Anda di halaman 1dari 139

BACK UP VOLUME

LANTAI DAK
HITUNGAN VOLUME PASANGAN DINDING BATA & PLESTERAN 1 : 5 & 1 : 3

Nama Proyek
Lokasi
Pekerjaan : Pasangan Dinding Baru

DIMENSI PENGURANG LUAS


NAMA RUANG DINDING LEBAR TINGGI JUMLAH LUAS DINDINGTIPE KUSEN LUAS KUSEN
JUMLAH KUSEN
LUAS KUSEN TOTAL
(m) (m) (m2) (m2) (m) (m2) (m2)
PEK. DINDING BATA

RUANG DALAM B (1-3) 6 4 1 24 P1 3.68 1 3.68 15.76


J1 2.28 2 4.56
B (3-4) 6 4 1 24 P1 3.68 1 3.68 15.76
J1 2.28 2 4.56
B (4-5) 6 4 1 24 P1 3.68 1 3.68 15.76
J1 2.28 2 4.56
B (5-6) 6 4 1 24 P1 3.68 1 3.68 15.76
4 1 J1 2.28 2 4.56
B' (3-4) 6 4 1 24 P2 2.03 1 2.03 21.98
B' (5-6) 6 4 1 24 P2 2.03 1 2.03 21.98
C (1-2) 3 4 1 12 J1 2.28 1 2.28 9.72
C (2-3) 3 4 1 12 12.00
C (3-3') 4 4 1 16 P2 2.03 1 2.03 13.98
C (4-5) 6 4 1 24 P1 3.68 1 3.68 20.32
C (5'-6) 4 4 1 16 P2 2.03 1 2.03 13.98
D (2-3) 3 4 1 12 J1 2.28 1 2.28 9.72
D (3--3') 4 4 1 16 J1 2.28 2 4.56 11.44
D (5'-6) 4 4 1 16 J1 2.28 2 4.56 11.44
E (4-5) 6 4 1 24 24.00
1 (B-C) 6 4 1 24 J1 2.28 3 6.84 17.16
2 (C-D) 4 4 1 16 J1 2.28 2 4.56 11.44
3 (B-C) 6 4 1 24 P2 2.03 1 2.03 21.98
4 (B-B') 4 4 1 16 16.00
4 (D-E) 2 4 1 8 J1 2.28 1 2.28 5.72
5 (B-B') 4 4 1 16 16.00
5 (D-E) 2 4 1 8 J1 2.28 1 2.28 5.72
6 (B-C) 6 4 1 24 P1 3.68 1 3.68 13.48
J1 2.28 3 6.84
6 (C-D) 4 4 1 16 J1 2.28 2 4.56 11.44
8 4 1 32 BV2 0.16 2 0.32 31.68
Jumlah 384.20

Dinding TOLIET HORIZONTAL 12 4 1 48 P3 1.49 6 8.91 39.09

VERTIKAL 17 4 1 68

Jumlah 39.09

PEK. PLESTERAN
Plesteeran kolom praktis beton 0.3 4 0 0.00
Jumlah 1 : 5 768.39

Jumlah 1 : 3 78.18
HITUNGAN VOLUME PASANGAN LANTAI KERAMIK

Nama Proyek
Lokasi
Pekerjaan : Pek. Pasangan lantai Keramik

DIMENSI
NAMA RUANG DINDING LEBAR TINGGI JUMLAH LUAS
(m) (m) (m2)

Ruangan Dalam - 208.37


Teras 49.6
Jumlah

Plint Keramik 60 115.3


Bordes Toilet
KORIDOR
Keramik Toilet - 13.8
Dinding Toilet 31.5
Jumlah

HITUNGAN VOLUME PASANGAN PLAFOND

Nama Proyek
Lokasi
Pekerjaan : Pek. Pasangan Plafond

DIMENSI
NAMA RUANG DINDING LEBAR TINGGI JUMLAH LUAS
(m) (m) (m2)

Ruang Dalam - 253.5


-
List plafond 261

Plafond TOILET - 11

LUAS TOTAL
KURVA S JADWAL PELAKSANAAN KONSTRUKSI
#REF!
#REF!
#REF!

BULAN KE 1 BULAN KE 2
NO URAIAN PEKERJAAN JUMLAH HARGA BOBOT PEKERJAAN MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU MINGGU
(Rp.) (%) I II III IV I II III IV

1. GEDUNG MASJID

A. PEKERJAAN PERSIAPAN #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

B. PEKERJAAN STRUKTUR
I PEKERJAAN TANAH, PONDASI #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
II #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

2. BANGUNAN KANTOR PENGELOLA

I. #REF! #REF! #REF! #REF! #REF! #REF! #REF!


II. #REF! #REF! #REF! #REF! #REF! #REF! #REF!
III #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

3. BANGUNAN TEMPAT WUDHU

TEMPAT WUDHU PRIA


I. PEKERJAAN TANAH, PONDASI #REF! #REF! #REF! #REF! #REF! #REF!
II. PEKERJAAN STRUKTUR R.WUDHU #REF! #REF! #REF! #REF! #REF! #REF!
III PEKERJAAN PASANGAN & PLESTERAN #REF! #REF! #REF! #REF! #REF!

TEMPAT WUDHU WANITA


I. PEKERJAAN TANAH, PONDASI #REF! #REF! #REF! #REF! #REF! #REF!
II. PEKERJAAN STRUKTUR R.WUDHU #REF! #REF! #REF! #REF! #REF! #REF!
III PEKERJAAN PASANGAN & PLESTERAN #REF! #REF! #REF! #REF! #REF!

4. PEKERJAAN SARANA LUAR DAN LANDSCAPE

I. #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

TOTAL HARGA #REF!


JUMLAH BOBOT % #REF!
JUMLAH BOBOT PER MINGGU #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
JUMLAH BOBOT KUMULATIF #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN DED JPO PARIAMAN
TAHUN ANGGARAN 2021

NO URAIAN PEKERJAAN JUMLAH BIAYA JUMLAH TOTAL


I PEKERJAAN PERSIAPAN 37,841,200.35 37,841,200.35
II PEKERJAAN TANAH 90,621,584.94 90,621,584.94
III PEKERJAAN BORE PILE 200,572,621.63 200,572,621.63
IV PEKERJAAN PILE CAP 119,984,824.14 119,984,824.14
V PEKERJAAN KONSTRUKSI BAJA 1,266,210,732.15 1,266,210,732.15
VI PEKERJAAN LANTAI BETON 65,335,317.80 65,335,317.80
VII PEKERJAAN CANOPY 98,476,863.90 98,476,863.90
VIII PEKERJAAN TANGGA 149,690,482.04 149,690,482.04

JUMLAH BIAYA 2,028,733,626.94 2,028,733,626.94


PPN 10 % 202,873,362.69 202,873,362.69
JUMLAH TOTAL 2,231,606,989.63 2,231,606,989.63
RINCIAN RENCANA ANGGARAN BIAYA (RAB)
PEKERJAAN DED JPO PARIAMAN
TAHUN ANGGARAN 2021

NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN (Rp) SUB JUMLAH HARGA (Rp)

I PEKERJAAN PERSIAPAN 37,841,200.35


1 Papan Nama Proyek 1.00 m2 475,000.00 475,000.00
2 Pengukuran Dan Pemasangan Bowplank 67.00 m1 115,059.63 7,708,995.35
3 Keselamatan dan Kesehatan Kerja, Tingkat Resiko Sedang 1.00 ls 29,657,205.00 29,657,205.00
II PEKERJAAN TANAH 90,621,584.94
1 Pek. Pengeboran Pondasi Bore Pile Ø 40 (20 titik X 16.7 m) 334.00 m1 252,810.25 84,438,623.50
2 Pek. Galian Pondasi Pile Cap 3600x2400x950 16.42 m3 120,175.00 1,972,792.80
3 Pek. Galian Pondasi Pile Cap 2400x1200x950 10.94 m3 120,175.00 1,315,195.20
4 Pek. Buangan tanah Galian/lumpur keluar Lokasi 58.37 m3 49,600.00 2,894,973.44
III PEKERJAAN BORE PILE 200,572,621.63
1 Pembesian Utama Ø16 SNI 4,221.76 kg 20,479.27 86,458,559.08
2 Pembesian Sengkang Ø10-100 SNI 1,922.00 kg 20,479.27 39,361,155.19
3 Pembesian Sengkang Ø10-150 SNI 307.93 kg 20,479.27 6,306,249.60
4 Pembesian Sengkang Ø10-200 SNI 116.25 kg 20,479.27 2,380,715.03
5 Beton Ready Mix K-300 41.95 m3 1,574,858.47 66,065,942.72
IV PEKERJAAN PILE CAP 119,984,824.14
a. Pek. Pile cap /PC1 , 3600x2400x800 cm
Urugan Pasir dengan Pasir Urug tebal 5 cm 0.86 m3 266,813.80 230,527.12
Lantai Kerja 1 PC : 3 pasir : 5 kerikil 1.73 m3 1,488,382.42 2,571,924.82
Pembesian Ø16 -150 SNI 566.27 kg 20,479.27 11,596,836.67
Pembesian Ø19 -150 SNI 795.65 kg 20,479.27 16,294,289.49
Pembesian Ø16 SNI 202.24 kg 20,479.27 4,141,727.38
Bekisting 19.20 m2 168,754.77 3,240,091.50
Beton Ready Mix K-300 13.82 m3 1,574,858.47 21,770,843.48
b. Pek. Pile cap /PC2 , 2400x1200x800 cm
Urugan Pasir dengan Pasir Urug tebal 5 cm 0.58 m3 266,813.80 153,684.75
Lantai Kerja 1 PC : 3 pasir : 5 kerikil 1.15 m3 1,488,382.42 1,714,616.55
Pembesian Ø16 -150 SNI 485.38 kg 20,479.27 9,940,145.71
Pembesian Ø19 -150 SNI 681.98 kg 20,479.27 13,966,533.85
Pembesian Ø16 SNI 242.69 kg 20,479.27 4,970,072.86
Bekisting 23.04 m2 168,754.77 3,888,109.80
Beton Ready Mix K-300 9.22 m3 1,574,858.47 14,513,895.65
c. Pek. Pondasi Tangga 1250x400x750
Urugan Pasir dengan Pasir Urug tebal 5 cm 0.10 m3 266,813.80 26,681.38
Lantai Kerja 1 PC : 3 pasir : 5 kerikil 1.50 m3 1,488,382.42 2,232,573.63
Pembesian Ø16 -150 SNI 188.55 kg 20,479.27 3,861,297.92
Pembesian Ø10 -150 SNI 40.92 kg 20,479.27 838,011.69
Bekisting 9.90 m2 168,754.77 1,670,672.18
Beton Ready Mix K-300 1.50 m3 1,574,858.47 2,362,287.70
V PEKERJAAN KONSTRUKSI BAJA 1,266,210,732.15
a. Pek. Kolom Pipa Shedule 80
Anchor 8m25 197.12 kg 20,479.27 4,036,873.52
Base Plate 22mm 1,382.48 kg 48,674.42 67,291,418.19
Kolom Antar Jembatan PIPA SCH 40 Ø609 /24 in 2,667.28 kg 48,674.42 129,828,318.61
KolomTumpuan Sasis 1 PIPA SCH 40 Ø609 /24 in 952.60 kg 48,674.42 46,367,256.65
KolomTumpuan Sasis 2 PIPA SCH 40 Ø609 /24 in 514.40 kg 48,674.42 25,038,318.59
Pekerjaan Perkitan 5,713.88 kg 796.64 4,551,882.11
b. Pek. Balok
Balok Girder IWF 900.300.16.28 12,490.20 kg 48,674.42 607,953,295.14
Voute IWF 400.200 237.60 kg 48,674.42 11,565,043.23
Sasis IWF 400.200 6,494.40 kg 48,674.42 316,111,181.56
Balok Anak IWF 400.200 475.20 kg 48,674.42 23,130,086.46
Balok Diafragma UNP 200.100.10.12 296.04 kg 48,674.42 14,409,576.59
Pekerjaan Perkitan 19,993.44 kg 796.64 15,927,481.51
VI PEKERJAAN LANTAI BETON 65,335,317.80
Pembesian Ø12 -150 SNI 1,707.61 kg 20,479.27 34,970,672.96
Bekisting 69.12 m2 128,218.91 8,862,490.71
Beton Ready Mix K-225 13.82 m3 1,555,422.03 21,502,154.12
VII PEKERJAAN CANOPY 98,476,863.90
a. Pek. Kolom Pipa Shedule 40
PIPA Hitam Ø 3 in 514.60 kg 24,258.43 12,483,436.27
PIPA Hitam Ø 2 in 916.99 kg 24,258.43 22,244,785.66
PIPA Hitam Ø 1 in 318.96 kg 24,258.43 7,737,468.63
PIPA Hitam Ø 3/4 in 832.84 kg 24,258.43 20,203,390.31
Pekerjaan Perakitan 2,583.39 kg 796.64 2,058,023.04
b. Pek. Atap
Atap Trimdek 120.32 m2 280,500.00 33,749,760.00
VIII PEKERJAAN TANGGA 149,690,482.04
a. Pek. Trap Tangga
Siku 60.60 2,146.32 kg 24,258.43 52,066,352.10
Plat Bodres 3.2mm 3,828.14 kg 24,258.43 92,864,663.77
Pekerjaan Perakitan 5,974.46 kg 796.64 4,759,466.16

JUMLAH BIAYA 2,028,733,626.94


PPN 10 % 202,873,362.69
JUMLAH TOTAL 2,231,606,989.63
-
HARGA SATUAN PEKERJAAN

PEKERJAAN DED JPO PARIAMAN


APBD TAHUN ANGGARAN 2021

PEKERJAAN STRUKTUR

NO URAIAN PEKERJAAN HARGA SATUAN


1 Pengukuran dan pemasangan 1 m’ Bouwplank 115,059.63
2 Pekerjaan 1 m' Pagar Sementara dari seng gelombang tinggi 2 m 584,963.71
3 Pekerjaan 1 m2 membersihkan Lapangan dan perataan 27,830.00
4 Penggalian 1 m3 tanah biasa sedalam 1 m 120,175.00
5 Penggalian 1 m3 tanah biasa sedalam 2 m 148,005.00
6 Pengurugan kembali 1 m3 galian tanah 88,550.00
7 Pemadatan tanah 1 m3 tanah ( per 20 cm ) 88,550.00
8 Pengurugan 1 m3 dengan tanah urug 157,441.90
9 Pengurugan 1 m3 dengan pasir urug 266,813.80
10 Pengeboran 1 m Tanah 252,810.25
11 Pemasangan 1 m3 pondasi batu belah campuran 1SP:3PP 1,285,943.26
12 Pemasangan 1 m3 pondasi batu belah campuran 1SP:5PP 1,194,322.47
13 Pemasangan 1 m3 batu kosong anstamping 671,162.06
14 Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 Mpa (K100), slump (3-6) cm, w/c = 0,87 1,263,007.70
15 Membuat 1 m3 beton mutu f'c = 14.5 Mpa (K175), slump (12 ± 2)cm, w/c = 0,85 1,488,382.42
16 Membuat 1 m3 beton mutu f'c = 16,9 Mpa (K200),slump (12 ± 2) cm, w/c = 0,61 1,526,914.01
17 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K225), slump (12 ± 2) cm, w/c = 0,58 1,555,422.03
18 Membuat 1 m3 beton f'c = 21,7 Mpa (K300),slump (12 ± 2) cm, w/c = 0,56 1,574,858.47
19 Membuat 1 m3 beton Ready Mix K-300 1,747,005.09
20 Pembesian 10 kg dengan besi polos atau besi ulir 204,792.69
21 Pemasangan 1 m2 bekisting untuk pondasi 168,754.77
22 Pemasangan 1 m2 bekisting untuk sloof 170,261.27
23 Pemasangan 1 m2 bekisting untuk kolom 343,521.36
24 Pemasangan 1 m2 bekisting untuk balok 349,362.81
25 Pemasangan 1 m2 bekisting untuk lantai 458,528.26
26 Pemasangan 1 m2 bekistig untuk dinding 401,995.84
27 Pemasangan 1 m2 bekisting untuk tangga 340,019.61
BANGUNAN MASJID
28 6 M' Pondasi Tiang Pancang persegi 30x30 cm 4,933,094.63
29 1 M3 Pondasi Poer - P1 (0,60x0,60x0,60 m3) Tul. 97 kg/m3 4,696,422.67
30 1 M3 Pondasi Poer - P2 (0,60x1,35x0,60 m3) Tul. 88 kg/m3 4,196,810.61
31 1 M3 Pondasi Poer - P3 Tul. 93 kg/m3 3,991,916.90
32 1 M3 Pondasi Poer - P4 (1,35x1,35x0,60 m3) Tul. 88 kg/m3 3,881,511.97
33 1 M3 Sloof SF.1 (0,20x0,40 m3) Tul. 151 kg/m3 6,369,840.76
34 1 M3 Sloof SF.2 (0,20x0,30 m3) Tul. 153 kg/m3 6,978,336.85
35 1 M3 Kolom Struktur K.1 50/50 cm Tul. 142 kg/m3 7,231,085.55
36 1 M3 Kolom Struktur K.2 Ø 50 cm Tul. 168 kg/m3 6,732,982.47
37 1 M3 Kolom Struktur K.3 30/30 Tul. 198 kg/m3 10,210,038.54
38 1 M3 Kolom Struktur K.4 15/15 Tul. 180 kg/m3 14,421,696.48
39 1 M3 Kolom Struktur KP 15/15 Tul. 180 kg/m3 14,421,696.48
40 1 M3 Balok Struktur B.1 30/50 Tul. 192 kg/m3 7,975,708.68
41 1 M3 Balok Struktur B.2 25/40 Tul. 136 kg/m3 7,189,877.85
42 1 M3 Balok Struktur B.A1 20/30 Tul. 188 kg/m3 8,685,680.64
43 1 M3 Balok Struktur RB.1 30/50 Tul. 192 kg/m3 7,975,708.68
44 1 M3 Balok Struktur RB.2 25/40 Tul. 136 kg/m3 7,189,877.85
45 1 M3 Balok Struktur RB.3 20/30 Tul. 188 kg/m3 8,685,680.64
46 1 M3 Balok Struktur RB.4 20/30 Tul. 188 kg/m3 8,685,680.64
47 1 M3 Balok Struktur RB.5 15/25 Tul. 168 kg/m3 8,835,075.76
48 1 M3 Pelat Lantai T.12 cm Tul. 136 kg/m3 8,181,107.89
49 1 M3 Pelat Atap Dak T.12 cm Tul. 96 kg/m3 7,361,937.13
50 1 M3 Pelat Atap Dak T.22.5 cm Tul. 136 kg/m3 6,397,942.44
51 1 M3 Dinding talang Luar 15/100 Tul. 102 kg/m3 8,671,277.57
52 1 M3 Sirip Talang Bagian Atas 10,5/60 Tul. 85 kg/m3 10,247,398.18
53 1 M3 Sirip Talang Melekat Pada Dinding Beton (sudutan) Tul. 85 kg/m3 10,247,398.18
54 1 M3 Beton Kaki Sirip 15/100 Tul. 102 kg/m3 8,671,277.57
55 1 M3 Beton Peninggian Dinding dasar Kubah 15/30 Tul. 90 kg/m3 8,464,344.43
56 1 M3 Beton Struktur Dudukan Kubah B4A 25/45 Tul. 251 kg/m3 10,286,419.32
57 1 M3 Beton Talang t = 15 cm Tul. 209 kg/m3 8,911,880.77
58 1 M3 Sirirp Talang T.12 cm Tul. 85 kg/m3 9,138,309.89
59 1 M3 Beton Sirip Vertikal t = 15 cm Tul. 76 kg/m3 7,789,453.76
60 1 M3 Kubah Beton t = 15 cm Tul. 282 kg/m3 10,406,867.41
61 1 M3 Plat Canopy t = 15/75 cm + Tali Air Tul. 125 kg/m3 7,191,622.17
62 1 M3 Frame Beton 15/25 Tul. 125 kg/m3 12,589,582.56
PEKERJAAN TANGGA
63 1 M3 Pondasi Plat t = 25 cm /Besi 139 kg/m3 5,102,521.94
64 1 M3 Pondasi Stump t = 20 /Besi 178 kg/m3 9,240,126.77
65 1 M3 Plat Tangga t = 15 cm /Besi 101 kg/m3 5,910,062.04
66 1 M3 Plat Bordes t = 15 cm /Besi 108 kg/m3 6,053,416.92
67 1 M3 Balok Bordes B3 20/30 /Besi 209 kg/m3 10,222,060.87
GROUND RESERVOAR
68 1 M3 Beton Plat lantai t = 20 cm Tul 127,490 kg/m3 4,356,021.75
69 1 M3 Beton Dinding t = 15 cm Tul 113,48 kg/m3 9,258,790.46
70 1 M3 Plat Beton Penutup Dinding Man Hole t = 12 cm Tul 141,95 kg/m3 11,181,821.39
71 1 M3 Beton Tutup Man Hole 0,7 x 0,8 x 0,1 Tul 129,77 kg/m3 8,817,735.81
72 1 M3 Balok Beton 20/30 Tul 213,95 kg/m3 7,726,081.35
73 1 M3 Kolom Struktur 15/15 Tul 213,95 kg/m3 6,733,552.58
BANGUNAN MENARA
74 1 M' Pondasi Bored Pile O 30cm ~ 10.00 M' Tul. 80 kg/m3 3,213,200.00
75 1 M3 Pondasi Poer - P6 (3x2x0,60 m3) Tul. 115 kg/m3 5,065,049.52
76 1 M3 Pondasi Poer - P8 (4x2x0,60 m3) Tul. 93 kg/m3 4,308,908.46
77 1 M3 Sloof 20/40 Tul. 120 kg/m3 5,734,983.42
78 1 M3 Kolom Stump 30/30 Tul. 118 kg/m3 8,571,697.01
79 1 M3 Kolom Struktur 30/30 Tul. 83 kg/m3 7,854,922.59
80 1 M3 Kolom Struktur 60/60 Tul. 164 kg/m3 7,223,600.99
81 1 M3 Balok Struktur B1 20/40 Tul. 151 kg/m3 8,950,416.19
82 1 M3 Balok Struktur B2 15/25 + 10/25 Tul. 147 kg/m3 10,962,568.72
83 1 M3 Balok Struktur B3 15/25 + 10/25 Tul. 147 kg/m3 10,962,568.72
84 1 M3 Balok Struktur B2' 15/25 Tul. 169 kg/m3 11,007,629.96
85 1 M3 Plat Lantai II t = 12 cm Tul. 136 kg/m3 8,181,107.89
86 1 M3 Kolom Struktur 60/60 Tul. 164 kg/m3 7,223,600.99
87 1 M3 Balok Struktur 20/40 Lantai II Tul. 151 kg/m3 9,034,263.26
88 1 M3 Balok Struktur 20/40 Lantai II Tul. 135 kg/m3 8,706,594.96
TEMPAT WUDHU
89 1 M3 Pondasi Plat 1,2 x 1,2 x 0,25 Tul. 143 kg/m3 5,070,931.50
90 1 M3 Sloof Praktis (0,15x0,20 m3) Tul 183 kg/m3 7,592,714.92
91 1 M3 Kolom Stump 30/30 Tul 190 kg/m3 9,282,823.59
92 1 M3 Kolom Stump 15/30 Tul 204 kg/m3 12,623,056.54
93 1 M3 Kolom Struktur 30/30 Tul 190 kg/m3 10,046,204.38
94 1 M3 Kolom Struktur 20/20 Tul 192 kg/m3 12,377,305.31
95 1 M3 Balok Struktur B1 25/40 Tul 187 kg/m3 8,988,944.25
96 1 M3 Balok Struktur B2 20/30 Tul 267kg/m3 11,617,147.08
97 1 M3 Balok Struktur BA1 20/30 Tul 192kg/m3 10,081,201.90
98 1 M3 Pelat Atap Dak T.15 cm Tul 116 kg/m3 8,535,736.27
99 1 M3 Pelat Atap Dak T.12 cm Tul 96 kg/m3 8,126,150.89
100 1 M3 Beton Lisplang 10/15 Tul 147 kg/m3 13,901,652.70
KANTOR PENGELOLA
101 1 M3 Pondasi Plat 1,4 x 1,4 x 0,3 Tul. 136 kg/m3 4,846,499.82
102 1 M3 Pondasi Plat 1,2 x 1,2 x 0,3 Tul. 143 kg/m3 5,070,931.50
103 1 M3 Pondasi Plat 1,0 x 1,0 x 0,30 Tul. 187 kg/m3 5,972,019.34
104 1 M3 Sloof Praktis (0,20x0,30 m3) Tul 183 kg/m3 7,025,177.37
105 1 M3 Kolom Stump 30/30 Tul 190 kg/m3 9,282,823.59
106 1 M3 Kolom Stump Ø 20 cm Tul 204 kg/m3 12,623,056.54
107 1 M3 Kolom Stump 20/20 Tul 192 kg/m3 12,377,305.31
108 1 M3 Kolom Struktur 30/30 Tul 190 kg/m3 10,046,204.38
109 1 M3 Kolom Struktur Ø 20 cm Tul 204 kg/m3 12,623,056.54
110 1 M3 Kolom Struktur 20/20 Tul 192 kg/m3 12,377,305.31
111 1 M3 Balok Struktur B1 25/40 Tul 187 kg/m3 8,988,944.25
112 1 M3 Balok Struktur B2 20/30 Tul 267kg/m3 11,617,147.08
113 1 M3 Balok Struktur BA1 20/30 Tul 192kg/m3 10,081,201.90
114 1 M3 Pelat Atap Dak T.12 cm Tul 96 kg/m3 8,740,528.96
115 Pemasangan 1 kg besi profil 24,258.43
116 Pemasangan 1 kg besi rangka kuda-kuda baja IWF 48,674.42
117 Pengerjaan 1 kg pekerjaan perakitan 796.64
118 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kamper samarinda Oven 19,444,731.58
119 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kayu kamper samarinda Oven 1,416,390.62
120 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kamper samarinda Oven 1,026,638.67
121 Pemasangan 1 m Kusen Aluminium ukuran 4" sek. YKK YBIC t = 1,35 mm Lengkap Assesoris 274,782.81
122 Pemasangan 1 m2 pintu alumunium strip lebar 8 cm 1,050,654.46
123 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3PP 156,953.19
124 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 5PP 149,646.81
125 Pemasangan 1 m2 dinding terawang (rooster) 15x15x15 campuran 1SP : 3PP 481,572.27
126 Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20 mm 117,333.64
127 Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20 mm 135,557.11
128 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 82,686.93
129 Pemasangan 1 m2 acian 62,800.03
130 Pemasangan 1 m' plesteran ban 1SP : 3PP lebar 10 cm 113,241.74
131 Pemasangan 1 m2 screeding plat dak beton / Self Leveling Floor MU 410 102,698.29
132 Pemasangan 1 m' plint ubin warna ukuran 10cm x 40cm 229,129.90
133 Pemasangan 1 m' stair nozing ukuran 10cm x 60cm 108,523.65
134 Pemasangan 1 m2 lantai ubin keramik ukuran 40cm x 40cm 266,955.15
135 Pemasangan 1 m2 lantai ubin keramik ukuran 40cm x 40cm (rock tile) 255,963.16
136 Pemasangan 1 m2 lantai granit tile ukuran 60cm x 60cm 401,827.00
137 Pemasangan 1 m2 dinding keramik 20cm x 40cm 380,841.91
138 Pemasangan 1 m2 dinding marmer ukuran 60cm x 60cm (mihrab) 1,161,270.21
139 Pemasangan 1 m2 dinding batu tempel Andesit 336,708.71
140 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60cm, plafond 170,307.34
141 Pemasangan 1 m2 langit-langit asbes semen, tebal 4mm 57,209.09
142 Pemasangan 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm, tebal 9 mm 72,591.44
143 Pemasangan 1 m' list langit-langit kayu profil 45,960.97
144 Pemasangan 1 m' list kangit-langit profil gypsum 62,908.75
145 Pemasangan 1 buah Body Kunci + Cylinder 529,696.58
146 Pemasangan 1 buah Body Kunci + Cylinder (KM/WC) 696,446.58
147 Pemasangan satu pasang engsel pintu 300,657.97
148 Pemasangan satu pasang Lever Hendle 429,457.97
149 Pemasangan satu pasang Flush Bolt 136,207.97
150 Pemasangan 1 buah Engsel Casement 85,430.22
151 Pemasangan 1 buah door closer 387,027.58
152 Pemasangan 1 buah Rambuncis 38,268.72
153 Pemasangan 1 m2 kaca tebal 5 mm 200,427.19
154 Pemasangan 1 m2 kaca es tebal 5 mm 132,981.81
155 Pengecetan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 76,327.53
156 Pengecetan 1 m2 tembok baru / Plapond Interior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup ) 38,427.23
157 Pengecetan 1 m2 tembok baru Interior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup ) 31,523.23
158 Pengecetan 1 m2 tembok baru Exterior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup ) 32,135.60
159 Finishing melamik 1 m2 351,551.16
160 Pengecatan 1 m2 permukaan besi secara manual sistem 3 lapis 102,906.07
161 Pemasangan 1 buah closet duduk/monoblock 4,060,153.87
162 Pemasangan 1 buah closet jongkok porslen 973,738.65
163 Pemasangan 1 buah urinoir 4,419,106.54
164 Pemasangan 1 buah wastafel meja 2,040,905.79
165 Pemasangan 1 buah wastafel gantung 1,062,025.79
166 Pemasangan 1 buah bak fibreglass vol 1 m3 588,750.72
167 Pemasangan 1 buah floor drain 126,197.72
168 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm 708,701.86
169 Pemasangan 1 buah kran diameter 1/2" atau 3/4" 309,404.63
170 Pemasangan 1 buah kran leher angsa diameter 1/2" atau 3/4" 848,754.63
171 Pemasangan 1 buah jet washer 414,054.63
172 Pemasangan 1 m' pipa PVC tipe AW diameter 1/2" 31,214.20
173 Pemasangan 1 m' pipa PVC tipe AW diameter 3/4" 35,126.50
174 Pemasangan 1 m' pipa PVC tipe AW diameter 1" 40,529.20
175 Pemasangan 1 m' pipa PVC tipe AW diameter 1,1/4" 50,542.83
176 Pemasangan 1 m' pipa PVC tipe AW diameter 1,5" 65,195.14
177 Pemasangan 1 m' pipa PVC tipe AW diameter 2" 95,236.02
178 Pemasangan 1 m' pipa PVC tipe AW diameter 2,5" 110,381.19
179 Pemasangan 1 m' pipa PVC tipe AW diameter 3" 136,789.22
180 Pemasangan 1 m' pipa PVC tipe AW diameter 4" 196,638.09
181 Pemasangan 1 m' pipa PVC tipe AW diameter 6" 381,121.67
182 Pemasangan 1 m' pipa PVC tipe AW diameter 8" 608,593.97
183 Pemasangan 1 m2 Coating Waterproofing 131,713.61
184 Pemasangan 1 m2 Lantai parquet 422,495.63
185 Pemasangan 1 m2 langit-langit Calsiboard t = 9 mm rangka hollow galvanis 165,609.71
186 Pemasangan 1 m2 Ornamen GRC t = 9 mm rangka hollow galvanis 831,613.28
187 Pemasangan 1 m3 Base Coarse CBR 80% Kelas A 805,988.43
188 Pemasangan 1 m2 Lapisan Hotmix T = 5 cm 177,776.18
189 Pemasangan 1 m2 Prime Coat 30,277.86
190 Pemasangan 1 m3 U-DITCH uk. 40x40 cm 8,739,437.12
191 Pemasangan 1 m3 U-DITCH uk. 40x40 cm 6,412,510.61
192 Pemasangan 1 m1 Pasangan Cansteen 15x30x60 cm 151,869.43

PEKERJAAN ELEKTRIKAL DAN MEKANIKAL

NO URAIAN PEKERJAAN SATUAN HARGA SATUAN

PEKERJAAN ELEKTRIKAL
1 Batrei Cadangan untuk lampu Kap.16, 30menit bh 689,810.39
2 Instalasi Kabel Ladder UK.30x10cm c/w asesoris,suppot&hanger m' 195,611.43
3 Instalasi Kabel Ladder UK.40x10cm c/w asesoris,suppot&hanger m' 208,316.43
4 Instalasi Kabel NYY 4 x 10mm2 + NYA 1 x 10mm2 m' 130,931.43
5 Instalasi Kabel NYY 4 x 16mm2 + NYA 1 x 16mm2 m' 152,298.93
6 Instalasi Kabel NYY 4 x 240mm2 + NYA 1 x 50mm2 m' 1,685,561.43
7 Instalasi Kabel NYY 4 x 25mm2 + NYA 1 x 16mm2 m' 240,078.93
8 Instalasi Kabel NYY 4 x 35mm2 + NYA 1 x 25mm2 m' 268,376.43
9 Instalasi Kabel NYY 4 x 4mm2 + NYA 1 x 4mm2 m' 76,530.93
10 Instalasi Kabel NYY 4 x 6mm2 + NYA 1 x 6mm2 m' 94,086.93
11 NYY 4 x 185mm2 + NYA 1 x 50mm2 1,685,500.00
12 Instalasi Kabel Tray UK.30x10cm c/w asesoris,suppot&hanger m' 299,500.00
13 Instalasi Kabel Tray UK.40x10cm c/w asesoris,suppot&hanger m' 352,600.00
14 Instalasi Kotak Kontak kabel NYM 3 x 2.5 mm2 + Conduit dia.20mm ttk 317,300.00
15 Instalasi Penerangan kabel NYM 3 x 2,5 mm2 + Conduit dia.20mm ttk 275,700.00
16 Instalasi Sakelar kabel NYM 2 x 2,5 mm2 + Conduit dia.20mm ttk 268,400.00
17 Kotak Kontak 1Fasa 250w ttk 42,300.00
18 Lampu Downlight LED 10W (E27) Recessed Mounted / RM bh 208,600.00
19 Lampu Exit Kap.10w c/w Batrei Cadangan Listrik bh 767,700.00
20 Lampu TL LED 2x16W Recessed Mounted / RM Cover Louvre M5 ttk 837,000.00
21 #REF! ttk 209,900.00
22 #REF! bh 1,453,800.00
23 Saklar Dua Arah 0 53,900.00
24 Saklar Ganda unit 46,900.00
25 Saklar Tunggal bh 43,500.00
26 Lampu TKO TL LED 2x16W Surface Mounted bh 536,700.00
27 #REF! bh 4,381,600.00
28 Penyambungan Daya PLN lkp SLO,UJL kVA 1,347,600.00
29 FRC 4x35mm2 + PVC∅50 mtr 790,900.00
30 Lampu PJU Solar Cell LED 60 tiang Hexagonal 9m + Pondasi bh 25,849,800.00
31 #REF! bh 27,004,800.00
32 Air Terminal Radius 120M c/w terminasi bh 17,739,300.00
33 Kabel BC 70 mm2 mtr 115,800.00
34 Grounding Rod dia 20mm unit 523,600.00
35 Bak Kontrol bh 573,800.00
36 Alarm Bell bh 438,100.00
37 Ceiling Speaker 3 watt bh 275,300.00
38 Indicator Lamp bh 302,200.00
39 Instalasi Titik Detector 2 x NYA 1,5 mm2+conduit 20mm bh 242,400.00
40 Instalasi Titik Speaker bh 194,500.00
41 Instalasi titik data dengan Kabel UTP cat 6 + HIC Ø 20 mm mtr 28,100.00
42 Instalasi titik stop kontak ttk 269,400.00
43 Instalasi titik data dengan Kabel UTP cat 6 + HIC Ø 20 mm ttk 434,100.00
44 Instalasi titik camera dengan Kabel UTP cat 6 + HIC Ø 20 mm ttk 861,400.00
45 Instalasi titik Telephone dengan Kabel UTP cat 6 + HIC Ø 20 mm ttk 861,400.00
46 Kabel Utama ke TB bh 68,900.00
47 Panel Control Fire Alarm 2 Loop unit 39,864,400.00
48 Koneksi titik grounding bh 883,200.00
49 Manual Break Glass bh 536,700.00
50 Terminal MDF-FA bh 998,700.00
51 Outlet data bh 92,000.00
52 Outlet data untuk telephone bh 92,000.00
53 Heat Detector bh 682,200.00
54 Smoke detector bh 738,800.00
55 Stop kontak bh 42,300.00
56 #REF! bh 8,816,900.00
57 Terminal Box TBF bh 2,673,400.00
58 Terminal Box Tata Suara bh 305,700.00
59 Panel MDF TS bh 883,200.00
60 #REF! bh 652,200.00
61 Volume Control bh 264,100.00
62 NVR kapasitas 16 channel bh 22,770,400.00
63 Monitor led 32 Inch bh 3,250,900.00
64 #REF! bh 1,044,900.00
65 IP CCTV camera 2 MP bh 2,418,000.00
66 LVMDP unit 257,322,879.00
67 PP - LIFT unit 11,322,795.00
68 SDP unit 30,825,080.00
69 LP/PP unit 8,231,300.00
70 PP,AC unit 7,602,100.00
71 PP-Booster unit 7,024,600.00
72 PP-Outdoor Unit unit 26,139,500.00
73 PP Utama Lift unit 36,958,125.00

PEKERJAAN MEKANIKAL
1 Air Trap bh 828,100.00
2 Automatic air vent Ø 25 mm bh 1,649,200.00
3 Check valve Ø 100 mm Cast iron, 300 Lbs, JIS 20 K bh 16,002,400.00
4 Check valve Ø 65mm bh 2,772,000.00
5 Check valve Ø 50mm bh 2,115,100.00
6 Flexible Joint Ø 65 mm bh 726,800.00
7 Flexible Joint Ø 50 mm bh 522,400.00
8 Gate Valve Ø 100 mm bh 4,390,600.00
9 Gate valve Ø 65mm Air Bersih bh 1,365,300.00
10 Gate valve Ø 50mm bh 576,700.00
11 Gate valve Ø 25 mm bh 256,900.00
12 Gate valve Ø 20mm bh 197,700.00
13 Gate valve Ø 15 mm bh 172,800.00
14 Kran Taman Ø 15 mm lengkap Pondasi bh 256,300.00
15 Strainer Ø 65mm bh 2,829,000.00
16 Anti Vortex Plate Ø 65 mm bh 404,000.00
17 Pipa bs sch 40 Ø 150 mm mtr 726,700.00
18 Pipa bs sch 40 Ø 100 mm mtr 430,900.00
19 Pipa bs sch 40 Ø 80 mm mtr 308,200.00
20 Pipa bs sch 40 Ø 65 mm mtr 273,100.00
21 Pipa galv medium Ø 20 mm mtr 70,900.00
22 Pipa galv medium Ø 15 mm mtr 55,700.00
23 Pipa Drainage PVC AW c/w isolasi mtr 181,700.00
24 Pipa Refregerant+ Isolasi mtr 442,000.00
25 Kabel control UTP cat 6+conduit dia 20mm mtr 66,400.00
26 Kabel power NYM 3x2,5 mm2 + conduit dia20mm ttk 659,800.00
27 Instalasi Listrik Exhaust Fan Dan saklar ttk 365,100.00
28 Pipa PPR PN 10 Ø 65 mm mtr 339,000.00
29 Pipa PPR PN 10 Ø 50 mm mtr 239,100.00
30 Pipa PPR PN 10 Ø 40 mm mtr 172,600.00
31 Pipa PPR PN 10 Ø 32 mm mtr 129,400.00
32 Pipa PPR PN 10 Ø 25 mm mtr 98,900.00
33 Pipa PPR PN 10 Ø 20 mm mtr 75,400.00
34 Pipa PPR PN 10 Ø 15 mm mtr 61,500.00
35 Pipa pvc aw Ø 150 mm mtr 292,700.00
36 Pipa pvc aw Ø 100 mm mtr 169,800.00
37 Pipa pvc aw Ø 80 mm mtr 125,100.00
38 Pipa pvc aw Ø 65 mm mtr 101,900.00
39 Pipa pvc aw Ø 50 mm mtr 83,112.22
40 Pipa pvc aw Ø 40 mm mtr 80,100.00
41 Pipa pvc d Ø 50 mm mtr 67,000.00
42 Pipa pvc d Ø 40 mm mtr 58,300.00
43 Pipa pvc d Ø 32 mm mtr 53,800.00
44 Bak Kontrol bh 708,700.00
45 Bak Kontrol Beton 800x500 bh 1,671,500.00
46 #REF! unit 68,120,800.00
47 Exhaust Fan 500 Cfm bh 13,047,700.00
48 Exhaust Fan 400 Cfm bh 2,897,500.00
49 Exhaust Fan 100 Cfm bh 713,000.00
50 Exhaust Fan 150 Cfm bh 713,005.86
51 EF Axial 400 cfm bh 2,897,572.86
52 Clean Out Dia 100 mm bh 269,500.00
53 Clean Out Dia 50 mm bh 211,800.00
54 #REF! bh 100,497,200.00
55 Roof Tank kap.8m3 bh 39,052,500.00
56 Roof drain Ø 100 mm bh 355,500.00
57 Roof drain Ø 80 mm bh 297,800.00
58 Exhaust Air Duct 150 x 150 bh 271,300.00
59 Exhaust Air Duct 200 x 200 bh 317,500.00
60 Exhaust Air Duct 100 x 100 bh 196,200.00
61 Exhaust Air Duct Ø 200 bh 288,600.00
62 Exhaust Air Duct Ø 250 bh 378,700.00
63 Fire Extinguisher DC Kap 6 kg, Standard NFPA International, dll bh 808,300.00
64 HP - Hydrant Pilar, Standard NFPA International, dll Lengkap, Accessories : 'Size 4' x 2 1/2' x 2 1/2' bh 4,215,600.00
65 Exhaust Air Duct Ø 100 bh 250,500.00
66 Exahaust Air Grille 150 x 150 mm bh 271,300.00
67 Exahaust Air Grille 250 x 250 mm bh 353,600.00
68 Louvre 350 x 350 mm bh 245,900.00
69 Louvre 200 x 200 mm bh 234,300.00
70 EF toilet 500 cfm bh 1,436,800.00
71 EF toilet 260 cfm bh 1,436,800.00
72 IHB - Indoor Hydrant Box Standard NFPA International, dll Lengkap, Accessories : bh 5,516,400.00
73 OHB - Outdoor Hydrant Box Standard NFPA International, dll Lengkap, Accessories : bh 3,206,400.00
74 SC - Siemese Connection Standard NFPA International, dll Lengkap, Accessories :Size 4' x 2 1/2' x 2 1/2' bh 2,859,900.00
75 Floating valve Ø 50 mm bh 257,300.00
76 Landing valve Ø 50 mm bh 657,100.00
77 Floor drain Dia 50 mm bh 198,600.00
78 Pressure Gauge bh 279,400.00
79 Keran Ø 15mm bh 198,600.00
80 V-Trap Dia 50 mm bh 94,600.00
81 Vent cap Ø 40 mm bh 77,300.00
82 AC Manager bh 72,854,100.00
83 IU Ceilling cassete 38.200 Btuh bh 12,816,800.00
84 Wall mounted 7.500 Btuh bh 6,614,400.00
85 Wall mounted 9.600 Btuh bh 6,810,800.00
86 Wall mounted 15400 Btuh bh 7,113,400.00
87 Wall mounted 24200 Btuh bh 9,525,000.00
88 IU Ceilling cassete 19.100 Btuh bh 26,746,100.00
89 IU Ceilling cassete 15.400 Btuh bh 10,287,300.00
90 IU Ceilling cassete 54.600 Btuh bh 14,676,300.00
91 IU Ceilling cassete 30.700 Btuh bh 11,615,600.00
92 OU 324.800 BTUH bh 196,335,200.00
93 OU 386.200 BTUH bh 372,542,000.00
94 OU 458.600 BTUH bh 270,024,200.00
95 OU 477.700 BTUH bh 281,204,600.00
96 Control Panel & Cable bh 5,944,500.00
97 Indoor Pipe BranchY-Branch bh 2,303,900.00
98 Remote bh 1,431,508.57
99 Pipe Size Reducer bh 1,239,800.00
100 Lift Penumpang bh 457,104,600.00
101 Sumur Dangkal , Pompa 1 PK , H 60mtr, Casing dia.100mm unit 28,022,100.00
102 Pompa Transfer Air Bersih unit 33,256,600.00
103 Instalasi Booster pump unit 134,770,100.00
104 Rooftank kap.8m3 unit 36,981,100.00

PEKERJAAN ARSITEKTUR

No. KODE Uraian Pekerjaan Harga Satuan

a b d

1 4.4.1.8 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3PP 136,811.28
2 4.4.1.10 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 5PP 129,822.57
3 4.4.2.14 Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20 mm 91,393.46
4 4.4.2.16 Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20 mm 106,283.61
5 4.4.2.23 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP 65,773.99
6 4.4.2.27 Pemasangan 1 m2 acian 48,456.73
7 4.4.1.22 Pemasangan 1 m2 dinding kerawang t : 5 1,778,316.49
8 4.2.1.11 Pemasangan 1 m Kusen Aluminium ukuran 4" sek. YKK YBIC t = 1,35 mm Lengkap Assesoris 258,120.44
9 4.2.1.12 Pemasangan 1 m2 pintu alumunium strip lebar 8 cm 3,003,810.66
10 4.4.3.13 Pemasangan 1 m2 lantai granit tile ukuran 60cm x 60cm 285,720.83
11 4.4.3.58 Pemasangan 1 m2 dinding batu tempel Andesit 233,024.19
12 4.2.1.10 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60cm, plafond 125,818.00
13 4.5.1.7 Pemasangan 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm, tebal 9 mm 63,484.54
14 4.5.1.7 Pemasangan 1 m2 langit-langit GRC ukuran (120 x 240 x 9) mm, tebal 4 mm 58,284.15
15 4.5.1.8 Pemasangan 1 m' list kangit-langit profil gypsum 49,275.41
16 4.6.2.4 Pemasangan 1 buah Body Kunci + Cylinder 331,911.80
17 4.6.2.3 Pemasangan 1 buah Body Kunci + Cylinder (KM/WC) 254,911.80
18 4.6.2.5 Pemasangan satu pasang engsel pintu 397,789.04
19 4.6.2.8 Pemasangan satu pasang Lever Hendle (handel pintu) 529,789.04
20 4.6.2.20 Pemasangan 1 m2 kaca tebal 5 mm 178,716.12
21 5.1.1.1 Pemasangan 1 buah closet duduk/monoblock 3,802,414.00
22 5.1.1.5 Pemasangan 1 buah wastafel meja 1,683,640.42
23 5.1.1.36 Pemasangan 1 buah floor drain 111,991.00
24 5.1.1.35 Pemasangan 1 buah kran leher angsa diameter 1/2" atau 3/4" 262,542.50
25 4.7.1.4 Pengecetan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup) 55,663.85
26 4.7.1.10 Pengecetan 1 m2 tembok baru / Plapond Interior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup ) 36,661.75
27 4.7.1.10 Pengecetan 1 m2 tembok baru Interior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup ) 24,982.86
28 4.7.1.10 Pengecetan 1 m2 tembok baru Exterior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup ) 24,893.76
29 4.6.1.3 Pembuatan dan Pemasangan 1 m' Kusen Kayu Klas II (Kamfer) 689,103.20
30 4.4.3.35 Pemasangan 1 m2 Lantai Keramik ukuran 30 x 30 cm 268,047.29
31 5.1.1.1 Pemasangan 1 buah closet duduk/monoblock 3,730,104.40
32 5.1.1.1 Pemasangan 1 buah closet duduk/monoblock Difable 3,730,104.40
33 5.1.1.5 Pemasangan 1 buah wastafel meja 1,660,673.55
34 5.1.1.35 Pemasangan 1 buah kran diameter 1/2" atau 3/4" 262,530.81
35 4.4.3.13 Pemasangan 1 m2 lantai granit tile ukuran 60cm x 60cm Warna 405,070.83
36 4.4.3.42 Pemasangan 1 m' stair nozing ukuran 10cm x 60cm 94,849.66
37 4.4.3.54 Pemasangan 1 m2 Keramik Dinding 345,801.75
38 4.4.1.22 Pemasangan 1 m2 dinding kerawang t : 3 1,527,994.71
39 A.4.4.3.58 Pekerjaan Pasangan Batu Andesit Bakar Hitam 20 x 40 cm 277,574.19
40 P2 Pekerjaan Pasangan Tembaga Kaligrafi + Arabesque (Custoom) 888,250.00
41 A.4.4.3.58 Pekerjaan Pasangan GRC Motif Batik Kesatrian (Custoom) 165,624.07
42 P1 Pekerjaan Pasangan Stainles steel Arabesque 1,402,500.00
by by Pekerjaan Pasangan Granit Slab Warna Putih (Motif Halus) 325,720.83
Perencana Perencana
43 A.1 Pekerjaan Pasang Atap Trimdek 280,500.00
44 A.2 Pekerjaan Pasangan Pagar Besi Hollow 365,000.00

PEKERJAAN LANSKAP

No. Uraian Pekerjaan Harga Satuan


a b c
1 Pekerjaan 1 m2 membersihkan Lapangan dan perataan m2 27,830.00
2 Penggalian 1 m3 tanah biasa sedalam 1 m m3 120,175.00
3 Pengurugan 1 m3 dengan pasir urug m3 266,813.80
4 Membuat 1 m3 lantai rabat beton mutu f'c = 7,4 Mpa (K175), slump (12 ± 2)cm, w/c = 0,85 m3 1,488,382.42
5 Membuat 1 m3 beton mutu f'c = 16,9 Mpa (K200),slump (12 ± 2) cm, w/c = 0,61 m3 1,526,914.01
6 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 5PP m2 129,822.57
7 Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20 mm m2 106,283.61
8 Pemasangan 1 m2 acian m2 48,456.73
9 Pemasangan 1 m2 Dinding Ciprat Putih m2 65,773.99
10 Pemasangan 1 m2 Dinding Koral Sikat Putih m2 168,319.52
11 Pemasangan 1 m2 Dinding batu Adesit bakar 10x20 cm m2 310,354.19
12 Pemasangan 1 m2 Lantai Batu Sikat/peralstone warna Krem m2 421,710.03
13 Pemasangan 1 m2 Lantai Batu Sikat/peralstone warna Abu Tua m2 421,710.03
14 Pemasangan 1 m2 Lantai Batu Adesit Bakar ukuran 15/30 cm m2 326,084.19
15 Pemasangan 1 m2 Lantai Batu Adesit Bakar Bintik ukuran 60/60 cm m2 356,499.19
16 Pemasangan 1 m2 Lantai Batu Templek m2 308,979.19
17 Pemasangan 1 m2 Lantai Paving Block Fullpave ukuran 200x200x80mm warna abu-abu m2 390,544.00
18 Pemasangan 1 m2 Lantai Paving Block Fullpave ukuran 100x200x80mm warna abu-abu m2 381,744.00
19 Pemasangan 1 m' Kastin Beton Pracetak ukuran 40x20x10 cm m' 200,950.86
20 Pemasangan 1 m2 Rangka Pergola Besi dia. 8mm , Jarak 20 cm Frame Pipa Galvanis dia. 2'' m2 621,665.00
21 Pemasangan 1 m2 Conwood deck 4'' uk. 300x100x25 mm m2 856,955.00
22 Pekerjaan Penanaman Rumput Gajah Mini m2 24,860.00
23 Pekerjaan Penanaman Kelapa Gading + Tertanam phn 239,552.50
24 Pekerjaan Penanaman Bambu Jepang (Bambusa Mutiplex) + Tertanam phn 355,052.50
25 Pekerjaan Penanaman Lontar (Bismarkia/Palem Perak)+ Tertanam phn 436,452.50
26 Pekerjaan Penanaman Trembesi (Samana Saman) + Tertanam phn 219,752.50
27 Pekerjaan Penanaman Liang Liu (Salix Babilonica) + Tertanam phn 311,052.50
28 Pekerjaan Penanaman Biola Cantik ( Ficus Lyrata) + Tertanam phn 588,252.50
29 Pekerjaan Penanaman Palem raja (Oreodoxa Regia) + Tertanam phn 630,052.50
30 Pekerjaan Penanaman Kamboja Bali + Tertanam phn 447,452.50
31 Pekerjaan Penanaman Dadap Merah (Erythrima Cristagali) + Tertanam phn 650,842.50
32 Pekerjaan Penanaman Sawo Kecik (Manilakara Kaukii) + Tertanam phn 196,652.50
33 Pekerjaan Penanaman Cycas Revoluta + Tertanam phn 245,052.50
34 Pekerjaan Penanaman Bungur Putih (Lagerstroemia Indica) + Tertanam phn 377,052.50
35 Pekerjaan Penanaman Cemara Laut + Tertanam phn 432,052.50
36 Pekerjaan Penanaman Boxwood + Tertanam phn 157,052.50
37 Pekerjaan Kursi Taman Tipe K1 unit 8,516,750.00
38 Pekerjaan Kursi Taman Tipe K2 unit 5,986,750.00
39 Pekerjaan Kursi Taman Tipe K3 unit 4,886,750.00
40 Pekerjaan Lampu Taman Tipe L1 unit 10,137,600.00
41 Pekerjaan Lampu Taman Tipe L2 unit 6,837,600.00
42 Pekerjaan Lampu Taman Tipe L3 unit 5,737,600.00
43 PEK. 1M² PEMBENTUKAN BADAN JALAN m2 21,531.83
44 PEK. 1M³ GALIAN DENGAN ALAT (MEKANIK) m3 62,042.50
45 PEK. 1M² URUGAN AGREGATE KASAR m2 334,642.81
46 PEK. 1 KG LAPIS RESAP PENGIKAT (PRIME COAT) kg 15,939.92
47 PEK. 1KG PEK. LAPIS PEREKAT TACK COAT kg 16,385.20
48 PEK. 1 TON LASTON LAPIS PONDASI PERATA (AC-BASE) ton 1,342,843.29
49 PEK. 1 TON LASTON LAPIS ANTARA (AC-BC) ton 1,356,564.11
50 PEK. 1 TON LASTON LAPIS AUS (AC-WC) ton 1,408,949.04
51 PEK. 1 M¹ SALURAN U-DITCH m1 840,650.00
52 PEK. 1 M¹ TUTUP SALURAN U-DITCH m1 557,750.00
53 PEK. 1 M¹ BUIS BETON DIA 60 CM m1 564,075.00
54 PEK. 1 BUAH BAK KONTROL bh 3,202,750.00
55 PEK. 1 M¹ KANSTEEN TYPE A m1 235,968.70
56 PEK. 1 M¹ KANSTEEN TYPE B m1 224,468.70
57 PEK. 1 M¹ PENGECATAN KANSTEEN m1 42,888.61
ANALISA HARGA SATUAN PEKERJAAN (AHSP)
LANSKAP
PEKERJAAN DED KAWASAN CIPUTRI BANTEN LAMA
APBD TAHUN ANGGARAN 2019

1 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.3000 120,000.00 36,000.00
Tukang Batu OH 0.1000 120,000.00 12,000.00
Kepala Tukang OH 0.0100 140,000.00 1,400.00
Mandor OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 51,650.00
B BAHAN
Semen PC Kg 4.3200 1,585.10 6,847.63
Pasir pasang m3 0.0060 216,150.00 1,296.90
JUMLAH HARGA BAHAN 8,144.53
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 59,794.53


E Overhead & Profit 10% x D 5,979.45
F Harga Satuan Pekerjaan (D+E) 65,773.99

2 Pemasangan 1 m2 Dinding Koral Sikat Putih


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.6200 120,000.00 74,400.00
Tukang Batu OH 0.3500 120,000.00 42,000.00
Kepala tukang OH 0.0350 140,000.00 4,900.00
Mandor OH 0.0300 150,000.00 4,500.00
JUMLAH TENAGA KERJA 125,800.00
B BAHAN
Koral Sikat Putih kg 1.6700 9,000.00 15,030.00
Semen Portland Kg 0.2350 1,585.10 372.50
HCL Ltr 0.5000 8,500.00 4,250.00
Pasir pasang m3 0.0350 216,150.00 7,565.25
JUMLAH HARGA BAHAN 27,217.75
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 153,017.75


E Overhead & Profit 10% x D 15,301.77
F Harga Satuan Pekerjaan (D+E) 168,319.52

3 Pemasangan 1 m2 Dinding batu Adesit bakar 10x20 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.6200 120,000.00 74,400.00
Tukang Batu OH 0.3500 120,000.00 42,000.00
Kepala tukang OH 0.0350 140,000.00 4,900.00
Mandor OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 121,750.00
B BAHAN
Batu Adesit bakar 10x20 cm m2 1.1000 122,000.00 134,200.00
Semen Portland Kg 11.7500 1,585.10 18,624.93
Pasir Pasang m3 0.0350 216,150.00 7,565.25
JUMLAH HARGA BAHAN 160,390.18
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 282,140.18


E Overhead & Profit 10% x D 28,214.02
F Harga Satuan Pekerjaan (D+E) 310,354.19
4 Pemasangan 1 m2 Lantai Batu Sikat/peralstone warna Krem
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 1.0000 120,000.00 120,000.00
Tukang batu OH 1.0000 120,000.00 120,000.00
JUMLAH TENAGA KERJA 240,000.00
B BAHAN
Batu Sikat/peralstone warna Abu Tua m2 1.0000 125,000.00 125,000.00
Semen Portland Kg 7.5000 1,585.10 11,888.25
Pasir Pasang m3 0.0300 216,150.00 6,484.50
JUMLAH HARGA BAHAN 143,372.75
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 383,372.75


E Overhead & Profit 10% x D 38,337.28
F Harga Satuan Pekerjaan (D+E) 421,710.03

5 Pemasangan 1 m2 Lantai Batu Sikat/peralstone warna Abu Tua


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 1.0000 120,000.00 120,000.00
Tukang batu OH 1.0000 120,000.00 120,000.00
JUMLAH TENAGA KERJA 240,000.00
B BAHAN
Batu Sikat/peralstone warna Abu Tua m2 1.0000 125,000.00 125,000.00
Semen Portland Kg 7.5000 1,585.10 11,888.25
Pasir Pasang m3 0.0300 216,150.00 6,484.50
JUMLAH HARGA BAHAN 143,372.75
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 383,372.75


E Overhead & Profit 10% x D 38,337.28
F Harga Satuan Pekerjaan (D+E) 421,710.03

6 Pemasangan 1 m2 Lantai Batu Adesit Bakar ukuran 15/30 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.6200 120,000.00 74,400.00
Tukang Batu OH 0.3500 120,000.00 42,000.00
Kepala tukang OH 0.0350 140,000.00 4,900.00
Mandor OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 121,750.00
B BAHAN
Batu Adesit Bakar ukuran 15/30 cm m2 1.1000 135,000.00 148,500.00
Semen Portland Kg 11.7500 1,585.10 18,624.93
Pasir Pasang m3 0.0350 216,150.00 7,565.25
JUMLAH HARGA BAHAN 174,690.18
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 296,440.18


E Overhead & Profit 10% x D 29,644.02
F Harga Satuan Pekerjaan (D+E) 326,084.19

7 Pemasangan 1 m2 Lantai Batu Adesit Bakar Bintik ukuran 60/60 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.6200 120,000.00 74,400.00
Tukang Batu OH 0.3500 120,000.00 42,000.00
Kepala tukang OH 0.0350 - -
Mandor OH 0.0030 - -
JUMLAH TENAGA KERJA 116,400.00
B BAHAN
Batu Adesit Bakar Bintik ukuran 60/60 cm m2 1.1000 165,000.00 181,500.00
Semen Portland Kg 11.7500 1,585.10 18,624.93
Pasir Pasang m3 0.0350 216,150.00 7,565.25
JUMLAH HARGA BAHAN 207,690.18
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 324,090.18


E Overhead & Profit 10% x D 32,409.02
F Harga Satuan Pekerjaan (D+E) 356,499.19

8 Pemasangan 1 m2 Lantai Batu Templek


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.7000 120,000.00 84,000.00
Tukang Batu OH 0.3500 120,000.00 42,000.00
Kepala tukang OH 0.0350 - -
Mandor OH 0.0030 - -
JUMLAH TENAGA KERJA 126,000.00
B BAHAN
Batu Templek m2 1.1000 117,000.00 128,700.00
Semen Portland Kg 11.7500 1,585.10 18,624.93
Pasir Pasang m3 0.0350 216,150.00 7,565.25
JUMLAH HARGA BAHAN 154,890.18
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 280,890.18


E Overhead & Profit 10% x D 28,089.02
F Harga Satuan Pekerjaan (D+E) 308,979.19

9 Pemasangan 1 m2 Lantai Paving Block Fullpave ukuran 200x200x80mm warna abu-abu


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 1.5000 120,000.00 180,000.00
Tukang Batu OH 0.2000 120,000.00 24,000.00
Kepala tukang OH 0.0200 - -
Mandor OH 0.0100 - -
JUMLAH TENAGA KERJA 204,000.00
B BAHAN
Paving Block Fullpave ukuran 200x200x80mm warna abu-abu m2 1.0000 132,000.00 132,000.00
Abu Batu m3 0.0800 238,000.00 19,040.00
JUMLAH HARGA BAHAN 151,040.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 355,040.00


E Overhead & Profit 10% x D 35,504.00
F Harga Satuan Pekerjaan (D+E) 390,544.00

10 Pemasangan 1 m2 Lantai Paving Block Fullpave ukuran 100x200x80mm warna abu-abu


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 1.5000 120,000.00 180,000.00
Tukang Batu OH 0.2000 120,000.00 24,000.00
Kepala tukang OH 0.0200 - -
Mandor OH 0.0100 - -
JUMLAH TENAGA KERJA 204,000.00
B BAHAN
Paving Block Fullpave ukuran 200x200x80mm warna abu-abu m2 1.0000 124,000.00 124,000.00
Abu Batu m3 0.0800 238,000.00 19,040.00
JUMLAH HARGA BAHAN 143,040.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 347,040.00
E Overhead & Profit 10% x D 34,704.00
F Harga Satuan Pekerjaan (D+E) 381,744.00

11 Pemasangan 1 m' Kastin Beton Pracetak ukuran 40x20x10 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.7000 120,000.00 84,000.00
Tukang Batu OH 0.3500 120,000.00 42,000.00
Kepala Tukang OH 0.0350 - -
Mandor OH 0.0350 - -
JUMLAH TENAGA KERJA 126,000.00
B BAHAN
Kastin Beton Pracetak ukuran 40x20x10 cm M2 1.6600 18,000.00 29,880.00
Portland cement Kg 6.0000 1,585.10 9,510.60
Pasir pasang m3 0.0800 216,150.00 17,292.00
JUMLAH HARGA BAHAN 56,682.60
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 182,682.60


E Overhead & Profit 10% x D 18,268.26
F Harga Satuan Pekerjaan (D+E) 200,950.86

12 Pemasangan 1 m2 Rangka Pergola Besi dia. 8mm , Jarak 20 cm Frame Pipa Galvanis dia. 2''
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.7000 120,000.00 84,000.00
Tukang Besi OH 0.3500 120,000.00 42,000.00
Kepala Tukang OH 0.0350 140,000.00 4,900.00
Mandor OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 136,150.00
B BAHAN
Besi dia. 8mm m' 12.0000 4,500.00 54,000.00
Pipa Galvanis dia. 2'' m' 8.0000 45,000.00 360,000.00
Perlengkapan Lot 1.0000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 429,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 565,150.00


E Overhead & Profit 10% x D 56,515.00
F Harga Satuan Pekerjaan (D+E) 621,665.00

13 Pemasangan 1 m2 Conwood deck 4'' uk. 300x100x25 mm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.7000 120,000.00 84,000.00
Tukang Kayu OH 0.3500 120,000.00 42,000.00
Kepala Tukang OH 0.0350 140,000.00 4,900.00
Mandor OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 136,150.00
B BAHAN
Conwood deck 4'' uk. 300x100x25 mm pack 3.2200 195,000.00 627,900.00
Perlengkapan Lot 1.0000 15,000.00 15,000.00
JUMLAH HARGA BAHAN 642,900.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 779,050.00


E Overhead & Profit 10% x D 77,905.00
F Harga Satuan Pekerjaan (D+E) 856,955.00

14 Pekerjaan Penanaman Rumput Gajah Mati


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.0400 120,000.00 4,800.00
Mandor OH 0.0040 150,000.00 600.00
JUMLAH TENAGA KERJA 5,400.00
B BAHAN
Rumput gajah mini M2 0.5000 32,000.00 16,000.00
Pupuk kandang Krg 0.0400 30,000.00 1,200.00
JUMLAH HARGA BAHAN 17,200.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,600.00


E Overhead & Profit 10% x D 2,260.00
F Harga Satuan Pekerjaan (D+E) 24,860.00

15 Pekerjaan Penanaman Kelapa Gading + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Kelapa Gading phn 1.0000 185,000.00 185,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
JUMLAH HARGA BAHAN 187,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 217,775.00


E Overhead & Profit 10% x D 21,777.50
F Harga Satuan Pekerjaan (D+E) 239,552.50

16 Pekerjaan Penanaman Bambu Jepang (Bambusa Mutiplex) + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Bambu Jepang (Bambusa Mutiplex) phn 1.0000 265,000.00 265,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 292,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 322,775.00


E Overhead & Profit 10% x D 32,277.50
F Harga Satuan Pekerjaan (D+E) 355,052.50

17 Pekerjaan Penanaman Lontar (Bismarkia/Palem Perak)+ Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Lontar (Bismarkia/Palem Perak) phn 1.0000 339,000.00 339,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 366,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 396,775.00


E Overhead & Profit 10% x D 39,677.50
F Harga Satuan Pekerjaan (D+E) 436,452.50

18 Pekerjaan Penanaman Trembesi (Samana Saman) + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Trembesi (Samana Saman) phn 1.0000 142,000.00 142,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 169,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 199,775.00


E Overhead & Profit 10% x D 19,977.50
F Harga Satuan Pekerjaan (D+E) 219,752.50

19 Pekerjaan Penanaman Liang Liu (Salix Babilonica) + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Liang Liu (Salix Babilonica) phn 1.0000 225,000.00 225,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 252,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 282,775.00


E Overhead & Profit 10% x D 28,277.50
F Harga Satuan Pekerjaan (D+E) 311,052.50

20 Pekerjaan Penanaman Biola Cantik ( Ficus Lyrata) + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Biola Cantik ( Ficus Lyrata) phn 1.0000 477,000.00 477,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 504,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 534,775.00


E Overhead & Profit 10% x D 53,477.50
F Harga Satuan Pekerjaan (D+E) 588,252.50

21 Pekerjaan Penanaman Palem raja (Oreodoxa Regia) + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Palem raja (Oreodoxa Regia) phn 1.0000 515,000.00 515,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 542,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 572,775.00


E Overhead & Profit 10% x D 57,277.50
F Harga Satuan Pekerjaan (D+E) 630,052.50

22 Pekerjaan Penanaman Kamboja Bali + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Kamboja Bali phn 1.0000 349,000.00 349,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 376,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 406,775.00


E Overhead & Profit 10% x D 40,677.50
F Harga Satuan Pekerjaan (D+E) 447,452.50

23 Pekerjaan Penanaman Dadap Merah (Erythrima Cristagali) + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Dadap Merah (Erythrima Cristagali) phn 1.0000 533,900.00 533,900.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 561,300.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 591,675.00


E Overhead & Profit 10% x D 59,167.50
F Harga Satuan Pekerjaan (D+E) 650,842.50

24 Pekerjaan Penanaman Sawo Kecik (Manilakara Kaukii) + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Sawo Kecik (Manilakara Kaukii) phn 1.0000 121,000.00 121,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 148,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 178,775.00


E Overhead & Profit 10% x D 17,877.50
F Harga Satuan Pekerjaan (D+E) 196,652.50

25 Pekerjaan Penanaman Cycas Revoluta + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Cycas Revoluta phn 1.0000 165,000.00 165,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 192,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 222,775.00


E Overhead & Profit 10% x D 22,277.50
F Harga Satuan Pekerjaan (D+E) 245,052.50

26 Pekerjaan Penanaman Bungur Putih (Lagerstroemia Indica) + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Bungur Putih (Lagerstroemia Indica) phn 1.0000 285,000.00 285,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 312,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 342,775.00


E Overhead & Profit 10% x D 34,277.50
F Harga Satuan Pekerjaan (D+E) 377,052.50

27 Pekerjaan Penanaman Cemara Laut + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Cemara Laut phn 1.0000 335,000.00 335,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 362,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 392,775.00


E Overhead & Profit 10% x D 39,277.50
F Harga Satuan Pekerjaan (D+E) 432,052.50

28 Pekerjaan Penanaman Boxwood + Tertanam


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2500 120,000.00 30,000.00
Mandor OH 0.0025 150,000.00 375.00
JUMLAH TENAGA KERJA 30,375.00
B BAHAN
Pohon Boxwood phn 1.0000 85,000.00 85,000.00
Pupuk kandang Krg 0.0800 30,000.00 2,400.00
Material bantu Lot 1.0000 25,000.00 25,000.00
JUMLAH HARGA BAHAN 112,400.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 142,775.00


E Overhead & Profit 10% x D 14,277.50
F Harga Satuan Pekerjaan (D+E) 157,052.50

29 Pekerjaan Pekerjaan Kursi Taman Tipe K1


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 2.0000 120,000.00 240,000.00
Tukang Besi OH 1.0000 120,000.00 120,000.00
Kepala Tukang OH 0.5000 140,000.00 70,000.00
Mandor OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 437,500.00
B BAHAN
Kursi Taman Tipe K1 unit 1.0000 6,800,000.00 6,800,000.00
Material bantu lot 1.0000 505,000.00 505,000.00
JUMLAH HARGA BAHAN 7,305,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 7,742,500.00


E Overhead & Profit 10% x D 774,250.00
F Harga Satuan Pekerjaan (D+E) 8,516,750.00

30 Pekerjaan Pekerjaan Kursi Taman Tipe K2


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 2.0000 120,000.00 240,000.00
Tukang Batu OH 1.0000 120,000.00 120,000.00
Kepala Tukang OH 0.5000 140,000.00 70,000.00
Mandor OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 437,500.00
B BAHAN
Kursi Taman Tipe K2 unit 1.0000 4,500,000.00 4,500,000.00
Material bantu lot 1.0000 505,000.00 505,000.00
JUMLAH HARGA BAHAN 5,005,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 5,442,500.00


E Overhead & Profit 10% x D 544,250.00
F Harga Satuan Pekerjaan (D+E) 5,986,750.00

31 Pekerjaan Pekerjaan Kursi Taman Tipe K3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 2.0000 120,000.00 240,000.00
Tukang Besi OH 1.0000 120,000.00 120,000.00
Kepala Tukang OH 0.5000 140,000.00 70,000.00
Mandor OH 0.0500 150,000.00 7,500.00
JUMLAH TENAGA KERJA 437,500.00
B BAHAN
Kursi Taman Tipe K3 unit 1.0000 3,500,000.00 3,500,000.00
Material bantu lot 1.0000 505,000.00 505,000.00
JUMLAH HARGA BAHAN 4,005,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 4,442,500.00


E Overhead & Profit 10% x D 444,250.00
F Harga Satuan Pekerjaan (D+E) 4,886,750.00

32 Pekerjaan Lampu Taman Tipe L1


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 3.0000 120,000.00 360,000.00
Tukang Listrik OH 1.5000 120,000.00 180,000.00
Kepala Tukang OH 0.9000 140,000.00 126,000.00
Mandor OH 0.3000 150,000.00 45,000.00
JUMLAH TENAGA KERJA 711,000.00
B BAHAN
Lampu type TLD 36 w 54 cool daylight unit 1.0000 7,500,000.00 7,500,000.00
uk. l..1200mm dia. 26 mm+ base penguat
Material bantu lot 1.0000 1,005,000.00 1,005,000.00
JUMLAH HARGA BAHAN 8,505,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 9,216,000.00


E Overhead & Profit 10% x D 921,600.00
F Harga Satuan Pekerjaan (D+E) 10,137,600.00

33 Pekerjaan Lampu Taman Tipe L2


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 3.0000 120,000.00 360,000.00
Tukang Listrik OH 1.5000 120,000.00 180,000.00
Kepala Tukang OH 0.9000 140,000.00 126,000.00
Mandor OH 0.3000 150,000.00 45,000.00
JUMLAH TENAGA KERJA 711,000.00
B BAHAN
Lampu type LED 2 x 50 w 54 cool daylight + base penguat unit 1.0000 4,500,000.00 4,500,000.00
Material bantu lot 1.0000 1,005,000.00 1,005,000.00
JUMLAH HARGA BAHAN 5,505,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 6,216,000.00


E Overhead & Profit 10% x D 621,600.00
F Harga Satuan Pekerjaan (D+E) 6,837,600.00

34 Pekerjaan Lampu Taman Tipe L3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 3.0000 120,000.00 360,000.00
Tukang Listrik OH 1.5000 120,000.00 180,000.00
Kepala Tukang OH 0.9000 140,000.00 126,000.00
Mandor OH 0.3000 150,000.00 45,000.00
JUMLAH TENAGA KERJA 711,000.00
B BAHAN
Lampu type LED 36 w 54 cool daylight + base penguat unit 1.0000 3,500,000.00 3,500,000.00
Material bantu lot 1.0000 1,005,000.00 1,005,000.00
JUMLAH HARGA BAHAN 4,505,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 5,216,000.00


E Overhead & Profit 10% x D 521,600.00
F Harga Satuan Pekerjaan (D+E) 5,737,600.00

35 PEK. 1M² PEMBENTUKAN BADAN JALAN


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.13 120,000.00 15,000.00
Mandor OH 0.13 150,000.00 18,750.00
JUMLAH TENAGA KERJA 33,750.00
B BAHAN
JUMLAH HARGA BAHAN -
C PERALATAN
Excavator Jam 1.00 426,750.00 426,750.00
Greader Jam 1.00 505,500.00 505,500.00
Vibro Roller Jam 1.00 438,250.00 438,250.00

JUMLAH HARGA ALAT 1,370,500.00


Jumlah (A+B+C) 1,404,250.00
D Volume pek. Dalam 1 Jam 75.00 18,723.33
E Overhead & Profit 15% x D 2,808.50
F Harga Satuan Pekerjaan (D+E) 21,531.83

36 PEK. 1M³ GALIAN DENGAN ALAT (MEKANIK)


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.15 120,000.00 18,000.00
Mandor OH 0.05 150,000.00 7,500.00

JUMLAH TENAGA KERJA 25,500.00


B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
Excavator Jam 0.07 426,750.00 28,450.00

JUMLAH HARGA ALAT 28,450.00


D Jumlah (A+B+C) 53,950.00
E Overhead & Profit 15% x D 8,092.50
F Harga Satuan Pekerjaan (D+E) 62,042.50

37 PEK. 1M² URUGAN AGREGATE KASAR


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.02 120,000.00 2,400.00
Mandor OH 0.02 150,000.00 3,000.00

JUMLAH TENAGA KERJA 5,400.00


B BAHAN
Agregate Kasar M³ 0.55 220,000.00 121,000.00
Agregate Halus M³ 0.60 235,000.00 141,000.00

JUMLAH HARGA BAHAN 262,000.00


C PERALATAN
Greader Jam 0.03 505,500.00 12,637.50
Vibro Roller Jam 0.03 438,250.00 10,956.25

JUMLAH HARGA ALAT 23,593.75


D Jumlah (A+B+C) 290,993.75
E Overhead & Profit 15% x D 43,649.06
F Harga Satuan Pekerjaan (D+E) 334,642.81

38 PEK. 1 KG LAPIS RESAP PENGIKAT (PRIME COAT)


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.01 120,000.00 600.00
Mandor OH 0.00 150,000.00 150.00

JUMLAH TENAGA KERJA 750.00


B BAHAN
Minyak Tanah Pertamina Liter 0.27 11,220.00 2,973.30
Aspal Emulsi M³ 0.85 11,000.00 9,350.00
JUMLAH HARGA BAHAN 12,323.30
C PERALATAN
Asphalt Sprayer Jam 0.0035 75,000.00 262.50
Compressor 4000-6500 L/M Jam 0.0030 175,000.00 525.00

JUMLAH HARGA ALAT 787.50


D Jumlah (A+B+C) 13,860.80
E Overhead & Profit 15% x D 2,079.12
F Harga Satuan Pekerjaan (D+E) 15,939.92

39 PEK. 1KG PEK. LAPIS PEREKAT TACK COAT


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.01 120,000.00 600.00
Mandor OH 0.00 150,000.00 150.00

JUMLAH TENAGA KERJA 750.00


B BAHAN
Minyak Tanah Pertamina Liter 0.28 11,220.00 3,085.50
Aspal Emulsi M³ 0.88 11,000.00 9,625.00

JUMLAH HARGA BAHAN 12,710.50


C PERALATAN
Asphalt Sprayer Jam 0.0035 75,000.00 262.50
Compressor 4000-6500 L/M Jam 0.0030 175,000.00 525.00

JUMLAH HARGA ALAT 787.50


D Jumlah (A+B+C) 14,248.00
E Overhead & Profit 15% x D 2,137.20
F Harga Satuan Pekerjaan (D+E) 16,385.20

40 PEK. 1 TON LASTON LAPIS PONDASI PERATA (AC-BASE)


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.30 120,000.00 36,000.00
Mandor OH 0.05 150,000.00 6,750.00

JUMLAH TENAGA KERJA 42,750.00


B BAHAN
Agregat Kasar 0.35 220,000.00 75,934.38
Agregat Halus 0.19 235,000.00 44,870.31
Pasir Beton 0.14 220,000.00 30,158.33
Aspal Drum 68.75 11,500.00 790,625.00
JUMLAH HARGA BAHAN 941,588.02
C PERALATAN
Asphalt Mixing Plant Jam 0.0301 4,950,000.00 149,096.39
Dump Truck 10-14 M3 Jam 0.0853 401,392.86 34,255.41
Vibro Roller Jam 0.0200 438,250.00 8,765.00
Asphalt Finisher Jam 0.0301 325,000.00 9,789.16
Wheel Loader 1.0-1.6 M3 Jam 0.0164 438,250.00 7,189.71
Generator Set Jam 0.0301 200,000.00 6,024.10

JUMLAH HARGA ALAT 183,351.80


D Jumlah (A+B+C) 1,167,689.82
E Overhead & Profit 15% x D 175,153.47
F Harga Satuan Pekerjaan (D+E) 1,342,843.29

41 PEK. 1 TON LASTON LAPIS ANTARA (AC-BC)


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.30 120,000.00 36,000.00
Mandor OH 0.05 150,000.00 6,750.00

JUMLAH TENAGA KERJA 42,750.00


B BAHAN
Agregat Kasar 0.31 220,000.00 68,933.33
Agregat Halus 0.29 235,000.00 68,110.83
Pasir Beton 0.12 220,000.00 25,850.00
Aspal Drum 68.75 11,500.00 790,625.00
JUMLAH HARGA BAHAN 953,519.17
C PERALATAN
Asphalt Mixing Plant Jam 0.0301 4,950,000.00 149,096.39
Dump Truck 10-14 M3 Jam 0.0853 401,392.86 34,255.41
Vibro Roller Jam 0.0200 438,250.00 8,765.00
Asphalt Finisher Jam 0.0301 325,000.00 9,789.16
Wheel Loader 1.0-1.6 M3 Jam 0.0164 438,250.00 7,189.71
Generator Set Jam 0.0301 200,000.00 6,024.10

JUMLAH HARGA ALAT 183,351.80


D Jumlah (A+B+C) 1,179,620.97
E Overhead & Profit 15% x D 176,943.15
F Harga Satuan Pekerjaan (D+E) 1,356,564.11

42 PEK. 1 TON LASTON LAPIS AUS (AC-WC)


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.30 120,000.00 36,000.00
Mandor OH 0.05 150,000.00 6,750.00

JUMLAH TENAGA KERJA 42,750.00


B BAHAN
Agregat Kasar 0.24 220,000.00 51,700.00
Agregat Halus 0.34 235,000.00 79,155.83
Abu Batu 0.10 - -
Pasir Beton 0.12 220,000.00 26,990.44
Aspal Drum 73.15 11,500.00 841,225.00
JUMLAH HARGA BAHAN 999,071.27
C PERALATAN
Asphalt Mixing Plant Jam 0.0301 4,950,000.00 149,096.39
Dump Truck 10-14 M3 Jam 0.0853 401,392.86 34,255.41
Vibro Roller Jam 0.0200 438,250.00 8,765.00
Asphalt Finisher Jam 0.0301 325,000.00 9,789.16
Wheel Loader 1.0-1.6 M3 Jam 0.0164 438,250.00 7,189.71
Generator Set Jam 0.0301 200,000.00 6,024.10

JUMLAH HARGA ALAT 183,351.80


D Jumlah (A+B+C) 1,225,173.07
E Overhead & Profit 15% x D 183,775.96
F Harga Satuan Pekerjaan (D+E) 1,408,949.04

43 PEK. 1 M¹ SALURAN U-DITCH


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.50 120,000.00 60,000.00
Mandor OH 0.10 150,000.00 15,000.00

JUMLAH TENAGA KERJA 75,000.00


B BAHAN
U-Ditch Bh 1.00 641,000.00 641,000.00

JUMLAH HARGA BAHAN 641,000.00


C PERALATAN

Alat Bantu Pemasangan Ls 1.0000 15,000.00 15,000.00

JUMLAH HARGA ALAT 15,000.00


D Jumlah (A+B+C) 731,000.00
E Overhead & Profit 15% x D 109,650.00
F Harga Satuan Pekerjaan (D+E) 840,650.00
44 PEK. 1 M¹ TUTUP SALURAN U-DITCH
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.25 120,000.00 30,000.00
Mandor OH 0.05 150,000.00 7,500.00

JUMLAH TENAGA KERJA 37,500.00


B BAHAN
Cover U-Ditch Bh 2.00 220,000.00 440,000.00

JUMLAH HARGA BAHAN 440,000.00


C PERALATAN

Alat Bantu Pemasangan Ls 1.0000 7,500.00 7,500.00

JUMLAH HARGA ALAT 7,500.00


D Jumlah (A+B+C) 485,000.00
E Overhead & Profit 15% x D 72,750.00
F Harga Satuan Pekerjaan (D+E) 557,750.00

45 PEK. 1 M¹ BUIS BETON DIA 60 CM


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.65 120,000.00 78,000.00
Mandor OH 0.10 150,000.00 15,000.00

JUMLAH TENAGA KERJA 93,000.00


B BAHAN
Buis Beton Dia 60 cm Bh 1.20 325,000.00 390,000.00

JUMLAH HARGA BAHAN 390,000.00


C PERALATAN

Alat Bantu Pemasangan Ls 1.0000 7,500.00 7,500.00

JUMLAH HARGA ALAT 7,500.00


D Jumlah (A+B+C) 490,500.00
E Overhead & Profit 15% x D 73,575.00
F Harga Satuan Pekerjaan (D+E) 564,075.00

46 PEK. 1 BUAH BAK KONTROL


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 2.00 120,000.00 240,000.00
Mandor OH 0.25 150,000.00 37,500.00

JUMLAH TENAGA KERJA 277,500.00


B BAHAN
Bak Kontrol Bh 1.00 2,500,000.00 2,500,000.00

JUMLAH HARGA BAHAN 2,500,000.00


C PERALATAN

Alat Bantu Pemasangan Ls 1.0000 7,500.00 7,500.00

JUMLAH HARGA ALAT 7,500.00


D Jumlah (A+B+C) 2,785,000.00
E Overhead & Profit 15% x D 417,750.00
F Harga Satuan Pekerjaan (D+E) 3,202,750.00

47 PEK. 1 M¹ KANSTEEN TYPE A


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.15 120,000.00 18,000.00
Tukang Batu OH 0.15 120,000.00 18,000.00
Kepala Tukang OH 0.08 140,000.00 10,500.00
Mandor OH 0.05 150,000.00 7,500.00

JUMLAH TENAGA KERJA 54,000.00


B BAHAN
Kasteen Type A M² 2.0000 60,000.00 120,000.00
Semen Portland Kg 11.7500 1,585.10 18,624.93
Pasir Pasang m3 0.0350 216,150.00 7,565.25

JUMLAH HARGA BAHAN 146,190.18


C PERALATAN
Alat Bantu Pemasangan Ls 1.0000 5,000.00 5,000.00

JUMLAH HARGA ALAT 5,000.00


D Jumlah (A+B+C) 205,190.18
E Overhead & Profit 15% x D 30,778.53
F Harga Satuan Pekerjaan (D+E) 235,968.70

48 PEK. 1 M¹ KANSTEEN TYPE B


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.15 120,000.00 18,000.00
Tukang Batu OH 0.15 120,000.00 18,000.00
Kepala Tukang OH 0.08 140,000.00 10,500.00
Mandor OH 0.05 150,000.00 7,500.00

JUMLAH TENAGA KERJA 54,000.00


B BAHAN
Kasteen Type B M² 2.0000 55,000.00 110,000.00
Semen Portland Kg 11.7500 1,585.10 18,624.93
Pasir Pasang m3 0.0350 216,150.00 7,565.25

JUMLAH HARGA BAHAN 136,190.18


C PERALATAN
Alat Bantu Pemasangan Ls 1.0000 5,000.00 5,000.00

JUMLAH HARGA ALAT 5,000.00


D Jumlah (A+B+C) 195,190.18
E Overhead & Profit 15% x D 29,278.53
F Harga Satuan Pekerjaan (D+E) 224,468.70

49 PEK. 1 M¹ PENGECATAN KANSTEEN


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.07 120,000.00 7,800.00
Tukang Cat OH 0.07 120,000.00 7,800.00
Mandor OH 0.01 150,000.00 750.00

JUMLAH TENAGA KERJA 16,350.00


B BAHAN
Cat Tenokote Kg 0.5000 38,888.89 19,444.44

JUMLAH HARGA BAHAN 19,444.44


C PERALATAN
Alat Bantu Pemasangan Ls 1.0000 1,500.00 1,500.00

JUMLAH HARGA ALAT 1,500.00


D Jumlah (A+B+C) 37,294.44
E Overhead & Profit 15% x D 5,594.17
F Harga Satuan Pekerjaan (D+E) 42,888.61
ANALISA HARGA SATUAN PEKERJAAN
PEKERJAAN DED JPO PARIAMAN
TAHUN ANGGARAN 2021

1 Pengukuran dan pemasangan 1 m’ Bouwplank


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.10 132,000.00 13,200.00
Tukang Kayu OH 0.10 188,571.44 18,857.14
Kepala Tukang OH 0.01 200,000.00 2,000.00
Mandor OH 0.01 220,000.00 1,100.00
JUMLAH TENAGA KERJA 35,157.14
B BAHAN
Kayu balok 5/7 M3 0.01 3,386,350.00 40,636.20
Paku 2”-3” Kg 0.02 27,703.00 554.06
Kayu papan 3/20 M3 0.01 3,386,350.00 23,704.45
JUMLAH HARGA BAHAN 64,894.71
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 100,051.85


E Overhead & Profit 15% x D 15,007.78
F Harga Satuan Pekerjaan (D+E) 115,059.63

2 1 m2 PEMBUATAN GUDANG SEMENTARA DAN ALAT - ALAT


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A BAHAN
1 Dolken kayu dia. 8 - 10/400 cm btg 1.70 50,003.00 85,005.10
2 Kayu kelas III m3 0.21 3,200,000.00 672,000.00
3 Paku kg 0.30 22,749.00 6,824.70
4 Semen portland kg 10.50 1,585.10 16,643.55
5 Pasir beton m3 0.03 396,275.00 11,888.25
6 Koral beton m3 0.05 198,600.00 9,930.00
7 Seng gelombang lbr 1.50 70,900.00 106,350.00
8 Seng plat lbr 0.25 70,900.00 17,725.00
B TENAGA -
1 Pekerja Oh 1.00 132,000.00 132,000.00
2 Tukang kayu kasar Oh 2.00 188,571.44 377,142.88
3 Kepala tukang Oh 0.20 200,000.00 40,000.00
4 Mandor Oh 0.05 220,000.00 11,000.00
C PERALATAN - -

D Jumlah (A+B+C) 1,486,509.48


E Overhead & Profit 15% x D 222,976.42
F Harga Satuan Pekerjaan (D+E) 1,709,485.90

2 1 m2 1 m2 PEMBUATAN KANTOR SEMENTARA DGN LANTAI PLESTERAN


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A BAHAN
1 Dolken kayu dia. 8 - 10/400 cm btg 1.25 50,003.00 62,503.75
2 Kayu kelas III m3 0.18 3,200,000.00 576,000.00
3 Paku kg 0.08 22,749.00 1,819.92
4 Besi strip kg 1.10 14,122.00 15,534.20
5 Semen portland kg 35.00 1,585.10 55,478.50
6 Pasir pasang m3 0.15 216,150.00 32,422.50
7 Pasir beton m3 0.10 396,275.00 39,627.50
8 Koral beton m3 0.15 331,430.00 49,714.50
9 Bata merah bh 30.00 590.00 17,700.00
10 Seng Plat lbr 0.25 70,900.00 17,725.00
11 Jendela naco bh 0.20 70,900.00 14,180.00
12 Kaca polos, t = 5 mm m2 0.08 126,448.00 10,115.84
13 Kunci tanam bh 0.15 91,000.00 13,650.00
14 Plywood 4 mm lbr 0.06 152,468.00 9,148.08
B TENAGA -
1 Pekerja Oh 1.00 132,000.00 132,000.00
2 Tukang kayu kasar Oh 2.00 188,571.44 377,142.88
3 Kepala tukang Oh 0.20 200,000.00 40,000.00
4 Mandor Oh 0.05 220,000.00 11,000.00
C PERALATAN -

D Jumlah (A+B+C) 1,475,762.67


E Overhead & Profit 15% x D 221,364.40
F Harga Satuan Pekerjaan (D+E) 1,697,127.07

2 Pekerjaan 1 m' Pagar Sementara dari seng gelombang tinggi 2 m


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.20 132,000.00 26,400.00
Tukang Kayu OH 0.40 188,571.44 75,428.58
Kepala Tukang OH 0.02 200,000.00 4,000.00
Mandor OH 0.02 220,000.00 4,400.00
JUMLAH TENAGA KERJA 110,228.58
B BAHAN
Dolken kayu dia 8 - 10/400 cm btg 1.25 50,003.00 62,503.75
Semen portland zak 0.05 1,585.10 79.26
Pasir beton m3 0.01 396,275.00 1,981.38
Koral beton m3 0.01 198,600.00 1,787.40
kayu 5/7 m3 0.07 3,200,000.00 230,400.00
Paku biasa 2" - 5" kg 0.06 22,749.00 1,364.94
Seng gelombang lbr 1.20 70,900.00 85,080.00
Meni besi kg 0.45 33,864.00 15,238.80
JUMLAH HARGA BAHAN 398,435.52
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 508,664.10


E Overhead & Profit 15% x D 76,299.61
F Harga Satuan Pekerjaan (D+E) 584,963.71

3 Pekerjaan 1 m2 membersihkan Lapangan dan perataan


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.10 132,000.00 13,200.00
Mandor OH 0.05 220,000.00 11,000.00
JUMLAH TENAGA KERJA 24,200.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 24,200.00


E Overhead & Profit 15% x D 3,630.00
F Harga Satuan Pekerjaan (D+E) 27,830.00

4 Penggalian 1 m3 tanah biasa sedalam 1 m


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.75 132,000.00 99,000.00
Mandor OH 0.03 220,000.00 5,500.00
JUMLAH TENAGA KERJA 104,500.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 104,500.00


E Overhead & Profit 15% x D 15,675.00
F Harga Satuan Pekerjaan (D+E) 120,175.00

5 Penggalian 1 m3 tanah biasa sedalam 2 m


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.90 132,000.00 118,800.00
Mandor OH 0.05 220,000.00 9,900.00
JUMLAH TENAGA KERJA 128,700.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 128,700.00


E Overhead & Profit 15% x D 19,305.00
F Harga Satuan Pekerjaan (D+E) 148,005.00

6 Pengurugan kembali 1 m3 galian tanah


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.50 132,000.00 66,000.00
Mandor OH 0.05 220,000.00 11,000.00
JUMLAH TENAGA KERJA 77,000.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 77,000.00


E Overhead & Profit 15% x D 11,550.00
F Harga Satuan Pekerjaan (D+E) 88,550.00

7 Pemadatan tanah 1 m3 tanah ( per 20 cm )


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.50 132,000.00 66,000.00
Mandor OH 0.05 220,000.00 11,000.00
JUMLAH TENAGA KERJA 77,000.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 77,000.00


E Overhead & Profit 15% x D 11,550.00
F Harga Satuan Pekerjaan (D+E) 88,550.00

8 Pengurugan 1 m3 dengan tanah urug


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.30 132,000.00 39,600.00
Mandor OH 0.01 220,000.00 2,200.00
JUMLAH TENAGA KERJA 41,800.00
B BAHAN
Tanah Urug m3 1.20 79,255.00 95,106.00
JUMLAH HARGA BAHAN 95,106.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 136,906.00


E Overhead & Profit 15% x D 20,535.90
F Harga Satuan Pekerjaan (D+E) 157,441.90

9 Pengurugan 1 m3 dengan pasir urug


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.30 132,000.00 39,600.00
Mandor OH 0.01 220,000.00 2,200.00
JUMLAH TENAGA KERJA 41,800.00
B BAHAN
Pasir urug M3 1.20 158,510.00 190,212.00
JUMLAH HARGA BAHAN 190,212.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 232,012.00


E Overhead & Profit 15% x D 34,801.80
F Harga Satuan Pekerjaan (D+E) 266,813.80

10 Pengeboran 1 m Tanah
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Operator alat berat OH 0.46 132,000.00 60,060.00
Mandor OH 0.07 220,000.00 15,400.00
JUMLAH TENAGA KERJA 75,460.00
B BAHAN

JUMLAH HARGA BAHAN -


C PERALATAN
Bor mesin dia 60 cm jam 0.19 450,000.00 84,375.00
Alat Bantu ls 1.00 60,000.00 60,000.00
JUMLAH HARGA ALAT 144,375.00

D Jumlah (A+B+C) 219,835.00


E Overhead & Profit 15% x D 32,975.25
F Harga Satuan Pekerjaan (D+E) 252,810.25

11 Pemasangan 1 m3 pondasi batu belah campuran 1SP:3PP


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.50 132,000.00 198,000.00
Tukang Batu OH 0.75 188,571.44 141,428.58
Kepala Tukang OH 0.08 200,000.00 15,000.00
Mandor OH 0.08 220,000.00 16,500.00
JUMLAH TENAGA KERJA 370,928.58
B BAHAN
Batu belah M3 1.20 268,550.00 322,260.00
Semen Portlan Kg 202.00 1,585.10 320,190.20
Pasir Pasang M3 0.49 216,150.00 104,832.75
JUMLAH HARGA BAHAN 747,282.95
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,118,211.53


E Overhead & Profit 15% x D 167,731.73
F Harga Satuan Pekerjaan (D+E) 1,285,943.26

12 Pemasangan 1 m3 pondasi batu belah campuran 1SP:5PP


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.50 132,000.00 198,000.00
Tukang Batu OH 0.75 188,571.44 141,428.58
Kepala Tukang OH 0.08 200,000.00 27,193.50
Mandor OH 0.08 220,000.00 16,500.00
JUMLAH TENAGA KERJA 383,122.08
B BAHAN
Batu belah M3 1.20 268,550.00 322,260.00
Semen Portlan Kg 136.00 1,585.10 215,573.60
Pasir Pasang M3 0.54 216,150.00 117,585.60
JUMLAH HARGA BAHAN 655,419.20
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,038,541.28


E Overhead & Profit 15% x D 155,781.19
F Harga Satuan Pekerjaan (D+E) 1,194,322.47

13 Pemasangan 1 m3 batu kosong anstamping


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.78 132,000.00 102,960.00
Tukang Batu OH 0.39 188,571.44 73,542.86
Kepala Tukang OH 0.04 200,000.00 7,800.00
Mandor OH 0.04 220,000.00 8,580.00
JUMLAH TENAGA KERJA 192,882.86
B BAHAN
Batu belah M3 1.20 268,550.00 322,260.00
Pasir urug M3 0.43 158,510.00 68,476.32
JUMLAH HARGA BAHAN 390,736.32
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 583,619.18


E Overhead & Profit 15% x D 87,542.88
F Harga Satuan Pekerjaan (D+E) 671,162.06

14 Membuat 1 m3 lantai kerja beton mutu f'c = 7,4 Mpa (K100), slump (3-6) cm, w/c = 0,87
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.20 132,000.00 158,400.00
Tukang Batu OH 0.20 188,571.44 37,714.29
Kepala Tukang OH 0.02 200,000.00 4,000.00
Mandor OH 0.06 220,000.00 13,200.00
JUMLAH TENAGA KERJA 213,314.29
B BAHAN
Semen Portland Kg 230.00 1,585.10 364,573.00
Pasir Beton M3 0.64 396,275.00 252,766.84
Kerikil M3 0.76 338,635.00 257,613.44
(Maks 30mm)
Air Liter 200.00 50.00 10,000.00
JUMLAH HARGA BAHAN 884,953.28
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,098,267.57


E Overhead & Profit 15% x D 164,740.14
F Harga Satuan Pekerjaan (D+E) 1,263,007.70

15 Membuat 1 m3 beton mutu f'c = 14.5 Mpa (K175), slump (12 ± 2)cm, w/c = 0,85
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.65 132,000.00 217,800.00
Tukang Batu OH 0.28 188,571.44 51,857.15
Kepala Tukang OH 0.03 200,000.00 5,600.00
Mandor OH 0.08 220,000.00 18,260.00
JUMLAH TENAGA KERJA 293,517.15
B BAHAN
Semen Portland Kg 326.00 1,585.10 516,742.60
Pasir Beton M3 0.54 396,275.00 215,120.71
Kerikil M3 0.76 338,635.00 258,115.12
(Maks 30mm)
Air Liter 215.00 50.00 10,750.00
JUMLAH HARGA BAHAN 1,000,728.44
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,294,245.58


E Overhead & Profit 15% x D 194,136.84
F Harga Satuan Pekerjaan (D+E) 1,488,382.42

16 Membuat 1 m3 beton mutu f'c = 16,9 Mpa (K200),slump (12 ± 2) cm, w/c = 0,61
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.65 132,000.00 217,800.00
Tukang Batu OH 0.28 188,571.44 51,857.15
Kepala Tukang OH 0.03 200,000.00 5,600.00
Mandor OH 0.08 220,000.00 18,260.00
JUMLAH TENAGA KERJA 293,517.15
B BAHAN
Semen Portland Kg 352.00 1,585.10 557,955.20
Pasir Beton M3 0.52 396,275.00 206,912.16
Kerikil M3 0.76 338,635.00 258,616.80
(Maks 30mm)
Air Liter 215.00 50.00 10,750.00
JUMLAH HARGA BAHAN 1,034,234.16
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,327,751.31


E Overhead & Profit 15% x D 199,162.70
F Harga Satuan Pekerjaan (D+E) 1,526,914.01

17 Membuat 1 m3 beton mutu f'c = 19,3 Mpa (K225), slump (12 ± 2) cm, w/c = 0,58
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.65 132,000.00 217,800.00
Tukang Batu OH 0.28 188,571.44 51,857.15
Kepala Tukang OH 0.03 200,000.00 5,600.00
Mandor OH 0.08 220,000.00 18,260.00
JUMLAH TENAGA KERJA 293,517.15
B BAHAN
Semen Portland Kg 371.00 1,585.10 588,072.10
Pasir Beton M3 0.50 396,275.00 197,571.39
Kerikil (Maks 30mm) M3 0.78 338,635.00 262,630.26
Air Liter 215.00 50.00 10,750.00
JUMLAH HARGA BAHAN 1,059,023.75
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,352,540.89


E Overhead & Profit 15% x D 202,881.13
F Harga Satuan Pekerjaan (D+E) 1,555,422.03

18 Membuat 1 m3 beton f'c = 21,7 Mpa (K300),slump (12 ± 2) cm, w/c = 0,56
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.65 132,000.00 217,800.00
Tukang Batu OH 0.28 188,571.44 51,857.15
Kepala Tukang OH 0.03 200,000.00 5,600.00
Mandor OH 0.08 220,000.00 18,260.00
JUMLAH TENAGA KERJA 293,517.15
B BAHAN
Semen Portland Kg 384.00 1,585.10 608,678.40
Pasir Beton M3 0.49 396,275.00 195,873.07
Kerikil M3 0.77 338,635.00 260,623.53
(Maksimum 30mm)
Air Liter 215.00 50.00 10,750.00
JUMLAH HARGA BAHAN 1,075,925.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,369,442.15


E Overhead & Profit 15% x D 205,416.32
F Harga Satuan Pekerjaan (D+E) 1,574,858.47

19 Membuat 1 m3 beton Ready Mix K-300


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.00 132,000.00 132,000.00
Tukang Batu OH 0.25 188,571.44 47,142.86
Kepala Tukang OH 0.03 200,000.00 5,000.00
Mandor OH 0.10 220,000.00 22,000.00
JUMLAH TENAGA KERJA 206,142.86
B BAHAN
Campuran Beton Ready Mix K-300 m3 1.02 1,208,600.00 1,232,772.00
JUMLAH HARGA BAHAN 1,232,772.00
C PERALATAN
Pompa dan Conveyor beton sewa/hari 0.12 668,500.00 80,220.00
JUMLAH HARGA ALAT 80,220.00

D Jumlah (A+B+C) 1,519,134.86


E Overhead & Profit 15% x D 227,870.23
F Harga Satuan Pekerjaan (D+E) 1,747,005.09
20 Pembesian 10 kg dengan besi polos atau besi ulir
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.07 132,000.00 9,240.00
Tukang Besi OH 0.07 188,571.44 13,200.00
Kepala Tukang OH 0.01 200,000.00 1,400.00
Mandor OH 0.00 220,000.00 880.00
JUMLAH TENAGA KERJA 24,720.00
B BAHAN
Besi beton Kg 10.50 14,122.00 148,281.00
(polos/ulir)
Kawat beton Kg 0.15 33,864.00 5,079.60
JUMLAH HARGA BAHAN 153,360.60
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 178,080.60


E Overhead & Profit 15% x D 26,712.09
F Harga Satuan Pekerjaan (D+E) 204,792.69
G Harga Satuan Pekerjaan (D+E) Per 1 Kg 20,479.27

21 Pemasangan 1 m2 bekisting untuk pondasi


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.52 132,000.00 68,640.00
Tukang Kayu OH 0.26 188,571.44 49,028.57
Kepala Tukang OH 0.03 200,000.00 5,200.00
Mandor OH 0.03 220,000.00 5,720.00
JUMLAH TENAGA KERJA 128,588.57
B BAHAN
Kayu kelas III (50 %) M3 0.02 524,000.00 10,480.00
Paku 5 – 10 cm Kg 0.30 22,749.00 6,824.70
Minyak bekisting Liter 0.10 8,500.00 850.00
JUMLAH HARGA BAHAN 18,154.70
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 146,743.27


E Overhead & Profit 15% x D 22,011.49
F Harga Satuan Pekerjaan (D+E) 168,754.77

22 Pemasangan 1 m2 bekisting untuk sloof


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.52 132,000.00 68,640.00
Tukang Kayu OH 0.26 188,571.44 49,028.57
Kepala Tukang OH 0.03 200,000.00 5,200.00
Mandor OH 0.03 220,000.00 5,720.00
JUMLAH TENAGA KERJA 128,588.57
B BAHAN
Kayu kelas III (50%) M3 0.02 524,000.00 11,790.00
Paku 5 cm – 10 cm Kg 0.30 22,749.00 6,824.70
Minyak bekisting Liter 0.10 8,500.00 850.00
JUMLAH HARGA BAHAN 19,464.70
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 148,053.27


E Overhead & Profit 15% x D 22,207.99
F Harga Satuan Pekerjaan (D+E) 170,261.27

23 Pemasangan 1 m2 bekisting untuk kolom


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.66 132,000.00 87,120.00
Tukang Kayu OH 0.33 188,571.44 62,228.58
Kepala Tukang OH 0.03 200,000.00 6,600.00
Mandor OH 0.03 220,000.00 7,260.00
JUMLAH TENAGA KERJA 163,208.58
B BAHAN
Kayu kelas III (50%) M3 0.02 524,000.00 10,480.00
Paku 5 cm – 12 cm Kg 0.40 21,344.00 8,537.60
Minyak bekisting Liter 0.20 8,500.00 1,700.00
Balok kayu kelas II (50%) M3 0.01 3,386,350.00 25,397.63
Plywood tebal 9 mm (50%) Lbr 0.18 225,071.00 39,387.43
Dolken kayu galam, Batang 1.00 50,003.00 50,003.00
8–10 cm panjang 4 m (50%)
JUMLAH HARGA BAHAN 135,505.65
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 298,714.23


E Overhead & Profit 15% x D 44,807.13
F Harga Satuan Pekerjaan (D+E) 343,521.36

24 Pemasangan 1 m2 bekisting untuk balok


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.66 132,000.00 87,120.00
Tukang Kayu OH 0.33 188,571.44 62,228.58
Kepala Tukang OH 0.03 200,000.00 6,600.00
Mandor OH 0.03 220,000.00 7,260.00
JUMLAH TENAGA KERJA 163,208.58
B BAHAN
Kayu kelas III (50%) M3 0.02 524,000.00 10,480.00
Paku 5 cm – 12 cm Kg 0.40 21,344.00 8,537.60
Minyak bekisting Liter 0.20 8,500.00 1,700.00
Balok kayu kelas II (50%) M3 0.01 3,386,350.00 30,477.15
Plywood tebal 9 mm (50%) Lbr 0.18 225,071.00 39,387.43
Dolken kayu galam, Batang 1.00 50,003.00 50,003.00
8–10 cm panjang 4 m (50%)
JUMLAH HARGA BAHAN 140,585.18
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 303,793.75


E Overhead & Profit 15% x D 45,569.06
F Harga Satuan Pekerjaan (D+E) 349,362.81

25 Pemasangan 1 m2 bekisting untuk lantai


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.66 132,000.00 87,120.00
Tukang Kayu OH 0.33 188,571.44 62,228.58
Kepala Tukang OH 0.03 200,000.00 6,600.00
Mandor OH 0.03 220,000.00 7,260.00
JUMLAH TENAGA KERJA 163,208.58
B BAHAN
Kayu kelas III (50%) M3 0.02 524,000.00 10,480.00
Paku 5 cm – 12 cm Kg 0.40 21,344.00 8,537.60
Minyak bekisting Liter 0.20 8,500.00 1,700.00
Balok kayu kelas II (50%) M3 0.01 3,386,350.00 25,397.63
Plywood tebal 9 mm (50%) Lbr 0.18 225,071.00 39,387.43
Dolken kayu galam, Batang 3.00 50,003.00 150,009.00
8–10 cm panjang 4 m (50%)
JUMLAH HARGA BAHAN 235,511.65
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 398,720.23


E Overhead & Profit 15% x D 59,808.03
F Harga Satuan Pekerjaan (D+E) 458,528.26

26 Pemasangan 1 m2 bekistig untuk dinding


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja L.01 0.66 132,000.00 87,120.00
Tukang Kayu L.02 0.33 188,571.44 62,228.58
Kepala Tukang L.03 0.03 200,000.00 6,600.00
Mandor L.04 0.03 220,000.00 7,260.00
JUMLAH TENAGA KERJA 163,208.58
B BAHAN
Kayu kelas III (50%) M3 0.02 524,000.00 7,860.00
Paku 5 cm – 12 cm Kg 0.40 21,344.00 8,537.60
Minyak bekisting Liter 0.20 8,500.00 1,700.00
Balok kayu kelas II (50%) M3 0.01 3,386,350.00 33,863.50
Plywood tebal 9 mm (50%) Lbr 0.18 225,071.00 39,387.43
Dolken kayu galam, Batang 1.50 50,003.00 75,004.50
8–10 cm panjang 4 m (50%)
Penjaga jarak Buah 4.00 5,000.00 20,000.00
bekisting/spacer
JUMLAH HARGA BAHAN 186,353.03
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 349,561.60


E Overhead & Profit 15% x D 52,434.24
F Harga Satuan Pekerjaan (D+E) 401,995.84

27 Pemasangan 1 m2 bekisting untuk tangga


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.66 132,000.00 87,120.00
Tukang Kayu OH 0.33 188,571.44 62,228.58
Kepala Tukang OH 0.03 200,000.00 6,600.00
Mandor OH 0.03 220,000.00 7,260.00
JUMLAH TENAGA KERJA 163,208.58
B BAHAN
Kayu kelas III (50%) M3 0.02 524,000.00 7,860.00
Paku 5 cm – 12 cm Kg 0.40 21,344.00 8,537.60
Minyak bekisting Liter 0.15 8,500.00 1,275.00
Balok kayu kelas II (50%) M3 0.01 3,386,350.00 25,397.63
Plywood tebal 9 mm (50%) Lbr 0.18 225,071.00 39,387.43
Dolken kayu, φ 8–10 cm,panjang 4 m (50%) Batang 1.00 50,003.00 50,003.00
JUMLAH HARGA BAHAN 132,460.65
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 295,669.23


E Overhead & Profit 15% x D 44,350.38
F Harga Satuan Pekerjaan (D+E) 340,019.61

28 6 M' Pondasi Tiang Pancang persegi 30x30 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A BAHAN
Mob & demob alat pancang jenis hydraulic jam 0.45 1,897,500.00 844,387.50
Tiang Pancang persegi m' 6.00 481,860.00 2,891,160.00
Sepatu sambungan bh 1.00 128,900.00 128,900.00
Las Penyambungan titik 1.00 199,600.00 199,600.00
Pemotongan tiang pancang bh 1.00 225,600.00 225,600.00

B Jumlah (A) 4,289,647.50


C Overhead & Profit 15% x B 643,447.13
D Harga Satuan Pekerjaan (B+C) 4,933,094.63

1 6 M' Pondasi Tiang Pancang persegi 25x25 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A BAHAN
Mob & demob alat pancang jenis hydraulic jam 0.45 1,897,500.00 844,387.50
Tiang Pancang persegi m' 6.00 401,550.00 2,409,300.00
Sepatu sambungan bh 1.00 128,900.00 128,900.00
Las Penyambungan titik 1.00 199,600.00 199,600.00
Pemotongan tiang pancang bh 1.00 225,600.00 225,600.00

B Jumlah (A) 3,807,787.50


C Overhead & Profit 15% x B 571,168.13
D Harga Satuan Pekerjaan (B+C) 4,378,955.63
29 1 M3 Pondasi Poer - P1 (0,60x0,60x0,60 m3) Tul. 97 kg/m3
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 97.00 20,479.27 1,986,489.10
Bekisting M2 6.67 170,261.27 1,135,075.10
Harga Satuan Pekerjaan 4,696,422.67

30 1 M3 Pondasi Poer - P2 (0,60x1,35x0,60 m3) Tul. 88 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 88.00 20,479.27 1,802,175.68
Bekisting M2 4.81 170,261.27 819,776.46
Harga Satuan Pekerjaan 4,196,810.61

31 1 M3 Pondasi Poer - P3 Tul. 93 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 93.00 20,479.27 1,904,572.03
Bekisting M2 3.01 170,261.27 512,486.41
Harga Satuan Pekerjaan 3,991,916.90

32 1 M3 Pondasi Poer - P4 (1,35x1,35x0,60 m3) Tul. 88 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 88.00 20,479.27 1,802,175.68
Bekisting M2 2.96 170,261.27 504,477.82
Harga Satuan Pekerjaan 3,881,511.97

33 1 M3 Sloof SF.1 (0,20x0,40 m3) Tul. 151 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 151.00 20,479.27 3,092,369.63
Bekisting M2 10.00 170,261.27 1,702,612.66
Harga Satuan Pekerjaan 6,369,840.76

34 1 M3 Sloof SF.2 (0,20x0,30 m3) Tul. 153 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 153.00 20,479.27 3,133,328.17
Bekisting M2 13.33 170,261.27 2,270,150.21
Harga Satuan Pekerjaan 6,978,336.85

35 1 M3 Kolom Struktur K.1 50/50 cm Tul. 142 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 142.00 20,479.27 2,908,056.21
Bekisting M2 8.00 343,521.36 2,748,170.87
Harga Satuan Pekerjaan 7,231,085.55

36 1 M3 Kolom Struktur K.2 Ø 50 cm Tul. 168 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 168.00 20,479.27 3,440,517.21
Bekisting M2 5.00 343,521.36 1,717,606.79
Harga Satuan Pekerjaan 6,732,982.47

37 1 M3 Kolom Struktur K.3 30/30 Tul. 198 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 198.00 20,479.27 4,054,895.28
Bekisting M2 13.33 343,521.36 4,580,284.79
Harga Satuan Pekerjaan 10,210,038.54

38 1 M3 Kolom Struktur K.4 15/15 Tul. 180 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 180.00 20,479.27 3,686,268.44
Bekisting M2 26.67 343,521.36 9,160,569.57
Harga Satuan Pekerjaan 14,421,696.48
39 1 M3 Kolom Struktur KP 15/15 Tul. 180 kg/m3
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 180.00 20,479.27 3,686,268.44
Bekisting M2 26.67 343,521.36 9,160,569.57
Harga Satuan Pekerjaan 14,421,696.48

40 1 M3 Balok Struktur B.1 30/50 Tul. 192 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 192.00 20,479.27 3,932,019.67
Bekisting M2 7.07 349,362.81 2,468,830.54
Harga Satuan Pekerjaan 7,975,708.68

41 1 M3 Balok Struktur B.2 25/40 Tul. 136 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 136.00 20,479.27 2,785,180.60
Bekisting M2 8.10 349,362.81 2,829,838.78
Harga Satuan Pekerjaan 7,189,877.85

42 1 M3 Balok Struktur B.A1 20/30 Tul. 188 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 188.00 20,479.27 3,850,102.59
Bekisting M2 9.33 349,362.81 3,260,719.59
Harga Satuan Pekerjaan 8,685,680.64

43 1 M3 Balok Struktur RB.1 30/50 Tul. 192 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 192.00 20,479.27 3,932,019.67
Bekisting M2 7.07 349,362.81 2,468,830.54
Harga Satuan Pekerjaan 7,975,708.68

44 1 M3 Balok Struktur RB.2 25/40 Tul. 136 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 136.00 20,479.27 2,785,180.60
Bekisting M2 8.10 349,362.81 2,829,838.78
Harga Satuan Pekerjaan 7,189,877.85

45 1 M3 Balok Struktur RB.3 20/30 Tul. 188 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 188.00 20,479.27 3,850,102.59
Bekisting M2 9.33 349,362.81 3,260,719.59
Harga Satuan Pekerjaan 8,685,680.64

46 1 M3 Balok Struktur RB.4 20/30 Tul. 188 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 188.00 20,479.27 3,850,102.59
Bekisting M2 9.33 349,362.81 3,260,719.59
Harga Satuan Pekerjaan 8,685,680.64

47 1 M3 Balok Struktur RB.5 15/25 Tul. 168 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 168.00 20,479.27 3,440,517.21
Bekisting M2 10.93 349,362.81 3,819,700.09
Harga Satuan Pekerjaan 8,835,075.76

48 1 M3 Pelat Lantai T.12 cm Tul. 136 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 136.00 20,479.27 2,785,180.60
Bekisting M2 8.33 458,528.26 3,821,068.82
Harga Satuan Pekerjaan 8,181,107.89

49 1 M3 Pelat Atap Dak T.12 cm Tul. 96 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 96.00 20,479.27 1,966,009.83
Bekisting M2 8.33 458,528.26 3,821,068.82
Harga Satuan Pekerjaan 7,361,937.13

50 1 M3 Pelat Atap Dak T.22.5 cm Tul. 136 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 136.00 20,479.27 2,785,180.60
Bekisting M2 4.44 458,528.26 2,037,903.37
Harga Satuan Pekerjaan 6,397,942.44

51 1 M3 Dinding talang Luar 15/100 Tul. 102 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 102.00 20,479.27 2,088,885.45
Bekisting M2 14.33 349,362.81 5,007,533.65
Harga Satuan Pekerjaan 8,671,277.57

52 1 M3 Sirip Talang Bagian Atas 10,5/60 Tul. 85 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 85.00 20,479.27 1,740,737.87
Bekisting M2 19.84 349,362.81 6,931,801.84
Harga Satuan Pekerjaan 10,247,398.18

53 1 M3 Sirip Talang Melekat Pada Dinding Beton (sudutan) Tul. 85 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 85.00 20,479.27 1,740,737.87
Bekisting M2 19.84 349,362.81 6,931,801.84
Harga Satuan Pekerjaan 10,247,398.18

54 1 M3 Beton Kaki Sirip 15/100 Tul. 102 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 102.00 20,479.27 2,088,885.45
Bekisting M2 14.33 349,362.81 5,007,533.65
Harga Satuan Pekerjaan 8,671,277.57

55 1 M3 Beton Peninggian Dinding dasar Kubah 15/30 Tul. 90 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 90.00 20,479.27 1,843,134.22
Bekisting M2 14.44 349,362.81 5,046,351.74
Harga Satuan Pekerjaan 8,464,344.43

56 1 M3 Beton Struktur Dudukan Kubah B4A 25/45 Tul. 251 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 251.00 20,479.27 5,140,296.54
Bekisting M2 10.22 349,362.81 3,571,264.31
Harga Satuan Pekerjaan 10,286,419.32

57 1 M3 Beton Talang t = 15 cm Tul. 209 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 209.00 20,479.27 4,280,167.24
Bekisting M2 6.67 458,528.26 3,056,855.06
Harga Satuan Pekerjaan 8,911,880.77

58 1 M3 Sirirp Talang T.12 cm Tul. 85 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 85.00 20,479.27 1,740,737.87
Bekisting M2 16.67 349,362.81 5,822,713.55
Harga Satuan Pekerjaan 9,138,309.89

59 1 M3 Beton Sirip Vertikal t = 15 cm Tul. 76 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 76.00 20,479.27 1,556,424.45
Bekisting M2 13.33 349,362.81 4,658,170.84
Harga Satuan Pekerjaan 7,789,453.76

60 1 M3 Kubah Beton t = 15 cm Tul. 282 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 282.00 20,479.27 5,775,153.88
Bekisting M2 6.67 458,528.26 3,056,855.06
Harga Satuan Pekerjaan 10,406,867.41

61 1 M3 Plat Canopy t = 15/75 cm + Tali Air Tul. 125 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 125.00 20,479.27 2,559,908.64
Bekisting M2 6.67 458,528.26 3,056,855.06
Harga Satuan Pekerjaan 7,191,622.17

62 1 M3 Frame Beton 15/25 Tul. 125 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 180.00 20,479.27 3,686,268.44
Bekisting M2 21.33 343,521.36 7,328,455.66
Harga Satuan Pekerjaan 12,589,582.56

PEKERJAAN TANGGA
63 1 M3 Pondasi Plat t = 25 cm /Besi 139 kg/m3
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 139.00 20,479.27 2,846,618.40
Bekisting M2 4.00 170,261.27 681,045.06
Harga Satuan Pekerjaan 5,102,521.94

64 1 M3 Pondasi Stump t = 20 /Besi 178 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 178.00 20,479.27 3,645,309.90
Bekisting M2 10.00 401,995.84 4,019,958.40
Harga Satuan Pekerjaan 9,240,126.77

65 1 M3 Plat Tangga t = 15 cm /Besi 101 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 101.00 20,479.27 2,068,406.18
Bekisting M2 6.67 340,019.61 2,266,797.39
Harga Satuan Pekerjaan 5,910,062.04

66 1 M3 Plat Bordes t = 15 cm /Besi 108 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 108.00 20,479.27 2,211,761.06
Bekisting M2 6.67 340,019.61 2,266,797.39
Harga Satuan Pekerjaan 6,053,416.92

67 1 M3 Balok Bordes B3 20/30 /Besi 209 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 209.00 20,479.27 4,280,167.24
Bekisting M2 12.50 349,362.81 4,367,035.16
Harga Satuan Pekerjaan 10,222,060.87
GROUND RESERVOAR
68 1 M3 Beton Plat lantai t = 20 cm Tul 127,490 kg/m3
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 127.49 20,479.27 2,610,902.02
Bekisting M2 1.00 170,261.27 170,261.27
Harga Satuan Pekerjaan 4,356,021.75

69 1 M3 Beton Dinding t = 15 cm Tul 113,48 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 113.48 20,479.27 2,323,987.46
Bekisting M2 13.33 401,995.84 5,359,944.54
Harga Satuan Pekerjaan 9,258,790.46

70 1 M3 Plat Beton Penutup Dinding Man Hole t = 12 cm Tul 141,95 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 141.95 20,479.27 2,907,032.25
Bekisting M2 16.67 401,995.84 6,699,930.67
Harga Satuan Pekerjaan 11,181,821.39

71 1 M3 Beton Tutup Man Hole 0,7 x 0,8 x 0,1 Tul 129,77 kg/m3
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 129.77 20,479.27 2,657,594.75
Bekisting M2 10.00 458,528.26 4,585,282.59
Harga Satuan Pekerjaan 8,817,735.81

72 1 M3 Balok Beton 20/30 Tul 213,95 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 129.77 20,479.27 2,657,594.75
Bekisting M2 10.00 349,362.81 3,493,628.13
Harga Satuan Pekerjaan 7,726,081.35

73 1 M3 Kolom Struktur 15/15 Tul 213,95 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 168.76 20,479.27 3,456,081.45
Bekisting M2 10.00 170,261.27 1,702,612.66
Harga Satuan Pekerjaan 6,733,552.58

BANGUNAN MENARA
74 1 M' Pondasi Bored Pile O 30cm ~ 10.00 M' Tul. 80 kg/m3
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 80.00 20,479.27 1,638,341.53
Harga Satuan Pekerjaan 3,213,200.00

75 1 M3 Pondasi Poer - P6 (3x2x0,60 m3) Tul. 115 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 115.00 20,479.27 2,355,115.95
Bekisting M2 6.67 170,261.27 1,135,075.10
Harga Satuan Pekerjaan 5,065,049.52

76 1 M3 Pondasi Poer - P8 (4x2x0,60 m3) Tul. 93 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 93.00 20,479.27 1,904,572.03
Bekisting M2 4.87 170,261.27 829,477.96
Harga Satuan Pekerjaan 4,308,908.46

77 1 M3 Sloof 20/40 Tul. 120 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 120.00 20,479.27 2,457,512.29
Bekisting M2 10.00 170,261.27 1,702,612.66
Harga Satuan Pekerjaan 5,734,983.42

78 1 M3 Kolom Stump 30/30 Tul. 118 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 118.00 20,479.27 2,416,553.75
Bekisting M2 13.33 343,521.36 4,580,284.79
Harga Satuan Pekerjaan 8,571,697.01

79 1 M3 Kolom Struktur 30/30 cm Tul. 83 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 83.00 20,479.27 1,699,779.33
Bekisting M2 13.33 343,521.36 4,580,284.79
Harga Satuan Pekerjaan 7,854,922.59

80 1 M3 Kolom Struktur 60/60 Tul. 192 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 164.00 20,479.27 3,358,600.13
Bekisting M2 6.67 343,521.36 2,290,142.39
Harga Satuan Pekerjaan 7,223,600.99

81 1 M3 Balok Struktur B1 20/40 Tul. 151 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 151.00 20,479.27 3,092,369.63
Bekisting M2 12.26 349,362.81 4,283,188.08
Harga Satuan Pekerjaan 8,950,416.19

82 1 M3 Balok Struktur B2 15/25 + 10/25 Tul. 147 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 147.00 20,479.27 3,010,452.56
Bekisting M2 18.25 349,362.81 6,377,257.69
Harga Satuan Pekerjaan 10,962,568.72

83 1 M3 Balok Struktur B3 15/25 + 10/25 Tul. 147 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 147.00 20,479.27 3,010,452.56
Bekisting M2 18.25 349,362.81 6,377,257.69
Harga Satuan Pekerjaan 10,962,568.72

84 1 M3 Balok Struktur B2' 15/25 Tul. 169 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 169.00 20,479.27 3,460,996.48
Bekisting M2 17.09 349,362.81 5,971,775.01
Harga Satuan Pekerjaan 11,007,629.96

85 1 M3 Plat Lantai II t = 12 cm Tul. 136 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 136.00 20,479.27 2,785,180.60
Bekisting M2 8.33 458,528.26 3,821,068.82
Harga Satuan Pekerjaan 8,181,107.89

86 1 M3 Kolom Struktur 60/60 Tul. 164 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 164.00 20,479.27 3,358,600.13
Bekisting M2 6.67 343,521.36 2,290,142.39
Harga Satuan Pekerjaan 7,223,600.99

87 1 M3 Balok Struktur 20/40 Lantai II Tul. 151 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 151.00 20,479.27 3,092,369.63
Bekisting M2 12.50 349,362.81 4,367,035.16
Harga Satuan Pekerjaan 9,034,263.26

88 1 M3 Balok Struktur 20/40 Lantai II Tul. 135 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 135.00 20,479.27 2,764,701.33
Bekisting M2 12.50 349,362.81 4,367,035.16
Harga Satuan Pekerjaan 8,706,594.96

TEMPAT WUDHU
89 1 M3 Pondasi Plat 1,2 x 1,2 x 0,25 Tul. 143 kg/m3
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 143.00 20,479.27 2,928,535.48
Bekisting M2 3.33 170,261.27 567,537.55
Harga Satuan Pekerjaan 5,070,931.50

90 1 M3 Sloof Praktis (0,15x0,20 m3) Tul 183 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 183.00 20,479.27 3,747,706.24
Bekisting M2 13.33 170,261.27 2,270,150.21
Harga Satuan Pekerjaan 7,592,714.92

91 1 M3 Kolom Stump 30/30 Tul 190 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 190.00 20,479.27 3,891,061.13
Bekisting M2 11.11 343,521.36 3,816,903.99
Harga Satuan Pekerjaan 9,282,823.59

92 1 M3 Kolom Stump 15/30 Tul 204 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 204.00 20,479.27 4,177,770.89
Bekisting M2 20.00 343,521.36 6,870,427.18
Harga Satuan Pekerjaan 12,623,056.54

93 1 M3 Kolom Struktur 30/30 Tul 190 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 190.00 20,479.27 3,891,061.13
Bekisting M2 13.33 343,521.36 4,580,284.79
Harga Satuan Pekerjaan 10,046,204.38

94 1 M3 Kolom Struktur 20/20 Tul 192 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 192.00 20,479.27 3,932,019.67
Bekisting M2 20.00 343,521.36 6,870,427.18
Harga Satuan Pekerjaan 12,377,305.31

95 1 M3 Balok Struktur B1 25/40 Tul 187 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 187.00 20,479.27 3,829,623.32
Bekisting M2 10.26 349,362.81 3,584,462.46
Harga Satuan Pekerjaan 8,988,944.25

96 1 M3 Balok Struktur B2 20/30 Tul 267kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 267.00 20,479.27 5,467,964.85
Bekisting M2 13.09 349,362.81 4,574,323.76
Harga Satuan Pekerjaan 11,617,147.08
97 1 M3 Balok Struktur BA1 20/30 Tul 192kg/m3
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 192.00 20,479.27 3,932,019.67
Bekisting M2 13.09 349,362.81 4,574,323.76
Harga Satuan Pekerjaan 10,081,201.90

98 1 M3 Pelat Atap Dak T.15 cm Tul 116 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 116.00 20,479.27 2,375,595.21
Bekisting M2 10.00 458,528.26 4,585,282.59
Harga Satuan Pekerjaan 8,535,736.27

99 1 M3 Pelat Atap Dak T.12 cm Tul 96 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 96.00 20,479.27 1,966,009.83
Bekisting M2 10.00 458,528.26 4,585,282.59
Harga Satuan Pekerjaan 8,126,150.89

100 1 M3 Beton Lisplang 10/15 Tul 147 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 147.00 20,479.27 3,010,452.56
Bekisting M2 26.67 349,362.81 9,316,341.67
Harga Satuan Pekerjaan 13,901,652.70

KANTOR PENGELOLA
101 1 M3 Pondasi Plat 1,4 x 1,4 x 0,3 Tul. 136 kg/m3
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 136.00 20,479.27 2,785,180.60
Bekisting M2 2.86 170,261.27 486,460.76
Harga Satuan Pekerjaan 4,846,499.82

102 1 M3 Pondasi Plat 1,2 x 1,2 x 0,3 Tul. 143 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 143.00 20,479.27 2,928,535.48
Bekisting M2 3.33 170,261.27 567,537.55
Harga Satuan Pekerjaan 5,070,931.50

103 1 M3 Pondasi Plat 1,0 x 1,0 x 0,30 Tul. 187 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 187.00 20,479.27 3,829,623.32
Bekisting M2 3.33 170,261.27 567,537.55
Harga Satuan Pekerjaan 5,972,019.34

104 1 M3 Sloof Praktis (0,20x0,30 m3) Tul 183 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 183.00 20,479.27 3,747,706.24
Bekisting M2 10.00 170,261.27 1,702,612.66
Harga Satuan Pekerjaan 7,025,177.37

105 1 M3 Kolom Stump 30/30 Tul 190 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 190.00 20,479.27 3,891,061.13
Bekisting M2 11.11 343,521.36 3,816,903.99
Harga Satuan Pekerjaan 9,282,823.59

106 1 M3 Kolom Stump Ø 20 cm Tul 204 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 204.00 20,479.27 4,177,770.89
Bekisting M2 20.00 343,521.36 6,870,427.18
Harga Satuan Pekerjaan 12,623,056.54

107 1 M3 Kolom Stump 20/20 Tul 192 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 192.00 20,479.27 3,932,019.67
Bekisting M2 20.00 343,521.36 6,870,427.18
Harga Satuan Pekerjaan 12,377,305.31

108 1 M3 Kolom Struktur 30/30 Tul 190 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 190.00 20,479.27 3,891,061.13
Bekisting M2 13.33 343,521.36 4,580,284.79
Harga Satuan Pekerjaan 10,046,204.38

109 1 M3 Kolom Struktur Ø 20 cm Tul 204 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 204.00 20,479.27 4,177,770.89
Bekisting M2 20.00 343,521.36 6,870,427.18
Harga Satuan Pekerjaan 12,623,056.54

110 1 M3 Kolom Struktur 20/20 Tul 192 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 192.00 20,479.27 3,932,019.67
Bekisting M2 20.00 343,521.36 6,870,427.18
Harga Satuan Pekerjaan 12,377,305.31

111 1 M3 Balok Struktur B1 25/40 Tul 187 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 187.00 20,479.27 3,829,623.32
Bekisting M2 10.26 349,362.81 3,584,462.46
Harga Satuan Pekerjaan 8,988,944.25

112 1 M3 Balok Struktur B2 20/30 Tul 267kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 267.00 20,479.27 5,467,964.85
Bekisting M2 13.09 349,362.81 4,574,323.76
Harga Satuan Pekerjaan 11,617,147.08

113 1 M3 Balok Struktur BA1 20/30 Tul 192kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 192.00 20,479.27 3,932,019.67
Bekisting M2 13.09 349,362.81 4,574,323.76
Harga Satuan Pekerjaan 10,081,201.90

114 1 M3 Pelat Atap Dak T.12 cm Tul 96 kg/m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
Beton K 250 M3 1.00 1,574,858.47 1,574,858.47
Besi Beton Kg 126.00 20,479.27 2,580,387.91
Bekisting M2 10.00 458,528.26 4,585,282.59
Harga Satuan Pekerjaan 8,740,528.96
115 Pemasangan 1 kg besi profil
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.06 132,000.00 7,920.00
Tukang Las OH 0.06 188,571.44 11,314.29
Konstruksi
Kepala tukang OH 0.01 200,000.00 1,200.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 21,094.29
B BAHAN
Besi Profil Kg 1.15 - -
JUMLAH HARGA BAHAN -
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 21,094.29


E Overhead & Profit 15% x D 3,164.14
F Harga Satuan Pekerjaan (D+E) 24,258.43

116 Pemasangan 1 kg besi rangka kuda-kuda baja IWF


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.06 132,000.00 7,920.00
Tukang Las OH 0.06 188,571.44 11,314.29
Konstruksi
Kepala tukang OH 0.01 200,000.00 1,200.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 21,094.29
B BAHAN
Besi Baja IWF Kg 1.15 18,462.00 21,231.30
JUMLAH HARGA BAHAN 21,231.30
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 42,325.59


E Overhead & Profit 15% x D 6,348.84
F Harga Satuan Pekerjaan (D+E) 48,674.42

117 Pengerjaan 100 kg pekerjaan perakitan


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.10 132,000.00 13,200.00
Tukang Besi OH 0.10 188,571.44 18,857.14
Konstruksi
Kepala tukang OH 0.00 200,000.00 200.00
Mandor OH 0.01 220,000.00 1,100.00
JUMLAH TENAGA KERJA 33,357.14
B BAHAN
Solar Liter 1.00 11,700.00 11,700.00
Minyak pelumas Liter 0.10 62,225.00 6,222.50
JUMLAH HARGA BAHAN 17,922.50
C PERALATAN
Sewa alat Jam 0.80 12,500.00 10,000.00
JUMLAH HARGA ALAT 10,000.00

D Jumlah (A+B+C) 61,279.64


E Overhead & Profit 15% x D 9,191.95
F Harga Satuan Pekerjaan (D+E) 70,471.59
G Harga Satuan Pekerjaan (D+E) Per 1 Kg 796.64

118 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kamper samarinda Oven
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 7.00 132,000.00 924,000.00
Tukang kayu OH 21.00 188,571.44 3,960,000.24
Kepala tukang OH 2.10 200,000.00 420,000.00
Mandor OH 0.35 220,000.00 77,000.00
JUMLAH TENAGA KERJA 5,381,000.24
B BAHAN
Balok kayu M3 1.10 10,418,430.00 11,460,273.00
Paku 10 cm Kg 1.25 21,344.00 26,680.00
Lem kayu Kg 1.00 40,509.00 40,509.00
JUMLAH HARGA BAHAN 11,527,462.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 16,908,462.24


E Overhead & Profit 15% x D 2,536,269.34
F Harga Satuan Pekerjaan (D+E) 19,444,731.58
119 Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kayu kamper samarinda Oven
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.00 132,000.00 132,000.00
Tukang kayu OH 3.00 188,571.44 565,714.32
Kepala tukang OH 0.30 200,000.00 60,000.00
Mandor OH 0.05 220,000.00 11,000.00
JUMLAH TENAGA KERJA 768,714.32
B BAHAN
Papan kayu M3 0.04 11,066,880.00 442,675.20
Lem kayu Kg 0.50 40,509.00 20,254.50
JUMLAH HARGA BAHAN 462,929.70
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,231,644.02


E Overhead & Profit 15% x D 184,746.60
F Harga Satuan Pekerjaan (D+E) 1,416,390.62

120 Pembuatan dan pemasangan 1 m2 pintu dan jendela kaca, kayu kamper samarinda Oven
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.80 132,000.00 105,600.00
Tukang kayu OH 2.40 188,571.44 452,571.46
Kepala tukang OH 0.24 200,000.00 48,000.00
Mandor OH 0.04 220,000.00 8,800.00
JUMLAH TENAGA KERJA 614,971.46
B BAHAN
Papan kayu M3 0.02 11,066,880.00 265,605.12
Lem kayu Kg 0.30 40,509.00 12,152.70
JUMLAH HARGA BAHAN 277,757.82
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 892,729.28


E Overhead & Profit 15% x D 133,909.39
F Harga Satuan Pekerjaan (D+E) 1,026,638.67

121 Pemasangan 1 m Kusen Aluminium ukuran 4" sek. YKK YBIC t = 1,35 mm Lengkap Assesoris
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.04 132,000.00 5,676.00
Tukang Khusus OH 0.04 188,571.44 8,108.57
Alumunium
Kepala tukang OH 0.00 200,000.00 860.00
Mandor OH 0.00 220,000.00 462.00
JUMLAH TENAGA KERJA 15,106.57
B BAHAN
Profil alluminium M 1.10 200,850.00 220,935.00
Skrup fixer Buah 2.00 400.00 800.00
Sealant Tube 0.06 35,000.00 2,100.00
JUMLAH HARGA BAHAN 223,835.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 238,941.57


E Overhead & Profit 15% x D 35,841.24
F Harga Satuan Pekerjaan (D+E) 274,782.81

122 Pemasangan 1 m2 pintu alumunium strip lebar 8 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.09 132,000.00 11,220.00
Tukang Khusus OH 0.09 188,571.44 16,028.57
Allumunium
Kepala tukang OH 0.01 200,000.00 1,700.00
Mandor OH 0.00 220,000.00 924.00
JUMLAH TENAGA KERJA 29,872.57
B BAHAN
Profil alluminium M 4.40 200,850.00 883,740.00
Alluminium strip M 14.60 - -
JUMLAH HARGA BAHAN 883,740.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 913,612.57


E Overhead & Profit 15% x D 137,041.89
F Harga Satuan Pekerjaan (D+E) 1,050,654.46

123 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3PP
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.30 132,000.00 39,600.00
Tukang Batu OH 0.10 188,571.44 18,857.14
Kepala Tukang OH 0.01 200,000.00 2,000.00
Mandor OH 0.02 220,000.00 3,300.00
JUMLAH TENAGA KERJA 63,757.14
B BAHAN
Bata merah M3 70.00 590.00 41,300.00
Semen Portlan Kg 14.37 1,585.10 22,777.89
Pasir Pasang M3 0.04 216,150.00 8,646.00
JUMLAH HARGA BAHAN 72,723.89
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 136,481.03


E Overhead & Profit 15% x D 20,472.15
F Harga Satuan Pekerjaan (D+E) 156,953.19

124 Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 5PP
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.30 132,000.00 39,600.00
Tukang Batu OH 0.10 188,571.44 18,857.14
Kepala Tukang OH 0.01 200,000.00 2,000.00
Mandor OH 0.02 220,000.00 3,300.00
JUMLAH TENAGA KERJA 63,757.14
B BAHAN
Bata merah M3 70.00 590.00 41,300.00
Semen Portlan Kg 9.68 1,585.10 15,343.77
Pasir Pasang M3 0.05 216,150.00 9,726.75
JUMLAH HARGA BAHAN 66,370.52
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 130,127.66


E Overhead & Profit 15% x D 19,519.15
F Harga Satuan Pekerjaan (D+E) 149,646.81

125 Pemasangan 1 m2 dinding terawang (rooster) 15x15x15 campuran 1SP : 3PP


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.30 132,000.00 39,600.00
Tukang Batu OH 0.10 188,571.44 18,857.14
Kepala Tukang OH 0.01 200,000.00 2,000.00
Mandor OH 0.02 220,000.00 3,300.00
JUMLAH TENAGA KERJA 63,757.14
B BAHAN
Bata rooster M3 44.00 7,500.00 330,000.00
Semen Portland Kg 11.00 1,585.10 17,436.10
Pasir Pasang M3 0.04 216,150.00 7,565.25
JUMLAH HARGA BAHAN 355,001.35
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 418,758.49


E Overhead & Profit 15% x D 62,813.77
F Harga Satuan Pekerjaan (D+E) 481,572.27

126 Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20 mm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.26 132,000.00 34,320.00
Tukang Batu OH 0.20 188,571.44 37,714.29
Kepala Tukang OH 0.02 200,000.00 4,000.00
Mandor OH 0.01 220,000.00 2,860.00
JUMLAH TENAGA KERJA 78,894.29
B BAHAN
Semen PC Kg 10.37 1,585.10 16,434.32
Pasir pasang M3 0.03 216,150.00 6,700.65
JUMLAH HARGA BAHAN 23,134.97
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 102,029.25


E Overhead & Profit 15% x D 15,304.39
F Harga Satuan Pekerjaan (D+E) 117,333.64

127 Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20 mm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.40 132,000.00 52,800.00
Tukang Batu OH 0.20 188,571.44 37,714.29
Kepala Tukang OH 0.02 200,000.00 4,000.00
Mandor OH 0.02 220,000.00 4,840.00
JUMLAH TENAGA KERJA 99,354.29
B BAHAN
Semen PC Kg 6.91 1,585.10 10,956.21
Pasir pasang M3 0.04 216,150.00 7,565.25
JUMLAH HARGA BAHAN 18,521.46
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 117,875.75


E Overhead & Profit 15% x D 17,681.36
F Harga Satuan Pekerjaan (D+E) 135,557.11

128 Pemasangan 1 m2 plesteran ciprat 1SP : 2PP


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.30 132,000.00 39,600.00
Tukang Batu OH 0.10 188,571.44 18,857.14
Kepala Tukang OH 0.01 200,000.00 2,000.00
Mandor OH 0.02 220,000.00 3,300.00
JUMLAH TENAGA KERJA 63,757.14
B BAHAN
Semen PC Kg 4.32 1,585.10 6,847.63
Pasir pasang Kg 0.01 216,150.00 1,296.90
JUMLAH HARGA BAHAN 8,144.53
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 71,901.68


E Overhead & Profit 15% x D 10,785.25
F Harga Satuan Pekerjaan (D+E) 82,686.93

129 Pemasangan 1 m2 acian


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.20 132,000.00 26,400.00
Tukang Batu OH 0.10 188,571.44 18,857.14
Kepala Tukang OH 0.01 200,000.00 2,000.00
Mandor OH 0.01 220,000.00 2,200.00
JUMLAH TENAGA KERJA 49,457.14
B BAHAN
Semen PC Kg 3.25 1,585.10 5,151.58
JUMLAH HARGA BAHAN 5,151.58
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 54,608.72


E Overhead & Profit 15% x D 8,191.31
F Harga Satuan Pekerjaan (D+E) 62,800.03

130 Pemasangan 1 m' plesteran ban 1SP : 3PP lebar 10 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.08 132,000.00 10,560.00
Tukang Batu OH 0.40 188,571.44 75,428.58
Kepala Tukang OH 0.04 200,000.00 8,000.00
Mandor OH 0.00 220,000.00 880.00
JUMLAH TENAGA KERJA 94,868.58
B BAHAN
Semen PC Kg 0.50 1,585.10 792.55
Pasir pasang M3 0.01 216,150.00 2,809.95
JUMLAH HARGA BAHAN 3,602.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 98,471.08


E Overhead & Profit 15% x D 14,770.66
F Harga Satuan Pekerjaan (D+E) 113,241.74

131 Pemasangan 1 m2 screeding plat dak beton / Self Leveling Floor MU 410
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.15 132,000.00 19,800.00
Tukang Batu OH 0.08 188,571.44 14,142.86
Kepala Tukang OH 0.01 200,000.00 1,600.00
Mandor OH 0.01 220,000.00 1,760.00
JUMLAH TENAGA KERJA 37,302.86
B BAHAN
Self Leveling Floor MU 410 Kg 5.00 10,400.00 52,000.00
JUMLAH HARGA BAHAN 52,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 89,302.86


E Overhead & Profit 15% x D 13,395.43
F Harga Satuan Pekerjaan (D+E) 102,698.29

132 Pemasangan 1 m' plint ubin warna ukuran 10cm x 40cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.09 132,000.00 11,880.00
Tukang Batu OH 0.09 188,571.44 16,971.43
Kepala tukang OH 0.04 200,000.00 7,000.00
Mandor OH 0.01 220,000.00 1,100.00
JUMLAH TENAGA KERJA 36,951.43
B BAHAN
Plint ubin warna Bh 2.65 59,500.00 157,675.00
Semen Portlan Kg 1.14 1,585.10 1,807.01
Semen warna Kg 0.10 21,615.00 2,161.50
Pasir pasang M3 0.00 216,150.00 648.45
JUMLAH HARGA BAHAN 162,291.96
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 199,243.39


E Overhead & Profit 15% x D 29,886.51
F Harga Satuan Pekerjaan (D+E) 229,129.90

133 Pemasangan 1 m' stair nozing ukuran 10cm x 60cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.09 132,000.00 11,880.00
Tukang Batu OH 0.09 188,571.44 16,971.43
Kepala tukang OH 0.01 200,000.00 1,800.00
Mandor OH 0.01 220,000.00 1,100.00
JUMLAH TENAGA KERJA 31,751.43
B BAHAN
Stair nozing Bh 2.00 29,000.00 58,000.00
Semen Portlan Kg 1.14 1,585.10 1,807.01
Semen warna Kg 0.10 21,615.00 2,161.50
Pasir pasang M3 0.00 216,150.00 648.45
JUMLAH HARGA BAHAN 62,616.96
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 94,368.39


E Overhead & Profit 15% x D 14,155.26
F Harga Satuan Pekerjaan (D+E) 108,523.65

134 Pemasangan 1 m2 lantai ubin keramik ukuran 40cm x 40cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.25 132,000.00 33,000.00
Tukang Batu OH 0.13 188,571.44 23,571.43
Kepala tukang OH 0.01 200,000.00 2,600.00
Mandor OH 0.01 220,000.00 2,860.00
JUMLAH TENAGA KERJA 62,031.43
B BAHAN
Ubin keramik Bh 6.63 17,608.33 116,743.25
Semen Portlan Kg 9.80 1,585.10 15,533.98
Semen warna Kg 1.30 21,615.00 28,099.50
Pasir pasang M3 0.05 216,150.00 9,726.75
JUMLAH HARGA BAHAN 170,103.48
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 232,134.91


E Overhead & Profit 15% x D 34,820.24
F Harga Satuan Pekerjaan (D+E) 266,955.15

135 Pemasangan 1 m2 lantai ubin keramik ukuran 40cm x 40cm (rock tile)
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.25 132,000.00 33,000.00
Tukang Batu OH 0.13 188,571.44 23,571.43
Kepala tukang OH 0.01 200,000.00 2,600.00
Mandor OH 0.01 220,000.00 2,860.00
JUMLAH TENAGA KERJA 62,031.43
B BAHAN
Ubin keramik Bh 6.63 16,166.67 107,185.00
Semen Portlan Kg 9.80 1,585.10 15,533.98
Semen warna Kg 1.30 21,615.00 28,099.50
Pasir pasang M3 0.05 216,150.00 9,726.75
JUMLAH HARGA BAHAN 160,545.23
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 222,576.66


E Overhead & Profit 15% x D 33,386.50
F Harga Satuan Pekerjaan (D+E) 255,963.16

136 Pemasangan 1 m2 lantai granit tile ukuran 60cm x 60cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.24 132,000.00 31,680.00
Tukang Batu OH 0.12 188,571.44 22,628.57
Kepala tukang OH 0.01 200,000.00 2,400.00
Mandor OH 0.12 220,000.00 26,400.00
JUMLAH TENAGA KERJA 83,108.57
B BAHAN
Granite tile Bh 3.10 67,400.00 208,940.00
Semen Portlan Kg 9.60 1,585.10 15,216.96
Semen warna Kg 1.50 21,615.00 32,422.50
Pasir pasang M3 0.05 216,150.00 9,726.75
JUMLAH HARGA BAHAN 266,306.21
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 349,414.78


E Overhead & Profit 15% x D 52,412.22
F Harga Satuan Pekerjaan (D+E) 401,827.00

137 Pemasangan 1 m2 dinding keramik 20cm x 40cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.90 132,000.00 118,800.00
Tukang Batu OH 0.45 188,571.44 84,857.15
Kepala tukang OH 0.05 200,000.00 9,000.00
Mandor OH 0.05 220,000.00 9,900.00
JUMLAH TENAGA KERJA 222,557.15
B BAHAN
Keramik artistik Bh 13.25 3,626.00 48,044.50
Semen Portlan Kg 9.30 1,585.10 14,741.43
Pasir Pasang M3 0.02 216,150.00 3,890.70
Semen warna Kg 1.94 21,615.00 41,933.10
JUMLAH HARGA BAHAN 108,609.73
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 331,166.88


E Overhead & Profit 15% x D 49,675.03
F Harga Satuan Pekerjaan (D+E) 380,841.91

138 Pemasangan 1 m2 dinding marmer ukuran 60cm x 60cm (mihrab)


Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.30 132,000.00 171,600.00
Tukang Batu OH 0.65 188,571.44 122,571.44
Kepala tukang OH 0.07 200,000.00 13,000.00
Mandor OH 0.07 220,000.00 14,300.00
JUMLAH TENAGA KERJA 321,471.44
B BAHAN
Marmer Alam Bh 3.10 20,500.00 63,550.00
AM 30 + AM 54 Liquid Kg 8.00 76,000.00 608,000.00
Pasir Pasang M3 0.03 216,150.00 5,403.75
Nat AM 50 Tile Grout + AM 54 Liquid Grout Aditive Kg 0.65 17,500.00 11,375.00
JUMLAH HARGA BAHAN 688,328.75
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,009,800.19


E Overhead & Profit 15% x D 151,470.03
F Harga Satuan Pekerjaan (D+E) 1,161,270.21

139 Pemasangan 1 m2 dinding batu tempel Andesit


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.70 132,000.00 92,400.00
Tukang Batu OH 0.35 188,571.44 66,000.00
Kepala tukang OH 0.04 200,000.00 7,000.00
Mandor OH 0.04 220,000.00 7,700.00
JUMLAH TENAGA KERJA 173,100.00
B BAHAN
Batu temple hitam Bh 1.10 85,000.00 93,500.00
Semen Portlan Kg 11.75 1,585.10 18,624.93
Pasir Pasang M3 0.04 216,150.00 7,565.25
JUMLAH HARGA BAHAN 119,690.18
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 292,790.18


E Overhead & Profit 15% x D 43,918.53
F Harga Satuan Pekerjaan (D+E) 336,708.71

140 Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60cm, plafond


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.35 132,000.00 46,200.00
Tukang Besi OH 0.35 188,571.44 66,000.00
Kepala Tukang OH 0.04 200,000.00 7,000.00
Mandor OH 0.02 220,000.00 3,960.00
JUMLAH TENAGA KERJA 123,160.00
B BAHAN
Rangka metal M1 4.00 5,666.67 22,666.67
hollow 40.40.0,5 mm
Assesoris Ls 0.10 22,666.67 2,266.67
(perkuatan, las dll)
JUMLAH HARGA BAHAN 24,933.33
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 148,093.34


E Overhead & Profit 15% x D 22,214.00
F Harga Satuan Pekerjaan (D+E) 170,307.34

141 Pemasangan 1 m2 langit-langit asbes semen, tebal 4mm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.03 132,000.00 3,960.00
Tukang kayu OH 0.07 188,571.44 13,200.00
Kepala tukang OH 0.01 200,000.00 1,400.00
Mandor OH 0.00 220,000.00 880.00
JUMLAH TENAGA KERJA 19,440.00
B BAHAN
Asbes semen Lbr 0.36 82,500.00 30,030.00
Paku tripleks Kg 0.01 27,703.00 277.03
JUMLAH HARGA BAHAN 30,307.03
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 49,747.03


E Overhead & Profit 15% x D 7,462.05
F Harga Satuan Pekerjaan (D+E) 57,209.09

142 Pemasangan 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm, tebal 9 mm
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.10 132,000.00 13,200.00
Tukang kayu OH 0.05 188,571.44 9,428.57
Kepala tukang OH 0.01 200,000.00 1,000.00
Mandor OH 0.01 220,000.00 1,100.00
JUMLAH TENAGA KERJA 24,728.57
B BAHAN
Gypsum board Lembar 0.36 97,988.00 35,667.63
Paku skrup Kg 0.11 24,789.00 2,726.79
JUMLAH HARGA BAHAN 38,394.42
C PERALATAN

D Jumlah (A+B+C) 63,122.99


E Overhead & Profit 15% x D 9,468.45
F Harga Satuan Pekerjaan (D+E) 72,591.44

143 Pemasangan 1 m' list langit-langit kayu profil


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.05 132,000.00 6,600.00
Tukang Kayu OH 0.05 188,571.44 9,428.57
Kepala tukang OH 0.01 200,000.00 1,000.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 17,688.57
B BAHAN
List kayu profil M 1.05 21,000.00 22,050.00
Paku Kg 0.01 22,749.00 227.49
JUMLAH HARGA BAHAN 22,277.49
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 39,966.06


E Overhead & Profit 15% x D 5,994.91
F Harga Satuan Pekerjaan (D+E) 45,960.97

144 Pemasangan 1 m' list kangit-langit profil gypsum


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.05 132,000.00 6,600.00
Tukang Kayu OH 0.05 188,571.44 9,428.57
Kepala tukang OH 0.01 200,000.00 1,000.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 17,688.57
B BAHAN
List profil gypsum M 1.05 35,016.00 36,766.80
Paku Kg 0.01 24,789.00 247.89
JUMLAH HARGA BAHAN 37,014.69
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 54,703.26


E Overhead & Profit 15% x D 8,205.49
F Harga Satuan Pekerjaan (D+E) 62,908.75

145 Pemasangan 1 buah Body Kunci + Cylinder


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.01 132,000.00 660.00
Tukang kayu OH 0.50 188,571.44 94,285.72
Kepala tukang OH 0.05 200,000.00 10,000.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 105,605.72
B BAHAN
Kunci silinder Bh 1.00 355,000.00 355,000.00
JUMLAH HARGA BAHAN 355,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 460,605.72


E Overhead & Profit 15% x D 69,090.86
F Harga Satuan Pekerjaan (D+E) 529,696.58

146 Pemasangan 1 buah Body Kunci + Cylinder (KM/WC)


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.01 132,000.00 660.00
Tukang kayu OH 0.50 188,571.44 94,285.72
Kepala tukang OH 0.05 200,000.00 10,000.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 105,605.72
B BAHAN
Kunci silinder Bh 1.00 500,000.00 500,000.00
JUMLAH HARGA BAHAN 500,000.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 605,605.72
E Overhead & Profit 15% x D 90,840.86
F Harga Satuan Pekerjaan (D+E) 696,446.58

147 Pemasangan satu pasang engsel pintu


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.02 132,000.00 1,980.00
Tukang kayu OH 0.15 188,571.44 28,285.72
Kepala tukang OH 0.02 200,000.00 3,000.00
Mandor OH 0.00 220,000.00 176.00
JUMLAH TENAGA KERJA 33,441.72
B BAHAN
Engsel pintu Bh 1.00 228,000.00 228,000.00
JUMLAH HARGA BAHAN 228,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 261,441.72


E Overhead & Profit 15% x D 39,216.26
F Harga Satuan Pekerjaan (D+E) 300,657.97

148 Pemasangan satu pasang Lever Hendle


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.02 132,000.00 1,980.00
Tukang kayu OH 0.15 188,571.44 28,285.72
Kepala tukang OH 0.02 200,000.00 3,000.00
Mandor OH 0.00 220,000.00 176.00
JUMLAH TENAGA KERJA 33,441.72
B BAHAN
Lever Hendle Bh 1.00 340,000.00 340,000.00
JUMLAH HARGA BAHAN 340,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 373,441.72


E Overhead & Profit 15% x D 56,016.26
F Harga Satuan Pekerjaan (D+E) 429,457.97

149 Pemasangan satu pasang Flush Bolt


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.02 132,000.00 1,980.00
Tukang kayu OH 0.15 188,571.44 28,285.72
Kepala tukang OH 0.02 200,000.00 3,000.00
Mandor OH 0.00 220,000.00 176.00
JUMLAH TENAGA KERJA 33,441.72
B BAHAN
Flush Bolt Bh 1.00 85,000.00 85,000.00
JUMLAH HARGA BAHAN 85,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 118,441.72


E Overhead & Profit 15% x D 17,766.26
F Harga Satuan Pekerjaan (D+E) 136,207.97

150 Pemasangan 1 buah Engsel Casement


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.01 132,000.00 1,320.00
Tukang kayu OH 0.10 188,571.44 18,857.14
Kepala tukang OH 0.01 200,000.00 2,000.00
Mandor OH 0.00 220,000.00 110.00
JUMLAH TENAGA KERJA 22,287.14
B BAHAN
Engsel kupu-kupu Bh 1.00 52,000.00 52,000.00
JUMLAH HARGA BAHAN 52,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 74,287.14


E Overhead & Profit 15% x D 11,143.07
F Harga Satuan Pekerjaan (D+E) 85,430.22

151 Pemasangan 1 buah door closer


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.05 132,000.00 6,600.00
Tukang kayu OH 0.50 188,571.44 94,285.72
Kepala tukang OH 0.05 200,000.00 10,000.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 111,545.72
B BAHAN
Door closer Set 1.00 225,000.00 225,000.00
JUMLAH HARGA BAHAN 225,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 336,545.72


E Overhead & Profit 15% x D 50,481.86
F Harga Satuan Pekerjaan (D+E) 387,027.58

152 Pemasangan 1 buah Rambuncis


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.01 132,000.00 1,320.00
Tukang kayu OH 0.10 188,571.44 18,857.14
Kepala tukang OH 0.01 200,000.00 2,000.00
Mandor OH 0.01 220,000.00 1,100.00
JUMLAH TENAGA KERJA 23,277.14
B BAHAN
Rambuncis Bh 1.00 10,000.00 10,000.00
JUMLAH HARGA BAHAN 10,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 33,277.14


E Overhead & Profit 15% x D 4,991.57
F Harga Satuan Pekerjaan (D+E) 38,268.72

153 Pemasangan 1 m2 kaca tebal 5 mm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.02 132,000.00 1,980.00
Tukang kayu OH 0.15 188,571.44 28,285.72
Kepala tukang OH 0.02 200,000.00 3,000.00
Mandor OH 0.00 220,000.00 176.00
JUMLAH TENAGA KERJA 33,441.72
B BAHAN
Kaca tebal 5 mm M2 1.10 126,448.00 139,092.80
Sealant Kg 0.05 35,000.00 1,750.00
JUMLAH HARGA BAHAN 140,842.80
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 174,284.52


E Overhead & Profit 15% x D 26,142.68
F Harga Satuan Pekerjaan (D+E) 200,427.19

154 Pemasangan 1 m2 kaca es tebal 5 mm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.02 132,000.00 1,980.00
Tukang kayu OH 0.15 188,571.44 28,285.72
Kepala tukang OH 0.02 200,000.00 3,000.00
Mandor OH 0.00 220,000.00 176.00
JUMLAH TENAGA KERJA 33,441.72
B BAHAN
Kaca ryban tebal 6 mm M2 1.10 64,976.00 71,473.60
Sealant Kg 0.05 35,000.00 10,721.04
JUMLAH HARGA BAHAN 82,194.64
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 115,636.36


E Overhead & Profit 15% x D 17,345.45
F Harga Satuan Pekerjaan (D+E) 132,981.81

155 Pengecetan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.07 132,000.00 9,240.00
Tukang cat OH 0.01 188,571.44 1,697.14
Kepala tukang OH 0.01 200,000.00 1,200.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 12,797.14
B BAHAN
Cat menie Kg 0.20 33,864.00 6,772.80
Plamuur Kg 0.15 32,325.00 4,848.75
Cat dasar Kg 0.17 85,000.00 14,450.00
Cat penutup Kg 0.26 93,665.00 24,352.90
Kuas Bh 0.01 5,044.00 50.44
Pengencer Kg 0.03 31,271.00 938.13
Ampelas Lbr 0.20 10,808.00 2,161.60
JUMLAH HARGA BAHAN 53,574.62
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 66,371.76


E Overhead & Profit 15% x D 9,955.76
F Harga Satuan Pekerjaan (D+E) 76,327.53

156 Pengecetan 1 m2 tembok baru / Plapond Interior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.02 132,000.00 2,640.00
Tukang cat OH 0.06 188,571.44 11,880.00
Kepala tukang OH 0.01 200,000.00 1,260.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 16,440.00
B BAHAN
Plamuur Kg 0.10 50,435.00 5,043.50
Cat dasar Kg 0.10 33,143.00 3,314.30
Cat Tembok sek. Catylac Kg 0.26 33,143.00 8,617.18
JUMLAH HARGA BAHAN 16,974.98
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 33,414.98


E Overhead & Profit 15% x D 5,012.25
F Harga Satuan Pekerjaan (D+E) 38,427.23

157 Pengecetan 1 m2 tembok baru Interior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.02 132,000.00 2,640.00
Tukang cat OH 0.06 188,571.44 11,880.00
Kepala tukang OH 0.01 200,000.00 1,260.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 16,440.00
B BAHAN
Plamuur Kg 0.10 50,435.00 5,043.50
Cat Dinding sek. ICI Dulux (Interior) Pearl Glo - A913 L Kg 0.26 22,800.00 5,928.00
JUMLAH HARGA BAHAN 10,971.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 27,411.50


E Overhead & Profit 15% x D 4,111.73
F Harga Satuan Pekerjaan (D+E) 31,523.23

158 Pengecetan 1 m2 tembok baru Exterior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.02 132,000.00 2,640.00
Tukang cat OH 0.06 188,571.44 11,880.00
Kepala tukang OH 0.01 200,000.00 1,260.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 16,440.00
B BAHAN
Alkali Resisting Primer A931 - 1050 N Kg 0.10 33,400.00 3,340.00
Cat Dinding sek. ICI Dulux (Exterior) Weather Shield MAX - A 194 Kg 0.26 31,400.00 8,164.00
JUMLAH HARGA BAHAN 11,504.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 27,944.00


E Overhead & Profit 15% x D 4,191.60
F Harga Satuan Pekerjaan (D+E) 32,135.60

159 Finishing melamik 1 m2


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.42 132,000.00 55,440.00
Tukang cat OH 0.36 188,571.44 67,885.72
Kepala tukang OH 0.04 200,000.00 7,200.00
Mandor OH 0.02 220,000.00 4,620.00
JUMLAH TENAGA KERJA 135,145.72
B BAHAN
Wood Filler Kg 0.28 33,143.00 9,280.04
Wood Stain Kg 0.40 33,143.00 13,257.20
Melamin Sending Siller MSS 123 Kg 0.22 - -
ML 131 Clear Danagloss Kg 0.22 - -
Tiner Ltr 1.30 70,969.00 92,259.70
Ampelas Lbr 4.00 10,808.00 43,232.00
Kwas 3" Bh 0.50 5,044.00 2,522.00
JUMLAH HARGA BAHAN 160,550.94
C PERALATAN
Alat bantu Ls 1.00 10,000.00 10,000.00
JUMLAH HARGA ALAT 10,000.00

D Jumlah (A+B+C) 305,696.66


E Overhead & Profit 15% x D 45,854.50
F Harga Satuan Pekerjaan (D+E) 351,551.16

160 Pengecatan 1 m2 permukaan besi secara manual sistem 3 lapis


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.07 132,000.00 9,240.00
Tukang cat OH 0.01 188,571.44 1,697.14
Kepala tukang OH 0.01 200,000.00 1,200.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 12,797.14
B BAHAN
Cat menie Kg 0.20 33,864.00 6,772.80
Plamuur Besi Kg 0.15 32,325.00 4,848.75
Cat dasar Kg 0.17 141,218.00 24,007.06
Cat penutup Kg 0.26 141,218.00 36,716.68
Kuas Bh 0.01 5,044.00 50.44
Tiner Kg 0.03 70,969.00 2,129.07
Ampelas Lbr 0.20 10,808.00 2,161.60
JUMLAH HARGA BAHAN 76,686.40
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 89,483.54


E Overhead & Profit 15% x D 13,422.53
F Harga Satuan Pekerjaan (D+E) 102,906.07

161 Pemasangan 1 buah closet duduk/monoblock


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 3.30 132,000.00 435,600.00
Tukang batu OH 1.10 188,571.44 207,428.58
Kepala tukang OH 0.01 200,000.00 2,000.00
Mandor OH 0.16 220,000.00 35,200.00
JUMLAH TENAGA KERJA 680,228.58
B BAHAN
Closet duduk Unit 1.00 2,689,000.00 2,689,000.00
Perlengkapan % 0.06 2,689,000.00 161,340.00
JUMLAH HARGA BAHAN 2,850,340.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 3,530,568.58


E Overhead & Profit 15% x D 529,585.29
F Harga Satuan Pekerjaan (D+E) 4,060,153.87

162 Pemasangan 1 buah closet jongkok porslen


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.00 132,000.00 132,000.00
Tukang batu OH 1.50 188,571.44 282,857.16
Kepala tukang OH 0.15 200,000.00 30,000.00
Mandor OH 0.16 220,000.00 35,200.00
JUMLAH TENAGA KERJA 480,057.16
B BAHAN
Closet jongkok Unit 1.00 355,000.00 355,000.00
Semen Portland Kg 6.00 1,585.10 9,510.60
Pasir pasang M3 0.01 216,150.00 2,161.50
JUMLAH HARGA BAHAN 366,672.10
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 846,729.26


E Overhead & Profit 15% x D 127,009.39
F Harga Satuan Pekerjaan (D+E) 973,738.65

163 Pemasangan 1 buah urinoir


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.00 132,000.00 132,000.00
Tukang batu OH 1.00 188,571.44 188,571.44
Kepala tukang OH 0.10 200,000.00 20,000.00
Mandor OH 0.05 220,000.00 11,000.00
JUMLAH TENAGA KERJA 351,571.44
B BAHAN
Urinoir Unit 1.00 2,676,506.00 2,676,506.00
Semen Portland Kg 6.00 1,585.10 9,510.60
Pasir pasang M3 0.01 216,150.00 2,161.50
Perlengkapan % 0.30 2,676,506.00 802,951.80
JUMLAH HARGA BAHAN 3,491,129.90
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 3,842,701.34


E Overhead & Profit 15% x D 576,405.20
F Harga Satuan Pekerjaan (D+E) 4,419,106.54
164 Pemasangan 1 buah wastafel meja
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.20 132,000.00 158,400.00
Tukang batu OH 1.45 188,571.44 273,428.59
Kepala tukang OH 0.15 200,000.00 30,000.00
Mandor OH 0.06 220,000.00 13,200.00
JUMLAH TENAGA KERJA 475,028.59
B BAHAN
Wastafel Unit 1.00 1,150,000.00 1,150,000.00
Semen Portland Kg 6.00 1,585.10 9,510.60
Pasir pasang M3 0.01 216,150.00 2,161.50
Perlengkapan % 0.12 1,150,000.00 138,000.00
JUMLAH HARGA BAHAN 1,299,672.10
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,774,700.69


E Overhead & Profit 15% x D 266,205.10
F Harga Satuan Pekerjaan (D+E) 2,040,905.79

165 Pemasangan 1 buah wastafel gantung


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.20 132,000.00 158,400.00
Tukang batu OH 1.45 188,571.44 273,428.59
Kepala tukang OH 0.15 200,000.00 30,000.00
Mandor OH 0.06 220,000.00 13,200.00
JUMLAH TENAGA KERJA 475,028.59
B BAHAN
Wastafel Unit 1.00 390,000.00 390,000.00
Semen Portland Kg 6.00 1,585.10 9,510.60
Pasir pasang M3 0.01 216,150.00 2,161.50
Perlengkapan % 0.12 390,000.00 46,800.00
JUMLAH HARGA BAHAN 448,472.10
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 923,500.69


E Overhead & Profit 15% x D 138,525.10
F Harga Satuan Pekerjaan (D+E) 1,062,025.79

166 Pemasangan 1 buah bak fibreglass vol 1 m3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.30 132,000.00 39,600.00
Tukang batu OH 0.45 188,571.44 84,857.15
Kepala tukang OH 0.05 200,000.00 9,000.00
Mandor OH 0.02 220,000.00 3,300.00
JUMLAH TENAGA KERJA 136,757.15
B BAHAN
Bak fibreglass Unit 1.00 335,000.00 335,000.00
Perlengkapan % 0.12 335,000.00 40,200.00
JUMLAH HARGA BAHAN 375,200.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 511,957.15


E Overhead & Profit 15% x D 76,793.57
F Harga Satuan Pekerjaan (D+E) 588,750.72

167 Pemasangan 1 buah floor drain


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.01 132,000.00 1,320.00
Tukang batu OH 0.10 188,571.44 18,857.14
Kepala tukang OH 0.01 200,000.00 2,000.00
Mandor OH 0.01 220,000.00 1,100.00
JUMLAH TENAGA KERJA 23,277.14
B BAHAN
Floor drain Unit 1.00 86,460.00 86,460.00
JUMLAH HARGA BAHAN 86,460.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 109,737.14


E Overhead & Profit 15% x D 16,460.57
F Harga Satuan Pekerjaan (D+E) 126,197.72

168 Pemasangan 1 buah bak kontrol pasangan bata 30x30 tinggi 35 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 2.16 132,000.00 285,120.00
Tukang batu OH 0.72 188,571.44 135,771.44
Kepala tukang OH 0.07 200,000.00 14,400.00
Mandor OH 0.01 220,000.00 2,420.00
JUMLAH TENAGA KERJA 437,711.44
B BAHAN
Bata merah Bh 40.00 590.00 23,600.00
Semen portland Kg 44.00 1,585.10 69,744.40
Pasir pasang M3 0.07 216,150.00 15,130.50
Pasir beton M3 0.06 396,275.00 23,776.50
Kerikil M3 0.07 338,635.00 23,704.45
Baja tulangan Kg 1.60 14,122.00 22,595.20
JUMLAH HARGA BAHAN 178,551.05
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 616,262.49


E Overhead & Profit 15% x D 92,439.37
F Harga Satuan Pekerjaan (D+E) 708,701.86

169 Pemasangan 1 buah kran diameter 1/2" atau 3/4"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.01 132,000.00 1,320.00
Tukang batu OH 0.40 188,571.44 75,428.58
Kepala tukang OH 0.04 200,000.00 8,000.00
Mandor OH 0.01 220,000.00 1,100.00
JUMLAH TENAGA KERJA 85,848.58
B BAHAN
Kran air M 1.00 183,000.00 183,000.00
Sealtape Buah 0.03 7,957.00 198.93
JUMLAH HARGA BAHAN 183,198.93
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 269,047.50


E Overhead & Profit 15% x D 40,357.13
F Harga Satuan Pekerjaan (D+E) 309,404.63

170 Pemasangan 1 buah kran leher angsa diameter 1/2" atau 3/4"
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.01 132,000.00 1,320.00
Tukang batu OH 0.40 188,571.44 75,428.58
Kepala tukang OH 0.04 200,000.00 8,000.00
Mandor OH 0.01 220,000.00 1,100.00
JUMLAH TENAGA KERJA 85,848.58
B BAHAN
Kran air M 1.00 652,000.00 652,000.00
Sealtape Buah 0.03 7,957.00 198.93
JUMLAH HARGA BAHAN 652,198.93
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 738,047.50
E Overhead & Profit 15% x D 110,707.13
F Harga Satuan Pekerjaan (D+E) 848,754.63

171 Pemasangan 1 buah jet washer


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.01 132,000.00 1,320.00
Tukang batu OH 0.40 188,571.44 75,428.58
Kepala tukang OH 0.04 200,000.00 8,000.00
Mandor OH 0.01 220,000.00 1,100.00
JUMLAH TENAGA KERJA 85,848.58
B BAHAN
Jet washer M 1.00 274,000.00 274,000.00
Sealtape Buah 0.03 7,957.00 198.93
JUMLAH HARGA BAHAN 274,198.93
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 360,047.50


E Overhead & Profit 15% x D 54,007.13
F Harga Satuan Pekerjaan (D+E) 414,054.63

172 Pemasangan 1 m' pipa PVC tipe AW diameter 1/2"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.04 132,000.00 4,752.00
Tukang batu OH 0.06 188,571.44 11,314.29
Kepala tukang OH 0.01 200,000.00 1,200.00
Mandor OH 0.00 220,000.00 440.00
JUMLAH TENAGA KERJA 17,706.29
B BAHAN
Pipa PVC 1/2” M 1.20 5,825.00 6,990.00
Perlengkapan % 0.35 6,990.00 2,446.50
JUMLAH HARGA BAHAN 9,436.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 27,142.79


E Overhead & Profit 15% x D 4,071.42
F Harga Satuan Pekerjaan (D+E) 31,214.20

173 Pemasangan 1 m' pipa PVC tipe AW diameter 3/4"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.04 132,000.00 4,752.00
Tukang batu OH 0.06 188,571.44 11,314.29
Kepala tukang OH 0.01 200,000.00 1,200.00
Mandor OH 0.00 220,000.00 440.00
JUMLAH TENAGA KERJA 17,706.29
B BAHAN
Pipa PVC 3/4” M 1.20 7,925.00 9,510.00
Perlengkapan % 0.35 9,510.00 3,328.50
JUMLAH HARGA BAHAN 12,838.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 30,544.79


E Overhead & Profit 15% x D 4,581.72
F Harga Satuan Pekerjaan (D+E) 35,126.50

174 Pemasangan 1 m' pipa PVC tipe AW diameter 1"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.04 132,000.00 4,752.00
Tukang batu OH 0.06 188,571.44 11,314.29
Kepala tukang OH 0.01 200,000.00 1,200.00
Mandor OH 0.00 220,000.00 440.00
JUMLAH TENAGA KERJA 17,706.29
B BAHAN
Pipa PVC 1” M 1.20 10,825.00 12,990.00
Perlengkapan % 0.35 12,990.00 4,546.50
JUMLAH HARGA BAHAN 17,536.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 35,242.79


E Overhead & Profit 15% x D 5,286.42
F Harga Satuan Pekerjaan (D+E) 40,529.20

175 Pemasangan 1 m' pipa PVC tipe AW diameter 1,1/4"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.04 132,000.00 4,752.00
Tukang batu OH 0.06 188,571.44 11,314.29
Kepala tukang OH 0.01 200,000.00 1,200.00
Mandor OH 0.00 220,000.00 440.00
JUMLAH TENAGA KERJA 17,706.29
B BAHAN
Pipa PVC 1,1/4” M 1.20 16,200.00 19,440.00
Perlengkapan % 0.35 19,440.00 6,804.00
JUMLAH HARGA BAHAN 26,244.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 43,950.29


E Overhead & Profit 15% x D 6,592.54
F Harga Satuan Pekerjaan (D+E) 50,542.83

176 Pemasangan 1 m' pipa PVC tipe AW diameter 1,5"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.05 132,000.00 7,128.00
Tukang batu OH 0.09 188,571.44 16,971.43
Kepala tukang OH 0.01 200,000.00 1,800.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 26,559.43
B BAHAN
Pipa PVC 1,5” M 1.20 18,600.00 22,320.00
Perlengkapan % 0.35 22,320.00 7,812.00
JUMLAH HARGA BAHAN 30,132.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 56,691.43


E Overhead & Profit 15% x D 8,503.71
F Harga Satuan Pekerjaan (D+E) 65,195.14

177 Pemasangan 1 m' pipa PVC tipe AW diameter 2"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.05 132,000.00 7,128.00
Tukang batu OH 0.09 188,571.44 16,971.43
Kepala tukang OH 0.01 200,000.00 1,800.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 26,559.43
B BAHAN
Pipa PVC 2” M 1.20 34,725.00 41,670.00
Perlengkapan % 0.35 41,670.00 14,584.50
JUMLAH HARGA BAHAN 56,254.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 82,813.93


E Overhead & Profit 15% x D 12,422.09
F Harga Satuan Pekerjaan (D+E) 95,236.02

178 Pemasangan 1 m' pipa PVC tipe AW diameter 2,5"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.08 132,000.00 10,692.00
Tukang batu OH 0.14 188,571.44 25,457.14
Kepala tukang OH 0.01 200,000.00 2,700.00
Mandor OH 0.00 220,000.00 880.00
JUMLAH TENAGA KERJA 39,729.14
B BAHAN
Pipa PVC 2,5” M 1.20 34,725.00 41,670.00
Perlengkapan % 0.35 41,670.00 14,584.50
JUMLAH HARGA BAHAN 56,254.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 95,983.64


E Overhead & Profit 15% x D 14,397.55
F Harga Satuan Pekerjaan (D+E) 110,381.19

179 Pemasangan 1 m' pipa PVC tipe AW diameter 3"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.08 132,000.00 10,692.00
Tukang batu OH 0.14 188,571.44 25,457.14
Kepala tukang OH 0.01 200,000.00 2,700.00
Mandor OH 0.00 220,000.00 880.00
JUMLAH TENAGA KERJA 39,729.14
B BAHAN
Pipa PVC 3” M 1.20 48,900.00 58,680.00
Perlengkapan % 0.35 58,680.00 20,538.00
JUMLAH HARGA BAHAN 79,218.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 118,947.14


E Overhead & Profit 15% x D 17,842.07
F Harga Satuan Pekerjaan (D+E) 136,789.22

180 Pemasangan 1 m' pipa PVC tipe AW diameter 4"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.08 132,000.00 10,692.00
Tukang batu OH 0.14 188,571.44 25,457.14
Kepala tukang OH 0.01 200,000.00 2,700.00
Mandor OH 0.00 220,000.00 880.00
JUMLAH TENAGA KERJA 39,729.14
B BAHAN
Pipa PVC 4” M 1.20 81,025.00 97,230.00
Perlengkapan % 0.35 97,230.00 34,030.50
JUMLAH HARGA BAHAN 131,260.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 170,989.64


E Overhead & Profit 15% x D 25,648.45
F Harga Satuan Pekerjaan (D+E) 196,638.09

181 Pemasangan 1 m' pipa PVC tipe AW diameter 6"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.08 132,000.00 10,692.00
Tukang batu OH 0.14 188,571.44 25,457.14
Kepala tukang OH 0.01 200,000.00 2,700.00
Mandor OH 0.00 220,000.00 880.00
JUMLAH TENAGA KERJA 39,729.14
B BAHAN
Pipa PVC 6” M 1.20 180,050.00 216,060.00
Perlengkapan % 0.35 216,060.00 75,621.00
JUMLAH HARGA BAHAN 291,681.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 331,410.14


E Overhead & Profit 15% x D 49,711.52
F Harga Satuan Pekerjaan (D+E) 381,121.67

182 Pemasangan 1 m' pipa PVC tipe AW diameter 8"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.08 132,000.00 10,692.00
Tukang batu OH 0.14 188,571.44 25,457.14
Kepala tukang OH 0.01 200,000.00 2,700.00
Mandor OH 0.00 220,000.00 880.00
JUMLAH TENAGA KERJA 39,729.14
B BAHAN
Pipa PVC 8” M 1.20 302,150.00 362,580.00
Perlengkapan % 0.35 362,580.00 126,903.00
JUMLAH HARGA BAHAN 489,483.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 529,212.14


E Overhead & Profit 15% x D 79,381.82
F Harga Satuan Pekerjaan (D+E) 608,593.97
183 Pemasangan 1 m2 Coating Waterproofing
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.12 132,000.00 15,840.00
Tukang OH 0.12 188,571.44 22,628.57
Kepala tukang OH 0.01 200,000.00 2,400.00
Mandor OH 0.01 220,000.00 1,320.00
JUMLAH TENAGA KERJA 42,188.57
B BAHAN
Waterproofing m2 1.05 68,900.00 72,345.00
JUMLAH HARGA BAHAN 72,345.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 114,533.57


E Overhead & Profit 15% x D 17,180.04
F Harga Satuan Pekerjaan (D+E) 131,713.61
184 Pemasangan 1 m2 Lantai parquet
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.70 132,000.00 92,400.00
Tukang Kayu OH 0.35 188,571.44 66,000.00
Kepala tukang kayu OH 0.04 200,000.00 7,000.00
Mandor OH 0.04 220,000.00 7,700.00
JUMLAH TENAGA KERJA 173,100.00
B BAHAN
Parquet Jati m2 1.05 147,550.00 154,927.50
Lem Vinyl m2 0.60 65,600.00 39,360.00
JUMLAH HARGA BAHAN 194,287.50
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 367,387.50


E Overhead & Profit 15% x D 55,108.13
F Harga Satuan Pekerjaan (D+E) 422,495.63
185 Pemasangan 1 m2 langit-langit Calsiboard t = 9 mm rangka hollow galvanis
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.20 132,000.00 26,400.00
Tukang Kayu OH 0.05 188,571.44 9,428.57
Tukang Besi OH 0.23 188,571.44 42,428.57
Kepala tukang kayu OH 0.03 200,000.00 5,500.00
Mandor OH 0.01 220,000.00 2,200.00
JUMLAH TENAGA KERJA 85,957.15
B BAHAN
Hollow 40x40 mm m' 1.83 5,666.67 10,370.00
Hollow 20x20 mm m' 1.83 4,583.33 8,387.50
Pake sekrup kg 0.20 24,789.00 4,957.80
Calsiboard t = 9 mm lbr 0.36 82,500.00 30,030.00
Gypsum tape roll 0.05 29,800.00 1,490.00
Paku Gypsum kg 0.11 25,600.00 2,816.00
JUMLAH HARGA BAHAN 58,051.30
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 144,008.45


E Overhead & Profit 15% x D 21,601.27
F Harga Satuan Pekerjaan (D+E) 165,609.71
186 Pemasangan 1 m2 Ornamen GRC t = 9 mm rangka hollow galvanis
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.00 132,000.00 132,000.00
Tukang Kayu OH 0.50 188,571.44 94,285.72
Tukang Besi OH 0.25 188,571.44 47,142.86
Kepala tukang kayu OH 0.13 200,000.00 25,000.00
Mandor OH 0.08 220,000.00 17,600.00
JUMLAH TENAGA KERJA 316,028.58
B BAHAN
Hollow 40x40 mm m' 5.00 5,666.67 28,333.33
Hollow 20x20 mm m' 2.00 4,583.33 9,166.67
Pake sekrup kg 0.60 24,789.00 14,873.40
Calsiboard t = 9 mm lbr 3.84 82,500.00 316,800.00
Gypsum tape roll 0.50 29,800.00 14,900.00
Paku Gypsum kg 0.90 25,600.00 23,040.00
JUMLAH HARGA BAHAN 407,113.40
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 723,141.98


E Overhead & Profit 15% x D 108,471.30
F Harga Satuan Pekerjaan (D+E) 831,613.28

187 Pemasangan 1 m3 Base Coarse CBR 80% Kelas A


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 1.00 132,000.00 132,000.00
Mandor OH 0.10 220,000.00 22,000.00
JUMLAH TENAGA KERJA 154,000.00
B BAHAN
Batu + Pasir Urug M3 1.10 497,145.00 546,859.50
JUMLAH HARGA BAHAN 546,859.50
C PERALATAN
Biaya Pemadatan M3 1.00 88,550.00 88,550.00
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 700,859.50


E Overhead & Profit 15% x D 105,128.93
F Harga Satuan Pekerjaan (D+E) 805,988.43

188 Pemasangan 1 m2 Lapisan Hotmix T = 5 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.13 132,000.00 17,160.00
Tukang OH 0.06 188,571.44 11,314.29
Kepala tukang OH 0.00 200,000.00 400.00
Mandor OH 0.00 220,000.00 220.00
JUMLAH TENAGA KERJA 29,094.29
B BAHAN
Screan + Split 1/2 M3 0.03 256,700.00 6,776.88
Aspal Kg 5.00 14,550.00 72,750.00
Kayu Bakar M3 0.02 1,565,700.00 25,051.20
JUMLAH HARGA BAHAN 104,578.08
C PERALATAN
Peralatan Bantu ls 1.00 20,915.62 20,915.62
JUMLAH HARGA ALAT 20,915.62

D Jumlah (A+B+C) 154,587.98


E Overhead & Profit 15% x D 23,188.20
F Harga Satuan Pekerjaan (D+E) 177,776.18

189 Pemasangan 1 m2 Prime Coat


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.03 132,000.00 4,290.00
Tukang OH 0.02 188,571.44 2,828.57
Kepala tukang OH 0.01 200,000.00 1,000.00
Mandor OH 0.00 220,000.00 660.00
JUMLAH TENAGA KERJA 8,778.57
B BAHAN
Prime Coat ltr 2.50 6,750.00 16,875.00
JUMLAH HARGA BAHAN 16,875.00
C PERALATAN
Peralatan Bantu ls 0.20 3,375.00 675.00
JUMLAH HARGA ALAT 675.00

D Jumlah (A+B+C) 26,328.57


E Overhead & Profit 15% x D 3,949.29
F Harga Satuan Pekerjaan (D+E) 30,277.86

190 Pemasangan 1 m3 U-DITCH uk. 40x40 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
JUMLAH TENAGA KERJA
B BAHAN
Beton K-300 M3 1.00 1,574,858.47 1,574,858.47
Pembesian Kg 69.97 20,479.27 1,432,975.42
Bekisting Plat M2 25.00 229,264.13 5,731,603.24
JUMLAH HARGA BAHAN 8,739,437.12
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) ( include. Keuntungan pemborong ) 8,739,437.12


F Harga Satuan Pekerjaan (D+E) per M3 8,739,437.12
Harga Satuan Pekerjaan (D+E) per M1 Err:540

191 Pemasangan 1 m3 U-DITCH uk. 40x40 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
JUMLAH TENAGA KERJA
B BAHAN
Beton K-300 M3 1.00 1,574,858.47 1,574,858.47
Pembesian Kg 96.29 20,479.27 1,971,850.52
Bekisting Plat M2 12.50 229,264.13 2,865,801.62
JUMLAH HARGA BAHAN 6,412,510.61
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) ( include. Keuntungan pemborong ) 6,412,510.61


F Harga Satuan Pekerjaan (D+E) per M3 6,412,510.61
Harga Satuan Pekerjaan (D+E) per M1 Err:540

192 Pemasangan 1 m1 Pasangan Cansteen 15x30x60 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
(Rp) (Rp)
A TENAGA
Pekerja OH 0.25 132,000.00 33,000.00
Tukang OH 0.15 188,571.44 28,285.72
Kepala tukang OH 0.02 200,000.00 4,000.00
Mandor OH 0.00 220,000.00 440.00
JUMLAH TENAGA KERJA 65,725.72
B BAHAN
Cansteen 15x30x60 cm bh 1.67 39,800.00 66,334.66
Pas. Spesi 1 : 3 m2 0.17 47,700.00 7,899.12
JUMLAH HARGA BAHAN 66,334.66
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 132,060.38


E Overhead & Profit 15% x D 19,809.06
F Harga Satuan Pekerjaan (D+E) 151,869.43

ANALISA HARGA SATUAN PEKERJAAN ME

NO KOEF SAT HARGA SATUAN JUMLAH HARGA SATUAN

a c d e

1 Air Trap
MATERIAL
Air Trap 1.00 bh 670,000.00 670,000.00
Material bantu 1.00 Lot 33,500.00 33,500.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 752,825.72
Overhead + Keuntungan Max 10% 75,282.57
Jumlah keseluruhan 828,108.29
DIBULATKAN 828,100.00

2 Automatic air vent Ø 25 mm


MATERIAL
Automatic air vent Ø 25 mm 1.00 bh 725,000.00 725,000.00
Material bantu 1.00 Lot 36,250.00 725,000.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 1,499,325.72
Overhead + Keuntungan Max 10% 149,932.57
Jumlah keseluruhan 1,649,258.29
DIBULATKAN 1,649,200.00

3 Check valve Ø 100 mm Cast iron, 300 Lbs, JIS 20 K


MATERIAL
Check valve Ø 100 mm Cast iron, 300 Lbs, JIS 20 K 1.00 bh 13,722,800.00 13,722,800.00
Material bantu 1.00 Lot 686,140.00 686,140.00
UPAH KERJA
Pekerja 0.45 oh 132,000.00 59,400.00
Tukang Pipa 0.23 oh 188,571.44 42,428.57
Kepala Tukang Pipa 0.14 oh 200,000.00 27,000.00
Mandor 0.05 oh 220,000.00 9,900.00
Jumlah 14,547,668.57
Overhead + Keuntungan Max 10% 1,454,766.86
Jumlah keseluruhan 16,002,435.43
DIBULATKAN 16,002,400.00

4 Check valve Ø 65mm


MATERIAL
Check valve Ø 65mm 1.00 bh 2,267,900.00 2,267,900.00
Material bantu 1.00 Lot 113,395.00 113,395.00
UPAH KERJA
Pekerja 0.45 oh 132,000.00 59,400.00
Tukang Pipa 0.23 oh 188,571.44 42,428.57
Kepala Tukang Pipa 0.14 oh 200,000.00 27,000.00
Mandor 0.05 oh 220,000.00 9,900.00
Jumlah 2,520,023.57
Overhead + Keuntungan Max 10% 252,002.36
Jumlah keseluruhan 2,772,025.93
DIBULATKAN 2,772,000.00

5 Check valve Ø 50mm


MATERIAL
Check valve Ø 50mm 1.00 bh 1,784,300.00 1,784,300.00
Material bantu 1.00 Lot 89,215.00 89,215.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 1,922,840.72
Overhead + Keuntungan Max 10% 192,284.07
Jumlah keseluruhan 2,115,124.79
DIBULATKAN 2,115,100.00

6 Flexible Joint Ø 65 mm
MATERIAL
Flexible Joint Ø 65 mm 1.00 bh 497,200.00 497,200.00
Material bantu 1.00 Lot 24,860.00 24,860.00
UPAH KERJA
Pekerja 0.45 oh 132,000.00 59,400.00
Tukang Pipa 0.23 oh 188,571.44 42,428.57
Kepala Tukang Pipa 0.14 oh 200,000.00 27,000.00
Mandor 0.05 oh 220,000.00 9,900.00
Jumlah 660,788.57
Overhead + Keuntungan Max 10% 66,078.86
Jumlah keseluruhan 726,867.43
DIBULATKAN 726,800.00

7 Flexible Joint Ø 50 mm
MATERIAL
Flexible Joint Ø 50 mm 1.00 bh 405,400.00 405,400.00
Material bantu 1.00 Lot 20,270.00 20,270.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 474,995.72
Overhead + Keuntungan Max 10% 47,499.57
Jumlah keseluruhan 522,495.29
DIBULATKAN 522,400.00

8 Gate Valve Ø 100 mm


MATERIAL
Gate Valve Ø 100 mm 1.00 bh 3,669,300.00 3,669,300.00
Material bantu 1.00 Lot 183,465.00 183,465.00
UPAH KERJA
Pekerja 0.45 oh 132,000.00 59,400.00
Tukang Pipa 0.23 oh 188,571.44 42,428.57
Kepala Tukang Pipa 0.14 oh 200,000.00 27,000.00
Mandor 0.05 oh 220,000.00 9,900.00
Jumlah 3,991,493.57
Overhead + Keuntungan Max 10% 399,149.36
Jumlah keseluruhan 4,390,642.93
DIBULATKAN 4,390,600.00

9 Gate valve Ø 65mm Air Bersih


MATERIAL
Gate valve Ø 65mm Air Bersih 1.00 bh 2,160,000.00 1,050,000.00
Material bantu 1.00 Lot 52,500.00 52,500.00
UPAH KERJA
Pekerja 0.45 oh 132,000.00 59,400.00
Tukang Pipa 0.23 oh 188,571.44 42,428.57
Kepala Tukang Pipa 0.14 oh 200,000.00 27,000.00
Mandor 0.05 oh 220,000.00 9,900.00
Jumlah 1,241,228.57
Overhead + Keuntungan Max 10% 124,122.86
Jumlah keseluruhan 1,365,351.43
DIBULATKAN 1,365,300.00

10 Gate valve Ø 50mm


MATERIAL
Gate valve Ø 50mm 1.00 bh 452,400.00 452,400.00
Material bantu 1.00 Lot 22,620.00 22,620.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 524,345.72
Overhead + Keuntungan Max 10% 52,434.57
Jumlah keseluruhan 576,780.29
DIBULATKAN 576,700.00

11 Gate valve Ø 25 mm
MATERIAL
Gate valve Ø 25 mm 1.00 bh 175,500.00 175,500.00
Material bantu 1.00 Lot 8,775.00 8,775.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 233,600.72
Overhead + Keuntungan Max 10% 23,360.07
Jumlah keseluruhan 256,960.79
DIBULATKAN 256,900.00

12 Gate valve Ø 20mm


MATERIAL
Gate valve Ø 20mm 1.00 bh 124,200.00 124,200.00
Material bantu 1.00 Lot 6,210.00 6,210.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 179,735.72
Overhead + Keuntungan Max 10% 17,973.57
Jumlah keseluruhan 197,709.29
DIBULATKAN 197,700.00

13 Gate valve Ø 15 mm
MATERIAL
Gate valve Ø 15 mm 1.00 bh 102,700.00 102,700.00
Material bantu 1.00 Lot 5,135.00 5,135.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 157,160.72
Overhead + Keuntungan Max 10% 15,716.07
Jumlah keseluruhan 172,876.79
DIBULATKAN 172,800.00
14 Kran Taman Ø 15 mm lengkap Pondasi
MATERIAL
Kran Taman Ø 15 mm lengkap Pondasi 1.00 bh 175,000.00 175,000.00
Material bantu 1.00 Lot 8,750.00 8,750.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 233,075.72
Overhead + Keuntungan Max 10% 23,307.57
Jumlah keseluruhan 256,383.29
DIBULATKAN 256,300.00

15 Strainer Ø 65mm
MATERIAL
Strainer Ø 65mm 1.00 bh 2,317,300.00 2,317,300.00
Material bantu 1.00 Lot 115,865.00 115,865.00
UPAH KERJA
Pekerja 0.45 oh 132,000.00 59,400.00
Tukang Pipa 0.23 oh 188,571.44 42,428.57
Kepala Tukang Pipa 0.14 oh 200,000.00 27,000.00
Mandor 0.05 oh 220,000.00 9,900.00
Jumlah 2,571,893.57
Overhead + Keuntungan Max 10% 257,189.36
Jumlah keseluruhan 2,829,082.93
DIBULATKAN 2,829,000.00

16 Anti Vortex Plate Ø 65 mm


MATERIAL
Anti Vortex Plate Ø 65 mm 1.00 bh 217,700.00 217,700.00
Material bantu 1.00 Lot 10,885.00 10,885.00
UPAH KERJA
Pekerja 0.45 oh 132,000.00 59,400.00
Tukang Pipa 0.23 oh 188,571.44 42,428.57
Kepala Tukang Pipa 0.14 oh 200,000.00 27,000.00
Mandor 0.05 oh 220,000.00 9,900.00
Jumlah 367,313.57
Overhead + Keuntungan Max 10% 36,731.36
Jumlah keseluruhan 404,044.93
DIBULATKAN 404,000.00

17 Pipa bs sch 40 Ø 150 mm


MATERIAL
Pipa bs sch 40 Ø 150 mm 1.00 bh 570,500.00 570,500.00
Material bantu 1.00 Lot 28,525.00 28,525.00
UPAH KERJA
Pekerja 0.20 oh 132,000.00 26,400.00
Tukang Pipa 0.10 oh 188,571.44 18,857.14
Kepala Tukang Pipa 0.06 oh 200,000.00 12,000.00
Mandor 0.02 oh 220,000.00 4,400.00
Jumlah 660,682.14
Overhead + Keuntungan Max 10% 66,068.21
Jumlah keseluruhan 726,750.36
DIBULATKAN 726,700.00

18 Pipa bs sch 40 Ø 100 mm


MATERIAL
Pipa bs sch 40 Ø 100 mm 1.00 bh 326,166.67 326,166.67
Material bantu 1.00 Lot 16,308.33 16,308.33
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 391,800.72
Overhead + Keuntungan Max 10% 39,180.07
Jumlah keseluruhan 430,980.79
DIBULATKAN 430,900.00
19 Pipa bs sch 40 Ø 80 mm
MATERIAL
Pipa bs sch 40 Ø 80 mm 1.00 bh 229,333.33 229,333.33
Material bantu 1.00 Lot 11,466.67 11,466.67
UPAH KERJA
Pekerja 0.13 oh 132,000.00 16,896.00
Tukang Pipa 0.06 oh 188,571.44 12,068.57
Kepala Tukang Pipa 0.04 oh 200,000.00 7,680.00
Mandor 0.01 oh 220,000.00 2,816.00
Jumlah 280,260.57
Overhead + Keuntungan Max 10% 28,026.06
Jumlah keseluruhan 308,286.63
DIBULATKAN 308,200.00

20 Pipa bs sch 40 Ø 65 mm
MATERIAL
Pipa bs sch 40 Ø 65 mm 1.00 bh 206,400.00 206,400.00
Material bantu 1.00 Lot 10,320.00 10,320.00
UPAH KERJA
Pekerja 0.10 oh 132,000.00 13,516.80
Tukang Pipa 0.05 oh 188,571.44 9,654.86
Kepala Tukang Pipa 0.03 oh 200,000.00 6,144.00
Mandor 0.01 oh 220,000.00 2,252.80
Jumlah 248,288.46
Overhead + Keuntungan Max 10% 24,828.85
Jumlah keseluruhan 273,117.30
DIBULATKAN 273,100.00

21 Pipa bs sch 40 Ø 40 mm
MATERIAL
Pipa bs sch 40 Ø 40 mm 1.00 bh 165,120.00 165,120.00
Material bantu 1.00 Lot 8,256.00 8,256.00
UPAH KERJA
Pekerja 0.08 oh 132,000.00 10,813.44
Tukang Pipa 0.04 oh 188,571.44 7,723.89
Kepala Tukang Pipa 0.02 oh 200,000.00 4,915.20
Mandor 0.01 oh 220,000.00 1,802.24
Jumlah 198,630.77
Overhead + Keuntungan Max 10% 19,863.08
Jumlah keseluruhan 218,493.84
DIBULATKAN 218,400.00

22 Pipa galv medium Ø 20 mm


MATERIAL
Pipa galv medium Ø 20 mm 1.00 bh 42,166.67 42,166.67
Material bantu 1.00 Lot 2,108.33 2,108.33
UPAH KERJA
Pekerja 0.07 oh 132,000.00 8,650.75
Tukang Pipa 0.03 oh 188,571.44 6,179.11
Kepala Tukang Pipa 0.02 oh 200,000.00 3,932.16
Mandor 0.01 oh 220,000.00 1,441.79
Jumlah 64,478.81
Overhead + Keuntungan Max 10% 6,447.88
Jumlah keseluruhan 70,926.69
DIBULATKAN 70,900.00

23 Pipa galv medium Ø 15 mm


MATERIAL
Pipa galv medium Ø 15 mm 1.00 bh 32,833.33 32,833.33
Material bantu 1.00 Lot 1,641.67 1,641.67
UPAH KERJA
Pekerja 0.05 oh 132,000.00 6,920.60
Tukang Pipa 0.03 oh 188,571.44 4,943.29
Kepala Tukang Pipa 0.02 oh 200,000.00 3,145.73
Mandor 0.01 oh 220,000.00 1,153.43
Jumlah 50,638.05
Overhead + Keuntungan Max 10% 5,063.81
Jumlah keseluruhan 55,701.86
DIBULATKAN 55,700.00

24 Pipa Drainage PVC AW c/w isolasi


MATERIAL
Pipa Drainage PVC AW c/w isolasi 1.00 bh 113,333.33 113,333.33
Material bantu 1.00 Lot 5,666.67 5,666.67
UPAH KERJA
Pekerja 0.15 oh 132,000.00 19,800.00
Tukang Pipa 0.08 oh 188,571.44 14,142.86
Kepala Tukang Pipa 0.05 oh 200,000.00 9,000.00
Mandor 0.02 oh 220,000.00 3,300.00
Jumlah 165,242.86
Overhead + Keuntungan Max 10% 16,524.29
Jumlah keseluruhan 181,767.14
DIBULATKAN 181,700.00

25 Pipa Refregerant+ Isolasi


MATERIAL
Pipa Refregerant+ Isolasi 1.00 bh 338,683.33 338,683.33
Material bantu 1.00 Lot 16,934.17 16,934.17
UPAH KERJA
Pekerja 0.15 oh 132,000.00 19,800.00
Tukang Pipa 0.08 oh 188,571.44 14,142.86
Kepala Tukang Pipa 0.05 oh 200,000.00 9,000.00
Mandor 0.02 oh 220,000.00 3,300.00
Jumlah 401,860.36
Overhead + Keuntungan Max 10% 40,186.04
Jumlah keseluruhan 442,046.39
DIBULATKAN 442,000.00

26 AC Manager
MATERIAL
AC Manager 1.00 bh 65,430,000.00 65,430,000.00
Material bantu 1.00 Lot 654,300.00 654,300.00
UPAH KERJA
Pekerja 1.00 oh 132,000.00 132,000.00
Tukang Pipa 0.05 oh 188,571.44 8,485.71
Kepala Tukang Pipa 0.02 oh 200,000.00 3,000.00
Mandor 0.02 oh 220,000.00 3,300.00
Jumlah 66,231,085.71
Overhead + Keuntungan Max 10% 6,623,108.57
Jumlah keseluruhan 72,854,194.29
DIBULATKAN 72,854,100.00

27 Kabel control UTP cat 6+conduit dia 20mm


MATERIAL
Kabel control UTP cat 6+conduit dia 20mm 1.00 mtr 13,500.00 13,500.00
Material bantu 1.00 Lot 675.00 675.00
UPAH KERJA
Pekerja 0.15 oh 132,000.00 19,800.00
Tukang Pipa 0.08 oh 188,571.44 14,142.86
Kepala Tukang Pipa 0.05 oh 200,000.00 9,000.00
Mandor 0.02 oh 220,000.00 3,300.00
Jumlah 60,417.86
Overhead + Keuntungan Max 10% 6,041.79
Jumlah keseluruhan 66,459.64
DIBULATKAN 66,400.00

28 Kabel power NYM 3x2,5 mm2 + conduit dia20mm


MATERIAL
Kabel power NYM 3x2,5 mm2 + conduit dia20mm 30.00 mtr 18,500.00 555,000.00
Material bantu 1.00 Lot 925.00 925.00
UPAH KERJA
Pekerja 0.14 oh 132,000.00 18,810.00
Tukang Pipa 0.07 oh 188,571.44 13,435.72
Kepala Tukang Pipa 0.04 oh 200,000.00 8,550.00
Mandor 0.01 oh 220,000.00 3,135.00
Jumlah 599,855.72
Overhead + Keuntungan Max 10% 59,985.57
Jumlah keseluruhan 659,841.29
DIBULATKAN 659,800.00
29 Instalasi Listrik Exhaust Fan Dan saklar
MATERIAL
Instalasi Listrik Exhaust Fan Dan saklar
Kabel power NYM 3x2,5 mm2 + conduit dia20mm 15.00 mtr 18,500.00 277,500.00
Saklar Tunggal 1.00 bh 32,000.00 32,000.00
Material bantu 1.00 Lot 1,600.00 1,600.00
UPAH KERJA
Pekerja 0.07 oh 132,000.00 8,934.75
Tukang Pipa 0.03 oh 188,571.44 6,381.96
Kepala Tukang Pipa 0.02 oh 200,000.00 4,061.25
Mandor 0.01 oh 220,000.00 1,489.13
Jumlah 331,967.09
Overhead + Keuntungan Max 10% 33,196.71
Jumlah keseluruhan 365,163.80
DIBULATKAN 365,100.00
30 Pipa PPR PN 10 Ø 65 mm
MATERIAL
Pipa PPR PN 10 Ø 65 mm 1.00 bh 190,750.00 190,750.00
Material bantu 1.00 Lot 9,537.50 9,537.50
UPAH KERJA
Pekerja 0.35 oh 132,000.00 46,200.00
Tukang Pipa 0.18 oh 188,571.44 33,000.00
Kepala Tukang Pipa 0.11 oh 200,000.00 21,000.00
Mandor 0.04 oh 220,000.00 7,700.00
Jumlah 308,187.50
Overhead + Keuntungan Max 10% 30,818.75
Jumlah keseluruhan 339,006.25
DIBULATKAN 339,000.00

31 Pipa PPR PN 10 Ø 50 mm
MATERIAL
Pipa PPR PN 10 Ø 50 mm 1.00 bh 119,750.00 119,750.00
Material bantu 1.00 Lot 5,987.50 5,987.50
UPAH KERJA
Pekerja 0.30 oh 132,000.00 39,270.00
Tukang Pipa 0.15 oh 188,571.44 28,050.00
Kepala Tukang Pipa 0.09 oh 200,000.00 17,850.00
Mandor 0.03 oh 220,000.00 6,545.00
Jumlah 217,452.50
Overhead + Keuntungan Max 10% 21,745.25
Jumlah keseluruhan 239,197.75
DIBULATKAN 239,100.00

32 Pipa PPR PN 10 Ø 40 mm
MATERIAL
Pipa PPR PN 10 Ø 40 mm 1.00 bh 75,250.00 75,250.00
Material bantu 1.00 Lot 3,762.50 3,762.50
UPAH KERJA
Pekerja 0.25 oh 132,000.00 33,379.50
Tukang Pipa 0.13 oh 188,571.44 23,842.50
Kepala Tukang Pipa 0.08 oh 200,000.00 15,172.50
Mandor 0.03 oh 220,000.00 5,563.25
Jumlah 156,970.25
Overhead + Keuntungan Max 10% 15,697.03
Jumlah keseluruhan 172,667.28
DIBULATKAN 172,600.00

33 Pipa PPR PN 10 Ø 32 mm
MATERIAL
Pipa PPR PN 10 Ø 32 mm 1.00 bh 49,000.00 49,000.00
Material bantu 1.00 Lot 2,450.00 2,450.00
UPAH KERJA
Pekerja 0.21 oh 132,000.00 28,372.58
Tukang Pipa 0.11 oh 188,571.44 20,266.13
Kepala Tukang Pipa 0.06 oh 200,000.00 12,896.63
Mandor 0.02 oh 220,000.00 4,728.76
Jumlah 117,714.09
Overhead + Keuntungan Max 10% 11,771.41
Jumlah keseluruhan 129,485.50
DIBULATKAN 129,400.00

34 Pipa PPR PN 10 Ø 25 mm
MATERIAL
Pipa PPR PN 10 Ø 25 mm 1.00 bh 32,000.00 32,000.00
Material bantu 1.00 Lot 1,600.00 1,600.00
UPAH KERJA
Pekerja 0.18 oh 132,000.00 24,116.69
Tukang Pipa 0.09 oh 188,571.44 17,226.21
Kepala Tukang Pipa 0.05 oh 200,000.00 10,962.13
Mandor 0.02 oh 220,000.00 4,019.45
Jumlah 89,924.48
Overhead + Keuntungan Max 10% 8,992.45
Jumlah keseluruhan 98,916.92
DIBULATKAN 98,900.00

35 Pipa PPR PN 10 Ø 20 mm
MATERIAL
Pipa PPR PN 10 Ø 20 mm 1.00 bh 19,750.00 19,750.00
Material bantu 1.00 Lot 987.50 987.50
UPAH KERJA
Pekerja 0.16 oh 132,000.00 20,499.19
Tukang Pipa 0.08 oh 188,571.44 14,642.28
Kepala Tukang Pipa 0.05 oh 200,000.00 9,317.81
Mandor 0.02 oh 220,000.00 3,416.53
Jumlah 68,613.30
Overhead + Keuntungan Max 10% 6,861.33
Jumlah keseluruhan 75,474.63
DIBULATKAN 75,400.00

36 Pipa PPR PN 10 Ø 15 mm
MATERIAL
Pipa PPR PN 10 Ø 15 mm 1.00 bh 14,500.00 14,500.00
Material bantu 1.00 Lot 725.00 725.00
UPAH KERJA
Pekerja 0.13 oh 132,000.00 17,424.31
Tukang Pipa 0.07 oh 188,571.44 12,445.93
Kepala Tukang Pipa 0.04 oh 200,000.00 7,920.14
Mandor 0.01 oh 220,000.00 2,904.05
Jumlah 55,919.43
Overhead + Keuntungan Max 10% 5,591.94
Jumlah keseluruhan 61,511.38
DIBULATKAN 61,500.00

37 Pipa pvc aw Ø 150 mm


MATERIAL
Pipa pvc aw Ø 150 mm 1.00 bh 180,050.00 180,050.00
Material bantu 1.00 Lot 9,002.50 9,002.50
UPAH KERJA
Pekerja 0.25 oh 132,000.00 33,000.00
Tukang Pipa 0.13 oh 188,571.44 23,571.43
Kepala Tukang Pipa 0.08 oh 200,000.00 15,000.00
Mandor 0.03 oh 220,000.00 5,500.00
Jumlah 266,123.93
Overhead + Keuntungan Max 10% 26,612.39
Jumlah keseluruhan 292,736.32
DIBULATKAN 292,700.00

38 Pipa pvc aw Ø 100 mm


MATERIAL
Pipa pvc aw Ø 100 mm 1.00 bh 81,025.00 81,025.00
Material bantu 1.00 Lot 4,051.25 4,051.25
UPAH KERJA
Pekerja 0.23 oh 132,000.00 29,700.00
Tukang Pipa 0.11 oh 188,571.44 21,214.29
Kepala Tukang Pipa 0.07 oh 200,000.00 13,500.00
Mandor 0.02 oh 220,000.00 4,950.00
Jumlah 154,440.54
Overhead + Keuntungan Max 10% 15,444.05
Jumlah keseluruhan 169,884.59
DIBULATKAN 169,800.00

39 Pipa pvc aw Ø 80 mm
MATERIAL
Pipa pvc aw Ø 80 mm 1.00 bh 48,900.00 48,900.00
Material bantu 1.00 Lot 2,445.00 2,445.00
UPAH KERJA
Pekerja 0.20 oh 132,000.00 26,730.00
Tukang Pipa 0.10 oh 188,571.44 19,092.86
Kepala Tukang Pipa 0.06 oh 200,000.00 12,150.00
Mandor 0.02 oh 220,000.00 4,455.00
Jumlah 113,772.86
Overhead + Keuntungan Max 10% 11,377.29
Jumlah keseluruhan 125,150.14
DIBULATKAN 125,100.00

40 Pipa pvc aw Ø 65 mm
MATERIAL
Pipa pvc aw Ø 65 mm 1.00 bh 34,725.00 34,725.00
Material bantu 1.00 Lot 1,736.25 1,736.25
UPAH KERJA
Pekerja 0.18 oh 132,000.00 24,057.00
Tukang Pipa 0.09 oh 188,571.44 17,183.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,935.00
Mandor 0.02 oh 220,000.00 4,009.50
Jumlah 92,646.32
Overhead + Keuntungan Max 10% 9,264.63
Jumlah keseluruhan 101,910.95
DIBULATKAN 101,900.00

41 Pipa pvc aw Ø 50 mm
MATERIAL
Pipa pvc aw Ø 50 mm 1.00 bh 23,800.00 23,800.00
Material bantu 1.00 Lot 1,190.00 1,190.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,651.30
Tukang Pipa 0.08 oh 188,571.44 15,465.22
Kepala Tukang Pipa 0.05 oh 200,000.00 9,841.50
Mandor 0.02 oh 220,000.00 3,608.55
Jumlah 75,556.57
Overhead + Keuntungan Max 10% 7,555.66
Jumlah keseluruhan 83,112.22
DIBULATKAN 83,100.00
42 Pipa pvc aw Ø 40 mm
MATERIAL
Pipa pvc aw Ø 40 mm 1.00 bh 21,200.00 21,200.00
Material bantu 1.00 Lot 1,060.00 1,060.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,651.30
Tukang Pipa 0.08 oh 188,571.44 15,465.22
Kepala Tukang Pipa 0.05 oh 200,000.00 9,841.50
Mandor 0.02 oh 220,000.00 3,608.55
Jumlah 72,826.57
Overhead + Keuntungan Max 10% 7,282.66
Jumlah keseluruhan 80,109.22
DIBULATKAN 80,100.00
43 Pipa pvc d Ø 50 mm
MATERIAL
Pipa pvc d Ø 50 mm 1.00 bh 14,750.00 14,750.00
Material bantu 1.00 Lot 737.50 737.50
UPAH KERJA
Pekerja 0.15 oh 132,000.00 19,486.17
Tukang Pipa 0.07 oh 188,571.44 13,918.69
Kepala Tukang Pipa 0.04 oh 200,000.00 8,857.35
Mandor 0.01 oh 220,000.00 3,247.70
Jumlah 60,997.41
Overhead + Keuntungan Max 10% 6,099.74
Jumlah keseluruhan 67,097.15
DIBULATKAN 67,000.00

44 Pipa pvc d Ø 40 mm
MATERIAL
Pipa pvc d Ø 40 mm 1.00 bh 11,500.00 11,500.00
Material bantu 1.00 Lot 575.00 575.00
UPAH KERJA
Pekerja 0.13 oh 132,000.00 17,537.55
Tukang Pipa 0.07 oh 188,571.44 12,526.82
Kepala Tukang Pipa 0.04 oh 200,000.00 7,971.62
Mandor 0.01 oh 220,000.00 2,922.93
Jumlah 53,033.92
Overhead + Keuntungan Max 10% 5,303.39
Jumlah keseluruhan 58,337.31
DIBULATKAN 58,300.00

45 Pipa pvc d Ø 32 mm
MATERIAL
Pipa pvc d Ø 32 mm 1.00 bh 11,500.00 11,500.00
Material bantu 1.00 Lot 575.00 575.00
UPAH KERJA
Pekerja 0.12 oh 132,000.00 15,783.80
Tukang Pipa 0.06 oh 188,571.44 11,274.14
Kepala Tukang Pipa 0.04 oh 200,000.00 7,174.45
Mandor 0.01 oh 220,000.00 2,630.63
Jumlah 48,938.03
Overhead + Keuntungan Max 10% 4,893.80
Jumlah keseluruhan 53,831.83
DIBULATKAN 53,800.00

46 Bak Kontrol
Bak Kontrol 1.00 bh 320,000.00 320,000.00
Material bantu 1.00 Lot 16,000.00 16,000.00
UPAH KERJA
Pekerja 1.00 oh 132,000.00 132,000.00
Tukang Pipa 0.50 oh 188,571.44 94,285.72
Kepala Tukang Pipa 0.30 oh 200,000.00 60,000.00
Mandor 0.10 oh 220,000.00 22,000.00
Jumlah 644,285.72
Overhead + Keuntungan Max 10% 64,428.57
Jumlah keseluruhan 708,714.29
DIBULATKAN 708,700.00

47 Bak Kontrol Beton 800x500


Bak Kontrol Beton 800x500 1.00 bh 860,000.00 860,000.00
Material bantu 1.00 Lot 43,000.00 43,000.00
UPAH KERJA
Pekerja 2.00 oh 132,000.00 264,000.00
Tukang Pipa 1.00 oh 188,571.44 188,571.44
Kepala Tukang Pipa 0.60 oh 200,000.00 120,000.00
Mandor 0.20 oh 220,000.00 44,000.00
Jumlah 1,519,571.44
Overhead + Keuntungan Max 10% 151,957.14
Jumlah keseluruhan 1,671,528.58
DIBULATKAN 1,671,500.00

48 #REF!
#REF! 1.00 bh 54,000,000.00 54,000,000.00
Material bantu 1.00 Lot 2,700,000.00 2,700,000.00
UPAH KERJA
Pekerja 14.00 oh 132,000.00 1,848,000.00
Tukang Pipa 7.00 oh 188,571.44 1,320,000.08
Kepala Tukang Pipa 7.00 oh 200,000.00 1,400,000.00
Mandor 3.00 oh 220,000.00 660,000.00
Jumlah 61,928,000.08
Overhead + Keuntungan Max 10% 6,192,800.01
Jumlah keseluruhan 68,120,800.09
DIBULATKAN 68,120,800.00

49 Exhaust Fan 500 Cfm


Exhaust Fan 500 Cfm 1.00 bh 11,238,000.00 11,238,000.00
Material bantu 1.00 Lot 561,900.00 561,900.00
UPAH KERJA
Pekerja 0.20 oh 132,000.00 26,400.00
Tukang Pipa 0.10 oh 188,571.44 18,857.14
Kepala Tukang Pipa 0.06 oh 200,000.00 12,000.00
Mandor 0.02 oh 220,000.00 4,400.00
Jumlah 11,861,557.14
Overhead + Keuntungan Max 10% 1,186,155.71
Jumlah keseluruhan 13,047,712.86
DIBULATKAN 13,047,700.00

50 Exhaust Fan 400 Cfm


Exhaust Fan 400 Cfm 1.00 bh 2,450,000.00 2,450,000.00
Material bantu 1.00 Lot 122,500.00 122,500.00
UPAH KERJA
Pekerja 0.20 oh 132,000.00 26,400.00
Tukang Pipa 0.10 oh 188,571.44 18,857.14
Kepala Tukang Pipa 0.06 oh 200,000.00 12,000.00
Mandor 0.02 oh 220,000.00 4,400.00
Jumlah 2,634,157.14
Overhead + Keuntungan Max 10% 263,415.71
Jumlah keseluruhan 2,897,572.86
DIBULATKAN 2,897,500.00

51 Exhaust Fan 100 Cfm


Exhaust Fan 100 Cfm 1.00 bh 558,600.00 558,600.00
Material bantu 1.00 Lot 27,930.00 27,930.00
UPAH KERJA
Pekerja 0.20 oh 132,000.00 26,400.00
Tukang Pipa 0.10 oh 188,571.44 18,857.14
Kepala Tukang Pipa 0.06 oh 200,000.00 12,000.00
Mandor 0.02 oh 220,000.00 4,400.00
Jumlah 648,187.14
Overhead + Keuntungan Max 10% 64,818.71
Jumlah keseluruhan 713,005.86
DIBULATKAN 713,000.00

52 Exhaust Fan 150 Cfm


Exhaust Fan 150 Cfm 1.00 bh 558,600.00 558,600.00
Material bantu 1.00 Lot 27,930.00 27,930.00
UPAH KERJA
Pekerja 0.20 oh 132,000.00 26,400.00
Tukang Pipa 0.10 oh 188,571.44 18,857.14
Kepala Tukang Pipa 0.06 oh 200,000.00 12,000.00
Mandor 0.02 oh 220,000.00 4,400.00
Jumlah 648,187.14
Overhead + Keuntungan Max 10% 64,818.71
Jumlah keseluruhan 713,005.86

53 EF Axial 400 cfm


EF Axial 400 cfm 1.00 bh 2,450,000.00 2,450,000.00
Material bantu 1.00 Lot 122,500.00 122,500.00
UPAH KERJA
Pekerja 0.20 oh 132,000.00 26,400.00
Tukang Pipa 0.10 oh 188,571.44 18,857.14
Kepala Tukang Pipa 0.06 oh 200,000.00 12,000.00
Mandor 0.02 oh 220,000.00 4,400.00
Jumlah 2,634,157.14
Overhead + Keuntungan Max 10% 263,415.71
Jumlah keseluruhan 2,897,572.86

54 Clean Out Dia 100 mm


Clean Out Dia 100 mm 1.00 bh 160,000.00 160,000.00
Material bantu 1.00 Lot 8,000.00 8,000.00
UPAH KERJA
Pekerja 0.25 oh 132,000.00 33,000.00
Tukang Pipa 0.13 oh 188,571.44 23,571.43
Kepala Tukang Pipa 0.08 oh 200,000.00 15,000.00
Mandor 0.03 oh 220,000.00 5,500.00
Jumlah 245,071.43
Overhead + Keuntungan Max 10% 24,507.14
Jumlah keseluruhan 269,578.57
DIBULATKAN 269,500.00

55 Clean Out Dia 50 mm


Clean Out Dia 50 mm 1.00 bh 110,000.00 110,000.00
Material bantu 1.00 Lot 5,500.00 5,500.00
UPAH KERJA
Pekerja 0.25 oh 132,000.00 33,000.00
Tukang Pipa 0.13 oh 188,571.44 23,571.43
Kepala Tukang Pipa 0.08 oh 200,000.00 15,000.00
Mandor 0.03 oh 220,000.00 5,500.00
Jumlah 192,571.43
Overhead + Keuntungan Max 10% 19,257.14
Jumlah keseluruhan 211,828.57
DIBULATKAN 211,800.00

56 #REF!
#REF! 1.00 bh 86,000,000.00 86,000,000.00
Material bantu/Pondasi dll 1.00 Lot 4,300,000.00 4,300,000.00
UPAH KERJA
Pekerja 2.00 oh 132,000.00 264,000.00
Tukang Pipa 2.00 oh 188,571.44 377,142.88
Kepala Tukang Pipa 1.00 oh 200,000.00 200,000.00
Mandor 1.00 oh 220,000.00 220,000.00
Jumlah 91,361,142.88
Overhead + Keuntungan Max 10% 9,136,114.29
Jumlah keseluruhan 100,497,257.17
DIBULATKAN 100,497,200.00

57 Roof Tank kap.8m3


Roof Tank kap.8m3 1.00 bh 32,000,000.00 32,000,000.00
Material bantu 1.00 Lot 1,600,000.00 1,600,000.00
UPAH KERJA
Pekerja 4.00 oh 132,000.00 528,000.00
Tukang Pipa 4.00 oh 188,571.44 754,285.76
Kepala Tukang Pipa 2.00 oh 200,000.00 400,000.00
Mandor 1.00 oh 220,000.00 220,000.00
Jumlah 35,502,285.76
Overhead + Keuntungan Max 10% 3,550,228.58
Jumlah keseluruhan 39,052,514.34
DIBULATKAN 39,052,500.00

58 Roof drain Ø 100 mm


Roof drain Ø 100 mm 1.00 bh 255,000.00 255,000.00
Material bantu 1.00 Lot 12,750.00 12,750.00
UPAH KERJA
Pekerja 0.18 oh 132,000.00 23,760.00
Tukang Pipa 0.09 oh 188,571.44 16,971.43
Kepala Tukang Pipa 0.05 oh 200,000.00 10,800.00
Mandor 0.02 oh 220,000.00 3,960.00
Jumlah 323,241.43
Overhead + Keuntungan Max 10% 32,324.14
Jumlah keseluruhan 355,565.57
DIBULATKAN 355,500.00

59 Roof drain Ø 80 mm
Roof drain Ø 80 mm 1.00 bh 205,000.00 205,000.00
Material bantu 1.00 Lot 10,250.00 10,250.00
UPAH KERJA
Pekerja 0.18 oh 132,000.00 23,760.00
Tukang Pipa 0.09 oh 188,571.44 16,971.43
Kepala Tukang Pipa 0.05 oh 200,000.00 10,800.00
Mandor 0.02 oh 220,000.00 3,960.00
Jumlah 270,741.43
Overhead + Keuntungan Max 10% 27,074.14
Jumlah keseluruhan 297,815.57
DIBULATKAN 297,800.00

60 Exhaust Air Duct 150 x 150


Exhaust Air Duct 150 x 150 1.00 bh 185,000.00 185,000.00
Material bantu 1.00 Lot 9,250.00 9,250.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 246,658.57
Overhead + Keuntungan Max 10% 24,665.86
Jumlah keseluruhan 271,324.43
DIBULATKAN 271,300.00

61 Exhaust Air Duct 250 x 250


Exhaust Air Duct 250 x 250 1.00 bh 256,300.00 256,300.00
Material bantu 1.00 Lot 12,815.00 12,815.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 321,523.57
Overhead + Keuntungan Max 10% 32,152.36
Jumlah keseluruhan 353,675.93
DIBULATKAN 353,600.00

62 Exhaust Air Duct 200 x 200


Exhaust Air Duct 200 x 200 1.00 bh 225,000.00 225,000.00
Material bantu 1.00 Lot 11,250.00 11,250.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 288,658.57
Overhead + Keuntungan Max 10% 28,865.86
Jumlah keseluruhan 317,524.43
DIBULATKAN 317,500.00
63 Exhaust Air Duct 100 x 100
Exhaust Air Duct 100 x 100 1.00 bh 120,000.00 120,000.00
Material bantu 1.00 Lot 6,000.00 6,000.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 178,408.57
Overhead + Keuntungan Max 10% 17,840.86
Jumlah keseluruhan 196,249.43
DIBULATKAN 196,200.00

64 Exhaust Air Duct 200 x 200


Exhaust Air Duct 200 x 200 1.00 bh 225,000.00 225,000.00
Material bantu 1.00 Lot 11,250.00 11,250.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 288,658.57
Overhead + Keuntungan Max 10% 28,865.86
Jumlah keseluruhan 317,524.43
DIBULATKAN 317,500.00

65 Exhaust Air Duct Ø 200


Exhaust Air Duct Ø 200 1.00 bh 200,000.00 200,000.00
Material bantu 1.00 Lot 10,000.00 10,000.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 262,408.57
Overhead + Keuntungan Max 10% 26,240.86
Jumlah keseluruhan 288,649.43
DIBULATKAN 288,600.00

66 Exhaust Air Duct Ø 250


Exhaust Air Duct Ø 250 1.00 bh 278,000.00 278,000.00
Material bantu 1.00 Lot 13,900.00 13,900.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 344,308.57
Overhead + Keuntungan Max 10% 34,430.86
Jumlah keseluruhan 378,739.43
DIBULATKAN 378,700.00
67 Fire Extinguisher DC Kap 6 kg, Standard NFPA International, dll
Fire Extinguisher DC Kap 6 kg, Standard NFPA International, dll 1.00 bh 650,000.00 650,000.00
Material bantu 1.00 Lot 32,500.00 32,500.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 734,908.57
Overhead + Keuntungan Max 10% 73,490.86
Jumlah keseluruhan 808,399.43
DIBULATKAN 808,300.00

67 HP - Hydrant Pilar, Standard NFPA International, dll Lengkap, Accessories : 'Size 4' x 2 1/2' x 2 1/2'
HP - Hydrant Pilar, Standard NFPA International, dll Lengkap, Accessories : 'Size 1.00 bh 3,600,000.00 3,600,000.00
Material bantu 1.00 Lot 180,000.00 180,000.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 3,832,408.57
Overhead + Keuntungan Max 10% 383,240.86
Jumlah keseluruhan 4,215,649.43
DIBULATKAN 4,215,600.00

68 Exhaust Air Duct Ø 100


Exhaust Air Duct Ø 100 1.00 bh 167,000.00 167,000.00
Material bantu 1.00 Lot 8,350.00 8,350.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 227,758.57
Overhead + Keuntungan Max 10% 22,775.86
Jumlah keseluruhan 250,534.43
DIBULATKAN 250,500.00

69 Exahaust Air Grille 150 x 150 mm


Exahaust Air Grille 150 x 150 mm 1.00 bh 185,000.00 185,000.00
Material bantu 1.00 Lot 9,250.00 9,250.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 246,658.57
Overhead + Keuntungan Max 10% 24,665.86
Jumlah keseluruhan 271,324.43
DIBULATKAN 271,300.00

70 Exahaust Air Grille 250 x 250 mm


Exahaust Air Grille 250 x 250 mm 1.00 bh 256,300.00 256,300.00
Material bantu 1.00 Lot 12,815.00 12,815.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 321,523.57
Overhead + Keuntungan Max 10% 32,152.36
Jumlah keseluruhan 353,675.93
DIBULATKAN 353,600.00

71 Louvre 350 x 350 mm


Louvre 350 x 350 mm 1.00 bh 163,000.00 163,000.00
Material bantu 1.00 Lot 8,150.00 8,150.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 223,558.57
Overhead + Keuntungan Max 10% 22,355.86
Jumlah keseluruhan 245,914.43
DIBULATKAN 245,900.00

72 Louvre 200 x 200 mm


Louvre 200 x 200 mm 1.00 bh 153,000.00 153,000.00
Material bantu 1.00 Lot 7,650.00 7,650.00
UPAH KERJA
Pekerja 0.17 oh 132,000.00 22,440.00
Tukang Pipa 0.09 oh 188,571.44 16,028.57
Kepala Tukang Pipa 0.05 oh 200,000.00 10,200.00
Mandor 0.02 oh 220,000.00 3,740.00
Jumlah 213,058.57
Overhead + Keuntungan Max 10% 21,305.86
Jumlah keseluruhan 234,364.43
DIBULATKAN 234,300.00

73 EF toilet 500 cfm


EF toilet 500 cfm 1.00 bh 1,200,000.00 1,200,000.00
Material bantu 1.00 Lot 60,000.00 60,000.00
UPAH KERJA
Pekerja 0.15 oh 132,000.00 19,800.00
Tukang Pipa 0.08 oh 188,571.44 14,142.86
Kepala Tukang Pipa 0.05 oh 200,000.00 9,000.00
Mandor 0.02 oh 220,000.00 3,300.00
Jumlah 1,306,242.86
Overhead + Keuntungan Max 10% 130,624.29
Jumlah keseluruhan 1,436,867.14
DIBULATKAN 1,436,800.00

74 EF toilet 260 cfm


EF toilet 260 cfm 1.00 bh 1,200,000.00 1,200,000.00
Material bantu 1.00 Lot 60,000.00 60,000.00
UPAH KERJA
Pekerja 0.15 oh 132,000.00 19,800.00
Tukang Pipa 0.08 oh 188,571.44 14,142.86
Kepala Tukang Pipa 0.05 oh 200,000.00 9,000.00
Mandor 0.02 oh 220,000.00 3,300.00
Jumlah 1,306,242.86
Overhead + Keuntungan Max 10% 130,624.29
Jumlah keseluruhan 1,436,867.14
DIBULATKAN 1,436,800.00

75 IHB - Indoor Hydrant Box Standard NFPA International, dll Lengkap, Accessories :
IHB - Indoor Hydrant Box Standard NFPA International, dll Lengkap, Accessori 1.00 bh 4,600,000.00 4,600,000.00
Material bantu 1.00 Lot 230,000.00 230,000.00
UPAH KERJA
Pekerja 0.60 oh 132,000.00 79,200.00
Tukang Pipa 0.30 oh 188,571.44 56,571.43
Kepala Tukang Pipa 0.18 oh 200,000.00 36,000.00
Mandor 0.06 oh 220,000.00 13,200.00
Jumlah 5,014,971.43
Overhead + Keuntungan Max 10% 501,497.14
Jumlah keseluruhan 5,516,468.58
DIBULATKAN 5,516,400.00

76 OHB - Outdoor Hydrant Box Standard NFPA International, dll Lengkap, Accessories :
OHB - Outdoor Hydrant Box Standard NFPA International, dll Lengkap, Accesso 1.00 bh 2,600,000.00 2,600,000.00
Material bantu 1.00 Lot 130,000.00 130,000.00
UPAH KERJA
Pekerja 0.60 oh 132,000.00 79,200.00
Tukang Pipa 0.30 oh 188,571.44 56,571.43
Kepala Tukang Pipa 0.18 oh 200,000.00 36,000.00
Mandor 0.06 oh 220,000.00 13,200.00
Jumlah 2,914,971.43
Overhead + Keuntungan Max 10% 291,497.14
Jumlah keseluruhan 3,206,468.58
DIBULATKAN 3,206,400.00

77 SC - Siemese Connection Standard NFPA International, dll Lengkap, Accessories :Size 4' x 2 1/2' x 2 1/2'
SC - Siemese Connection Standard NFPA International, dll Lengkap, Accessories : 1.00 bh 2,300,000.00 2,300,000.00
Material bantu 1.00 Lot 115,000.00 115,000.00
UPAH KERJA
Pekerja 0.60 oh 132,000.00 79,200.00
Tukang Pipa 0.30 oh 188,571.44 56,571.43
Kepala Tukang Pipa 0.18 oh 200,000.00 36,000.00
Mandor 0.06 oh 220,000.00 13,200.00
Jumlah 2,599,971.43
Overhead + Keuntungan Max 10% 259,997.14
Jumlah keseluruhan 2,859,968.58
DIBULATKAN 2,859,900.00

78 Floating valve Ø 50 mm
Floating valve Ø 50 mm 1.00 bh 175,800.00 175,800.00
Material bantu 1.00 Lot 8,790.00 8,790.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 233,915.72
Overhead + Keuntungan Max 10% 23,391.57
Jumlah keseluruhan 257,307.29
DIBULATKAN 257,300.00

79 Landing valve Ø 50 mm
Landing valve Ø 50 mm 1.00 bh 522,000.00 522,000.00
Material bantu 1.00 Lot 26,100.00 26,100.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 597,425.72
Overhead + Keuntungan Max 10% 59,742.57
Jumlah keseluruhan 657,168.29
DIBULATKAN 657,100.00

80 Floor drain Dia 50 mm


Floor drain Dia 50 mm 1.00 bh 125,000.00 125,000.00
Material bantu 1.00 Lot 6,250.00 6,250.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 180,575.72
Overhead + Keuntungan Max 10% 18,057.57
Jumlah keseluruhan 198,633.29
DIBULATKAN 198,600.00

81 Pressure Gauge
Pressure Gauge 1.00 bh 195,000.00 195,000.00
Material bantu 1.00 Lot 9,750.00 9,750.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 254,075.72
Overhead + Keuntungan Max 10% 25,407.57
Jumlah keseluruhan 279,483.29
DIBULATKAN 279,400.00

82 Keran Ø 15mm
Keran Ø 15mm 1.00 bh 125,000.00 125,000.00
Material bantu 1.00 Lot 6,250.00 6,250.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 180,575.72
Overhead + Keuntungan Max 10% 18,057.57
Jumlah keseluruhan 198,633.29
DIBULATKAN 198,600.00

83 V-Trap Dia 50 mm
V-Trap Dia 50 mm 1.00 bh 35,000.00 35,000.00
Material bantu 1.00 Lot 1,750.00 1,750.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 86,075.72
Overhead + Keuntungan Max 10% 8,607.57
Jumlah keseluruhan 94,683.29
DIBULATKAN 94,600.00

84 Vent cap Ø 40 mm
Vent cap Ø 40 mm 1.00 bh 20,000.00 20,000.00
Material bantu 1.00 Lot 1,000.00 1,000.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 70,325.72
Overhead + Keuntungan Max 10% 7,032.57
Jumlah keseluruhan 77,358.29
DIBULATKAN 77,300.00

85 Pek. Floor Drain Type TX1BN


Pek. Floor Drain Type TX1BN 1.00 bh 198,600.00 198,600.00
Material bantu 1.00 Lot 9,930.00 9,930.00
UPAH KERJA
Pekerja 0.16 oh 132,000.00 21,120.00
Tukang Pipa 0.08 oh 188,571.44 15,085.72
Kepala Tukang Pipa 0.05 oh 200,000.00 9,600.00
Mandor 0.02 oh 220,000.00 3,520.00
Jumlah 257,855.72
Overhead + Keuntungan Max 10% 25,785.57
Jumlah keseluruhan 283,641.29
DIBULATKAN 283,600.00

86 IU Ceilling cassete 38.200 Btuh


IU Ceilling cassete 38.200 Btuh 1.00 bh 10,950,000.00 10,950,000.00
Material bantu 1.00 Lot 547,500.00 547,500.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 11,651,642.86
Overhead + Keuntungan Max 10% 1,165,164.29
Jumlah keseluruhan 12,816,807.15
DIBULATKAN 12,816,800.00

87 Wall mounted 7.500 Btuh


Wall mounted 7.500 Btuh 1.00 bh 5,580,000.00 5,580,000.00
Material bantu 1.00 Lot 279,000.00 279,000.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 6,013,142.86
Overhead + Keuntungan Max 10% 601,314.29
Jumlah keseluruhan 6,614,457.15
DIBULATKAN 6,614,400.00

88 Wall mounted 9.600 Btuh


Wall mounted 9.600 Btuh 1.00 bh 5,750,000.00 5,750,000.00
Material bantu 1.00 Lot 287,500.00 287,500.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 6,191,642.86
Overhead + Keuntungan Max 10% 619,164.29
Jumlah keseluruhan 6,810,807.15
DIBULATKAN 6,810,800.00

89 Wall mounted 15400 Btuh


Wall mounted 15400 Btuh 1.00 bh 6,012,000.00 6,012,000.00
Material bantu 1.00 Lot 300,600.00 300,600.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 6,466,742.86
Overhead + Keuntungan Max 10% 646,674.29
Jumlah keseluruhan 7,113,417.15
DIBULATKAN 7,113,400.00

90 Wall mounted 24200 Btuh


Wall mounted 24200 Btuh 1.00 bh 8,100,000.00 8,100,000.00
Material bantu 1.00 Lot 405,000.00 405,000.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 8,659,142.86
Overhead + Keuntungan Max 10% 865,914.29
Jumlah keseluruhan 9,525,057.15
DIBULATKAN 9,525,000.00

91 IU Ceilling cassete 19.100 Btuh


IU Ceilling cassete 19.100 Btuh 1.00 bh 23,010,000.00 23,010,000.00
Material bantu 1.00 Lot 1,150,500.00 1,150,500.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 24,314,642.86
Overhead + Keuntungan Max 10% 2,431,464.29
Jumlah keseluruhan 26,746,107.15
DIBULATKAN 26,746,100.00

92 IU Ceilling cassete 15.400 Btuh


IU Ceilling cassete 15.400 Btuh 1.00 bh 8,760,000.00 8,760,000.00
Material bantu 1.00 Lot 438,000.00 438,000.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 9,352,142.86
Overhead + Keuntungan Max 10% 935,214.29
Jumlah keseluruhan 10,287,357.15
DIBULATKAN 10,287,300.00

93 IU Ceilling cassete 54.600 Btuh


IU Ceilling cassete 54.600 Btuh 1.00 bh 12,560,000.00 12,560,000.00
Material bantu 1.00 Lot 628,000.00 628,000.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 13,342,142.86
Overhead + Keuntungan Max 10% 1,334,214.29
Jumlah keseluruhan 14,676,357.15
DIBULATKAN 14,676,300.00

94 IU Ceilling cassete 30.700 Btuh


IU Ceilling cassete 30.700 Btuh 1.00 bh 9,910,000.00 9,910,000.00
Material bantu 1.00 Lot 495,500.00 495,500.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 10,559,642.86
Overhead + Keuntungan Max 10% 1,055,964.29
Jumlah keseluruhan 11,615,607.15
DIBULATKAN 11,615,600.00

95 OU 324.800 BTUH
OU 324.800 BTUH 1.00 bh 169,400,000.00 169,400,000.00
Material bantu 1.00 Lot 8,470,000.00 8,470,000.00
UPAH KERJA
Pekerja 2.00 oh 132,000.00 264,000.00
Tukang Pipa 1.00 oh 188,571.44 188,571.44
Kepala Tukang Pipa 0.60 oh 200,000.00 120,000.00
Mandor 0.20 oh 220,000.00 44,000.00
Jumlah 178,486,571.44
Overhead + Keuntungan Max 10% 17,848,657.14
Jumlah keseluruhan 196,335,228.58
DIBULATKAN 196,335,200.00

96 OU 386.200 BTUH
OU 386.200 BTUH 1.00 bh 321,960,000.00 321,960,000.00
Material bantu 1.00 Lot 16,098,000.00 16,098,000.00
UPAH KERJA
Pekerja 2.00 oh 132,000.00 264,000.00
Tukang Pipa 1.00 oh 188,571.44 188,571.44
Kepala Tukang Pipa 0.60 oh 200,000.00 120,000.00
Mandor 0.20 oh 220,000.00 44,000.00
Jumlah 338,674,571.44
Overhead + Keuntungan Max 10% 33,867,457.14
Jumlah keseluruhan 372,542,028.58
DIBULATKAN 372,542,000.00
97 OU 458.600 BTUH
OU 458.600 BTUH 1.00 bh 233,200,000.00 233,200,000.00
Material bantu 1.00 Lot 11,660,000.00 11,660,000.00
UPAH KERJA
Pekerja 2.00 oh 132,000.00 264,000.00
Tukang Pipa 1.00 oh 188,571.44 188,571.44
Kepala Tukang Pipa 0.60 oh 200,000.00 120,000.00
Mandor 0.20 oh 220,000.00 44,000.00
Jumlah 245,476,571.44
Overhead + Keuntungan Max 10% 24,547,657.14
Jumlah keseluruhan 270,024,228.58
DIBULATKAN 270,024,200.00

98 OU 477.700 BTUH
OU 477.700 BTUH 1.00 bh 242,880,000.00 242,880,000.00
Material bantu 1.00 Lot 12,144,000.00 12,144,000.00
UPAH KERJA
Pekerja 2.00 oh 132,000.00 264,000.00
Tukang Pipa 1.00 oh 188,571.44 188,571.44
Kepala Tukang Pipa 0.60 oh 200,000.00 120,000.00
Mandor 0.20 oh 220,000.00 44,000.00
Jumlah 255,640,571.44
Overhead + Keuntungan Max 10% 25,564,057.14
Jumlah keseluruhan 281,204,628.58
DIBULATKAN 281,204,600.00

99 IU Ceilling cassete 24.200 Btuh


IU Ceilling cassete 24.200 Btuh 1.00 bh 169,400,000.00 169,400,000.00
Material bantu 1.00 Lot 8,470,000.00 8,470,000.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 178,024,142.86
Overhead + Keuntungan Max 10% 17,802,414.29
Jumlah keseluruhan 195,826,557.15
DIBULATKAN 195,826,500.00

100 Control Panel & Cable


Control Panel & Cable 1.00 bh 5,000,000.00 5,000,000.00
Material bantu 1.00 Lot 250,000.00 250,000.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 5,404,142.86
Overhead + Keuntungan Max 10% 540,414.29
Jumlah keseluruhan 5,944,557.15
DIBULATKAN 5,944,500.00

101 Indoor Pipe BranchY-Branch


Indoor Pipe BranchY-Branch 1.00 bh 1,848,000.00 1,848,000.00
Material bantu 1.00 Lot 92,400.00 92,400.00
UPAH KERJA
Pekerja 0.50 oh 132,000.00 66,000.00
Tukang Pipa 0.25 oh 188,571.44 47,142.86
Kepala Tukang Pipa 0.15 oh 200,000.00 30,000.00
Mandor 0.05 oh 220,000.00 11,000.00
Jumlah 2,094,542.86
Overhead + Keuntungan Max 10% 209,454.29
Jumlah keseluruhan 2,303,997.15
DIBULATKAN 2,303,900.00

102 Remote
Remote 1.00 bh 1,166,000.00 1,166,000.00
Material bantu 1.00 Lot 58,300.00 58,300.00
UPAH KERJA
Pekerja 0.25 oh 132,000.00 33,000.00
Tukang Pipa 0.13 oh 188,571.44 23,571.43
Kepala Tukang Pipa 0.08 oh 200,000.00 15,000.00
Mandor 0.03 oh 220,000.00 5,500.00
Jumlah 1,301,371.43
Overhead + Keuntungan Max 10% 130,137.14
Jumlah keseluruhan 1,431,508.57
DIBULATKAN 1,431,500.00

103 Pipe Size Reducer


Pipe Size Reducer 1.00 bh 1,000,100.00 1,000,100.00
Material bantu 1.00 Lot 50,005.00 50,005.00
UPAH KERJA
Pekerja 0.25 oh 132,000.00 33,000.00
Tukang Pipa 0.13 oh 188,571.44 23,571.43
Kepala Tukang Pipa 0.08 oh 200,000.00 15,000.00
Mandor 0.03 oh 220,000.00 5,500.00
Jumlah 1,127,176.43
Overhead + Keuntungan Max 10% 112,717.64
Jumlah keseluruhan 1,239,894.07
DIBULATKAN 1,239,800.00

104 Lift Penumpang


Lift Penumpang 1.00 bh 394,000,000.00 394,000,000.00
Material bantu 1.00 Lot 19,700,000.00 19,700,000.00
UPAH KERJA
Pekerja 6.00 oh 132,000.00 792,000.00
Tukang Pipa 3.00 oh 188,571.44 565,714.32
Kepala Tukang Pipa 1.80 oh 200,000.00 360,000.00
Mandor 0.60 oh 220,000.00 132,000.00
Jumlah 415,549,714.32
Overhead + Keuntungan Max 10% 41,554,971.43
Jumlah keseluruhan 457,104,685.75
DIBULATKAN 457,104,600.00

105 Sumur Dangkal , Pompa 1 PK , H 60mtr, Casing dia.100mm


Sumur Dangkal , Pompa 1 PK , H 60mtr, Casing dia.100mm 1.00 bh 22,500,000.00 22,500,000.00
Material bantu 1.00 Lot 1,125,000.00 1,125,000.00
UPAH KERJA
Pekerja 6.00 oh 132,000.00 792,000.00
Tukang Pipa 3.00 oh 188,571.44 565,714.32
Kepala Tukang Pipa 1.80 oh 200,000.00 360,000.00
Mandor 0.60 oh 220,000.00 132,000.00
Jumlah 25,474,714.32
Overhead + Keuntungan Max 10% 2,547,471.43
Jumlah keseluruhan 28,022,185.75
DIBULATKAN 28,022,100.00

106 Pompa Transfer Air Bersih


Pompa Transfer Air Bersih 1.00 bh 28,500,000.00 28,500,000.00
Material bantu 1.00 Lot 1,425,000.00 1,425,000.00
UPAH KERJA
Pekerja 1.00 oh 132,000.00 132,000.00
Tukang Pipa 0.50 oh 188,571.44 94,285.72
Kepala Tukang Pipa 0.30 oh 200,000.00 60,000.00
Mandor 0.10 oh 220,000.00 22,000.00
Jumlah 30,233,285.72
Overhead + Keuntungan Max 10% 3,023,328.57
Jumlah keseluruhan 33,256,614.29
DIBULATKAN 33,256,600.00

107 Instalasi Booster pump


Instalasi Booster pump 1.00 bh 121,000,000.00 121,000,000.00
Material bantu 1.00 Lot 1,210,000.00 1,210,000.00
UPAH KERJA
Pekerja 1.00 oh 132,000.00 132,000.00
Tukang Pipa 0.50 oh 188,571.44 94,285.72
Kepala Tukang Pipa 0.30 oh 200,000.00 60,000.00
Mandor 0.10 oh 220,000.00 22,000.00
Jumlah 122,518,285.72
Overhead + Keuntungan Max 10% 12,251,828.57
Jumlah keseluruhan 134,770,114.29
DIBULATKAN 134,770,100.00

108 Rooftank kap.8m3


Rooftank kap.8m3 1.00 bh 32,000,000.00 32,000,000.00
Material bantu 1.00 Lot 1,600,000.00 1,600,000.00
UPAH KERJA
Pekerja 0.06 oh 132,000.00 8,250.00
Tukang Pipa 0.03 oh 188,571.44 5,892.86
Kepala Tukang Pipa 0.02 oh 200,000.00 3,750.00
Mandor 0.01 oh 220,000.00 1,375.00
Jumlah 33,619,267.86
Overhead + Keuntungan Max 10% 3,361,926.79
Jumlah keseluruhan 36,981,194.64
DIBULATKAN 36,981,100.00

ANALISA ELEKTRIKAL

No Uraian Satuan Koefisien Harga Satuan Jumlah Harga


(Rp) (Rp)
URAIAN SAT KOEF HARGA SATUAN JUMLAH HARGA SATUAN
Rp. Rp.

bh Batrei Cadangan untuk lampu Kap.16, 30menit


Batrei Cadangan untuk lampu Kap.16, 30menit bh 1.00 573,750.00 573,750.00
Material bantu Lot 1.00 28,687.50 28,687.50
Jumlah 602,437.50
UPAH KERJA
Pekerja oh 0.08 132,000.00 10,560.00
Tukang Listrik oh 0.04 188,571.44 7,542.86
Kepala Tukang Listrik oh 0.02 200,000.00 4,800.00
Mandor oh 0.01 220,000.00 1,760.00
Jumlah 24,662.86
Jumlah keseluruhan 627,100.36
Keuntungan dan Overhead 10% 62,710.04
Total 689,810.39

m' Instalasi Kabel Ladder UK.30x10cm c/w asesoris,suppot&hanger


Instalasi Kabel Ladder UK.30x10cm c/w asesoris,suppot&hanger bh 1.00 140,000.00 140,000.00
Material bantu Lot 1.00 7,000.00 7,000.00
Jumlah 147,000.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 177,828.57
Keuntungan dan Overhead 10% 17,782.86
Total 195,611.43

m' Instalasi Kabel Ladder UK.40x10cm c/w asesoris,suppot&hanger


Instalasi Kabel Ladder UK.40x10cm c/w asesoris,suppot&hanger bh 1.00 151,000.00 151,000.00
Material bantu Lot 1.00 7,550.00 7,550.00
Jumlah 158,550.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 189,378.57
Keuntungan dan Overhead 10% 18,937.86
Total 208,316.43

m' Instalasi Kabel NYY 4 x 10mm2 + NYA 1 x 10mm2


Instalasi Kabel NYY 4 x 10mm2 + NYA 1 x 10mm2 bh 1.00 84,000.00 84,000.00
Material bantu Lot 1.00 4,200.00 4,200.00
Jumlah 88,200.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 119,028.57
Keuntungan dan Overhead 10% 11,902.86
Total 130,931.43

m' Instalasi Kabel NYY 4 x 16mm2 + NYA 1 x 16mm2


Instalasi Kabel NYY 4 x 16mm2 + NYA 1 x 16mm2 bh 1.00 102,500.00 102,500.00
Material bantu Lot 1.00 5,125.00 5,125.00
Jumlah 107,625.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 138,453.57
Keuntungan dan Overhead 10% 13,845.36
Total 152,298.93

m' Instalasi Kabel NYY 4 x 240mm2 + NYA 1 x 50mm2


Instalasi Kabel NYY 4 x 240mm2 + NYA 1 x 50mm2 bh 1.00 1,430,000.00 1,430,000.00
Material bantu Lot 1.00 71,500.00 71,500.00
Jumlah 1,501,500.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 1,532,328.57
Keuntungan dan Overhead 10% 153,232.86
Total 1,685,561.43

m' Instalasi Kabel NYY 4 x 25mm2 + NYA 1 x 16mm2


Instalasi Kabel NYY 4 x 25mm2 + NYA 1 x 16mm2 bh 1.00 178,500.00 178,500.00
Material bantu Lot 1.00 8,925.00 8,925.00
Jumlah 187,425.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 218,253.57
Keuntungan dan Overhead 10% 21,825.36
Total 240,078.93
DIBULATKAN 240,000.00
m' Instalasi Kabel NYY 4 x 35mm2 + NYA 1 x 25mm2
Instalasi Kabel NYY 4 x 35mm2 + NYA 1 x 25mm2 bh 1.00 203,000.00 203,000.00
Material bantu Lot 1.00 10,150.00 10,150.00
Jumlah 213,150.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 243,978.57
Keuntungan dan Overhead 10% 24,397.86
Total 268,376.43
DIBULATKAN 268,300.00
m' Instalasi Kabel NYY 4 x 4mm2 + NYA 1 x 4mm2
Instalasi Kabel NYY 4 x 4mm2 + NYA 1 x 4mm2 bh 1.00 36,900.00 36,900.00
Material bantu Lot 1.00 1,845.00 1,845.00
Jumlah 38,745.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 69,573.57
Keuntungan dan Overhead 10% 6,957.36
Total 76,530.93
DIBULATKAN 76,500.00
m' Instalasi Kabel NYY 4 x 6mm2 + NYA 1 x 6mm2
Instalasi Kabel NYY 4 x 6mm2 + NYA 1 x 6mm2 mtr 1.00 52,100.00 52,100.00
Material bantu Lot 1.00 2,605.00 2,605.00
Jumlah 54,705.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 85,533.57
Keuntungan dan Overhead 10% 8,553.36
Total 94,086.93
DIBULATKAN 94,000.00

m' NYY 4 x 185mm2 + NYA 1 x 50mm2


NYY 4 x 185mm2 + NYA 1 x 50mm2 mtr 1.00 1,430,000.00 1,430,000.00
Material bantu Lot 1.00 71,500.00 71,500.00
Jumlah 1,501,500.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 1,532,328.57
Keuntungan dan Overhead 10% 153,232.86
Total 1,685,561.43
DIBULATKAN 1,685,500.00
m' Instalasi Kabel Tray UK.30x10cm c/w asesoris,suppot&hanger
Instalasi Kabel Tray UK.30x10cm c/w asesoris,suppot&hanger bh 1.00 230,000.00 230,000.00
Material bantu Lot 1.00 11,500.00 11,500.00
Jumlah 241,500.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 272,328.57
Keuntungan dan Overhead 10% 27,232.86
Total 299,561.43
DIBULATKAN 299,500.00
m' Instalasi Kabel Tray UK.40x10cm c/w asesoris,suppot&hanger
Instalasi Kabel Tray UK.40x10cm c/w asesoris,suppot&hanger bh 1.00 276,000.00 276,000.00
Material bantu Lot 1.00 13,800.00 13,800.00
Jumlah 289,800.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 320,628.57
Keuntungan dan Overhead 10% 32,062.86
Total 352,691.43
DIBULATKAN 352,600.00
ttk Instalasi Kotak Kontak kabel NYM 3 x 2.5 mm2 + Conduit dia.20mm
Instalasi Kotak Kontak kabel NYM 3 x 2.5 mm2 + Conduit dia.20mm bh 12.00 18,000.00 216,000.00
Material bantu Lot 1.00 10,800.00 10,800.00
Jumlah 226,800.00
UPAH KERJA
Pekerja oh 0.20 132,000.00 26,400.00
Tukang Listrik oh 0.10 188,571.44 18,857.14
Kepala Tukang Listrik oh 0.06 200,000.00 12,000.00
Mandor oh 0.02 220,000.00 4,400.00
Jumlah 61,657.14
Jumlah keseluruhan 288,457.14
Keuntungan dan Overhead 10% 28,845.71
Total 317,302.86
DIBULATKAN 317,300.00

ttk Instalasi Penerangan kabel NYM 3 x 2,5 mm2 + Conduit dia.20mm


Instalasi Penerangan kabel NYM 3 x 2,5 mm2 + Conduit dia.20mm mtr 10.00 18,000.00 180,000.00
Material bantu Lot 1.00 9,000.00 9,000.00
Jumlah 189,000.00
UPAH KERJA
Pekerja oh 0.20 132,000.00 26,400.00
Tukang Listrik oh 0.10 188,571.44 18,857.14
Kepala Tukang Listrik oh 0.06 200,000.00 12,000.00
Mandor oh 0.02 220,000.00 4,400.00
Jumlah 61,657.14
Jumlah keseluruhan 250,657.14
Keuntungan dan Overhead 10% 25,065.71
Total 275,722.86
DIBULATKAN 275,700.00
ttk Instalasi Sakelar kabel NYM 2 x 2,5 mm2 + Conduit dia.20mm
Instalasi Sakelar kabel NYM 2 x 2,5 mm2 + Conduit dia.20mm bh 1.00 173,700.00 173,700.00
Material bantu Lot 1.00 8,685.00 8,685.00
Jumlah 182,385.00
UPAH KERJA
Pekerja oh 0.20 132,000.00 26,400.00
Tukang Listrik oh 0.10 188,571.44 18,857.14
Kepala Tukang Listrik oh 0.06 200,000.00 12,000.00
Mandor oh 0.02 220,000.00 4,400.00
Jumlah 61,657.14
Jumlah keseluruhan 244,042.14
Keuntungan dan Overhead 10% 24,404.21
Total 268,446.36
DIBULATKAN 268,400.00

bh #REF!
#REF! bh 1.00 1,200,000.00 1,200,000.00
Material bantu Lot 1.00 60,000.00 60,000.00
Jumlah 1,260,000.00
UPAH KERJA
Pekerja oh 0.20 132,000.00 26,400.00
Tukang Listrik oh 0.10 188,571.44 18,857.14
Kepala Tukang Listrik oh 0.06 200,000.00 12,000.00
Mandor oh 0.02 220,000.00 4,400.00
Jumlah 61,657.14
Jumlah keseluruhan 1,321,657.14
Keuntungan dan Overhead 10% 132,165.71
Total 1,453,822.86
DIBULATKAN 1,453,800.00

unit Kotak Kontak 1Fasa 250w


Kotak Kontak 1Fasa 250w bh 1.00 22,000.00 22,000.00
Material bantu Lot 1.00 1,100.00 1,100.00
Jumlah 23,100.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 38,514.29
Keuntungan dan Overhead 10% 3,851.43
Total 42,365.71
DIBULATKAN 42,300.00

unit Lampu Downlight LED 10W (E27) Recessed Mounted / RM


Lampu Downlight LED 10W (E27) Recessed Mounted / RM bh 1.00 166,000.00 166,000.00
Material bantu Lot 1.00 8,300.00 8,300.00
Jumlah 174,300.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 189,714.29
Keuntungan dan Overhead 10% 18,971.43
Total 208,685.71
DIBULATKAN 208,600.00

unit Lampu Exit Kap.10w c/w Batrei Cadangan Listrik


Lampu Exit Kap.10w c/w Batrei Cadangan Listrik bh 1.00 650,000.00 650,000.00
Material bantu Lot 1.00 32,500.00 32,500.00
Jumlah 682,500.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 697,914.29
Keuntungan dan Overhead 10% 69,791.43
Total 767,705.71
DIBULATKAN 767,700.00

unit Lampu TL LED 2x16W Recessed Mounted / RM Cover Louvre M5


Lampu TL LED 2x16W Recessed Mounted / RM Cover Louvre M5 bh 1.00 710,000.00 710,000.00
Material bantu Lot 1.00 35,500.00 35,500.00
Jumlah 745,500.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 760,914.29
Keuntungan dan Overhead 10% 76,091.43
Total 837,005.71
DIBULATKAN 837,000.00

unit #REF!
#REF! bh 1.00 175,000.00 175,000.00
Material bantu Lot 1.00 8,750.00 8,750.00
Jumlah 183,750.00
UPAH KERJA
Pekerja oh 0.05 - -
Tukang Listrik oh 0.03 132,000.00 3,300.00
Kepala Tukang Listrik oh 0.02 188,571.44 2,828.57
Mandor oh 0.01 200,000.00 1,000.00
Jumlah 7,128.57
Jumlah keseluruhan 190,878.57
Keuntungan dan Overhead 10% 19,087.86
Total 209,966.43
DIBULATKAN 209,900.00

unit Saklar Dua Arah


Saklar Dua Arah bh 1.00 32,000.00 32,000.00
Material bantu Lot 1.00 1,600.00 1,600.00
Jumlah 33,600.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 49,014.29
Keuntungan dan Overhead 10% 4,901.43
Total 53,915.71
DIBULATKAN 53,900.00
unit Saklar Ganda
Saklar Ganda bh 1.00 26,000.00 26,000.00
Material bantu Lot 1.00 1,300.00 1,300.00
Jumlah 27,300.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 42,714.29
Keuntungan dan Overhead 10% 4,271.43
Total 46,985.71
DIBULATKAN 46,900.00
unit Saklar Tunggal
Saklar Tunggal bh 1.00 23,000.00 23,000.00
Material bantu Lot 1.00 1,150.00 1,150.00
Jumlah 24,150.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 39,564.29
Keuntungan dan Overhead 10% 3,956.43
Total 43,520.71
DIBULATKAN 43,500.00
unit Lampu TKO TL LED 2x16W Surface Mounted
Lampu TKO TL LED 2x16W Surface Mounted bh 1.00 450,000.00 450,000.00
Material bantu Lot 1.00 22,500.00 22,500.00
Jumlah 472,500.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 487,914.29
Keuntungan dan Overhead 10% 48,791.43
Total 536,705.71
DIBULATKAN 536,700.00

bh #REF!
#REF! bh 1.00 3,500,000.00 3,500,000.00
Material bantu Lot 1.00 175,000.00 175,000.00
Jumlah 3,675,000.00
UPAH KERJA
Pekerja oh 1.00 132,000.00 132,000.00
Tukang Listrik oh 0.50 188,571.44 94,285.72
Kepala Tukang Listrik oh 0.30 200,000.00 60,000.00
Mandor oh 0.10 220,000.00 22,000.00
Jumlah 308,285.72
Jumlah keseluruhan 3,983,285.72
Keuntungan dan Overhead 10% 398,328.57
Total 4,381,614.29
DIBULATKAN 4,381,600.00
lot Penyambungan Daya PLN lkp SLO,UJL
Penyambungan Daya PLN lkp SLO,UJL kVA 1.00 1,020,000.00 1,020,000.00
Material bantu Lot 1.00 51,000.00 51,000.00
Jumlah 1,071,000.00
UPAH KERJA
Pekerja oh 0.50 132,000.00 66,000.00
Tukang Listrik oh 0.25 188,571.44 47,142.86
Kepala Tukang Listrik oh 0.15 200,000.00 30,000.00
Mandor oh 0.05 220,000.00 11,000.00
Jumlah 154,142.86
Jumlah keseluruhan 1,225,142.86
Keuntungan dan Overhead 10% 122,514.29
Total 1,347,657.15
DIBULATKAN 1,347,600.00
mtr FRC 4x35mm2 + PVC∅50
FRC 4x35mm2 + PVC∅50 bh 1.00 649,600.00 649,600.00
Material bantu Lot 1.00 32,480.00 32,480.00
Jumlah 682,080.00
UPAH KERJA
Pekerja oh 0.12 132,000.00 15,840.00
Tukang Listrik oh 0.06 188,571.44 11,314.29
Kepala Tukang Listrik oh 0.04 200,000.00 7,200.00
Mandor oh 0.01 220,000.00 2,640.00
Jumlah 36,994.29
Jumlah keseluruhan 719,074.29
Keuntungan dan Overhead 10% 71,907.43
Total 790,981.72
DIBULATKAN 790,900.00
bh Lampu PJU Solar Cell LED 60 tiang Hexagonal 9m + Pondasi
Lampu PJU Solar Cell LED 60 tiang Hexagonal 9m + Pondasi bh 1.00 21,500,000.00 21,500,000.00
Material bantu Lot 1.00 1,075,000.00 1,075,000.00
Jumlah 22,575,000.00
UPAH KERJA
Pekerja oh 3.00 132,000.00 396,000.00
Tukang Listrik oh 1.50 188,571.44 282,857.16
Kepala Tukang Listrik oh 0.90 200,000.00 180,000.00
Mandor oh 0.30 220,000.00 66,000.00
Jumlah 924,857.16
Jumlah keseluruhan 23,499,857.16
Keuntungan dan Overhead 10% 2,349,985.72
Total 25,849,842.88
DIBULATKAN 25,849,800.00
bh #REF!
#REF! bh 1.00 22,500,000.00 22,500,000.00
Material bantu Lot 1.00 1,125,000.00 1,125,000.00
Jumlah 23,625,000.00
UPAH KERJA
Pekerja oh 3.00 132,000.00 396,000.00
Tukang Listrik oh 1.50 188,571.44 282,857.16
Kepala Tukang Listrik oh 0.90 200,000.00 180,000.00
Mandor oh 0.30 220,000.00 66,000.00
Jumlah 924,857.16
Jumlah keseluruhan 24,549,857.16
Keuntungan dan Overhead 10% 2,454,985.72
Total 27,004,842.88
DIBULATKAN 27,004,800.00
bh Air Terminal Radius 120M c/w terminasi
Air Terminal Radius 120M c/w terminasi bh 1.00 15,300,000.00 15,300,000.00
Material bantu Lot 1.00 765,000.00 765,000.00
Jumlah 16,065,000.00
UPAH KERJA
Pekerja oh 0.20 132,000.00 26,400.00
Tukang Listrik oh 0.10 188,571.44 18,857.14
Kepala Tukang Listrik oh 0.06 200,000.00 12,000.00
Mandor oh 0.02 220,000.00 4,400.00
Jumlah 61,657.14
Jumlah keseluruhan 16,126,657.14
Keuntungan dan Overhead 10% 1,612,665.71
Total 17,739,322.86
DIBULATKAN 17,739,300.00
bh Kabel BC 70 mm2
Kabel BC 70 mm2 bh 1.00 56,300.00 56,300.00
Material bantu Lot 1.00 2,815.00 2,815.00
Jumlah 59,115.00
UPAH KERJA
Pekerja oh 0.15 132,000.00 19,800.00
Tukang Listrik oh 0.08 188,571.44 14,142.86
Kepala Tukang Listrik oh 0.05 200,000.00 9,000.00
Mandor oh 0.02 220,000.00 3,300.00
Jumlah 46,242.86
Jumlah keseluruhan 105,357.86
Keuntungan dan Overhead 10% 10,535.79
Total 115,893.64
DIBULATKAN 115,800.00
bh Grounding Rod dia 20mm
Grounding Rod dia 20mm bh 1.00 380,000.00 380,000.00
Material bantu Lot 1.00 19,000.00 19,000.00
Jumlah 399,000.00
UPAH KERJA
Pekerja oh 0.25 132,000.00 33,000.00
Tukang Listrik oh 0.13 188,571.44 23,571.43
Kepala Tukang Listrik oh 0.08 200,000.00 15,000.00
Mandor oh 0.03 220,000.00 5,500.00
Jumlah 77,071.43
Jumlah keseluruhan 476,071.43
Keuntungan dan Overhead 10% 47,607.14
Total 523,678.57
DIBULATKAN 523,600.00
bh Bak Kontrol
Bak Kontrol bh 1.00 350,000.00 350,000.00
Material bantu Lot 1.00 17,500.00 17,500.00
Jumlah 367,500.00
UPAH KERJA
Pekerja oh 0.50 132,000.00 66,000.00
Tukang Listrik oh 0.25 188,571.44 47,142.86
Kepala Tukang Listrik oh 0.15 200,000.00 30,000.00
Mandor oh 0.05 220,000.00 11,000.00
Jumlah 154,142.86
Jumlah keseluruhan 521,642.86
Keuntungan dan Overhead 10% 52,164.29
Total 573,807.15
DIBULATKAN 573,800.00
Bh Alarm Bell
Alarm Bell bh 1.00 350,000.00 350,000.00
Material bantu Lot 1.00 17,500.00 17,500.00
Jumlah 367,500.00
UPAH KERJA
Pekerja oh 0.10 132,000.00 13,200.00
Tukang Listrik oh 0.05 188,571.44 9,428.57
Kepala Tukang Listrik oh 0.03 200,000.00 6,000.00
Mandor oh 0.01 220,000.00 2,200.00
Jumlah 30,828.57
Jumlah keseluruhan 398,328.57
Keuntungan dan Overhead 10% 39,832.86
Total 438,161.43
DIBULATKAN 438,100.00

Bh Ceiling Speaker 3 watt


Ceiling Speaker 3 watt bh 1.00 165,000.00 165,000.00
Material bantu Lot 1.00 8,250.00 8,250.00
Jumlah 173,250.00
UPAH KERJA
Pekerja oh 0.25 132,000.00 33,000.00
Tukang Listrik oh 0.13 188,571.44 23,571.43
Kepala Tukang Listrik oh 0.08 200,000.00 15,000.00
Mandor oh 0.03 220,000.00 5,500.00
Jumlah 77,071.43
Jumlah keseluruhan 250,321.43
Keuntungan dan Overhead 10% 25,032.14
Total 275,353.57
DIBULATKAN 275,300.00

bh Indicator Lamp
Indicator Lamp bh 1.00 247,000.00 247,000.00
Material bantu Lot 1.00 12,350.00 12,350.00
Jumlah 259,350.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 274,764.29
Keuntungan dan Overhead 10% 27,476.43
Total 302,240.71
DIBULATKAN 302,200.00
Ttk Instalasi Titik Detector 2 x NYA 1,5 mm2+conduit 20mm
Instalasi Titik Detector 2 x NYA 1,5 mm2+conduit 20mm mtr 15.00 13,600.00 204,000.00
Material bantu Lot 1.00 10,200.00 10,200.00
Jumlah 214,200.00
UPAH KERJA
Pekerja oh 0.02 132,000.00 2,640.00
Tukang Listrik oh 0.01 188,571.44 1,885.71
Kepala Tukang Listrik oh 0.01 200,000.00 1,200.00
Mandor oh 0.00 220,000.00 440.00
Jumlah 6,165.71
Jumlah keseluruhan 220,365.71
Keuntungan dan Overhead 10% 22,036.57
Total 242,402.29
DIBULATKAN 242,400.00
Ttk Instalasi Titik Speaker
Instalasi Titik Speaker bh 1.00 162,600.00 162,600.00
Material bantu Lot 1.00 8,130.00 8,130.00
Jumlah 170,730.00
UPAH KERJA
Pekerja oh 0.02 132,000.00 2,640.00
Tukang Listrik oh 0.01 188,571.44 1,885.71
Kepala Tukang Listrik oh 0.01 200,000.00 1,200.00
Mandor oh 0.00 220,000.00 440.00
Jumlah 6,165.71
Jumlah keseluruhan 176,895.71
Keuntungan dan Overhead 10% 17,689.57
Total 194,585.29
DIBULATKAN 194,500.00
titik Instalasi titik data dengan Kabel UTP cat 6 + HIC Ø 20 mm
Instalasi titik data dengan Kabel UTP cat 6 + HIC Ø 20 mm bh 1.00 18,500.00 18,500.00
Material bantu Lot 1.00 925.00 925.00
Jumlah 19,425.00
UPAH KERJA
Pekerja oh 0.02 132,000.00 2,640.00
Tukang Listrik oh 0.01 188,571.44 1,885.71
Kepala Tukang Listrik oh 0.01 200,000.00 1,200.00
Mandor oh 0.00 220,000.00 440.00
Jumlah 6,165.71
Jumlah keseluruhan 25,590.71
Keuntungan dan Overhead 10% 2,559.07
Total 28,149.79
DIBULATKAN 28,100.00
titik Instalasi titik stop kontak
Instalasi titik stop kontak bh 1.00 227,400.00 227,400.00
Material bantu Lot 1.00 11,370.00 11,370.00
Jumlah 238,770.00
UPAH KERJA
Pekerja oh 0.02 132,000.00 2,640.00
Tukang Listrik oh 0.01 188,571.44 1,885.71
Kepala Tukang Listrik oh 0.01 200,000.00 1,200.00
Mandor oh 0.00 220,000.00 440.00
Jumlah 6,165.71
Jumlah keseluruhan 244,935.71
Keuntungan dan Overhead 10% 24,493.57
Total 269,429.29
DIBULATKAN 269,400.00
titik Instalasi titik data dengan Kabel UTP cat 6 + HIC Ø 20 mm
Instalasi titik data dengan Kabel UTP cat 6 + HIC Ø 20 mm mtr 20.00 18,500.00 370,000.00
Material bantu Lot 1.00 18,500.00 18,500.00
Jumlah 388,500.00
UPAH KERJA
Pekerja oh 0.02 132,000.00 2,640.00
Tukang Listrik oh 0.01 188,571.44 1,885.71
Kepala Tukang Listrik oh 0.01 200,000.00 1,200.00
Mandor oh 0.00 220,000.00 440.00
Jumlah 6,165.71
Jumlah keseluruhan 394,665.71
Keuntungan dan Overhead 10% 39,466.57
Total 434,132.29
DIBULATKAN 434,100.00
titik Instalasi titik camera dengan Kabel UTP cat 6 + HIC Ø 20 mm
Instalasi titik camera dengan Kabel UTP cat 6 + HIC Ø 20 mm mtr 40.00 18,500.00 740,000.00
Material bantu Lot 1.00 37,000.00 37,000.00
Jumlah 777,000.00
UPAH KERJA
Pekerja oh 0.02 132,000.00 2,640.00
Tukang Listrik oh 0.01 188,571.44 1,885.71
Kepala Tukang Listrik oh 0.01 200,000.00 1,200.00
Mandor oh 0.00 220,000.00 440.00
Jumlah 6,165.71
Jumlah keseluruhan 783,165.71
Keuntungan dan Overhead 10% 78,316.57
Total 861,482.29
DIBULATKAN 861,400.00
titik Instalasi titik Telephone dengan Kabel UTP cat 6 + HIC Ø 20 mm
Instalasi titik Telephone dengan Kabel UTP cat 6 + HIC Ø 20 mm bh 40.00 18,500.00 740,000.00
Material bantu Lot 1.00 37,000.00 37,000.00
Jumlah 777,000.00
UPAH KERJA
Pekerja oh 0.02 132,000.00 2,640.00
Tukang Listrik oh 0.01 188,571.44 1,885.71
Kepala Tukang Listrik oh 0.01 200,000.00 1,200.00
Mandor oh 0.00 220,000.00 440.00
Jumlah 6,165.71
Jumlah keseluruhan 783,165.71
Keuntungan dan Overhead 10% 78,316.57
Total 861,482.29
DIBULATKAN 861,400.00

bh Kabel Utama ke TB
Kabel Utama ke TB bh 1.00 45,000.00 45,000.00
Material bantu Lot 1.00 2,250.00 2,250.00
Jumlah 47,250.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 62,664.29
Keuntungan dan Overhead 10% 6,266.43
Total 68,930.71
DIBULATKAN 68,900.00
bh Panel Control Fire Alarm 2 Loop
Panel Control Fire Alarm 2 Loop bh 1.00 34,500,000.00 34,500,000.00
Material bantu Lot 1.00 1,725,000.00 1,725,000.00
Jumlah 36,225,000.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 36,240,414.29
Keuntungan dan Overhead 10% 3,624,041.43
Total 39,864,455.71
DIBULATKAN 39,864,400.00
bh Koneksi titik grounding
Koneksi titik grounding bh 1.00 750,000.00 750,000.00
Material bantu Lot 1.00 37,500.00 37,500.00
Jumlah 787,500.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 802,914.29
Keuntungan dan Overhead 10% 80,291.43
Total 883,205.71
DIBULATKAN 883,200.00
Bh Manual Break Glass
Manual Break Glass bh 1.00 450,000.00 450,000.00
Material bantu Lot 1.00 22,500.00 22,500.00
Jumlah 472,500.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 487,914.29
Keuntungan dan Overhead 10% 48,791.43
Total 536,705.71
DIBULATKAN 536,700.00
unit Terminal MDF-FA
Terminal MDF-FA bh 1.00 850,000.00 850,000.00
Material bantu Lot 1.00 42,500.00 42,500.00
Jumlah 892,500.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 907,914.29
Keuntungan dan Overhead 10% 90,791.43
Total 998,705.71
DIBULATKAN 998,700.00

bh Outlet data
Outlet data bh 1.00 65,000.00 65,000.00
Material bantu Lot 1.00 3,250.00 3,250.00
Jumlah 68,250.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 83,664.29
Keuntungan dan Overhead 10% 8,366.43
Total 92,030.71
DIBULATKAN 92,000.00

bh Outlet data untuk telephone


Outlet data untuk telephone bh 1.00 65,000.00 65,000.00
Material bantu Lot 1.00 3,250.00 3,250.00
Jumlah 68,250.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 83,664.29
Keuntungan dan Overhead 10% 8,366.43
Total 92,030.71
DIBULATKAN 92,000.00

bh Heat Detector
Heat Detector bh 1.00 576,000.00 576,000.00
Material bantu Lot 1.00 28,800.00 28,800.00
Jumlah 604,800.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 620,214.29
Keuntungan dan Overhead 10% 62,021.43
Total 682,235.71
DIBULATKAN 682,200.00
Bh Smoke detector
Smoke detector bh 1.00 625,000.00 625,000.00
Material bantu Lot 1.00 31,250.00 31,250.00
Jumlah 656,250.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 671,664.29
Keuntungan dan Overhead 10% 67,166.43
Total 738,830.71
DIBULATKAN 738,800.00
bh Stop kontak
Stop kontak bh 1.00 22,000.00 22,000.00
Material bantu Lot 1.00 1,100.00 1,100.00
Jumlah 23,100.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 38,514.29
Keuntungan dan Overhead 10% 3,851.43
Total 42,365.71
DIBULATKAN 42,300.00

unit #REF!
#REF! bh 1.00 3,500,000.00 3,500,000.00
Material bantu + Switch 48 Port Gigabit Tp lInk Lot 1.00 4,500,000.00 4,500,000.00
Jumlah 8,000,000.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 8,015,414.29
Keuntungan dan Overhead 10% 801,541.43
Total 8,816,955.71
DIBULATKAN 8,816,900.00
Unt Terminal Box Tata Suara
Terminal Box Tata Suara bh 1.00 250,000.00 250,000.00
Material bantu Lot 1.00 12,500.00 12,500.00
Jumlah 262,500.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 277,914.29
Keuntungan dan Overhead 10% 27,791.43
Total 305,705.71
DIBULATKAN 305,700.00
Bh Terminal Box TBF
Terminal Box TBF bh 1.00 2,300,000.00 2,300,000.00
Material bantu Lot 1.00 115,000.00 115,000.00
Jumlah 2,415,000.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 2,430,414.29
Keuntungan dan Overhead 10% 243,041.43
Total 2,673,455.71
DIBULATKAN 2,673,400.00
Bh Panel MDF TS
Panel MDF TS bh 1.00 750,000.00 750,000.00
Material bantu Lot 1.00 37,500.00 37,500.00
Jumlah 787,500.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 802,914.29
Keuntungan dan Overhead 10% 80,291.43
Total 883,205.71
DIBULATKAN 883,200.00
bh #REF!
#REF! bh 1.00 550,000.00 550,000.00
Material bantu Lot 1.00 27,500.00 27,500.00
Jumlah 577,500.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 592,914.29
Keuntungan dan Overhead 10% 59,291.43
Total 652,205.71
DIBULATKAN 652,200.00
bh Volume Control
Volume Control bh 1.00 214,001.00 214,001.00
Material bantu Lot 1.00 10,700.05 10,700.05
Jumlah 224,701.05
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 240,115.34
Keuntungan dan Overhead 10% 24,011.53
Total 264,126.87
DIBULATKAN 264,100.00

bh NVR kapasitas 16 channel


NVR kapasitas 16 channel bh 1.00 19,700,000.00 19,700,000.00
Material bantu Lot 1.00 985,000.00 985,000.00
Jumlah 20,685,000.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 20,700,414.29
Keuntungan dan Overhead 10% 2,070,041.43
Total 22,770,455.71
DIBULATKAN 22,770,400.00

bh Monitor led 32 Inch


Monitor led 32 Inch bh 1.00 2,800,000.00 2,800,000.00
Material bantu Lot 1.00 140,000.00 140,000.00
Jumlah 2,940,000.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 2,955,414.29
Keuntungan dan Overhead 10% 295,541.43
Total 3,250,955.71
DIBULATKAN 3,250,900.00

bh #REF!
#REF! bh 1.00 890,000.00 890,000.00
Material bantu Lot 1.00 44,500.00 44,500.00
Jumlah 934,500.00
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 949,914.29
Keuntungan dan Overhead 10% 94,991.43
Total 1,044,905.71
DIBULATKAN 1,044,900.00

bh IP CCTV camera 2 MP
IP CCTV camera 2 MP bh 1.00 2,078,865.94 2,078,865.94
Material bantu Lot 1.00 103,943.30 103,943.30
Jumlah 2,182,809.23
UPAH KERJA
Pekerja oh 0.05 132,000.00 6,600.00
Tukang Listrik oh 0.03 188,571.44 4,714.29
Kepala Tukang Listrik oh 0.02 200,000.00 3,000.00
Mandor oh 0.01 220,000.00 1,100.00
Jumlah 15,414.29
Jumlah keseluruhan 2,198,223.52
Keuntungan dan Overhead 10% 219,822.35
Total 2,418,045.87
DIBULATKAN 2,418,000.00

ANALISA HARGA SATUAN PEKERJAAN (AHSP)

PEKERJAAN DED KAWASAN CIPUTRI BANTEN LAMA


APBD TAHUN ANGGARAN 2019

4.4.1.8Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 3PP
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.3000 120,000.00 36,000.00
Tukang Batu OH 0.1000 120,000.00 12,000.00
Kepala Tukang OH 0.0100 140,000.00 1,400.00
Mandor OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 51,650.00
B BAHAN
Bata merah M3 70.0000 590.00 41,300.00
Semen Portlan Kg 14.3700 1,585.10 22,777.89
Pasir Pasang M3 0.0400 216,150.00 8,646.00
JUMLAH HARGA BAHAN 72,723.89
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 124,373.89


E Overhead & Profit 10% x D 12,437.39
F Harga Satuan Pekerjaan (D+E) 136,811.28

4.4.1.10Pemasangan 1 m2 dinding bata merah (5x11x22) cm tebal 1/2 batu campuran 1SP : 5PP
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.3000 120,000.00 36,000.00
Tukang Batu OH 0.1000 120,000.00 12,000.00
Kepala Tukang OH 0.0100 140,000.00 1,400.00
Mandor OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 51,650.00
B BAHAN
Bata merah M3 70.0000 590.00 41,300.00
Semen Portlan Kg 9.6800 1,585.10 15,343.77
Pasir Pasang M3 0.0450 216,150.00 9,726.75
JUMLAH HARGA BAHAN 66,370.52
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 118,020.52


E Overhead & Profit 10% x D 11,802.05
F Harga Satuan Pekerjaan (D+E) 129,822.57

4.4.2.14Pemasangan 1 m2 plesteran 1SP : 3PP tebal 20 mm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2600 120,000.00 31,200.00
Tukang Batu OH 0.2000 120,000.00 24,000.00
Kepala Tukang OH 0.0200 140,000.00 2,800.00
Mandor OH 0.0130 150,000.00 1,950.00
JUMLAH TENAGA KERJA 59,950.00
B BAHAN
Semen PC Kg 10.3680 1,585.10 16,434.32
Pasir pasang M3 0.0310 216,150.00 6,700.65
JUMLAH HARGA BAHAN 23,134.97
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 83,084.97


E Overhead & Profit 10% x D 8,308.50
F Harga Satuan Pekerjaan (D+E) 91,393.46

4.4.2.16Pemasangan 1 m2 plesteran 1SP : 5PP tebal 20 mm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.4000 120,000.00 48,000.00
Tukang Batu OH 0.2000 120,000.00 24,000.00
Kepala Tukang OH 0.0200 140,000.00 2,800.00
Mandor OH 0.0220 150,000.00 3,300.00
JUMLAH TENAGA KERJA 78,100.00
B BAHAN
Semen PC Kg 6.9120 1,585.10 10,956.21
Pasir pasang M3 0.0350 216,150.00 7,565.25
JUMLAH HARGA BAHAN 18,521.46
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 96,621.46


E Overhead & Profit 10% x D 9,662.15
F Harga Satuan Pekerjaan (D+E) 106,283.61

4.4.2.23Pemasangan 1 m2 plesteran ciprat 1SP : 2PP


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.3000 120,000.00 36,000.00
Tukang Batu OH 0.1000 120,000.00 12,000.00
Kepala Tukang OH 0.0100 140,000.00 1,400.00
Mandor OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 51,650.00
B BAHAN
Semen PC Kg 4.3200 1,585.10 6,847.63
Pasir pasang Kg 0.0060 216,150.00 1,296.90
JUMLAH HARGA BAHAN 8,144.53
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 59,794.53


E Overhead & Profit 10% x D 5,979.45
F Harga Satuan Pekerjaan (D+E) 65,773.99
4.4.2.27Pemasangan 1 m2 acian
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2000 120,000.00 24,000.00
Tukang Batu OH 0.1000 120,000.00 12,000.00
Kepala Tukang OH 0.0100 140,000.00 1,400.00
Mandor OH 0.0100 150,000.00 1,500.00
JUMLAH TENAGA KERJA 38,900.00
B BAHAN
Semen PC Kg 3.2500 1,585.10 5,151.58
JUMLAH HARGA BAHAN 5,151.58
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 44,051.58


E Overhead & Profit 10% x D 4,405.16
F Harga Satuan Pekerjaan (D+E) 48,456.73

4.4.1.22Pemasangan 1 m2 dinding kerawang t : 5


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.3000 120,000.00 36,000.00
Tukang Batu OH 0.1000 120,000.00 12,000.00
Kepala Tukang OH 0.0100 140,000.00 1,400.00
Mandor OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 51,650.00
B BAHAN
Kerawang t : 5 bh 44.0000 35,000.00 1,540,000.00
Semen Portland Kg 11.0000 1,585.10 17,436.10
Pasir Pasang M3 0.0350 216,150.00 7,565.25
JUMLAH HARGA BAHAN 1,565,001.35
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,616,651.35


E Overhead & Profit 10% x D 161,665.14
F Harga Satuan Pekerjaan (D+E) 1,778,316.49

4.2.1.11Pemasangan 1 m Kusen Aluminium ukuran 4" sek. YKK YBIC t = 1,35 mm Lengkap Assesoris
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0430 120,000.00 5,160.00
Tukang Khusus OH 0.0430 117,376.00 5,047.17
Alumunium
Kepala tukang OH 0.0043 140,000.00 602.00
Mandor OH 0.0021 150,000.00 315.00
JUMLAH TENAGA KERJA 11,124.17
B BAHAN
Profil alluminium M 1.1000 200,850.00 220,935.00
Skrup fixer Buah 2.0000 247.89 495.78
Sealant Tube 0.0600 35,000.00 2,100.00
JUMLAH HARGA BAHAN 223,530.78
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 234,654.95


E Overhead & Profit 10% x D 23,465.49
F Harga Satuan Pekerjaan (D+E) 258,120.44

4.2.1.12Pemasangan 1 m2 pintu alumunium strip lebar 8 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0850 120,000.00 10,200.00
Tukang Khusus OH 0.0850 117,376.00 9,976.96
Allumunium
Kepala tukang OH 0.0085 140,000.00 1,190.00
Mandor OH 0.0042 150,000.00 630.00
JUMLAH TENAGA KERJA 21,996.96
B BAHAN
Profil alluminium M 4.4000 200,850.00 883,740.00
Alluminium strip M 14.6000 125,000.00 1,825,000.00
JUMLAH HARGA BAHAN 2,708,740.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 2,730,736.96


E Overhead & Profit 10% x D 273,073.70
F Harga Satuan Pekerjaan (D+E) 3,003,810.66

4.4.3.13Pemasangan 1 m2 lantai granit tile ukuran 60cm x 60cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2400 120,000.00 28,800.00
Tukang Batu OH 0.1200 120,000.00 14,400.00
Kepala tukang OH 0.0120 140,000.00 1,680.00
Mandor OH 0.1200 150,000.00 18,000.00
JUMLAH TENAGA KERJA 62,880.00
B BAHAN
Granite tile Bh 3.1000 45,000.00 139,500.00
Semen Portlan Kg 9.6000 1,585.10 15,216.96
Semen warna Kg 1.5000 21,615.00 32,422.50
Pasir pasang M3 0.0450 216,150.00 9,726.75
JUMLAH HARGA BAHAN 196,866.21
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 259,746.21


E Overhead & Profit 10% x D 25,974.62
F Harga Satuan Pekerjaan (D+E) 285,720.83

4.4.3.58Pemasangan 1 m2 dinding batu tempel Andesit


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.7000 120,000.00 84,000.00
Tukang Batu OH 0.3500 120,000.00 42,000.00
Kepala tukang OH 0.0350 140,000.00 4,900.00
Mandor OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 136,150.00
B BAHAN
Batu temple hitam Bh 1.1000 45,000.00 49,500.00
Semen Portlan Kg 11.7500 1,585.10 18,624.93
Pasir Pasang M3 0.0350 216,150.00 7,565.25
JUMLAH HARGA BAHAN 75,690.18
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 211,840.18


E Overhead & Profit 10% x D 21,184.02
F Harga Satuan Pekerjaan (D+E) 233,024.19

4.2.1.10Pemasangan 1 m2 rangka besi hollow 1x40.40.2mm, modul 60 x 60cm, plafond


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.3500 120,000.00 42,000.00
Tukang Besi OH 0.3500 120,000.00 42,000.00
Kepala Tukang OH 0.0350 140,000.00 4,900.00
Mandor OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 91,600.00
B BAHAN
Rangka metal M1 4.0000 5,666.67 22,666.67
hollow 40.40.0,5 mm
Assesoris Ls 0.1000 1,133.33 113.33
(perkuatan, las dll) JUMLAH HARGA BAHAN 22,780.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 114,380.00


E Overhead & Profit 10% x D 11,438.00
F Harga Satuan Pekerjaan (D+E) 125,818.00

4.5.1.7Pemasangan 1 m2 langit-langit gypsum board ukuran (120 x 240 x 9) mm, tebal 9 mm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.1000 120,000.00 12,000.00
Tukang kayu OH 0.0500 117,376.00 5,868.80
Kepala tukang OH 0.0050 140,000.00 700.00
Mandor OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 19,318.80
B BAHAN
Gypsum board Lembar 0.3640 97,988.00 35,667.63
Paku skrup Kg 0.1100 24,789.00 2,726.79
JUMLAH HARGA BAHAN 38,394.42
C PERALATAN

D Jumlah (A+B+C) 57,713.22


E Overhead & Profit 10% x D 5,771.32
F Harga Satuan Pekerjaan (D+E) 63,484.54

4.5.1.7Pemasangan 1 m2 langit-langit GRC ukuran (120 x 240 x 9) mm, tebal 4 mm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.1000 120,000.00 12,000.00
Tukang kayu OH 0.0500 117,376.00 5,868.80
Kepala tukang OH 0.0050 140,000.00 700.00
Mandor OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 19,318.80
B BAHAN
GRC Lembar 0.3640 85,000.00 30,940.00
Paku skrup Kg 0.1100 24,789.00 2,726.79
JUMLAH HARGA BAHAN 33,666.79
C PERALATAN

D Jumlah (A+B+C) 52,985.59


E Overhead & Profit 10% x D 5,298.56
F Harga Satuan Pekerjaan (D+E) 58,284.15

4.5.1.8Pemasangan 1 m' list kangit-langit profil gypsum


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0500 120,000.00 6,000.00
Tukang Kayu OH 0.0500 117,376.00 5,868.80
Kepala tukang OH 0.0050 140,000.00 700.00
Mandor OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 13,018.80
B BAHAN
List profil gypsum M 1.0500 30,000.00 31,500.00
Paku Kg 0.0100 27,703.00 277.03
JUMLAH HARGA BAHAN 31,777.03
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 44,795.83


E Overhead & Profit 10% x D 4,479.58
F Harga Satuan Pekerjaan (D+E) 49,275.41

4.6.2.4 Pemasangan 1 buah Body Kunci + Cylinder


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0050 120,000.00 600.00
Tukang kayu OH 0.5000 117,376.00 58,688.00
Kepala tukang OH 0.0500 140,000.00 7,000.00
Mandor OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 66,738.00
B BAHAN
Kunci silinder Bh 1.0000 235,000.00 235,000.00
JUMLAH HARGA BAHAN 235,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 301,738.00


E Overhead & Profit 10% x D 30,173.80
F Harga Satuan Pekerjaan (D+E) 331,911.80

4.6.2.3 Pemasangan 1 buah Body Kunci + Cylinder (KM/WC)


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0050 120,000.00 600.00
Tukang kayu OH 0.5000 117,376.00 58,688.00
Kepala tukang OH 0.0500 140,000.00 7,000.00
Mandor OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 66,738.00
B BAHAN
Kunci silinder Bh 1.0000 165,000.00 165,000.00
JUMLAH HARGA BAHAN 165,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 231,738.00


E Overhead & Profit 10% x D 23,173.80
F Harga Satuan Pekerjaan (D+E) 254,911.80

4.6.2.5 Pemasangan satu pasang engsel pintu


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0150 120,000.00 1,800.00
Tukang kayu OH 0.1500 117,376.00 17,606.40
Kepala tukang OH 0.0150 140,000.00 2,100.00
Mandor OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 21,626.40
B BAHAN
Engsel pintu Bh 1.0000 340,000.00 340,000.00
JUMLAH HARGA BAHAN 340,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 361,626.40


E Overhead & Profit 10% x D 36,162.64
F Harga Satuan Pekerjaan (D+E) 397,789.04

4.6.2.8 Pemasangan satu pasang Lever Hendle (handel pintu)


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0150 120,000.00 1,800.00
Tukang kayu OH 0.1500 117,376.00 17,606.40
Kepala tukang OH 0.0150 140,000.00 2,100.00
Mandor OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 21,626.40
B BAHAN
Lever Hendle Bh 1.0000 460,000.00 460,000.00
JUMLAH HARGA BAHAN 460,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 481,626.40


E Overhead & Profit 10% x D 48,162.64
F Harga Satuan Pekerjaan (D+E) 529,789.04

4.6.2.20Pemasangan 1 m2 kaca tebal 5 mm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0150 120,000.00 1,800.00
Tukang kayu OH 0.1500 117,376.00 17,606.40
Kepala tukang OH 0.0150 140,000.00 2,100.00
Mandor OH 0.0008 150,000.00 120.00
JUMLAH TENAGA KERJA 21,626.40
B BAHAN
Kaca tebal 5 mm M2 1.1000 126,448.00 139,092.80
Sealant Tube 0.0500 35,000.00 1,750.00
JUMLAH HARGA BAHAN 140,842.80
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 162,469.20


E Overhead & Profit 10% x D 16,246.92
F Harga Satuan Pekerjaan (D+E) 178,716.12

5.1.1.1Pemasangan 1 buah closet duduk/monoblock


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 3.3000 120,000.00 396,000.00
Tukang batu OH 1.1000 120,000.00 132,000.00
Kepala tukang OH 0.0100 140,000.00 1,400.00
Mandor OH 0.1600 150,000.00 24,000.00
JUMLAH TENAGA KERJA 553,400.00
B BAHAN
Closet duduk Unit 1.0000 2,739,000.00 2,739,000.00
Perlengkapan % 0.0600 2,739,000.00 164,340.00
JUMLAH HARGA BAHAN 2,903,340.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 3,456,740.00


E Overhead & Profit 10% x D 345,674.00
F Harga Satuan Pekerjaan (D+E) 3,802,414.00

5.1.1.5Pemasangan 1 buah wastafel meja


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 1.2000 120,000.00 144,000.00
Tukang batu OH 1.4500 120,000.00 174,000.00
Kepala tukang OH 0.1500 140,000.00 21,000.00
Mandor OH 0.0600 150,000.00 9,000.00
JUMLAH TENAGA KERJA 348,000.00
B BAHAN
Wastafel Unit 1.0000 1,150,000.00 1,150,000.00
Semen Portland Kg 6.0000 1,585.10 9,510.60
Pasir pasang M3 0.0100 216,150.00 2,161.50
Perlengkapan % 0.1200 174,250.82 20,910.10
JUMLAH HARGA BAHAN 1,182,582.20
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,530,582.20


E Overhead & Profit 10% x D 153,058.22
F Harga Satuan Pekerjaan (D+E) 1,683,640.42

5.1.1.36Pemasangan 1 buah floor drain


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0100 120,000.00 1,200.00
Tukang batu OH 0.1000 120,000.00 12,000.00
Kepala tukang OH 0.0100 140,000.00 1,400.00
Mandor OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 15,350.00
B BAHAN
Floor drain Unit 1.0000 86,460.00 86,460.00
JUMLAH HARGA BAHAN 86,460.00
C PERALATAN
JUMLAH HARGA ALAT
D Jumlah (A+B+C) 101,810.00
E Overhead & Profit 10% x D 10,181.00
F Harga Satuan Pekerjaan (D+E) 111,991.00

5.1.1.35Pemasangan 1 buah kran leher angsa diameter 1/2" atau 3/4"


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0100 120,000.00 1,200.00
Tukang batu OH 0.4000 120,000.00 48,000.00
Kepala tukang OH 0.0400 140,000.00 5,600.00
Mandor OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 55,550.00
B BAHAN
Kran air bh 1.0000 183,000.00 183,000.00
Sealtape Buah 0.0250 5,000.00 125.00
JUMLAH HARGA BAHAN 183,125.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 238,675.00


E Overhead & Profit 10% x D 23,867.50
F Harga Satuan Pekerjaan (D+E) 262,542.50

4.7.1.4Pengecetan bidang kayu baru (1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0700 120,000.00 8,400.00
Tukang cat OH 0.0090 117,376.00 1,056.38
Kepala tukang OH 0.0060 140,000.00 840.00
Mandor OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 10,746.38
B BAHAN
Cat menie Kg 0.2000 33,864.00 6,772.80
Plamuur Kg 0.1500 50,850.00 7,627.50
Cat dasar Kg 0.1700 85,000.00 14,450.00
Cat penutup Kg 0.2600 25,000.00 6,500.00
Kuas Bh 0.0100 21,615.00 216.15
Pengencer Kg 0.0300 70,969.00 2,129.07
Ampelas Lbr 0.2000 10,808.00 2,161.60
JUMLAH HARGA BAHAN 39,857.12
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 50,603.50


E Overhead & Profit 10% x D 5,060.35
F Harga Satuan Pekerjaan (D+E) 55,663.85

4.7.1.10Pengecetan 1 m2 tembok baru / Plapond Interior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0200 120,000.00 2,400.00
Tukang cat OH 0.0630 117,376.00 7,394.69
Kepala tukang OH 0.0063 140,000.00 882.00
Mandor OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 11,126.69
B BAHAN
Plamuur Kg 0.1000 50,850.00 5,085.00
Cat dasar Kg 0.1000 85,000.00 8,500.00
Cat Tembok sek. Catylac Kg 0.2600 33,143.00 8,617.18
JUMLAH HARGA BAHAN 22,202.18
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 33,328.87


E Overhead & Profit 10% x D 3,332.89
F Harga Satuan Pekerjaan (D+E) 36,661.75

4.7.1.10Pengecetan 1 m2 tembok baru Interior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0200 120,000.00 2,400.00
Tukang cat OH 0.0630 117,376.00 7,394.69
Kepala tukang OH 0.0063 140,000.00 882.00
Mandor OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 11,126.69
B BAHAN
Plamuur Kg 0.1000 50,850.00 5,085.00
Cat Dinding sek. ICI Dulux (Interior) Pearl Glo - A913 L Kg 0.2600 25,000.00 6,500.00
JUMLAH HARGA BAHAN 11,585.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,711.69


E Overhead & Profit 10% x D 2,271.17
F Harga Satuan Pekerjaan (D+E) 24,982.86

4.7.1.10Pengecetan 1 m2 tembok baru Exterior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup )
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0200 120,000.00 2,400.00
Tukang cat OH 0.0630 117,376.00 7,394.69
Kepala tukang OH 0.0063 140,000.00 882.00
Mandor OH 0.0030 150,000.00 450.00
JUMLAH TENAGA KERJA 11,126.69
B BAHAN
Alkali Resisting Primer A931 - 1050 N Kg 0.1000 33,400.00 3,340.00
Cat Dinding sek. ICI Dulux (Exterior) Weather Shield MAX - A 194 Kg 0.2600 31,400.00 8,164.00
JUMLAH HARGA BAHAN 11,504.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 22,630.69


E Overhead & Profit 10% x D 2,263.07
F Harga Satuan Pekerjaan (D+E) 24,893.76

4.6.1.3Pembuatan dan Pemasangan 1 m' Kusen Kayu Klas II (Kamfer)


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.3500 120,000.00 42,000.00
Tukang cat OH 1.0500 117,376.00 123,244.80
Kepala tukang OH 0.1050 140,000.00 14,700.00
Mandor OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 182,644.80
B BAHAN
Kayu klas II (Kamfer) - papan m³ 0.0400 11,066,880.00 442,675.20
Paku biasa 2" - 5" Kg 0.0500 22,749.00 1,137.45
JUMLAH HARGA BAHAN 443,812.65
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 626,457.45


E Overhead & Profit 10% x D 62,645.75
F Harga Satuan Pekerjaan (D+E) 689,103.20

4.4.3.35Pemasangan 1 m2 Lantai Keramik ukuran 30 x 30 cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.7000 120,000.00 84,000.00
Tukang cat OH 0.3500 117,376.00 41,081.60
Kepala tukang OH 0.0350 140,000.00 4,900.00
Mandor OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 135,231.60
B BAHAN
Keramik uk. 30 x 30 cm Buah 11.8700 4,250.00 50,447.50
Portland cement Kg 10.0000 1,585.10 15,851.00
Semen warna Kg 1.5000 21,615.00 32,422.50
Pasir pasang m³ 0.0450 216,150.00 9,726.75
JUMLAH HARGA BAHAN 108,447.75
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 243,679.35


E Overhead & Profit 10% x D 24,367.94
F Harga Satuan Pekerjaan (D+E) 268,047.29

5.1.1.1 Pemasangan 1 buah closet duduk/monoblock


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 3.3000 120,000.00 396,000.00
Tukang batu OH 1.1000 120,000.00 132,000.00
Kepala tukang OH 0.0100 140,000.00 1,400.00
Mandor OH 0.1600 150,000.00 24,000.00
JUMLAH TENAGA KERJA 553,400.00
B BAHAN
Closet duduk Unit 1.0000 2,739,000.00 2,739,000.00
Perlengkapan % 0.0600 1,643,400.00 98,604.00
JUMLAH HARGA BAHAN 2,837,604.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 3,391,004.00


E Overhead & Profit 10% x D 339,100.40
F Harga Satuan Pekerjaan (D+E) 3,730,104.40

5.1.1.1 Pemasangan 1 buah closet duduk/monoblock Difable


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 3.3000 120,000.00 396,000.00
Tukang batu OH 1.1000 120,000.00 132,000.00
Kepala tukang OH 0.0100 140,000.00 1,400.00
Mandor OH 0.1600 150,000.00 24,000.00
JUMLAH TENAGA KERJA 553,400.00
B BAHAN
Closet duduk Unit 1.0000 2,739,000.00 2,739,000.00
Perlengkapan % 0.0600 1,643,400.00 98,604.00
JUMLAH HARGA BAHAN 2,837,604.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 3,391,004.00


E Overhead & Profit 10% x D 339,100.40
F Harga Satuan Pekerjaan (D+E) 3,730,104.40

5.1.1.5 Pemasangan 1 buah wastafel meja


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 1.2000 120,000.00 144,000.00
Tukang batu OH 1.4500 120,000.00 174,000.00
Kepala tukang OH 0.1500 140,000.00 21,000.00
Mandor OH 0.0600 150,000.00 9,000.00
JUMLAH TENAGA KERJA 348,000.00
B BAHAN
Wastafel Unit 1.0000 1,150,000.00 1,150,000.00
Semen Portland Kg 6.0000 1,585.10 9,510.60
Pasir pasang M3 0.0100 216,150.00 2,161.50
Perlengkapan % 0.1200 259.38 31.13
JUMLAH HARGA BAHAN 1,161,703.23
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,509,703.23


E Overhead & Profit 10% x D 150,970.32
F Harga Satuan Pekerjaan (D+E) 1,660,673.55
5.1.1.35Pemasangan 1 buah kran diameter 1/2" atau 3/4"
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0100 120,000.00 1,200.00
Tukang batu OH 0.4000 120,000.00 48,000.00
Kepala tukang OH 0.0400 140,000.00 5,600.00
Mandor OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 55,550.00
B BAHAN
Kran air M 1.000 183,000.00 183,000.00
Sealtape Buah 0.025 4,575.00 114.38
JUMLAH HARGA BAHAN 183,114.38
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 238,664.38


E Overhead & Profit 10% x D 23,866.44
F Harga Satuan Pekerjaan (D+E) 262,530.81

4.4.3.13Pemasangan 1 m2 lantai granit tile ukuran 60cm x 60cm Warna


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.2400 120,000.00 28,800.00
Tukang Batu OH 0.1200 120,000.00 14,400.00
Kepala tukang OH 0.0120 140,000.00 1,680.00
Mandor OH 0.1200 150,000.00 18,000.00
JUMLAH TENAGA KERJA 62,880.00
B BAHAN
Granite tile Bh 3.1000 80,000.00 248,000.00
Semen Portlan Kg 9.6000 1,585.10 15,216.96
Semen warna Kg 1.5000 21,615.00 32,422.50
Pasir pasang M3 0.0450 216,150.00 9,726.75
JUMLAH HARGA BAHAN 305,366.21
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 368,246.21


E Overhead & Profit 10% x D 36,824.62
F Harga Satuan Pekerjaan (D+E) 405,070.83

4.4.3.42Pemasangan 1 m' stair nozing ukuran 10cm x 60cm


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.0900 120,000.00 10,800.00
Tukang Batu OH 0.0900 120,000.00 10,800.00
Kepala tukang OH 0.0090 140,000.00 1,260.00
Mandor OH 0.0050 150,000.00 750.00
JUMLAH TENAGA KERJA 23,610.00
B BAHAN
Stair nozing Bh 2.0000 29,000.00 58,000.00
Semen Portlan Kg 1.1400 1,585.10 1,807.01
Semen warna Kg 0.1000 21,615.00 2,161.50
Pasir pasang M3 0.0030 216,150.00 648.45
JUMLAH HARGA BAHAN 62,616.96
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 86,226.96


E Overhead & Profit 10% x D 8,622.70
F Harga Satuan Pekerjaan (D+E) 94,849.66

4.4.3.54Pemasangan 1 m2 Keramik Dinding


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.9000 120,000.00 108,000.00
Tukang Batu OH 0.4500 120,000.00 54,000.00
Kepala tukang OH 0.0450 140,000.00 6,300.00
Mandor OH 0.0450 150,000.00 6,750.00
JUMLAH TENAGA KERJA 175,050.00
B BAHAN
Keramik 30 x 60 Granite Tile Bh 1.0500 75,000.00 78,750.00
Semen Portlan Kg 9.3000 1,585.10 14,741.43
Semen warna Kg 1.9400 21,615.00 41,933.10
Pasir pasang M3 0.0180 216,150.00 3,890.70
JUMLAH HARGA BAHAN 139,315.23
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 314,365.23


E Overhead & Profit 10% x D 31,436.52
F Harga Satuan Pekerjaan (D+E) 345,801.75

4.4.1.22Pemasangan 1 m2 dinding kerawang t : 3


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.3000 120,000.00 36,000.00
Tukang Batu OH 0.1000 120,000.00 12,000.00
Kepala Tukang OH 0.0100 140,000.00 1,400.00
Mandor OH 0.0150 150,000.00 2,250.00
JUMLAH TENAGA KERJA 51,650.00
B BAHAN
Bata rooster M2 44.0000 30,000.00 1,320,000.00
Semen Portland Kg 11.0000 1,585.10 17,436.10
JUMLAH HARGA BAHAN 1,337,436.10
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,389,086.10


E Overhead & Profit 10% x D 138,908.61
F Harga Satuan Pekerjaan (D+E) 1,527,994.71
A.4.4.3.581 m2 Pemasangan Dinding Batu Andesit Bakar
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.7000 120,000.00 84,000.00
Tukang Batu OH 0.3500 120,000.00 42,000.00
Kepala Tukang OH 0.0350 140,000.00 4,900.00
Mandor OH 0.0350 150,000.00 5,250.00
JUMLAH TENAGA KERJA 136,150.00
B BAHAN
Batu Andesit Bakar M2 13.7500 6,545.45 90,000.00
Portland cement Kg 11.7500 1,585.10 18,624.93
Pasir pasang m3 0.0350 216,150.00 7,565.25
JUMLAH HARGA BAHAN 116,190.18
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 252,340.18


E Overhead & Profit 10% x D 25,234.02
F Harga Satuan Pekerjaan (D+E) 277,574.19

P2 Pekerjaan Pasangan Tembaga Kaligrafi + Arabesque (Custoom)


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Upah Pasang ls 1.0000 190,000.00 190,000.00
JUMLAH TENAGA KERJA 190,000.00
B BAHAN
Bahan Tembaga Kaligrafi + Arabesque m2 1.1000 475,000.00 522,500.00
Alat Bantu ls 0.2000 475,000.00 95,000.00
-
JUMLAH HARGA BAHAN 617,500.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 807,500.00


E Overhead & Profit 10% x D 80,750.00
F Harga Satuan Pekerjaan (D+E) 888,250.00
A.4.4.3.58
Pemasangan 1 m2 Pekerjaan Pasangan GRC Motif Batik Kesatrian (Custoom)
No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Pekerja OH 0.3500 120,000.00 42,000.00
Tukang Batu OH 0.3500 120,000.00 42,000.00
Kepala Tukang OH 0.0350 140,000.00 4,900.00
Mandor OH 0.0180 150,000.00 2,700.00
JUMLAH TENAGA KERJA 91,600.00
B BAHAN
Rangka metal M1 4.0000 5,666.67 22,666.67
hollow
GRC 40.40.0,5 mm Lbr 0.3640 85,000.00 30,940.00
Assesoris Ls 0.1000 53,606.67 5,360.67
(perkuatan, las dll) JUMLAH HARGA BAHAN 58,967.33
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 150,567.33


E Overhead & Profit 10% x D 15,056.73
F Harga Satuan Pekerjaan (D+E) 165,624.07

P1 Pekerjaan Pasangan Stainles steel Arabesque


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Upah Pasang ls 1.0000 300,000.00 300,000.00
JUMLAH TENAGA KERJA 300,000.00
B BAHAN
Bahan Stainles Stell m2 1.1000 750,000.00 825,000.00
Alat Bantu ls 0.2000 750,000.00 150,000.00
JUMLAH HARGA BAHAN 975,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 1,275,000.00


E Overhead & Profit 10% x D 127,500.00
F Harga Satuan Pekerjaan (D+E) 1,402,500.00

A.1 Pekerjaan Pasang Atap Trimdek


No Uraian Satuan Koefisien Harga Satuan Jumlah Harga
A TENAGA (Rp) (Rp)
Upah Pasang ls 1.0000 60,000.00 60,000.00
JUMLAH TENAGA KERJA 60,000.00
B BAHAN
Atap Trimdex m2 1.1000 150,000.00 165,000.00
Alat Bantu ls 0.2000 150,000.00 30,000.00
JUMLAH HARGA BAHAN 195,000.00
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) 255,000.00


E Overhead & Profit 10% x D 25,500.00
F Harga Satuan Pekerjaan (D+E) 280,500.00
NO DESCRIPTION BRAND QTY SAT HARGA JUMLAH Rp.
Rp.
a b d f g h i

1 LVMDP

1 ACB 4P 1600A 65KA SCHNEIDER 2 pcs 47,362,920.00 94,725,840.00


-Motor SCHNEIDER 2 pcs 15,500,000.00 31,000,000.00
-UVT SCHNEIDER 2 pcs 2,607,000.00 5,214,000.00
-Closing release SCHNEIDER 2 pcs 2,607,000.00 5,214,000.00
-Shunt release SCHNEIDER 2 pcs 2,607,000.00 5,214,000.00
2 MCCB 3P 400A 36KA SCHNEIDER 1 3,200,000.00 3,200,000.00
3 MCCB 3P 100A 36KA SCHNEIDER 4 pcs 1,725,900.00 6,903,600.00
4 MCCB 3P 125A 36KA 2 pcs 1,980,000.00 3,960,000.00
5 MCCB 3P 80A 18KA SCHNEIDER 2 pcs 1,690,000.00 3,380,000.00
6 MCCB 3P 50A 10KA SCHNEIDER 1 pc 703,450.00 703,450.00
7 MCB 3P 40A 10KA SCHNEIDER 1 pcs 550,000.00 550,000.00
8 MCB 3P 20A 6KA SCHNEIDER 1 pc 454,000.00 454,000.00
9 MCB 3P 16A 6KA SCHNEIDER 2 pc 423,000.00 846,000.00
10 MCB 3P 10A 6KA SCHNEIDER 1 pc 415,000.00 415,000.00
11 POWER METER SCHNEIDER 2 pcs 4,555,000.00 9,110,000.00
12 CT 1600/5A AXLE/EQ 3 pcs 1,200,000.00 3,600,000.00
13 ARESTER 3P+N 100KA OBO 1 pc 6,800,000.00 6,800,000.00
14 TIMER 30SEC OMRON/EQ 2 pcs 880,000.00 1,760,000.00
15 TIMER OMRON/EQ 1 pc 880,000.00 880,000.00
16 SELECTOR SWITCH AXLE/EQ 2 pcs 125,000.00 250,000.00
17 RELAY OMRON/EQ 5 pcs 480,000.00 2,400,000.00
18 PUSH BUTTON AXLE/EQ 1 pc 175,000.00 175,000.00
19 PILOT LAMP AXLE/EQ 10 pcs 125,000.00 1,250,000.00
20 FUSE AXLE/EQ 5 pcs 45,000.00 225,000.00
21 BUSBAR EX IMPORT 1 lot 12,500,000.00 12,500,000.00
22 CUBICLE 80 X 200 X 80 JEFTA 2 unit 12,600,000.00 25,200,000.00
23 GROUNDING DAN WIRING DILAPANGAN 1 LS 8,000,000.00 8,000,000.00
Jumlah 233,929,890.00
keuntungan dan Overhead 10% 23,392,989.00
Total 257,322,879.00

5 PP - LIFT
1 MCCB 3P 40A 10KA SCHNEIDER 1 pc 903,450.00 903,450.00
2 MCB 3P 30A 6KA SCHNEIDER 1 pc 415,000.00 415,000.00
3 PILOT LAMP AXLE/EQ 6 pcs 125,000.00 750,000.00
4 FUSE AXLE/EQ 5 pcs 45,000.00 225,000.00
5 BUSBAR EX IMPORT 1 lot 1,500,000.00 1,500,000.00
6 BOX PANEL 50 X 60 X 25 JEFTA 1 unit 2,500,000.00 2,500,000.00
7 GROUNDING DAN WIRING DILAPANGAN 1 LS 4,000,000.00 4,000,000.00
Jumlah 10,293,450.00
keuntungan dan Overhead 10% 1,029,345.00
Total 11,322,795.00
6 SDP

1 MCCB 3P 100A 25KA SCHNEIDER 1 pc 1,725,900.00 1,725,900.00


7 MCCB 3P 40A 10KA SCHNEIDER 2 pc 703,450.00 1,406,900.00
8 MCB 3P 25A 10KA SCHNEIDER 2 pc 550,000.00 1,100,000.00
9 MCB 3P 20A 10KA SCHNEIDER 2 pcs 540,000.00 1,080,000.00
10 MCB 3P 16A 10KA SCHNEIDER 4 pcs 525,000.00 2,100,000.00
11 ARRESTER 3P+N 40KA SCHNEIDER 1 pc 3,500,000.00 3,500,000.00
12 POWER METER SCHNEIDER 1 pc 3,550,000.00 3,550,000.00
13 CT 100/5A AXLE/EQ 3 pcs 1,200,000.00 3,600,000.00
14 PILOT LAMP AXLE/EQ 3 pcs 125,000.00 375,000.00
15 FUSE AXLE/EQ 3 pcs 45,000.00 135,000.00
16 BUSBAR EX IMPORT 1 lot 2,500,000.00 2,500,000.00
17 CUBICLE 60 X 90 X 25 JEFTA 1 unit 2,500,000.00 2,500,000.00
18 MAGNETIC CONTACTOR SCHNEIDER 1 UNIT 1,450,000.00 1,450,000.00
19 GROUNDING DAN WIRING DILAPANGAN 1 LS 3,000,000.00 3,000,000.00
Jumlah 28,022,800.00
keuntungan dan Overhead 10% 2,802,280.00
Total 30,825,080.00
7 LP/PP

1 MCB 3P 25A 6KA SCHNEIDER 1 pc 423,000.00 423,000.00


2 MCB 1P 6A 6KA SCHNEIDER 14 pcs 81,500.00 1,141,000.00
3 MCB 1P 10A 6KA SCHNEIDER 6 pcs 81,500.00 489,000.00
4 PILOT LAMP AXLE/EQ 6 pcs 125,000.00 750,000.00
5 FUSE AXLE/EQ 4 pcs 45,000.00 180,000.00
6 BUSBAR EX IMPORT 1 lot 1,500,000.00 1,500,000.00
7 CUBICLE 60 X 90 X 25 JEFTA 1 unit 3,000,000.00 3,000,000.00
8 MAGNETIC CONTACTOR SCHNEIDER 1 UNIT 1,450,000.00 1,450,000.00
9 GROUNDING DAN WIRING DILAPANGAN 1 LS 1,000,000.00 1,000,000.00
Jumlah 7,483,000.00
keuntungan dan Overhead 10% 748,300.00
Total 8,231,300.00
8 PP,AC
1 MCB 3P 16A 6KA SCHNEIDER 1 pc 423,000.00 423,000.00
2 MCB 1P 6A 6KA SCHNEIDER 12 pcs 81,500.00 978,000.00
3 PILOT LAMP AXLE/EQ 3 pcs 125,000.00 375,000.00
4 FUSE AXLE/EQ 3 pcs 45,000.00 135,000.00
5 BUSBAR EX IMPORT 1 lot 1,500,000.00 1,500,000.00
6 BOX PANEL 50 X 60 X 25 JEFTA 1 unit 2,500,000.00 2,500,000.00
7 GROUNDING DAN WIRING DILAPANGAN 1 LS 1,000,000.00 1,000,000.00
Jumlah 6,911,000.00
keuntungan dan Overhead 10% 691,100.00
Total 7,602,100.00
9 PP-Booster

1 MCB 3P 20A 6KA SCHNEIDER 1 pc 550,000.00 550,000.00


2 MCB 1P 16A 6KA SCHNEIDER 2 pcs 81,500.00 163,000.00
3 MCB 1P 6A 6KA SCHNEIDER 2 pcs 81,500.00 163,000.00
4 PILOT LAMP AXLE/EQ 3 pcs 125,000.00 375,000.00
5 FUSE AXLE/EQ 3 pcs 45,000.00 135,000.00
6 BUSBAR EX IMPORT 1 lot 1,500,000.00 1,500,000.00
7 BOX PANEL 50 X 60 X 25 JEFTA 1 unit 2,500,000.00 2,500,000.00
8 GROUNDING DAN WIRING DILAPANGAN 1 LS 1,000,000.00 1,000,000.00
Jumlah 6,386,000.00
keuntungan dan Overhead 10% 638,600.00
Total 7,024,600.00
25 PP-Outdoor Unit

1 MCCB 3P 400A 36KA SCHNEIDER 1 pc 3,200,000.00 3,200,000.00


2 MCCB 3P 80A 18KA SCHNEIDER 8 pcs 1,690,000.00 13,520,000.00
3 PILOT LAMP AXLE/EQ 3 pcs 125,000.00 375,000.00
4 FUSE AXLE/EQ 3 pcs 45,000.00 135,000.00
5 BUSBAR EX IMPORT 1 lot 1,500,000.00 1,500,000.00
6 CUBICLE 60 X 90 X 25 JEFTA 1 unit 3,000,000.00 3,000,000.00
7 GROUNDING DAN WIRING DILAPANGAN 1 LS 1,000,000.00 1,000,000.00
Jumlah 22,730,000.00
keuntungan dan Overhead 10% 3,409,500.00
Total 26,139,500.00
26 PP Utama Lift

1 MCCB 3P 150A 25KA SCHNEIDER 2 pc 1,800,500.00 3,601,000.00


2 Interlock 1 unit 12,500,000.00 12,500,000.00
3 MCCB 3P 80A 18KA SCHNEIDER 1 pcs 1,690,000.00 1,690,000.00
4 MCCB 3P 40A 10KA SCHNEIDER 4 pc 550,000.00 2,200,000.00
5 MCB 1P 16A 10KA SCHNEIDER 1 pcs 81,500.00 81,500.00
6 FUSE AXLE/EQ 3 pcs 1,690,000.00 5,070,000.00
7 BUSBAR EX IMPORT 1 lot 2,500,000.00 2,500,000.00
8 CUBICLE JEFTA 1 unit 45,000.00 45,000.00
9 MAGNETIC CONTACTOR SCHNEIDER 1 UNIT 1,450,000.00 1,450,000.00
10 GROUNDING DAN WIRING DILAPANGAN 1 LS 3,000,000.00 3,000,000.00
Jumlah 32,137,500.00
keuntungan dan Overhead 10% 4,820,625.00
Total 36,958,125.00
KATEGORI JASA KONSULTASI DAN JASA LAINNYA -

DAFTAR UPAH PEKERJA BANGUNAN


TAHUN ANGGARAN 2019

#REF!

KODE JENIS PEKERJA SATUAN WAKTU HARGA UPAH


Rp.
a b d c

L.01 PEKERJA 1 ORANG/ HR/ 8 JAM 132,000.00


L.02 TUKANG GALI 1 ORANG/ HR/ 8 JAM 188,571.44
L.02 TUKANG BATU 1 ORANG/ HR/ 8 JAM 188,571.44
L.02 TUKANG KAYU 1 ORANG/ HR/ 8 JAM 188,571.44
L.02 TUKANG CAT / PELITUR 1 ORANG/ HR/ 8 JAM 188,571.44
L.02 TUKANG BESI BETON 1 ORANG/ HR/ 8 JAM 188,571.44
L.02 TUKANG BESI PROFIL 1 ORANG/ HR/ 8 JAM 188,571.44
L.02 TUKANG KHUSUS ALUMINIUM 1 ORANG/ HR/ 8 JAM 188,571.44
L.03 KEPALA TUKANG 1 ORANG/ HR/ 8 JAM 200,000.00
L.04 MANDOR 1 ORANG/ HR/ 8 JAM 220,000.00
L.05 SUPIR 1 ORANG/ HR/ 8 JAM 188,571.44
L.06 OPERATOR 1 ORANG/ HR/ 8 JAM 188,571.44
L.07 PEKERJA GALIAN & URUG 1 ORANG/ HR/ 8 JAM 132,000.00

NO. JENIS BAHAN BANGUNAN SAT HARGA SATUAN


Rp.

BAHAN ARSITEKTUR
A. AGREGAT KASAR, BAHAN PEREKAT & BAHAN JADINYA
1 Pasir Urug M3 158,510.00
2 Tanah Urug M3 79,255.00
3 Sirtu M3 236,324.00
4 Pasir Pasang M3 216,150.00
5 Pasir Beton M3 396,275.00
6 Batu Pecah Mesin 1/2 M3 331,430.00
7 Batu Pecah Mesin 2/3 M3 338,635.00
8 Batu Pecah 5 - 7 cm M3 353,045.00
9 Batu Belah Pondasi M3 268,550.00
10 Batu Pecah 15 - 20 cm M3 317,020.00
11 Bata Merah Bakar Bh 590.00
12 Bata Terawang (Roster) type R.09 ex. Cisangkan Bh 7,500.00
13 Batu Tempel Andesit ukuran 15 x 30 cm M2 85,000.00
14 Semen PC Tiga Roda / 50 kg Kg 1,585.10
15 Semen Warna Kg 21,615.00
16 Self Leveling Floor MU 410 Kg 10,400.00
17 AM 30 + AM 54 Liquid Kg 76,000.00
18 Nat AM 50 Tile Grout + AM 54 Liquid Grout Aditive Kg 17,500.00

B. BAHAN FINISHING :
LABURAN, PENGISI DAN ALATNYA
1 Plamir Tembok sek. ICI Kg 50,435.00
2 Cat Tembok sek. Vinilex Ltr 33,143.00
3 Cat Tembok sek. vinilex Plapond Ltr 33,143.00
4 Rool Cat Tembok Uk. Besar Bh 36,025.00
5 Rool Cat Tembok Uk. Kecil Bh 25,938.00
6 Solignem 1 blek (5 Ltr) Ltr 21,615.00
7 Kwas Putih 1" ETERNA Bh 5,044.00
8 Kwas Putih 2" ETERNA Bh 10,087.00
9 Kwas Putih 3" ETERNA Bh 14,410.00
10 Kwas Putih 4" ETERNA Bh 21,615.00
11 Terpentin Ltr 31,271.00
12 Tiner A Ltr 70,969.00
13 Ampelas Lbr 10,808.00
14 Dempul Halus / Imfra ( Wood Filler ) Kg 69,168.00
15 Politur Ltr
16 Ultran Kg
17 Wood Stain Kg
18 Melamine Sending Siller Kg
19 ML 131 Clear Dana Gloss Kg
20 Dempul Kayu Cap Kucing Kg 32,325.00
21 Dempul Besi Kg 32,325.00
22 Meni Kayu / Besi Kg 33,864.00
23 Cat Zincromat Kg 82,137.00
24 Cat Dasar Kayu Kg 85,000.00
25 Cat Kayu SEIV Kg 93,665.00
26 Cat Besi SEIV Kg 141,218.00
27 Cat Dinding sek. ICI Dulux (Interior) Pearl Glo - A913 L Ltr 22,800.00
28 Cat Dinding sek. ICI Dulux (Exterior) Weather Shield MAX - A 194 Ltr 31,400.00
29 Alkali Resisting Primer A931 - 1050 N Kg 33,400.00

C. BAHAN KAYU BERIKUT BAHAN JADINYA


1 Kayu Balok Borneo Super M3 6,196,300.00
2 Kayu Papan Borneo M3 6,196,300.00
3 Kayu Balok Kamper Medan (kruing) M3 6,282,760.00
4 Kayu Papan Kamper Medan (Kruing) M3 6,282,760.00
5 Kayu Balok Kamper Samarinda Oven M3 10,418,430.00
6 Kayu Papan Kamper Samarinda Oven M3 11,066,880.00
7 Kayu Hutan Kelas I ( Terentang,Segeng, Mahoni, Laban ) M3 3,386,350.00
8 Kayu Albasia M3 524,000.00
9 List profil kamper 4 cm M' 21,000.00
10 Dolken 7 s/d 10 Btng 50,003.00

D. BAHAN KAYU LAPIS


1 Teak Wod 4 mm 120 x 240 Lbr 188,770.00
2 Triplek 3 mm 120 x 240 Lbr 79,865.00
3 Triplek 4 mm 120 x 241 Lbr 98,015.00
4 Triplek 6 mm 120 x 240 Lbr 152,468.00
5 Multiplek 9 mm 120 x 240 Lbr 225,071.00
6 Multiplek 12 mm 120 x 224 Lbr 261,374.00
7 Multiplek 15 mm 120 x 240 Lbr
8 Multiplek 18 mm 120 x 242 Lbr 326,718.00
9 Lem Kuning Aibon Kg 61,487.00
10 Formika 120 x 240 Lbr 225,071.00

E. BAHAN PENUTUP RANGKA PLAFOND + PARTISI


1 Calciboard t = 9 mm Lbr 82,500.00
2 Gypsumboard 9 mm sek. Jaya Board Lbr 97,988.00
3 Gypsumboard 12 mm sek. Jaya Board Lbr
4 List Profil Gypsum M' 35,016.00

F. BAHAN LANTAI DAN PELAPIS DINDING


1 Marmer Alam 60 x 60 KW I DN (Warna Muda) Bh 20,500.00
2 Granite Tile 80 x 80 KW I DN sek. Granito (Warna Muda) Bh
3 Granite Tile 60 x 60 KW I DN sek. Granito (Warna Muda) Bh 67,400.00
4 Granite Tile 40 x 40 KW I DN sek. Granito (Warna Tua) Bh 67,400.00
5 Granite Tile 60 x 60 ex import t = 2 cm Bh
6 Stair Nozing 10 x 60 (Fabrikasi) sek. Granito Bh 29,000.00
7 Granite Tile 30 x 30 KW I DN sek. Granito Bh 28,000.00
8 Keramik 40 x 40 KW I DN sek. Roman Bh 17,608.33
9 Keramik 40 x 40 KW I DN (Rock tile) Bh 16,166.67
10 Plint Keramik 10 x 40 KW I DN Bh 59,500.00
11 Keramik 20 x 20 Lantai KM KWI DN Corak Bh 3,626.00
12 Keramik 20 x 20 Dinding KM KWI DN Corak Bh 3,626.00
13 Keramik 20 x 40 Dinding KM KWI DN Corak Gol B Bh 3,626.00
14 Keramik 10 x 20 Dinding KM KWI DN Bh 2,260.00

G. BAHAN LOGAM DAN BAHAN JADINYA


1 Besi Beton U-24 Rata - Rata Kg 14,122.00
2 Besi Beton U-32 Rata - Rata Kg 14,122.00
3 Wire Mesh M7 (5.4*2.1) Kg
4 Wire Mesh M6 (5.4*2.1) Kg
5 IWF Ex DN SII Kg 18,462.00
6 Besi Profil DN SII Kg
7 Besi C Lip Chanel Kg
8 Plat Besi Kg
9 Kawat Beton Kg 33,864.00
10 Lem Kuning (aibond) Kg 61,487.00
11 Lem Fox Kg 40,509.00
12 Kusen Aluminium ukuran 4" sek. YKK YBIC t = 1,35 mm Lengkap Assesories M' 200,850.00
13 Frame Daun Pintu sek. YKK YBIC Lengkap Assesories M' 200,850.00
14 Frame Daun Jendela sek. YKK YBIC Lengkap Assesories M' 200,850.00
15 Pintu Alumunium strip lebar 8 cm sek. YKK YBIC M'
16 Profil kaca sek. YKK YBIC M'
17 Skruf Fixer Bh 400.00
18 Sealent sek. Dow Corning Tube 35,000.00
19 Besi Hollow Galvanis 4 x 4 t = 0,5 mm M' 5,666.67
20 Besi Hollow Galvanis 2 x 4 t = 0,5 mm M' 4,583.33
21 Kawat Las Listrik Kg 28,820.00
22 Box Covert 400x400 Mm 1,399,154.00
23 Box Covert 500x500 Mm 1,755,378.00
24 Box Covert 600x600 Mm 2,206,224.00
25 Box Covert 800x800 Mm 3,606,211.00
26 Box Covert 1000x1000 Mm 4,935,372.00
27 Box Covert 1200x1200 Mm 6,738,618.00
28 Box Covert 1500x1500 Mm 11,807,296.00
29 Box Covert 2000x2000 Mm 17,776,831.00
30 U - Ditch 300x300 Mm 402,742.00
31 U - Ditch 300x400 Mm 465,505.00
32 U - Ditch 400x400 Mm 645,820.00
33 U - Ditch 400x500 Mm 772,663.00
34 U - Ditch 400x600 Mm 870,697.00
34 U - Ditch 500x500 Mm 992,952.00
35 U - Ditch 500x600 Mm 1,055,872.00
36 U - Ditch 500x700 Mm 1,163,939.00
37 U - Ditch 600x600 Mm 1,241,471.00
38 U - Ditch 600x700 Mm 1,308,123.00
39 U - Ditch 600x800 Mm 1,430,236.00
40 U - Ditch 800x800 Mm 1,691,946.00
41 U - Ditch 800x900 Mm 1,815,205.00
42 U - Ditch 800x1000 Mm 1,943,767.00
43 U - Ditch 1000x1000 Mm 2,412,582.00
44 U - Ditch 1000x1100 Mm 2,626,709.00
45 U - Ditch 1000x1200 Mm 2,739,935.00
46 U - Ditch 1200x1200 Mm 3,683,010.00
47 U - Ditch 1200x1400 Mm 4,075,433.00
48 U - Ditch 1400x1400 Mm 5,725,814.00
49 U - Ditch 1400x1600 Mm 5,925,321.00
50 U - Ditch 1500x1500 Mm 6,231,463.00
51 U - Ditch 1600x1600 Mm 7,803,446.00
52 U - Ditch 2000x2000 Mm 10,996,716.00

H. BAHAN ALAT PENGANTUNG DAN KUNCI


1 Lever Handle Ps 340,000.00
2 Lever Handle Ps 460,000.00
3 Body Kunci + Cylinder Set 235,000.00
Set 120,000.00
4 Body Kunci + Cylinder Set 165,000.00
Set 91,000.00
5 Body Kunci + Cylinder Set 400,000.00
Set 100,000.00
6 Escutheon Ps 80,000.00
7 Flush Bolt Ps 85,000.00
8 Flush Bolt Ps 85,000.00
9 Rambucis Bh 10,000.00
10 Engsel Pintu Ps 228,000.00
11 Door Closer Set 225,000.00
12 Engsel Casement Ps 52,000.00
13 Dust Proof Strike Ps 57,000.00
14 Door Stopper Set 50,000.00

I. BAHAN KACA
1 Kaca Polos 5 mm M2 126,448.00
2 Kaca Es 5 mm M2 64,976.00

J. BAHAN PAKU DAN MUR BAUT


1 Paku 1 cm s/d 3 cm Kg 27,703.00
2 Paku 4 cm s/d 7 cm Kg 22,749.00
3 Paku 8 cm s/d 12 cm Kg 21,344.00
4 Paku Sekrup Rata - Rata Kg 24,789.00

K. BAHAN PERPIPAAN
PIPA PVC CLASS AW
1 Pipa Besi Hitam dia 1" t = 2 mm Btng 122,100.00
2 Pipa Besi Hitam dia 1,5" t = 2 mm Btng 186,600.00
3 Pipa Besi Hitam dia 2" t = 2 mm Btng 266,100.00
4 Pipa Besi Hitam dia 3" t = 2 mm Btng 431,800.00
5 Pipa Besi Hitam dia 4" t = 2 mm Btng 612,100.00
6 Pipa PVC type AW Ø 1/2" (15 mm2) Btng 23,300.00
7 Pipa PVC type AW Ø 3/4" (20 mm2) Btng 31,700.00
8 Pipa PVC type AW Ø 1" (25 mm2) Btng 43,300.00
9 Pipa PVC type AW Ø 1 1/4" (32 mm2) Btng 64,800.00
10 Pipa PVC type AW Ø 1 1/2" (40 mm2) Btng 74,400.00
11 Pipa PVC type AW Ø 2" (50 mm2) Btng 95,200.00
12 Pipa PVC type AW Ø 2 1/2" (65 mm2) Btng 138,900.00
13 Pipa PVC type AW Ø 3" (80 mm2) Btng 195,600.00
14 Pipa PVC type AW Ø 4" (100 mm2) Btng 324,100.00
15 Pipa PVC type AW Ø 5" (125 mm2) Btng 513,500.00
16 Pipa PVC type AW Ø 6" (150 mm2) Btng 720,200.00
17 Pipa PVC type AW Ø 8" (216 mm2) Btng 1,208,600.00
18 Lem Paralon Tb 5,044.00
19 Solatip Leideng Glng 7,957.00

L. BAHAN SANITAIR
1 Floor Drain TX1AN sek. Toto Bh 86,460.00
2 Kran Tembok T23 B13 V7NB sek Toto dia. 1/2 " Bh 183,000.00
3 Jet Washer THX20NBPIV sek. Toto Bh 274,000.00
4 Kran Shower TGB9 MZNC SEK. Toto Bh 468,000.00
5 Closet duduk (complete set - putih) T. CW421J/SW420JP Unit 2,689,000.00
6 Closet jongkok (putih) Type CE 7 Unit 355,000.00
7 Kran Leher Angsa sek. Toto dia. 1/2 " Bh 652,000.00
8 Kitchen Zink Stainless sek Henson Bh 749,000.00
9 Wastafel Meja Lengkap Cermin sek. Toto (standart) Unit 1,150,000.00
10 Wastafel Gantung Lengkap Cermin sek. Toto (standart) Unit 390,000.00
11 Urinoar Lengkap U 57 sek. Toto Unit 2,676,506.00
12 Bak Fiber Unit 335,000.00

M. BAHAN BAKAR DAN PELUMAS


1 Minyak Bekisting Ltr 8,500.00
2 Solar Ltr 11,700.00
3 Minyak Pelumas Ltr 62,225.00

BAHAN ME

1 Air Trap Bh 670,000.00


2 Automatic air vent Ø 25 mm Bh 725,000.00
3 Check valve Ø 100 mm Cast iron, 300 Lbs, JIS 20 K Bh 13,722,800.00
4 Check valve Ø 65mm Bh 2,267,900.00
5 Check valve Ø 50mm Bh 1,784,300.00
6 Flexible Joint Ø 65 mm Bh 497,200.00
7 Flexible Joint Ø 50 mm Bh 405,400.00
8 Gate Valve Ø 100 mm Bh 3,669,300.00
9 Gate valve Ø 65mm (Hydrant) Bh 2,160,000.00
10 Gate valve Ø 65mm (Air Bersih) Bh 1,050,000.00
11 Gate valve Ø 50mm Bh 452,400.00
12 Gate valve Ø 25 mm Bh 175,500.00
13 Gate valve Ø 20mm Bh 124,200.00
14 Gate valve Ø 15 mm Bh 102,700.00
15 Landing valve Ø 65 mm Bh 522,000.00
16 Strainer Ø 65mm Bh 2,317,300.00
17 Anti Vortex Plate Ø 65 mm Bh 217,700.00
18 Kran Taman Ø 15 mm lengkap Pondasi Bh 175,000.00
19 Pipa bs sch 40 Ø 150 mm Mtr 570,500.00
20 Pipa bs sch 40 Ø 100 mm Mtr 326,166.67
21 Pipa bs sch 40 Ø 80 mm Mtr 229,333.33
22 Pipa bs sch 40 Ø 65 mm Mtr 206,400.00
23 Pipa bs sch 40 Ø 40 mm Mtr 165,120.00
24 Pipa galv medium Ø 65 mm Mtr 170,833.33
25 Pipa galv medium Ø 50 mm Mtr 134,000.00
26 Pipa galv medium Ø 20 mm Mtr 42,166.67
27 Pipa galv medium Ø 15 mm Mtr 32,833.33
28 Pipa Drainage PVC AW c/w isolasi armaflex t = 13mm, klem mtr 113,333.33
30 Pipa Refrigerant + Isolasi m' 338,683.33
31 Pipa Refregerant Ø19.1mm + Isolasi insulflex tbl = Ø34.9mm m' 269,166.67
32 Pipa Refregerant Ø22.2mm + Isolasi insulflex tbl = Ø41.3mm m' 236,500.00
33 Pipa Refregerant Ø6.4mm + Isolasi insulflex tbl = Ø12.7mm m' 181,500.00
34 Pipa Refregerant Ø6.4mm + Isolasi insulflex tbl = Ø9.5mm m' 149,166.67
35 Pipa Refregerant Ø9.5mm + Isolasi insulflex tbl = Ø12.7mm m' 131,083.33
37 Pipa Refregerant Ø9.5mm + Isolasi insulflex tbl = Ø22.2mm m' 163,000.00
38 Kabel control UTP cat 6+conduit dia 20mm mtr 13,500.00
39 Kabel power NYM 3x2,5 mm2 + conduit dia20mm mtr 18,500.00
40 Pipa PPR PN 10 Ø 65 mm Mtr 190,750.00
41 Pipa PPR PN 10 Ø 50 mm Mtr 119,750.00
42 Pipa PPR PN 10 Ø 40 mm Mtr 75,250.00
43 Pipa PPR PN 10 Ø 32 mm Mtr 49,000.00
44 Pipa PPR PN 10 Ø 25 mm Mtr 32,000.00
45 Pipa PPR PN 10 Ø 20 mm Mtr 19,750.00
46 Pipa PPR PN 10 Ø 15 mm Mtr 14,500.00
47 Pipa pvc aw Ø 150 mm Mtr 180,050.00
48 Pipa pvc aw Ø 100 mm Mtr 81,025.00
49 Pipa pvc aw Ø 80 mm Mtr 48,900.00
50 Pipa pvc aw Ø 65 mm Mtr 34,725.00
51 Pipa pvc aw Ø 50 mm Mtr 23,800.00
52 Pipa pvc aw Ø 40 mm Mtr 21,200.00
53 Pipa pvc d Ø 50 mm Mtr 14,750.00
54 Pipa pvc d Ø 40 mm Mtr 11,500.00
55 Pipa pvc d Ø 32 mm Mtr 10,175.00
56 Bak Kontrol Bh 320,000.00
57 Bak Kontrol Beton 800x500 Bh 860,000.00
58 #REF! Bh 54,000,000.00
71 Exhaust Fan 500 Cfm Bh 11,238,000.00
72 Exhaust Fan 400 Cfm Bh 2,450,000.00
73 Exhaust Fan 100 Cfm Bh 558,600.00
74 Intake air fan kap 1175 Cfm Bh 2,200,000.00
75 Intake air fan 1170 CFM Bh 2,200,000.00
76 Intake air fan 2070 CFM Bh 2,200,000.00
77 Clean Out Dia 100 mm Bh 160,000.00
78 Clean Out Dia 50 mm Bh 110,000.00
79 #REF! Bh 86,000,000.00
80 Rooftank kap.8m3 Bh 32,000,000.00
81 Roof drain Ø 100 mm Bh 255,000.00
82 Roof drain Ø 80 mm Bh 205,000.00
83 Exhaust Air Duct 150 x 150 Bh 185,000.00
84 Exhaust Air Duct 125 x 125 Bh 125,000.00
85 Exhaust Air Duct 100 x 100 Bh 120,000.00
86 Exhaust Air Duct 250 x 250 Bh 256,300.00
87 Exhaust Air Duct 200 x 200 Bh 225,000.00
88 Exhaust Air Duct Ø 200 Bh 200,000.00
89 Exhaust Air Duct Ø 250 Bh 278,000.00
90 Exhaust Air Duct Ø 150 Bh 178,000.00
91 Exhaust Air Duct Ø 100 Bh 167,000.00
92 Exahaust Air Grille 150 x 150 mm Bh 185,000.00
Exahaust Air Grille 250 x 250 mm Bh 285,000.00
93 Louvre 350 x 350 mm Bh 163,000.00
94 Louvre 200 x 200 mm Bh 153,000.00
95 EF toilet 210 cfm Bh 650,000.00
96 EF toilet 260 cfm Bh 690,000.00
97 EF Axial 400 cfm Bh 1,200,000.00
98 Rotary Turbin Bh 1,750,000.00
99 Electric Hydrant Pump Bh 133,500,000.00
100 Jockey Hydrant Pump Bh 41,500,000.00
101 Fire Extinguisher DC Kap 6 kg, Standard NFPA International, dll Bh 650,000.00
102 HP - Hydrant Pilar, Standard NFPA International, dll Lengkap, Accessories : 'Size 4' x 2 1 Bh 3,600,000.00
103 IHB - Indoor Hydrant Box Standard NFPA International, dll Lengkap, Accessories : Bh 4,600,000.00
104 OHB - Outdoor Hydrant Box Standard NFPA International, dll Lengkap, Accessories : Bh 2,600,000.00
105 SC - Siemese Connection Standard NFPA International, dll Lengkap, Accessories :Size 4' x Mtr 2,300,000.00
106 Floating valve Ø 50 mm Bh 175,800.00
107 Floor drain Dia 50 mm Bh 125,000.00
108 Pressure Gauge Bh 195,000.00
109 Keran Ø 15mm Bh 125,000.00
110 Shower drain Dia 50 mm Bh 85,000.00
111 V-Trap Dia 50 mm Bh 35,000.00
112 Vent cap Ø 40 mm Bh 20,000.00
113 Pek. Keran Elbow Bh 15,000.00
114 Pek. Floor Drain Type TX1BN Bh 198,600.00
115 Wall mounted 9.600 Btuh Bh 5,750,000.00
116 Wall mounted 7.500 Btuh Bh 5,580,000.00
117 Wall mounted 15400 Btuh Bh 6,012,000.00
118 Wall mounted 24200 Btuh Bh 8,100,000.00
119 AC Manager Bh 65,430,000.00
120 IU Ceilling cassete 19.100 Btuh Bh 23,010,000.00
121 IU Ceilling cassete 15.400 Btuh Bh 8,760,000.00
122 IU Ceilling cassete 54.600 Btuh Bh 12,560,000.00
123 IU Ceilling cassete 24.200 Btuh Bh 24,046,000.00
124 IU Ceilling cassete 30.700 Btuh Bh 9,910,000.00
125 IU Ceilling cassete 38.200 Btuh Bh 10,950,000.00
126 IU Ceilling cassete 12.300 Btuh Bh 15,321,000.00
127 OU 324.800 BTUH Bh 169,400,000.00
128 OU 386.200 BTUH Bh 321,960,000.00
129 OU 458.600 BTUH Bh 233,200,000.00
130 OU 477.700 BTUH Bh 242,880,000.00
131 Split Wall mounted 18000 Btuh Bh 7,260,000.00
132 Indoor Pipe BranchY-Branch Bh 1,848,000.00
133 Remote Bh 1,166,000.00
134 Pipe Size Reducer Bh 1,000,100.00
135 Control Panel & Cable Bh 5,000,000.00
136 Lift Penumpang Bh 394,000,000.00
137 Sumur Dangkal , Pompa 1 PK , H 60mtr, Casing dia.100mm Set 22,500,000.00
140 Pompa Transfer Air Bersih Set 28,500,000.00
141 Instalasi Booster pump Bh 121,000,000.00

ELEKTRIKAL
NO SAT HARGA SATUAN
BAHAN
a b c d
(Rp)

1 Baterai Cadangan untuk lampu Kap.16, 30menit bh 573,750.00


2 Instalasi Kabel Ladder UK.30x10cm c/w asesoris,suppot&hanger m' 140,000.00
3 Instalasi Kabel Ladder UK.40x10cm c/w asesoris,suppot&hanger m' 151,000.00
4 Instalasi Kabel Tray UK.30x10cm c/w asesoris,suppot&hanger m' 230,000.00
5 Instalasi Kabel Tray UK.40x10cm c/w asesoris,suppot&hanger m' 276,000.00
6 Instalasi Kotak Kontal kabel NYM 3 x 10 mm2 + Conduit dia.20mm m' 56,500.00
7 Instalasi Kotak Kontal kabel NYM 3 x 16 mm2 + Conduit dia.20mm m' 64,500.00
8 Instalasi Kotak Kontal kabel NYM 3 x 16 mm2 + Conduit dia.25mm m' 66,000.00
9 Instalasi Kotak Kontal kabel NYM 3 x 2.5 mm2 + Conduit dia.20mm m' 18,000.00
10 Instalasi Kotak Kontal kabel NYM 3 x 4 mm2 + Conduit dia.20mm m' 27,500.00
11 Instalasi Kotak Kontal kabel NYY 5x4 mm2 m' 36,900.00
12 Instalasi Penerangan kabel NYM 3 x 2,5 mm2 + Conduit dia.20mm ttk 194,500.00
13 Instalasi Sakelar kabel NYM 2 x 2,5 mm2 + Conduit dia.20mm ttk 173,700.00
15 Kotak Kontak 1Fasa 250w unit 22,000.00
19 Lampu Downlight LED 10W (E27) Recessed Mounted / RM unit 166,000.00
20 Lampu Downlight LED 10W (E27) Recessed Mounted / RM Cover Acrylic unit 175,000.00
22 Lampu Exit Kap.10w c/w Batrei Cadangan Listrik unit 650,000.00
23 Lampu TKO TL LED 2x16W Surface Mounted unit 450,000.00
24 Lampu TL LED 2x16W Recessed Mounted / RM Cover Louvre M5 unit 710,000.00
27 Lampu TKO TL LED 2x16W Surface Mounted unit 278,000.00
28 #REF! unit 1,200,000.00
30 Saklar Dua Arah unit 32,000.00
31 Saklar Ganda unit 26,000.00
32 Saklar Tunggal unit 23,000.00
34 Generator Set ,Open Type 800kVA bh 1,900,000,000.00
35 Pengadaan dan pemasangan pipa gas buang 1 Unit dengan menggunakan BSP bh 6,545,000.00
36 Sistem Gas buang (Silencer) Lengkap Dengan pipa 12'' dan Fiting bh 10,625,000.00
37 Instalasions Ducting Exhaust Radiator bh 7,310,000.00
38 Tangki Bahan Bakar Harian ( Daily Tank) bh 15,130,000.00
39 Fuel Hand Pump (manual hand pump) Kap 10 Liter /Minute bh 1,530,000.00
40 Pemipaan Bahan bakar Solar dari tangki bulanan ke tangki harian Genset lengkap pipa GIP bh 3,485,000.00
41 Isolasi ruang Genset dengan Menggunakan Rockwool densinity 80kg/M3 lengkap bh 384,200.00
42 Isolasi Acoustic door ruang Genset dengan Menggunakan Rackwool densinity 1000kg/M bh 1,275,000.00
43 Intake Attenator 3000(w) X 1500 (H) x 800 (I)mm bh 4,675,000.00
44 Exhaus fan kap 1500 CFM bh 2,210,000.00
45 TRAFO Kapasitas : 1000 KVA bh 190,000,000.00
46 Manual and Fixed type, c/w : bh 35,700,000.00
47 Manual and fixed type, C/W : bh 55,250,000.00
48 Lighning Arrester Cubicel ,Tegangan Menengah bh 31,875,000.00
49 LVMDP (Low Voltage Main Distribution Panel) bh 413,950,000.00
50 Grounding Panel BC 50mm2 s/d max 2 Ohm bh 3,500,000.00
51 Penyambungan Daya PLN lkp SLO,UJL kVA 1,020,000.00
52 Kabel Ladder uk 600 x 100 mm - di power House bh 173,666.67
53 N2XSY 3 x1c X50 mm2 mtr 163,000.00
54 NA2XSEFGbY 3Cx240mm2 mtr 590,000.00
55 NYFGbY 2x (4x300mm2) mtr 2,674,000.00
56 NYFGbY 4X25mm2 mtr 132,000.00
57 NYFGbY 4x10mm2 mtr 67,300.00
58 NYFGbY 4X6MM2 mtr 44,300.00
59 NYFGbY 2x 6mm2 mtr 29,600.00
60 NYFGbY 2x4mm2 mtr 25,300.00
61 NYY 2 X (4x1c X300) mm2 mtr 4,008,000.00
62 NYY 4 X( 4x1c X240) mm2 mtr 6,304,000.00
63 NYY 4 x 185mm2 + NYA 1 x 50mm2 m' 1,430,000.00
64 NYY 4 x 35mm2 + NYA 1 x 25mm2 m' 203,000.00
65 NYY 4 x 25mm2 + NYA 1 x 16mm2 m' 178,500.00
66 NYY 4 x 16mm2 + NYA 1 x 16mm2 m' 102,500.00
67 NYY 4 x 10mm2 + NYA 1 x 10mm2 m' 84,000.00
68 NYY 4 x 6mm2 + NYA 1 x 6mm2 m' 52,100.00
69 NYY 4 x 4mm2 + NYA 1 x 4mm2 m' 36,900.00
70 FRC 4x70mm2 + FRC 1x25mm2 mtr 649,600.00
71 NYMHY 4Cx2,5mm2 + PVC∅20 mtr 21,000.00
72 NYFGbY 4x6mm2 mtr 44,300.00
73 NYY 4X6mm2 mtr 42,000.00
74 NYY 4x6 mm2 + NYA 1Cx6mm2 mtr 52,100.00
75 FRC 4x50 mm2 + NYA 1Cx25mm2 mtr 1,077.00
76 NYY 4x25 mm2 + NYA 1Cx16mm2 mtr 144,500.00
77 NYY 4x6 mm2 + NYA 1Cx16mm2 mtr 68,500.00
78 Pipa GIP Dia.100 mtr 156,000.00
79 NYY 2x4 mm2 mtr 16,000.00
80 NYY 2x2,5 mm2 mtr 11,000.00
81 Panel PJU lengkap timer bh 3,570,000.00
82 Lampu PJU Solar Cell LED 60 tiang Hexagonal 9m + Pondasi bh 21,500,000.00
83 Lampu PJU Solar Cell LED 2x60 tiang Hexagonal 9m+Pondasi bh 22,500,000.00
84 Air Terminal Radius 120M c/w terminasi bh 15,300,000.00
85 Kabel BC 70 mm2 bh 56,300.00
86 Grounding Rod dia 20mm bh 380,000.00
87 Bak Kontrol bh 350,000.00
88 Material Bantu (klem,Socket dll) lot 1,000,000.00
89 Alarm Bell Bh 350,000.00
90 Biaya setting area server lot 25,000,000.00
91 Cabinet Rack w/ Acc. bh 5,600,000.00
92 Ceiling Speaker 3 watt Bh 119,500.00
93 #REF! Unit 550,000.00
94 Core switch FO 2 X 48 port unit 12,600,000.00
95 FM Tuner bh 3,900,000.00
96 Fine arrester,+ arrester 6 ka Unit 1,600,000.00
97 Indicator Lamp FA bh 247,000.00
98 Instalasi area ruang server koneksi antar equipment lot 1,276,000.00
99 Instalasi Titik Detector 2 x NYA 1,5 mm2+conduit 20mm mtr 13,600.00
100 Instalasi Titik Speaker Ttk 162,600.00
101 Instalasi titik data dengan Kabel UTP cat 6 + HIC Ø 20 mm mtr 18,500.00
102 Instalasi titik stop kontak titik 227,400.00
104 Instalasi titik camera dengan Kabel UTP cat 6 + HIC Ø 20 mm mtr 18,500.00
105 Instalasi titik Telephone dengan Kabel UTP cat 6 + HIC Ø 20 mm mtr 18,500.00
106 IP Digital Key telephone Untuk Conference - 2,078,865.94
107 IP CCTV camera 2 MP bh 2,078,865.94
108 IP PBX unit 32,337,345.75
109 IP Telephone bh 1,619,070.75
110 Kabel Utama ke TB bh 45,000.00
111 Komputer Server bh 17,500,000.00
112 Koneksi titik grounding bh 750,000.00
113 Manual Break Glass Bh 450,000.00
114 Mixer Pre Amplifier 240 watt lengkap Voice Evacuation sistem bh 36,937,808.60
115 Mixer amplifier / Car call bh 4,532,687.50
116 Master akses kontrol lengkap power supply unit 43,709,305.75
117 NVR kapasitas 16 channel unit 19,700,000.00
118 Monitor led 32 Inch unit 2,800,000.00
119 NYFGBY Ø 3 x 4 mm mtr 29,600.00
120 Panel Control Fire Alarm 2 Loop Unit 34,500,000.00
121 Paging Microphone bh 6,900,000.00
122 Panel MDF TS unit 750,000.00
123 OTB 3 X 48 port - Incoming 3 + Outgoing 3 unit 7,971,570.75
124 Panel Power data utama lot 2,427,829.25
125 Outlet data bh 65,000.00
126 Panel Power data Gedung lot 2,427,829.25
127 Outlet data untuk telephone bh 65,000.00
128 Panel Announciator unit 6,900,000.00
129 Power Amplifier 240W bh 4,100,000.00
130 Relay bh 35,000.00
131 Router Fire wall bh 10,036,270.75
132 Heat Detector bh 576,000.00
133 Smoke detector Bh 625,000.00
134 Stop kontak bh 22,000.00
135 Switch hub kapasitas 24 port Gygabit unit 1,200,000.00
136 Switch Poe 16 Gigabit unit 890,000.00
137 TB data unit 3,500,000.00
138 Terminal Box Tata Suara Unt 250,000.00
139 Terminal Box TBF Bh 2,300,000.00
140 Terminal MDF-FA Bh 850,000.00
141 Zone Selector bh 3,500,000.00
142 Volume Control bh 214,001.00
143 Ceiling Speaker 3W unit 165,000.00
144 UPS kapasitas 6 Kva 1 phase Unit 28,700,000.00
145 Wireless Akses point Long Range bh 2,860,000.00
146 ACB 4P 1250 A 65 KA bh 69,841,000.00
147 MCCB 3P 1000 A 36 KA bh 3,800,000.00
148 MCCB 4P 250 - 630 A 36 KA bh 1,600,000.00
149 MCCB 3P 100 A 36 KA bh 1,200,000.00
150 MCCB 3P 60 A 16 KA bh 800,000.00
151 MCCB 3P 40 A 25 KA bh 800,000.00
152 MCB 3P 30 A 6 KA bh 600,000.00
153 MCCB 3P 25 A 16 KA bh 550,000.00
154 MCCB 3P 20 A 16 KA bh 550,000.00
155 MCCB 3P 10 A 16 KA bh 550,000.00
156 MCB 3P 6 A 6 KA bh 300,000.00
157 MCB 3P 16 A 6 KA bh 300,000.00
158 MCB 3P 16 A 25 KA bh 600,000.00
159 MCB 3P 10 A 6 KA bh 600,000.00
160 MCB 3P 10 A 4.5 KA bh 250,000.00
161 MCB 1P 10 A 4.5 KA bh 107,000.00
162 MCB 1P 6 A 4.5 KA bh 107,000.00
163 Lighting arrester bh 6,750,000.00
164 Interlock system bh 67,500,000.00
165 Indikator lamp bh 40,000.00
166 DPM bh 3,800,000.00
167 Current transformer bh 625,000.00
168 Capasitor bank 300 Kvar 12 step bh 105,600,000.00
169 Bok panel free standing bh 1,900,000.00
170 Bok panel 300 x 500 x 150 mm bh 350,000.00

BAHAN STRUKTUR
A. AGREGAT KASAR, BAHAN PEREKAT & BAHAN JADINYA
1 Pasir Urug M3 158,510.00
2 Tanah Urug M3 79,255.00
3 Sirtu M3 236,324.00
4 Pasir Pasang M3 216,150.00
5 Pasir Beton M3 396,275.00
6 Batu Pecah Mesin 1/2 M3 331,430.00
7 Batu Pecah Mesin 2/3 M3 338,635.00
8 Batu Pecah 5 - 7 cm M3 353,045.00
9 Batu Belah Pondasi M3 268,550.00
10 Batu Pecah 15 - 20 cm M3 317,020.00
11 Bata Merah Bakar Bh 590.00
12 Bata Terawang (Roster) type R.09 ex. Cisangkan Bh 7,500.00
13 Batu Tempel Andesit ukuran 15 x 30 cm M2 85,000.00
13 Batu Tempel Andesit ukuran 15 x 30 cm Bh 6,545.45
14 Semen PC Tiga Roda / 50 kg Kg 1,585.10
15 Semen Warna Kg 21,615.00
16 Self Leveling Floor MU 410 Kg 10,400.00
17 AM 30 + AM 54 Liquid Kg 76,000.00
18 Nat AM 50 Tile Grout + AM 54 Liquid Grout Aditive Kg 17,500.00
19 Kerawang T: 5 bh 35,000.00
20 Kerawang T: 5 bh 30,000.00
21 Genteng Bintumen bh 150,000.00
22 Abu Batu m3 238,000.00

B. BAHAN FINISHING :
LABURAN, PENGISI DAN ALATNYA
1 Plamir Tembok sek. ICI Kg 50,850.00
2 Cat Tembok sek. Vinilex Ltr 33,143.00
3 Cat Tembok sek. vinilex Plapond Ltr 33,143.00
4 Rool Cat Tembok Uk. Besar Bh 36,025.00
5 Rool Cat Tembok Uk. Kecil Bh 25,938.00
6 Solignem 1 blek (5 Ltr) Ltr 21,615.00
7 Kwas Putih 1" ETERNA Bh 5,044.00
8 Kwas Putih 2" ETERNA Bh 10,087.00
9 Kwas Putih 3" ETERNA Bh 14,410.00
10 Kwas Putih 4" ETERNA Bh 21,615.00
11 Terpentin Ltr 31,271.00
12 Tiner A Ltr 70,969.00
13 Ampelas Lbr 10,808.00
14 Dempul Halus / Imfra ( Wood Filler ) Kg 69,168.00
15 Dempul Kayu Cap Kucing Kg 32,325.00
16 Dempul Besi Kg 32,325.00
17 Meni Kayu / Besi Kg 33,864.00
18 Cat Zincromat Kg 82,137.00
19 Cat Dasar Kayu Kg 85,000.00
20 Cat Kayu SEIV Kg 93,665.00
21 Cat Besi SEIV Kg 141,218.00
22 Cat Dinding sek. ICI Dulux (Interior) Pearl Glo - A913 L Ltr 25,000.00
23 Cat Dinding sek. ICI Dulux (Exterior) Weather Shield MAX - A 194 Ltr 31,400.00
24 Alkali Resisting Primer A931 - 1050 N Kg 33,400.00
26 HCL Ltr 8,500.00
C. BAHAN KAYU BERIKUT BAHAN JADINYA
1 Kayu Balok Borneo Super M3 6,196,300.00
2 Kayu Papan Borneo M3 6,196,300.00
3 Kayu Balok Kamper Medan (kruing) M3 6,282,760.00
4 Kayu Papan Kamper Medan (Kruing) M3 a
5 Kayu Balok Kamper Samarinda Oven M3 10,418,430.00
6 Kayu Papan Kamper Samarinda Oven M3 11,066,880.00
7 Kayu Hutan Kelas I ( Terentang,Segeng, Mahoni, Laban ) M3 3,386,350.00
8 Kayu Albasia M3 524,000.00
9 List profil kamper 4 cm M' 21,000.00
10 Dolken 7 s/d 10 Btng 50,003.00
11 Sealent Tube 45,000.00
12 Sealtape buah 5,000.00
13 Conwood deck 4'' uk. 300x100x25 mm pack 195,000.00

E. BAHAN PENUTUP RANGKA PLAFOND + PARTISI


1 Calciboard t = 9 mm Lbr 82,500.00
2 Gypsumboard 9 mm sek. Jaya Board Lbr 97,988.00
3 GRC Board Lbr 85,000.00
4 List Profil Gypsum M' 30,000.00

F. BAHAN LANTAI DAN PELAPIS DINDING


1 Marmer Alam 60 x 60 KW I DN (Warna Muda) Bh 45,000.00
2 Granite Tile 80 x 80 KW I DN sek. Granito (Warna Muda) Bh
3 Granite Tile 60 x 60 KW I DN sek. Granito (Warna Muda) Bh 80,000.00
4 Granite Tile 40 x 40 KW I DN sek. Granito (Warna Tua) Bh 67,400.00
5 Granite Tile 60 x 60 ex import t = 2 cm Bh
6 Stair Nozing 10 x 60 (Fabrikasi) sek. Granito Bh 29,000.00
7 Granite Tile 30 x 30 KW I DN sek. Granito Bh 28,000.00
8 Keramik 40 x 40 KW I DN sek. Roman Bh 4,250.00
9 Keramik 40 x 40 KW I DN (Rock tile) Bh 16,166.67
10 Plint Keramik 10 x 40 KW I DN Bh 59,500.00
11 Keramik 30 x 60 Lantai KM KWI DN Corak Bh 75,000.00
12 Keramik 20 x 20 Dinding KM KWI DN Corak Bh 3,626.00
13 Keramik 20 x 40 Dinding KM KWI DN Corak Gol B Bh 3,626.00
14 Keramik 10 x 20 Dinding KM KWI DN Bh 2,260.00
Bahan Tembaga Kaligrafi + Arabesque bh 475,000.00

G. BAHAN LOGAM DAN BAHAN JADINYA


1 Besi Beton U-24 Rata - Rata Kg 14,122.00
2 Besi Beton U-32 Rata - Rata Kg 14,122.00
3 Wire Mesh M7 (5.4*2.1) Kg
4 Wire Mesh M6 (5.4*2.1) Kg
5 IWF Ex DN SII Kg 18,462.00
6 Besi Profil DN SII Kg
7 Besi C Lip Chanel Kg
8 Plat Besi Kg
9 Kawat Beton Kg 33,864.00
10 Lem Kuning (aibond) Kg 61,487.00
11 Lem Fox Kg 40,509.00
12 Kusen Aluminium ukuran 4" sek. ALEXINDO Lengkap Assesories M' 200,850.00
13 Frame Daun Pintu sek. YKK YBIC Lengkap Assesories M' 200,850.00
14 Frame Daun Jendela sek. YKK YBIC Lengkap Assesories M' 200,850.00
15 Pintu Alumunium strip lebar 8 cm sek. YKK YBIC M' 125,000.00
16 Profil kaca sek. YKK YBIC M' 80,000.00
17 Skruf Fixer Bh 400.00
18 Sealent sek. Dow Corning Tube 35,000.00
19 Alumunium M' 87,500.00
20 Besi Hollow Galvanis 4 x 4 t = 0,5 mm M' 5,666.67
21 Besi Hollow Galvanis 2 x 4 t = 0,5 mm M' 4,583.33
22 Bahan Stainles Stell m2 750,000.00

H. BAHAN ALAT PENGANTUNG DAN KUNCI


1 Lever Handle Ps 340,000.00
2 Lever Handle Ps 460,000.00
3 Body Kunci + Cylinder Set 235,000.00
Set 120,000.00
4 Body Kunci + Cylinder Set 165,000.00
Set 91,000.00
5 Body Kunci + Cylinder Set 400,000.00
Set 100,000.00
6 Escutheon Ps 80,000.00
7 Flush Bolt Ps 85,000.00
8 Flush Bolt Ps 85,000.00
9 Rambucis Bh 10,000.00
10 Engsel Pintu Ps 228,000.00
11 Door Closer Set 225,000.00
12 Engsel Casement Ps 52,000.00
13 Dust Proof Strike Ps 57,000.00
14 Door Stopper Set 50,000.00

I. BAHAN KACA
1 Kaca Polos 5 mm M2 126,448.00
2 Kaca Es 5 mm M2 64,976.00

J. BAHAN PAKU DAN MUR BAUT


1 Paku 1 cm s/d 3 cm Kg 27,703.00
2 Paku 4 cm s/d 7 cm Kg 22,749.00
3 Paku 8 cm s/d 12 cm Kg 21,344.00
4 Paku Sekrup Rata - Rata Kg 24,789.00

L. BAHAN SANITAIR
1 Floor Drain TX1AN sek. Toto Bh 86,460.00
2 Kran Tembok T23 B13 V7NB sek Toto dia. 1/2 " Bh 183,000.00
3 Jet Washer THX20NBPIV sek. Toto Bh 274,000.00
4 Kran Shower TGB9 MZNC SEK. Toto Bh 468,000.00
5 Closet duduk (complete set - putih) T. CW421J/SW420JP Unit 2,739,000.00
6 Closet jongkok (putih) Type CE 7 Unit 355,000.00
7 Kran Leher Angsa sek. Toto dia. 1/2 " Bh 652,000.00
8 Kitchen Zink Stainless sek Henson Bh 749,000.00
9 Wastafel Meja Lengkap Cermin sek. Toto (standart) Unit 1,150,000.00
10 Wastafel Gantung Lengkap Cermin sek. Toto (standart) Unit 390,000.00
11 Urinoar Lengkap U 57 sek. Toto Unit 2,676,506.00
12 Bak Fiber Unit 335,000.00
13 Closet Jongkok Difable Unit 3,250,000.00
14 Wastafel Unit 1,050,000.00

L. BAHAN LANSKAP
1 Koral Sikat Putih kg 9,000.00
2 Batu Adesit bakar 10x20 cm m2 122,000.00
3 Batu Sikat/peralstone (20 kg) krg/m2 125,000.00
4 Batu Adesit Bakar ukuran 15/30 cm m2 135,000.00
5 Batu Adesit Bakar Bintik ukuran 60/60 cm m2 165,000.00
6 Batu Templek + coating m2 117,000.00
7 Paving Block Fullpave ukuran 200x200x80mm warna abu-abu m2 132,000.00
8 Paving Block Fullpave ukuran 100x200x80mm warna abu-abu m2 124,000.00
9 Kastin Beton Pracetak ukuran 40x20x10 cm bh 18,000.00
10 Rumput Gajah Mini m2 32,000.00
11 Kelapa Gading Pohon 185,000.00
12 Bambu Jepang (Bambusa Mutiplex) Pohon 265,000.00
13 Lontar (Bismarkia/Palem Perak) Pohon 339,000.00
14 Trembesi (Samana Saman) , Pohon Pelindung btg 4 - 7 cm, tinggi 100 - 300 cm Pohon 142,000.00
15 Liang Liu (Salix Babilonica) Pohon 225,000.00
16 Biola Cantik ( Ficus Lyrata) , Pohon Pelindung batang > 16 cm, tinggi 100 - 300 cm Pohon 477,000.00
17 Palem raja (Oreodoxa Regia) Pohon 515,000.00
18 Kamboja Bali ,diameter 5-8 cm, tinggi 2.5-3 m, subur dan bebas hama Pohon 349,000.00
19 Dadap Merah (Erythrima Cristagali),Pohon Pelindung batang > 16 cm, tinggi 100 - 300 c Pohon 533,900.00
20 Sawo Kecik (Manilakara Kaukii) , Pohon Pelindung btg 4 - 7 cm, tinggi 100 - 300 cm Pohon 121,000.00
21 Cycas Revoluta Pohon 165,000.00
22 Bungur Putih (Lagerstroemia Indica), btg 4 - 7 cm, tinggi 100 - 300 cm Pohon 285,000.00
23 Cemara Laut (Tan sehat, rimbun) Pohon 335,000.00
24 Boxwood Pohon 85,000.00
Pupuk kandang Krg 30,000.00
25 Kursi Taman Tipe K1 unit 6,800,000.00
26 Kursi Taman Tipe K2 unit 4,500,000.00
27 Kursi Taman Tipe K3 unit 3,500,000.00
28 Lampu Taman Tipe L1 (Lampu type TLD 36 w 54 cool daylight uk. l..1200mm dia. 26 mm) unit 7,500,000.00
+ base penguat
29 Lampu Taman Tipe L2 (Lampu type LED 2 x 50 w 54 cool daylight ) + base penguat unit 4,500,000.00
30 Lampu Taman Tipe L3 (Lampu type LED 36 w 54 cool daylight) + base penguat unit 3,500,000.00
16,500 132,000
23,571 188,571
23,571 188,571
23,571 188,571
23,571 188,571
23,571 188,571
23,571 188,571
23,571 188,571
25,000 200,000
27,500 220,000
23,571 188,571
23,571 188,571
16,500 132,000
675,000 1 573,750
420,000 3 140,000
453,000 3 151,000
690,000.00 3 230,000
828,000.00 3 276,000
52,000.00 4,500 56,500
60,000.00 4,500 64,500
60,000.00 6,000 66,000
13,500.00 4,500 18,000
23,000.00 4,500 27,500

194,500.00 13,500 4,500 600 600 250 19,450 10 194,500.0000


173,700.00 23,000 4,500 600 600 250 28,950 6 173,700.0000

773,522,200 1 657,493,870
7,700,000 1 6,545,000
12,500,000 1 10,625,000
8,600,000 1 7,310,000
17,800,000 1 15,130,000
1,800,000 1 1,530,000
4,100,000 1 3,485,000
452,000 1 384,200
1,500,000 1 1,275,000
5,500,000 1 4,675,000
2,600,000 1 2,210,000
190,000,000 1 190,000,000
42,000,000 1 35,700,000
65,000,000 1 55,250,000
37,500,000 1 31,875,000
487,000,000 1 413,950,000
3,500,000 1 3,500,000
1,200,000 1 1,020,000
521,000.00 3 173,667
163,000.00
700,000.00
2,674,000.00 1 oh
132,000.00 1 oh
67,300.00 0 oh
44,300.00 0 oh

1,347,500.00 82,500 1,430,000


160,000.00 43,000 203,000
152,000.00 26,500 178,500
76,000.00 26,500 102,500
67,000.00 17,000 84,000
42,000.00 10,100 52,100
30,000.00 6,900 36,900

44,300.00
42,000.00
42,000.00 10,100 52,100

118,000.00 26,500 144,500


42,000.00 26,500 68,500

4,200,000 1 3,570,000
9,200,000 1 7,820,000
10,600,000 1 9,010,000
18,000,000 1 15,300,000

10,000 4,500 600 600 250 15,950 80 ###


4,200.00 4,500 600 600 250 10,150 12 121,800
7,600.00 4,500 600 600 250 13,550 12 162,600
13,114.75 4,500 600 600 250 19,065 18 343,166
13,000.00 4,500 600 600 250 18,950 12 227,400
13,114.75 4,500 600 600 250 19,065 28 533,813
13,114.75 4,500 600 600 250 19,065 28 533,813
12 5,500,000 66,000,000 2 105,600,000

Anda mungkin juga menyukai