATAS
2.01.01.05.01.003 Pekerjaan Pemasangan Lantai Keramik Polos Uk. 40x40 cm 0.514 m2 254,259 130,689
2.01.01.05.02.004 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x25 cm 0.119 m2 289,670 34,471

PEKERJAAN DAUN PINTU, JENDELA, DAN KUSEN


LANTAI DASAR
2.01.01.07.03.007 Pekerjaan Pembuatan Kusen Alumunium 4 inch 1.485 m' 204,380 303,504

LANTAI ATAS
2.01.01.07.03.007 Pekerjaan Pembuatan Kusen Alumunium 4 inch 1.760 m' 204,380 359,709

PEKERJAAN ATAP DAN PLAFOND


2.01.01.07.01.005 Pekerjaan Pemasangan Penutup Atap Genteng Keramik Glazur 0.846 m2 541,770 458,337
2.01.01.07.03.010 Pekerjaan Pemasangan Rangka Atap Galvalum Genteng Biasa/Metal 0.846 m2 263,900 223,259
2.01.01.07.01.022 Pekerjaan Pemasangan Bubungan Genteng Keramik Glazur 0.156 m' 177,604 27,706
2.01.01.06.03.014 Pekerjaan Pemasangan Listplank Kayu Kelas II (Kamper) 3/20 0.172 m' 130,993 22,531
2.01.01.07.03.019 Pekerjaan Pemasangan Talang Datar/Jurai Seng 0.064 m' 184,115 11,783

LANTAI DASAR
2.01.01.06.04.017 Pekerjaan Partisi Kalsiboard Rangka Hollow 0.478 m2 204,245 97,629
2.01.01.07.01.043 Pekerjaan Pemasangan Lis Langit-langit Gypsum 0.691 m' 183,595 126,933

LANTAI ATAS
2.01.01.06.04.017 Pekerjaan Partisi Kalsiboard Rangka Hollow 0.682 m2 204,245 139,295
2.01.01.07.01.043 Pekerjaan Pemasangan Lis Langit-langit Gypsum 0.826 m' 183,595 151,619

PEKERJAAN PENGECATAN
2.01.01.07.05.015 Pekerjaan Pengecatan Tembok Exterior 1.213 m2 35,776 43,396
2.01.01.07.05.013 Pekerjaan Pengecatan Bidang Tembok Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Interior) 1.738 m2 49,338 85,749
2.01.01.07.05.023 Pekerjaan Pengecatan Plafon 1.160 m2 38,693 44,884

PEKERJAAN INSTALASI LISTRIK


LANTAI DASAR
2.01.01.07.06.002 Pekerjaan Pemasangan Titik Lampu 0.060 titik 226,950 13,617
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak 0.020 titik 184,890 3,698
2.01.01.07.06.004 Pekerjaan Pemasangan Saklar Tunggal 0.060 titik 55,600 3,336
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak 0.020 titik 184,890 3,698
2.01.01.07.06.007 Pekerjaan Pemasangan Lampu TL 36 watt 0.036 unit 150,850 5,431
2.01.01.07.06.012 Pekerjaan Pemasangan Lampu Downlight 0.033 unit 108,250 3,572

LANTAI ATAS
2.01.01.07.06.002 Pekerjaan Pemasangan Titik Lampu 0.042 titik 226,950 9,532
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak 0.021 titik 184,890 3,883
2.01.01.07.06.004 Pekerjaan Pemasangan Saklar Tunggal 0.042 titik 55,600 2,335
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak 0.105 titik 184,890 19,413
2.01.01.07.06.007 Pekerjaan Pemasangan Lampu TL 36 watt 0.025 unit 150,850 3,771
2.01.01.07.06.012 Pekerjaan Pemasangan Lampu Downlight 0.038 unit 108,250 4,114

PEKERJAAN SANITASI AIR KOTOR


3.01.02.04.01.002 Septictank Pasasangan Bata Kapasitas 6 m3 + Rembesan 0.003 unit 8,955,168 26,866

TANDON DAN BAK PENAMPUNG AIR

214
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.012 m3 80,000 960
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 0.003 m3 890,439 2,671
2.01.01.05.01.008 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 20x20 cm 0.013 m2 276,791 3,598
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.001 m3 254,600 255
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 0.001 m3 890,439 890

PEKERJAAN INSTALASI AIR


2.01.01.07.02.005 Pekerjaan Pemasangan Wastafel 0.003 unit 956,150 2,868
2.01.01.07.02.020 Pekerjaan Pemasangan Kran Air 0.020 unit 85,298 1,706
2.01.01.07.02.023 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1 inch 0.230 m' 33,973 7,814
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch 0.302 m' 177,921 53,732
2.01.01.07.02.001 Pekerjaan Pemasangan Kloset Duduk 0.014 unit 2,017,800 28,249
3.01.01.01.01.003 Pembangunan Rumah Negara - Type A m2 6,704,796
PEKERJAAN PENDAHULUAN
2.01.01.01.01.004 Pekerjaan Pengukuran dan Pemasangan Bouwplank 0.284 m' 145,360 41,282

PEKERJAAN TANAH
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.977 m3 80,000 78,144
2.01.01.02.01.011 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 20 cm Sedalam 3 m 0.017 titik 192,720 3,195
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.326 m3 60,000 19,536
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.089 m3 299,760 26,619
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.049 m3 254,600 12,552

PEKERJAAN STRUKTUR BETON


2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.022 m3 5,828,054 129,383
2.01.01.03.01.023 Pekerjaan Pembuatan Kolom Praktis Beton Bertulang 11x11 cm 0.324 m' 83,912 27,187
2.01.01.03.01.018 Pekerjaan Pembuatan Kolom Beton Bertulang (300 kg Besi + Bekisting) 0.024 m3 10,378,596 246,595
2.01.01.03.01.024 Pekerjaan Pembuatan Ring Balok Beton Bertulang 10x15 cm 0.740 m3 121,081 89,600
2.01.01.03.01.002 Pekerjaan Pembuatan Beton K-100 0.044 m3 803,529 35,677
2.01.01.03.01.016 Pekerjaan Pembuatan Pondasi Beton Bertulang (150 kg Besi + Bekisting) 0.053 m3 4,671,766 246,669
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 0.017 m3 890,439 14,763
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.049 m3 729,451 35,962

PEKERJAAN PASANGAN
2.01.01.04.01.002 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 2 Ps) 3.046 m2 131,282 399,834
2.01.01.04.02.005 Pekerjaan Plesteran 1 Pc : 5 Ps tbl 15 mm 6.091 m2 67,609 411,819
2.01.01.04.02.015 Pekerjaan Benangan 0.740 m' 54,899 40,625
2.01.01.02.01.003 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 5 Pp) 0.326 m3 724,881 236,021
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) 0.118 m3 432,606 51,221

PEKERJAAN LANTAI
2.01.01.05.01.009 Pekerjaan Pemasangan Lantai Marmer Uk. 100x100 cm 0.920 m2 558,324 513,770
2.01.01.05.02.004 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x25 cm 0.193 m2 289,670 55,964
2.01.01.05.01.008 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 20x20 cm 0.066 m2 276,791 18,213
2.01.01.05.02.007 Pekerjaan Pemasangan Plint Keramik 10x20 cm 0.135 m2 53,432 7,235

PEKERJAAN DAUN PINTU,JENDELA DAN KUSEN


2.01.01.06.01.020 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas II (Kamper) 0.106 m2 694,774 73,507
2.01.01.06.01.011 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas II (Kamper) 0.032 m2 679,400 21,401
2.01.01.07.04.016 Pekerjaan Pemasangan Kaca Tebal 3 mm 0.042 m2 110,926 4,681
2.01.01.06.01.002 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas II (Kamper) 0.028 m3 13,118,630 367,322

PEKERJAAN ATAP DAN PLAFOND


2.01.01.07.01.005 Pekerjaan Pemasangan Penutup Atap Genteng Keramik Glazur 1.624 m2 541,770 879,997

215
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.07.03.001 Pekerjaan Pemasangan Besi Profil 27.228 kg 37,085 1,009,765
2.01.01.07.01.022 Pekerjaan Pemasangan Bubungan Genteng Keramik Glazur 0.068 m' 177,604 12,077
2.01.01.07.03.010 Pekerjaan Pemasangan Rangka Atap Galvalum Genteng Biasa/Metal 1.206 m2 263,900 318,211
2.01.01.06.03.016 Pekerjaan Pemasangan Listplank Kayu Kelas II (Kamper) 3/30 0.002 m' 131,557 237
2.01.01.07.03.019 Pekerjaan Pemasangan Talang Datar/Jurai Seng 0.001 m' 184,115 110
2.01.01.07.01.041 Pekerjaan Pemasangan Langit-langit Gypsum Board Tebal 9 mm 1.206 m2 50,462 60,847
2.01.01.07.01.043 Pekerjaan Pemasangan Lis Langit-langit Gypsum 1.354 m' 183,595 248,514

PEKERJAAN PENGECATAN
2.01.01.07.05.004 Pekerjaan Pengecatan Bidang Kayu Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Penutup) 0.121 m2 59,123 7,178
2.01.01.07.05.006 Pekerjaan Pelaburan Bidang Kayu dengan Politur 0.271 m2 55,906 15,134
2.01.01.07.05.015 Pekerjaan Pengecatan Tembok Exterior 0.873 m2 35,776 31,232
2.01.01.07.05.013 Pekerjaan Pengecatan Bidang Tembok Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Interior) 6.091 m2 49,338 300,526
2.01.01.07.05.023 Pekerjaan Pengecatan Plafon 1.206 m2 38,693 46,656

PEKERJAAN INSTALASI LISTRIK


2.01.01.07.06.002 Pekerjaan Pemasangan Titik Lampu 0.120 titik 226,950 27,234
2.01.01.07.06.007 Pekerjaan Pemasangan Lampu TL 36 watt 0.088 buah 150,850 13,275
2.01.01.07.06.006 Pekerjaan Pemasangan Lampu TL 18 watt 0.016 buah 116,050 1,857
2.01.01.07.06.014 Pekerjaan Pemasangan Panel Phase 2200 VA 0.004 buah 2,884,490 11,538
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak 0.060 titik 184,890 11,093
2.01.01.07.06.004 Pekerjaan Pemasangan Saklar Tunggal 0.108 buah 55,600 6,005
2.01.01.07.06.005 Pekerjaan Pemasangan Saklar Ganda 0.012 buah 57,800 694

PEKERJAAN SANITASI
3.01.02.04.01.002 Septictank Pasasangan Bata Kapasitas 6 m3 + Rembesan 0.008 unit 8,955,168 74,328

PEKERJAAN INSTALASI AIR BERSIH


2.01.01.07.02.005 Pekerjaan Pemasangan Wastafel 0.017 unit 956,150 15,968
1.3.2.01.03.05.010.00023 Pompa Air Jet Pump 200 Watt 0.008 unit 1,552,500 12,886
2.01.01.07.02.020 Pekerjaan Pemasangan Kran Air 0.067 buah 85,298 5,689
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch 0.958 m' 177,921 170,502
2.01.01.07.02.031 Pekerjaan Pemasangan Pipa PVC Type D Diameter 4 inch 0.917 m' 110,496 101,292
2.01.01.07.02.001 Pekerjaan Pemasangan Kloset Duduk 0.033 buah 2,017,800 67,193
2.01.01.07.02.010 Pekerjaan Pemasangan Floor Drain 0.033 buah 28,100 936
2.01.01.06.01.027 Pekerjaan Pemasangan Pintu HPL (High Pressure Laminated) 0.033 buah 545,500 18,165
1.1.7.01.03.07.003.00014 Tandon Air - Stainless Steel, Kapasitas 1000 L 0.008 unit 3,225,800 26,882
3.01.01.01.01.004 Pembangunan Rumah Negara - Type B m2 5,961,703
PEKERJAAN PENDAHULUAN
2.01.01.01.01.004 Pekerjaan Pengukuran dan Pemasangan Bouwplank 0.417 m' 145,360 60,572

PEKERJAAN TANAH
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 1.221 m3 80,000 97,680
2.01.01.02.01.011 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 20 cm Sedalam 3 m 0.028 titik 192,720 5,454
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.407 m3 60,000 24,420
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.111 m3 299,760 33,273
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.046 m3 254,600 11,584

PEKERJAAN STRUKTUR BETON


2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.028 m3 5,828,054 162,020
2.01.01.03.01.023 Pekerjaan Pembuatan Kolom Praktis Beton Bertulang 11x11 cm 0.263 m' 83,912 22,027
2.01.01.03.01.018 Pekerjaan Pembuatan Kolom Beton Bertulang (300 kg Besi + Bekisting) 0.036 m3 10,378,596 373,629
2.01.01.03.01.024 Pekerjaan Pembuatan Ring Balok Beton Bertulang 10x15 cm 0.925 m3 121,081 112,000

216
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.03.01.002 Pekerjaan Pembuatan Beton K-100 0.056 m 803,529 44,596
2.01.01.03.01.016 Pekerjaan Pembuatan Pondasi Beton Bertulang (150 kg Besi + Bekisting) 0.090 m3 4,671,766 420,459
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 0.028 m3 890,439 25,199
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.046 m3 729,451 33,190

PEKERJAAN PASANGAN
2.01.01.04.01.002 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 2 Ps) 3.506 m2 131,282 460,315
2.01.01.04.02.005 Pekerjaan Plesteran 1 Pc : 5 Ps tbl 15 mm 7.013 m2 67,609 474,107
2.01.01.04.02.015 Pekerjaan Benangan 0.925 m1 54,899 50,781
2.01.01.02.01.003 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 5 Pp) 0.407 m3 724,881 295,027
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) 0.148 m3 432,606 64,026

PEKERJAAN LANTAI
2.01.01.05.01.002 Pekerjaan Pemasangan Lantai Granit Uk. 40x40 cm 0.819 m2 489,356 400,880
2.01.01.05.02.004 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x25 cm 0.290 m2 289,670 84,004
2.01.01.05.01.008 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 20x20 cm 0.091 m2 276,791 25,271
2.01.01.05.02.007 Pekerjaan Pemasangan Plint Keramik 10x20 cm 0.156 m' 53,432 8,325

PEKERJAAN DAUN PINTU,JENDELA DAN KUSEN


2.01.01.06.01.020 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas II (Kamper) 0.142 m2 694,774 98,519
2.01.01.06.01.011 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas II (Kamper) 0.039 m2 679,400 26,768
2.01.01.07.04.016 Pekerjaan Pemasangan Kaca Tebal 3 mm 0.059 m2 110,926 6,511
2.01.01.06.01.002 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas II (Kamper) 0.051 m3 13,118,630 664,196

PEKERJAAN ATAP DAN PLAFOND


2.01.01.07.01.003 Pekerjaan Pemasangan Penutup Atap Genteng Tanah Liat (Plentong, Kodok) Glazur 1.666 m2 89,050 148,393
2.01.01.07.03.010 Pekerjaan Pemasangan Rangka Atap Galvalum Genteng Biasa/Metal 1.225 m2 263,900 323,278
2.01.01.07.01.021 Pekerjaan Pemasangan Bubungan Genteng Tanah Liat (Plentong, Kodok) Glazur 0.096 m' 72,204 6,917
2.01.01.06.03.016 Pekerjaan Pemasangan Listplank Kayu Kelas II (Kamper) 3/30 0.003 m' 131,557 342
2.01.01.07.03.019 Pekerjaan Pemasangan Talang Datar/Jurai Seng 0.001 m' 184,115 166
2.01.01.07.01.041 Pekerjaan Pemasangan Langit-langit Gypsum Board Tebal 9 mm 1.225 m2 50,462 61,816
2.01.01.07.01.043 Pekerjaan Pemasangan Lis Langit-langit Gypsum 1.558 m' 183,595 286,096

PEKERJAAN PENGECATAN
2.01.01.07.05.004 Pekerjaan Pengecatan Bidang Kayu Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Penutup) 0.176 m2 59,123 10,394
2.01.01.07.05.006 Pekerjaan Pelaburan Bidang Kayu dengan Politur 0.312 m2 55,906 17,426
2.01.01.07.05.015 Pekerjaan Pengecatan Tembok Exterior 1.144 m2 35,776 40,921
2.01.01.07.05.013 Pekerjaan Pengecatan Bidang Tembok Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Interior) 7.013 m2 49,338 345,981
2.01.01.07.05.023 Pekerjaan Pengecatan Plafon 1.225 m2 38,693 47,399

PEKERJAAN INSTALASI LISTRIK


2.01.01.07.06.002 Pekerjaan Pemasangan Titik Lampu 0.142 titik 226,950 32,159
2.01.01.07.06.007 Pekerjaan Pemasangan Lampu TL 36 watt 0.083 buah 150,850 12,566
2.01.01.07.06.006 Pekerjaan Pemasangan Lampu TL 18 watt 0.033 buah 116,050 3,864
2.01.01.07.06.014 Pekerjaan Pemasangan Panel Phase 2200 VA 0.008 buah 2,884,490 23,941
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak 0.083 titik 184,890 15,401
2.01.01.07.06.004 Pekerjaan Pemasangan Saklar Tunggal 0.083 buah 55,600 4,631
2.01.01.07.06.005 Pekerjaan Pemasangan Saklar Ganda 0.025 buah 57,800 1,445

PEKERJAAN SANITASI
3.01.02.04.01.002 Septictank Pasasangan Bata Kapasitas 6 m3 + Rembesan 0.008 unit 8,955,168 74,328

PEKERJAAN INSTALASI AIR BERSIH


2.01.01.07.02.005 Pekerjaan Pemasangan Wastafel 0.017 unit 956,150 15,968

217
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.3.2.01.03.05.010.00023 Pompa Air Jet Pump 200 Watt 0.008 unit 1,552,500 12,886
2.01.01.07.02.020 Pekerjaan Pemasangan Kran Air 0.067 buah 85,298 5,689
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch 0.958 m' 177,921 170,502
2.01.01.07.02.031 Pekerjaan Pemasangan Pipa PVC Type D Diameter 4 inch 0.917 m' 110,496 101,292
2.01.01.07.02.001 Pekerjaan Pemasangan Kloset Duduk 0.033 buah 2,017,800 67,193
2.01.01.07.02.010 Pekerjaan Pemasangan Floor Drain 0.033 buah 28,100 936
2.01.01.06.01.027 Pekerjaan Pemasangan Pintu HPL (High Pressure Laminated) 0.033 buah 545,500 18,165
1.1.7.01.03.07.003.00014 Tandon Air - Stainless Steel, Kapasitas 1000 L 0.008 unit 3,225,800 26,774
3.01.01.01.01.005 Pembangunan Rumah Negara - Type C m2 5,315,573
PEKERJAAN PENDAHULUAN
2.01.01.01.01.004 Pekerjaan Pengukuran dan Pemasangan Bouwplank 0.900 m' 145,360 130,824

PEKERJAAN TANAH
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 1.394 m3 80,000 111,483
2.01.01.02.01.011 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 20 cm Sedalam 3 m 0.016 titik 192,720 3,112
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.465 m3 60,000 27,871
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.127 m3 299,760 37,975
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.039 m3 254,600 10,002

PEKERJAAN STRUKTUR BETON


2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.032 m3 5,828,054 184,583
2.01.01.03.01.023 Pekerjaan Pembuatan Kolom Praktis Beton Bertulang 11x11 cm 0.257 m' 83,912 21,577
2.01.01.03.01.018 Pekerjaan Pembuatan Kolom Beton Bertulang (300 kg Besi + Bekisting) 0.036 m3 10,378,596 373,629
2.01.01.03.01.024 Pekerjaan Pembuatan Ring Balok Beton Bertulang 10x15 cm 1.056 m3 121,081 127,827
2.01.01.03.01.002 Pekerjaan Pembuatan Beton K-100 0.063 m 803,529 50,898
2.01.01.03.01.016 Pekerjaan Pembuatan Pondasi Beton Bertulang (150 kg Besi + Bekisting) 0.051 m3 4,671,766 240,262
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 0.016 m3 890,439 14,379
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.039 m3 729,451 28,657

PEKERJAAN PASANGAN
2.01.01.04.01.002 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 2 Ps) 3.529 m2 131,282 463,333
2.01.01.04.02.005 Pekerjaan Plesteran 1 Pc : 5 Ps tbl 15 mm 7.059 m2 67,609 477,222
2.01.01.04.02.015 Pekerjaan Benangan 1.056 m1 54,899 57,957
2.01.01.02.01.003 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 5 Pp) 0.465 m3 724,881 336,718
2.01.01.02.01.008 0.169 m3 432,606 73,073

PEKERJAAN LANTAI
2.01.01.05.01.006 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 40x40 cm 1.150 m2 310,931 357,571
2.01.01.05.02.004 Pekerjaan Pemasangan Dinding Keramik Motif Uk. 20x25 cm 0.214 m2 289,670 62,072
2.01.01.05.01.008 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 20x20 cm 0.086 m2 276,791 23,725
2.01.01.05.02.007 Pekerjaan Pemasangan Plint Keramik 10x20 cm 0.157 m' 53,432 8,381

PEKERJAAN DAUN PINTU,JENDELA DAN KUSEN


2.01.01.06.01.020 Pembuatan dan Pemasangan Pintu Taekwood Rangkap, Rangka Kayu Kelas II (Kamper) 0.135 m2 694,774 93,794
2.01.01.06.01.011 Pembuatan dan Pemasangan Pintu/Jendela Kaca Kayu Kelas II (Kamper) 0.023 m2 679,400 15,286
2.01.01.07.04.016 Pekerjaan Pemasangan Kaca Tebal 3 mm 0.088 m2 110,926 9,761
2.01.01.06.01.002 Pembuatan dan Pemasangan Kusen Pintu/Jendela Kayu Kelas II (Kamper) 0.003 m3 13,118,630 41,043

PEKERJAAN ATAP DAN PLAFOND


2.01.01.07.01.001 Pekerjaan Pemasangan Penutup Atap Genteng Tanah Liat (Karang Pilang) 2.438 m2 73,050 178,075
2.01.01.07.03.010 Pekerjaan Pemasangan Rangka Atap Galvalum Genteng Biasa/Metal 1.456 m2 263,900 384,318
2.01.01.07.01.020 Pekerjaan Pemasangan Bubungan Genteng Tanah Liat (Karang Pilang) 0.157 m' 121,554 19,101
2.01.01.06.03.016 Pekerjaan Pemasangan Listplank Kayu Kelas II (Kamper) 3/30 0.005 m' 131,557 707

218
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.07.03.019 Pekerjaan Pemasangan Talang Datar/Jurai Seng 0.001 m' 184,115 260
2.01.01.07.01.041 Pekerjaan Pemasangan Langit-langit Gypsum Board Tebal 9 mm 1.456 m2 50,462 73,488
2.01.01.07.01.043 Pekerjaan Pemasangan Lis Langit-langit Gypsum 1.569 m' 183,595 287,987

PEKERJAAN PENGECATAN
2.01.01.07.05.004 Pekerjaan Pengecatan Bidang Kayu Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Penutup) 0.358 m2 59,123 21,183
2.01.01.07.05.006 Pekerjaan Pelaburan Bidang Kayu dengan Politur 0.314 m2 55,906 17,539
2.01.01.07.05.015 Pekerjaan Pengecatan Tembok Exterior 1.736 m2 35,776 62,097
2.01.01.07.05.013 Pekerjaan Pengecatan Bidang Tembok Baru (1 Lps. Plamir, 1 Lps. Dasar, 2 Lps. Interior) 7.059 m2 49,338 348,254
2.01.01.07.05.023 Pekerjaan Pengecatan Plafon 1.456 m2 38,693 56,348

PEKERJAAN INSTALASI LISTRIK


2.01.01.07.06.002 Pekerjaan Pemasangan Titik Lampu 0.143 titik 226,950 32,421
2.01.01.07.06.007 Pekerjaan Pemasangan Lampu TL 36 watt 0.086 buah 150,850 12,930
2.01.01.07.06.006 Pekerjaan Pemasangan Lampu TL 18 watt 0.014 buah 116,050 1,658
2.01.01.07.06.014 Pekerjaan Pemasangan Panel Phase 2200 VA 0.014 buah 2,884,490 41,207
2.01.01.07.06.001 Pekerjaan Pemasangan Stop Kontak 0.100 titik 184,890 18,489
2.01.01.07.06.004 Pekerjaan Pemasangan Saklar Tunggal 0.057 buah 55,600 3,177
2.01.01.07.06.005 Pekerjaan Pemasangan Saklar Ganda 0.029 buah 57,800 1,651

PEKERJAAN SANITASI
3.01.02.04.01.001 Septictank Pasasangan Bata Kapasitas 3 m3 + Rembesan 0.014 unit 6,720,496 96,007

PEKERJAAN INSTALASI AIR BERSIH


2.01.01.07.02.005 Pekerjaan Pemasangan Wastafel 0.029 unit 956,150 27,346
1.3.2.01.03.05.010.00023 Pompa Air Jet Pump 200 Watt 0.008 unit 1,552,500 12,886
2.01.01.07.02.020 Pekerjaan Pemasangan Kran Air 0.058 buah 85,298 4,973
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch 0.595 m' 177,921 105,863
2.01.01.07.02.031 Pekerjaan Pemasangan Pipa PVC Type D Diameter 4 inch 0.510 m' 110,496 56,353
2.01.01.07.02.001 Pekerjaan Pemasangan Kloset Duduk 0.016 buah 2,017,800 32,285
2.01.01.07.02.010 Pekerjaan Pemasangan Floor Drain 0.016 buah 28,100 450
2.01.01.06.01.027 Pekerjaan Pemasangan Pintu HPL (High Pressure Laminated) 0.016 buah 545,500 8,728
1.1.7.01.03.07.003.00014 Tandon Air - Stainless Steel, Kapasitas 1000 L 0.008 unit 3,225,800 26,774
3.01.01.01.01.008 Pekerjaan Pagar Bata Expose Desain Majapahit Tinggi 1.5 m, Tebal 1 Bata m' 2,517,530
2.01.02.01.04.001 Pekerjaan Galian Biasa + Pembuangan Sisa Galian 1.080 m3 38,802 41,906
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.080 m3 299,760 23,981
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) 0.120 m3 432,606 51,913
2.01.01.02.01.002 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 4 Pp) 0.440 m3 747,566 328,929
2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.060 m3 5,828,054 349,683
2.01.01.03.01.023 Pekerjaan Pembuatan Kolom Praktis Beton Bertulang 11x11 cm 0.007 m' 83,912 555
2.01.01.04.01.019 Pekerjaan Pemasangan Dinding Bata Expose tbl 1 Bata (1 Pc : 3 Ps) 1.544 m2 1,099,504 1,697,763
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.380 m3 60,000 22,800
3.01.01.01.01.009 Pekerjaan Pagar Bata Expose Desain Majapahit Tinggi 2 m, Tebal 1 Bata m' 3,083,451
2.01.02.01.04.001 Pekerjaan Galian Biasa + Pembuangan Sisa Galian 1.080 m3 38,802 41,906
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.080 m3 299,760 23,981
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) 0.120 m3 432,606 51,913
2.01.01.02.01.002 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 4 Pp) 0.440 m3 747,566 328,929
2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.060 m3 5,828,054 349,683
2.01.01.03.01.023 Pekerjaan Pembuatan Kolom Praktis Beton Bertulang 11x11 cm 0.007 m' 83,912 555
2.01.01.04.01.019 Pekerjaan Pemasangan Dinding Bata Expose tbl 1 Bata (1 Pc : 3 Ps) 2.059 m2 1,099,504 2,263,684
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.380 m3 60,000 22,800

DRAINASE DAN SALURAN


3.01.02.01.01.001 Pekerjaan Saluran U-ditch 30.40.120 Gandar 5 Ton unit 622,897

219
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.022.00398 U-ditch - Uk. 30 x 40 x 120 cm, Gandar 5 ton 1.000 unit 378,800 378,800
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 0.596 m3 36,850 21,962
1.1.7.01.01.01.022.00398 Pekerjaan Pemasangan U-ditch 0.080 unit 378,800 30,304
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.207 m3 60,000 12,420
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.270 m3 299,760 80,935
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.135 m3 729,451 98,476
3.01.02.01.01.002 Pekerjaan Saluran U-ditch 40.50.120 Gandar 5 Ton unit 869,138
1.1.7.01.01.01.022.00401 U-ditch - Uk. 40 x 50 x 120 cm, Gandar 5 ton 1.000 unit 582,700 582,700
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 0.925 m3 36,850 34,086
1.1.7.01.01.01.022.00401 Pekerjaan Pemasangan U-ditch 0.080 unit 582,700 46,616
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.328 m3 60,000 19,680
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.280 m3 299,760 83,933
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.140 m3 729,451 102,123
3.01.02.01.01.003 Pekerjaan Saluran U-ditch 40.60.120 Gandar 5 Ton unit 957,449
1.1.7.01.01.01.022.00402 U-ditch - Uk. 40 x 60 x 120 cm, Gandar 5 ton 1.000 unit 658,400 658,400
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.038 m3 36,850 38,241
1.1.7.01.01.01.022.00402 Pekerjaan Pemasangan U-ditch 0.080 unit 658,400 52,672
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.368 m3 60,000 22,080
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.280 m3 299,760 83,933
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.140 m3 729,451 102,123
3.01.02.01.01.004 Pekerjaan Saluran U-ditch 50.50.120 Gandar 5 Ton unit 964,227
1.1.7.01.01.01.022.00403 U-ditch - Uk. 50 x 50 x 120 cm, Gandar 5 ton 1.000 unit 651,900 651,900
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.155 m3 36,850 42,575
1.1.7.01.01.01.022.00403 Pekerjaan Pemasangan U-ditch 0.080 unit 651,900 52,152
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.415 m3 60,000 24,900
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.290 m3 299,760 86,930
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.145 m3 729,451 105,770
3.01.02.01.01.005 Pekerjaan Saluran U-ditch 50.60.120 Gandar 5 Ton unit 1,057,353
1.1.7.01.01.01.022.00404 U-ditch - Uk. 50 x 60 x 120 cm, Gandar 5 ton 1.000 unit 730,600 730,600
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.295 m3 36,850 47,704
1.1.7.01.01.01.022.00404 Pekerjaan Pemasangan U-ditch 0.080 unit 730,600 58,448
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.465 m3 60,000 27,900
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.290 m3 299,760 86,930
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.145 m3 729,451 105,770
3.01.02.01.01.006 Pekerjaan Saluran U-ditch 50.70.120 Gandar 5 Ton unit 1,165,058
1.1.7.01.01.01.022.00405 U-ditch - Uk. 50 x 70 x 120 cm, Gandar 5 ton 1.000 unit 822,800 822,800
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.434 m3 36,850 52,833
1.1.7.01.01.01.022.00405 Pekerjaan Pemasangan U-ditch 0.080 unit 822,800 65,824
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.515 m3 60,000 30,900
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.290 m3 299,760 86,930
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.145 m3 729,451 105,770
3.01.02.01.01.007 Pekerjaan Saluran U-ditch 60.60.120 Gandar 5 Ton unit 1,179,301
1.1.7.01.01.01.022.00406 U-ditch - Uk. 60 x 60 x 120 cm, Gandar 5 ton 1.000 unit 822,800 822,800
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.550 m3 36,850 57,132
1.1.7.01.01.01.022.00406 Pekerjaan Pemasangan U-ditch 0.080 unit 822,800 65,824
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.570 m3 60,000 34,200
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.300 m3 299,760 89,928
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.150 m3 729,451 109,418
3.01.02.01.01.008 Pekerjaan Saluran U-ditch 60.70.120 Gandar 5 Ton unit 1,093,227
1.1.7.01.01.01.022.00407 U-ditch - Uk. 60 x 70 x 120 cm, Gandar 5 ton 1.000 unit 734,200 734,200
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.714 m3 36,850 63,145
1.1.7.01.01.01.022.00407 Pekerjaan Pemasangan U-ditch 0.080 unit 734,200 58,736
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.630 m3 60,000 37,800

220
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.300 m3 299,760 89,928
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.150 m3 729,451 109,418
3.01.02.01.01.009 Pekerjaan Saluran U-ditch 60.80.120 Gandar 5 Ton unit 1,190,753
1.1.7.01.01.01.022.00537 U-ditch - Uk. 60 x 80 x 120 cm, Gandar 5 ton 1.000 unit 815,600 815,600
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.877 m3 36,850 69,159
1.1.7.01.01.01.022.00537 Pekerjaan Pemasangan U-ditch 0.080 unit 815,600 65,248
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.690 m3 60,000 41,400
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.300 m3 299,760 89,928
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.150 m3 729,451 109,418
3.01.02.01.01.010 Pekerjaan Saluran U-ditch 80.80.120 Gandar 5 Ton unit 2,036,486
1.1.7.01.01.01.022.00541 U-ditch - Uk. 80 x 80 x 120 cm, Gandar 5 ton 1.000 unit 1,555,000 1,555,000
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 2.435 m3 36,850 89,730
1.1.7.01.01.01.022.00541 Pekerjaan Pemasangan U-ditch 0.080 unit 1,555,000 124,400
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.912 m3 60,000 54,720
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.320 m3 299,760 95,923
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.160 m3 729,451 116,712
3.01.02.01.01.011 Pekerjaan Saluran U-ditch 80.100.120 Gandar 5 Ton unit 2,061,828
1.1.7.01.01.01.022.00541 U-ditch - Uk. 80 x 80 x 120 cm, Gandar 5 ton 1.000 unit 1,555,000 1,555,000
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 2.862 m3 36,850 105,472
1.1.7.01.01.01.022.00541 Pekerjaan Pemasangan U-ditch 0.080 unit 1,555,000 124,400
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 1.072 m3 60,000 64,320
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.320 m3 299,760 95,923
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.160 m3 729,451 116,712
3.01.02.01.01.012 Pekerjaan Saluran U-ditch 40.60.120 Gandar 10 Ton unit 958,760
1.1.7.01.01.01.022.00402 U-ditch - Uk. 40 x 60 x 120 cm, Gandar 10 ton 1.000 unit 658,400 658,400
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.060 m3 36,850 39,072
1.1.7.01.01.01.022.00402 Pekerjaan Pemasangan U-ditch 0.080 unit 658,400 52,672
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.376 m3 60,000 22,560
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.280 m3 299,760 83,933
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.140 m3 729,451 102,123
3.01.02.01.01.013 Pekerjaan Saluran U-ditch 50.50.120 Gandar 10 Ton unit 1,152,801
1.1.7.01.01.01.022.00531 U-ditch - Uk. 50 x 50 x 120 cm, Gandar 10 ton 1.000 unit 825,000 825,000
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.183 m3 36,850 43,600
1.1.7.01.01.01.022.00531 Pekerjaan Pemasangan U-ditch 0.080 unit 825,000 66,000
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.425 m3 60,000 25,500
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.290 m3 299,760 86,930
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.145 m3 729,451 105,770
3.01.02.01.01.014 Pekerjaan Saluran U-ditch 50.60.120 Gandar 10 Ton unit 1,267,743
1.1.7.01.01.01.022.00532 U-ditch - Uk. 50 x 60 x 120 cm, Gandar 10 ton 1.000 unit 923,900 923,900
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.322 m3 36,850 48,730
1.1.7.01.01.01.022.00532 Pekerjaan Pemasangan U-ditch 0.080 unit 923,900 73,912
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.475 m3 60,000 28,500
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.290 m3 299,760 86,930
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.145 m3 729,451 105,770
3.01.02.01.01.015 Pekerjaan Saluran U-ditch 50.70.120 Gandar 10 Ton unit 1,380,308
1.1.7.01.01.01.022.00533 U-ditch - Uk. 50 x 70 x 120 cm, Gandar 10 ton 1.000 unit 1,020,600 1,020,600
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.462 m3 36,850 53,859
1.1.7.01.01.01.022.00533 Pekerjaan Pemasangan U-ditch 0.080 unit 1,020,600 81,648
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.525 m3 60,000 31,500
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.290 m3 299,760 86,930
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.145 m3 729,451 105,770
3.01.02.01.01.016 Pekerjaan Saluran U-ditch 60.60.120 Gandar 10 Ton unit 1,351,108
1.1.7.01.01.01.022.00534 U-ditch - Uk. 60 x 60 x 120 cm, Gandar 10 ton 1.000 unit 980,100 980,100

221
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.583 m3 36,850 58,334
1.1.7.01.01.01.022.00534 Pekerjaan Pemasangan U-ditch 0.080 unit 980,100 78,408
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.582 m3 60,000 34,920
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.300 m3 299,760 89,928
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.150 m3 729,451 109,418
3.01.02.01.01.017 Pekerjaan Saluran U-ditch 60.70.120 Gandar 10 Ton unit 1,465,158
1.1.7.01.01.01.022.00535 U-ditch - Uk. 60 x 70 x 120 cm, Gandar 10 ton 1.000 unit 1,076,800 1,076,800
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.746 m3 36,850 64,348
1.1.7.01.01.01.022.00535 Pekerjaan Pemasangan U-ditch 0.080 unit 1,076,800 86,144
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.642 m3 60,000 38,520
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.300 m3 299,760 89,928
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.150 m3 729,451 109,418
3.01.02.01.01.018 Pekerjaan Saluran U-ditch 60.80.120 Gandar 10 Ton unit 1,192,676
1.1.7.01.01.01.022.00536 U-ditch - Uk. 60 x 80 x 120 cm, Gandar 10 ton 1.000 unit 815,600 815,600
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.909 m3 36,850 70,362
1.1.7.01.01.01.022.00536 Pekerjaan Pemasangan U-ditch 0.080 unit 815,600 65,248
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.702 m3 60,000 42,120
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.300 m3 299,760 89,928
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.150 m3 729,451 109,418
3.01.02.01.01.019 Pekerjaan Saluran U-ditch 80.80.120 Gandar 10 Ton unit 2,212,900
1.1.7.01.01.01.022.00540 U-ditch - Uk. 80 x 80 x 120 cm, Gandar 10 ton 1.000 unit 1,716,000 1,716,000
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 2.478 m3 36,850 91,304
1.1.7.01.01.01.022.00540 Pekerjaan Pemasangan U-ditch 0.080 unit 1,716,000 137,280
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.928 m3 60,000 55,680
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.320 m3 299,760 95,923
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.160 m3 729,451 116,712
3.01.02.01.01.020 Pekerjaan Saluran U-ditch 80.100.120 Gandar 10 Ton unit 2,314,922
1.1.7.01.01.01.022.00538 U-ditch - Uk. 80 x 100 x 120 cm, Gandar 10 ton 1.000 unit 1,787,000 1,787,000
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 2.905 m3 36,850 107,047
1.1.7.01.01.01.022.00538 Pekerjaan Pemasangan U-ditch 0.080 unit 1,787,000 142,960
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 1.088 m3 60,000 65,280
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.320 m3 299,760 95,923
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.160 m3 729,451 116,712
3.01.02.01.01.021 Pekerjaan Saluran U-ditch 100.120.120 Gandar 10 Ton unit 2,807,819
1.1.7.01.01.01.022.00529 U-ditch - Uk. 100 x 120 x 120 cm, Gandar 10 ton 1.000 unit 2,162,000 2,162,000
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 4.145 m3 36,850 152,734
1.1.7.01.01.01.022.00529 Pekerjaan Pemasangan U-ditch 0.080 unit 2,162,000 172,960
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 1.570 m3 60,000 94,200
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.340 m3 299,760 101,918
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.170 m3 729,451 124,007
3.01.02.01.01.022 Pekerjaan Saluran U-ditch 80.100.120 Gandar 20 Ton unit 2,515,283
1.1.7.01.01.01.022.00539 U-ditch - Uk. 80 x 100 x 120 cm, Gandar 20 ton 1.000 unit 1,969,000 1,969,000
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 2.969 m3 36,850 109,408
1.1.7.01.01.01.022.00539 Pekerjaan Pemasangan U-ditch 0.080 unit 1,969,000 157,520
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 1.112 m3 60,000 66,720
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.320 m3 299,760 95,923
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.160 m3 729,451 116,712
3.01.02.01.01.023 Pekerjaan Saluran U-ditch 100.120.120 Gandar 20 Ton unit 5,013,124
1.1.7.01.01.01.022.00530 U-ditch - Uk. 100 x 120 x 120 cm, Gandar 20 ton 1.000 unit 4,199,580 4,199,580
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 4.224 m3 36,850 155,653
1.1.7.01.01.01.022.00530 Pekerjaan Pemasangan U-ditch 0.080 unit 4,199,580 335,966
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 1.600 m3 60,000 96,000
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.340 m3 299,760 101,918

222
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.170 m3 729,451 124,007
3.01.02.01.01.024 Pekerjaan Cover U-ditch 30.8.120 Gandar 5 Ton unit 129,060
1.1.7.01.01.01.022.00485 Cover U-ditch - 30 x 8 x 120 cm, Gandar 5 ton 1.000 unit 119,500 119,500
1.1.7.01.01.01.022.00485 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 119,500 9,560
3.01.02.01.01.025 Pekerjaan Cover U-ditch 40.10.120 Gandar 5 Ton unit 190,674
1.1.7.01.01.01.022.00486 Cover U-ditch - 40 x 10 x 120 cm, Gandar 5 ton 1.000 unit 176,550 176,550
1.1.7.01.01.01.022.00486 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 176,550 14,124
3.01.02.01.01.026 Pekerjaan Cover U-ditch 40.12.120 Gandar 10 Ton unit 105,613
1.1.7.01.01.01.022.00487 Cover U-ditch - 40 x 12 x 120 cm, Gandar 10 ton 1.000 unit 97,790 97,790
1.1.7.01.01.01.022.00487 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 97,790 7,823
3.01.02.01.01.027 Pekerjaan Cover U-ditch 50.10.120 Gandar 5 Ton unit 270,000
1.1.7.01.01.01.022.00488 Cover U-ditch - 50 x 10 x 120 cm, Gandar 5 ton 1.000 unit 250,000 250,000
1.1.7.01.01.01.022.00488 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 250,000 20,000
3.01.02.01.01.028 Pekerjaan Cover U-ditch 50.12.120 Gandar 10 Ton unit 296,406
1.1.7.01.01.01.022.00489 Cover U-ditch - 50 x 12 x 120 cm, Gandar 10 ton 1.000 unit 274,450 274,450
1.1.7.01.01.01.022.00489 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 274,450 21,956
3.01.02.01.01.029 Pekerjaan Cover U-ditch 60.12.120 Gandar 5 Ton unit 325,296
1.1.7.01.01.01.022.00492 Cover U-ditch - 60 x 12 x 120 cm, Gandar 5 ton 1.000 unit 301,200 301,200
1.1.7.01.01.01.022.00492 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 301,200 24,096
3.01.02.01.01.030 Pekerjaan Cover U-ditch 60.14.120 Gandar 10 Ton unit 415,800
1.1.7.01.01.01.022.00491 Cover U-ditch - 60 x 14 x 120 cm, Gandar 10 ton 1.000 unit 385,000 385,000
1.1.7.01.01.01.022.00491 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 385,000 30,800
3.01.02.01.01.031 Pekerjaan Cover U-ditch 80.10.120 Gandar 5 Ton unit 414,720
1.1.7.01.01.01.022.00492 Cover U-ditch - 80 x 10 x 120 cm, Gandar 5 ton 1.000 unit 384,000 384,000
1.1.7.01.01.01.022.00492 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 384,000 30,720
3.01.02.01.01.032 Pekerjaan Cover U-ditch 80.12.120 Gandar 10 Ton unit 658,800
1.1.7.01.01.01.022.00493 Cover U-ditch - 80 x 12 x 120 cm, Gandar 10 ton 1.000 unit 610,000 610,000
1.1.7.01.01.01.022.00493 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 610,000 48,800
3.01.02.01.01.033 Pekerjaan Cover U-ditch 80.15.120 Gandar 20 Ton unit 825,120
1.1.7.01.01.01.022.00494 Cover U-ditch - 80 x 15 x 120 cm, Gandar 20 ton 1.000 unit 764,000 764,000
1.1.7.01.01.01.022.00494 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 764,000 61,120
3.01.02.01.01.034 Pekerjaan Cover U-ditch 100.12.120 Gandar 10 Ton unit 694,440
1.1.7.01.01.01.022.00483 Cover U-ditch - 100 x 12 x 120 cm, Gandar 10 ton 1.000 unit 643,000 643,000
1.1.7.01.01.01.022.00483 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 643,000 51,440
3.01.02.01.01.035 Pekerjaan Cover U-ditch 100.15.120 Gandar 20 Ton unit 907,524
1.1.7.01.01.01.022.00484 Cover U-ditch - 100 x 15 x 120 cm, Gandar 20 ton 1.000 unit 840,300 840,300
1.1.7.01.01.01.022.00484 Pekerjaan Pemasangan Cover U-ditch 0.080 unit 840,300 67,224
3.01.02.01.01.036 Pekerjaan Saluran Box Culvert 100/100 Gandar 20 Ton unit 4,064,893
1.1.7.01.01.01.022.00479 Box Culvert Heavy Duty - Uk. 100 x 100 x 120 cm, Gandar 20 ton 1.000 unit 3,202,000 3,202,000
1.1.7.01.01.05.007.00039 Cerucuk Bambu - Dia. 12 cm, pjg. 600 cm 5.000 batang 22,500 112,500
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 3.335 m3 36,850 122,893
1.1.7.01.01.01.022.00479 Pekerjaan Pemasangan Box Culvert 0.100 unit 3,202,000 320,200
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.725 m3 60,000 43,500
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.150 m3 299,760 44,964
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.300 m3 729,451 218,835
3.01.02.01.01.037 Pekerjaan Saluran Box Culvert 200/200 Gandar 20 Ton unit 13,237,805
1.1.7.01.01.01.022.00480 Box Culvert Heavy Duty - Uk. 200 x 200 x 120 cm, Gandar 20 ton 1.000 unit 11,163,000 11,163,000
1.1.7.01.01.05.007.00039 Cerucuk Bambu - Dia. 12 cm, pjg. 600 cm 7.000 batang 22,500 157,500
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 10.535 m3 36,850 388,210
1.1.7.01.01.01.022.00480 Pekerjaan Pemasangan Box Culvert 0.100 unit 11,163,000 1,116,300
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 2.450 m3 60,000 147,000
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.400 m3 299,760 119,904
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.200 m3 729,451 145,890

223
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
3.01.02.01.01.038 Pekerjaan Saluran Box Culvert 250/250 Gandar 20 Ton unit 18,711,942
1.1.7.01.01.01.022.00481 Box Culvert Heavy Duty - Uk. 250 x 250 x 120 cm, Gandar 20 ton 1.000 unit 15,830,000 15,830,000
1.1.7.01.01.05.007.00039 Cerucuk Bambu - Dia. 12 cm, pjg. 600 cm 9.000 batang 22,500 202,500
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 15.635 m3 36,850 576,143
1.1.7.01.01.01.022.00481 Pekerjaan Pemasangan Box Culvert 0.100 unit 15,830,000 1,583,000
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 3.688 m3 60,000 221,280
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.450 m3 299,760 134,892
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.225 m3 729,451 164,126
3.01.02.01.01.039 Pekerjaan Saluran Box Culvert 400/200 Gandar 20 Ton unit 23,489,528
1.1.7.01.01.01.022.00482 Box Culvert Heavy Duty - Uk. 400 x 200 x 120 cm, Gandar 20 ton 1.000 unit 19,900,000 19,900,000
1.1.7.01.01.05.007.00039 Cerucuk Bambu - Dia. 12 cm, pjg. 600 cm 7.000 batang 22,500 157,500
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 20.335 m3 36,850 749,337
1.1.7.01.01.01.022.00482 Pekerjaan Pemasangan Box Culvert 0.100 unit 19,900,000 1,990,000
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 4.900 m3 60,000 294,000
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.600 m3 299,760 179,856
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.300 m3 729,451 218,835
3.01.02.01.01.040 Pekerjaan Saluran Batu Kali 40/60 + Tutup Precast m' 1,453,287
1.1.7.01.01.01.022.00511 Pelat Beton K-350 Pre-Cast Tb.10 Cm (Fabrikan) 2.000 unit 463,430 926,860
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 0.680 m3 36,850 25,058
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.240 m3 299,760 71,942
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) 0.120 m3 432,606 51,913
2.01.01.02.01.002 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 4 Pp) 0.180 m3 747,566 134,562
2.01.02.01.03.004 Pekerjaan Pemasangan Lubang Drainase 2.000 unit 25,705 51,410
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.120 m3 729,451 87,534
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 1.470 m2 68,305 100,409
3.01.02.01.01.041 Pekerjaan Saluran Batu Kali 60/80 + Tutup Precast m' 1,901,391
1.1.7.01.01.01.022.00512 Pelat Beton K-350 Pre-Cast Tb.12 Cm (Fabrikan) 2.000 unit 567,600 1,135,200
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.260 m3 36,850 46,430
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.260 m3 299,760 77,938
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) 0.180 m3 432,606 77,869
2.01.01.02.01.002 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 4 Pp) 0.360 m3 747,566 269,124
2.01.02.01.03.004 Pekerjaan Pemasangan Lubang Drainase 2.000 unit 25,705 51,410
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.120 m3 60,000 7,200
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.130 m3 729,451 94,829
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 2.070 m2 68,305 141,392
3.01.02.01.01.042 Pekerjaan Saluran Batu Kali 80/100 + Tutup Precast m' 2,193,105
1.1.7.01.01.01.022.00512 Pelat Beton K-350 Pre-Cast Tb.12 Cm (Fabrikan) 2.000 unit 567,600 1,135,200
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 2.000 m3 36,850 73,699
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.280 m3 299,760 83,933
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) 0.240 m3 432,606 103,825
2.01.01.02.01.002 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 4 Pp) 0.600 m3 747,566 448,540
2.01.02.01.03.004 Pekerjaan Pemasangan Lubang Drainase 2.000 unit 25,705 51,410
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.200 m3 60,000 12,000
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.140 m3 729,451 102,123
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 2.670 m2 68,305 182,375
3.01.02.01.01.043 Pekerjaan Saluran Batu Kali 100/120 + Tutup Precast m' 2,536,769
1.1.7.01.01.01.022.00512 Pelat Beton K-350 Pre-Cast Tb.12 Cm (Fabrikan) 2.000 unit 567,600 1,135,200
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 2.900 m3 36,850 106,864
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.300 m3 299,760 89,928
2.01.01.02.01.008 Pekerjaan Pemasangan Batu Kosong (Aanstamping) 0.300 m3 432,606 129,782
2.01.01.02.01.002 Pekerjaan Pasangan Pondasi Batu Belah 15/20 cm, Campuran (1 Pc : 4 Pp) 0.900 m3 747,566 672,809
2.01.02.01.03.004 Pekerjaan Pemasangan Lubang Drainase 2.000 unit 25,705 51,410

224
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.300 m3 60,000 18,000
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.150 m3 729,451 109,418
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 3.270 m2 68,305 223,358
3.01.02.01.01.044 Pekerjaan Pembuatan Lubang Biopori Sedalam 1 m Titik 151,370
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 0.013 m3 36,850 463
2.01.01.07.02.031 Pekerjaan Pemasangan Pipa PVC Type D Diameter 4 inch 1.050 m' 110,496 116,021
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.005 m3 729,451 3,437
1.1.7.01.01.01.022.00209 Roster - Uk. 20 x 20 cm 1.000 unit 30,900 30,900
2.01.02.01.03.003 Bahan Porous untuk Filter 0.002 m3 348,996 548
3.01.02.01.01.045 Pekerjaan Pembuatan Lubang Biopori Sedalam 2 m titik 267,738
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 0.022 m3 36,850 810
2.01.01.07.02.031 Pekerjaan Pemasangan Pipa PVC Type D Diameter 4 inch 2.100 m' 110,496 232,042
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.005 m3 729,451 3,437
1.1.7.01.01.01.022.00209 Roster - Uk. 20 x 20 cm 1.000 unit 30,900 30,900
2.01.02.01.03.003 Bahan Porous untuk Filter 0.002 m3 348,996 548
3.01.02.01.01.046 Pekerjaan Pembuatan Sumur Resapan Sedalam 3 m + Tutup Plat titik 3,320,258
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 3.393 m3 36,850 125,028
2.01.01.04.01.002 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 2 Ps) 10.367 m2 131,282 1,361,038
2.01.02.01.03.003 Bahan Porous untuk Filter 0.079 m3 348,996 27,410
1.1.7.01.01.01.005.00006 Batu Belah - 15/20 cm 0.314 m3 168,600 52,966
2.01.01.03.01.020 Pekerjaan Pembuatan Plat Beton Bertulang (150 kg Besi + Bekisting) 0.113 m3 7,678,812 868,453
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.283 m3 60,000 16,965
2.01.01.07.02.031 Pekerjaan Pemasangan Pipa PVC Type D Diameter 4 inch 3.000 m' 110,496 331,489
2.01.01.07.02.039 Pekerjaan Pemasangan Socket Pipa PVC Type D Diameter 4 inch 3.000 unit 101,310 303,930
2.01.01.07.02.038 Pekerjaan Pemasangan Elbow Pipa PVC Type D Diameter 4 inch 2.000 unit 116,490 232,980
3.01.02.01.01.047 Pekerjaan Saluran Buis Beton Ø 30 m' 188,888
1.1.7.01.01.01.015.00003 Buis Beton - Dia. 30 x 100 cm 1.000 unit 95,500 95,500
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 0.480 m3 36,850 17,688
1.1.7.01.01.01.015.00003 Pekerjaan Pemasangan Buis Beton 0.100 ls 95,500 9,550
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.260 m3 60,000 15,600
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.140 m3 299,760 41,966
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 0.126 m2 68,305 8,583
3.01.02.01.01.048 Pekerjaan Saluran Buis Beton Ø 40 m' 289,024
1.1.7.01.01.01.015.00004 Buis Beton - Dia. 40 x 100 cm 1.000 unit 146,100 146,100
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 0.750 m3 36,850 27,637
1.1.7.01.01.01.015.00004 Pekerjaan Pemasangan Buis Beton 0.100 ls 146,100 14,610
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.406 m3 60,000 24,375
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.219 m3 299,760 65,573
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 0.157 m2 68,305 10,729
3.01.02.01.01.049 Pekerjaan Saluran Buis Beton Ø 50 m' 349,067
1.1.7.01.01.01.015.00005 Buis Beton - Dia. 50 x 100 cm 1.000 unit 151,700 151,700
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.080 m3 36,850 39,798
1.1.7.01.01.01.015.00005 Pekerjaan Pemasangan Buis Beton 0.100 ls 151,700 15,170
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.585 m3 60,000 35,100
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.315 m3 299,760 94,424
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 0.188 m2 68,305 12,875
3.01.02.01.01.050 Pekerjaan Saluran Buis Beton Ø 60 m' 469,484
1.1.7.01.01.01.015.00006 Buis Beton - Dia. 60 x 100 cm 1.000 unit 191,100 191,100
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 1.555 m3 36,850 57,308
1.1.7.01.01.01.015.00006 Pekerjaan Pemasangan Buis Beton 0.100 ls 191,100 19,110
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.842 m3 60,000 50,544
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.454 m3 299,760 135,971
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 0.226 m2 68,305 15,450

225
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
3.01.02.01.01.051 Pekerjaan Saluran Buis Beton Ø 80 m' 635,565
1.1.7.01.01.01.015.00015 Buis Beton - Dia. 80 x 100 cm 1.000 unit 165,000 165,000
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 2.765 m3 36,850 101,882
1.1.7.01.01.01.015.00015 Pekerjaan Pemasangan Buis Beton 0.100 ls 165,000 16,500
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 1.498 m3 60,000 89,856
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.806 m3 299,760 241,726
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 0.302 m2 68,305 20,600
3.01.02.01.01.052 Pekerjaan Saluran Buis Beton Ø 100 m' 945,038
1.1.7.01.01.01.015.00014 Buis Beton - Dia. 100 x 100 cm 1.000 unit 220,000 220,000
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 4.320 m3 36,850 159,190
1.1.7.01.01.01.015.00014 Pekerjaan Pemasangan Buis Beton 0.100 ls 220,000 22,000
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 2.340 m3 60,000 140,400
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 1.260 m3 299,760 377,698
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 0.377 m2 68,305 25,750

JALAN DAN KELENGKAPAN LALU LINTAS


3.01.02.02.01.001 Pekerjaan Perkerasan Jalan Beton (Rigid Pavement) m2 3,220,760
Pekerjaan Asphalt
3.01.02.02.01.018 Pekerjaan Laston Lapis Aus (AC-WC) 1.000 m2 76,091 76,091
3.01.02.02.01.020 Pekerjaan Laston Lapis Antara (AC-BC) 1.000 m2 108,010 108,010
Pekerjaan Struktur Beton
2.01.02.01.08.002 Beton Mutu Tinggi Fc'=35 Mpa 0.350 m3 3,541,313 1,239,459
2.01.01.03.01.015 Pekerjaan Pemasangan Wiremesh 35.038 kg 12,131 425,032
2.01.01.03.02.005 Pekerjaan Pasang Bekisting untuk Lantai 0.022 m2 712,655 15,678
2.01.01.07.03.001 Pekerjaan Pemasangan Besi Profil 2.189 kg 37,085 81,179
Pekerjaan Sub-Base
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.100 m3 729,451 72,945
2.01.02.01.05.001 Pekerjaan Lapis Pondasi Agregat Kelas A 0.300 m3 352,185 105,656
2.01.02.01.05.002 Pekerjaan Lapis Pondasi Agregat Kelas B 0.400 m3 351,646 140,658
2.01.02.01.05.008 Pekerjaan Lapis Pondasi Agregat Kelas S 0.500 m3 336,327 168,163
2.01.02.01.07.019 Pekerjaan Lapis Pondasi/Perata Penetrasi Macadam 0.500 m3 1,455,135 727,567
Pekerjaan Tanah
2.01.02.01.04.001 Pekerjaan Galian Biasa + Pembuangan Sisa Galian 0.700 m3 38,802 27,161
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.100 m3 299,760 29,976
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.013 m3 254,600 3,183
3.01.02.02.01.002 Pembangunan Halte / Shelter Angkutan Umum m2 3,560,078
2.01.01.01.01.004 Pekerjaan Pengukuran dan Pemasangan Bouwplank 1.197 m' 145,360 173,938
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.274 m3 80,000 21,880
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.274 m3 60,000 16,410
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.091 m3 299,760 27,248
2.01.01.03.01.016 Pekerjaan Pembuatan Pondasi Beton Bertulang (150 kg Besi + Bekisting) 0.023 m3 4,671,766 107,918
2.01.01.03.01.018 Pekerjaan Pembuatan Kolom Beton Bertulang (300 kg Besi + Bekisting) 0.012 m3 10,378,596 119,354
2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.123 m3 5,828,054 717,433
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.021 m3 729,451 15,610
2.01.01.03.01.020 Pekerjaan Pembuatan Plat Beton Bertulang (150 kg Besi + Bekisting) 0.011 m3 7,678,812 83,699
2.01.01.04.01.004 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 3 Ps) 0.285 m2 127,062 36,162
2.01.01.04.02.003 Pekerjaan Plesteran 1 Pc : 3 Ps tbl 15 mm 0.470 m2 69,661 32,748
2.01.01.05.01.007 Pekerjaan Pemasangan Lantai Keramik Motif Uk. 30x30 cm 0.897 m2 289,143 259,477
2.01.01.07.03.030 Pekerjaan Pemasangan Kanopi Rangka Besi Hollow Penutup Atap Polycarbonate 0.081 m2 900,590 73,128
3.01.02.02.01.012 Pekerjaan Pemasangan Rambu Lalu Lintas 90 cm 0.024 m2 1,771,751 42,699
2.01.01.07.02.016 Pekerjaan Pemasangan Pipa Galvanis Diameter 1 inch 3.918 m1 138,335 541,983
2.01.01.07.02.017 Pekerjaan Pemasangan Pipa Galvanis Diameter 1 1/2 inch 3.227 m1 210,269 678,623
2.01.01.07.02.019 Pekerjaan Pemasangan Pipa Galvanis Diameter 4 inch 0.513 m1 591,629 303,387
1.1.7.01.01.01.008.00025 Plat Besi - Uk. 30 x 30 cm, Tbl. 15 mm 2.174 kg 14,400 31,303

226
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.008.00077 Angkur - Dia. 19 mm, pjg. 60 cm + Mur + Ring 1.026 buah 54,300 55,690
2.01.01.07.03.005 Pekerjaan Pengelasan dengan Las Listrik 8.547 cm 2,766 23,638
2.02.03.02.01.014 Pekerjaan Cat Besi 1.539 m2 128,535 197,751
3.01.02.02.01.003 Pemasangan PJU Cabang 1 Lampu LED 150W/220V unit 16,469,899
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.288 m3 80,000 23,040
2.02.03.01.01.042 Pekerjaan Pondasi Strouss PJU 1.000 unit 1,514,192 1,514,192
2.02.03.01.01.049 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Cabang 1 1.000 unit 3,120,888 3,120,888
2.02.03.01.01.056 Pemasangan Lampu LED 150W/220V Lengkap 1.000 unit 3,744,800 3,744,800
2.02.03.01.01.029 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 6600 VA 1.000 unit 5,256,640 5,256,640
2.02.03.01.01.035 Pekerjaan Pengecatan Tiang PJU 1.000 unit 321,839 321,839
2.02.03.01.01.015 Pekerjaan Instalasi Tarikan Kabel Udara 25.000 m' 99,540 2,488,500
3.01.02.02.01.004 Pemasangan PJU Cabang 2 Lampu LED 150W/220V unit 20,510,256
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.288 m3 80,000 23,040
2.02.03.01.01.042 Pekerjaan Pondasi Strouss PJU 1.000 unit 1,514,192 1,514,192
2.02.03.01.01.050 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 7 m Cabang 2 1.000 unit 3,416,445 3,416,445
2.02.03.01.01.056 Pemasangan Lampu LED 150W/220V Lengkap 2.000 unit 3,744,800 7,489,600
2.02.03.01.01.030 Pekerjaan Pemasangan Panel Lampu PJU 3 Phase 10600 VA 1.000 unit 5,256,640 5,256,640
2.02.03.01.01.035 Pekerjaan Pengecatan Tiang PJU 1.000 unit 321,839 321,839
2.02.03.01.01.015 Pekerjaan Instalasi Tarikan Kabel Udara 25.000 m' 99,540 2,488,500
3.01.02.02.01.005 Pekerjaan Pemasangan Lampu Peringatan (Warning Light) Tiang Lengkung + Solar Cell unit 55,922,408
Warning Light - LED, 2 Aspek, dia. 30 cm
+ Armateur Cap
1.3.2.18.01.01.001.00008 2.000 unit 15,845,940 31,691,880
+ Internal Ignitor and Capacitor
+ Electric Ballast
1.3.2.18.01.01.001.00009 Warning Light Flash Controller - Double Flasher 2.000 unit 1,100,000 2,200,000
1.3.2.18.01.01.003.00234 Solar Cell Module - 100 Watt 18 Volt 2.000 unit 1,644,500 3,289,000
1.3.2.18.01.01.003.00193 Solar Cell Controller - 10 Ampere 12 Volt 2.000 unit 375,500 751,000
1.1.7.01.02.11.001.00006 ACCU Gel - 50Ah 12 Volt + Panel 2.000 unit 1,526,700 3,053,400
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 0.721 m2 308,440 222,385
1.1.7.01.01.01.008.00077 Angkur - Dia. 19 mm, pjg. 90 cm + Mur + Ring 16.000 Buah 54,300 868,800
1.1.7.01.01.01.008.00003 Plat Baja - Tbl. 1.2 mm 33.912 kg 224,800 7,623,418
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.545 m3 80,000 43,560
2.01.01.01.02.004 Pekerjaan Galian Tanah Keras 0.760 m3 106,400 80,864
3.01.02.03.01.006 Pekerjaan Pemasangan Kabel NYY 4 x 2.5 mm 15.000 m' 143,367 2,150,505
2.01.01.02.01.011 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 20 cm Sedalam 3 m 1.000 titik 192,720 192,720
2.01.01.03.01.013 Pekerjaan Pembesian dengan Besi Polos/Ulir 51.490 kg 13,352 687,469
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 0.593 m3 906,467 537,081
2.02.03.01.01.047 Pembuatan dan Pemasangan Tiang Lengkung Galvanized 5 m Cabang 1 1.000 Buah 2,530,326 2,530,326
3.01.02.02.01.006 Pekerjaan Pemasangan Lampu Peringatan (Warning Light) Tiang L + Solar Cell unit 56,851,146
Warning Light - LED, 2 Aspek, dia. 30 cm
+ Armateur Cap
1.3.2.18.01.01.001.00008 2.000 unit 15,845,940 31,691,880
+ Internal Ignitor and Capacitor
+ Electric Ballast
1.3.2.18.01.01.001.00009 Warning Light Flash Controller - Double Flasher 2.000 unit 1,100,000 2,200,000
1.3.2.18.01.01.003.00234 Solar Cell Module - 100 Watt 18 Volt 2.000 unit 1,644,500 3,289,000
1.3.2.18.01.01.003.00193 Solar Cell Controller - 10 Ampere 12 Volt 2.000 unit 375,500 751,000
1.1.7.01.02.11.001.00006 ACCU Gel - 50Ah 12 Volt + Panel 2.000 unit 1,526,700 3,053,400
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 0.721 m2 308,440 222,385
1.1.7.01.01.01.008.00077 Angkur - Dia. 19 mm, pjg. 90 cm + Mur + Ring 16.000 buah 54,300 868,800
1.1.7.01.01.01.008.00003 Plat Baja - Tbl. 1.2 mm 33.912 kg 224,800 7,623,418
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.545 m3 80,000 43,560
2.01.01.01.02.004 Pekerjaan Galian Tanah Keras 0.760 m3 106,400 80,864
3.01.02.03.01.006 Pekerjaan Pemasangan Kabel NYY 4 x 2.5 mm 15.000 m' 143,367 2,150,505

227
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.02.01.011 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 20 cm Sedalam 3 m 1.000 titik 192,720 192,720
2.01.01.03.01.013 Pekerjaan Pembesian dengan Besi Polos/Ulir 51.490 kg 13,352 687,469
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 0.593 m3 906,467 537,081
2.02.03.01.01.043 Pekerjaan Pemasangan Tiang Oktagonal 5 m Single HDG 1.000 buah 2,602,175 2,602,175
2.02.03.01.01.025 Pekerjaan Pemasangan Ornamen Tiang Panjang 2 m 1.000 unit 685,614 685,614
1.1.7.01.03.08.012.00030 Terminal Block - 4 Pole, 25 A, 600 V 1.000 Buah 108,675 108,675
1.3.2.18.01.01.003.00233 MCB Fuse Thermal Tripping - 4 Pole, 10 A 1.000 Buah 62,600 62,600
3.01.02.02.01.012 Pekerjaan Pemasangan Rambu Lalu Lintas 90 cm unit 1,771,751
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4 mm 0.617 batang 884,900 545,629
1.1.7.01.01.01.008.00039 Besi Siku - Uk. 3 x 30 x 30 cm 1.632 kg 13,000 21,216
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.100 m3 80,000 8,000
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.016 m3 299,760 4,796
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 0.112 m3 906,467 101,524
2.02.03.02.01.044 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 90 cm 1.000 unit 1,090,586 1,090,586
3.01.02.02.01.011 Pekerjaan Pemasangan Rambu Lalu Lintas 75 cm unit 1,561,059
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4 mm 0.617 batang 884,900 545,629
1.1.7.01.01.01.008.00039 Besi Siku - Uk. 3 x 30 x 30 cm 1.632 kg 13,000 21,216
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.100 m3 80,000 8,000
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.016 m3 299,760 4,796
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 0.112 m3 906,467 101,524
2.02.03.02.01.045 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 75 cm 1.000 unit 879,893 879,893
3.01.02.02.01.010 Pekerjaan Pemasangan Rambu Lalu Lintas 60 cm unit 1,344,730
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4 mm 0.617 batang 884,900 545,629
1.1.7.01.01.01.008.00039 Besi Siku - Uk. 3 x 30 x 30 cm 1.632 kg 13,000 21,216
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.100 m3 80,000 8,000
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.016 m3 299,760 4,796
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 0.112 m3 906,467 101,524
2.02.03.02.01.046 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 60 cm 1.000 unit 663,564 663,564
3.01.02.02.01.009 Pekerjaan Pemasangan Rambu Lalu Lintas 45 cm unit 1,197,703
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4 mm 0.617 batang 884,900 545,629
1.1.7.01.01.01.008.00039 Besi Siku - Uk. 3 x 30 x 30 cm 1.632 kg 13,000 21,216
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.100 m3 80,000 8,000
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.016 m3 299,760 4,796
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 0.112 m3 906,467 101,524
2.02.03.02.01.047 Pekerjaan Pembuatan dan Pemasangan Daun Rambu 45 cm 1.000 unit 516,538 516,538
3.01.02.02.01.013 Pekerjaan Pemasangan Pagar Pengamanan Jalan (Terminal End Fish Tail) - Panjang 4 m unit 5,159,776
2.01.02.01.04.001 Pekerjaan Galian Biasa + Pembuangan Sisa Galian 0.480 m3 38,802 18,625
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.048 m3 254,600 12,221
2.01.01.03.01.005 Pekerjaan Pembuatan Beton K-175 0.480 m3 869,019 417,129
2.01.01.03.02.001 Pekerjaan Pasang Bekisting untuk Pondasi 0.800 m2 355,126 284,101
1.3.2.18.01.01.003.00126 U-Shape Post - Uk. 1800 x 176 x 74 x 4.5 mm 3.000 buah 783,100 2,349,300
1.1.7.01.01.01.008.00083 U-Shape Blocking Piece - Uk. 350 x 176 x 74 x 4.5 mm 3.000 buah 85,600 256,800
1.1.7.01.01.01.008.00085 W-Beam - Uk. 4320 x 312 x 2.7 mm, Hot-Dip Galvanized Flex Beam 1.000 buah 1,141,800 1,141,800
1.3.2.18.01.01.003.00158 Terminal End Fish Tail 1.000 buah 399,000 399,000
1.1.7.01.01.01.022.00116 Mushroom Bolt Beam - Uk. 12 x 25 mm 16.000 buah 8,800 140,800
1.1.7.01.01.01.022.00117 Hexagon Bolt Blocking - Uk. 16 x 35 mm 3.000 buah 9,500 28,500
1.1.7.01.01.01.022.00118 Mushroom Bolt Post - Uk. 16 x 45 mm 6.000 buah 9,000 54,000
1.3.2.18.01.01.003.00195 Guardrail Reflector 1.000 buah 57,500 57,500
3.01.02.02.01.024 Pekerjaan Pemasangan Pagar Pengamanan Jalan (Terminal End Buffer) - Panjang 4 m unit 5,943,476
2.01.02.01.04.001 Pekerjaan Galian Biasa + Pembuangan Sisa Galian 0.480 m3 38,802 18,625
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.048 m3 254,600 12,221
2.01.01.03.01.005 Pekerjaan Pembuatan Beton K-175 0.480 m3 869,019 417,129
2.01.01.03.02.001 Pekerjaan Pasang Bekisting untuk Pondasi 0.800 m2 355,126 284,101

228
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.3.2.18.01.01.003.00126 U-Shape Post - Uk. 1800 x 176 x 74 x 4.5 mm 3.000 buah 783,100 2,349,300
1.1.7.01.01.01.008.00083 U-Shape Blocking Piece - Uk. 350 x 176 x 74 x 4.5 mm 3.000 buah 85,600 256,800
1.1.7.01.01.01.008.00085 W-Beam - Uk. 4320 x 312 x 2.7 mm, Hot-Dip Galvanized Flex Beam 1.000 buah 1,141,800 1,141,800
1.3.2.18.01.01.003.00157 Terminal End Buffer 1.000 buah 1,106,700 1,106,700
1.1.7.01.01.01.022.00116 Mushroom Bolt Beam - Uk. 12 x 25 mm 16.000 buah 8,800 140,800
1.1.7.01.01.01.022.00117 Hexagon Bolt Blocking - Uk. 16 x 35 mm 11.000 buah 9,500 104,500
1.1.7.01.01.01.022.00118 Mushroom Bolt Post - Uk. 16 x 45 mm 6.000 buah 9,000 54,000
1.3.2.18.01.01.003.00195 Guardrail Reflector 1.000 buah 57,500 57,500
3.01.02.02.01.014 Pekerjaan Lataston Lapis Aus (HRS-WC) m2 63,948
2.01.02.01.07.007 Bahan Lataston Lapis Aus (HRS-WC) 0.067 ton 955,879 63,948
3.01.02.02.01.015 Pekerjaan Lataston Lapis Perata (HRS-WC L) m2 63,948
2.01.02.01.07.008 Bahan Lataston Lapis Aus Perata (HRS-WC L) 0.067 ton 955,879 63,948
3.01.02.02.01.016 Pekerjaan Lataston Lapis Pondasi (HRS-BASE) m2 64,898
2.01.02.01.07.009 Bahan Lataston Lapis Pondasi (HRS-BASE) 0.078 ton 831,493 64,898
3.01.02.02.01.017 Pekerjaan Lataston Lapis Pondasi Perata (HRS-BASE L) m2 64,898
2.01.02.01.07.010 Bahan Lataston Lapis Pondasi Perata (HRS-BASE L) 0.078 ton 831,493 64,898
3.01.02.02.01.018 Pekerjaan Laston Lapis Aus (AC-WC) m2 76,091
2.01.02.01.07.011 Bahan Laston Lapis Aus (AC-WC) 0.089 ton 853,037 76,091
3.01.02.02.01.019 Pekerjaan Laston Lapis Aus Perata (AC-WC L) m2 76,091
2.01.02.01.07.012 Bahan Laston Lapis Aus Perata (AC-WC L) 0.089 ton 853,037 76,091
3.01.02.02.01.020 Pekerjaan Laston Lapis Antara (AC-BC) m2 108,010
2.01.02.01.07.013 Bahan Laston Lapis Antara (AC-BC) 0.134 ton 807,252 108,010
3.01.02.02.01.021 Pekerjaan Laston Lapis Antara Perata (AC-BC L) m2 108,010
2.01.02.01.07.014 Bahan Laston Lapis Antara Perata (AC-BC L) 0.134 ton 807,252 108,010
3.01.02.02.01.022 Pekerjaan Laston Lapis Pondasi (AC-BASE) m2 124,075
2.01.02.01.07.015 Bahan Laston Lapis Pondasi (AC-BASE) 0.167 ton 741,856 124,075
3.01.02.02.01.023 Pekerjaan Laston Lapis Pondasi Perata(AC-BASE L) m2 124,075
2.01.02.01.07.016 Bahan Laston Lapis Pondasi Perata (AC-BASE L) 0.167 ton 741,856 124,075
3.01.02.02.01.025 Pekerjaan Pemasangan Patok Pengaman (Delineator) unit 623,896
1.3.2.18.01.01.003.00187 Delineator 1.000 buah 230,400 230,400
1.1.7.01.01.01.022.00520 Scotch Light - White, Engineering Grade 0.500 m2 308,440 154,220
2.02.03.02.01.014 Pekerjaan Cat Besi 0.340 kg 128,535 43,702
2.01.01.03.01.005 Pekerjaan Pembuatan Beton K-175 0.100 m3 869,019 86,902
2.01.02.01.04.016 Pekerjaan Galian Perkerasan Beton 0.180 m3 171,491 30,868
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.180 m3 60,000 10,800
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.040 m3 254,600 10,184
2.01.01.03.02.001 Pekerjaan Pasang Bekisting untuk Pondasi 0.160 m3 355,126 56,820
3.01.02.02.01.026 Pekerjaan Pemasangan Cermin Tikungan unit 2,899,921
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4 mm 0.617 batang 884,900 545,629
1.3.2.18.01.01.003.00180 Cermin Tikungan - Uk. 90 cm, Acrylic + Klem + Mur + Baut 1.050 unit 2,113,100 2,218,755
1.1.7.01.01.01.008.00039 Besi Siku - Uk. 3 x 30 x 30 cm 1.632 kg 13,000 21,216
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.100 m3 80,000 8,000
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.016 m3 299,760 4,796
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 0.112 m3 906,467 101,524
3.01.02.02.01.027 Pekerjaan Pemasangan RPPJ 120 x 180 (Overhead) unit 23,557,759
2.01.01.01.02.004 Pekerjaan Galian Tanah Keras 0.560 m3 106,400 59,584
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 0.430 m3 906,467 389,781
2.01.01.03.01.013 Pekerjaan Pembesian dengan Besi Polos/Ulir 36.000 kg 13,352 480,654
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.050 m3 299,760 14,988
2.01.01.07.03.001 Pekerjaan Pemasangan Besi Profil 293.400 kg 37,085 10,880,739
2.01.01.03.02.001 Pekerjaan Pasang Bekisting untuk Pondasi 3.600 m3 355,126 1,278,454
1.1.7.01.01.01.008.00039 Besi Siku - Uk. 3 x 30 x 30 cm 12.920 kg 13,000 167,960
1.1.7.01.01.01.008.00077 Angkur - Dia. 19 mm, pjg. 60 cm + Mur + Ring 4.000 buah 54,300 217,200

229
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.1.7.01.01.01.022.00126 Mur Baut - Uk. 10 cm 16.000 buah 1,700 27,200
1.1.7.01.01.01.022.00108 Rivet 22.000 buah 11,200 246,400
1.1.7.01.01.01.022.00473 Klem Galvanish - Uk. 3 x 40 x 450 mm 16.000 buah 19,600 313,600
1.1.7.01.01.01.022.00129 Mur Baut - Uk. 3/4 inch. 8.000 buah 1,500 12,000
1.1.7.02.02.07.001.00339 Steel Plate Flange - Dia. 3 inch., tbl. 10 mm 4.000 buah 181,100 724,400
1.1.7.02.02.07.001.00342 Steel Base Plate - Uk. 400 x 400 cm, tbl. 10 mm 1.000 buah 481,600 481,600
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4.5 mm 1.000 batang 884,900 884,900
1.1.7.02.02.07.001.00011 Pipa Galvanis - Medium Dia. 6 inch. Pjg. 600 cm, tbl. 4.5 mm 1.000 batang 3,337,000 3,337,000
1.1.7.02.02.07.001.00005 Pipa Galvanis - Medium Dia. 1 1/2 inch. Pjg. 600 cm, tbl. 3.2 mm 0.267 batang 653,300 174,431
1.1.7.02.02.07.001.00341 Rib Plate Flange - Tbl. 10 mm 24.000 buah 21,400 513,600
1.1.7.02.02.07.001.00340 Rib Base Plate - Tbl. 10 mm 4.000 buah 165,000 660,000
1.1.7.01.01.01.022.00516 Plat Alumunium - Tbl. 2 mm 2.160 m2 440,000 950,400
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 2.160 m2 308,440 666,230
1.1.7.01.01.01.022.00520 Scotch Light - White, Engineering Grade 1.296 m2 308,440 399,738
1.1.7.01.03.09.006.00010 Logo Kementerian 1.000 buah 30,900 30,900
9.1.2.09.03.01.001.00095 Crane - 30 ton 4.000 jam 161,500 646,000
3.01.02.02.01.028 Pekerjaan Pemasangan RPPJ 120 x 240 (Overhead) unit 24,248,862
2.01.01.01.02.004 Pekerjaan Galian Tanah Keras 0.560 m3 106,400 59,584
2.01.01.03.01.007 Pekerjaan Pembuatan Beton K-225 0.430 m3 906,467 389,781
2.01.01.03.01.013 Pekerjaan Pembesian dengan Besi Polos/Ulir 36.000 kg 13,352 480,654
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.050 m3 299,760 14,988
2.01.01.07.03.001 Pekerjaan Pemasangan Besi Profil 293.400 kg 37,085 10,880,739
2.01.01.03.02.001 Pekerjaan Pasang Bekisting untuk Pondasi 3.600 m3 355,126 1,278,454
1.1.7.01.01.01.008.00039 Besi Siku - Uk. 3 x 30 x 30 cm 14.380 kg 13,000 186,940
1.1.7.01.01.01.008.00077 Angkur - Dia. 19 mm, pjg. 60 cm + Mur + Ring 4.000 buah 54,300 217,200
1.1.7.01.01.01.022.00126 Mur Baut - Uk. 10 cm 16.000 buah 1,700 27,200
1.1.7.01.01.01.022.00108 Rivet 22.000 buah 11,200 246,400
1.1.7.01.01.01.022.00473 Klem Galvanish - Uk. 3 x 40 x 450 mm 16.000 buah 19,600 313,600
1.1.7.01.01.01.022.00129 Mur Baut - Uk. 3/4 inch. 8.000 buah 1,500 12,000
1.1.7.02.02.07.001.00339 Steel Plate Flange - Dia. 3 inch., tbl. 10 mm 4.000 buah 181,100 724,400
1.1.7.02.02.07.001.00342 Steel Base Plate - Uk. 400 x 400 cm, tbl. 10 mm 1.000 buah 481,600 481,600
1.1.7.02.02.07.001.00006 Pipa Galvanis - Medium Dia. 2 inch. Pjg. 600 cm, tbl. 4.5 mm 1.000 batang 884,900 884,900
1.1.7.02.02.07.001.00011 Pipa Galvanis - Medium Dia. 6 inch. Pjg. 600 cm, tbl. 4.5 mm 1.000 batang 3,337,000 3,337,000
1.1.7.02.02.07.001.00005 Pipa Galvanis - Medium Dia. 1 1/2 inch. Pjg. 600 cm, tbl. 3.2 mm 0.267 batang 653,300 174,431
1.1.7.02.02.07.001.00341 Rib Plate Flange - Tbl. 10 mm 24.000 buah 21,400 513,600
1.1.7.02.02.07.001.00340 Rib Base Plate - Tbl. 10 mm 4.000 buah 165,000 660,000
1.1.7.01.01.01.022.00516 Plat Alumunium - Tbl. 2 mm 2.880 m2 440,000 1,267,200
1.1.7.01.01.01.022.00519 Scotch Light - Colour, Engineering Grade 2.880 m2 308,440 888,307
1.1.7.01.01.01.022.00520 Scotch Light - White, Engineering Grade 1.728 m2 308,440 532,984
1.1.7.01.03.09.006.00010 Logo Kementerian 1.000 buah 30,900 30,900
9.1.2.09.03.01.001.00095 Crane - 30 ton 4.000 jam 161,500 646,000
3.01.02.02.01.029 Pekerjaan Pemasangan ATCS 3 Simpang unit 191,318,000
1.3.2.10.02.04.033.00049 Switch Hub - 8 Port 1.000 unit 4,390,600 4,390,600
1.3.2.10.02.04.033.00024 Kabel VGA 1.000 buah 393,400 393,400
1.3.2.10.02.04.033.00025 NVR - 16 Channel 1.000 unit 6,462,000 6,462,000
1.3.2.10.02.04.033.00026 High Speed Wireless + Antena 5G30 2.000 set 1,938,900 3,877,800
1.3.2.10.02.04.033.00050 Connector RJ-45 20.000 buah 1,461,200 29,224,000
1.3.2.10.02.04.033.00018 Kabel LAN STP CAT.5e 250.000 m' 8,900 2,225,000
1.3.2.18.01.01.003.00213 Traffic Light Controller ATCS + Box 1.000 unit 60,289,700 60,289,700
1.3.2.18.01.01.003.00214 Set Program ATCS 1.000 set 9,330,600 9,330,600
1.3.2.10.02.04.033.00019 Connector Camera 6.000 buah 28,100 168,600
1.3.2.10.02.04.033.00027 HIK Vision - DS-2AEI123TI PTZ, 23x Zoom + Power Suply 1.000 unit 5,153,400 5,153,400
1.3.2.10.02.04.033.00028 Camera Analog - Samsung SCZ-2370 + Housing + Powersupply 2.000 unit 5,226,500 10,453,000

230
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
1.3.2.10.02.04.033.00029 DVR 4CH HIK Vision 2TB 1.000 unit 3,990,100 3,990,100
1.3.2.10.02.04.033.00030 Tiang Antena 21 m 1.000 set 48,884,000 48,884,000
1.3.2.10.02.04.033.00031 Grounding 1.000 unit 2,248,000 2,248,000
1.3.2.10.02.04.033.00032 Pemasangan Antena dan Set Up Radio Link 2.000 set 2,113,900 4,227,800
3.01.02.02.01.030 Pekerjaan Pemasangan ATCS 4 Simpang unit 226,424,400
1.3.2.10.02.04.033.00049 Switch Hub - 8 Port 1.000 unit 4,390,600 4,390,600
1.3.2.10.02.04.033.00024 Kabel VGA 1.000 buah 393,400 393,400
1.3.2.10.02.04.033.00034 Monitor LED - 19 inch. (Monitor Control) 1.000 buah 1,101,500 1,101,500
1.3.2.10.02.04.033.00033 Monitor LED - 60 inch. (CCTV) 1.000 buah 16,352,800 16,352,800
1.3.2.10.02.04.033.00035 CPU Server CCTV 1.000 buah 12,498,700 12,498,700
1.3.2.10.02.04.033.00025 NVR - 16 Channel 1.000 unit 6,462,000 6,462,000
1.3.2.10.02.04.033.00026 High Speed Wireless + Antena 5G30 2.000 set 1,938,900 3,877,800
1.3.2.10.02.04.033.00050 Connector RJ-45 20.000 buah 1,461,200 29,224,000
1.3.2.10.02.04.033.00018 Kabel LAN STP CAT.5e 250.000 m' 8,900 2,225,000
1.3.2.18.01.01.003.00213 Traffic Light Controller ATCS + Box 1.000 unit 60,289,700 60,289,700
1.3.2.18.01.01.003.00214 Set Program ATCS 1.000 set 9,330,600 9,330,600
1.3.2.10.02.04.033.00019 Connector Camera 6.000 buah 28,100 168,600
1.3.2.10.02.04.033.00027 HIK Vision - DS-2AEI123TI PTZ, 23x Zoom + Power Suply 2.000 unit 5,153,400 10,306,800
1.3.2.10.02.04.033.00028 Camera Analog - Samsung SCZ-2370 + Housing + Powersupply 2.000 unit 5,226,500 10,453,000
1.3.2.10.02.04.033.00029 DVR 4CH HIK Vision 2TB 1.000 unit 3,990,100 3,990,100
1.3.2.10.02.04.033.00030 Tiang Antena 21 m 1.000 set 48,884,000 48,884,000
1.3.2.10.02.04.033.00031 Grounding 1.000 unit 2,248,000 2,248,000
1.3.2.10.02.04.033.00032 Pemasangan Antena dan Set Up Radio Link 2.000 set 2,113,900 4,227,800
3.01.02.02.01.031 Pekerjaan Overlay Jalan (Manual) m2 243,826
2.01.02.01.07.023 Lapis Perekat - Aspal Cair (Manual) 0.575 liter 10,640 6,118
2.01.02.01.07.024 Bahan Laston Lapis Aus (AC-WC) (Manual) 0.089 ton 701,769 62,598
2.01.02.01.07.025 Bahan Laston Lapis Antara (AC-BC) (Manual) 0.105 ton 659,221 69,218

ELEKTRIKAL DAN INSTALASI JARINGAN


3.01.02.03.01.001 Pekerjaan Pemasangan Kabel NYFGBY 4 x 2.5 mm m' 57,292
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.080 m3 80,000 6,400
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00028 Kabel NYFGBY 4 x 2.5 mm 1.000 m' 37,200 37,200
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.020 m3 254,600 5,092
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
3.01.02.03.01.002 Pekerjaan Pemasangan Kabel NYFGBY 4 x 4 mm m' 57,292
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.080 m3 80,000 6,400
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00028 Kabel NYFGBY 4 x 4 mm 1.000 m' 37,200 37,200
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.020 m3 254,600 5,092
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
3.01.02.03.01.003 Pekerjaan Pemasangan Kabel NYFGBY 4 x 6 mm m' 87,892
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.080 m3 80,000 6,400
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00030 Kabel NYFGBY 4 x 6 mm 1.000 m' 67,800 67,800
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.020 m3 254,600 5,092
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
3.01.02.03.01.004 Pekerjaan Pemasangan Kabel NYFGBY 4 x 10 mm m' 116,792
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.080 m3 80,000 6,400
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00031 Kabel NYFGBY 4 x 10 mm 1.000 m' 96,700 96,700
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.020 m3 254,600 5,092
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600

231
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
3.01.02.03.01.005 Pekerjaan Pemasangan Kabel NYFGBY 4 x 16 mm m' 160,592
2.01.01.01.02.001 Pekerjaan Galian Tanah Biasa 0.080 m3 80,000 6,400
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00032 Kabel NYFGBY 4 x 16 mm 1.000 m' 140,500 140,500
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.020 m3 254,600 5,092
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
3.01.02.03.01.006 Pekerjaan Pemasangan Kabel NYY 4 x 2.5 mm m' 143,367
2.02.03.01.01.008 Pekerjaan Pemasangan Pipa untuk Kabel Tanam 1.000 m' 100,975 100,975
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00018 Kabel NYY 4 x 2.5 mm 1.000 m' 28,700 28,700
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.020 m3 254,600 5,092
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
3.01.02.03.01.007 Pekerjaan Pemasangan Kabel NYY 4 x 4 mm m' 155,167
2.02.03.01.01.008 Pekerjaan Pemasangan Pipa untuk Kabel Tanam 1.000 m' 100,975 100,975
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00020 Kabel NYY 4 x 4 mm 1.000 m' 40,500 40,500
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.020 m3 254,600 5,092
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
3.01.02.03.01.008 Pekerjaan Pemasangan Kabel NYY 4 x 6 mm m' 182,067
2.02.03.01.01.008 Pekerjaan Pemasangan Pipa untuk Kabel Tanam 1.000 m' 100,975 100,975
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00021 Kabel NYY 4 x 6 mm 1.000 m' 67,400 67,400
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.020 m3 254,600 5,092
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
3.01.02.03.01.009 Pekerjaan Pemasangan Kabel NYY 4 x 10 mm m' 196,167
2.02.03.01.01.008 Pekerjaan Pemasangan Pipa untuk Kabel Tanam 1.000 m' 100,975 100,975
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00022 Kabel NYY 4 x 10 mm 1.000 m' 81,500 81,500
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.020 m3 254,600 5,092
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
3.01.02.03.01.010 Pekerjaan Pemasangan Kabel NYY 4 x 16 mm m' 258,567
2.02.03.01.01.008 Pekerjaan Pemasangan Pipa untuk Kabel Tanam 1.000 m' 100,975 100,975
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00023 Kabel NYY 4 x 16 mm 1.000 m' 143,900 143,900
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.020 m3 254,600 5,092
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
3.01.02.03.01.011 Pekerjaan Pemasangan Kabel NYY 4 x 25 mm m' 324,351
2.02.03.01.01.008 Pekerjaan Pemasangan Pipa untuk Kabel Tanam 1.000 m' 100,975 100,975
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00024 Kabel NYY 4 x 25 mm 1.000 m' 199,500 199,500
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.060 m3 254,600 15,276
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
3.01.02.03.01.012 Pekerjaan Pemasangan Kabel NYY 4 x 35 mm m' 396,951
2.02.03.01.01.008 Pekerjaan Pemasangan Pipa untuk Kabel Tanam 1.000 m' 100,975 100,975
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00025 Kabel NYY 4 x 35 mm 1.000 m' 272,100 272,100
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.060 m3 254,600 15,276
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.060 m3 60,000 3,600
3.01.02.03.01.013 Pekerjaan Pemasangan Kabel NYM 2 x 1.5 mm m' 113,800
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00008 Kabel NYM 2 x 1.5 mm 1.000 m' 10,800 10,800
1.1.7.01.03.08.001.00037 Klem Kabel 5.000 buah 19,600 98,000
3.01.02.03.01.014 Pekerjaan Pemasangan Kabel NYM 2 x 2.5 mm m' 121,900

232
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00009 Kabel NYM 2 x 2.5 mm 1.000 m' 18,900 18,900
1.1.7.01.03.08.001.00037 Klem Kabel 5.000 buah 19,600 98,000
3.01.02.03.01.015 Pekerjaan Pemasangan Kabel Twisted 2 x 10 mm m' 109,700
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00034 Kabel Twisted 2 x 10 mm 1.000 m' 6,700 6,700
1.1.7.01.03.08.001.00037 Klem Kabel 5.000 buah 19,600 98,000
3.01.02.03.01.016 Pekerjaan Pemasangan Kabel Twisted 2 x 16 mm m' 111,400
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00035 Kabel Twisted 2 x 16 mm 1.000 m' 8,400 8,400
1.1.7.01.03.08.001.00037 Klem Kabel 5.000 buah 19,600 98,000
3.01.02.03.01.017 Pekerjaan Pemasangan Kabel Twisted 4 x 16 mm m' 130,000
2.02.03.01.01.006 Pekerjaan Penarikan Kabel 1.000 m' 5,000 5,000
1.1.7.01.03.08.001.00036 Kabel Twisted 4 x 16 mm 1.000 m' 27,000 27,000
1.1.7.01.03.08.001.00037 Klem Kabel 5.000 buah 19,600 98,000

BANGUNAN MASYARAKAT DAN LINGKUNGAN


3.01.02.04.01.001 Septictank Pasasangan Bata Kapasitas 3 m3 + Rembesan unit 6,720,496
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 5.100 m3 36,850 187,933
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.300 m3 299,760 89,928
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 3.000 m2 729,451 2,188,352
2.01.01.04.01.001 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 2 Ps) 10.500 m2 268,884 2,823,282
2.01.01.04.02.020 Pekerjaan Acian 12.000 m2 41,750 501,000
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 0.360 m3 890,439 320,558
2.01.01.07.02.023 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1 inch 3.600 m' 33,973 122,301
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch 0.800 m' 177,921 142,337
1.1.7.01.01.01.005.00004 Batu Pecah 1.050 m3 264,100 277,305
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 1.125 m3 60,000 67,500
3.01.02.04.01.002 Septictank Pasasangan Bata Kapasitas 6 m3 + Rembesan unit 8,955,168
2.01.02.01.03.001 Pekerjaan Galian Untuk Selokan Drainase dan Saluran Air 9.250 m3 36,850 340,859
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.300 m3 299,760 89,928
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 3.000 m2 729,451 2,188,352
2.01.01.04.01.001 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 2 Ps) 17.000 m2 268,884 4,571,028
2.01.01.04.02.020 Pekerjaan Acian 20.000 m2 41,750 835,000
2.01.01.03.01.006 Pekerjaan Pembuatan Beton K-200 0.360 m3 890,439 320,558
2.01.01.07.02.023 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 1 inch 3.600 m' 33,973 122,301
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch 0.800 m' 177,921 142,337
1.1.7.01.01.01.005.00004 Batu Pecah 1.050 m3 264,100 277,305
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 1.125 m3 60,000 67,500
3.01.02.04.01.003 Pemasangan Pipa Saluran Air Bersih Ø 4" m' 615,318
2.01.02.01.04.001 Pekerjaan Galian Biasa + Pembuangan Sisa Galian 0.270 m3 38,802 10,477
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch 1.000 m' 177,921 177,921
2.01.01.07.02.037 Pekerjaan Pemasangan Tee Pipa PVC Type D Diameter 4 inch 0.004 unit 156,640 627
2.01.01.07.02.038 Pekerjaan Pemasangan Elbow Pipa PVC Type D Diameter 4 inch 0.003 unit 116,490 349
2.01.01.07.02.039 Pekerjaan Pemasangan Socket Pipa PVC Type D Diameter 4 inch 0.015 unit 101,310 1,520
2.01.01.07.02.040 Pekerjaan Pemasangan Valve Pipa PVC Type D Diameter 4 inch 0.008 unit 226,349 1,698
2.01.01.07.02.041 Pekerjaan Pemasangan Blank Flanged Diameter 4 inch 0.001 unit 203,773 204
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 4.100 buah 87,700 359,570
2.01.01.01.02.009 Pekerjaan Pengurugan Kembali Galian Tanah Biasa 0.065 m3 60,000 3,900
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.197 m3 299,760 59,053
3.01.02.04.01.004 Pemasangan IPAL Komunal Panjang 7 m, Diameter 3 m unit 357,887,785
Pekerjaan Tanah
2.01.02.01.04.001 Pekerjaan Galian Biasa + Pembuangan Sisa Galian 124.313 m3 38,802 4,823,589

233
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 3.825 m3 299,760 1,146,582
Pekerjaan Struktur Beton
2.01.01.02.01.011 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 20 cm Sedalam 3 m 6.000 titik 192,720 1,156,320
2.01.01.03.01.016 Pekerjaan Pembuatan Pondasi Beton Bertulang (150 kg Besi + Bekisting) 0.790 m3 4,671,766 3,690,695
2.01.01.03.01.020 Pekerjaan Pembuatan Plat Beton Bertulang (150 kg Besi + Bekisting) 9.563 m3 7,678,812 73,432,479
2.01.01.03.01.021 Pekerjaan Pembuatan Dinding Beton Bertulang (150 kg Besi + Bekisting) 9.881 m3 7,296,126 72,093,021
2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.780 m3 5,828,054 4,545,882
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 0.988 m2 68,305 67,486
Pekerjaan Instalasi Reaktor
1.1.7.01.01.05.007.00060 Reaktor IPAL Komunal (Fabrikasi) 1.000 unit 175,000,000 175,000,000
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch 4.000 m' 177,921 711,685
2.01.01.07.02.037 Pekerjaan Pemasangan Tee Pipa PVC Type D Diameter 4 inch 0.016 unit 156,640 2,506
2.01.01.07.02.038 Pekerjaan Pemasangan Elbow Pipa PVC Type D Diameter 4 inch 0.012 unit 116,490 1,398
2.01.01.07.02.039 Pekerjaan Pemasangan Socket Pipa PVC Type D Diameter 4 inch 0.060 unit 101,310 6,079
2.01.01.07.02.040 Pekerjaan Pemasangan Valve Pipa PVC Type D Diameter 4 inch 0.032 unit 226,349 7,243
2.01.01.07.02.041 Pekerjaan Pemasangan Blank Flanged Diameter 4 inch 0.004 unit 203,773 815
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 16.000 buah 87,700 1,403,200
1.3.2.01.03.05.005.00034 Pompa Submersible - Ejector IPAL, 400 Watt 1.000 unit 5,335,000 5,335,000
1.3.2.01.03.05.005.00035 Pompa Submersible - Input Biofilter, 180 Watt 1.000 unit 3,575,000 3,575,000
Pekerjaan Instalasi Listrik
3.01.02.03.01.006 Pekerjaan Pemasangan Kabel NYY 4 x 2.5 mm 45.000 m' 143,367 6,451,515
2.01.01.07.06.013 Pekerjaan Pemasangan Panel Box 1.000 unit 793,100 793,100
1.1.7.01.01.01.022.00508 Panel kWh Meter - 1 Phase 1.000 buah 571,300 571,300
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm (for ARDE) 6.000 m' 31,400 188,400
2.01.01.07.06.014 Pekerjaan Pemasangan Panel Phase 2200 VA 1.000 unit 2,884,490 2,884,490
3.01.02.04.01.005 Pemasangan Septictank Komunal Tinggi 3.5 m, Diameter 2 m unit 145,099,921
Pekerjaan Tanah
2.01.02.01.04.001 Pekerjaan Galian Biasa + Pembuangan Sisa Galian 30.375 m3 38,802 1,178,610
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 1.350 m3 299,760 404,676
Pekerjaan Struktur Beton
2.01.01.02.01.011 Pekerjaan Pembuatan Lubang Strouss Pile Diameter 20 cm Sedalam 3 m 4.000 titik 192,720 770,880
2.01.01.03.01.016 Pekerjaan Pembuatan Pondasi Beton Bertulang (150 kg Besi + Bekisting) 0.527 m3 4,671,766 2,462,021
2.01.01.03.01.020 Pekerjaan Pembuatan Plat Beton Bertulang (150 kg Besi + Bekisting) 3.375 m3 7,678,812 25,915,991
2.01.01.03.01.021 Pekerjaan Pembuatan Dinding Beton Bertulang (150 kg Besi + Bekisting) 3.544 m3 7,296,126 25,855,647
2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.450 m3 5,828,054 2,622,624
2.01.01.04.02.004 Pekerjaan Plesteran 1 Pc : 4 Ps tbl 15 mm 0.354 m2 68,305 24,206
Pekerjaan Instalasi Reaktor
1.1.7.01.01.05.007.00059 Septictank Komunal (Fabrikasi) 1.000 unit 65,000,000 65,000,000
2.01.01.07.02.028 Pekerjaan Pemasangan Pipa PVC Type AW Diameter 4 inch 2.000 m' 177,921 355,843
2.01.01.07.02.037 Pekerjaan Pemasangan Tee Pipa PVC Type D Diameter 4 inch 0.008 unit 156,640 1,253
2.01.01.07.02.038 Pekerjaan Pemasangan Elbow Pipa PVC Type D Diameter 4 inch 0.006 unit 116,490 699
2.01.01.07.02.039 Pekerjaan Pemasangan Socket Pipa PVC Type D Diameter 4 inch 0.030 unit 101,310 3,039
2.01.01.07.02.040 Pekerjaan Pemasangan Valve Pipa PVC Type D Diameter 4 inch 0.016 unit 226,349 3,622
2.01.01.07.02.041 Pekerjaan Pemasangan Blank Flanged Diameter 4 inch 0.002 unit 203,773 408
1.1.7.01.01.01.008.00063 Beugel Mur + Baut - Uk. 60 x 60 mm, 6 mm 8.000 buah 87,700 701,600
1.3.2.01.03.05.005.00034 Pompa Submersible - Ejector IPAL, 400 Watt 1.000 unit 5,335,000 5,335,000
1.3.2.01.03.05.005.00035 Pompa Submersible - Input Biofilter, 180 Watt 1.000 unit 3,575,000 3,575,000
Pekerjaan Instalasi Listrik
3.01.02.03.01.006 Pekerjaan Pemasangan Kabel NYY 4 x 2.5 mm 45.000 m' 143,367 6,451,515
2.01.01.07.06.013 Pekerjaan Pemasangan Panel Box 1.000 unit 793,100 793,100
1.1.7.01.01.01.022.00508 Panel kWh Meter - 1 Phase 1.000 unit 571,300 571,300
1.1.7.02.02.06.001.00103 Pipa PVC - Type C Dia. 1/2 inch. pjg. 400 cm (for ARDE) 6.000 m' 31,400 188,400
2.01.01.07.06.014 Pekerjaan Pemasangan Panel Phase 2200 VA 1.000 unit 2,884,490 2,884,490

234
KODE BARANG URAIAN KEGIATAN KOEF. SATUAN HARGA JUMLAH
(a) (b) (c) (d) (e) (f)
9.1.2.09.03.01.001.00095 Crane - 30 ton 8.000 jam 161,500 1,292,000
3.01.02.04.01.007 Pekerjaan Pembuatan Taman Aktif m2 888,233
PEKERJAAN PERSIAPAN
2.01.01.01.01.008 Pekerjaan Pembersihan Lapangan "Ringan" dan Perataan 1.000 m2 10,000 10,000
PEKERJAAN TANAH
2.01.01.01.02.020 Pekerjaan Pengurugan Sirtu Padat 0.040 m3 299,760 11,990
2.01.01.01.02.019 Pekerjaan Pengurugan Pasir Urug 0.020 m3 254,600 5,092
2.02.03.03.01.033 Penyiapan Media Tanam 0.110 m3 426,720 46,939
PEKERJAAN STRUKTUR
2.01.01.03.01.001 Pekerjaan Pembuatan Lantai Kerja K-100 0.020 m3 729,451 14,589
PEKERJAAN DINDING
2.01.01.04.01.018 Pekerjaan Pemasangan Bata Merah tbl 1/2 Bata (1 Pc : 5 Ps) 0.190 m2 123,271 23,421
2.01.01.04.01.017 Pekerjaan Pemasangan Bata Merah tbl 1 Bata (1 Pc : 5 Ps) 0.100 m2 251,540 25,154
2.01.01.04.02.005 Pekerjaan Plesteran 1 Pc : 5 Ps tbl 15 mm 0.330 m2 67,609 22,311
2.01.01.04.02.020 Pekerjaan Acian 0.330 m2 41,750 13,778
PEKERJAAN LANTAI
2.02.03.03.01.035 Pekerjaan Pasangan Lantai Batu Andesit 0.350 m2 338,271 118,395
PEKERJAAN FINISHING
2.02.03.03.01.034 Pekerjaan Pasangan Batu Refleksi 0.020 m2 283,300 5,666
2.01.01.07.02.018 Pekerjaan Pemasangan Pipa Galvanis Diameter 3 inch 0.050 m' 426,115 21,306
2.01.01.07.05.024 Pekerjaan Pengecatan Outdoor Antislip 0.080 m2 53,403 4,272
PEKERJAAN PEMASANGAN MAINAN ANAK
1.3.2.08.03.16.001.00081 Mainan Anak Perosotan Ganda + Pemasangan 0.005 unit 2,500,000 12,000
1.3.2.08.03.16.001.00079 Mainan Anak Ayun Ganda + Pemasangan 0.005 unit 2,800,000 13,440
1.3.2.08.03.16.001.00080 Mainan Anak Jungkat-Jungkit + Pemasangan 0.005 unit 2,800,000 13,440
1.3.2.08.03.16.001.00082 Mainan Fitnes Outdoor + Pemasangan 0.014 unit 10,000,000 144,000
PEKERJAAN PENANAMAN
2.02.03.03.01.036 Penanaman Pohon Diameter < 15 cm Batang Tunggal 0.063 batang 14,000 876
1.3.5.05.01.01.006.00470 Pohon Hias - Besar 0.010 batang 3,000,000 28,800
1.3.5.05.01.01.006.00471 Pohon Hias - Sedang 0.053 batang 1,650,000 87,450
2.02.03.03.01.031 Penanaman Semak Hias 2.369 batang 18,500 43,827
1.3.5.05.01.01.006.00472 Tanaman Semak Hias - Kecil 0.976 batang 55,000 53,669
1.3.5.05.01.01.006.00473 Tanaman Semak Hias - Sedang 1.393 batang 110,000 153,230
2.02.03.03.01.030 Penanaman Rumput Taman 0.245 m2 34,300 8,390
1.3.5.05.01.01.006.00145 Rumput Taman - Lamur 0.245 m2 25,300 6,199
3.01.02.04.01.011 Pekerjaan Pembuatan Trotoar dengan Tegel Batu Ampyang m2 286,079
2.01.01.01.01.004 Pekerjaan Pengukuran dan Pemasangan Bouwplank 0.045 titik 145,360 6,570
2.01.01.03.01.017 Pekerjaan Pembuatan Sloof Beton Bertulang (200 kg Besi + Bekisting) 0.007 m3 5,828,054 43,128
2.01.01.04.02.003 Pekerjaan Plesteran 1 Pc : 3 Ps tbl 15 mm 0.090 m2 69,661 6,297
2.01.02.01.01.015 Pekerjaan Tegel Batu Ampyang 1.000 m2 208,060 208,060
3.01.02.02.01.025 Pekerjaan Pemasangan Patok Pengaman (Delineator) 0.035 unit 623,896 22,024

235
A
A S na
lis
a
B
St N
MOJOKERTO

an
da
r
O
N
PEMERINTAH KOTA

Be
l an
ja F
K I
eg
ia
SI
ta
n
K
N
on
Fi
si k

2020
TAHUN ANGGARAN
REKAP
KODE BARANG URAIAN KEGIATAN SATUAN HARGA
(a) (b) (c) (d)
3.02 ASB NON FISIK
3.02.01 ANALISIS STANDAR BELANJA NON FISIK
3.02.01.01 KEGIATAN PERENCANAAN
3.02.01.01.01 PENELITIAN/KAJIAN
3.02.01.01.01.001 Kegiatan Penelitian / Kajian Tipe 1 : Kajian ( 46,000,300)
3.02.01.01.01.002 Kegiatan Penelitian / Kajian Tipe 2 : Kajian ( 64,328,600)
3.02.01.01.02.001 Kegiatan Penyusunan Rumusan Kebijakan Tipe 1 : Paket Kebijakan ( 57,825,100)
3.02.01.01.02.002 Kegiatan Penyusunan Rumusan Kebijakan Tipe 2 : Paket Kebijakan ( 154,672,000)
3.02.01.02 KEGIATAN PELAKSANAAN
3.02.01.02.01 KEGIATAN SOSIALISASI / PENYULUHAN
3.02.01.02.01.001 Kegiatan Sosialisasi / Penyuluhan Tipe 1 : Per Kegiatan ( 28,896,900)
3.02.01.02.01.004 Kegiatan Sosialisasi / Penyuluhan Tipe 1 : Per Kegiatan ( 27,913,500)
3.02.01.02.01.002 Kegiatan Sosialisasi / Penyuluhan Tipe 2 : Per Kegiatan ( 26,967,500)
3.02.01.02.01.005 Kegiatan Sosialisasi / Penyuluhan Tipe 2 : Per Kegiatan ( 27,964,100)
3.02.01.02.01.003 Kegiatan Sosialisasi / Penyuluhan Tipe 3 : Per Kegiatan ( 35,267,900)
3.02.01.02.01.006 Kegiatan Sosialisasi / Penyuluhan Tipe 3 : Per Kegiatan ( 36,264,500)
3.02.01.02.02 KEGIATAN PELATIHAN/BIMTEK/WORKSHOP
3.02.01.02.02.001 Kegiatan Pelatihan / Bimtek / Workshop Tipe 1 : Per Kegiatan ( 41,546,500)
3.02.01.02.02.002 Kegiatan Pelatihan / Bimtek / Workshop Tipe 2 : Per Kegiatan ( 47,150,600)
3.02.01.02.02.005 Kegiatan Pelatihan / Bimtek / Workshop Tipe 2 : Per Kegiatan ( 43,076,200)
3.02.01.02.02.003 Kegiatan Pelatihan / Bimtek / Workshop Tipe 3 : Per Kegiatan ( 26,810,400)
3.02.01.02.02.004 Kegiatan Pelatihan / Bimtek / Workshop Tipe 4 : Per Kegiatan ( 32,879,900)
3.02.01.02.02.006 Kegiatan Pelatihan / Bimtek / Workshop Tipe 4 : Per Kegiatan ( 33,876,500)
3.02.01.02.03 KEGIATAN PAGELARAN/FESTIVAL/PAWAI
3.02.01.02.03.001 Kegiatan Pagelaran / Festival / Pawai Tipe 1 : Per Kegiatan ( 93,576,600)
3.02.01.02.03.002 Kegiatan Pagelaran / Festival / Pawai Tipe 2 : Grup ( 46,630,100)
3.02.01.02.03.003 Kegiatan Pagelaran / Festival / Pawai Tipe 3 : Peserta ( 68,698,500)
3.02.01.02.04 KEGIATAN PAMERAN/EXPO
3.02.01.02.04.001 Kegiatan Pameran / Expo Tipe 1 : Peserta ( 17,510,000)
3.02.01.02.04.002 Kegiatan Pameran / Expo Tipe 2 : Peserta ( 25,208,100)
3.02.01.02.04.003 Kegiatan Pameran / Expo Tipe 3 : Peserta ( 40,335,600)
3.02.01.02.04.004 Kegiatan Pameran / Expo Tipe 4 : Stand ( 17,923,900)
3.02.01.02.05 KEGIATAN LOMBA
3.02.01.02.05.001 Kegiatan Lomba Tipe 1 : Peserta ( 54,919,600)
3.02.01.02.05.002 Kegiatan Lomba Tipe 2 : Peserta ( 81,346,600)
3.02.01.02.05.003 Kegiatan Lomba Tipe 3 : Peserta ( 12,884,940)

236
A
A S
na
l isa B
St N
MOJOKERTO

an
da
r
O
N
PEMERINTAH KOTA

Be
l an
ja F
K I
eg
ia
SI
taK
n
N
on
Fi
si k

2020
TAHUN ANGGARAN
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
3.02 ASB NON FISIK
3.02.01 ANALISIS STANDAR BELANJA NON FISIK
3.02.01.01 KEGIATAN PERENCANAAN
3.02.01.01.01 PENELITIAN/KAJIAN
3.02.01.01.01.001 Kegiatan Penelitian / Kajian Tipe 1 : Output Kajian ( 46,000,300)
Spesifikasi :
Pendampingan Pihak Ke-3, 2 Tenaga Ahli, 5 Surveyor, 150 Respoden, 6
Kali Rapat, Lama Pelaksanaan 3 Bulan
Honorarium ( 39,840,000)
1.10.28.02.02.002.028 Jasa Surveyor 150 OH 50,000 ( 7,500,000)
1.10.28.02.03.002.072 Ahli Madya 6 OB 5,390,000 ( 32,340,000)
Bahan Pakai Habis ( 1,193,600)
1.1.7.01.03.01.006.00014 Stop Map 30 buah 13,500 ( 405,000)
1.1.7.01.03.02.001.00007 HVS 70 Gr 6 rim 50,600 ( 303,600)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pak 1,700 ( 5,100)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.01.001.00002 Ball Point 12 buah 13,700 ( 164,400)
1.1.7.01.03.01.004.00003 Correction 1 buah 5,600 ( 5,600)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dos 24,700 ( 24,700)
1.1.7.01.03.03.007.00001 Materai 21 buah 4,500 ( 94,500)
1.1.7.01.03.06.004.00003 Refil Printer 1 buah 172,000 ( 172,000)
Cetak dan Penggandaan ( 414,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
1.1.7.01.03.01.014.00182 Cetak Laporan 5 eksemplar 42,900 ( 214,500)
Konsumsi ( 4,552,200)
1.1.7.01.07.01.001.00080 Nasi Kotak 162 kotak 28,100 ( 4,552,200)
3.02.01.01.01.002 Kegiatan Penelitian / Kajian Tipe 2 : Output Kajian ( 64,328,600)
Spesifikasi :
Pendampingan Pihak Ke-3, 3 Tenaga Ahli, 5 Surveyor, 150 Respoden, 6
Kali Rapat, FGD, Lama Pelaksanaan 3 Bulan
Honorarium ( 56,010,000)
1.10.28.02.02.002.028 Jasa Surveyor 150 OH 50,000 ( 7,500,000)
1.10.28.02.03.002.072 Ahli Madya 9 OB 5,390,000 ( 48,510,000)
Bahan Pakai Habis ( 1,441,100)
1.1.7.01.03.01.006.00014 Stop Map 30 buah 13,500 ( 405,000)
1.1.7.01.03.02.001.00007 HVS 70 Gr 9 rim 50,600 ( 455,400)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.01.001.00002 Ball Point 18 buah 13,700 ( 246,600)
1.1.7.01.03.01.004.00003 Correction 1 buah 5,600 ( 5,600)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dus 24,700 ( 24,700)
1.1.7.01.03.03.007.00001 Materai 24 buah 4,500 ( 108,000)
1.1.7.01.03.06.004.00003 Refil Printer 1 buah 172,000 ( 172,000)
Cetak dan Penggandaan ( 414,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
1.1.7.01.03.01.014.00182 Cetak Laporan 5 eksemplar 42,900 ( 214,500)
Konsumsi ( 6,463,000)
1.1.7.01.07.01.001.00080 Nasi Kotak 230 kotak 28,100 ( 6,463,000)
3.02.01.01.02.001 Kegiatan Penyusunan Rumusan Kebijakan Tipe 1 : Output Paket Kebijakan ( 57,825,100)

237
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
Spesifikasi :
Pendampingan Pihak Ke-3, 3 Tenaga Ahli, 12 Kali Rapat/FGD, Lama
Pelaksanaan 3 Bulan
Honorarium ( 49,066,800)
1.10.28.02.03.002.072 Ahli Madya 9 OB 5,390,000 ( 48,510,000)
Bahan Pakai Habis ( 556,800)
1.1.7.01.03.01.006.00014 Stop Map 30 buah 13,500 ( 405,000)
1.1.7.01.03.02.001.00007 HVS 70 Gr 3 rim 50,600 ( 151,800)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.01.001.00002 Ball Point 27 buah 13,700 ( 369,900)
1.1.7.01.03.01.004.00003 Correction 1 buah 5,600 ( 5,600)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dus 24,700 ( 24,700)
1.1.7.01.03.03.007.00001 Materai 9 buah 4,500 ( 40,500)
1.1.7.01.03.06.004.00003 Refil Printer 1 buah 172,000 ( 172,000)
Cetak dan Penggandaan ( 614,500)
1.1.7.01.03.01.014.00062 Photo Copy 2500 lembar 200 ( 500,000)
1.1.7.01.03.01.014.00182 Cetak Laporan 5 eksemplar 42,900 ( 214,500)
Konsumsi ( 7,587,000)
1.1.7.01.07.01.001.00080 Nasi Kotak 270 kotak 28,100 ( 7,587,000)
3.02.01.01.02.002 Kegiatan Penyusunan Rumusan Kebijakan Tipe 2 : Output Paket Kebijakan ( 154,672,000)
Spesifikasi :
Pendampingan Pihak Ke-3, 5 Tenaga Ahli, 20 Kali Rapat/FGD, Lama
Pelaksanaan 5 Bulan
Honorarium ( 134,750,000)
1.10.28.02.03.002.072 Ahli Madya 25 OB 5,390,000 ( 134,750,000)
Bahan Pakai Habis ( 2,347,500)
1.1.7.01.03.01.006.00014 Stop Map 30 buah 13,500 ( 405,000)
1.1.7.01.03.02.001.00007 HVS 70 Gr 5 rim 50,600 ( 253,000)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 5 pack 1,700 ( 8,500)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.01.001.00002 Ball Point 100 buah 13,700 ( 1,370,000)
1.1.7.01.03.01.004.00003 Correction 1 buah 5,600 ( 5,600)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dus 24,700 ( 24,700)
1.1.7.01.03.03.007.00001 Materai 20 buah 4,500 ( 90,000)
1.1.7.01.03.06.004.00003 Refil Printer 1 buah 172,000 ( 172,000)
Cetak dan Penggandaan ( 714,500)
1.1.7.01.03.01.014.00062 Photo Copy 2500 lembar 200 ( 500,000)
1.1.7.01.03.01.014.00182 Cetak Laporan 5 eksemplar 42,900 ( 214,500)
Konsumsi ( 16,860,000)
1.1.7.01.07.01.001.00080 Nasi Kotak 600 kotak 28,100 ( 16,860,000)
3.02.01.02 KEGIATAN PELAKSANAAN
3.02.01.02.01 KEGIATAN SOSIALISASI/PENYULUHAN
3.02.01.02.01.001 Kegiatan Sosialisasi / Penyuluhan Tipe 1 : Output Per Kegiatan ( 28,896,900)
Spesifikasi :
Gedung Eksternal (Room Only), PNS/Internal Pegawai Pemkot Mojokerto per orang ( 577,938)
(Narsum : Kepala OPD, Direktur, dan Setara Eselon II)
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari

238
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)

Honorarium ( 1,300,000)
1.10.28.02.02.002.001 Moderator 1 OH 700,000 ( 700,000)
1.10.28.02.02.002.002 Pembawa Acara 1 OH 400,000 ( 400,000)
1.10.28.02.02.002.003 Pembaca Doa 1 OH 200,000 ( 200,000)
Biaya Tetap Sewa Gedung ( 6,069,500)
9.1.2.07.03.01.001.00001 Sewa Ruang Pertemuan (Room Only, Cap. 80) 1 ruang 5,619,900 ( 5,619,900)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
Biaya Sewa Perlengkapan ( 2,035,100)
9.1.2.10.03.01.001.00001 Sewa LCD Proyektor 1 unit/hari 393,400 ( 393,400)
9.1.2.10.03.01.001.00002 Sewa Layar Proyektor (Tripot) 1 unit/hari 393,400 ( 393,400)
9.1.2.10.01.01.001.00002 Sewa Meja Sidang 6 unit/hari 84,300 ( 505,800)
9.1.2.10.01.01.001.00030 Sewa Kursi Backled + Cover 55 buah 13,500 ( 742,500)
Bahan Pakai Habis ( 2,141,800)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dos 24,700 ( 24,700)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.003.00003 Binder Clip 1 dos 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pak 1,700 ( 5,100)
1.1.7.01.03.01.001.00010 Spidol 3 buah 7,900 ( 23,700)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.06.004.00003 Refil Printer 1 buah 172,000 ( 172,000)
1.1.7.01.03.01.006.00014 Stop Map 55 buah 13,500 ( 742,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Cetak dan Penggandaan ( 2,714,000)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00182 Cetak Handout Seminar 55 eksemplar 42,900 ( 2,359,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
Biaya Jasa Narasumber ( 10,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 4 OJ 2,500,000 ( 10,000,000)
Bintek (Kegiatan Sejenis)
Konsumsi ( 4,636,500)
1.1.7.01.07.01.001.00083 Prasmanan 55 per pack 84,300 ( 4,636,500)
1.1.7.01.07.01.001.00088 Coffee break 55 Per Pack 56,200 ( 3,091,000)
3.02.01.02.01.004 Kegiatan Sosialisasi / Penyuluhan Tipe 1 : Output Per Kegiatan ( 27,913,500)
Spesifikasi :
Gedung Eksternal (All In), PNS/Internal Pegawai Pemkot Mojokerto per orang ( 558,270)
(Narsum : Kepala OPD, Direktur, dan Setara Eselon II)
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari

Honorarium ( 1,300,000)
1.10.28.02.02.002.001 Moderator 1 OH 700,000 ( 700,000)
1.10.28.02.02.002.002 Pembawa Acara 1 OH 400,000 ( 400,000)
1.10.28.02.02.002.003 Pembaca Doa 1 OH 200,000 ( 200,000)
Biaya Tetap Sewa Gedung ( 9,722,600)
9.1.2.07.03.01.001.00007 Sewa Ruang Pertemuan (All In) 55 pax 168,600 ( 9,273,000)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
Biaya Sewa Perlengkapan ( 2,035,100)
9.1.2.10.03.01.001.00001 Sewa LCD Proyektor 1 unit/hari 393,400 ( 393,400)

239
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
9.1.2.10.03.01.001.00002 Sewa Layar Proyektor (Tripot) 1 unit/hari 393,400 ( 393,400)
9.1.2.10.01.01.001.00002 Sewa Meja Sidang 6 unit/hari 84,300 ( 505,800)
9.1.2.10.01.01.001.00030 Sewa Kursi Backled + Cover 55 buah 13,500 ( 742,500)
Bahan Pakai Habis ( 2,141,800)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dos 24,700 ( 24,700)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.003.00003 Binder Clip 1 dos 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pak 1,700 ( 5,100)
1.1.7.01.03.01.001.00010 Spidol 3 buah 7,900 ( 23,700)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.06.004.00003 Refil Printer 1 buah 172,000 ( 172,000)
1.1.7.01.03.01.006.00014 Stop Map 55 buah 13,500 ( 742,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Cetak dan Penggandaan ( 2,714,000)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00182 Cetak Handout Seminar 55 eksemplar 42,900 ( 2,359,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
Biaya Jasa Narasumber ( 10,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 4 OJ 2,500,000 ( 10,000,000)
Bintek (Kegiatan Sejenis)
3.02.01.02.01.002 Kegiatan Sosialisasi / Penyuluhan Tipe 2 : Output Per Kegiatan ( 26,967,500)
Spesifikasi :
Gedung Eksternal (Room Only), PNS/Internal Pegawai Pemkot Mojokerto
per orang ( 539,350)
(Narsum : Sekretaris - Eselon III, Pimpinan Perusahaan, BUMN/BUMD
atau Setara)
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari

Honorarium ( 1,300,000)
1.10.28.02.02.002.001 Moderator 1 OH 700,000 ( 700,000)
1.10.28.02.02.002.002 Pembawa Acara 1 OH 400,000 ( 400,000)
1.10.28.02.02.002.003 Pembaca Doa 1 OH 200,000 ( 200,000)
Biaya Tetap Sewa Gedung ( 6,069,500)
9.1.2.07.03.01.001.00001 Sewa Ruang Pertemuan (Room Only, Cap. 80) 1 ruang 5,619,900 ( 5,619,900)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
Biaya Sewa Perlengkapan ( 2,035,100)
9.1.2.10.03.01.001.00001 Sewa LCD Proyektor 1 unit/hari 393,400 ( 393,400)
9.1.2.10.03.01.001.00002 Sewa Layar Proyektor (Tripot) 1 unit/hari 393,400 ( 393,400)
9.1.2.10.01.01.001.00002 Sewa Meja Sidang 6 unit/hari 84,300 ( 505,800)
9.1.2.10.01.01.001.00030 Sewa Kursi Backled + Cover 55 buah 13,500 ( 742,500)
Bahan Pakai Habis ( 2,192,400)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dos 24,700 ( 24,700)
1.1.7.01.03.02.001.00007 HVS 70 Gr 2 rim 50,600 ( 101,200)
1.1.7.01.03.01.003.00003 Binder Clip 1 dos 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pak 1,700 ( 5,100)
1.1.7.01.03.01.001.00010 Spidol 3 buah 7,900 ( 23,700)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.06.004.00003 Refil Printer 1 buah 172,000 ( 172,000)

240
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
1.1.7.01.03.01.006.00014 Stop Map 55 buah 13,500 ( 742,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Cetak dan Penggandaan ( 2,714,000)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00182 Cetak Handout Seminar 55 eksemplar 42,900 ( 2,359,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
Biaya Jasa Narasumber ( 10,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 4 OJ 2,500,000 ( 10,000,000)
Bintek (Kegiatan Sejenis)
Konsumsi ( 2,656,500)
1.1.7.01.07.01.001.00080 Nasi Kotak 55 kotak 28,100 ( 1,545,500)
1.1.7.01.07.01.001.00086 Snack Kotak 55 kotak 20,200 ( 1,111,000)
3.02.01.02.01.005 Kegiatan Sosialisasi / Penyuluhan Tipe 2 : Output Per Kegiatan ( 27,964,100)
Spesifikasi :
Gedung Eksternal (All In), PNS/Internal Pegawai Pemkot Mojokerto
per orang ( 559,282)
(Narsum : Sekretaris - Eselon III, Pimpinan Perusahaan, BUMN/BUMD
atau Setara)
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari

Honorarium ( 1,300,000)
1.10.28.02.02.002.001 Moderator 1 OH 700,000 ( 700,000)
1.10.28.02.02.002.002 Pembawa Acara 1 OH 400,000 ( 400,000)
1.10.28.02.02.002.003 Pembaca Doa 1 OH 200,000 ( 200,000)
Biaya Tetap Sewa Gedung ( 9,722,600)
9.1.2.07.03.01.001.00007 Sewa Ruang Pertemuan (All In) 55 pax 168,600 ( 9,273,000)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
Biaya Sewa Perlengkapan ( 2,035,100)
9.1.2.10.03.01.001.00001 Sewa LCD Proyektor 1 unit/hari 393,400 ( 393,400)
9.1.2.10.03.01.001.00002 Sewa Layar Proyektor (Tripot) 1 unit/hari 393,400 ( 393,400)
9.1.2.10.01.01.001.00002 Sewa Meja Sidang 6 unit/hari 84,300 ( 505,800)
9.1.2.10.01.01.001.00030 Sewa Kursi Backled + Cover 55 buah 13,500 ( 742,500)
Bahan Pakai Habis ( 2,192,400)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dos 24,700 ( 24,700)
1.1.7.01.03.02.001.00007 HVS 70 Gr 2 rim 50,600 ( 101,200)
1.1.7.01.03.01.003.00003 Binder Clip 1 dos 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pak 1,700 ( 5,100)
1.1.7.01.03.01.001.00010 Spidol 3 buah 7,900 ( 23,700)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.06.004.00003 Refil Printer 1 buah 172,000 ( 172,000)
1.1.7.01.03.01.006.00014 Stop Map 55 buah 13,500 ( 742,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Cetak dan Penggandaan ( 2,714,000)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00182 Cetak Handout Seminar 55 eksemplar 42,900 ( 2,359,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
Biaya Jasa Narasumber ( 10,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 4 OJ 2,500,000 ( 10,000,000)
Bintek (Kegiatan Sejenis)

241
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
3.02.01.02.01.003 Kegiatan Sosialisasi / Penyuluhan Tipe 3 : Output Per Kegiatan ( 35,267,900)
Spesifikasi :
per orang ( 705,358)
Gedung Eksternal (Room Only), Non PNS/Masyarakat
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari

Honorarium ( 1,300,000)
1.10.28.02.02.002.001 Moderator 1 OH 700,000 ( 700,000)
1.10.28.02.02.002.002 Pembawa Acara 1 OH 400,000 ( 400,000)
1.10.28.02.02.002.003 Pembaca Doa 1 OH 200,000 ( 200,000)
Biaya Tetap Sewa Gedung ( 6,069,500)
9.1.2.07.03.01.001.00001 Sewa Ruang Pertemuan (Room Only, Cap. 80) 1 per ruang 5,619,900 ( 5,619,900)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
Biaya Sewa Perlengkapan ( 1,386,100)
9.1.2.10.03.01.001.00001 Sewa LCD Proyektor 1 unit/hari 393,400 ( 393,400)
9.1.2.10.03.01.001.00002 Sewa Layar Proyektor (Tripot) 1 unit/hari 393,400 ( 393,400)
9.1.2.10.01.01.001.00002 Sewa Meja Sidang 6 unit/hari 84,300 ( 505,800)
9.1.2.10.01.01.001.00026 Sewa Kursi Plastik 55 buah 1,700 ( 93,500)
Bahan Pakai Habis ( 2,141,800)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dus 24,700 ( 24,700)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.001.00010 Spidol 3 buah 7,900 ( 23,700)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.06.004.00003 Refil Printer 1 buah 172,000 ( 172,000)
1.1.7.01.03.01.006.00014 Stop Map 55 buah 13,500 ( 742,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Perjalanan Dinas ( 4,000,000)
1.10.28.03.01.011.004 Transport Peserta (Dalam Kota) 50 OH 80,000 ( 4,000,000)
Cetak dan Penggandaan ( 2,714,000)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00182 Cetak Handout Seminar 55 eksemplar 42,900 ( 2,359,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
Biaya Jasa Narasumber ( 15,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 6 OJ 2,500,000 ( 15,000,000)
Bintek (Kegiatan Sejenis)
Konsumsi ( 2,656,500)
1.1.7.01.07.01.001.00080 Nasi Kotak 55 kotak 28,100 ( 1,545,500)
1.1.7.01.07.01.001.00086 Snack Kotak 55 kotak 20,200 ( 1,111,000)
3.02.01.02.01.006 Kegiatan Sosialisasi / Penyuluhan Tipe 3 : Output Per Kegiatan ( 36,264,500)
Spesifikasi :
per orang ( 725,290)
Gedung Eksternal (All In), Non PNS/Masyarakat
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari

Honorarium ( 1,300,000)
1.10.28.02.02.002.001 Moderator 1 OH 700,000 ( 700,000)

242
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
1.10.28.02.02.002.002 Pembawa Acara 1 OH 400,000 ( 400,000)
1.10.28.02.02.002.003 Pembaca Doa 1 OH 200,000 ( 200,000)
Biaya Tetap Sewa Gedung ( 9,722,600)
9.1.2.07.03.01.001.00007 Sewa Ruang Pertemuan (All In) 55 pax 168,600 ( 9,273,000)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
Biaya Sewa Perlengkapan ( 1,386,100)
9.1.2.10.03.01.001.00001 Sewa LCD Proyektor 1 unit/hari 393,400 ( 393,400)
9.1.2.10.03.01.001.00002 Sewa Layar Proyektor (Tripot) 1 unit/hari 393,400 ( 393,400)
9.1.2.10.01.01.001.00002 Sewa Meja Sidang 6 unit/hari 84,300 ( 505,800)
9.1.2.10.01.01.001.00026 Sewa Kursi Plastik 55 buah 1,700 ( 93,500)
Bahan Pakai Habis ( 2,141,800)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dus 24,700 ( 24,700)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.001.00010 Spidol 3 buah 7,900 ( 23,700)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.06.004.00003 Refil Printer 1 buah 172,000 ( 172,000)
1.1.7.01.03.01.006.00014 Stop Map 55 buah 13,500 ( 742,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Perjalanan Dinas ( 4,000,000)
1.10.28.03.01.011.004 Transport Peserta (Dalam Kota) 50 OH 80,000 ( 4,000,000)
Cetak dan Penggandaan ( 2,714,000)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00182 Cetak Handout Seminar 55 eksemplar 42,900 ( 2,359,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
Biaya Jasa Narasumber ( 15,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 6 OJ 2,500,000 ( 15,000,000)
Bintek (Kegiatan Sejenis)
3.02.01.02.02 KEGIATAN PELATIHAN/BIMTEK/WORKSHOP
3.02.01.02.02.001 Kegiatan Pelatihan / Bimtek / Workshop Tipe 1 : Output Per Kegiatan ( 41,546,500)
Spesikasi :
per orang ( 830,930)
Gedung Internal, Pejabat Eselon II/Kepala OPD/Setara
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari
Bahan Pakai Habis ( 16,141,400)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dus 24,700 ( 24,700)
1.1.7.01.03.01.006.00014 Stop Map 50 buah 13,500 ( 675,000)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.001.00010 Spidol 3 buah 7,900 ( 23,700)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.01.001.00002 Ball Point 12 buah 13,700 ( 164,400)
1.1.7.01.03.01.004.00003 Correction 2 buah 5,600 ( 11,200)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.09.008.00119 Tas Pelatihan 55 buah 255,700 ( 14,063,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)

243
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Cetak dan Penggandaan ( 698,500)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
1.1.7.01.03.06.004.00003 Refil Printer 2 buah 172,000 ( 344,000)
Biaya Jasa Narasumber ( 15,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 6 OJ 2,500,000 ( 15,000,000)
Bintek (Kegiatan Sejenis)
Biaya Sewa Perlengkapan ( 1,979,100)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
9.1.2.10.01.01.001.00002 Sewa Meja Sidang 4 unit/hari 84,300 ( 337,200)
9.1.2.10.01.01.001.00017 Sewa Meja Kotak 13 unit 24,000 ( 312,000)
9.1.2.10.01.01.001.00026 Sewa Kursi Plastik 55 buah 1,700 ( 93,500)
9.1.2.10.03.01.001.00001 Sewa LCD Proyektor 1 unit/hari 393,400 ( 393,400)
9.1.2.10.03.01.001.00002 Sewa Layar Proyektor (Tripot) 1 unit/hari 393,400 ( 393,400)
Konsumsi ( 7,727,500)
1.1.7.01.07.01.001.00083 Prasmanan 55 pax 84,300 ( 4,636,500)
1.1.7.01.07.01.001.00088 Coffee break 55 pax 56,200 ( 3,091,000)
3.02.01.02.02.002 Kegiatan Pelatihan / Bimtek / Workshop Tipe 2 : Output Per Kegiatan ( 47,150,600)
Spesikasi :
per orang ( 943,012)
Gedung External (Room Only), Pejabat Eselon II/Kepala OPD/Setara
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari
Bahan Pakai Habis ( 16,125,600)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dus 24,700 ( 24,700)
1.1.7.01.03.01.006.00014 Stop Map 50 buah 13,500 ( 675,000)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.001.00010 Spidol 1 buah 7,900 ( 7,900)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.01.001.00002 Ball Point 12 buah 13,700 ( 164,400)
1.1.7.01.03.01.004.00003 Correction 2 buah 5,600 ( 11,200)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.09.008.00119 Tas Pelatihan 55 buah 255,700 ( 14,063,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Cetak dan Penggandaan ( 698,500)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
1.1.7.01.03.06.004.00003 Refil Printer 2 buah 172,000 ( 344,000)
Biaya Jasa Narasumber ( 15,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 6 OJ 2,500,000 ( 15,000,000)
Bintek (Kegiatan Sejenis)
Biaya Sewa Perlengkapan ( 7,599,000)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
9.1.2.07.03.01.001.00001 Sewa Ruang Pertemuan (Room Only, Cap. 80) 1 per ruang 5,619,900 ( 5,619,900)
9.1.2.10.01.01.001.00002 Sewa Meja Sidang 4 unit/hari 84,300 ( 337,200)
9.1.2.10.01.01.001.00017 Sewa Meja Kotak 13 unit 24,000 ( 312,000)
9.1.2.10.01.01.001.00026 Sewa Kursi Plastik 55 buah 1,700 ( 93,500)
9.1.2.10.03.01.001.00001 Sewa LCD Proyektor 1 unit/hari 393,400 ( 393,400)

244
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
9.1.2.10.03.01.001.00002 Sewa Layar Proyektor (Tripot) 1 unit/hari 393,400 ( 393,400)
Konsumsi ( 7,727,500)
1.1.7.01.07.01.001.00083 Prasmanan 55 pax 84,300 ( 4,636,500)
1.1.7.01.07.01.001.00088 Coffee break 55 pax 56,200 ( 3,091,000)
3.02.01.02.02.005 Kegiatan Pelatihan / Bimtek / Workshop Tipe 2 : Output Per Kegiatan ( 43,076,200)
Spesikasi :
per orang ( 861,524)
Gedung External (All In), Pejabat Eselon II/Kepala OPD/Setara
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari
Bahan Pakai Habis ( 16,125,600)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dus 24,700 ( 24,700)
1.1.7.01.03.01.006.00014 Stop Map 50 buah 13,500 ( 675,000)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.001.00010 Spidol 1 buah 7,900 ( 7,900)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.01.001.00002 Ball Point 12 buah 13,700 ( 164,400)
1.1.7.01.03.01.004.00003 Correction 2 buah 5,600 ( 11,200)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.09.008.00119 Tas Pelatihan 55 buah 255,700 ( 14,063,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Cetak dan Penggandaan ( 698,500)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
1.1.7.01.03.06.004.00003 Refil Printer 2 buah 172,000 ( 344,000)
Biaya Jasa Narasumber ( 15,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 6 OJ 2,500,000 ( 15,000,000)
Bintek (Kegiatan Sejenis)
Biaya Sewa Perlengkapan ( 11,252,100)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
9.1.2.07.03.01.001.00007 Sewa Ruang Pertemuan (All In) 55 pax 168,600 ( 9,273,000)
9.1.2.10.01.01.001.00002 Sewa Meja Sidang 4 unit/hari 84,300 ( 337,200)
9.1.2.10.01.01.001.00017 Sewa Meja Kotak 13 unit 24,000 ( 312,000)
9.1.2.10.01.01.001.00026 Sewa Kursi Plastik 55 buah 1,700 ( 93,500)
9.1.2.10.03.01.001.00001 Sewa LCD Proyektor 1 unit/hari 393,400 ( 393,400)
9.1.2.10.03.01.001.00002 Sewa Layar Proyektor (Tripot) 1 unit/hari 393,400 ( 393,400)
3.02.01.02.02.003 Kegiatan Pelatihan / Bimtek / Workshop Tipe 3 : Output Per Kegiatan ( 26,810,400)
Spesikasi :
per orang ( 536,208)
Gedung Internal, Non PNS/Masyarakat
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari
Bahan Pakai Habis ( 2,863,100)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dus 24,700 ( 24,700)
1.1.7.01.03.01.006.00014 Stop Map 50 buah 13,500 ( 675,000)
1.1.7.01.03.02.001.00007 HVS 70 Gr 2 rim 50,600 ( 101,200)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)

245
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
1.1.7.01.03.01.001.00010 Spidol 2 buah 7,900 ( 15,800)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.01.001.00002 Ball Point 12 buah 13,700 ( 164,400)
1.1.7.01.03.01.004.00003 Correction 2 buah 5,600 ( 11,200)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.01.006.00014 Stop Map 55 buah 13,500 ( 742,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Cetak dan Penggandaan ( 698,500)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
1.1.7.01.03.06.004.00003 Refil Printer 2 buah 172,000 ( 344,000)
Biaya Jasa Narasumber ( 15,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 6 OJ 2,500,000 ( 15,000,000)
Bintek (Kegiatan Sejenis)
Perjalanan Dinas ( 4,400,000)
1.10.28.03.01.011.004 Transport Peserta (Dalam Kota) 55 OH 80,000 ( 4,400,000)
Biaya Sewa Perlengkapan ( 1,192,300)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
9.1.2.10.01.01.001.00002 Sewa Meja Sidang 4 unit/hari 84,300 ( 337,200)
9.1.2.10.01.01.001.00017 Sewa Meja Kotak 13 unit 24,000 ( 312,000)
9.1.2.10.01.01.001.00026 Sewa Kursi Plastik 55 buah 1,700 ( 93,500)
Konsumsi ( 2,656,500)
1.1.7.01.07.01.001.00080 Nasi Kotak 55 kotak 28,100 ( 1,545,500)
1.1.7.01.07.01.001.00086 Snack Kotak 55 kotak 20,200 ( 1,111,000)
3.02.01.02.02.004 Kegiatan Pelatihan / Bimtek / Workshop Tipe 4 : Output Per Kegiatan ( 32,879,900)
Spesikasi :
per orang ( 657,598)
Gedung Eskternal (Room Only), Non PNS/Masyarakat
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari
Bahan Pakai Habis ( 3,561,600)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dus 24,700 ( 24,700)
1.1.7.01.03.01.006.00014 Stop Map 50 buah 13,500 ( 675,000)
1.1.7.01.03.02.001.00007 HVS 70 Gr 2 rim 50,600 ( 101,200)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.001.00010 Spidol 2 buah 7,900 ( 15,800)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.01.001.00002 Ball Point 12 buah 13,700 ( 164,400)
1.1.7.01.03.01.004.00003 Correction 2 buah 5,600 ( 11,200)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
1.1.7.01.03.06.004.00003 Refil Printer 2 buah 172,000 ( 344,000)
1.1.7.01.03.01.006.00014 Stop Map 55 buah 13,500 ( 742,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Biaya Jasa Narasumber ( 15,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 6 OJ 2,500,000 ( 15,000,000)
Bintek (Kegiatan Sejenis)
Perjalanan Dinas ( 4,400,000)

246
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
1.10.28.03.01.011.004 Transport Peserta (Dalam Kota) 55 OH 80,000 ( 4,400,000)
Biaya Sewa Perlengkapan ( 7,261,800)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
9.1.2.07.03.01.001.00001 Sewa Ruang Pertemuan (Room Only, Cap. 80) 1 per ruang 5,619,900 ( 5,619,900)
9.1.2.10.01.01.001.00017 Sewa Meja Kotak 13 unit 24,000 ( 312,000)
9.1.2.10.01.01.001.00026 Sewa Kursi Plastik 55 buah 1,700 ( 93,500)
9.1.2.10.03.01.001.00001 Sewa LCD Proyektor 1 unit/hari 393,400 ( 393,400)
9.1.2.10.03.01.001.00002 Sewa Layar Proyektor (Tripot) 1 unit/hari 393,400 ( 393,400)
Konsumsi ( 2,656,500)
1.1.7.01.07.01.001.00080 Nasi Kotak 55 kotak 28,100 ( 1,545,500)
1.1.7.01.07.01.001.00086 Snack Kotak 55 kotak 20,200 ( 1,111,000)
3.02.01.02.02.006 Kegiatan Pelatihan / Bimtek / Workshop Tipe 4 : Output Per Kegiatan ( 33,876,500)
Spesikasi :
per orang ( 677,530)
Gedung Eskternal (All In), Non PNS/Masyarakat
Parameter :
Jumlah Peserta (wajib diisi) 50 orang
Lama Kegiatan (wajib diisi) 1 hari
Bahan Pakai Habis ( 3,561,600)
1.1.7.01.03.02.004.00011 Amplop Putih 1 dus 24,700 ( 24,700)
1.1.7.01.03.01.006.00014 Stop Map 50 buah 13,500 ( 675,000)
1.1.7.01.03.02.001.00007 HVS 70 Gr 2 rim 50,600 ( 101,200)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.001.00010 Spidol 2 buah 7,900 ( 15,800)
1.1.7.01.03.01.012.00001 Staples/Hechmachine 1 buah 12,100 ( 12,100)
1.1.7.01.03.01.001.00002 Ball Point 12 buah 13,700 ( 164,400)
1.1.7.01.03.01.004.00003 Correction 2 buah 5,600 ( 11,200)
1.1.7.01.03.03.007.00001 Materai 12 buah 4,500 ( 54,000)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00062 Photo Copy 1000 lembar 200 ( 200,000)
1.1.7.01.03.06.004.00003 Refil Printer 2 buah 172,000 ( 344,000)
1.1.7.01.03.01.006.00014 Stop Map 55 buah 13,500 ( 742,500)
1.1.7.01.03.01.005.00002 Buku Block Note 55 buah 5,400 ( 297,000)
1.1.7.01.03.01.001.00002 Ball Point 55 buah 13,700 ( 753,500)
Biaya Jasa Narasumber ( 15,000,000)
Jasa Narasumber Kegiatan Seminar/ Rakor/ Sosialisasi/ Diseminasi / FGD /
1.10.28.02.02.003.001 6 OJ 2,500,000 ( 15,000,000)
Bintek (Kegiatan Sejenis)
Perjalanan Dinas ( 4,400,000)
1.10.28.03.01.011.004 Transport Peserta (Dalam Kota) 55 OH 80,000 ( 4,400,000)
Biaya Sewa Perlengkapan ( 10,914,900)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
9.1.2.07.03.01.001.00007 Sewa Ruang Pertemuan (All In) 55 pax 168,600 ( 9,273,000)
9.1.2.10.01.01.001.00017 Sewa Meja Kotak 13 unit 24,000 ( 312,000)
9.1.2.10.01.01.001.00026 Sewa Kursi Plastik 55 buah 1,700 ( 93,500)
9.1.2.10.03.01.001.00001 Sewa LCD Proyektor 1 unit/hari 393,400 ( 393,400)
9.1.2.10.03.01.001.00002 Sewa Layar Proyektor (Tripot) 1 unit/hari 393,400 ( 393,400)
3.02.01.02.03 KEGIATAN PAGELARAN/FESTIVAL/PAWAI
3.02.01.02.03.001 Kegiatan Pagelaran / Festival / Pawai Tipe 1 : Output Per Kegiatan ( 93,576,600)
Spesifikasi :
OPD Selaku Penyelenggara,1 Hari Pelaksanaan, Peserta Perorangan Max. per orang ( 1,701,393)
50 Orang, Bersifat Lomba
Honorarium ( 6,800,000)

247
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
1.10.28.02.02.002.006 Jasa Juri Profesional / Juri Propinsi 3 OH 1,000,000 ( 3,000,000)
1.10.28.02.02.002.002 Pembawa Acara 2 OH 400,000 ( 800,000)
1.10.28.02.02.002.038 Jasa Petugas Keamanan 30 OH 100,000 ( 3,000,000)
Bahan Pakai Habis ( 303,600)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.001.00002 Ball Point 5 buah 13,700 ( 68,500)
1.1.7.01.03.01.003.00003 Binder Clip 2 dus 4,400 ( 8,800)
1.1.7.01.03.01.006.00014 Stop Map 2 buah 13,500 ( 27,000)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.03.007.00001 Materai 4 buah 4,500 ( 18,000)
1.1.7.01.07.01.002.00003 Air Mineral 6 botol 3,900 ( 23,400)
1.1.7.01.03.01.014.00062 Photo Copy 500 lembar 200 ( 100,000)
Biaya Sewa Perlengkapan ( 63,013,500)
9.1.2.10.07.01.001.00056 Sewa Dekorasi 25 m2 2,158,000 ( 53,950,000)
9.1.2.10.07.01.001.00029 Sewa Panggung 25 m2 22,500 ( 562,500)
9.1.2.10.07.01.001.00048 Sewa Taman, Backdrop,dll 20 m2 300,000 ( 6,000,000)
9.1.2.10.07.01.001.00051 Sewa Umbul-umbul 10 unit 25,300 ( 253,000)
9.1.2.10.07.01.001.00018 Sewa Sound System 1 unit 2,248,000 ( 2,248,000)
Cetak dan Penggandaan ( 4,399,600)
1.1.7.01.03.01.014.00013 Cetak Brosur/Leaflet 2 pack 168,600 ( 337,200)
1.1.7.01.03.01.014.00023 Cetak Poster 1 rim 1,583,900 ( 1,583,900)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00007 Cetak Backdrop/Banner 20 m2 116,200 ( 2,324,000)
Uang/barang yang diberikan pada masyarakat ( 14,712,900)
1.3.5.02.03.01.004.00009 Hadiah Perlombaan Non Akademik Bidang Seni Budaya Tingkat Kota 1 paket 13,487,800 ( 13,487,800)
1.3.5.02.03.01.001.00040 Trophy Kaki Empat (a) 1 buah 483,300 ( 483,300)
1.3.5.02.03.01.001.00037 Trophy Kaki Empat (b) 1 buah 393,400 ( 393,400)
1.3.5.02.03.01.001.00035 Trophy Kaki Empat (c) 1 buah 348,400 ( 348,400)
Konsumsi ( 4,347,000)
1.1.7.01.07.01.001.00080 Nasi Kotak 90 kotak 28,100 ( 2,529,000)
1.1.7.01.07.01.001.00086 Snack Kotak 90 kotak 20,200 ( 1,818,000)
3.02.01.02.03.002 Kegiatan Pagelaran / Festival / Pawai Tipe 2 : Output Grup ( 46,630,100)
Spesifikasi :
OPD Selaku Penyelenggara, 1 Hari Pelaksanaan, Peserta Max. 20 per grup ( 1,165,753)
Orang/Grup, Bersifat Lomba
Honorarium ( 6,800,000)
1.10.28.02.02.002.006 Jasa Juri Profesional / Juri Propinsi 3 OH 1,000,000 ( 3,000,000)
1.10.28.02.02.002.002 Pembawa Acara 2 OH 400,000 ( 800,000)
1.10.28.02.02.002.038 Jasa Petugas Keamanan 30 OH 100,000 ( 3,000,000)
Bahan Pakai Habis ( 303,600)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.001.00002 Ball Point 5 buah 13,700 ( 68,500)
1.1.7.01.03.01.003.00003 Binder Clip 2 dus 4,400 ( 8,800)
1.1.7.01.03.01.006.00014 Stop Map 2 buah 13,500 ( 27,000)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.03.007.00001 Materai 4 buah 4,500 ( 18,000)
1.1.7.01.07.01.002.00003 Air Mineral 6 botol 3,900 ( 23,400)
1.1.7.01.03.01.014.00062 Photo Copy 500 lembar 200 ( 100,000)
Biaya Sewa Perlengkapan ( 9,063,500)
9.1.2.10.07.01.001.00029 Sewa Panggung 25 m2 22,500 ( 562,500)
9.1.2.10.07.01.001.00048 Sewa Taman, Backdrop,dll 20 m2 300,000 ( 6,000,000)

248
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
9.1.2.10.07.01.001.00051 Sewa Umbul-umbul 10 unit 25,300 ( 253,000)
9.1.2.10.07.01.001.00018 Sewa Sound System 1 unit 2,248,000 ( 2,248,000)
Cetak dan Penggandaan ( 4,399,600)
1.1.7.01.03.01.014.00013 Cetak Brosur/Leaflet 2 pack 168,600 ( 337,200)
1.1.7.01.03.01.014.00023 Cetak Poster 1 rim 1,583,900 ( 1,583,900)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00007 Cetak Backdrop/Banner 20 m2 116,200 ( 2,324,000)
Uang/barang yang diberikan pada masyarakat ( 14,712,900)
1.3.5.02.03.01.004.00009 Hadiah Perlombaan Non Akademik Bidang Seni Budaya Tingkat Kota 1 paket 13,487,800 ( 13,487,800)
1.3.5.02.03.01.001.00040 Trophy Kaki Empat (a) 1 buah 483,300 ( 483,300)
1.3.5.02.03.01.001.00037 Trophy Kaki Empat (b) 1 buah 393,400 ( 393,400)
1.3.5.02.03.01.001.00035 Trophy Kaki Empat (c) 1 buah 348,400 ( 348,400)
Konsumsi ( 11,350,500)
1.1.7.01.07.01.001.00080 Nasi Kotak 235 kotak 28,100 ( 6,603,500)
1.1.7.01.07.01.001.00086 Snack Kotak 235 kotak 20,200 ( 4,747,000)
3.02.01.02.03.003 Kegiatan Pagelaran / Festival / Pawai Tipe 3 : Output Peserta ( 68,698,500)
Spesifikasi :
Mengirim Delegasi, 1 Delegasi 40 Orang, Bersifat Lomba
Parameter :
Jumlah Hari (wajib diisi) 1 hari
Cetak dan Penggandaan ( 60,000)
1.1.7.01.03.01.014.00062 Photo Copy 300 lembar 200 ( 60,000)
Biaya Sewa Perlengkapan ( 66,341,700)
9.1.2.08.01.01.001.00008 Sewa Truk Angkutan Dalam Kota 1 unit/hari 1,601,700 ( 1,601,700)
9.1.2.10.07.01.001.00056 Sewa Dekorasi 30 m2 2,158,000 ( 64,740,000)
Konsumsi ( 2,296,800)
1.1.7.01.07.01.001.00080 Nasi Kotak 44 kotak 28,100 ( 1,236,400)
1.1.7.01.07.01.001.00086 Snack Kotak 44 kotak 20,200 ( 888,800)
1.1.7.01.07.01.002.00003 Air Mineral 44 botol 3,900 ( 171,600)
3.02.01.02.04 KEGIATAN PAMERAN/EXPO
3.02.01.02.04.001 Kegiatan Pameran / Expo Tipe 1 : Output Peserta ( 17,510,000)
Spesifikasi : OPD Sebagai Penyelenggaraan, Lokasi Acara (Asset Internal
per peserta ( 175,100)
Pemkot), Max. 50 Stand (3 x 3 m) Peserta, Pelaksanaan Max. 10 Hari
Parameter :
Jumlah Hari (wajib diisi) 1 hari
Honorarium ( 1,000,000)
1.10.28.02.02.002.002 Pembawa Acara 1 OH 400,000 ( 400,000)
1.10.28.02.02.002.003 Pembaca Doa 1 OH 200,000 ( 200,000)
1.10.28.02.02.002.038 Jasa Petugas Keamanan 4 OH 100,000 ( 400,000)
Bahan Pakai Habis ( 387,300)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.001.00002 Ball Point 5 buah 13,700 ( 68,500)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.006.00014 Stop Map 1 buah 13,500 ( 13,500)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.006.00011 Snelhecter Map 50 buah 2,500 ( 125,000)
1.1.7.01.03.03.007.00001 Materai 4 buah 4,500 ( 18,000)
1.1.7.01.03.01.014.00062 Photo Copy 500 lembar 200 ( 100,000)
Cetak dan Penggandaan ( 4,399,600)
1.1.7.01.03.01.014.00013 Cetak Brosur/Leaflet 2 pack 168,600 ( 337,200)
1.1.7.01.03.01.014.00023 Cetak Poster 1 rim 1,583,900 ( 1,583,900)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)

249
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
1.1.7.01.03.01.014.00007 Cetak Backdrop/Banner 20 m2 116,200 ( 2,324,000)
Biaya Sewa Perlengkapan ( 6,410,100)
9.1.2.10.07.01.001.00036 Sewa Panggung Unit 1 unit/hari 359,700 ( 359,700)
9.1.2.10.07.01.001.00048 Sewa Taman, Backdrop,dll 12 m2 300,000 ( 3,600,000)
9.1.2.10.07.01.001.00051 Sewa Umbul-umbul 8 unit 25,300 ( 202,400)
9.1.2.10.07.01.001.00018 Sewa Sound System 1 unit 2,248,000 ( 2,248,000)
Konsumsi ( 5,313,000)
1.1.7.01.07.01.001.00080 Nasi Kotak 110 kotak 28,100 ( 3,091,000)
1.1.7.01.07.01.001.00086 Snack Kotak 110 kotak 20,200 ( 2,222,000)
3.02.01.02.04.002 Kegiatan Pameran / Expo Tipe 2 : Output Peserta ( 25,208,100)
Spesifikasi :
OPD Sebagai Penyelenggaraan, Lokasi Acara (Eksternal Indoor), Max. 25 per stand ( 1,008,324)
Stand (3 x 3 m) Peserta, Pelaksanaan Max. 3 Hari
Parameter :
Jumlah Hari (wajib diisi) 1 hari
Honorarium ( 900,000)
1.10.28.02.02.002.002 Pembawa Acara 1 OH 400,000 ( 400,000)
1.10.28.02.02.002.003 Pembaca Doa 1 OH 200,000 ( 200,000)
1.10.28.02.02.002.038 Jasa Petugas Keamanan 3 OH 100,000 ( 300,000)
Bahan Pakai Habis ( 167,300)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.001.00002 Ball Point 5 buah 13,700 ( 68,500)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.006.00014 Stop Map 1 buah 13,500 ( 13,500)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.006.00011 Snelhecter Map 2 buah 2,500 ( 5,000)
1.1.7.01.03.03.007.00001 Materai 4 buah 4,500 ( 18,000)
Cetak dan Penggandaan ( 4,499,600)
1.1.7.01.03.01.014.00062 Photo Copy 500 lembar 200 ( 100,000)
1.1.7.01.03.01.014.00013 Cetak Brosur/Leaflet 2 pack 168,600 ( 337,200)
1.1.7.01.03.01.014.00023 Cetak Poster 1 rim 1,583,900 ( 1,583,900)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00007 Cetak Backdrop/Banner 20 m2 116,200 ( 2,324,000)
Biaya Sewa Perlengkapan ( 16,984,700)
9.1.2.07.02.01.001.00023 Sewa Stand Pameran 225 m2/hari 45,000 ( 10,125,000)
9.1.2.10.07.01.001.00036 Sewa Panggung Unit 1 unit/hari 359,700 ( 359,700)
9.1.2.10.07.01.001.00048 Sewa Taman, Backdrop,dll 12 m2 300,000 ( 3,600,000)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
9.1.2.10.07.01.001.00051 Sewa Umbul-umbul 8 unit 25,300 ( 202,400)
9.1.2.10.07.01.001.00018 Sewa Sound System 1 unit 2,248,000 ( 2,248,000)
Konsumsi ( 2,656,500)
1.1.7.01.07.01.001.00080 Nasi Kotak 55 kotak 28,100 ( 1,545,500)
1.1.7.01.07.01.001.00086 Snack Kotak 55 kotak 20,200 ( 1,111,000)
3.02.01.02.04.003 Kegiatan Pameran / Expo Tipe 3 : Output Peserta ( 40,335,600)
Spesifikasi :
per expo ( 40,335,600)
Sebagai Pengirim Delegasi/Peserta, Skala Nasional
Parameter :
Jumlah Peserta (wajib diisi) 10 orang
Jumlah Hari (wajib diisi) 1 hari
Cetak dan Penggandaan ( 4,399,600)
1.1.7.01.03.01.014.00013 Cetak Brosur/Leaflet 2 pack 168,600 ( 337,200)
1.1.7.01.03.01.014.00023 Cetak Poster 1 rim 1,583,900 ( 1,583,900)

250
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00007 Cetak Backdrop/Banner 20 m2 116,200 ( 2,324,000)
Biaya Sewa Gedung ( 35,404,700)
9.1.2.07.02.01.001.00027 Sewa Stand Apeksi 1 m2 3,034,700 ( 3,034,700)
9.1.2.10.07.01.001.00056 Sewa Dekorasi 15 m2/hari 2,158,000 ( 32,370,000)
Konsumsi ( 531,300)
1.1.7.01.07.01.001.00080 Nasi Kotak 11 kotak 28,100 ( 309,100)
1.1.7.01.07.01.001.00086 Snack Kotak 11 kotak 20,200 ( 222,200)
3.02.01.02.04.004 Kegiatan Pameran / Expo Tipe 4 : Output Stand ( 17,923,900)
Spesifikasi :
per expo ( 17,923,900)
Sebagai Pengirim Delegasi/Peserta, Skala Regional, 1 Stand 2 Orang
Parameter :
Jumlah Peserta (wajib diisi) 10 orang
Jumlah Stand (wajib diisi) 1 stand
Jumlah Hari (wajib diisi) 1 hari
Cetak dan Penggandaan ( 4,399,600)
1.1.7.01.03.01.014.00013 Cetak Brosur/Leaflet 2 pack 168,600 ( 337,200)
1.1.7.01.03.01.014.00023 Cetak Poster 1 rim 1,583,900 ( 1,583,900)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00007 Cetak Backdrop/Banner 20 m2 116,200 ( 2,324,000)
Biaya Sewa Gedung ( 12,993,000)
9.1.2.10.07.01.001.00056 Sewa Dekorasi 6 m2 2,158,000 ( 12,948,000)
9.1.2.07.02.01.001.00023 Sewa Stand Pameran 1 m2/hari 45,000 ( 45,000)
Konsumsi ( 531,300)
1.1.7.01.07.01.001.00080 Nasi Kotak 11 kotak 28,100 ( 309,100)
1.1.7.01.07.01.001.00086 Snack Kotak 11 kotak 20,200 ( 222,200)
3.02.01.02.05 KEGIATAN LOMBA
3.02.01.02.05.001 Kegiatan Lomba Tipe 1 : Output Peserta ( 54,919,600)
Spesifikasi :
OPD Selaku Penyelenggara, Lomba Bersifat Olahraga (1 Cabor), Peserta per pertandingan ( 5,491,960)
Perorangan
Parameter :
Jumlah Peserta (wajib diisi) 30 orang
Jumlah Hari (wajib diisi) 2 hari
Jumlah Pertandingan (wajib diisi) 10 Pertandingan
Honorarium ( 3,000,000)
1.10.28.02.02.004.005 Wasit Per Paket Pertandingan 10 per pertandingan 300,000 ( 3,000,000)
Bahan Pakai Habis ( 164,800)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.001.00002 Ball Point 5 buah 13,700 ( 68,500)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.006.00014 Stop Map 1 buah 13,500 ( 13,500)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.006.00011 Snelhecter Map 1 buah 2,500 ( 2,500)
1.1.7.01.03.03.007.00001 Materai 4 buah 4,500 ( 18,000)
Cetak dan Penggandaan ( 4,459,600)
1.1.7.01.03.01.014.00062 Photo Copy 300 lembar 200 ( 60,000)
1.1.7.01.03.01.014.00013 Cetak Brosur/Leaflet 2 pack 168,600 ( 337,200)
1.1.7.01.03.01.014.00023 Cetak Poster 1 rim 1,583,900 ( 1,583,900)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00007 Cetak Backdrop/Banner 20 m2 116,200 ( 2,324,000)
Uang/barang yang diberikan pada masyarakat ( 18,084,800)

251
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
1.3.5.02.03.01.004.00003 Hadiah Perlombaan Non Akademik Bidang Olahraga Tingkat Kota (a) 1 paket 16,859,700 ( 16,859,700)
1.3.5.02.03.01.001.00040 Trophy Kaki Empat (a) 1 buah 483,300 ( 483,300)
1.3.5.02.03.01.001.00037 Trophy Kaki Empat (b) 1 buah 393,400 ( 393,400)
1.3.5.02.03.01.001.00035 Trophy Kaki Empat (c) 1 buah 348,400 ( 348,400)
Biaya Sewa Gedung ( 26,022,600)
9.1.2.10.07.01.001.00036 Sewa Panggung Unit 2 unit/hari 359,700 ( 719,400)
9.1.2.10.07.01.001.00048 Sewa Taman, Backdrop,dll 48 m2 300,000 ( 14,400,000)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 2 unit 449,600 ( 899,200)
9.1.2.10.07.01.001.00051 Sewa Umbul-umbul 40 unit 25,300 ( 1,012,000)
9.1.2.10.07.01.001.00018 Sewa Sound System 4 unit 2,248,000 ( 8,992,000)
Konsumsi ( 3,187,800)
1.1.7.01.07.01.001.00080 Nasi Kotak 66 kotak 28,100 ( 1,854,600)
1.1.7.01.07.01.001.00086 Snack Kotak 66 kotak 20,200 ( 1,333,200)
3.02.01.02.05.002 Kegiatan Lomba Tipe 2 : Output Peserta ( 81,346,600)
Spesifikasi :
OPD Selaku Penyelenggara, Lomba Bersifat Olahraga (1 Cabor), Peserta per kelompok ( 2,711,553)
Kelompok, Max. 20 Orang/Kelompok
Parameter :
Jumlah Peserta (wajib diisi) 30 kelompok
Jumlah Hari (wajib diisi) 1 hari
Jumlah Pertandingan (wajib diisi) 10 pertandingan
Honorarium ( 3,000,000)
1.10.28.02.02.004.005 Wasit Per Paket Pertandingan 10 per pertandingan 300,000 ( 3,000,000)
Bahan Pakai Habis ( 164,800)
1.1.7.01.03.02.001.00007 HVS 70 Gr 1 rim 50,600 ( 50,600)
1.1.7.01.03.01.001.00002 Ball Point 5 buah 13,700 ( 68,500)
1.1.7.01.03.01.003.00003 Binder Clip 1 dus 4,400 ( 4,400)
1.1.7.01.03.01.006.00014 Stop Map 1 buah 13,500 ( 13,500)
1.1.7.01.03.01.016.00001 Paper Clips 1 buah 2,200 ( 2,200)
1.1.7.01.03.01.013.00001 Isi Stapples 3 pack 1,700 ( 5,100)
1.1.7.01.03.01.006.00011 Snelhecter Map 1 buah 2,500 ( 2,500)
1.1.7.01.03.03.007.00001 Materai 4 buah 4,500 ( 18,000)
Cetak dan Penggandaan ( 4,499,600)
1.1.7.01.03.01.014.00062 Photo Copy 500 lembar 200 ( 100,000)
1.1.7.01.03.01.014.00013 Cetak Brosur/Leaflet 2 pack 168,600 ( 337,200)
1.1.7.01.03.01.014.00023 Cetak Poster 1 rim 1,583,900 ( 1,583,900)
1.1.7.01.03.01.014.00066 Spanduk Print Digital 5 m2 30,900 ( 154,500)
1.1.7.01.03.01.014.00007 Cetak Backdrop/Banner 20 m2 116,200 ( 2,324,000)
Uang/barang yang diberikan pada masyarakat ( 34,944,500)
1.3.5.02.03.01.004.00006 Hadiah Perlombaan Non Akademik Bidang Olahraga Tingkat Kota (b) 1 paket 33,719,400 ( 33,719,400)
1.3.5.02.03.01.001.00040 Trophy Kaki Empat (a) 1 buah 483,300 ( 483,300)
1.3.5.02.03.01.001.00037 Trophy Kaki Empat (b) 1 buah 393,400 ( 393,400)
1.3.5.02.03.01.001.00035 Trophy Kaki Empat (c) 1 buah 348,400 ( 348,400)
Biaya Sewa Perlengkapan ( 6,859,700)
9.1.2.10.07.01.001.00036 Sewa Panggung Unit 1 unit/hari 359,700 ( 359,700)
9.1.2.10.07.01.001.00048 Sewa Taman, Backdrop,dll 12 m2 300,000 ( 3,600,000)
9.1.2.10.07.01.001.00043 Sewa Podium Lengkap 1 unit 449,600 ( 449,600)
9.1.2.10.07.01.001.00051 Sewa Umbul-umbul 8 unit 25,300 ( 202,400)
9.1.2.10.07.01.001.00018 Sewa Sound System 1 unit 2,248,000 ( 2,248,000)
Konsumsi ( 31,878,000)
1.1.7.01.07.01.001.00080 Nasi Kotak 660 kotak 28,100 ( 18,546,000)
1.1.7.01.07.01.001.00086 Snack Kotak 660 kotak 20,200 ( 13,332,000)
3.02.01.02.05.003 Kegiatan Lomba Tipe 3 : Output: Peserta ( 12,884,940)

252
HARGA
KODE BARANG URAIAN KEGIATAN VOL. SATUAN HARGA
SATUAN
(a) (b) (c) (d) (e) (f)
Spesifikasi :
per peserta ( 515,398)
Sebagai Pengirim Delegasi/Peserta
Parameter :
Jumlah Peserta (wajib diisi) 25 orang
Jumlah Pendamping (wajib diisi) 3 orang
Jumlah Hari (wajib diisi) 1 hari
Perjalanan Dinas ( 11,397,300)
1.10.28.02.02.002.005 Uang Saku Official 3 OH 200,000 ( 600,000)
1.10.28.02.02.002.004 Uang Saku Atlet 25 OH 100,000 ( 2,500,000)
9.1.2.07.02.01.001.00015 Penginapan Dalam Propinsi 14 kamar/hari 258,500 ( 3,619,000)
9.1.2.08.01.01.001.00043 Sewa Roda 6 / Bus 1 hari 4,678,300 ( 4,678,300)
Konsumsi ( 1,487,640)
1.1.7.01.07.01.001.00080 Nasi Kotak 31 kotak 28,100 ( 865,480)
1.1.7.01.07.01.001.00086 Snack Kotak 31 kotak 20,200 ( 622,160)

253

Anda mungkin juga menyukai