00% Segmen 2
00% Segmen 3
00% Segmen 5
Supervisi
Konsultan Supervisi :
Nomor Kontrak : 27 30 31 31 30
Tgl Kontrak :
Nilai Kontrak 7,545,454,545.71
DIVISI 1. U M U M 100
1.2 Mobilisasi Ls 1.00 100,125,000.00 1.327 0.221 0.221 0.221 0.221 0.221 0.221
1.8.(1) Manajemen dan Keselamatan Lalu Lintas Ls 1.00 46,512,000.00 0.616 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027 0.027
DIVISI 2. DRAINASE
2.1.(1) Galian untuk Selokan Drainase dan Saluran Air M3 1,615.50 107,854,140.54 1.429 0.476 0.476 0.476
2.2.(1) Pasangan Batu dengan Mortar M3 861.60 533,595,381.83 7.072 1.414 1.414 1.414 1.414 1.414
Schedule RENCANA
DIVISI 3. PEKERJAAN TANAH Schedule KIPAS
3.1(7) Galian Perkerasan Beraspal Tanpa Cold Milling Machine M3 119.03 129,047,217.06 1.710 0.285 0.285 0.285 0.285 0.285 0.285
3.3.(1) Penyiapan Badan Jalan M2 24,975.00 120,821,956.99 1.601 0.801 0.801
DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN
I
4.2.(2b) Lapis Pondasi Agregat Kelas S M3 310.88 104,177,249.52 1.381 0.690 0.690
ITR
6.(2)a Lapis Perekat - Aspal Cair LTR 6,541.31 79,681,162.36 1.056 0.117 0.117 0.117 0.117 0.117 0.117 0.117 0.117 0.117
AYAID
6.3(5a) Laston Lapis Aus (AC-WC) TON 2,668.27 3,818,415,862.65 50.606 7.229 7.229 7.229 7.229 7.229 7.229 7.229
RIR
6.3(6a) Laston Lapis Pondasi Perata (A-Base (L)) TON 256.95 316,511,840.21 4.195 0.699 0.699 0.699 0.699 0.699 0.699
A
6.3.(8) Bahan Anti Pengelupasan KG 526.00 29,982,000.00 0.397 0.044 0.044 0.044 0.044 0.044 0.044 0.044 0.044 0.044
LIBU
DIVISI 7. STRUKTUR
7.1 (8) Beton Mutu Sedang Fc'15 Mpa M3 1,350.00 1,557,930,532.29 20.647 5.162 5.162 5.162 5.162
7.9.(1) Pasangan Batu M3 760.75 475,998,216.73 6.308 0.789 0.789 0.789 0.789 0.789 0.789 0.789 0.789
DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR
8.4. (1) Marka Jalan Termoplastik M2 520.17 124,801,985.53 1.654 0.827 0.827
0.0
7,545,454,545.71 100.0000
RENCANA AWAL KEMAJUAN PEKERJAAN TIAP MINGGU %
RENCANA AWAL KEMAJUAN PEKERJAAN KUMULATIF % - 0.143 0.430 0.574 0.717 1.146 1.574 2.479 4.799 6.997 8.720 12.534 16.349 28.273 40.196 42.559 44.921 57.838 70.754 83.671 96.587 98.127 99.667 99.690 99.713 99.857 100.000
KEMAJUAN PEKERJAAN TIAP MINGGU % - 0.248 0.248 0.248 0.248 0.312 0.312 1.577 2.991 2.991 2.515 3.891 3.891 8.905 8.905 8.117 8.117 7.418 - 12.579 12.579 6.706 6.706 0.248 0.248
KEMAJUAN PEKERJAAN KUMULATIF % - 0.000 0.248 0.496 0.744 0.992 1.304 1.616 3.192 6.184 9.175 11.690 15.580 19.471 28.377 37.282 45.399 53.516 60.933 60.933 73.513 86.092 92.798 99.504 99.752 100.000
REALISASI KEMAJUAN PEKERJAAN TIAP MINGGU %
REALISASI KEMAJUAN PEKERJAAN KUMULATIF %
DEVIASI ( + / - ) %
Supervisi Teknis Berkala Jalan Wilayah PPK.04 Dan Wilayah SKPD