METODE KERJA
Galian Fondasi dan Tie Beam Ramp Arumaya
METODE KERJA
DAFTAR ISI
I. Tujuan ................................................................................................................................................................... 2
II. Ruang Lingkup Pekerjaan ................................................................................................................................ 2
III. Diagram Alir Pekerjaan.................................................................................................................................... 3
IV. Peralatan dan Bahan ......................................................................................................................................... 3
V. Metode Pekerjaan ............................................................................................................................................. 4
5.1 Stake out posisi fondasi dan tie beam .......................................................................................................... 4
5.2 Marking area yang akan digali..................................................................................................................... 4
5.3 Bobok lantai ramp eksisting ........................................................................................................................ 4
5.4 Pasang Bouwplank....................................................................................................................................... 5
5.5 Gali hingga elevasi rencana ......................................................................................................................... 5
5.6 Buang hasil galian........................................................................................................................................ 5
1
METODE KERJA
I. TUJUAN
Metode galian fondasi ramp Arumaya ini ditujukan untuk:
1. Pedoman dalam pelaksanaan pekerjaan, sehingga meminimalisasi kesalahan yang mungkin
terjadi selama pekerjaan berlangsung dan menyebabkan kerugian bagi semua pihak.
2. Pedoman dalam alokasi pekerja serta alat dan bahan yang digunakan dalam bekerja.
3. Meminimalisasi risiko kecelakaan kerja.
2
METODE KERJA
Mulai
Pasang Bouwplank
Mulai
3
METODE KERJA
V. METODE PEKERJAAN
4
METODE KERJA