Elevasi Hulu BB S1
BB S1 El.Tanggul = + 136
El.MA = + 135
El.MTA = + 134
El.Dasar Sal = + 133
SS D1 Dimensi SS D1
Q = 0,91793 m3/dt
2646 m V = 0,61 m/dt
b = 1,528 m
h = 0,611 m
Gorong - gorong i = 0,0008
7m m = 1,0
n = 2,5
600 m w = 0,5 m
L = 2646 m
BB D1
Elevasi Hilir BB D1
El.Tanggul = + 135,5
El.MA = + 134,5
El.MTA = + 133,5
El.Dasar Sal = + 132,5
= + 133,61
= + 132,61
= + 133,613
= + 132,613
= + 133,612
El. Dasar Saluran = + 132,5 + ( x (133 – 132,5))
= + 132,612
Kelas jalan II dengan lebar lajur ideal 3.5 m sehingga lebar jalan = 7 m
Analisa Perhitungan
= 0,611 m2
A =bxh
0,611 m2 = 2,5 h x h
h2 = 0,24
h = 0,489 m
Maka ;
b = 2,5 x 0,489 m
= 1,222 m
3. Kehilangan Energi
Va = 1,5 m/dt
V = 0,61 m/dt
(Va V ) 2
h masuk = 0,5
2g
= 0,0226 m
(Va V ) 2
h keluar = 1
2g
= 0,0403 m
h = hm + hk
= 0,0226 + 0,0403
= 0,0629 m
PERENCANAAN SIPHON
BB G1 Elevasi Hulu BB G1
El.Tanggul = + 133,5
El.MA = + 132,5
El.MTA = + 131,5
El.Dasar Sal = + 130,5
Elevasi Hilir BB G2
El.Tanggul = + 133
El.MA = + 132
El.MTA = + 131
2230 m El.Dasar Sal = + 130
10 m
Dimensi
Siphon Q = 0,33753 m3/dt
V = 0,5054 m/dt
1115 b = 0,775 m
m h = 0,576 m
i = 0,0008
m = 1,0
BB G2 n = 1,0
w = 0,5 m
= + 131,25
= + 130,25
= + 131,251
= + 130,251
= + 131,248
= + 130,248
=
= 0,22502 m2
A =bxh
0,22502 m2 = 1,0 h x h
h2 = 0,22502
h = 0,474 m
Maka ;
b = 1,0 x 0,474
= 0,474 m
3. Kehilangan Energi
Va = 1,5 m/dt
V = 0,5054 m/dt
(Va V ) 2
h masuk = m 0,5
2g
=
= 0,0252 m
(Va V ) 2
h keluar = k 1
2g
=
= 0,05041 m
(Va ) 2 xL
hf =
C 2 xR
dimana :
P = b + 2.h
= 0,576 + (2 x 0,474)
= 1,524 m
A = bxh
= 0,576 x 0,474
= 0,273 m2
R = A/P
= 0,273 / 1,524
= 0,17 m
C = K x R1/6
= 35 x (0,17)1/6
= 26,050
(Va ) 2 xL
hf1 =
C 2 xR
= 0,195 m
(Va ) 2 xL
hf2 =
C 2 xR
=
= 0,072 m
(Va ) 2 xL
hf3 =
C 2 xR
=
= 0,064 m
V2
h saringan = c.
2g
s
c=β[ ]^4/3 . sin δ
b s = 8 mm Ø jeruji
b = 5 cm jarak antar jeruji
= 2,4 . sin 30 δ = sudut kemiringan dari
bidang horisontal
= 0,000224 saringan
β = bentuk jeruji bulat
V2
h saringan = c. = 0.000224 X = (2,4)
2g Harga Kb dr Kp-4 hal 256
2,9x10 -6 tabel 5.2
Va 2
h belokan = Kb. = 0,14 = 0,0161
2g
Elevasi Hulu BB G2
BB G2 El.Tanggul = + 133
El.MA = + 132
El.MTA = + 131
El.Dasar Sal = + 130
1004,5 m
Data-data SS G3:
SS G3
Q = 0,18564 m3/dt
V = 0,416 m/dt
b = 0,714 m
h = 0,357 m
B. Terjun 2009 m i = 0,0008
w = 0,5 m
g = 9,81 m
1004,5 p = 2002 m
m
Elevasi Hilir BB G3
BB G3
El.Tanggul = + 132,5
El.MA = + 131,5
El.MTA = + 130,5
El.Dasar Sal = + 129,5
= + 130,75
= + 129,75
= 0,365 = Y1 + 2,002
= 0,365 m Y1 = 1,823 m
Menghitung tinggi energi hilir pada kolam olak ( Hd )
Hd = 1,48 x H1
= 1,48 x 0,365
= 0,5402 m
Menghitung perkiraan awal tinggi bangunan terjun (∆Z )
∆Z = ( ∆H + Hd ) - H1
= ( 0,357 + 0,5402 ) – 0,365
= 0,5322 m
Jadi bangunan terjun ≤ 1,5 → tegak …OK!
= =
= 0,08 m = 3,647
Yd =
Yu
2
1 8Fru^2 1
=
= 0,374
SS D2
BB D2
ST Kiri 2 ST Kanan 2
Ruas Saluran Sekunder Sungai (SS D2), dan Ruas Saluran Sekunder Sungai (SS D3)
Q = 0,57493 m3 / dt Q = 0,15680 m3 / dt
V = 0,5518 m / dt V = 0,3988 m / dt
h = 0,546 m h = 0,335 m
b = 1,091 m b = 0,670 m
W = 0,5 m W = 0,5 m
Ruas Tersier (SBD Kiri 2), dan Ruas Tersier (SBD Kanan 2)
Q = 0,15778 m3 / dt Q = 0,15092 m3 / dt
V = 0,5828 m / dt V = 0,5764 m / dt
h = 0,368 m h = 0,362 m
b = 0,368 m b = 0,362 m
W = 0,4 m W = 0,4 m
DESAIN HIDROLIK BANGUNAN SADAP
1. Desain Hidrolik pintu sekunder SS D2
Type Slide Gate / Pintu sorong
Direncanakan Lebar = 1,5 m
Q = ( k.µ ).a .b 2.g.h
a = 0,19 m
a = 19 cm
Kontrol 19 cm < 0,63 . h
19 cm < 0,63 . 54 cm
19 cm < 34,02 cm .............................(OK)
a = 0,06 m
a = 6 cm
Kontrol 6 cm < 0,63 . h
6 cm < 0,63 . 33,5 cm
6 cm < 21,105 cm .............................(OK)
a = 0,062 m
a = 6,2 cm
Kontrol 6,2 cm < 0,63 . h
6.2 cm < 0,63 . 36,2 cm
6,2 cm < 22,806 cm .............................(OK)
a = 0,065 m
a = 6,5 cm
Kontrol 6,5 cm < 0,63 . h
6,5 cm < 0,63 . 36,8 cm
6,5 cm < 23,184 cm .............................(OK)