Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 13.334 238.01 92,000.00 21,897,094.80
2 Tukang HOK - - 130,000.00 -
3 Kepala Tukang HOK - - 146,000.00 -
4 Mandor HOK 0.666 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 6.667 281.21 92,000.00 25,871,693.52
2 Tukang HOK - - 130,000.00 -
3 Kepala Tukang HOK - - 146,000.00 -
4 Mandor HOK 0.333 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.750 45.02 92,000.00 4,142,070.00
2 Tukang HOK - - 130,000.00 -
3 Kepala Tukang HOK - - 146,000.00 -
4 Mandor HOK 0.025 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 2.302 Err:509 92,000.00 Err:509
2 Tukang HOK - - 130,000.00 -
3 Kepala Tukang HOK - - 146,000.00 -
4 Mandor HOK 0.115 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.750 Err:509 92,000.00 Err:509
2 Tukang HOK - - 130,000.00 -
3 Kepala Tukang HOK - - 146,000.00 -
4 Mandor HOK 0.025 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.500 0.50 92,000.00 45,540.00
2 Tukang HOK 0.75 0.25 130,000.00 32,175.00
3 Kepala Tukang HOK 0.08 - 146,000.00 -
4 Mandor HOK 0.08 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.13 Err:509 92,000.00 Err:509
2 Tukang HOK 0.10 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.01 - 146,000.00 -
4 Mandor HOK 0.01 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.300 Err:509 92,000.00 Err:509
2 Tukang HOK 0.15 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.02 - 146,000.00 -
4 Mandor HOK 0.015 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.200 Err:509 92,000.00 Err:509
2 Tukang HOK 0.10 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.01 - 146,000.00 -
4 Mandor HOK 0.010 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.007 Err:509 92,000.00 Err:509
2 Tukang HOK 0.007 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.001 - 146,000.00 -
4 Mandor HOK 0.000 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.120 Err:509 92,000.00 Err:509
2 Tukang HOK 0.060 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.006 - 146,000.00 -
4 Mandor HOK 0.006 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.650 Err:509 92,000.00 Err:509
2 Tukang HOK 0.275 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.028 - 146,000.00 -
4 Mandor HOK 0.083 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.750 13.39 92,000.00 1,231,650.00
2 Tukang HOK - - 130,000.00 -
3 Kepala Tukang HOK - - 146,000.00 -
4 Mandor HOK 0.025 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.200 50.62 92,000.00 4,656,672.00
2 Tukang HOK - - 130,000.00 -
3 Kepala Tukang HOK - - 146,000.00 -
4 Mandor HOK 0.045 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.356 21.37 92,000.00 1,966,102.56
2 Tukang HOK - - 130,000.00 -
3 Kepala Tukang HOK - - 146,000.00 -
4 Mandor HOK 0.018 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.500 0.50 92,000.00 45,540.00
2 Tukang HOK 0.75 0.25 130,000.00 32,175.00
3 Kepala Tukang HOK 0.08 - 146,000.00 -
4 Mandor HOK 0.08 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.007 Err:509 92,000.00 Err:509
2 Tukang HOK 0.007 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.001 - 146,000.00 -
4 Mandor HOK 0.000 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.300 Err:509 92,000.00 Err:509
2 Tukang HOK 0.15 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.015 - 146,000.00 -
4 Mandor HOK 0.030 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.650 Err:509 92,000.00 Err:509
2 Tukang HOK 0.275 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.028 - 146,000.00 -
4 Mandor HOK 0.083 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.500 Err:509 92,000.00 Err:509
2 Tukang HOK 0.75 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.08 - 146,000.00 -
4 Mandor HOK 0.08 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.007 Err:509 92,000.00 Err:509
2 Tukang HOK 0.007 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.001 - 146,000.00 -
4 Mandor HOK 0.000 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.300 Err:509 92,000.00 Err:509
2 Tukang HOK 0.15 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.015 - 146,000.00 -
4 Mandor HOK 0.030 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.650 Err:509 92,000.00 Err:509
2 Tukang HOK 0.275 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.028 - 146,000.00 -
4 Mandor HOK 0.083 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.650 Err:509 92,000.00 Err:509
2 Tukang HOK 0.275 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.028 - 146,000.00 -
4 Mandor HOK 0.083 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.081 Err:509 92,000.00 Err:509
2 Tukang HOK 0.135 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.014 - 146,000.00 -
4 Mandor HOK 0.004 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.300 Err:509 92,000.00 Err:509
2 Tukang HOK 0.15 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.015 - 146,000.00 -
4 Mandor HOK 0.030 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.007 Err:509 92,000.00 Err:509
2 Tukang HOK 0.007 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.001 - 146,000.00 -
4 Mandor HOK 0.000 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.650 Err:509 92,000.00 Err:509
2 Tukang HOK 0.275 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.028 - 146,000.00 -
4 Mandor HOK 0.083 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.250 Err:509 92,000.00 Err:509
2 Tukang HOK - Err:509 130,000.00 Err:509
3 Kepala Tukang HOK - Err:509 146,000.00 Err:509
4 Mandor HOK 0.025 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.32 Err:509 92,000.00 Err:509
2 Tukang HOK 0.22 Err:509 130,000.00 Err:509
3 Kepala Tukang HOK 0.02 - 146,000.00 -
4 Mandor HOK 0.13 - 140,000.00 -
Jack Hammer
Kawat Beton
Kaso 5/7 cm
Tanah Urug
Papan 3/20
SATUAN VOLUME
Besi Beton
Paku 5 cm
NO URAIAN PEKERJAAN
dan 7 cm
bekisting
Batu kali
PEKERJAAN PEKERJAAN
cm kayu
Mandor
Cangkul
Pekerja
Minyak
Tukang
Tukang
Semen
kelas II
PVC 3"
Kepala
Kerikil
Sekop
Martil
Pasir
(HOK) (HOK) (HOK) (HOK) (Zak) (M3) (M2) (Kg) (Kg) (M3) (M3) (M3) (Kg) (Ltr) (M3) (M) ( Sewa/Hari ) (Buah) (Buah) (Buah)
1. Pek. galian sedimen pada saluran terbuka (L= 51 M) M3 17.85 - - - 13.39
2. Pek. galian sedimen pada saluran tertutup ( L=120.5 M3 42.18 - - - 50.62
3. Pek. mengangkut material atau hasil galian dan bong M3 60.03 - - - 21.37
4. Pek. Beton Site Mix K. 175 M3 0.33 - - 0.25 0.50 1.08 0.17 0.4
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509
### ### Err:509 Err:509 - - Err:509 Err:509 Err:509 Err:509 Err:509
### ### Err:509 Err:509 - -
Total Volume - - Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 - - - -
2. BAHAN/MATERIAL
1 Semen Zak 165.00 62,000.00 10,230,000.00
2 Pasir M3 14.50 150,000.00 2,175,000.00
3 Batu kali M3 2.25 250,000.00 562,500.00
4 Besi Beton
Besi 8 Btg 24.00 55,000.00 1,320,000.00
Besi 10 Btg 28.00 86,500.00 2,422,000.00
Besi 12 Btg 6.00 124,000.00 744,000.00
5 Kawat Beton Kg 5.50 20,000.00 110,000.00
6 Kerikil M3 19.25 175,000.00 3,368,750.00
7 Papan 3/20 cm kayu kelas II Lbr 28.0 51,500.00 1,442,000.00
8 Kaso 5/7
Paku 5 cmcm
dan 7 cm Btg 9.0 34,500.00 310,500.00
9 Kg 12.4 18,000.00 222,300.00
10 Minyak bekisting Ltr 8.0 5,000.00 40,000.00
11 Tanah Urug M3 15.50 50,000.00 775,000.00
12 Pipa PVC 3" M3 14.00 44,250.00 619,500.00
24,341,550.00
PPN ( 10%) 2,434,155.00
HARGA
VOLUME
NO URAIAN Satuan SATUAN JUMLAH BIAYA (Rp)
KEBUTUHAN
(Rp)
1. TENAGA KERJA
1 Mandor HOK - 140,000.00 -
2 Kepala Tukang HOK - 146,000.00 -
3 Tukang HOK Err:509 130,000.00 Err:509
4 Pekerja HOK Err:509 92,000.00 Err:509
Err:509 Err:509
2. BAHAN/MATERIAL
1 Semen Zak Err:509 Err:509 Err:509
2 Pasir M3 Err:509 Err:509 Err:509
3 Batu kali M3 Err:509 Err:509 Err:509
4 Besi Beton Kg Err:509 11,600.00 Err:509
5 Kawat Beton Kg Err:509 20,000.00 Err:509
6 Kerikil M3 Err:509 Err:509 Err:509
7 Papan 3/20 cm kayu kelas II M2 Err:509 2,500,000.00 Err:509
8 Kaso 5/7
Paku 5 cmcm
dan 7 cm M3 Err:509 2,500,000.00 Err:509
9 Kg Err:509 18,000.00 Err:509
10 Minyak bekisting Ltr Err:509 5,000.00 Err:509
11 Tanah Urug M3 Err:509 50,000.00 Err:509
12 PVC 3" M Err:509 44,250.00 Err:509
Err:509
3. ALAT
1 Sewa/hari - -
2 Buah
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.750 0.75 92,000.00 69,000.00
2 Tukang HOK - - 130,000.00 -
3 Kepala Tukang HOK - - 146,000.00 -
4 Mandor HOK 0.025 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.200 1.20 92,000.00 110,400.00
2 Tukang HOK - - 130,000.00 -
3 Kepala Tukang HOK - - 146,000.00 -
4 Mandor HOK 0.045 - 140,000.00 -
Item Pekerjaan : Pek. mengangkut material atau hasil galian dan bongkaran sejauh 30 M
Vol. Item Pekerjaan : 1.00 M3
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 0.356 0.36 92,000.00 32,752.00
2 Tukang HOK - - 130,000.00 -
3 Kepala Tukang HOK - - 146,000.00 -
4 Mandor HOK 0.018 - 140,000.00 -
Volume per
NO URAIAN Satuan Satu Satuan JUMLAH/VOLUME Harga Jumlah
Pekerjaan KEBUTUHAN Satuan Harga
(Koefisien)
(1) (2) (3) (4) (5) (6) 7
A TENAGA KERJA :
1 Pekerja HOK 1.500 1.50 92,000.00 138,000.00
2 Tukang HOK 0.75 0.75 130,000.00 97,500.00
3 Kepala Tukang HOK 0.08 - 146,000.00 -
4 Mandor HOK 0.08 - 140,000.00 -
HARGA
JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp) (Rp)
I Pengerukkan Sedimen Saluran Drainase
1. Pek. galian sedimen pada saluran terbuka (L= 51 M) M3 17.85 69,000 1,231,650.00
2. Pek. galian sedimen pada saluran tertutup ( L=120.5 M) M3 42.18 110,400 4,656,120.00
3. Pek. mengangkut material atau hasil galian dan bongkaran M3 60.03 32,752 1,965,938.80
JUMLAH 7,853,708.80
II Rehab Buis Beton (L=2 M)
4. Pek. Beton Site Mix K. 175 M3 0.33 815,620 269,154.60
JUMLAH 269,154.60
JUMLAH TOTAL 8,122,863.40
PPN 10% 812,286.34
JUMLAH TOTAL + PPN 10% 8,935,149.74
DIBULATKAN 8,935,000.00
Terbilang : Delapan Juta Sembilan Ratus Tiga Puluh Lima Ribu Rupiah
ALRISMAN, ST ELFIANA, ST
NIP. 19830120 201001 1 014 NIP. 19861216 201902 2 002
HARGA
JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp) (Rp)
I Pengerukkan Sedimen Saluran Drainase
1. Pek. galian sedimen pada saluran terbuka (L= 51 M) M3 17.85 69,000 1,231,650.00
2. Pek. galian sedimen pada saluran tertutup ( L=120.5 M) M3 42.18 110,400 4,656,672.00
3. Pek. mengangkut material atau hasil galian dan bongkaran M3 60.03 32,752 1,966,102.56
JUMLAH 7,854,424.56
II Rehab Buis Beton (L=2 M)
4. Pek. Beton Site Mix K. 175 M3 0.33 815,620 269,154.60
JUMLAH 269,154.60
JUMLAH TOTAL 8,123,579.16
PPN 10% 812,357.92
JUMLAH TOTAL + PPN 10% 8,935,937.08
DIBULATKAN 8,935,000.00
Terbilang : Delapan Juta Sembilan Ratus Tiga Puluh Lima Ribu Rupiah
ALRISMAN, ST ELFIANA, ST
NIP. 19830120 201001 1 014 NIP. 19861216 201902 2 002
HARGA
JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp) (Rp)
I Pengerukkan Sedimen Saluran Drainase
1. Pek. galian sedimen pada saluran terbuka (L= 51 M) M3 17.85 69,000 1,231,650.00
2. Pek. galian sedimen pada saluran tertutup ( L=120.5 M) M3 42.18 110,400 4,656,672.00
3. Pek. mengangkut material atau hasil galian dan bongkaran M3 60.03 32,752 1,966,102.56
JUMLAH 7,854,424.56
II Rehab Buis Beton (L=2 M)
4. Pek. Beton Site Mix K. 175 M3 0.33 815,620 269,154.60
JUMLAH 269,154.60
JUMLAH TOTAL 8,123,579.16
PPN 10% 812,357.92
JUMLAH TOTAL + PPN 10% 8,935,937.08
DIBULATKAN 8,935,000.00
Terbilang : Delapan Juta Sembilan Ratus Tiga Puluh Lima Ribu Rupiah
Diketahui Oleh,
Pejabat Pembuat Komitmen (PPK)
ALRISMAN, ST
NIP. 19830120 201001 1 014
RENCANA ANGGARAN BIAYA BAHAN
HARGA
JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp) (Rp)
I Pengerukkan Sedimen Saluran Drainase
1. Pek. galian sedimen pada saluran terbuka (L= 51 M) M3 17.85 - -
2. Pek. galian sedimen pada saluran tertutup ( L=120.5 M) M3 42.18 - -
3. Pek. mengangkut material atau hasil galian dan bongkaran M3 60.03 - -
JUMLAH -
II Rehab Buis Beton (L=2 M)
4. Pek. Beton Site Mix K. 175 M3 0.33 580,120 191,439.60
JUMLAH 191,439.60
JUMLAH TOTAL 191,439.60
PPN 10% 19,143.96
JUMLAH TOTAL + PPN 10% 210,583.56
DIBULATKAN 211,000.00
Diketahui Oleh,
Pejabat Pelaksana Teknis Kegiatan
ALRISMAN, ST
NIP. 19830120 201001 1 014
RENCANA ANGGARAN BIAYA UPAH
HARGA
JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp) (Rp)
I Pengerukkan Sedimen Saluran Drainase
1. Pek. galian sedimen pada saluran terbuka (L= 51 M) M3 17.85 69,000 1,231,650.00
2. Pek. galian sedimen pada saluran tertutup ( L=120.5 M) M3 42.18 110,400 4,656,672.00
3. Pek. mengangkut material atau hasil galian dan bongkaran M3 60.03 32,752 1,966,102.56
JUMLAH 7,854,424.56
II Rehab Buis Beton (L=2 M)
4. Pek. Beton Site Mix K. 175 M3 0.33 235,500 77,715.00
JUMLAH 77,715.00
JUMLAH TOTAL 7,932,139.56
PPN 10% 793,213.96
JUMLAH TOTAL + PPN 10% 8,725,353.52
DIBULATKAN 8,726,000.00
Terbilang : Delapan Juta Tujuh Ratus Dua Puluh Enam Ribu Rupiah
Diketahui Oleh,
Pejabat Pelaksana Teknis Kegiatan
ALRISMAN, ST
NIP. 19830120 201001 1 014
RENCANA ANGGARAN BIAYA UPAH (TAWARAN UPAH)
HARGA
JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp) (Rp)
I Pengerukkan Sedimen Saluran Drainase
1. Pek. galian sedimen pada saluran terbuka (L= 51 M) M3 17.85 69,000 1,231,650.00
2. Pek. galian sedimen pada saluran tertutup ( L=120.5 M) M3 42.18 110,000 4,639,800.00
3. Pek. mengangkut material atau hasil galian dan bongkaran M3 60.03 32,000 1,920,960.00
JUMLAH 7,792,410.00
II Rehab Buis Beton (L=2 M)
4. Pek. Beton Site Mix K. 175 M3 0.33 187,000 61,710.00
JUMLAH 61,710.00
JUMLAH TOTAL 7,854,120.00
DIBULATKAN 7,854,000.00
Terbilang : Tujuh Juta Delapan Ratus Lima Puluh Empat Ribu Rupiah
MAHYUDIN
Kepala Pekerja
RINCIAN KLARIFIKASI DAN NEGOSIASI
3. Pek. mengangkut material atau hasil galian dan bongkaran M3 60.03 32,752
JUMLAH
II Rehab Buis Beton (L=2 M)
4. Pek. Beton Site Mix K. 175 M3 0.33 235,500
JUMLAH
JUMLAH PEKERJAAN
DIBULATKAN
PIHAK KEDUA
MAHYUDIN
Kepala Pekerja
AN KLARIFIKASI DAN NEGOSIASI
Dibuat Oleh,
PIHAK PERTAMA
ALRISMAN, ST
NIP. 19830120 201001 1 014
B U K I T T I N G G I
Nomor : II.22/PPK-PD/DPUPR-CK/2019
Tanggal : 25 Juni 2109
ANTARA
PEJABAT PEMBUAT KOMITMEN
DINAS PEKERJAAN UMUM DAN PENATAAN RUANG
KOTA BUKITTINGGI
DENGAN
PELAKSANA SWAKELOLA
TENTANG
TOTAL JUMLAH
NO URAIAN PEKERJAAN
(Rp)
Terbilang : Tujuh Juta Sembilan Ratus Tiga Puluh Dua Ribu Rupiah
Dibuat Oleh,
Pejabat Pembuat Komitmen
ALRISMAN, ST
NIP. 19830120 201001 1 014
RENCANA ANGGARAN BIAYA UPAH
HARGA
JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp) (Rp)
I Pengerukkan Sedimen Saluran Drainase
1. Pek. galian sedimen pada saluran terbuka (L= 51 M) M3 17.85 69,000 1,231,650.00
2. Pek. galian sedimen pada saluran tertutup ( L=120.5 M) M3 42.18 110,400 4,656,672.00
3. Pek. mengangkut material atau hasil galian dan bongkaran M3 60.03 32,752 1,966,102.56
JUMLAH 7,854,424.56
II Rehab Buis Beton (L=2 M)
4. Pek. Beton Site Mix K. 175 M3 0.33 235,500 77,715.00
JUMLAH 77,715.00
JUMLAH TOTAL 7,932,139.56
Dibuat Oleh,
Pejabat Pembuat Komitmen
ALRISMAN, ST
NIP. 19830120 201001 1 014
REKAP RENCANA ANGGARAN BIAYA UPAH (TAWARAN UPAH)
TOTAL JUMLAH
NO URAIAN PEKERJAAN
(Rp)
Terbilang : Tujuh Juta Delapan Ratus Lima Puluh Empat Ribu Rupiah
MAHYUDIN
Kepala Pekerja
RENCANA ANGGARAN BIAYA UPAH (TAWARAN UPAH)
HARGA
JUMLAH HARGA
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN
(Rp) (Rp)
I Pengerukkan Sedimen Saluran Drainase
1. Pek. galian sedimen pada saluran terbuka (L= 51 M) M3 17.85 69,000 1,231,650.00
2. Pek. galian sedimen pada saluran tertutup ( L=120.5 M) M3 42.18 110,000 4,639,800.00
3. Pek. mengangkut material atau hasil galian dan bongkaran M3 60.03 32,000 1,920,960.00
JUMLAH 7,792,410.00
II Rehab Buis Beton (L=2 M)
4. Pek. Beton Site Mix K. 175 M3 0.33 187,000 61,710.00
JUMLAH 61,710.00
JUMLAH TOTAL 7,854,120.00
DIBULATKAN 7,854,000.00
MAHYUDIN
Kepala Pekerja
RINCIAN KLARIFIKASI DAN NEGOSIASI
3. Pek. mengangkut material atau hasil galian dan bongkaran M3 60.03 32,752 1,966,103 32,000 1,920,960 30,000 1,800,900
Terbilang : Tujuh Juta Dua Ratus Tiga Puluh Delapan Ribu Rupiah
MAHYUDIN ALRISMAN, ST
Kepala Pekerja NIP. 19830120 201001 1 014
JALAN
43.0000
4.0000 9.0000
0.70
0.20
1.20
JALAN ADINEGORO
43.0000
9.0000 4.3000